JP2023079740A - Elevator lifting monitoring system, elevator lifting monitoring method and program - Google Patents

Elevator lifting monitoring system, elevator lifting monitoring method and program Download PDF

Info

Publication number
JP2023079740A
JP2023079740A JP2021193346A JP2021193346A JP2023079740A JP 2023079740 A JP2023079740 A JP 2023079740A JP 2021193346 A JP2021193346 A JP 2021193346A JP 2021193346 A JP2021193346 A JP 2021193346A JP 2023079740 A JP2023079740 A JP 2023079740A
Authority
JP
Japan
Prior art keywords
elevator
lifting
unit
lifting work
operation information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2021193346A
Other languages
Japanese (ja)
Inventor
拓宏 林
Takuhiro Hayashi
寛 中村
Hiroshi Nakamura
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2021193346A priority Critical patent/JP2023079740A/en
Publication of JP2023079740A publication Critical patent/JP2023079740A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

To clearly grasp an elevator lifting work status.SOLUTION: An elevator lifting monitoring system for monitoring an elevator lifting work status includes: an operation information acquisition part for acquiring elevator operation information collected by a data collection part installed in an elevator; a lifting work status calculation part for calculating an elevator lifting work status on the basis of the elevator operation information; a display image generation part for generating an elevator animation image which changes with elapse of time on the basis of the elevator lifting work status, and corresponds to an image photographed from a direction perpendicular to an elevator lifting direction; and a display part for displaying the elevator animation image.SELECTED DRAWING: Figure 1

Description

本発明は、エレベータ揚重モニタリングシステム、エレベータ揚重モニタリング方法およびプログラムに関する。 The present invention relates to an elevator lift monitoring system, an elevator lift monitoring method, and a program.

従来から行われているエレベータ揚重作業の予定・実績の管理手法では、エレベータの機種や台数、配置が、初期計画時に建物の構造や構法、工程的な忙しさ、1フロア当たりの資材量、想定入場者数等を総合的に考慮して計画される。工事開始後にエレベータの計画台数の不足が判明した場合(搬送能力が足りず残業が多い、大渋滞が起きている場合)には、運用計画を改善することで対処するのが一般的である。(一般的に工事の途中で初期計画から台数を増やすことはない。)
ところで、従来から行われているエレベータ揚重作業の予定・実績の管理手法では、エレベータ揚重作業の予定を立てる時点からエレベータ揚重作業の実績が出る時点までの期間中に、エレベータ揚重作業が順調であるか、あるいは、遅れているか等の進捗状況をリアルタイムに把握することが困難であり、エレベータ揚重作業の進捗状況をリアルタイムに情報共有することも困難である。
In the conventional method of managing the schedule and performance of elevator lifting work, the model, number, and layout of elevators are considered at the time of initial planning. Plans are made with comprehensive consideration of the expected number of visitors. If it is found that the planned number of elevators is insufficient after the start of construction (many overtime work due to lack of transportation capacity, heavy traffic congestion), it is common to deal with it by improving the operation plan. (In general, the number of units is not increased from the initial plan during construction.)
By the way, in the conventional method of managing the schedule and performance of the elevator lifting work, during the period from the time when the schedule of the elevator lifting work is made until the time when the performance of the elevator lifting work is obtained, the elevator lifting work is performed. It is difficult to grasp the progress of the elevator lifting work in real time, such as whether it is smooth or delayed, and it is also difficult to share information on the progress of the elevator lifting work in real time.

従来から行われている手法では、現場において、揚重予定と実積とを照らし合わせながら日々の計画が改善される。例えば、朝礼後に大渋滞ができている場合には、朝礼を複数回に分けて運用する改善が行われる。例えば、残業が多い場合には、工程を見直す改善が行われる。例えば、本設エレベータの稼働時期を早める、時間がかかっている作業を特定して段取りを変更する等の改善が行われる。
また、エレベータオペレータが「資材種類、積込階/行先階、揚重開始時刻、完了時刻」などを手書きでメモすることによって、エレベータ揚重実積の記録が行われる。
しかしながら、手書きによって記録が行われる従来手法では、集計に時間と手間がかかってしまう。特に、エレベータが複数台あるような大型現場では、エレベータ揚重作業の進捗状況の把握がさらに困難になる。また、手書きによって記録が行われる従来手法では、記録されたエレベータ揚重実積の資料が、エレベータ揚重作業の現場内で埋没し、施工事業者において全社的な蓄積や共有化ができないおそれがある。実績を参考に適正なエレベータ計画ができない場合には、「搬送能力が足りず大残業」ということになるおそれがある。
In the conventional method, the daily plan is improved by checking the lifting schedule and the actual volume at the site. For example, if there is a heavy traffic jam after the morning assembly, improvement is made by dividing the morning assembly into multiple times. For example, when there is a lot of overtime work, improvements are made by reviewing the process. For example, improvements are made such as moving up the operating time of the permanent elevator, specifying work that is taking a long time, and changing the setup.
In addition, the elevator operator records the actual lifted load by handwriting the "material type, loading floor/destination floor, lifting start time, completion time" and the like.
However, in the conventional method of recording by handwriting, totaling takes time and effort. In particular, in a large site where there are multiple elevators, it is even more difficult to grasp the progress of the elevator lifting work. In addition, in the conventional method of recording by handwriting, the recorded materials of the actual elevator lifting work may be buried in the elevator lifting work site, and the contractor may not be able to accumulate and share it company-wide. . If an appropriate elevator plan cannot be made based on the actual results, there is a risk of "long overtime work due to lack of transport capacity".

特許文献1には、揚重実績を記録し一元管理する揚重管理システムについて記載されている。特許文献1に記載された技術では、揚重管理システムが、高層建築物の建設現場に設置された仮設の揚重エレベータ等である揚重装置の揚重実績を記録し一元管理する。
ところで、特許文献1に記載された技術では、揚重装置の揚重実績を記録し一元管理するために、揚重装置の稼働ログ(例えば荷重、階数、電流/電圧値、及び警報/故障情報等)を集計・加工することによって揚重実績データが生成される。
つまり、特許文献1に記載された技術では、記録・一元管理される揚重実績データが、例えば荷重、階数、電流/電圧値、及び警報/故障情報等を集計・加工したものであるため、単に揚重実績データを記録し一元管理しただけでは、あたかもエレベータから側方(エレベータの昇降方向に直交する方向)に離れた位置からエレベータ全体を監視しているかのようにエレベータの揚重作業状況を明確に把握することができない。
Patent Literature 1 describes a lifting management system that records and centrally manages lifting performance. In the technique described in Patent Literature 1, a lifting management system records and centrally manages lifting results of lifting devices such as temporary lifting elevators installed at construction sites of high-rise buildings.
By the way, in the technique described in Patent Document 1, in order to record and centrally manage the lifting performance of the lifting device, the operation log of the lifting device (for example, load, floor number, current / voltage value, and alarm / failure information etc.) are aggregated and processed to generate actual lifting data.
In other words, in the technology described in Patent Document 1, the lifting performance data that is recorded and centrally managed is, for example, aggregated and processed load, floor number, current / voltage value, alarm / failure information, etc. Simply recording and centrally managing the actual lifting data will make it appear as if the entire elevator is being monitored from a position away from the elevator (perpendicular to the elevator's ascending/descending direction). cannot be clearly understood.

特開2019-089640号公報JP 2019-089640 A

上述した点に鑑み、本発明は、あたかもエレベータから側方に離れた位置からエレベータ全体を監視しているかのようにエレベータの揚重作業状況を明確に把握することができるエレベータ揚重モニタリングシステム、エレベータ揚重モニタリング方法およびプログラムを提供することを目的とする。 In view of the above points, the present invention provides an elevator lifting monitoring system that can clearly grasp the lifting work status of the elevator as if the entire elevator was monitored from a position laterally away from the elevator. An object of the present invention is to provide an elevator lift monitoring method and program.

本発明の一態様は、エレベータの揚重作業の状況をモニタリングするエレベータ揚重モニタリングシステムであって、前記エレベータに設置されたデータ収集部によって収集された前記エレベータの稼働情報を取得する稼働情報取得部と、前記稼働情報取得部によって取得された前記エレベータの稼働情報に基づいて、前記エレベータの揚重作業状況を算出する揚重作業状況算出部と、前記揚重作業状況算出部によって算出された前記エレベータの揚重作業状況に基づいて、時間の経過に伴って変化する前記エレベータのアニメーション画像であって、前記エレベータの昇降方向に直交する方向から撮影された画像に相当する前記エレベータのアニメーション画像を生成する表示画像生成部と、前記表示画像生成部によって生成された前記エレベータのアニメーション画像を表示する表示部とを備えるエレベータ揚重モニタリングシステムである。 One aspect of the present invention is an elevator lifting monitoring system for monitoring the status of lifting work of an elevator, wherein operation information acquisition is performed to acquire operating information of the elevator collected by a data collection unit installed in the elevator. a lifting work situation calculation unit that calculates the lifting work situation of the elevator based on the operation information of the elevator acquired by the operation information acquisition unit; An animation image of the elevator that changes with the lapse of time based on the lifting work status of the elevator, the animation image of the elevator corresponding to an image taken in a direction orthogonal to the ascending/descending direction of the elevator. and a display unit for displaying the animation image of the elevator generated by the display image generation unit.

