JP2016094796A - Demolition method - Google Patents

Demolition method Download PDF

Info

Publication number
JP2016094796A
JP2016094796A JP2014232796A JP2014232796A JP2016094796A JP 2016094796 A JP2016094796 A JP 2016094796A JP 2014232796 A JP2014232796 A JP 2014232796A JP 2014232796 A JP2014232796 A JP 2014232796A JP 2016094796 A JP2016094796 A JP 2016094796A
Authority
JP
Japan
Prior art keywords
hole
pile
concrete
explosive
crushing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2014232796A
Other languages
Japanese (ja)
Other versions
JP6423690B2 (en
Inventor
紗惠子 杉下
Saeko Sugishita
紗惠子 杉下
柳田 克巳
Katsumi Yanagida
克巳 柳田
隆寛 中村
Takahiro Nakamura
隆寛 中村
福島 隆
Takashi Fukushima
隆 福島
昌章 加藤
Masaaki Kato
昌章 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2014232796A priority Critical patent/JP6423690B2/en
Publication of JP2016094796A publication Critical patent/JP2016094796A/en
Application granted granted Critical
Publication of JP6423690B2 publication Critical patent/JP6423690B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a demolition method that enables efficient demolition of an underground concrete structure.SOLUTION: A pile 1 in ground 3 is drilled downward from an upper end, and an approximately vertical hole 5 is formed to a bottom of the pile 1. A detonating fuse 7 is inserted into the hole 5 and arranged in such a manner as to continue to a bottom of the hole almost throughout the length of the hole 5, and water is poured into the hole 5. Subsequently, concrete of the pile 1 is crushed by blasting of the detonating fuse 7; the ground 3 is excavated to the bottom of the pile 1; and debris 15 after the blasting is removed.SELECTED DRAWING: Figure 2

Description

本発明は、地中のコンクリート構造物の解体方法に関する。   The present invention relates to a method for demolishing an underground concrete structure.

従来、地中のコンクリート杭を解体する方法として、ブレーカーやニブラ等の解体重機によりコンクリートを打撃破砕または圧砕して解体する工法や、ウォールソー、ワイヤーソー等によってコンクリートを小ブロックに切断し、必要に応じてさらに二次破砕を行って解体する工法があった。   Conventional methods of dismantling underground concrete piles include a method of breaking and crushing concrete with a breaker, nibra, or other demolition machine, or breaking the concrete into small blocks with a wall saw, wire saw, etc. Depending on the situation, there was a method of dismantling by further secondary crushing.

また近年では、コンクリートに穿孔して多数の孔を形成し、各孔に導爆線を設置して発破を行うMB(マイクロブラスティング)工法も知られている(特許文献1、2参照)。さらに、特許文献3には、コンクリートに縦孔を穿孔した後、孔内に爆薬等を多段に設置して発破を行う工法について記載されている。   In recent years, there has also been known an MB (microblasting) method in which a large number of holes are formed by drilling in concrete, and a blast wire is installed in each hole for blasting (see Patent Documents 1 and 2). Furthermore, Patent Document 3 describes a method of performing blasting by placing explosives or the like in multiple stages in a hole after drilling a vertical hole in concrete.

特開2011−157807号公報JP 2011-157807 A 特開2013−087413号公報JP 2013-087413 A 特開平5−247939号公報JP-A-5-247939

ブレーカーやニブラ等の解体重機により解体を行うと、騒音や振動が大きくその発生時間も長い。また粉塵が多量に発生するので粉塵対策に大量の水を要し、さらに、大口径の杭等の場合には一部材の解体に時間がかかるという問題がある。ウォールソーやワイヤーソー等により解体を行う場合も、同じく解体に時間がかかり、粉塵対策のため大量の水を要する。またコストも高額となり、切断したブロックを吊り上げるための重機が別途必要になる問題もある。二次破砕を行う場合はさらにコスト・工期がかさむ。加えて、これらの方法では、地盤の掘削を途中でストップし、一旦杭を地上に露出させた後解体を行うので、工程を圧迫する要因となっていた。   When dismantling using a breaker or nibler, the noise and vibration are large and the generation time is long. In addition, since a large amount of dust is generated, a large amount of water is required for dust countermeasures. Further, in the case of a large-diameter pile or the like, it takes time to disassemble one member. Similarly, when disassembling with a wall saw or wire saw, it takes time to disassemble, and a large amount of water is required to prevent dust. In addition, the cost is high, and there is a problem that a separate heavy machine for lifting the cut block is required. In the case of secondary crushing, the cost and construction period are further increased. In addition, in these methods, the excavation of the ground is stopped halfway, and the piles are once exposed to the ground and then dismantled.

