JP2022080696A - Pile and its construction method and underground structure - Google Patents

Pile and its construction method and underground structure Download PDF

Info

Publication number
JP2022080696A
JP2022080696A JP2020191905A JP2020191905A JP2022080696A JP 2022080696 A JP2022080696 A JP 2022080696A JP 2020191905 A JP2020191905 A JP 2020191905A JP 2020191905 A JP2020191905 A JP 2020191905A JP 2022080696 A JP2022080696 A JP 2022080696A
Authority
JP
Japan
Prior art keywords
pile
existing
ground
piles
tip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2020191905A
Other languages
Japanese (ja)
Inventor
匡 前嶋
Tadashi Maejima
義明 塚田
Yoshiaki Tsukada
俊行 玉井
Toshiyuki Tamai
武彦 野口
Takehiko Noguchi
智志 室城
Tomoshi Muroki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Kasei Construction Materials Corp
Original Assignee
Asahi Kasei Construction Materials Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Kasei Construction Materials Corp filed Critical Asahi Kasei Construction Materials Corp
Priority to JP2020191905A priority Critical patent/JP2022080696A/en
Publication of JP2022080696A publication Critical patent/JP2022080696A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

To provide a pile, its construction method, and an underground structure that can solve the problem of dealing with existing piles in the case of constructing a new structure on a site with the existing piles, especially the problem of securing additional space in the case of installing new piles while keeping the existing piles in place.SOLUTION: The inventive pile 100 is a pile that is buried underground to support a structure 300 above ground, and has an open tip 120 and a pile body 110 with an inside diameter that encapsulates an existing structure P in the ground at a construction target site. The pile 100 is constructed on the ground so as to encapsulate the existing structure P around the existing structure P in the ground at the construction target site.SELECTED DRAWING: Figure 1

Description

本発明は、杭とその施工方法および地中構造物に関する。 The present invention relates to piles, construction methods thereof, and underground structures.

家の建て直しのごとく、基礎杭の上に建つ既設構造物を撤去してそこに新たな構造物を構築する場合、既存杭の処理形態は主として(1)「直接利用」、(2)「存置」、(3)「撤去」の3つに分類される。「直接利用」は存置した既存杭を新築建造物に有効な形で直接的に利用する形態(例えば特許文献1参照)、「存置」は既存杭を敷地の一部として地中に残しつつ杭を新設する形態、「撤去」は既存杭を引き抜き新しい杭を打設する形態(例えば特許文献2参照)である(図28参照)。 When removing the existing structure built on the foundation pile and constructing a new structure there, like rebuilding a house, the treatment form of the existing pile is mainly (1) "direct use", (2) "retention". , (3) "Removal". "Direct use" is a form in which existing existing piles are directly used in a new building (see, for example, Patent Document 1), and "retention" is a pile while leaving the existing piles in the ground as a part of the site. "Removal" is a form in which an existing pile is pulled out and a new pile is placed (see, for example, Patent Document 2) (see FIG. 28).

特開2017-122364号公報JP-A-2017-122364 特開2017-66721号公報Japanese Unexamined Patent Publication No. 2017-66721

しかし、これらの形態にはそれぞれ課題がある。すなわち、「直接利用」の場合、存置した既存杭によって所定の支持力が得られるかどうか未知数である。「存置」の場合、杭を新設するためのスペースを確保できるとは限らず、これはとくに敷地が狭小である場合に顕在化しやすい。また、「撤去」の場合、既存杭の撤去に伴う基礎工事の作業量は新設時の2~4倍となるのが一般的であり、また、施工後の敷地地盤の再評価が簡単でないというのが現状である。こういった現状に照らし、既存杭の処理の形態(再利用、存置、撤去)に応じた地盤調査の方法や基礎構造の設計方法の技術開発は喫緊の課題となっている。 However, each of these forms has its own challenges. That is, in the case of "direct use", it is unknown whether a predetermined bearing capacity can be obtained by the existing existing pile. In the case of "retention", it is not always possible to secure a space for constructing a new pile, which is likely to become apparent especially when the site is small. Also, in the case of "removal", the amount of work for foundation work associated with the removal of existing piles is generally two to four times that at the time of new construction, and it is not easy to re-evaluate the site ground after construction. is the current situation. In light of this situation, technological development of ground survey methods and foundation structure design methods according to the form of treatment of existing piles (reuse, retention, removal) has become an urgent issue.

そこで、本発明は、既存の杭などがある敷地に新たな構造物を構築する場合の既存杭の処理時における問題、とくに、既存杭を存置させつつ杭を新設する場合における新設スペース確保の問題を解消しうる杭とその施工方法および地中構造物を提供することを目的とする。 Therefore, the present invention presents a problem in processing existing piles when constructing a new structure on a site having existing piles, and in particular, a problem in securing new space when constructing new piles while preserving existing piles. The purpose is to provide piles, their construction methods, and underground structures that can solve the problem.

本発明の一態様は、地中に埋設されて地上の構造物を支持する杭であって、
開口した先端部と、
施工対象現場における地中の既設構造物を内包する杭本体部と、
を有する杭である。
One aspect of the present invention is a pile buried in the ground to support a structure on the ground.
With the open tip,
The pile body that contains the existing structure in the ground at the construction site, and
It is a stake with.

この杭は、既存杭をはじめとする既設構造物が内包された状態となるようにその外側へ被せるように設置することができる。このように構成された杭を利用することで、杭新設のためのスペースが確保し難いという問題を解消しつつ、既存杭を存置させた地盤に杭を新設することで新規構造物を支持するに足る支持力を確保することが可能となる。 This pile can be installed so as to cover the outside of the existing structure such as the existing pile so as to be contained therein. By using the piles constructed in this way, the problem that it is difficult to secure space for new piles will be solved, and new structures will be supported by constructing new piles on the ground where existing piles have been retained. It is possible to secure sufficient bearing capacity.

