JP2023062342A - Method of underground installation of large pipes and bottomed buried pipes - Google Patents
Method of underground installation of large pipes and bottomed buried pipes Download PDFInfo
- Publication number
- JP2023062342A JP2023062342A JP2021172246A JP2021172246A JP2023062342A JP 2023062342 A JP2023062342 A JP 2023062342A JP 2021172246 A JP2021172246 A JP 2021172246A JP 2021172246 A JP2021172246 A JP 2021172246A JP 2023062342 A JP2023062342 A JP 2023062342A
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- buried
- bottomed
- excavation
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Earth Drilling (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
Description
本発明は、地震、津波、台風等自然災害や人災時の人や物の一時避難用のシェルター、、物や食物保管用の保管庫、レジャー用その他多目的の空間を形成可能な大型管の地中建込み方法及び有底埋設管に関する。 The present invention is a large-scale pipe land that can form a temporary evacuation shelter for people and goods in the event of natural disasters such as earthquakes, tsunamis, typhoons, and man-made disasters, a storehouse for storing goods and food, and a multi-purpose space for leisure. It relates to a medium erection method and a bottomed buried pipe.
出願人は、地震、津波、台風等自然災害や人災時に人や物の一時避難、物や食物保管用のシェルター、レジャー用その他多目的空間を、比較的短期で地下設置可能であり、低コストで簡易に施工でき、しかも占有平面スペースが小さくて地上構築物や設備に左右されにくい大型有底管体について、特許文献1において提案した。
Applicant can install temporary evacuation shelter for people and goods, shelter for storage of goods and food, leisure and other multi-purpose space in the event of natural disasters such as earthquakes, tsunamis and typhoons or man-made disasters in a relatively short period of time and at a low cost.
特許文献1は大型管体を地中に圧入後、管体の上端開口から水中コンクリートを供給して大型管体の下端より下方の凹部に投入して管の下端外部のコンクリート基盤を形成し、この後に管体内を下降させて充填孔付きの底蓋を管体の下端部分に配置し、さらにその充填孔を介して底蓋下面と管外のコンクリート基盤との隙間にモルタルを注入して底蓋と管外のコンクリート基盤とを一体化させて管体底部を構築しようとするものである。
In
この方法では、大型管体の地中建込みについて管体の地中圧入後に管の下端側において管内への水の進入を抑制しながら底蓋の端部を管の内壁に溶接接合することができる。しかしながら、管体を地中に圧入後にコンクリートを供給していったん大型管体の下端の下方の凹部に該コンクリートを投入し、その後管体の下端側に配置した底蓋の充填孔からモルタル注入して底蓋下面と管外のコンクリート基盤との隙間にモルタルを注入するので、底蓋下面側のコンクリート基盤の状態を確認できないままに作業を行わなければならない。また、底蓋の充填孔からのモルタル注入作業は限られたスペースでの狭所作業であり、作業段取りや注入作業に時間がかかり、作業コストがかかる。また、注入後の底蓋下面と管外のコンクリート基盤との隙間の充填を確認できないので必要以上のモルタル注入を行って作業全体、あるいは材料に無用なコストがかかる問題があった。これに対し、出願人は、管内壁にリブ部等を取り付けた管本体の内側の土を排出しながら該管本体を地中鉛直方向に圧入する工程と、管本体を計画深さまで圧入後に管本体内のリブ部分に対応する高さまで生コンクリートを投入する工程と、生コンクリートの硬化後に、管本体内で底蓋を吊下ろして硬化コンクリートの上部に配置する工程と、底蓋の外縁と管本体の内壁面とを溶接して管本体と底蓋とを接合する工程と、を含む大型有底管体の建込み方法を特願2020-192207号により提案した。 In this method, when a large pipe is erected underground, it is possible to weld the end of the bottom cover to the inner wall of the pipe while suppressing the ingress of water into the pipe at the lower end of the pipe after the pipe is pressed into the ground. can. However, after the tubular body is pressed into the ground, concrete is supplied, once the concrete is put into the concave portion below the lower end of the large tubular body, and then mortar is injected from the filling hole of the bottom cover arranged on the lower end side of the tubular body. Since the mortar is injected into the gap between the lower surface of the bottom lid and the concrete base outside the pipe, the work must be done without checking the condition of the concrete base on the lower surface of the bottom lid. In addition, the mortar injection work from the filling hole of the bottom cover is work in a narrow space in a limited space, and work setup and injection work take time and work costs. In addition, since filling of the gap between the lower surface of the bottom lid and the concrete base outside the pipe cannot be confirmed after pouring, there is a problem in that the mortar is poured more than necessary, resulting in unnecessary costs for the entire work and materials. On the other hand, the applicant proposes a process of press-fitting the pipe body vertically into the ground while discharging the soil inside the pipe body with ribs attached to the inner wall of the pipe, and A process of pouring ready-mixed concrete up to a height corresponding to the rib part inside the main body, a process of suspending the bottom cover inside the pipe body after the ready-mixed concrete has hardened and placing it on top of the hardened concrete, and a process of placing the outer edge of the bottom cover and the pipe Japanese Patent Application No. 2020-192207 proposes a method for erecting a large-sized bottomed tubular body including a step of welding the inner wall surface of the main body to join the pipe main body and the bottom cover.
この方法では、管本体内のリブ部分まで投入するコンクリートの状態等を目視しながら充填作業を行えるので作業状態や作業終了の確認を確実に行える利点がある。一方、この方法では、管本体の地下十数メートルまでの圧入後、生コンクリートを管内に投入して管内下端部の所要高さまで充填する作業であるから、暗所で多湿の劣悪な作業環境下で作業者による管内補助作業が必要である。また、作業時間が掛かりまた、コンクリートの場所打ち工法の一つであるから水の漏洩の有無確認を確実に行うことは困難であった。さらに、作業コストが大幅に膨らむ問題があった。 This method has the advantage that the filling work can be performed while visually checking the state of the concrete to be poured up to the rib portion in the pipe body, so that the working state and the completion of the work can be confirmed reliably. On the other hand, in this method, after the main body of the pipe is pressed into the pipe to a depth of ten and several meters underground, ready-mixed concrete is poured into the pipe and filled to the required height at the lower end of the pipe. Assistance work inside the pipe by workers is required. In addition, it takes a long time to work, and since it is one of the cast-in-place concrete construction methods, it is difficult to reliably check for water leakage. Furthermore, there is a problem that the work cost increases significantly.
本発明は上記従来の課題に鑑みてなされたものであり、その一つの目的は、簡単な工程の組合せで円滑、確実に埋設管の埋設作業を遂行し、かつ施工後に漏水等を生じることを確実に防止し得る大型管の地中建込み方法及び有底埋設管を提供することにある。また、本発明の他の目的は、短時間で低コストにより埋設管の埋設作業を完了させることができる大型管の地中建込み方法及び有底埋設管を提供することにある。 SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned conventional problems, and one of the objects thereof is to achieve smooth and reliable burying work of buried pipes by a combination of simple processes and to prevent water leakage after construction. To provide an underground installation method for a large-sized pipe and a bottomed buried pipe which can surely prevent such accidents. Another object of the present invention is to provide a method for burying a large pipe underground and a bottomed buried pipe, which can complete the work of burying a buried pipe in a short period of time and at low cost.