本発明の一態様は、エレベータの揚重作業の状況をモニタリングするエレベータ揚重モニタリング方法であって、前記エレベータに設置されたデータ収集部によって収集された前記エレベータの稼働情報を取得する稼働情報取得ステップと、前記稼働情報取得ステップにおいて取得された前記エレベータの稼働情報に基づいて、前記エレベータの揚重作業状況を算出する揚重作業状況算出ステップと、前記揚重作業状況算出ステップにおいて算出された前記エレベータの揚重作業状況に基づいて、時間の経過に伴って変化する前記エレベータのアニメーション画像であって、前記エレベータの昇降方向に直交する方向から撮影された画像に相当する前記エレベータのアニメーション画像を生成する表示画像生成ステップと、前記表示画像生成ステップにおいて生成された前記エレベータのアニメーション画像を表示する表示ステップとを備えるエレベータ揚重モニタリング方法である。 One aspect of the present invention is an elevator lifting monitoring method for monitoring the status of lifting work of an elevator, which is an operation information acquisition method for acquiring operation information of the elevator collected by a data collection unit installed in the elevator. a lifting work situation calculating step of calculating a lifting work situation of the elevator based on the operating information of the elevator acquired in the operating information acquiring step; and a lifting work situation calculated in the lifting work situation calculating step An animation image of the elevator that changes with the lapse of time based on the lifting work status of the elevator, the animation image of the elevator corresponding to an image taken in a direction orthogonal to the ascending/descending direction of the elevator. and a display step of displaying the animation image of the elevator generated in the display image generating step.

本発明の一態様は、エレベータの揚重作業の状況をモニタリングする揚重モニタリングサーバを構成するコンピュータに、前記エレベータに設置されたデータ収集部によって収集された前記エレベータの稼働情報を取得する稼働情報取得ステップと、前記稼働情報取得ステップにおいて取得された前記エレベータの稼働情報に基づいて、前記エレベータの揚重作業状況を算出する揚重作業状況算出ステップと、前記揚重作業状況算出ステップにおいて算出された前記エレベータの揚重作業状況に基づいて、時間の経過に伴って変化する前記エレベータのアニメーション画像であって、前記エレベータの昇降方向に直交する方向から撮影された画像に相当する前記エレベータのアニメーション画像を生成する表示画像生成ステップとを実行させるためのプログラムであって、前記表示画像生成ステップにおいて生成された前記エレベータのアニメーション画像は端末装置において表示される、プログラムである。 According to one aspect of the present invention, a computer constituting a lifting monitoring server that monitors the status of elevator lifting work is provided with operating information for acquiring operating information of the elevator collected by a data collecting unit installed in the elevator. an acquisition step; a lifting work situation calculating step of calculating a lifting work situation of the elevator based on the operating information of the elevator acquired in the operation information acquiring step; an animation image of the elevator that changes with the passage of time based on the lifting work situation of the elevator, the animation of the elevator corresponding to an image taken in a direction perpendicular to the ascending/descending direction of the elevator. and a display image generating step of generating an image, wherein the animation image of the elevator generated in the display image generating step is displayed on a terminal device.

本発明によれば、あたかもエレベータから側方に離れた位置からエレベータ全体を監視しているかのようにエレベータの揚重作業状況を明確に把握することができる。 According to the present invention, it is possible to clearly grasp the lifting operation status of the elevator as if the entire elevator was monitored from a position laterally away from the elevator.

第1実施形態のエレベータ揚重モニタリングシステム1の一例を示す図である。BRIEF DESCRIPTION OF THE DRAWINGS It is a figure which shows an example of the elevator lifting monitoring system 1 of 1st Embodiment. 第1実施形態のエレベータ揚重モニタリングシステム1が適用される建物BD、エレベータELV(1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5、6号機ELV6)の一例を示す図である。A diagram showing an example of a building BD and elevator ELVs (No. 1 ELV1, No. 2 ELV2, No. 3 ELV3, No. 4 ELV4, No. 5 ELV5, No. 6 ELV6) to which the elevator lifting monitoring system 1 of the first embodiment is applied. is. 端末装置12の表示画面の一例を示す図である。4 is a diagram showing an example of a display screen of the terminal device 12; FIG. 第1実施形態のエレベータ揚重モニタリングシステム1において実行される処理の一例を説明するためのフローチャートである。4 is a flowchart for explaining an example of processing executed in the elevator lifting monitoring system 1 of the first embodiment;

以下、図面を参照し、本発明のエレベータ揚重モニタリングシステム、エレベータ揚重モニタリング方法およびプログラムの実施形態について説明する。 Hereinafter, embodiments of an elevator lift monitoring system, an elevator lift monitoring method, and a program according to the present invention will be described with reference to the drawings.

[第1実施形態]
図1は第1実施形態のエレベータ揚重モニタリングシステム1の一例を示す図である。図2は第1実施形態のエレベータ揚重モニタリングシステム1が適用される建物BD、エレベータELV(1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5、6号機ELV6)の一例を示す図である。詳細には、図2(A)は第1実施形態のエレベータ揚重モニタリングシステム1が適用される建物BDと例えば6台のエレベータELV(1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5、6号機ELV6)との位置関係を示しており、図2(B)は各エレベータELVの構成の一例を示している。
[First embodiment]
FIG. 1 is a diagram showing an example of an elevator lifting monitoring system 1 according to the first embodiment. FIG. 2 shows an example of a building BD and elevator ELVs (Elevator ELV1, ELV2, ELV3, ELV4, ELV5, ELV6, ELV6) to which the elevator lifting monitoring system 1 of the first embodiment is applied. It is a figure which shows. Specifically, FIG. 2A shows a building BD to which the elevator lifting monitoring system 1 of the first embodiment is applied and, for example, six elevator ELVs (1st ELV1, 2nd ELV2, 3rd ELV3, 4th ELV4). , No. 5 ELV5, No. 6 ELV6), and FIG. 2B shows an example of the configuration of each elevator ELV.

図1および図2に示す例では、エレベータ揚重モニタリングシステム1が、例えば工事用エレベータ等のようなエレベータELVの揚重作業の状況をモニタリングする。エレベータ揚重モニタリングシステム1によるモニタリングの対象のエレベータELVには、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6が含まれる。
他の例では、エレベータ揚重モニタリングシステム1によるモニタリングの対象のエレベータELVの台数が、6以外の任意の台数であってもよい。
また、他の例では、エレベータ揚重モニタリングシステム1が、例えば本設エレベータ等のような、工事用エレベータ以外のエレベータの揚重作業の状況をモニタリングしてもよい。
In the example shown in FIGS. 1 and 2, the elevator lifting monitoring system 1 monitors the status of the lifting work of an elevator ELV, such as a construction elevator. Elevator ELVs to be monitored by the elevator lifting monitoring system 1 include No. 1 ELV1, No. 2 ELV2, No. 3 ELV3, No. 4 ELV4, No. 5 ELV5 and No. 6 ELV6.
In another example, the number of elevator ELVs to be monitored by the elevator lifting monitoring system 1 may be any number other than six.
In another example, the elevator lifting monitoring system 1 may monitor the status of lifting work of elevators other than construction elevators, such as permanent elevators.

図1および図2に示す例では、各エレベータELV(1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5、6号機ELV6)が、例えば可動部ELVAと、アクチュエータELVBと、制御部ELVCと、センサELVDと、データ収集部ELVEと、入力部ELVFとを備えている。可動部ELVAには、例えばゲージなどが含まれる。アクチュエータELVBには、例えば可動部ELVAを動かす駆動モータ等が含まれる。制御部ELVCには、例えばアクチュエータELVBを制御するPLC(Programmable Logic Controller)等が含まれる。センサELVDには、例えばリミットスイッチ等が含まれる。データ収集部ELVEは、例えば制御部ELVCがアクチュエータELVB等に対して出力する制御信号、センサELVDの出力信号などであるエレベータ稼働情報を例えば1秒毎に収集する。データ収集部ELVEによって収集されるエレベータ稼働情報には、例えば積荷の荷重値、現在階/行先階、電流/電圧値、警報/故障情報などが含まれる。入力部ELVFは、エレベータオペレータによる例えば揚重資材名、揚重資材の数量(作業員の人数)、揚重フロア等の入力を受け付ける。入力部ELVFが、エレベータオペレータによって行われた作業時間計測の結果、揚重タスク形成の内容などの入力を受け付けてもよい。 In the example shown in FIGS. 1 and 2, each elevator ELV (1st elevator ELV1, 2nd elevator ELV2, 3rd elevator ELV3, 4th elevator ELV4, 5th elevator ELV5, 6th elevator ELV6) includes, for example, a movable part ELVA, an actuator ELVB, It comprises a control unit ELVC, a sensor ELVD, a data collection unit ELVE, and an input unit ELVF. The movable part ELVA includes, for example, a gauge. The actuator ELVB includes, for example, a drive motor for moving the movable part ELVA. The controller ELVC includes, for example, a PLC (Programmable Logic Controller) that controls the actuator ELVB. Sensor ELVD includes, for example, a limit switch. The data collection unit ELVE collects, for example, elevator operation information, such as control signals output from the control unit ELVC to the actuator ELVB and the like, output signals of the sensor ELVD, and the like, every second, for example. The elevator operation information collected by the data collection unit ELVE includes, for example, the load value of cargo, the current floor/destination floor, current/voltage values, alarm/failure information, and the like. The input unit ELVF receives input from the elevator operator of, for example, the name of the material to be lifted, the quantity of material to be lifted (the number of workers), the floor to be lifted, and the like. The input unit ELVF may receive inputs such as the result of work time measurement performed by the elevator operator and the contents of the lifting task formation.

