JP2018053449A - Construction method for spray lining concrete - Google Patents

Construction method for spray lining concrete Download PDF

Info

Publication number
JP2018053449A
JP2018053449A JP2016187387A JP2016187387A JP2018053449A JP 2018053449 A JP2018053449 A JP 2018053449A JP 2016187387 A JP2016187387 A JP 2016187387A JP 2016187387 A JP2016187387 A JP 2016187387A JP 2018053449 A JP2018053449 A JP 2018053449A
Authority
JP
Japan
Prior art keywords
concrete
spraying
tunnel
sprayed
spray
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016187387A
Other languages
Japanese (ja)
Other versions
JP6840498B2 (en
Inventor
博章 谷口
Hiroaki Taniguchi
博章 谷口
浩司 ▲高▼野
浩司 ▲高▼野
Koji Takano
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2016187387A priority Critical patent/JP6840498B2/en
Publication of JP2018053449A publication Critical patent/JP2018053449A/en
Application granted granted Critical
Publication of JP6840498B2 publication Critical patent/JP6840498B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction method for spray lining concrete to make it possible to reduce dependence on an operator's sense as determining a thickness of concrete sprayed to precisely ensure the sprayed thickness compared with before and to perform the construction of spray lining concrete preferably.SOLUTION: This method includes a concrete spray construction step, at which concrete is sprayed to form a concrete spray lining construction area R by spraying concrete from one frame 2a (2) side toward the next frame 2b (2) side, a first piecework management step, at which a thickness of sprayed concrete at the side of the next frame 2b (2) is measured, and a second piecework management step, at which a thickness of sprayed concrete at the edge faces of both sides of the area R is measured.SELECTED DRAWING: Figure 1

Description

本発明は、吹付け覆工コンクリートの施工方法に関する。   The present invention relates to a method for constructing spray lining concrete.

従来、山岳トンネルでは、例えば、ドリルジャンボを用いるなどして地山を掘削するとともにずりをトンネル坑外に順次排出し、鋼製支保工をトンネル軸方向に所定の間隔をあけて設置する。そして、地山の掘削面にコンクリートを吹付けるとともに地山内にロックボルトの打設、防水シートの敷設を行い、セントルを用いるなどして二次覆工のコンクリート覆工を構築する(例えば、特許文献1参照)。   Conventionally, in a mountain tunnel, for example, a natural ground is excavated by using a drill jumbo and the shear is sequentially discharged out of the tunnel well, and steel supporters are installed at a predetermined interval in the tunnel axial direction. Then, concrete is sprayed on the excavation surface of the natural ground, a rock bolt is placed in the natural ground, a waterproof sheet is laid, and a concrete lining of the secondary lining is constructed by using a centle (for example, patent Reference 1).

一方、トンネルの用途や環境、地山の状況などに応じ、覆工に吹付けコンクリートを用いるケースがある。   On the other hand, there are cases where shotcrete is used for lining depending on the use and environment of the tunnel and the situation of natural ground.

そして、このような吹付け覆工コンクリートを施工する際には、例えば、鋼製支保工を設置して一次吹付けを行った後、施工スパンに応じた位置(1打設長のトンネル軸方向の終点位置)に一次吹付けの内面からトンネル内側に所定の突出量で突出させてトンネル周方向に繋がる妻枠を設置する。そして、トンネル軸方向に所定の間隔をあけて設置した対の妻枠の間の吹付け施工領域(施工スパン)にコンクリートを吹付け、吹付け覆工コンクリートを構築してゆく。   And when constructing such sprayed lining concrete, for example, after installing a steel support and performing primary spraying, the position corresponding to the construction span (tunnel axial direction of one casting length) The end frame of the end) is provided with a wife frame that protrudes from the inner surface of the primary spray to the inner side of the tunnel with a predetermined protrusion amount and is connected in the circumferential direction of the tunnel. And concrete is sprayed to the spray construction area (construction span) between the pair of frame frames installed at a predetermined interval in the tunnel axis direction, and the spray lining concrete is constructed.

特開2011−26943号公報JP 2011-26943 A

しかしながら、上記従来の吹付け覆工コンクリートの施工方法においては、吹付け施工領域の終点位置(1打設長のトンネル軸方向の終点位置)に設置した妻枠を吹付け厚さの指標に用いる場合には、妻枠から離れるほど、吹付け厚さにバラつきが生じやすくなる。すなわち、妻枠から離れた施工領域の中央側ほど、吹付け厚さを作業員の感覚にゆだねることになる。   However, in the conventional method for constructing sprayed lining concrete, the end frame position (end point position in the tunnel axis direction of one casting length) of the spraying construction area is used as a spray thickness index. In some cases, as the distance from the wife frame increases, the spray thickness tends to vary. That is, the spraying thickness is left to the operator's sense toward the center side of the construction area away from the wife frame.

上記の目的を達するために、この発明は以下の手段を提供している。   In order to achieve the above object, the present invention provides the following means.

