JP2022054028A - Management method, management system, and program for bim model - Google Patents

Management method, management system, and program for bim model Download PDF

Info

Publication number
JP2022054028A
JP2022054028A JP2020160989A JP2020160989A JP2022054028A JP 2022054028 A JP2022054028 A JP 2022054028A JP 2020160989 A JP2020160989 A JP 2020160989A JP 2020160989 A JP2020160989 A JP 2020160989A JP 2022054028 A JP2022054028 A JP 2022054028A
Authority
JP
Japan
Prior art keywords
progress
bim model
degree
classification
index
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2020160989A
Other languages
Japanese (ja)
Inventor
隆二 谷口
Ryuji Taniguchi
潤 中嶋
Jun Nakajima
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2020160989A priority Critical patent/JP2022054028A/en
Publication of JP2022054028A publication Critical patent/JP2022054028A/en
Pending legal-status Critical Current

Links

Images

Abstract

To provide a management method, a management system, and a program for a BIM model that enhances accuracy in grasping progress of components in the BIM model.SOLUTION: A flow for calculating a degree of progress index and calculating a progress rate of a BIM model using the degree of progress index includes: an option presentation step in which a computer presents a materialization degree option in which a materialization degree of a component of the BIM model is presented in plural by level and an approval stage option in which a stage up to approval of the materialization degree is presented in plural by stage; a selection acceptance step in which the computer accepts selection from among the presented materialization degree option and approval stage option; a degree of progress index calculation step in which the computer calculates a degree of progress index indicating how much the component has been determined based on the selected materialization degree and approval stage; and an association step in which the computer associates the calculated degree of progress index with the component.SELECTED DRAWING: Figure 6

Description

本発明は、BIMモデルの管理方法、管理システム、及びプログラムに関する。 The present invention relates to a BIM model management method, management system, and program.

構造物(建築物、土木構造物等)のプロジェクトの進捗を管理する方法として、三次元モデル(3D-CAD)に構造物の情報を関連付けて管理するBIM(Building Information Modeling)またはCIM(Construction Information Modeling)(以下、BIMまたはCIMをBIMモデルともいう)による進捗管理の方法が知られている。(例えば、特許文献1参照)。 As a method of managing the progress of a project of a structure (building, civil engineering structure, etc.), BIM (Building Information Modeling) or CIM (Construction Information) that manages the information of the structure in association with a three-dimensional model (3D-CAD) A method of progress management by Modeling (hereinafter, BIM or CIM is also referred to as a BIM model) is known. (See, for example, Patent Document 1).

特開2018-198019号公報Japanese Unexamined Patent Publication No. 2018-198019

BIMモデルは、複数の利用者(意匠、構造、設備のそれぞれの設計者や承認者、施行者、プロジェクト管理者等)が各々閲覧等してその進捗を確認することができるが、その正確性については不明瞭な点があった。例えば、BIMモデルの壁の位置が承認待ちであり、まだ決定していない(変更の余地が十分にある)場合でも、決定していないという情報は設計者、承認者等の入力者の頭の中にしかなく、その他の利用者は、その壁の位置が決まっている(位置が決定するまで設計が進んでいる)と認識してしまう場合があった。 The BIM model can be viewed by multiple users (design, structure, equipment designers, approvers, enforcers, project managers, etc.) to check the progress, but its accuracy. There was an ambiguity about. For example, even if the position of the wall of the BIM model is awaiting approval and has not been decided yet (there is ample room for change), the information that it has not been decided is the head of the designer, approver, etc. It was only inside, and other users sometimes recognized that the position of the wall was fixed (the design was in progress until the position was decided).

本発明は、かかる課題に鑑みてなされたものであって、その目的とするところは、BIMモデルにおける部品(構成要素に相当)の進捗把握の正確性を高めることにある。 The present invention has been made in view of the above problems, and an object of the present invention is to improve the accuracy of grasping the progress of parts (corresponding to components) in a BIM model.

上記目的を達成するための主たる発明は、BIMモデルの構成要素の具体化度合(進展度合い)がレベル別に複数表された具体化度合選択肢と、前記具体化度合の承認までの段階が段階別に複数表された承認段階選択肢と、をコンピュータが提示する選択肢提示ステップと、提示された前記具体化度合選択肢及び前記承認段階選択肢の中からの選択をコンピュータが受け付ける選択受付ステップと、選択された前記具体化度合及び前記承認段階に基づいて、前記構成要素がどの程度決定されているかを示す進展度指数をコンピュータが算出する進展度指数算出ステップと、算出された前記進展度指数をコンピュータが前記構成要素に関連付ける関連付けステップと、を有することを特徴とするBIMモデルの管理方法である。 The main inventions for achieving the above object are a plurality of concreteness degree options in which a plurality of concreteness degrees (progress degree) of the components of the BIM model are represented for each level, and a plurality of stages until the approval of the specificity degree is obtained. The presented approval stage option, the option presentation step presented by the computer, the selection acceptance step in which the computer accepts the selection from the presented reification degree option and the approval stage option, and the selected specific. A progress index calculation step in which a computer calculates a progress index indicating how much the component is determined based on the degree of reification and the approval stage, and the computer calculates the progress index as the component. It is a management method of a BIM model characterized by having an association step associated with.

本発明の他の特徴については、本明細書及び添付図面の記載により明らかにする。 Other features of the present invention will be clarified by the description in the present specification and the accompanying drawings.

本発明によれば、BIMモデルにおける部品の進捗把握の正確性を高めることができる。 According to the present invention, it is possible to improve the accuracy of grasping the progress of parts in the BIM model.

本実施形態に係る管理システム1の構成図である。It is a block diagram of the management system 1 which concerns on this embodiment. 部位分類情報記憶部11に記憶される情報の一例である。This is an example of information stored in the site classification information storage unit 11. 状態指標記憶部12に記憶される情報の一例である。This is an example of information stored in the state index storage unit 12. 状態記憶部13に記憶される情報の一例である。This is an example of information stored in the state storage unit 13. 登録情報の事前登録手順の一例を示したフローチャートである。It is a flowchart which showed an example of the pre-registration procedure of registration information. 進展度指数の算出及び進展度指数を用いたBIMモデル2aの進捗率算出のフローチャートの一例である。This is an example of a flowchart for calculating the progress index and calculating the progress rate of the BIM model 2a using the progress index. 進展度指数の算出に係るデータの一例である。This is an example of data related to the calculation of the progress index. 部位分類進展度指数の算出結果の一例である。This is an example of the calculation result of the site classification progress index. フェーズ進展率の算出結果の一例である。This is an example of the calculation result of the phase progress rate. パラメータ入力状態の抽出からBIMモデル2aの進捗率の算出までのフローチャートの一例である。This is an example of a flowchart from the extraction of the parameter input state to the calculation of the progress rate of the BIM model 2a. パラメータ入力状態の抽出結果から入力のあるパラメータの割合、加算値、及び累積値の算出結果の一例である。It is an example of the calculation result of the ratio, the addition value, and the cumulative value of the parameter with the input from the extraction result of the parameter input state. フェーズ進展率の算出結果の一例である。This is an example of the calculation result of the phase progress rate. 具体化度合選択肢及び承認段階選択肢を表示したGUIの一例である。This is an example of a GUI that displays the reification degree option and the approval stage option. BIMモデル2aの進捗率を表示したGUIの一例である。This is an example of a GUI that displays the progress rate of the BIM model 2a. 進展度管理装置110を有する管理システム101の構成図である。It is a block diagram of the management system 101 which has the progress degree management apparatus 110. 進展度管理装置210内に全体をまとめた管理システム201の構成図である。It is a block diagram of the management system 201 which put together the whole in the progress degree management apparatus 210. BIMソフト302内に全体をまとめた管理システム301の構成図である。It is a block diagram of the management system 301 which put together in the BIM software 302.

本明細書及び添付図面により、少なくとも、以下の事項が明らかとなる。 The present specification and the accompanying drawings clarify at least the following matters.

BIMモデルの構成要素の具体化度合がレベル別に複数表された具体化度合選択肢と、前記具体化度合の承認までの段階が段階別に複数表された承認段階選択肢と、をコンピュータが提示する選択肢提示ステップと、提示された前記具体化度合選択肢及び前記承認段階選択肢の中からの選択をコンピュータが受け付ける選択受付ステップと、選択された前記具体化度合及び前記承認段階に基づいて、前記構成要素がどの程度決定されているかを示す進展度指数をコンピュータが算出する進展度指数算出ステップと、算出された前記進展度指数をコンピュータが前記構成要素に関連付ける関連付けステップと、を有することを特徴とするBIMモデルの管理方法。 The computer presents options for the degree of concreteness in which the degree of concreteness of the components of the BIM model is expressed for each level, and the option for the approval stage in which the stages up to the approval of the degree of concreteness are expressed in multiple stages. Which of the components is based on the step, the selection acceptance step in which the computer accepts the selection from the presented reification degree options and the approval stage options, and the selected reification degree and approval stages. A BIM model characterized by having a progress index calculation step in which a computer calculates a progress index indicating whether or not the degree is determined, and an association step in which the computer associates the calculated progress index with the component. How to manage.

このようなBIMモデルの管理方法によると、BIMモデルの部品の具体化度合と承認段階から部品の進展度指数を算出することにより、BIMモデルにおける部品の進捗把握の正確性を高めることが可能となる。 According to such a BIM model management method, it is possible to improve the accuracy of grasping the progress of parts in the BIM model by calculating the progress index of the parts from the concreteness degree of the parts of the BIM model and the approval stage. Become.

かかるBIMモデルの管理方法であって、前記構成要素は複数種類の部位分類のいずれかに属しており、共通の部位分類に属する前記構成要素に関連付けられた前記進展度指数を平均化して、部位分類毎の部位分類進展度指数をコンピュータが算出する部位分類進展度指数算出ステップを有することが望ましい。 In such a BIM model management method, the component belongs to one of a plurality of types of site classifications, and the progress index associated with the component belonging to a common site classification is averaged to form a site. It is desirable to have a part classification progress index calculation step in which a computer calculates the part classification progress index for each classification.

このようなBIMモデルの管理方法によると、部位分類(外壁、外部ドア、柱等)毎に部位分類進展度指数で進捗を確認することができる。 According to such a BIM model management method, the progress can be confirmed by the part classification progress index for each part classification (outer wall, outer door, pillar, etc.).

かかるBIMモデルの管理方法であって、前記部位分類進展度指数は、前記BIMモデルに対応したプロジェクトの複数のフェーズ毎に算出され、前記複数のフェーズ毎に設定される目標部位分類進展度指数の事前登録をコンピュータが受け付ける事前登録受け付けステップと、現フェーズ及び前記現フェーズの一つ前の前フェーズに対応する前記目標部位分類進展度指数と、前記現フェーズに対応する前記部位分類進展度指数とに基づいて、前記現フェーズまでの進展度合を示す進展率をコンピュータが算出する進展率算出ステップと、を有することが望ましい。 In such a BIM model management method, the site classification progress index is a target site classification progress index calculated for each of a plurality of phases of a project corresponding to the BIM model and set for each of the plurality of phases. The pre-registration acceptance step in which the computer accepts the pre-registration, the target site classification progress index corresponding to the current phase and the previous phase immediately before the current phase, and the site classification progress index corresponding to the current phase. Based on the above, it is desirable to have a progress rate calculation step in which a computer calculates a progress rate indicating the degree of progress up to the current phase.

