JP2019127799A - Crushed stone filling device and method - Google Patents

Crushed stone filling device and method Download PDF

Info

Publication number
JP2019127799A
JP2019127799A JP2018011737A JP2018011737A JP2019127799A JP 2019127799 A JP2019127799 A JP 2019127799A JP 2018011737 A JP2018011737 A JP 2018011737A JP 2018011737 A JP2018011737 A JP 2018011737A JP 2019127799 A JP2019127799 A JP 2019127799A
Authority
JP
Japan
Prior art keywords
crushed stone
groove
hopper
filling
stone filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2018011737A
Other languages
Japanese (ja)
Other versions
JP7096546B2 (en
Inventor
小野寺 恒雄
Tsuneo Onodera
恒雄 小野寺
晃介 若杉
Kosuke Wakasugi
晃介 若杉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
National Agriculture and Food Research Organization
Paddy Research Co Ltd
Original Assignee
National Agriculture and Food Research Organization
Paddy Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by National Agriculture and Food Research Organization, Paddy Research Co Ltd filed Critical National Agriculture and Food Research Organization
Priority to JP2018011737A priority Critical patent/JP7096546B2/en
Publication of JP2019127799A publication Critical patent/JP2019127799A/en
Application granted granted Critical
Publication of JP7096546B2 publication Critical patent/JP7096546B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

To provide crushed stone filling device and method which can efficiently fill the groove with a crushed stone and can improve workability.SOLUTION: A crushed stone filling device 11 that fills a groove 15 with a crushed stone 16 includes: a crushed stone filling part 21 which is opened in a vertical direction, is formed such that dimensions of outer surfaces of both of side walls are narrower than the groove width of the groove, and is inserted into the groove; a hopper part 22 continuously arranged above the crushed stone filling part; a work machine mounting part 23 provided at the upper part on one side in a groove length direction of the hopper part; a crushed stone support member 24 which is provided between the hopper part and the crushed stone filling part, prevents falling of the crushed stone to the crushed stone filling part from the hopper part and is removal; a falling amount control member 25 which controls the falling amount of the crushed stone falling from the hopper part to the crushed stone filling part; and a side wall protective member 26 formed so that a tip width dimension in a movement direction is small.SELECTED DRAWING: Figure 1

Description

本発明は、砕石充填装置及び方法に関し、詳しくは、あらかじめ形成されている溝内に砕石を充填するための砕石充填装置及び方法に関する。   The present invention relates to a crushed stone filling apparatus and method, and more particularly, to a crushed stone filling apparatus and method for filling crushed stone in a previously formed groove.

各種圃場や運動競技場、校庭、公園などにおいて、地下水位を制御するため、掘削形成した溝の底部に給排水管を敷設し、該給排水管の上に砕石を充填し、さらに、砕石の上に土砂を充填することが広く行われている(例えば、特許文献1,2参照。)。また、圃場の地中に形成した溝内に、排水促進材として籾殻や木材チップなどを充填する排水用暗渠形成装置が知られている(例えば、特許文献3参照。)。   In various fields, athletic fields, schoolyards, parks, etc., to control the groundwater level, a water supply / drainage pipe is laid at the bottom of the excavated groove, and crushed stone is filled on the water supply / drainage pipe. Filling with earth and sand is widely performed (for example, refer to Patent Documents 1 and 2). In addition, a drainage culvert forming device is known in which grooves formed in the ground of a farm are filled with rice husks, wood chips, and the like as drainage promotion materials (see, for example, Patent Document 3).

特開平9−248081号公報Japanese Patent Laid-Open No. 9-248081 特開平11−46605号公報Japanese Patent Laid-Open No. 11-46605 特開2004−244803号公報JP 2004-244803 A

給排水管の上に砕石を充填する作業は、一般的に、油圧ショベルのバケットに砕石をすくい取り、バケットから砕石を少量ずつ溝内に投入した後、作業員が砕石の上面を均すことで行われていた。したがって、作業効率が低く、作業性にも問題があった。また、砕石は、籾殻や木材チップに比べて重いため、従来の排水用暗渠形成装置をそのまま適用することはできず、砕石移載用の油圧ショベルを別途必要とする。   The work of filling crushed stone on the water supply / drainage pipe is generally done by scooping the crushed stone into the bucket of the hydraulic excavator, putting the crushed stone from the bucket into the groove little by little, and then the operator leveling the upper surface of the crushed stone. It was done. Therefore, the work efficiency is low and there is a problem in workability. Further, since crushed stone is heavier than rice husks and wood chips, the conventional drainage culvert forming apparatus cannot be applied as it is, and a hydraulic excavator for transferring crushed stone is separately required.

そこで本発明は、溝内への砕石の充填を効率よく行うことができ、作業性の向上も図れる砕石充填装置及び方法を提供することを目的としている。   Then, this invention aims at providing the crushed stone filling apparatus and method which can perform the filling of the crushed stone in a groove | channel efficiently, and can aim at the improvement of workability | operativity.

