JP2017050953A - Parallel uninterruptible power supply system - Google Patents

Parallel uninterruptible power supply system Download PDF

Info

Publication number
JP2017050953A
JP2017050953A JP2015171594A JP2015171594A JP2017050953A JP 2017050953 A JP2017050953 A JP 2017050953A JP 2015171594 A JP2015171594 A JP 2015171594A JP 2015171594 A JP2015171594 A JP 2015171594A JP 2017050953 A JP2017050953 A JP 2017050953A
Authority
JP
Japan
Prior art keywords
power supply
peak shift
uninterruptible power
power
upss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2015171594A
Other languages
Japanese (ja)
Other versions
JP6685671B2 (en
Inventor
勝也 峯野
Katsuya Mineno
勝也 峯野
暁 末吉
Akira Sueyoshi
暁 末吉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP2015171594A priority Critical patent/JP6685671B2/en
Publication of JP2017050953A publication Critical patent/JP2017050953A/en
Application granted granted Critical
Publication of JP6685671B2 publication Critical patent/JP6685671B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/10Energy storage using batteries

Landscapes

  • Stand-By Power Supply Arrangements (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)
  • Secondary Cells (AREA)
  • Inverter Devices (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve efficiency of peak shift operation by grasping total residual capacity of a power storage unit and selecting a UPS capable of being used for the peak shift operation.SOLUTION: A device selection unit 5 selects a UPS from UPSs 11 to 13 so that difference between total residual capacity of storage batteries 11a to 13a and capacity of a load 2 is minimized and the total residual capacity of the storage batteries 11a to 13a is larger than the capacity of the load 2. Operation control units 61 to 63, when a time zone for peak shift operation has come, transmit a peak shift signal to the UPS selected from the UPSs 11 to 13 by the device selection unit 5 to make the UPS perform peak shift operation. Time arithmetic units 81 to 83 calculate residual dischargeable time periods of the storage batteries 11a to 13a. Stop control units 91 to 93, when the residual dischargeable time periods are shorter than a preset set time period, transmit a residual amount threshold signal to rectifiers 3 of the UPSs 11 to 13; the storage batteries 11a to 13a, then, stop discharging.SELECTED DRAWING: Figure 1

Description

本発明の実施形態は、無停電電源装置(以下、UPSと呼ぶ)にピークシフト運転を実施させる並列無停電電源システムに関する。   Embodiments of the present invention relate to a parallel uninterruptible power supply system that causes an uninterruptible power supply (hereinafter referred to as UPS) to perform peak shift operation.

近年、情報インフラの重要性が益々高まっている。そのため、UPSが広く導入されている。UPSは、接続された負荷に対して所定の時間だけ電力を供給し続ける装置である。UPSには、充放電可能な蓄電部が接続されている。蓄電部としては、例えばリチウムイオン蓄電池などがある。   In recent years, the importance of information infrastructure has increased. Therefore, UPS has been widely introduced. A UPS is a device that continues to supply power to a connected load for a predetermined time. Connected to the UPS is a chargeable / dischargeable power storage unit. Examples of the power storage unit include a lithium ion storage battery.

蓄電部は通常運用時には系統電源から給電を受け、系統電源からの電力供給が停止すると放電する。UPSがこの電力を負荷に供給する。これにより、系統停電が発生しても、接続された負荷に対し、同一規格の電力を所定時間与え続けることができる。このようなUPSが電力を供給する負荷は、停電が許されないサーバーなどである。そのため、UPSでは冗長性を確保することが重要である。したがって、複数台のUPSを並列に接続した並列無停電電源システムが主流となっている。   The power storage unit receives power from the system power supply during normal operation, and discharges when the power supply from the system power supply is stopped. The UPS supplies this power to the load. As a result, even if a system power failure occurs, it is possible to continue to supply the same standard power for a predetermined time to the connected load. The load to which such UPS supplies power is a server that does not allow power outages. Therefore, it is important to ensure redundancy in the UPS. Therefore, a parallel uninterruptible power supply system in which a plurality of UPSs are connected in parallel has become mainstream.

ところで最近では、UPSの余剰容量は増大傾向にある。そのため、系統停電時だけではなく通常運用時にもUPSを用いることが期待されている。具体的にはUPSをピークシフト運転に利用することが提案されている。ピークシフト運転とは、系統電源からの給電ピークと電力需要のピークの時間帯をずらして、使用電力の平準化を図る運転手法である。   Recently, however, the surplus capacity of UPS has been increasing. For this reason, it is expected to use UPS not only during a system power failure but also during normal operation. Specifically, it has been proposed to use UPS for peak shift operation. The peak shift operation is an operation technique for leveling the power used by shifting the time zone between the power supply peak from the system power supply and the peak of power demand.

ピークシフト運転を実施するUPSには、ピークシフト運転をUPSに行わせる運転制御部が接続されている。運転制御部は、予め設定されたスケジュールに従ってピークシフト信号をUPSに送信する。UPSは、ピークシフト信号を受けて、ピークシフト運転を実施する。   An operation control unit that causes the UPS to perform peak shift operation is connected to the UPS that performs peak shift operation. The operation control unit transmits a peak shift signal to the UPS according to a preset schedule. The UPS receives the peak shift signal and performs peak shift operation.

具体的には、朝や昼間などの電力需要が大きく電力料金が高い時間帯には、運転制御部がピークシフト信号をUPSに送信する。これを受けたUPSは、系統電源から受ける電力を絞ることで、絞った分だけ自然に蓄電部から放電されるようになっている。これにより、電力料金の高い時間帯での買電量を低減させて経済性を高めることが可能である。   Specifically, the operation control unit transmits a peak shift signal to the UPS during a time period when the power demand is large such as morning or daytime and the power rate is high. Receiving this, the UPS receives the power from the system power supply, and discharges from the power storage unit naturally by the amount that is reduced. Thereby, it is possible to increase the economic efficiency by reducing the amount of power purchased in the time zone when the power rate is high.

また、夜間の電力需要が少なく電力料金が安い時間帯にも、運転制御部がピークシフト信号をUPSに送信する。これを受けたUPSは、別のUPSに負荷給電を任せ、系統電源から受ける電力を蓄電部の充電に費やす。これにより、電力需要が少ない時間帯では、系統電源からの入力電力量を増やすことができる。蓄電部への充電が終了すると、UPSは通常運転に戻る。このようなUPSでは、系統電源から受ける電力に応じて、蓄電部の充放電量が受け身で制御される。その結果、系統電源からの給電ピークと電力需要のピークの時間帯をずらすことができる。   In addition, the operation control unit transmits a peak shift signal to the UPS even during a time period when the power demand at night is low and the power charge is low. Receiving this, the UPS entrusts another UPS to load power and spends the power received from the system power supply for charging the power storage unit. As a result, the amount of input power from the system power supply can be increased in a time zone where the power demand is low. When the charging of the power storage unit is completed, the UPS returns to normal operation. In such a UPS, the charge / discharge amount of the power storage unit is passively controlled according to the power received from the system power supply. As a result, the time zone between the power supply peak from the system power supply and the peak of power demand can be shifted.

特開2014−222982号公報JP 2014-222982 A

UPSは、ピークシフト運転よりも系統停電時の負荷への電力供給を優先し、ピークシフト運転の実施には余剰容量だけを利用することが基本である。そのため、各UPSがピークシフト運転を実施するか否かは、そのUPSに接続された蓄電部の残容量に依存する。つまり、UPSでは余剰容量を超えてまで、蓄電部の電力を利用してピークシフト運転を実施することはない。   UPS gives priority to the power supply to the load at the time of a system power failure rather than the peak shift operation, and it is fundamental to use only the surplus capacity for the peak shift operation. Therefore, whether or not each UPS performs peak shift operation depends on the remaining capacity of the power storage unit connected to the UPS. That is, in UPS, peak shift operation is not performed using the power of the power storage unit until the surplus capacity is exceeded.

複数台のUPSを接続した並列無停電電源システムでは、システム全体として見ると、非常に大きな余剰容量を有するが、既存のピークシフト手法では、UPS一台の蓄電部の残容量しか見ていない。すなわち、複数台のUPSにおける蓄電部の残容量を同時に監視していない。   A parallel uninterruptible power supply system in which a plurality of UPSs are connected has a very large surplus capacity when viewed as a whole system, but the existing peak shift method only looks at the remaining capacity of one power storage unit of the UPS. That is, the remaining capacity of the power storage units in a plurality of UPSs is not monitored at the same time.

したがって、並列無停電電源システムとして合計でどの程度の余剰容量があるのか分からず、ピークシフトが十分に行えない。また、複数台のUPSをどのように制御してピークシフトを行うか、制御手法が確立していない。そこで並列無停電電源システムにおいては、蓄電部の電力を有効に利用して、ピークシフト運転を効率良く実施することが求められていた。   Therefore, it is not known how much surplus capacity is in total as a parallel uninterruptible power supply system, and peak shift cannot be performed sufficiently. In addition, a control method has not been established as to how to control a plurality of UPSs to perform peak shift. Therefore, in the parallel uninterruptible power supply system, it has been required to efficiently use the peak shift operation by effectively using the power of the power storage unit.

本実施形態は、上記の課題を解決するために提案されたものであり、その目的は、蓄電部の総残容量を把握してピークシフト運転に使用できるUPSを選択することにより、ピークシフト運転の効率向上を図った並列無停電電源システムを提供することにある。   The present embodiment has been proposed to solve the above-described problem. The purpose of this embodiment is to grasp the total remaining capacity of the power storage unit and select a UPS that can be used for peak shift operation. It is to provide a parallel uninterruptible power supply system that improves the efficiency of the system.