図1および図2に示す例では、エレベータ揚重モニタリングシステム1が、例えば揚重モニタリングサーバ11と、端末装置12と、予定管理システム13とを備えている。揚重モニタリングサーバ11は、エレベータELVのデータ収集部ELVE、入力部ELVF、端末装置12、予定管理システム13等と例えばインターネット、携帯電話回線、有線LAN、無線LAN、Wi-fi等を介して通信可能に構成されている。端末装置12は、エレベータELVの揚重作業状況を把握するために用いられる。予定管理システム13は、エレベータELVの予定管理情報(例えば揚重予定資材名、揚重予定フロア、作業予定時刻などの情報)を管理する。予定管理システム13は記憶部13Aを備えている。記憶部13Aには、エレベータELVの予定管理情報が格納されている。
図1および図2に示す例では、エレベータ揚重モニタリングシステム1が、3つの端末装置12(例えば、エレベータELVの揚重作業状況を把握する必要がある現場担当者などによって携帯される端末装置12、作業所事務所に設置される端末装置12、施工事業者の本社に設置される端末装置12など)を備えているが、他の例では、エレベータ揚重モニタリングシステム1が、3以外の任意の数の端末装置12を備えていてもよい。
In the example shown in FIGS. 1 and 2, the elevator lift monitoring system 1 includes, for example, a lift monitoring server 11, a terminal device 12, and a schedule management system 13. FIG. The lifting monitoring server 11 communicates with the data collection unit ELVE of the elevator ELV, the input unit ELVF, the terminal device 12, the schedule management system 13, etc. via the Internet, mobile phone line, wired LAN, wireless LAN, Wi-fi, etc. configured as possible. The terminal device 12 is used to grasp the lifting work status of the elevator ELV. The schedule management system 13 manages schedule management information for the elevator ELV (for example, information such as names of materials scheduled to be lifted, floors scheduled to be lifted, and scheduled work times). The schedule management system 13 has a storage unit 13A. The storage unit 13A stores schedule management information for the elevator ELV.
In the example shown in FIGS. 1 and 2, the elevator lifting monitoring system 1 includes three terminal devices 12 (for example, a terminal device 12 carried by a field worker who needs to grasp the lifting work status of the elevator ELV). , a terminal device 12 installed in a work place office, a terminal device 12 installed in a construction company's headquarters, etc.), but in other examples, the elevator lifting monitoring system 1 may include any other than 3 number of terminal devices 12 may be provided.

図1および図2に示す例では、揚重モニタリングサーバ11が例えばクラウドサーバなどである。揚重モニタリングサーバ11は、例えば稼働情報取得部11Aと、入力情報取得部11Bと、予定管理情報取得部11Cと、揚重作業状況算出部11Dと、表示画像生成部11Eと、分析部11Fと、記憶部11Gとを備えている。
稼働情報取得部11Aは、エレベータELV(1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6)に設置されたデータ収集部ELVEによって収集されたエレベータELVの稼働情報(例えば積荷の荷重値、現在階/行先階、電流/電圧値、警報/故障情報など)を取得する。入力情報取得部11Bは、エレベータELVに設置された入力部ELVFにエレベータオペレータによって入力された入力情報(例えば揚重資材名、揚重資材の数量(作業員の人数)、揚重フロア等)を取得する。予定管理情報取得部11Cは、予定管理システム13によって管理されているエレベータELVの予定管理情報(例えば揚重予定資材名、揚重予定フロア、作業予定時刻などの情報)を取得する。
In the example shown in FIGS. 1 and 2, the lifting monitoring server 11 is, for example, a cloud server. The lifting monitoring server 11 includes, for example, an operation information acquisition unit 11A, an input information acquisition unit 11B, a schedule management information acquisition unit 11C, a lifting work situation calculation unit 11D, a display image generation unit 11E, and an analysis unit 11F. , and a storage unit 11G.
The operation information acquisition unit 11A acquires the operation of the elevator ELV collected by the data collection units ELVE installed in the elevators ELV (No. 1 ELV1, No. 2 ELV2, No. 3 ELV3, No. 4 ELV4, No. 5 ELV5 and No. 6 ELV6). Acquire information (eg, load value of cargo, current floor/destination floor, current/voltage value, alarm/failure information, etc.). The input information acquisition unit 11B receives input information (for example, name of lifting material, quantity of lifting material (number of workers), lifting floor, etc.) input by the elevator operator to the input unit ELVF installed in the elevator ELV. get. The schedule management information acquisition unit 11C acquires the schedule management information of the elevator ELV managed by the schedule management system 13 (for example, the name of materials to be lifted, the floor to be lifted, the scheduled work time, etc.).

揚重作業状況算出部11Dは、稼働情報取得部11Aによって取得されたエレベータELV(1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5、6号機ELV6)の稼働情報に基づいて、エレベータELVの揚重作業状況を算出する。つまり、揚重作業状況算出部11Dは、稼働情報取得部11Aによって取得されたエレベータELVの稼働情報に基づいて、エレベータELVの実際の揚重作業状況(例えばエレベータELVが建物BDのどの階に位置するか。エレベータELVが停止中であるか、あるいは、移動中であるか等)を再現する。表示画像生成部11Eは、揚重作業状況算出部11Dによって算出されたエレベータELVの揚重作業状況に基づいて、時間の経過に伴って変化するエレベータELVのアニメーション画像であって、エレベータELVの昇降方向に直交する方向から撮影された画像に相当するエレベータELVのアニメーション画像を生成する。
分析部11Fは、稼働情報取得部11Aによって取得されたエレベータELVの稼働情報(積荷の荷重値、現在階/行先階、電流/電圧値、警報/故障情報など)と、入力情報取得部11Bによって取得された入力情報(揚重資材名、揚重資材の数量(作業員の人数)、揚重フロア等)と、予定管理情報取得部11Cによって取得されたエレベータELVの予定管理情報(揚重予定資材名、揚重予定フロア、作業予定時刻など)とを組み合わせることによって、エレベータELVの揚重作業の進捗状況(例えば揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率など)をリアルタイムに分析する。記憶部11Gは、分析部11Fによって分析されたエレベータELVの揚重作業の進捗状況と、表示画像生成部11Eによって生成されたエレベータELVの揚重作業の進捗状況を示す画像とを記憶する。
Based on the operation information of the elevator ELVs (No. 1 ELV 1, No. 2 ELV 2, No. 3 ELV 3, No. 4 ELV 4, No. 5 ELV 5, and No. 6 ELV 6) acquired by the operation information acquisition unit 11A, the lifting work status calculation unit 11D to calculate the lifting work status of the elevator ELV. That is, the lifting work situation calculation unit 11D calculates the actual lifting work situation of the elevator ELV (for example, on which floor of the building BD the elevator ELV is located) based on the operation information of the elevator ELV acquired by the operation information acquisition unit 11A. whether the elevator ELV is stopped or is moving, etc.). The display image generation unit 11E generates an animation image of the elevator ELV that changes over time based on the lifting work situation of the elevator ELV calculated by the lifting work situation calculation unit 11D. Generate an animated image of the elevator ELV that corresponds to the image taken from the direction perpendicular to the direction.
The analysis unit 11F acquires the operation information of the elevator ELV (cargo load value, current floor/destination floor, current/voltage value, alarm/failure information, etc.) acquired by the operation information acquisition unit 11A, and the input information acquisition unit 11B Acquired input information (name of lifting material, quantity of lifting material (number of workers), lifting floor, etc.) and elevator ELV schedule management information (lifting schedule material name, scheduled lifting floor, scheduled work time, etc.), the progress status of the lifting work of the elevator ELV (for example, the name of the material being lifted, the load value of the load, the cumulative weight lifted, the actual number of times of lifting, Planned number of times of lifting, actual number of times of lifting/progress rate of planned number of times of lifting, etc.) are analyzed in real time. The storage unit 11G stores the progress of the lifting work of the elevator ELV analyzed by the analysis unit 11F and the image showing the progress of the lifting work of the elevator ELV generated by the display image generation unit 11E.

端末装置12は、表示部12Aと、操作部12Bとを備えている。
表示部12Aは、表示画像生成部11Eによって生成されたエレベータELV(1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5、6号機ELV6)のアニメーション画像を表示する。表示部12Aは、表示画像生成部11Eによって生成されたエレベータELVの揚重作業の進捗状況(揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率)を示す画像を、エレベータELVのアニメーション画像の周囲にリアルタイムに表示可能である。また、表示部12Aは、記憶部11Gに記憶されているエレベータELVの揚重作業の進捗状況(揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率)を示す画像を表示可能である。
操作部12Bは、端末装置12の利用者による入力操作を受け付ける。
The terminal device 12 includes a display section 12A and an operation section 12B.
The display unit 12A displays animation images of the elevators ELV (first elevator ELV1, second elevator ELV2, third elevator ELV3, fourth elevator ELV4, fifth elevator ELV5, sixth elevator ELV6) generated by the display image generator 11E. The display unit 12A displays the progress of the lifting work of the elevator ELV generated by the display image generation unit 11E (name of lifting material, load value of cargo, cumulative weight lifted, actual number of times of lifting, planned number of times of lifting, actual number of times of lifting). An image showing the number of times of lifting/progress rate, which is the planned number of times of lifting, can be displayed in real time around the animated image of the elevator ELV. In addition, the display unit 12A displays the progress of the lifting work of the elevator ELV stored in the storage unit 11G (name of lifting material, load value of cargo, cumulative weight lifted, actual number of times of lifting, planned number of times of lifting, It is possible to display an image showing the actual number of times of lifting/progress rate, which is the planned number of times of lifting.
The operation unit 12B receives input operations by the user of the terminal device 12 .

図3は端末装置12の表示画面の一例を示す図である。
図3に示す例では、揚重作業状況算出部11Dによって算出されたエレベータELV(1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5、6号機ELV6)の揚重作業状況に基づいて、表示画像生成部11Eによって生成された時間の経過に伴って変化するエレベータELVのアニメーション画像(エレベータELVの昇降方向に直交する方向から撮影された画像に相当するエレベータELVのアニメーション画像)が、端末装置12の表示画面の中央に表示される。そのため、端末装置12の利用者は、端末装置12の表示画面を見ることにより、あたかもエレベータELVから側方に離れた位置からエレベータELV全体を監視しているかのようにエレベータELVの揚重作業状況を明確に把握することができる。
FIG. 3 is a diagram showing an example of the display screen of the terminal device 12. As shown in FIG.
In the example shown in FIG. 3, the lifting work status of the elevator ELV (No. 1 ELV1, No. 2 ELV2, No. 3 ELV3, No. 4 ELV4, No. 5 ELV5, No. 6 ELV6) calculated by the lifting work status calculator 11D based on the animation image of the elevator ELV that changes with the passage of time generated by the display image generation unit 11E (animation image of the elevator ELV corresponding to the image taken from the direction perpendicular to the ascending/descending direction of the elevator ELV) is displayed in the center of the display screen of the terminal device 12 . Therefore, by viewing the display screen of the terminal device 12, the user of the terminal device 12 can see the lifting work status of the elevator ELV as if he were monitoring the entire elevator ELV from a position away from the side of the elevator ELV. can be clearly understood.

