JP2019094616A - Roadbed improvement method - Google Patents

Roadbed improvement method Download PDF

Info

Publication number
JP2019094616A
JP2019094616A JP2017221957A JP2017221957A JP2019094616A JP 2019094616 A JP2019094616 A JP 2019094616A JP 2017221957 A JP2017221957 A JP 2017221957A JP 2017221957 A JP2017221957 A JP 2017221957A JP 2019094616 A JP2019094616 A JP 2019094616A
Authority
JP
Japan
Prior art keywords
crushed stone
roadbed
filling
confirmation
filled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017221957A
Other languages
Japanese (ja)
Other versions
JP7107665B2 (en
Inventor
壱記 伊藤
Itsuki Ito
壱記 伊藤
尚嗣 桃谷
Yoshitsugu Momotani
尚嗣 桃谷
俊之 小西
Toshiyuki Konishi
俊之 小西
大輔 神津
Daisuke Kozu
大輔 神津
陽紀 面高
Yoki Omodaka
陽紀 面高
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Railway Technical Research Institute
East Japan Railway Co
Original Assignee
Railway Technical Research Institute
East Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Railway Technical Research Institute, East Japan Railway Co filed Critical Railway Technical Research Institute
Priority to JP2017221957A priority Critical patent/JP7107665B2/en
Publication of JP2019094616A publication Critical patent/JP2019094616A/en
Application granted granted Critical
Publication of JP7107665B2 publication Critical patent/JP7107665B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Railway Tracks (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

To provide a roadbed improvement method that has good workability and can improve a roadbed of a railroad suitably while enlarging a construction area.SOLUTION: A roadbed improvement method comprises: a ballast removal/existing roadbed exposure step of removing existing ballast and exposing an existing roadbed 5; an existing roadbed excavation step of excavating the roadbed 5 and forming a recess 6 in a construction area; a crushed stone packing step of packing crushed stone 7 in the recess 6 by laying the crushed stone and forming a packed crushed stone layer 13; a grout material packing step of injecting and packing a grout material 16 in the packed crushed stone layer 13; and an inlet and confirmation port exposure formation means installation step of installing, at the grout material packing step, inlet and confirmation port exposure formation means for exposing and forming an inlet 14 in which the grout material 16 is injected and a packing confirmation port 15 for confirming a packing state of the grout material 16 each in the packed crushed stone layer 13.SELECTED DRAWING: Figure 8

Description

本発明は、鉄道の路盤を改良する路盤改良工法に関する。   The present invention relates to a roadbed improvement method for improving a railway roadbed.

従来、路盤を改良する手法として置換工法やセメント安定処理工法が多用されている。   Conventionally, replacement methods and cement stabilization methods have been widely used as methods for improving roadbeds.

置換工法は、軟弱な路盤を良質な路盤材料(鉄道構造物等設計標準・同解説 土構造物に記載のA群材料、粒度調整砕石、クラッシャラン等)に置き換え、路盤剛性を改善する工法であり、良質な路盤材料への置き換え作業時にプレートランマやタイピングランマ等の締固め機械/転圧機械によって十分に締固める(締固め度95%以上)ことが重要である。   The replacement method is a method to replace the soft roadbed with a good quality roadbed material (Railway design etc. Design standard / explanation A group material described in the soil structure, particle size control crushed stone, crusher run etc.) and improve the roadbed rigidity. It is important to fully compact (more than 95% compacting degree) with a compacting machine / compaction machine such as a plate rammer or a typing rammer at the time of replacement work with a high quality base material.

セメント安定処理工法は、軟弱な路盤または粒度調整砕石及びクラッシャラン等に対し、セメントを添加し混合することにより路盤剛性を改善する工法であり、置換工法と同様、締固め機械/転圧機械によって十分に締固めることが重要である。なお、粒度調整砕石やクラッシャラン等の良質な路盤材料とセメントを混合した材料を用いることもある。   The cement stabilization method is a method to improve the stiffness of the roadbed by adding and mixing cement to a soft roadbed or particle size control crushed stone and crusher, etc. As with the replacement method, it is sufficient by the compaction machine / rolling machine It is important to In addition, there may be used a material obtained by mixing a high quality roadbed material such as particle size control crushed stone or crusher and cement.

このように置換工法やセメント安定処理工法は、十分な締固めを行う必要があり、例えば終電から始発の限られた時間内に作業を行うことが求められる鉄道軌道の路盤改良、言い換えれば保線の現場にはほとんど用いられていない。   Thus, the replacement method and the cement stabilization method require sufficient compaction, for example, the improvement of the track base of the railway track where work is required to be performed within the limited time of the first train from the last power, in other words It is rarely used in the field.

これを受け、本願の出願人により、鉄道の路盤改良工法として簡易且つ短時間に施工が可能なグラウト充填路盤改良工法に関する研究が進められ、その成果工法が提案、実用化されている(例えば、非特許文献1参照)。   In response to this, the applicant of the present application has conducted research on a grout-filled roadbed base improvement method that can be simply and quickly constructed as a roadbed base improvement method for railways, and a result construction method has been proposed and put to practical use (for example, Non-Patent Document 1).

このグラウト充填路盤改良工法では、路盤改良の施工領域の路盤を掘削撤去し、その掘削した範囲に、バラスト等の砕石を敷き詰め、敷き詰めた砕石の間隙にグラウト材を充填して路盤改良層を構築する。   In this grout-filled roadbed improvement method, the roadbed in the construction area of the roadbed improvement is excavated and removed, the excavated area is covered with crushed stone such as ballast, and the gap between the crushed crushed stone is filled with grout material to construct a roadbed improved layer Do.

これによれば、グラウト材を充填しこれが硬化することで、従来の路盤改良工法で必要な締固め作業を不要にでき、且つ均一な剛性の層を構築することが可能になる。また、敷き詰める砕石に発生バラストを用いれば環境負荷低減を図ることができ、新品のバラスト(砕石)を用いれば施工スピードの向上を図ることができる。   According to this, by filling the grout material and curing it, it becomes possible to eliminate the need for the compaction operation required in the conventional roadbed improvement method and to construct a uniform rigid layer. In addition, if the generated ballast is used for the crushed stone to be laid, environmental load can be reduced, and if a new ballast (crushed stone) is used, the construction speed can be improved.