上記のごとき杭は、杭本体部に形成された羽根部をさらに備えていてもよい。 The pile as described above may further include a blade portion formed on the pile main body portion.

上記のごとき杭における羽根部は、先端部の周面にのみ設けられていてもよい。 The blade portion of the pile as described above may be provided only on the peripheral surface of the tip portion.

上記のごとき杭における羽根部は、本体部の周面に連続的かつスパイラル状に設けられていてもよい。 The blade portion of the pile as described above may be continuously and spirally provided on the peripheral surface of the main body portion.

上記のごとき杭における羽根部は、本体部の周面に断続的に設けられていてもよい。 The blade portion of the pile as described above may be provided intermittently on the peripheral surface of the main body portion.

上記のごとき杭において、杭本体部の内周側、先端部または周面に、既設構造物の一部に当接する掘削補助具が設けられていてもよい。 In the pile as described above, an excavation assisting tool that comes into contact with a part of the existing structure may be provided on the inner peripheral side, the tip portion or the peripheral surface of the pile main body portion.

本発明の別の一態様は、上記のごとき杭が埋設されて地中に構成された地中構造物である。 Another aspect of the present invention is an underground structure in which piles such as those described above are buried and constructed in the ground.

本発明のさらに別の一態様は、先端部が開口した杭を、施工対象現場における地中の既設構造物の周囲に、構造物を内包するように地盤に施工する、杭の施工方法である。 Yet another aspect of the present invention is a pile construction method in which a pile having an open tip is constructed on the ground so as to include the structure around the existing structure in the ground at the construction target site. ..

上記のごとき杭の施工方法において、地中にて当該杭の支持力を発揮する支持部を、当該地中にて所定の支持力が得られる土層中に位置させてもよい。 In the pile construction method as described above, the support portion that exerts the bearing capacity of the pile in the ground may be positioned in the soil layer where a predetermined bearing capacity can be obtained in the ground.

上記のごとき杭の施工方法において、先端部が既設構造物の下端よりも深くなる位置まで杭を地盤に施工してもよい。 In the pile construction method as described above, the pile may be constructed on the ground to a position where the tip portion is deeper than the lower end of the existing structure.

上記のごとき杭の施工方法において、杭の内部に水硬性材料を供給し、杭に内包される既設構造物と当該杭とを一体化させるようにしてもよい。 In the pile construction method as described above, a hydraulic material may be supplied to the inside of the pile to integrate the existing structure contained in the pile with the pile.

本発明によれば、既存の杭などがある敷地に新たな構造物を構築する場合の既存杭の処理時における問題、とくに、既存杭を存置させつつ杭を新設する場合における新設スペース確保の問題を解消しうる。 According to the present invention, there is a problem in processing existing piles when constructing a new structure on a site with existing piles, and in particular, a problem of securing new space when constructing new piles while keeping existing piles. Can be resolved.