図3に示す例では、エレベータELV(1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5、6号機ELV6)の稼働情報が稼働情報取得部11Aによって取得された場合に、揚重作業状況算出部11Dは、稼働情報取得部11Aによって取得されたエレベータELVの稼働情報に基づいて、昇降するエレベータELVの揚重作業状況をリアルタイムに算出する。表示画像生成部11Eは、揚重作業状況算出部11Dによって算出された昇降するエレベータELVの揚重作業状況に基づいて、昇降するエレベータELVのアニメーション画像をリアルタイムに生成する。端末装置12の表示部12Aは、表示画像生成部11Eによって生成された昇降するエレベータELVのアニメーション画像をリアルタイムに表示する。
他の例では、表示画像生成部11Eによって生成された昇降するエレベータELVのアニメーション画像が記憶部11Gに記憶されてもよい。この例では、端末装置12の表示部12Aが、記憶部11Gに記憶された昇降するエレベータELVのアニメーション画像を表示することができる。
In the example shown in FIG. 3, when the operation information of elevator ELVs (1st elevator ELV1, 2nd elevator ELV2, 3rd elevator ELV3, 4th elevator ELV4, 5th elevator ELV5, 6th elevator ELV6) is acquired by the operation information acquisition unit 11A, The lifting work status calculation unit 11D calculates in real time the lifting work status of the ascending and descending elevator ELV based on the operation information of the elevator ELV acquired by the operation information acquisition unit 11A. The display image generation unit 11E generates an animation image of the elevator ELV moving up and down in real time based on the lifting work situation of the moving elevator ELV calculated by the lifting work situation calculation unit 11D. The display unit 12A of the terminal device 12 displays in real time the animation image of the ascending and descending elevator ELV generated by the display image generating unit 11E.
In another example, the animation image of the ascending and descending elevator ELV generated by the display image generation unit 11E may be stored in the storage unit 11G. In this example, the display unit 12A of the terminal device 12 can display the animation image of the ascending and descending elevator ELV stored in the storage unit 11G.

図3に示す例では、揚重作業状況算出部11Dが、稼働情報取得部11Aによって取得されたエレベータELV(1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5、6号機ELV6)の稼働情報と建物BDの設計データとに基づいて、建物BDに対して昇降するエレベータELVの揚重作業状況をリアルタイムに算出する。表示画像生成部11Eは、揚重作業状況算出部11Dによって算出された建物BDに対して昇降するエレベータELVの揚重作業状況に基づいて、建物BDを含むエレベータELVのアニメーション画像をリアルタイムに生成する。端末装置12の表示部12Aは、表示画像生成部11Eによって生成された建物BDを含むエレベータELVのアニメーション画像をリアルタイムに表示する。
例えば、稼働情報取得部11Aによって取得されたエレベータELV(2号機ELV2)の稼働情報には、2号機ELV2の現在階(45F)、行先階(60F)、2号機ELV2が上昇中であることを示す電流/電圧値などが含まれる。また、稼働情報取得部11Aによって取得されたエレベータELV(6号機ELV6)の稼働情報には、6号機ELV6の現在階(1F)、行先階(なし)、6号機ELV6が停止中であることを示す電流/電圧値などが含まれる。揚重作業状況算出部11Dは、稼働情報取得部11Aによって取得された2号機ELV2の現在階(45F)、行先階(60F)、2号機ELV2が上昇中であることを示す電流/電圧値などと、6号機ELV6の現在階(1F)、行先階(なし)、6号機ELV6が停止中であることを示す電流/電圧値などと、建物BDの設計データとに基づいて、建物BDに対して昇降する2号機ELV2の揚重作業状況(45Fに位置し、60Fに向かって上昇中)と、建物BDに対して昇降する6号機ELV6の揚重作業状況(1Fに位置し、停止中)とを算出する。表示画像生成部11Eは、揚重作業状況算出部11Dによって算出された建物BDに対して昇降する2号機ELV2および6号機ELV6の揚重作業状況に基づいて、建物BDを含む2号機ELV2、6号機ELV6などのアニメーション画像を生成する。端末装置12の表示部12Aは、表示画像生成部11Eによって生成された建物BDを含む2号機ELV2、6号機ELV6などのアニメーション画像を表示する。
In the example shown in FIG. 3, the lifting work status calculation unit 11D obtains the elevator ELVs (1st ELV1, 2nd ELV2, 3rd ELV3, 4th ELV4, 5th ELV5, 6th elevator ELV) acquired by the operation information acquisition unit 11A. Based on the operation information of the ELV 6) and the design data of the building BD, the lifting work status of the elevator ELV moving up and down with respect to the building BD is calculated in real time. The display image generation unit 11E generates an animation image of the elevator ELV including the building BD in real time based on the lifting work situation of the elevator ELV moving up and down with respect to the building BD calculated by the lifting work situation calculation unit 11D. . The display unit 12A of the terminal device 12 displays in real time the animation image of the elevator ELV including the building BD generated by the display image generation unit 11E.
For example, the operation information of the elevator ELV (second elevator ELV2) acquired by the operation information acquiring unit 11A indicates that the current floor (45F) of the second elevator ELV2, the destination floor (60F), and that the second elevator ELV2 is ascending. including current/voltage values to indicate. In addition, the operation information of the elevator ELV (Elevator ELV6) acquired by the operation information acquisition unit 11A includes the current floor (1F) of ELV6, the destination floor (none), and the fact that ELV6 is stopped. including current/voltage values to indicate. The lifting work status calculation unit 11D obtains the current floor (45F), the destination floor (60F) of the No. 2 ELV2 acquired by the operation information acquisition unit 11A, current/voltage values indicating that the No. 2 ELV2 is ascending, etc. Then, based on the current floor (1F) of Unit 6 ELV6, the destination floor (none), the current/voltage value indicating that Unit 6 ELV6 is out of service, and the design data of building BD, Lifting work status of Unit 2 ELV2 (located on 45F, ascending toward 60F) and lifting work status of Unit 6 ELV6 moving up and down against building BD (located on 1F, stopped) and The display image generation unit 11E calculates the lifting work status of the second equipment ELV2 and the sixth equipment ELV6 moving up and down with respect to the building BD calculated by the lifting work condition calculation unit 11D, and calculates the number of the second equipment ELV2, 6 including the building BD. An animation image such as ELV6 is generated. The display unit 12A of the terminal device 12 displays animation images of the second car ELV2, the sixth car ELV6, etc. including the building BD generated by the display image generating unit 11E.

詳細には、図3に示す例では、稼働情報取得部11Aによって取得されるエレベータELVの稼働情報に、1号機ELV1の稼働情報と、2号機ELV2の稼働情報と、3号機ELV3の稼働情報と、4号機ELV4の稼働情報と、5号機ELV5の稼働情報と、6号機ELV6の稼働情報とが含まれる。揚重作業状況算出部11Dは、稼働情報取得部11Aによって取得された1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6の稼働情報と建物BDの設計データとに基づいて、建物BDに対して昇降する1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6の揚重作業状況を算出する。
表示画像生成部11Eは、揚重作業状況算出部11Dによって算出された建物BDに対して昇降する1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6の揚重作業状況に基づいて、建物BDを含む1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像を生成する。
端末装置12の操作部12Bは、端末装置12の利用者による選択操作(2号機ELV2を選択する操作)を受け付ける。
端末装置12の表示部12Aは、建物BDを含む1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像を表示する。詳細には、表示部12Aは、端末装置12の利用者によって選択された2号機ELV2のアニメーション画像をハイライト表示する。
Specifically, in the example shown in FIG. 3, the operating information of the elevator ELV acquired by the operating information acquiring unit 11A includes the operating information of the first elevator ELV1, the operating information of the second elevator ELV2, and the operating information of the third elevator ELV3. , the operating information of the No. 4 machine ELV4, the operating information of the No. 5 machine ELV5, and the operating information of the No. 6 machine ELV6. The lifting work status calculation unit 11D obtains the operation information of the first machine ELV1, the second machine ELV2, the third machine ELV3, the fourth machine ELV4, the fifth machine ELV5 and the sixth machine ELV6 acquired by the operation information acquisition part 11A, and the design data of the building BD. , the lifting work status of No. 1 machine ELV1, No. 2 machine ELV2, No. 3 machine ELV3, No. 4 machine ELV4, No. 5 machine ELV5 and No. 6 machine ELV6 that ascends and descends with respect to the building BD is calculated.
The display image generation unit 11E lifts the first machine ELV1, the second machine ELV2, the third machine ELV3, the fourth machine ELV4, the fifth machine ELV5, and the sixth machine ELV6 that ascend and descend with respect to the building BD calculated by the lifting work situation calculation part 11D. Based on the heavy work situation, animation images of No. 1 machine ELV1, No. 2 machine ELV2, No. 3 machine ELV3, No. 4 machine ELV4, No. 5 machine ELV5 and No. 6 machine ELV6 including building BD are generated.
The operation unit 12B of the terminal device 12 receives a selection operation (operation of selecting the second device ELV2) by the user of the terminal device 12 .
The display unit 12A of the terminal device 12 displays animation images of the first machine ELV1, the second machine ELV2, the third machine ELV3, the fourth machine ELV4, the fifth machine ELV5 and the sixth machine ELV6 including the building BD. Specifically, the display unit 12A highlights the animation image of the second vehicle ELV2 selected by the user of the terminal device 12 .