このようなBIMモデルの管理方法によると、各フェーズにおける進展率を確認することができる。 According to such a BIM model management method, the progress rate in each phase can be confirmed.

かかるBIMモデルの管理方法であって、前記進展率は、前記部位分類毎に算出され、前記部位分類毎の前記進展率を平均化して前記BIMモデルの進捗率をコンピュータが算出するBIMモデル進捗率算出ステップを有することが望ましい。 In such a BIM model management method, the progress rate is calculated for each part classification, and the progress rate of the BIM model is calculated by a computer by averaging the progress rate for each part classification. It is desirable to have a calculation step.

このようなBIMモデルの管理方法によると、BIMモデルの進捗率を確認することができる。 According to such a BIM model management method, the progress rate of the BIM model can be confirmed.

BIMモデルを管理する管理方法であって、前記BIMモデルに対応したプロジェクトの複数のフェーズ毎に、かつ、前記BIMモデルの部位分類毎に設定される目標部位分類進展度指数であって、前記目標部位分類進展度指数の各々に前記部位分類のパラメータが関連付けられている目標部位分類進展度指数の事前登録をコンピュータが受け付ける事前登録受け付けステップと、前記パラメータの確定有無についての情報をコンピュータが抽出する情報抽出ステップと、現フェーズ及び前記現フェーズの一つ前の前フェーズに対応する前記目標部位分類進展度指数と、前記パラメータについての情報抽出結果と、に基づいて、前記現フェーズまでの進展度合を示す進展率をコンピュータが前記部位分類毎に算出する進展率算出ステップと、を有することを特徴とするBIMモデルの管理方法。 A management method for managing a BIM model, which is a target site classification progress index set for each of a plurality of phases of a project corresponding to the BIM model and for each site classification of the BIM model. The computer extracts the pre-registration acceptance step in which the computer accepts the pre-registration of the target site classification progress index in which the parameter of the site classification is associated with each of the site classification progress index, and the information on whether or not the parameter is confirmed. The degree of progress up to the current phase based on the information extraction step, the target site classification progress index corresponding to the current phase and the previous phase immediately before the current phase, and the information extraction result for the parameter. A method for managing a BIM model, comprising: a progress rate calculation step in which a computer calculates a progress rate indicating each of the site classifications.

このようなBIMモデルの管理方法によると、パラメータの確定有無の情報から各フェーズにおける進展率を確認することができる。 According to such a BIM model management method, the progress rate in each phase can be confirmed from the information on whether or not the parameters are fixed.

かかるBIMモデルの管理方法であって、前記進展率は、前記部位分類毎に算出され、前記部位分類毎の前記進展率を平均化して前記BIMモデルの進捗率をコンピュータが算出するBIMモデル進捗率算出ステップを有することが望ましい。 In such a BIM model management method, the progress rate is calculated for each part classification, and the progress rate of the BIM model is calculated by a computer by averaging the progress rate for each part classification. It is desirable to have a calculation step.

このようなBIMモデルの管理方法によると、パラメータの確定有無の情報からBIMモデルの進捗率を確認することができる。 According to such a BIM model management method, the progress rate of the BIM model can be confirmed from the information on whether or not the parameters are fixed.

BIMモデルを管理する管理システムであって、上記したBIMモデルの管理方法のいずれかを実行することを特徴とする管理システム。 A management system that manages a BIM model and is characterized by executing any of the above-mentioned BIM model management methods.

このような管理システムによれば、上記したBIM管理方法と同様の効果を得ることができる。 According to such a management system, the same effect as the above-mentioned BIM management method can be obtained.

BIMモデルを管理するプログラムであって、上記したBIMモデルの管理方法のいずれかを実行させることを特徴とするプログラム。 A program that manages a BIM model and is characterized by executing any of the above-mentioned BIM model management methods.

このようなプログラムによれば、上記したBIM管理方法と同様の効果を得ることができる。 According to such a program, the same effect as the above-mentioned BIM management method can be obtained.

===本実施形態===
本実施形態に係る管理システム1を用いた管理方法(進捗等を確認する方法)について、図を用いて説明する。図1は、本実施形態に係る管理システム1の構成図である。なお、以下では、先ず、管理システム1を構成する各部を説明し、その後に管理システム1を用いた管理方法について説明する。
=== This embodiment ===
A management method (method for confirming progress, etc.) using the management system 1 according to the present embodiment will be described with reference to the drawings. FIG. 1 is a configuration diagram of a management system 1 according to the present embodiment. In the following, first, each part constituting the management system 1 will be described, and then a management method using the management system 1 will be described.

本実施形態に係る管理システム1は、BIMソフト2と、記憶部10と、状態処理部20と、表示部30と、を有している。 The management system 1 according to the present embodiment includes BIM software 2, a storage unit 10, a state processing unit 20, and a display unit 30.

BIMソフト2は、コンピュータ上で動作し、構造物(建築物等)の三次元モデルであるBIMモデル2aを作成する機能を有するソフトウェアである。そして、BIMモデル2aは、複数の部品(構成要素に相当)により構成されている。つまり、BIMモデル2aは、コンピュータ上のBIMソフト2において作成された構造物の3次元(3D)モデルであり、構造物を構成する部品の集合体である。 BIM software 2 is software that operates on a computer and has a function of creating a BIM model 2a that is a three-dimensional model of a structure (building or the like). The BIM model 2a is composed of a plurality of parts (corresponding to constituent elements). That is, the BIM model 2a is a three-dimensional (3D) model of the structure created by the BIM software 2 on the computer, and is a collection of parts constituting the structure.

また、BIMモデル2aの部品は、3Dモデルで表された形状以外にも素材や仕上げ等の様々な情報を有しており、各々の部品を進展させる(より詳細な情報を設定して具体化する)ことにより、BIMモデル2aが進展する(BIMモデル2aの完成度が高まる)。 In addition, the parts of the BIM model 2a have various information such as materials and finishes in addition to the shape represented by the 3D model, and each part is advanced (more detailed information is set and embodied). By doing so, the BIM model 2a progresses (the degree of perfection of the BIM model 2a increases).

BIMモデル2aにおける部品は、その進展した状態を示すものとして、BIMモデル2aの位置、大きさの情報を示した位置状態と、属性の情報(例えば部品が扉の場合、扉の素材、防火仕様の有無等の情報)を示した属性状態と、を有している。そして、位置状態及び属性状態は、その部品の進展(具体化)の程度によりそれぞれが具体化度合として数値化されており、かかる数値は、LOD(Level Of Development)に基づいている(詳しくは後述する)。 The parts in the BIM model 2a show the advanced state, the position state showing the position and size information of the BIM model 2a, and the attribute information (for example, when the part is a door, the door material and fireproof specifications). It has an attribute state indicating (information such as the presence or absence of). The position state and the attribute state are each quantified as the degree of materialization according to the degree of progress (materialization) of the part, and such numerical values are based on LOD (Level Of Development) (details will be described later). do).

なお、複数の部品に共通の属性情報(例えば、複数の壁(部品)の素材がコンクリートである事を管理する情報要素)については、部品の属性情報とは別にBIMモデル2a上における共通属性として管理されるBIMソフトもあり、その進展(具体化)の程度についても部品の属性状態と同じように具体化度合としてLODに基づいて数値化されている。 The attribute information common to a plurality of parts (for example, an information element that manages that the material of a plurality of walls (parts) is concrete) is set as a common attribute on the BIM model 2a separately from the attribute information of the parts. There is also BIM software that is managed, and the degree of progress (materialization) is also quantified based on the LOD as the degree of materialization, similar to the attribute state of parts.

記憶部10は、部位分類情報記憶部11と、状態指標記憶部12と、状態記憶部13と、を有しており、様々な情報を保存している部分である。記憶部10としては、例えば、コンピュータのハードディスク、RAM(Random Access Memory)等を用いることができる。 The storage unit 10 has a site classification information storage unit 11, a state index storage unit 12, and a state storage unit 13, and is a portion that stores various information. As the storage unit 10, for example, a hard disk of a computer, a RAM (Random Access Memory), or the like can be used.

部位分類情報記憶部11には、部品を部位(以下、部位分類ともいう)に分類するための情報が保存されている。図2は、部位分類情報記憶部11に記憶される情報の一例であって、図2aは、部位分類データ11aの一例であり、図2bは、部位分類基準データ11bの一例である。 The part classification information storage unit 11 stores information for classifying parts into parts (hereinafter, also referred to as part classification). FIG. 2 is an example of information stored in the site classification information storage unit 11, FIG. 2a is an example of site classification data 11a, and FIG. 2b is an example of site classification reference data 11b.

部位分類データ11aには、部品の分類するための基本データとして部位分類の名称が保存されており、図2aに示すように、外壁、外部ドア、外部窓等が記憶されている。そして、BIMモデル2aの部品は、例えば、部品1~5の部位分類が外壁、部品6~10の部位分類が外部ドアというように分類される。 The part classification data 11a stores the name of the part classification as basic data for classifying the parts, and as shown in FIG. 2a, the outer wall, the outer door, the outer window, and the like are stored. Then, the parts of the BIM model 2a are classified, for example, the part classification of the parts 1 to 5 is the outer wall, and the part classification of the parts 6 to 10 is the outer door.

部位分類基準データ11bには、部品を部位分類に分類する基準が保存されており、図2bに示すように、部位分類(外壁、外部ドア等)に対応する項目(カテゴリ、内/外等)と、それぞれの項目の基準値(壁、外等)が保存されている。そして、BIMモデル2aの部品は、この情報に基づいて、例えば、部品1はカテゴリが壁であって、内/外が外であるので、部品1の部位分類は外壁、部品2はカテゴリがドアであって、内/外が外であるので、部品2の部位分類は外部ドア、というように分類される。 The site classification standard data 11b stores the criteria for classifying parts into the site classification, and as shown in FIG. 2b, the items (category, inside / outside, etc.) corresponding to the site classification (outer wall, outer door, etc.). And the reference value (wall, outside, etc.) of each item is saved. Then, based on this information, for the parts of the BIM model 2a, for example, the category of the part 1 is the wall and the inside / outside is the outside, so that the part classification of the part 1 is the outer wall and the category of the part 2 is the door. Since the inside / outside is the outside, the part classification of the part 2 is classified as an external door.

状態指標記憶部12には、部品の進展程度等を数値化したデータが保存されている。図3は、状態指標記憶部12に記憶される情報の一例であって、図3aは、具体化度合データ12aの一例であり、図3bは、目標値(目標部位分類進展度指数に相当)データ12bの一例であり、図3cは、パラメータデータ12cの一例である。 The state index storage unit 12 stores data in which the degree of progress of parts and the like are quantified. FIG. 3 is an example of information stored in the state index storage unit 12, FIG. 3a is an example of materialization degree data 12a, and FIG. 3b is a target value (corresponding to a target site classification progress index). It is an example of the data 12b, and FIG. 3c is an example of the parameter data 12c.

ここで、本実施形態においては、部品の具体化(進展)の程度の数値化には、LODをベースとした数値(以下、状態指標値ともいう)が用いられている。LOD(Level Of Development)とは、アメリカ建築家協会がBIMモデルの進展度の基準として2008年に制定したものであり、2013年にはLOD仕様書(LOD Specification)が公開され、以降、ほぼ毎年更新されている。 Here, in the present embodiment, a numerical value based on LOD (hereinafter, also referred to as a state index value) is used for quantifying the degree of materialization (progress) of the component. LOD (Level Of Development) was established by the American Institute of Architects in 2008 as a standard for the progress of BIM models. In 2013, the LOD Specification was released, and almost every year since then. It has been updated.