上記目的を達成するために、本発明の実施形態は、系統電源から電力の入力を受け所定の負荷へ電力を供給する無停電電源装置を、並列に複数台接続した並列無停電電源システムにおいて、次の構成要素(1)〜(3)を有している。
(1)前記各無停電電源装置に接続される充放電可能な蓄電部。
(2)予め設定されたスケジュールに従ってピークシフト信号を前記無停電電源装置に送信することにより、前記蓄電部の電力を利用して系統電源からの入力電力を増減させるピークシフト運転を、前記無停電電源装置に行わせる運転制御部。
(3)前記各蓄電部の残容量の和である総残容量と前記負荷の容量との差が最小で、且つ前記蓄電部の総残容量の方が負荷の容量よりも大きくなるように、ピークシフト運転に使用するための前記無停電電源装置を選択する装置選択部。
In order to achieve the above object, an embodiment of the present invention is a parallel uninterruptible power supply system in which a plurality of uninterruptible power supplies that receive power input from a system power supply and supply power to a predetermined load are connected in parallel. It has the following components (1) to (3).
(1) A chargeable / dischargeable power storage unit connected to each uninterruptible power supply.
(2) A peak shift operation for increasing / decreasing input power from a system power supply using power of the power storage unit by transmitting a peak shift signal to the uninterruptible power supply according to a preset schedule is performed on the uninterruptible power supply. Operation control unit to be performed by the power supply device.
(3) The difference between the total remaining capacity, which is the sum of the remaining capacity of each power storage unit, and the capacity of the load is minimum, and the total remaining capacity of the power storage unit is greater than the capacity of the load. A device selection unit that selects the uninterruptible power supply to be used for peak shift operation.

第1の実施形態のブロック図。The block diagram of 1st Embodiment. 第1の実施形態の要部ブロック図(通常運転時)。The principal part block diagram of 1st Embodiment (at the time of normal driving | operation). 第1の実施形態の要部ブロック図(一括蓄電池アシストモードの開始時)。The principal part block diagram of 1st Embodiment (at the time of the start of batch storage battery assist mode). 第1の実施形態の要部ブロック図(一括蓄電池アシストモードの終了時)。The principal part block diagram of 1st Embodiment (at the time of completion | finish of batch storage battery assist mode). 第1の実施形態の要部ブロック図(一括蓄電池急速充電モード時)。The principal part block diagram of 1st Embodiment (at the time of a batch storage battery quick charge mode). 第1の実施形態の要部ブロック図(蓄電池11aのアシストモードの開始時)。The principal part block diagram of 1st Embodiment (at the time of the start of assist mode of the storage battery 11a). 第1の実施形態の要部ブロック図(蓄電池11aのアシストモードの終了時&蓄電池12aのアシストモードの開始時)。The principal part block diagram of 1st Embodiment (at the time of the end of the assist mode of the storage battery 11a & the start of the assist mode of the storage battery 12a). 第1の実施形態の要部ブロック図(蓄電池12aのアシストモードの終了時)。The principal part block diagram of 1st Embodiment (at the time of completion | finish of the assist mode of the storage battery 12a). 第1の実施形態の要部ブロック図(蓄電池11aの急速充電モードの開始時)。The principal part block diagram of 1st Embodiment (at the time of the start of the quick charge mode of the storage battery 11a). 第1の実施形態の要部ブロック図(蓄電池11aの急速充電モードの終了時&蓄電池12aの急速充電モードの開始時)。The principal part block diagram of 1st Embodiment (at the time of completion | finish of the quick charge mode of the storage battery 11a & the start of the quick charge mode of the storage battery 12a).

(1)第1の実施形態
(構成)
以下、本発明の第1の実施形態の構成について、図面を用いて具体的に説明する。図1は第1の実施形態のブロック図である。図1に示すように、第1の実施形態は、n台(図では3台)のUPS11〜13を、並列に接続した並列無停電電源システム1である。UPS11〜13には負荷2が接続されている。負荷2としては停電を許容しないサーバーなどが代表的であるが、これに限らず交流電力が供給される負荷であればよい。
(1) First embodiment (configuration)
Hereinafter, the configuration of the first exemplary embodiment of the present invention will be specifically described with reference to the drawings. FIG. 1 is a block diagram of the first embodiment. As shown in FIG. 1, the first embodiment is a parallel uninterruptible power supply system 1 in which n (three in the figure) UPSs 11 to 13 are connected in parallel. A load 2 is connected to the UPSs 11 to 13. The load 2 is typically a server that does not allow a power failure, but is not limited to this and may be any load that is supplied with AC power.

[並列無停電電源システムの概要]
並列無停電電源システム1には、装置選択部5と、運転制御部61〜63と、必要台数演算部7と、時間演算部81〜83と、停止制御部91〜93が設けられている。運転制御部61〜63と、時間演算部81〜83と、停止制御部91〜93は、UPS11〜13ごとに設けられている。
[Overview of parallel uninterruptible power supply system]
The parallel uninterruptible power supply system 1 is provided with a device selection unit 5, operation control units 61 to 63, a required number calculation unit 7, time calculation units 81 to 83, and stop control units 91 to 93. The operation control units 61 to 63, the time calculation units 81 to 83, and the stop control units 91 to 93 are provided for each UPS 11-13.

[UPS]
UPS11〜13は、系統電源10から電力の入力を受け負荷2へ電力を供給する。UPS11〜13にはそれぞれ、整流器3と、インバータ4が設けられている。整流器3は、系統電源10から入力される交流電力を直流電力に変換する。インバータ4は、整流器3が変換した直流電力を交流電力に変換する。各UPS11〜13には蓄電池11a〜13aが接続されている。蓄電池11a〜13aは、例えばリチウムイオン蓄電池などからなる。
[UPS]
The UPSs 11 to 13 receive power input from the system power supply 10 and supply power to the load 2. Each of the UPSs 11 to 13 is provided with a rectifier 3 and an inverter 4. The rectifier 3 converts AC power input from the system power supply 10 into DC power. The inverter 4 converts the DC power converted by the rectifier 3 into AC power. Storage batteries 11a to 13a are connected to the UPSs 11 to 13, respectively. Storage battery 11a-13a consists of a lithium ion storage battery etc., for example.

UPS11〜13は通常運転及びピークシフト運転を実施する。通常運転時のUPS11〜13は、系統電源10から入力された交流電力を、整流器3及びインバータ4を通して負荷2に交流電力を供給する。また、UPS11〜13は、系統停電が発生して系統電源10から入力電力が無くなると、蓄電池11a〜13aを放電させる。そのため、UPS11〜13は負荷2に交流電力を所定時間だけ供給する。   The UPSs 11 to 13 perform normal operation and peak shift operation. The UPSs 11 to 13 during normal operation supply AC power input from the system power supply 10 to the load 2 through the rectifier 3 and the inverter 4. Further, the UPSs 11 to 13 discharge the storage batteries 11 a to 13 a when the system power failure occurs and the input power is lost from the system power supply 10. Therefore, the UPSs 11 to 13 supply AC power to the load 2 for a predetermined time.

さらに、系統電源10が復電するとUPS11〜13は通常運転に戻る。このとき、整流器3にて交流電力から変換した直流電力を、蓄電池11a〜13aへ送る。これにより、放電で低下した蓄電池11a〜13aの蓄電量を、元の値まで戻す。   Further, when the system power supply 10 is restored, the UPSs 11 to 13 return to normal operation. At this time, DC power converted from AC power by the rectifier 3 is sent to the storage batteries 11a to 13a. As a result, the storage amount of the storage batteries 11a to 13a that has decreased due to the discharge is returned to the original value.

ピークシフト運転とは、蓄電池11a〜13aの電力を利用して系統電源10からの入力電力を増減させる運転である。ピークシフト運転は、運転制御部61〜63からUPS11〜13がピークシフト信号を受信することで実施される。ピークシフト信号とは、蓄電池11a〜13aに放電を行わせる入力制限信号及び蓄電池11a〜13aに充電を急速に行わせる蓄電池急速充電信号である。   The peak shift operation is an operation that increases or decreases the input power from the system power supply 10 using the power of the storage batteries 11a to 13a. The peak shift operation is performed when the UPSs 11 to 13 receive the peak shift signal from the operation control units 61 to 63. The peak shift signal is an input restriction signal that causes the storage batteries 11a to 13a to discharge and a storage battery quick charge signal that causes the storage batteries 11a to 13a to be rapidly charged.

入力制限信号は、各蓄電池11a〜13aを放電させるための信号であり、UPS11〜13の整流器3に送られる。蓄電池急速充電信号は、各蓄電池11a〜13aを急速に充電させるための信号であり、UPS11〜13のインバータ4に送られる。   The input restriction signal is a signal for discharging the storage batteries 11a to 13a, and is sent to the rectifier 3 of the UPSs 11 to 13. The storage battery quick charge signal is a signal for rapidly charging each of the storage batteries 11 a to 13 a and is sent to the inverter 4 of the UPS 11 to 13.

系統電源10からの入力電力を低減させるピークシフト運転時のUPS11〜13では、運転制御部61〜63から入力制限信号を整流器3が受信する。入力制限信号を受けた整流器3は、系統電源10からの入力を低減させ、低減させた電力分だけ自然に蓄電池11a〜13aを放電させる。   In UPS 11-13 during peak shift operation that reduces input power from the system power supply 10, the rectifier 3 receives an input restriction signal from the operation control units 61-63. The rectifier 3 that has received the input restriction signal reduces the input from the system power supply 10 and discharges the storage batteries 11a to 13a naturally by the reduced power.

例えば、負荷2の容量が「3P」であり、系統電源10からの入力電力量を「1P」に絞ると、蓄電池11a〜13aの放電量は「3−1=2P」となる。ここで、ピークシフト運転において蓄電池11a〜13aの放電量が負荷2への電力供給量の2/3を賄っているが、放電量の大きさに関係なく、概念的には蓄電池11a〜13aの放電量が系統電源10からの入力電力量をアシストしているとして、蓄電池11a〜13aの放電動作を蓄電池アシストモードと呼ぶこととする。   For example, when the capacity of the load 2 is “3P” and the amount of input power from the system power supply 10 is reduced to “1P”, the discharge amount of the storage batteries 11a to 13a is “3-1 = 2P”. Here, in the peak shift operation, the discharge amount of the storage batteries 11a to 13a covers 2/3 of the power supply amount to the load 2, but the storage batteries 11a to 13a are conceptually irrespective of the magnitude of the discharge amount. The discharge operation of the storage batteries 11a to 13a is referred to as a storage battery assist mode, assuming that the discharge amount assists the input power amount from the system power supply 10.

