JP2018104989A - Ceiling suspending member - Google Patents

Ceiling suspending member Download PDF

Info

Publication number
JP2018104989A
JP2018104989A JP2016252470A JP2016252470A JP2018104989A JP 2018104989 A JP2018104989 A JP 2018104989A JP 2016252470 A JP2016252470 A JP 2016252470A JP 2016252470 A JP2016252470 A JP 2016252470A JP 2018104989 A JP2018104989 A JP 2018104989A
Authority
JP
Japan
Prior art keywords
ceiling
plate
hanging jig
holding
board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2016252470A
Other languages
Japanese (ja)
Inventor
英一 大野
Eiichi Ono
英一 大野
浩二 臼木
Koji Usuki
浩二 臼木
太一 安田
Taichi Yasuda
太一 安田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ono Komuten Kk
Usuki Komuten Kk
Daiwa House Industry Co Ltd
Original Assignee
Ono Komuten Kk
Usuki Komuten Kk
Daiwa House Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ono Komuten Kk, Usuki Komuten Kk, Daiwa House Industry Co Ltd filed Critical Ono Komuten Kk
Priority to JP2016252470A priority Critical patent/JP2018104989A/en
Publication of JP2018104989A publication Critical patent/JP2018104989A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a ceiling suspending member with which an operation to fix a ceiling panel on a ceiling beam can be efficiently carried out.SOLUTION: A ceiling suspending member comprises: supporting parts 11, 21 being supported by being hooked at a ceiling beam B; holding parts 12, 22 holding a ceiling panel A by receiving a lower surface of the ceiling panel A arranged at a lower part of the beam B; connection parts 13, 23 connecting the supporting parts 11, 21 with the holding parts 12, 22; and suction parts 14, 24 configured by a magnet and capable of being stuck to the beam B.SELECTED DRAWING: Figure 3

Description

本発明は、天井パネルを天井の梁に固定する際に用いられる天井吊治具の技術に関する。   The present invention relates to a technique of a ceiling hanging jig used when a ceiling panel is fixed to a ceiling beam.

従来、天井パネルを天井の梁に固定する際に用いられる天井吊治具の技術は公知となっている。例えば、特許文献1に記載の如くである。   Conventionally, the technique of the ceiling hanging jig used when fixing a ceiling panel to a ceiling beam is known. For example, as described in Patent Document 1.

特許文献1に記載される天井吊治具(組付け治具)は、長尺の水平部材及び複数の取付け部を具備する。複数の取付け部は、互いに間隔を空けて水平部材に固定される。複数の取付け部は、それぞれ複数の天井パネルにビスで固定されることで、複数の天井パネル同士を接続する。当該複数の天井パネルは、吊り上げられて梁に対して位置合わせされた後で、梁に固定される。その後、前記天井吊治具は、複数の天井パネルから取り外される。   The ceiling suspension jig (assembly jig) described in Patent Document 1 includes a long horizontal member and a plurality of attachment portions. The plurality of attachment portions are fixed to the horizontal member at intervals. The plurality of attachment portions are fixed to the plurality of ceiling panels with screws, thereby connecting the plurality of ceiling panels to each other. The plurality of ceiling panels are fixed to the beam after being lifted and aligned with the beam. Thereafter, the ceiling hanging jig is removed from the plurality of ceiling panels.

特許文献1に記載される天井吊治具は、複数の天井パネルから取り外すために、工具を用いてビスを取り外す必要がある。このため、天井パネルを梁に固定する作業を効率的に行うことが困難であった。   In order to remove the ceiling hanging jig described in Patent Document 1 from a plurality of ceiling panels, it is necessary to remove the screws using a tool. For this reason, it has been difficult to efficiently perform the work of fixing the ceiling panel to the beam.

特許第5064948号公報Japanese Patent No. 5064948

本発明は、以上の如き状況を鑑みてなされたものであり、その解決しようとする課題は、天井パネルを天井の梁に固定する作業を効率的に行うことが可能な天井吊治具を提供するものである。   The present invention has been made in view of the situation as described above, and a problem to be solved is to provide a ceiling hanging jig capable of efficiently performing a work of fixing a ceiling panel to a ceiling beam. To do.

本発明の解決しようとする課題は以上の如くであり、次にこの課題を解決するための手段を説明する。   The problem to be solved by the present invention is as described above. Next, means for solving the problem will be described.

即ち、請求項1においては、天井の梁に支持される支持部と、梁の下方に配置された天井パネルを保持する保持部と、支持部と保持部とを接続する接続部と、を具備するものである。   That is, according to the first aspect of the present invention, a support portion supported by the beam on the ceiling, a holding portion that holds the ceiling panel disposed below the beam, and a connection portion that connects the support portion and the holding portion are provided. To do.

請求項2においては、支持部は、接続部から突出し、梁に引っ掛けられることで支持されるものである。   According to a second aspect of the present invention, the support portion protrudes from the connection portion and is supported by being hooked on the beam.

請求項3においては、保持部は、接続部から突出し、天井パネルの下面を受けることで保持するものである。   According to a third aspect of the present invention, the holding portion protrudes from the connection portion and is held by receiving the lower surface of the ceiling panel.

請求項4においては、梁に吸着可能な吸着部をさらに具備するものである。   According to a fourth aspect of the present invention, the apparatus further includes an adsorption portion that can be adsorbed to the beam.

請求項5においては、吸着部は、磁石によって構成されるものである。   According to a fifth aspect of the present invention, the attracting portion is constituted by a magnet.

請求項6においては、支持部、保持部及び接続部は、一枚の板状部材に一体的に形成されるものである。   According to a sixth aspect of the present invention, the support portion, the holding portion, and the connection portion are integrally formed on a single plate-like member.

請求項7においては、板面の向きが互いに異なる一対の板状部材によって構成されるものである。   In Claim 7, it is comprised by a pair of plate-shaped member from which the direction of a plate surface differs mutually.

請求項8においては、一対の板状部材は、互いに開閉自在に連結されるものである。   In the eighth aspect, the pair of plate-like members are connected to each other so as to be freely opened and closed.

本発明の効果として、以下に示すような効果を奏する。   As effects of the present invention, the following effects can be obtained.

請求項1においては、天井パネルを天井の梁に固定する作業を効率的に行うことができる。   In Claim 1, the operation | work which fixes a ceiling panel to a beam of a ceiling can be performed efficiently.

請求項2においては、支持部を梁に簡単に支持させることができる。   In the second aspect, the support portion can be easily supported by the beam.

請求項3においては、天井パネルを保持部で簡単に保持できる。   In Claim 3, a ceiling panel can be easily hold | maintained with a holding | maintenance part.

請求項4においては、支持部を梁から外れ難くすることができる。   According to the fourth aspect of the present invention, the support portion can be made difficult to come off the beam.

請求項5においては、金属製の梁に吸着部を簡単に吸着させることができる。   According to the fifth aspect of the present invention, the adsorption portion can be easily adsorbed to the metal beam.

請求項6においては、天井吊治具の構成を簡素化できる。   In Claim 6, the structure of a ceiling suspension jig | tool can be simplified.

請求項7においては、向きが互いに異なる複数の部材をまとめて仮固定することができる。   In the seventh aspect, a plurality of members having different directions can be temporarily fixed together.

請求項8においては、天井吊治具を持ち運び易くなる。   In Claim 8, it becomes easy to carry a ceiling hanging jig.