上記目的を達成するため、本発明の砕石充填装置は、あらかじめ形成された溝内に、あらかじめ設定された高さで砕石を充填する砕石充填装置において、上下方向が開口し、両側壁の外面同士の寸法が前記溝の溝幅より幅狭に形成されて前記溝内に挿入される砕石充填部と、該砕石充填部の上方に連設されたホッパー部と、該ホッパー部の溝長さ方向一側上部に設けられた作業機装着部と、前記ホッパー部と前記砕石充填部との間に設けられてホッパー部内に砕石をすくい取る際には閉じ状態となってホッパー部から砕石充填部への砕石の落下を防止し、砕石充填部から溝内に砕石を充填する際には開状態となってホッパー部から砕石充填部への砕石の落下を許容する着脱可能な砕石支持部材と、前記ホッパー部と前記砕石充填部との間に設けられてホッパー部から砕石充填部に落下する砕石の落下量を制御する落下量制御部材と、前記砕石充填部の進行方向前端に設けられて先端幅寸法が小さく形成された側壁保護部材とを備えていることを特徴としている。   In order to achieve the above object, the crushed stone filling device of the present invention is a crushed stone filling device for filling crushed stone at a preset height in a groove formed in advance, which is open in the vertical direction and the outer surfaces of both side walls The crushed stone filling portion formed to be narrower than the groove width of the groove and inserted into the groove, the hopper portion continuously provided above the crushed stone filling portion, and the groove length direction of the hopper portion The work machine mounting unit provided on the upper side of one side, and between the hopper unit and the crushed stone charging unit, is closed when the crushed stone is skimmed in the hopper unit, and the hopper unit is closed to the crushed stone charging unit And a removable crush support member for preventing the falling of crushed stone and being open when filling the crushed stone into the groove from the crushed stone filling portion and allowing the falling of the crushed stone from the hopper portion to the crushed stone filled portion; Installed between the hopper and the crushed stone filling part A falling amount control member for controlling the falling amount of crushed stone falling from the hopper portion to the crushed stone filling portion, and a side wall protecting member provided at the front end in the advancing direction of the crushed stone filled portion and having a small tip width dimension. It is characterized by having.

さらに、本発明の砕石充填装置は、前記作業機装着部は、油圧ショベルの作業アーム先端に装着されること、前記砕石充填部の両側壁上端部に、前記溝の開口両側の地表面に接地する挿入量設定部材がそれぞれ配置されていることを特徴としている。   Furthermore, in the crushed stone filling apparatus according to the present invention, the work machine mounting portion is mounted on the tip of a working arm of a hydraulic excavator, and is grounded to the upper surface of both side walls of the crushed stone filling portion and to the ground surface on both sides of the opening of the groove. The insertion amount setting members are arranged respectively.

また、本発明の砕石充填方法は、あらかじめ形成された溝内に、あらかじめ設定された高さで砕石を充填する砕石充填方法において、上下方向が開口し、両側壁の外面同士の寸法が前記溝の溝幅より幅狭に形成され、前記溝内に挿入される砕石充填部と、該砕石充填部の上方に連設されたホッパー部と、該ホッパー部の溝長さ方向一側上部に設けられた作業機装着部と、前記ホッパー部と前記砕石充填部との間に設けられてホッパー部から砕石充填部への砕石の落下を防止する着脱可能な砕石支持部材と、前記ホッパー部と前記砕石充填部との間に、ホッパー部から砕石充填部に落下する砕石の落下量を制御する落下量制御部材と、前記砕石充填部の進行方向前端に設けられて先端幅寸法が小さく形成された側壁保護部材とを備え、前記作業機装着部を油圧ショベルの作業アーム先端に装着した砕石充填装置を使用し、前記砕石支持部材を取り付けてホッパー部から砕石充填部への砕石の落下を防止した状態として油圧ショベルの作業アームを操作し、前記ホッパー部内に砕石をすくい取り、ホッパー部内に砕石をすくい取った後に前記側壁保護部材を移動方向前方に向けた前記砕石充填部を前記溝内に挿入するとともに、前記砕石支持部材を取り外してホッパー部から砕石充填部へ砕石を落下可能とし、前記油圧ショベルを操作して砕石充填装置を溝に沿って移動させ、ホッパー部から砕石充填部を介して溝内に砕石を順次充填し、ホッパー部内の砕石を溝内に充填した後、砕石充填部を溝内から取り出して砕石支持部材を取り付けて砕石をホッパー部内にすくい取ることを順次繰り返して溝内に砕石を充填することを特徴としている。   Further, according to the crushed stone filling method of the present invention, in the crushed stone filling method in which crushed stone is filled at a preset height in a groove formed in advance, the vertical direction is open and the dimensions of the outer surfaces of both side walls are the groove A crushed stone filling portion inserted into the groove, a hopper portion continuously provided above the crushed stone filling portion, and provided at an upper portion on one side in the groove length direction of the hopper portion. And a removable crushed stone supporting member provided between the hopper unit and the crushed stone filling unit to prevent the crushed stone from falling from the hopper unit to the crushed stone filling unit, the hopper unit, and the hopper unit A falling amount control member for controlling the falling amount of crushed stone falling from the hopper portion to the crushed stone filling portion, and a forward end in the traveling direction of the crushed stone filled portion, and the tip width dimension is formed small A side wall protection member, Using the crushed stone loading device with the mounting unit mounted at the tip of the working arm of the hydraulic shovel, operating the working arm of the hydraulic shovel in a state where the crushed stone supporting member is attached to prevent falling of crushed stone from the hopper unit to the crushed stone filling unit. , Scooping crushed stone into the hopper, and scooping crushed stone into the hopper, then inserting the crushed filler with the side wall protection member facing forward in the moving direction and removing the crushed stone supporting member The crushed stone can be dropped from the hopper portion to the crushed stone filling portion, the crushed stone filling device is moved along the groove by operating the hydraulic excavator, and the crushed stone is sequentially filled into the groove from the hopper portion through the crushed stone filling portion. After filling the crushed stone in the groove into the groove, take out the crushed stone filled part from the groove, attach the crushed stone support member and scoop the crushed stone into the hopper sequentially It is characterized by filling the crushed stone in the groove returned Ri.