上記課題を解決するために本発明は、管内空間を種々の用途に用いるべく地中に縦方向に埋設させる大型の埋設管の建込み方法であり、埋設させる管1より径大の先行掘削管20であり、埋設管1の平面視埋設外径を内包する管壁位置となるように埋設管1の埋設に先立って地面に対して該先行掘削管20を圧入掘削させる工程と、先行掘削管20の掘削と同時に管内の掘削土を排土する工程と、計画深さまで先行掘削管20を圧入させた後に掘削管20の管内空間100に有底埋設管1を挿入降下させて先行掘削管20と埋設管1とで二重管状に配置させる工程と、埋設管1を所定深さ位置まで挿入した後に先行掘削管20を抜き上げる工程と、を含む大型管の地中建込み方法から構成される。
In order to solve the above problems, the present invention is a method for erecting a large-sized buried pipe that is vertically buried in the ground so that the pipe inner space can be used for various purposes. 20, a step of press-fitting and excavating the preceding
その際、先行掘削管20を計画深さまで圧入させた後に該先行掘削管の管内空間100に挿入降下させる有底埋設管1の内底部には、地中側からの浮力に対する抗浮力錘部が設けられるとよい。
At that time, the inner bottom of the bottomed buried
また、有底埋設管1の底外部には下方に先端側を向けた旋回食込器401が設けられ、有底埋設管1の先行掘削管20の管内空間100への挿入降下後に有底埋設管1自体を縦軸回りに旋回させる工程を含むとなおよい。
In addition, a swivel inserter 401 is provided on the outside of the bottom of the bottomed buried
また、本発明は、先行掘削管20を計画深さまで圧入させた後に 先行掘削管20の管内空間100に挿入降下させる有底埋設管1であり、その内底部には、地中側からの浮力に対する抗浮力錘部30が設けられ有底埋設管から構成される。
In addition, the present invention is a bottomed buried
その際、底外部に下方に先端側を向けた旋回食込器4が設けられてもよい。
In this case, a
本発明の大型有底管体の建込み方法及び有底埋設管によれば、管本体の改良により作業工程を大幅に簡略化でき、各作業自体が簡単、明確で作業時間を大幅に短縮でき、さらに作業コストを大幅に低減することが可能である。 According to the method of erecting a large bottomed pipe body and the bottomed buried pipe of the present invention, the work process can be greatly simplified by improving the pipe body, and each work itself is simple and clear, and the work time can be greatly shortened. Furthermore, it is possible to greatly reduce the work cost.
以下、添付図面を参照しつつ本発明の大型管の地中建込み方法及び有底埋設管の実施形態について説明する。 BEST MODE FOR CARRYING OUT THE INVENTION An embodiment of a large pipe underground installation method and a bottomed buried pipe according to the present invention will be described below with reference to the accompanying drawings.
本発明に係る大型管の地中建込み方法に用いられる大型の有底埋設管は、管内空間を種々の用途に用いるために埋設し建込みされる。例えば地震その他の自然災害、戦争その他の人的災害からの避難用シェルター等として使用される。また書類、宝飾品、磁気テープ、フィルムその他の電子記録媒体等の保管庫等として使用され得る。また、薬品、薬剤、水、その他の液体、その他の有価物資材の倉庫、その他任意の用途の空間利用用管体として用いられる。本発明に係る大型の有底埋設管は内部に空間を有し底部が閉鎖された中空の有底管体である。管体は、例えば直径が2メートル以上~5メートル程度で、地中深さが例えば5メートル~20メートル、あるいはそれ以上の地中深さで埋設される管体であり、火山灰土や粘土質土の地中はもとより、特に地中に水や転石を多く含む地域においても有効に用いられる。本発明の大型管の地中建込み方法は、これらの地域において有効に活用し得る。 A large-sized buried pipe with a bottom used in the underground installation method for a large-sized pipe according to the present invention is buried and erected in order to use the space inside the pipe for various purposes. For example, it is used as an evacuation shelter from earthquakes and other natural disasters, wars and other man-made disasters, and the like. It can also be used as a storehouse for documents, jewelry, magnetic tapes, films and other electronic recording media. In addition, it is used as a space-utilizing tubular body for storage of chemicals, drugs, water, other liquids, other valuable materials, and other arbitrary uses. A large-sized buried pipe with a bottom according to the present invention is a hollow bottomed tubular body having a space inside and a closed bottom. The tubular body is, for example, a tubular body having a diameter of about 2 m to 5 m and a depth of 5 m to 20 m or more, which is buried in the ground, and is made of volcanic ash or clay. It can be effectively used not only in the ground of the soil, but also in areas where the ground contains a lot of water and boulders. The underground installation method for large pipes of the present invention can be effectively utilized in these areas.
本発明の大型有底管体はその建込み工程によって部材の構成が異なるので、各工程とともに大型有底管体について説明する。 Since the structure of the members of the large-sized bottomed tubular body of the present invention differs depending on the erection process, the large-sized bottomed tubular body will be described together with each process.
[第一工程]
図1ないし図7は、本発明の大型管の地中建込み方法の一実施形態を説明している。図1は地中に略鉛直方向に圧入させる先行掘削管20と、埋設管1と、の圧入位置関係を示す平面説明図であり、内側の一点鎖線示の管が最終的に埋設して建込みする埋設管1であり、外側の実線示の管が先行掘削管20を示す。この方法では、建て込み位置が設定された地盤G中に先行掘削管20を圧入しつつ排土させ、先行掘削管20内側の空間100に最終的に建込みする埋設管1を挿入降下させ、その後、先行掘削管20を地上に抜き上げることにより大型管を建込みさせるものである。
[First step]
1 to 7 illustrate an embodiment of the method for erecting large pipes underground according to the present invention. FIG. 1 is an explanatory plan view showing the press-fit positional relationship between a preceding