MB工法では、24mm程度の細径のドリルを使用して穿孔を行い小径の孔を形成するのが一般的であるが、このようなドリルは、現状、1度に穿孔できる穿孔長がそれほど大きくない(例えば、1.8m程度)。そのため、地中深くまで構築されたコンクリート杭を解体する場合には、数回に分けての解体が必要であった。また、細かいピッチで多数の孔を穿孔し、各孔に少量の導爆線を設置して発破を行うため、穿孔に工期を要し、また導爆線の加工と設置、及び吹き出し防止の為の砂込め作業にも手間がかかる。さらに、発破後のコンクリートガラが大きくなることもあり、その場合には二次破砕が必要となる。   In the MB method, it is common to drill using a drill with a small diameter of about 24 mm to form a small diameter hole, but such drills currently have a very long drilling length that can be drilled at once. No (for example, about 1.8m). Therefore, when dismantling a concrete pile constructed deep underground, it was necessary to disassemble it in several times. In addition, since a large number of holes are drilled at a fine pitch, and a small amount of explosive lines are installed in each hole for blasting, drilling requires a work period, and for the processing and installation of explosive lines, and to prevent blowout It takes a lot of work to put sand in. Furthermore, the concrete blast after blasting may become large, in which case secondary crushing is required.

特許文献3の方法では爆薬が孔内で不連続に設置される為、解体対象の杭に対して力が均等にかからず、爆薬近傍は細かく破砕されるがその他の部分は十分に破砕されず大きなブロックとして残る恐れがあり、二次破砕が必要となる点で問題がある。また、孔内に多段に配置した爆薬のそれぞれに雷管を使用するのでコストがかさみ、各爆薬及び爆薬間のタンピング材の設置に手間もかかる。タンピング材を省略して空隙とすると、爆薬発破時の衝撃波がうまく伝播されなくなる。   In the method of Patent Document 3, since the explosive is discontinuously installed in the hole, the force is not evenly applied to the pile to be demolished, and the vicinity of the explosive is finely crushed, but the other parts are sufficiently crushed. There is a possibility that it may remain as a large block, and there is a problem in that secondary crushing is required. Moreover, since the detonator is used for each of the explosives arranged in multiple stages in the hole, the cost is increased, and it takes time to install the tamping material between each explosive and the explosive. If the tamping material is omitted to create a void, the shock wave at the time of explosive blasting will not propagate well.

本発明は、前述した問題点に鑑みてなされたもので、その目的は、地中のコンクリート構造物を効率良く解体できる解体方法を提供することである。   The present invention has been made in view of the above-described problems, and an object of the present invention is to provide a dismantling method that can dismantle an underground concrete structure efficiently.

前述した目的を達成するための本発明は、地中のコンクリート構造物の解体方法であって、前記コンクリート構造物の上端から略鉛直方向の孔を所定深さまで穿孔する工程と、線状の破砕剤を前記孔の略全長に渡って連続するように配置し、孔内に液体を満たす工程と、前記破砕剤により前記コンクリート構造物のコンクリートを破砕する工程と、前記所定深さまで地盤を掘削するとともに、破砕された前記コンクリートを除去する工程と、を具備することを特徴とする解体方法である。   The present invention for achieving the above-described object is a method for dismantling an underground concrete structure, comprising a step of drilling a hole in a substantially vertical direction from the upper end of the concrete structure to a predetermined depth, and a linear crushing Disposing the agent continuously over substantially the entire length of the hole, filling the hole with liquid, crushing the concrete of the concrete structure with the crushing agent, and excavating the ground to the predetermined depth And a step of removing the crushed concrete.

前記孔は、前記コンクリート構造物の底部まで一度に穿孔して形成されることが望ましい。
また、前記液体が水であることが望ましい。
前記コンクリート構造物は、例えば杭である。
The hole is preferably formed by drilling at a time to the bottom of the concrete structure.
The liquid is preferably water.
The concrete structure is, for example, a pile.

本発明では、コンクリート構造物に略鉛直方向の孔を穿孔した後、線状の破砕剤を孔底まで連続配置し、孔内に液体を満たす。そして、破砕剤によりコンクリートを破砕し、地盤の掘削と同時にガラを除去する。これにより、本発明では、ブレーカーやニブラ等を用いた解体方法と比較して、発破が一瞬で終了するため騒音・振動・粉塵の発生を大幅に抑えることができ、ウォールソーやワイヤーソー等による解体方法と比較して工期やコストも削減できる。また、地盤を掘削することなくコンクリートを破砕して十分に細かくでき、その後、バックホーなどの掘削重機を用いて地盤を掘削すると同時にガラを除去できるので、施工効率も高く工程を圧迫することもない。   In the present invention, after a hole in a substantially vertical direction is drilled in a concrete structure, a linear crushing agent is continuously arranged to the bottom of the hole to fill the hole with liquid. Then, the concrete is crushed with a crushing agent, and the glass is removed simultaneously with excavation of the ground. Thereby, in this invention, compared with the dismantling method using a breaker, a nibler, etc., since blasting is completed in an instant, generation of noise, vibration, and dust can be greatly suppressed. Compared to the dismantling method, the construction period and cost can be reduced. In addition, the concrete can be crushed and made fine enough without excavating the ground, and then the ground can be removed simultaneously with excavating heavy equipment such as backhoes, so that the construction efficiency is high and the process is not compressed. .