中村貴久、桃谷尚嗣、伊藤壱記、村本勝己:「発生バラストを活用した既設線路盤改良工法の開発」、公益財団法人鉄道総合技術研究所、総研報告(RTRI REPORT)Vol.27,No.4,2013年4月Takahisa Nakamura, Naosuke Momoya, Miki Ito, Katsumi Muramoto: "Development of an existing track improvement method using generated ballast", Research Report of Railway General Research Institute, Research Report (RTRI REPORT) Vol. 27, No. 4, April 2013

一方、上記従来のグラウト充填路盤改良工法においては、路盤の掘削、バラストの敷き詰め、グラウト材の充填を行って路盤改良層を構築し、構築した路盤改良層の上に道床バラスト、まくらぎを再敷設するという一連の作業を、例えば終電から始電までの間の限られた時間内で行う必要が生じる。このため、施工領域(施工区間)を大きくとることが難しく、この点で改良の余地が残されていた。   On the other hand, in the above-mentioned conventional grout-filled roadbed improvement method, excavating the roadbed, laying the ballast, filling the grout material to construct the roadbed improved layer, and re-establishing the roadbed ballast and sleeper on the constructed roadbed improved layer. A series of installation work needs to be performed within a limited time between, for example, the last power and the last power. Therefore, it is difficult to take a large construction area (construction section), and there is room for improvement in this respect.

言い換えれば、上記従来のグラウト充填路盤改良工法は、スポット的な施工に用いて好適であるため、施工区間が例えば50m以上であっても適用できるようにすることが強く望まれていた。   In other words, since the above-described conventional grout-filled roadbed improvement method is suitable for spot-like construction, it has been strongly desired to be able to apply it even if the construction section is 50 m or more, for example.

本発明は、上記事情に鑑み、施工性に優れ、施工領域を大きくして好適に鉄道の路盤改良を行うことを可能にする路盤改良工法を提供することを目的とする。   In view of the above circumstances, the present invention has an object to provide a roadbed improvement construction method which is excellent in workability and enables a roadbed improvement of a railway to be suitably performed by enlarging a construction area.

上記の目的を達するために、この発明は以下の手段を提供している。   In order to achieve the above object, the present invention provides the following means.

本発明の路盤改良工法は、鉄道の路盤を改良するための工法であって、既存の道床バラストを撤去して既存の路盤を露出させる道床バラスト撤去/既存路盤露出工程と、前記路盤を掘削して施工領域に凹所を形成する既存路盤掘削工程と、前記凹所に砕石を敷き詰めて充填し、充填砕石層を形成する砕石充填工程と、前記充填砕石層にグラウト材を注入充填するグラウト材充填工程とを備えるとともに、前記グラウト材充填工程を行う際に前記グラウト材を注入するための注入口と前記グラウト材の充填状況を確認するための充填確認口をそれぞれ、前記充填砕石層に形成、露出させるための注入口・確認口露出形成手段を設置する注入口・確認口露出形成手段設置工程を備えることを特徴とする。   The roadbed improvement method of the present invention is a method for improving the roadbed of a railway, and the roadbed ballast removing / existing roadbed exposing step for removing the existing roadbed ballast and exposing the existing roadbed and excavating the roadbed The existing roadbed excavating step of forming a recess in the construction area, the crushed stone filling step of filling and filling the crushed stone in the concave portion to form a filled crushed stone layer, and the grout material injecting and filling the filled crushed stone layer with grout material Forming an filling port for injecting the grout material when performing the grouting material filling process, and a filling confirmation port for confirming the filling condition of the grout material in the filling crushed stone layer. The method further comprises the steps of installing an inlet / confirmation port exposure forming means for installing an injection port / confirmation port exposure forming means for exposing.

本発明の路盤改良工法においては、前記注入口・確認口露出形成手段として、袋体に砕石を充填した砕石充填袋体を用い、前記凹所に前記砕石を敷き詰めて充填するとともに前記砕石充填袋体を前記凹所内に配設し、前記グラウト材充填工程を行う際に前記砕石充填袋体を撤去することによって前記注入口と前記充填確認口を露出、形成することが望ましい。   In the base course improvement method of the present invention, a crushed stone filled bag body filled with crushed stone in a bag body is used as the injection port and confirmation port exposure forming means, and the crushed stone is spread and filled in the recess and the crushed stone filled bag Preferably, the body is disposed in the recess and the injection port and the filling confirmation port are exposed and formed by removing the crushed stone filling bag body when performing the grout filling process.

本発明の路盤改良工法においては、前記注入口・確認口露出形成手段設置工程では、前記注入口・確認口露出形成手段のうち注入口露出形成手段を、平面視において前記充填砕石層の一方端部に設置し、前記注入口・確認口露出形成手段のうち確認口露出形成手段を、平面視において前記充填砕石層の他方端部に設置してもよい。   In the base course improvement method of the present invention, in the injection port / confirmation port exposure forming means installation step, the injection port exposure forming means among the injection port / confirmation port exposure forming means is one end of the filled crushed stone layer in plan view. It may be installed in a portion, and the confirmation port exposure forming means among the injection port / confirmation port exposure forming means may be installed at the other end of the filled crushed stone layer in plan view.

本発明の路盤改良工法においては、路盤を掘削撤去して路盤改良の施工領域に形成される凹所にバラストなどの砕石を敷き詰めて充填砕石層を形成する際に、グラウト材の注入口、充填確認口を形成、露出させるための注入口・確認口露出形成手段を設けることによって、充填砕石層(凹所)へのグラウト材の充填作業を任意のタイミングで行うことが可能になる。   In the roadbed improvement method according to the present invention, a grout injection port and a filling are formed when a roadbed is excavated and removed and a recess formed in a construction area for road improvement is filled with crushed stone such as ballast to form a filled crushed stone layer. By providing the injection port and the confirmation port exposure forming means for forming and exposing the confirmation port, it becomes possible to perform the filling operation of the grout material to the packed crushed stone layer (recess) at any timing.

これにより、道床バラスト撤去/既存路盤露出工程、既存路盤掘削工程、砕石充填工程、注入口・確認口露出形成手段設置工程、軌道復旧工程まで、例えば、終電から始電までの間に行って鉄道運転を再開させ、後日、注入口/充填確認口形成工程、グラウト材充填工程、道床バラスト敷設工程を終電から始電までの間に行って、施工領域の路盤改良工事を完了させることができる。   In this way, track ballast removal / existing roadbed exposure process, existing roadbed excavation process, crushed stone filling process, injection port / confirmation port exposure forming means installation process, track recovery process, for example, between the last train and the first train The operation can be resumed, and at a later date, the inlet / filling confirmation hole forming step, the grout filling step, and the track ballast laying step can be performed between the last turn and the turn-on to complete the base block improvement work in the construction area.