先行掘削管20は、図2,4,5に示すように、両端部(図中では上下)を開口した鋼製の円筒管からなる、いわゆるケーシングチューブと称される鋼管である。単一鋼管で目的の地中深さに到達できる場合には1本の鋼管で構成されるが、複数鋼管を連結して使用するのが通常である。通常は、数メートル直径で数メートルの軸方向長さのユニット管をチュービング装置で把持させて軸回り方向に回転させながら地中に圧入させる。チュービング装置内で1つのユニット管の圧入降下が完了しない状態で他のユニット管の管端同士を溶接又は管内外の水密保持状態で任意の締結手段により接続しながら、順次、圧入下降させる。例えば、カップリング部材を用いて上下対向させたユニット管の管端どうしをねじ締結し、複数の管体を連結して例えば20m程度の長さの一体の先行掘削管を形成しながら圧入下降させてもよい。本実施形態では、図4(b)に示すように、管内外を水密保持のために地上にて予め溶接部10において、溶接連結している。先行掘削管20は、下端に複数の掘削ビット部21を取り付けており、チュービング装置40の軸回り回転に伴い回転あるいは旋回掘削しながら下方に掘り進んでいく。これによって、転石が多い地盤であっても掘削ビット21部で岩盤等を破砕しつつ確実に下方へ掘進することができる。掘削ビット部21は、掘削ビット21aを間隔を設けて管本体の下端縁に環状に複数個固定して構成されている。後述するように、管本体1を地中に圧入するには専用機械装置により管本体の長手軸周り方向に回転させながら圧入するが、管本体1の下端縁に掘削ビット部21を取り付けることにより圧入途中に硬い岩盤層などが存在している場合でも管本体を回転させながらこれらを切り崩して地中に進入させることができる。
As shown in FIGS. 2, 4 and 5, the
図2,3において、地面上にチュービング装置40が設置されており、このチュービング装置40の中央に軸心を縦方向に配置した先行掘削管20をチャックで掴み、先行掘削管20を回転させながら地中に押し込みさせる。図2において、チュービング装置40は、機体枠41に支持された図示しない管回転用の回転体、回転体を回転可能に支持する昇降フレーム、昇降装置、チャック部材、チャックシリンダ等を有する公知の全回転チュービング装置である。チュービング装置40の下面で地面上には受板42が予め載置されている。また、チュービング装置40を両側から挟みつけるようにカウンタウエイト43が配置されている。カウンタウエイト43は、大型の管体の圧入操作に際してチュービング装置40が反動で移動しないようにチュービング装置40全体を安定化させる。
In FIGS. 2 and 3, a
本発明に係る大型管の地中建込み方法における第1の工程は、埋設させる管より径大の先行掘削管であり、埋設管1の平面視埋設外径を内包する管壁位置となるように埋設管1の埋設に先立って地面に対して該先行掘削管20を圧入掘削させる。すなわち、例えば図1において最終的に埋設して建て込むべき管1の地上平面位置に対応した中心位置Qについて、チュービング装置40の回動中心を設定し、これに埋設すべき管1より径大の先行掘削管20の中心位置をセットして、先行掘削管20を圧入埋設する。先行掘削管20と埋設本管1とは必ずしも同心位置に設定される必要はない。先行掘削管20の圧入掘削後、その管20内に本埋設用の管1を挿入配置させる間隔的余裕があればよい。実施形態では、理解を容易化するために、先行掘削管内に降下挿入される埋設本管1と先行掘削管20とは、直径線で縦断すると両端側にそれぞれ所要の間隔D(図5(b)参照)が形成され、先行掘削管20に接触しないように同心位置で直径が異なる円のように圧入される。これによって、先行掘削管20の圧入埋設位置が図1に示すように、埋設管1の平面視埋設外径を内包する先行掘削管の管壁位置となるように埋設管1の埋設に先立って地面に対して該先行掘削管20を圧入掘削させる。
The first step in the method of burying a large pipe in the ground according to the present invention is to excavate a pre-excavated pipe having a diameter larger than that of the pipe to be buried. Prior to burying the buried
先行掘削管20は、埋設本管1の埋設建込みに先立って該埋設管1を挿入配置するための地中空隙を形成すべく、先行して掘削しつつ管内を排土し、管内に空間100を形成する。そして、掘削後の管内空間に埋設本管を挿入配置させる際に形成された縦穴の周壁が崩壊しないように崩落防止管として機能する。
Prior to the construction of the buried
[第二工程]
先行掘削管20のチュービング装置40による回転圧入掘削と同時に先行掘削管の下端の掘削ビット21を介した掘削により管内に排出されて生じる掘削土は排土される。すなわち、図30において、チュービング装置40で先行掘削管20を回転させながら地中に圧入する際、同時に先行掘削管20の内側の土を排土機44で地上側に排出させる。実施形態において、排土機は、クローラクレーン等重機により吊支され、落下力によって地盤に打ち込み、土砂をつかみ取る方式のグラブハンマー等の公知の大口径掘削機械が用いられている。なお、先行掘削管の掘削に際し、深度を徐々に大きくするに従い通常は、管本体の下端側の地中から水が管の内側に浸出してくる場合が多い。水の浸出は数メートルの深度でも数十メートルの深度でも
あり得る。
[Second step]
Simultaneously with rotary press-in excavation of the preceding
[第三工程]
図4において、排土機44により管内を排土させながら計画深さまで先行掘削管20を圧入させた後に該先行掘削管20の管内空間に埋設本管としての有底埋設管1を挿入降下させて先行掘削管と埋設管とで二重管状に配置させる(図5参照)。図4(b)において、先行掘削管20の内側に配置しする有底埋設管1は、上端側となる一端側を開口した鋼製の円筒管からなる、いわゆるケーシングチューブと称される鋼管である。複数鋼管を連結して構成される。
[Third step]
In FIG. 4, after the preceding
有底埋設管1は、下端が水密状態を保持して内外を閉鎖するように底壁2が予め地上側の製作で取付られている。さらに、埋設管1の内部であって底壁2の上部、すなわち有底埋設管1の内底部には抗浮力錘部3が設けられている。抗浮力錘部3は、先行掘削管を計画深さまで圧入掘削させた後に該先行掘削管の管内空間に有底埋設管1を挿入降下させる際に、管の下端の地中側からの浸出水の浮力に対抗して有底埋設管1が浮き上がらないようにするものである。抗浮力錘部3は、浮力に対抗し得る重力を有する有体物であればよく、鋼材やコンクリート、あるいはそれらの廃材等でもよい。なお、それらの抗浮力錘部3の上面は、管内空間の利用形態に応じて任意のフローリングが施される。
The bottomed buried
さらに、本実施形態において、有底埋設管1の底壁1の外部には下方に先端側を向けた旋回食込器4が設けられている。旋回食込器4は、有底埋設管1を先行掘削管20の管内空間へ挿入降下させて着底した後に、有底埋設管1自体を縦軸回りに旋回させて底壁2外の地盤に有底埋設管1の底部を食い込ませて地盤Gに一体化させる手段であり、本実施形態において、図4~図7に示すように、スクリュ軸5とスクリュ軸5外周回りに螺旋刃6を取り付けたスクリュ羽根7から構成されている。旋回食込器4は本体側を旋回させることにより地面に食い込んでいく機構であれば、任意の構造の装置を採用することができる。また、計画深さ部分の地盤状態に応じて下方に長いスクリュ羽根としてもよい。実施形態では、二重管状態に配置された先行掘削管とその内側に挿入された有底埋設管1との上部を連結し、両管を一体としてチュービング装置で旋回させて有底埋設管1の地盤への食い込み状態を確保するようにしている。
Further, in the present embodiment, a
有底埋設管1を先行掘削管20の内側に同心状位置に挿入降下させるに際しては、所要の軸方向長さのユニット管をチュービング装置40で把持しながらそのまま降下させてもよいし、また、重機クレーン等の吊支装置に支持させた状態で挿入降下させてもよい。その際、両管間の空隙Dを保持して円滑迅速に有底埋設管1は先行掘削管20の内側に挿入配置される。
When inserting and lowering the bottomed buried
[第四工程]
埋設管1を所定深さ位置まで挿入した後に先行掘削管20を抜き上げる。先行掘削管20の地上側への抜き上げ作業について、チュービング装置40で把持させて軸回り反対方向に回転させながら地中に抜き上げることもできる。この場合、先行掘削管20の圧入掘削、埋設管1の管20内側への挿入配置、先行掘削管20の抜き上げ操作まで、主要な装置の段取り替えの必要がない。したがって、作業工数が大幅に削減でき、作業時間短縮、作業労力の軽減、作業コストの大幅低減を達成し得る。なお、クレーンその他の吊り上げ機能を有する重機を用いて先行掘削管20を抜き上げるようにしてもよい。
[Fourth step]
After inserting the buried
実施形態では、先行掘削管20を地上側に抜き上げた跡に形成される隙間に例えばグラウト材等の流動固化材を注入して固化部12を形成し、地盤と一体化させている。なお、両管間の間隔の大きさや地盤の状態によってはこの固化部12の形成は必ずしも行わなくともよい。
In the embodiment, a solidified
上記のように、地中において先行掘削管20でその内側に有底埋設管1の収容空間を形成し、周壁の土留めを施した状態で収容空間に有底埋設管1を挿入降下させ、地盤側と固定させるから、有底埋設管1内での諸設備の設置、施工、構築、インテリア配備その他の管内空間利用のための設備等を地上にて行うことができる。また、有底埋設管1の止水のための全体工事、確認も地上側で行えるから埋設管1内への水の侵入対策の万全を期することができる。例えば動力付きの昇降ラックや、換気装置、設備、備品、食料、物品の保管設備等構築、災害避難用のシェルター、その他任意の用途の利用形態について、地上側で設計し具体的に管内に設備した状態で挿入降下して埋設管を利用することができる。
As described above, a storage space for the bottomed buried