また本発明では、前記した爆薬の多段配置による方法と異なり、孔の略全長に渡って破砕剤を連続配置することで、コンクリート構造物の鉛直方向に均等にバランスよく破砕剤が配置され、装薬作業も一回で済み雷管等も1箇所でよいので施工効率が高く低コストである。加えて、本発明では孔内に液体を満たすので砂込め作業が不要であり、前記したMB工法と比較しても施工効率が高く、液体は非弾性体であるのでコンクリートを破砕する力が弱まることもない。さらに、孔の底部では孔の上部に比べて液体の圧力が大きく、コンクリートを破砕する力の伝播効率が向上する。従って、土圧による拘束力が大きい地中深くの箇所でもコンクリートを細かく破砕でき、結果、最少の装薬量で最も効率的に、コンクリート構造物のコンクリートを均等に細かく破砕できる。   Further, in the present invention, unlike the method using the multistage arrangement of explosives described above, the crushing agent is arranged in a balanced manner in the vertical direction of the concrete structure by continuously arranging the crushing agent over substantially the entire length of the hole. Since only one chemical work is required and only one detonator is required, the construction efficiency is high and the cost is low. In addition, in the present invention, since the liquid is filled in the hole, the sand filling work is unnecessary, and the construction efficiency is high even compared with the MB method described above, and the liquid is an inelastic body, so the force to crush the concrete is weakened. There is nothing. Furthermore, the pressure of the liquid is larger at the bottom of the hole than at the top of the hole, and the propagation efficiency of the force for crushing the concrete is improved. Accordingly, the concrete can be finely crushed even in a deep underground place where the restraint force due to earth pressure is large. As a result, the concrete of the concrete structure can be evenly and finely crushed most efficiently with the minimum amount of charge.

また本発明では、MB工法と異なり孔の径を大きくし、一度に穿孔できる穿孔長の大きな穿孔機を用いてコンクリート構造物の底部まで一度に穿孔でき、1つの孔に設置できる破砕剤の量を増やすことができる。結果、コンクリート構造物のコンクリート全体を少ない穿孔数で一度に破砕し、二次破砕が不要となる又は軽減できる程度まで細かくできる。   Also, in the present invention, unlike the MB method, the diameter of the hole is increased, and the amount of the crushing agent that can be drilled to the bottom of the concrete structure at once using a drilling machine with a long drilling length that can be drilled at one time. Can be increased. As a result, the entire concrete of the concrete structure can be crushed at a time with a small number of perforations, and can be made fine enough to eliminate or reduce secondary crushing.

また本発明では、孔に注入する液体として水を用いることができる。水を用いる場合、どの現場でも比較的簡単に入手でき、注入も容易である。また本発明は、コンクリート構造物の中でも、地中深くまで構築されることが多い杭の解体を行うのに特に適している。   In the present invention, water can be used as the liquid injected into the holes. When water is used, it is relatively easy to obtain at any site and injection is easy. The present invention is also particularly suitable for dismantling piles that are often built deep into the ground among concrete structures.

本発明によれば、地中のコンクリート構造物を効率良く解体できる解体方法を提供することができる。   ADVANTAGE OF THE INVENTION According to this invention, the dismantling method which can dismantle an underground concrete structure efficiently can be provided.

杭1の穿孔を示す図Diagram showing drilling of pile 1 孔5への導爆線7の配置および注水について示す図The figure which shows about arrangement | positioning and water injection of the explosive wire 7 to the hole 5 杭1のコンクリートの破砕について示す図Figure showing concrete crushing of pile 1 地盤3の掘削とガラ15の除去について示す図The figure shown about the excavation of the ground 3 and the removal of the glass 15 解体方法の別の例を示す図Diagram showing another example of dismantling method 解体方法の別の例を示す図Diagram showing another example of dismantling method

以下、図面に基づいて、本発明の解体方法の実施形態について説明する。   Hereinafter, an embodiment of a disassembly method of the present invention will be described based on the drawings.

本実施形態では、地中のコンクリート構造物として、図1に示す杭1を解体する例について説明する。杭1は地盤3中の既存杭であり、コンクリートの内部に補強筋として鉄筋籠(不図示)を埋設し構築したものである。なお、図1(a)は杭1の鉛直方向の断面を見た図であり、図1(b)は杭頭の平面を見た図である。これは後述する図2でも同様である。   This embodiment demonstrates the example which disassembles the pile 1 shown in FIG. 1 as an underground concrete structure. The pile 1 is an existing pile in the ground 3 and is constructed by embedding a reinforcing bar rod (not shown) as a reinforcing bar inside the concrete. 1A is a view of a vertical section of the pile 1, and FIG. 1B is a view of a plane of the pile head. The same applies to FIG. 2 described later.