また、系統電源10からの入力電力を増加させるピークシフト運転時のUPS11〜13では、運転制御部61〜63からインバータ4が蓄電池急速充電信号を受信する。蓄電池急速充電信号を受けたインバータ4は一時的に出力を切り、負荷給電を他の並列号機であるUPSに任せることで、入力電力を全て充電に使う。これにより、インバータ4は蓄電池11a〜13aを急速充電させる。すなわち、蓄電池急速充電信号を受信したインバータ4では、他の並列号機で負荷給電を行っているのとは別で、蓄電池11a〜13aへの急速充電を行う。そのため、系統電源10からの交流電力の総入力量を増やすことができる。   Moreover, in UPS11-13 at the time of the peak shift operation which increases the input electric power from the system power supply 10, the inverter 4 receives a storage battery quick charge signal from the operation control parts 61-63. The inverter 4 that has received the storage battery quick charge signal temporarily cuts the output and leaves the load power supply to UPS, which is another parallel unit, so that all input power is used for charging. Thereby, the inverter 4 charges the storage batteries 11a-13a rapidly. That is, in the inverter 4 that has received the storage battery quick charge signal, quick charge to the storage batteries 11a to 13a is performed separately from the load power feeding performed by other parallel units. Therefore, the total input amount of AC power from the system power supply 10 can be increased.

例えば、負荷2の容量が「3P」であり、蓄電池11a〜13aの充電量を「2P」とすると、系統電源10からの総入力電力量は、通常運転時の「3P」から、「3+2=5P」に増えることになる。蓄電池11a〜13aの充電動作を蓄電池急速充電モードと呼ぶ。ここでいう急速充電とは、通常運転時にも蓄電池11a〜13aの充電を行うが、このときの充電に比べて急速に充電を行うということを示したものであり、具体的な充電速度を示すものではない。   For example, when the capacity of the load 2 is “3P” and the charge amount of the storage batteries 11a to 13a is “2P”, the total input power amount from the system power supply 10 is “3 + 2 = Will increase to 5P ". The charging operation of the storage batteries 11a to 13a is referred to as a storage battery quick charge mode. The rapid charging here indicates that the storage batteries 11a to 13a are charged even during normal operation, but the charging is performed more rapidly than the charging at this time, and indicates a specific charging speed. It is not a thing.

[必要台数演算部]
必要台数演算部7は、負荷2の容量とUPS11〜13の台数に基づいて負荷2に必要なUPS11〜13の台数を求める。必要台数演算部7は、求めた台数を装置選択部5に送る。例えば、負荷2に流れる電流×電圧が200kVAで、500kVA×3台のUPS11〜13である場合には、負荷2に必要なUPSは、3台のうち1台あれば十分である。また、負荷2に流れる電流×電圧が700kVAで、同じく500kVA×3台のUPS11〜13である場合には、負荷2に必要なUPSは、3台のうち2台のUPSが必要となる。
[Required number calculation section]
The required number calculation unit 7 obtains the number of UPSs 11 to 13 necessary for the load 2 based on the capacity of the load 2 and the number of UPSs 11 to 13. The required number calculation unit 7 sends the determined number to the device selection unit 5. For example, when the current × voltage flowing through the load 2 is 200 kVA and 500 kVA × 3 UPSs 11 to 13, one UPS out of three is sufficient. Further, when the current × voltage flowing through the load 2 is 700 kVA and the same 500 kVA × 3 UPSs 11 to 13, the UPS required for the load 2 requires two of the three UPSs.

[装置選択部]
装置選択部5は、必要台数演算部7が求めた台数に従い、蓄電池11a〜13aの総残容量と負荷2の容量との差が最小で、且つ蓄電池11a〜13aの総残容量の方が負荷2の容量よりも大きくなるように、ピークシフト運転に使用するためのUPS11〜13を選択する。蓄電池11a〜13aの総残容量とは、各蓄電池11a〜13aの残容量の和である。例えば、負荷2の容量が「3P」であれば、装置選択部5は、蓄電池11a〜13aの総残容量が「3P」以上で、且つ極力「3P」に近づくようにUPS11〜13を選択する。
[Device selection section]
According to the number obtained by the required number calculation unit 7, the device selection unit 5 has the smallest difference between the total remaining capacity of the storage batteries 11a to 13a and the capacity of the load 2, and the total remaining capacity of the storage batteries 11a to 13a is more loaded. The UPSs 11 to 13 for use in peak shift operation are selected so as to be larger than the capacity of 2. The total remaining capacity of the storage batteries 11a to 13a is the sum of the remaining capacity of each of the storage batteries 11a to 13a. For example, when the capacity of the load 2 is “3P”, the device selection unit 5 selects the UPSs 11 to 13 so that the total remaining capacity of the storage batteries 11a to 13a is “3P” or more and approaches “3P” as much as possible. .

また、装置選択部5は、複数のUPS11〜13を選択する時、複数のUPS11〜13を一括して制御する一括制御と、複数のUPS11〜13を1つずつ個別に制御する個別制御を取る。さらに装置選択部5にはUPS11〜13に関して優先的に選択される順番が予め設定されている。そのため、装置選択部5は、優先順位に従って、UPS11〜13の組合せを決めている。   In addition, when selecting a plurality of UPSs 11 to 13, the device selection unit 5 takes a batch control for collectively controlling the plurality of UPSs 11 to 13 and an individual control for individually controlling the plurality of UPSs 11 to 13 one by one. . Further, the order in which the apparatus selection unit 5 is preferentially selected with respect to the UPSs 11 to 13 is set in advance. Therefore, the device selection unit 5 determines combinations of UPSs 11 to 13 according to the priority order.

[運転制御部]
運転制御部61〜63は、通常運転信号及びピークシフト信号をUPS11〜13に送信する。運転制御部61〜63がUPS11〜13に通常運転信号を送信することで、UPS11〜13は通常運転を実施する。運転制御部61〜63がUPS11〜13にピークシフト信号を送信する。このピークシフト信号を受信することでUPS11〜13はピークシフト運転を実施する。
[Operation control unit]
The operation controllers 61 to 63 transmit the normal operation signal and the peak shift signal to the UPSs 11 to 13. When the operation control units 61 to 63 transmit normal operation signals to the UPSs 11 to 13, the UPSs 11 to 13 perform normal operations. The operation controllers 61 to 63 transmit peak shift signals to the UPSs 11 to 13. By receiving this peak shift signal, the UPSs 11 to 13 perform peak shift operation.

運転制御部61〜63では、通常運転信号及びピークシフト信号を送信するタイミングとして、ピークシフト運転の時間帯と通常運転の時間帯に分けたスケジュールを、予め設定しておく。ピークシフト運転の時間帯は、朝や昼など電力需要が大きい時間帯と、夜などの電力需要が少ない時間帯に分かれる。   In the operation control units 61 to 63, as a timing for transmitting the normal operation signal and the peak shift signal, a schedule divided into a peak shift operation time zone and a normal operation time zone is set in advance. The peak shift operation time period is divided into a time period where the power demand is large such as morning and noon and a time period where the power demand is small such as night.

運転制御部61〜63は、このスケジュールに従って通常運転の時間帯になると、全てのUPS11〜13に通常運転信号を送信して通常運転を実施させる。また、運転制御部61〜63は、ピークシフト運転の時間帯になると、装置選択部5が選択したUPS11〜13にピークシフト信号を送信してピークシフト運転を実施させる。既に述べたようにピークシフト信号には入力制限信号と蓄電池急速充電信号がある。   When the normal operation time zone is reached according to this schedule, the operation control units 61 to 63 transmit normal operation signals to all the UPSs 11 to 13 to perform normal operation. Moreover, the operation control parts 61-63 will transmit a peak shift signal to UPS11-13 which the apparatus selection part 5 selected when the time zone of peak shift operation comes, and will implement a peak shift operation. As already described, the peak shift signal includes an input limit signal and a storage battery quick charge signal.

より詳しくは、運転制御部61〜63は、電力需要が大きい時間帯になると、UPS11〜13の整流器3に入力制限信号を送信する。入力制限信号を受けた整流器3は系統電源10からの入力を低減させ、低減させた電力分だけ自然に蓄電池11a〜13aを放電させる。また、運転制御部61〜63は、電力需要が少ない時間帯になると、UPS11〜13のインバータ4に蓄電池急速充電信号を送信する。蓄電池急速充電信号を受けたインバータ4は入力した電力を全て蓄電池11a〜13aの充電に使うことで、蓄電池11a〜13aを急速充電させる。   More specifically, the operation control units 61 to 63 transmit an input restriction signal to the rectifier 3 of the UPS 11 to 13 when the power demand is large. The rectifier 3 that has received the input restriction signal reduces the input from the system power supply 10 and discharges the storage batteries 11a to 13a naturally by the reduced power. Moreover, the operation control parts 61-63 will transmit a storage battery quick charge signal to the inverter 4 of UPS11-13, when it becomes a time slot | zone with little electric power demand. The inverter 4 that has received the storage battery quick charge signal uses all the input power to charge the storage batteries 11a to 13a, thereby rapidly charging the storage batteries 11a to 13a.

装置選択部5が一括制御を取る場合、運転制御部61〜63は、装置選択部5が選択した複数のUPS11〜13に対しピークシフト信号を同時に送信する。このとき、装置選択部5が選択した台数をx台とすると、運転制御部61〜63は、UPS11〜13に対してx分の1ずつの放電量又は充電量となるように指示するピークシフト信号を送信する。   When the apparatus selection part 5 takes batch control, the operation control parts 61-63 transmit a peak shift signal simultaneously with respect to several UPS11-13 which the apparatus selection part 5 selected. At this time, assuming that the number of units selected by the device selection unit 5 is x, the operation control units 61 to 63 instruct the UPSs 11 to 13 to set the discharge amount or the charge amount by 1 / x. Send a signal.

具体的には、装置選択部5が一括制御でUPS11、12を選択する場合、運転制御部61、62は、UPS11、12に対し1/2ずつの放電量となるように入力制限信号を同時に送信する。あるいは、運転制御部61、62は、UPS11、12に対し1/2ずつの充電量となるように蓄電池急速充電信号を同時に送信する。   Specifically, when the device selection unit 5 selects the UPSs 11 and 12 by batch control, the operation control units 61 and 62 simultaneously input the input restriction signal so that the discharge amount is ½ each of the UPSs 11 and 12. Send. Alternatively, the operation control units 61 and 62 simultaneously transmit a storage battery quick charge signal so that the charge amount is ½ each for the UPSs 11 and 12.