したがって、本発明の路盤改良工法によれば、限られた時間内で施工の全工程を完了させる必要がなく、全工程を区分して段階的に進めることができ、施工の全工程を限られた時間内に行うことが必要な従来の路盤改良工法と比較し、施工領域を大きく設定することが可能にある。よって、施工性の向上、路盤改良工事の低コスト化を図ることが可能になる。   Therefore, according to the roadbed improvement method of the present invention, it is not necessary to complete all the steps of construction within a limited time, and all steps can be divided and advanced stepwise, and all steps of construction are limited. Compared with the conventional roadbed improvement method that needs to be performed within a short time, it is possible to set a large construction area. Therefore, it becomes possible to aim at improvement of construction nature, and cost reduction of road base improvement construction.

本発明の一実施形態に係る路盤改良工法において、道床バラストを撤去して既存の路盤を露出させた状態を示す図である。In the base course improvement method concerning one embodiment of the present invention, it is a figure showing the state where the roadbed ballast was removed and the existing base course was exposed. 本発明の一実施形態に係る路盤改良工法において、既存の路盤を掘削して凹所を形成した状態を示す図である。The roadbed improvement construction method which concerns on one Embodiment of this invention WHEREIN: It is a figure which shows the state which excavated the existing roadbed and formed the recess. 本発明の一実施形態に係る路盤改良工法において、凹所に砕石を充填して充填砕石層を形成した状態を示す図である。The roadbed improvement construction method which concerns on one Embodiment of this invention WHEREIN: It is a figure which shows the state which filled the recess with crushed stone and formed the filled crushed stone layer. 本発明の一実施形態に係る路盤改良工法において、凹所に砕石を充填するとともに注入口・確認口露出形成手段の砕石充填袋体を凹所に設置した状態を示す図である。The roadbed improvement construction method concerning one embodiment of the present invention is a figure showing the state where a crushed stone was filled in a recess and a crushed stone filled bag body of an injection port and confirmation port exposure formation means was installed in a recess. 本発明の一実施形態に係る路盤改良工法において、充填砕石層の上にバラストを敷設するとともに注入口・確認口露出形成手段の砕石充填袋体を設置した状態を示す図である。In the base course improvement construction method concerning one embodiment of the present invention, it is a figure showing the state where a ballast was installed on a filling crushed stone layer and a crushed stone filling bag body of injection port and confirmation port exposure formation means was installed. 本発明の一実施形態に係る路盤改良工法において、充填砕石層の上にバラストを敷設するとともに注入口・確認口露出形成手段の砕石充填袋体を設置した状態で鉄道運行を再開させることを示す図である。In the base course improvement method according to one embodiment of the present invention, it is shown that the ballast operation is performed on the packed crushed stone layer and the railway operation is resumed with the crushed stone filled bag body of the inlet / outlet opening forming means installed. FIG. 本発明の一実施形態に係る路盤改良工法において、注入口・確認口露出形成手段の砕石充填袋体を撤去してグラウト材の注入口と充填確認口を形成、露出させた状態を示す図である。In the base course improvement method according to an embodiment of the present invention, the crushed stone filled bag body of the inlet / confirmation port exposure forming means is removed to form a grout material inlet and a filling confirmation port, and a diagram showing the exposed state. is there. 本発明の一実施形態に係る路盤改良工法において、充填砕石層、凹所にグラウト材を充填している状態を示す図である。The roadbed improvement construction method concerning one embodiment of the present invention WHEREIN: It is a figure which shows the state which is filling grout material in a filling crushed stone layer and a recess. 本発明の一実施形態に係る路盤改良工法において、充填砕石層、凹所にグラウト材を充填している状態を示す図である。The roadbed improvement construction method concerning one embodiment of the present invention WHEREIN: It is a figure which shows the state which is filling grout material in a filling crushed stone layer and a recess. 本発明の一実施形態に係る路盤改良工法において、充填砕石層、凹所にグラウト材を充填している状態を示す図である。The roadbed improvement construction method concerning one embodiment of the present invention WHEREIN: It is a figure which shows the state which is filling grout material in a filling crushed stone layer and a recess. 本発明の一実施形態に係る路盤改良工法において、充填砕石層、凹所にグラウト材を充填した状態を示す図である。The roadbed improvement construction method concerning one embodiment of the present invention WHEREIN: It is a figure which shows the state which filled the filling crushed stone layer and the recess with the grout material. 本発明の一実施形態に係る路盤改良工法において、路盤改良が完了した状態を示す図である。In the base course improvement method concerning one embodiment of the present invention, it is a figure showing the state where base course improvement was completed. 本発明の一実施形態に係る路盤改良工法において、注入口・確認口露出形成手段の変更例を示す図である。In the base course improvement method concerning one embodiment of the present invention, it is a figure showing the example of change of a pouring opening and confirmation opening exposure formation means. 図13の平面図である。It is a top view of FIG.

以下、図1から図12を参照し、本発明の一実施形態に係る路盤改良工法について説明する。ここで、本実施形態は、路盤改良の施工領域の路盤を掘削撤去し、その掘削した範囲にバラストなどの砕石を敷き詰め、敷き詰めた砕石の間隙にグラウト材を充填して路盤改良層を構築する鉄道の路盤改良工法に関するものである。   Hereinafter, with reference to FIGS. 1-12, the road-base improvement construction method which concerns on one Embodiment of this invention is demonstrated. Here, this embodiment excavates and removes the roadbed in the construction area of roadbed improvement, lays up crushed stone such as ballast in the excavated area, and fills grout material in the space of the laid crushed stone to construct a roadbed improved layer It relates to the roadbed improvement method for railways.

具体的に、本実施形態の路盤改良工法では、図1に示すように、施工領域(施工区間)のまくらぎ1及びレール2を適宜支保手段を用いて仮支持し、バックホウ等の建設機械3を用いるなどして既存の道床バラスト4を施工領域外に仮置きする。これにより、改良対象の既存の路盤5を露出させる(道床バラスト撤去/既存路盤露出工程)。   Specifically, in the roadbed improvement method of the present embodiment, as shown in FIG. 1, the sleepers 1 and the rails 2 in the construction area (construction section) are temporarily supported using support means as appropriate, and construction machines such as backhoes 3 Temporarily place the existing roadbed ballast 4 outside the construction area. Thereby, the existing roadbed 5 to be improved is exposed (roadbed ballast removal / existing roadbed exposure step).