(1.杭1の穿孔)
本実施形態では、杭1を解体するに際し、図1(a)に示すように、まず杭1の上端から下へと略鉛直方向に穿孔し、孔5を形成する。孔5は、杭1の底部の所定深さまで杭1の略全長に渡って形成される。
(1. Drilling of pile 1)
In this embodiment, when disassembling the pile 1, as shown in FIG. 1A, first, the hole 1 is drilled in a substantially vertical direction from the upper end of the pile 1 to the bottom. The hole 5 is formed over substantially the entire length of the pile 1 to a predetermined depth at the bottom of the pile 1.

図1(b)に示すように、本実施形態では杭1に3本の孔5を形成している。各孔5は、例えば杭1中の鉄筋籠(不図示)の内側の範囲に形成する。また、孔5の径は例えばφ50mmからφ100mm程度の範囲とし、前記のMB工法の場合よりも大きくする。大きな孔径であれば、一度に穿孔できる穿孔長(例えば、ドリルをコンクリートに挿入する深さの最大値)の大きな穿孔機が存在するので、本実施形態では、このような長距離(例えば、10m程度)の穿孔ができる穿孔機を用いて、杭1の底部までの孔5を一度に穿孔する。   As shown in FIG. 1B, in the present embodiment, three holes 5 are formed in the pile 1. Each hole 5 is formed in the range inside the reinforcing bar rod (not shown) in the pile 1, for example. Further, the diameter of the hole 5 is, for example, in the range of about φ50 mm to φ100 mm, and is larger than that in the MB method. If there is a large hole diameter, there is a drilling machine having a large drilling length (for example, the maximum depth at which the drill is inserted into the concrete) that can be drilled at one time. In this embodiment, such a long distance (for example, 10 m) The hole 5 to the bottom of the pile 1 is drilled at a time using a drilling machine capable of drilling a degree).

(2.孔5への導爆線7の配置および注水)
本発明では、孔5に線状の破砕剤を配置し、これによって杭1のコンクリートの破砕を行う。破砕剤は、爆薬・火薬・非火薬破砕剤等の高エネルギー物質であり、その点火(起爆)によって爆発衝撃波またはガス圧力を発生させ、これにより対象物の破砕を行うものである。破砕剤として爆薬を使用する場合は爆発衝撃波が発生し、火薬や非火薬破砕剤を使用する場合はガス圧力が発生する。
(2. Arrangement and water injection of explosive wire 7 in hole 5)
In this invention, a linear crushing agent is arrange | positioned in the hole 5, and the concrete of the pile 1 is crushed by this. The crushing agent is a high-energy substance such as an explosive, an explosive, or a non-explosive crushing agent, and generates an explosion shock wave or gas pressure by ignition (detonation), thereby crushing the object. When an explosive is used as a crushing agent, an explosion shock wave is generated, and when an explosive or non-explosive crushing agent is used, a gas pressure is generated.

本実施形態では、線状の破砕剤として図2(a)に示す導爆線7を用いる。導爆線7は、爆薬を芯薬とし、これを紙と糸で被覆したものに防水加工して形成され、上下端はテープ等で閉じて止水される。図2(a)に示すように、この導爆線7を孔5に挿入し、孔5の略全長に渡って孔底まで連続するように配置する。本実施形態では、杭1のコンクリートを細かく破砕するために必要な装薬量に応じて、導爆線7を1または複数本束ねて用いる。例えば導爆線7により杭コンクリート1m3当たり200gの装薬が行われるようにしておく。導爆線7の上端は孔5の上端から若干下方に位置し、発破用の雷管(不図示)が取付けられる。雷管には脚線(不図示)が接続される。 In the present embodiment, an explosive wire 7 shown in FIG. 2A is used as a linear crushing agent. The explosive wire 7 is formed by waterproofing an explosive as a core and covering it with paper and thread, and the upper and lower ends are closed with a tape or the like to stop water. As shown in FIG. 2A, the explosive wire 7 is inserted into the hole 5 and arranged so as to continue to the bottom of the hole over substantially the entire length of the hole 5. In the present embodiment, one or a plurality of explosive wires 7 are bundled and used according to the amount of charge necessary for finely crushing the concrete of the pile 1. For example, the explosive wire 7 is used to charge 200 g of charge per 1 m 3 of pile concrete. The upper end of the explosive wire 7 is located slightly below the upper end of the hole 5, and a blasting detonator (not shown) is attached. A leg wire (not shown) is connected to the detonator.

こうして導爆線7を配置するとともに孔5に注水を行い、孔5の上端まで水13(液体)を満たす。   In this way, the explosive wire 7 is disposed and water is poured into the hole 5 to fill the water 13 (liquid) up to the upper end of the hole 5.

(3.杭1のコンクリートの破砕)
その後、導爆線7の脚線を発破器(不図示)に結線し、各孔5の導爆線7を発破する。本実施形態では各孔5の導爆線7の発破をほぼ同時に行う。すると、孔5の略全長に渡って連続配置された導爆線7から衝撃波が発生し、水13を伝播して周囲の杭1に伝わる。
(3. Concrete crushing of pile 1)
Thereafter, the leg of the explosive wire 7 is connected to a blasting device (not shown), and the explosive wire 7 of each hole 5 is blasted. In the present embodiment, the explosion lines 7 of each hole 5 are blasted almost simultaneously. Then, a shock wave is generated from the explosive wire 7 arranged continuously over substantially the entire length of the hole 5, and propagates through the water 13 to the surrounding pile 1.