また、装置選択部5が個別制御を取る場合、運転制御部61〜63は、装置選択部5が選択した複数のUPS11〜13に対しピークシフト信号を1台ずつ順番に送信する。例えば、装置選択部5がUPS11、12を選択するとき、運転制御部61がUPS11に対して入力制限信号及び蓄電池急速充電信号を連続して送信し、続いて、運転制御部62がUPS12に対して入力制限信号及び蓄電池充電信号を連続して送信する。   Moreover, when the apparatus selection part 5 takes individual control, the operation control parts 61-63 transmit a peak shift signal to the some UPS11-13 selected by the apparatus selection part 5 one by one in order. For example, when the device selection unit 5 selects the UPSs 11 and 12, the operation control unit 61 continuously transmits an input restriction signal and a storage battery quick charge signal to the UPS 11, and then the operation control unit 62 transmits to the UPS 12. The input restriction signal and the storage battery charging signal are transmitted continuously.

[時間演算部]
時間演算部81〜83は、蓄電池11a〜13aから蓄電池11a〜13aの容量及び電流量を取り込み蓄電池11a〜13aの残り放電可能時間を求める。
[Time calculation section]
The time calculation units 81 to 83 take in the capacity and current amount of the storage batteries 11a to 13a from the storage batteries 11a to 13a, and obtain the remaining dischargeable time of the storage batteries 11a to 13a.

[停止制御部]
停止制御部91〜93は、時間演算部81〜83の求めた残り放電可能時間が予め設定された時間を下回ると、残量閾値信号をUPS11〜13の整流器3に送信する。残量閾値信号は、残り放電可能時間が予め設定された時間を下回ったことを示す信号である。
[Stop control section]
When the remaining dischargeable time obtained by the time calculators 81 to 83 falls below a preset time, the stop controllers 91 to 93 transmit a remaining amount threshold signal to the rectifiers 3 of the UPSs 11 to 13. The remaining amount threshold signal is a signal indicating that the remaining dischargeable time is less than a preset time.

停止制御部91〜93にて設定される時間としては、蓄電池11a〜13aの残り放電量の和が、系統停電時に供給される負荷2への電力量を下回らないようにした時間であればよい。残量閾値信号を受けた整流器3は、系統電源10からの入力制限を解除して元のレベルに復帰させる。これにより、蓄電池12aは放電を停止して通常運転に戻る。   The time set by the stop control units 91 to 93 may be a time that prevents the sum of the remaining discharge amounts of the storage batteries 11a to 13a from falling below the amount of power supplied to the load 2 supplied at the time of a system power failure. . The rectifier 3 that has received the remaining amount threshold signal releases the input restriction from the system power supply 10 and restores the original level. Thereby, the storage battery 12a stops discharging and returns to normal operation.

(作用)
[通常運転時]
図2は、UPS11〜13が通常運転を行っている場合を示している。このとき、運転制御部61〜63はUPS11〜13の整流器3に通常運転信号を送信する。通常運転信号を受けたUPS11〜13はそれぞれ、系統電源10から交流電力Pを入力し、インバータ4が交流電力Pを出力する。これにより、UPS11〜13は負荷2に交流電力3Pを出力する。
(Function)
[During normal operation]
FIG. 2 shows a case where the UPSs 11 to 13 are performing normal operation. At this time, the operation control units 61 to 63 transmit normal operation signals to the rectifiers 3 of the UPSs 11 to 13. Receiving the normal operation signal, each of the UPSs 11 to 13 receives AC power P from the system power supply 10, and the inverter 4 outputs AC power P. Thereby, the UPSs 11 to 13 output the AC power 3P to the load 2.

[一括蓄電池アシストモードの開始時]
図3では、UPS11、12がピークシフト運転を行い、UPS13が通常運転を行っている。装置選択部5は一括制御を取り、蓄電池アシストモードを開始する。図3において、必要台数演算部7がピークシフト運転の実施に必要なUPS11〜13の台数を2台としており、装置選択部5は、必要台数演算部7の演算結果に従い、ピークシフト運転に使用するUPSを、UPS11、12の2台とする。
[When starting batch battery assist mode]
In FIG. 3, the UPSs 11 and 12 perform peak shift operation, and the UPS 13 performs normal operation. The device selection unit 5 takes batch control and starts the storage battery assist mode. In FIG. 3, the necessary number calculation unit 7 uses two UPSs 11 to 13 necessary for the peak shift operation, and the device selection unit 5 is used for the peak shift operation according to the calculation result of the necessary number calculation unit 7. Two UPSs 11 and 12 are used.

運転制御部61、62は、装置選択部5が選択したUPS11、12の整流器3に対して入力制限信号を同時に送信する。入力制限信号を受けた整流器3は、系統電源10からの入力を低減させる。蓄電池11a、12aは、低減した電力に応じて自然に放電する。   The operation control units 61 and 62 simultaneously transmit an input restriction signal to the rectifiers 3 of the UPSs 11 and 12 selected by the device selection unit 5. The rectifier 3 that has received the input restriction signal reduces the input from the system power supply 10. Storage battery 11a, 12a discharges naturally according to the reduced electric power.

この放電した直流電力をインバータ4に取り込む。インバータ4はそれぞれ交流電力Pを出力して、合計2Pを負荷2に出力する。なお、時間演算部81、82は、蓄電池11a、12aから蓄電池11a、12aの容量及び電流量を取り込んでおり、蓄電池11a、12aの残り放電可能時間を求めている。   This discharged DC power is taken into the inverter 4. Each inverter 4 outputs AC power P and outputs a total of 2P to the load 2. The time calculation units 81 and 82 take in the capacity and current amount of the storage batteries 11a and 12a from the storage batteries 11a and 12a, and obtain the remaining dischargeable time of the storage batteries 11a and 12a.

運転制御部63は、UPS13の整流器3に対し通常運転信号を送信する。このため、UPS13は、通常運転を実施している。すなわち、UPS13では、系統電源10から交流電力Pを入力し、インバータ4が交流電力Pを出力する。これにより、並列無停電電源システム1では、系統電源10からの入力電力を、通常運転時の3Pから1Pだけに抑えることができ、ピークシフト運転を実現させている。また、負荷2への出力電力は蓄電池11a、12aからの放電電力を利用することで、交流電力3Pを確保している。   The operation control unit 63 transmits a normal operation signal to the rectifier 3 of the UPS 13. For this reason, the UPS 13 performs a normal operation. That is, in the UPS 13, AC power P is input from the system power supply 10, and the inverter 4 outputs AC power P. Thereby, in the parallel uninterruptible power supply system 1, the input electric power from the system power supply 10 can be suppressed from 3P in normal operation to only 1P, and the peak shift operation is realized. Moreover, the output electric power to the load 2 has secured the alternating current power 3P by utilizing the discharge electric power from the storage batteries 11a and 12a.

[一括蓄電池アシストモードの終了時]
図4では、図3の蓄電池アシストモードが終了した状態を示している。時間演算部81、82は、蓄電池11a、12aから蓄電池11a、12aの容量及び電流量を取り込み、蓄電池11a、12aの残り放電可能時間を求める。停止制御部91、92は、時間演算部81、82の求めた残り放電可能時間が予め設定された時間を下回った時点で、残量閾値信号をUPS11、12の整流器3に送信する。残量閾値信号を受けた整流器3では系統電源10からの入力制限を解除して、元の入力値に戻す。整流器3において系統電源10からの入力電力が通常運転時に戻ると、蓄電池11a、12aは放電を停止し、共に通常運転に戻る。
[At the end of the batch storage battery assist mode]
FIG. 4 shows a state where the storage battery assist mode of FIG. 3 has been completed. The time calculation units 81 and 82 take in the capacity and current amount of the storage batteries 11a and 12a from the storage batteries 11a and 12a, and obtain the remaining dischargeable time of the storage batteries 11a and 12a. The stop control units 91 and 92 transmit the remaining amount threshold signal to the rectifiers 3 of the UPSs 11 and 12 when the remaining dischargeable time obtained by the time calculation units 81 and 82 falls below a preset time. The rectifier 3 that has received the remaining amount threshold signal cancels the input restriction from the system power supply 10 and returns it to the original input value. When the input power from the system power supply 10 returns to normal operation in the rectifier 3, the storage batteries 11a and 12a stop discharging and return to normal operation.

[一括蓄電池急速充電モード時]
図5では、UPS11、12がピークシフト運転を行っている。ここで、装置選択部5は一括制御を取り、蓄電池急速充電モードを行う。図5において、必要台数演算部7がピークシフト運転の実施に必要なUPS11〜13の台数を2台とする。このため、装置選択部5は、必要台数演算部7の演算結果に従い、ピークシフト運転に使用するUPSを、UPS11、12の2台とする。
[In batch storage battery quick charge mode]
In FIG. 5, the UPSs 11 and 12 are performing peak shift operation. Here, the apparatus selection part 5 takes batch control, and performs storage battery quick charge mode. In FIG. 5, the required number calculation unit 7 sets the number of UPSs 11 to 13 required for performing the peak shift operation to two. For this reason, the device selection unit 5 sets two UPSs 11 and 12 to be used for peak shift operation according to the calculation result of the necessary number calculation unit 7.

運転制御部61、62は、装置選択部5が選択したUPS11、12のインバータ4に対し、蓄電池急速充電信号を同時に送信する。蓄電池急速充電信号を受けたUPS11、12では、整流器3が変換した直流電力を蓄電池11a、12aへ送り、蓄電池11a、12aは直流電力を充電する。すなわち、UPS11、12では、インバータ4が一時的に出力を切り、他の並列号機であるUPSに負荷給電を任せる。このため、UPS11、12は負荷2側には電力を供給していない。したがって、UPS11、12は、系統電源10からの交流電力2Pchを、全て蓄電池11a、12aへの充電用電力分として用いることができる。   The operation control units 61 and 62 simultaneously transmit a storage battery quick charge signal to the inverters 4 of the UPSs 11 and 12 selected by the device selection unit 5. In the UPSs 11 and 12 that have received the storage battery quick charge signal, the DC power converted by the rectifier 3 is sent to the storage batteries 11a and 12a, and the storage batteries 11a and 12a charge the DC power. That is, in the UPSs 11 and 12, the inverter 4 temporarily cuts off the output, and leaves the power supply to other UPSs that are parallel units. For this reason, the UPSs 11 and 12 do not supply power to the load 2 side. Therefore, the UPSs 11 and 12 can use all the AC power 2Pch from the system power supply 10 as power for charging the storage batteries 11a and 12a.