(a)天井吊治具を示した左前方斜視図。(b)同じく、右後方斜視図。(A) Left front perspective view showing a ceiling hanging jig. (B) Similarly, a right rear perspective view. 第一の板材及び第二の板材を閉じて天井パネルを仮固定する様子を示した一部断面斜視図。The partial cross section perspective view which showed a mode that the 1st board | plate material and the 2nd board | plate material were closed and the ceiling panel was temporarily fixed. 第一の板材及び第二の板材を開いて天井パネルを仮固定する様子を示した一部断面斜視図。The partial cross section perspective view which showed a mode that the 1st board | plate material and the 2nd board | plate material were opened and a ceiling panel was temporarily fixed. 天井パネル及び梁を示した右側面図。The right view which showed the ceiling panel and the beam. 同じく、斜視図。Similarly, a perspective view. 別実施形態に係る天井吊治具を示した斜視図。The perspective view which showed the ceiling hanging jig | tool which concerns on another embodiment.

以下の説明においては、図中に記した矢印に従って、上下方向、左右方向及び前後方向をそれぞれ定義する。   In the following description, the up-down direction, the left-right direction, and the front-rear direction are defined according to the arrows shown in the figure.

以下では、本発明の一実施形態に係る天井吊治具1について説明する。   Below, the ceiling hanging jig 1 which concerns on one Embodiment of this invention is demonstrated.

天井吊治具1は、図4に示す天井パネルAを天井の梁Bに固定する際に用いられるものである。   The ceiling hanging jig 1 is used when the ceiling panel A shown in FIG.

まず、図4及び図5を参照して、天井パネルA及び梁Bの構成について簡単に説明する。   First, with reference to FIG.4 and FIG.5, the structure of the ceiling panel A and the beam B is demonstrated easily.

天井パネルAは、建物の天井面を構成するためのものである。また、天井パネルAは、格子状に形成される枠体である。図5において、天井パネルAは、左右方向に並んで二つ配置される。天井パネルAは、長尺材A1〜A3及び短尺材A4〜A8を具備する。   The ceiling panel A is for constituting the ceiling surface of the building. The ceiling panel A is a frame formed in a lattice shape. In FIG. 5, two ceiling panels A are arranged side by side in the left-right direction. The ceiling panel A includes long materials A1 to A3 and short materials A4 to A8.

長尺材A1〜A3は、その長手方向を前後方向に向けた略直方体状の部材である。長尺材A1〜A3は、木材によって構成される。長尺材A1〜A3は、左右方向に間隔をあけて三つ配置される。長尺材A1〜A3は、左側に配置される長尺材A1から順に符号に付した数字が大きくなっている。左右中央の長尺材A2は、左側及び右側の長尺材A1・A3よりもその高さが低くなっている。   The long materials A1 to A3 are substantially rectangular parallelepiped members whose longitudinal directions are directed in the front-rear direction. The long materials A1 to A3 are made of wood. Three long materials A1 to A3 are arranged at intervals in the left-right direction. As for long material A1-A3, the number attached | subjected to the code | symbol becomes large in order from long material A1 arrange | positioned on the left side. The length of the long material A2 at the center of the left and right is lower than that of the left and right long materials A1 and A3.

短尺材A4〜A8は、その長手方向を左右方向に向けて配置される略直方体状の部材である。短尺材A4〜A8は、前後方向に間隔をあけて五つ配置される。短尺材A4〜A8は、前側に配置される短尺材A4から順に符号に付した数字が大きくなっている。短尺材A4〜A8は、その長さ(左右方向幅)が長尺材A1〜A3の長さ(前後方向幅)よりも短くなるように形成される。短尺材A4〜A8の左端部は、左側の長尺材A1に固定される。短尺材A4〜A8の右端部は、右側の長尺材A3に固定される。短尺材A4〜A8は、その左右中央部に凹部が形成されており、当該凹部に左右中央の長尺材A2が挿通されて固定される。   The short materials A4 to A8 are substantially rectangular parallelepiped members that are arranged with their longitudinal directions directed in the left-right direction. Five short materials A4-A8 are arrange | positioned at intervals in the front-back direction. As for short material A4-A8, the number attached | subjected to the code | symbol becomes large sequentially from short material A4 arrange | positioned at the front side. The short materials A4 to A8 are formed so that the length (width in the left-right direction) is shorter than the length (width in the front-rear direction) of the long materials A1 to A3. The left end portions of the short materials A4 to A8 are fixed to the left long material A1. The right ends of the short materials A4 to A8 are fixed to the right long material A3. As for short material A4-A8, the recessed part is formed in the left-right center part, and the elongate material A2 of the left-right center is penetrated to the said recessed part, and is fixed.

なお、天井パネルAは、天井の全域に亘って適宜並んで配置されている。すなわち、天井パネルAは、図5に示す天井パネルA以外にも前後方向及び左右方向に並んで複数配置されている。   In addition, the ceiling panel A is arrange | positioned along with the whole area of the ceiling suitably. That is, a plurality of ceiling panels A are arranged side by side in the front-rear direction and the left-right direction in addition to the ceiling panel A shown in FIG.

梁Bは、その長手方向を左右方向(短尺材A4〜A8の長手方向と同一方向)に向けて配置される。梁Bには、金具Cを介して天井パネルAが固定される。本実施形態に係る梁Bは、H形鋼によって構成される。図4及び図5において、梁Bは、前後方向に間隔を空けて三つ配置される。前側の梁Bの下方には、前端部の短尺材A4が配置される。前後中央の梁Bの下方には、前後中央の短尺材A6が配置される。後側の梁Bの下方には、後端部の短尺材A8が配置される。梁Bは、上フランジB1、下フランジB2及びウェブB3を具備する。   The beam B is arranged with its longitudinal direction directed in the left-right direction (the same direction as the longitudinal direction of the short materials A4 to A8). A ceiling panel A is fixed to the beam B via a metal fitting C. The beam B according to this embodiment is made of H-section steel. 4 and 5, three beams B are arranged at intervals in the front-rear direction. Below the front beam B, a short material A4 at the front end is arranged. Below the front-rear center beam B, a front-rear center short material A6 is arranged. Below the rear beam B, a short material A8 at the rear end is arranged. The beam B includes an upper flange B1, a lower flange B2, and a web B3.

上フランジB1は、梁Bの上部に形成される板状の部分である。下フランジB2は、梁Bの下部(上フランジB1の下方)に形成される板状の部分である。上フランジB1及び下フランジB2は、その板面を上下方向に向けて互いに対向するように配置される。   The upper flange B <b> 1 is a plate-like part formed on the upper part of the beam B. The lower flange B2 is a plate-like portion formed below the beam B (below the upper flange B1). The upper flange B1 and the lower flange B2 are arranged so that their plate surfaces face each other in the vertical direction.

ウェブB3は、梁Bの上下中途部に形成される板状の部分である。ウェブB3は、その板面を前後方向に向けて配置される。ウェブB3は、その上端部が上フランジB1の前後中央部と接続される。ウェブB3は、その下端部が下フランジB2の前後中央部と接続される。   The web B <b> 3 is a plate-like part formed in the middle part of the beam B. The web B3 is disposed with its plate surface facing in the front-rear direction. The upper end of the web B3 is connected to the front / rear center of the upper flange B1. The lower end of the web B3 is connected to the front and rear center of the lower flange B2.

なお、梁Bは、天井の全域に亘って間隔をあけて複数配置されている。より詳細には、梁Bは、図4及び図5に示す梁B以外にも前後方向に間隔をあけて複数配置されている。また、梁Bは、その長手方向を前後方向に向けたものが左右方向に間隔をあけて複数配置されている。   A plurality of beams B are arranged at intervals over the entire area of the ceiling. More specifically, a plurality of beams B are arranged at intervals in the front-rear direction other than the beams B shown in FIGS. 4 and 5. Further, a plurality of beams B whose longitudinal direction is directed in the front-rear direction are arranged at intervals in the left-right direction.