ここで、図3(a)に示すように杭1には周囲から土圧Pが加わっており、杭1の底部では土圧Pが大きくコンクリートに大きな拘束力が加わって破砕されにくくなっている。しかしながら、本実施形態では水13を孔5内に注入しており、孔5の底部へゆくほど水圧が大きくなる。従って、孔5の底部の水13が、衝撃波の伝播に関し、より剛体に近い振る舞いとなり、効率よく衝撃波のエネルギーが伝播され、杭1のコンクリートを破砕する力となる。これにより、土圧Pによる拘束力の大きい杭1の底部でも、杭1の上部と変わらない程度にコンクリートが破砕され、結果、全体として均等にコンクリートが破砕されることになる。   Here, as shown in FIG. 3 (a), earth pressure P is applied to the pile 1 from the periphery, and at the bottom of the pile 1, the earth pressure P is large, and a large restraining force is applied to the concrete so that it is difficult to be crushed. . However, in this embodiment, the water 13 is injected into the hole 5, and the water pressure increases as it goes to the bottom of the hole 5. Therefore, the water 13 at the bottom of the hole 5 behaves more like a rigid body with respect to the propagation of the shock wave, and the energy of the shock wave is efficiently propagated and becomes a force for crushing the concrete of the pile 1. Thereby, even at the bottom of the pile 1 having a large restraining force due to the earth pressure P, the concrete is crushed to the same extent as the top of the pile 1, and as a result, the concrete is crushed evenly as a whole.

以上のようにして杭1のコンクリートが破砕された状態を示すのが図3(b)である。図に示すように、本実施形態では杭1のコンクリート全体に亀裂が入り、細かく分断、破砕される。破砕されたコンクリートは鉄筋籠(不図示)の鉄筋からも剥離する。   FIG. 3B shows a state in which the concrete of the pile 1 is crushed as described above. As shown in the figure, in this embodiment, the entire concrete of the pile 1 is cracked, and is finely divided and crushed. The crushed concrete also peels off from the reinforcing bars of the reinforcing bar rod (not shown).

(4.地盤3の掘削とガラ15の除去)
以降は、図4(a)に示すように、バックホー17などの掘削重機を用いて地盤3を掘削するとともに破砕後のコンクリートガラ15を除去してゆく手順となる。細かく破砕されたガラ15は、人手などで取り出し、バックホー17で掘削土とともに搬出することができ、二次破砕用の解体重機なども不要である。露出した杭1の鉄筋(不図示)は、必要に応じて曲げたり切断したりする。
(4. Excavation of ground 3 and removal of glass 15)
Thereafter, as shown in FIG. 4A, the ground 3 is excavated by using a heavy excavator such as the backhoe 17 and the crushed concrete glass 15 is removed. The finely crushed glass 15 can be taken out manually and taken out along with excavated soil by the backhoe 17, and a weight breaking machine for secondary crushing is not necessary. The exposed reinforcing bars (not shown) of the pile 1 are bent or cut as necessary.

こうして図4(b)に示すように杭1の底部の所定深さまで地盤3を掘削するとともにガラ15の除去を行うと、解体作業が完了する。   When the ground 3 is excavated to a predetermined depth at the bottom of the pile 1 as shown in FIG. 4 (b) and the glass 15 is removed, the dismantling operation is completed.

以上説明したように、本実施形態では、杭1に略鉛直方向の孔5を穿孔した後、孔5に導爆線7を挿入して孔底まで連続配置し、孔5内に水13を満たす。そして、導爆線7の発破により杭1のコンクリートを破砕し、地盤3の掘削と同時にガラ15を除去する。これにより、本実施形態では、ブレーカーやニブラ等の解体重機を用いた解体方法と比較して、発破が一瞬で終了するため騒音・振動・粉塵の発生を大幅に抑えることができ、ウォールソーやワイヤーソー等による解体方法と比較して工期やコストも削減できる。また、地盤3を掘削することなく地盤3中の杭1のコンクリートを破砕し十分に細かくでき、その後、バックホー17などの掘削重機を用いて地盤3を掘削すると同時に破砕後のガラ15を除去できるので、施工効率も高く工程を圧迫することもない。   As described above, in the present embodiment, after the hole 5 in the substantially vertical direction is drilled in the pile 1, the explosive wire 7 is inserted into the hole 5 and continuously disposed to the bottom of the hole 5. Fulfill. Then, the concrete of the pile 1 is crushed by blasting the detonation wire 7 and the glass 15 is removed simultaneously with the excavation of the ground 3. As a result, in this embodiment, compared to a disassembly method using a breaker, nibbler, or other dismantling machine, the blasting is completed in an instant, so the generation of noise, vibration, and dust can be greatly suppressed. Compared with the dismantling method using a wire saw, the construction period and cost can be reduced. Moreover, the concrete of the pile 1 in the ground 3 can be crushed and sufficiently fine without excavating the ground 3, and then the ground 15 can be removed simultaneously with excavating the ground 3 using a heavy excavator such as the backhoe 17. Therefore, construction efficiency is high and there is no pressure on the process.

