JP2015186276A - Power management system, power management method, and program - Google Patents

Power management system, power management method, and program Download PDF

Info

Publication number
JP2015186276A
JP2015186276A JP2014057993A JP2014057993A JP2015186276A JP 2015186276 A JP2015186276 A JP 2015186276A JP 2014057993 A JP2014057993 A JP 2014057993A JP 2014057993 A JP2014057993 A JP 2014057993A JP 2015186276 A JP2015186276 A JP 2015186276A
Authority
JP
Japan
Prior art keywords
power
amount
unit
storage unit
measured
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2014057993A
Other languages
Japanese (ja)
Inventor
尚 梅岡
Takashi Umeoka
尚 梅岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Chemical Co Ltd
Original Assignee
Sekisui Chemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Chemical Co Ltd filed Critical Sekisui Chemical Co Ltd
Priority to JP2014057993A priority Critical patent/JP2015186276A/en
Publication of JP2015186276A publication Critical patent/JP2015186276A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a power management system capable of measuring electric energy for calculating a compensation according to transferred electric energy in the case of transferring power from a storage battery installed on the power user side to a commercial power system.SOLUTION: A power storage system 52 is installed so as to discharge power to a commercial power system 2. A power storage system watt-hour meter 62 for measuring electric energy for charging in the case of charging the power storage system 52 is installed. A power bill calculation unit 72 calculates, from information including a measurement value of the electric energy for charging measured by the power storage system watt-hour meter 62, electric energy to be sold by a power user in which the power storage system 52 is installed.

Description

本発明は、電力管理システム、電力管理方法及びプログラムに関する。   The present invention relates to a power management system, a power management method, and a program.

近年、太陽光発電などの自然エネルギーを利用した発電装置と蓄電池を備えたエネルギー管理システムが知られるようになっている。また、複数の電力需要家からなるコミュニティにおいて電力管理を行う電力管理システムも知られている(例えば、特許文献1参照)。特許文献1によれば、蓄電システムと太陽光発電設備とを備えることにより、電力需要家の太陽光発電設備から発生する余剰電力を複数の蓄電システムに貯めておき、必要時にその電力を放電して使えることが示されている。
また、一般的に、電気事業者と電力需要家との間の電力需給契約における電力料金は、商用電力系統からの受電点に対応させて設けられた積算電力量計の計測値に基づいて算出されている。
2. Description of the Related Art In recent years, an energy management system including a power generation device using natural energy such as solar power generation and a storage battery has been known. A power management system that performs power management in a community composed of a plurality of power consumers is also known (see, for example, Patent Document 1). According to Patent Document 1, by providing a power storage system and a solar power generation facility, surplus power generated from the solar power generation facility of a power consumer is stored in a plurality of power storage systems, and the power is discharged when necessary. It is shown that it can be used.
In general, the electricity charge in the electricity supply-demand contract between the electric power company and the electricity consumer is calculated based on the measured value of the integrated watt-hour meter provided corresponding to the receiving point from the commercial power system Has been.

特開2014−030334号公報JP, 2014-030334, A

しかしながら、上記の積算電力量計を用いた一般的な電力量の計測方法では、受電した電力は当該電力需要家の負荷で消費され、太陽光発電設備などで発電した電力の一部が電気事業者に供給されることを前提としており、蓄電システムに蓄えた電力を電力需要家が提供する際の電力量の計測方法ではない。また、特許文献1には、複数の電力需要家からなる区域内において、蓄電システムを用いて電力を融通することが示されているが、電力需要家が融通する電力量を測定する方法について記載されていない。そのため、上記のように、複数の電力需要家からなる区域内において、特許文献1のような蓄電システムを用いて電力を融通しようとしても、対価を算出するための電力量を計測することができないという問題がある。   However, in the general method for measuring electric energy using the above integrated watt-hour meter, the received electric power is consumed by the load of the electric power consumer, and a part of the electric power generated by the solar power generation facility is used in the electric power business. This is not a method for measuring the amount of electric power when the electric power consumer provides the electric power stored in the power storage system. Patent Document 1 discloses that power is accommodated by using a power storage system in an area composed of a plurality of power consumers, but describes a method for measuring the amount of power that power consumers can accommodate. It has not been. Therefore, as described above, even in an area composed of a plurality of power consumers, even if an attempt is made to exchange power using a power storage system such as Patent Document 1, it is not possible to measure the amount of power for calculating the price. There is a problem.

上述の課題を鑑み、本発明は、電力需要家側に設けた蓄電池から商用電力系統に電力を融通する場合に、融通した電力量の対価を算出するための電力量を測定できる電力管理システム、電力管理方法及びプログラムを提供することを目的とする。   In view of the above-described problems, the present invention provides a power management system capable of measuring the amount of power for calculating the consideration of the amount of power accommodated when accumulating power from a storage battery provided on the power consumer side to the commercial power system, An object is to provide a power management method and program.

上述の課題を解決するために、本発明の一態様による電力管理システムは、商用電力系統から電力を充電できると共に該商用電力系統に電力を放電できる蓄電部が設けられており、該蓄電部に充放電する電力の電力量を計測する蓄電部電力計測部と、該商用電力系統から受電及び該商用電力系統に送電する潮流方向及び逆潮流方向の電力量を計測する系統電力計測部と、前記蓄電部電力計測部によって計測された蓄電電力の充電又は放電の電力量と、前記系統電力計測部によって計測された潮流方向又は逆潮流方向の電力量の情報から、電力需要家が売買する電力量を算出する電力量算出部とを備えることを特徴とする。   In order to solve the above-described problem, a power management system according to one embodiment of the present invention includes a power storage unit that can charge power from a commercial power system and can discharge power to the commercial power system. A power storage unit power measuring unit that measures the amount of electric power to be charged and discharged, a system power measuring unit that receives power from the commercial power system and transmits power to the commercial power system in a power flow direction and a reverse power flow direction, and The amount of power that electric power consumers buy and sell from the information on the amount of charge or discharge of the stored power measured by the power storage unit power measuring unit and the amount of power in the tidal direction or reverse power direction measured by the grid power measuring unit And an electric power amount calculation unit for calculating.

上記電力管理システムにおいて、前記蓄電部電力計測部は、前記蓄電部に充電される充電電力量のうち少なくとも一部の電力を売電する電力量として計測することを特徴とする。   In the power management system, the power storage unit power measurement unit measures at least a part of the charged power amount charged in the power storage unit as the amount of power sold.

上記電力管理システムにおいて、該商用電力系統から受電する潮流方向の電力量を計測する系統電力計測部を備え、前記電力量算出部は、前記蓄電部電力計測部によって計測された前記充電の電力量と、前記系統電力計測部によって計測された前記潮流方向の電力量とから、電力需要家が売電する電力の電力量を算出することを特徴とする。   In the power management system, the power management system further includes a system power measurement unit that measures a power amount in a power flow direction received from the commercial power system, and the power amount calculation unit includes the power amount of the charge measured by the power storage unit power measurement unit And the amount of power sold by the power consumer is calculated from the amount of power in the tidal direction measured by the grid power measuring unit.

上記電力管理システムにおいて、前記電力量算出部は、前記蓄電部電力計測部によって計測された充電の電力量から前記系統電力計測部により計測された順潮流方向の電力量を減じた電力量、又は、前記系統電力計測部により計測された逆潮流方向の電力量から前記蓄電部電力計測部によって計測された放電の電力量を減じた電力量、又は、前記蓄電部電力計測部によって計測された充電の電力量と前記系統電力計測部により計測された逆潮流方向の電力量とを加えた電力量により、電力需要家が売電する電力の電力量を算出することを特徴とする。   In the power management system, the power amount calculation unit is a power amount obtained by subtracting a power amount in a forward power flow direction measured by the grid power measurement unit from a charge power amount measured by the power storage unit power measurement unit, or The amount of power obtained by subtracting the amount of electric power of discharge measured by the power storage unit power measurement unit from the amount of power in the reverse power flow direction measured by the grid power measurement unit, or the charge measured by the power storage unit power measurement unit The amount of power sold by the power consumer is calculated based on the amount of power that is the sum of the amount of power and the amount of power in the reverse flow direction measured by the grid power measuring unit.

上記電力管理システムにおいて、前記電力量算出部は、前記系統電力計測部により計測された順潮流方向の電力量から前記蓄電部電力計測部によって計測された充電の電力量を減じた電力量、又は、前記蓄電部電力計測部によって計測された放電の電力量から前記系統電力計測部により計測された逆潮流方向の電力量を減じた電力量により、電力需要家が買電する電力の電力量を算出することを特徴とする。   In the power management system, the power amount calculation unit is a power amount obtained by subtracting a power amount of charging measured by the power storage unit power measurement unit from a power amount in a forward power flow direction measured by the grid power measurement unit, or The amount of power purchased by the power consumer is calculated by subtracting the amount of power in the reverse flow direction measured by the grid power measuring unit from the amount of discharge measured by the power storage unit power measuring unit. It is characterized by calculating.

上記電力管理システムにおいて、前記系統電力計測部は、前記商用電力系統からの引き込み線に設けられており、前記系統電力計測部から負荷に向かう第1接続線に、前記第1接続線から前記蓄電部に向かう第2接続線を分岐する分岐部が設けられ、前記蓄電部電力計測部は、前記第2接続線に設けられることを特徴とする。   In the power management system, the grid power measurement unit is provided on a lead-in line from the commercial power grid, and the power storage system is connected to the first connection line from the grid power measurement unit toward the load. A branching portion for branching the second connection line toward the portion is provided, and the power storage unit power measurement unit is provided in the second connection line.

上記電力管理システムにおいて、前記電力量算出部は、前記蓄電部を前記商用電力系統から遮断した状態で、前記蓄電部電力計測部によって計測された充電電力の電力量から、電力需要家が売電する電力の電力量を算出することを特徴とする。   In the power management system, the power amount calculating unit sells power from a power amount of charging power measured by the power storage unit power measurement unit in a state where the power storage unit is disconnected from the commercial power system. The power amount of the power to be calculated is calculated.

上記電力管理システムにおいて、前記電力量算出部は、前記蓄電部を前記商用電力系統から遮断した状態で、前記蓄電部電力計測部によって計測された前記放電の電力量から、電力需要家が買電する電力の電力量を算出することを特徴とする。   In the power management system, the power amount calculation unit is configured such that a power consumer purchases power from the electric energy of the discharge measured by the power storage unit power measurement unit in a state where the power storage unit is disconnected from the commercial power system. The power amount of the power to be calculated is calculated.

本発明の一態様による電力管理方法は、商用電力系統に電力を放電できるように蓄電部を設けておき、蓄電部電力計測部により該蓄電部に充電する場合の充電の電力量を計測し、前記蓄電部電力計測部によって計測された前記充電の電力量を含む情報から、前記蓄電部が設けられている電力需要家が売電する電力量を算出することを特徴とする。   In the power management method according to one aspect of the present invention, a power storage unit is provided so that power can be discharged to a commercial power system, and the power storage unit power measurement unit measures the amount of power charged when charging the power storage unit, From the information including the amount of power of the charge measured by the power storage unit power measurement unit, the amount of power sold by a power consumer provided with the power storage unit is calculated.

本発明の一態様によるプログラムは、商用電力系統に電力を放電できるように蓄電部を設けておき、蓄電部電力計測部により該蓄電部に充電する場合の充電の電力量を計測するステップと、前記蓄電部電力計測部によって計測された前記充電の電力量b2を含む情報から、前記蓄電部が設けられている電力需要家が売電する電力量を算出するステップと含むことを特徴とする。   A program according to an aspect of the present invention is provided with a power storage unit so that electric power can be discharged to a commercial power system, and a step of measuring the amount of electric power for charging when the power storage unit is charged by the power storage unit power measurement unit; And calculating the amount of electric power sold by an electric power consumer provided with the electric storage unit from information including the electric energy b2 of the charging measured by the electric storage unit electric power measurement unit.