本発明の第1の実施形態における杭が施工された地盤の概略を示す図である。It is a figure which shows the outline of the ground where the pile was constructed in the 1st Embodiment of this invention. 本発明の第2の実施形態における杭の一例を示す、(A)先端部付近の図と、(B)底面図である。It is (A) the figure near the tip part and (B) the bottom view which shows the example of the pile in the 2nd Embodiment of this invention. 本発明の第2の実施形態における杭の他の例を示す、(A)先端部付近の図と、(B)底面図である。It is (A) the figure near the tip part and (B) the bottom view which shows the other example of the pile in 2nd Embodiment of this invention. 本発明の第3の実施形態における杭の一例を示す、(A)先端部付近の図と、(B)底面図である。It is (A) the figure near the tip part and (B) the bottom view which shows the example of the pile in the 3rd Embodiment of this invention. 本発明の第3の実施形態における杭の他の例を示す図である。It is a figure which shows the other example of the pile in the 3rd Embodiment of this invention. 本発明の第3の実施形態における杭の他の例を示す図である。It is a figure which shows the other example of the pile in the 3rd Embodiment of this invention. 本発明の第3の実施形態における杭の他の例を示す図である。It is a figure which shows the other example of the pile in the 3rd Embodiment of this invention. 本発明の第3の実施形態における杭の他の例を示す図である。It is a figure which shows the other example of the pile in the 3rd Embodiment of this invention. (A)杭先端部が既存杭の先端よりも深くなる深度まで埋設した杭、(B)杭先端部が既存杭の先端よりも浅い深度で止まるように埋設した杭の概略を示す図である。It is a figure which shows the outline of the pile (A) the pile buried to the depth that the tip of the pile becomes deeper than the tip of the existing pile, and (B) the pile buried so that the tip of the pile stops at the shallower depth than the tip of the existing pile. .. 本発明の第4の実施形態における杭の一例を示す縦断面図である。It is a vertical sectional view which shows an example of the pile in 4th Embodiment of this invention. プレボーリング工法によって施工された既存杭の例を示す図である。It is a figure which shows the example of the existing pile constructed by the pre-boring method. プレボーリング工法によって施工された既存杭の周囲に、掘削補助具が設けられた杭を施工する際の様子を示す図である。It is a figure which shows the state at the time of constructing the pile with the excavation assisting tool around the existing pile constructed by the pre-boring method. 掘削リングで構成された掘削補助具を示す杭の(A)縦断面図と(B)底面図である。It is (A) vertical sectional view and (B) bottom view of the pile which shows the excavation auxiliary tool composed of the excavation ring. 波状歯で構成された掘削補助具を示す杭の(A)縦断面図と(B)底面図である。It is (A) vertical sectional view and (B) bottom view of the pile which shows the excavation assist tool composed of a wavy tooth. スパイラル状の内周突部で構成された掘削補助具を示す杭の(A)縦断面図と(B)底面図である。It is (A) vertical sectional view and (B) bottom view of the pile which shows the excavation auxiliary tool which was composed of a spiral inner peripheral protrusion. 中心を向いて突出する複数の爪で構成された掘削補助具を示す杭の(A)縦断面図と(B)底面図である。It is (A) vertical sectional view and (B) bottom view of the pile which shows the excavation auxiliary tool which consisted of a plurality of claws projecting toward a center. 本発明の第5の実施形態の一例を示す、水硬化性材料が内部に充填されて既存杭と一体化された杭の概略を示す縦断面図である。FIG. 5 is a vertical cross-sectional view showing an outline of a pile in which a water-curable material is filled therein and integrated with an existing pile, showing an example of a fifth embodiment of the present invention. 本発明の第5の実施形態の一例を示す、水硬化性材料が先端部付近に供給されて既存杭と一体化された杭の概略を示す縦断面図である。FIG. 5 is a vertical cross-sectional view showing an outline of a pile in which a water-curable material is supplied near the tip portion and integrated with an existing pile, showing an example of a fifth embodiment of the present invention. 本発明の第6の実施形態において、拡大部がある既存杭の周囲に杭を施工する際の一例を示す図である。In the sixth embodiment of the present invention, it is a figure which shows an example at the time of constructing a pile around the existing pile which has an enlarged part. 本発明の第6の実施形態において、拡大部がある既存杭の周囲に杭を施工する際の他の例を示す図である。In the sixth embodiment of the present invention, it is a figure which shows the other example at the time of constructing a pile around the existing pile which has an enlarged part. 本発明の第6の実施形態において、拡大部がある既存杭の周囲に杭を施工する際の他の例を示す図である。In the sixth embodiment of the present invention, it is a figure which shows the other example at the time of constructing a pile around the existing pile which has an enlarged part. 本発明の第7の実施形態において、拡大部がある既存杭の周囲に杭を施工する際の一例を示す図である。It is a figure which shows an example at the time of constructing a pile around the existing pile which has an enlarged part in 7th Embodiment of this invention. 本発明の第7の実施形態において、拡大部がある既存杭の周囲に杭を施工する際の他の例を示す図である。It is a figure which shows the other example at the time of constructing a pile around the existing pile which has an enlarged part in 7th Embodiment of this invention. 本発明の第8の実施形態において、途中が曲がっている既存杭の周囲に杭を施工する際の一例を示す図である。In the eighth embodiment of the present invention, it is a figure which shows an example at the time of constructing a pile around the existing pile which is bent in the middle. 本発明の第8の実施形態において、途中が曲がっている既存杭の周囲に杭を施工する際の他の例を示す図である。It is a figure which shows the other example at the time of constructing a pile around the existing pile which is bent in the middle in the 8th Embodiment of this invention. 本発明の第8の実施形態において、途中が曲がっている既存杭の周囲に杭を施工する際の他の例を示す図である。It is a figure which shows the other example at the time of constructing a pile around the existing pile which is bent in the middle in the 8th Embodiment of this invention. 本発明の第8の実施形態において、途中が曲がっている既存杭の周囲に杭を施工する際の他の例を示す図である。It is a figure which shows the other example at the time of constructing a pile around the existing pile which is bent in the middle in the 8th Embodiment of this invention. 基礎杭の上に建つ既設構造物を撤去してそこに新たな構造物を構築する場合の従来の既存杭の処理形態を参考として示す図である。It is a figure which shows the processing form of the conventional existing pile as a reference in the case of removing the existing structure built on the foundation pile and constructing a new structure there.

以下、本発明の構成を図面に示す実施の形態の一例に基づいて詳細に説明する(図1等参照)。 Hereinafter, the configuration of the present invention will be described in detail based on an example of the embodiment shown in the drawings (see FIG. 1 and the like).

[第1の実施形態]
杭100は、地中に埋設されて構造物300を支持するように構成されている。本実施形態の杭100は、施工対象現場における地中の既存杭Pが内包された状態となるようにその外側へ被せるように設置される(図1参照)。杭100は、このように設置されるに適した構造、具体的には、対象とする既存杭Pを内包するに足る杭本体部110と、開口した先端部120とを有している開放端杭である。
[First Embodiment]
The pile 100 is buried in the ground and is configured to support the structure 300. The pile 100 of the present embodiment is installed so as to cover the existing pile P in the ground at the construction target site so as to be contained therein (see FIG. 1). The pile 100 has a structure suitable for such installation, specifically, an open end having a pile main body portion 110 sufficient to include the existing pile P as a target and an open tip portion 120. It is a stake.

この杭100は、既存杭Pの外側へ被せるように設置することができることから、杭を新設のためのスペースが確保し難いという問題を解消しつつ、既存杭Pを存置させた地盤に杭を新たに設け、新規構造物を支持するに足る支持力を確保することを可能とする(図1参照)。敷地が狭小である敷地(狭隘地)においては、既存杭Pを当該地盤に存置させつつそれらの隙間や四隅などに杭を新設することが難しいことがある。とくにこのような状況において、本実施形態の杭100は、既存杭Pを撤去することなく存置させたまま、既存杭Pの周囲の狭いスペースを利用して新しい杭を設置して支持力を増大させることを可能とする。なお、各図においては、他の部分との違いをわかりやすく示すために、既存杭Pを濃く表現し、あるいはハッチングを付して表現している(既存杭Pの断面を表しているのではない)。 Since this pile 100 can be installed so as to cover the outside of the existing pile P, the pile is placed on the ground where the existing pile P is retained while solving the problem that it is difficult to secure a space for new construction of the pile. It is newly provided and makes it possible to secure sufficient bearing capacity to support the new structure (see FIG. 1). In a site where the site is small (narrow land), it may be difficult to install new piles in the gaps and four corners of the existing piles P while keeping them in the ground. In particular, in such a situation, the pile 100 of the present embodiment is left without removing the existing pile P, and a new pile is installed by using the narrow space around the existing pile P to increase the bearing capacity. It is possible to make it. In addition, in each figure, in order to show the difference from other parts in an easy-to-understand manner, the existing pile P is expressed darkly or with hatching (it may represent the cross section of the existing pile P). do not have).