時間演算部81、82は、蓄電池11a、12aから蓄電池11a、12aの容量及び電流量を取り込み、蓄電池11a、12aの残り放電可能時間を求めている。ここで、蓄電池11a、12aの残り放電可能時間が、予め定められた規定の残り放電可能時間まで戻ると、蓄電池11a、12aの充電が終了したことになり、運転制御部61、62はUPS11、12のインバータ4への信号を蓄電池急速充電信号から通常運転信号に切り替え、蓄電池11a、12aを通常運転に戻す。   The time calculation units 81 and 82 take in the capacity and current amount of the storage batteries 11a and 12a from the storage batteries 11a and 12a, and obtain the remaining dischargeable time of the storage batteries 11a and 12a. Here, when the remaining dischargeable time of the storage batteries 11a, 12a returns to a predetermined remaining dischargeable time, charging of the storage batteries 11a, 12a is completed, and the operation control units 61, 62 are connected to the UPS 11, The signal to 12 inverters 4 is switched from the storage battery quick charge signal to the normal operation signal, and the storage batteries 11a and 12a are returned to the normal operation.

運転制御部63は、UPS13に対し通常運転信号を送信する。このため、UPS13は、通常運転を実施している。ここで、UPS13だけが負荷2に電力を供給するので、UPS13は系統電源10から交流電力3Pを入力し、インバータ4が交流電力3Pを出力する。このように、並列無停電電源システム1では、負荷2への交流電力3Pだけではなく、これに蓄電池11a、12aへの充電用の電力2Pchに加えて、交流電力5Pを入力している。すなわち、蓄電池11a、12aが急速充電を行うことで、系統電源10からの入力電力を増やし、ピークシフト運転を実現させている。   The operation control unit 63 transmits a normal operation signal to the UPS 13. For this reason, the UPS 13 performs a normal operation. Here, since only the UPS 13 supplies power to the load 2, the UPS 13 receives AC power 3P from the system power supply 10, and the inverter 4 outputs AC power 3P. As described above, in the parallel uninterruptible power supply system 1, not only the AC power 3P to the load 2 but also the AC power 5P is input in addition to the power 2Pch for charging the storage batteries 11a and 12a. That is, the storage batteries 11a and 12a perform quick charging, thereby increasing the input power from the system power supply 10 and realizing peak shift operation.

[蓄電池11aのアシストモードの開始時]
図6では、電力需要が大きい時間帯において、UPS11だけがピークシフト運転を行い、UPS12、13が通常運転を行っている。装置選択部5は個別制御を取り、UPS11が蓄電池アシストモードを開始する。図6において、必要台数演算部7はピークシフト運転の実施に必要なUPS11〜13の台数を1台とする。このため、装置選択部5は、必要台数演算部7の演算結果に従い、ピークシフト運転に使用するUPSを、UPS11の1台とする。
[At the start of the assist mode of the storage battery 11a]
In FIG. 6, only the UPS 11 performs the peak shift operation and the UPSs 12 and 13 perform the normal operation in the time zone when the power demand is large. The device selection unit 5 takes individual control, and the UPS 11 starts the storage battery assist mode. In FIG. 6, the required number calculation unit 7 sets the number of UPSs 11 to 13 required for performing the peak shift operation as one. Therefore, the device selection unit 5 sets the UPS used for peak shift operation as one UPS 11 according to the calculation result of the necessary number calculation unit 7.

運転制御部61は、装置選択部5が選択したUPS11の整流器3に対し、入力制限信号を送信する。入力制限信号を受けたUPS11の整流器3では、系統電源10からの入力を低減させる。蓄電池11aは、低減した電力に応じて自然に放電する。この放電した直流電力をインバータ4に取り込む。インバータ4は交流電力Pを負荷2に出力する。   The operation control unit 61 transmits an input restriction signal to the rectifier 3 of the UPS 11 selected by the device selection unit 5. In the rectifier 3 of the UPS 11 that has received the input restriction signal, the input from the system power supply 10 is reduced. The storage battery 11a naturally discharges according to the reduced power. This discharged DC power is taken into the inverter 4. The inverter 4 outputs AC power P to the load 2.

運転制御部62、63は、UPS12、13の整流器3に対し通常運転信号を送信する。したがって、UPS12、13は、系統電源10からそれぞれ交流電力Pを入力し、各インバータ4が交流電力Pを出力する。すなわち、2台のUPS12、13で交流電力2Pを出力する。これにより、並列無停電電源システム1では、系統電源10からの入力電力を交流電力2Pに抑えながらも、負荷2への出力電力は交流電力3Pを出力することが可能となる。   The operation control units 62 and 63 transmit normal operation signals to the rectifiers 3 of the UPSs 12 and 13. Accordingly, the UPSs 12 and 13 each receive AC power P from the system power supply 10, and each inverter 4 outputs AC power P. That is, the AC power 2P is output by the two UPSs 12 and 13. Thereby, in the parallel uninterruptible power supply system 1, the output power to the load 2 can output the AC power 3P while suppressing the input power from the system power supply 10 to the AC power 2P.

[蓄電池11aのアシストモードの終了時&蓄電池12aのアシストモードの開始時]
図7では、図6に示した蓄電池11aのアシストモードが終了した状態を示している。時間演算部81は、蓄電池11aから蓄電池11aの容量及び電流量を取り込み、蓄電池11aの残り放電可能時間を求める。停止制御部91は、時間演算部81の求めた残り放電可能時間が予め設定された時間を下回った時点で、残量閾値信号をUPS11に送信する。残量閾値信号を受けた整流器3では系統電源10からの入力制限を解除し、元の入力値に戻す。整流器3において系統電源10からの入力電力が通常運転時の値に復帰すると、蓄電池11aは放電を停止し、通常運転に戻る。
[At the end of the assist mode of the storage battery 11a & at the start of the assist mode of the storage battery 12a]
FIG. 7 shows a state where the assist mode of the storage battery 11a shown in FIG. 6 has ended. The time calculation part 81 takes in the capacity | capacitance and electric current amount of the storage battery 11a from the storage battery 11a, and calculates | requires the remaining dischargeable time of the storage battery 11a. The stop controller 91 transmits a remaining amount threshold signal to the UPS 11 when the remaining dischargeable time obtained by the time calculator 81 falls below a preset time. The rectifier 3 that has received the remaining amount threshold signal releases the input restriction from the system power supply 10 and restores the original input value. When the input power from the system power supply 10 returns to the normal operation value in the rectifier 3, the storage battery 11a stops discharging and returns to the normal operation.

また、図7では、UPS12だけがピークシフト運転を行い、UPS11、13が通常運転を行っている。ここで装置選択部5は個別制御を取っており、UPS12が蓄電池アシストモードを開始する。図7においては、必要台数演算部7がピークシフト運転の実施に必要なUPS11〜13の台数を1台としている。このため、装置選択部5は、必要台数演算部7の演算結果に従い、ピークシフト運転に使用するUPSを、UPS12とする。   In FIG. 7, only the UPS 12 performs peak shift operation, and the UPSs 11 and 13 perform normal operation. Here, the device selection unit 5 takes individual control, and the UPS 12 starts the storage battery assist mode. In FIG. 7, the required number calculation unit 7 sets the number of UPSs 11 to 13 necessary for performing the peak shift operation as one. For this reason, the device selection unit 5 sets the UPS used for the peak shift operation as the UPS 12 according to the calculation result of the necessary number calculation unit 7.

運転制御部62は、装置選択部5が選択したUPS12の整流器3に対し、入力制限信号を送信する。入力制限信号を受けたUPS12では、蓄電池12aが直流電力を放電し、この放電した直流電力をインバータ4に取り込む。インバータ4は交流電力Pを負荷2に出力する。   The operation control unit 62 transmits an input restriction signal to the rectifier 3 of the UPS 12 selected by the device selection unit 5. In the UPS 12 that has received the input restriction signal, the storage battery 12 a discharges DC power, and this discharged DC power is taken into the inverter 4. The inverter 4 outputs AC power P to the load 2.

運転制御部61、63は、UPS11、13の整流器3に対し通常運転信号を送信する。したがって、UPS11、13は、系統電源10からそれぞれ交流電力Pを入力し、各インバータ4が交流電力Pを出力する。すなわち、2台のUPS11、13で交流電力2Pを出力する。これにより、並列無停電電源システム1では、系統電源10からの入力電力を、通常運転時の3Pから2Pに抑えることができ、ピークシフト運転を実現させている。また、負荷2への出力電力は蓄電池12aからの放電電力を利用することで、交流電力3Pを確保している。   The operation control units 61 and 63 transmit normal operation signals to the rectifiers 3 of the UPSs 11 and 13. Accordingly, the UPSs 11 and 13 each receive AC power P from the system power supply 10, and each inverter 4 outputs AC power P. That is, the AC power 2P is output by the two UPSs 11 and 13. Thereby, in the parallel uninterruptible power supply system 1, the input power from the system power supply 10 can be suppressed from 3P during normal operation to 2P, and the peak shift operation is realized. Moreover, the output power to the load 2 secures AC power 3P by using the discharge power from the storage battery 12a.

[蓄電池12aのアシストモードの終了時]
図8では、図7に示した蓄電池12aのアシストモードが終了した状態を示している。時間演算部82は、蓄電池12aから蓄電池12aの容量及び電流量を取り込み、蓄電池12aの残り放電可能時間を求める。
[At the end of the assist mode of the storage battery 12a]
FIG. 8 shows a state where the assist mode of the storage battery 12a shown in FIG. 7 has been completed. The time calculation part 82 takes in the capacity | capacitance and electric current amount of the storage battery 12a from the storage battery 12a, and calculates | requires the remaining dischargeable time of the storage battery 12a.

停止制御部92は、時間演算部82の求めた残り放電可能時間が予め設定された時間を下回った時点で、残量閾値信号をUPS12の整流器3に送信する。残量閾値信号を受けた整流器3では系統電源10からの入力制限を解除し、元の入力値に戻す。整流器3において系統電源10からの入力電力が通常運転時に戻ると、蓄電池12aは放電を停止し、通常運転に戻る。   The stop control unit 92 transmits a remaining amount threshold signal to the rectifier 3 of the UPS 12 when the remaining dischargeable time obtained by the time calculation unit 82 falls below a preset time. The rectifier 3 that has received the remaining amount threshold signal releases the input restriction from the system power supply 10 and restores the original input value. When the input power from the system power supply 10 returns to the normal operation in the rectifier 3, the storage battery 12a stops discharging and returns to the normal operation.