次に、図1を参照して、天井吊治具1の構成について説明する。天井吊治具1は、天井パネルAを梁Bに仮固定するためのものである。なお、本実施形態において仮固定とは、天井吊治具1を天井パネルA及び梁Bから簡単に(例えば、作業者が工具を用いることなく)外せるような状態で、天井パネルAを梁Bに固定することを指す。天井吊治具1は、第一の板材10、第二の板材20及びヒンジ30を具備する。   Next, the configuration of the ceiling hanging jig 1 will be described with reference to FIG. The ceiling hanging jig 1 is for temporarily fixing the ceiling panel A to the beam B. In the present embodiment, the temporary fixing means that the ceiling panel A can be easily removed from the ceiling panel A and the beam B (for example, without an operator using a tool). Refers to fixing to. The ceiling hanging jig 1 includes a first plate member 10, a second plate member 20, and a hinge 30.

第一の板材10は、その上部及び下部が前方に突出するような側面視略C字状に形成される板状部材である。第一の板材10は、支持部11、保持部12、接続部13及び吸着部14を具備する。   The first plate member 10 is a plate-like member formed in a substantially C shape in a side view so that the upper and lower portions protrude forward. The first plate member 10 includes a support part 11, a holding part 12, a connection part 13, and a suction part 14.

支持部11は、第一の板材10の上部(前方に突出する部分)である。支持部11は、その突出している長さ(前後方向幅)が梁Bの下フランジB2の短手方向幅(前後方向幅)の半分程度となるような側面視略矩形状に形成される(図2参照)。支持部11は、切欠部11aを具備する。切欠部11aは、支持部11の前上端部を前下方に切り欠いたような形状に形成される。   The support part 11 is an upper part (a part protruding forward) of the first plate member 10. The support portion 11 is formed in a substantially rectangular shape in a side view such that the protruding length (width in the front-rear direction) is about half the width in the short direction (width in the front-rear direction) of the lower flange B2 of the beam B ( (See FIG. 2). The support part 11 comprises a notch part 11a. The notch portion 11a is formed in a shape such that the front upper end portion of the support portion 11 is notched forward and downward.

保持部12は、第一の板材10の下部(前方に突出する部分)である。保持部12は、その突出している長さ(前後方向幅)が支持部11の突出している長さ(前後方向幅)よりも長い側面視略矩形状に形成される。また、保持部12は、その突出している長さが長尺材A1〜A3(図3参照)の短手方向幅(左右方向幅)の2倍程度となるように形成される。保持部12は、切欠部12aを具備する。切欠部12aは、保持部12の前下端部を前上方に切り欠いたような形状に形成される。   The holding part 12 is a lower part (a part protruding forward) of the first plate member 10. The holding part 12 is formed in a substantially rectangular shape in a side view in which the protruding length (front-rear direction width) is longer than the protruding length (front-rear direction width) of the support part 11. Moreover, the holding | maintenance part 12 is formed so that the protrusion length may become about twice the short direction width | variety (left-right direction width | variety) of long material A1-A3 (refer FIG. 3). The holding | maintenance part 12 comprises the notch part 12a. The cutout portion 12a is formed in a shape such that the front lower end portion of the holding portion 12 is cut out in the front upper direction.

接続部13は、支持部11と保持部12とを接続する部分である。接続部13は、側面視略矩形状に形成される。接続部13は、第一の板材10の上端部から下端部までに亘って形成される。接続部13は、上側切欠部13a及び下側切欠部13bを具備する。上側切欠部13aは、接続部13の後上端部を後下方に切り欠いたような形状に形成される。下側切欠部13bは、接続部13の後下端部を後上方に切り欠いたような形状に形成される。   The connection portion 13 is a portion that connects the support portion 11 and the holding portion 12. The connection part 13 is formed in a substantially rectangular shape in a side view. The connecting portion 13 is formed from the upper end portion to the lower end portion of the first plate member 10. The connection part 13 includes an upper notch part 13a and a lower notch part 13b. The upper notch 13a is formed in a shape such that the rear upper end portion of the connecting portion 13 is notched rearward and downward. The lower notch 13b is formed in a shape such that the rear lower end of the connecting portion 13 is notched rearward and upward.

吸着部14は、梁B(金属製の部材)に吸着可能な部分である。吸着部14は、略直方体状に形成される。吸着部14は、その下面が支持部11の下面と面一となるように、支持部11の右面の下端部に固定される。吸着部14は、磁石によって構成される。   The adsorption part 14 is a part that can be adsorbed to the beam B (metal member). The adsorption part 14 is formed in a substantially rectangular parallelepiped shape. The suction portion 14 is fixed to the lower end portion of the right surface of the support portion 11 so that the lower surface thereof is flush with the lower surface of the support portion 11. The adsorption part 14 is configured by a magnet.

このように構成される第一の板材10は、支持部11、保持部12及び接続部13が合板によって一体的に形成される。   As for the 1st board | plate material 10 comprised in this way, the support part 11, the holding | maintenance part 12, and the connection part 13 are integrally formed by the plywood.

第二の板材20は、その板面の向きが異なる(前後方向を向けて配置される)点を除いて、第一の板材10と同様に構成される。すなわち、第二の板材20は、第一の板材10の支持部11、保持部12、接続部13及び吸着部14と同様に構成される支持部21、保持部22、接続部23及び吸着部24を具備する。また、支持部21及び保持部22は、第一の板材10の支持部11及び保持部12の切欠部11a・12aと同一形状に形成される切欠部21a・22aを具備する。また、接続部23は、第一の板材10の接続部13の上側切欠部13a及び下側切欠部13bと同一形状に形成される上側切欠部23a及び下側切欠部23bを具備する。   The 2nd board | plate material 20 is comprised similarly to the 1st board | plate material 10 except the point from which the direction of the board surface differs (it arrange | positions toward the front-back direction). That is, the second plate member 20 includes a support unit 21, a holding unit 22, a connection unit 23, and a suction unit configured similarly to the support unit 11, the holding unit 12, the connection unit 13, and the suction unit 14 of the first plate member 10. 24. Further, the support portion 21 and the holding portion 22 include notches 21 a and 22 a formed in the same shape as the support portions 11 of the first plate member 10 and the notches 11 a and 12 a of the holding portion 12. The connecting portion 23 includes an upper notch portion 23a and a lower notch portion 23b that are formed in the same shape as the upper notch portion 13a and the lower notch portion 13b of the connecting portion 13 of the first plate member 10.

ヒンジ30は、第一の板材10及び第二の板材20を開閉自在(相対的に回動自在)に連結する部材である。ヒンジ30は、第一の板材10(接続部13)の左面及び第二の板材20(接続部23)の前面に固定される。本実施形態に係るヒンジ30は、第一の板材10の板面と第二の板材20の板面とが成す角度(鋭角)が90°となるまで、第一の板材10及び第二の板材20を開くことができる。また、ヒンジ30は、第一の板材10の板面と第二の板材20の板面とが同一方向を向くまで、第一の板材10及び第二の板材20を閉じることができる(図2参照)。   The hinge 30 is a member that connects the first plate member 10 and the second plate member 20 so as to be freely opened and closed (relatively rotatable). The hinge 30 is fixed to the left surface of the first plate member 10 (connection portion 13) and the front surface of the second plate member 20 (connection portion 23). The hinge 30 according to this embodiment includes the first plate member 10 and the second plate member until the angle (acute angle) formed by the plate surface of the first plate member 10 and the plate surface of the second plate member 20 becomes 90 °. 20 can be opened. Further, the hinge 30 can close the first plate member 10 and the second plate member 20 until the plate surface of the first plate member 10 and the plate surface of the second plate member 20 face the same direction (FIG. 2). reference).

なお、以下においては、第一の板材10の板面と第二の板材20の板面とが成す角度が90°となるまで開いた状態(図1に示す状態)を「全開状態」と称する。また、第一の板材10の板面と第二の板材20の板面とが同一方向を向くまで閉じた状態(図2に示す状態)を「全閉状態」と称する。   In the following description, a state where the angle between the plate surface of the first plate member 10 and the plate surface of the second plate member 20 is 90 ° (state shown in FIG. 1) is referred to as a “fully open state”. . A state where the plate surface of the first plate member 10 and the plate surface of the second plate member 20 are closed in the same direction (state shown in FIG. 2) is referred to as a “fully closed state”.