このLOD仕様書では、進展度の基準を6段階にレベル分けしており、LOD100、200、300、350、400、500の進展度の基準が決められている。なお、LODの数値は、大きくなるほど進展していることを意味し、大きくなるほどBIMモデルがより完成に近づいていることを意味する。 In this LOD specification, the standard of progress is divided into 6 levels, and the standard of progress of LOD 100, 200, 300, 350, 400, and 500 is determined. It should be noted that the larger the value of LOD, the more advanced it is, and the larger the value, the closer the BIM model is to completion.

LOD仕様書の数値をそのまま用いて具体化(進展)の程度を数値化してもよいが、本実施形態においては、LOD仕様書に示された6段階のレベルに加えて、さらに細かくレベルを設定した状態指標値を用いて具体化(進展)の程度を数値化している。 The degree of materialization (progress) may be quantified by using the numerical value of the LOD specification as it is, but in this embodiment, the level is set more finely in addition to the 6 levels shown in the LOD specification. The degree of materialization (progress) is quantified using the state index values.

具体化度合データ12aには、図3aに示すように、部品の進展程度を示す具体化度合が記憶されており、上述したように、具体化度合は状態指標値により設定されている(LOD仕様書より細かいレベルが設定されている)。例えば、LOD200と300の間には、LOD225、250、275の具体化度合が設定されている。 As shown in FIG. 3a, the materialization degree data 12a stores the materialization degree indicating the degree of progress of the parts, and as described above, the materialization degree is set by the state index value (LOD specification). A finer level than the book is set). For example, between LOD200 and 300, the degree of reification of LOD225, 250, and 275 is set.

目標値データ12bには、図3bに示すように、部位分類(外壁、外部ドア等)と、基底値(進捗管理の基準値であり本実施形態ではLOD仕様書に基づき100)と、目標値とが設定されている。 As shown in FIG. 3b, the target value data 12b includes a site classification (outer wall, external door, etc.), a base value (a reference value for progress management, which is 100 based on the LOD specification in this embodiment), and a target value. And are set.

目標値は、状態指標値であって、プロジェクトのフェーズが完了する値として設定されている。図3bにおいては、フェーズ0~2に対して設定されており、例えば、外壁においては、状態指標値が225に達するとフェーズ1が完了する。 The target value is a state index value and is set as a value at which the phase of the project is completed. In FIG. 3b, it is set for phases 0 to 2. For example, on the outer wall, phase 1 is completed when the state index value reaches 225.

なお、本実施形態に係るフェーズとは、プロジェクトの進捗を段階的な工程に分割したうちの1つの工程のことである(例えば、プロジェクトの全行程を第1工程(フェーズ0)~第3工程(フェーズ2)の3つの工程に分割したうちの1つの工程のこと(例えば、第1工程(フェーズ0)のこと))。 The phase according to the present embodiment is one of the steps obtained by dividing the progress of the project into stepwise steps (for example, the entire process of the project is the first step (phase 0) to the third step. (Phase 2) One of the three steps (for example, the first step (Phase 0)).

また、プロジェクトやBIMモデルによって、管理対象となる部位分類が異なるので、図3bに示すように、状態管理の項を設けて、管理する、管理しないを選択できる方が好ましい。また、図3bに示すように、部位分類の重要度等による重み付けが設定できる方が好ましい。 Further, since the part classification to be managed differs depending on the project and the BIM model, it is preferable to provide a state management section and select whether to manage or not to manage, as shown in FIG. 3b. Further, as shown in FIG. 3b, it is preferable that the weighting can be set according to the importance of the site classification and the like.

パラメータデータ12cは、部品のあるパラメータが確定すれば(入力され適合条件を満たせば)そのパラメータの具体化(進展)の程度が状態指標値でいくつになるかを示したものである。パラメータデータ12cには、図3cに示すように、部位分類(外壁、外部ドア等)と、パラメータID(パラメータID毎の集計のために便宜上名付けたもの)と、上記した目標値と、該当するパラメータと、目標値を満足するためのパラメータ値の適合条件が設定されて保存されている。例えば、外壁の目標値225のパラメータは厚さであり、明示の有無が適合条件なので、外壁に厚さが入力されていれば外壁のパラメータである厚さは目標値225に達していることとなる。 The parameter data 12c indicates how much the degree of materialization (progress) of a certain parameter of a component is determined by the state index value (if it is input and the conforming condition is satisfied). As shown in FIG. 3c, the parameter data 12c corresponds to the site classification (outer wall, external door, etc.), the parameter ID (named for convenience for aggregation for each parameter ID), and the above-mentioned target value. The parameters and the conditions for conforming the parameter values to satisfy the target values are set and saved. For example, the parameter of the target value 225 of the outer wall is the thickness, and the presence or absence of the specification is a conforming condition, so if the thickness is input to the outer wall, the thickness which is the parameter of the outer wall has reached the target value 225. Become.

状態記憶部13には、現在のBIMモデル2aの進展程度に関する情報が保存されている。図4は、状態記憶部13に記憶される情報の一例であって、図4aは、構成要素状態データ13aの一例であり、図4bは、パラメータ入力状態データ13bの一例である。 The state storage unit 13 stores information regarding the degree of progress of the current BIM model 2a. FIG. 4 is an example of information stored in the state storage unit 13, FIG. 4a is an example of component state data 13a, and FIG. 4b is an example of parameter input state data 13b.

構成要素状態データ13aには、図4aに示すように、要素Id(部品が固有に有するId)、要素名、部位分類、状態分類、進展度指数、入力者、及び入力日時が保存されている。ここで、進展度指数とは、部品の具体化度合と、かかる具体化度合の承認段階が反映された状態指標値であり、部品の管理(進捗確認)の際に参考とする数値である(図7d参照。詳しくは後述する)。例えば、図4aにおいて、壁1の位置状態の進捗確認の際には、進展度指数が230であることを確認する。 As shown in FIG. 4a, the component state data 13a stores the element Id (Id uniquely possessed by the component), the element name, the part classification, the state classification, the progress index, the input person, and the input date and time. .. Here, the progress index is a state index value that reflects the degree of concreteness of the part and the approval stage of the degree of concreteness, and is a numerical value to be referred to when managing the part (progress confirmation). See FIG. 7d. Details will be described later). For example, in FIG. 4a, when confirming the progress of the position state of the wall 1, it is confirmed that the progress index is 230.

パラメータ入力状態データ13bには、図4bに示すように、要素Id、部位分類、パラメータID、目標値、及び適合状態が保存されている。ここで、適合状態とは、パラメータデータ12c(図3c参照)に示したパラメータが上記した適合条件を満たしているか否かを表しており、適合していれば、かかるパラメータは目標値まで進展していることとなる。例えば、図4bにおいては、外壁の目標値225のパラメータ外壁属性2が3つとも “適合”なので、このパラメータは目標値225まで進展していることとなる(外部ドアの目標値225のパラメータ外部ドア属性3のように3つのうち1つが“適合”の場合については後述する)。 As shown in FIG. 4b, the parameter input state data 13b stores the element Id, the part classification, the parameter ID, the target value, and the conforming state. Here, the conforming state indicates whether or not the parameter shown in the parameter data 12c (see FIG. 3c) satisfies the above-mentioned conforming condition, and if conforming, the parameter progresses to the target value. It will be. For example, in FIG. 4b, since all three parameter outer wall attributes 2 of the target value 225 of the outer wall are “fit”, this parameter has progressed to the target value 225 (outside the parameter of the target value 225 of the outer door). The case where one of the three is "conforming" as in the door attribute 3 will be described later).

表示部30は、状態処理部20で算出された結果等が表示される部分であり、例えば、利用者がBIMモデル2aの進捗率を確認する部分である。表示部30としては、例えば、コンピュータのディスプレイ等を用いることができる。 The display unit 30 is a part where the result calculated by the state processing unit 20 is displayed, and is, for example, a part where the user confirms the progress rate of the BIM model 2a. As the display unit 30, for example, a computer display or the like can be used.

<<<管理システム1を用いた管理方法について>>>
次に、管理システム1を用いた管理方法(進捗等を確認する方法)の一例を説明する。先ずは、BIMモデル2aを管理するための登録情報を管理システム1の記憶部10に事前登録する(事前登録受け付けステップに相当)。図5は、登録情報の事前登録手順の一例を示したフローチャートである。
<<< Management method using management system 1 >>>
Next, an example of a management method (method for confirming progress, etc.) using the management system 1 will be described. First, the registration information for managing the BIM model 2a is pre-registered in the storage unit 10 of the management system 1 (corresponding to the pre-registration acceptance step). FIG. 5 is a flowchart showing an example of the procedure for pre-registering registration information.

<登録情報の事前登録について>
以下、登録情報の事前登録について手順の一例を説明する。先ず、図2aに示した部位分類データ11aを登録する(ステップS1)。なお、部位分類データ11aの情報は、BIMソフト2が予め有している情報に限るものではなく、BIMモデル2aの進捗を管理するために必要に応じて自由に設定してもよい。
<Pre-registration of registration information>
Hereinafter, an example of the procedure for pre-registering registration information will be described. First, the site classification data 11a shown in FIG. 2a is registered (step S1). The information of the part classification data 11a is not limited to the information that the BIM software 2 has in advance, and may be freely set as necessary for managing the progress of the BIM model 2a.

次に、図2bに示した部位分類基準データ11bを登録する(ステップS2)。なお、部位分類基準データ11bの情報は、BIMソフト2が予め有している情報に限るものではなく、必要に応じて分類に使用するための部位分類基準を追加等してもよい。 Next, the site classification reference data 11b shown in FIG. 2b is registered (step S2). The information of the site classification standard data 11b is not limited to the information that the BIM software 2 has in advance, and a site classification standard for use in classification may be added as needed.

また、部位分類に分類する際に使用する項目(基準値)の数も自由に設定してよい。つまり、図2bに示す2つに限るものではなく、例えば、カテゴリの基準値のみの1つであってもよいし、3つ以上であってもよい。 In addition, the number of items (reference values) used when classifying into the site classification may be freely set. That is, it is not limited to the two shown in FIG. 2b, and may be, for example, only one of the reference values of the category, or may be three or more.

次に、図3aに示した具体化度合データ12aを登録する(ステップS3)。本実施形態においては、状態指標値を用いて図3aで示した具体化度合データ12aを設定し、具体化度合データ12aと、位置状態の具体化度合選択肢及び属性状態の具体化度合選択肢と、を関連付けて設定する(図7b及び図7c参照。詳しくは後述する)。 Next, the reification degree data 12a shown in FIG. 3a is registered (step S3). In the present embodiment, the materialization degree data 12a shown in FIG. 3a is set using the state index value, and the materialization degree data 12a, the materialization degree option of the position state, and the materialization degree option of the attribute state are used. (See FIGS. 7b and 7c. Details will be described later).

次に、図3bに示した目標値データ12bを登録する(ステップS4)。建設物のプロジェクトでは、企画から設計、施工と長期間に及ぶ場合が多いので、上述したように、プロジェクトの進展度をフェーズとして段階的に分割するのが一般的であり、フェーズ毎に目標値を定めることが一般的である(目標値を設定(フェーズ分け)しなくても構わないが、目標値を設定(フェーズ分け)するのが一般的である)。 Next, the target value data 12b shown in FIG. 3b is registered (step S4). In a building project, it often takes a long time from planning to design and construction, so as mentioned above, it is common to divide the progress of the project into phases, and the target value for each phase. (It is not necessary to set the target value (phase division), but it is common to set the target value (phase division)).

つまり、本実施形態においては、プロジェクトを部位分類毎にフェーズ分けして、状態指標値を用いて基底値とフェーズ毎の目標値を設定する。換言すれば、管理システム1を用いた管理方法は、複数のフェーズ毎に設定される目標値の事前登録をコンピュータが受け付ける事前登録受け付けステップを有する。この事前登録受け付けステップにおいては、例えば、外壁のフェーズ1の目標値は225と設定する。 That is, in the present embodiment, the project is divided into phases for each part classification, and the base value and the target value for each phase are set using the state index value. In other words, the management method using the management system 1 has a pre-registration acceptance step in which the computer accepts the pre-registration of the target value set for each of a plurality of phases. In this pre-registration acceptance step, for example, the target value of Phase 1 of the outer wall is set to 225.

次に、図3cに示したパラメータデータ12cを登録する(ステップS5)。本実施形態においては、プロジェクトが部位分類毎に複数のフェーズに分けられているので、部位分類の入力されるべきパラメータ毎に目標値とかかる目標値を満足するための適合条件を設定する。 Next, the parameter data 12c shown in FIG. 3c is registered (step S5). In the present embodiment, since the project is divided into a plurality of phases for each part classification, a target value and a conforming condition for satisfying the target value are set for each parameter to be input in the part classification.

換言すれば、管理システム1を用いた管理方法は、BIMモデル2aに対応したプロジェクトの複数のフェーズ毎に、かつ、BIMモデル2aの部位分類毎に設定される目標値であって、目標値の各々に部位分類のパラメータが関連付けられている目標値の事前登録をコンピュータが受け付ける事前登録受け付けステップを有する。この事前登録受け付けステップにおいては、例えば、外壁の入力されるべきパラメータが厚さの場合、目標値225を満足するための適合条件は明示の有無と設定する。 In other words, the management method using the management system 1 is a target value set for each of a plurality of phases of the project corresponding to the BIM model 2a and for each part classification of the BIM model 2a, and is a target value. Each has a pre-registration acceptance step in which the computer accepts pre-registration of the target value associated with the site classification parameter. In this pre-registration acceptance step, for example, when the parameter to be input to the outer wall is the thickness, the conformity condition for satisfying the target value 225 is set to be explicit or not.

なお、パラメータは、部品のパラメータ(部品そのものが持つ属性情報。例えば、建具の塗装色)であっても良いし、共通属性のパラメータ(例えば、建具の素材)であってもよい。また、BIMソフト2が予め有しているパラメータに限るものではなく、必要に応じて追加してもよい。 The parameter may be a parameter of the part (attribute information possessed by the part itself, for example, the paint color of the fitting), or may be a parameter of a common attribute (for example, the material of the fitting). Further, the parameters are not limited to the parameters that the BIM software 2 has in advance, and may be added as needed.

<進展度指数の算出について>
次に、上記にも記載した、部品の具体化度合と、かかる具体化度合の承認段階が反映された状態指標値であって、部品の管理(進捗確認)の際に参考とする数値である進展度指数の算出の一例について図を用いて説明する。なお、具体化度合のレベルが進んでいるほど、また、承認までの段階が進んでいるほど進展度指数は高くなるように算出される。
<Calculation of progress index>
Next, it is a state index value that reflects the degree of concreteness of the part and the approval stage of the degree of concreteness described above, and is a numerical value to be referred to when managing the part (progress confirmation). An example of calculating the progress index will be described with reference to a figure. It should be noted that the progress index is calculated to be higher as the level of the degree of reification progresses and as the stage until approval progresses.

図6は、進展度指数の算出及び進展度指数を用いたBIMモデル2aの進捗率算出のフローチャートの一例である。図7は、進展度指数の算出に係るデータの一例を示しており、図7aは部品と進展度指数が関連付けられた状態を示すデータの一例であり、図7bは位置状態の具体化度合選択肢と具体化度合を示したデータの一例であり、図7cは属性状態の具体化度合選択肢と具体化度合を示したデータの一例であり、図7dは属性状態の進展度指数を示したデータの一例である。 FIG. 6 is an example of a flowchart for calculating the progress index and calculating the progress rate of the BIM model 2a using the progress index. FIG. 7 shows an example of data related to the calculation of the progress index, FIG. 7a is an example of data showing a state in which the component and the progress index are associated, and FIG. 7b shows a concreteness option of the position state. 7c is an example of the data showing the degree of concreteness and the choice of the degree of concreteness of the attribute state, and FIG. 7d is the example of the data showing the degree of progress index of the attribute state. This is just one example.

本実施形態に係る進展度指数の算出は、以下のように行われる。先ず、図7b及び図7cに示す、具体化度合がレベル別に示された具体化度合選択肢を選択することにより、具体化度合が決定される。例えば、部品の属性状態の具体化度合選択肢として「基本的な分類の確定。」を選択すれば、この部品の具体化度合は230となる。なお、具体化度合を選択し、対応する具体化度合選択肢を表示させて具体化度合選択肢を選択してもよい。つまり、選択肢として具体化度合である「230」を選択して、対応する具体化度合選択肢である「基本的な分類の確定。」を提示させ、かかる具体化度合選択肢で問題ないことを確認してもよい(かかる具体化度合選択肢を選択してもよい)。 The progress index according to this embodiment is calculated as follows. First, the degree of materialization is determined by selecting the degree of materialization option shown in FIGS. 7b and 7c in which the degree of materialization is indicated for each level. For example, if "determination of basic classification" is selected as the materialization degree option of the attribute state of the part, the materialization degree of this part is 230. It should be noted that the degree of materialization may be selected, the corresponding degree of materialization option may be displayed, and the degree of materialization option may be selected. In other words, select "230", which is the degree of concreteness, as an option, and have them present "determination of basic classification", which is the corresponding degree of concreteness option, and confirm that there is no problem with such specificity degree option. You may (you may select such a degree of reification option).

次に、図7dに示す、具体化度合の承認までの段階が段階別に示された承認段階選択肢を選択することにより、進展度指数が決定される。例えば、部品の属性状態の具体化度合選択肢として「基本的な分類の確定。」を選択し、承認段階選択肢として「設計者作業済」を選択すれば、この部品の進展度指数は210となる。そして、かかる進展度指数は、図7aに示すように、部品毎に関連付けられて保存される。 Next, the progress index is determined by selecting the approval stage option showing the stage up to the approval of the degree of reification shown in FIG. 7d for each stage. For example, if "determine basic classification" is selected as the concreteness option of the attribute state of the part and "designer work completed" is selected as the approval stage option, the progress index of this part is 210. .. Then, as shown in FIG. 7a, the progress index is associated and stored for each component.

つまり、管理システム1を用いた管理方法は、BIMモデル2aの部品の具体化度合がレベル別に複数表された具体化度合選択肢と、具体化度合の承認までの段階が段階別に複数表された承認段階選択肢と、をコンピュータが提示する選択肢提示ステップ(ステップS10)と、提示された具体化度合選択肢及び承認段階選択肢の中からの選択をコンピュータが受け付ける選択受付ステップ(ステップS11)と、選択された具体化度合及び承認段階に基づいて、部品がどの程度決定されているかを示す進展度指数をコンピュータが算出する進展度指数算出ステップ(ステップS12)と、算出された進展度指数をコンピュータが部品に関連付ける関連付けステップ(ステップS13)と、を有している。 That is, in the management method using the management system 1, a plurality of concreteness degree options in which the degree of concreteness of the parts of the BIM model 2a is expressed by level and approval in which multiple stages up to the approval of the degree of concreteness are expressed are expressed in stages. The stage option was selected as an option presentation step (step S10) in which the computer presents, and a selection acceptance step (step S11) in which the computer accepts a selection from the presented reification degree options and approval stage options. The progress index calculation step (step S12) in which the computer calculates the progress index indicating how much the part is determined based on the degree of reification and the approval stage, and the computer uses the calculated progress index for the part. It has an association step (step S13) and an association.

なお、図7dにおいては、承認段階選択肢として作業済又は承認を記載しているが、これに限るものではなく、例えば、「確認者が考え中である」「承認者がNGと考えている」など入力者の細かい意思等を値として反映させてもよい。 In addition, in FIG. 7d, work completed or approval is described as an approval stage option, but the present invention is not limited to this, and for example, "the confirmer is thinking" and "the approver thinks NG". The detailed intention of the input person may be reflected as a value.

また、上記した具体化度合選択肢及び承認段階選択肢の選択は、入力者にこれらの選択肢を提示していずれかを選択させることにより行われる。承認段階は具体化度合毎に選択されることで進展度指数が確定するため、入力者は具体化度合の選択と承認段階の選択を同時に行う。これにより、例えば具体化度合「230」の承認段階が「承認済み」という状態を示すことができる。図7dは具体化度合と承認段階を合わせた表であり、各々が独立した入力によって進展度指数を確定しても良い。ここで入力者とは、オペレータ、設計者、確認者、および承認者等となる。 Further, the selection of the specificity degree option and the approval stage option described above is performed by presenting these options to the input person and having the input person select one of them. Since the progress index is determined by selecting the approval stage for each degree of materialization, the input person selects the degree of materialization and the approval stage at the same time. Thereby, for example, it is possible to indicate that the approval stage of the degree of concreteness “230” is “approved”. FIG. 7d is a table showing the degree of reification and the approval stage, and the degree of progress index may be determined by each input independently. Here, the input person is an operator, a designer, a confirmer, an approver, and the like.

また、図7aに示す位置状態及び属性状態の入力者及び入力日時の項目は無くても構わないが、進展度指数の情報元や入力日時が明確となるので(進展度指数の正確性がより高くなるので)、入力者と入力日時の項を設ける方が好ましい。 Further, although the input person and the input date and time items of the position state and the attribute state shown in FIG. 7a may not be provided, the information source of the progress index and the input date and time are clarified (the accuracy of the progress index is higher). (Because it will be expensive), it is preferable to provide a section for the input person and the input date and time.

また、部品毎に関連付けられた進展度指数は記憶部10に保存されるが、保存される際には図4aに示したように構成要素状態データ13aとして保存される。つまり、進展度指数は、部位分類等の他のデータと関連付けられて保存される。 Further, the progress index associated with each component is stored in the storage unit 10, but when stored, it is stored as component state data 13a as shown in FIG. 4a. That is, the progress index is stored in association with other data such as site classification.

そして、上記した進展度指数に関連付けられた部品を部位分類に分類する処理等は、進展度指数を保存する段階(ステップS13)で行われてもよいし、例えば、後述する部位分類進展度指数の算出を行う段階(ステップS14)で部位分類基準データ11bと照合する事で行われてもよい。 Then, the process of classifying the parts associated with the progress index into the site classification may be performed at the stage of storing the progress index (step S13), and for example, the site classification progress index described later may be performed. It may be performed by collating with the site classification reference data 11b at the stage of performing the calculation (step S14).

(進展度指数を用いたBIMモデル2aの進捗率の算出について)
進展度指数を算出したら、次に、進展度指数を用いたBIMモデル2aの進捗率を算出する。本実施形態においては、進展度指数から部位分類進展度指数を算出し、部位分類進展度指数からフェーズ毎の進展度合を示す進展率(以下、フェーズ進展率ともいう)を算出し、フェーズ進展率からBIMモデル2aの進捗率を算出する。
(About calculation of progress rate of BIM model 2a using progress index)
After calculating the progress index, next, the progress rate of the BIM model 2a using the progress index is calculated. In the present embodiment, the site classification progress index is calculated from the progress index, and the progress rate indicating the progress of each phase (hereinafter, also referred to as the phase progress rate) is calculated from the site classification progress index, and the phase progress rate is calculated. The progress rate of the BIM model 2a is calculated from.

先ずは、部品に関連付けられた進展度指数を部位分類毎に平均化し、部位分類毎の部位分類進展度指数を算出する(ステップS14)。図8は、部位分類進展度指数の算出結果の一例である。図8に示すように、部位分類進展度指数は、部位分類、状態分類、及び目標値毎に算出されており、例えば、部位分類を外壁、状態分類を位置状態、目標値を225とした場合、算出される部位分類進展度指数は223であることを示している。 First, the progress index associated with the parts is averaged for each site classification, and the site classification progress index for each site classification is calculated (step S14). FIG. 8 is an example of the calculation result of the site classification progress index. As shown in FIG. 8, the site classification progress index is calculated for each site classification, state classification, and target value. For example, when the site classification is the outer wall, the state classification is the position state, and the target value is 225. , The calculated site classification progress index is 223.

つまり、管理システム1を用いた管理方法は、部品は複数種類の部位分類のいずれかに属しており、共通の部位分類に属する部品に関連付けられた進展度指数を平均化して、部位分類毎の部位分類進展度指数をコンピュータが算出する部位分類進展度指数算出ステップを有する。 That is, in the management method using the management system 1, the parts belong to one of a plurality of types of part classifications, and the progress index associated with the parts belonging to the common part classifications is averaged for each part classification. It has a part classification progress index calculation step in which a computer calculates the part classification progress index.

ここで、部位分類進展度指数は、BIMモデル2aに対応したプロジェクトの複数のフェーズ毎(目標値毎)に算出される。つまり、部位分類進展度指数の算出の際に、部品の進展度指数が算出するフェーズの目標値よりも大きい場合、例えば、BIMモデル2aの部品の中で部品1のみが大きく進展しており、部品1の進展度指数が240、算出するフェーズの目標値が225の場合、部品1の進展度指数を225として部位分類進展度指数を算出する必要がある。そうすると、部品1による部位分類進展度指数の過度な引き上げを抑制することができ、部位分類進展度指数が示す進展程度の正確性を向上させることができる。 Here, the site classification progress index is calculated for each of a plurality of phases (for each target value) of the project corresponding to the BIM model 2a. That is, when the part classification progress index is calculated, if the progress index of the part is larger than the target value of the calculated phase, for example, only the part 1 is greatly progressed among the parts of the BIM model 2a. When the progress index of the component 1 is 240 and the target value of the phase to be calculated is 225, it is necessary to calculate the site classification progress index with the progress index of the component 1 as 225. Then, it is possible to suppress an excessive increase in the site classification progress index by the component 1, and it is possible to improve the accuracy of the degree of progress indicated by the site classification progress index.

そのため、本実施形態における「平均化」には、ただ単に数値の平均を算出するだけではなく、上記のように上限値を設けて算出した平均等が含まれている(後述する重み付けして算出した平均も含まれる)。 Therefore, the "averaging" in the present embodiment includes not only the averaging of numerical values but also the averaging calculated by setting an upper limit value as described above (calculated by weighting described later). Includes the average).

次に、部位分類進展度指数からフェーズ進展率を算出する(ステップS15)。フェーズ進展率とは、フェーズにおける部位分類進展度指数の進展率(最大1.0)である。具体的には、例えば、図8に示す1行目(外壁、位置状態)は、部位分類進展度指数が223、目標値が225であり、この(現フェーズの)目標値225の前(下位)フェーズの目標値が200の場合(例えば現フェーズがフェーズ1で目標値が225であり、前フェーズのフェーズ0の目標値が200の場合)、以下の式からフェーズ進展率を求めることができる。 Next, the phase progress rate is calculated from the site classification progress index (step S15). The phase progress rate is the progress rate (maximum 1.0) of the site classification progress index in the phase. Specifically, for example, in the first row (outer wall, position state) shown in FIG. 8, the site classification progress index is 223 and the target value is 225, which is before (lower) the target value 225 (in the current phase). ) When the target value of the phase is 200 (for example, when the current phase is phase 1, the target value is 225, and the target value of phase 0 of the previous phase is 200), the phase progress rate can be calculated from the following formula. ..

(部位分類進展度指数-前フェーズの目標値)/(現フェーズの目標値-前フェーズの目標値)=(223-200)/(225-200)=0.92
つまり、管理システム1を用いた管理方法は、現フェーズ及び現フェーズの一つ前の前フェーズに対応する目標値と、現フェーズに対応する部位分類進展度指数とに基づいて、現フェーズまでの進展度合を示すフェーズ進展率をコンピュータが算出する進展率算出ステップを有する。
(Part classification progress index-target value of previous phase) / (target value of current phase-target value of previous phase) = (223-200) / (225-200) = 0.92
That is, the management method using the management system 1 is based on the target value corresponding to the current phase and the previous phase immediately before the current phase, and the site classification progress index corresponding to the current phase, up to the current phase. It has a progress rate calculation step in which a computer calculates a phase progress rate indicating the degree of progress.

図9は、フェーズ進展率の算出結果の一例であり、図9aはフェーズ1におけるフェーズ進展率の一覧を示しており、図9bはフェーズ1におけるフェーズ進展率のグラフを示している。このように、フェーズ進展率を算出して、フェーズ進展率一覧、フェーズ進展率グラフ等でフェーズ進展率を確認すると、同じフェーズに部位分類毎で異なる目標値が設定されていても(外壁のフェーズ1の目標値が225、外部ドアのフェーズ1の目標値が250と設定されていても)、部位分類毎のフェーズ進展率を一目で比較して確認することができる。 FIG. 9 is an example of the calculation result of the phase progress rate, FIG. 9a shows a list of the phase progress rate in the phase 1, and FIG. 9b shows a graph of the phase progress rate in the phase 1. In this way, when the phase progress rate is calculated and the phase progress rate is confirmed in the phase progress rate list, phase progress rate graph, etc., even if different target values are set for each part classification in the same phase (phase of the outer wall). Even if the target value of 1 is set to 225 and the target value of phase 1 of the external door is set to 250), the phase progress rate for each part classification can be compared and confirmed at a glance.

次に、フェーズ進展率からBIMモデル2aの進捗率(フェーズ毎の進捗率)を算出する(ステップS16)。具体的には、同じフェーズにおける部位分類毎のフェーズ進展率を平均化してBIMモデル2aの進捗率を算出する。図9aに示すフェーズ進展率からBIMモデル2aの進捗率を算出すると以下のようになる(図9aに示すBIMモデル2aのフェーズ1における進捗率は以下のようになる)。 Next, the progress rate (progress rate for each phase) of the BIM model 2a is calculated from the phase progress rate (step S16). Specifically, the progress rate of the BIM model 2a is calculated by averaging the phase progress rates for each part classification in the same phase. The progress rate of the BIM model 2a is calculated from the phase progress rate shown in FIG. 9a as follows (the progress rate of the BIM model 2a shown in FIG. 9a in phase 1 is as follows).

(0.92+0.72+0.58+0.97+0.75+0.88+0.82+0.91)/8=0.82
つまり、管理システム1を用いた管理方法は、フェーズ進展率は、部位分類毎に算出され、部位分類毎のフェーズ進展率を平均化してBIMモデル2aの進捗率をコンピュータが算出するBIMモデル進捗率算出ステップを有する。なお、上式のように部位分類のフェーズ進展率を同じように扱っても構わないが、図9aの右端の列に示すように、部位分類毎に重み付けの項目を設定して部位分類毎の重要度等を反映させてもよい。
(0.92 + 0.72 + 0.58 + 0.97 + 0.75 + 0.88 + 0.82 + 0.91) / 8 = 0.82
That is, in the management method using the management system 1, the phase progress rate is calculated for each part classification, the phase progress rate for each part classification is averaged, and the progress rate of the BIM model 2a is calculated by the computer. It has a calculation step. It should be noted that the phase progress rate of the site classification may be treated in the same manner as in the above equation, but as shown in the rightmost column of FIG. 9a, a weighting item is set for each site classification and each site classification is set. The importance may be reflected.

<パラメータ入力状態の抽出による進捗率の算出について>
次に、パラメータ入力状態の抽出(パラメータ確定有無の抽出)によるBIMモデル2aの進捗率の算出の一例について図を用いて説明する。図10は、パラメータ入力状態の抽出からBIMモデル2aの進捗率の算出までのフローチャートの一例である。
<Calculation of progress rate by extracting parameter input state>
Next, an example of calculating the progress rate of the BIM model 2a by extracting the parameter input state (extracting whether or not the parameter is confirmed) will be described with reference to the figure. FIG. 10 is an example of a flowchart from the extraction of the parameter input state to the calculation of the progress rate of the BIM model 2a.

先ずは、BIMモデル2aよりパラメータ(パラメータデータ12cで設定されたパラメータ)のパラメータデータ12cで設定した適合条件に対する適否を抽出する(ステップS20)。 First, the suitability for the conformity condition set in the parameter data 12c of the parameter (parameter set in the parameter data 12c) is extracted from the BIM model 2a (step S20).

つまり、パラメータへの数値、文字等が確定されているか(正しい入力か)どうかを抽出する。すなわち、管理システム1を用いた管理方法は、パラメータの確定有無についての情報をコンピュータが抽出する情報抽出ステップを有する。かかる抽出は、定期的に自動でなされてもよいし、パラメータ入力状態の抽出による進捗を確認する際に行われてもよい。 That is, it is extracted whether or not the numerical values and characters for the parameters are fixed (correct input). That is, the management method using the management system 1 has an information extraction step in which the computer extracts information about whether or not the parameter is fixed. Such extraction may be performed automatically on a regular basis, or may be performed when confirming the progress of the extraction of the parameter input state.

次に、抽出されたデータからパラメータ入力状態データ13bを作成して保存する(ステップS21)。パラメータ入力状態データ13bとは、図4bに示したデータである。 Next, the parameter input state data 13b is created from the extracted data and saved (step S21). The parameter input state data 13b is the data shown in FIG. 4b.

次に、条件に適合するパラメータの割合を算出して、フェーズ進展率を算出する(ステップS22)。ここでは、上記した進展度指数を用いたフェーズ進展率の算出方法とは異なる方法でフェーズ進展率を算出する。 Next, the ratio of the parameters that meet the conditions is calculated, and the phase progress rate is calculated (step S22). Here, the phase progress rate is calculated by a method different from the method for calculating the phase progress rate using the progress index described above.

具体的には、パラメータのうち、条件に適合する数と、抽出対象となるパラメータ数から、条件に適合する割合を算出して、前フェーズの目標値に加算する加算値を算出し、前フェーズの目標値に加算値を加算した累積値(進展度指数を用いたフェーズ進展率の算出の際の部位分類進展度指数に相当)を算出して、フェーズ進展率を算出する。 Specifically, among the parameters, the ratio that meets the conditions is calculated from the number of parameters that meet the conditions and the number of parameters that are to be extracted, and the addition value to be added to the target value of the previous phase is calculated. The phase progress rate is calculated by calculating the cumulative value (corresponding to the site classification progress index when calculating the phase progress rate using the progress index) by adding the added value to the target value of.

つまり、管理システム1を用いた管理方法は、現フェーズ及び現フェーズの一つ前の前フェーズに対応する目標値と、パラメータについての情報抽出結果と、に基づいて、現フェーズまでの進展度合を示すフェーズ進展率をコンピュータが部位分類毎に算出する進展率算出ステップを有する。 That is, in the management method using the management system 1, the degree of progress up to the current phase is determined based on the target values corresponding to the current phase and the previous phase immediately before the current phase, and the information extraction result regarding the parameters. It has a progress rate calculation step in which a computer calculates the indicated phase progress rate for each part classification.

図11は、パラメータ入力状態の抽出結果から条件に適合するパラメータの割合、加算値、及び累積値の算出結果の一例であり、図11aは条件に適合するパラメータの割合の算出結果の一例であり、図11bは、加算値と累積値の算出結果の一例である。 FIG. 11 is an example of the calculation result of the parameter ratio, the addition value, and the cumulative value that meet the conditions from the extraction result of the parameter input state, and FIG. 11a is an example of the calculation result of the parameter ratio that meets the conditions. , FIG. 11b is an example of the calculation result of the added value and the cumulative value.

図11aに示すように、抽出対象となるパラメータ数は、部位分類、目標値によって異なるため、部位分類、目標値毎に入力のあるパラメータの割合を算出する。具体的には、例えば、外壁の目標値225においては、抽出対象となるパラメータ数は168であり、条件に適合するパラメータ数は165であるので、条件に適合するパラメータの割合は、165/168=0.98となる。そして、この条件に適合するパラメータの割合は、前(下位)フェーズの目標値からの加算割合(増加割合)とみなすことができる。 As shown in FIG. 11a, since the number of parameters to be extracted differs depending on the part classification and the target value, the ratio of the input parameter is calculated for each part classification and the target value. Specifically, for example, at the target value 225 of the outer wall, the number of parameters to be extracted is 168, and the number of parameters that meet the conditions is 165. Therefore, the ratio of the parameters that meet the conditions is 165/168. = 0.98. Then, the ratio of the parameters that meet this condition can be regarded as the addition ratio (increase ratio) from the target value in the previous (lower) phase.

つまり、現フェーズの目標値と前フェーズの目標値の差に加算割合を掛けることで加算値を算出することができる。図11bに示すように、例えば、外壁の現フェーズの目標値が225においては、前フェーズの目標値が200となり、条件に適合するパラメータの割合が0.98なので(図11a参照)、(225-220)×0.98=24が加算値となる。 That is, the addition value can be calculated by multiplying the difference between the target value of the current phase and the target value of the previous phase by the addition ratio. As shown in FIG. 11b, for example, when the target value of the current phase of the outer wall is 225, the target value of the previous phase is 200, and the ratio of the parameters that meet the conditions is 0.98 (see FIG. 11a), so (225). -220) × 0.98 = 24 is the added value.

そして、前フェーズの累積値(図11bにおいては、現フェーズの1つ上の行の累積値)に加算値を加えることで累積値を算出することができる。図11bに示すように、例えば、外壁の目標値が225においては、前フェーズの目標値が200となり、前フェーズの累積値が200なので、200+24=224が累積値となる。 Then, the cumulative value can be calculated by adding the added value to the cumulative value of the previous phase (in FIG. 11b, the cumulative value of the row immediately above the current phase). As shown in FIG. 11b, for example, when the target value of the outer wall is 225, the target value of the previous phase is 200 and the cumulative value of the previous phase is 200, so 200 + 24 = 224 is the cumulative value.

そうすると、現フェーズの目標値、前フェーズの目標値、及び累積値からフェーズ進展率を以下の式から算出することができる。 Then, the phase progress rate can be calculated from the following formula from the target value of the current phase, the target value of the previous phase, and the cumulative value.

(累積値-前フェーズの目標値)/(現フェーズの目標値-前フェーズの目標値)=(224-200)/(225-200)=0.96
そうしたら、パラメータ入力進捗率からBIMモデル2aの進捗率(フェーズ毎の進捗率)を算出する(ステップS23)。なお、かかる算出方法は、ステップS16と同様の算出方法であるのでここでは説明を省略する。
(Cumulative value-Target value of previous phase) / (Target value of current phase-Target value of previous phase) = (224-200) / (225-200) = 0.96
Then, the progress rate (progress rate for each phase) of the BIM model 2a is calculated from the parameter input progress rate (step S23). Since the calculation method is the same as that in step S16, the description thereof is omitted here.

<BIMモデル2aの進捗率の算出について>
上述したように、同じ部位分類(例えば、外壁)のフェーズ進展率として、位置状態及び属性状態の進展度指数を用いたフェーズ進展率と、パラメータ入力状態の情報抽出結果を用いたフェーズ進展率と、を算出することができる。そして、算出されたフェーズ進展率からそれぞれBIMモデル2aの進捗率を算出することができるが、これらのフェーズ進展率をまとめてから、BIMモデル2aの進捗率を算出することもできる。
<Calculation of progress rate of BIM model 2a>
As described above, as the phase progress rate of the same site classification (for example, outer wall), the phase progress rate using the progress index of the position state and the attribute state, and the phase progress rate using the information extraction result of the parameter input state. , Can be calculated. Then, the progress rate of the BIM model 2a can be calculated from each of the calculated phase progress rates, but the progress rate of the BIM model 2a can also be calculated after summarizing these phase progress rates.

図12は、フェーズ進展率の算出結果の一例であり、図12aは、外壁におけるフェーズ進展率の算出元別のフェーズ進展率の一覧を示した図であり、図12bは、算出元別のフェーズ進展率をまとめて部位分類のフェーズ進展率とし、部位分類毎のフェーズ進展率を示した図である。 FIG. 12 is an example of the calculation result of the phase progress rate, FIG. 12a is a diagram showing a list of the phase progress rates for each calculation source of the phase progress rate on the outer wall, and FIG. 12b is a diagram showing the phases for each calculation source. It is a figure which shows the phase progress rate for each part classification by collecting the progress rate into the phase progress rate of a part classification.

図12aに示すように、位置状態の進展度指数、属性状態の進展度指数、及びパラメータ入力状態データからそれぞれ外壁のフェーズ進展率を算出することができる。そうしたら、これらを平均化して外壁のフェーズ進展率とする。図12aにおいては、(0.92+0.88+0.93)/3=0.91となる。ここで、図12aに記載はないが、重み付けして平均化してもよい。 As shown in FIG. 12a, the phase progress rate of the outer wall can be calculated from the progress index of the position state, the progress index of the attribute state, and the parameter input state data. Then, these are averaged to obtain the phase progress rate of the outer wall. In FIG. 12a, (0.92 + 0.88 + 0.93) / 3 = 0.91. Here, although not shown in FIG. 12a, they may be weighted and averaged.

そして、図12bに示すように、このフェーズ進展率の算出を外壁以外の部位分類(外部ドア、外部窓等)に対して行い、算出結果をそれぞれの部位分類のフェーズ進展率とする。そして、かかるフェーズ進展率からステップS16、S23と同様の算出方法でBIMモデル2aの進捗率を算出する。ここでも、図12bの右端の列に記載のように重み付けをしてBIMモデル2aの進捗率を算出してもよい。 Then, as shown in FIG. 12b, the calculation of this phase progress rate is performed for the part classification (external door, external window, etc.) other than the outer wall, and the calculation result is used as the phase progress rate of each part classification. Then, the progress rate of the BIM model 2a is calculated from the phase progress rate by the same calculation method as in steps S16 and S23. Here, too, the progress rate of the BIM model 2a may be calculated by weighting as described in the rightmost column of FIG. 12b.

<GUIについて>
本実施形態においては、上述した管理システム1を用いた管理方法が、コンピュータ上のプログラムを起動させて表示部30に映し出されたGUI(グラフィックユーザーインターフェース)を経由して行われる。つまり、例えば、コンピュータ上の入力用プログラムを起動させると、表示部30には入力者に対して入力を促すGUIが表示され、入力者はGUIに入力することで上述した管理方法を実行する。
<About GUI>
In the present embodiment, the management method using the management system 1 described above is performed via the GUI (graphic user interface) displayed on the display unit 30 by activating the program on the computer. That is, for example, when an input program on a computer is started, a GUI for prompting an input person to input is displayed on the display unit 30, and the input person executes the above-mentioned management method by inputting to the GUI.

以下、GUIの一例として、具体化度合選択肢及び承認段階選択肢を表示したGUIと、上記したBIMモデル2aの進捗率とは異なるBIMモデル2aの達成率(部位分類毎のある状態指標値(図14では簡易的にLODと記載)に対する達成率であり、図14においては、例えば、外壁の状態指標値230に対しては、82/100=82%の達成率)を表示したGUIについて図を用いて説明する。 Hereinafter, as an example of the GUI, the GUI displaying the reification degree option and the approval stage option and the achievement rate of the BIM model 2a different from the progress rate of the BIM model 2a described above (a certain state index value for each part classification (FIG. 14). In FIG. 14, the achievement rate is simply described as LOD), and in FIG. 14, for example, a figure is used for a GUI displaying 82/100 = 82% achievement rate for the state index value 230 of the outer wall. I will explain.

図13は、具体化度合選択肢及び承認段階選択肢を表示したGUIの一例であり、図13aと図13bはプルダウンによる選択を表示したGUIの一例であり、図13cは、承認段階選択肢に確認者の考えが反映されるGUIの一例である。 FIG. 13 is an example of a GUI displaying the reification degree option and the approval stage option, FIGS. 13a and 13b are examples of the GUI displaying the selection by pull-down, and FIG. 13c shows the approval stage option of the confirmer. This is an example of a GUI that reflects ideas.

図13aの場合、入力者は、プルダウンから具体化度合選択肢を選択し、プルダウンから承認段階選択肢を選択する。図13aの属性状態では、具体化度合選択肢として「基本的な分類を確定」、承認段階選択肢として「確認者考え中」が選択されている。このように入力者が選択することにより、「基本的な分類を確定」に対応する具体化度合と「確認者考え中」に対応する承認段階に基づいて進展度指数が算出され保存される。 In the case of FIG. 13a, the input person selects the reification degree option from the pull-down menu and the approval stage option from the pull-down menu. In the attribute state of FIG. 13a, "determine basic classification" is selected as the materialization degree option, and "confirmer thinking" is selected as the approval stage option. By selecting by the input person in this way, the progress index is calculated and stored based on the degree of concreteness corresponding to "determine the basic classification" and the approval stage corresponding to "under consideration of the confirmer".

図13bの場合、具体化度合をプルダウンから選択し、対応する具体化度合選択肢を表示させて具体化度合選択肢を選択する。図13bの属性状態では、具体化度合「230」が選択され、この具体化度合に対応する具体化度合選択肢「基本的な分類を確定」が表示されている。つまり、入力者が具体化度合を選択する事で対応する具体化度合選択肢「基本的な分類を確定」が提示され、これを入力者が問題ないことを確認する(具体化度合選択肢を選択する)。そして、承認段階選択肢としては「確認者考え中」が選択されているので、具体化度合「230」と「確認者考え中」に対応する承認段階に基づいて進展度指数が算出され保存される。 In the case of FIG. 13b, the degree of concreteness is selected from the pull-down menu, the corresponding degree of concreteness option is displayed, and the degree of concreteness option is selected. In the attribute state of FIG. 13b, the degree of concreteness “230” is selected, and the degree of concreteness option “determine basic classification” corresponding to the degree of concreteness is displayed. In other words, when the input person selects the degree of concreteness, the corresponding specific degree option "determine the basic classification" is presented, and it is confirmed that the input person has no problem (select the specific degree option). ). Since "confirmer thinking" is selected as the approval stage option, the progress index is calculated and saved based on the approval stage corresponding to the concreteness degree "230" and "confirmer thinking". ..

図13cの場合、入力者は、具体化度合選択肢は図13bと同様に選択するが、承認段階選択肢の選択は複数の確認者の考えが反映されるようになっており、かかる確認者の考えを承認者が考慮できる構成となっている。図13cの属性情報では、具体化度合「230」が選択され具体化度合選択肢として「基本的な分類を確定」が選択されており、承認段階選択肢として確認者に「Good」、「Bad」、「Neutral」の選択肢が提示され、かかる選択肢に対して確認者の考えは「Good」3人、「Bad」0人、「Neutral」2人となっている。そして、例えば、かかる状態においては、確認者の考えが全て揃っていないので、承認段階選択肢としては確認者考え中が選択される(このような承認段階選択肢の場合、確認者の確認済み人数、選択された選択肢の種類等により確認者考え中においても進展度指数を変えることができる。また、承認する場合は、承認者が承認ボタンを押下する)。そして、具体化度合「230」と「確認者考え中」に対応する承認段階に基づいて進展度指数が算出されて保存される。 In the case of FIG. 13c, the input person selects the reification degree option in the same manner as in FIG. 13b, but the selection of the approval stage option reflects the ideas of a plurality of confirmers, and the ideas of the confirmers. Is configured so that the approver can consider. In the attribute information of FIG. 13c, the degree of concreteness “230” is selected and “determine basic classification” is selected as the degree of concreteness option, and “Good”, “Bad”, etc. The option of "Information" is presented, and the confirmers' thoughts on such option are "Good" 3 people, "Bad" 0 people, and "Neutral" 2 people. And, for example, in such a state, since all the ideas of the confirmer are not prepared, the confirmer is being considered as the approval stage option (in the case of such an approval stage option, the confirmed number of confirmers, The progress index can be changed even while the confirmer is thinking, depending on the type of selected option, etc. Also, when approving, the approver presses the approval button). Then, the progress index is calculated and stored based on the approval stage corresponding to the degree of concreteness "230" and "thinking about the confirmer".

図14は、BIMモデル2aの達成率を表示したGUIの一例である。BIMモデル2aの達成率としては、例えば、図14に示すように、部位分類毎、段階的な状態指標値(図では200、230、250・・・)の一覧が表示され、さらに、右端の表示ボダン(図14では外部ドアの右端の表示ボタン)をクリックすると、その部位分類における各状態指標値の達成率等の詳細が表示される。 FIG. 14 is an example of a GUI displaying the achievement rate of the BIM model 2a. As the achievement rate of the BIM model 2a, for example, as shown in FIG. 14, a list of stepwise state index values (200, 230, 250 ... In the figure) for each part classification is displayed, and further, at the right end. When the display button (display button at the right end of the external door in FIG. 14) is clicked, details such as the achievement rate of each state index value in the site classification are displayed.

<<<管理システム1を用いた管理方法の有効性について>>>
上述したように、本実施形態においては、BIMモデル2aの部品の具体化度合がレベル別に複数表された具体化度合選択肢と、具体化度合の承認までの段階が段階別に複数表された承認段階選択肢と、をコンピュータが提示する選択肢提示ステップと、提示された具体化度合選択肢及び承認段階選択肢の中からの選択をコンピュータが受け付ける選択受付ステップと、選択された具体化度合及び承認段階に基づいて、部品がどの程度決定されているかを示す進展度指数をコンピュータが算出する進展度指数算出ステップと、算出された進展度指数をコンピュータが部品に関連付ける関連付けステップと、を有することとした。そのため、BIMモデル2aにおける部品の進捗把握の正確性を高めることが可能となる。
<<< Effectiveness of management method using management system 1 >>>
As described above, in the present embodiment, a plurality of concreteness degree options in which the degree of concreteness of the parts of the BIM model 2a is represented by a level and a plurality of stages up to the approval of the degree of concreteness are represented in a staged approval stage. Based on the option presentation step presented by the computer, the selection acceptance step in which the computer accepts the selection from the presented reification degree options and approval stage options, and the selected reification degree and approval stage. , The progress index calculation step in which the computer calculates the progress index indicating how much the part is determined, and the association step in which the computer associates the calculated progress index with the part. Therefore, it is possible to improve the accuracy of grasping the progress of the parts in the BIM model 2a.

BIMモデルは、複数の利用者が各々閲覧等してその進捗を確認することができるが、その正確性については不明瞭な点があった。例えば、BIMモデルの壁の位置が承認待ちであり、まだ決定していない(変更の余地が十分にある)場合でも、決定していないという情報は設計者、承認者等の入力者の頭の中にしかなく、その他の利用者は、その壁の位置が決まっている(位置が決定するまで設計が進んでいる)と認識してしまう場合があった。 The BIM model can be viewed by a plurality of users and the progress can be confirmed, but its accuracy is unclear. For example, even if the position of the wall of the BIM model is awaiting approval and has not been decided yet (there is ample room for change), the information that it has not been decided is the head of the designer, approver, etc. It was only inside, and other users sometimes recognized that the position of the wall was fixed (the design was in progress until the position was decided).

これに対し、本実施形態においては、部品の具体化度合別の具体化度合選択肢と、具体化度合の承認段階別の承認段階選択肢を入力者に選択させ、かかる2つの選択肢から進展度指数を算出し、部品と関連付けることとした。そうすると、入力者以外のBIMモデル2aの利用者にも、例えば、部品の承認否認の状態が分かるので、かかる部品の進展程度を誤解することを抑制することができ、正確な情報が伝わりやすい。すなわち、BIMモデル2aにおける部品の進捗把握の正確性を高めることが可能となる。 On the other hand, in the present embodiment, the input person is made to select the concreteness degree option according to the concreteness degree of the part and the approval stage option according to the approval stage of the concreteness degree, and the progress index is selected from these two options. It was calculated and associated with the parts. Then, since the user of the BIM model 2a other than the input person can know the state of approval / disapproval of the part, for example, it is possible to suppress misunderstanding of the degree of progress of the part, and accurate information can be easily transmitted. That is, it is possible to improve the accuracy of grasping the progress of parts in the BIM model 2a.

また、本実施形態においては、部品は複数種類の部位分類のいずれかに属しており、共通の部位分類に属する部品に関連付けられた進展度指数を平均化して、部位分類毎の部位分類進展度指数をコンピュータが算出する部位分類進展度指数算出ステップを有することとした。そうすると、部位分類(外壁、外部ドア、柱等)毎に部位分類進展度指数で進捗を確認することができる。 Further, in the present embodiment, the parts belong to one of a plurality of types of site classifications, and the progress index associated with the parts belonging to the common site classification is averaged to determine the progress of the site classification for each site classification. It was decided to have a part classification progress index calculation step in which the index is calculated by a computer. Then, the progress can be confirmed by the part classification progress index for each part classification (outer wall, outer door, pillar, etc.).

また、本実施形態においては、部位分類進展度指数は、BIMモデル2aに対応したプロジェクトの複数のフェーズ毎(目標値毎)に算出され、複数のフェーズ毎に設定される目標値の事前登録をコンピュータが受け付ける事前登録受け付けステップと、現フェーズ及び現フェーズの一つ前の前フェーズに対応する目標値と、現フェーズに対応する部位分類進展度指数とに基づいて、現フェーズまでの進展度合を示すフェーズ進展率をコンピュータが算出する進展率算出ステップを有することとした。そうすると、各フェーズにおけるフェーズ進展率を確認することができる。 Further, in the present embodiment, the site classification progress index is calculated for each of a plurality of phases (for each target value) of the project corresponding to the BIM model 2a, and the target value set for each of the plurality of phases is pre-registered. Based on the pre-registration acceptance step accepted by the computer, the target value corresponding to the current phase and the previous phase immediately before the current phase, and the site classification progress index corresponding to the current phase, the degree of progress up to the current phase is determined. It was decided to have a progress rate calculation step in which the indicated phase progress rate is calculated by a computer. Then, the phase progress rate in each phase can be confirmed.

また、本実施形態においては、フェーズ進展率は、部位分類毎に算出され、部位分類毎のフェーズ進展率を平均化してBIMモデル2aの進捗率をコンピュータが算出するBIMモデル進捗率算出ステップを有することとした。そうすると、BIMモデルの進捗率を確認することができる。 Further, in the present embodiment, the phase progress rate is calculated for each part classification, and has a BIM model progress rate calculation step in which the computer calculates the progress rate of the BIM model 2a by averaging the phase progress rate for each part classification. I decided. Then, the progress rate of the BIM model can be confirmed.

また、本実施形態においては、BIMモデル2aに対応したプロジェクトの複数のフェーズ毎に、かつ、BIMモデル2aの部位分類毎に設定される目標値であって、目標値の各々に部位分類のパラメータが関連付けられている目標値の事前登録をコンピュータが受け付ける事前登録受け付けステップと、パラメータの確定有無についての情報をコンピュータが抽出する情報抽出ステップと、現フェーズ及び現フェーズの一つ前の前フェーズに対応する目標値と、パラメータについての情報抽出結果と、に基づいて、現フェーズまでの進展度合を示すフェーズ進展率をコンピュータが部位分類毎に算出する進展率算出ステップと、を有することとした。そうすると、パラメータの確定有無の情報から各フェーズにおけるフェーズ進展率を確認することができる。 Further, in the present embodiment, the target values are set for each of a plurality of phases of the project corresponding to the BIM model 2a and for each part classification of the BIM model 2a, and each of the target values is a parameter of the part classification. In the pre-registration acceptance step in which the computer accepts the pre-registration of the target value associated with, the information extraction step in which the computer extracts information about whether or not the parameter is fixed, and the current phase and the previous phase immediately before the current phase. Based on the corresponding target value and the information extraction result for the parameter, it is decided to have a progress rate calculation step in which the computer calculates the phase progress rate indicating the degree of progress up to the current phase for each part classification. Then, the phase progress rate in each phase can be confirmed from the information on whether or not the parameter is fixed.

===その他の実施形態について===
上記実施形態は、本発明の理解を容易にするためのものであり、本発明を限定して解釈するためのものではない。本発明は、その趣旨を逸脱することなく、変更、改良され得ると共に、本発明にはその等価物が含まれることはいうまでもない。
=== About other embodiments ===
The above embodiment is for facilitating the understanding of the present invention, and is not for limiting the interpretation of the present invention. It goes without saying that the present invention can be modified and improved without departing from the spirit thereof, and the present invention includes an equivalent thereof.

また、上記実施形態では、管理システム1を用いた管理方法であったが、管理システム1に限るものではない。以下、図15~図17を示して異なる管理システムを説明する。 Further, in the above embodiment, the management method using the management system 1 is used, but the method is not limited to the management system 1. Hereinafter, different management systems will be described with reference to FIGS. 15 to 17.