次に、図2に示すように、バラスト4を撤去して露出した施工領域の路盤5を、所定の幅(例えば3m)、所定の深さ(例えば30cm)まで掘削し、施工領域全体に凹所6を形成する(既存路盤掘削工程)。   Next, as shown in FIG. 2, the roadbed 5 in the construction area exposed by removing the ballast 4 is excavated to a predetermined width (for example 3 m) and a predetermined depth (for example 30 cm) and recessed all over the construction area Station 6 (existing roadbed excavation process).

次に、図3に示すように、例えば発生バラスト4、新品バラストなどの砕石7を凹所6に敷き詰めて充填する(砕石充填工程)。このとき、例えば、凹所6の底面6a側から砕石7を複数層(多段階:本実施形態では例えば15cm厚の2層)に分けて敷き詰めるようにし、各層の砕石7を敷設する毎にプレートランマ等の締固め機械/転圧機械8を用いてしっかりと締固める。   Next, as shown in FIG. 3, crushed stones 7 such as, for example, a generated ballast 4 and a new ballast are laid in the recess 6 and filled (crushed stone filling step). At this time, for example, the crushed stone 7 is divided into a plurality of layers (multistage: for example, two layers of 15 cm thick in this embodiment) from the bottom 6a side of the recess 6 and a plate is provided each time the crushed stone 7 of each layer is laid. Firmly compact using a compactor / rolling machine 8 such as a rammer.

また、本実施形態の路盤改良工法においては、図4に示すように、上層の砕石7を凹所6に敷設する際に、土嚢などの袋体にバラスト等の砕石7を充填した砕石充填袋体9を上層の一部に配置し、他の部分に砕石7をそのまま充填して上層の砕石敷設、転圧を行う(第一砕石充填袋体敷設工程/注入口・確認口露出形成手段設置工程)。   Further, in the roadbed improvement method of the present embodiment, as shown in FIG. 4, when laying the crushed stone 7 in the upper layer in the recess 6, a crushed stone filled bag in which a bag body such as sandbag is filled with crushed stone 7 such as ballast. Place the body 9 in a part of the upper layer, fill the other part with the crushed stone 7 as it is, lay the crushed stone in the upper layer, and carry out rolling pressure (First crushed stone filled bag body laying process / inlet and confirmation port exposure forming means installed Process).

この砕石充填袋体9は、後工程のグラウト材充填工程を行う際にグラウト材の注入口、グラウト材の充填確認口を形成、露出させるための注入口・確認口露出形成手段である。   The crushed stone filling bag 9 is a means for forming an injection port and a confirmation port for forming and exposing a grout material inlet and a grout material filling confirmation port when performing a grout material filling process in a later step.

本実施形態では、凹所6の幅方向両端部側と、中央部とに砕石充填袋体9を敷設する。また、中央部の砕石充填袋体9は軌道方向に隣り合うまくらぎ1の間に配設し、幅方向両端部側の砕石充填袋体9は、適宜施工領域/施工区間の軌道方向に例えば5m〜10m程度の間隔をあけて配設する。なお、後述するグラウト材の充填時に、砕石充填袋体9の下面位置までグラウト材の充填が確認されたら、配設部(注入口及び充填確認口)にバラスト(砕石)を投入し、再度グラウト材を充填する。このようにすると、グラウト材を充填する際、凹所6の砕石充填位置よりも低い位置でグラウト材を充填し、そのオーバーフローを考慮した充填を行うことができる。すなわち、グラウト材が砕石充填袋体9の下面位置までグラウト材の充填が確認されたら、配設部(注入口及び充填確認口)にバラストを投入し、再度グラウト材を充填することで、砕石充填袋体9の配設高さまで精度良くグラウト材を充填することが可能になる。   In the present embodiment, the crushed stone-filled bag body 9 is laid on both widthwise end portions of the recess 6 and the central portion. In addition, the crushed stone filling bag body 9 in the central part is disposed adjacent to each other in the track direction and is disposed between the side walls 1, and the crushed stone filling bag body 9 on both ends in the width direction is appropriately It arranges at intervals of about 5m-10m. In addition, when filling of the grout material is confirmed to the lower surface position of the crushed stone filling bag body 9 at the time of filling of the grout material described later, ballast (crushed stone) is put into the arrangement portion (injection port and filling confirmation port), and grout again Fill the material. In this way, when the grout material is filled, the grout material can be filled at a position lower than the crushed stone filling position of the recess 6, and the filling can be performed in consideration of the overflow. That is, when it is confirmed that the grout material is filled with the grout material to the lower surface position of the crushed stone filling bag body 9, ballast is charged into the arrangement portion (the inlet and the filling confirmation port) and the grout material is filled again. The grout material can be filled with high accuracy up to the height at which the filling bag 9 is disposed.

次に、図5に示すように、凹所6に敷設した砕石充填袋体9の上方に仮支保用且つ注入口・確認口露出形成手段として砕石充填袋体10を積み上げ(第二砕石充填袋体敷設工程/注入口・確認口露出形成手段設置工程)、仮支保用の砕石充填袋体10を積み上げて形成された砕石袋体群11の間に発生バラスト4あるいは新品バラストなどのバラスト12を敷設する。これとともに、支保手段による仮支持状態を解除して施工領域のまくらぎ1を新たに敷設し直したバラスト12に支持させて敷設する。また、敷設したまくらぎ1にレール2を接続する(軌道復旧工程)。   Next, as shown in FIG. 5, a crushed stone filled bag body 10 is stacked above the crushed stone filled bag body 9 laid in the recess 6 as a temporary support and an inlet / outlet opening forming means (second crushed stone filled bag Between the laying of crushed stone bags 11 formed by stacking the crushed stone filled bags 10 for temporary support, and a ballast 12 such as a new ballast etc. Lay down. At the same time, the temporary support state by the support means is released, and the sleeper 1 in the construction area is supported by the newly re-layed ballast 12 for laying. In addition, the rail 2 is connected to the laid sleeper 1 (track recovery process).