上記第1~第4工程により大型管の地中建込みを行うことにより、有底埋設管1内での利用目的に応じた組立て設備施工を予め地上側で管内について行うから設備の精度の良い完成状態を保持することができるばかりでなく、作業工程が簡単で工程数も少なく作業時間短縮、工期短縮、作業コスト大幅低減に資する。特に、地上側で管底部からの地下水の侵入防止対策を万全に施して安定的かつ安全に管内利用を持続させることが可能である。
By carrying out the underground installation of the large-sized pipe in the above-mentioned first to fourth steps, the assembly equipment construction according to the purpose of use in the bottomed buried
また、先行掘削管を計画深さまで圧入させた後に該先行掘削管の管内空間に挿入降下させる有底埋設管の内底部には、地中側からの浮力に対する抗浮力錘部が設けられていることにより、先行掘削管の管内空間に有底埋設管1を挿入降下させる際に、管の下端の地中側からの浸出水の浮力により埋設本管1が不安定となることなく安定的に先行掘削管の管内空間に配置させることができる。
In addition, an anti-buoyancy weight section against buoyancy from the underground side is provided on the inner bottom of the bottomed buried pipe that is inserted and lowered into the internal space of the preceding drilling pipe after the preceding drilling pipe has been press-fitted to the planned depth. As a result, when the bottomed buried
また、有底埋設管の底外部には下方に先端側を向けた旋回食込器が設けられ、有底埋設管の先行掘削管の管内空間への挿入降下後に有底埋設管自体を縦軸回りに旋回させる工程を含むことにより、先行掘削管20の管内空間において着底した後に、有底埋設管1自体の縦軸回り旋回により、旋回食込器を介して底壁22外の地盤に有底埋設管1の底部を食い込ませて地盤Gに一体化させることが可能である。
In addition, on the outside of the bottom of the bottomed buried pipe, a swivel inserter is provided with the tip side facing downward, and after the preceding excavation pipe of the bottomed buried pipe is inserted and lowered into the pipe interior space, the bottomed buried pipe itself is vertically rotated. By including the step of turning around, after reaching the bottom in the pipe inner space of the preceding
また、本発明の有底埋設管は、上記の方法により大型管の地中建込みを行う方法において用いる有底埋設管であり、先行掘削管を計画深さまで圧入させた後に先行掘削管の管内空間に挿入降下させる有底埋設管であり、その内底部には、地中側からの浮力に対する抗浮力錘部が設けられている構成とすることにより、先行掘削管の管内空間に有底埋設管1を挿入降下させる際に、管の下端の地中側からの浸出水の浮力により埋設本管1が不安定となることなく安定的に先行掘削管の管内空間に配置させることができる。
Further, the bottomed buried pipe of the present invention is a bottomed buried pipe used in the above-described method for burying a large pipe underground. It is a bottomed burial pipe that is inserted and lowered into a space, and the inner bottom is provided with a buoyancy counterweight against the buoyancy from the underground side. When the
また、上記の有底埋設管は、底外部に下方に先端側を向けた旋回食込器が設けられていることにより、先行掘削管20の管内空間において着底した後に、有底埋設管1自体の縦軸回り旋回により、旋回食込器を介して底壁2外の地盤に有底埋設管1の底部を食い込ませて地盤Gに一体化させることが可能である。
In addition, since the above-mentioned bottomed buried pipe is provided with a swivel bite device facing downward on the outside of the bottom, the bottomed buried
以上説明した本発明の大型管の地中建込み方法及び有底埋設管は、上記した実施形態のみの構成に限定されるものではなく、特許請求の範囲に記載した発明の本質を逸脱しない範囲において、他の実施形態を用いるようにしてもよい。 The method for erecting a large pipe underground and the buried pipe with a bottom according to the present invention described above are not limited to the configurations of the above-described embodiments only, and are within the scope of the invention described in the claims. , other embodiments may be used.
本発明の大型管の地中建込み方法及び有底埋設管は、地震、津波、土砂災害、戦時危険状態等でシェルターとして利用できるうえ、通常には種々の物品の収納、保管倉庫などでも利用することができる。また、光や空気についての生育条件がそれほど厳しくないきのこ類栽培空間を形成することもできる。 The method for erecting large pipes underground and the bottomed buried pipe of the present invention can be used as a shelter in the event of an earthquake, tsunami, landslide disaster, wartime danger, etc., and can also be used for the storage of various goods, storage warehouses, etc. can do. It is also possible to create a mushroom cultivation space where the growing conditions for light and air are not so severe.
1 有底埋設管(埋設本管)
2 底壁
3 抗浮力錘部
4 旋回食込器
5 スクリュ軸
6 螺旋刃
7 スクリュ羽根
20 先行掘削管
21 掘削ビット部
21a 掘削ビット
40 チュービング装置
44 排土機
D 両管間の間隙
G 地盤
1 Bottomed buried pipe (buried main pipe)
2
本発明は、地震、津波、台風等自然災害や人災時の人や物の一時避難用のシェルター、、物や食物保管用の保管庫、レジャー用その他多目的の空間を形成可能な大型管の地中建込み方法及び有底埋設管に関する。 The present invention is a large-scale pipe land that can form a temporary evacuation shelter for people and goods in the event of natural disasters such as earthquakes, tsunamis, typhoons, and man-made disasters, a storehouse for storing goods and food, and a multi-purpose space for leisure. It relates to a medium erection method and a bottomed buried pipe.
出願人は、地震、津波、台風等自然災害や人災時に人や物の一時避難、物や食物保管用のシェルター、レジャー用その他多目的空間を、比較的短期で地下設置可能であり、低コストで簡易に施工でき、しかも占有平面スペースが小さくて地上構築物や設備に左右されにくい大型有底管体について、特許文献1において提案した。
Applicant can install temporary evacuation shelter for people and goods, shelter for storage of goods and food, leisure and other multi-purpose space in the event of natural disasters such as earthquakes, tsunamis and typhoons or man-made disasters in a relatively short period of time and at a low cost.