本発明の一態様による電力管理システムは、商用電力系統からの電力を充電できるように設けられており、貯えた電力を放電する蓄電部と、前記蓄電部から放電する電力の電力量を計測する前記蓄電部電力計測部と、前記蓄電部電力計測部によって計測された前記電力の電力量を含む情報から、前記蓄電部が設けられている電力需要家が買電する電力の電力量を算出する電力量算出部とを備えることを特徴とする。   A power management system according to an aspect of the present invention is provided so as to be able to charge power from a commercial power system, and measures a power storage unit that discharges stored power and a power amount of power that is discharged from the power storage unit. From the power storage unit power measurement unit and information including the power amount of the power measured by the power storage unit power measurement unit, the amount of power to be purchased by the power consumer provided with the power storage unit is calculated. And a power amount calculation unit.

本発明によれば、電力需要家側に設けた蓄電池から商用電力系統に電力を融通する場合に、融通した電力量に応じた対価を算出するための電力量を計測できる。   ADVANTAGE OF THE INVENTION According to this invention, when accommodating electric power from the storage battery provided in the electric power consumer side to a commercial electric power grid | system, the electric energy for calculating the consideration according to the interchanged electric energy can be measured.

本発明の第1の実施形態における電力管理システムの全体構成例を示すブロック図である。It is a block diagram which shows the example of whole structure of the power management system in the 1st Embodiment of this invention. 本発明の第1の実施形態における想定されるケースと、そのケースに対応する電力購入量及び電力販売量の計算式を示す説明図である。It is explanatory drawing which shows the calculation formula of the electric power purchase amount corresponding to the case in the 1st Embodiment of this invention, and the electric power sales amount corresponding to the case. 本発明の第1の実施形態において想定されるケースに対応する電力の流れを示す説明図である。It is explanatory drawing which shows the flow of the electric power corresponding to the case assumed in the 1st Embodiment of this invention. 本発明の第1の実施形態において想定されるケースに対応する電力の流れを示す説明図である。It is explanatory drawing which shows the flow of the electric power corresponding to the case assumed in the 1st Embodiment of this invention. 本発明の第1の実施形態における電力料金の算出処理を示すフローチャートである。It is a flowchart which shows the calculation process of the electric power charge in the 1st Embodiment of this invention. 本発明の第1の実施形態における課金の対象にする電力量を算出する処理を示すフローチャートである。It is a flowchart which shows the process which calculates the electric energy made into the object of charge in the 1st Embodiment of this invention. 本発明の第2の実施形態における電力管理システムの全体構成例を示すブロック図である。It is a block diagram which shows the example of whole structure of the power management system in the 2nd Embodiment of this invention. 本発明の第2の実施形態における想定されるケースと、そのケースに対応する電力購入量及び電力販売量の計算式を示す説明図である。It is explanatory drawing which shows the calculation formula of the electric power purchase amount corresponding to the case in the 2nd Embodiment of this invention, and the electric power sales amount corresponding to the case. 本発明の第2の実施形態において想定されるケースに対応する電力の流れを示す説明図である。It is explanatory drawing which shows the flow of the electric power corresponding to the case assumed in the 2nd Embodiment of this invention. 本発明の第2の実施形態における電力料金の算出処理を示すフローチャートである。It is a flowchart which shows the calculation process of the electric power charge in the 2nd Embodiment of this invention. 本発明の第2の実施形態における課金の対象にする電力量を算出する処理を示すフローチャートである。It is a flowchart which shows the process which calculates the electric energy made into the object of charge in the 2nd Embodiment of this invention.

以下、本発明の実施の形態について図面を参照しながら説明する。図1は、本発明の第1の実施形態における電力管理システムの全体構成例を示すブロック図である。本実施形態における電力管理システムは、例えば、一定範囲の区域における複数の電力需要家(以下、単に「需要家」という。)に対応する住宅、商業施設、産業施設などの需要家施設における電力を一括して管理するものである。このような電力管理システムは、例えばTEMS(Town Energy Management System)やCEMS(Community Energy Management System)などといわれるものに対応する。なお、このような電力管理システムは、例えば、商用電力系統2に係る電気事業者(上位の電気事業者)から電力の供給を受け、需要家に電力を小売りする電気事業者(小売事業者)によって運用されるものであってもよい。以下の説明において、このような電力管理システムを用いて需要家に電力を小売りする電気事業者のことを、単に小売事業者といい、小売事業者に電力を供給する電気事業者のことを上位の電気事業者という。また、需要家が小売事業者等から電力を購入する場合を「買電」といい、需要家が小売事業者等に電力を売る場合を「売電」という。また、上位の電気事業者側と小売事業者側のことを区別することなく総じて示す場合、需要家施設の「外部」ということがある。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. FIG. 1 is a block diagram showing an example of the overall configuration of the power management system according to the first embodiment of the present invention. The power management system in the present embodiment, for example, generates power in a customer facility such as a house, a commercial facility, or an industrial facility corresponding to a plurality of power consumers (hereinafter simply referred to as “customer”) in a certain range of area. It is managed collectively. Such a power management system corresponds to a so-called TEMS (Town Energy Management System), CEMS (Community Energy Management System), or the like. Note that such a power management system is, for example, an electric power company (retail business) that receives power supplied from an electric power company (high-order electric power company) related to the commercial power system 2 and retails the power to consumers. It may be operated by. In the following description, an electric power company that retails electric power to consumers using such a power management system is simply referred to as a retailer, and an electric power company that supplies electric power to the retailer. Is called an electric utility. A case where a customer purchases power from a retailer or the like is called “power purchase”, and a case where a customer sells power to a retailer or the like is called “power sale”. Moreover, when it shows collectively, without distinguishing a high-order electric power supplier side and a retailer side, it may be called "the exterior" of a consumer facility.

本実施形態の電力管理システム100は、図1において電力管理区域1として示す一定範囲の区域(以下、単に「区域」ということがある。)における需要家施設10ごとの電気設備を対象として電力管理を行う。需要家施設10は、例えば、住宅、商業施設、あるいは産業施設などに該当する。
商用電力系統2からの電力を需要家施設10毎に分配するように系統電力線3が構成されており、これらの需要家施設10には、それぞれ、商用電力系統2からの電力が系統電力線3を介して供給される。
The power management system 100 according to the present embodiment targets power management for each electric facility 10 in a certain area (hereinafter, simply referred to as “area”) shown as the power management area 1 in FIG. I do. The customer facility 10 corresponds to, for example, a house, a commercial facility, or an industrial facility.
The grid power line 3 is configured to distribute the power from the commercial power grid 2 to each customer facility 10, and the power from the commercial power grid 2 is supplied to the grid power line 3 in each consumer facility 10. Supplied through.

1つの需要家施設10は、発電設備51、蓄電システム52、負荷53、電力経路分岐部54、蓄電システム制御部55、自動開閉器56、系統電力電力量計61、蓄電システム電力量計62とを備える。   One customer facility 10 includes a power generation facility 51, a power storage system 52, a load 53, a power path branching unit 54, a power storage system control unit 55, an automatic switch 56, a system power watt-hour meter 61, and a power storage system watt-hour meter 62. Is provided.

発電設備51は、需要家施設10側で発電する設備である。発電設備51としては、太陽光発電、燃料電池、ガスエンジン発電機などが想定される。一つの需要家施設10に複数の発電設備があっても良く、又は、複数の種類の発電設備があっても良い。発電設備51には、発電設備51の電力を、商用電力系統の電圧、周波数、相数と、それぞれ同じ電圧、周波数、相数の交流に変換する回路が含まれる。なお、区域内の少なくとも1以上の需要家施設10に発電設備51が設置されているものとする。   The power generation facility 51 is a facility that generates power on the customer facility 10 side. As the power generation facility 51, a solar power generation, a fuel cell, a gas engine generator, or the like is assumed. One customer facility 10 may have a plurality of power generation facilities, or a plurality of types of power generation facilities. The power generation facility 51 includes a circuit that converts the power of the power generation facility 51 into alternating current having the same voltage, frequency, and number of phases as the voltage, frequency, and number of phases of the commercial power system. It is assumed that the power generation equipment 51 is installed in at least one customer facility 10 in the area.

蓄電システム52は、余剰電力を蓄積し、また、蓄積した電力を放電して出力する。なお、余剰電力とは、発電設備51で発電された電力から、その需要家の負荷53が消費した電力を差し引いた余剰分の電力のことである。この蓄電システム52に使用する蓄電池としては、例えばリチウムイオン電池などの各種電池を採用することができる。蓄電システム52には、交流の充電電力を直流に変換し、また、放電による直流の電力(放電電力)を商用電力系統と同じ電圧、周波数、相数の交流に変換する回路が含まれる。蓄電システム52は、蓄電システム制御部55の制御の下、予め定められた一定の電力量で充電するCP(Constant Power)充電モードや、予め定められた一定の電力量で放電するCP(Constant Power)放電モード、需要家の負荷53が消費する電力量の変動に追従する電力量で放電する負荷追従モード、余剰電力の電力量の変動に追従する電力量で充電する余剰電力追従モードなどが設定できる。なお、区域内の少なくとも1以上の需要家施設10に蓄電システム52が設置されているものとする。   The power storage system 52 stores surplus power, and discharges and outputs the stored power. The surplus power is the surplus power obtained by subtracting the power consumed by the load 53 of the customer from the power generated by the power generation facility 51. As a storage battery used for this electrical storage system 52, various batteries, such as a lithium ion battery, are employable, for example. The power storage system 52 includes a circuit that converts alternating-current charging power into direct current, and converts direct-current power (discharge power) due to discharge into alternating current having the same voltage, frequency, and number of phases as the commercial power system. The power storage system 52 is controlled by a power storage system control unit 55 under a CP (Constant Power) charging mode in which charging is performed with a predetermined constant power amount or a CP (Constant Power) discharging with a predetermined constant power amount. ) A discharge mode, a load following mode for discharging with the amount of power following the variation in the amount of power consumed by the customer's load 53, a surplus power following mode for charging with the amount of power following the variation in the amount of surplus power, etc. are set. it can. It is assumed that the power storage system 52 is installed in at least one customer facility 10 in the area.

負荷53は、需要家施設10において、電力を消費する機器や設備などを一括して示したものである。負荷53としては、照明器具、冷蔵庫、テレビ、冷暖房器具等、各種の電化製品が含まれる。   The load 53 collectively indicates devices and facilities that consume power in the customer facility 10. Examples of the load 53 include various electric appliances such as a lighting fixture, a refrigerator, a television, and an air conditioning appliance.

電力経路分岐部54は、例えば、分電盤60に組み込まれており、需要家施設10内の電路(以下、単に「電力経路」という。)を分岐する。電力経路分岐部54は、需要家施設10において、商用電力系統2を負荷53に供給するように電力経路を形成することができる。また、電力経路分岐部54は、需要家施設10において、発電設備51により発生された電力を負荷53に供給するように電力経路を形成することができる。また、電力経路分岐部54は、需要家施設10において、商用電力系統2と発電設備51の一方または両方から供給される電力を蓄電システム52に充電するように電力経路を形成することができる。また、電力経路分岐部54は、需要家施設10において、蓄電システム52から放電により出力させた電力を、負荷53に供給するように電力経路を形成することができる。   The power path branching unit 54 is incorporated in, for example, the distribution board 60 and branches an electric circuit in the customer facility 10 (hereinafter simply referred to as “power path”). The power path branching unit 54 can form a power path so as to supply the commercial power system 2 to the load 53 in the customer facility 10. Further, the power path branching unit 54 can form a power path so that the power generated by the power generation equipment 51 is supplied to the load 53 in the customer facility 10. Further, the power path branching unit 54 can form a power path in the customer facility 10 so as to charge the power storage system 52 with power supplied from one or both of the commercial power system 2 and the power generation equipment 51. In addition, the power path branching unit 54 can form a power path in the customer facility 10 so that the power output from the power storage system 52 by discharging is supplied to the load 53.