次に、図2から図5までを参照して、天井吊治具1を用いて天井パネルAを梁Bに固定する手順について説明する。なお、以下においては、図5に示す左側及び右側の天井パネルAを、図4に示す三つの梁Bに固定する手順を例に挙げて説明する。また、以下においては、左側の天井パネルAを「天井パネルA10」、右側の天井パネルAを「天井パネルA20」と称する。また、以下においては、前側の梁Bを「梁B10」、前後中央の梁Bを「梁B20」、後側の梁Bを「梁B30」と称する。   Next, a procedure for fixing the ceiling panel A to the beam B using the ceiling hanging jig 1 will be described with reference to FIGS. In the following, a procedure for fixing the left and right ceiling panels A shown in FIG. 5 to the three beams B shown in FIG. 4 will be described as an example. In the following, the left ceiling panel A is referred to as “ceiling panel A10”, and the right ceiling panel A is referred to as “ceiling panel A20”. In the following, the front beam B is referred to as “beam B10”, the front and rear central beam B is referred to as “beam B20”, and the rear beam B is referred to as “beam B30”.

まず、左側の天井パネルA10は、図5に示す符号P1で前側の梁B10に仮固定される。このとき、図4及び図5に示すように、天井パネルA10は、作業者に持ち上げられる等して、三つの梁B10〜B30の下方に移動される。そして、天井パネルA10は、天井吊治具1によって仮固定される。   First, the left ceiling panel A10 is temporarily fixed to the front beam B10 with reference P1 shown in FIG. At this time, as shown in FIGS. 4 and 5, the ceiling panel A <b> 10 is moved below the three beams B <b> 10 to B <b> 30 by being lifted by an operator. The ceiling panel A10 is temporarily fixed by the ceiling hanging jig 1.

このとき、図2に示すように、天井吊治具1は、全閉状態となるまで閉じられ、第一の板材10及び第二の板材20の板面が左右方向に向けられる。当該第一の板材10及び第二の板材20の支持部11・21は、前側の梁B10の下フランジB2に後方から引っ掛けられて当該下フランジB2に支持される。このとき、保持部12・22は、短尺材A4の下方に配置され、当該短尺材A4の下面を受ける。また、吸着部14・24は、下フランジB2に吸着する。また、接続部13・23は、その前面が下フランジB2の後端部と当接する。これによって、天井吊治具1は、梁B10及び天井パネルA10に後方から取り付けられる。以上によって、天井吊治具1は、符号P1で短尺材A4を梁B10に仮固定する。   At this time, as shown in FIG. 2, the ceiling hanging jig 1 is closed until it is fully closed, and the plate surfaces of the first plate member 10 and the second plate member 20 are directed in the left-right direction. The support portions 11 and 21 of the first plate member 10 and the second plate member 20 are hooked from behind on the lower flange B2 of the front beam B10 and supported by the lower flange B2. At this time, the holding portions 12 and 22 are disposed below the short material A4 and receive the lower surface of the short material A4. Moreover, the adsorption | suction parts 14 and 24 adsorb | suck to lower flange B2. Further, the front surfaces of the connection portions 13 and 23 come into contact with the rear end portion of the lower flange B2. Thereby, the ceiling hanging jig 1 is attached to the beam B10 and the ceiling panel A10 from the rear. As described above, the ceiling hanging jig 1 temporarily fixes the short material A4 to the beam B10 with the symbol P1.

本実施形態に係る天井吊治具1は、前側の梁B10に支持部11・21を引っ掛けるだけ(単純な動作)で、支持部11・21を梁B10に支持させることができると共に、保持部12・22で短尺材A4を保持することができる。   The ceiling hanging jig 1 according to the present embodiment can support the support portions 11 and 21 on the beam B10 only by hooking the support portions 11 and 21 on the beam B10 on the front side (simple operation). The short material A4 can be held at 12.22.

また、左側の天井パネルA10は、図5に示す符号P2で後側の梁B30に仮固定される。このとき、天井パネルA10は、天井吊治具1(符号P1で仮固定した天井吊治具1とは異なる天井吊治具1)によって、符号P1で仮固定された手順と同じ手順により、短尺材A8が梁B30に仮固定される。   Further, the left ceiling panel A10 is temporarily fixed to the rear beam B30 with reference P2 shown in FIG. At this time, the ceiling panel A10 is shortened by the same procedure as the procedure temporarily fixed by the reference sign P1 by the ceiling suspension jig 1 (the ceiling suspension jig 1 different from the ceiling suspension jig 1 temporarily fixed by the reference sign P1). The material A8 is temporarily fixed to the beam B30.

次に、右側の天井パネルA20は、図5に示す符号P3・P4で天井吊治具1(符号P1・P2で仮固定した天井吊治具1とは異なる天井吊治具1)によって仮固定される。このとき、天井パネルA20は、符号P1・P2で仮固定された手順と同じ手順により仮固定される。   Next, the ceiling panel A20 on the right side is temporarily fixed by the ceiling hanging jig 1 (the ceiling hanging jig 1 different from the ceiling hanging jig 1 temporarily fixed by the signs P1 and P2) by the symbols P3 and P4 shown in FIG. Is done. At this time, the ceiling panel A20 is temporarily fixed by the same procedure as that temporarily fixed by the symbols P1 and P2.

次に、左側及び右側の天井パネルA10・A20は、図5に示す符号P5で天井吊治具1(符号P1〜P4で仮固定した天井吊治具1とは異なる天井吊治具1)によって前後中央の梁B20に仮固定される。   Next, the left and right ceiling panels A10 and A20 are provided with a ceiling suspension jig 1 (ceiling suspension jig 1 different from the ceiling suspension jig 1 temporarily fixed with reference numerals P1 to P4) with a reference symbol P5 shown in FIG. Temporarily fixed to the front and rear beams B20.

図3及び図5に示すように、天井吊治具1は、符号P5で左側及び右側の天井パネルA10・A20をまとめて仮固定する。このとき、天井吊治具1は、全開状態となるまで開かれる。そして、第一の板材10は、その板面が左右方向に向けられる。また、第二の板材20は、その板面が前後方向を向けられる。第一の板材10の支持部11は、前後中央の梁B20の下フランジB2に後方から引っ掛けられて当該下フランジB2に支持される。このとき、第一の板材10の保持部12は、天井パネルA20の短尺材A6の下方に配置され、当該短尺材A6の下面を受ける。また、第一の板材10の吸着部14は、下フランジB2に吸着する。また、第一の板材10の接続部13は、その前面が下フランジB2の後端部と当接する。   As shown in FIGS. 3 and 5, the ceiling suspension jig 1 temporarily fixes the left and right ceiling panels A10 and A20 together with reference numeral P5. At this time, the ceiling hanging jig 1 is opened until it is fully opened. And as for the 1st board | plate material 10, the board surface is orient | assigned to the left-right direction. Further, the plate surface of the second plate member 20 is directed in the front-rear direction. The support portion 11 of the first plate member 10 is hooked from behind at the lower flange B2 of the beam B20 at the front and rear center and supported by the lower flange B2. At this time, the holding | maintenance part 12 of the 1st board | plate material 10 is arrange | positioned under the short material A6 of ceiling panel A20, and receives the lower surface of the said short material A6. Moreover, the adsorption | suction part 14 of the 1st board | plate material 10 adsorb | sucks to lower flange B2. Further, the front surface of the connection portion 13 of the first plate member 10 is in contact with the rear end portion of the lower flange B2.