特許文献1は大型管体を地中に圧入後、管体の上端開口から水中コンクリートを供給して大型管体の下端より下方の凹部に投入して管の下端外部のコンクリート基盤を形成し、この後に管体内を下降させて充填孔付きの底蓋を管体の下端部分に配置し、さらにその充填孔を介して底蓋下面と管外のコンクリート基盤との隙間にモルタルを注入して底蓋と管外のコンクリート基盤とを一体化させて管体底部を構築しようとするものである。
In
この方法では、大型管体の地中建込みについて管体の地中圧入後に管の下端側において管内への水の進入を抑制しながら底蓋の端部を管の内壁に溶接接合することができる。しかしながら、管体を地中に圧入後にコンクリートを供給していったん大型管体の下端の下方の凹部に該コンクリートを投入し、その後管体の下端側に配置した底蓋の充填孔からモルタル注入して底蓋下面と管外のコンクリート基盤との隙間にモルタルを注入するので、底蓋下面側のコンクリート基盤の状態を確認できないままに作業を行わなければならない。また、底蓋の充填孔からのモルタル注入作業は限られたスペースでの狭所作業であり、作業段取りや注入作業に時間がかかり、作業コストがかかる。また、注入後の底蓋下面と管外のコンクリート基盤との隙間の充填を確認できないので必要以上のモルタル注入を行って作業全体、あるいは材料に無用なコストがかかる問題があった。これに対し、出願人は、管内壁にリブ部等を取り付けた管本体の内側の土を排出しながら該管本体を地中鉛直方向に圧入する工程と、管本体を計画深さまで圧入後に管本体内のリブ部分に対応する高さまで生コンクリートを投入する工程と、生コンクリートの硬化後に、管本体内で底蓋を吊下ろして硬化コンクリートの上部に配置する工程と、底蓋の外縁と管本体の内壁面とを溶接して管本体と底蓋とを接合する工程と、を含む大型有底管体の建込み方法を特願2020-192207号により提案した。 In this method, when a large pipe is erected underground, it is possible to weld the end of the bottom cover to the inner wall of the pipe while suppressing the ingress of water into the pipe at the lower end of the pipe after the pipe is pressed into the ground. can. However, after the tubular body is pressed into the ground, concrete is supplied, once the concrete is put into the concave portion below the lower end of the large tubular body, and then mortar is injected from the filling hole of the bottom cover arranged on the lower end side of the tubular body. Since the mortar is injected into the gap between the lower surface of the bottom lid and the concrete base outside the pipe, the work must be done without checking the condition of the concrete base on the lower surface of the bottom lid. In addition, the mortar injection work from the filling hole of the bottom cover is work in a narrow space in a limited space, and work setup and injection work take time and work costs. In addition, since filling of the gap between the lower surface of the bottom lid and the concrete base outside the pipe cannot be confirmed after pouring, there is a problem in that the mortar is poured more than necessary, resulting in unnecessary costs for the entire work and materials. On the other hand, the applicant proposes a process of press-fitting the pipe body vertically into the ground while discharging the soil inside the pipe body with ribs attached to the inner wall of the pipe, and A process of pouring ready-mixed concrete up to a height corresponding to the rib part inside the main body, a process of suspending the bottom cover inside the pipe body after the ready-mixed concrete has hardened and placing it on top of the hardened concrete, and a process of placing the outer edge of the bottom cover and the pipe Japanese Patent Application No. 2020-192207 proposes a method for erecting a large-sized bottomed tubular body including a step of welding the inner wall surface of the main body to join the pipe main body and the bottom cover.
この方法では、管本体内のリブ部分まで投入するコンクリートの状態等を目視しながら充填作業を行えるので作業状態や作業終了の確認を確実に行える利点がある。一方、この方法では、管本体の地下十数メートルまでの圧入後、生コンクリートを管内に投入して管内下端部の所要高さまで充填する作業であるから、暗所で多湿の劣悪な作業環境下で作業者による管内補助作業が必要である。また、作業時間が掛かりまた、コンクリートの場所打ち工法の一つであるから水の漏洩の有無確認を確実に行うことは困難であった。さらに、作業コストが大幅に膨らむ問題があった。 This method has the advantage that the filling work can be performed while visually checking the state of the concrete to be poured up to the rib portion in the pipe body, so that the working state and the completion of the work can be confirmed reliably. On the other hand, in this method, after the main body of the pipe is pressed into the pipe to a depth of ten and several meters underground, ready-mixed concrete is poured into the pipe and filled to the required height at the lower end of the pipe. Assistance work inside the pipe by workers is required. In addition, it takes a long time to work, and since it is one of the cast-in-place concrete construction methods, it is difficult to reliably check for water leakage. Furthermore, there is a problem that the work cost increases significantly.
本発明は上記従来の課題に鑑みてなされたものであり、その一つの目的は、簡単な工程の組合せで円滑、確実に埋設管の埋設作業を遂行し、かつ施工後に漏水等を生じることを確実に防止し得る大型管の地中建込み方法及び有底埋設管を提供することにある。また、本発明の他の目的は、短時間で低コストにより埋設管の埋設作業を完了させることができる大型管の地中建込み方法及び有底埋設管を提供することにある。 SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned conventional problems, and one of the objects thereof is to achieve smooth and reliable burying work of buried pipes by a combination of simple processes and to prevent water leakage after construction. To provide an underground installation method for a large-sized pipe and a bottomed buried pipe which can surely prevent such accidents. Another object of the present invention is to provide a method for burying a large pipe underground and a bottomed buried pipe, which can complete the work of burying a buried pipe in a short period of time and at low cost.
上記課題を解決するために本発明は、管内空間を種々の用途に用いるべく地中に縦方向に埋設させる大型の埋設管の建込み方法であり、埋設させる管1より径大の先行掘削管20であり、埋設管1の平面視埋設外径を内包する管壁位置となるように埋設管1の埋設に先立って地面に対して該先行掘削管20を圧入掘削させる工程と、先行掘削管20の掘削と同時に管内の掘削土を排土する工程と、計画深さまで先行掘削管20を圧入させた後に掘削管20の管内空間100に有底埋設管1を挿入降下させて先行掘削管20と埋設管1とで二重管状に配置させる工程と、埋設管1を所定深さ位置まで挿入した後に先行掘削管20を抜き上げる工程と、を含む大型管の地中建込み方法から構成される。
In order to solve the above problems, the present invention is a method for erecting a large-sized buried pipe that is vertically buried in the ground so that the pipe inner space can be used for various purposes. 20, a step of press-fitting and excavating the preceding
その際、先行掘削管20を計画深さまで圧入させた後に該先行掘削管の管内空間100に挿入降下させる有底埋設管1の内底部には、地中側からの浮力に対する抗浮力錘部3が設けられるとよい。
At that time, the inner bottom of the bottomed buried
また、有底埋設管1の底外部には下方に先端側を向けた旋回食込器4が設けられ、有底埋設管1の先行掘削管20の管内空間100への挿入降下後に有底埋設管1自体を縦軸回りに旋回させる工程を含むとなおよい。
In addition, a
また、本発明は、先行掘削管20を計画深さまで圧入させた後に先行掘削管20の管内空間100に挿入降下させる有底埋設管1であり、底外部に下方に先端側を向けた旋回食込器4が設けられた有底埋設管から構成される。
In addition, the present invention is a bottomed buried
その際、内底部には、地中側からの浮力に対する抗浮力錘部3を設けるとよい。
In this case, it is preferable to provide an
本発明の大型有底管体の建込み方法及び有底埋設管によれば、管本体の改良により作業工程を大幅に簡略化でき、各作業自体が簡単、明確で作業時間を大幅に短縮でき、さらに作業コストを大幅に低減することが可能である。 According to the method of erecting a large bottomed pipe body and the bottomed buried pipe of the present invention, the work process can be greatly simplified by improving the pipe body, and each work itself is simple and clear, and the work time can be greatly shortened. Furthermore, it is possible to greatly reduce the work cost.
以下、添付図面を参照しつつ本発明の大型管の地中建込み方法及び有底埋設管の実施形態について説明する。 BEST MODE FOR CARRYING OUT THE INVENTION An embodiment of a large pipe underground installation method and a bottomed buried pipe according to the present invention will be described below with reference to the accompanying drawings.
本発明に係る大型管の地中建込み方法に用いられる大型の有底埋設管は、管内空間を種々の用途に用いるために埋設し建込みされる。例えば地震その他の自然災害、戦争その他の人的災害からの避難用シェルター等として使用される。また書類、宝飾品、磁気テープ、フィルムその他の電子記録媒体等の保管庫等として使用され得る。また、薬品、薬剤、水、その他の液体、その他の有価物資材の倉庫、その他任意の用途の空間利用用管体として用いられる。本発明に係る大型の有底埋設管は内部に空間を有し底部が閉鎖された中空の有底管体である。管体は、例えば直径が2メートル以上~5メートル程度で、地中深さが例えば5メートル~20メートル、あるいはそれ以上の地中深さで埋設される管体であり、火山灰土や粘土質土の地中はもとより、特に地中に水や転石を多く含む地域においても有効に用いられる。本発明の大型管の地中建込み方法は、これらの地域において有効に活用し得る。 A large-sized buried pipe with a bottom used in the underground installation method for a large-sized pipe according to the present invention is buried and erected in order to use the space inside the pipe for various purposes. For example, it is used as an evacuation shelter from earthquakes and other natural disasters, wars and other man-made disasters, and the like. It can also be used as a storehouse for documents, jewelry, magnetic tapes, films and other electronic recording media. In addition, it is used as a space-utilizing tubular body for storage of chemicals, drugs, water, other liquids, other valuable materials, and other arbitrary uses. A large-sized buried pipe with a bottom according to the present invention is a hollow bottomed tubular body having a space inside and a closed bottom. The tubular body is, for example, a tubular body having a diameter of about 2 m to 5 m and a depth of 5 m to 20 m or more, which is buried in the ground, and is made of volcanic ash or clay. It can be effectively used not only in the ground of the soil, but also in areas where the ground contains a lot of water and boulders. The underground installation method for large pipes of the present invention can be effectively utilized in these areas.