[第2の実施形態]
本実施形態の杭100は、施工時における当該杭100の地中への推進力を向上させる推進力向上部を備えている。推進力向上部の具体例は、当該100の先端部120における底面121に設けられた掘削爪122(図2参照)、あるいは、先端部120の周面130に、底面121よりも先端側(鉛直下方)に突出するように設けられた掘削刃124(図3参照)などである。これら掘削爪122や掘削刃124は、打撃により杭100に推進力を作用させた際、あるいは杭100自体を回転させた際、地盤の一部を削って推進力を向上させる。
[Second Embodiment]
The pile 100 of the present embodiment includes a propulsion force improving unit for improving the propulsion force of the pile 100 into the ground at the time of construction. Specific examples of the propulsion force improving portion include an excavation claw 122 (see FIG. 2) provided on the bottom surface 121 of the tip portion 120 of the 100, or a peripheral surface 130 of the tip portion 120 on the tip side (vertical) of the bottom surface 121. An excavation blade 124 (see FIG. 3) provided so as to project downward). These excavation claws 122 and excavation blades 124 scrape a part of the ground to improve the propulsive force when a propulsive force is applied to the pile 100 by impact or when the pile 100 itself is rotated.

[第3の実施形態]
本実施形態の杭100は、杭本体部110に形成された羽根部140をさらに備えていてもよい。羽根部40は、地中にて当該杭100の支持力を発揮する支持部として機能することができ、また、その形態によっては(たとえば螺旋状に形成されていれば)杭100を回転させたときの推進力を向上させる部材(推進力向上部)として機能することもできる。羽根部140の具体例を挙げつつ説明する。
[Third Embodiment]
The pile 100 of the present embodiment may further include a blade portion 140 formed on the pile main body portion 110. The blade portion 40 can function as a support portion that exerts a support force of the pile 100 in the ground, and depending on its form (for example, if it is formed in a spiral shape), the pile 100 is rotated. It can also function as a member (propulsion force improvement unit) that improves the propulsion force of the time. A specific example of the blade portion 140 will be described.

羽根部140の一例は、杭100の先端部120付近の周面130のみに設けられた螺旋状の羽根からなるものである(図4参照)。螺旋状の羽根部140の回転方向の端面141に、回転方向(周方向)に突出する掘削爪142が設けられていてもよい。螺旋状の羽根部140は、底面121から連なるように形成されていてもよいし(図5参照)、底面121との間にスペースが形成されるように底面から少し離れた位置に形成されていてもよい(図6参照)。あるいは、羽根部140は、杭本体部110の周面130に連続的かつスパイラル状に形成されていてもよいし(図8参照)、断続的に形成された複数の不連続な羽根によって形成されていてもよい(図7参照)。断続的に形成された複数の不連続な各羽根は、切れ目(シーム)の位置がそろっていてもよいし、交互やばらばらであってもよい。なお、羽根部140の径は一定でなくてもよい。特に図示していないが、羽根部140は、径の異なる複数の羽根で形成されていてもよいし、漸次あるいは段階的に径が異なる羽根を含むように形成されていてもよい。さらに付け加えるならば、羽根部140は螺旋状でなくともよい。 An example of the blade portion 140 is composed of a spiral blade provided only on the peripheral surface 130 near the tip portion 120 of the pile 100 (see FIG. 4). An excavation claw 142 projecting in the rotation direction (circumferential direction) may be provided on the end surface 141 of the spiral blade portion 140 in the rotation direction. The spiral blade portion 140 may be formed so as to be continuous with the bottom surface 121 (see FIG. 5), or may be formed at a position slightly distant from the bottom surface so as to form a space between the spiral blade portion 140 and the bottom surface 121. It may be (see FIG. 6). Alternatively, the blade portion 140 may be formed continuously and spirally on the peripheral surface 130 of the pile body portion 110 (see FIG. 8), or is formed by a plurality of discontinuous blades formed intermittently. It may be (see FIG. 7). The intermittently formed discontinuous blades may have the same seam position, or may be alternate or disjointed. The diameter of the blade portion 140 does not have to be constant. Although not particularly shown, the blade portion 140 may be formed of a plurality of blades having different diameters, or may be formed so as to include blades having different diameters gradually or stepwise. In addition, the blade 140 does not have to be spiral.