本発明の吹付け覆工コンクリートの施工方法は、トンネル内面にコンクリートを吹付け、吹付け覆工コンクリートを施工する方法であって、トンネル軸方向に所定の間隔をあけ、トンネル内面から内側に所定の突出量で突出しトンネル周方向に繋がる妻枠をトンネル軸方向に所定の間隔をあけて設置する妻枠設置工程と、トンネル軸方向に隣り合う一対の妻枠の間の吹付け施工領域にコンクリートを吹付けて吹付け覆工コンクリートを構築してゆくコンクリート吹付け工程とを備え、且つ、コンクリート吹付け工程で前記吹付け施工領域を形成する一方の妻枠から他方の妻枠に向けてコンクリートを吹付けるとともに、前記他方の妻枠側で吹付け厚さを計測する第一出来高管理工程と、前記吹付け施工領域にコンクリートを吹付けた段階で、該吹付け施工領域に吹付けたコンクリートの端面の厚さを計測する第二出来高管理工程とを備えることを特徴とする。   The method of constructing sprayed lining concrete according to the present invention is a method of spraying concrete on the inner surface of a tunnel and constructing sprayed lining concrete, with a predetermined interval in the tunnel axial direction, and a predetermined distance from the inner surface of the tunnel to the inner side. The frame is installed at a predetermined interval in the tunnel axis direction, and the concrete frame is installed between the adjacent frame frames in the tunnel axis direction. A concrete spraying process for constructing sprayed lining concrete, and concrete from one end frame to the other end frame that forms the sprayed construction area in the concrete spraying process In the first volume management process of measuring the spray thickness on the other wife frame side, and at the stage of spraying concrete on the spray construction area, Characterized in that it comprises a second volume control step of measuring the thickness of the end faces of concrete sprayed onto spray installation area.

この発明においては、吹付け施工領域にコンクリートを吹付ける際に、吹付け施工領域を形成する一方の妻枠から他方の妻枠に向けてコンクリートを吹付け施工するようにし、第一出来高管理工程によって他方の妻枠側でコンクリートの吹付け厚さを計測することで、他方の妻枠側の吹付け厚さにバラつきが生じることを抑止できる。さらに、第二出来高管理工程で吹付け施工領域に吹付けたコンクリートの端面の厚さを計測することにより、吹付け施工領域の両端側の吹付け厚さにバラつきが生じることを抑止できる。   In this invention, when concrete is sprayed onto the spray construction area, the concrete is sprayed from one end frame to the other end frame that forms the spray installation area, and the first volume control process By measuring the spraying thickness of concrete on the other end frame side, it is possible to prevent the spraying thickness on the other end frame side from varying. Furthermore, by measuring the thickness of the end face of the concrete sprayed to the spraying construction area in the second volume management process, it is possible to prevent variations in the spraying thickness on both ends of the spraying construction area.

このように第一出来高管理工程と第二出来高管理工程で吹付け施工の管理を行うことにより、吹付け厚さを作業員の感覚にゆだねることを減らし、従来よりも吹付け厚さを精度よく確保し、好適に吹付け覆工コンクリートの施工を行うことが可能になる。   In this way, by managing the spraying construction in the first volume management process and the second volume management process, it is less likely to leave the spraying thickness to the operator's sense, and the spraying thickness is more accurate than before. It is possible to secure and suitably apply the spray lining concrete.

また、本発明の吹付け覆工コンクリートの施工方法において、前記第一出来高管理工程と前記第二出来高管理工程では、少なくとも、トンネルの天端部と、左右のアーチ肩部と、左右のアーチ部の下端部と、左右の側壁部で吹付け厚さを計測することが望ましい。   Moreover, in the construction method of the sprayed lining concrete of the present invention, at least the top end portion of the tunnel, the left and right arch shoulder portions, and the left and right arch portions in the first volume management step and the second volume management step It is desirable to measure the spraying thickness at the lower end of each and the left and right side walls.

この発明においては、第一出来高管理工程と第二出来高管理工程で出来高管理を行う際に、トンネルの天端部と、左右のアーチ肩部と、左右のアーチ部の下端部と、左右の側壁部のトンネル周方向の少なくとも7箇所で吹付け厚さの計測を行うことによって、より確実に吹付け厚さを精度よく確保でき、好適に吹付け覆工コンクリートの施工を行うことが可能になる。   In this invention, when performing volume management in the first volume management process and the second volume management process, the top end of the tunnel, the left and right arch shoulders, the lower end of the left and right arch parts, and the left and right side walls By measuring the spraying thickness at at least seven locations in the circumferential direction of the tunnel, the spraying thickness can be more accurately ensured and the sprayed lining concrete can be suitably constructed. .