本発明によれば、砕石支持部材を取り付けて閉状態でホッパー部に砕石をすくい取った後、砕石充填部を溝内に所定量挿入し、砕石支持部材を取り外して開状態とした状態で砕石充填装置を作業機により溝に沿って移動させることにより、作土層への砕石の混入を防止しながら、溝内に均一な高さで砕石を充填していくことができる。   According to the present invention, after the crushed stone supporting member is attached and skimmed in the hopper portion in the closed state, a predetermined amount of the crushed stone filled portion is inserted into the groove, and the crushed stone supporting member is removed to open the crushed state By moving the filling device along the groove by the working machine, it is possible to fill the groove with a uniform height while preventing the crushed stone from being mixed into the soil formation layer.

本発明の砕石充填装置を油圧ショベルの作業アーム先端に装着して砕石充填作業を行っている状態の一形態例を示す側面図である。It is a side view which shows one example of the state which mounts the crushed stone filling apparatus of this invention in the working arm front-end | tip of a hydraulic excavator, and is performing the crushed stone filling operation | work. 図1のII−II断面図である。It is II-II sectional drawing of FIG. 砕石充填装置の断面側面図である。It is a cross-sectional side view of a crushed stone filling apparatus. 図3のIV−IV断面図である。It is IV-IV sectional drawing of FIG. ホッパー部内に砕石をすくい取る工程における砕石充填装置の動きを示す説明図である。It is explanatory drawing which shows a motion of the crushed stone filling apparatus in the process of scooping up crushed stone in a hopper part. 砕石充填部を溝内に挿入し、砕石支持部材を取り外して砕石を溝内に挿入可能とした状態の説明図である。It is explanatory drawing of the state which inserted the crushed stone filling part in a groove | channel, removed the crushed stone support member, and made it possible to insert a crushed stone in a groove | channel. ホッパー部内の砕石を残らず溝内に落下させている状態の説明図である。It is explanatory drawing of the state which is falling in the groove | channel, without leaving the crushed stone in a hopper part. 砕石充填作業終了後に砕石支持部材を取り付ける状態を示す説明図である。It is explanatory drawing which shows the state which attaches a crushed stone support member after completion | finish of a crushed stone filling operation | work.

図1乃至図4は、本発明の砕石充填装置の一形態例を示している。本形態例に示す砕石充填装置11は、油圧ショベル12における作業アーム13の先端に、通常装着されているバケットに代えて装着されるもので、あらかじめ各種溝形成装置により形成され、底部に給排水パイプ14を敷設した溝15の内部に、あらかじめ設定された高さに砕石16を充填するように形成されている。なお、溝の形状や形成方法は任意であり、給排水パイプ14は無くてもよい。   1 to 4 show one embodiment of the crushed stone filling device of the present invention. The crushed stone filling device 11 shown in this embodiment is attached to the tip of the working arm 13 of the hydraulic shovel 12 instead of the bucket usually attached, and is formed in advance by various groove forming devices, 14 is formed so that the crushed stone 16 is filled in a preset height. In addition, the shape and formation method of a groove | channel are arbitrary and the water supply / drainage pipe 14 may not be provided.

砕石充填装置11は、溝15の内部に挿入される砕石充填部21と、該砕石充填部21の上方に連設されたホッパー部22と、該ホッパー部22の一側上部に設けられた作業機装着部23と、ホッパー部22と砕石充填部21との間に設けられた砕石支持部材24と、該砕石支持部材24の上部に設けられた落下量制御部材25と、砕石充填部21の進行方向前端に設けられた側壁保護部材26と、砕石充填部21の両側壁上端部にそれぞれ配置された挿入量設定部材27とを備えている。   The crushed stone filling device 11 includes a crushed stone filling portion 21 inserted into the groove 15, a hopper portion 22 continuously provided above the crushed stone filling portion 21, and an operation provided on one upper side of the hopper portion 22. Of the machine mounting portion 23, the crushed stone support member 24 provided between the hopper portion 22 and the crushed stone filling portion 21, the fall amount control member 25 provided on the upper portion of the crushed stone support member 24, and the crushed stone filling portion 21 A side wall protection member 26 provided at the front end in the traveling direction and an insertion amount setting member 27 respectively disposed at the upper end portions of both side walls of the crushed stone filling portion 21 are provided.