これにより、図6に示すように、施工領域は、凹所6に充填した砕石7の分だけ道床が厚い状態となり、鉄道車両20の運行を再開できる状態となる(鉄道運行再開工程)。すなわち、上述の既存のバラスト撤去から新たにバラストを敷設し直す作業までを例えば終電から始電までの間に行えば、路盤改良工事によって鉄道車両20の運行に支障をきたすことがない。   As a result, as shown in FIG. 6, in the construction area, the roadbed becomes thicker by the amount of crushed stone 7 filled in the recess 6, and the operation of the railcar 20 can be resumed (railroad operation restart process). That is, if the work from the removal of the existing ballast described above to the work of laying the ballast anew is performed, for example, from the last power to the power delivery, the operation of the railway vehicle 20 is not hindered by the road improvement work.

次に、上記の鉄道軌道の状態で鉄道運行を通常通りに行い、例えば終電をむかえ、再度路盤改良工事を再開する際には、図7に示すように、仮支保用の砕石充填袋体10の少なくとも一部を撤去するとともに、凹所6に敷設した砕石充填袋体9を撤去し、凹所6の充填砕石層13の各層を露出させる。このとき、砕石充填袋体9、10が土嚢などの袋体にバラスト等の砕石7を充填したものであるため、袋部分を持って人力で引き上げるなどして砕石充填袋体9、10を撤去することができる。   Next, the railway operation is normally performed in the above-mentioned railway track condition, for example, when the final power is cut off and the road improvement work is resumed again, as shown in FIG. And the crushed stone-filled bag body 9 laid in the recess 6 is removed to expose each layer of the filled crushed stone layer 13 in the recess 6. At this time, since the crushed stone filling bags 9 and 10 are filled with crushed stones 7 such as ballast in bags such as sandbags, the broken bags 9 and 10 are removed by manually pulling up the bag portion and holding the bag portion. can do.

そして、施工領域の複数箇所で充填砕石層13が露出し、これら複数の充填砕石層13の露出面をグラウト材の注入口14やグラウト材の充填確認口15とする(注入口/充填確認口形成工程)。   Then, the filled crushed stone layer 13 is exposed at a plurality of locations in the construction area, and the exposed surfaces of the plurality of filled crushed stone layers 13 are used as the inlet 14 for grout material and the filling confirmation port 15 for grout material (inlet / filling confirmation port Formation process).

次に、図8、図9に示すように、注入口14からゲルタイムを有するセメント系のグラウト材(A液、B液の注入材を用いた2液、懸濁型の注入材)16を充填砕石層13の最下層に充填する。このとき、充填砕石層13の最下層の充填確認口15からのグラウト材16の漏出を確認することでグラウト材16の充填管理を行う。なお、セメント系グラウト材16としては、例えば2〜5分程度のゲルタイム(グラウト材の流動性が著しく低下するまでの時間)を有するグラウト材を用いることが好ましい。   Next, as shown in FIGS. 8 and 9, a cement-based grout material (a two-component liquid using a liquid A, a liquid B, and a liquid of suspension type) 16 having a gel time is filled from the injection port 14 The bottom layer of the crushed stone layer 13 is filled. At this time, filling control of the grout material 16 is performed by confirming leakage of the grout material 16 from the filling confirmation opening 15 of the lowermost layer of the filled crushed stone layer 13. In addition, as the cement-based grout material 16, it is preferable to use a grout material having, for example, a gel time of about 2 to 5 minutes (a time until the fluidity of the grout material significantly decreases).

図10、図11に示すように、充填砕石層13の最下層にグラウト材16を充填した後、上層に順次、最下層と同様にしてグラウト材16を注入、充填してゆく。このとき、砕石充填袋体9を撤去して形成された凹所6内の空間には、適宜充填確認口15、注入口14を形成するように層毎に砕石7を充填する(グラウト材充填工程)。   As shown in FIGS. 10 and 11, after the lowermost layer of the packed crushed stone layer 13 is filled with the grout material 16, the grout material 16 is sequentially injected and filled in the upper layer in the same manner as the lowermost layer. At this time, crushed stone 7 is filled in each layer so as to form the filling confirmation port 15 and the injection port 14 appropriately in the space in the recess 6 formed by removing the crushed stone filled bag body 9 (grout material filled Process).

そして、充填砕石層13の全て、すなわち凹所6全体にグラウト材16を注入充填して路盤改良部17を形成した段階で、図12に示すように、残りの仮支保用の砕石充填袋体10を撤去するとともに、撤去した砕石充填袋体10の部分等に新たにバラスト12を敷設して埋め戻す(道床バラスト敷設工程)。なお、砕石充填袋体10を残置して道床軌道を形成してもよい。   Then, after the grouting material 16 is injected and filled in all of the filled crushed stone layer 13, that is, the entire recess 6, to form the base improvement section 17, as shown in FIG. 10 is removed, and a ballast 12 is newly laid on the portion of the crushed stone-filled bag body 10 or the like which has been removed, and is backfilled (roadbed ballast laying step). The crushed stone-filled bag body 10 may be left to form a track bed track.

したがって、本実施形態の路盤改良工法においては、路盤5を掘削撤去して路盤改良の施工領域に形成される凹所6にバラストなどの砕石7を敷き詰めて充填砕石層13を形成する際に、グラウト材16の注入口14、充填確認口15を形成、露出させるための注入口・確認口露出形成手段9を設けることによって、充填砕石層13(凹所6)へのグラウト材16の充填作業を任意のタイミングで行うことが可能になる。   Therefore, in the roadbed improvement method of the present embodiment, when the roadbed 5 is excavated and removed and the crushed stone 7 such as a ballast is spread in the recess 6 formed in the installation area of the roadbed improvement to form the filled crushed stone layer 13 Filling the grout material 16 into the crushed crushed stone layer 13 (recess 6) by providing the inlet / confirmation port exposure forming means 9 for forming and exposing the injection port 14 and the filling confirmation port 15 of the grout material 16 Can be performed at any time.

これにより、道床バラスト撤去/既存路盤露出工程、既存路盤掘削工程、砕石充填工程、注入口・確認口露出形成手段設置工程、軌道復旧工程まで、例えば、終電から始電までの間に行って鉄道運転を再開させ、後日、注入口/充填確認口形成工程、グラウト材充填工程、道床バラスト敷設工程を終電から始電までの間に行って、施工領域の路盤改良工事を完了させることができる。   In this way, track ballast removal / existing roadbed exposure process, existing roadbed excavation process, crushed stone filling process, injection port / confirmation port exposure forming means installation process, track recovery process, for example, between the last train and the first train The operation can be resumed, and at a later date, the inlet / filling confirmation hole forming step, the grout filling step, and the track ballast laying step can be performed between the last turn and the turn-on to complete the base block improvement work in the construction area.