本発明の大型有底管体はその建込み工程によって部材の構成が異なるので、各工程とともに大型有底管体について説明する。 Since the structure of the members of the large-sized bottomed tubular body of the present invention differs depending on the erection process, the large-sized bottomed tubular body will be described together with each process.
[第一工程]
図1ないし図7は、本発明の大型管の地中建込み方法の一実施形態を説明している。図1は地中に略鉛直方向に圧入させる先行掘削管20と、埋設管1と、の圧入位置関係を示す平面説明図であり、内側の一点鎖線示の管が最終的に埋設して建込みする埋設管1であり、外側の実線示の管が先行掘削管20を示す。この方法では、建て込み位置が設定された地盤G中に先行掘削管20を圧入しつつ排土させ、先行掘削管20内側の空間100に最終的に建込みする埋設管1を挿入降下させ、その後、先行掘削管20を地上に抜き上げることにより大型管を建込みさせるものである。
[First step]
1 to 7 illustrate an embodiment of the method for erecting large pipes underground according to the present invention. FIG. 1 is an explanatory plan view showing the press-fit positional relationship between a preceding
先行掘削管20は、図2,4,5に示すように、両端部(図中では上下)を開口した鋼製の円筒管からなる、いわゆるケーシングチューブと称される鋼管である。単一鋼管で目的の地中深さに到達できる場合には1本の鋼管で構成されるが、複数鋼管を連結して使用するのが通常である。通常は、数メートル直径で数メートルの軸方向長さのユニット管をチュービング装置で把持させて軸回り方向に回転させながら地中に圧入させる。チュービング装置内で1つのユニット管の圧入降下が完了しない状態で他のユニット管の管端同士を溶接又は管内外の水密保持状態で任意の締結手段により接続しながら、順次、圧入下降させる。例えば、カップリング部材を用いて上下対向させたユニット管の管端どうしをねじ締結し、複数の管体を連結して例えば20m程度の長さの一体の先行掘削管を形成しながら圧入下降させてもよい。本実施形態では、図4(b)に示すように、管内外を水密保持のために地上にて予め溶接部10において、溶接連結している。先行掘削管20は、下端に複数の掘削ビット部21を取り付けており、チュービング装置40の軸回り回転に伴い回転あるいは旋回掘削しながら下方に掘り進んでいく。これによって、転石が多い地盤であっても掘削ビット21部で岩盤等を破砕しつつ確実に下方へ掘進することができる。掘削ビット部21は、掘削ビット21aを間隔を設けて管本体の下端縁に環状に複数個固定して構成されている。後述するように、管本体1を地中に圧入するには専用機械装置により管本体の長手軸周り方向に回転させながら圧入するが、管本体1の下端縁に掘削ビット部21を取り付けることにより圧入途中に硬い岩盤層などが存在している場合でも管本体を回転させながらこれらを切り崩して地中に進入させることができる。
As shown in FIGS. 2, 4 and 5, the
図2,3において、地面上にチュービング装置40が設置されており、このチュービング装置40の中央に軸心を縦方向に配置した先行掘削管20をチャックで掴み、先行掘削管20を回転させながら地中に押し込みさせる。図2において、チュービング装置40は、機体枠41に支持された図示しない管回転用の回転体、回転体を回転可能に支持する昇降フレーム、昇降装置、チャック部材、チャックシリンダ等を有する公知の全回転チュービング装置である。チュービング装置40の下面で地面上には受板42が予め載置されている。また、チュービング装置40を両側から挟みつけるようにカウンタウエイト43が配置されている。カウンタウエイト43は、大型の管体の圧入操作に際してチュービング装置40が反動で移動しないようにチュービング装置40全体を安定化させる。
In FIGS. 2 and 3, a
本発明に係る大型管の地中建込み方法における第1の工程は、埋設させる管より径大の先行掘削管であり、埋設管1の平面視埋設外径を内包する管壁位置となるように埋設管1の埋設に先立って地面に対して該先行掘削管20を圧入掘削させる。すなわち、例えば図1において最終的に埋設して建て込むべき管1の地上平面位置に対応した中心位置Qについて、チュービング装置40の回動中心を設定し、これに埋設すべき管1より径大の先行掘削管20の中心位置をセットして、先行掘削管20を圧入埋設する。先行掘削管20と埋設本管1とは必ずしも同心位置に設定される必要はない。先行掘削管20の圧入掘削後、その管20内に本埋設用の管1を挿入配置させる間隔的余裕があればよい。実施形態では、理解を容易化するために、先行掘削管内に降下挿入される埋設本管1と先行掘削管20とは、直径線で縦断すると両端側にそれぞれ所要の間隔D(図5(b)参照)が形成され、先行掘削管20に接触しないように同心位置で直径が異なる円のように圧入される。これによって、先行掘削管20の圧入埋設位置が図1に示すように、埋設管1の平面視埋設外径を内包する先行掘削管の管壁位置となるように埋設管1の埋設に先立って地面に対して該先行掘削管20を圧入掘削させる。
The first step in the method of burying a large pipe in the ground according to the present invention is to excavate a pre-excavated pipe having a diameter larger than that of the pipe to be buried. Prior to burying the buried
先行掘削管20は、埋設本管1の埋設建込みに先立って該埋設管1を挿入配置するための地中空隙を形成すべく、先行して掘削しつつ管内を排土し、管内に空間100を形成する。そして、掘削後の管内空間に埋設本管を挿入配置させる際に形成された縦穴の周壁が崩壊しないように崩落防止管として機能する。
Prior to the construction of the buried
[第二工程]
先行掘削管20のチュービング装置40による回転圧入掘削と同時に先行掘削管の下端の掘削ビット21を介した掘削により管内に排出されて生じる掘削土は排土される。すなわち、図30において、チュービング装置40で先行掘削管20を回転させながら地中に圧入する際、同時に先行掘削管20の内側の土を排土機44で地上側に排出させる。実施形態において、排土機は、クローラクレーン等重機により吊支され、落下力によって地盤に打ち込み、土砂をつかみ取る方式のグラブハンマー等の公知の大口径掘削機械が用いられている。なお、先行掘削管の掘削に際し、深度を徐々に大きくするに従い通常は、管本体の下端側の地中から水が管の内側に浸出してくる場合が多い。水の浸出は数メートルの深度でも数十メートルの深度でもあり得る。
[Second step]
Simultaneously with rotary press-in excavation of the preceding
[第三工程]
図4において、排土機44により管内を排土させながら計画深さまで先行掘削管20を圧入させた後に該先行掘削管20の管内空間に埋設本管としての有底埋設管1を挿入降下させて先行掘削管と埋設管とで二重管状に配置させる(図5参照)。図4(b)において、先行掘削管20の内側に配置しする有底埋設管1は、上端側となる一端側を開口した鋼製の円筒管からなる、いわゆるケーシングチューブと称される鋼管である。複数鋼管を連結して構成される。
[Third step]
In FIG. 4, after the preceding
有底埋設管1は、下端が水密状態を保持して内外を閉鎖するように底壁2が予め地上側の製作で取付られている。さらに、埋設管1の内部であって底壁2の上部、すなわち有底埋設管1の内底部には抗浮力錘部3が設けられている。抗浮力錘部3は、先行掘削管を計画深さまで圧入掘削させた後に該先行掘削管の管内空間に有底埋設管1を挿入降下させる際に、管の下端の地中側からの浸出水の浮力に対抗して有底埋設管1が浮き上がらないようにするものである。抗浮力錘部3は、浮力に対抗し得る重力を有する有体物であればよく、鋼材やコンクリート、あるいはそれらの廃材等でもよい。なお、それらの抗浮力錘部3の上面は、管内空間の利用形態に応じて任意のフローリングが施される。
The bottomed buried
さらに、本実施形態において、有底埋設管1の底壁1の外部には下方に先端側を向けた旋回食込器4が設けられている。旋回食込器4は、有底埋設管1を先行掘削管20の管内空間へ挿入降下させて着底した後に、有底埋設管1自体を縦軸回りに旋回させて底壁2外の地盤に有底埋設管1の底部を食い込ませて地盤Gに一体化させる手段であり、本実施形態において、図4~図7に示すように、スクリュ軸5とスクリュ軸5外周回りに螺旋刃6を取り付けたスクリュ羽根7から構成されている。旋回食込器4は本体側を旋回させることにより地面に食い込んでいく機構であれば、任意の構造の装置を採用することができる。また、計画深さ部分の地盤状態に応じて下方に長いスクリュ羽根としてもよい。実施形態では、二重管状態に配置された先行掘削管とその内側に挿入された有底埋設管1との上部を連結し、両管を一体としてチュービング装置で旋回させて有底埋設管1の地盤への食い込み状態を確保するようにしている。