砕石充填部21は、平面視が、溝15の長手方向(前後方向)に長く、幅方向が短い偏平な直方体形状で、上下方向が開口した角筒状に形成され、幅方向の寸法は、溝15の幅寸法に対して同一か、僅かに狭い寸法に設定され、溝15の幅寸法によって異なるが、例えば、1〜15mm狭く形成されている。挿入量設定部材27は、下面が溝15の開口両側の地表面15aに接地する接地部27aと、該接地部27aの前端から斜め上方に屈曲したガイド部27bと、ホッパー部22の下面に挿入量設定部材27を固定するための支持脚27cとを有している。砕石充填作業中に、接地部27aを地表面15aに接地させることにより、砕石充填部21をあらかじめ設定された深さまで溝12内に挿入した状態にでき、砕石充填部21の下端部、特に、進行方向後部側下端部が溝15内への砕石16の充填高さになるように形成されている。   The crushed stone filling portion 21 is formed in a rectangular parallelepiped shape that is long in the longitudinal direction (front-rear direction) of the groove 15 and short in the width direction in a plan view, and is formed in a rectangular tube shape having an opening in the vertical direction. The width is set to be the same as or slightly narrower than the width of the groove 15, and is narrowed by, for example, 1 to 15 mm, depending on the width of the groove 15. The insertion amount setting member 27 is inserted into the ground portion 27a whose lower surface is in contact with the ground surface 15a on both sides of the opening of the groove 15, the guide portion 27b bent obliquely upward from the front end of the ground portion 27a And a support leg 27c for fixing the amount setting member 27. By putting the ground contact portion 27a into contact with the ground surface 15a during the crushed stone filling operation, the crushed stone filled portion 21 can be inserted into the groove 12 to a preset depth, and the lower end portion of the crushed stone filled portion 21, particularly, The lower end on the rear side in the traveling direction is formed to have a filling height of the crushed stone 16 into the groove 15.

ホッパー部22は、前後方向から見た形状が、砕石充填部21の上部開口から上方に向かって徐々に拡大した漏斗状部22aと、該漏斗状部22aの上部に連続した箱形部22bと、箱形部22bの上端部に設けられた補強部材22cとを有しており、箱形部22b及び補強部材22cの前部側に、前記作業機装着部23が設けられている。作業機装着部23は、通常のバケットと同形状に形成されており、作業アーム13に対するバケットと砕石充填装置11との交換を容易に行えるようにしている。   The hopper portion 22 has a funnel-shaped portion 22a gradually enlarged upward from the upper opening of the crushed stone filling portion 21 and a box-shaped portion 22b continuous with the upper portion of the funnel-shaped portion 22a when viewed from the front-rear direction And the reinforcing member 22c provided at the upper end of the box-shaped part 22b, and the work implement mounting part 23 is provided on the front side of the box-shaped part 22b and the reinforcing member 22c. The work implement mounting portion 23 is formed in the same shape as a normal bucket, and allows the bucket and the crushed stone filling device 11 to be easily exchanged with respect to the work arm 13.

砕石支持部材24は、漏斗状部22aの下部前後方向に設けられたガイドレール24aの上にスライド可能に設けられた板状部材であり、漏斗状部22aから砕石充填部21に向かう開口を完全に閉塞する大きさを有している。漏斗状部22aの前壁に設けられたスリット22dを貫通してホッパー部22の前方に突出した砕石支持部材24の前端部先端には、砕石充填装置11に対して砕石支持部材24を着脱する際に使用する手掛け部24bが設けられている。この砕石支持部材24を取り付けて閉状態にすることによって砕石16をホッパー部22内にすくい取る状態にでき、砕石支持部材24を取り外して開状態にすることによってホッパー部22から砕石充填部21への砕石の落下を許容して砕石充填部21から溝15内に砕石16を充填する状態にできる。   The crushed stone supporting member 24 is a plate member slidably provided on a guide rail 24a provided in the lower front and rear direction of the funnel shaped portion 22a, and the opening from the funnel shaped portion 22a to the crushed stone filling portion 21 is completely It has a size to be closed. The crushed stone supporting member 24 is attached to and detached from the crushed stone filling device 11 at the front end of the crushed stone supporting member 24 which protrudes through the slit 22d provided on the front wall of the funnel portion 22a and protrudes forward of the hopper portion 22. A handle 24b is provided for use. By attaching the crushed stone supporting member 24 and closing it, the crushed stone 16 can be skimmed into the hopper portion 22. By removing the crushed stone supporting member 24 and opening it, the hopper portion 22 to the crushed stone filled portion 21 The crushed stone 16 can be allowed to fall, and the crushed stone 16 can be filled into the groove 15 from the crushed stone filling portion 21.

落下量制御部材25は、砕石支持部材24の上部に設けられており、漏斗状部22aの後壁との間に、あらかじめ設定された大きさの開口25aを形成する大きさの板材からなるもので、漏斗状部22aの両側壁に固定部材25bによって固定されている。   The fall amount control member 25 is provided on the upper portion of the crushed stone support member 24 and is made of a plate material having a size that forms an opening 25a having a preset size between the rear wall of the funnel-shaped portion 22a. And it is being fixed to the both sides wall of the funnel-shaped part 22a by the fixing member 25b.

側壁保護部材26は、平面視で、前端側が先鋭化した三角形状に形成されており、側壁保護部材26の後部側外面と砕石充填部21の前部側外面とを連続させることにより、砕石充填部21の前端角部によって溝15の側壁が損傷することを防止している。   The side wall protection member 26 is formed in a triangular shape whose front end side is sharpened in a plan view, and the crushed stone is filled by connecting the rear side outer surface of the side wall protection member 26 and the front outer surface of the crushed stone filling portion 21. The side wall of the groove 15 is prevented from being damaged by the front end corner portion of the portion 21.