図15は、進展度管理装置110を有する管理システム101の構成図である。図15に示すように、記憶部10と状態処理部20をWebサーバーでまとめて進展度管理装置110とした構成である。 FIG. 15 is a configuration diagram of a management system 101 having a progress management device 110. As shown in FIG. 15, the storage unit 10 and the state processing unit 20 are combined by a Web server to form a progress management device 110.

図16は、進展度管理装置210内に全体をまとめた管理システム201の構成図である。図16に示すように、BIMソフト202の内部に状態処理部20と表示部30を設けて、BIMソフト202を進展度管理装置210に含めた構成である。 FIG. 16 is a block diagram of the management system 201 as a whole in the progress management device 210. As shown in FIG. 16, a state processing unit 20 and a display unit 30 are provided inside the BIM software 202, and the BIM software 202 is included in the progress management device 210.

図17は、BIMソフト302内に全体をまとめた管理システム301の構成図である。図17に示すように、進展度管理装置310をBIMソフト302に含めた構成である。 FIG. 17 is a configuration diagram of the management system 301 as a whole in the BIM software 302. As shown in FIG. 17, the progress management device 310 is included in the BIM software 302.

また、上記実施形態では、BIMモデルの設計段階について説明したが、これに限るものではない。例えば、施工段階においても用いることができ、部品が壁であれば、例えば、骨組みの組立完了、下地の施工完了、上地の施工完了、仕上げ完了のそれぞれの段階をフェーズとすることより、上記実施形態と同様の管理方法で施工の進捗を確認することができる。 Further, in the above embodiment, the design stage of the BIM model has been described, but the present invention is not limited to this. For example, it can also be used in the construction stage, and if the part is a wall, for example, by setting each stage of skeleton assembly completion, foundation construction completion, upper ground construction completion, and finishing completion as phases, the above The progress of construction can be confirmed by the same management method as in the embodiment.

1 管理システム、2 BIMソフト、2a BIMモデル、
10 記憶部、11 部位分類情報記憶部、11a 部位分類データ、
11b 部位分類基準データ、12 状態指標記憶部、12a 具体化度合データ、
12b 目標値(目標部位分類進展度指数)データ、12c パラメータデータ、
13 状態記憶部、13a 構成要素状態データ、13b パラメータ入力状態データ、
20 状態処理部、30 表示部、
101 管理システム、110 進展度管理装置、
201 管理システム、202 BIMソフト、210 進展度管理装置、
301 管理システム、302 BIMソフト、310 進展度管理装置、
1 management system, 2 BIM software, 2a BIM model,
10 storage unit, 11 site classification information storage unit, 11a site classification data,
11b part classification standard data, 12 state index storage unit, 12a concreteness degree data,
12b target value (target part classification progress index) data, 12c parameter data,
13 state storage unit, 13a component state data, 13b parameter input state data,
20 status processing unit, 30 display unit,
101 management system, 110 progress management device,
201 management system, 202 BIM software, 210 progress management device,
301 management system, 302 BIM software, 310 progress management device,

Claims (8)

BIMモデルの構成要素の具体化度合がレベル別に複数表された具体化度合選択肢と、前記具体化度合の承認までの段階が段階別に複数表された承認段階選択肢と、をコンピュータが提示する選択肢提示ステップと、
提示された前記具体化度合選択肢及び前記承認段階選択肢の中からの選択をコンピュータが受け付ける選択受付ステップと、
選択された前記具体化度合及び前記承認段階に基づいて、前記構成要素がどの程度決定されているかを示す進展度指数をコンピュータが算出する進展度指数算出ステップと、
算出された前記進展度指数をコンピュータが前記構成要素に関連付ける関連付けステップと、
を有することを特徴とするBIMモデルの管理方法。
The computer presents options for the degree of concreteness in which the degree of concreteness of the components of the BIM model is expressed for each level, and the option for the approval stage in which the stages up to the approval of the degree of concreteness are expressed in multiple stages. Steps and
A selection acceptance step in which the computer accepts a selection from the presented specificity degree options and approval stage options.
A progress index calculation step in which a computer calculates a progress index indicating how much the component is determined based on the selected degree of reification and the approval stage.
An association step in which the computer associates the calculated progress index with the component.
A method of managing a BIM model, characterized in having.
請求項1に記載のBIMモデルの管理方法であって、
前記構成要素は複数種類の部位分類のいずれかに属しており、
共通の部位分類に属する前記構成要素に関連付けられた前記進展度指数を平均化して、部位分類毎の部位分類進展度指数をコンピュータが算出する部位分類進展度指数算出ステップを有することを特徴とするBIMモデルの管理方法。
The BIM model management method according to claim 1.
The components belong to one of a plurality of types of site classifications.
It is characterized by having a part classification progress index calculation step in which a computer calculates a part classification progress index for each part classification by averaging the progress indexes associated with the components belonging to a common part classification. How to manage the BIM model.
請求項2に記載のBIMモデルの管理方法であって、
前記部位分類進展度指数は、前記BIMモデルに対応したプロジェクトの複数のフェーズ毎に算出され、
前記複数のフェーズ毎に設定される目標部位分類進展度指数の事前登録をコンピュータが受け付ける事前登録受け付けステップと、
現フェーズ及び前記現フェーズの一つ前の前フェーズに対応する前記目標部位分類進展度指数と、前記現フェーズに対応する前記部位分類進展度指数とに基づいて、前記現フェーズまでの進展度合を示す進展率をコンピュータが算出する進展率算出ステップと、
を有することを特徴とするBIMモデルの管理方法。
The BIM model management method according to claim 2.
The site classification progress index is calculated for each of a plurality of phases of the project corresponding to the BIM model.
The pre-registration acceptance step in which the computer accepts the pre-registration of the target site classification progress index set for each of the plurality of phases, and the pre-registration acceptance step.
Based on the target site classification progress index corresponding to the current phase and the previous phase immediately before the current phase, and the site classification progress index corresponding to the current phase, the progress to the current phase is determined. The progress rate calculation step in which the computer calculates the progress rate shown, and
A method of managing a BIM model, characterized in having.
請求項3に記載のBIMモデルの管理方法であって、
前記進展率は、前記部位分類毎に算出され、
前記部位分類毎の前記進展率を平均化して前記BIMモデルの進捗率をコンピュータが算出するBIMモデル進捗率算出ステップを有することを特徴とするBIMモデルの管理方法。
The BIM model management method according to claim 3.
The progress rate is calculated for each part classification.
A method for managing a BIM model, which comprises a BIM model progress rate calculation step in which a computer calculates the progress rate of the BIM model by averaging the progress rate for each part classification.
BIMモデルを管理する管理方法であって、
前記BIMモデルに対応したプロジェクトの複数のフェーズ毎に、かつ、前記BIMモデルの部位分類毎に設定される目標部位分類進展度指数であって、前記目標部位分類進展度指数の各々に前記部位分類のパラメータが関連付けられている目標部位分類進展度指数の事前登録をコンピュータが受け付ける事前登録受け付けステップと、
前記パラメータの確定有無についての情報をコンピュータが抽出する情報抽出ステップと、
現フェーズ及び前記現フェーズの一つ前の前フェーズに対応する前記目標部位分類進展度指数と、前記パラメータについての情報抽出結果と、に基づいて、前記現フェーズまでの進展度合を示す進展率をコンピュータが前記部位分類毎に算出する進展率算出ステップと、
を有することを特徴とするBIMモデルの管理方法。
It is a management method to manage the BIM model.
It is a target site classification progress index set for each of a plurality of phases of the project corresponding to the BIM model and for each site classification of the BIM model, and the site classification is applied to each of the target site classification progress indexes. The pre-registration acceptance step, in which the computer accepts the pre-registration of the target site classification progress index associated with the parameters of
An information extraction step in which a computer extracts information about whether or not the parameters are fixed, and
Based on the current phase and the target site classification progress index corresponding to the previous phase immediately before the current phase, and the information extraction result for the parameter, the progress rate indicating the progress to the current phase is calculated. The progress rate calculation step calculated by the computer for each part classification,
A method of managing a BIM model, characterized in having.
請求項5に記載のBIMモデルの管理方法であって、
前記進展率は、前記部位分類毎に算出され、
前記部位分類毎の前記進展率を平均化して前記BIMモデルの進捗率をコンピュータが算出するBIMモデル進捗率算出ステップを有することを特徴とするBIMモデルの管理方法。
The BIM model management method according to claim 5.
The progress rate is calculated for each part classification.
A method for managing a BIM model, which comprises a BIM model progress rate calculation step in which a computer calculates the progress rate of the BIM model by averaging the progress rate for each part classification.
BIMモデルを管理する管理システムであって、
請求項1~請求項6のいずれか1項の管理方法を実行することを特徴とする管理システム。
A management system that manages BIM models
A management system comprising executing the management method according to any one of claims 1 to 6.
BIMモデルを管理するプログラムであって、
請求項1~請求項6のいずれか1項の管理方法を実行させることを特徴とするプログラム。
A program that manages BIM models
A program characterized by executing the management method according to any one of claims 1 to 6.
JP2020160989A 2020-09-25 2020-09-25 Management method, management system, and program for bim model Pending JP2022054028A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020160989A JP2022054028A (en) 2020-09-25 2020-09-25 Management method, management system, and program for bim model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020160989A JP2022054028A (en) 2020-09-25 2020-09-25 Management method, management system, and program for bim model

Publications (1)

Publication Number Publication Date
JP2022054028A true JP2022054028A (en) 2022-04-06

Family

ID=80994253

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020160989A Pending JP2022054028A (en) 2020-09-25 2020-09-25 Management method, management system, and program for bim model

Country Status (1)

Country Link
JP (1) JP2022054028A (en)

Similar Documents

Publication Publication Date Title
US20130218780A1 (en) System and Method for Digitally Monitoring Construction Project Progress
McKinney et al. Generating, evaluating and visualizing construction schedules with CAD tools
US8229715B1 (en) System and methods facilitating collaboration in the design, analysis, and implementation of a structure
US20080183483A1 (en) Office management solution
US8155928B2 (en) Method for generating data of plant construction simulation and system thereof
US10331807B2 (en) Generating a rules database for multi condition takeoff in a construction project
US9483754B2 (en) Interactive building stacking plans
US20120297330A1 (en) Method and System for Generating Reports
US20140019148A1 (en) Change process for construction projects
US7676428B2 (en) System and method for aiding commercial property assessment
US9443261B2 (en) Method and apparatus for optimization of floor covering and system for user configuration and real time pricing information
US20140278703A1 (en) Enterprise resource management system and method
US8341042B2 (en) On-demand and configurable earned value measurements reporting
US20090066698A1 (en) Systems And Methods For Performing Quantity Takeoff Computations From Computer Aided Design Drawings
US20140358617A1 (en) Method and system for project planning and estimation
US10296665B2 (en) Image management in construction project software programs
US20120323535A1 (en) Quantification of Structure Fitness Enabling Evaluation and Comparison of Structure Designs
Jrade et al. Computer-integrated system for estimating the costs of building projects
US20120016699A1 (en) Systems and methods for inventory management
US11620599B2 (en) Real-time labor tracking and validation on a construction project using computer aided design
JP2022054028A (en) Management method, management system, and program for bim model
JPWO2008142729A1 (en) Program, apparatus, and method for assisting price estimation
US20130151420A1 (en) Online building
US8463580B2 (en) Systems and methods for performing quantity takeoff computations from computer aided design drawings
JP2002215686A (en) Building estimation system and computer readable recording medium recording its processing program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230818