更に、電力経路分岐部54は、蓄電システム52により発生された電力を、系統電力線3を経由して、他の需要家施設10(以下、需要家施設ごとの説明をする場合、需要家施設10に代えて「需要家施設11」という。)に向けて供給するように電力経路を形成することができる。需要家施設11では、この電力を、需要家施設11における負荷53に供給したり、需要家施設11における蓄電システム52に蓄電したりすることができる。   Furthermore, the power path branching unit 54 transmits the power generated by the power storage system 52 via the system power line 3 to other customer facilities 10 (hereinafter, when describing each customer facility, the customer facility 10 The power path can be formed so as to be supplied toward the “customer facility 11”. In the customer facility 11, this electric power can be supplied to the load 53 in the customer facility 11 or stored in the power storage system 52 in the customer facility 11.

蓄電システム制御部55は、蓄電システム52の制御を行う。また、蓄電システム制御部55は、融通区域内電力管理部71とネットワーク70を介して通信可能な状態に接続されている。蓄電システム制御部55は、融通区域内電力管理部71から受信した蓄電システムの充放電の計画に従って、充電・放電の開始や停止を指示したり、充電・放電電力の電力量を指示したりするなどの指令を蓄電システム52に伝達し、蓄電システム52を動作させる。   The power storage system control unit 55 controls the power storage system 52. In addition, the power storage system control unit 55 is connected in a communicable state with the in-compartment power management unit 71 via the network 70. The power storage system control unit 55 instructs the start / stop of charging / discharging or instructs the amount of charge / discharge power according to the charging / discharging plan of the power storage system received from the power management unit 71 in the interchange area. Are transmitted to the power storage system 52 to operate the power storage system 52.

なお、蓄電システム制御部55は、例えば、HEMS(ホームエネルギーマネジメントシステム)のゲートウェイに組み込むようにしても良い。   The power storage system control unit 55 may be incorporated in a gateway of a HEMS (Home Energy Management System), for example.

自動開閉器56は、例えば、分電盤60に組み込まれており、商用電力系統2からの電力の供給を、商用電力系統2の状態などに応じて遮断する。自動開閉器56を遮断状態にして、系統電力線3と分電盤60から分岐する電力系路とを切り離すことで、商用電力系統2を停電させるような事故が生じた場合に、その事故の事故点に電力を供給することなく安全性を担保できる。例えば、商用電力系統2の停電の検出は、発電設備51や蓄電システム52などに設けられた単独運転検出機能や系統保護機能、低電圧検出リレーなどで検知することができる。これらの停電検出の方法によって停電が検出された後に発せられる信号に連動させて、自動開閉器56を遮断させることができる。このように商用電力系統2の停電時には、商用電力系統2から遮断された状態になるが、需要家単体で電力の自給自足を可能にする。   The automatic switch 56 is incorporated in the distribution board 60, for example, and cuts off the supply of power from the commercial power system 2 according to the state of the commercial power system 2, and the like. When an accident that causes a power failure of the commercial power system 2 by disconnecting the system power line 3 and the power system branching from the distribution board 60 by turning off the automatic switch 56, the accident of the accident Safety can be ensured without supplying power to the point. For example, the detection of a power failure in the commercial power system 2 can be detected by an isolated operation detection function, a system protection function, a low voltage detection relay, or the like provided in the power generation facility 51, the power storage system 52, or the like. The automatic switch 56 can be shut off in conjunction with a signal issued after a power failure is detected by these power failure detection methods. Thus, at the time of a power failure of the commercial power system 2, the commercial power system 2 is cut off, but the consumer alone can make the power self-sufficient.

系統電力電力量計61は、系統電力線3から入出力される電力を計測する電力量計である。系統電力電力量計61は、系統電力線3の屋内への引込口に設置されている。系統電力電力量計61は、系統電力線3側から受電する電力(順潮流)と共に、系統電力線3側に送電する電力(逆潮流)を計測できる。系統電力電力量計61の計測値は、ネットワーク70を介して、通信により電力料金算出部72に転送できる。系統電力電力量計61の計測値を電力料金算出部72に転送する際には、電力量の計測値と共に、どの需要家の電力量かを識別するために、メータIDが送られる。   The system power watt-hour meter 61 is a watt-hour meter that measures the power input / output from the system power line 3. The grid power meter 61 is installed at the entrance to the grid power line 3 indoors. The system power watt-hour meter 61 can measure the power (forward power flow) received from the system power line 3 side and the power (reverse power flow) transmitted to the system power line 3 side. The measured value of the grid power watt-hour meter 61 can be transferred to the power rate calculation unit 72 by communication via the network 70. When the measured value of the grid power watt-hour meter 61 is transferred to the power rate calculator 72, a meter ID is sent together with the measured value of the power amount to identify which consumer's power amount.

系統電力電力量計61は、ある時間間隔で、電力量を記録する構成とされている。一般的には、30分間隔に、電力量が記録され、30分前に記録された電力量との差分が当該30分間の積算電力量になる。0時〜24時まで30分間隔での順潮流、逆潮流の電力量が記録される。   The grid power meter 61 is configured to record the power amount at a certain time interval. In general, the amount of power is recorded at 30-minute intervals, and the difference from the amount of power recorded 30 minutes ago is the accumulated power amount for the 30 minutes. The amount of electric power in the forward and reverse flow at intervals of 30 minutes from 0:00 to 24:00 is recorded.

なお、系統電力電力量計61は、系統電力線3側から受電する電力(順潮流)の電力計と、系統電力線3側に送電する電力(逆潮流)の電力計とを、別々に設けるようにしても良い。また、系統電力電力量計61の計測値は、PLC(電力線通信)で電力料金算出部72に転送しても良い。なお、この通信に用いる方式に制限はなく、一般的な通信方式を利用することができる。   The grid power meter 61 is provided with a wattmeter for power (forward power flow) received from the grid power line 3 side and a wattmeter for power (reverse power flow) transmitted to the grid power line 3 side separately. May be. Further, the measured value of the grid power watt-hour meter 61 may be transferred to the power rate calculation unit 72 by PLC (power line communication). In addition, there is no restriction | limiting in the system used for this communication, A general communication system can be utilized.

蓄電システム電力量計62は、蓄電システム52に充電される電力及び蓄電システム52から放電される電力を積算する電力量計である。蓄電システム電力量計62は、蓄電システム52に充放電される電力を個別に計測できるように、電力経路分岐部54と蓄電システム52との間に設置される。蓄電システム電力量計62の計測値は、ネットワーク70を介して、通信により電力料金算出部72に転送できる。蓄電システム電力量計62の計測値を電力料金算出部72に転送する際には、電力量の計測値と共に、どの需要家の電力量かを識別するために、メータIDが送られる。   The power storage system watt-hour meter 62 is a watt-hour meter that integrates the power charged in the power storage system 52 and the power discharged from the power storage system 52. The power storage system watt-hour meter 62 is installed between the power path branching unit 54 and the power storage system 52 so that the power charged and discharged to the power storage system 52 can be individually measured. The measured value of the power storage system watt-hour meter 62 can be transferred to the power rate calculation unit 72 via the network 70 by communication. When the measured value of the power storage system watt-hour meter 62 is transferred to the power rate calculation unit 72, a meter ID is sent together with the measured value of the power amount to identify which consumer's power amount.

なお、蓄電システム電力量計62は、蓄電システム52に充電する電力の電力計と、蓄電システム52から放電される電力の電力計とを、別々に設けるようにしても良い。また、蓄電システム電力量計62の計測値は、PLC(電力線通信)で電力料金算出部72に転送しても良い。なお、この通信に用いる方式に制限はなく、一般的な通信方式を利用することができる。   The power storage system watt-hour meter 62 may be provided with a power meter for charging the power storage system 52 and a power meter for discharging power from the power storage system 52 separately. Further, the measurement value of the power storage system watt-hour meter 62 may be transferred to the power charge calculation unit 72 by PLC (power line communication). In addition, there is no restriction | limiting in the system used for this communication, A general communication system can be utilized.

複数の需要家施設10からなる電力管理区域1において、その電力管理区域1に属する需要家施設10全体における電気設備を対象として、融通区域内電力管理部71、電力料金算出部72が備えられる。   In the power management area 1 composed of a plurality of customer facilities 10, an in-compartment-area power management unit 71 and a power charge calculation unit 72 are provided for the electrical facilities in the entire customer facility 10 belonging to the power management area 1.

融通区域内電力管理部71は、ネットワーク70を介して、各需要家施設10の蓄電システム制御部55と接続される。ネットワーク70としては、既存のインターネット網を利用することなどが考えられる。融通区域内電力管理部71は、少なくともその電力管理区域1における、充電又は放電する需要家施設10の蓄電システム52を決定し、充放電の計画又は、充電・放電の開始や停止を蓄電システム制御部55に指令する機能を有する。蓄電システム制御部55への指令内容は、この他、充電・放電電力や充放電モードなども考えられる。   The accommodation area power management unit 71 is connected to the power storage system control unit 55 of each customer facility 10 via the network 70. As the network 70, it is possible to use an existing Internet network. The power management unit 71 in the accommodation area determines the power storage system 52 of the customer facility 10 to be charged or discharged at least in the power management area 1, and controls the charge / discharge plan or the start / stop of the charge / discharge. A function of instructing the unit 55; In addition to this, the content of the command to the power storage system control unit 55 may be a charge / discharge power, a charge / discharge mode, or the like.

電力料金算出部72は、各需要家施設10の系統電力電力量計61及び蓄電システム電力量計62の計測値を取得できる。電力料金算出部72は、系統電力電力量計61で計測された電力量の計測値と、蓄電システム電力量計62で計測された電力量の計測値とから、需要家施設10における電力購入量及び電力販売量を決定する。そして、電力料金算出部72は、求められた電力購入量及び電力販売量に、予め決められた単価を乗算することで課金額を決定する。なお、電力料金算出部72は、HEMSゲートウェイに組み込まれていても良いし、電力管理システム100内の何れかの装置にこの機能を有するように構成することなども考えられる。   The power rate calculation unit 72 can acquire the measured values of the grid power watt hour meter 61 and the power storage system watt hour meter 62 of each customer facility 10. The power rate calculation unit 72 uses the measured power amount measured by the grid power watt-hour meter 61 and the measured power amount measured by the power storage system watt-hour meter 62 to purchase power at the customer facility 10. And determine the amount of electricity sales. Then, the power rate calculation unit 72 determines the billing amount by multiplying the determined power purchase amount and power sales amount by a predetermined unit price. The power rate calculation unit 72 may be incorporated in the HEMS gateway, or may be configured to have this function in any device in the power management system 100.

なお、本実施形態の構成は、一定範囲の区域における複数の需要家の各需要家施設10内の既設の発電設備51や蓄電システム52をそのまま利用して、当該複数の需要家に対応する住宅、商業施設、産業施設などの需要家施設における電力を一括して管理する電力管理システム100に移行できる。   In addition, the structure of this embodiment uses the existing electric power generation equipment 51 and the electrical storage system 52 in each customer facility 10 of the some customer in the area of a fixed range as it is, and the house corresponding to the said some customer Further, it is possible to shift to a power management system 100 that collectively manages power in a customer facility such as a commercial facility or an industrial facility.

次に、本実施形態における電力料金の算出について説明する。上述のように、本実施形態では、複数の需要家施設10からなる電力管理区域1において、電力が融通される。本実施形態における電力料金算出部72では、このような電力管理区域1に属する需要家施設10に対して、公平性の高い電力料金算出を行っている。   Next, calculation of the power charge in this embodiment will be described. As described above, in the present embodiment, power is interchanged in the power management area 1 including a plurality of customer facilities 10. The power rate calculation unit 72 in the present embodiment performs a highly fair power rate calculation for the customer facility 10 belonging to such a power management area 1.

図1に示したような電力管理システム100では、各需要家施設10の蓄電システム52に充電される電力は、当該需要家施設10の発電設備51で発電された電力であるとは限られない。また、蓄電システム52から放電される電力は、当該需要家施設10の負荷53で使われるとは限られない。例えば、図1に示すように構成した電力管理システム100では、需要家施設10の発電設備51によって発電された電力に余剰電力が生じた場合、その余剰電力は、系統電力線3を経由して、別の需要家施設10に送られ、別の需要家施設10の負荷53で使用され、若しくは、別の需要家施設10の蓄電システム52に充電される可能性がある。また、需要家施設11の発電設備51によって発電された電力に余剰電力が生じた場合、その余剰電力は、系統電力線3を経由して、当該需要家施設10に送られ、当該需要家施設10の負荷53で使用され、若しくは、当該需要家施設10の蓄電システム52に充電される可能性がある。このことを考慮すると、系統電力電力量計61の電力量だけで電力料金を算出する方法では、余剰電力がどこにどの程度供給されたかの情報さえ正確に掌握することができず、系統電力電力量計61の電力量だけで電力料金を算出したとても、算出された電気料金の信頼度が低くなることから、公平性の高い電力料金を得ることができない。   In the power management system 100 as shown in FIG. 1, the power charged in the power storage system 52 of each customer facility 10 is not necessarily the power generated by the power generation facility 51 of the customer facility 10. . Further, the electric power discharged from the power storage system 52 is not necessarily used by the load 53 of the customer facility 10. For example, in the power management system 100 configured as shown in FIG. 1, when surplus power is generated in the power generated by the power generation equipment 51 of the customer facility 10, the surplus power passes through the system power line 3, There is a possibility that it is sent to another customer facility 10 and used in a load 53 of another customer facility 10 or charged in the power storage system 52 of another customer facility 10. Further, when surplus power is generated in the power generated by the power generation facility 51 of the customer facility 11, the surplus power is sent to the customer facility 10 via the system power line 3, and the customer facility 10 There is a possibility that the power storage system 52 of the customer facility 10 is charged. In consideration of this, in the method of calculating the power rate only by the power amount of the grid power watt-hour meter 61, it is impossible to accurately grasp even where and how much surplus power is supplied, and the grid power watt-hour meter Since the electricity charge is calculated only with the amount of power 61, the reliability of the calculated electricity charge is low, and thus a highly fair electricity charge cannot be obtained.

そこで、本実施形態では、蓄電システム52に蓄電された時点で、需要家から小売事業者等の電気事業者等に売電したと考えて、売電した電力料金を算出している。
ここで、比較のため本実施形態と異なる一般的な場合を例示する。一般的な場合には、需要家施設10の需要家は、当該需要家施設10の発電設備51や蓄電システム52を物理的に所有しており、蓄電システム52の物理的な所有者と、蓄電システム52に蓄電されている電力の利用権の所有者とを区別して考えることはない。
これに対して、本実施形態では、公平性の高い電力料金を算出できるように、蓄電システム52の物理的な所有者と、蓄電システム52に蓄電されている電力の利用権の所有者とを区別して考えている。そして、蓄電システム52に蓄電される電力については、蓄電システム52の物理的な所有者とは無関係に、蓄電システム52に電力が蓄電された時点で、電力売買があったと考える。ここで、蓄電システム52の物理的な所有者と蓄電システム52に蓄電されている電力の利用権の所有者が異なる場合を例示する。例えば、蓄電システム52の物理的な所有者が需要家であり、蓄電システム52に蓄電されている電力の利用権の所有者は、他の需要家や電気事業者(小売事業者)である場合が挙げられる。また、蓄電システム52の物理的な所有者と蓄電システム52に蓄電されている電力の利用権の所有者が同一となる場合を例示する。例えば、蓄電システム52の物理的な所有者と、蓄電システム52に蓄電されている電力の利用権の所有者の双方が、同一の電気事業者(小売事業者)である場合が挙げられる。
Therefore, in the present embodiment, when the power is stored in the power storage system 52, it is assumed that the power is sold from the consumer to an electric power company such as a retail business, and the electric power price for the sold power is calculated.
Here, a general case different from the present embodiment is illustrated for comparison. In a general case, the consumer of the customer facility 10 physically owns the power generation equipment 51 and the power storage system 52 of the customer facility 10, and the physical owner of the power storage system 52 The owner of the right to use the power stored in the system 52 is not considered separately.
On the other hand, in the present embodiment, the physical owner of the power storage system 52 and the owner of the right to use the power stored in the power storage system 52 are calculated so that a highly fair power charge can be calculated. I think in distinction. Then, regarding the power stored in the power storage system 52, it is considered that there was power trading when the power was stored in the power storage system 52 regardless of the physical owner of the power storage system 52. Here, a case where the physical owner of the power storage system 52 and the owner of the right to use the power stored in the power storage system 52 are different is illustrated. For example, the physical owner of the power storage system 52 is a consumer, and the owner of the right to use the power stored in the power storage system 52 is another consumer or an electric power company (retailer). Is mentioned. Further, a case where the physical owner of the power storage system 52 and the owner of the right to use the power stored in the power storage system 52 are the same is illustrated. For example, the physical owner of the power storage system 52 and the owner of the right to use the power stored in the power storage system 52 may be the same electric power company (retail business).

すなわち、本実施形態では、需要家は、当該需要家施設10の蓄電システム52に電力を充電する場合も、系統電力線3を介して、当該需要家施設10から別場所に電力を送電した場合も、同様に、これらの電力は、売電されたものとする。そして、蓄電システム52に充電された電力は、蓄電システム52の物理的な所有者を問わず、例えば、電気事業者に売電されたものとする。また、需要家は、当該需要家施設10の蓄電システム52から放電された電力を使う場合も、系統電力線3を介して、別場所からの電力を受電する場合も、同様に、その電力は買電されたものとする。   In other words, in the present embodiment, the customer may charge power to the power storage system 52 of the customer facility 10 or may transmit power from the customer facility 10 to another place via the system power line 3. Similarly, it is assumed that these electric powers are sold. The power charged in the power storage system 52 is assumed to have been sold to, for example, an electric power company regardless of the physical owner of the power storage system 52. Similarly, when a consumer uses power discharged from the power storage system 52 of the customer facility 10 or receives power from another location via the system power line 3, the power is purchased. It is assumed that it was electrified.

以上のような考え方に基づき、本実施形態では、系統電力電力量計61の他に、蓄電システム電力量計62が需要家施設10に設置され、公平性の高い電力売買量を算出できるようにしている。以下、図2から図4を参照して、想定されるケース毎に、電力購入量及び電力販売量の算出について説明する。   Based on the above concept, in this embodiment, in addition to the grid power meter 61, a power storage system energy meter 62 is installed in the customer facility 10 so that a highly fair power trading amount can be calculated. ing. Hereinafter, with reference to FIG. 2 to FIG. 4, calculation of the power purchase amount and the power sales amount will be described for each assumed case.

図2は、想定されるケースと、そのケースに対応する電力購入量及び電力販売量の計算式とを示す説明図である。ここで、k1は、系統電力電力量計61で計測される順潮流(系統電力線3側から受電する電力)の電力量である。k2は、系統電力電力量計61で計測される逆潮流(系統電力線3側に送電する電力)の電力量である。b1は、蓄電システム電力量計62で計測される放電電力量である。b2は、蓄電システム電力量計62で計測される充電電力量である。Pは、需要家と、小売事業者等の電気事業者との間で売電又は買電する電力量である。図3と図4は、図2に示す想定されるケースに対応する電力の流れを示す説明図である。   FIG. 2 is an explanatory diagram illustrating an assumed case and formulas for calculating a power purchase amount and a power sales amount corresponding to the case. Here, k1 is the electric energy of the forward flow (electric power received from the system power line 3 side) measured by the system power energy meter 61. k2 is the electric energy of the reverse power flow (electric power transmitted to the system power line 3 side) measured by the system power energy meter 61. b <b> 1 is the amount of discharged power measured by the power storage system watt hour meter 62. b <b> 2 is the amount of charging power measured by the power storage system watt-hour meter 62. P is the amount of electric power sold or purchased between a consumer and an electric power company such as a retailer. 3 and 4 are explanatory diagrams showing the flow of power corresponding to the assumed case shown in FIG.

図2に示すように、系統電力線3を介して別場所から入力された電力と発電設備51の余剰電力とで蓄電システム52を充電する場合には、売電となり、売電の電力量Pは、「P=b2−k1」として求められる(ケース(1))。なお、このとき、負荷53は、当該需要家施設10の発電設備51により賄われる。   As shown in FIG. 2, when the power storage system 52 is charged with power input from another place via the system power line 3 and surplus power of the power generation equipment 51, power is sold, and the power amount P of power sales is , “P = b2−k1” (case (1)). At this time, the load 53 is covered by the power generation equipment 51 of the customer facility 10.

図3(A)は、ケース(1)における電力の流れを説明するものである。このケース(1)では、蓄電システム52に電力を充電しているので、売電である。蓄電システム52への電力量は、蓄電システム電力量計62により電力量b2として計測される。蓄電システム52へ充電される電力量が売電される電力量であるが、そのうちの一部は、系統電力線3を介して別場所から送られてきた電力量である。別場所からの電力量は、系統電力電力量計61で電力量k1として計測される。したがって、売電される電力量Pは、
P=b2−k1
として求められる。
FIG. 3A illustrates the flow of power in case (1). In this case (1), since the power storage system 52 is charged with power, it is sold. The amount of power to the power storage system 52 is measured by the power storage system watt-hour meter 62 as the power amount b2. The amount of power charged in the power storage system 52 is the amount of power sold, and part of the amount is the amount of power sent from another location via the system power line 3. The amount of power from another location is measured by the system power watt-hour meter 61 as the amount of power k1. Therefore, the amount of power P sold is
P = b2-k1
As required.

次に、図2に示すように、発電設備51の余剰電力と、蓄電システム52の放電電力を系統電力線3を介して別場所で使う場合には、売電となり、売電の電力量Pは、「P=k2−b1」として求められる(ケース(2))。   Next, as shown in FIG. 2, when the surplus power of the power generation facility 51 and the discharge power of the power storage system 52 are used at different locations via the system power line 3, the power is sold, and the power amount P of the power sale is , “P = k2−b1” (case (2)).

図3(B)は、ケース(2)おける電力の流れを説明するものである。このケース(2)では、系統電力線3を介して、外部に電力を送電しているので、売電である。系統電力線3を介して別場所に送る電力量は、系統電力電力量計61の電力量k2として計測される。この電力量k2には、蓄電システム52から放電された電力量が含まれている。蓄電システム52から放電された電力量は、蓄電システム電力量計62で計測される電力量b1であり、この電力量は、既に、売買済みである。したがって、売電される電力量Pは、
P=k2−b1
として求められる。
FIG. 3B illustrates the flow of power in the case (2). In this case (2), since electric power is transmitted to the outside via the system power line 3, the power is sold. The amount of power sent to another place via the system power line 3 is measured as the amount of power k2 of the system power watt-hour meter 61. The electric energy k2 includes the electric energy discharged from the power storage system 52. The amount of power discharged from the power storage system 52 is the power amount b1 measured by the power storage system watt hour meter 62, and this power amount has already been bought and sold. Therefore, the amount of power P sold is
P = k2-b1
As required.