すなわち、本実施形態の路盤改良工法においては、限られた時間内で施工の全工程を完了させる必要がなく、全工程を区分して段階的に進めることが可能になる。   That is, in the roadbed improvement method of the present embodiment, it is not necessary to complete all the steps of construction within a limited time, and it becomes possible to divide all the steps and proceed stepwise.

よって、本実施形態の路盤改良工法によれば、施工の全工程を限られた時間内に行うことが必要な従来の路盤改良工法と比較し、施工領域を大きく設定することができ、施工性の向上、路盤改良工事の低コスト化を図ることが可能になる。   Therefore, according to the roadbed improvement method of the present embodiment, the construction area can be set larger compared to the conventional roadbed improvement method which requires that all the steps of the construction be performed within a limited time, and the workability And cost reduction of road improvement work.

以上、本発明に係る路盤改良工法の一実施形態について説明したが、本発明は上記の一実施形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。   As mentioned above, although one Embodiment of the road-base improvement construction method which concerns on this invention was described, this invention is not limited to said one embodiment, It can change suitably in the range which does not deviate from the meaning.

例えば、本実施形態では、グラウト材16の注入口14、充填確認口15を形成、露出させるための注入口・確認口露出形成手段が砕石充填袋体9、10であるものとしたが、これに限定する必要はない。例えば、図13に示すように、砕石充填工程で凹所6に砕石7を敷設充填し、軌道復旧工程時に、注入口・確認口露出形成手段としての注入管18、確認管19を凹所6に一端部側を挿入しつつ他端部側を外部に配して設置し(注入口・確認口露出形成手段設置工程)、これら注入管18、確認管19によってグラウト材16の注入口14、充填確認口15を形成、露出させるようにしてもよい。この場合には、注入管18、確認管19を利用してグラウト材16の注入、充填確認管理を行うことができ、本実施系と同様の作用効果を得ることが可能である。   For example, in the present embodiment, the injection port / confirmation port exposure forming means for forming and exposing the injection port 14 and the filling confirmation port 15 of the grout material 16 is the crushed stone filling bags 9 and 10, but There is no need to limit it to For example, as shown in FIG. 13, the crushed stone 7 is placed and filled in the recess 6 in the crushed stone filling process, and the injection pipe 18 and the confirmation pipe 19 as the injection port / confirmation port exposure forming means are recessed 6 The other end side is placed outside and installed while inserting one end side (inlet and confirmation port exposure forming means installation step), the inlet 14 of the grout material 16 by the injection pipe 18 and the confirmation pipe 19, The filling confirmation port 15 may be formed and exposed. In this case, the injection of the grout material 16 and the filling confirmation management can be performed using the injection pipe 18 and the confirmation pipe 19, and it is possible to obtain the same function and effect as the present embodiment.

図14は、図13の平面図である。前述した注入口・確認口露出形成手段設置工程では、注入口露出形成手段としての注入管18を、平面視において充填砕石層13の一方端部に設置し、確認口露出形成手段としての確認管19のうち端部確認管191(第1端部確認管191a、第2端部確認管191b)を、平面視において充填砕石層13の他方端部に設置する。注入管18および端部確認管191は、一対のレール2を挟んで相互に反対側に配置される。なお、凹所6の内部に形成された充填砕石層13は、レール2の延伸方向に沿って伸びる。注入管18は、充填砕石層13の幅方向の一方端部に配置される。端部確認管191は、充填砕石層13の幅方向の他方端部に配置される。第1端部確認管191aは、レール2の延伸方向において注入管18と同じ位置に配置される。第2端部確認管191bは、レール2の延伸方向において路盤改良の施工区間の末端部に配置される。なお端部確認管191の他に、中間部確認管192を設置してもよい。中間部確認管192は、例えば一対のレール2の間であって、隣り合うまくらぎ1の間に配置される。   FIG. 14 is a plan view of FIG. In the injection port / confirmation port exposure forming means installation step described above, the injection pipe 18 as the injection port exposure forming means is installed at one end of the crushed crushed stone layer 13 in plan view, and the confirmation pipe as the inspection port exposure forming means The end confirmation pipe 191 (a first end confirmation pipe 191a and a second end confirmation pipe 191b) among the parts 19 is installed at the other end of the packed crushed stone layer 13 in plan view. The injection pipe 18 and the end confirmation pipe 191 are disposed on opposite sides of the pair of rails 2. The packed crushed stone layer 13 formed inside the recess 6 extends along the extending direction of the rail 2. The injection pipe 18 is disposed at one end in the width direction of the packed crushed stone layer 13. The end confirmation pipe 191 is disposed at the other end of the packed crushed stone layer 13 in the width direction. The first end confirmation pipe 191 a is disposed at the same position as the injection pipe 18 in the extending direction of the rail 2. The second end confirmation pipe 191 b is disposed at the end of the installation section of the base improvement in the extension direction of the rail 2. In addition to the end portion confirmation pipe 191, an intermediate portion confirmation pipe 192 may be installed. The middle part confirmation tube 192 is disposed, for example, between the pair of rails 2 and between adjacent pairs 1.

注入管18により露出した注入口14から充填砕石層13にグラウト材16を注入する。注入管18を充填砕石層13の一方端部に設置したので、グラウト材16は充填砕石層13の一方端部から充填される。グラウト材16は、図14に示す第1領域A1、第2領域A2の順に流れ広がる。その後、端部確認管191により露出した充填確認口15でグラウト材の充填を確認する。端部確認管191を充填砕石層13の他方端部に設置したので、グラウト材16が充填砕石層13の他方端部まで充填されたことを確認できる。第1端部確認管191aに加えて、施工区間の末端部に配置した第2端部確認管191bでグラウト材16の充填を確認する。これにより、充填砕石層13の全体にグラウト材が充填されたことを確認できる。
図14では、実施形態の変形例(注入口・確認口露出形成手段として注入管18、確認管19を採用する場合)について説明したが、実施形態(注入口・確認口露出形成手段として砕石充填袋体10を採用する場合)についても同様である。
The grout material 16 is injected into the packed crushed stone layer 13 from the injection port 14 exposed by the injection pipe 18. Since the injection pipe 18 is disposed at one end of the packed crushed stone layer 13, the grout material 16 is filled from one end of the filled crushed stone layer 13. The grout material 16 flows and spreads in the order of the first area A1 and the second area A2 shown in FIG. Thereafter, the filling of the grout material is confirmed at the filling confirmation port 15 exposed by the end confirmation pipe 191. Since the end confirmation pipe 191 is installed at the other end of the packed crushed stone layer 13, it can be confirmed that the grout material 16 is filled up to the other end of the filled crushed stone layer 13. In addition to the first end confirmation tube 191a, the filling of the grout material 16 is confirmed by the second end confirmation tube 191b disposed at the end of the construction section. Thereby, it can be confirmed that the whole of the packed crushed stone layer 13 is filled with the grout material.
In FIG. 14, the modified example of the embodiment (in the case where the injection pipe 18 and the confirmation pipe 19 are adopted as the injection port / confirmation port exposure forming means) has been described, The same applies to the case where the bag 10 is adopted.