また、本実施形態では、前記した爆薬の多段配置による方法と異なり、孔5の略全長に渡って導爆線7を連続配置することで、杭1の鉛直方向に均等にバランスよく爆薬が配置され、導爆線7の固定も容易である。また装薬作業も一回で済み雷管等も1箇所でよいので施工効率が高く低コストである。また本実施形態では、水13を孔5に満たすので砂込め作業が不要であり前記したMB工法と比較しても施工効率が高く、水13はどの現場でも比較的簡単に入手でき注入も容易である。また、水13は非弾性体であるので衝撃波の力が弱まることもない。さらに、孔底では水圧による衝撃波の伝播効率の向上効果が期待でき、土圧による拘束力が大きい地中深くの箇所でもコンクリートを細かく破砕できる。結果、最少の装薬量で最も効率的に、杭1のコンクリートを均等に細かく破砕できる。   Further, in the present embodiment, unlike the method using the multistage arrangement of explosives described above, the explosives are arranged in a balanced manner in the vertical direction of the pile 1 by continuously arranging the explosive wires 7 over substantially the entire length of the hole 5. In addition, it is easy to fix the explosive wire 7. In addition, since the charging operation is performed only once and a detonator or the like is only required in one place, the construction efficiency is high and the cost is low. Moreover, in this embodiment, since the water 13 is filled in the hole 5, sand filling work is unnecessary, and the construction efficiency is higher than the MB method described above, and the water 13 can be obtained relatively easily at any site and can be easily injected. It is. Further, since the water 13 is an inelastic body, the force of the shock wave is not weakened. Furthermore, at the bottom of the hole, the effect of improving the propagation efficiency of shock waves due to water pressure can be expected, and concrete can be finely crushed even in deep underground locations where the restraint force due to earth pressure is large. As a result, the concrete of the pile 1 can be evenly and finely crushed most efficiently with the minimum amount of charge.

また本実施形態では、MB工法と異なり孔5の径を大きくし、一度に穿孔できる穿孔長の大きな穿孔機を用いて杭1の底部まで一度に穿孔でき、1つの孔5に設置できる導爆線7の量を増やすことができる。結果、杭1のコンクリート全体を少ない穿孔数で一度に破砕し、二次破砕が不要となる又は軽減できる程度まで細かくできる。   Further, in this embodiment, unlike the MB method, the diameter of the hole 5 is increased, and a boring machine having a large drilling length that can be drilled at once can be drilled all the way to the bottom of the pile 1 and installed in one hole 5. The amount of line 7 can be increased. As a result, the entire concrete of the pile 1 can be crushed at a time with a small number of perforations, and can be made fine enough to eliminate or reduce secondary crushing.

しかしながら、本発明はこれに限らない。例えば、本実施形態では導爆線7を用いたが、これに限ることはなく、必要に応じてその他の破砕剤を線状に配置して用いることができる。また、本実施形態では杭1の解体を行う例を説明したが、地中のコンクリート構造物であれば解体対象は特に限定されず、有筋または無筋の他のコンクリート構造物でもよい。ただし、杭1は地中深くまで構築されていることが多く、本実施形態の方法はこのような杭1の解体に特に適している。また、孔5には比重調整した水を注水してもよく、水のかわりに各種の液体を孔5に注入することも可能である。   However, the present invention is not limited to this. For example, although the explosive wire 7 is used in the present embodiment, the present invention is not limited to this, and other crushing agents can be arranged in a linear shape and used as necessary. Moreover, although the example which disassembles the pile 1 was demonstrated in this embodiment, if it is an underground concrete structure, a disassembly object will not be specifically limited, The other concrete structure with reinforcement or unreinforced may be sufficient. However, the pile 1 is often constructed deep into the ground, and the method of the present embodiment is particularly suitable for dismantling such a pile 1. Further, water having a specific gravity adjusted may be poured into the holes 5, and various liquids can be injected into the holes 5 instead of water.

また、穿孔機で一度に穿孔できる穿孔長よりも杭が長い場合には、図5(a)に示すように杭1’の途中の所定深さまで孔5を穿孔して前記と同様に導爆線7の発破による杭1のコンクリートの破砕を行った後、図5(b)に示すように当該所定深さまで地盤3の掘削とガラ15の除去を行い、以下この一連の作業を繰り返すことで杭1’全体の解体を行うことも可能である。   Also, if the pile is longer than the drilling length that can be drilled at once with a drilling machine, the hole 5 is drilled to a predetermined depth in the middle of the pile 1 'as shown in FIG. After crushing the concrete of the pile 1 by blasting the wire 7, the ground 3 is excavated to the predetermined depth and the glass 15 is removed as shown in FIG. 5 (b), and this series of operations is repeated thereafter. It is also possible to disassemble the entire pile 1 ′.