上記のごとき各種羽根部140は、地中にて当該杭100の支持力を発揮する支持部として機能しうる。また、杭100を施工する際には、これら羽根部140の態様に基づいて当該杭100の深度を適宜設定・変更することとしてもよい。例えば、少なくとも先端部分が固い支持層Bに届くように施工された既存杭Pがある場合に、羽根部140が1枚状の羽根からなる杭100を、その先端部120が既存杭Pの先端よりも深くなる深度まで埋設し、羽根部140が支持層Bに入って十分な支持力が得られるように施工することができる(図9(A)参照)。あるいは、複数の羽根からなる羽根部140が形成されている杭100を、その先端部120が既存杭Pの先端よりも浅い深度で止まるように埋設し、羽根部140が支持層Bよりも上の軟弱層Aにある状態となるよう施工してもよい(図9(B)参照)。羽根部140が支持層Bに届いていなくても、複数の羽根を介して軟弱層Aから所定の支持力が得られるようにすることが可能である。なお、杭100を支持層Bの上で止める場合には、ここで説明した軟弱層Aの他、とくに図示はしていないが硬質な中間支持層がある場合(別言すれば、軟弱層Aの中に軟弱でない部分がある場合)はそこに止める場合もありえる。 The various blade portions 140 as described above can function as support portions that exert the bearing capacity of the pile 100 in the ground. Further, when constructing the pile 100, the depth of the pile 100 may be appropriately set or changed based on the mode of the blade portions 140. For example, when there is an existing pile P constructed so that at least the tip portion reaches the hard support layer B, the blade portion 140 is a pile 100 composed of a single blade, and the tip portion 120 is the tip of the existing pile P. It can be buried to a depth deeper than that, and the blade portion 140 can be installed so as to enter the support layer B and obtain sufficient support force (see FIG. 9A). Alternatively, a pile 100 having a blade portion 140 composed of a plurality of blades is embedded so that the tip portion 120 stops at a depth shallower than the tip of the existing pile P, and the blade portion 140 is above the support layer B. It may be constructed so as to be in the soft layer A of (see FIG. 9B). Even if the blade portion 140 does not reach the support layer B, it is possible to obtain a predetermined supporting force from the soft layer A via the plurality of blades. When the pile 100 is stopped on the support layer B, in addition to the soft layer A described here, there is a hard intermediate support layer (not shown in particular) (in other words, the soft layer A). If there is a non-soft part in it), it may stop there.

[第4の実施形態]
本実施形態の杭100は、主としてプレボーリング工法によって施工された杭(既存杭P)の周囲に施工する場合にとくに適した構造となっている(図10等参照)。ここで、プレボーリング工法とは、地盤に掘削孔をあらかじめ孔を設けておき、そこに既製の杭を建て込み施工する工法のことである。かかるプレポーリング工法においては、掘削孔に根固め液(セメントミルクなど)を注入し、さらに杭周固定液を注入した後、杭を建て込むといったことが行われることがあり、こうした場合には、既存杭Pの底部付近には根固め液が固化した部分(根固め部P1)、それ以外の部分には杭周固定液が固化した部分(杭周固定部P2)が形成されていることがある(図11参照)。これら杭周固定部P2や根固め部P1が杭100の施工の妨げとなる場合が生じうるが、本実施形態では、新設する杭100として、杭本体部110の内周側に、既設構造物の一部(本実施形態であれば、杭周固定部P2や根固め部P1の一部)に当接する掘削補助具150が設けられた杭を適用する(図10参照)。掘削補助具150は、杭100を施工する際、杭周固定部P2の一部を削り取ることで杭内面の摩擦抵抗を小さくし、埋設しやすくする(図12参照)。掘削補助具150はこのように機能しうるものであれば形状、構造などが特に限定されることはなく、具体例を挙げれば、円形の掘削リング(図13参照)、内周に楔型の波状刃が形成された連続したリングからなる掘削リング(図14参照)、スパイラル状に形成された内周突部(図15参照)、中心を向いて突出する断続的な複数の爪(図16参照)などによって掘削補助具150を構成することができる。また、これらの掘削補助具150のようにも杭100の内周側に形成するほか、特に図示してはいないが、杭100の先端部120に設けた爪などによって掘削補助具150を構成することもできる。あるいは、こちらも特に図示していないが、掘削補助具150が杭本体部110の周面130に構成されていてもよい。数ある既存杭Pの中には、杭周固定部P2が施工者らの予想を超えて外側に張り出しているものが存在する可能性があり、このようなとき、杭本体部110の周面130に構成された掘削補助具150によれば、杭周固定部P2などを効率よく掘削できる場合がある。
[Fourth Embodiment]
The pile 100 of the present embodiment has a structure particularly suitable for construction around a pile (existing pile P) constructed mainly by the pre-boring method (see FIG. 10 and the like). Here, the pre-boring method is a method in which an excavation hole is provided in the ground in advance and a ready-made pile is built in the hole. In such a pre-polling method, a rooting liquid (such as cement milk) may be injected into the drilling hole, and then a pile circumference fixing liquid may be injected before the pile is built. A portion where the root compaction liquid is solidified (root compaction portion P1) is formed near the bottom of the existing pile P, and a portion where the pile circumference fixing liquid is solidified (pile circumference fixing portion P2) is formed in the other portions. There is (see FIG. 11). These pile circumference fixing portions P2 and rooting portions P1 may interfere with the construction of the pile 100, but in the present embodiment, as the newly installed pile 100, an existing structure is provided on the inner peripheral side of the pile body portion 110. (In the present embodiment, a pile provided with the excavation assist tool 150 that abuts on a part of the pile circumference fixing portion P2 or a part of the root compaction portion P1) is applied (see FIG. 10). When constructing the pile 100, the excavation assist tool 150 reduces the frictional resistance on the inner surface of the pile by scraping off a part of the pile peripheral fixing portion P2, making it easier to bury (see FIG. 12). The shape and structure of the excavation aid 150 are not particularly limited as long as it can function in this way. Specific examples include a circular excavation ring (see FIG. 13) and a wedge-shaped inner circumference. An excavation ring consisting of a continuous ring with wavy blades (see FIG. 14), a spirally formed inner peripheral protrusion (see FIG. 15), and a plurality of intermittent claws protruding toward the center (FIG. 16). The excavation aid 150 can be configured by (see) or the like. Further, like these excavation assist tools 150, the excavation assist tool 150 is formed on the inner peripheral side of the pile 100, and although not particularly shown, the excavation assist tool 150 is formed by a claw or the like provided at the tip portion 120 of the pile 100. You can also do it. Alternatively, although not particularly shown here, the excavation assisting tool 150 may be configured on the peripheral surface 130 of the pile main body 110. Among the many existing piles P, there is a possibility that the pile circumference fixing portion P2 overhangs outward beyond the expectations of the installers, and in such a case, the peripheral surface of the pile main body portion 110 According to the excavation assist tool 150 configured in 130, the pile circumference fixing portion P2 and the like may be efficiently excavated.

[第5の実施形態]
本実施形態では、既存杭Pと新設する杭100とを一体化させることにより、新設杭100の強度を向上させる工法を採用する。一体化させるための具体的な手段の一例としては、施工中に杭100の基端から水硬性材料Qを供給し、杭100の内部(別言すれば、杭100と既存杭Pとの間の空間)に(好ましくはその全体に)充填することが挙げられる(図17参照)。あるいは、杭100の基端から水硬性材料Qを供給し、杭100の内部(別言すれば、杭100と既存杭Pとの間の空間)のうち先端部120のあたりにおいて既存杭Pと杭100とを一体化させることもできる(図18参照)。水硬性材料としてはセメントミルク、グラウト、コンクリート等を使用することができる。
[Fifth Embodiment]
In this embodiment, a construction method is adopted in which the strength of the newly constructed pile 100 is improved by integrating the existing pile P and the newly constructed pile 100. As an example of specific means for integrating, the hydraulic material Q is supplied from the base end of the pile 100 during construction, and the inside of the pile 100 (in other words, between the pile 100 and the existing pile P). (Preferably the entire space) is filled (see FIG. 17). Alternatively, the hydraulic material Q is supplied from the base end of the pile 100, and the existing pile P and the inside of the pile 100 (in other words, the space between the pile 100 and the existing pile P) around the tip portion 120. It can also be integrated with the pile 100 (see FIG. 18). As the hydraulic material, cement milk, grout, concrete and the like can be used.

[第6の実施形態]
本実施形態では、既存杭Pの一部に羽根部、拡底部といった他よりも太径の部分ないしは他よりも外側に突出している部分(以下「拡大部」といい図中において符号Pfで示す)がある場合にも施工可能または容易とする杭100ないしは工法を採用する。これは、羽根付き鋼管杭、拡底現場造成杭などといった既存杭Pを対象とする場合にとくに有用である。以下、具体例を挙げて説明する(図19~図21参照)。
[Sixth Embodiment]
In the present embodiment, a part of the existing pile P has a larger diameter than the other such as a blade portion and an expanded bottom portion, or a portion protruding outward from the others (hereinafter referred to as “enlarged portion”, which is indicated by the reference numeral Pf in the figure. ) Will be adopted, and the pile 100 or construction method will be adopted, which makes it possible or easy to construct. This is particularly useful when targeting existing piles P such as steel pipe piles with blades and piles created at the bottom expansion site. Hereinafter, a specific example will be described (see FIGS. 19 to 21).

杭100として、本実施形態では、その内径が対象とする既存杭Pの拡大部Pfより大きく、少なくとも当該拡大部Pfを内包した状態とすることができる杭を採用する。このような杭100は、外径、内径、断面形状ともに一律のものであってもよいし(図19参照)、先端部120を含む部分のみ、拡大部Pfを内包可能な大きさに拡径した形状のものであってもよい(図20参照)。あるいは、既存杭Pの拡大部Pfよりも内径が小さい杭100を、拡大部Pfと干渉する前の深さまで埋設するという工法を採用してもよい(図21参照)。これらのような各種杭100ないしは施工方法を採用することで、杭100が既存杭Pに干渉することに起因して施工に支障が生じるのを回避することができる。 As the pile 100, in the present embodiment, a pile whose inner diameter is larger than the enlarged portion Pf of the existing pile P to be targeted and which can contain at least the enlarged portion Pf is adopted. Such a pile 100 may have a uniform outer diameter, inner diameter, and cross-sectional shape (see FIG. 19), and the diameter of such a pile 100 is expanded to a size that can include the enlarged portion Pf only in the portion including the tip portion 120. It may have a shaped shape (see FIG. 20). Alternatively, a construction method may be adopted in which the pile 100 having an inner diameter smaller than that of the enlarged portion Pf of the existing pile P is buried to a depth before it interferes with the enlarged portion Pf (see FIG. 21). By adopting various piles 100 or construction methods such as these, it is possible to avoid problems in construction due to the pile 100 interfering with the existing pile P.

[第7の実施形態]
上記した第6の実施形態とは逆に、既存杭Pの杭頭部に羽根部、拡底部といった他よりも太径の部分ないしは他よりも外側に突出している部分(拡大部Pf)がある場合、以下のごとき杭100ないしは工法を採用して杭施工を可能または容易とすることができる。すなわち、杭100として、その内径が対象とする既存杭Pの拡大部Pfより大きく、少なくとも当該拡大部Pfを内包した状態とすることができる杭を採用する。このような杭100は、外径、内径、断面形状ともに一律のものであってもよいし(図22参照)、外径、内径、断面形状が途中で変わるものであってもよい(図示省略)。あるいは、既存杭Pのうち拡大部Pfのみを先に撤去し、その後、当該既存杭Pの残りの部分の周囲に杭10を施工するという工法を採用してもよい(図23参照)。
[7th Embodiment]
Contrary to the sixth embodiment described above, the pile head of the existing pile P has a portion having a larger diameter than the others, such as a blade portion and a bottom expansion portion, or a portion protruding outward from the others (enlarged portion Pf). In this case, the following pile 100 or construction method can be adopted to enable or facilitate pile construction. That is, as the pile 100, a pile whose inner diameter is larger than the enlarged portion Pf of the existing pile P to be targeted and which can contain at least the enlarged portion Pf is adopted. Such a pile 100 may have a uniform outer diameter, inner diameter, and cross-sectional shape (see FIG. 22), or may have an outer diameter, inner diameter, and cross-sectional shape that change in the middle (not shown). ). Alternatively, a construction method may be adopted in which only the enlarged portion Pf of the existing pile P is removed first, and then the pile 10 is constructed around the remaining portion of the existing pile P (see FIG. 23).

[第8の実施形態]
既存杭Pをはじめとする既設構造物が真っすぐの状態であればよいが常にそうであるとは限らず、施工時に作用する力あるいは施工後の外力などの影響により地盤の中で曲がった状態となっていることが起こりうる(図24等参照)。本実施形態では、このような既存杭Pをはじめとする既設構造物の周囲に杭100を施工する場合にも杭施工を可能または容易とするべく、以下のごとき杭100ないしは工法を採用する。具体例を挙げて説明する(図24~図27参照)。
[Eighth Embodiment]
It suffices if the existing structure such as the existing pile P is in a straight state, but this is not always the case. (See Fig. 24, etc.). In the present embodiment, the following pile 100 or construction method is adopted in order to enable or facilitate the pile construction even when the pile 100 is constructed around the existing structure such as the existing pile P. A specific example will be given (see FIGS. 24 to 27).

杭100として、途中が曲がっている既存杭Pの一部または全部を内包できる程度の内径の杭100を採用し、当該杭100を既存杭Pの傾斜・曲がりに沿った斜杭として施工することとしてもよい(図24参照)。あるいは、杭100の先端部120に掘削補助爪といった補助的な破壊用治具152を設けておき、既存杭Pのうち当該杭100よりも径方向外側に出っ張る部分を破壊しながら施工することとしてもよい(図25参照)。あるいは、杭100の先端部120付近にローラーといった補助的な誘導用治具154を設けておき、既存杭Pの湾曲に沿って杭100が追随するように誘導しながら施工することとしてもよい(図26参照)。あるいは、杭100の途中(たとえば長手方向の中間部あたり)に蛇腹を設けるなどして軸力を十分に伝達し尚かつフレキシブルに曲がる継手部156を形成し、既存杭Pの湾曲に沿って杭100が追随するように曲がりながら施工することとしてもよい(図27参照)。 As the pile 100, a pile 100 having an inner diameter that can include a part or all of the existing pile P that is bent in the middle is adopted, and the pile 100 is constructed as an inclined pile along the inclination / bending of the existing pile P. (See FIG. 24). Alternatively, an auxiliary destructive jig 152 such as an excavation auxiliary claw is provided at the tip 120 of the pile 100, and the existing pile P is constructed while destroying the portion of the existing pile P that protrudes radially outward from the pile 100. It may be good (see FIG. 25). Alternatively, an auxiliary guiding jig 154 such as a roller may be provided near the tip 120 of the pile 100, and the pile 100 may be guided so as to follow the curve of the existing pile P. See FIG. 26). Alternatively, a bellows is provided in the middle of the pile 100 (for example, around the middle portion in the longitudinal direction) to form a joint portion 156 that sufficiently transmits axial force and bends flexibly, and the pile is formed along the curve of the existing pile P. It may be constructed while bending so that the 100 follows (see FIG. 27).

なお、上述の実施形態は本発明の好適な実施の一例ではあるがこれに限定されるものではなく本発明の要旨を逸脱しない範囲において種々変形実施可能である。例えば、上述の各実施形態では地中に埋設されて構造物を支持する杭100を施工する例を主として説明したが、ここでいう杭は文字通り単純な杭として地上などの構造物の重量を支えるものの他、その他の種々の杭ないしは杭状の補強物などに対しても本発明を適用しうることはいうまでもない。また、施工された杭100は、地中に構成される地中構造物の一部となってもよい。 Although the above-described embodiment is an example of a preferred embodiment of the present invention, the present invention is not limited to this, and various modifications can be made without departing from the gist of the present invention. For example, in each of the above-described embodiments, an example of constructing a pile 100 buried in the ground to support a structure has been mainly described, but the pile referred to here literally supports the weight of a structure such as above ground as a simple pile. Needless to say, the present invention can be applied to various other piles or pile-shaped reinforcements in addition to the above. Further, the constructed pile 100 may be a part of an underground structure constructed in the ground.

また、上述の各実施形態では既存杭Pの周囲に杭100を施工する場合について説明したが、既存杭Pは、施工対象現場における地中の既設構造物の一例にすぎない。既存杭の他、直接基礎、柱状改良体等といった既設の各種構造物、別言すれば地中にて障害になりうる物の周囲に杭100を施工する場合に本発明を適用することも当然に可能である。 Further, in each of the above-described embodiments, the case where the pile 100 is constructed around the existing pile P has been described, but the existing pile P is only an example of the existing structure in the ground at the construction target site. In addition to existing piles, it is natural to apply the present invention when constructing piles 100 around existing structures such as direct foundations, columnar improved bodies, etc., in other words, objects that may be obstacles in the ground. Is possible.

本発明は、杭とその施工方法および地中構造物に適用して好適である。 The present invention is suitable for application to piles, construction methods thereof, and underground structures.