また、グラウト材16の注入口14、充填確認口15の配置、数は、施工条件等に応じて適宜決めればよく、本実施形態のように限定する必要はない。   Further, the arrangement and the number of the inlets 14 and the filling confirmation openings 15 of the grout material 16 may be determined appropriately according to the construction conditions and the like, and it is not necessary to limit as in the present embodiment.

1 まくらぎ
2 レール
3 建設機械
4 道床バラスト
5 路盤
6 凹所
6a 底面
7 砕石
8 締固め機械/転圧機械
9 砕石充填袋体(注入口・確認口露出形成手段)
10 砕石充填袋体(注入口・確認口露出形成手段)
11 砕石袋体群
12 バラスト
13 充填砕石層
14 注入口
15 充填確認口
16 グラウト材
17 路盤改良部
18 注入管
19 確認管
191 端部確認管
191a 第1端部確認管
191b 第2端部確認管
192 中間部確認管
DESCRIPTION OF SYMBOLS 1 sleeper 2 rail 3 construction machine 4 floor ballast 5 base 6 recess 6a bottom 7 crushed stone 8 compacting machine / rolling machine 9 crushed stone filled bag body (inlet / confirmation port exposure forming means)
10 crushed stone filled bag (inlet and confirmation port exposure forming means)
11 Crushed Bag Group 12 Ballast 13 Filled Crushed Bed 14 Inlet 15 Filling Confirmation Port 16 Grout Material 17 Basement Improvement Part 18 Injection Pipe 19 Verification Pipe 191 End Verification Pipe 191a First End Verification Pipe 191b Second End Verification Pipe 192 Intermediate check tube

Claims (3)

鉄道の路盤を改良するための工法であって、
既存の道床バラストを撤去して既存の路盤を露出させる道床バラスト撤去/既存路盤露出工程と、
前記路盤を掘削して施工領域に凹所を形成する既存路盤掘削工程と、
前記凹所に砕石を敷き詰めて充填し、充填砕石層を形成する砕石充填工程と、
前記充填砕石層にグラウト材を注入充填するグラウト材充填工程とを備えるとともに、
前記グラウト材充填工程を行う際に前記グラウト材を注入するための注入口と前記グラウト材の充填状況を確認するための充填確認口をそれぞれ、前記充填砕石層に形成、露出させるための注入口・確認口露出形成手段を設置する注入口・確認口露出形成手段設置工程を備えることを特徴とする路盤改良工法。
It is a construction method to improve the roadbed of the railway,
Road floor ballast removal / existing road base exposure process, which removes existing road base ballast and exposes existing road base,
An existing roadbed excavating step of excavating the roadbed and forming a recess in a construction area;
Crushed stone filling step of laying the crushed stone in the recess and filling it, to form a filled crushed stone layer;
Grouting material filling step of injecting and filling grout material into the packed crushed stone layer;
An injection port for injecting the grout material when performing the grout material filling step and an injection port for forming and exposing a filling confirmation port for confirming the filling condition of the grout material in the filled crushed stone layer -A channel improvement method characterized in that it comprises an injection port and confirmation port exposure forming means installation step of installing a confirmation port exposure forming means.
請求項1記載の路盤改良工法において、
前記注入口・確認口露出形成手段として、袋体に砕石を充填した砕石充填袋体を用い、
前記凹所に前記砕石を敷き詰めて充填するとともに前記砕石充填袋体を前記凹所内に配設し、前記グラウト材充填工程を行う際に前記砕石充填袋体を撤去することによって前記注入口と前記充填確認口を露出、形成することを特徴とする路盤改良工法。
In the roadbed improvement method according to claim 1,
The crushed stone filled bag body in which the crushed body is filled in the bag body is used as the injection port / confirmation port exposure forming means,
The crushed stone is laid and filled in the recess and the crushed stone filled bag is disposed in the recess, and the inlet and the inlet are removed by removing the crushed stone filled bag when performing the grout filling step. A basement improvement method characterized by exposing and forming a filling confirmation opening.
請求項1または2記載の路盤改良工法において、
前記注入口・確認口露出形成手段設置工程では、
前記注入口・確認口露出形成手段のうち注入口露出形成手段を、平面視において前記充填砕石層の一方端部に設置し、
前記注入口・確認口露出形成手段のうち確認口露出形成手段を、平面視において前記充填砕石層の他方端部に設置することを特徴とする路盤改良工法。
In the subgrade improvement method according to claim 1 or 2,
In the injection port / confirmation port exposure forming means installation step,
The injection port exposure forming means of the injection port / confirmation port exposure forming means is disposed at one end of the packed crushed stone layer in plan view,
A channel improvement method characterized in that the confirmation port exposure forming means among the injection port / confirmation port exposure forming means is installed at the other end of the packed crushed stone layer in plan view.
JP2017221957A 2017-11-17 2017-11-17 Roadbed improvement method Active JP7107665B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017221957A JP7107665B2 (en) 2017-11-17 2017-11-17 Roadbed improvement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017221957A JP7107665B2 (en) 2017-11-17 2017-11-17 Roadbed improvement method

Publications (2)

Publication Number Publication Date
JP2019094616A true JP2019094616A (en) 2019-06-20
JP7107665B2 JP7107665B2 (en) 2022-07-27

Family

ID=66971075

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017221957A Active JP7107665B2 (en) 2017-11-17 2017-11-17 Roadbed improvement method

Country Status (1)