Further, in the present embodiment, a
有底埋設管1を先行掘削管20の内側に同心状位置に挿入降下させるに際しては、所要の軸方向長さのユニット管をチュービング装置40で把持しながらそのまま降下させてもよいし、また、重機クレーン等の吊支装置に支持させた状態で挿入降下させてもよい。その際、両管間の空隙Dを保持して円滑迅速に有底埋設管1は先行掘削管20の内側に挿入配置される。
When inserting and lowering the bottomed buried
[第四工程]
埋設管1を所定深さ位置まで挿入した後に先行掘削管20を抜き上げる。先行掘削管20の地上側への抜き上げ作業について、チュービング装置40で把持させて軸回り反対方向に回転させながら地中に抜き上げることもできる。この場合、先行掘削管20の圧入掘削、埋設管1の管20内側への挿入配置、先行掘削管20の抜き上げ操作まで、主要な装置の段取り替えの必要がない。したがって、作業工数が大幅に削減でき、作業時間短縮、作業労力の軽減、作業コストの大幅低減を達成し得る。なお、クレーンその他の吊り上げ機能を有する重機を用いて先行掘削管20を抜き上げるようにしてもよい。
[Fourth step]
After inserting the buried
実施形態では、先行掘削管20を地上側に抜き上げた跡に形成される隙間に例えばグラウト材等の流動固化材を注入して固化部12を形成し、地盤と一体化させている。なお、両管間の間隔の大きさや地盤の状態によってはこの固化部12の形成は必ずしも行わなくともよい。
In the embodiment, a solidified
上記のように、地中において先行掘削管20でその内側に有底埋設管1の収容空間を形成し、周壁の土留めを施した状態で収容空間に有底埋設管1を挿入降下させ、地盤側と固定させるから、有底埋設管1内での諸設備の設置、施工、構築、インテリア配備その他の管内空間利用のための設備等を地上にて行うことができる。また、有底埋設管1の止水のための全体工事、確認も地上側で行えるから埋設管1内への水の侵入対策の万全を期することができる。例えば動力付きの昇降ラックや、換気装置、設備、備品、食料、物品の保管設備等構築、災害避難用のシェルター、その他任意の用途の利用形態について、地上側で設計し具体的に管内に設備した状態で挿入降下して埋設管を利用することができる。
As described above, a storage space for the bottomed buried
上記第1~第4工程により大型管の地中建込みを行うことにより、有底埋設管1内での利用目的に応じた組立て設備施工を予め地上側で管内について行うから設備の精度の良い完成状態を保持することができるばかりでなく、作業工程が簡単で工程数も少なく作業時間短縮、工期短縮、作業コスト大幅低減に資する。特に、地上側で管底部からの地下水の侵入防止対策を万全に施して安定的かつ安全に管内利用を持続させることが可能である。
By carrying out the underground installation of the large-sized pipe in the above-mentioned first to fourth steps, the assembly equipment construction according to the purpose of use in the bottomed buried
また、先行掘削管を計画深さまで圧入させた後に該先行掘削管の管内空間に挿入降下させる有底埋設管の内底部には、地中側からの浮力に対する抗浮力錘部が設けられていることにより、先行掘削管の管内空間に有底埋設管1を挿入降下させる際に、管の下端の地中側からの浸出水の浮力により埋設本管1が不安定となることなく安定的に先行掘削管の管内空間に配置させることができる。
In addition, an anti-buoyancy weight section against buoyancy from the underground side is provided on the inner bottom of the bottomed buried pipe that is inserted and lowered into the internal space of the preceding drilling pipe after the preceding drilling pipe has been press-fitted to the planned depth. As a result, when the bottomed buried
また、有底埋設管の底外部には下方に先端側を向けた旋回食込器が設けられ、有底埋設管の先行掘削管の管内空間への挿入降下後に有底埋設管自体を縦軸回りに旋回させる工程を含むことにより、先行掘削管20の管内空間において着底した後に、有底埋設管1自体の縦軸回り旋回により、旋回食込器を介して底壁22外の地盤に有底埋設管1の底部を食い込ませて地盤Gに一体化させることが可能である。
In addition, on the outside of the bottom of the bottomed buried pipe, a swivel inserter is provided with the tip side facing downward, and after the preceding excavation pipe of the bottomed buried pipe is inserted and lowered into the pipe interior space, the bottomed buried pipe itself is vertically rotated. By including the step of turning around, after reaching the bottom in the pipe inner space of the preceding
また、本発明の有底埋設管は、上記の方法により大型管の地中建込みを行う方法において用いる有底埋設管であり、先行掘削管を計画深さまで圧入させた後に先行掘削管の管内空間に挿入降下させる有底埋設管であり、その内底部には、地中側からの浮力に対する抗浮力錘部が設けられている構成とすることにより、先行掘削管の管内空間に有底埋設管1を挿入降下させる際に、管の下端の地中側からの浸出水の浮力により埋設本管1が不安定となることなく安定的に先行掘削管の管内空間に配置させることができる。
Further, the bottomed buried pipe of the present invention is a bottomed buried pipe used in the above-described method for burying a large pipe underground. It is a bottomed burial pipe that is inserted and lowered into a space, and the inner bottom is provided with a buoyancy counterweight against the buoyancy from the underground side. When the
また、上記の有底埋設管は、底外部に下方に先端側を向けた旋回食込器が設けられていることにより、先行掘削管20の管内空間において着底した後に、有底埋設管1自体の縦軸回り旋回により、旋回食込器を介して底壁2外の地盤に有底埋設管1の底部を食い込ませて地盤Gに一体化させることが可能である。
In addition, since the above-mentioned bottomed buried pipe is provided with a swivel bite device facing downward on the outside of the bottom, the bottomed buried
以上説明した本発明の大型管の地中建込み方法及び有底埋設管は、上記した実施形態のみの構成に限定されるものではなく、特許請求の範囲に記載した発明の本質を逸脱しない範囲において、他の実施形態を用いるようにしてもよい。 The method for erecting a large pipe underground and the buried pipe with a bottom according to the present invention described above are not limited to the configurations of the above-described embodiments only, and are within the scope of the invention described in the claims. , other embodiments may be used.