さらに、本発明の吹付け覆工コンクリートの施工方法においては、前記隣り合う一対の妻枠の設計吹付け厚さの位置に接続して線材をトンネル軸方向に張設し、コンクリート吹付け前に前記吹付け施工領域の中間部のトンネル内面と前記線材の離間を計測する第三出来高管理工程を備え、該第三出来高管理工程の計測結果を反映させてコンクリート吹付け工程を実施することがより望ましい。   Furthermore, in the construction method of the sprayed lining concrete of the present invention, the wire rod is stretched in the tunnel axial direction by connecting to the position of the design spraying thickness of the pair of adjacent end frames, and before the concrete spraying It is provided with a third volume control process for measuring the distance between the inner surface of the tunnel in the middle of the spraying construction area and the wire, and the concrete spraying process is performed by reflecting the measurement result of the third volume control process. desirable.

この発明においては、第三出来高管理工程で、ワイヤーや水糸などの線材を隣り合う一対の妻枠の設計吹付け厚さの位置に接続してトンネル軸方向に張設し、コンクリート吹付け前に吹付け施工領域の中間部のトンネル内面と線材の離間を計測することによって、吹付け施工領域の中間部のトンネル内面の凹凸(不陸量)を把握することができる。これにより、線材を指標に用い、把握したトンネル内面の凹凸に応じてコンクリートの吹付け量(吹付け面の位置)を調節することで、さらに確実に吹付け厚さを精度よく確保し、好適に吹付け覆工コンクリートの施工を行うことが可能になる。   In this invention, in the third volume management process, a wire rod such as a wire or water thread is connected to the position of the design spraying thickness of a pair of adjacent frame frames and stretched in the tunnel axial direction, before concrete spraying In addition, by measuring the distance between the inner surface of the tunnel in the middle of the spray construction area and the wire rod, the unevenness (uneven amount) on the inner surface of the tunnel in the middle of the spray construction area can be grasped. As a result, the wire thickness is used as an index, and the concrete spraying amount (position of the spraying surface) is adjusted according to the grasped unevenness of the tunnel inner surface, ensuring a more accurate spraying thickness and more suitable. It becomes possible to perform the construction of spray lining concrete.

また、本発明の吹付け覆工コンクリートの施工方法においては、予め設定した所定の施工長毎に、トンネル天端部とトンネルアーチ部に検測孔を設け、前記検測孔で吹付け覆工コンクリートの厚さを計測する第四出来高管理工程を備えることがさらに望ましい。   Further, in the method of constructing the spray lining concrete according to the present invention, an inspection hole is provided in the tunnel top end portion and the tunnel arch portion for each predetermined construction length set in advance, and the spray lining is performed at the inspection hole. It is further desirable to provide a fourth volume management process for measuring the thickness of the concrete.

この発明においては、第四出来高管理工程で、予め設定した所定の施工長毎に、トンネル天端部とトンネルアーチ部に検測孔を設け、これら検測孔で吹付け覆工コンクリートの厚さを計測することによって、好適に施工が行えているか否かを確認できる。これにより、さらに確実に吹付け厚さを精度よく確保し、好適に吹付け覆工コンクリートの施工を行うことが可能になる。   In this invention, in the fourth work volume management step, for each predetermined construction length set in advance, inspection holes are provided in the tunnel top and tunnel arches, and the thickness of the sprayed lining concrete is measured by these inspection holes. It is possible to confirm whether or not construction is suitably performed by measuring. As a result, it is possible to more reliably ensure the spraying thickness with high accuracy and to perform the sprayed lining concrete appropriately.

本発明の吹付け覆工コンクリートの施工方法においては、吹付け厚さを作業員の感覚にゆだねることを減らし、従来よりも吹付け厚さを精度よく確保し、好適に吹付け覆工コンクリートの施工を行うことが可能になる。   In the method of constructing the spray lining concrete according to the present invention, it is less likely to leave the spray thickness to the operator's sense, ensuring the spray thickness more accurately than in the past, and preferably using the spray lining concrete. It becomes possible to perform construction.

本発明の一実施形態に係る吹付け覆工コンクリートの施工方法において、妻枠を設置した状態を示す図である。It is a figure which shows the state which installed the wife frame in the construction method of the spraying lining concrete which concerns on one Embodiment of this invention. 本発明の一実施形態に係る吹付け覆工コンクリートの施工方法において、一対の妻枠の間の吹付け施工領域にコンクリートを吹付け、吹付け覆工コンクリートを構築した状態を示す図である。In the construction method of the spray lining concrete which concerns on one Embodiment of this invention, it is a figure which shows the state which sprayed concrete to the spray construction area | region between a pair of wife frames, and constructed the spray lining concrete. 本発明の一実施形態に係る吹付け覆工コンクリートの施工方法において、トンネル周方向の吹付け厚さの計測位置の一例を示した図である。In the construction method of the spraying lining concrete which concerns on one Embodiment of this invention, it is the figure which showed an example of the measurement position of the spraying thickness of a tunnel circumferential direction. 本発明の一実施形態に係る吹付け覆工コンクリートの施工方法において、検測孔の設置位置の一例を示した図である。It is the figure which showed an example of the installation position of a test hole in the construction method of the spraying lining concrete which concerns on one Embodiment of this invention.

以下、図1から図4を参照し、本発明の一実施形態に係る吹付け覆工コンクリートの施工方法について説明する。   Hereinafter, with reference to FIGS. 1-4, the construction method of the spray lining concrete which concerns on one Embodiment of this invention is demonstrated.