このように形成した砕石充填装置11は、図1に示すように、油圧ショベル12における作業アーム13の先端に砕石充填装置11を装着し、ホッパー部22に砕石16を入れた状態で、砕石充填部21を溝15内に挿入し、挿入量設定部材27を地表面15aに接地させ、砕石支持部材24を取り外した状態で油圧ショベル12を前進させ、砕石充填装置11を溝15に沿って移動させることによって砕石充填作業が行われ、ホッパー部22内の砕石16が落下量制御部材25の開口25aを通って砕石充填部21の下部開口から溝15内に落下し、砕石充填部21の後壁の高さまで砕石16が溝15内に充填される。   As shown in FIG. 1, the crushed stone filling device 11 thus formed is mounted with the crushed stone filling device 11 mounted on the tip of the working arm 13 of the hydraulic shovel 12 and with the crushed stone 16 placed in the hopper portion 22. The portion 21 is inserted into the groove 15, the insertion amount setting member 27 is grounded to the ground surface 15a, the hydraulic shovel 12 is advanced in a state where the crushed stone supporting member 24 is removed, and the crushed stone filling device 11 is moved along the groove 15. The crushed stone filling operation is performed by causing the crushed stone 16 in the hopper portion 22 to fall into the groove 15 from the lower opening of the crushed stone filling portion 21 through the opening 25a of the fall amount control member 25 and after the crushed stone filled portion 21. The crushed stone 16 is filled in the groove 15 up to the height of the wall.

図5乃至図8は、前記砕石充填装置11を使用して溝15内に砕石16を充填する手順の一例を示している。なお、以下の説明において、前記形態例に示した砕石充填装置の構成要素と同一の構成要素には同一の符号を付して詳細な説明は省略する。   5 to 8 show an example of a procedure for filling the crushed stone 16 into the groove 15 using the crushed stone filling device 11. In addition, in the following description, the same code | symbol is attached | subjected to the component same as the component of the crushed stone filling apparatus shown to the said example, and detailed description is abbreviate | omitted.

まず、図5に示すように、油圧ショベル12における作業アーム13を、通常のバケットで土砂をすくい取る操作と同様に、砕石支持部材24を取り付けた砕石充填装置11を操作し、例えば、ダンプトラックの荷台に積載されている砕石16をホッパー部22内にすくい取る。このとき、砕石支持部材24が取り付けられて閉状態となっているので、砕石16は、ホッパー部22から砕石充填部21に落下することなく、ホッパー部22内に保持される。   First, as shown in FIG. 5, the crusher 11 is attached with the crusher support member 24 in the same manner as the operation for scooping earth and sand with the normal bucket with the working arm 13 in the hydraulic shovel 12, for example, dump truck The crushed stone 16 loaded on the loading platform is scooped into the hopper 22. At this time, since the crushed stone support member 24 is attached and is in the closed state, the crushed stone 16 is held in the hopper portion 22 without falling from the hopper portion 22 to the crushed stone filling portion 21.

次に、図6に示すように、側壁保護部材26を移動方向前方に向け、挿入量設定部材27が地表面15aに接地するまで砕石充填部21を溝15内に挿入するとともに、砕石支持部材24を前方に引き抜いて砕石充填装置11から取り外して開状態とした後、油圧ショベル12を前進させる。これにより、前記図1に示したように、ホッパー部22から砕石充填部21に落下した砕石16が溝15内に充填され、砕石充填装置11の進行方向後部側の溝15内のあらかじめ設定された高さ(深さ)まで砕石16が順次充填されていく。このとき、側壁保護部材26によって溝15の側壁の損傷が抑えられるので、側壁の損傷によって落下した土砂で給排水パイプ14が埋まってしまうことを防止できる。   Next, as shown in FIG. 6, the side wall protection member 26 is directed forward in the moving direction, and the crushed stone filling portion 21 is inserted into the groove 15 until the insertion amount setting member 27 contacts the ground surface 15a, and the crushed stone support member 24 is pulled forward and removed from the crushed stone filling device 11 to be opened, and then the excavator 12 is advanced. Thereby, as shown in FIG. 1, the crushed stone 16 dropped from the hopper portion 22 to the crushed stone filling portion 21 is filled in the groove 15 and preset in the groove 15 on the rear side in the traveling direction of the crushed stone filling device 11 The crushed stone 16 is sequentially filled up to a certain height (depth). At this time, damage to the side wall of the groove 15 is suppressed by the side wall protection member 26, so that it is possible to prevent the water supply / drainage pipe 14 from being buried with the earth and sand that has fallen due to the damage to the side wall.

また、途中まで砕石16を充填した溝15内に次の砕石16を充填する際には、先に充填されている砕石16の上に砕石充填部21を降ろしてから砕石支持部材24を取り外して砕石充填装置11を前進させることにより、砕石16を連続状態で溝15内に充填していくことができる。また、落下量制御部材25を設けることにより、ホッパー部22が大容量であっても、大量の砕石16が溝15内に同時に落下することがないので、砕石充填装置11の移動(前進)を円滑にできるとともに、砕石支持部材24に加わる砕石16の重量も小さくなるので、砕石支持部材24の抜き取りを容易に行うことができる   Also, when filling the next crushed stone 16 in the groove 15 filled with crushed stone 16 halfway, the crushed stone filling portion 21 is lowered onto the crushed stone 16 previously filled, and then the crushed stone support member 24 is removed. By moving the crushed stone filling device 11 forward, the crushed stone 16 can be filled into the groove 15 in a continuous state. In addition, by providing the fall amount control member 25, even if the hopper portion 22 has a large capacity, a large amount of crushed stone 16 does not fall into the groove 15 at the same time. Since the weight of the crushed stone 16 applied to the crushed stone support member 24 is reduced, the crushed stone support member 24 can be easily extracted.