また、孔数や平面位置など孔5の配置、あるいは導爆線7による1孔当たりの装薬量なども、解体対象のコンクリート構造物のサイズや形状、構造形式や補強筋の量等に応じて、コンクリートに均等に力が加わって目標とする細かさのガラ15に破砕されるよう適宜定めることができ、特に限定されない。例えば孔5の配置に関しては、図6に示すように、杭1の平面中央部を中心とする内外の同心円(図6の点線参照)の各々に沿って複数の孔5を間隔を空けて形成することもでき、この場合、例えば外側の導爆線7を発破した後、内側の導爆線7の発破を行う。これにより、(外側の導爆線7より)外側のコンクリートを外方に押し出すように破砕した後、その内側のコンクリートを同じく外方に押し出すように破砕できる。   In addition, the arrangement of the holes 5 such as the number of holes and the plane position, or the amount of charge per hole by the explosive wire 7 depends on the size and shape of the concrete structure to be demolished, the structure type, the amount of reinforcing bars, etc. Thus, it can be determined appropriately so that the force is applied evenly to the concrete and crushed into the target fine glass 15, and is not particularly limited. For example, with respect to the arrangement of the holes 5, as shown in FIG. 6, a plurality of holes 5 are formed at intervals along each of inner and outer concentric circles (see the dotted line in FIG. 6) centered on the center of the plane of the pile 1. In this case, for example, after blasting the outer explosive line 7, the inner explosive line 7 is blasted. Thereby, after crushing the outer concrete (from the outer explosive wire 7) so as to be pushed outward, the inner concrete can be broken so as to be pushed outward as well.

以上、添付図を参照しながら、本発明の実施形態を説明したが、本発明の技術的範囲は、前述した実施形態に左右されない。当業者であれば、特許請求の範囲に記載された技術的思想の範疇内において各種の変更例または修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。   As mentioned above, although embodiment of this invention was described referring an accompanying drawing, the technical scope of this invention is not influenced by embodiment mentioned above. It is obvious for those skilled in the art that various modifications or modifications can be conceived within the scope of the technical idea described in the claims, and these are naturally within the technical scope of the present invention. It is understood that it belongs.

1;杭
3;地盤
5;孔
7;導爆線
13;水
15;ガラ
17;バックホー
1; pile 3; ground 5; hole 7; explosive wire 13; water 15;

Claims (4)

地中のコンクリート構造物の解体方法であって、
前記コンクリート構造物の上端から略鉛直方向の孔を所定深さまで穿孔する工程と、
線状の破砕剤を前記孔の略全長に渡って連続するように配置し、孔内に液体を満たす工程と、
前記破砕剤により前記コンクリート構造物のコンクリートを破砕する工程と、
前記所定深さまで地盤を掘削するとともに、破砕された前記コンクリートを除去する工程と、
を具備することを特徴とする解体方法。
A method for dismantling underground concrete structures,
Drilling a substantially vertical hole from the upper end of the concrete structure to a predetermined depth;
Arranging a linear crushing agent so as to be continuous over substantially the entire length of the hole, and filling the liquid in the hole;
Crushing the concrete of the concrete structure with the crushing agent;
Excavating the ground to the predetermined depth and removing the crushed concrete;
A disassembling method comprising:
前記孔は、前記コンクリート構造物の底部まで一度に穿孔して形成されることを特徴とする請求項1記載の解体方法。   The dismantling method according to claim 1, wherein the hole is formed by drilling to the bottom of the concrete structure at a time. 前記液体が水であることを特徴とする請求項1または請求項2記載の解体方法。   The disassembling method according to claim 1 or 2, wherein the liquid is water. 前記コンクリート構造物が杭であることを特徴とする請求項1から請求項3のいずれかに記載の解体方法。   The dismantling method according to any one of claims 1 to 3, wherein the concrete structure is a pile.
JP2014232796A 2014-11-17 2014-11-17 Dismantling method Active JP6423690B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014232796A JP6423690B2 (en) 2014-11-17 2014-11-17 Dismantling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014232796A JP6423690B2 (en) 2014-11-17 2014-11-17 Dismantling method

Publications (2)

Publication Number Publication Date
JP2016094796A true JP2016094796A (en) 2016-05-26
JP6423690B2 JP6423690B2 (en) 2018-11-14

Family

ID=56070726

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014232796A Active JP6423690B2 (en) 2014-11-17 2014-11-17 Dismantling method

Country Status (1)