本発明の大型管の地中建込み方法及び有底埋設管は、地震、津波、土砂災害、戦時危険状態等でシェルターとして利用できるうえ、通常には種々の物品の収納、保管倉庫などでも利用することができる。また、光や空気についての生育条件がそれほど厳しくないきのこ類栽培空間を形成することもできる。 The method for erecting large pipes underground and the bottomed buried pipe of the present invention can be used as a shelter in the event of an earthquake, tsunami, landslide disaster, wartime danger, etc., and can also be used for the storage of various goods, storage warehouses, etc. can do. It is also possible to create a mushroom cultivation space where the growing conditions for light and air are not so strict.
1 有底埋設管(埋設本管)
2 底壁
3 抗浮力錘部
4 旋回食込器
5 スクリュ軸
6 螺旋刃
7 スクリュ羽根
20 先行掘削管
21 掘削ビット部
21a 掘削ビット
40 チュービング装置
44 排土機
D 両管間の間隙
G 地盤
1 Bottomed buried pipe (buried main pipe)
2
Claims (5)
埋設させる管より径大の先行掘削管であり、埋設管の平面視埋設外径を内包する管壁位
置となるように埋設管の埋設に先立って地面に対して該先行掘削管を圧入掘削させる工程
と、
先行掘削管の掘削と同時に管内の掘削土を排土する工程と、
計画深さまで先行掘削管を圧入させた後に掘削管の管内空間に有底埋設管を挿入降下させて先行掘削管と埋設管とで二重管状に配置させる工程と、
埋設管を所定深さ位置まで挿入した後に先行掘削管を抜き上げる工程と、を含むことを特徴とする大型管の地中建込み方法。 A method for burying a large-sized buried pipe vertically in the ground so that the space inside the pipe can be used for various purposes,
The pre-excavation pipe is larger in diameter than the pipe to be buried, and is press-fitted and excavated into the ground prior to burying the buried pipe so that the pipe wall position includes the burial outer diameter of the buried pipe in plan view. process and
A step of discharging the excavated soil in the pipe at the same time as excavating the preceding excavation pipe;
a step of inserting and lowering a buried buried pipe with a bottom into the internal space of the excavated pipe after press-fitting the preceding excavated pipe to the planned depth, and arranging the preceding excavated pipe and the buried pipe in a double pipe shape;
and extracting the preceding excavated pipe after inserting the buried pipe to a predetermined depth position.
先行掘削管の管内空間への挿入降下後に有底埋設管自体を縦軸回りに旋回させる工程を含むことを特徴とする請求項1又は2記載の大型管の地中建込み方法。 A swivel inserter is provided on the outside of the bottom of the bottomed buried pipe with the tip side facing downward, and after the bottomed buried pipe is inserted and lowered into the pipe space of the preceding excavation pipe, the bottomed buried pipe itself is rotated around the vertical axis. 3. The underground erection method for a large pipe according to claim 1 or 2, further comprising a turning step.
その内底部には、地中側からの浮力に対する抗浮力錘部が設けられていることを特徴とする有底埋設管。 A bottomed buried pipe that is inserted and lowered into the pipe inner space of the preceding excavation pipe after the preceding excavation pipe of claim 2 is press-fitted to a planned depth,
A bottomed buried pipe, characterized in that an anti-buoyancy weight is provided on the inner bottom to resist buoyancy from the underground side.
5. A buried buried pipe with a bottom according to claim 4, wherein a swirl chewing device is provided outside the bottom with its leading end facing downward.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2021172246A JP7057582B1 (en) | 2021-10-21 | 2021-10-21 | Underground construction method for large pipes and bottomed buried pipes |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2021172246A JP7057582B1 (en) | 2021-10-21 | 2021-10-21 | Underground construction method for large pipes and bottomed buried pipes |
Publications (2)
Publication Number | Publication Date |
---|---|
JP7057582B1 JP7057582B1 (en) | 2022-04-20 |
JP2023062342A true JP2023062342A (en) | 2023-05-08 |
Family
ID=81291798
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2021172246A Active JP7057582B1 (en) | 2021-10-21 | 2021-10-21 | Underground construction method for large pipes and bottomed buried pipes |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP7057582B1 (en) |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5419682B2 (en) * | 1971-10-05 | 1979-07-17 | ||
JPS5559235A (en) * | 1978-10-26 | 1980-05-02 | Nippon Dev Consult | Method and device for sinking improved radial well |
JPH0734711A (en) * | 1993-07-20 | 1995-02-03 | Heat Pump Gijutsu Kaihatsu Center | Building method for underground tank made of thin metal |
JP2003074076A (en) * | 2001-08-31 | 2003-03-12 | Penta Ocean Constr Co Ltd | Construction method of building having underground part |
WO2018047696A1 (en) * | 2016-09-06 | 2018-03-15 | 株式会社シェルタージャパン | Shelter and construction method therefor |
JP6585787B1 (en) * | 2018-08-23 | 2019-10-02 | 株式会社九建総合開発 | Construction method of large bottomed tubular body and large bottomed tubular body |
-
2021
- 2021-10-21 JP JP2021172246A patent/JP7057582B1/en active Active
Also Published As
Publication number | Publication date |
---|---|
JP7057582B1 (en) | 2022-04-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102758430B (en) | Large-diameter rotary digging pile construction technology for ultra-deep dumped unconsolidated soil bodies | |
WO2021109144A1 (en) | Modular intelligent dado cast-in-place pile and construction process therefor | |
JP5282541B2 (en) | How to prevent lifting of the lining body | |
CN106930276A (en) | The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles | |
CN103485347A (en) | Batter pile used for building foundation pit support and construction method thereof | |
CN209687494U (en) | A kind of precast concrete open caisson device for jacking construction | |
JP6319935B2 (en) | Tubing pile driving method | |
JP2023062342A (en) | Method of underground installation of large pipes and bottomed buried pipes | |
JP2006194031A (en) | Pillar construction method | |
JPH11166231A (en) | Bottom widening existing pile and embedding machine | |
JP2004316411A (en) | Assembling type steel pipe pile | |
JP2007308951A (en) | Method of constructing outer peripheral column by inverted construction method | |
JP5282542B2 (en) | Ground deformation prevention method and ground deformation prevention structure | |
CN203334292U (en) | Batter pile for supporting building foundation pit | |
JP2020029726A (en) | Method for installing large bottomed tubular body and large bottomed tubular body | |
CN112431195B (en) | Pile planting and grouting construction method for tubular piles | |
TWI748533B (en) | Construction method of high-pressure pouring type spiral pile | |
CN216517822U (en) | Drill and dig prefabricated well structure of quick installation of pore-forming and drill and dig pore-forming device | |
JP2003082689A (en) | Execution method for foundation of steel pipe pile | |
CN212405120U (en) | Bored concrete pile of construction is executed to underground reinforced concrete structure department | |
JPH09256766A (en) | Pit construction method and system | |
JPS6143517B2 (en) | ||
CN116695729A (en) | Hanging foot pile supporting structure and construction method | |
JP2000226980A (en) | Jacking shaft, its construction method and jacking method | |
TWI551773B (en) | Hoist and backfill construction method of shaft |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20211021 |
|
A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20211021 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20211214 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20220210 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20220315 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20220326 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 7057582 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |