JP2021064255A - Maintenance schedule creation program, maintenance schedule creation method, and maintenance schedule creation device - Google Patents

Maintenance schedule creation program, maintenance schedule creation method, and maintenance schedule creation device Download PDF

Info

Publication number
JP2021064255A
JP2021064255A JP2019189431A JP2019189431A JP2021064255A JP 2021064255 A JP2021064255 A JP 2021064255A JP 2019189431 A JP2019189431 A JP 2019189431A JP 2019189431 A JP2019189431 A JP 2019189431A JP 2021064255 A JP2021064255 A JP 2021064255A
Authority
JP
Japan
Prior art keywords
maintenance
processing capacity
work
schedule
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2019189431A
Other languages
Japanese (ja)
Other versions
JP7322656B2 (en
Inventor
左千夫 小林
Sachio Kobayashi
左千夫 小林
丈夫 笠嶋
Takeo Kasashima
丈夫 笠嶋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP2019189431A priority Critical patent/JP7322656B2/en
Publication of JP2021064255A publication Critical patent/JP2021064255A/en
Application granted granted Critical
Publication of JP7322656B2 publication Critical patent/JP7322656B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

To efficiently create a maintenance schedule for a plant having a plurality of facilities.SOLUTION: A first processing capacity of a process without facility outage is acquired based on first information that defines each step of a process using a plurality of facilities, an interrelationship between the processes, and a processing capacity of each process. A second processing capacity of a process with one of the plurality of facilities stopped is acquired based on the first information. A maintenance cost of a maintenance schedule is calculated based on the first processing capacity and the second processing capacity. A start date constraint for a maintenance task is created for each pair of maintenance tasks that can be performed on overlapping dates based on the second information that defines the conditions for each of a plurality of maintenance tasks. A maintenance schedule is created and the maintenance cost is calculated while switching the validness or invalidness of each of the plurality of constraints.SELECTED DRAWING: Figure 9

Description

本発明は、メンテナンススケジュール作成プログラム、メンテナンススケジュール作成方法、及びメンテナンススケジュール作成装置に関する。 The present invention relates to a maintenance schedule creation program, a maintenance schedule creation method, and a maintenance schedule creation device.

工場や発電所等のプラントでは、プラントに配置された複数の設備の各々に対して、長期的、及び/又は、周期的な保全作業が行なわれる。 In a plant such as a factory or a power plant, long-term and / or periodic maintenance work is performed on each of a plurality of facilities arranged in the plant.

「設備」としては、例えば、機械、機器、配管等が挙げられる。「保全作業」とは、例えば、設備の点検、清掃、補修、交換、更新等の維持管理又は保守に係る作業である。保全作業は、「メンテナンス」と称されてもよい。 Examples of "equipment" include machines, equipment, piping and the like. "Maintenance work" is, for example, work related to maintenance or maintenance such as inspection, cleaning, repair, replacement, and renewal of equipment. Maintenance work may be referred to as "maintenance".

保全作業の管理者は、複数の設備の各々について作業を実行可能な日程を事前に調整し、年単位の保全スケジュールを作成して、保全スケジュールに従って保全作業を実施することが考えられる。 It is conceivable that the maintenance work manager adjusts the schedule for executing the work for each of the plurality of facilities in advance, creates an annual maintenance schedule, and carries out the maintenance work according to the maintenance schedule.

特開2010−282353号公報Japanese Unexamined Patent Publication No. 2010-282353 特開平9−285948号公報Japanese Unexamined Patent Publication No. 9-285948

プラントには、大小の設備が数多く存在することが多い。保全作業には、保全対象の設備ごとに複数の作業が存在するため、プラント全体の保全作業の総作業数や、作業ごとのスケジュールの組み合わせの数は膨大となる。 Plants often have many large and small facilities. Since there are a plurality of maintenance works for each equipment to be maintained, the total number of maintenance works for the entire plant and the number of combinations of schedules for each work are enormous.

従って、このようなプラントについて、管理者により、最適な(例えば保全コストが最小となる)スケジュールを容易に作成することは難しい。 Therefore, it is difficult for the manager to easily create an optimal schedule (for example, the maintenance cost is minimized) for such a plant.

1つの側面では、本発明は、複数の設備が配置されたプラントにおけるメンテナンススケジュールを効率的に作成することを目的とする。 In one aspect, the present invention aims to efficiently create a maintenance schedule for a plant in which a plurality of facilities are arranged.

1つの側面では、メンテナンススケジュール作成プログラムは、複数の設備の各々のメンテナンススケジュールを作成するコンピュータに、以下の処理を実行させてよい。前記処理は、前記複数の設備を利用するプロセスの各工程と、前記各工程間の相互関係と、前記各工程の処理能力とを定義する第1情報に基づき、設備停止のない状態での前記プロセスの第1処理能力を取得してよい。また、前記処理は、前記第1情報に基づき、前記複数の設備のうちのいずれかの設備停止状態での前記プロセスの第2処理能力を取得してよい。さらに、前記処理は、前記第1処理能力及び前記第2処理能力に基づき、前記メンテナンススケジュールのメンテナンスコストを算出してよい。また、前記処理は、複数のメンテナンス作業の各々の条件を定義する第2情報に基づき、メンテナンス作業の開始日に関する制約を、重なる日程で実行可能なメンテナンス作業のペアごとに作成してよい。さらに、前記処理は、複数の前記制約の各々の有効又は無効を切り替えながら、前記メンテナンススケジュールの作成と、前記メンテナンスコストの算出とを実行してよい。 In one aspect, the maintenance schedule creation program may cause the computer that creates the maintenance schedule for each of the plurality of facilities to perform the following processes. The processing is based on the first information that defines each step of the process using the plurality of facilities, the interrelationship between the steps, and the processing capacity of each step, and the processing is performed in a state without equipment stoppage. The first processing capacity of the process may be acquired. Further, in the processing, the second processing capacity of the process in the equipment stopped state of any of the plurality of equipments may be acquired based on the first information. Further, in the processing, the maintenance cost of the maintenance schedule may be calculated based on the first processing capacity and the second processing capacity. In addition, the process may create a constraint on the start date of the maintenance work for each pair of maintenance work that can be executed on the overlapping schedule, based on the second information that defines the conditions for each of the plurality of maintenance work. Further, in the process, the maintenance schedule may be created and the maintenance cost may be calculated while switching the validity or invalidity of each of the plurality of constraints.

1つの側面では、複数の設備が配置されたプラントにおけるメンテナンススケジュールを効率的に作成することができる。 On one side, maintenance schedules can be efficiently created in plants with multiple facilities.

保全スケジュールの作成手法の比較例を示す図である。It is a figure which shows the comparative example of the maintenance schedule creation method. 保全スケジュールの作成手法の比較例を示す図である。It is a figure which shows the comparative example of the maintenance schedule creation method. 機会損失コストの算出例を示す図である。It is a figure which shows the calculation example of the opportunity loss cost. プラントの処理プロセスを、各工程間を流れる製品のネットワーク図として表現した例を示す図である。It is a figure which shows the example which expressed the processing process of a plant as the network diagram of the product which flows between each process. 一実施形態に係る保全スケジュール作成装置の機能を実現するコンピュータのハードウェア構成例を示すブロック図である。It is a block diagram which shows the hardware configuration example of the computer which realizes the function of the maintenance schedule creation apparatus which concerns on one Embodiment. 一実施形態に係る保全スケジュール作成装置の機能構成例を示すブロック図である。It is a block diagram which shows the functional structure example of the maintenance schedule creation apparatus which concerns on one Embodiment. 処理プロセス情報の一例を示す図である。It is a figure which shows an example of the processing process information. 保全スケジュール情報の一例を示す図である。It is a figure which shows an example of maintenance schedule information. 作成装置による保全スケジュールの作成に係る全体の動作例を示すフローチャートである。It is a flowchart which shows the whole operation example which concerns on the creation of maintenance schedule by a creation apparatus. 処理プロセス情報を、前工程から次工程に向かう矢印で工程間を繋いだ有向グラフとして可視化した図である。It is a figure which visualized the processing process information as a directed graph which connected the process by the arrow from the previous process to the next process. 図7に例示する処理プロセスのネットワーク図の一例を示す図である。It is a figure which shows an example of the network diagram of the processing process illustrated in FIG. 7. ネットワーク図作成部による動作例を示すフローチャートである。It is a flowchart which shows the operation example by a network diagram creation part. 図11に示すネットワーク図の作成手法の一例を示す図である。It is a figure which shows an example of the creation method of the network diagram shown in FIG. 図11に示すネットワーク図の作成手法の一例を示す図である。It is a figure which shows an example of the creation method of the network diagram shown in FIG. 最大処理能力計算部による動作例を示すフローチャートである。It is a flowchart which shows the operation example by the maximum processing capacity calculation part. 図11に示すネットワーク図に基づく最大処理能力の計算手法の一例を示す図である。It is a figure which shows an example of the calculation method of the maximum processing capacity based on the network diagram shown in FIG. 図11に示すネットワーク図に基づく最大処理能力の計算手法の一例を示す図である。It is a figure which shows an example of the calculation method of the maximum processing capacity based on the network diagram shown in FIG. 作業間制約作成部による収集処理の一例を示す図である。It is a figure which shows an example of the collection processing by the inter-working constraint creation part. 作業間制約作成部による実行可否確認処理の一例を示す図である。It is a figure which shows an example of the executionability confirmation processing by the work-to-work constraint creation part. 作業間制約の一例を示す図である。It is a figure which shows an example of the inter-working constraint. スケジュール作成部による保全スケジュールの作成処理の一例を示すフローチャートである。It is a flowchart which shows an example of the maintenance schedule creation process by a schedule creation part. 保全スケジュール作成手法の一例を示す図である。It is a figure which shows an example of the maintenance schedule creation method. 保全スケジュール作成手法の一例を示す図である。It is a figure which shows an example of the maintenance schedule creation method. 保全スケジュール作成手法の一例を示す図である。It is a figure which shows an example of the maintenance schedule creation method. 保全コスト決定部による保全コストの決定処理の一例を示すフローチャートである。It is a flowchart which shows an example of the maintenance cost determination process by the maintenance cost determination part. 日々の処理能力の計算手法の一例を示す図である。It is a figure which shows an example of the calculation method of the daily processing capacity. 保全スケジュール及び保全コストの作成結果の表示例を示す図である。It is a figure which shows the display example of the creation result of maintenance schedule and maintenance cost. 作成装置と、端末とを備えるシステムの構成例を示す図である。It is a figure which shows the configuration example of the system which includes a creation apparatus and a terminal.

以下、図面を参照して本発明の実施の形態を説明する。ただし、以下に説明する実施形態は、あくまでも例示であり、その趣旨を逸脱しない範囲で種々変形して実施することができる。なお、以下の実施形態で用いる図面において、同一符号を付した部分は、特に断らない限り、同一若しくは同様の部分を表す。 Hereinafter, embodiments of the present invention will be described with reference to the drawings. However, the embodiments described below are merely examples, and can be variously modified and implemented without departing from the spirit. In the drawings used in the following embodiments, the parts having the same reference numerals represent the same or similar parts unless otherwise specified.

〔1〕一実施形態
〔1−1〕保全スケジュールの作成について
図1及び図2は、保全スケジュールの作成手法の比較例を示す図である。図1に示すように、管理者は、比較例において、設備の保全作業100における作業ごとに作業の日程調整を行ない、保全スケジュール200を作成する。日程調整では、管理者は、例えば、作業の実行期間(締切日)、作業日数、対象設備、作業の担当者、保全作業に使用する使用機器、等に関する制約(条件)を考慮する。
[1] Embodiment [1-1] Creation of maintenance schedule FIGS. 1 and 2 are diagrams showing comparative examples of maintenance schedule creation methods. As shown in FIG. 1, in the comparative example, the manager adjusts the work schedule for each work in the equipment maintenance work 100 and creates the maintenance schedule 200. In schedule adjustment, the administrator considers, for example, restrictions (conditions) regarding the work execution period (deadline), the number of work days, the target equipment, the person in charge of the work, the equipment used for the maintenance work, and the like.

一例として、管理者は、図2に示すように、設備及び作業ごとに決めた周期に基づいて仮スケジュールを作成し、制約充足チェックと、コスト評価とを行ないながら日程調整を行なう。そして、管理者は、制約を満たし且つ保全コストが小さくなるような作業の開始日を決定することで、保全スケジュール200を作成する。 As an example, as shown in FIG. 2, the manager creates a provisional schedule based on a cycle determined for each facility and work, and adjusts the schedule while performing a constraint satisfaction check and a cost evaluation. Then, the manager creates the maintenance schedule 200 by determining the start date of the work that satisfies the restrictions and reduces the maintenance cost.

制約には、例えば、指定された実行期間内に作業を実行すること、担当者が同時に実行できる作業が1個であること、重機等の使用機器の個数に上限があること、等が挙げられる。 Restrictions include, for example, that work is executed within a specified execution period, that the person in charge can execute one work at the same time, that there is an upper limit on the number of devices used such as heavy machinery, and the like. ..

保全コストには、例えば、部材費や人件費等の保全日に依存しない作業のコスト、部材の残存価値(簿価)等の保全日に依存する作業のコスト、及び、作業の組み合わせで決まる機会損失のコスト、が含まれてよい。 The maintenance cost includes, for example, the cost of work that does not depend on the maintenance date such as material cost and labor cost, the cost of work that depends on the maintenance date such as the residual value (book value) of the material, and the opportunity determined by the combination of work. The cost of loss, may be included.

しかし、上述のように、大小の設備が数多く配置されたプラントの保全スケジュールを作成する場合、スケジュールの組み合わせの数は膨大であるため、制約を満たしながら、保全コストが小さくなるようなスケジュールを作成することは難しい。例えば、熟練者である管理者が、経験と知見に基づいて保全スケジュールを作成する場合であっても、作業数が多くなるほど作成の難易度は高まり、時間もかかるため、人手では、保全コストを最小化するスケジュールを特定することは困難である。 However, as described above, when creating a maintenance schedule for a plant with many large and small facilities, the number of combinations of schedules is enormous, so create a schedule that satisfies the constraints and reduces the maintenance cost. It's difficult to do. For example, even if a skilled manager creates a maintenance schedule based on experience and knowledge, the more work is done, the more difficult and time-consuming it is to create, so the maintenance cost is manually reduced. It is difficult to identify the schedule to minimize.

また、数理最適化等のアルゴリズムによってスケジュールを自動生成する手法も考えられるが、当該手法を機会損失コストに基づく保全スケジュール作成に適用する場合、以下の不都合がある。 Further, a method of automatically generating a schedule by an algorithm such as mathematical optimization can be considered, but when this method is applied to the creation of a maintenance schedule based on the opportunity loss cost, there are the following inconveniences.

(a)機会損失コストは、単純な数式や関数として表現することができないため、機会損失コストを適切に算出することが困難である。 (A) Since the opportunity loss cost cannot be expressed as a simple mathematical formula or function, it is difficult to properly calculate the opportunity loss cost.

(b)作業数が多いほど作業の組み合わせの探索範囲が広くなるため、最適化の処理時間が大きくなり、また、局所最適な結果しか得られない。 (B) As the number of operations increases, the search range for the combination of operations becomes wider, so that the optimization processing time increases, and only locally optimal results can be obtained.

そこで、一実施形態では、保全スケジュールを効率的に作成する手法の一例として、短時間に保全コストの小さいスケジュール作成を可能とする手法を説明する。 Therefore, in one embodiment, as an example of a method for efficiently creating a maintenance schedule, a method that enables a schedule with a low maintenance cost to be created in a short time will be described.

〔1−2〕一実施形態の説明
まず、機会損失コストについて説明する。図3は、機会損失コストの算出例を示す図である。図3に例示するように、機会損失コストは、正常時の製造プロセス及び生産量を示すモデル300(図3の左上参照)に基づき、1以上の設備を停止させた場合の生産量をシミュレートすることで取得されてよい。
[1-2] Description of One Embodiment First, the opportunity loss cost will be described. FIG. 3 is a diagram showing an example of calculating the opportunity loss cost. As illustrated in FIG. 3, the opportunity loss cost simulates the production volume when one or more facilities are shut down based on the model 300 (see the upper left of FIG. 3) showing the normal manufacturing process and production volume. It may be obtained by doing.

図3の例では、1以上の設備として、機械B1を停止させた場合(図3の左下参照)、機械Cを停止させた場合(図3の右上参照)、及び、機械B2及びCを停止させた場合(図3の右下参照)、のそれぞれの生産量が算出される。機会損失コストは、このモデル300の(正常時の)生産量、設備を停止させた場合の生産量、設備の停止期間等に基づき算出可能である。なお、図3に示す生産量は、所定期間(例えば1日、1時間、1分等)の最大生産量を示す。 In the example of FIG. 3, as one or more facilities, the machine B1 is stopped (see the lower left of FIG. 3), the machine C is stopped (see the upper right of FIG. 3), and the machines B2 and C are stopped. When this is done (see the lower right of FIG. 3), the respective production amounts are calculated. The opportunity loss cost can be calculated based on the production amount (normal time) of this model 300, the production amount when the equipment is stopped, the equipment stop period, and the like. The production amount shown in FIG. 3 indicates the maximum production amount for a predetermined period (for example, 1 day, 1 hour, 1 minute, etc.).

図3に例示するように、設備停止に起因する機会損失コストは、処理プロセスや設備の生産能力に加え、同時に停止する設備の組み合わせにも依存する。機会損失コストを小さくするには、設備停止の影響範囲が重なる複数の保全作業を、重なる日程で処理することが有効である。 As illustrated in FIG. 3, the opportunity loss cost due to equipment outages depends not only on the processing process and equipment production capacity, but also on the combination of equipments that are shut down at the same time. In order to reduce the opportunity loss cost, it is effective to process multiple maintenance operations with overlapping equipment outages on overlapping schedules.

上述のように、プラントの規模(設備の数)が大きいほど、作業の組み合わせは膨大となる。また、機会損失コストを計算するには、図2に例示するように、設備や作業ごとのコストを計算して総和を取る手法では不十分であり、また、手間(時間)もかかる。 As described above, the larger the scale of the plant (the number of facilities), the greater the number of combinations of work. Further, in order to calculate the opportunity loss cost, as illustrated in FIG. 2, the method of calculating the cost for each equipment or work and taking the sum is not sufficient, and it takes time and effort.

そこで、一実施形態に係る作成装置は、プラントの処理プロセスと、各工程間を流れる製品との関係に着目して、保全スケジュールを作成する。以下、作成装置を単に「作成装置」と表記する場合がある。 Therefore, the production apparatus according to one embodiment creates a maintenance schedule by paying attention to the relationship between the processing process of the plant and the products flowing between the processes. Hereinafter, the creating device may be simply referred to as a "creating device".

図4は、プラントの処理プロセスを、各工程間を流れる製品のネットワーク図NEとして表現した例を示す図である。以下、便宜上、作成装置が、プラントの処理プロセスと各工程間を流れる製品との関係を示す情報の一例として、ネットワーク図NEを作成するものとして説明するが、これに限定されるものではない。 FIG. 4 is a diagram showing an example in which the processing process of the plant is represented as a network diagram NE of products flowing between the processes. Hereinafter, for convenience, the production apparatus will be described as creating a network diagram NE as an example of information indicating the relationship between the processing process of the plant and the products flowing between the processes, but the present invention is not limited to this.

一実施形態において、ネットワーク図NEは必須ではなく、例えば、作成装置は、ネットワーク図NEに代えて、上記関係を示すテーブル、DB(Database)、配列等の種々の情報を利用又は作成してもよい。 In one embodiment, the network diagram NE is not essential. For example, the creating device may use or create various information such as a table, a DB (Database), and an array showing the above relationship instead of the network diagram NE. Good.

ネットワーク図NEは、プラントの処理プロセスの開始「s」及び終了「e」の間に、各「工程」をノードNDとして配置し、ノードND間を矢印で接続した図である。矢印は、工程間の製品の流れを示す。なお、図4の上段に示すネットワーク図NEでは、矢印の上に、各工程で処理可能な処理量の一例を示す。 The network diagram NE is a diagram in which each "process" is arranged as a node ND between the start "s" and the end "e" of the processing process of the plant, and the nodes ND are connected by arrows. Arrows indicate product flow between processes. In the network diagram NE shown in the upper part of FIG. 4, an example of the processing amount that can be processed in each process is shown above the arrow.

「工程」は、処理プロセスを細分化した1つの処理であり、「手順」と称されてもよい。「工程」では、1以上の設備が使用されてよい。設備は、「工程」間で重複して使用されてもよい。保全作業では、各「工程」につき1以上の作業が行なわれてよい。 A "process" is one process in which a process is subdivided, and may be referred to as a "procedure". In the "process", one or more facilities may be used. Equipment may be used in duplicate between "processes". In the maintenance work, one or more operations may be performed for each "process".

一実施形態において、作成装置は、図4の左側に例示するように、ネットワーク図NEを用いて機会損失コストを計算してよい。図4の左中段に示すネットワーク図NEでは、矢印の上に、上流から下流に製品が流れる場合の各工程の最大流量の一例を示す。図4の左下段には、工程C1の保全作業を実施する場合を想定し、工程C1において流入及び流出する処理量(製品の数量)を“0”に設定した場合の各工程の処理量の一例を示す。図4の左中段から左下段にかけて、処理量が“20”から“10”に減少することがわかる。 In one embodiment, the creation device may calculate the opportunity loss cost using the network diagram NE, as illustrated on the left side of FIG. In the network diagram NE shown in the middle left of FIG. 4, an example of the maximum flow rate of each process when the product flows from the upstream to the downstream is shown above the arrow. In the lower left of FIG. 4, assuming the case where the maintenance work of the process C1 is carried out, the processing amount of each process when the inflow and outflow processing amount (quantity of products) in the process C1 is set to "0". An example is shown. It can be seen that the processing amount decreases from "20" to "10" from the middle left to the lower left in FIG.

また、一実施形態において、作成装置は、図4の右側に例示するように、ネットワーク図NEを用いて、機会損失コストを削減するための制約を生成してよい。図4の右中段に例示するように、設備“EQ04−1”を使用する工程C1を停止させる場合、設備“EQ05”を使用する工程D1における製品の流量も“0”となる。このため、工程D1は、工程C1と日程が重なるように作業するとよい工程である、換言すれば、機会損失コストの削減に有効であることがわかる。このような制約を利用することにより、保全スケジュールの最適化計算において良い解を短時間に得ることができる。 Further, in one embodiment, the creation device may generate a constraint for reducing the opportunity loss cost by using the network diagram NE as illustrated on the right side of FIG. As illustrated in the middle right of FIG. 4, when the process C1 using the equipment “EQ04-1” is stopped, the flow rate of the product in the process D1 using the equipment “EQ05” is also “0”. Therefore, it can be seen that the process D1 is a process in which the work should be performed so that the schedule overlaps with the process C1, in other words, it is effective in reducing the opportunity loss cost. By using such constraints, a good solution can be obtained in a short time in the optimization calculation of the maintenance schedule.

そこで、作成装置は、図4の右下段に例示するように、単独実行される複数の作業の日程が互いに重なるような制約を適宜追加することで、保全スケジュール特有の性質を利用した、最適化計算を実施することができる。 Therefore, as illustrated in the lower right part of FIG. 4, the creation device is optimized by appropriately adding restrictions such that the schedules of a plurality of independently executed works overlap each other, thereby utilizing the characteristics peculiar to the maintenance schedule. Calculations can be carried out.

このように、一実施形態に係る作成装置は、ネットワーク図NEに示すような関係に基づき、図4の左側に例示するように、保全作業を実施する場合の処理量の変化から、機会損失コストを計算し、スケジュールを評価する。 As described above, the creation device according to the first embodiment has an opportunity loss cost due to a change in the processing amount when the maintenance work is performed, as illustrated on the left side of FIG. 4, based on the relationship shown in the network diagram NE. And evaluate the schedule.

また、作成装置は、図4の右側に例示するように、重なる日程で実行するとよい作業のペアを見つけて最適化における制約(作業間制約)とし、制約を適宜有効化することで、解探索空間を良い解の存在する領域に限定することができる。これにより、計算量の削減、及び、解品質の向上を図ることができる。 Further, as illustrated on the right side of FIG. 4, the creation device finds a pair of work that should be executed on overlapping schedules, sets it as a constraint in optimization (inter-work constraint), and enables the constraint as appropriate to search for a solution. The space can be limited to the area where a good solution exists. As a result, the amount of calculation can be reduced and the solution quality can be improved.

〔1−3〕一実施形態の構成例
作成装置は、情報処理装置、例えばサーバやPC(Personal Computer)等のコンピュータとして構成されてよい。作成装置は、例えば、仮想サーバ(VM;Virtual Machine)であってもよいし、物理サーバであってもよい。また、作成装置の機能は、1台のコンピュータにより実現されてもよいし、2台以上のコンピュータにより実現されてもよい。
[1-3] Configuration Example of One Embodiment The creating device may be configured as an information processing device, for example, a computer such as a server or a PC (Personal Computer). The creating device may be, for example, a virtual server (VM) or a physical server. Further, the function of the creating device may be realized by one computer or may be realized by two or more computers.

作成装置は、プラントやデータセンタ等に設置され、いわゆるオンプレミスとして運用されてもよい。また、作成装置の機能のうちの少なくとも一部は、クラウド環境において提供されるHW(Hardware)リソース及びNW(Network)リソースを用いて実現されてもよい。 The creation device may be installed in a plant, a data center, or the like and operated as a so-called on-premises. Further, at least a part of the functions of the creation device may be realized by using HW (Hardware) resources and NW (Network) resources provided in the cloud environment.

〔1−3−1〕ハードウェア構成例
図5は、作成装置の機能を実現するコンピュータ10のHW構成例を示すブロック図である。作成装置の機能を実現するHWリソースとして、複数のコンピュータが用いられる場合は、各コンピュータが図5に例示するHW構成を備えてよい。
[1-3-1] Hardware Configuration Example FIG. 5 is a block diagram showing an HW configuration example of a computer 10 that realizes the function of the creation device. When a plurality of computers are used as the HW resource that realizes the function of the creating device, each computer may have the HW configuration illustrated in FIG.

図5に示すように、コンピュータ10は、HW構成として、例示的に、プロセッサ10a、メモリ10b、記憶部10c、IF(Interface)部10d、I/O(Input / Output)部10e、及び読取部10fを備えてよい。 As shown in FIG. 5, the computer 10 has an HW configuration, for example, a processor 10a, a memory 10b, a storage unit 10c, an IF (Interface) unit 10d, an I / O (Input / Output) unit 10e, and a reading unit. It may be provided with 10f.

プロセッサ10aは、種々の制御や演算を行なう演算処理装置の一例である。プロセッサ10aは、コンピュータ10内の各ブロックとバス10iで相互に通信可能に接続されてよい。なお、プロセッサ10aは、複数のプロセッサを含むマルチプロセッサであってもよいし、複数のプロセッサコアを有するマルチコアプロセッサであってもよく、或いは、マルチコアプロセッサを複数有する構成であってもよい。 The processor 10a is an example of an arithmetic processing unit that performs various controls and operations. The processor 10a may be connected to each block in the computer 10 so as to be able to communicate with each other by the bus 10i. The processor 10a may be a multiprocessor including a plurality of processors, a multicore processor having a plurality of processor cores, or a configuration having a plurality of multicore processors.

プロセッサ10aとしては、例えば、CPU、MPU、GPU、APU、DSP、ASIC、FPGA等の集積回路(IC;Integrated Circuit)が挙げられる。なお、プロセッサ10aとして、これらの集積回路の2以上の組み合わせが用いられてもよい。CPUはCentral Processing Unitの略称であり、MPUはMicro Processing Unitの略称である。GPUはGraphics Processing Unitの略称であり、APUはAccelerated Processing Unitの略称である。DSPはDigital Signal Processorの略称であり、ASICはApplication Specific ICの略称であり、FPGAはField-Programmable Gate Arrayの略称である。 Examples of the processor 10a include integrated circuits (ICs) such as CPUs, MPUs, GPUs, APUs, DSPs, ASICs, and FPGAs. A combination of two or more of these integrated circuits may be used as the processor 10a. CPU is an abbreviation for Central Processing Unit, and MPU is an abbreviation for Micro Processing Unit. GPU is an abbreviation for Graphics Processing Unit, and APU is an abbreviation for Accelerated Processing Unit. DSP is an abbreviation for Digital Signal Processor, ASIC is an abbreviation for Application Specific IC, and FPGA is an abbreviation for Field-Programmable Gate Array.

メモリ10bは、種々のデータやプログラム等の情報を格納するHWの一例である。メモリ10bとしては、例えばDRAM(Dynamic Random Access Memory)等の揮発性メモリが挙げられる。 The memory 10b is an example of an HW that stores information such as various data and programs. Examples of the memory 10b include a volatile memory such as a DRAM (Dynamic Random Access Memory).

記憶部10cは、種々のデータやプログラム等の情報を格納するHWの一例である。記憶部10cとしては、HDD(Hard Disk Drive)等の磁気ディスク装置、SSD(Solid State Drive)等の半導体ドライブ装置、不揮発性メモリ等の各種記憶装置が挙げられる。不揮発性メモリとしては、例えば、フラッシュメモリ、SCM(Storage Class Memory)、ROM(Read Only Memory)等が挙げられる。 The storage unit 10c is an example of an HW that stores information such as various data and programs. Examples of the storage unit 10c include a magnetic disk device such as an HDD (Hard Disk Drive), a semiconductor drive device such as an SSD (Solid State Drive), and various storage devices such as a non-volatile memory. Examples of the non-volatile memory include flash memory, SCM (Storage Class Memory), ROM (Read Only Memory) and the like.

また、記憶部10cは、コンピュータ10の各種機能の全部若しくは一部を実現するプログラム10g(メンテナンススケジュール作成プログラム)を格納してよい。例えば、作成装置のプロセッサ10aは、記憶部10cに格納されたプログラム10gをメモリ10bに展開して実行することにより、作成装置としての機能を実現できる。 Further, the storage unit 10c may store a program 10g (maintenance schedule creation program) that realizes all or a part of various functions of the computer 10. For example, the processor 10a of the creating device can realize the function as the creating device by expanding and executing the program 10g stored in the storage unit 10c in the memory 10b.

IF部10dは、ネットワークとの間の接続及び通信の制御等を行なう通信IFの一例である。例えば、IF部10dは、イーサネット(登録商標)等のLAN(Local Area Network)、或いは、光通信(例えばFC(Fibre Channel))等に準拠したアダプタを含んでよい。当該アダプタは、無線及び有線の一方又は双方の通信方式に対応してよい。例えば、プログラム10gは、当該通信IFを介して、ネットワークからコンピュータ10にダウンロードされ、記憶部10cに格納されてもよい。 The IF unit 10d is an example of a communication IF that controls connection with a network and communication. For example, the IF unit 10d may include an adapter compliant with LAN (Local Area Network) such as Ethernet (registered trademark) or optical communication (for example, FC (Fibre Channel)). The adapter may support one or both wireless and wired communication methods. For example, the program 10g may be downloaded from the network to the computer 10 via the communication IF and stored in the storage unit 10c.

I/O部10eは、入力装置、及び、出力装置、の一方又は双方を含んでよい。入力装置としては、例えば、キーボード、マウス、タッチパネル等が挙げられる。出力装置としては、例えば、モニタ、プロジェクタ、プリンタ等が挙げられる。 The I / O unit 10e may include one or both of an input device and an output device. Examples of the input device include a keyboard, a mouse, a touch panel, and the like. Examples of the output device include a monitor, a projector, a printer and the like.

読取部10fは、記録媒体10hに記録されたデータやプログラムの情報を読み出すリーダの一例である。読取部10fは、記録媒体10hを接続可能又は挿入可能な接続端子又は装置を含んでよい。読取部10fとしては、例えば、USB(Universal Serial Bus)等に準拠したアダプタ、記録ディスクへのアクセスを行なうドライブ装置、SDカード等のフラッシュメモリへのアクセスを行なうカードリーダ等が挙げられる。なお、記録媒体10hにはプログラム10gが格納されてもよく、読取部10fが記録媒体10hからプログラム10gを読み出して記憶部10cに格納してもよい。 The reading unit 10f is an example of a reader that reads data and program information recorded on the recording medium 10h. The reading unit 10f may include a connection terminal or device to which the recording medium 10h can be connected or inserted. Examples of the reading unit 10f include an adapter compliant with USB (Universal Serial Bus) and the like, a drive device for accessing a recording disk, a card reader for accessing a flash memory such as an SD card, and the like. The program 10g may be stored in the recording medium 10h, or the reading unit 10f may read the program 10g from the recording medium 10h and store it in the storage unit 10c.

記録媒体10hとしては、例示的に、磁気/光ディスクやフラッシュメモリ等の非一時的なコンピュータ読取可能な記録媒体が挙げられる。磁気/光ディスクとしては、例示的に、フレキシブルディスク、CD(Compact Disc)、DVD(Digital Versatile Disc)、ブルーレイディスク、HVD(Holographic Versatile Disc)等が挙げられる。フラッシュメモリとしては、例示的に、USBメモリやSDカード等の半導体メモリが挙げられる。 Examples of the recording medium 10h include a non-temporary computer-readable recording medium such as a magnetic / optical disk or a flash memory. Examples of magnetic / optical disks include flexible discs, CDs (Compact Discs), DVDs (Digital Versatile Discs), Blu-ray discs, HVDs (Holographic Versatile Discs), and the like. Examples of the flash memory include semiconductor memories such as USB memory and SD card.

上述したコンピュータ10のHW構成は例示である。従って、コンピュータ10内でのHWの増減(例えば任意のブロックの追加や削除)、分割、任意の組み合わせでの統合、又は、バスの追加若しくは削除等は適宜行なわれてもよい。 The HW configuration of the computer 10 described above is an example. Therefore, the increase / decrease of HW (for example, addition or deletion of arbitrary blocks), division, integration in any combination, addition or deletion of buses, etc. in the computer 10 may be performed as appropriate.