次に、図2に示すように、別場所から系統電力線3を介して入力された電力で蓄電システム52を充電し、負荷53は、発電設備51からの電力と別場所からの電力とで賄う場合には、買電となり、買電の電力量Pは、「P=k1−b2」として求められる(ケース(3))。   Next, as shown in FIG. 2, the power storage system 52 is charged with electric power input from another place through the system power line 3, and the load 53 is covered with electric power from the power generation facility 51 and electric power from another place. In this case, power purchase is made, and the amount of power P for power purchase is obtained as “P = k1−b2” (case (3)).

図3(C)は、ケース(3)における電力の流れを説明するものである。このケース(3)では、系統電力線3を介して、外部からの電力を受電しているので、買電である。図3(C)に示すように、系統電力線3を介して別場所から送られてくる電力量は、蓄電システム52に蓄電されると共に、負荷53に送られる。蓄電システム52に電力は蓄電されるが、別場所からの電力を蓄電システム52に蓄電しても、電力の所有者は同じであるから、売買にはならない。別場所から送られてくる電力量から蓄電システム52に蓄電される電力量を減じた電力量が、当該需要家施設10の購入した電力量である。別場所から送られてくる電力量は、系統電力電力量計61の電力量k1として計測される。蓄電システム52に蓄電される電力量は、蓄電システム電力量計62の電力量b2として計測される。したがって、買電される電力量Pは、
P=k1−b2
として求められる。
FIG. 3C illustrates the flow of power in case (3). In this case (3), since power from the outside is received via the system power line 3, it is a power purchase. As shown in FIG. 3C, the amount of power sent from another place via the system power line 3 is stored in the power storage system 52 and sent to the load 53. Electric power is stored in the power storage system 52, but even if power from another place is stored in the power storage system 52, the owner of the power is the same, so it is not sold. The amount of power obtained by subtracting the amount of power stored in the power storage system 52 from the amount of power sent from another location is the amount of power purchased by the customer facility 10. The amount of power sent from another location is measured as the amount of power k1 of the grid power watt-hour meter 61. The amount of power stored in the power storage system 52 is measured as the power amount b2 of the power storage system watt-hour meter 62. Therefore, the amount of power P to be purchased is
P = k1-b2
As required.

次に、図2に示すように、蓄電システム52から放電される電力を系統電力線3を介して別場所で使い、負荷53は発電設備51からの電力と蓄電システム52からの電力で賄われる場合には、買電となり、買電の電力量Pは、「P=b1−k2」として求められる(ケース(4))。   Next, as shown in FIG. 2, when the electric power discharged from the power storage system 52 is used at another location via the system power line 3, the load 53 is covered by the power from the power generation facility 51 and the power from the power storage system 52. Therefore, the power purchase amount P is obtained as “P = b1−k2” (case (4)).

図4(A)は、ケース(4)における電力の流れを説明するものである。このケース(4)では、蓄電システム52から電力を放電しているので、買電である。すなわち、蓄電システム52に蓄電されている電力は、既に、売買済みであるから、蓄電システム52から放電された電力を使用することは、買電にあたる。蓄電システム52から放電された電力量のうち、当該需要家施設10の負荷53で消費された電力量は、蓄電システム52から放電された電力量から、別場所に送った電力量を減じた電力量である。蓄電システム52から放電された電力量は、蓄電システム電力量計62の電力量b1として計測される。別場所に送った電力量は、系統電力電力量計61の電力量k2として計測される。したがって、買電される電力量Pは、
P=b1−k2
として求められる。
FIG. 4A illustrates the flow of power in case (4). In this case (4), power is purchased because the power is discharged from the power storage system 52. That is, since the power stored in the power storage system 52 has already been bought and sold, using the power discharged from the power storage system 52 is equivalent to purchasing power. Of the amount of power discharged from the power storage system 52, the amount of power consumed by the load 53 of the customer facility 10 is the power obtained by subtracting the amount of power sent to another location from the amount of power discharged from the power storage system 52. Amount. The amount of power discharged from the power storage system 52 is measured as the power amount b1 of the power storage system watt-hour meter 62. The amount of power sent to another location is measured as the amount of power k2 of the grid power watt-hour meter 61. Therefore, the amount of power P to be purchased is
P = b1-k2
As required.

次に、図2に示すように、負荷53を、発電設備51からの発電電力と、系統電力線3を介して別場所から送られてきた電力で賄う場合には、買電となり、買電の電力量Pは、「P=k1」として求められる(ケース(5))。   Next, as shown in FIG. 2, when the load 53 is covered by the generated power from the power generation facility 51 and the power sent from another place via the system power line 3, the power purchase is made. The electric energy P is obtained as “P = k1” (case (5)).

図4(B)は、ケース(5)での電力の流れを説明するものである。このようなケース(5)では、負荷53に送られる電力量は、発電設備51からの電力量と、別場所からの電力量との和になる。発電設備51から負荷53への電力は、料金の算出に無関係である。別場所からの電力量は、系統電力電力量計61の電力量k1として計測される。したがって、買電される電力量Pは、
P=k1
として求められる。
FIG. 4B illustrates the flow of power in case (5). In such a case (5), the amount of power sent to the load 53 is the sum of the amount of power from the power generation facility 51 and the amount of power from another location. The power from the power generation facility 51 to the load 53 is irrelevant to the calculation of the charge. The amount of power from another location is measured as the amount of power k1 of the grid power watt-hour meter 61. Therefore, the amount of power P to be purchased is
P = k1
As required.

次に、図2に示すように、発電設備51で発電された余剰電力を、蓄電システム52で充電し、且つ、系統電力線3を介して別場所でも使う場合には、売電となり、売電の電力量Pは、「P=k2+b2」として求められる(ケース(6))。   Next, as shown in FIG. 2, when the surplus power generated by the power generation facility 51 is charged by the power storage system 52 and used in another place via the system power line 3, the power is sold. Is obtained as “P = k2 + b2” (case (6)).

図4(C)は、ケース(6)における電力の流れを説明するものである。このようなケース(6)では、蓄電システム52に充電をし、且つ、外部の電力を供給しているので、売電となる。   FIG. 4C illustrates the flow of power in case (6). In such a case (6), since the power storage system 52 is charged and external power is supplied, the power is sold.

このようなケース(6)では、発電設備51からの電力量は、蓄電システム52の充電電力と、系統電力線3を介して別場所へ送る電力量との和になる。蓄電システム52への充電電力と、別場所に送る電力は、共に売電である。蓄電システム52の充電電力は、蓄電システム電力量計62の電力量b1として計測される。別場所へ送る電力量は、系統電力電力量計61の電力量k2として計測される。したがって、売電のための電力量Pは、
P=k2+b2
として求められる。
In such a case (6), the amount of power from the power generation facility 51 is the sum of the charged power of the power storage system 52 and the amount of power sent to another location via the system power line 3. The charging power for the power storage system 52 and the power sent to another place are both sold. The charging power of the power storage system 52 is measured as the power amount b1 of the power storage system watt-hour meter 62. The amount of power sent to another location is measured as the amount of power k2 of the grid power watt-hour meter 61. Therefore, the power amount P for selling power is
P = k2 + b2
As required.

次に、図5と図6を参照して、電力料金算出部72での電力料金の算出処理について説明する。図5は、電力料金算出部72による電力料金の算出処理を示すフローチャートである。   Next, with reference to FIG. 5 and FIG. 6, the power rate calculation process in the power rate calculation unit 72 will be described. FIG. 5 is a flowchart showing the calculation process of the power charge by the power charge calculation unit 72.

図5に示すように、電力料金算出部72は、ネットワーク70を介して、需要家施設10の系統電力電力量計61の計測値を取得し(ステップS1)、蓄電システム電力量計62の計測値を取得する(ステップS2)。そして、電力料金算出部72は、図2に示した算出式に基づいて、課金の対象にする電力量を算出し(ステップS3)、この課金の対象にする電力量に所定値を乗算して、電力料金を算出する(ステップS4)。   As shown in FIG. 5, the power rate calculation unit 72 acquires the measured value of the grid power watt hour meter 61 of the customer facility 10 via the network 70 (step S1), and measures the power storage system watt hour meter 62. A value is acquired (step S2). Then, the power charge calculation unit 72 calculates the amount of power to be charged based on the calculation formula shown in FIG. 2 (step S3), and multiplies the amount of power to be charged by a predetermined value. Then, a power charge is calculated (step S4).

図6は、ステップS3における課金の対象にする電力量を算出する処理を示すフローチャートである。   FIG. 6 is a flowchart showing processing for calculating the amount of power to be charged in step S3.

図6に示すように、電力料金算出部72は、蓄電システム電力量計62の計測値b1とb2とがともに「0」であるか否かを判定する(ステップS101)。蓄電システム電力量計62の計測値bが「0」でないと判定された場合(ステップS101:No)、電力料金算出部72は、蓄電システム電力量計62の計測値b1とb2とに基づいて、蓄電システム電力量計62で計測された電力量が放電電力量であるか、充電電力量であるかを判定する(ステップS102)。充電電力量であると判定された場合(ステップS102:Yes)、電力料金算出部72は、系統電力電力量計61で計測された計測値k1とk2とに基づいて、系統電力電力量計61で計測された電力量が順潮流の電力量であるか、逆潮流の電力量であるかを判定する(ステップS103)。ステップS103で、系統電力電力量計61で計測された電力量が順潮流の電力量であると判定された場合(ステップS103:Yes)には、電力料金算出部72は、蓄電システム電力量計62で計測された充電電力量(b2)と、系統電力電力量計61で計測された順潮流電力量(k1)とを比較する(ステップS104)。ステップS104の判定の結果、充電電力量(b2)が順潮流電力量(k1)より大きいと判定された場合(ステップS104:Yes)、電力料金算出部72は、図2におけるケース(1)であるとして、売電の電力量Pを、「P=b2−k1」として算出する(ステップS105)。   As illustrated in FIG. 6, the power rate calculation unit 72 determines whether or not the measured values b1 and b2 of the power storage system watt hour meter 62 are both “0” (step S101). When it is determined that the measurement value b of the power storage system watt hour meter 62 is not “0” (step S101: No), the power charge calculation unit 72 is based on the measurement values b1 and b2 of the power storage system watt hour meter 62. Then, it is determined whether the amount of power measured by the power storage system watt-hour meter 62 is the amount of discharged power or the amount of charged power (step S102). When it is determined that the amount of charging power is present (step S102: Yes), the power charge calculation unit 72 is based on the measured values k1 and k2 measured by the system power watt-hour meter 61. It is determined whether the amount of power measured in step 1 is a forward power flow amount or a reverse power flow amount (step S103). When it is determined in step S103 that the power amount measured by the grid power watt hour meter 61 is a forward tidal power amount (step S103: Yes), the power rate calculation unit 72 includes the power storage system watt hour meter. The charging power amount (b2) measured at 62 is compared with the forward power flow amount (k1) measured by the grid power watt-hour meter 61 (step S104). As a result of the determination in step S104, when it is determined that the charging power amount (b2) is greater than the forward power flow amount (k1) (step S104: Yes), the power rate calculation unit 72 is the case (1) in FIG. Assuming that there is power, P is calculated as “P = b2−k1” (step S105).

一方、ステップS101で、蓄電システム電力量計62の計測値bが「0」であると判定された場合(ステップS101:Yes)、電力料金算出部72は、図2におけるケース(5)であるとして、買電の電力量Pを、「P=k1」として算出する(ステップS106)。なお、このケース(5)において、「K1=0」であってもよいものとする。   On the other hand, when it is determined in step S101 that the measurement value b of the power storage system watt hour meter 62 is “0” (step S101: Yes), the power rate calculation unit 72 is case (5) in FIG. Then, the power amount P for power purchase is calculated as “P = k1” (step S106). In this case (5), “K1 = 0” may be used.

また、ステップS102で、蓄電システム電力量計62で計測された電力量が放電電力であると判定された場合(ステップS102:No)、電力料金算出部72は、蓄電システム電力量計62で計測された放電電力量(b1)と、系統電力電力量計61で計測された逆潮流電力量(k2)とを比較する(ステップS107)。ステップS107の判定の結果、放電電力量(b1)が逆潮流電力量(k2)より大きいと判定された場合(ステップS107:Yes)、電力料金算出部72は、図2におけるケース(4)であるとして、買電の電力量Pを、「P=b1−k2」として算出する(ステップS108)。   When it is determined in step S102 that the amount of power measured by the power storage system watt hour meter 62 is discharge power (step S102: No), the power rate calculation unit 72 measures the power amount of power measured by the power storage system watt hour meter 62. The discharge electric energy (b1) thus measured is compared with the reverse flow electric energy (k2) measured by the system electric energy meter 61 (step S107). As a result of the determination in step S107, when it is determined that the discharge power amount (b1) is larger than the reverse power flow amount (k2) (step S107: Yes), the power rate calculation unit 72 is the case (4) in FIG. Assuming that there is power, P is calculated as “P = b1−k2” (step S108).

ステップS107で、放電電力量(b1)が逆潮流電力量(k2)より小さいと判定された場合(ステップS107:No)、電力料金算出部72は、図2におけるケース(2)であるとして、売電の電力量Pを、「P=k2−b1」として算出する(ステップS109)。   When it is determined in step S107 that the discharge power amount (b1) is smaller than the reverse power flow amount (k2) (step S107: No), the power rate calculation unit 72 is assumed to be case (2) in FIG. The amount of power P for power sale is calculated as “P = k2−b1” (step S109).

また、ステップS103で、系統電力電力量計61で計測された電力量が逆潮流の電力であると判定された場合(ステップS103:No)、電力料金算出部72は、図2におけるケース(6)であるとして、売電の電力量Pを、「P=k2+b1」として算出する(ステップS107)。   When it is determined in step S103 that the amount of power measured by the grid power watt-hour meter 61 is reverse power flow (step S103: No), the power rate calculation unit 72 uses the case (6 in FIG. 2). ) Is calculated as “P = k2 + b1” (step S107).

以上に示したように、本実施形態の電力管理システム100は、電力需要家側に設けた蓄電システムから商用電力系統102に電力を融通する場合に、融通した電力量の対価を算出するための電力量を測定することができる。   As described above, the power management system 100 according to the present embodiment calculates the consideration for the amount of power accommodated when accumulating power from the power storage system provided on the power consumer side to the commercial power system 102. The amount of power can be measured.

<第2の実施形態>
次に、本発明の第2の実施形態について説明する。図7は、本発明の第2の実施形態における電力管理システムの全体構成例を示す構成図である。本実施形態の電力管理システム100Aは、図7において電力管理区域101として示す一定範囲の区域における需要家施設110ごとの電気設備を対象として電力管理を行う。
商用電力系統2からの電力を需要家施設110毎に分配するように系統電力線103が構成されており、これらの需要家施設110には、それぞれ、商用電力系統102からの電力が系統電力線3を介して供給される。
<Second Embodiment>
Next, a second embodiment of the present invention will be described. FIG. 7 is a configuration diagram showing an example of the overall configuration of the power management system according to the second embodiment of the present invention. The power management system 100A according to the present embodiment performs power management for the electrical equipment for each customer facility 110 in a certain range of areas shown as the power management area 101 in FIG.
The grid power line 103 is configured to distribute the power from the commercial power grid 2 to each customer facility 110, and the power from the commercial power grid 102 is supplied to the grid power line 3 in each of the consumer facilities 110. Supplied through.

なお、発電設備151、蓄電システム152、負荷153、電力経路分岐部154、蓄電システム制御部155、自動開閉器156、分電盤160、系統電力電力量計161、蓄電システム電力量計162、ネットワーク170、融通区域内電力管理部171、電力料金算出部172は、第1の実施形態における、発電設備51、蓄電システム52、負荷53、電力経路分岐部54、蓄電システム制御部55、自動開閉器56、分電盤60、系統電力電力量計61、蓄電システム電力量計62、ネットワーク70、融通区域内電力管理部71、電力料金算出部72と対応しており、その説明は、省略する。   In addition, the power generation equipment 151, the power storage system 152, the load 153, the power path branching unit 154, the power storage system control unit 155, the automatic switch 156, the distribution board 160, the system power watt-hour meter 161, the power storage system watt-hour meter 162, the network 170, the in-compartment power management unit 171 and the power rate calculation unit 172 are the power generation equipment 51, the power storage system 52, the load 53, the power path branching unit 54, the power storage system control unit 55, and the automatic switch in the first embodiment. 56, distribution board 60, grid power watt-hour meter 61, power storage system watt-hour meter 62, network 70, interchangeable area power management unit 71, and power rate calculation unit 72, and description thereof will be omitted.

本実施形態の電力管理システム100Aは、第1の実施形態の電力管理システム100と異なり、開閉動作記憶部181を備える。開閉動作記憶部181には、需要家施設110内の各部と系統電力線103との間の接続状態が自動開閉器156により遮断された状態にあるか否かを示す自動開閉器156の開閉情報が記憶される。この開閉動作記憶部181の開閉情報が、ネットワーク170を介して、通信により電力料金算出部172に転送される。   Unlike the power management system 100 of the first embodiment, the power management system 100A of the present embodiment includes an opening / closing operation storage unit 181. In the switching operation storage unit 181, switching information of the automatic switch 156 indicating whether or not the connection state between each unit in the customer facility 110 and the system power line 103 is blocked by the automatic switch 156. Remembered. The opening / closing information in the opening / closing operation storage unit 181 is transferred to the power rate calculation unit 172 through communication via the network 170.

前述の第1の実施形態では、電力料金算出部72は、系統電力電力量計61で計測された電力量の計測値(k1とk2)と、蓄電システム電力量計62で計測された電力量の計測値(b1とb2)とから、需要家施設10における電力購入量及び電力販売量を決定している。   In the first embodiment described above, the power rate calculation unit 72 uses the measured values (k1 and k2) of the power measured by the grid power watt-hour meter 61 and the power measured by the power storage system watt-hour meter 62. From the measured values (b1 and b2), the power purchase amount and the power sales amount in the customer facility 10 are determined.

これに対して、この第2の実施形態では、電力料金算出部172は、系統電力電力量計161で計測された電力量の計測値(k1とk2)と、蓄電システム電力量計162で計測された電力量の計測値(b1とb2)から、需要家施設110における電力購入量及び電力販売量を決定すると共に、開閉動作記憶部181からの自動開閉器156の開閉情報を使って、需要家施設110における電力購入量及び電力販売量を決定している。   On the other hand, in the second embodiment, the power rate calculation unit 172 measures the measured values of energy (k1 and k2) measured by the grid power energy meter 161 and the power storage system energy meter 162. From the measured values (b1 and b2) of the electric energy, the power purchase amount and the electric power sales amount at the customer facility 110 are determined, and the opening / closing information of the automatic switch 156 from the opening / closing operation storage unit 181 is used to determine the demand. The amount of electricity purchased and the amount of electricity sold at the home facility 110 are determined.

図8は、自動開閉器156がオフ(自動開閉器156が開かれて回路が遮断状態に保持されている状態)の場合において、想定されるケースと、そのケースに対応する電力購入量及び販売量の計算式とを示す説明図である。図9は、図8に示す想定されるケースに対応する電力の流れを示す説明図である。
例えば、商用電力系統102が停電したことにより自動開閉器156がオフにされた場合には、需要家施設110内で供給可能な電力を利用して、需要家毎に需要家単体で電力の自給自足を可能にする。
FIG. 8 shows an assumed case, the power purchase amount and sales corresponding to the case when the automatic switch 156 is off (the automatic switch 156 is opened and the circuit is held in a cut-off state). It is explanatory drawing which shows the calculation formula of quantity. FIG. 9 is an explanatory diagram showing the flow of power corresponding to the assumed case shown in FIG.
For example, when the automatic switch 156 is turned off due to a power failure in the commercial power system 102, the self-sufficiency of electric power for each consumer is used for each consumer using the power that can be supplied in the customer facility 110. Enable self-sufficiency.

図9に示すように、自動開閉器156がオフの場合には、需要家施設110は系統電力線103と切り離されている。例えば、上記の場合には、図9(A)に示すように、発電設備151からの余剰電力の売電先は、当該需要家施設110の蓄電システム152だけとなる。蓄電システム電力量計162の電力量は、蓄電システム電力量計162により電力量b2として計測される。したがって、自動開閉器156がオフの場合には、売電される電力量Pは、
P=b2
として求められる。
As shown in FIG. 9, when the automatic switch 156 is off, the customer facility 110 is disconnected from the system power line 103. For example, in the above case, as shown in FIG. 9A, the surplus power from the power generation facility 151 is sold only to the power storage system 152 of the customer facility 110. The power amount of the power storage system power meter 162 is measured by the power storage system power meter 162 as the power amount b2. Therefore, when the automatic switch 156 is off, the amount of power P to be sold is
P = b2
As required.

また、同じく上記の場合には、図9(B)に示すように、需要家が電力を購入できる相手方は、当該需要家施設110の蓄電システム152だけとなる。蓄電システム152から放電された電力量は、蓄電システム電力量計162で計測される電力量b1として計測される。したがって、自動開閉器156がオフの場合には、買電される電力量Pは、
P=b1
として求められる。
Similarly, in the above case, as shown in FIG. 9B, the other party from which the consumer can purchase power is only the power storage system 152 of the consumer facility 110. The amount of power discharged from power storage system 152 is measured as power amount b <b> 1 measured by power storage system watt-hour meter 162. Therefore, when the automatic switch 156 is off, the amount of power P to be purchased is
P = b1
As required.

図10は、電力料金算出部172における電力料金の算出処理を示すフローチャートである。   FIG. 10 is a flowchart showing the calculation process of the power charge in the power charge calculation unit 172.

図10に示すように、電力料金算出部172は、ネットワーク170を介して、需要家施設110の系統電力電力量計161の計測値を取得し(ステップS201)、蓄電システム電力量計162の計測値を取得する(ステップS202)。また、電力料金算出部172は、ネットワーク170を介して、自動開閉器156の開閉情報を取得する(ステップS203)。そして、電力料金算出部172は、取得した自動開閉器156の開閉情報から、自動開閉器156がオフか否かを判定する(ステップS204)。   As illustrated in FIG. 10, the power rate calculation unit 172 acquires the measurement value of the grid power watt hour meter 161 of the customer facility 110 via the network 170 (step S201), and measures the power storage system watt hour meter 162. A value is acquired (step S202). Moreover, the electric power charge calculation part 172 acquires the opening / closing information of the automatic switch 156 via the network 170 (step S203). Then, the power rate calculation unit 172 determines whether or not the automatic switch 156 is off from the acquired opening / closing information of the automatic switch 156 (step S204).

ステップS204で、自動開閉器156がオンの場合には、各計測値に基づいて、開閉器オン時の課金の対象にする電力量を算出する(ステップS205)。この開閉器オン時の課金の対象にする電力量の算出は、図6に示した第1の実施形態での処理と同様であり、その説明を省略する。ステップS204で、自動開閉器156がオフの場合には、各計測値に基づいて、開閉器オフ時の課金の対象にする電力量を算出する(ステップS206)。ステップS205又はステップS206で、課金の対象にする電力量が算出された後、電力料金算出部172は、この電力量に所定値を乗算して、電力料金を算出する(ステップS207)。   If the automatic switch 156 is on in step S204, the amount of power to be charged when the switch is on is calculated based on each measured value (step S205). The calculation of the amount of power to be charged when the switch is on is the same as the processing in the first embodiment shown in FIG. 6, and the description thereof is omitted. If the automatic switch 156 is off in step S204, the amount of power to be charged when the switch is off is calculated based on each measured value (step S206). After the amount of power to be charged is calculated in step S205 or step S206, the power rate calculation unit 172 multiplies this power amount by a predetermined value to calculate a power rate (step S207).

図11は、ステップS206における開閉器オン時の課金の対象にする電力量を算出する処理を示すフローチャートである。以下に示す処理は、自動開閉器156がオフであることから、上位の電気事業者と小売事業者との間で電力の供給が行われない条件の基で実施される。   FIG. 11 is a flowchart showing processing for calculating the amount of power to be charged when the switch is turned on in step S206. Since the automatic switch 156 is off, the processing shown below is performed based on a condition in which power is not supplied between the higher-level electric utility and the retailer.

電力料金算出部172は、蓄電システム電力量計162で計測された電力量が放電電力であるか、充電電力であるかを判定する(ステップS301)。充電電力であると判定された場合(ステップS301:Yes)には、電力料金算出部172は、売電の電力量Pを、「P=b2」として算出する(ステップS302)。放電電力であると判定された場合(ステップS301:No)には、電力料金算出部172は、買電の電力量Pを、「P=b1」として算出する(ステップS303)。   The power rate calculation unit 172 determines whether the amount of power measured by the power storage system watt-hour meter 162 is discharge power or charge power (step S301). When it is determined that the electric power is charged (step S301: Yes), the power charge calculation unit 172 calculates the power amount P for selling power as “P = b2” (step S302). When it is determined that the electric power is discharged (step S301: No), the power rate calculation unit 172 calculates the power amount P for purchasing power as “P = b1” (step S303).

以上説明したように、本発明の第2の実施形態では、停電時に、自動開閉器156がオフした場合にも、電力の購入又は販売量を計算できる。   As described above, in the second embodiment of the present invention, even when the automatic switch 156 is turned off at the time of a power failure, the purchase or sales amount of power can be calculated.

なお、上述の第2の実施形態では、開閉動作記憶部181は、自動開閉器156の開閉情報を記憶しているが、自動開閉器156をオン/オフする条件や指令信号等の情報を記憶するようにしても良い。また、自動開閉器156より系統電力線103側の系統電源の電圧を計測し、この系統電源の電圧が所定電圧に満たない時間を開閉動作記憶部181に記憶しても良い。   In the second embodiment described above, the opening / closing operation storage unit 181 stores opening / closing information of the automatic switch 156, but stores information such as a condition for turning on / off the automatic switch 156 and a command signal. You may make it do. Alternatively, the voltage of the system power supply on the system power line 103 side may be measured from the automatic switch 156, and the time when the voltage of the system power supply does not reach a predetermined voltage may be stored in the switching operation storage unit 181.

以上に示したように、本実施形態の電力管理システム100Aは、電力需要家側に設けた蓄電システムから商用電力系統102に電力を融通する場合に、融通した電力量の対価を算出ための電力量を測定することができる。なお、電力管理システム100Aは、自動開閉器156を遮断状態にしている期間に発電設備151が発電した電力を一時的に蓄電システムに蓄えることができる。また、その蓄えた電力を自動開閉器156の遮断状態が解除された後に、他の需要家に融通するための電力として利用することができる。これにより、自動開閉器156を遮断状態にしている期間の余剰電力を無駄なく利用することを可能にし、更に適正な課金方法で電力料金を算出することが可能になる。   As described above, the power management system 100 </ b> A according to the present embodiment uses the power for calculating the consideration of the accommodated power amount when the power is accommodated from the power storage system provided on the power consumer side to the commercial power system 102. The amount can be measured. Note that the power management system 100A can temporarily store, in the power storage system, the power generated by the power generation equipment 151 during the period when the automatic switch 156 is in the cut-off state. In addition, the stored power can be used as power for accommodating other consumers after the automatic switch 156 is released from the shut-off state. As a result, it is possible to use surplus power during the period when the automatic switch 156 is in the cut-off state without waste, and it is possible to calculate the power charge by an appropriate charging method.

また、上記の電力管理システム100(100A)を適用することにより以下の効果を期待できる。例えば、蓄電システムに充電可能な電力容量や太陽光発電設備の発電量によって、発電電力を蓄電システムに貯めきれない場合が、需要家ごとに生じる場合がある。一方で、太陽光発電設備で発電できる電力量に対し日中の電気消費量が多い電力需要家や、太陽光発電設備で発電できる電力量が比較的少ない需要家では、太陽光発電の余剰電力はほとんど発生せず、蓄電設備を設けたとしも十分な充電量を確保することができない場合がある。このような場合、太陽光発電が発電状態にある時間帯を除く時間帯に、太陽光発電によって発電した電力を利用することができない。このように、実際に設けられた設備の容量や各種条件により、太陽光発電で発電された電力が余り、可能な電力が有効に利用されない場合が生じ得る。この場合に、これらの蓄電システムに貯めきれないことが見込まれる余剰電力を、貯める電力量に余裕がある蓄電システムを設けている需要家に送り、その蓄電システムに貯めることで無駄なく余剰電力を利用することができる。電力管理システム100(100A)はこのような場合の電力融通についても、その電力量を測定することができる。   Moreover, the following effects can be expected by applying the power management system 100 (100A). For example, the case where the generated power cannot be stored in the power storage system depending on the power capacity that can be charged in the power storage system or the amount of power generated by the solar power generation facility may occur for each consumer. On the other hand, surplus power of solar power generation is required for power consumers who consume a lot of electricity during the day compared to the amount of power that can be generated by solar power generation facilities Is hardly generated, and even if a power storage facility is provided, a sufficient amount of charge may not be ensured. In such a case, the electric power generated by the solar power generation cannot be used in the time zone except the time zone in which the solar power generation is in the power generation state. Thus, depending on the capacity of the actually installed equipment and various conditions, there may be a case where the power generated by the photovoltaic power generation is excessive and the available power cannot be used effectively. In this case, surplus power that is expected to be unable to be stored in these power storage systems is sent to a customer who has a power storage system with a sufficient amount of power to be stored. Can be used. The power management system 100 (100A) can also measure the amount of power for power interchange in such a case.

また、ある住戸で発電された太陽光発電電力の所有者は、通常、その太陽光発電設備の所有者である。この太陽光発電電力を他の住戸の蓄電システムに充電し、その電力を更に別の住戸で使用する場合、太陽光発電電力の所有者は、これを使用した住戸の住人から、提供した電力の対価を受けられると考えられる。このような場合にも、電力管理システム100(100A)を適用することで、太陽光発電電力の所有者は、提供した電力の対価を、提供した電力を使用した住戸の住人から受けることが可能になる。
また、以上の例は、二つの住戸間の電力融通であるが、もっと多くの住戸や住戸以外の店舗、マンション、オフィスビル、工場などとの間で蓄電池を利用した電力融通により、電力を融通し合える区域内において、電力をより有効に利用することが可能である。
Moreover, the owner of the photovoltaic power generated in a certain dwelling unit is usually the owner of the photovoltaic power generation facility. When this photovoltaic power is charged into another storage unit's power storage system and the power is used in another unit, the owner of the photovoltaic power generation is responsible for the power provided by the dwelling unit. It is thought that we can receive consideration. Even in such a case, by applying the power management system 100 (100A), the owner of the photovoltaic power generation can receive the price of the provided power from the resident of the dwelling unit using the provided power. become.
In addition, the above example is the power interchange between two dwelling units. However, power can be interchanged with more dwelling units and stores, condominiums, office buildings, factories, etc. using a storage battery. It is possible to use electric power more effectively in the area where it can compete.

なお、電力管理システム100(100A)の全部または一部の機能を実現するためのプログラムをコンピュータ読み取り可能な記録媒体に記録して、この記録媒体に記録されたプログラムをコンピュータシステムに読み込ませ、実行することにより各部の処理を行ってもよい。なお、ここでいう「コンピュータシステム」とは、OSや周辺機器等のハードウェアを含むものとする。
また、「コンピュータシステム」は、WWWシステムを利用している場合であれば、ホームページ提供環境(あるいは表示環境)も含むものとする。
また、「コンピュータ読み取り可能な記録媒体」とは、フレキシブルディスク、光磁気ディスク、ROM、CD−ROM等の可搬媒体、コンピュータシステムに内蔵されるハードディスク等の記憶装置のことをいう。さらに「コンピュータ読み取り可能な記録媒体」とは、インターネット等のネットワークや電話回線等の通信回線を介してプログラムを送信する場合の通信線のように、短時間の間、動的にプログラムを保持するもの、その場合のサーバやクライアントとなるコンピュータシステム内部の揮発性メモリのように、一定時間プログラムを保持しているものも含むものとする。また上記プログラムは、前述した機能の一部を実現するためのものであっても良く、さらに前述した機能をコンピュータシステムにすでに記録されているプログラムとの組み合わせで実現できるものであっても良い。
A program for realizing all or part of the functions of power management system 100 (100A) is recorded on a computer-readable recording medium, and the program recorded on this recording medium is read into the computer system and executed. By doing so, you may process each part. Here, the “computer system” includes an OS and hardware such as peripheral devices.
Further, the “computer system” includes a homepage providing environment (or display environment) if a WWW system is used.
The “computer-readable recording medium” refers to a storage device such as a flexible medium, a magneto-optical disk, a portable medium such as a ROM and a CD-ROM, and a hard disk incorporated in a computer system. Furthermore, the “computer-readable recording medium” dynamically holds a program for a short time like a communication line when transmitting a program via a network such as the Internet or a communication line such as a telephone line. In this case, a volatile memory in a computer system serving as a server or a client in that case, and a program that holds a program for a certain period of time are also included. The program may be a program for realizing a part of the functions described above, and may be a program capable of realizing the functions described above in combination with a program already recorded in a computer system.

以上、本発明の実施形態について図面を参照して詳述してきたが、具体的な構成はこの実施形態に限られるものではなく、この発明の要旨を逸脱しない範囲の設計変更等も含まれる。
また、上記の実施形態においては、電力管理システムは、商用電力系統2に係る電気事業者(上位の電気事業者)から電力の供給を受け、需要家に電力を小売りする電気事業者(小売事業者)によって運用される場合を例示した。このように、上記の小売事業者が上位の電気事業者と異なる場合に限られず、小売事業者は、上位の電気事業者であってもよい。
The embodiment of the present invention has been described in detail with reference to the drawings. However, the specific configuration is not limited to this embodiment, and includes design changes and the like without departing from the gist of the present invention.
In the above-described embodiment, the power management system receives an electric power supply from the electric power company (upper electric power company) related to the commercial power system 2 and retails the electric power to the consumer (retail business). The case where it is operated by the As described above, the retailer is not limited to a case where the retailer is different from the higher-order electric utility. The retailer may be a higher-order electric operator.