また、第二の板材20の保持部22は、右側の天井パネルA20の長尺材A1及び左側の天井パネルA10の長尺材A3の下方に配置され、当該長尺材A1・A3の下面を同時に受ける。これによって、天井吊治具1は、前後中央の梁B20及び天井パネルA10・A20に取り付けられる。以上によって、天井吊治具1は、符号P5で長尺材A1・A3及び短尺材A6(天井パネルA10・A20)をまとめて梁B20に仮固定する。   The holding portion 22 of the second plate member 20 is disposed below the long material A1 of the right ceiling panel A20 and the long material A3 of the left ceiling panel A10, and the lower surfaces of the long materials A1 and A3 are arranged on the lower surface. Receive at the same time. Thereby, the ceiling hanging jig 1 is attached to the beam B20 and the ceiling panels A10 and A20 at the front and rear center. As described above, the ceiling hanging jig 1 temporarily fixes the long materials A1 and A3 and the short materials A6 (ceiling panels A10 and A20) to the beam B20 by reference P5.

左側及び右側の天井パネルA10・A20は、符号P1〜P5で三つの梁B10〜B30に仮固定された後で、梁B10〜B30に対する位置合わせが行われる。上述の如く、天井吊治具1は、支持部11・21が下フランジB2に引っ掛けられて支持されているだけである。また、天井吊治具1は、天井パネルA10・A20の下面を保持部12・22で受けているだけである。このため、天井パネルA10・A20は、簡単に(例えば、前後方向に押されるだけで)梁B10〜B30に対して相対移動することができる。このように、天井吊治具1によって天井パネルA10・A20を仮固定することで、天井パネルA10・A20の位置合わせを簡単に行うことができる。   The left and right ceiling panels A10 and A20 are temporarily fixed to the three beams B10 to B30 with reference numerals P1 to P5, and then aligned with the beams B10 to B30. As described above, the ceiling hanging jig 1 is only supported by the support portions 11 and 21 being hooked on the lower flange B2. Moreover, the ceiling suspension jig 1 only receives the lower surfaces of the ceiling panels A10 and A20 by the holding portions 12 and 22. For this reason, the ceiling panels A10 and A20 can be moved relative to the beams B10 to B30 easily (for example, simply by being pushed in the front-rear direction). In this way, by temporarily fixing the ceiling panels A10 and A20 with the ceiling hanging jig 1, the ceiling panels A10 and A20 can be easily aligned.

図4に示すように、左側及び右側の天井パネルA10・A20は、位置合わせが行われた後で、金具Cを介して三つの梁B10〜B30に固定される。そして、天井吊治具1は、梁B10〜B30及び天井パネルA10・A20から引き抜かれることで、梁B10〜B30等から外される。以上によって、天井吊治具1を用いた天井パネルA10・A20の固定が完了する。なお、梁B10〜B30に固定された天井パネルA10・A20には、下方から天井面を成す面材(不図示)が固定される。   As shown in FIG. 4, the left and right ceiling panels A10 and A20 are fixed to the three beams B10 to B30 via the metal fittings C after being aligned. The ceiling hanging jig 1 is removed from the beams B10 to B30 and the like by being pulled out from the beams B10 to B30 and the ceiling panels A10 and A20. Thus, the fixing of the ceiling panels A10 and A20 using the ceiling hanging jig 1 is completed. A face material (not shown) that forms the ceiling surface from below is fixed to the ceiling panels A10 and A20 fixed to the beams B10 to B30.

本実施形態に係る天井吊治具1によれば、左側及び右側の天井パネルA10・A20を三つの梁B10〜B30に仮固定できるため、当該天井パネルA10・A20を位置合わせした状態を維持することができる。このため、当該天井パネルA10・A20を固定する際に当該天井パネルA10・A20の位置がずれてしまうことを抑制できる。また、梁B10〜B30等から天井吊治具1を引き抜くだけで、梁B10〜B30から簡単に(工具等を用いることなく)天井吊治具1を外すことができる。以上により、天井パネルA10・A20を固定する作業を効率的に行うことができる。   According to the ceiling hanging jig 1 according to the present embodiment, since the left and right ceiling panels A10 and A20 can be temporarily fixed to the three beams B10 to B30, the state in which the ceiling panels A10 and A20 are aligned is maintained. be able to. For this reason, when fixing the said ceiling panel A10 * A20, it can suppress that the position of the said ceiling panel A10 * A20 shifts | deviates. Moreover, the ceiling suspension jig 1 can be easily removed from the beams B10 to B30 by simply pulling the ceiling suspension jig 1 out of the beams B10 to B30. As described above, the work of fixing the ceiling panels A10 and A20 can be efficiently performed.

また、天井吊治具1は、吸着部14・24を三つの梁B10〜B30(下フランジB2)に吸着させることで、支持部11・21を梁B10〜B30から外れ難くすることができる。これによれば、振動等によって意図しないタイミングで天井吊治具1が梁B10〜B30から外れてしまうことを抑制できる。   Moreover, the ceiling hanging jig 1 can make it difficult to remove the support parts 11 and 21 from the beams B10 to B30 by adsorbing the adsorption parts 14 and 24 to the three beams B10 to B30 (lower flange B2). According to this, it can suppress that the ceiling suspension jig | tool 1 remove | deviates from beams B10-B30 at the timing which is not intended by vibration etc.

また、本実施形態に係る三つの梁B10〜B30は、H形鋼、すなわち金属製の部材によって構成されている。そこで、本実施形態においては、吸着部14・24を磁石によって構成している。これによれば、支持部11・21を梁B10〜B30に引っ掛けた際に、吸着部14・24を梁B10〜B30に吸着させることができる。これによって、吸盤等を梁B10〜B30に吸着させる場合と比較して、吸着部14・24を梁B10〜B30に吸着させる動作が不要となるため、吸着部14・24を簡単に吸着させることができる。   Moreover, three beam B10-B30 which concerns on this embodiment is comprised by the member made from H-section steel, ie, metal. Therefore, in the present embodiment, the attracting portions 14 and 24 are configured by magnets. According to this, when the support parts 11 and 21 are hooked on the beams B10 to B30, the suction parts 14 and 24 can be attracted to the beams B10 to B30. This eliminates the need to suck the suction portions 14 and 24 to the beams B10 to B30 as compared with the case where the suction cups are sucked to the beams B10 to B30, so that the suction portions 14 and 24 can be easily sucked. Can do.

また、支持部11・21、保持部12・22及び接続部13・23は、第一の板材10及び第二の板材20に一体的に形成されている。これによれば、支持部11・21、保持部12・22及び接続部13・23を一つの部材で形成することができるため、天井吊治具1の部品点数を減らして天井吊治具1の構成を簡素化することができる。また、板状部材を適宜加工する(例えば、矩形状の板状部材を適宜切り欠く)だけで支持部11・21、保持部12・22及び接続部13・23を簡単に形成することができる。   Further, the support portions 11 and 21, the holding portions 12 and 22, and the connection portions 13 and 23 are formed integrally with the first plate member 10 and the second plate member 20. According to this, since the support parts 11 and 21, the holding parts 12 and 22 and the connection parts 13 and 23 can be formed by one member, the number of parts of the ceiling hanging jig 1 is reduced and the ceiling hanging jig 1 is reduced. The configuration can be simplified. Further, the support portions 11 and 21, the holding portions 12 and 22, and the connection portions 13 and 23 can be easily formed simply by appropriately processing the plate-like member (for example, appropriately cutting out the rectangular plate-like member). .

また、天井吊治具1は、ヒンジ30によって第一の板材10及び第二の板材20の板面の向きを互いに異なる向きにする(例えば、全開状態にする)ことができる。これによれば、梁B10〜B30の長手方向とは長手方向の向きが異なる長尺材A1〜A3を仮固定することができる。これにより、仮固定可能な部材を増やすことができるため、汎用性を向上させることができる。   Moreover, the ceiling hanging jig | tool 1 can make the direction of the plate | board surface of the 1st board | plate material 10 and the 2nd board | plate material 20 into mutually different directions by the hinge 30 (for example, let it be a full open state). According to this, long material A1-A3 from which the direction of a longitudinal direction differs from the longitudinal direction of beams B10-B30 can be temporarily fixed. Thereby, since the member which can be temporarily fixed can be increased, versatility can be improved.