〔1−3−2〕機能構成例
次に、図6を参照して、一実施形態に係る保全スケジュール作成装置(作成装置)1の機能構成例を説明する。作成装置1は、複数の設備の各々のメンテナンススケジュールを作成する。図6に示すように、作成装置1は、例示的に、メモリ部11、ネットワーク図作成部12、最大処理能力計算部13、作業間制約作成部14、スケジュール作成部15、及び、保全コスト決定部16を備えてよい。ブロック12〜16の機能の少なくとも一部は、プログラム10gに書き込まれ、プロセッサ10aがプログラム10gをメモリ10bに展開して実行することにより実現されてよい。
[1-3-2] Functional configuration example Next, a functional configuration example of the maintenance schedule creating device (creating device) 1 according to the embodiment will be described with reference to FIG. The creation device 1 creates a maintenance schedule for each of the plurality of facilities. As shown in FIG. 6, the creation device 1 exemplifies the memory unit 11, the network diagram creation unit 12, the maximum processing capacity calculation unit 13, the inter-work constraint creation unit 14, the schedule creation unit 15, and the maintenance cost determination. The unit 16 may be provided. At least a part of the functions of blocks 12 to 16 may be written in the program 10g and realized by the processor 10a expanding the program 10g into the memory 10b and executing it.

メモリ部11は、記憶部の一例であり、作成装置1が利用する種々の情報を格納してよい。メモリ部11は、例えば、コンピュータ10のメモリ10b、記憶部10c、及び記録媒体10hの少なくとも1つが有する記憶領域により実現されてよい。 The memory unit 11 is an example of a storage unit, and may store various information used by the creating device 1. The memory unit 11 may be realized by, for example, a storage area included in at least one of the memory 10b, the storage unit 10c, and the recording medium 10h of the computer 10.

メモリ部11は、図7及び図8に示す処理プロセス情報11a及び保全スケジュール情報11dを格納してよい。処理プロセス情報11a及び保全スケジュール情報11dの少なくとも一方は、プラントの管理に利用される既存の情報であってよく、作成装置1において、事前に取得(入力)され、メモリ部11に格納されてよい。 The memory unit 11 may store the processing process information 11a and the maintenance schedule information 11d shown in FIGS. 7 and 8. At least one of the processing process information 11a and the maintenance schedule information 11d may be existing information used for plant management, and may be acquired (input) in advance by the creation device 1 and stored in the memory unit 11. ..

処理プロセス情報11aは、複数の設備を利用するプロセスの各工程と、各工程間の相互関係と、各工程の処理能力とを定義する第1情報の一例である。例えば、処理プロセス情報11aは、投入された材料をいくつかの工程を経て製品に仕上げるプラントの処理プロセスと各工程の処理能力とを示す情報である。処理プロセスにおける1工程では、前工程から受け取った中間製品に対してその工程での所定の処理を施して次工程に渡す、という処理(流れ)が実施される。なお、処理プロセスは、製品ごとに定義される。 The processing process information 11a is an example of first information that defines each process of a process using a plurality of facilities, the mutual relationship between the processes, and the processing capacity of each process. For example, the processing process information 11a is information indicating the processing process of the plant that finishes the input material into a product through several steps and the processing capacity of each process. In one step in the processing process, a process (flow) is carried out in which the intermediate product received from the previous step is subjected to a predetermined process in that step and passed to the next step. The processing process is defined for each product.

図7は、処理プロセス情報11aの一例を示す図である。図7に示すように、処理プロセス情報11aは、例示的に、製品の識別子の一例である製品ID(Identifier)、工程の識別子の一例である工程ID、工程の名称である工程名、使用設備、処理能力、及び、次工程IDの項目を含んでよい。図7の例では、製品ID“ABC00123”の製品について定義された処理プロセス情報11aを示す。 FIG. 7 is a diagram showing an example of processing process information 11a. As shown in FIG. 7, the processing process information 11a is exemplified by a product ID (Identifier) which is an example of a product identifier, a process ID which is an example of a process identifier, a process name which is a process name, and equipment used. , Processing capacity, and next step ID may be included. In the example of FIG. 7, the processing process information 11a defined for the product with the product ID “ABC00123” is shown.

使用設備は、当該工程で使用される設備の識別子の一例である。当該工程で複数の設備が使用される場合、使用設備には複数の設備の識別子が設定されてよい。処理能力には、当該工程の処理能力を示す数値が設定されてよい。同一製品IDの工程間では、処理能力の時間単位及び単位系が揃えられる。次工程IDは、当該工程の次工程の識別子の一例である。次工程IDには、複数の次工程の識別子が設定されてもよく、この場合、次工程でプロセスが分岐し、並列処理されることを意味する。 The equipment used is an example of an identifier of the equipment used in the process. When a plurality of equipments are used in the process, identifiers of the plurality of equipments may be set in the equipments used. A numerical value indicating the processing capacity of the process may be set in the processing capacity. Time units and unit systems of processing capacity are arranged between processes having the same product ID. The next process ID is an example of an identifier of the next process of the process. A plurality of identifiers of the next process may be set in the next process ID, which means that the processes are branched and processed in parallel in the next process.

保全スケジュール情報11dは、複数のメンテナンス作業の各々の条件を定義する第2情報の一例であり、保全作業ごとに、保全スケジュールの決定に利用される種々の情報が設定された情報である。 The maintenance schedule information 11d is an example of the second information that defines the conditions for each of the plurality of maintenance operations, and is information in which various information used for determining the maintenance schedule is set for each maintenance operation.

図8は、保全スケジュール情報11dの一例を示す図である。図8に示すように、保全スケジュール情報11dは、例示的に、保全作業の識別子の一例である作業ID、作業内容、対象設備ID、担当者ID、作業日数、開始期限、完了期限、及び、作業開始予定日、の項目を含んでよい。 FIG. 8 is a diagram showing an example of maintenance schedule information 11d. As shown in FIG. 8, the maintenance schedule information 11d exemplifies the work ID, the work content, the target equipment ID, the person in charge ID, the number of work days, the start deadline, the completion deadline, and the maintenance work identifier. The item of scheduled work start date may be included.

作業内容は、保全作業の対象設備と保全作業の内容とが設定されてよい。対象設備IDは、保全作業の対象となる設備の識別子の一例である。対象設備IDは、処理プロセス情報11a(図7参照)の使用設備と共通のIDであってよい。担当者IDは、保全作業を実施する保全作業者の識別子の一例である。作業日数は、保全作業を開始してから完了するまでにかかる日数の一例である。 As the work content, the target equipment for the maintenance work and the content of the maintenance work may be set. The target equipment ID is an example of an identifier of the equipment that is the target of maintenance work. The target equipment ID may be an ID common to the equipment used in the processing process information 11a (see FIG. 7). The person in charge ID is an example of the identifier of the maintenance worker who carries out the maintenance work. The number of working days is an example of the number of days required from the start to the completion of maintenance work.

開始期限、完了期限は、保全作業を開始すべき日付、及び、作業を完了すべき日付の一例である。開始期限及び完了期限は、例えば、法令等により予め定められた期限であってもよく、保全作業の実行周期と過去の実行タイミング等に従って予め設定されてもよい。 The start deadline and the completion deadline are examples of the date on which the maintenance work should be started and the date on which the work should be completed. The start deadline and the completion deadline may be, for example, predetermined deadlines by laws and regulations, or may be preset according to the execution cycle of maintenance work and the past execution timing.

作業開始予定日は、保全作業を開始する予定日の一例である。作業開始予定日には、予め、仮の予定日(例えば、開始期限(+α)、又は、完了期限−作業日数(−α)等)が設定されてもよい。一実施形態では、後述する処理により、作業開始予定日が更新されることで、保全スケジュールが作成される。 The scheduled work start date is an example of the scheduled start date of maintenance work. A tentative scheduled date (for example, start deadline (+ α) or completion deadline-number of working days (-α)) may be set in advance as the scheduled work start date. In one embodiment, a maintenance schedule is created by updating the scheduled work start date by a process described later.

(作成装置1の動作例)
まず、図9を参照して、作成装置1による保全スケジュールの作成に係る全体の動作例を説明する。
(Operation example of creation device 1)
First, with reference to FIG. 9, an overall operation example related to the creation of the maintenance schedule by the creation device 1 will be described.

図9に例示するように、作成装置1は、処理プロセス情報11aから製品の流れのネットワーク図11bを作成する(ステップS1)。 As illustrated in FIG. 9, the creating apparatus 1 creates a network diagram 11b of the product flow from the processing process information 11a (step S1).

ここで、図7に示す処理プロセス情報11aは、前工程から次工程に向かう矢印で工程間を繋いだ有向グラフとして可視化すると、図10に例示するような処理のフローを記述していることがわかる。 Here, when the processing process information 11a shown in FIG. 7 is visualized as a directed graph connecting the processes with arrows from the previous process to the next process, it can be seen that the processing flow as illustrated in FIG. 10 is described. ..

図10では、図7に例示する製品ID“ABC00123”の処理プロセス情報11aを可視化した例を示す。図10に例示するように、図7において次工程IDに指定されていない工程PRは、最初の工程PR、すなわち工程A(ID:1)である。また、図7において次工程IDが複数指定の工程PRは、次工程で並列処理に分岐する工程PR、すなわち工程B(ID:2)である。さらに、図7において次工程IDとして複数指定されている工程PRは、合流する工程PR、すなわち工程E(ID:7)である。 FIG. 10 shows an example in which the processing process information 11a of the product ID “ABC00123” illustrated in FIG. 7 is visualized. As illustrated in FIG. 10, the process PR not designated as the next process ID in FIG. 7 is the first process PR, that is, process A (ID: 1). Further, the process PR in which a plurality of next process IDs are designated in FIG. 7 is a process PR that branches into parallel processing in the next process, that is, process B (ID: 2). Further, the process PRs designated as the next process IDs in FIG. 7 are the merging process PRs, that is, the process E (ID: 7).

図11は、図7に例示する製品ID“ABC00123”の処理プロセスのネットワーク図11bの一例を示す図である。製品の流れを示すネットワーク図11bは、以下の規則により作成されてよい。 FIG. 11 is a diagram showing an example of a network diagram 11b of the processing process of the product ID “ABC00123” illustrated in FIG. 7. The network diagram 11b showing the product flow may be created according to the following rules.

(i)各工程、すなわちノードNDが次工程に向いた矢印で接続される。
(ii)最初の工程(第1工程)の前に開始ノードNsが存在し、最終工程の後に終了ノードNeが存在する。
(iii)各矢印は、工程間を流れる製品の最大量の情報を持つ。なお、各辺を流れる最大量は、両端の工程の処理能力のうち小さい方と同等である。但し、開始ノードNsと第1工程との間の最大量は、第1工程の処理能力と等しく、終了ノードNeと最終工程との間の最大量は、最終工程の処理能力と等しい。
(I) Each process, that is, the node ND, is connected by an arrow pointing to the next process.
(Ii) The start node Ns exists before the first step (first step), and the end node Ne exists after the final step.
(Iii) Each arrow has information on the maximum amount of product flowing between processes. The maximum amount flowing on each side is equivalent to the smaller of the processing capacities of the processes at both ends. However, the maximum amount between the start node Ns and the first process is equal to the processing capacity of the first process, and the maximum amount between the end node Ne and the final process is equal to the processing capacity of the final process.

図9の説明に戻り、作成装置1は、ネットワーク図11bを利用して、停止設備がない時の処理能力(最大処理能力11c)(Pmax)を計算する(ステップS2)。 Returning to the description of FIG. 9, the creating apparatus 1 calculates the processing capacity (maximum processing capacity 11c) (Pmax) when there is no stop equipment using the network diagram 11b (step S2).

作成装置1は、変数jに1を設定する(ステップS3)。そして、作成装置1は、作業wjの対象設備を含む工程の処理能力を0として修正したネットワーク図11bを利用し、工程iと日程を重なるように保全作業を行なうとよい工程Xの情報を収集する(ステップS4)。iは、処理プロセス情報11aに設定された工程IDのうちのいずれかである。 The creation device 1 sets the variable j to 1 (step S3). Then, the creating device 1 collects information on the process X in which the maintenance work should be performed so that the schedule overlaps with the process i by using the network diagram 11b in which the processing capacity of the process including the target equipment of the work wj is corrected to 0. (Step S4). i is one of the process IDs set in the processing process information 11a.

ここで、複数の作業w1,・・・,wnを含む保全作業Wを、W(w1,・・・,wn)と表記する。なお、nは、1以上の整数であり、保全作業Wに含まれる作業数である。また、jは、1以上且つn以下の整数である。例えば、図8に示す保全スケジュール情報11dにおいて、対象設備ID:EQ01に対する保全作業をWとすると、対象設備ID:EQ01を対象とする3つ(n=3)の作業ID:T001〜T003が、それぞれ、w1〜w3に相当する。 Here, the maintenance work W including a plurality of works w1, ..., Wn is referred to as W (w1, ..., Wn). Note that n is an integer of 1 or more, and is the number of operations included in the maintenance work W. Further, j is an integer of 1 or more and n or less. For example, in the maintenance schedule information 11d shown in FIG. 8, assuming that the maintenance work for the target equipment ID: EQ01 is W, the three (n = 3) work IDs: T001 to T003 for the target equipment ID: EQ01 are Each corresponds to w1 to w3.

作成装置1は、変数kに1を設定する(ステップS5)。そして、作成装置1は、工程Xの使用設備に関する作業Y={y1,・・・,ym}を収集する(ステップS6)。なお、mは、1以上の整数であり、作業Yの数である。また、kは、1以上且つm以下の整数である。 The creation device 1 sets the variable k to 1 (step S5). Then, the creating apparatus 1 collects the work Y = {y1, ..., ym} related to the equipment used in the process X (step S6). Note that m is an integer of 1 or more and is the number of work Y. Further, k is an integer of 1 or more and m or less.

作成装置1は、保全スケジュール情報11dに基づき、作業wj及び作業ykの担当者が異なり、且つ、作業wjと作業ykとが重なった日程で実施可能か否かを判定する(ステップS7)。 Based on the maintenance schedule information 11d, the creation device 1 determines whether or not the person in charge of the work wj and the work yk is different and the work wj and the work yk can be carried out on the overlapping schedule (step S7).

ステップS7でNOであれば、処理がステップS9に移行する。ステップS7でYESであれば、保全スケジュール情報11dは、作業wjと作業ykとを重なった日程で実施するための作業開始予定日の条件(作業間制約11e)を収集し(ステップS8)、kが作業Yの数m未満か否かを判定する(ステップS9)。 If NO in step S7, the process proceeds to step S9. If YES in step S7, the maintenance schedule information 11d collects the condition of the scheduled work start date (inter-work constraint 11e) for carrying out the work wj and the work yk on the overlapping schedule (step S8), and k. Is less than a few meters of work Y (step S9).

ステップS9でYESであれば、作成装置1は、kに1を加算し(ステップS10)、処理がステップS7に移行する。ステップS9でNOであれば、作成装置1は、jが作業数n未満か否かを判定する(ステップS11)。 If YES in step S9, the creation device 1 adds 1 to k (step S10), and the process proceeds to step S7. If NO in step S9, the creation device 1 determines whether or not j is less than the number of operations n (step S11).

ステップS11でYESであれば、作成装置1は、jに1を加算し(ステップS12)、処理がステップS4に移行する。ステップS11でNOであれば、作成装置1は、各作業の開始予定日の決定(スケジュール自動作成)を行ない(ステップS13)、処理が終了する。 If YES in step S11, the creating device 1 adds 1 to j (step S12), and the process proceeds to step S4. If NO in step S11, the creation device 1 determines the scheduled start date of each work (automatic schedule creation) (step S13), and the process ends.

次に、上述した各ステップの処理を実行するブロック12〜16の構成例を説明する。 Next, a configuration example of blocks 12 to 16 for executing the processing of each step described above will be described.

(ネットワーク図作成部12の説明)
ネットワーク図作成部12は、メモリ部11に格納された処理プロセス情報11aに基づき、複数の設備を利用するプロセスを、各工程に流入又は流出する製品の数量を示すネットワーク図11bとして表現する作成部の一例である。また、ネットワーク図作成部12は、作成したネットワーク図11bをメモリ部11に格納してよい。
(Explanation of network diagram creation unit 12)
The network diagram creation unit 12 represents a process using a plurality of facilities as a network diagram 11b showing the quantity of products flowing into or out of each process based on the processing process information 11a stored in the memory unit 11. This is an example. Further, the network diagram creation unit 12 may store the created network diagram 11b in the memory unit 11.

以下、ネットワーク図作成部12による、処理プロセス情報11aに基づくネットワーク図11bの作成手法の一例を説明する。 Hereinafter, an example of a method for creating the network diagram 11b based on the processing process information 11a by the network diagram creating unit 12 will be described.

図12は、ネットワーク図作成部12による動作例を示すフローチャートであり、図13及び図14は、図11に示すネットワーク図11bの作成手法の一例を示す図である。図12〜図14に例示する処理は、図9のステップS1の処理に相当する。 FIG. 12 is a flowchart showing an operation example by the network diagram creating unit 12, and FIGS. 13 and 14 are diagrams showing an example of the method of creating the network diagram 11b shown in FIG. The processes illustrated in FIGS. 12 to 14 correspond to the processes in step S1 of FIG.

図12に例示するように、ネットワーク図作成部12は、開始ノードNs及び終了ノードNeを追加する(ステップS21;図13の手順A参照)。 As illustrated in FIG. 12, the network diagram creation unit 12 adds a start node Ns and an end node Ne (step S21; see procedure A in FIG. 13).

ネットワーク図作成部12は、処理プロセス情報11aにおいて、次工程がない工程をXとし(図13の手順Bでは、工程EをX={E}とし)、工程XのノードNDを追加して、追加したノードNDと終了ノードNeとを矢印で接続する(ステップS22)。また、ネットワーク図作成部12は、接続した各矢印の最大流量を、矢印の根元にあたる工程の処理能力(図13の手順Bでは工程Eの“30”)と等しい値に設定する(ステップS23)。 In the processing process information 11a, the network diagram creation unit 12 sets the process without the next process as X (in step B in FIG. 13, sets the process E as X = {E}), adds the node ND of the process X, and adds the node ND of the process X. The added node ND and the end node Ne are connected by an arrow (step S22). Further, the network diagram creating unit 12 sets the maximum flow rate of each connected arrow to a value equal to the processing capacity of the process corresponding to the base of the arrow (“30” in step E in step B in FIG. 13) (step S23). ..

ネットワーク図作成部12は、処理プロセス情報11aにおいて、工程Xのいずれか(図13の手順Cでは工程E)を次工程に持つ工程Yを探索し(ステップS24)、工程Yが存在するか否かを判定する(ステップS25)。 In the processing process information 11a, the network diagram creating unit 12 searches for a process Y having any of the processes X (process E in the procedure C in FIG. 13) as the next process (step S24), and whether or not the process Y exists. (Step S25).

ステップS25でYESであれば、ネットワーク図作成部12は、工程YのノードNDを追加し(図13の手順CではY={D1,D2}とし)、追加したノードNDと次工程(図13の手順Cでは工程E)のノードNDとを接続する(ステップS26)。 If YES in step S25, the network diagram creation unit 12 adds the node ND of step Y (Y = {D1, D2} in step C of FIG. 13), and the added node ND and the next step (FIG. 13). In step C of the above, the node ND of step E) is connected (step S26).

また、ネットワーク図作成部12は、接続した各矢印の最大流量を、両端の工程の処理能力のうちの小さい方と等しい値に設定する(ステップS27)。例えば、ネットワーク図作成部12は、図13の手順Cでは、工程D1→工程Eの矢印の最大流量を、工程D1の“10”と等しい値に設定し、工程D2→工程Eの矢印の最大流量を、工程D2の“15”と等しい値に設定する。 Further, the network diagram creating unit 12 sets the maximum flow rate of each connected arrow to a value equal to the smaller of the processing capacities of the processes at both ends (step S27). For example, in the procedure C of FIG. 13, the network diagram creating unit 12 sets the maximum flow rate of the arrow of the process D1 → the process E to a value equal to “10” of the process D1, and the maximum of the arrow of the process D2 → the process E. The flow rate is set to a value equal to “15” in step D2.

そして、ネットワーク図作成部12は、XにYを設定し(図13の手順DではX={D1,D2}とし)(ステップS28)、処理がステップS24に移行する。 Then, the network diagram creation unit 12 sets Y in X (X = {D1, D2} in the procedure D of FIG. 13) (step S28), and the process shifts to step S24.

図13の手順Dに続けて、ネットワーク図作成部12は、ステップS24〜S28のループにおいて以下の処理を実行する。 Following the procedure D in FIG. 13, the network diagram creating unit 12 executes the following processing in the loop of steps S24 to S28.

ネットワーク図作成部12は、図14の手順Eにおいて、工程X={D1,D2}のいずれかを次工程に持つ工程を探索し、Y={C1,C2}とする。そして、ネットワーク図作成部12は、工程YのノードNDを追加して、追加したノードNDと次工程とを接続する。また、ネットワーク図作成部12は、接続した各矢印の最大流量を、両端の工程の処理能力のうちの小さい方と等しい値に設定する。そして、ネットワーク図作成部12は、X=Y={C1,C2}とする。 In the procedure E of FIG. 14, the network diagram creating unit 12 searches for a process having any of the steps X = {D1, D2} as the next process, and sets Y = {C1, C2}. Then, the network diagram creation unit 12 adds the node ND of the process Y and connects the added node ND and the next process. Further, the network diagram creating unit 12 sets the maximum flow rate of each connected arrow to a value equal to the smaller of the processing capacities of the processes at both ends. Then, the network diagram creation unit 12 sets X = Y = {C1, C2}.

また、ネットワーク図作成部12は、図14の手順Fにおいて、工程X={C1,C2}のいずれかを次工程に持つ工程Y={B}を探索し、手順Eと同様の処理を実行する。さらに、ネットワーク図作成部12は、図14の手順Gにおいて、工程X={B}を次工程に持つ工程Y={A}を探索し、手順E又はFと同様の処理を実行する。 Further, in the procedure F of FIG. 14, the network diagram creating unit 12 searches for the process Y = {B} having any of the steps X = {C1, C2} in the next process, and executes the same process as the procedure E. To do. Further, in the procedure G of FIG. 14, the network diagram creating unit 12 searches for the process Y = {A} having the process X = {B} as the next process, and executes the same process as the procedure E or F.

次いで、ネットワーク図作成部12は、図14の手順Hにおいて、工程X={A}を次工程に持つ工程Yを探索するが、このような工程Yは存在しない。すなわち、図12のステップS25でNOとなる。 Next, in the procedure H of FIG. 14, the network diagram creating unit 12 searches for a step Y having the step X = {A} as the next step, but such a step Y does not exist. That is, it becomes NO in step S25 of FIG.

この場合、ネットワーク図作成部12は、開始ノードNsと工程X(図14の手順Iでは工程A)との間を工程Xに向いた矢印で接続する(ステップS29)。そして、ネットワーク図作成部12は、接続した各矢印の最大流量を、矢印の先にある工程Xの処理能力(図14の手順Iでは工程Aの“30”)と等しい値に設定し(ステップS30)、現在のネットワーク図11bをメモリ部11に格納し、処理が終了する。 In this case, the network diagram creation unit 12 connects the start node Ns and the process X (process A in the procedure I of FIG. 14) with an arrow pointing toward the process X (step S29). Then, the network diagram creating unit 12 sets the maximum flow rate of each connected arrow to a value equal to the processing capacity of the process X at the tip of the arrow (“30” in the process A in the procedure I of FIG. 14) (step). S30), the current network diagram 11b is stored in the memory unit 11, and the process ends.

(最大処理能力計算部13の説明)
最大処理能力計算部13は、ネットワーク図作成部12が作成したネットワーク図11bにおいて、開始ノードNsから終了ノードNeに製品を流した場合の終了ノードNeに流れ込む最大流量を算出する。換言すれば、最大処理能力計算部13は、処理プロセス情報11aに基づき、設備停止のない状態でのプロセスの第1処理能力を取得する第1取得部の一例である。
(Explanation of maximum processing capacity calculation unit 13)
The maximum processing capacity calculation unit 13 calculates the maximum flow rate flowing into the end node Ne when the product is flowed from the start node Ns to the end node Ne in the network diagram 11b created by the network diagram creation unit 12. In other words, the maximum processing capacity calculation unit 13 is an example of a first acquisition unit that acquires the first processing capacity of the process without equipment stoppage based on the processing process information 11a.

また、最大処理能力計算部13は、算出した最大流量を、処理プロセスの最大処理能力11c(Pmax)としてメモリ部11に格納してよい。 Further, the maximum processing capacity calculation unit 13 may store the calculated maximum flow rate in the memory unit 11 as the maximum processing capacity 11c (Pmax) of the processing process.

ネットワーク図11bを流れる最大流量は、例えば、フォード・ファルカーソンのアルゴリズム等の増加路アルゴリズム等によって計算可能である。 The maximum flow rate flowing through the network diagram 11b can be calculated by, for example, an increasing path algorithm such as the Ford-Fulkerson algorithm.

以下、最大処理能力計算部13による、最大処理能力11cの計算手法の一例を説明する。 Hereinafter, an example of the calculation method of the maximum processing capacity 11c by the maximum processing capacity calculation unit 13 will be described.

図15は、最大処理能力計算部13による動作例を示すフローチャートであり、図16及び図17は、図11に示すネットワーク図11bに基づく最大処理能力11cの計算手法の一例を示す図である。図15〜図17に例示する処理は、図9のステップS2の処理に相当する。 FIG. 15 is a flowchart showing an operation example by the maximum processing capacity calculation unit 13, and FIGS. 16 and 17 are diagrams showing an example of a calculation method of the maximum processing capacity 11c based on the network FIG. 11b shown in FIG. The processes illustrated in FIGS. 15 to 17 correspond to the processes in step S2 of FIG.

図15に例示するように、最大処理能力計算部13は、図11に示すネットワーク図11bの現在のフローを、全ての矢印の流量=0とする(ステップS31;図16の手順A参照)。 As illustrated in FIG. 15, the maximum processing capacity calculation unit 13 sets the current flow of the network FIG. 11b shown in FIG. 11 to the flow rate of all arrows = 0 (step S31; see procedure A in FIG. 16).

最大処理能力計算部13は、現在のフローに対する余剰流量を付した逆向きの矢印を記載したネットワーク(残余ネットワーク)を作成する(ステップS32;図16の手順Bの破線矢印参照)。 The maximum processing capacity calculation unit 13 creates a network (residual network) in which a reverse arrow with a surplus flow rate with respect to the current flow is described (step S32; see the broken line arrow in step B in FIG. 16).

次いで、最大処理能力計算部13は、残余ネットワークにおいて、終了ノードNeから開始ノードNsにたどり着く経路を探索する(ステップS33;図16の手順Cの一点鎖線矢印参照)。 Next, the maximum processing capacity calculation unit 13 searches for a route from the end node Ne to the start node Ns in the residual network (step S33; see the alternate long and short dash arrow in step C in FIG. 16).

最大処理能力計算部13は、経路が存在するか否かを判定する(ステップS34)。ステップS34でYESの場合、最大処理能力計算部13は、終了ノードNeから開始ノードNsにたどり着く経路を1つ採用し、当該経路を用いて現在のフローを更新し(ステップS35;図16の手順D参照)、処理がステップS32に移行する。図16の手順Dでは、最大処理能力計算部13は、経路上の最小流量分である“10”を残余ネットワークと逆向きに流す例を示す。 The maximum processing capacity calculation unit 13 determines whether or not a route exists (step S34). If YES in step S34, the maximum processing capacity calculation unit 13 adopts one route from the end node Ne to the start node Ns, and updates the current flow using the route (step S35; procedure of FIG. 16). D), the process proceeds to step S32. In procedure D of FIG. 16, the maximum processing capacity calculation unit 13 shows an example in which “10”, which is the minimum flow rate on the path, is flowed in the direction opposite to that of the residual network.

図16の手順Dに続けて、最大処理能力計算部13は、ステップS32〜S35のループにおいて以下の処理を実行する。 Following the procedure D in FIG. 16, the maximum processing capacity calculation unit 13 executes the following processing in the loop of steps S32 to S35.

最大処理能力計算部13は、図17の手順Eにおいて、再度、残余ネットワークを作成し、終了ノードNeから開始ノードNsにたどり着く経路(一点鎖線参照)を探索する。そして、最大処理能力計算部13は、図17の手順Fにおいて、図16の手順Cの経路とは逆向きに流量“10”を流して、現在のフローを更新する。なお、最大処理能力計算部13は、既に流量“10”が設定済みの矢印(例えば開始ノードNs〜工程B、及び、工程E〜終了ノードNe)に対しては、手順Eの探索で得た流量“10”を加算する。 In the procedure E of FIG. 17, the maximum processing capacity calculation unit 13 creates the residual network again and searches for a route (see the alternate long and short dash line) from the end node Ne to the start node Ns. Then, in the procedure F of FIG. 17, the maximum processing capacity calculation unit 13 updates the current flow by flowing the flow rate “10” in the direction opposite to the path of the procedure C of FIG. The maximum processing capacity calculation unit 13 obtained the arrows (for example, start node Ns to process B and process E to end node Ne) for which the flow rate “10” has already been set by searching the procedure E. Add the flow rate "10".

次いで、最大処理能力計算部13は、図17の手順Gにおいて、再度、残余ネットワークを作成するが、終了ノードNeから開始ノードNsにたどり着く経路が存在しない(一点鎖線参照)。すなわち、図15のステップS34でNOとなる。 Next, the maximum processing capacity calculation unit 13 creates the residual network again in the procedure G of FIG. 17, but there is no route from the end node Ne to the start node Ns (see the alternate long and short dash line). That is, it becomes NO in step S34 of FIG.

この場合、現在のフローが最大流路であり、終了ノードNeに入る流量(図17の手順Hでは“20”)が最大流量となる。従って、最大処理能力計算部13は、最大流量をこのプロセスの最大処理能力11c(Pmax)に決定し(ステップS36;図17の手順H参照)、最大処理能力11cをメモリ部11に格納し、処理が終了する。 In this case, the current flow is the maximum flow path, and the flow rate entering the end node Ne (“20” in procedure H in FIG. 17) is the maximum flow rate. Therefore, the maximum processing capacity calculation unit 13 determines the maximum flow rate to be the maximum processing capacity 11c (Pmax) of this process (step S36; see procedure H in FIG. 17), stores the maximum processing capacity 11c in the memory unit 11, and stores the maximum processing capacity 11c in the memory unit 11. The process ends.

(作業間制約作成部14の説明)
作業間制約作成部14は、保全スケジュール情報11dに基づき、メンテナンス作業の開始日に関する制約を、重なる日程で実行可能なメンテナンス作業のペアごとに作成する制約作成部の一例である。
(Explanation of Inter-Work Constraint Creation Unit 14)
The inter-work constraint creation unit 14 is an example of a constraint creation unit that creates a constraint on the start date of the maintenance work for each pair of maintenance work that can be executed on the overlapping schedule based on the maintenance schedule information 11d.

例えば、作業間制約作成部14は、処理プロセス情報11a、ネットワーク図11b、及び保全スケジュール情報11dに基づいて、2つの作業の組み合わせを抽出し、作業間の作業開始日に関する作業間制約11eを生成してよい。 For example, the inter-work constraint creation unit 14 extracts a combination of two works based on the processing process information 11a, the network diagram 11b, and the maintenance schedule information 11d, and generates the inter-work constraint 11e regarding the work start date between the works. You can do it.

抽出される2つの作業の組み合わせは、以下で説明する、「工程X」及び「保全作業Y」の収集処理と、「作業wj」及び「作業yk」の実行可否確認処理と、により決定されてよい。 The combination of the two extracted works is determined by the collection process of "process X" and "maintenance work Y" and the execution feasibility confirmation process of "work wj" and "work yk" described below. Good.

(収集処理)
以下、作業間制約作成部14による、収集処理の一例を説明する。図18は、作業間制約作成部14による収集処理の一例を示す図である。図18に例示する処理は、図9のステップS3〜S6、S11、S12の処理に対応する。
(Collection process)
Hereinafter, an example of the collection process by the inter-work constraint creation unit 14 will be described. FIG. 18 is a diagram showing an example of collection processing by the inter-work constraint creation unit 14. The process illustrated in FIG. 18 corresponds to the process of steps S3 to S6, S11, and S12 in FIG.

作業間制約作成部14は、作業wjを実施する場合に、作業wjと重なる日程で作業すると機会損失コストの削減につながる工程Xを収集する。例えば、作業間制約作成部14は、工程iの処理能力を0として修正したネットワーク図11bを利用して、処理能力の計算を実施する。 When the work wj is carried out, the work-to-work constraint creation unit 14 collects the process X that leads to a reduction in the opportunity loss cost if the work is performed on a schedule that overlaps with the work wj. For example, the inter-working constraint creation unit 14 calculates the processing capacity by using the network diagram 11b modified by setting the processing capacity of the process i to 0.

一例として、作業間制約作成部14は、図18の手順Aにおいて、作業wjの対象設備が設置された工程C1の処理能力を0としたときのネットワーク図11bを作成する。 As an example, the inter-work constraint creation unit 14 creates a network diagram 11b when the processing capacity of the process C1 in which the target equipment of the work wj is installed is set to 0 in the procedure A of FIG.

そして、作業間制約作成部14は、図18の手順Bにおいて、図15〜図17を参照して説明した最大処理能力11cの計算と同様の手法により、ネットワークの最大処理能力を計算する(一点鎖線参照)。 Then, the inter-work constraint creation unit 14 calculates the maximum processing capacity of the network in the procedure B of FIG. 18 by the same method as the calculation of the maximum processing capacity 11c described with reference to FIGS. 15 to 17 (one point). See chain line).

このとき、処理量が0となる工程Xは、設備が停止しているのと変わらない。つまり、処理量が0となる工程Xは、工程iと重なる日程で作業を行なうことで、別日に実施する場合より機会損失コストを削減できることを意味する。 At this time, the process X in which the processing amount becomes 0 is the same as when the equipment is stopped. That is, the process X in which the processing amount becomes 0 means that the opportunity loss cost can be reduced as compared with the case where the process X is performed on another day by performing the work on the schedule overlapping with the process i.

そこで、作業間制約作成部14は、処理プロセス情報11a及び保全スケジュール情報11dを参照して、工程Xの使用設備に関する作業Y={y1,・・・ym}を収集する。例えば、図18の手順Cに示すように、作業間制約作成部14は、入出力が0となる工程を工程Xとして収集する。 Therefore, the inter-work constraint creation unit 14 collects the work Y = {y1, ... ym} related to the equipment used in the process X with reference to the processing process information 11a and the maintenance schedule information 11d. For example, as shown in procedure C of FIG. 18, the inter-work constraint creation unit 14 collects the process in which the input / output becomes 0 as the process X.

図18の例では、使用設備:EQ04−1を使用する工程C1を停止した場合に、使用設備:EQ05を使用する工程D1の入出力が0となる。従って、作業間制約作成部14は、工程D1を、工程C1と日程が重なるように作業するとよい工程Xと判定し、このような情報を収集する。 In the example of FIG. 18, when the process C1 using the equipment used: EQ04-1 is stopped, the input / output of the process D1 using the equipment used: EQ05 becomes 0. Therefore, the inter-work constraint creation unit 14 determines that the process D1 is a process X in which the work should be performed so that the schedule overlaps with the process C1, and collects such information.

(実行可否確認処理)
以下、作業間制約作成部14による、実行可否確認処理の一例を説明する。図19は、作業間制約作成部14による実行可否確認処理の一例を示す図であり、図20は、作業間制約11eの一例を示す図である。図19及び図20に例示する処理は、図9のステップS7〜S10の処理に対応する。
(Executability confirmation process)
Hereinafter, an example of the execution feasibility confirmation process by the inter-work constraint creation unit 14 will be described. FIG. 19 is a diagram showing an example of execution feasibility confirmation processing by the inter-work constraint creation unit 14, and FIG. 20 is a diagram showing an example of the inter-work constraint 11e. The processes illustrated in FIGS. 19 and 20 correspond to the processes of steps S7 to S10 of FIG.

作業間制約作成部14は、収集処理において収集した、作業Wの情報と、工程Xの使用設備に関する作業Yの情報とに基づき、作業wjと作業ykの担当者が異なり、且つ、重なった日程で実施可能か否かを、保全スケジュール情報11dを基に確認する。 The inter-work constraint creation unit 14 has different and overlapping schedules for work wj and work yk based on the information of work W collected in the collection process and the information of work Y regarding the equipment used in process X. It is confirmed based on the maintenance schedule information 11d whether or not it can be carried out in.

そして、作業間制約作成部14は、重なる日程で実行可能であれば、作業間の作業開始予定日に関する制約(作業間制約11e)を生成する。 Then, the inter-work constraint creation unit 14 generates a constraint (inter-work constraint 11e) regarding the scheduled work start date between works if it can be executed on the overlapping schedule.

例えば、図19に示すように、作業間制約作成部14は、図8に示す保全スケジュール情報11dにおいて、作業w1を作業ID:T006とし、作業y1を作業ID:T008とした場合に、担当者IDが一致するか否かを判定する。図19の例では、担当者IDがそれぞれW003及びW004であるため、作業間制約作成部14は、担当者が異なると判定する。 For example, as shown in FIG. 19, the inter-work constraint creation unit 14 is in charge of the maintenance schedule information 11d shown in FIG. 8 when the work w1 is set to the work ID: T006 and the work y1 is set to the work ID: T008. It is determined whether or not the IDs match. In the example of FIG. 19, since the person in charge IDs are W003 and W004, respectively, the inter-working constraint creation unit 14 determines that the person in charge is different.

また、作業間制約作成部14は、図19に示すように、作業T006及びT008の開始日をS6及びS8とし、作業T006及びT008の作業日数をd6及びd8とした場合に、符号A又はBで示すように日程が重なるか否かを判定する。 Further, as shown in FIG. 19, the inter-work constraint creation unit 14 sets the start dates of the work T006 and T008 to S6 and S8, and sets the number of work days of the work T006 and T008 to d6 and d8, and sets the reference numerals A or B. As shown in, it is determined whether or not the schedules overlap.

図19の符号Aでは、作業間制約作成部14は、作業wjの開始日が、作業ykの開始日と完了日との間であれば日程が重なると判定してよい。或いは、図19の符号Bでは、作業間制約作成部14は、作業ykの開始日が、作業wjの開始日と完了日との間であれば日程が重なると判定してよい。符号A及びBは、互いに逆のパターンである。 In reference numeral A of FIG. 19, the inter-work constraint creation unit 14 may determine that the schedules overlap if the start date of the work wj is between the start date and the completion date of the work yk. Alternatively, in reference numeral B of FIG. 19, the inter-work constraint creation unit 14 may determine that the schedules overlap if the start date of the work yk is between the start date and the completion date of the work wj. Reference numerals A and B are opposite patterns to each other.

作業間制約作成部14は、図20に例示するように、作業間制約11eを作成し、メモリ部11に格納してよい。作業間制約11eは、2つの作業の組み合わせごとの制約の有無を示すテーブル(マトリクス)11e−1と、制約のある2つの作業の組み合わせごとに作成された作業間制約11e−2(一例として、S8≦S6≦S8+d8)とを含んでよい。 As illustrated in FIG. 20, the inter-work constraint creation unit 14 may create the inter-work constraint 11e and store it in the memory unit 11. The inter-work constraint 11e includes a table (matrix) 11e-1 showing the presence or absence of a constraint for each combination of two tasks, and an inter-work constraint 11e-2 created for each combination of two constrained tasks (as an example). S8 ≦ S6 ≦ S8 + d8) may be included.

以上のように、実行可否確認処理では、重なる日程で実行可能なメンテナンス作業のペアを特定でき、収集処理では、日程をずらして実行させる場合よりも機会損失コストが減少するメンテナンス作業のペアを特定できる。このように、作業間制約作成部14は、重なる日程で実行可能なメンテナンス作業のペアであって、日程をずらして実行させる場合よりも機会損失コストが減少するメンテナンス作業のペアを複数抽出するのである。 As described above, in the execution enablement confirmation process, the pair of maintenance work that can be executed on the overlapping schedule can be specified, and in the collection process, the pair of maintenance work whose opportunity loss cost is reduced as compared with the case where the schedule is staggered can be specified. it can. In this way, the inter-work constraint creation unit 14 extracts a plurality of maintenance work pairs that can be executed on overlapping schedules and whose opportunity loss cost is reduced as compared with the case where the schedules are staggered. is there.

なお、上述した例では、作業間制約作成部14は、担当者の一致を判定するものとしたが、これに限定されるものではない。例えば、作業間制約作成部14は、担当者の一致に加えて、又は、代えて、作業の実施に用いられる、工具や設備(クレーン等)等の備品が、作業wj及び作業yk間で少なくとも一部が一致するか否かを判定してもよい。 In the above-mentioned example, the inter-work constraint creation unit 14 determines the match of the person in charge, but the present invention is not limited to this. For example, in the inter-work constraint creation unit 14, in addition to or instead of the agreement of the person in charge, equipment such as tools and equipment (crane, etc.) used for carrying out the work is at least between the work wj and the work yk. It may be determined whether or not the parts match.

(スケジュール作成部15の説明)
スケジュール作成部15は、作業間制約作成部14が作成した作業間制約11eの、2つの作業の組み合わせごとの有効及び無効を切り替えながら、スケジュール作成と評価とを繰り返し実行し、保全コストが小さくなる保全スケジュールを作成する。なお、スケジュール作成部15による保全スケジュールの作成は、例えば、保全スケジュール情報11dの「作業開始予定日」を更新することであってもよい。
(Explanation of schedule creation unit 15)
The schedule creation unit 15 repeatedly executes schedule creation and evaluation while switching between valid and invalid for each combination of the two works of the inter-work constraint 11e created by the inter-work constraint creation unit 14, and the maintenance cost is reduced. Create a maintenance schedule. The maintenance schedule created by the schedule creation unit 15 may be, for example, updating the "scheduled work start date" of the maintenance schedule information 11d.

換言すれば、スケジュール作成部15は、複数の制約の各々の有効又は無効を切り替えながら、メンテナンススケジュールの作成と、メンテナンスコストの算出とを実行する実行部の一例である。 In other words, the schedule creation unit 15 is an example of an execution unit that creates a maintenance schedule and calculates a maintenance cost while switching the validity or invalidity of each of the plurality of constraints.

スケジュール作成部15は、例えば、タブー探索、GA(Genetic Algorithm)等のメタヒューリスティクスを利用した最適化手法と同様に、現在の状態を少し変更すること(近傍探索)を繰り返して、最適解(最適な作業開始日)を探索する。 The schedule creation unit 15 repeats changing the current state a little (neighborhood search) in the same manner as the optimization method using metaheuristics such as tabu search and GA (Genetic Algorithm), and repeats the optimum solution (neighborhood search). Search for the optimal work start date).

以下、スケジュール作成部15による保全スケジュールの作成処理の一例を説明する。図21は、スケジュール作成部15による保全スケジュールの作成処理の一例を示すフローチャートであり、図22〜図24は、保全スケジュール作成手法の一例を示す図である。図21〜図24に例示する処理は、図9のステップS13の処理の少なくとも一部に対応する。 Hereinafter, an example of the maintenance schedule creation process by the schedule creation unit 15 will be described. FIG. 21 is a flowchart showing an example of the maintenance schedule creation process by the schedule creation unit 15, and FIGS. 22 to 24 are diagrams showing an example of the maintenance schedule creation method. The processes illustrated in FIGS. 21 to 24 correspond to at least a part of the processes in step S13 of FIG.

図21に例示するように、スケジュール作成部15は、作業間制約11eを全て無効化し(ステップS41)、全作業の開始予定日の初期値を作成、例えば保全スケジュール情報11dの「作業開始予定日」に初期値を設定する(ステップS42)。 As illustrated in FIG. 21, the schedule creation unit 15 invalidates all the inter-work constraint 11e (step S41) and creates an initial value of the scheduled start date of all the work. For example, the “scheduled work start date” of the maintenance schedule information 11d. The initial value is set in (step S42).

スケジュール作成部15は、後述する保全コスト決定部16により計算される、現在のスケジュールの保全コストを最良案とし(ステップS43)、反復回数I(Iは1以上の整数)に0を設定する(ステップS44)。 The schedule creation unit 15 sets the maintenance cost of the current schedule, which is calculated by the maintenance cost determination unit 16 described later, as the best plan (step S43), and sets 0 to the number of iterations I (I is an integer of 1 or more) (I is an integer of 1 or more). Step S44).

スケジュール作成部15は、作業開始予定日の割合を少し変更し(ステップS45)、制約違反の数が変更前よりも多いか否かを判定する(ステップS46)。 The schedule creation unit 15 slightly changes the ratio of the scheduled work start dates (step S45), and determines whether or not the number of constraint violations is larger than that before the change (step S46).

ステップS46でYESの場合、スケジュール作成部15は、作業開始予定日の割合を変更前の状態に戻し(ステップS47)、処理がステップS50に移行する。 If YES in step S46, the schedule creation unit 15 returns the ratio of the scheduled work start date to the state before the change (step S47), and the process shifts to step S50.

ステップS46でNOの場合、後述する保全コスト決定部16により、スケジュールの保全コストが計算され(ステップS48)、スケジュール作成部15は、保全コストが変更前よりも小さいか否かを判定する(ステップS49)。 If NO in step S46, the maintenance cost determination unit 16 described later calculates the maintenance cost of the schedule (step S48), and the schedule creation unit 15 determines whether or not the maintenance cost is smaller than that before the change (step). S49).

ステップS49でNOの場合、処理がステップS47に移行する。一方、ステップS49でYESの場合、スケジュール作成部15は、Iが反復回数上限Mよりも小さいか否かを判定する(ステップS50)。 If NO in step S49, the process proceeds to step S47. On the other hand, if YES in step S49, the schedule creation unit 15 determines whether or not I is smaller than the upper limit M of the number of iterations (step S50).

ステップS50でYESの場合、スケジュール作成部15は、Iに1を加算し(ステップS51)、処理がステップS45に移行する。 If YES in step S50, the schedule creation unit 15 adds 1 to I (step S51), and the process shifts to step S45.

なお、図21に示すステップS44〜S51の処理は、スケジュール作成部15による近傍探索の処理であり、既知の手法により実現されてもよい。 The processes of steps S44 to S51 shown in FIG. 21 are neighborhood search processes by the schedule creation unit 15, and may be realized by a known method.

ステップS50でNOの場合、スケジュール作成部15は、現在案の保全コストが最良案よりも小さいか否かを判定する(ステップS52)。 If NO in step S50, the schedule creation unit 15 determines whether or not the maintenance cost of the current plan is smaller than the best plan (step S52).

ステップS52でNOの場合、スケジュール作成部15は、最後に追加した作業間制約11eがあればそれを無効化する(ステップS53)。そして、スケジュール作成部15は、スケジュールで、いずれの作業とも重なる日程で実行されない作業に関する作業間制約11eのうち、無効になっているものを収集する(ステップS54)。 If NO in step S52, the schedule creation unit 15 invalidates the last added work-to-work constraint 11e (step S53). Then, the schedule creation unit 15 collects invalid work-to-work constraints 11e relating to work that is not executed on a schedule that overlaps with any work in the schedule (step S54).

例えば、スケジュール作成部15は、図22の手順Aのスケジュールに示す、いずれの作業とも重なる日程で実行されない作業(実線の円で囲った作業)を抽出する。また、スケジュール作成部15は、抽出された作業に関する作業間制約11eで無効になっている制約(図22の手順Bのテーブル11e−1において黒丸で示される制約)を収集(特定)する。 For example, the schedule creation unit 15 extracts the work (work surrounded by a solid line circle) that is not executed on a schedule that overlaps with any of the work shown in the schedule of procedure A in FIG. Further, the schedule creation unit 15 collects (specifies) the constraint invalidated by the inter-work constraint 11e related to the extracted work (the constraint indicated by the black circle in the table 11e-1 of the procedure B in FIG. 22).

スケジュール作成部15は、収集した制約を1つ以上有効化し(ステップS55)、新規に有効化した制約と矛盾する作業間制約11eを無効化して(ステップS56)、処理がステップS44に移行する。 The schedule creation unit 15 validates one or more of the collected constraints (step S55), invalidates the inter-work constraint 11e that contradicts the newly enabled constraint (step S56), and shifts the process to step S44.

例えば、スケジュール作成部15は、図23の手順Cに示すように、収集した作業間制約11eを、一様確率分布に従い1つ選択して有効化する。手順Cの例では、スケジュール作成部15は、作業T010とT002とを重ねる制約を選択して有効化する。 For example, as shown in procedure C of FIG. 23, the schedule creation unit 15 selects and activates one of the collected inter-work constraints 11e according to a uniform probability distribution. In the example of procedure C, the schedule creation unit 15 selects and activates the constraint of overlapping the work T010 and T002.

これにより、スケジュール作成部15は、再度、近傍探索(局所探索)を実行してスケジュール生成を行なうと、例えば、図23の手順Dに示すように、実線の円で囲った期間の機会損失コストを削減することができる。 As a result, when the schedule creation unit 15 executes the neighborhood search (local search) again to generate the schedule, for example, as shown in step D of FIG. 23, the opportunity loss cost during the period surrounded by the solid line circle. Can be reduced.

なお、作業間制約11eを追加しすぎると、充足不可能な状態が発生することがある。新規に有効化した作業間制約11eと、既に有効な作業間制約11eとに矛盾が生じた場合、スケジュール作成部15は、図21のステップS56に示すように、矛盾が生じた、既に有効な作業間制約11eを無効化する。 If the inter-working constraint 11e is added too much, an unsatisfactory state may occur. When there is a contradiction between the newly activated inter-work constraint 11e and the already valid inter-work constraint 11e, the schedule creation unit 15 causes a contradiction and is already valid as shown in step S56 of FIG. The inter-work constraint 11e is invalidated.

例えば、スケジュール作成部15は、新規に有効化した作業間制約Xに関する2作業と関連し、且つ、既に有効である作業間制約Yを全て抽出する。そして、スケジュール作成部15は、制約Xと制約Yとで数式処理を行ない、制約充足が可能か否かを数式処理によって判定する。制約充足できない場合、スケジュール作成部15は、制約Yを無効化する。 For example, the schedule creation unit 15 extracts all the work-to-work constraints Y that are related to and already valid for the two works related to the newly activated work-to-work constraint X. Then, the schedule creation unit 15 performs mathematical expression processing on the constraint X and the constraint Y, and determines whether or not the constraint can be satisfied by the mathematical expression processing. If the constraint cannot be satisfied, the schedule creation unit 15 invalidates the constraint Y.

例えば、図24の手順Eに示すように、既に有効な作業間制約として、下記の(1)及び(2)が存在し、下記の(3)を新規に有効化した場合を想定する。 For example, as shown in procedure E of FIG. 24, it is assumed that the following (1) and (2) exist as already effective inter-work constraints, and the following (3) is newly enabled.

(1) S2≦S10≦ S2+ d2
(2)S10≦ S2≦S10+d10
(3) S9≦ S2≦ S9+ d9
(1) S2 ≦ S10 ≦ S2 + d2
(2) S10 ≦ S2 ≦ S10 + d10
(3) S9 ≤ S2 ≤ S9 + d9

この場合、T2及びT9に関する制約について、数式処理すると、S9≦S2=S10≦S9+d9となり、作業者が同じ作業T9及びT10を同時実行する必要が生じ、作業間制約11eに矛盾が発生する。 In this case, when the constraints related to T2 and T9 are processed by mathematical formulas, S9 ≦ S2 = S10 ≦ S9 + d9, and the worker needs to execute the same work T9 and T10 at the same time, which causes a contradiction in the work-to-work constraint 11e.

そこで、手順Eの例において、スケジュール作成部15は、作業間制約(1)及び(2)を無効化する。 Therefore, in the example of the procedure E, the schedule creation unit 15 invalidates the inter-work restrictions (1) and (2).

図21の説明に戻り、ステップS52でYESの場合、スケジュール作成部15は、現在案を最良案として採用し(ステップS58)、判定終了か否かを判定する(ステップS59)。判定終了か否かの条件としては、例えば、スケジュール作成処理の実行回数(ステップS59の判定回数でもよい)が所定の閾値以上となった場合や、保全コストの変化量が所定の閾値以下になった場合等が挙げられる。 Returning to the description of FIG. 21, if YES in step S52, the schedule creation unit 15 adopts the current plan as the best plan (step S58) and determines whether or not the determination is completed (step S59). As a condition for whether or not the determination is completed, for example, when the number of times the schedule creation process is executed (the number of determinations in step S59 may be) exceeds a predetermined threshold value, or the amount of change in the maintenance cost becomes equal to or less than a predetermined threshold value. For example.

ステップS59でNOの場合、処理がステップS54に移行する。一方、ステップS59でYESの場合、処理が終了する。 If NO in step S59, the process proceeds to step S54. On the other hand, if YES in step S59, the process ends.

なお、図21に示すステップS53〜S56の処理は、保全スケジュール作成に特化した探索空間の修正処理(ステップS60)である。 The process of steps S53 to S56 shown in FIG. 21 is a search space modification process (step S60) specialized for creating a maintenance schedule.

(保全コスト決定部16の説明)
保全コスト決定部16は、第1処理能力(最大処理能力11c)と、複数の設備のうちのいずれかの設備停止状態でのプロセスの第2処理能力とに基づき、メンテナンススケジュールのメンテナンスコストを算出する算出部の一例である。
(Explanation of maintenance cost determination unit 16)
The maintenance cost determination unit 16 calculates the maintenance cost of the maintenance schedule based on the first processing capacity (maximum processing capacity 11c) and the second processing capacity of the process when one of the plurality of facilities is stopped. This is an example of a calculation unit to be used.

保全コスト決定部16は、図6に示すように、例示的に、処理能力計算部16a、機会損失コスト計算部16b、及び、保全コスト計算部16cの機能を備えてよい。 As shown in FIG. 6, the maintenance cost determination unit 16 may optionally include the functions of the processing capacity calculation unit 16a, the opportunity loss cost calculation unit 16b, and the maintenance cost calculation unit 16c.

処理能力計算部16aは、処理プロセス情報11aに基づき、複数の設備のうちのいずれかの設備停止状態でのプロセスの第2処理能力を取得する第2取得部の一例であり、設備停止時の処理能力(第2処理能力)を計算する。 The processing capacity calculation unit 16a is an example of a second acquisition unit that acquires the second processing capacity of the process in the equipment stop state of any one of the plurality of equipments based on the processing process information 11a, and is an example of the second acquisition unit when the equipment is stopped. Calculate the processing capacity (second processing capacity).

機会損失コスト計算部16bは、最大処理能力と、設備停止時の処理能力との差分に基づき、日ごとの機会損失コストを計算する。 The opportunity loss cost calculation unit 16b calculates the daily opportunity loss cost based on the difference between the maximum processing capacity and the processing capacity when the equipment is stopped.

保全コスト計算部16cは、日々の機会損失コストの総和から、作成した保全スケジュールの保全コストを計算する。 The maintenance cost calculation unit 16c calculates the maintenance cost of the created maintenance schedule from the sum of the daily opportunity loss costs.

以下、保全コスト決定部16による保全コストの決定(計算)処理の一例を説明する。なお、以下の説明では、保全スケジュールに示された期間の全日付を、D={d1,・・・dx}(xは1以上の整数)で示す。 Hereinafter, an example of the maintenance cost determination (calculation) process by the maintenance cost determination unit 16 will be described. In the following description, all dates of the period indicated in the maintenance schedule are indicated by D = {d1, ... dx} (x is an integer of 1 or more).

図25は、保全コスト決定部16による保全コストの決定処理の一例を示すフローチャートであり、図26は、日々の処理能力の計算手法の一例を示す図である。図25及び図26に例示する処理は、図9のステップS13の処理の少なくとも一部、図21のステップS43の一部、及び、図21のステップS48の処理に対応する。 FIG. 25 is a flowchart showing an example of the maintenance cost determination process by the maintenance cost determination unit 16, and FIG. 26 is a diagram showing an example of a daily processing capacity calculation method. The processes illustrated in FIGS. 25 and 26 correspond to at least a part of the process of step S13 of FIG. 9, a part of step S43 of FIG. 21, and the process of step S48 of FIG.

図25に例示するように、保全コスト決定部16は、変数iに1を設定する(ステップS61)。 As illustrated in FIG. 25, the maintenance cost determination unit 16 sets the variable i to 1 (step S61).

処理能力計算部16aは、ネットワーク図11bを保全スケジュール情報11dに基づき設備停止を考慮するよう修正し、日付diの処理能力piを計算する(ステップS62)。 The processing capacity calculation unit 16a modifies the network diagram 11b so as to consider the equipment stop based on the maintenance schedule information 11d, and calculates the processing capacity pi of the date di (step S62).

例えば、日付diにおいて、その日に実施される作業の対象設備が含まれる工程は、設備停止の影響で処理を行なえないので、工程の処理能力を0と考える。なお、その日に実施される作業は、保全スケジュール情報11dに設定されている。 For example, on the date di, the process including the target equipment for the work to be performed on that day cannot be processed due to the influence of the equipment stop, so the processing capacity of the process is considered to be 0. The work to be carried out on that day is set in the maintenance schedule information 11d.

そこで、処理能力計算部16aは、保全スケジュール情報11dに基づき、当該工程の処理能力を0としてネットワーク図11bを修正する。そして、処理能力計算部16aは、修正したネットワーク図11bを利用して、図15〜図17を参照して説明した最大処理能力11cの計算と同様の手法により、最大処理能力を計算する。処理能力計算部16aは、計算した最大処理能力を、日付diのプロセスの処理能力piとする。 Therefore, the processing capacity calculation unit 16a corrects the network diagram 11b based on the maintenance schedule information 11d, setting the processing capacity of the process to 0. Then, the processing capacity calculation unit 16a calculates the maximum processing capacity by the same method as the calculation of the maximum processing capacity 11c described with reference to FIGS. 15 to 17 by using the modified network FIG. 11b. The processing capacity calculation unit 16a sets the calculated maximum processing capacity as the processing capacity pi of the process on the date di.

例えば、図26に示すように、日付di=2019/3/11の場合(対象設備ID:EQ04−1に関する作業(T006)の1作業の予定あり)を想定する。 For example, as shown in FIG. 26, it is assumed that the date di = 2019/3/11 (one work of the work (T006) related to the target equipment ID: EQ04-1 is scheduled).

処理能力計算部16aは、図26の左上に示すように、設備EQ04−1を使用する工程の処理能力を0とし、図26の左下に示すように、工程C1の処理能力を0としたときのネットワーク図11bを作成する。 When the processing capacity of the process using the equipment EQ04-1 is set to 0 as shown in the upper left of FIG. 26 and the processing capacity of the process C1 is set to 0 as shown in the lower left of FIG. The network diagram 11b of the above is created.

また、処理能力計算部16aは、図26の右上に示すように、図15〜図17を参照して説明した最大処理能力11cの計算と同様の手法により、ネットワーク図11bの最大処理能力を計算する。そして、処理能力計算部16aは、図26の右下に示すように、最大処理能力を日付diのプロセスの処理能力piとする。 Further, as shown in the upper right of FIG. 26, the processing capacity calculation unit 16a calculates the maximum processing capacity of the network FIG. 11b by the same method as the calculation of the maximum processing capacity 11c described with reference to FIGS. 15 to 17. To do. Then, as shown in the lower right of FIG. 26, the processing capacity calculation unit 16a sets the maximum processing capacity as the processing capacity pi of the process of the date di.

図25の説明に戻り、機会損失コスト計算部16bは、piと、Pmax(最大処理能力11c)とに基づき、日付diの処理能力の低下率riを計算する(ステップS63)。 Returning to the description of FIG. 25, the opportunity loss cost calculation unit 16b calculates the reduction rate ri of the processing capacity of the date di based on pi and Pmax (maximum processing capacity 11c) (step S63).

ここで、設備停止によるプラント処理能力の低下により、製品を作ることができなかった製品相当の利益を機会損失コストとする。 Here, the profit equivalent to the product for which the product could not be manufactured due to the decrease in the plant processing capacity due to the equipment stop is taken as the opportunity loss cost.

日付diにおけるプラントの処理能力の低下率riは、下記(1)式により算出されてよい。なお、下記(1)式中、Pmaxは、最大処理能力11cであり、piは、日付diにおける処理能力を示す。 The reduction rate ri of the processing capacity of the plant on the date di may be calculated by the following equation (1). In the following equation (1), Pmax is the maximum processing capacity 11c, and pi indicates the processing capacity on the date di.

Figure 2021064255
Figure 2021064255

機会損失コスト計算部16bは、低下率riを利用して、日付diの機会損失コストciを計算する(ステップS64)。 The opportunity loss cost calculation unit 16b calculates the opportunity loss cost ci on the date di by using the reduction rate ri (step S64).

例えば、機会損失コスト計算部16bは、日付diにおける機会損失コストciを、下記(2)式により計算してよい。なお、下記(2)式中、Nは、1日の最大生産量[個/日]、であり、gは、製品1個あたりの利益[円]を示す。最大生産量N及び利益gは、それぞれ、最大生産量11f及び利益11gとして、メモリ部11に予め格納されてもよい。 For example, the opportunity loss cost calculation unit 16b may calculate the opportunity loss cost ci on the date di by the following equation (2). In the following equation (2), N is the maximum daily production amount [pieces / day], and g is the profit [yen] per product. The maximum production amount N and the profit g may be stored in advance in the memory unit 11 as the maximum production amount 11f and the profit 11g, respectively.

ci=riNg (2) ci = riNg (2)

機会損失コスト計算部16bは、保全スケジュールの期間の全日付について、図25に示す処理を繰り返すと、期間中の日ごとの機会損失コスト{c1,・・・,cNday}を得ることができる。なお、Ndayは、保全スケジュールの期間内の日数を示す。 The opportunity loss cost calculation unit 16b can obtain the daily opportunity loss cost {c1, ..., cNday} during the period by repeating the process shown in FIG. 25 for all the dates of the maintenance schedule period. .. Nday indicates the number of days within the maintenance schedule period.

図25の説明に戻り、保全コスト計算部16cは、iがxよりも小さいか否かを判定する(ステップS65)。ステップS65でYESの場合、保全コスト計算部16cは、iに1を加算し(ステップS66)、処理がステップS62に移行する。 Returning to the description of FIG. 25, the maintenance cost calculation unit 16c determines whether or not i is smaller than x (step S65). If YES in step S65, the maintenance cost calculation unit 16c adds 1 to i (step S66), and the process shifts to step S62.

ステップS65でNOの場合、保全コスト計算部16cは、スケジュールに示された全期間の保全コストCを計算し(ステップS67)、処理が終了する。 If NO in step S65, the maintenance cost calculation unit 16c calculates the maintenance cost C for the entire period indicated in the schedule (step S67), and the process ends.

例えば、保全コスト計算部16cは、保全スケジュールの期間における保全コストCtotalを計算する。保全コストCtotalは、下記(3)式に示すように、保全期間における機会損失コストClossと保全作業にかかる総コストCtaskとの合計であってよい。 For example, the maintenance cost calculation unit 16c calculates the maintenance cost total during the maintenance schedule period. Maintenance costs C total, as shown in the following equation (3) may be the sum of the total cost C task according to the lost opportunity cost C loss and maintenance work in the maintenance period.

total=Closs+Ctask (3) C total = C loss + C task (3)

また、機会損失コストClossは、日ごとの機会損失コストciの総和として、下記(4)式により算出される。 The opportunity loss cost Cross is calculated by the following equation (4) as the sum of the daily opportunity loss costs ci.

Figure 2021064255
Figure 2021064255

さらに、保全作業にかかる総コストCtaskは、作業jにかかるコストctask,jの総和として、下記(5)式により算出される。 Further, the total cost C task for the maintenance work is calculated by the following equation (5) as the total of the costs c task and j for the work j.

Figure 2021064255
Figure 2021064255

ここで、メモリ部11は、保全作業コスト情報11iを格納してよい。保全作業コスト情報11iには、以下の情報が保持されるものとする。 Here, the memory unit 11 may store the maintenance work cost information 11i. The following information shall be retained in the maintenance work cost information 11i.

・作業jの実施にかかるコスト(保全実施日に非依存な定数):c1,j
・作業jと関連して保全実施日に依存して変化するコストc1,jを計算するために使用する、作業jの保全日diと実施期限Djを引数とする関数:f2,j(di,Dj)
・コストc2,jとして、部材の残存価値のみを考慮する場合、保守期限で残存価値が0円になるとしたとき、下記(6)式で示す関数情報が保全作業コスト情報11iに保持される。
-Cost of performing work j (constant independent of maintenance implementation date): c 1, j
-A function that takes the maintenance date di of work j and the implementation deadline Dj as arguments, which is used to calculate the costs c 1, j that change depending on the maintenance implementation date in relation to the work j: f 2, j ( di, Dj)
-When considering only the residual value of the member as the costs c 2 and j , if the residual value becomes 0 yen at the maintenance deadline, the function information shown by the following equation (6) is retained in the maintenance work cost information 11i. ..

2,j(di,Dj)=a(Dj−di) (6) f 2, j (di, Dj) = a (Dj-di) (6)

また、各作業にかかるコストctask,jは、2つのコストc1,j、c2,jの和として計算されてよい。すなわち、下記(7)式により算出されてよい。 Further, the costs c task, j required for each work may be calculated as the sum of the two costs c 1, j , c 2, j. That is, it may be calculated by the following equation (7).

task,j=c1,j+c2,j=c1,j+f2,j(di,Dj) (7) c task, j = c 1, j + c 2, j = c 1, j + f 2, j (di, Dj) (7)

以上の手法により、保全コスト計算部16cは、保全作業にかかる総コストCtaskを計算する。 By the above method, the maintenance cost calculation unit 16c calculates the total cost C task for the maintenance work.

なお、保全コスト決定部16は、算出した各コスト、例えば、保全コストCtotal、機会損失コストCloss、総コストCtask等を、コスト11hとしてメモリ部11に格納してもよい。 The maintenance cost determination unit 16 may store each calculated cost, for example, maintenance cost Total , opportunity loss cost Clos , total cost Task, etc. in the memory unit 11 as a cost 11h.

以上のように、一実施形態に係る作成装置1によれば、機会損失コストを含む保全コストの小さい保全スケジュールを短時間で自動的に作成することができる。 As described above, according to the creation device 1 according to the embodiment, it is possible to automatically create a maintenance schedule with a small maintenance cost including the opportunity loss cost in a short time.

また、保全コストの小さいスケジュールを立案することができる。 In addition, it is possible to formulate a schedule with low maintenance costs.

さらに、機会損失コストを削減するための制約を追加することで、良い解の存在する領域に限定して解探索を行なうため、試すべき組み合わせの数を減らすことができる。従って、計算量が削減でき、短時間で良い解を得られる。すなわち、スケジュール作成時間の短縮を図ることができる。 Furthermore, by adding a constraint for reducing the opportunity loss cost, the solution search is performed only in the area where a good solution exists, so that the number of combinations to be tried can be reduced. Therefore, the amount of calculation can be reduced and a good solution can be obtained in a short time. That is, the schedule creation time can be shortened.

〔1−4〕適用例
図27は、保全スケジュール及び保全コストの作成結果の表示例を示す図である。図27に示すように、表示画面20には、以下の少なくとも1つ以上の項目が表示されてよい。
[1-4] Application Example FIG. 27 is a diagram showing a display example of a maintenance schedule and a maintenance cost creation result. As shown in FIG. 27, at least one or more of the following items may be displayed on the display screen 20.

・保全スケジュール情報11dをガントチャートで可視化した保全スケジュール(符号A参照)。
・スケジュール期間中の日ごとの機会損失コスト{c1,・・・,cNday}を棒グラフで可視化した、保全コスト[円](符号B参照)。
・スケジュール期間。
・全期間の保全コスト[円]の算出結果。
-A maintenance schedule in which the maintenance schedule information 11d is visualized on a Gantt chart (see reference numeral A).
-Maintenance cost [yen] (see symbol B), which is a bar graph visualization of the daily opportunity loss cost {c1, ..., cNday} during the schedule period.
・ Schedule period.
・ Calculation result of maintenance cost [yen] for the whole period.

図28は、作成装置1と、端末40とを備えるシステム30の構成例を示す図である。図28に示すように、保全スケジュールの作成者は、端末40を操作して、処理プロセス情報11a及び保全スケジュール情報11dを作成装置1に入力する。作成装置1のスケジュール作成部15は、上述した手法によって、保全スケジュール情報11d(保全コスト最小)を出力し、端末40に送信する。このとき、スケジュール作成部15は、図27に示す表示画面20を端末40のモニタ等に表示するための情報(HTMLファイルやグラフデータ等)を端末40に送信してもよい。 FIG. 28 is a diagram showing a configuration example of a system 30 including a creating device 1 and a terminal 40. As shown in FIG. 28, the creator of the maintenance schedule operates the terminal 40 to input the processing process information 11a and the maintenance schedule information 11d into the creation device 1. The schedule creation unit 15 of the creation device 1 outputs the maintenance schedule information 11d (minimum maintenance cost) by the method described above, and transmits it to the terminal 40. At this time, the schedule creation unit 15 may transmit information (HTML file, graph data, etc.) for displaying the display screen 20 shown in FIG. 27 on the monitor or the like of the terminal 40 to the terminal 40.

このように、スケジュール作成部15は、メンテナンスコストが最小となるメンテナンススケジュールを特定し、特定したメンテナンススケジュールの情報を出力してよい。 In this way, the schedule creation unit 15 may specify the maintenance schedule that minimizes the maintenance cost, and output the information of the specified maintenance schedule.

なお、作成装置1は、端末40等の他の装置と、ネットワークを介して相互に通信可能に接続されてよい。ネットワークは、WAN(Wide Area Network)、LAN、又はこれらの組み合わせを含んでよい。WANにはインターネットが含まれてよい。 The creation device 1 may be connected to another device such as the terminal 40 so as to be able to communicate with each other via a network. The network may include a WAN (Wide Area Network), a LAN, or a combination thereof. The WAN may include the Internet.

これにより、保全スケジュールの作成者は、処理プロセス情報11a及び保全スケジュール情報11dを作成装置1に入力するだけで、保全コストの小さいスケジュールを短時間で容易に取得することができる。また、得られたスケジュールは、作成装置1により評価結果とともに可視化されるため、作業者は、適切な保全スケジュールを容易に把握することが可能となる。 As a result, the creator of the maintenance schedule can easily acquire the schedule with low maintenance cost in a short time only by inputting the processing process information 11a and the maintenance schedule information 11d into the creation device 1. Further, since the obtained schedule is visualized together with the evaluation result by the creating device 1, the operator can easily grasp an appropriate maintenance schedule.

〔2〕その他
上述した一実施形態に係る技術は、以下のように変形、変更して実施することができる。
[2] Others The technology according to the above-described embodiment can be modified or modified as follows.

例えば、図6に示す各機能ブロックは、それぞれ任意の組み合わせで併合してもよく、分割してもよい。 For example, the functional blocks shown in FIG. 6 may be merged or divided in any combination.

〔3〕付記
以上の実施形態に関し、さらに以下の付記を開示する。
[3] Additional Notes The following additional notes will be further disclosed with respect to the above embodiments.

(付記1)
複数の設備の各々のメンテナンススケジュールを作成するコンピュータに、
前記複数の設備を利用するプロセスの各工程と、前記各工程間の相互関係と、前記各工程の処理能力とを定義する第1情報に基づき、設備停止のない状態での前記プロセスの第1処理能力を取得し、
前記第1情報に基づき、前記複数の設備のうちのいずれかの設備停止状態での前記プロセスの第2処理能力を取得し、
前記第1処理能力及び前記第2処理能力に基づき、前記メンテナンススケジュールのメンテナンスコストを算出し、
複数のメンテナンス作業の各々の条件を定義する第2情報に基づき、メンテナンス作業の開始日に関する制約を、重なる日程で実行可能なメンテナンス作業のペアごとに作成し、
複数の前記制約の各々の有効又は無効を切り替えながら、前記メンテナンススケジュールの作成と、前記メンテナンスコストの算出とを実行する、
処理を実行させる、メンテナンススケジュール作成プログラム。
(Appendix 1)
On a computer that creates a maintenance schedule for each of multiple facilities
Based on the first information that defines each step of the process using the plurality of facilities, the interrelationship between the steps, and the processing capacity of each step, the first step of the process without equipment stoppage. Acquire processing power,
Based on the first information, the second processing capacity of the process in the stopped state of any one of the plurality of facilities is acquired.
Based on the first processing capacity and the second processing capacity, the maintenance cost of the maintenance schedule is calculated.
Based on the second information that defines the conditions for each of multiple maintenance tasks, constraints on the start date of maintenance tasks are created for each pair of maintenance tasks that can be performed on overlapping dates.
The maintenance schedule is created and the maintenance cost is calculated while switching the validity or invalidity of each of the plurality of constraints.
A maintenance schedule creation program that executes processing.

(付記2)
前記メンテナンスコストの算出は、
前記第1処理能力と前記第2処理能力との差分に基づき、前記プロセスの日ごとの機会損失コストを算出し、
前記日ごとの機会損失コストの総和に基づき、前記メンテナンスコストを算出する、
付記1に記載のメンテナンススケジュール作成プログラム。
(Appendix 2)
The calculation of the maintenance cost is
Based on the difference between the first processing capacity and the second processing capacity, the daily opportunity loss cost of the process is calculated.
The maintenance cost is calculated based on the sum of the daily opportunity loss costs.
The maintenance schedule creation program described in Appendix 1.

(付記3)
前記制約の作成は、
重なる日程で実行可能なメンテナンス作業のペアであって、日程をずらして実行させる場合よりも機会損失コストが減少するメンテナンス作業のペアを複数抽出し、
前記抽出したペアごとにメンテナンス作業の開始日に関する制約を生成する、
付記2に記載のメンテナンススケジュール作成プログラム。
(Appendix 3)
The creation of the constraint
Extract multiple pairs of maintenance work that can be performed on overlapping schedules, and the opportunity loss cost is reduced compared to the case where the schedules are staggered.
Generate a constraint on the start date of maintenance work for each extracted pair.
The maintenance schedule creation program described in Appendix 2.

(付記4)
前記コンピュータに、
前記第1情報に基づき、前記プロセスを、前記各工程に流入又は流出する製品の数量を示すネットワーク図として表現し、
前記ネットワーク図に基づき、前記第1処理能力及び前記第2処理能力を取得する、
処理を実行させる、付記1〜3のいずれか1項に記載のメンテナンススケジュール作成プログラム。
(Appendix 4)
On the computer
Based on the first information, the process is represented as a network diagram showing the quantity of products flowing into or out of each process.
Acquire the first processing capacity and the second processing capacity based on the network diagram.
The maintenance schedule creation program according to any one of Items 1 to 3 for executing the process.

(付記5)
前記コンピュータに、
前記ネットワーク図におけるいずれかの第1工程に流入又は流出する製品の数量を0とした場合に、流入又は流出する製品の数量が0となる第2工程が存在する場合であって、前記第1工程に対する第1メンテナンス作業と、前記第2工程に対する第2メンテナンス作業とが重なった日程で実施可能である場合に、前記第1及び第2メンテナンス作業のペアについて前記制約を作成する、
処理を実行させる、付記4に記載のメンテナンススケジュール作成プログラム。
(Appendix 5)
On the computer
When the quantity of products flowing in or out is set to 0 in any of the first steps in the network diagram, there is a second step in which the quantity of products flowing in or out is 0, and the first step is described above. When the first maintenance work for the process and the second maintenance work for the second process can be performed on an overlapping schedule, the constraint is created for the pair of the first and second maintenance work.
The maintenance schedule creation program according to Appendix 4, which executes the process.

(付記6)
前記コンピュータに、
前記メンテナンスコストが最小となる前記メンテナンススケジュールを特定し、
特定した前記メンテナンススケジュールの情報を出力する、
処理を実行させる、付記1〜5のいずれか1項に記載のメンテナンススケジュール作成プログラム。
(Appendix 6)
On the computer
Identify the maintenance schedule that minimizes the maintenance cost
Output the specified maintenance schedule information,
The maintenance schedule creation program according to any one of Appendix 1 to 5, which executes the process.

(付記7)
複数の設備の各々のメンテナンススケジュールを作成するコンピュータが、
前記複数の設備を利用するプロセスの各工程と、前記各工程間の相互関係と、前記各工程の処理能力とを定義する第1情報に基づき、設備停止のない状態での前記プロセスの第1処理能力を取得し、
前記第1情報に基づき、前記複数の設備のうちのいずれかの設備停止状態での前記プロセスの第2処理能力を取得し、
前記第1処理能力及び前記第2処理能力に基づき、前記メンテナンススケジュールのメンテナンスコストを算出し、
複数のメンテナンス作業の各々の条件を定義する第2情報に基づき、メンテナンス作業の開始日に関する制約を、重なる日程で実行可能なメンテナンス作業のペアごとに作成し、
複数の前記制約の各々の有効又は無効を切り替えながら、前記メンテナンススケジュールの作成と、前記メンテナンスコストの算出とを実行する、
メンテナンススケジュール作成方法。
(Appendix 7)
A computer that creates a maintenance schedule for each of multiple facilities
Based on the first information that defines each step of the process using the plurality of facilities, the interrelationship between the steps, and the processing capacity of each step, the first step of the process without equipment stoppage. Acquire processing power,
Based on the first information, the second processing capacity of the process in the stopped state of any one of the plurality of facilities is acquired.
Based on the first processing capacity and the second processing capacity, the maintenance cost of the maintenance schedule is calculated.
Based on the second information that defines the conditions for each of multiple maintenance tasks, constraints on the start date of maintenance tasks are created for each pair of maintenance tasks that can be performed on overlapping dates.
The maintenance schedule is created and the maintenance cost is calculated while switching the validity or invalidity of each of the plurality of constraints.
How to create a maintenance schedule.

(付記8)
前記メンテナンスコストの算出は、
前記第1処理能力と前記第2処理能力との差分に基づき、前記プロセスの日ごとの機会損失コストを算出し、
前記日ごとの機会損失コストの総和に基づき、前記メンテナンスコストを算出する、
付記7に記載のメンテナンススケジュール作成方法。
(Appendix 8)
The calculation of the maintenance cost is
Based on the difference between the first processing capacity and the second processing capacity, the daily opportunity loss cost of the process is calculated.
The maintenance cost is calculated based on the sum of the daily opportunity loss costs.
The maintenance schedule creation method described in Appendix 7.

(付記9)
前記制約の作成は、
重なる日程で実行可能なメンテナンス作業のペアであって、日程をずらして実行させる場合よりも機会損失コストが減少するメンテナンス作業のペアを複数抽出し、
前記抽出したペアごとにメンテナンス作業の開始日に関する制約を生成する、
付記8に記載のメンテナンススケジュール作成方法。
(Appendix 9)
The creation of the constraint
Extract multiple pairs of maintenance work that can be performed on overlapping schedules, and the opportunity loss cost is reduced compared to the case where the schedules are staggered.
Generate a constraint on the start date of maintenance work for each extracted pair.
The maintenance schedule creation method described in Appendix 8.

(付記10)
前記コンピュータが、
前記第1情報に基づき、前記プロセスを、前記各工程に流入又は流出する製品の数量を示すネットワーク図として表現し、
前記ネットワーク図に基づき、前記第1処理能力及び前記第2処理能力を取得する、
付記7〜9のいずれか1項に記載のメンテナンススケジュール作成方法。
(Appendix 10)
The computer
Based on the first information, the process is represented as a network diagram showing the quantity of products flowing into or out of each process.
Acquire the first processing capacity and the second processing capacity based on the network diagram.
The maintenance schedule creation method according to any one of Appendix 7 to 9.

(付記11)
前記コンピュータが、
前記ネットワーク図におけるいずれかの第1工程に流入又は流出する製品の数量を0とした場合に、流入又は流出する製品の数量が0となる第2工程が存在する場合であって、前記第1工程に対する第1メンテナンス作業と、前記第2工程に対する第2メンテナンス作業とが重なった日程で実施可能である場合に、前記第1及び第2メンテナンス作業のペアについて前記制約を作成する、
付記10に記載のメンテナンススケジュール作成方法。
(Appendix 11)
The computer
When the quantity of products flowing in or out is set to 0 in any of the first steps in the network diagram, there is a second step in which the quantity of products flowing in or out is 0, and the first step is described above. When the first maintenance work for the process and the second maintenance work for the second process can be performed on an overlapping schedule, the constraint is created for the pair of the first and second maintenance work.
The maintenance schedule creation method according to Appendix 10.

(付記12)
前記コンピュータが、
前記メンテナンスコストが最小となる前記メンテナンススケジュールを特定し、
特定した前記メンテナンススケジュールの情報を出力する、
付記7〜11のいずれか1項に記載のメンテナンススケジュール作成方法。
(Appendix 12)
The computer
Identify the maintenance schedule that minimizes the maintenance cost
Output the specified maintenance schedule information,
The maintenance schedule creation method according to any one of Appendix 7 to 11.

(付記13)
複数の設備の各々のメンテナンススケジュールを作成するメンテナンススケジュール作成装置であって、
前記複数の設備を利用するプロセスの各工程と、前記各工程間の相互関係と、前記各工程の処理能力とを定義する第1情報と、複数のメンテナンス作業の各々の条件を定義する第2情報と、を記憶する記憶部と、
前記第1情報に基づき、設備停止のない状態での前記プロセスの第1処理能力を取得する第1取得部と、
前記第1情報に基づき、前記複数の設備のうちのいずれかの設備停止状態での前記プロセスの第2処理能力を取得する第2取得部と、
前記第1処理能力及び前記第2処理能力に基づき、前記メンテナンススケジュールのメンテナンスコストを算出する算出部と、
複数のメンテナンス作業の各々の条件を定義する第2情報に基づき、メンテナンス作業の開始日に関する制約を、重なる日程で実行可能なメンテナンス作業のペアごとに作成する制約作成部と、
複数の前記制約の各々の有効又は無効を切り替えながら、前記メンテナンススケジュールの作成と、前記メンテナンスコストの算出とを実行する実行部と、
を備える、メンテナンススケジュール作成装置。
(Appendix 13)
A maintenance schedule creation device that creates maintenance schedules for each of multiple facilities.
The first information that defines each process of the process using the plurality of facilities, the interrelationship between the processes, and the processing capacity of each process, and the second that defines the conditions of each of the plurality of maintenance operations. A storage unit that stores information and
Based on the first information, the first acquisition unit that acquires the first processing capacity of the process without equipment stoppage, and
Based on the first information, a second acquisition unit that acquires the second processing capacity of the process when any of the plurality of facilities is stopped, and
A calculation unit that calculates the maintenance cost of the maintenance schedule based on the first processing capacity and the second processing capacity.
Based on the second information that defines the conditions for each of multiple maintenance tasks, a constraint creation unit that creates constraints on the start date of maintenance tasks for each pair of maintenance tasks that can be executed on overlapping dates.
An execution unit that creates the maintenance schedule and calculates the maintenance cost while switching the validity or invalidity of each of the plurality of constraints.
A maintenance schedule creation device.

(付記14)
前記算出部は、
前記第1処理能力と前記第2処理能力との差分に基づき、前記プロセスの日ごとの機会損失コストを算出し、
前記日ごとの機会損失コストの総和に基づき、前記メンテナンスコストを算出する、
付記13に記載のメンテナンススケジュール作成装置。
(Appendix 14)
The calculation unit
Based on the difference between the first processing capacity and the second processing capacity, the daily opportunity loss cost of the process is calculated.
The maintenance cost is calculated based on the sum of the daily opportunity loss costs.
The maintenance schedule creation device according to Appendix 13.

(付記15)
前記制約作成部は、
重なる日程で実行可能なメンテナンス作業のペアであって、日程をずらして実行させる場合よりも機会損失コストが減少するメンテナンス作業のペアを複数抽出し、
前記抽出したペアごとにメンテナンス作業の開始日に関する制約を生成する、
付記14に記載のメンテナンススケジュール作成装置。
(Appendix 15)
The constraint creation unit
Extract multiple pairs of maintenance work that can be performed on overlapping schedules, and the opportunity loss cost is reduced compared to the case where the schedules are staggered.
Generate a constraint on the start date of maintenance work for each extracted pair.
The maintenance schedule creation device according to Appendix 14.

(付記16)
前記第1情報に基づき、前記プロセスを、前記各工程に流入又は流出する製品の数量を示すネットワーク図として表現する作成部、を備え、
前記第1取得部及び前記第2取得部は、前記ネットワーク図に基づき、前記第1処理能力及び前記第2処理能力をそれぞれ取得する、
付記13〜15のいずれか1項に記載のメンテナンススケジュール作成装置。
(Appendix 16)
Based on the first information, a creation unit for expressing the process as a network diagram showing the quantity of products flowing into or out of each process is provided.
The first acquisition unit and the second acquisition unit acquire the first processing capacity and the second processing capacity, respectively, based on the network diagram.
The maintenance schedule creation device according to any one of Appendix 13 to 15.