[蓄電池11aの急速充電モードの開始時]
図9では、電力需要が少ない時間帯において、UPS11がピークシフト運転を行う。ここで、装置選択部5は個別制御を取り、蓄電池急速充電モードを開始する。図9において、必要台数演算部7はピークシフト運転の実施に必要なUPS11〜13の台数を1台とする。このため、装置選択部5は、必要台数演算部7の演算結果に従い、ピークシフト運転に使用するUPSを、UPS11の1台とする。運転制御部61は、装置選択部5が選択したUPS11のインバータ4に対し、蓄電池急速充電信号を送信する。
[At the start of the quick charge mode of the storage battery 11a]
In FIG. 9, the UPS 11 performs the peak shift operation in the time zone when the power demand is low. Here, the apparatus selection part 5 takes individual control, and starts storage battery quick charge mode. In FIG. 9, the required number calculation unit 7 sets the number of UPSs 11 to 13 necessary for performing the peak shift operation to one. Therefore, the device selection unit 5 sets the UPS used for peak shift operation as one UPS 11 according to the calculation result of the necessary number calculation unit 7. The operation control unit 61 transmits a storage battery quick charge signal to the inverter 4 of the UPS 11 selected by the device selection unit 5.

蓄電池急速充電信号を受けたUPS11では、整流器3が変換した直流電力を蓄電池11aへ送り、蓄電池11aは直流電力を充電する。すなわち、UPS11は、蓄電池11aへの充電用電力分として、系統電源10から交流電力Pchを入力する。このとき、UPS11は負荷2には電力を供給していない。   In the UPS 11 that has received the storage battery quick charge signal, the DC power converted by the rectifier 3 is sent to the storage battery 11a, and the storage battery 11a charges the DC power. That is, the UPS 11 inputs AC power Pch from the system power supply 10 as power for charging the storage battery 11a. At this time, the UPS 11 is not supplying power to the load 2.

運転制御部62、63は、UPS12、13に対して通常運転信号を送信する。このため、UPS12、13は、通常運転を実施している。したがって、UPS12、13の2台が負荷2に電力を供給する。ここで、UPS12、13は系統電源10からそれぞれ1.5Pの交流電力、併せて3Pの交流電力を入力し、インバータ4が交流電力3Pを出力する。このように、並列無停電電源システム1では、系統電源10からの入力電力を交流電力3P+充電用の電力Pch=4Pに増やして蓄電池11aの急速充電を行う。すなわち、蓄電池11aが急速充電を行うことで、系統電源10からの入力電力を増やし、ピークシフト運転を実現させている。   The operation control units 62 and 63 transmit normal operation signals to the UPSs 12 and 13. For this reason, UPS12, 13 is implementing normal driving | operation. Accordingly, the two UPSs 12 and 13 supply power to the load 2. Here, the UPSs 12 and 13 receive 1.5P AC power and 3P AC power from the system power supply 10 respectively, and the inverter 4 outputs AC power 3P. As described above, in the parallel uninterruptible power supply system 1, the input power from the system power supply 10 is increased to AC power 3P + charging power Pch = 4P to perform rapid charging of the storage battery 11a. That is, the storage battery 11a performs rapid charging, thereby increasing the input power from the system power supply 10 and realizing the peak shift operation.

[蓄電池11aの急速充電モードの終了時&蓄電池12aの急速充電モードの開始時]
図10では、蓄電池11aの急速充電モードが終わり、UPS12がピークシフト運転を行って蓄電池12aの急速充電モードが開始する。ここでも装置選択部5は個別制御を取る。図10において、時間演算部81は、蓄電池11aから蓄電池11aの容量及び電流量を取り込み、蓄電池11aの残り放電可能時間を求めている。
[At the end of the quick charge mode of the storage battery 11a & at the start of the quick charge mode of the storage battery 12a]
In FIG. 10, the quick charge mode of the storage battery 11a ends, the UPS 12 performs a peak shift operation, and the quick charge mode of the storage battery 12a starts. Again, the device selector 5 takes individual control. In FIG. 10, the time calculation part 81 takes in the capacity | capacitance and electric current amount of the storage battery 11a from the storage battery 11a, and is calculating | requiring the remaining dischargeable time of the storage battery 11a.

ここで、蓄電池11aの残り放電可能時間が、予め定められた規定の残り放電可能時間にまで戻ると、蓄電池11aの充電が終了したことになる。このとき、運転制御部61はUPS11のインバータ4への信号を蓄電池急速充電信号から通常運転信号に切り替え、蓄電池11aを通常運転に戻す。   Here, when the remaining dischargeable time of the storage battery 11a returns to a predetermined remaining dischargeable time, charging of the storage battery 11a is completed. At this time, the operation control unit 61 switches the signal to the inverter 4 of the UPS 11 from the storage battery quick charge signal to the normal operation signal, and returns the storage battery 11a to the normal operation.

また、必要台数演算部7はピークシフト運転の実施に必要なUPS11〜13の台数を1台とする。このため、装置選択部5は、必要台数演算部7の演算結果に従い、ピークシフト運転に使用するUPSを、UPS12の1台とする。運転制御部62は、装置選択部5が選択したUPS12のインバータ4に対し、蓄電池急速充電信号を送信する。   Further, the required number calculation unit 7 sets the number of UPSs 11 to 13 necessary for performing the peak shift operation to one. Therefore, the device selection unit 5 sets the UPS used for peak shift operation as one UPS 12 according to the calculation result of the necessary number calculation unit 7. The operation control unit 62 transmits a storage battery quick charge signal to the inverter 4 of the UPS 12 selected by the device selection unit 5.

蓄電池急速充電信号を受けたUPS12では、整流器3が変換した直流電力を蓄電池12aへ送り、蓄電池12aは直流電力を充電する。すなわち、UPS12は、蓄電池12aへの充電用電力分として、系統電源10から交流電力Pchを入力する。このとき、UPS12は負荷2側には電力を供給していない。   In the UPS 12 that has received the storage battery quick charge signal, the DC power converted by the rectifier 3 is sent to the storage battery 12a, and the storage battery 12a charges the DC power. That is, the UPS 12 inputs the AC power Pch from the system power supply 10 as the power for charging the storage battery 12a. At this time, the UPS 12 does not supply power to the load 2 side.

運転制御部61、63は、UPS11、13に対して通常運転信号を送信するため、UPS11、13が通常運転を実施する。したがって、UPS11、13の2台が負荷2に電力を供給する。すなわち、UPS11、13は系統電源10からそれぞれ1.5Pの交流電力、併せて3Pの交流電力を入力する。このように、並列無停電電源システム1では、系統電源10からの入力電力を交流電力3P+充電用の電力Pch=4Pに増やして蓄電池12aの急速充電を行う。すなわち、蓄電池12aが急速充電を行うことで、系統電源10からの入力電力を増やし、ピークシフト運転を実現させる。   Since the operation control units 61 and 63 transmit normal operation signals to the UPSs 11 and 13, the UPSs 11 and 13 perform normal operation. Accordingly, the two UPSs 11 and 13 supply power to the load 2. That is, the UPSs 11 and 13 receive 1.5P AC power and 3P AC power from the system power supply 10 respectively. As described above, in the parallel uninterruptible power supply system 1, the input power from the system power supply 10 is increased to AC power 3P + charging power Pch = 4P to perform rapid charging of the storage battery 12a. That is, when the storage battery 12a performs rapid charging, the input power from the system power supply 10 is increased and the peak shift operation is realized.

なお、蓄電池12aの残り放電可能時間が、予め定められた規定の残り放電可能時間にまで戻ると、蓄電池12aの充電が終了したことになる。このとき、運転制御部61はUPS11のインバータ4への信号を蓄電池急速充電信号から通常運転信号に切り替え、蓄電池11aを通常運転に戻す。   When the remaining dischargeable time of the storage battery 12a returns to a predetermined remaining dischargeable time, charging of the storage battery 12a is completed. At this time, the operation control unit 61 switches the signal to the inverter 4 of the UPS 11 from the storage battery quick charge signal to the normal operation signal, and returns the storage battery 11a to the normal operation.

(効果)
以上のような第1の実施形態では、装置選択部5が蓄電池11a〜13aの総残容量と負荷2の容量との差が最小で、且つ蓄電池11a〜13aの総残容量の方が負荷2の容量よりも大きくなるように、ピークシフト運転に使用するためのUPS11〜13を選択する。そして、運転制御部61〜63が、装置選択部5の選択したUPS11〜13にピークシフト運転を実施させる。
(effect)
In the first embodiment as described above, the device selection unit 5 has the smallest difference between the total remaining capacity of the storage batteries 11a to 13a and the capacity of the load 2, and the total remaining capacity of the storage batteries 11a to 13a is the load 2 The UPSs 11 to 13 for use in the peak shift operation are selected so as to be larger than the capacity. Then, the operation control units 61 to 63 cause the UPSs 11 to 13 selected by the device selection unit 5 to perform the peak shift operation.

このような第1の実施形態においては、並列無停電電源システム1を全体的に見て蓄電池11a〜13aの総残容量を捉えている。つまり、並列無停電電源システム1として合計でどの程度の余剰容量があるのかを把握しており、ピークシフト運転を効率良く実施することが可能である。   In such 1st Embodiment, the total remaining capacity of storage battery 11a-13a is caught as the parallel uninterruptible power supply system 1 is seen as a whole. That is, it is possible to grasp how much excess capacity is in total as the parallel uninterruptible power supply system 1 and to efficiently perform the peak shift operation.

例えば、蓄電池11aの残容量が「1P」を割り込むと、蓄電池11aの余剰容量を使い切ったことになるとする。この場合、従来技術では、UPS11は系統停電発生時に負荷2へ供給する電力量が不足するとして、ピークシフト運転の実施は取りやめることになる。しかし、本実施形態においては、3台の蓄電池11a〜13aの総残容量が「1P」を超えているのであれば、たとえ蓄電池11aの残容量が「1P」を下回っていたとしても、装置選択部5が複数台のUPS11〜13を選択することで、ピークシフト運転を実施することが可能である。   For example, when the remaining capacity of the storage battery 11a falls below “1P”, the surplus capacity of the storage battery 11a is used up. In this case, in the prior art, the UPS 11 cancels the peak shift operation because the amount of power supplied to the load 2 is insufficient when a system power failure occurs. However, in the present embodiment, if the total remaining capacity of the three storage batteries 11a to 13a exceeds "1P", even if the remaining capacity of the storage battery 11a is less than "1P", the device is selected. When the unit 5 selects a plurality of UPSs 11 to 13, peak shift operation can be performed.