図3に示す例では、表示画像生成部11Eが、分析部11Fによって分析された1号機ELV1の揚重作業の進捗状況(揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率)を示す画像をリアルタイムに生成する。端末装置12の表示部12Aは、表示画像生成部11Eによって生成された1号機ELV1の揚重作業の進捗状況を示す画像を、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像の周囲(図3の左上部分)にリアルタイムに表示する。
表示画像生成部11Eは、分析部11Fによって分析された2号機ELV2の揚重作業の進捗状況(揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率)を示す画像をリアルタイムに生成する。端末装置12の表示部12Aは、表示画像生成部11Eによって生成された2号機ELV2の揚重作業の進捗状況を示す画像を、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像の周囲(図3の左中央部分)にリアルタイムに表示する。
表示画像生成部11Eは、分析部11Fによって分析された3号機ELV3の揚重作業の進捗状況(揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率)を示す画像をリアルタイムに生成する。端末装置12の表示部12Aは、表示画像生成部11Eによって生成された3号機ELV3の揚重作業の進捗状況を示す画像を、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像の周囲(図3の左下部分)にリアルタイムに表示する。
In the example shown in FIG. 3, the display image generation unit 11E displays the progress status of the lifting work of the first machine ELV1 analyzed by the analysis unit 11F (name of lifting material, load value of cargo, cumulative lifting weight, actual lifting weight). An image showing the number of times of lifting, the planned number of times of lifting, and the progress rate (actual number of times of lifting/scheduled number of times of lifting) is generated in real time. The display unit 12A of the terminal device 12 displays the image showing the progress of the lifting work of the first machine ELV1 generated by the display image generating unit 11E as the first machine ELV1, the second machine ELV2, the third machine ELV3, the fourth machine ELV4, 5 The animation images of the ELV5 and ELV6 No. 6 are displayed in real time around the animation images (upper left part of FIG. 3).
The display image generation unit 11E displays the progress of the lifting work of the No. 2 ELV2 analyzed by the analysis unit 11F (name of lifting material, load value of cargo, total weight lifted, actual number of times of lifting, planned number of times of lifting, An image showing the actual number of times of lifting/progress rate (scheduled number of times of lifting) is generated in real time. The display unit 12A of the terminal device 12 displays the image showing the progress of the lifting work of the second machine ELV2 generated by the display image generating unit 11E as the first machine ELV1, the second machine ELV2, the third machine ELV3, the fourth machine ELV4, 5 The animation images of the ELV5 and ELV6 No. 6 machines are displayed in real time around the animation images (the central left part of FIG. 3).
The display image generation unit 11E displays the progress of the lifting work of Unit 3 ELV3 analyzed by the analysis unit 11F (name of lifting material, load value of cargo, total weight lifted, actual number of times of lifting, planned number of times of lifting, An image showing the actual number of times of lifting/progress rate (scheduled number of times of lifting) is generated in real time. The display unit 12A of the terminal device 12 displays the image showing the progress of the lifting work of the No. 3 ELV3 generated by the display image generation unit 11E as the No. 1 ELV1, No. 2 ELV2, No. 3 ELV3, No. 4 ELV4, 5 The animation images of the ELV5 and ELV6 No. 6 machines are displayed in real time around the animation images (lower left part of FIG. 3).

図3に示す例では、表示画像生成部11Eが、分析部11Fによって分析された4号機ELV4の揚重作業の進捗状況(揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率)を示す画像をリアルタイムに生成する。端末装置12の表示部12Aは、表示画像生成部11Eによって生成された4号機ELV4の揚重作業の進捗状況を示す画像を、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像の周囲(図3の右上部分)にリアルタイムに表示する。
表示画像生成部11Eは、分析部11Fによって分析された5号機ELV5の揚重作業の進捗状況(揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率)を示す画像をリアルタイムに生成する。端末装置12の表示部12Aは、表示画像生成部11Eによって生成された5号機ELV5の揚重作業の進捗状況を示す画像を、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像の周囲(図3の右中央部分)にリアルタイムに表示する。
表示画像生成部11Eは、分析部11Fによって分析された6号機ELV6の揚重作業の進捗状況(揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率)を示す画像をリアルタイムに生成する。端末装置12の表示部12Aは、表示画像生成部11Eによって生成された6号機ELV6の揚重作業の進捗状況を示す画像を、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像の周囲(図3の右下部分)にリアルタイムに表示する。
In the example shown in FIG. 3, the display image generation unit 11E displays the progress status of the lifting work of the No. 4 ELV4 analyzed by the analysis unit 11F (name of lifting material, load value of cargo, cumulative lifting weight, actual lifting weight). An image showing the number of times of lifting, the planned number of times of lifting, and the progress rate (actual number of times of lifting/scheduled number of times of lifting) is generated in real time. The display unit 12A of the terminal device 12 displays the image showing the progress of the lifting work of the fourth machine ELV4 generated by the display image generating unit 11E as the first machine ELV1, the second machine ELV2, the third machine ELV3, the fourth machine ELV4, 5, and so on. The animation images of the ELV5 and ELV6 No. 6 machines are displayed in real time around the animation images (upper right part of FIG. 3).
The display image generation unit 11E displays the progress of the lifting work of the No. 5 ELV5 analyzed by the analysis unit 11F (name of lifting material, load value of cargo, cumulative weight lifted, actual number of times of lifting, planned number of times of lifting, An image showing the actual number of times of lifting/progress rate (scheduled number of times of lifting) is generated in real time. The display unit 12A of the terminal device 12 displays the image showing the progress of the lifting work of the fifth machine ELV5 generated by the display image generating unit 11E as the first machine ELV1, the second machine ELV2, the third machine ELV3, the fourth machine ELV4, 5 The animation images of the ELV5 and ELV6 No. 6 machines are displayed in real time around the animation images (the central right part of FIG. 3).
The display image generation unit 11E displays the progress of the lifting work of the No. 6 ELV6 analyzed by the analysis unit 11F (name of lifting material, load value of cargo, total weight lifted, actual number of times of lifting, planned number of times of lifting, An image showing the actual number of times of lifting/progress rate (scheduled number of times of lifting) is generated in real time. The display unit 12A of the terminal device 12 displays the image showing the progress of the lifting work of the sixth machine ELV6 generated by the display image generating unit 11E as the first machine ELV1, the second machine ELV2, the third machine ELV3, the fourth machine ELV4, 5 The animation images of the ELV5 and ELV6 No. 6 machines are displayed in real time around the animation images (lower right part of FIG. 3).

図3に示す例では、分析部11Fが、稼働情報取得部11Aによって取得された1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のそれぞれの稼働情報と、入力情報取得部11Bによって取得された1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のそれぞれの入力情報と、予定管理情報取得部11Cによって取得された1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のそれぞれの予定管理情報とを組み合わせることによって、フロアごとの資材揚重回数と、全フロアの累計の資材揚重回数と、フロアごとの作業員の搬送人数と、全フロアの累計の作業員の搬送人数とをリアルタイムに分析する。
表示画像生成部11Eは、分析部11Fによって分析されたフロアごとの資材揚重回数と全フロアの累計の資材揚重回数とを示す画像と、フロアごとの作業員の搬送人数と全フロアの累計の作業員の搬送人数とを示す画像とをリアルタイムに生成する。
端末装置12の表示部12Aは、表示画像生成部11Eによって生成されたフロアごとの資材揚重回数と全フロアの累計の資材揚重回数とを示す画像を、1号機ELV1、2号機ELV2および3号機ELV3の揚重作業の進捗状況(揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率)を示す画像と、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像との間にリアルタイムに表示する。
また、端末装置12の表示部12Aは、表示画像生成部11Eによって生成されたフロアごとの作業員の搬送人数と全フロアの累計の作業員の搬送人数とを示す画像を、4号機ELV4、5号機ELV5および6号機ELV6の揚重作業の進捗状況(揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率)を示す画像と、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像との間にリアルタイムに表示する。
In the example shown in FIG. 3, the analysis unit 11F obtains the operating information of the first machine ELV1, the second machine ELV2, the third machine ELV3, the fourth machine ELV4, the fifth machine ELV5, and the sixth machine ELV6, and , No. 1 machine ELV1, No. 2 machine ELV2, No. 3 machine ELV3, No. 4 machine ELV4, No. 5 machine ELV5 and No. 6 machine ELV6 acquired by the input information acquisition unit 11B, and the input information acquired by the schedule management information acquisition unit 11C By combining the schedule management information of No. 1 machine ELV1, No. 2 machine ELV2, No. 3 machine ELV3, No. 4 machine ELV4, No. 5 machine ELV5 and No. 6 machine ELV6, the number of material liftings for each floor and the cumulative total of materials for all floors can be calculated. The number of lifting operations, the number of transported workers for each floor, and the total number of transported workers for all floors are analyzed in real time.
The display image generation unit 11E generates an image showing the number of times materials were lifted for each floor analyzed by the analysis unit 11F and the total number of times materials were lifted for all floors, the number of workers transported for each floor, and the total number of times for all floors. and an image showing the number of workers to be transported are generated in real time.
The display unit 12A of the terminal device 12 displays the images generated by the display image generation unit 11E showing the number of times the material was lifted for each floor and the total number of times the material was lifted for all floors on the first machine ELV1, the second machine ELV2 and 3. The progress of the lifting work of Unit ELV3 (name of lifting material, load value of cargo, cumulative weight lifted, actual number of times of lifting, scheduled number of times of lifting, progress rate of actual number of times of lifting/scheduled number of times of lifting) Animated images of No. 1 machine ELV1, No. 2 machine ELV2, No. 3 machine ELV3, No. 4 machine ELV4, No. 5 machine ELV5 and No. 6 machine ELV6 are displayed in real time.
In addition, the display unit 12A of the terminal device 12 displays the images generated by the display image generation unit 11E that indicate the number of transported workers for each floor and the total number of transported workers for all floors. Progress status of lifting work of Units ELV5 and Unit 6 ELV6 (name of lifting material, load value of cargo, cumulative weight lifted, actual number of times of lifting, planned number of times of lifting, actual number of times of lifting/scheduled number of times of lifting) progress rate) and animation images of No. 1 machine ELV1, No. 2 machine ELV2, No. 3 machine ELV3, No. 4 machine ELV4, No. 5 machine ELV5 and No. 6 machine ELV6 are displayed in real time.