(付記17)
前記制約作成部は、
前記ネットワーク図におけるいずれかの第1工程に流入又は流出する製品の数量を0とした場合に、流入又は流出する製品の数量が0となる第2工程が存在する場合であって、前記第1工程に対する第1メンテナンス作業と、前記第2工程に対する第2メンテナンス作業とが重なった日程で実施可能である場合に、前記第1及び第2メンテナンス作業のペアについて前記制約を作成する、
付記16に記載のメンテナンススケジュール作成装置。
(Appendix 17)
The constraint creation unit
When the quantity of products flowing in or out is set to 0 in any of the first steps in the network diagram, there is a second step in which the quantity of products flowing in or out is 0, and the first step is described above. When the first maintenance work for the process and the second maintenance work for the second process can be performed on an overlapping schedule, the constraint is created for the pair of the first and second maintenance work.
The maintenance schedule creation device according to Appendix 16.

(付記18)
前記実行部は、
前記メンテナンスコストが最小となる前記メンテナンススケジュールを特定し、
特定した前記メンテナンススケジュールの情報を出力する、
付記13〜17のいずれか1項に記載のメンテナンススケジュール作成。
(Appendix 18)
The execution unit
Identify the maintenance schedule that minimizes the maintenance cost
Output the specified maintenance schedule information,
Create the maintenance schedule described in any one of Appendix 13 to 17.

1 保全スケジュール作成装置
10 コンピュータ
11 メモリ部
11a 処理プロセス情報
11b ネットワーク図
11c 最大処理能力
11d 保全スケジュール情報
11e 作業間制約
11f 最大生産量
11g 利益
11h コスト
11i 保全作業コスト情報
12 ネットワーク図作成部
13 最大処理能力計算部
14 作業間制約作成部
15 スケジュール作成部
16 保全コスト決定部
16a 処理能力計算部
16b 機会損失コスト計算部
16c 保全コスト計算部
20 表示画面
30 システム
40 端末
1 Maintenance schedule creation device 10 Computer 11 Memory unit 11a Processing process information 11b Network diagram 11c Maximum processing capacity 11d Maintenance schedule information 11e Inter-work constraint 11f Maximum production 11g Profit 11h Cost 11i Maintenance work cost information 12 Network diagram creation unit 13 Maximum processing Capacity calculation unit 14 Work-to-work constraint creation unit 15 Schedule creation unit 16 Maintenance cost determination unit 16a Processing capacity calculation unit 16b Opportunity loss cost calculation unit 16c Maintenance cost calculation unit 20 Display screen 30 System 40 Terminal

Claims (8)

複数の設備の各々のメンテナンススケジュールを作成するコンピュータに、
前記複数の設備を利用するプロセスの各工程と、前記各工程間の相互関係と、前記各工程の処理能力とを定義する第1情報に基づき、設備停止のない状態での前記プロセスの第1処理能力を取得し、
前記第1情報に基づき、前記複数の設備のうちのいずれかの設備停止状態での前記プロセスの第2処理能力を取得し、
前記第1処理能力及び前記第2処理能力に基づき、前記メンテナンススケジュールのメンテナンスコストを算出し、
複数のメンテナンス作業の各々の条件を定義する第2情報に基づき、メンテナンス作業の開始日に関する制約を、重なる日程で実行可能なメンテナンス作業のペアごとに作成し、
複数の前記制約の各々の有効又は無効を切り替えながら、前記メンテナンススケジュールの作成と、前記メンテナンスコストの算出とを実行する、
処理を実行させる、メンテナンススケジュール作成プログラム。
On a computer that creates a maintenance schedule for each of multiple facilities
Based on the first information that defines each step of the process using the plurality of facilities, the interrelationship between the steps, and the processing capacity of each step, the first step of the process without equipment stoppage. Acquire processing power,
Based on the first information, the second processing capacity of the process in the stopped state of any one of the plurality of facilities is acquired.
Based on the first processing capacity and the second processing capacity, the maintenance cost of the maintenance schedule is calculated.
Based on the second information that defines the conditions for each of multiple maintenance tasks, constraints on the start date of maintenance tasks are created for each pair of maintenance tasks that can be performed on overlapping dates.
The maintenance schedule is created and the maintenance cost is calculated while switching the validity or invalidity of each of the plurality of constraints.
A maintenance schedule creation program that executes processing.
前記メンテナンスコストの算出は、
前記第1処理能力と前記第2処理能力との差分に基づき、前記プロセスの日ごとの機会損失コストを算出し、
前記日ごとの機会損失コストの総和に基づき、前記メンテナンスコストを算出する、
請求項1に記載のメンテナンススケジュール作成プログラム。
The calculation of the maintenance cost is
Based on the difference between the first processing capacity and the second processing capacity, the daily opportunity loss cost of the process is calculated.
The maintenance cost is calculated based on the sum of the daily opportunity loss costs.
The maintenance schedule creation program according to claim 1.
前記制約の作成は、
重なる日程で実行可能なメンテナンス作業のペアであって、日程をずらして実行させる場合よりも機会損失コストが減少するメンテナンス作業のペアを複数抽出し、
前記抽出したペアごとにメンテナンス作業の開始日に関する制約を生成する、
請求項2に記載のメンテナンススケジュール作成プログラム。
The creation of the constraint
Extract multiple pairs of maintenance work that can be performed on overlapping schedules, and the opportunity loss cost is reduced compared to the case where the schedules are staggered.
Generate a constraint on the start date of maintenance work for each extracted pair.
The maintenance schedule creation program according to claim 2.
前記コンピュータに、
前記第1情報に基づき、前記プロセスを、前記各工程に流入又は流出する製品の数量を示すネットワーク図として表現し、
前記ネットワーク図に基づき、前記第1処理能力及び前記第2処理能力を取得する、
処理を実行させる、請求項1〜3のいずれか1項に記載のメンテナンススケジュール作成プログラム。
On the computer
Based on the first information, the process is represented as a network diagram showing the quantity of products flowing into or out of each process.
Acquire the first processing capacity and the second processing capacity based on the network diagram.
The maintenance schedule creation program according to any one of claims 1 to 3, which executes the process.
前記コンピュータに、
前記ネットワーク図におけるいずれかの第1工程に流入又は流出する製品の数量を0とした場合に、流入又は流出する製品の数量が0となる第2工程が存在する場合であって、前記第1工程に対する第1メンテナンス作業と、前記第2工程に対する第2メンテナンス作業とが重なった日程で実施可能である場合に、前記第1及び第2メンテナンス作業のペアについて前記制約を作成する、
処理を実行させる、請求項4に記載のメンテナンススケジュール作成プログラム。
On the computer
When the quantity of products flowing in or out is set to 0 in any of the first steps in the network diagram, there is a second step in which the quantity of products flowing in or out is 0, and the first step is described above. When the first maintenance work for the process and the second maintenance work for the second process can be performed on an overlapping schedule, the constraint is created for the pair of the first and second maintenance work.
The maintenance schedule creation program according to claim 4, wherein the process is executed.
前記コンピュータに、
前記メンテナンスコストが最小となる前記メンテナンススケジュールを特定し、
特定した前記メンテナンススケジュールの情報を出力する、
処理を実行させる、請求項1〜5のいずれか1項に記載のメンテナンススケジュール作成プログラム。
On the computer
Identify the maintenance schedule that minimizes the maintenance cost
Output the specified maintenance schedule information,
The maintenance schedule creation program according to any one of claims 1 to 5, which executes the process.
複数の設備の各々のメンテナンススケジュールを作成するコンピュータが、
前記複数の設備を利用するプロセスの各工程と、前記各工程間の相互関係と、前記各工程の処理能力とを定義する第1情報に基づき、設備停止のない状態での前記プロセスの第1処理能力を取得し、
前記第1情報に基づき、前記複数の設備のうちのいずれかの設備停止状態での前記プロセスの第2処理能力を取得し、
前記第1処理能力及び前記第2処理能力に基づき、前記メンテナンススケジュールのメンテナンスコストを算出し、
複数のメンテナンス作業の各々の条件を定義する第2情報に基づき、メンテナンス作業の開始日に関する制約を、重なる日程で実行可能なメンテナンス作業のペアごとに作成し、
複数の前記制約の各々の有効又は無効を切り替えながら、前記メンテナンススケジュールの作成と、前記メンテナンスコストの算出とを実行する、
メンテナンススケジュール作成方法。
A computer that creates a maintenance schedule for each of multiple facilities
Based on the first information that defines each step of the process using the plurality of facilities, the interrelationship between the steps, and the processing capacity of each step, the first step of the process without equipment stoppage. Acquire processing power,
Based on the first information, the second processing capacity of the process in the stopped state of any one of the plurality of facilities is acquired.
Based on the first processing capacity and the second processing capacity, the maintenance cost of the maintenance schedule is calculated.
Based on the second information that defines the conditions for each of multiple maintenance tasks, constraints on the start date of maintenance tasks are created for each pair of maintenance tasks that can be performed on overlapping dates.
The maintenance schedule is created and the maintenance cost is calculated while switching the validity or invalidity of each of the plurality of constraints.
How to create a maintenance schedule.
複数の設備の各々のメンテナンススケジュールを作成するメンテナンススケジュール作成装置であって、
前記複数の設備を利用するプロセスの各工程と、前記各工程間の相互関係と、前記各工程の処理能力とを定義する第1情報と、複数のメンテナンス作業の各々の条件を定義する第2情報と、を記憶する記憶部と、
前記第1情報に基づき、設備停止のない状態での前記プロセスの第1処理能力を取得する第1取得部と、
前記第1情報に基づき、前記複数の設備のうちのいずれかの設備停止状態での前記プロセスの第2処理能力を取得する第2取得部と、
前記第1処理能力及び前記第2処理能力に基づき、前記メンテナンススケジュールのメンテナンスコストを算出する算出部と、
複数のメンテナンス作業の各々の条件を定義する第2情報に基づき、メンテナンス作業の開始日に関する制約を、重なる日程で実行可能なメンテナンス作業のペアごとに作成する制約作成部と、
複数の前記制約の各々の有効又は無効を切り替えながら、前記メンテナンススケジュールの作成と、前記メンテナンスコストの算出とを実行する実行部と、
を備える、メンテナンススケジュール作成装置。
A maintenance schedule creation device that creates maintenance schedules for each of multiple facilities.
The first information that defines each process of the process using the plurality of facilities, the interrelationship between the processes, and the processing capacity of each process, and the second that defines the conditions of each of the plurality of maintenance operations. A storage unit that stores information and
Based on the first information, the first acquisition unit that acquires the first processing capacity of the process without equipment stoppage, and
Based on the first information, a second acquisition unit that acquires the second processing capacity of the process when any of the plurality of facilities is stopped, and
A calculation unit that calculates the maintenance cost of the maintenance schedule based on the first processing capacity and the second processing capacity.
Based on the second information that defines the conditions for each of multiple maintenance tasks, a constraint creation unit that creates constraints on the start date of maintenance tasks for each pair of maintenance tasks that can be executed on overlapping dates.
An execution unit that creates the maintenance schedule and calculates the maintenance cost while switching the validity or invalidity of each of the plurality of constraints.
A maintenance schedule creation device.
JP2019189431A 2019-10-16 2019-10-16 Maintenance schedule creation program, maintenance schedule creation method, and maintenance schedule creation device Active JP7322656B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019189431A JP7322656B2 (en) 2019-10-16 2019-10-16 Maintenance schedule creation program, maintenance schedule creation method, and maintenance schedule creation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019189431A JP7322656B2 (en) 2019-10-16 2019-10-16 Maintenance schedule creation program, maintenance schedule creation method, and maintenance schedule creation device

Publications (2)

Publication Number Publication Date
JP2021064255A true JP2021064255A (en) 2021-04-22
JP7322656B2 JP7322656B2 (en) 2023-08-08

Family

ID=75486317

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019189431A Active JP7322656B2 (en) 2019-10-16 2019-10-16 Maintenance schedule creation program, maintenance schedule creation method, and maintenance schedule creation device

Country Status (1)

Country Link
JP (1) JP7322656B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2023074371A1 (en) * 2021-10-26 2023-05-04 パナソニックIpマネジメント株式会社 Maintenance work reporting system and maintenance work reporting method
WO2023188214A1 (en) * 2022-03-30 2023-10-05 富士通株式会社 Information processing program, information processing method, and information processing device
WO2023223650A1 (en) * 2022-05-18 2023-11-23 株式会社日立製作所 Maintenance planning system and maintenance planning method
DE112022001971T5 (en) 2021-04-05 2024-01-18 Denso Corporation Rotor and Rotating Electric Machine
WO2024048053A1 (en) * 2022-08-29 2024-03-07 株式会社神戸製鋼所 Work procedure creation system, work procedure creation method, and recording medium for maintenance of production property machinery

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08339400A (en) * 1995-06-13 1996-12-24 Idemitsu Kosan Co Ltd Integrated control system of oil factory
JPH09285948A (en) * 1996-04-19 1997-11-04 Matsushita Electric Ind Co Ltd Stop time scheduling system for manufacturing device
JP2978778B2 (en) * 1996-08-29 1999-11-15 山形日本電気株式会社 Production line management method
JP2002330541A (en) * 2001-02-27 2002-11-15 Hitachi Ltd Supporting system for operation and maintenance program of generator equipment
JP2009205387A (en) * 2008-02-27 2009-09-10 Hitachi Ltd Scheduling device, program, and scheduling method
JP2010282353A (en) * 2009-06-03 2010-12-16 Hitachi Ltd Dynamic maintenance planning apparatus
WO2018003879A1 (en) * 2016-06-30 2018-01-04 日本電気株式会社 Maintenance plan generation device, method, and program

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08339400A (en) * 1995-06-13 1996-12-24 Idemitsu Kosan Co Ltd Integrated control system of oil factory
JPH09285948A (en) * 1996-04-19 1997-11-04 Matsushita Electric Ind Co Ltd Stop time scheduling system for manufacturing device
JP2978778B2 (en) * 1996-08-29 1999-11-15 山形日本電気株式会社 Production line management method
JP2002330541A (en) * 2001-02-27 2002-11-15 Hitachi Ltd Supporting system for operation and maintenance program of generator equipment
JP2009205387A (en) * 2008-02-27 2009-09-10 Hitachi Ltd Scheduling device, program, and scheduling method
JP2010282353A (en) * 2009-06-03 2010-12-16 Hitachi Ltd Dynamic maintenance planning apparatus
WO2018003879A1 (en) * 2016-06-30 2018-01-04 日本電気株式会社 Maintenance plan generation device, method, and program

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE112022001971T5 (en) 2021-04-05 2024-01-18 Denso Corporation Rotor and Rotating Electric Machine
WO2023074371A1 (en) * 2021-10-26 2023-05-04 パナソニックIpマネジメント株式会社 Maintenance work reporting system and maintenance work reporting method
WO2023188214A1 (en) * 2022-03-30 2023-10-05 富士通株式会社 Information processing program, information processing method, and information processing device
WO2023223650A1 (en) * 2022-05-18 2023-11-23 株式会社日立製作所 Maintenance planning system and maintenance planning method
WO2024048053A1 (en) * 2022-08-29 2024-03-07 株式会社神戸製鋼所 Work procedure creation system, work procedure creation method, and recording medium for maintenance of production property machinery

Also Published As

Publication number Publication date
JP7322656B2 (en) 2023-08-08

Similar Documents

Publication Publication Date Title
JP7322656B2 (en) Maintenance schedule creation program, maintenance schedule creation method, and maintenance schedule creation device
Bogus et al. Concurrent engineering approach to reducing design delivery time
US11036483B2 (en) Method for predicting the successfulness of the execution of a DevOps release pipeline
US9459980B1 (en) Varying cluster sizes in a predictive test load while testing a productive system
Hammad et al. Allocation and management of cost contingency in projects
JP2018139041A (en) Task plan optimizing device and task plan optimizing method
JP2018063598A (en) Business supporting system and business supporting method
Lin et al. Performance evaluation for a footwear manufacturing system with multiple production lines and different station failure rates
US8781869B2 (en) Determining estimation variance associated with project planning
Duda et al. Product lifecycle management (PLM) in the context of industry 4.0
Li Parallel nonconvex generalized Benders decomposition for natural gas production network planning under uncertainty
US20200380437A1 (en) Business process design support method and business process design support apparatus
Taylor et al. Defining production and financial data streams required for a factory digital twin to optimise the deployment of labour
Arndt et al. Lessons Learned from the US Nuclear Regulatory Commission’s Digital System Risk Research
Nguyen et al. Strategic capacity portfolio planning under demand uncertainty and technological change
CN114004505A (en) BPM platform and method for recommending business process based on BPM platform
Huang et al. Modelling software corrective maintenance productivity using an analytical economic model and simulation
Alves Portela Santos et al. Supervisory control service for supporting flexible processes
WO2014192072A1 (en) Computer, association calculation method, and storage medium
CN113253991A (en) Task visualization processing method and device, electronic equipment and storage medium
Gu et al. Optimal rules for single machine scheduling with stochastic breakdowns
Hu et al. Petri Net‐Based R&D Process Modeling and Optimization for Composite Materials
Mylnikov The model of effective management in the formation of a production portfolio
Dangelmaier et al. Simulation assisted optimization and real-time control aspects of flexible production systems subject to disturbances
Carydias et al. Towards 2030: Transforming Asset Emissions in Upstream Production Operations

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220708

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230322

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230404

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230601

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20230601

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230627

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230710

R150 Certificate of patent or registration of utility model

Ref document number: 7322656

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150