このように、本実施形態では、蓄電池11a〜13aの総残容量を利用して、ピークシフト運転の効率を高めることができる。特に、大きな余剰容量を持つ並列無停電電源システム1では蓄電池11a〜13aの総残容量も大きくなる。そのため、ピークシフト運転の効率が格段に向上する。これにより、電力需要ピーク時の電力消費量を、より効率良く抑えることができ、電力料金の高い時間帯での買電量が低減して、経済性がさらに向上する。   Thus, in this embodiment, the efficiency of peak shift operation can be improved using the total remaining capacity of the storage batteries 11a to 13a. In particular, in the parallel uninterruptible power supply system 1 having a large surplus capacity, the total remaining capacity of the storage batteries 11a to 13a also increases. As a result, the efficiency of peak shift operation is significantly improved. Thereby, the power consumption at the time of peak power demand can be more efficiently suppressed, the amount of power purchased in a time zone with a high power charge is reduced, and the economy is further improved.

また、第1の実施形態では、装置選択部5がUPS11〜13を選択するとき、選択したUPS11〜13に接続される蓄電池11a〜13aの総残容量は、常に負荷2の容量を超えている。したがって、ピークシフト運転時に系統停電が発生しても、蓄電池11a〜13aを用いて負荷2の容量をカバーすることができる。つまり、UPS11〜13は、系統停電発生時に、停電が許されないサーバーなどの負荷2に所定の時間だけ電力を供給し続けることが可能である。その結果、UPS11〜13は、系統停電時の電力供給機能を確実に発揮することができる。   In the first embodiment, when the device selection unit 5 selects the UPSs 11 to 13, the total remaining capacity of the storage batteries 11 a to 13 a connected to the selected UPSs 11 to 13 always exceeds the capacity of the load 2. . Therefore, even if a system power failure occurs during peak shift operation, the capacity of the load 2 can be covered using the storage batteries 11a to 13a. That is, the UPSs 11 to 13 can continue to supply power for a predetermined time to the load 2 such as a server that does not allow a power failure when a system power failure occurs. As a result, the UPSs 11 to 13 can reliably exhibit the power supply function at the time of a system power failure.

しかも、第1の実施形態では、時間演算部81〜83が蓄電池11a〜13aからその容量及び電流量を取り込んで蓄電池11a〜13aの残り放電可能時間を求めている。そして、残り放電可能時間が予め設定された設定時間を下回ると、停止制御部91〜93が残量閾値信号をUPS11〜13に送信して蓄電池11a〜13aの放電を停止させている。   In addition, in the first embodiment, the time calculation units 81 to 83 obtain the remaining dischargeable time of the storage batteries 11a to 13a by taking the capacity and current amount from the storage batteries 11a to 13a. When the remaining dischargeable time is less than the preset set time, the stop control units 91 to 93 transmit the remaining amount threshold signal to the UPSs 11 to 13 to stop the discharge of the storage batteries 11a to 13a.

したがって、第1の実施形態においては蓄電池11a〜13aの蓄電量が、負荷2の容量よりも低下することがない。このため、系統停電が発生しても、UPS11〜13は負荷2への電力供給を途絶えさせることがなく、UPS11〜13としての信頼性を維持することが可能である。   Therefore, in the first embodiment, the storage amount of the storage batteries 11 a to 13 a does not decrease below the capacity of the load 2. For this reason, even if a system power failure occurs, the UPSs 11 to 13 do not interrupt the power supply to the load 2, and the reliability as the UPSs 11 to 13 can be maintained.

また、第1の実施形態では、装置選択部5が一括制御を取るとき、運転制御部61〜63が、蓄電池11a〜13aの放電量又は充電量が均等になるようにUPS11〜13にピークシフト信号を送信している。このため、蓄電池11a〜13aは均等に放電量あるいは充電量を負担することになる。   Moreover, in 1st Embodiment, when the apparatus selection part 5 takes collective control, the operation control parts 61-63 peak shift to UPS11-13 so that the discharge amount or charge amount of storage battery 11a-13a may become equal. A signal is being transmitted. For this reason, the storage batteries 11a to 13a bear the discharge amount or the charge amount evenly.

したがって、UPS11〜13は均一にピークシフト運転に寄与することができる。その結果、蓄電池11a〜13aは充放電回数が偏ることがなく、性能の低下を抑えることができる。しかも、負荷容量が低減して余剰容量が増大した場合、装置選択部5が複数のUPS11〜13を一度に選択することで、蓄電池11a〜13aの放電量又は充電量を大きく利用することができる。このため、ピークシフト運転の効果を最大限に引き出すことが可能となる。   Therefore, UPS11-13 can contribute to a peak shift driving | operation uniformly. As a result, the storage batteries 11a to 13a are not biased in the number of charge and discharge, and can suppress a decrease in performance. In addition, when the load capacity is reduced and the surplus capacity is increased, the apparatus selection unit 5 can select the plurality of UPSs 11 to 13 at a time to greatly use the discharge amount or the charge amount of the storage batteries 11a to 13a. . For this reason, it is possible to maximize the effect of the peak shift operation.

さらに、第1の実施形態では、装置選択部5が個別制御を取ることで、複数のUPS11〜13が順番にピークシフト運転を実施することができる。したがって、ある時間帯においてピークシフト運転に寄与するUPS11〜13は1台であり、系統停電が発生しても並列無停電電源システム1の冗長性を確保することができる。また、第1の実施形態では、運転制御部61〜63がピークシフト信号に加えて、通常運転信号をUPS11〜13に送信している。このため、運転制御部61〜63は、UPS11〜13の通常運転とピークシフト運転の両方を制御することができ、スケジュールに沿った運転切替をスムーズに実施することができる。   Furthermore, in the first embodiment, the apparatus selection unit 5 takes individual control, so that a plurality of UPSs 11 to 13 can sequentially perform peak shift operation. Therefore, there is one UPS 11-13 that contributes to the peak shift operation in a certain time zone, and the redundancy of the parallel uninterruptible power supply system 1 can be ensured even if a system power failure occurs. In the first embodiment, the operation control units 61 to 63 transmit normal operation signals to the UPSs 11 to 13 in addition to the peak shift signal. For this reason, the operation control units 61 to 63 can control both the normal operation and the peak shift operation of the UPSs 11 to 13 and can smoothly perform the operation switching according to the schedule.

(2)他の実施形態
上記の実施形態は、本明細書において一例として提示したものであって、発明の範囲を限定することを意図するものではない。すなわち、その他の様々な形態で実施されることが可能であり、発明の範囲を逸脱しない範囲で、種々の省略や置き換え、変更を行うことが可能である。これらの実施形態やその変形例は、発明の範囲や要旨に含まれると同様に、特許請求の範囲に記載された発明とその均等の範囲に含まれるものである。
(2) Other Embodiments The above-described embodiments are presented as examples in this specification, and are not intended to limit the scope of the invention. In other words, the present invention can be implemented in various other forms, and various omissions, replacements, and changes can be made without departing from the scope of the invention. These embodiments and modifications thereof are included in the invention described in the claims and equivalents thereof in the same manner as included in the scope and gist of the invention.

例えば、UPSの台数や蓄電池の容量などは適宜変更可能である。また、ピークシフト運転の時間帯と通常運転の時間帯に分けたスケジュールの設定も適宜選択可能であり、ピークシフト運転の時間帯である電力需要が大きい時間帯及び電力需要が少ない時間帯も、設定は自由である。   For example, the number of UPS and the capacity of the storage battery can be changed as appropriate. In addition, the schedule setting divided into the peak shift operation time zone and the normal operation time zone can be selected as appropriate, and the peak shift operation time zone where the power demand is large and the power demand time is low, Setting is free.

さらに、上記の実施形態では、装置選択部5が複数のUPS11〜13を選択した場合、運転制御部61〜63が、装置選択部5の選択したUPS11〜13に対し、放電量あるいは充電量が等しい大きさとなるようにピークシフト信号を送信していたが、これに限定されるものではない。すなわち、放電量あるいは充電量が予め設定された大きさとなるようにピークシフト信号を送信するようにしてもよい。   Further, in the above embodiment, when the device selection unit 5 selects a plurality of UPSs 11 to 13, the operation control units 61 to 63 have a discharge amount or a charge amount with respect to the UPSs 11 to 13 selected by the device selection unit 5. Although the peak shift signal is transmitted so as to have the same magnitude, the present invention is not limited to this. That is, the peak shift signal may be transmitted so that the discharge amount or the charge amount has a preset size.

このような実施形態では、蓄電池11a〜13aの放電量又は充電量を所望の大きさにすることができ、ピークシフト運転の効果を効率良く引き出すことができる。また、ピークシフト運転を実施するUPS11〜13を最小限に抑えることで、並列無停電電源システム1の冗長性を確保することも可能である。   In such an embodiment, the discharge amount or the charge amount of the storage batteries 11a to 13a can be set to a desired size, and the effect of the peak shift operation can be efficiently extracted. Moreover, it is also possible to ensure the redundancy of the parallel uninterruptible power supply system 1 by minimizing the UPSs 11 to 13 that perform the peak shift operation.

また、UPS11〜13が順番にピークシフト運転を実施する場合、ピークシフト運転を実施するUPS11〜13を交代させる単位は、適宜選択可能であり、1日単位でも1週間単位でもよい。さらに、ピークシフト運転を複数のUPS11〜13により実施する場合、その組合せは自由であり、例えば、1日目にはUPS11、12を使用し、2日目にはUPS12、13を使用し、3日目にはUPS13、11を使用するようにしてもよい。   Moreover, when UPS11-13 implements peak shift operation in order, the unit which replaces UPS11-13 which implements peak shift operation can be selected suitably, and may be a day unit or a week unit. Further, when the peak shift operation is performed by a plurality of UPSs 11 to 13, the combination is arbitrary. For example, UPSs 11 and 12 are used on the first day, UPSs 12 and 13 are used on the second day, 3 UPS 13 and 11 may be used on the day.