図3に示す例では、分析部11Fが、稼働情報取得部11Aによって取得された1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のそれぞれの稼働情報(積荷の荷重値など)と、入力情報取得部11Bによって取得された1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のそれぞれの入力情報(揚重資材名、揚重資材の数量(作業員の人数)、揚重フロア)と、予定管理情報取得部11Cによって取得された1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のそれぞれの予定管理情報(揚重予定資材名、揚重予定フロア、作業予定時刻)とに基づいて、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6の揚重作業の進捗状況をリアルタイムに分析する。
表示画像生成部11Eは、分析部11Fによって分析された1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6の揚重作業の進捗状況を示す画像として、1号機ELV1単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像と、2号機ELV2単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像と、3号機ELV3単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像と、4号機ELV4単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像と、5号機ELV5単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像と、6号機ELV6単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像と、端末装置12の利用者によって選択された2号機ELV2の稼働状況、揚重重量、フロアを時系列で示す画像(グラフ)とを生成する。
端末装置12の表示部12Aは、表示画像生成部11Eによって生成された1号機ELV1単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像(図3の左上部分)と、2号機ELV2単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像(図3の左中央部分)と、3号機ELV3単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像(図3の左下部分)と、4号機ELV4単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像(図3の右上部分)と、5号機ELV5単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像(図3の右中央部分)と、6号機ELV6単独の揚重資材名、積荷の荷重値、累計揚重重量、実績揚重回数、予定揚重回数、実績揚重回数/予定揚重回数である進捗率を示す画像(図3の右下部分)と、端末装置12の利用者によって選択された2号機ELV2の稼働状況、揚重重量、フロアを時系列で示す画像(グラフ)(図3の下側中央部分)とを、1号機ELV1、2号機ELV2、3号機ELV3、4号機ELV4、5号機ELV5および6号機ELV6のアニメーション画像(図3の中央)の周囲に表示する。
In the example shown in FIG. 3, the analysis unit 11F acquires the operating information ( and the input information (lifting material name , the number of lifting materials (the number of workers), the lifting floor), and the No. 1 machine ELV1, No. 2 machine ELV2, No. 3 machine ELV3, No. 4 machine ELV4, No. 5 machine ELV5 and 6 acquired by the schedule management information acquisition unit 11C Based on the schedule management information (name of materials to be lifted, floor to be lifted, scheduled work time) for ELV6, ELV1 for ELV1, ELV2 for ELV2, ELV3 for ELV3, ELV4 for ELV4, ELV5 and ELV6 for ELV5 Real-time analysis of the progress of the lifting work of Unit ELV6.
The display image generation unit 11E generates 1 image as an image showing the progress of the lifting work of the 1st machine ELV1, 2nd machine ELV2, 3rd machine ELV3, 4th machine ELV4, 5th machine ELV5 and 6th machine ELV6 analyzed by the analysis part 11F. An image showing the name of the lifting material of ELV1 alone, the load value of the cargo, the total lifted weight, the actual number of times of lifting, the planned number of times of lifting, and the progress rate of the actual number of times of lifting/scheduled number of times of lifting, and the second machine ELV2. An image showing the individual lifting material name, the load value of the load, the cumulative lifting weight, the actual number of lifting, the planned number of lifting, the actual number of lifting/planned number of lifting, and the progress rate of the No. 3 ELV3 alone An image showing the name of the lifting material, the load value of the cargo, the total weight lifted, the actual number of times of lifting, the planned number of times of lifting, the actual number of times of lifting / the planned number of times of lifting, and the lifting of Unit 4 ELV4 alone. Image showing material name, load value of cargo, cumulative lifted weight, actual number of times of lifting, planned number of times of lifting, actual number of times of lifting/scheduled number of times of lifting, and name of lifting material for Unit 5 ELV5 alone , the load value of the cargo, the cumulative weight, the actual number of times of lifting, the number of times of lifting, the number of times of lifting, the number of times of actual lifting/scheduled number of times of lifting, and the image showing the progress rate, the name of the lifting material of Unit 6 ELV6 alone, the cargo Load value, cumulative weight, actual number of times of lifting, planned number of times of lifting, actual number of times of lifting/scheduled number of times of lifting, and an image showing the progress rate, and the second machine ELV2 selected by the user of the terminal device 12 An image (graph) showing the operating status, lifting weight, and floor in chronological order is generated.
The display unit 12A of the terminal device 12 displays the name of the lifting material for the single ELV1 of the first machine generated by the display image generation unit 11E, the load value of the cargo, the cumulative weight of the lifted weight, the actual number of times of lifting, the planned number of times of lifting, the actual number of times of lifting. An image showing the progress rate, which is the number of times of lifting/scheduled number of times of lifting (upper left part of Fig. 3), the name of the lifting material of Unit 2 ELV2 alone, the load value of the cargo, the cumulative weight of lifting, the actual number of times of lifting, and the scheduled number of liftings. An image showing the number of times of lifting, the actual number of times of lifting/the progress rate, which is the number of times of lifting (the left center part of Fig. 3), the name of the lifting material of Unit 3 ELV3 alone, the load value of the cargo, the total weight of lifting, the actual number of times of lifting An image showing the number of times of lifting, the planned number of times of lifting, the actual number of times of lifting/the progress rate of the number of times of lifting/planned number of liftings (lower left part of Fig. 3), the name of the lifting material of Unit 4 ELV4 alone, the load value of the cargo, and the total An image (upper right part of Fig. 3) showing the progress rate of lifting weight, actual number of times of lifting, planned number of times of lifting, actual number of times of lifting/planned number of times of lifting, name of lifting materials and cargo of Unit 5 ELV5 alone Load value, cumulative weight, actual number of times of lifting, planned number of times of lifting, image showing the progress rate of actual number of times of lifting / planned number of times of lifting (right center part of Figure 3), and Unit 6 ELV6 alone An image showing the name of the lifting material, the load value of the cargo, the total weight lifted, the actual number of times of lifting, the planned number of times of lifting, and the progress rate, which is the actual number of times of lifting / the planned number of times of lifting (lower right part of Fig. 3); , an image (graph) (lower central part of FIG. 3) showing the operation status, lifted weight, and floor of the second machine ELV2 selected by the user of the terminal device 12 in chronological order. Displayed around the animation image (center of FIG. 3) of ELV2, No. 3 machine ELV3, No. 4 machine ELV4, No. 5 machine ELV5 and No. 6 machine ELV6.

図4は第1実施形態のエレベータ揚重モニタリングシステム1において実行される処理の一例を説明するためのフローチャートである。
図4に示す例では、ステップS11において、稼働情報取得部11Aが、エレベータELVに設置されたデータ収集部ELVEによって収集されたエレベータELVの稼働情報を取得する。
次いで、ステップS12では、揚重作業状況算出部11Dが、ステップS11において取得されたエレベータELVの稼働情報に基づいて、エレベータELVの揚重作業状況を算出する。
次いで、ステップS13では、表示画像生成部11Eが、ステップS12において算出されたエレベータELVの揚重作業状況に基づいて、時間の経過に伴って変化するエレベータELVのアニメーション画像であって、エレベータELVの昇降方向に直交する方向から撮影された画像に相当するエレベータELVのアニメーション画像を生成する。
次いで、ステップS14では、端末装置12の表示部12Aが、ステップS13において生成された前記エレベータELVのアニメーション画像を表示する。
FIG. 4 is a flow chart for explaining an example of processing executed in the elevator lifting monitoring system 1 of the first embodiment.
In the example shown in FIG. 4, in step S11, the operation information acquisition unit 11A acquires the operation information of the elevator ELV collected by the data collection unit ELVE installed in the elevator ELV.
Next, in step S12, the lifting work status calculator 11D calculates the lifting work status of the elevator ELV based on the operation information of the elevator ELV acquired in step S11.
Next, in step S13, the display image generation unit 11E generates an animation image of the elevator ELV that changes over time based on the lifting work situation of the elevator ELV calculated in step S12. An animation image of the elevator ELV corresponding to the image taken from the direction orthogonal to the ascending/descending direction is generated.
Next, in step S14, the display unit 12A of the terminal device 12 displays the animation image of the elevator ELV generated in step S13.

[第2実施形態]
以下、本発明のエレベータ揚重モニタリングシステム、エレベータ揚重モニタリング方法およびプログラムの第2実施形態について説明する。
第2実施形態のエレベータ揚重モニタリングシステム1は、後述する点を除き、上述した第1実施形態のエレベータ揚重モニタリングシステム1と同様に構成されている。従って、第2実施形態のエレベータ揚重モニタリングシステム1によれば、後述する点を除き、上述した第1実施形態のエレベータ揚重モニタリングシステム1と同様の効果を奏することができる。
[Second embodiment]
A second embodiment of the elevator lift monitoring system, elevator lift monitoring method, and program according to the present invention will be described below.
The elevator lifting monitoring system 1 of the second embodiment is configured in the same manner as the elevator lifting monitoring system 1 of the first embodiment described above, except for the points described later. Therefore, according to the elevator lifting monitoring system 1 of the second embodiment, the same effects as the elevator lifting monitoring system 1 of the first embodiment described above can be obtained except for the points described later.