ここで、例えば、第一の板材10だけで天井パネルA10・A20を符号P5で仮固定しようとすると、天井パネルA10の短尺材A6を仮固定する第一の板材10と、天井パネルA20の短尺材A6を仮固定する第一の板材10と、が必要(二枚の第一の板材10が必要)となる。これに対して、天井吊治具1を全開状態にすれば、第一の板材10及び第二の板材20で天井パネルA10・A20をまとめて仮固定することができる。これにより、第一の板材10だけで仮固定する場合と比較して、仮固定に要する天井吊治具1の数を減らすことができる。このため、天井パネルA10・A20(梁B10〜B30の長手方向に並んだ二つの天井パネルA10・A20)を仮固定する作業を効率的に行うことができる。   Here, for example, if the ceiling panel A10 / A20 is to be temporarily fixed with the reference sign P5 only by the first plate member 10, the first plate member 10 temporarily fixing the short member A6 of the ceiling panel A10 and the short member of the ceiling panel A20. The first plate material 10 for temporarily fixing the material A6 is necessary (two first plate materials 10 are necessary). On the other hand, if the ceiling hanging jig 1 is fully opened, the ceiling panels A10 and A20 can be temporarily fixed together by the first plate member 10 and the second plate member 20. Thereby, compared with the case where it fixes temporarily only with the 1st board | plate material 10, the number of the ceiling suspension jig | tools 1 required for temporary fixing can be reduced. For this reason, the operation | work which temporarily fixes ceiling panel A10 * A20 (two ceiling panels A10 * A20 arranged in the longitudinal direction of the beams B10-B30) can be performed efficiently.

以上の如く、本実施形態に係る天井吊治具1は、天井の梁Bに支持される支持部11・21と、梁Bの下方に配置された天井パネルAを保持する保持部12・22と、支持部11・21と保持部12・22とを接続する接続部13・23と、を具備するものである。   As described above, the ceiling hanging jig 1 according to this embodiment includes the support portions 11 and 21 supported by the beam B on the ceiling and the holding portions 12 and 22 that hold the ceiling panel A disposed below the beam B. And connecting portions 13 and 23 for connecting the support portions 11 and 21 and the holding portions 12 and 22 to each other.

このように構成することにより、天井の梁Bに天井パネルAを仮固定できるため、天井パネルAを天井の梁Bに固定する作業を効率的に行うことができる。   With this configuration, the ceiling panel A can be temporarily fixed to the ceiling beam B, so that the operation of fixing the ceiling panel A to the ceiling beam B can be efficiently performed.

また、支持部11・21は、接続部13・23から突出し、梁Bに引っ掛けられることで支持されるものである。   The support portions 11 and 21 protrude from the connection portions 13 and 23 and are supported by being hooked on the beam B.

このように構成することにより、支持部11・21を梁Bに簡単に(単純な動作で)支持させることができる。   With this configuration, the support portions 11 and 21 can be easily supported (by a simple operation) on the beam B.

また、保持部12・22は、接続部13・23から突出し、天井パネルAの下面を受けることで保持するものである。   The holding parts 12 and 22 protrude from the connection parts 13 and 23 and are held by receiving the lower surface of the ceiling panel A.

このように構成することにより、天井パネルAを保持部12・22で簡単に(単純な動作で)保持できる。   By configuring in this way, the ceiling panel A can be easily held by the holding portions 12 and 22 (by a simple operation).

また、梁Bに吸着可能な吸着部14・24をさらに具備するものである。   Further, the apparatus further includes suction portions 14 and 24 that can be attracted to the beam B.

このように構成することにより、支持部11・21を梁Bに対して相対移動させ難くすることができるため、支持部11・21を梁Bから外れ難くすることができる。   By configuring in this way, it is possible to make it difficult for the support portions 11 and 21 to move relative to the beam B, so that the support portions 11 and 21 cannot be easily detached from the beam B.

また、吸着部14・24は、磁石によって構成されるものである。   Moreover, the adsorption | suction part 14 * 24 is comprised with a magnet.

このように構成することにより、吸着部14・24を金属製の梁Bに接近させるだけで、吸着部14・24を梁Bに簡単に吸着させることができる。   By configuring in this way, the adsorption parts 14 and 24 can be easily adsorbed to the beam B simply by bringing the adsorption parts 14 and 24 closer to the metal beam B.

また、支持部11・21、保持部12・22及び接続部13・23は、一枚の第一の板材10及び第二の板材20(板状部材)に一体的に形成されるものである。   Further, the support portions 11 and 21, the holding portions 12 and 22, and the connection portions 13 and 23 are integrally formed on one first plate member 10 and second plate member 20 (plate member). .

このように構成することにより、天井吊治具1の部品点数を減らすことができるため、天井吊治具1の構成を簡素化できる。   By comprising in this way, since the number of parts of the ceiling hanging jig 1 can be reduced, the structure of the ceiling hanging jig 1 can be simplified.

また、板面の向きが互いに異なる第一の板材10及び第二の板材20(一対の板状部材)によって構成されるものである。   Moreover, it is comprised by the 1st board | plate material 10 and the 2nd board | plate material 20 (a pair of plate-shaped member) from which the direction of a board surface differs mutually.

このように構成することにより、向きが互いに異なる複数の部材(長手方向の向きが互いに異なる長尺材A1〜A3及び短尺材A4〜A8)をまとめて仮固定することができる。これによれば、仮固定に要する天井吊治具1の数を減らして、複数の天井パネルA10・A20を仮固定する作業を効率的に行うことができる。また、梁Bに対して向きが異なる部材(長尺材A1〜A3)を当該梁Bに仮固定することができる。   By configuring in this way, a plurality of members having different directions (long materials A1 to A3 and short materials A4 to A8 having different longitudinal directions) can be temporarily fixed together. According to this, the number of ceiling hanging jigs 1 required for temporary fixing can be reduced, and the work of temporarily fixing a plurality of ceiling panels A10 and A20 can be performed efficiently. In addition, members (long materials A1 to A3) having different directions with respect to the beam B can be temporarily fixed to the beam B.

また、第一の板材10及び第二の板材20は、互いに開閉自在に連結されるものである。   Moreover, the 1st board | plate material 10 and the 2nd board | plate material 20 are connected mutually so that opening and closing is possible.

このように構成することにより、第一の板材10及び第二の板材20を閉じた状態で持ち運ぶことができるため、天井吊治具1を持ち運び易くなる。   By comprising in this way, since the 1st board | plate material 10 and the 2nd board | plate material 20 can be carried in the closed state, it becomes easy to carry the ceiling suspension jig | tool 1. FIG.

なお、本実施形態に係る第一の板材10及び第二の板材20は、本発明に係る板状部材の実施の一形態である。   In addition, the 1st board | plate material 10 and the 2nd board | plate material 20 which concern on this embodiment are one Embodiment of the plate-shaped member which concerns on this invention.

また、本実施形態において、支持部11・21は、接続部13・23に対する突出幅(図2に示す状態においては前後方向の長さ)が梁Bの下フランジB2の短手方向幅(前後方向幅)の半分程度となっている。このように構成することにより、支持部11・21が梁Bに引っ掛けられた(支持された)際に、接続部13・23が梁Bから大きく離間してしまうことを抑制できる。このため、仮固定に要するスペースを低減することができる。   Further, in the present embodiment, the support portions 11 and 21 have a protruding width with respect to the connection portions 13 and 23 (the length in the front-rear direction in the state shown in FIG. 2). It is about half of the (direction width). By comprising in this way, when the support parts 11 and 21 are hooked (supported) by the beam B, it can suppress that the connection parts 13 and 23 leave | separate from the beam B largely. For this reason, the space required for temporary fixation can be reduced.