1…並列無停電電源システム
2…負荷
3…整流器
4…インバータ
5…装置選択部
61〜63…運転制御部
7…必要台数演算部
81〜83…時間演算部
91〜93…停止制御部
10…系統電源
11〜13…UPS
11a〜13a…蓄電池
DESCRIPTION OF SYMBOLS 1 ... Parallel uninterruptible power supply system 2 ... Load 3 ... Rectifier 4 ... Inverter 5 ... Device selection part 61-63 ... Operation control part 7 ... Required number calculating part 81-83 ... Time calculation part 91-93 ... Stop control part 10 ... System power supply 11-13 ... UPS
11a-13a ... Storage battery

Claims (6)

系統電源から電力の入力を受け所定の負荷へ電力を供給する無停電電源装置を、並列に複数台接続した並列無停電電源システムにおいて、
前記各無停電電源装置に接続される充放電可能な蓄電部と、
予め設定されたスケジュールに従ってピークシフト信号を前記無停電電源装置に送信することにより、前記蓄電部の電力を利用して前記系統電源から前記無停電電源装置への入力電力を増減させるピークシフト運転を、前記無停電電源装置に行わせる運転制御部と、
前記各蓄電部の残容量の和である総残容量と前記負荷の容量との差が最小で、且つ前記蓄電部の総残容量の方が負荷の容量よりも大きくなるように、ピークシフト運転に使用するための前記無停電電源装置を選択する装置選択部と、
を備えたことを特徴とする並列無停電電源システム。
In a parallel uninterruptible power supply system in which multiple uninterruptible power supply units that receive power input from a system power supply and supply power to a predetermined load are connected in parallel.
A chargeable / dischargeable power storage unit connected to each uninterruptible power supply,
By transmitting a peak shift signal to the uninterruptible power supply according to a preset schedule, a peak shift operation for increasing / decreasing input power from the system power supply to the uninterruptible power supply using the power of the power storage unit is performed. An operation control unit for causing the uninterruptible power supply to perform,
Peak shift operation so that the difference between the total remaining capacity, which is the sum of the remaining capacity of each power storage unit, and the capacity of the load is minimum, and the total remaining capacity of the power storage unit is larger than the capacity of the load A device selection unit for selecting the uninterruptible power supply for use in
A parallel uninterruptible power supply system characterized by comprising:
前記蓄電部から当該蓄電部の容量及び電流量を取り込んで前記蓄電部の残り放電可能時間を求める時間演算部と、
前記残り放電可能時間が予め設定された設定時間を下回ると残量閾値信号を前記無停電電源装置に送信して前記蓄電部の放電を停止させる停止制御部と、を備えたことを特徴とする請求項1に記載の並列無停電電源システム。
A time calculation unit that takes in the capacity and current amount of the power storage unit from the power storage unit and obtains the remaining dischargeable time of the power storage unit;
And a stop control unit that transmits a remaining amount threshold signal to the uninterruptible power supply device when the remaining dischargeable time is less than a preset set time, and stops discharging of the power storage unit. The parallel uninterruptible power supply system according to claim 1.
前記装置選択部が複数の前記無停電電源装置を選択した場合、前記運転制御部は、前記装置選択部が選択した複数の前記無停電電源装置に対しピークシフト信号を1台ずつ順番に送信することを特徴とする請求項1又は2に記載の並列無停電電源システム。   When the device selection unit selects a plurality of uninterruptible power supply devices, the operation control unit sequentially transmits a peak shift signal one by one to the plurality of uninterruptible power supply devices selected by the device selection unit. The parallel uninterruptible power supply system according to claim 1 or 2. 前記装置選択部が複数の前記無停電電源装置を選択した場合、前記運転制御部は、前記装置選択部が選択した複数台の前記無停電電源装置に対し予め設定された放電量あるいは充電量を指示するピークシフト信号を、同時に送信することを特徴とする請求項1〜3のいずれか1項に記載の並列無停電電源システム。   When the device selection unit selects a plurality of the uninterruptible power supply devices, the operation control unit determines a discharge amount or a charge amount set in advance for the plurality of uninterruptible power supply devices selected by the device selection unit. The parallel uninterruptible power supply system according to any one of claims 1 to 3, wherein the instructing peak shift signal is transmitted simultaneously. 前記装置選択部が複数の前記無停電電源装置を選択した場合、前記運転制御部は、前記装置選択部が選択したx台の前記無停電電源装置に対しx分の1ずつの放電量あるいは充電量を指示するピークシフト信号を、同時に送信することを特徴とする請求項4記載の並列無停電電源システム。   When the device selection unit selects a plurality of uninterruptible power supply devices, the operation control unit discharges or charges each x times the x uninterruptible power supply devices selected by the device selection unit. 5. The parallel uninterruptible power supply system according to claim 4, wherein a peak shift signal indicating the quantity is simultaneously transmitted. 前記運転制御部は、前記無停電電源装置に通常運転信号を送信して通常運転を実施することを特徴とする請求項1〜5のいずれか1項に記載の並列無停電電源システム。   6. The parallel uninterruptible power supply system according to claim 1, wherein the operation control unit performs normal operation by transmitting a normal operation signal to the uninterruptible power supply. 7.
JP2015171594A 2015-08-31 2015-08-31 Parallel uninterruptible power supply system Active JP6685671B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015171594A JP6685671B2 (en) 2015-08-31 2015-08-31 Parallel uninterruptible power supply system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015171594A JP6685671B2 (en) 2015-08-31 2015-08-31 Parallel uninterruptible power supply system

Publications (2)

Publication Number Publication Date
JP2017050953A true JP2017050953A (en) 2017-03-09
JP6685671B2 JP6685671B2 (en) 2020-04-22

Family

ID=58280441

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015171594A Active JP6685671B2 (en) 2015-08-31 2015-08-31 Parallel uninterruptible power supply system

Country Status (1)

Country Link
JP (1) JP6685671B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107394883A (en) * 2017-09-04 2017-11-24 郑州云海信息技术有限公司 A kind of container-type data center and its method of supplying power to
CN107579592A (en) * 2017-09-21 2018-01-12 郑州云海信息技术有限公司 A kind of data center's electric power system and method for supplying power to
WO2024185005A1 (en) * 2023-03-06 2024-09-12 株式会社Tmeic Uninterruptible power supply device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0223031A (en) * 1988-07-07 1990-01-25 Yuasa Battery Co Ltd Parallel operation control system
JPH04372529A (en) * 1991-06-21 1992-12-25 Toshiba Corp Uninterruptible power supply
JP2009201327A (en) * 2008-02-25 2009-09-03 Chugoku Electric Power Co Inc:The Blackout compensating apparatus
JP2013207844A (en) * 2012-03-27 2013-10-07 Nec Corp Battery management device, battery device, disk array device, and battery management method
JP2013240201A (en) * 2012-05-15 2013-11-28 Toppan Printing Co Ltd Power unit, control method, and program
JP2014222982A (en) * 2013-05-14 2014-11-27 東芝三菱電機産業システム株式会社 Uninterruptible power device
JP2015029405A (en) * 2013-07-30 2015-02-12 イファ テクノロジーズ インフォメーション カンパニー リミテッド Energy storage system of uninterruptible power supply including battery and operational method thereof
JP2015061396A (en) * 2013-09-18 2015-03-30 株式会社東芝 Uninterruptible power-supply system and control method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0223031A (en) * 1988-07-07 1990-01-25 Yuasa Battery Co Ltd Parallel operation control system
JPH04372529A (en) * 1991-06-21 1992-12-25 Toshiba Corp Uninterruptible power supply
JP2009201327A (en) * 2008-02-25 2009-09-03 Chugoku Electric Power Co Inc:The Blackout compensating apparatus
JP2013207844A (en) * 2012-03-27 2013-10-07 Nec Corp Battery management device, battery device, disk array device, and battery management method
JP2013240201A (en) * 2012-05-15 2013-11-28 Toppan Printing Co Ltd Power unit, control method, and program
JP2014222982A (en) * 2013-05-14 2014-11-27 東芝三菱電機産業システム株式会社 Uninterruptible power device
JP2015029405A (en) * 2013-07-30 2015-02-12 イファ テクノロジーズ インフォメーション カンパニー リミテッド Energy storage system of uninterruptible power supply including battery and operational method thereof
JP2015061396A (en) * 2013-09-18 2015-03-30 株式会社東芝 Uninterruptible power-supply system and control method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107394883A (en) * 2017-09-04 2017-11-24 郑州云海信息技术有限公司 A kind of container-type data center and its method of supplying power to
CN107579592A (en) * 2017-09-21 2018-01-12 郑州云海信息技术有限公司 A kind of data center's electric power system and method for supplying power to
WO2024185005A1 (en) * 2023-03-06 2024-09-12 株式会社Tmeic Uninterruptible power supply device

Also Published As

Publication number Publication date
JP6685671B2 (en) 2020-04-22

Similar Documents

Publication Publication Date Title
US10658867B2 (en) Power supply system and method
JP6840525B2 (en) Battery control method, battery control device, and battery pack
KR101691618B1 (en) Switchable uninterruptible power supply system and battery charging method thereof
JP6085544B2 (en) Rapid charging equipment for electric vehicles, energy management method for charging equipment, and charging equipment system
CN106786980B (en) A kind of electronic equipment and charge control method based on electronic equipment
US20160226268A1 (en) Battery system and energy storage system including the same
JP5640387B2 (en) Power supply
CN112585837A (en) Enhanced battery management system for battery packs
US20140197686A1 (en) Battery system
JP2013009557A (en) Storage cell
JP2015195674A (en) Power storage battery assembly control system
JP2013102563A (en) Power storage device and power supply system
WO2012050195A1 (en) Electric power supply system
JP2015159631A (en) Power storage system, controller of power storage system, and control method
JP2021517448A (en) Balancing device, battery management system including it and battery pack
JPWO2013038764A1 (en) Secondary battery system and secondary battery operation method
JPWO2012050180A1 (en) Priority circuit and power supply system
JP6685671B2 (en) Parallel uninterruptible power supply system
JP5994027B2 (en) Power supply system and energy management system used therefor
CN112567586A (en) Enhanced switching balancing network for battery packs
JP2010119186A (en) Charging system for rechargeable lithium cells
JP2012253849A (en) Power storage system
JP6200086B2 (en) Storage battery control device
JP2009296719A (en) Dc backup power system and method of charging the same
JP4933465B2 (en) DC power supply system and charge control method thereof

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20170913

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20170913

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20171211

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20171225

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180314

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20181218

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190108

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190308

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190702

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190902

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200303

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200401

R150 Certificate of patent or registration of utility model

Ref document number: 6685671

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150