上述したように、第1実施形態のエレベータ揚重モニタリングシステム1は、エレベータELVの揚重作業の状況をモニタリングする。第1実施形態のエレベータ揚重モニタリングシステム1では、揚重モニタリングサーバ11と予定管理システム13とが連携することによって、揚重モニタリングサーバ11の予定管理情報取得部11Cは、予定管理システム13によって管理されているエレベータELVの予定管理情報(揚重予定資材名、揚重予定フロア、作業予定時刻)を取得する。一方、第1実施形態のエレベータ揚重モニタリングシステム1は、エレベータELVの揚重作業の予定を立てる機能を有さないが、第2実施形態のエレベータ揚重モニタリングシステム1は、エレベータELVの揚重作業の予定を立てる機能を有していてもよい。 As described above, the elevator lifting monitoring system 1 of the first embodiment monitors the status of the lifting work of the elevator ELV. In the elevator lifting monitoring system 1 of the first embodiment, the lifting monitoring server 11 and the schedule management system 13 work together so that the schedule management information acquisition unit 11C of the lifting monitoring server 11 is managed by the schedule management system 13. Elevator ELV scheduled management information (scheduled lifting material name, scheduled lifting floor, scheduled work time) is acquired. On the other hand, the elevator lift monitoring system 1 of the first embodiment does not have the function of scheduling the lifting work of the elevator ELV, but the elevator lift monitoring system 1 of the second embodiment It may have a function of scheduling work.

第1実施形態のエレベータ揚重モニタリングシステム1では、エレベータELVの入力部ELVFが、例えばタッチパネルなどのインタフェースを介してエレベータオペレータによる例えば揚重資材名、揚重資材の数量(作業員の人数)、揚重フロア等の入力を受け付ける。
第2実施形態のエレベータ揚重モニタリングシステム1では、エレベータELVの入力部ELVFが、音声入力機能、画像認識機能などを有していてもよい。つまり、入力部ELVFが、エレベータオペレータによる揚重資材名、揚重資材の数量(作業員の人数)、揚重フロア等の音声入力を受け付けたり、入力部ELVFが、揚重資材の画像を認識することによって揚重資材名を特定したりしてもよい。また、分析部11Fが、各種センサ情報(例えば温度センサ、ロードセル、振動センサなどの情報)を分析することによって故障の予知を行ってもよい。
In the elevator lifting monitoring system 1 of the first embodiment, the input unit ELVF of the elevator ELV receives, for example, the names of lifting materials, the quantity of lifting materials (the number of workers), Receives input such as lifting floor.
In the elevator lifting monitoring system 1 of the second embodiment, the input unit ELVF of the elevator ELV may have a voice input function, an image recognition function, and the like. That is, the input unit ELVF accepts voice input from the elevator operator such as the name of the lifting material, the quantity of the lifting material (the number of workers), the floor to be lifted, etc., and the input unit ELVF recognizes the image of the lifting material. You may specify a lifting material name by doing. Further, the analysis unit 11F may predict failure by analyzing various sensor information (for example, information from temperature sensors, load cells, vibration sensors, etc.).

第2実施形態のエレベータ揚重モニタリングシステム1が、エレベータELVのデータ収集部ELVE、入力部ELVF以外の外部システムとデータ連携してもよい。例えばエレベータ揚重モニタリングシステム1が、車両搬出入予定管理システム、搬入車両GPSシステム、資材管理システム等からデータを取得したり、エレベータ揚重モニタリングシステム1の内部において収集・分析したデータを外部システムに出力して活用したりしてもよい(例えば資材揚重フロア情報を出力し、資材管理システムにおいて活用してもよい)。 The elevator lift monitoring system 1 of the second embodiment may be data linked with an external system other than the data collection unit ELVE and the input unit ELVF of the elevator ELV. For example, the elevator lifting monitoring system 1 acquires data from a vehicle loading/unloading schedule management system, a loading vehicle GPS system, a material management system, etc., or collects and analyzes data inside the elevator lifting monitoring system 1 to an external system. It may be output and used (for example, material lifting floor information may be output and used in a material management system).

第2実施形態のエレベータ揚重モニタリングシステム1が、エレベータELVのセンサELVDの出力信号などであるエレベータ稼働情報のAI分析によるエレベータELVの故障予知/最適な作業員搬送計画の支援機能を備えていてもよい。 The elevator lifting monitoring system 1 of the second embodiment has a support function for failure prediction of the elevator ELV/optimal worker transport planning by AI analysis of the elevator operation information such as the output signal of the sensor ELVD of the elevator ELV. good too.

第1および第2実施形態のエレベータ揚重モニタリングシステム1によれば、エレベータが複数台あるような大型現場でも、現地に行くことなく施工状況の把握が可能になる。また、自動でリアルタイムに揚重作業を分析・表示できるため、手書きの実績記録・集計が行われる従来手法と比較して手間や工数を大幅に削減できる。更に、従来手法では把握が困難な荷重値などの詳細なデータがリアルタイムに収集可能になる。つまり、施工状況把握の効率化・自動化・リアルタイム化を促進することができる。
第1および第2実施形態のエレベータ揚重モニタリングシステム1によれば、揚重時間を例えば資材ごと/エレベータごと/乗員数ごと等のように多角的に分析できるため、どの作業に問題があるか、何が原因かを従来手法よりも早期に発見して計画改善に活用することができる。また、エレベータ故障情報(稼働情報)を遠隔からも確認できるため、故障時に早期対応、遠隔対応することができる。蓄積された様々な情報をAI故障予知の学習データとして利用することにより、故障を未然に防ぐことができる。更に、クラウドサーバを導入することにより、施工事業者において全社的な蓄積データの活用や一元管理が可能となる。
According to the elevator lifting monitoring system 1 of the first and second embodiments, it is possible to grasp the construction status without going to the site even in a large site where there are a plurality of elevators. In addition, since the lifting work can be automatically analyzed and displayed in real time, it is possible to greatly reduce the labor and man-hours compared to the conventional method of manually recording and tallying results. Furthermore, detailed data such as load values, which are difficult to grasp with conventional methods, can be collected in real time. In other words, it is possible to promote efficiency, automation, and real-time grasping of the construction status.
According to the elevator lifting monitoring system 1 of the first and second embodiments, the lifting time can be multilaterally analyzed for each material/elevator/number of passengers, etc., so which work has a problem. , it is possible to discover the cause earlier than the conventional method and utilize it for planning improvement. In addition, since the elevator failure information (operating information) can be confirmed remotely, it is possible to respond early and remotely in the event of a failure. By using various accumulated information as learning data for AI failure prediction, failures can be prevented. Furthermore, by introducing a cloud server, it becomes possible for construction companies to use company-wide accumulated data and centrally manage it.

以上、本発明の実施形態を、図面を参照して詳述してきたが、具体的な構成はこれらの実施形態および各例に限られるものではなく、本発明の趣旨を逸脱しない範囲で適宜変更を加えることができる。上述した各実施形態および各例に記載の構成を組み合わせてもよい。 Although the embodiments of the present invention have been described in detail above with reference to the drawings, the specific configuration is not limited to these embodiments and examples, and can be changed as appropriate without departing from the scope of the present invention. can be added. You may combine the structure as described in each embodiment and each example which were mentioned above.

なお、上述した実施形態におけるエレベータ揚重モニタリングシステム1が備える各部の機能全体あるいはその一部は、これらの機能を実現するためのプログラムをコンピュータ読み取り可能な記録媒体に記録して、この記録媒体に記録されたプログラムをコンピュータシステムに読み込ませ、実行することによって実現しても良い。なお、ここでいう「コンピュータシステム」とは、OSや周辺機器等のハードウェアを含むものとする。
また、「コンピュータ読み取り可能な記録媒体」とは、フレキシブルディスク、光磁気ディスク、ROM、CD-ROM等の可搬媒体、コンピュータシステムに内蔵されるハードディスク等の記憶部のことをいう。さらに「コンピュータ読み取り可能な記録媒体」とは、インターネット等のネットワークや電話回線等の通信回線を介してプログラムを送信する場合の通信線のように、短時間の間、動的にプログラムを保持するもの、その場合のサーバやクライアントとなるコンピュータシステム内部の揮発性メモリのように、一定時間プログラムを保持しているものも含んでも良い。また上記プログラムは、前述した機能の一部を実現するためのものであっても良く、さらに前述した機能をコンピュータシステムにすでに記録されているプログラムとの組み合わせで実現できるものであっても良い。
It should be noted that all or part of the function of each part provided in the elevator lifting monitoring system 1 in the above-described embodiment can be achieved by recording a program for realizing these functions in a computer-readable recording medium, and storing the program in this recording medium. It may be realized by loading the recorded program into a computer system and executing it. It should be noted that the "computer system" referred to here includes hardware such as an OS and peripheral devices.
The term "computer-readable recording medium" refers to portable media such as flexible discs, magneto-optical discs, ROMs and CD-ROMs, and storage units such as hard discs incorporated in computer systems. Furthermore, "computer-readable recording medium" refers to a program that dynamically retains programs for a short period of time, like a communication line when transmitting a program via a network such as the Internet or a communication line such as a telephone line. It may also include a device that holds a program for a certain period of time, such as a volatile memory inside a computer system that serves as a server or client in that case. Further, the program may be for realizing part of the functions described above, or may be capable of realizing the functions described above in combination with a program already recorded in the computer system.