また、本実施形態においては、支持部11・21及び保持部12・22が切欠部11a・12a・21a・22aを具備すると共に、接続部13・23が上側切欠部13a・23a及び下側切欠部13b・23bを具備している。このように構成することにより、天井吊治具1が他の部材(例えば、金具C等)と接触し難くすることができる。このため、梁Bに天井パネルAを固定する作業を効率的に行うことができる。   Further, in the present embodiment, the support portions 11 and 21 and the holding portions 12 and 22 include the notches 11a, 12a, 21a, and 22a, and the connection portions 13 and 23 are the upper notches 13a and 23a and the lower notches. It has parts 13b and 23b. By comprising in this way, the ceiling hanging jig | tool 1 can be made difficult to contact with other members (for example, metal fitting C etc.). For this reason, the operation | work which fixes the ceiling panel A to the beam B can be performed efficiently.

また、吸着部14・24は、第一の板材10及び第二の板材20の外側面(全閉状態において対向する面とは異なる面)に固定されている。このように構成することにより、第一の板材10及び第二の板材20を閉じる際に吸着部14・24が接触することを防止できる。このため、第一の板材10及び第二の板材20を閉じた際に、吸着部14・24が破損することを防止できる。   Moreover, the adsorption | suction part 14 * 24 is being fixed to the outer surface (surface different from the surface which opposes in a fully-closed state) of the 1st board | plate material 10 and the 2nd board | plate material 20. As shown in FIG. By comprising in this way, when closing the 1st board | plate material 10 and the 2nd board | plate material 20, it can prevent that the adsorption | suction part 14 * 24 contacts. For this reason, when the 1st board | plate material 10 and the 2nd board | plate material 20 are closed, it can prevent that the adsorption | suction part 14 * 24 is damaged.

また、吸着部14・24は、支持部11・21の下面(梁Bの下フランジB2に支持される面)とは異なる面に固定されている。このように構成することにより、仮固定した際に天井パネルAから受ける荷重が吸着部14・24に作用し難くすることができる。このため、吸着部14・24が破損することを抑制できる。   Moreover, the adsorption | suction part 14 * 24 is being fixed to the surface different from the lower surface (surface supported by the lower flange B2 of the beam B) of the support part 11 * 21. By comprising in this way, the load received from the ceiling panel A at the time of temporarily fixing can make it difficult to act on the adsorption | suction part 14 * 24. For this reason, it can control that adsorption parts 14 and 24 are damaged.

以上、本発明の実施形態を説明したが、本発明は上記構成に限定されるものではなく、特許請求の範囲に記載された発明の範囲内で種々の変更が可能である。   The embodiment of the present invention has been described above, but the present invention is not limited to the above-described configuration, and various modifications can be made within the scope of the invention described in the claims.

例えば、天井吊治具1は、H形鋼によって構成される梁Bに支持されるものとしたが、天井吊治具1が支持される梁Bの種類は、これに限定されるものではなく、例えば、C形鋼等であってもよい。また、梁Bの材料は、金属材料に限定されるものではなく、例えば、木材等であってもよい。   For example, the ceiling hanging jig 1 is supported by the beam B made of H-shaped steel, but the type of the beam B on which the ceiling hanging jig 1 is supported is not limited to this. For example, C-shaped steel or the like may be used. Moreover, the material of the beam B is not limited to a metal material, For example, wood etc. may be sufficient.

また、第一の板材10及び第二の板材20は、互いの板面の成す角度(鋭角)が90°となるまで開閉自在に連結されるものとしたが、第一の板材10及び第二の板材20の開閉角度はこれに限定されるものではなく、任意の角度にすることができる。   Moreover, although the 1st board | plate material 10 and the 2nd board | plate material 20 shall be connected so that opening and closing is possible until the angle (acute angle) which a mutual plate surface makes becomes 90 degrees, the 1st board | plate material 10 and the 2nd board | plate material were used. The opening / closing angle of the plate member 20 is not limited to this, and can be any angle.

また、第一の板材10及び第二の板材20は、必ずしも開閉自在に連結される必要はなく、例えば、互いに開いた状態で固定されるものであってもよい。この場合、第一の板材10と第二の板材20とは、全開状態で固定されることが望ましい。これにより、互いに直交する部材(長尺材A1〜A3及び短尺材A4〜A8)に第一の板材10及び第二の板材20を取り付け易くなる。   Moreover, the 1st board | plate material 10 and the 2nd board | plate material 20 do not necessarily need to be connected so that opening and closing is possible, For example, you may fix in the state opened mutually. In this case, it is desirable that the first plate member 10 and the second plate member 20 are fixed in a fully opened state. Thereby, it becomes easy to attach the 1st board | plate material 10 and the 2nd board | plate material 20 to the member (long material A1-A3 and short material A4-A8) orthogonal to each other.

また、天井吊治具1は、例えば、支持部11・21と保持部12・22との上下方向の間隔を調整可能に構成されるものであってもよい。このように構成することで、種々の梁Bに天井パネルAを仮固定することができる。例えば、複数階の戸建て住宅等においては、最上階とそれ以外の階とで梁Bの形状が異なる場合がある。このような場合においても、支持部11・21と保持部12・22との間隔を調整可能に構成すれば、一種類の天井吊治具1で、全ての階の梁Bに天井パネルAを仮固定することができるため、天井吊治具1の汎用性を向上することができる。   Moreover, the ceiling hanging jig 1 may be configured such that the vertical distance between the support portions 11 and 21 and the holding portions 12 and 22 can be adjusted, for example. With this configuration, the ceiling panel A can be temporarily fixed to various beams B. For example, in a multi-storey detached house, the shape of the beam B may be different between the top floor and other floors. Even in such a case, if the interval between the support portions 11 and 21 and the holding portions 12 and 22 is configured to be adjustable, the ceiling panel A can be attached to the beams B of all the floors with one type of ceiling hanging jig 1. Since it can be temporarily fixed, the versatility of the ceiling hanging jig 1 can be improved.

また、第一の板材10及び第二の板材20は、合板によって構成されるものとしたが、第一の板材10及び第二の板材20の材料は、これに限定されるものではなく、例えば、鉄等の金属材料であってもよい。また、第一の板材10及び第二の板材20は、互いに異なる形状(例えば、接続部13・23の高さが異なる形状等)であってもよい。   Moreover, although the 1st board | plate material 10 and the 2nd board | plate material 20 shall be comprised by the plywood, the material of the 1st board | plate material 10 and the 2nd board | plate material 20 is not limited to this, For example, Or a metal material such as iron. Further, the first plate member 10 and the second plate member 20 may have different shapes (for example, shapes in which the heights of the connecting portions 13 and 23 are different).

また、天井吊治具1は、第一の板材10及び第二の板材20を具備するものとしたが、これに限定されるものではなく、例えば、図6に示す別実施形態に係る天井吊治具101のような構成とすることも可能である。別実施形態に係る天井吊治具101は、第一の板材10だけを具備する。このように構成することで、本実施形態に係るヒンジ30等の連結部材が不要となるため、コストを低減することができる。   Moreover, although the ceiling suspension jig | tool 1 shall have comprised the 1st board | plate material 10 and the 2nd board | plate material 20, it is not limited to this, For example, the ceiling suspension which concerns on another embodiment shown in FIG. A configuration similar to the jig 101 is also possible. The ceiling hanging jig 101 according to another embodiment includes only the first plate member 10. By comprising in this way, since connection members, such as the hinge 30 which concern on this embodiment, become unnecessary, cost can be reduced.