さらに、図7に示すように、ホッパー部22内の砕石量が少なくなったときに、砕石充填部21の後部を溝15内に挿入した状態で、開口25aが下方を向くように砕石充填装置11を傾けることにより、ホッパー部22内の砕石16の全てを開口25aから溝15内に落下させることができる。   Furthermore, as shown in FIG. 7, when the amount of crushed stone in the hopper portion 22 decreases, the crushed stone filling device is directed such that the opening 25 a faces downward with the rear portion of the crushed stone filled portion 21 inserted in the groove 15. By tilting 11, all of the crushed stone 16 in the hopper 22 can be dropped into the groove 15 from the opening 25 a.

ホッパー部22内が空になったら、図8に示すように、砕石充填部21を溝15から取り出し、スリット22dを通して砕石支持部材24を取り付ける。砕石支持部材24を取り付けた後、前記図5に示した砕石をすくい取る作業に戻り、砕石のすくい取り、砕石充填部21の溝15内への挿入、砕石支持部材24の取り外し、溝15に沿った砕石充填装置11の移動、砕石充填部21の取り出し、砕石支持部材24の取り付け、という各作業を順次繰り返していくことにより、溝15の全長にわたって砕石16を所定高さで充填することができる。   When the inside of the hopper portion 22 becomes empty, as shown in FIG. 8, the crushed stone filling portion 21 is taken out from the groove 15, and the crushed stone support member 24 is attached through the slit 22d. After attaching the crushed stone support member 24, the operation returns to the step of skimming the crushed stone shown in FIG. 5, and the crushed stone is skimmed, inserted into the groove 15 of the crushed stone filling portion 21, removed the crushed stone support member 24, It is possible to fill the crushed stone 16 at a predetermined height over the entire length of the groove 15 by sequentially repeating the operations of moving the crushed stone filling device 11 along, taking out the crushed stone filling portion 21, and attaching the crushed stone support member 24. it can.

したがって、砕石充填装置11を油圧ショベル12に装着することにより、砕石充填装置11のホッパー部22内への砕石16の投入や、溝15内への砕石16の充填、溝15内の砕石16の均し作業などを人手に頼らずに、1台の油圧ショベル12の操作で容易に行うことができるので、溝15内への砕石充填作業を少人数で効率よく行うことができ、砕石をトラックの荷台などからホッパー部に移載するための油圧ショベルを別に用意する必要もなくなる。   Therefore, by mounting the crushed stone filling device 11 on the hydraulic shovel 12, the charging of the crushed stone 16 into the hopper portion 22 of the crushed stone filling device 11, the filling of the crushed stone 16 into the groove 15, the crushing stone 16 in the groove 15 Since the leveling work can be easily performed by operating one hydraulic excavator 12 without relying on human hands, the work of filling the crushed stone into the groove 15 can be performed efficiently by a small number of people. There is no need to prepare a separate hydraulic excavator for transferring from the loading platform to the hopper.

なお、砕石充填装置は、前記同様の砕石すくい取り動作や溝内への挿入動作などが可能ならば、各種作業機に装着することが可能であり、作業機装着部の形状は、作業機に応じた適宜な形状に形成することができる。さらに、側壁保護部材は前端側が円弧状であってもよく、挿入量設定部材は車輪などであってもよい。また、挿入量設定部材は、砕石充填部の上下位置を他の手段で制御できれば省略することができる。さらに、本発明の砕石充填装置は、溝内への砕石の充填を主としたものであるが、籾殻や木材チップ、火山灰などを溝内に充填する際にも使用可能である。   The crushed stone filling device can be mounted on various working machines as long as the crushed stone scooping operation or the inserting operation into the groove is possible, and the shape of the working machine mounting portion is the same as that of the working machine. It can be formed in an appropriate shape according to the condition. Further, the side wall protection member may have an arc shape on the front end side, and the insertion amount setting member may be a wheel or the like. Further, the insertion amount setting member can be omitted if the vertical position of the crushed stone filling portion can be controlled by other means. Furthermore, the crushed stone filling device of the present invention is mainly used for filling crushed stone into the groove, but can also be used when filling the groove with rice husks, wood chips, volcanic ash and the like.