ここで、本実施形態は、トンネルの用途や共用環境、地山の状況などに応じ、覆工として吹付けコンクリートを適用してトンネルを構築するにあたり、吹付け覆工コンクリートの出来高管理を好適に行えるようにする方法に関するものである。   Here, according to the use of the tunnel, the common environment, the condition of the natural ground, etc., this embodiment is suitable for managing the volume of sprayed lining concrete when constructing a tunnel by applying shotcrete as lining. It relates to a method for making it possible.

具体的に、本実施形態の吹付け覆工コンクリートの施工方法においては、従来と同様、例えば、掘削地山面に対する一次吹付け、ロックボルトの打設等を行って地山の安定化を図った後、図1に示すように、トンネル内面1から内側に所定の突出量で突出しトンネル周方向に繋がる妻枠2をトンネル軸方向に所定の間隔をあけて設置する(妻枠設置工程)。すなわち、施工スパン/吹付け施工領域Rに応じた位置に一次吹付けの表面や鋼製支保工の表面などのトンネル内面1からトンネル内側に所定の突出量で突出させて妻枠2を設置する。   Specifically, in the method for constructing sprayed lining concrete according to the present embodiment, as in the past, for example, primary spraying on the excavated ground surface, placement of rock bolts, etc. are performed to stabilize the natural ground. Then, as shown in FIG. 1, the frame 2 that protrudes inward from the tunnel inner surface 1 with a predetermined protrusion amount and is connected in the circumferential direction of the tunnel is installed at a predetermined interval in the tunnel axial direction (wife frame installation step). That is, the frame 2 is installed at a position corresponding to the construction span / spraying construction area R by projecting from the tunnel inner surface 1 such as the surface of primary spraying or the surface of steel support to the inside of the tunnel with a predetermined projection amount. .

そして、図2に示すように、この妻枠2を吹付け厚さの指標としながら、隣り合う一対の妻枠2の間の吹付け施工領域Rにコンクリートを吹付け、吹付け覆工コンクリート3を構築してゆく(コンクリート吹付け工程)。このとき、本実施形態では、一つの吹付け施工領域Rを形成する一方の妻枠2a(2)から他方の妻枠2b(2)に向けてコンクリートを吹付け、一方の妻枠2a(2)から他方の妻枠2b(2)に向かうトンネル軸方向の一方向に順次吹付け覆工コンクリート3が形成されるように施工を行う。   And as shown in FIG. 2, concrete is sprayed on the spray construction area | region R between a pair of adjacent wife frames 2 using this wife frame 2 as a parameter | index of spraying thickness, and sprayed lining concrete 3 (Concrete spraying process). At this time, in the present embodiment, concrete is sprayed from one end frame 2a (2) forming one spray construction region R toward the other end frame 2b (2), and one end frame 2a (2 ) To the other end frame 2b (2) so that the lining concrete 3 is formed sequentially in one direction in the tunnel axis direction.

一方、本実施形態の吹付け覆工コンクリートの施工方法では、吹付け覆工コンクリート3の出来形管理として、次の手法を用いる。   On the other hand, in the construction method of the sprayed lining concrete according to the present embodiment, the following method is used as the finished shape management of the sprayed lining concrete 3.

まず、第一出来高管理(第一出来高管理工程)として、吹付け施工領域Rを形成する一方の妻枠2a(2)から他方の妻枠2b(2)に向けてコンクリートを吹付けるとともに、あとから吹付けることになる他方の妻枠2b(2)側(1打設長の終点側)で吹付け厚さを計測する。   First, as the first volume management (first volume management process), concrete is sprayed from one end frame 2a (2) forming the spray construction area R toward the other end frame 2b (2). The spray thickness is measured on the other end frame 2b (2) side (end point side of one casting length) to be sprayed.

また、第二出来高管理(第二出来高管理工程)として、吹付け施工領域Rにコンクリートを吹付けた段階で、該吹付け施工領域Rに吹付けたコンクリートの端面の厚さを計測する。   In addition, as the second volume management (second volume management process), the thickness of the end face of the concrete sprayed on the spray construction area R is measured at the stage where the concrete is sprayed on the spray construction area R.

さらに、これら第一出来高管理と第二出来高管理では、図3に示すように、少なくとも、トンネルの天端部T1と、左右のアーチ肩部T2、T3と、左右のアーチ部の下端部(アーチ肩部よりも下方の部分)T4、T5と、左右の側壁部(スプリングライン付近など)T6、T7で吹付け厚さを計測する。   Further, in these first volume management and second volume management, as shown in FIG. 3, at least the top end T1 of the tunnel, the left and right arch shoulders T2 and T3, and the lower end of the left and right arches (arch) The spraying thickness is measured at T4 and T5 below the shoulder and T6 and T7 on the left and right side walls (such as near the spring line).

次に、例えば、吹付け施工領域Tのトンネル内面1の凹凸(不陸)が大きい場合など、必要に応じ、第三出来高管理(第三出来高管理工程)を行う。この第三出来高管理としては、隣り合う一対の妻枠2の設計吹付け厚さの位置に接続して定規用のワイヤーや水糸等の線材をトンネル軸方向に張設し、コンクリート吹付け前に吹付け施工領域Rの中間部のトンネル内面1と線材の離間を計測する。そして、この第三出来高管理の計測結果を反映させてコンクリート吹付け施工を実施する。すなわち、トンネル内面1の不陸によってトンネル内面1と線材の間の離間距離が設計吹付け厚さよりも小さい場合には、その分、線材よりもトンネル内側までコンクリートを吹付けるようにして施工を行う。   Next, for example, when the unevenness (unevenness) of the tunnel inner surface 1 in the spray construction area T is large, third volume management (third volume management process) is performed as necessary. For this third volume management, wire rods such as ruler wires and water threads are stretched in the tunnel axis direction and connected to the position of the design spraying thickness of a pair of adjacent end frames 2 before concrete spraying. The distance between the tunnel inner surface 1 and the wire in the middle of the spray construction region R is measured. And concrete spraying construction is carried out reflecting the measurement result of this third volume management. That is, when the distance between the tunnel inner surface 1 and the wire is smaller than the design spraying thickness due to the unevenness of the tunnel inner surface 1, the concrete is sprayed to the tunnel inner side rather than the wire. .

なお、この第三出来高管理においても、少なくとも、トンネルの天端部T1と、左右のアーチ肩部T2、T3と、左右のアーチ部の下端部T4、T5と、左右の側壁部T6、T7のトンネル周方向の7箇所以上でトンネル内面1と線材の離間を計測することが望ましい。   Even in this third volume management, at least the tunnel top end T1, the left and right arch shoulders T2 and T3, the left and right arch bottom ends T4 and T5, and the left and right side wall portions T6 and T7. It is desirable to measure the distance between the tunnel inner surface 1 and the wire at seven or more locations in the circumferential direction of the tunnel.

次に、本実施形態では、第四出来高管理(第四出来高管理工程)を行う。この第四出来高管理では、例えば、図4に示すように、施工長40m毎にトンネル天端部T8に検測孔を設け、施工長100m毎にトンネルアーチ部T9、T10に検測孔を設け、これら検測孔で吹付け覆工コンクリートの厚さを計測する。なお、検測孔の設置位置はトンネル状況等に合わせ適宜設定すればよい。   Next, in the present embodiment, fourth volume management (fourth volume management process) is performed. In this fourth volume management, for example, as shown in FIG. 4, a measurement hole is provided in the tunnel top end T8 every construction length 40m, and a measurement hole is provided in the tunnel arch portions T9 and T10 every construction length 100m. The thickness of sprayed lining concrete is measured with these inspection holes. In addition, what is necessary is just to set the installation position of a test hole suitably according to a tunnel condition etc.

そして、本実施形態の吹付け覆工コンクリートの施工方法においては、上記のように施工管理を行うことによって、吹付け厚さを作業員の感覚にゆだねることを減らし、従来よりも吹付け厚さを精度よく確保し、好適に吹付け覆工コンクリート3の施工を行うことが可能になる。   And in the construction method of the spray lining concrete of this embodiment, by performing construction management as described above, it is less likely to leave the spray thickness to the operator's sense, and the spray thickness is more than conventional. Can be ensured with high accuracy, and the sprayed lining concrete 3 can be suitably constructed.

すなわち、吹付け施工領域Rにコンクリートを吹付ける際に、吹付け施工領域Rを形成する一方の妻枠2a(2)から他方の妻枠2b(2)に向けてコンクリートを吹付け施工するようにし、第一出来高管理工程によって他方の妻枠2b(2)側でコンクリートの吹付け厚さを計測することで、他方の妻枠2b(2)側の吹付け厚さにバラつきが生じることを抑止できる。さらに、第二出来高管理工程で吹付け施工領域Rに吹付けたコンクリートの端面の厚さを計測することにより、吹付け施工領域Rの両端側の吹付け厚さにバラつきが生じることを抑止できる。   That is, when concrete is sprayed onto the spray construction area R, the concrete is sprayed from one end frame 2a (2) forming the spray construction area R toward the other end frame 2b (2). In addition, by measuring the spraying thickness of the concrete on the other end frame 2b (2) side by the first volume control process, it is possible that the spraying thickness on the other end frame 2b (2) side varies. Can be suppressed. Furthermore, by measuring the thickness of the end face of the concrete sprayed to the spraying construction area R in the second volume management process, it is possible to suppress the occurrence of variation in the spraying thickness on both ends of the spraying construction area R. .

このように第一出来高管理工程と第二出来高管理工程で吹付け施工の管理を行うことにより、吹付け厚さを作業員の感覚にゆだねることを減らし、従来よりも吹付け厚さを精度よく確保し、好適に吹付け覆工コンクリート3の施工を行うことが可能になる。   In this way, by managing the spraying construction in the first volume management process and the second volume management process, it is less likely to leave the spraying thickness to the operator's sense, and the spraying thickness is more accurate than before. It is possible to secure and suitably construct the spray lining concrete 3.

また、第一出来高管理工程と第二出来高管理工程で出来高管理を行う際に、トンネルの天端部と、左右のアーチ肩部と、左右のアーチ部の下端部と、左右の側壁部のトンネル周方向の少なくとも7箇所で吹付け厚さの計測を行うことによって、より確実に吹付け厚さを精度よく確保でき、好適に吹付け覆工コンクリート3の施工を行うことが可能になる。   Also, when performing volume management in the first volume management process and the second volume management process, the tunnel top end, left and right arch shoulders, left and right arch lower ends, and left and right side wall tunnels By measuring the spray thickness at at least seven locations in the circumferential direction, the spray thickness can be more reliably ensured and the sprayed lining concrete 3 can be suitably constructed.

さらに、第三出来高管理工程で、ワイヤーや水糸などの線材を隣り合う一対の妻枠2の設計吹付け厚さの位置に接続してトンネル軸方向に張設し、コンクリート吹付け前に吹付け施工領域Rの中間部のトンネル内面1と線材の離間を計測することによって、吹付け施工領域Rの中間部のトンネル内面1の凹凸(不陸量)を把握することができる。これにより、線材を指標に用い、把握したトンネル内面1の凹凸に応じてコンクリートの吹付け量(吹付け面の位置)を調節することで、さらに確実に吹付け厚さを精度よく確保し、好適に吹付け覆工コンクリート3の施工を行うことが可能になる。   Furthermore, in the third volume control process, wires such as wire and water thread are connected to the design spraying thickness positions of a pair of adjacent frames 2 and stretched in the tunnel axis direction. By measuring the distance between the tunnel inner surface 1 and the wire rod in the middle part of the spraying construction region R, the unevenness (unlanding amount) of the tunnel inner surface 1 in the middle part of the spraying construction region R can be grasped. Thereby, using the wire rod as an index, and adjusting the spraying amount of concrete (position of the spraying surface) according to the asperity of the tunnel inner surface 1 ascertained, the spraying thickness can be ensured more accurately and accurately. It becomes possible to perform the construction of the spray lining concrete 3 suitably.

また、第四出来高管理工程で、予め設定した所定の施工長毎に、トンネル天端部とトンネルアーチ部に検測孔を設け、これら検測孔で吹付け覆工コンクリート3の厚さを計測することによって、好適に施工が行えているか否かを確認できる。これにより、さらに確実に吹付け厚さを精度よく確保し、好適に吹付け覆工コンクリート3の施工を行うことが可能になる。   Also, in the fourth work volume management process, inspection holes are provided in the tunnel top and tunnel arches for each predetermined construction length set in advance, and the thickness of sprayed lining concrete 3 is measured using these inspection holes. By doing, it can be confirmed whether construction is being performed suitably. As a result, it is possible to more reliably secure the spraying thickness with high accuracy and to perform the construction of the sprayed lining concrete 3 appropriately.

以上、本発明に係る本実施形態の吹付け覆工コンクリートの施工方法の一実施形態について説明したが、本発明は上記の実施形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。   As mentioned above, although one Embodiment of the construction method of the spray lining concrete of this embodiment which concerns on this invention was described, this invention is not limited to said embodiment, In the range which does not deviate from the meaning, it is appropriate. It can be changed.

1 トンネル内面
2 妻枠
2a 一方の妻枠
2b 他方の妻枠
3 吹付け覆工コンクリート(吹付けコンクリート)
DESCRIPTION OF SYMBOLS 1 Tunnel inner surface 2 Wife frame 2a One wife frame 2b The other wife frame 3 Spraying lining concrete (spraying concrete)

Claims (4)