また、支持部11・21は、梁Bの下フランジB2に引っ掛けられることで支持されるものとしたが、支持部11・21が梁Bに支持される手段は、これに限定されるものではなく、例えば、上フランジB1と下フランジB2との間に嵌め合わされるものであってもよい。   The support portions 11 and 21 are supported by being hooked on the lower flange B2 of the beam B. However, the means for supporting the support portions 11 and 21 on the beam B is not limited to this. For example, it may be fitted between the upper flange B1 and the lower flange B2.

また、保持部12・22は、天井パネルA(長尺材A1〜A3及び短尺材A4〜A8)の下面を受けるものとしたが、保持部12・22が天井パネルAを保持する手段は、これに限定されるものではなく、例えば、天井パネルAの前面及び後面(短尺材A4〜A8の前面及び後面)を挟持するものであってもよい。   Moreover, although the holding | maintenance parts 12 and 22 shall receive the lower surface of the ceiling panel A (long material A1-A3 and short material A4-A8), the means by which the holding parts 12.22 hold | maintain the ceiling panel A is as follows. For example, the front and rear surfaces of the ceiling panel A (the front and rear surfaces of the short materials A4 to A8) may be sandwiched.

また、吸着部14・24は、支持部11・21の外側面に固定されるものとしたが、吸着部14・24が固定される箇所は、これに限定されるものではない。吸着部14・24が固定される箇所は、例えば、支持部11・21の内側面(全閉状態となった際に互いに対向する面)や接続部13・23の前上端部等であってもよい。また、吸着部14・24は、別々の箇所に固定されていてもよい。   Moreover, although the adsorption | suction part 14 * 24 shall be fixed to the outer surface of the support part 11 * 21, the location where the adsorption | suction part 14 * 24 is fixed is not limited to this. The locations where the suction portions 14 and 24 are fixed are, for example, the inner surfaces of the support portions 11 and 21 (surfaces that face each other when fully closed), the front upper ends of the connection portions 13 and 23, and the like. Also good. Moreover, the adsorption | suction part 14 * 24 may be fixed to a different location.

また、吸着部14・24は、磁石によって構成されるものとしたが、吸着部14・24の構成は、これに限定されるものではなく、例えば、吸盤等であってもよい。   Moreover, although the adsorption | suction parts 14 and 24 shall be comprised by the magnet, the structure of the adsorption | suction parts 14 and 24 is not limited to this, For example, a suction cup etc. may be sufficient.

また、天井吊治具1は、必ずしも吸着部14・24を具備する必要はない。   Moreover, the ceiling hanging jig 1 does not necessarily need to include the suction portions 14 and 24.

また、支持部11・21及び保持部12・22は、必ずしも切欠部11a・12a・21a・22aを具備する必要はない。また、接続部13・23は、必ずしも上側切欠部13a・23a及び下側切欠部13b・23bを具備する必要はない。   Further, the support portions 11 and 21 and the holding portions 12 and 22 do not necessarily need to include the notches 11a, 12a, 21a, and 22a. Moreover, the connection parts 13 and 23 do not necessarily need to be provided with the upper notch parts 13a and 23a and the lower notch parts 13b and 23b.

1 天井吊治具
11・21 支持部
12・22 保持部
13・23 接続部
A 天井パネル
B 梁
1 Ceiling hanging jig 11.21 Supporting part 12.22 Holding part 13.23 Connection part A Ceiling panel B Beam

Claims (8)

天井の梁に支持される支持部と、
梁の下方に配置された天井パネルを保持する保持部と、
支持部と保持部とを接続する接続部と、
を具備する、
天井吊治具。
A support part supported by a beam on the ceiling;
A holding part for holding a ceiling panel arranged below the beam;
A connecting portion for connecting the support portion and the holding portion;
Comprising
Ceiling hanging jig.
支持部は、
接続部から突出し、梁に引っ掛けられることで支持される、
請求項1に記載の天井吊治具。
The support is
Protruding from the connecting part and supported by being hooked on the beam,
The ceiling hanging jig according to claim 1.
保持部は、
接続部から突出し、天井パネルの下面を受けることで保持する、
請求項1又は請求項2に記載の天井吊治具。
The holding part
Protrusively from the connection and hold by receiving the lower surface of the ceiling panel,
The ceiling hanging jig according to claim 1 or 2.
梁に吸着可能な吸着部をさらに具備する、
請求項1から請求項3までのいずれか一項に記載の天井吊治具。
It further comprises an adsorbing part that can adsorb to the beam,
The ceiling hanging jig according to any one of claims 1 to 3.
吸着部は、
磁石によって構成される、
請求項4に記載の天井吊治具。
The adsorption part
Composed by magnet,
The ceiling hanging jig according to claim 4.
支持部、保持部及び接続部は、
一枚の板状部材に一体的に形成される、
請求項1から請求項5までのいずれか一項に記載の天井吊治具。
The support part, the holding part and the connection part are
Formed integrally with one plate-like member,
The ceiling hanging jig according to any one of claims 1 to 5.
板面の向きが互いに異なる一対の板状部材によって構成される、
請求項6に記載の天井吊治具。
It is constituted by a pair of plate-like members having different plate surface orientations.
The ceiling hanging jig according to claim 6.
一対の板状部材は、
互いに開閉自在に連結される、
請求項7に記載の天井吊治具。
A pair of plate-like members
Are connected to each other so that they can be opened and closed.
The ceiling hanging jig according to claim 7.
JP2016252470A 2016-12-27 2016-12-27 Ceiling suspending member Pending JP2018104989A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016252470A JP2018104989A (en) 2016-12-27 2016-12-27 Ceiling suspending member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016252470A JP2018104989A (en) 2016-12-27 2016-12-27 Ceiling suspending member

Publications (1)

Publication Number Publication Date
JP2018104989A true JP2018104989A (en) 2018-07-05

Family

ID=62787836

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016252470A Pending JP2018104989A (en) 2016-12-27 2016-12-27 Ceiling suspending member

Country Status (1)

Country Link
JP (1) JP2018104989A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7308675B2 (en) 2019-07-09 2023-07-14 三菱電機株式会社 COOKING EQUIPMENT, COOKING SYSTEM, TERMINAL DEVICE, AND NOTIFICATION METHOD

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7308675B2 (en) 2019-07-09 2023-07-14 三菱電機株式会社 COOKING EQUIPMENT, COOKING SYSTEM, TERMINAL DEVICE, AND NOTIFICATION METHOD

Similar Documents

Publication Publication Date Title
JP2018104989A (en) Ceiling suspending member
JP2007030681A (en) Automobile door mounting fixture
KR20180032047A (en) No-hole Corner bracket
JP6205217B2 (en) Beam reinforcing structure and method, and support for auxiliary beam
JP2016165363A (en) Desk apparatus
JP2018105113A (en) Jig for mounting components
JPWO2014196026A1 (en) Plate member fixture
JP6690912B2 (en) Assembling structure of building panel with temporary holding tool for building panel
KR20120110857A (en) Repeater mounting bracket
JP2007170009A (en) Vibration-isolation ceiling hanger metal fittings of ceiling material, and vibration-proof suspension structure of the ceiling material
JP2020105706A (en) Member temporary receiving jig
JP5670263B2 (en) Support fixing tool and support fixing device
JP6666812B2 (en) How to attach ceiling panels to building units
JP2007131127A (en) Mount structure for vehicular engine
KR20190126549A (en) steel reinforcement fixture
JP2012026095A (en) Runner fixing metallic material
JP2015098752A (en) Method and structure for reinforcing beam, structure for temporarily fixing auxiliary beam, and auxiliary beam support
JP5921184B2 (en) Ceiling structure
JP2020165122A (en) Ceiling structure and fixing reinforcement member
JP2020165123A (en) Ceiling structure and fixing reinforcement member
JP2013060703A (en) Ceiling reinforcement structure
JP2016223090A (en) Architectural jig and wooden building construction method
JP3112143B2 (en) Unit ceiling manufacturing method and manufacturing apparatus
JP2011220046A (en) Connection fitting
JP2018105069A (en) Fixture