11…砕石充填装置、12…油圧ショベル、13…作業アーム、14…給排水パイプ、15…溝、15a…地表面、16…砕石、21…砕石充填部、22…ホッパー部、22a…漏斗状部、22b…箱形部、22c…補強部材、22d…スリット、23…作業機装着部、24…砕石支持部材、24a…ガイドレール、24b…手掛け部、25…落下量制御部材、25a…開口、25b…固定部材、26…側壁保護部材、27…挿入量設定部材、27a…接地部、27b…ガイド部、27c…支持脚   11: crushed stone filling device, 12: hydraulic shovel, 13: working arm, 14: water supply and drainage pipe, 15: groove, 15a: ground surface, 16: crushed stone, 21: crushed stone filling portion, 22: hopper portion, 22a: funnel portion , 22b: box-shaped portion, 22c: reinforcing member, 22d: slit, 23: working machine mounting portion, 24: crushed stone supporting member, 24a: guide rail, 24b: handed portion, 25: falling amount control member, 25a: opening, 25b: Fixing member, 26 ... Side wall protection member, 27 ... Insertion amount setting member, 27a ... Grounding part, 27b ... Guide part, 27c ... Support leg

Claims (4)

あらかじめ形成された溝内に、あらかじめ設定された高さで砕石を充填する砕石充填装置において、上下方向が開口し、両側壁の外面同士の寸法が前記溝の溝幅より幅狭に形成されて前記溝内に挿入される砕石充填部と、該砕石充填部の上方に連設されたホッパー部と、該ホッパー部の溝長さ方向一側上部に設けられた作業機装着部と、前記ホッパー部と前記砕石充填部との間に設けられてホッパー部内に砕石をすくい取る際には閉じ状態となってホッパー部から砕石充填部への砕石の落下を防止し、砕石充填部から溝内に砕石を充填する際には開状態となってホッパー部から砕石充填部への砕石の落下を許容する着脱可能な砕石支持部材と、前記ホッパー部と前記砕石充填部との間に設けられてホッパー部から砕石充填部に落下する砕石の落下量を制御する落下量制御部材と、前記砕石充填部の進行方向前端に設けられて先端幅寸法が小さく形成された側壁保護部材とを備えていることを特徴とする砕石充填装置。   In the crushed stone filling device for filling crushed stone at a preset height in a previously formed groove, the vertical direction is open, and the dimensions of the outer surfaces of both side walls are formed narrower than the groove width of the groove A crushed stone filling portion to be inserted into the groove, a hopper portion continuously provided above the crushed stone filling portion, a work implement mounting portion provided on one upper side in the groove length direction of the hopper portion, and the hopper Provided between the crushed stone filling portion and the crushed stone filling portion, when scooping crushed stone into the hopper portion, it is in a closed state to prevent falling of crushed stone from the hopper portion to the crushed stone filling portion, and from the crushed stone filling portion into the groove A removable crushed stone supporting member which is opened when filling crushed stone and which allows falling of the crushed stone from the hopper portion to the crushed stone filled portion, and is provided between the hopper portion and the crushed stone filled portion to provide a hopper Of crushed stone falling from the section to the crushed stone filling section Lithotripsy filling device, characterized in that it comprises a drop amount control member for controlling the lower amount and a side wall protective member tip width provided in the traveling direction front end of the crushed stone filling portion is formed smaller. 前記作業機装着部は、油圧ショベルの作業アーム先端に装着されることを特徴とする請求項1記載の砕石充填装置。   The crushed stone filling apparatus according to claim 1, wherein the work machine mounting portion is mounted on a tip of a work arm of a hydraulic excavator. 前記砕石充填部の両側壁上端部に、前記溝の開口両側の地表面に接地する挿入量設定部材がそれぞれ配置されていることを特徴とする請求項1又は2記載の砕石充填装置。   The crushed stone filling device according to claim 1 or 2, wherein an insertion amount setting member that contacts the ground surface on both sides of the opening of the groove is disposed at the upper end of both side walls of the crushed stone filling portion. あらかじめ形成された溝内に、あらかじめ設定された高さで砕石を充填する砕石充填方法において、上下方向が開口し、両側壁の外面同士の寸法が前記溝の溝幅より幅狭に形成され、前記溝内に挿入される砕石充填部と、該砕石充填部の上方に連設されたホッパー部と、該ホッパー部の溝長さ方向一側上部に設けられた作業機装着部と、前記ホッパー部と前記砕石充填部との間に設けられてホッパー部から砕石充填部への砕石の落下を防止する着脱可能な砕石支持部材と、前記ホッパー部と前記砕石充填部との間に、ホッパー部から砕石充填部に落下する砕石の落下量を制御する落下量制御部材と、前記砕石充填部の進行方向前端に設けられて先端幅寸法が小さく形成された側壁保護部材とを備え、前記作業機装着部を油圧ショベルの作業アーム先端に装着した砕石充填装置を使用し、前記砕石支持部材を取り付けてホッパー部から砕石充填部への砕石の落下を防止した状態として油圧ショベルの作業アームを操作し、前記ホッパー部内に砕石をすくい取り、ホッパー部内に砕石をすくい取った後に前記側壁保護部材を移動方向前方に向けた前記砕石充填部を前記溝内に挿入するとともに、前記砕石支持部材を取り外してホッパー部から砕石充填部へ砕石を落下可能とし、前記油圧ショベルを操作して砕石充填装置を溝に沿って移動させ、ホッパー部から砕石充填部を介して溝内に砕石を順次充填し、ホッパー部内の砕石を溝内に充填した後、砕石充填部を溝内から取り出して砕石支持部材を取り付けて砕石をホッパー部内にすくい取ることを順次繰り返して溝内に砕石を充填することを特徴とする砕石充填方法。   In the crushed stone filling method in which crushed stone is filled at a preset height in a previously formed groove, the vertical direction is open, and the dimensions of the outer surfaces of both side walls are formed narrower than the groove width of the groove, A crushed stone filling portion to be inserted into the groove, a hopper portion continuously provided above the crushed stone filling portion, a work implement mounting portion provided on one upper side in the groove length direction of the hopper portion, and the hopper A removable crushed stone supporting member provided between the unit and the crushed stone packing unit to prevent the crushed stone from falling from the hopper unit to the crushed stone packing unit; a hopper unit between the hopper unit and the crushed stone packed unit; And a side wall protection member provided at the front end in the direction of movement of the crushed stone filling portion to control the falling amount of crushed stone falling to the crushed stone filling portion, and the side wall protecting member formed with a small tip width dimension; Mount the mounting part to the excavator working area. Using the crushed stone filling device attached to the tip of the system, the crushed stone support member is attached, the crushed stone is prevented from falling from the hopper to the crushed stone filled portion, the working arm of the hydraulic excavator is operated, and the crushed stone is put into the hopper. After scooping and scooping crushed stone into the hopper, the crushed stone filling portion with the side wall protection member facing forward in the moving direction is inserted into the groove, and the crushed stone supporting member is removed from the hopper to the crushed stone filling portion. The crushed stone can be dropped, the hydraulic excavator is operated to move the crushed stone filling device along the groove, the crushed stone is sequentially filled into the groove from the hopper portion through the crushed stone filling portion, and the crushed stone in the hopper portion is placed in the groove. After filling, the crushed stone filling part is taken out from the groove, a crushed stone support member is attached, and the crushed stone is scooped into the hopper part in order to fill the groove with crushed stone. Crushed stone filling wherein the door.
JP2018011737A 2018-01-26 2018-01-26 Crushed stone filling device and method Active JP7096546B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018011737A JP7096546B2 (en) 2018-01-26 2018-01-26 Crushed stone filling device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018011737A JP7096546B2 (en) 2018-01-26 2018-01-26 Crushed stone filling device and method