1…エレベータ揚重モニタリングシステム、11…揚重モニタリングサーバ、11A…稼働情報取得部、11B…入力情報取得部、11C…予定管理情報取得部、11D…揚重作業状況算出部、11E…表示画像生成部、11F…分析部、11G…記憶部、12…端末装置、12A…表示部、12B…操作部、13…予定管理システム、13A…記憶部 DESCRIPTION OF SYMBOLS 1... Elevator lifting monitoring system, 11... Lifting monitoring server, 11A... Operation information acquisition part, 11B... Input information acquisition part, 11C... Schedule management information acquisition part, 11D... Lifting work situation calculation part, 11E... Display image Generation unit 11F Analysis unit 11G Storage unit 12 Terminal device 12A Display unit 12B Operation unit 13 Schedule management system 13A Storage unit

Claims (5)

エレベータの揚重作業の状況をモニタリングするエレベータ揚重モニタリングシステムであって、
前記エレベータに設置されたデータ収集部によって収集された前記エレベータの稼働情報を取得する稼働情報取得部と、
前記稼働情報取得部によって取得された前記エレベータの稼働情報に基づいて、前記エレベータの揚重作業状況を算出する揚重作業状況算出部と、
前記揚重作業状況算出部によって算出された前記エレベータの揚重作業状況に基づいて、時間の経過に伴って変化する前記エレベータのアニメーション画像であって、前記エレベータの昇降方向に直交する方向から撮影された画像に相当する前記エレベータのアニメーション画像を生成する表示画像生成部と、
前記表示画像生成部によって生成された前記エレベータのアニメーション画像を表示する表示部とを備えるエレベータ揚重モニタリングシステム。
An elevator lifting monitoring system for monitoring the status of elevator lifting work,
an operation information acquisition unit that acquires operation information of the elevator collected by a data collection unit installed in the elevator;
a lifting work situation calculation unit that calculates a lifting work situation of the elevator based on the operation information of the elevator acquired by the operation information acquisition unit;
An animation image of the elevator that changes over time based on the lifting work situation of the elevator calculated by the lifting work situation calculation unit, and is photographed from a direction perpendicular to the ascending/descending direction of the elevator. a display image generation unit that generates an animation image of the elevator corresponding to the displayed image;
and a display unit for displaying the animation image of the elevator generated by the display image generation unit.
前記エレベータの稼働情報が前記稼働情報取得部によって取得された場合に、
前記揚重作業状況算出部は、前記稼働情報取得部によって取得された前記エレベータの稼働情報と建物の設計データとに基づいて、前記建物に対して昇降する前記エレベータの揚重作業状況をリアルタイムに算出し、
前記表示画像生成部は、前記揚重作業状況算出部によって算出された前記建物に対して昇降する前記エレベータの揚重作業状況に基づいて、前記建物を含む前記エレベータのアニメーション画像をリアルタイムに生成し、
前記表示部は、前記表示画像生成部によって生成された前記建物を含む前記エレベータのアニメーション画像をリアルタイムに表示する、
請求項1に記載のエレベータ揚重モニタリングシステム。
When the operating information of the elevator is acquired by the operating information acquiring unit,
The lifting work status calculation unit calculates the lifting work status of the elevator moving up and down relative to the building in real time based on the operation information of the elevator and the design data of the building acquired by the operation information acquisition unit. calculate,
The display image generation unit generates an animation image of the elevator including the building in real time based on the lifting work situation of the elevator moving up and down with respect to the building calculated by the lifting work situation calculation unit. ,
The display unit displays in real time an animation image of the elevator including the building generated by the display image generation unit.
The elevator lift monitoring system of claim 1.
前記エレベータ揚重モニタリングシステムは、
前記稼働情報取得部と前記揚重作業状況算出部と前記表示画像生成部とを備える揚重モニタリングサーバと、
前記表示部を備える端末装置と、
予定管理システムとを備え、
前記揚重モニタリングサーバは、
前記エレベータに設置された入力部にエレベータオペレータによって入力された入力情報を取得する入力情報取得部と、
前記予定管理システムによって管理されている前記エレベータの予定管理情報を取得する予定管理情報取得部と、
前記稼働情報取得部によって取得された前記エレベータの稼働情報と、前記入力情報取得部によって取得された入力情報と、前記予定管理情報取得部によって取得された前記エレベータの予定管理情報とを組み合わせることによって、前記エレベータの揚重作業の進捗状況をリアルタイムに分析する分析部とを備える、
請求項1に記載のエレベータ揚重モニタリングシステム。
The elevator lift monitoring system includes:
a lifting monitoring server comprising the operation information acquiring unit, the lifting work situation calculating unit, and the display image generating unit;
a terminal device comprising the display unit;
with an appointment management system,
The lifting monitoring server,
an input information acquisition unit that acquires input information input by an elevator operator to an input unit installed in the elevator;
a schedule management information acquisition unit that acquires schedule management information of the elevator managed by the schedule management system;
By combining the elevator operation information acquired by the operation information acquisition unit, the input information acquired by the input information acquisition unit, and the elevator schedule management information acquired by the schedule management information acquisition unit , an analysis unit that analyzes the progress of the lifting work of the elevator in real time,
The elevator lift monitoring system of claim 1.
エレベータの揚重作業の状況をモニタリングするエレベータ揚重モニタリング方法であって、
前記エレベータに設置されたデータ収集部によって収集された前記エレベータの稼働情報を取得する稼働情報取得ステップと、
前記稼働情報取得ステップにおいて取得された前記エレベータの稼働情報に基づいて、前記エレベータの揚重作業状況を算出する揚重作業状況算出ステップと、
前記揚重作業状況算出ステップにおいて算出された前記エレベータの揚重作業状況に基づいて、時間の経過に伴って変化する前記エレベータのアニメーション画像であって、前記エレベータの昇降方向に直交する方向から撮影された画像に相当する前記エレベータのアニメーション画像を生成する表示画像生成ステップと、
前記表示画像生成ステップにおいて生成された前記エレベータのアニメーション画像を表示する表示ステップとを備えるエレベータ揚重モニタリング方法。
An elevator lifting monitoring method for monitoring the status of elevator lifting work, comprising:
an operation information acquisition step of acquiring operation information of the elevator collected by a data collection unit installed in the elevator;
a lifting work situation calculating step of calculating a lifting work situation of the elevator based on the operating information of the elevator acquired in the operating information acquiring step;
An animation image of the elevator that changes over time based on the lifting work situation of the elevator calculated in the lifting work situation calculation step, and is photographed from a direction orthogonal to the ascending/descending direction of the elevator. a display image generating step of generating an animation image of the elevator corresponding to the image displayed;
and a display step of displaying the animation image of the elevator generated in the display image generation step.
エレベータの揚重作業の状況をモニタリングする揚重モニタリングサーバを構成するコンピュータに、
前記エレベータに設置されたデータ収集部によって収集された前記エレベータの稼働情報を取得する稼働情報取得ステップと、
前記稼働情報取得ステップにおいて取得された前記エレベータの稼働情報に基づいて、前記エレベータの揚重作業状況を算出する揚重作業状況算出ステップと、
前記揚重作業状況算出ステップにおいて算出された前記エレベータの揚重作業状況に基づいて、時間の経過に伴って変化する前記エレベータのアニメーション画像であって、前記エレベータの昇降方向に直交する方向から撮影された画像に相当する前記エレベータのアニメーション画像を生成する表示画像生成ステップとを実行させるためのプログラムであって、
前記表示画像生成ステップにおいて生成された前記エレベータのアニメーション画像は端末装置において表示される、
プログラム。
A computer that constitutes a lifting monitoring server that monitors the status of elevator lifting work,
an operation information acquisition step of acquiring operation information of the elevator collected by a data collection unit installed in the elevator;
a lifting work situation calculating step of calculating a lifting work situation of the elevator based on the operating information of the elevator acquired in the operating information acquiring step;
An animation image of the elevator that changes over time based on the lifting work situation of the elevator calculated in the lifting work situation calculation step, and is photographed from a direction orthogonal to the ascending/descending direction of the elevator. and a display image generating step of generating an animation image of the elevator corresponding to the displayed image,
the animated image of the elevator generated in the display image generating step is displayed on a terminal device;
program.
JP2021193346A 2021-11-29 2021-11-29 Elevator lifting monitoring system, elevator lifting monitoring method and program Pending JP2023079740A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021193346A JP2023079740A (en) 2021-11-29 2021-11-29 Elevator lifting monitoring system, elevator lifting monitoring method and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021193346A JP2023079740A (en) 2021-11-29 2021-11-29 Elevator lifting monitoring system, elevator lifting monitoring method and program

Publications (1)

Publication Number Publication Date
JP2023079740A true JP2023079740A (en) 2023-06-08

Family

ID=86647343

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021193346A Pending JP2023079740A (en) 2021-11-29 2021-11-29 Elevator lifting monitoring system, elevator lifting monitoring method and program

Country Status (1)

Country Link
JP (1) JP2023079740A (en)

Similar Documents

Publication Publication Date Title
JP4795457B2 (en) Elevator maintenance management system
JP5334010B2 (en) Elevator maintenance management device
US11030560B1 (en) Dispatch system
CN103910260A (en) Elevator automatic spot inspection system
CN110775734B (en) Method for understanding and planning elevator usage
JP2016166070A (en) Maintenance work support device, system and method for elevator
JP2006056677A (en) Elevator operational situation monitoring system
JP4533265B2 (en) Earthquake information providing device
CN116151547A (en) Cleaning task execution method and device
JP2009155042A (en) Group supervisory elevator performance assessment device
CN110300146A (en) With capture and the maintenance tool reset
JP2005272067A (en) Maintenance track record managing device of elevator
JP5502376B2 (en) Wide area disaster communication system and communication method
CN111086936B (en) Elevator information display system
JP2023079740A (en) Elevator lifting monitoring system, elevator lifting monitoring method and program
JP5334013B2 (en) Property data confirmation system for local elevators
JP4928761B2 (en) Group management elevator system
KR20140066451A (en) System for providing operation information of construction lift and display apparatus for construction lift
JP7185607B2 (en) An operating state information providing device, an operating state information providing method, and a program.
JP2023079739A (en) Crane lifting monitoring system, crane lifting monitoring method and program
JP2010218324A (en) Task allocation device, task allocation method and task allocation program
JPH08310757A (en) Elevator maintenance work support system
JP4523432B2 (en) Integrated elevator maintenance information provision system
JP7248073B1 (en) Confinement situation estimation device, dispatch planning system, confinement situation estimation method, control method, program
WO2017163757A1 (en) Information processing device and information processing method