トンネル内面にコンクリートを吹付け、吹付け覆工コンクリートを施工する方法であって、
トンネル軸方向に所定の間隔をあけ、トンネル内面から内側に所定の突出量で突出しトンネル周方向に繋がる妻枠をトンネル軸方向に所定の間隔をあけて設置する妻枠設置工程と、
トンネル軸方向に隣り合う一対の妻枠の間の吹付け施工領域にコンクリートを吹付けて吹付け覆工コンクリートを構築してゆくコンクリート吹付け工程とを備え、
且つ、コンクリート吹付け工程で前記吹付け施工領域を形成する一方の妻枠から他方の妻枠に向けてコンクリートを吹付けるとともに、前記他方の妻枠側で吹付け厚さを計測する第一出来高管理工程と、
前記吹付け施工領域にコンクリートを吹付けた段階で、該吹付け施工領域に吹付けたコンクリートの端面の厚さを計測する第二出来高管理工程とを備えることを特徴とする吹付け覆工コンクリートの施工方法。
A method of spraying concrete on the inner surface of a tunnel and constructing sprayed lining concrete,
A tread frame installation step of setting a predetermined interval in the tunnel axis direction with a predetermined interval in the tunnel axis direction, and setting a predetermined interval in the tunnel axis direction that protrudes inward from the tunnel inner surface with a predetermined protrusion amount
A concrete spraying process in which concrete is sprayed onto a spraying construction area between a pair of adjacent frame frames in the tunnel axial direction to construct sprayed lining concrete,
And the first work volume which measures spraying thickness on the said other wife frame side while spraying concrete toward the other wife frame from one wife frame which forms the said spray construction area in a concrete spraying process Management process;
A spray lining concrete comprising a second volume control step of measuring a thickness of an end face of the concrete sprayed to the spraying construction area when the concrete is sprayed to the spraying construction area. Construction method.
請求項1記載の吹付け覆工コンクリートの施工方法において、
前記第一出来高管理工程と前記第二出来高管理工程では、少なくとも、トンネルの天端部と、左右のアーチ肩部と、左右のアーチ部の下端部と、左右の側壁部で吹付け厚さを計測することを特徴とする吹付け覆工コンクリートの施工方法。
In the construction method of the spray lining concrete of Claim 1,
In the first volume management process and the second volume management process, at least the top of the tunnel, the left and right arch shoulders, the lower end of the left and right arch parts, and the right and left side wall parts are sprayed. A method of constructing sprayed lining concrete characterized by measuring.
請求項1または請求項2に記載の吹付け覆工コンクリートの施工方法において、
前記隣り合う一対の妻枠の設計吹付け厚さの位置に接続して線材をトンネル軸方向に張設し、コンクリート吹付け前に前記吹付け施工領域の中間部のトンネル内面と前記線材の離間を計測する第三出来高管理工程を備え、該第三出来高管理工程の計測結果を反映させてコンクリート吹付け工程を実施することを特徴とする吹付け覆工コンクリートの施工方法。
In the construction method of the spray lining concrete of Claim 1 or Claim 2,
The wire rod is stretched in the tunnel axial direction by connecting to the position of the design spraying thickness of the pair of adjacent frame frames, and the inner surface of the tunnel in the middle of the spray construction area is separated from the wire rod before spraying the concrete. A method for constructing sprayed lining concrete, comprising a third volume management process for measuring the concrete, and performing the concrete spraying process by reflecting the measurement result of the third volume management process.
請求項1から請求項3のいずれか一項に記載の吹付け覆工コンクリートの施工方法において、
予め設定した所定の施工長毎に、トンネル天端部とトンネルアーチ部に検測孔を設け、前記検測孔で吹付け覆工コンクリートの厚さを計測する第四出来高管理工程を備えることを特徴とする吹付け覆工コンクリートの施工方法。
In the construction method of the spray lining concrete as described in any one of Claims 1-3,
For each predetermined construction length set in advance, it is provided with a fourth work volume management step in which inspection holes are provided in the tunnel top and tunnel arches, and the thickness of the sprayed lining concrete is measured by the inspection holes. A characteristic method of sprayed lining concrete.
JP2016187387A 2016-09-26 2016-09-26 Construction method of spray lining concrete Active JP6840498B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016187387A JP6840498B2 (en) 2016-09-26 2016-09-26 Construction method of spray lining concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016187387A JP6840498B2 (en) 2016-09-26 2016-09-26 Construction method of spray lining concrete

Publications (2)

Publication Number Publication Date
JP2018053449A true JP2018053449A (en) 2018-04-05
JP6840498B2 JP6840498B2 (en) 2021-03-10

Family

ID=61835397

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016187387A Active JP6840498B2 (en) 2016-09-26 2016-09-26 Construction method of spray lining concrete

Country Status (1)

Country Link
JP (1) JP6840498B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939461A (en) * 2019-10-25 2020-03-31 中铁隧道局集团有限公司 Intelligent concrete spraying method

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59189966A (en) * 1983-04-13 1984-10-27 Nippon Sogo Bosui Kk Spraying method
JPS61270499A (en) * 1985-05-24 1986-11-29 株式会社神戸製鋼所 Spraying robot for concrete, etc.
JPH0559894A (en) * 1991-08-30 1993-03-09 Penta Ocean Constr Co Ltd Thickness control system for tunnel lining sprayed concrete
JPH0681595A (en) * 1992-09-02 1994-03-22 Kumagai Gumi Co Ltd Concrete spraying construction method to tunnel inner wall and its device
JP3002075U (en) * 1994-03-16 1994-09-13 東興建設株式会社 Two-point measurement scale
JPH06323094A (en) * 1993-05-11 1994-11-22 Kajima Corp Remote control system using imaginary real sense
JPH1144199A (en) * 1997-07-29 1999-02-16 Penta Ocean Constr Co Ltd Device for measuring configuration of sprayed surface using natm
JPH11229775A (en) * 1998-02-18 1999-08-24 Sato Kogyo Co Ltd Tunnel boring machine and timbering method in tunnel drilling
JP2000120393A (en) * 1998-10-19 2000-04-25 Sato Kogyo Co Ltd Spraying device for tunnel
JP2000120394A (en) * 1998-10-19 2000-04-25 Sato Kogyo Co Ltd Remote operating system and remote operating method of spraying operation in underground excavation
JP2003013699A (en) * 2001-07-03 2003-01-15 Penta Ocean Constr Co Ltd Method and apparatus for controlling spraying of concrete
JP2003074299A (en) * 2001-08-31 2003-03-12 Daiho Constr Co Ltd Spraying device in tunnel
JP2006183384A (en) * 2004-12-28 2006-07-13 Shimizu Corp Concrete sprayer and its spraying method
JP2015021322A (en) * 2013-07-22 2015-02-02 鉄建建設株式会社 Tunnel construction method and tunnel structure

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59189966A (en) * 1983-04-13 1984-10-27 Nippon Sogo Bosui Kk Spraying method
JPS61270499A (en) * 1985-05-24 1986-11-29 株式会社神戸製鋼所 Spraying robot for concrete, etc.
JPH0559894A (en) * 1991-08-30 1993-03-09 Penta Ocean Constr Co Ltd Thickness control system for tunnel lining sprayed concrete
JPH0681595A (en) * 1992-09-02 1994-03-22 Kumagai Gumi Co Ltd Concrete spraying construction method to tunnel inner wall and its device
JPH06323094A (en) * 1993-05-11 1994-11-22 Kajima Corp Remote control system using imaginary real sense
JP3002075U (en) * 1994-03-16 1994-09-13 東興建設株式会社 Two-point measurement scale
JPH1144199A (en) * 1997-07-29 1999-02-16 Penta Ocean Constr Co Ltd Device for measuring configuration of sprayed surface using natm
JPH11229775A (en) * 1998-02-18 1999-08-24 Sato Kogyo Co Ltd Tunnel boring machine and timbering method in tunnel drilling
JP2000120393A (en) * 1998-10-19 2000-04-25 Sato Kogyo Co Ltd Spraying device for tunnel
JP2000120394A (en) * 1998-10-19 2000-04-25 Sato Kogyo Co Ltd Remote operating system and remote operating method of spraying operation in underground excavation
JP2003013699A (en) * 2001-07-03 2003-01-15 Penta Ocean Constr Co Ltd Method and apparatus for controlling spraying of concrete
JP2003074299A (en) * 2001-08-31 2003-03-12 Daiho Constr Co Ltd Spraying device in tunnel
JP2006183384A (en) * 2004-12-28 2006-07-13 Shimizu Corp Concrete sprayer and its spraying method
JP2015021322A (en) * 2013-07-22 2015-02-02 鉄建建設株式会社 Tunnel construction method and tunnel structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939461A (en) * 2019-10-25 2020-03-31 中铁隧道局集团有限公司 Intelligent concrete spraying method

Also Published As

Publication number Publication date
JP6840498B2 (en) 2021-03-10

Similar Documents

Publication Publication Date Title
US9140005B2 (en) Self-aligning corner bead for fireproofing structural steel member and method of using same
KR101372292B1 (en) Catwalk rope erection method in suspension bridge by controling unreeling speed of catwalk rope
JP2018053449A (en) Construction method for spray lining concrete
CN106424161A (en) Method and special device for determining rolling center line
CN104537566B (en) A kind of prediction technique of hexagon coal road surface displacement amount
CN103899076B (en) Method and device for demarcating construction standard of brick wall or plaster layer
CN107313430A (en) The deep big foundation pit subregion construction method of three face Nearby Structures
CN211922298U (en) Recyclable tunnel anchor cable strand embedded pipe fine adjustment device
CN108225219A (en) A kind of interior external stator installs the measuring method of concentricity
CN201908439U (en) Reserved embedded grouting die for floor sleeve holes
KR101234372B1 (en) Method of Perpendicularity Supervising Survey using Totalstation
CN204788338U (en) It lays equipment to be used for tunnel radially to converge monitoring point
CN204626466U (en) Band wing ground-connecting-wall junction block
JP2015190967A (en) Building accuracy management system and method
JP5694977B2 (en) Ground condition prediction method
PL403404A1 (en) Method for determining the deformation area, especially of the mining area
JP2020034061A (en) Sleeve for fire-resisting structure, building, and method of constructing fire-resisting structure
CN208545905U (en) A kind of protection corner for stair step
CN105386531A (en) Locating device used between buttress and vibration insulation support and construction method thereof
CN104110139A (en) Method for mounting steel columns of super high-rise steel structure
CN204492207U (en) A kind of curved walls thickeies builds aid by laying bricks or stones
CN109972679A (en) Ultra-deep underground continuous wall forming construction method thereof
CN104878694A (en) Simple bridge deck pavement elevation control method
KR101693551B1 (en) Flat-tie for formwork
CN110630820B (en) Waterproof sleeve for group penetrating through floor and manufacturing, positioning and mounting method thereof

Legal Events

Date Code Title Description
RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20181005

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190626

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200804

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200928

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210209

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210217

R150 Certificate of patent or registration of utility model

Ref document number: 6840498

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150