Country Link
JP (1) JP6423690B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638693A (en) * 2016-12-24 2017-05-10 广东宏大广航工程有限公司 Dismantling construction method of immersed tunnel steel-pipe pile concrete wall by drilling and blasting
CN106759360A (en) * 2016-12-30 2017-05-31 青岛业高建设工程有限公司 A kind of slag removal grouting apparatus and the slag removal grouting method using the device
JP2017125309A (en) * 2016-01-12 2017-07-20 株式会社村上工業 Underground pile crushing method
JP2018048445A (en) * 2016-09-20 2018-03-29 鹿島建設株式会社 Demolition method
JP2019049196A (en) * 2018-12-18 2019-03-28 株式会社村上工業 Underground pile crushing method
JP2020063660A (en) * 2019-12-16 2020-04-23 株式会社村上工業 Underground pile breaking method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4449754A (en) * 1980-11-24 1984-05-22 Vsesojuzny Proektno-Izyskatelsky I Nauchno-Issledovatelsky Institut "Gidropoekt" Imeni S.Ya. Zhuka Device for breaking monolithic structures by pulsewise liquid pressure
JPS6136463A (en) * 1984-07-30 1986-02-21 大成建設株式会社 Static destruction by bentonite
JPH05247939A (en) * 1992-03-04 1993-09-24 Taisei Corp Demolition method of obstruction in deep ground
JP3028127U (en) * 1996-02-16 1996-08-30 エスビー工業株式会社 Explosive container
JP2003120051A (en) * 2001-10-12 2003-04-23 Hitachi Zosen Corp Fracturing method for concrete structure
JP2013087413A (en) * 2011-10-13 2013-05-13 Kajima Corp Demolition method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4449754A (en) * 1980-11-24 1984-05-22 Vsesojuzny Proektno-Izyskatelsky I Nauchno-Issledovatelsky Institut "Gidropoekt" Imeni S.Ya. Zhuka Device for breaking monolithic structures by pulsewise liquid pressure
JPS6136463A (en) * 1984-07-30 1986-02-21 大成建設株式会社 Static destruction by bentonite
JPH05247939A (en) * 1992-03-04 1993-09-24 Taisei Corp Demolition method of obstruction in deep ground
JP3028127U (en) * 1996-02-16 1996-08-30 エスビー工業株式会社 Explosive container
JP2003120051A (en) * 2001-10-12 2003-04-23 Hitachi Zosen Corp Fracturing method for concrete structure
JP2013087413A (en) * 2011-10-13 2013-05-13 Kajima Corp Demolition method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017125309A (en) * 2016-01-12 2017-07-20 株式会社村上工業 Underground pile crushing method
JP2018048445A (en) * 2016-09-20 2018-03-29 鹿島建設株式会社 Demolition method
CN106638693A (en) * 2016-12-24 2017-05-10 广东宏大广航工程有限公司 Dismantling construction method of immersed tunnel steel-pipe pile concrete wall by drilling and blasting
CN106759360A (en) * 2016-12-30 2017-05-31 青岛业高建设工程有限公司 A kind of slag removal grouting apparatus and the slag removal grouting method using the device
CN106759360B (en) * 2016-12-30 2020-01-17 青岛业高建设工程有限公司 Slag-cleaning grouting device and slag-cleaning grouting method adopting same
JP2019049196A (en) * 2018-12-18 2019-03-28 株式会社村上工業 Underground pile crushing method
JP2020063660A (en) * 2019-12-16 2020-04-23 株式会社村上工業 Underground pile breaking method

Also Published As

Publication number Publication date
JP6423690B2 (en) 2018-11-14

Similar Documents

Publication Publication Date Title
JP6423690B2 (en) Dismantling method
JP6634375B2 (en) Explosive tube tube having air gap and rock blasting method using the same
JP6145306B2 (en) Pile head processing method
KR101827341B1 (en) Rock Excavation Method in Tunnel
KR101245609B1 (en) Constructing Method of Steel Pile in Sea Ground
JP5620706B2 (en) Dismantling method
KR20190121551A (en) Method of excavation
CN108999596A (en) A kind of supercritical CO2The method of point type jet impulse gas explosion fracturing coal and rock
KR101256584B1 (en) Tunnel Constructing Method Using Double Excavation method
JP6461022B2 (en) Underground pile crushing method
JP2019148070A (en) Construction method of underground structure
JP2020045611A (en) Pile head treatment method
JP6854626B2 (en) Pile head treatment method
JP6310181B2 (en) Dismantling method
RU2473738C1 (en) Method to erect bearing underground base
JP6194223B2 (en) Pile head processing jig and pile head processing method
JP2000213900A (en) Blasting method
KR20070029152A (en) Discharge crushing method for crushing object to be crushed, method of excavating horizontal tunnel using discharge crushing method, and method of excavating vertical shaft
JP4253801B2 (en) Tunnel construction method
KR101153367B1 (en) Method for blasting core center-cut
JP6844082B2 (en) Underground pile crushing method
JP2018168545A (en) Method for removing concrete from surface of reinforced concrete skeleton
KR101256587B1 (en) Tunnel Constructing Method Applying Space For Reducing Vibration
JP7061853B2 (en) A method of manufacturing materials by collecting excavated materials from excavated parts of rocks as materials.
KR100446586B1 (en) Soil-Nail able to Withdraw Itself by Blasting

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170519

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180227

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180320

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180510

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20181009

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20181019

R150 Certificate of patent or registration of utility model

Ref document number: 6423690

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250