Country Link
JP (1) JP7107665B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111663385A (en) * 2020-06-24 2020-09-15 中铁二院工程集团有限责任公司 Construction method for completing rapid restoration of settlement of integral ballast bed in skylight period
CN112200503A (en) * 2020-11-26 2021-01-08 德阳中州创智科技有限公司 Evaluation method for evaluating railway roadbed compaction quality
CN115852767A (en) * 2022-12-08 2023-03-28 山西省交通科技研发有限公司 Structure and method for rapidly treating uneven settlement of bridge head
CN117051626A (en) * 2023-09-06 2023-11-14 中国铁道科学研究院集团有限公司 Continuous upward arch repairing method for ballastless track subgrade in end thorn area under operation condition

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS49119304A (en) * 1973-03-26 1974-11-14
JPH01207502A (en) * 1988-02-10 1989-08-21 Murayama Doken:Kk Temporary restoration in burying work for pipeline or the like
JPH07310302A (en) * 1994-05-16 1995-11-28 Osada Giken Kk Reinforcing method of ballast track foundation
JPH07317008A (en) * 1994-05-27 1995-12-05 Osaka Gas Co Ltd Temporary back-filling method
JP2002129503A (en) * 2000-10-25 2002-05-09 East Japan Railway Co Method for repairing slab type track
JP2005344475A (en) * 2004-06-07 2005-12-15 Railway Technical Res Inst Method of repairing base course and base course
JP2008274627A (en) * 2007-04-27 2008-11-13 Central Japan Railway Co Ballast fixing work and ballasted track
JP2015168969A (en) * 2014-03-06 2015-09-28 株式会社アレン Form for repairing slab type track, and construction method for repairing filling layer of slab type track
JP2015190178A (en) * 2014-03-28 2015-11-02 住友大阪セメント株式会社 Filler supply method and repair method for maintenance-free track

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS49119304A (en) * 1973-03-26 1974-11-14
JPH01207502A (en) * 1988-02-10 1989-08-21 Murayama Doken:Kk Temporary restoration in burying work for pipeline or the like
JPH07310302A (en) * 1994-05-16 1995-11-28 Osada Giken Kk Reinforcing method of ballast track foundation
JPH07317008A (en) * 1994-05-27 1995-12-05 Osaka Gas Co Ltd Temporary back-filling method
JP2002129503A (en) * 2000-10-25 2002-05-09 East Japan Railway Co Method for repairing slab type track
JP2005344475A (en) * 2004-06-07 2005-12-15 Railway Technical Res Inst Method of repairing base course and base course
JP2008274627A (en) * 2007-04-27 2008-11-13 Central Japan Railway Co Ballast fixing work and ballasted track
JP2015168969A (en) * 2014-03-06 2015-09-28 株式会社アレン Form for repairing slab type track, and construction method for repairing filling layer of slab type track
JP2015190178A (en) * 2014-03-28 2015-11-02 住友大阪セメント株式会社 Filler supply method and repair method for maintenance-free track

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
中村貴久、桃谷尚嗣、伊藤壱記、村本勝己: "発生バラストを活用した既設線路盤改良工法", 鉄道総研報告, vol. 第27巻第4号, JPN6021026504, April 2013 (2013-04-01), JP, pages 23 - 28, ISSN: 0004672151 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111663385A (en) * 2020-06-24 2020-09-15 中铁二院工程集团有限责任公司 Construction method for completing rapid restoration of settlement of integral ballast bed in skylight period
CN112200503A (en) * 2020-11-26 2021-01-08 德阳中州创智科技有限公司 Evaluation method for evaluating railway roadbed compaction quality
CN112200503B (en) * 2020-11-26 2022-07-22 德阳中州创智科技有限公司 Evaluation method for evaluating railway roadbed compaction quality
CN115852767A (en) * 2022-12-08 2023-03-28 山西省交通科技研发有限公司 Structure and method for rapidly treating uneven settlement of bridge head
CN117051626A (en) * 2023-09-06 2023-11-14 中国铁道科学研究院集团有限公司 Continuous upward arch repairing method for ballastless track subgrade in end thorn area under operation condition
CN117051626B (en) * 2023-09-06 2024-04-02 中国铁道科学研究院集团有限公司 Continuous upward arch repairing method for ballastless track subgrade in end thorn area under operation condition

Also Published As

Publication number Publication date
JP7107665B2 (en) 2022-07-27

Similar Documents

Publication Publication Date Title
JP2019094616A (en) Roadbed improvement method
CN108797249A (en) The construction method of soft soil roadbed high roadbed steep slope road section Foam lightweight soil
KR101260397B1 (en) Single Pile Concrete Track Structure and Its Settlement Recovering Device
CN109914173B (en) Foam light soil pouring table back structure in expressway reconstruction and extension project and construction method thereof
KR101076029B1 (en) Replacing Method of Old Train Track using Twin-Block Type Train Track
CN112048955A (en) Construction method for backfilling gravel roadbed
CN104358196B (en) Highway open to traffic Embankment Subsidence disposes the construction method of structure
CN209039896U (en) The soft soil roadbed three-dimensional reinforced structure of convolution is knitted in a kind of stake-
CN109371910B (en) Ground-cushion height-filling protection and construction method
JP5843413B1 (en) Lowering method of existing tunnel
KR101739657B1 (en) Roller Compacted Concrete And Rockfill Dam
CN110284432B (en) Construction method for filling bridge abutment in high-fill area after first construction
CN103993533B (en) For the comprehensive debulking methods of Canal in Loess Area high-filled embankment
JP6177468B1 (en) Installation or replacement of tunnel inverts in service
CA2848527A1 (en) Railway track support system
CN209836721U (en) Embankment widening longitudinal joint treatment structure
JP2019124019A (en) Invert construction method to existing tunnel
RU2551174C1 (en) Motor road on permafrost soils
CN101672182B (en) Method for leading shield to pass through underground structure
CN110778341B (en) Backfill construction method for construction vertical shaft and construction transverse passage
RU2344231C1 (en) Method of foundation bed construction by horizontal reinforcing with precast concrete components
CN110258625A (en) A kind of construction method of filled-up ground retaining wall
JP6523980B2 (en) Construction method of Tenchudo floor track
CN210856822U (en) New and old embankment longitudinal joint reinforced structure
KR20140036767A (en) Construction method for railway roadbed

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200903

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20200903

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20200903

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210630

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210713

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210823

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220104

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220218

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220705

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220714

R150 Certificate of patent or registration of utility model

Ref document number: 7107665

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150