100…開放端杭(杭)
110…杭本体部
120…先端部
121…底面
122…掘削爪
124…掘削刃
130…周面
140…羽根部(支持部)
141…羽根部の回転方向の端面
142…掘削爪
150…掘削補助具
152…掘削補助爪(補助的な破壊用治具)
154…誘導用治具
156…継手部
300…構造物
A…軟弱層
B…支持層
P…既存杭(既設構造物)
P1…根固め部
P2…杭周固定部
Pf…既存杭の拡大部
100 ... Open end pile (pile)
110 ... Pile body 120 ... Tip 121 ... Bottom 122 ... Excavation claw 124 ... Excavation blade 130 ... Peripheral surface 140 ... Blade (support)
141 ... End face in the direction of rotation of the blade 142 ... Excavation claw 150 ... Excavation assisting tool 152 ... Excavation assisting claw (auxiliary destruction jig)
154 ... Induction jig 156 ... Joint part 300 ... Structure A ... Soft layer B ... Support layer P ... Existing pile (existing structure)
P1 ... Root consolidation part P2 ... Pile circumference fixing part Pf ... Enlarged part of existing pile

Claims (11)

地中に埋設されて地上の構造物を支持する杭であって、
開口した先端部と、
施工対象現場における地中の既設構造物を内包する杭本体部と、
を有する杭。
A pile that is buried in the ground and supports structures on the ground.
With the open tip,
The pile body that contains the existing structure in the ground at the construction site, and
Stakes with.
前記杭本体部に形成された羽根部をさらに備える、請求項1に記載の杭。 The pile according to claim 1, further comprising a blade portion formed on the pile main body portion. 前記羽根部は、前記先端部の周面にのみ設けられている、請求項2に記載の杭。 The pile according to claim 2, wherein the blade portion is provided only on the peripheral surface of the tip portion. 前記羽根部は、前記本体部の周面に連続的かつスパイラル状に設けられている、請求項2に記載の杭。 The pile according to claim 2, wherein the blade portion is continuously and spirally provided on the peripheral surface of the main body portion. 前記羽根部は、前記本体部の周面に断続的に設けられている、請求項2に記載の杭。 The pile according to claim 2, wherein the blade portion is intermittently provided on the peripheral surface of the main body portion. 前記杭本体部の内周側、前記先端部または前記周面に、前記既設構造物の一部に当接する掘削補助具が設けられている、請求項1から5のいずれか一項に記載の杭。 The invention according to any one of claims 1 to 5, wherein an excavation assisting tool that abuts a part of the existing structure is provided on the inner peripheral side, the tip end portion, or the peripheral surface of the pile main body portion. Pile. 前記請求項1から6のいずれか一項に記載の杭が埋設されて地中に構成された地中構造物。 An underground structure formed in the ground by burying the pile according to any one of claims 1 to 6. 杭の施工方法であって、
先端部が開口した杭を、施工対象現場における地中の既設構造物の周囲に、前記既設構造物を内包するように地盤に施工する、杭の施工方法。
It ’s a pile construction method.
A pile construction method in which a pile with an open tip is constructed on the ground so as to include the existing structure around the existing structure in the ground at the construction target site.
地中にて当該杭の支持力を発揮する支持部を、当該地中にて所定の支持力が得られる土層中に位置させる、請求項8に記載の杭の施工方法。 The method for constructing a pile according to claim 8, wherein a support portion that exerts a supporting force of the pile in the ground is located in a soil layer in which a predetermined supporting force can be obtained in the ground. 前記先端部が前記既設構造物の下端よりも深くなる位置まで前記杭を地盤に施工する、請求項8または9に記載の杭の施工方法。 The method for constructing a pile according to claim 8 or 9, wherein the pile is constructed on the ground to a position where the tip portion is deeper than the lower end of the existing structure. 前記杭の内部に水硬性材料を供給し、前記杭に内包される前記既設構造物と当該杭とを一体化させる、請求項8から10のいずれか一項に記載の杭の施工方法。 The pile construction method according to any one of claims 8 to 10, wherein a hydraulic material is supplied to the inside of the pile, and the existing structure contained in the pile is integrated with the pile.
JP2020191905A 2020-11-18 2020-11-18 Pile and its construction method and underground structure Pending JP2022080696A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020191905A JP2022080696A (en) 2020-11-18 2020-11-18 Pile and its construction method and underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020191905A JP2022080696A (en) 2020-11-18 2020-11-18 Pile and its construction method and underground structure

Publications (1)

Publication Number Publication Date
JP2022080696A true JP2022080696A (en) 2022-05-30

Family

ID=81757197

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020191905A Pending JP2022080696A (en) 2020-11-18 2020-11-18 Pile and its construction method and underground structure

Country Status (1)

Country Link
JP (1) JP2022080696A (en)

Similar Documents

Publication Publication Date Title
JP5069873B2 (en) Steel pipe pile construction method
JP2008190116A (en) Liquefaction countermeasure structure of foundation ground of building
JP4974364B2 (en) Pile burying method
JP4946695B2 (en) Construction method of double pipe type pile head structure
JP2021121725A (en) Underground wall pile structure provided with expanded bottom part
JP2022080696A (en) Pile and its construction method and underground structure
KR101807366B1 (en) A Foundation Method Of Continuous and Cut Off wall By Overlap Casing
JP4029191B2 (en) Subsidence suppression structure, construction method of settlement suppression structure
JP5406628B2 (en) Cast-in-place pile installation method
JP2010163843A (en) Soil improving method
JP2015190192A (en) High strength rotary penetration pile
JP2009074309A (en) Vertical shaft and its construction method
JP2004332262A (en) Edge ground improving pile and its execution method
JP6769751B2 (en) Frame laying method
JP2017197910A (en) Construction method of earth retaining wall structure, and earth retaining wall structure
JP6885669B2 (en) Construction method of pile foundation and pile foundation
JP2007224537A (en) Foundation for steel pipe pole, and foundation method therefor
JP7153603B2 (en) Construction method of underground structure
JP6462298B2 (en) Foundation pile structure
JP7509679B2 (en) Structure and method for preventing subsidence of adjacent buildings
JP2675858B2 (en) Vertical shaft excavation method
JP2011106230A (en) Method for constructing earth retaining wall
JP7166137B2 (en) Thrust transmission structure and thrust transmission method for shield machine.
JP6466236B2 (en) H steel pile and its placing method, and steel pipe pile placing method
JP2881501B2 (en) Construction method for high strength cast-in-place concrete piles

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230906

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240528