Publications (2)

Publication Number Publication Date
JP2019127799A true JP2019127799A (en) 2019-08-01
JP7096546B2 JP7096546B2 (en) 2022-07-06

Family

ID=67472001

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018011737A Active JP7096546B2 (en) 2018-01-26 2018-01-26 Crushed stone filling device and method

Country Status (1)

Country Link
JP (1) JP7096546B2 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5592728U (en) * 1978-12-21 1980-06-26
JPH0667480U (en) * 1993-03-10 1994-09-22 北垣建設株式会社 Bucket device for hydraulic excavator
JP2001040697A (en) * 1999-07-30 2001-02-13 Life Line:Kk Laying and leveling equipment for trench excavation
JP2003184059A (en) * 2001-12-13 2003-07-03 Padei Kenkyusho:Kk Device for charging material for ditch
JP2009281123A (en) * 2008-05-20 2009-12-03 Kikuo Tokida Hydraulic shovel attachment for soil improvement and unevenness correction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5592728U (en) * 1978-12-21 1980-06-26
JPH0667480U (en) * 1993-03-10 1994-09-22 北垣建設株式会社 Bucket device for hydraulic excavator
JP2001040697A (en) * 1999-07-30 2001-02-13 Life Line:Kk Laying and leveling equipment for trench excavation
JP2003184059A (en) * 2001-12-13 2003-07-03 Padei Kenkyusho:Kk Device for charging material for ditch
JP2009281123A (en) * 2008-05-20 2009-12-03 Kikuo Tokida Hydraulic shovel attachment for soil improvement and unevenness correction

Also Published As

Publication number Publication date
JP7096546B2 (en) 2022-07-06

Similar Documents

Publication Publication Date Title
US3203188A (en) Method and apparatus for preparing a trench for a subsurface conduit line and for laying such a line
JP4445033B1 (en) Attachment for forming crushed stone pile and crushed stone pile forming apparatus provided with the attachment
US5791825A (en) Device and method for producing a containment barrier underneath and around in-situ buried waste
JP2019127799A (en) Crushed stone filling device and method
JP6498253B1 (en) Pipe burying method
JP6037982B2 (en) Waste treatment method at waste disposal site
JP5131512B2 (en) Laying a clay-based impermeable layer
JP3871686B2 (en) Absorber construction equipment and construction method
JP6404760B2 (en) Ground improvement device, ground improvement method
US10017916B2 (en) Earth working apparatus
JP4098296B2 (en) Open shield machine and open shield method using it
GB2565806A (en) Excavator bucket
JP2001040697A (en) Laying and leveling equipment for trench excavation
JP2016107224A (en) Waste volume reduction processing method for waste disposal site
JP5015809B2 (en) Open shield machine
JPH0754365A (en) Backfill charging method in large depth backfilling work and device therefor
JP4060836B2 (en) Open shield method
GB2158491A (en) Drainage trenching machine
JP2003184059A (en) Device for charging material for ditch
JP2021070962A (en) Backfilling device and backfilling method for pipe
JP6711652B2 (en) Continuous concrete molding method
JP3499779B2 (en) Protectors and equipment for tunnel construction
JP2006037656A (en) Hydrophobic material throw-in device and hydrophobic material throw-in vehicle
JPH06158993A (en) Method of open shield construction and open shielding machine
JP2002339691A (en) Earth retaining equipment and open-cut construction method using this equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20201111

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20211007

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20211130

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220127

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220531

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220614

R150 Certificate of patent or registration of utility model

Ref document number: 7096546

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150