1,101:電力管理区域
100,100A:電力管理システム
2,102:商用電力系統
3,103:系統電力線
10,110:需要家施設
51,151:発電設備
52,152:蓄電システム(蓄電部)
53,153:負荷
54,154:電力経路分岐部
55,155:蓄電システム制御部
56,156:自動開閉器
61,161:系統電力電力量計(系統電力計測部)
62,162:蓄電システム電力量計(蓄電部電力計測部)
70,170:ネットワーク
71,171:融通区域内電力管理部
72,172:電力料金算出部(電力量算出部)
181:開閉動作記憶部
1, 101: Power management area 100, 100A: Power management system 2, 102: Commercial power system 3, 103: System power line 10, 110: Customer facility 51, 151: Power generation facility 52, 152: Power storage system (power storage unit)
53, 153: Load 54, 154: Power path branching unit 55, 155: Power storage system control unit 56, 156: Automatic switch 61, 161: System power watt-hour meter (system power measuring unit)
62, 162: Power storage system watt-hour meter (power storage unit power measurement unit)
70, 170: Network 71, 171: Power management section 72, 172 in the interchange area: Electricity charge calculation section (electric energy calculation section)
181: Opening / closing operation storage unit

Claims (11)

商用電力系統から電力を充電できると共に該商用電力系統に電力を放電できる蓄電部が設けられており、
該蓄電部に充放電する電力の電力量を計測する蓄電部電力計測部と、
該商用電力系統から受電及び該商用電力系統に送電する潮流方向及び逆潮流方向の電力量を計測する系統電力計測部と、
前記蓄電部電力計測部によって計測された蓄電電力の充電又は放電の電力量と、前記系統電力計測部によって計測された潮流方向又は逆潮流方向の電力量の情報から、電力需要家が売買する電力量を算出する電力量算出部と
を備えることを特徴とする電力管理システム。
A power storage unit that can charge power from the commercial power system and discharge power to the commercial power system is provided,
A power storage unit power measurement unit that measures the amount of power to be charged and discharged to the power storage unit;
A system power measurement unit that measures the amount of power received from the commercial power system and transmitted in the power flow direction and the reverse power flow direction to the commercial power system;
The electric power consumer buys and sells from the information on the amount of charge or discharge of the stored power measured by the power storage unit power measurement unit and the amount of power in the tidal direction or reverse power direction measured by the grid power measurement unit A power management system comprising: a power amount calculation unit that calculates the amount.
前記蓄電部電力計測部は、前記蓄電部に充電される充電電力量のうち少なくとも一部の電力を売電する電力量として計測する
ことを特徴とする請求項1に記載の電力管理システム。
The power management system according to claim 1, wherein the power storage unit power measurement unit measures at least a part of the charged power amount charged in the power storage unit as power to sell.
該商用電力系統から受電する潮流方向の電力量を計測する系統電力計測部を備え、
前記電力量算出部は、前記蓄電部電力計測部によって計測された前記充電の電力量と、前記系統電力計測部によって計測された前記潮流方向の電力量とから、電力需要家が売電する電力の電力量を算出する
ことを特徴とする請求項1又は2に記載の電力管理システム。
A grid power measuring unit that measures the amount of power in the tidal direction to receive power from the commercial power grid,
The power amount calculating unit sells power sold by a power consumer from the power amount of the charge measured by the power storage unit power measuring unit and the power amount in the tidal direction measured by the grid power measuring unit. The power management system according to claim 1, wherein the power amount of the power is calculated.
前記電力量算出部は、前記蓄電部電力計測部によって計測された充電の電力量から前記系統電力計測部により計測された順潮流方向の電力量を減じた電力量、又は、前記系統電力計測部により計測された逆潮流方向の電力量から前記蓄電部電力計測部によって計測された放電の電力量を減じた電力量、又は、前記蓄電部電力計測部によって計測された充電の電力量と前記系統電力計測部により計測された逆潮流方向の電力量とを加えた電力量により、電力需要家が売電する電力の電力量を算出することを特徴とする請求項3に記載の電力管理システム。   The power amount calculation unit is a power amount obtained by subtracting a power amount in a forward power flow direction measured by the grid power measurement unit from a charge power amount measured by the power storage unit power measurement unit, or the grid power measurement unit The amount of electric power obtained by subtracting the amount of electric power of discharge measured by the power storage unit power measurement unit from the amount of power in the reverse power flow direction measured by the above, or the power amount of charging measured by the power storage unit power measurement unit and the system The power management system according to claim 3, wherein the amount of power sold by the power consumer is calculated based on the amount of power obtained by adding the amount of power in the reverse power flow direction measured by the power measuring unit. 前記電力量算出部は、前記系統電力計測部により計測された順潮流方向の電力量から前記蓄電部電力計測部によって計測された充電の電力量を減じた電力量、又は、前記蓄電部電力計測部によって計測された放電の電力量から前記系統電力計測部により計測された逆潮流方向の電力量を減じた電力量により、電力需要家が買電する電力の電力量を算出することを特徴とする請求項3又は4に記載の電力管理システム。   The power amount calculation unit is a power amount obtained by subtracting a power amount of charging measured by the power storage unit power measurement unit from a power amount in a forward power flow direction measured by the system power measurement unit, or the power storage unit power measurement. Calculating the amount of power to be purchased by a power consumer from the amount of power obtained by subtracting the amount of power in the reverse power flow direction measured by the grid power measuring unit from the amount of power of discharge measured by the unit. The power management system according to claim 3 or 4. 前記系統電力計測部は、前記商用電力系統からの引き込み線に設けられており、
前記系統電力計測部から負荷に向かう第1接続線に、前記第1接続線から前記蓄電部に向かう第2接続線を分岐する分岐部が設けられ、
前記蓄電部電力計測部は、前記第2接続線に設けられる
ことを特徴とする請求項3から5の何れか1項に記載の電力管理システム。
The grid power measurement unit is provided on a lead-in line from the commercial power grid,
The first connection line heading from the system power measurement unit to the load is provided with a branch unit that branches the second connection line heading from the first connection line to the power storage unit,
The power management system according to any one of claims 3 to 5, wherein the power storage unit power measurement unit is provided in the second connection line.
前記電力量算出部は、前記蓄電部を前記商用電力系統から遮断した状態で、前記蓄電部電力計測部によって計測された充電電力の電力量から、電力需要家が売電する電力の電力量を算出することを特徴とする請求項1から6の何れか1項に記載の電力管理システム。   The power amount calculation unit calculates the amount of power sold by the power consumer from the amount of charging power measured by the power storage unit power measurement unit in a state where the power storage unit is disconnected from the commercial power system. The power management system according to claim 1, wherein the power management system is calculated. 前記電力量算出部は、前記蓄電部を前記商用電力系統から遮断した状態で、前記蓄電部電力計測部によって計測された前記放電の電力量から、電力需要家が買電する電力の電力量を算出することを特徴とする請求項7に記載の電力管理システム。   The power amount calculation unit calculates the amount of power to be purchased by a power consumer from the amount of electric power of the discharge measured by the power storage unit power measurement unit in a state where the power storage unit is disconnected from the commercial power system. The power management system according to claim 7, wherein the power management system is calculated. 商用電力系統に電力を放電できるように蓄電部を設けておき、
蓄電部電力計測部により該蓄電部に充電する場合の充電の電力量を計測し、
前記蓄電部電力計測部によって計測された前記充電の電力量を含む情報から、前記蓄電部が設けられている電力需要家が売電する電力量を算出する
ことを特徴とする電力管理方法。
A power storage unit is provided so that power can be discharged to the commercial power system,
Measure the amount of power for charging when charging the power storage unit by the power storage unit power measurement unit,
A power management method, comprising: calculating the amount of power sold by a power consumer provided with the power storage unit from information including the amount of power of charging measured by the power storage unit power measurement unit.
商用電力系統に電力を放電できるように蓄電部を設けておき、
蓄電部電力計測部により該蓄電部に充電する場合の充電の電力量を計測するステップと、
前記蓄電部電力計測部によって計測された前記充電の電力量b2を含む情報から、前記蓄電部が設けられている電力需要家が売電する電力量を算出するステップと
を含むコンピュータにより実行可能なプログラム。
A power storage unit is provided so that power can be discharged to the commercial power system,
A step of measuring the amount of electric power for charging when the power storage unit is charged by the power storage unit power measurement unit;
Calculating the amount of power sold by the power consumer provided with the power storage unit from the information including the power amount b2 of the charging measured by the power storage unit power measurement unit. program.
商用電力系統からの電力を充電できるように設けられており、貯えた電力を放電する蓄電部と、
前記蓄電部から放電する電力の電力量を計測する蓄電部電力計測部と、
前記蓄電部電力計測部によって計測された前記電力の電力量を含む情報から、前記蓄電部が設けられている電力需要家が買電する電力の電力量を算出する電力量算出部と
を備えることを特徴とする電力管理システム。
A power storage unit that is provided so as to be able to charge power from a commercial power system, and that discharges the stored power;
A power storage unit power measurement unit that measures the amount of power discharged from the power storage unit;
A power amount calculation unit that calculates power amount of power to be purchased by a power consumer provided with the power storage unit from information including the power amount of the power measured by the power storage unit power measurement unit. Power management system characterized by
JP2014057993A 2014-03-20 2014-03-20 Power management system, power management method, and program Pending JP2015186276A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014057993A JP2015186276A (en) 2014-03-20 2014-03-20 Power management system, power management method, and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014057993A JP2015186276A (en) 2014-03-20 2014-03-20 Power management system, power management method, and program

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2017220491A Division JP6411616B2 (en) 2017-11-15 2017-11-15 Power management system, power management method and program

Publications (1)

Publication Number Publication Date
JP2015186276A true JP2015186276A (en) 2015-10-22

Family

ID=54352310

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014057993A Pending JP2015186276A (en) 2014-03-20 2014-03-20 Power management system, power management method, and program

Country Status (1)

Country Link
JP (1) JP2015186276A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017212843A (en) * 2016-05-27 2017-11-30 日本電気株式会社 Processing device, processing method, and program
JP2019050667A (en) * 2017-09-08 2019-03-28 日本電気株式会社 Processing apparatus, processing method, and program

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013143815A (en) * 2012-01-10 2013-07-22 Ntt Facilities Inc Power supply system, power supply control device, power supply method and program
JP2013169137A (en) * 2012-01-17 2013-08-29 Keio Gijuku Power network system
JP2014054084A (en) * 2012-09-07 2014-03-20 Sharp Corp Control device and photovoltaic power generation system comprising the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013143815A (en) * 2012-01-10 2013-07-22 Ntt Facilities Inc Power supply system, power supply control device, power supply method and program
JP2013169137A (en) * 2012-01-17 2013-08-29 Keio Gijuku Power network system
JP2014054084A (en) * 2012-09-07 2014-03-20 Sharp Corp Control device and photovoltaic power generation system comprising the same

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017212843A (en) * 2016-05-27 2017-11-30 日本電気株式会社 Processing device, processing method, and program
JP2019050667A (en) * 2017-09-08 2019-03-28 日本電気株式会社 Processing apparatus, processing method, and program

Similar Documents

Publication Publication Date Title
JP7455163B2 (en) Power supply system and method
JP5520574B2 (en) Power interchange system
JP6240009B2 (en) Power management system, power management method and program
US9722443B2 (en) Power distribution device
JP5575457B2 (en) Power distribution system
WO2011055208A1 (en) Electric power interchange system
US9819222B2 (en) Power control apparatus and control method
US20150149396A1 (en) Non-technical loss detection and localization
US20180034299A1 (en) Hybrid interactive storage system and method
KR101214323B1 (en) Smart watt-hour meter for power management connected with power exchange system
AU2017263912B2 (en) Charge/discharge planning system, planning method, and program
JP2015186276A (en) Power management system, power management method, and program
JP6411616B2 (en) Power management system, power management method and program
JP2015192485A (en) Power control unit
JP2016157438A (en) Electricity charge management device, electricity charge management method and program
JPWO2018078802A1 (en) POWER MANAGEMENT SYSTEM, CONTROL DEVICE, AND POWER MANAGEMENT METHOD
Yianni et al. Provision of Frequency Regulation Service and Peak Demand Reduction by Distributed Battery Storage
JP5886400B1 (en) Power market pricing system and method
JP5904850B2 (en) Electricity meter
WO2015015530A1 (en) Power feed control device
Barua et al. Demand side load management system for end user in micro grid
KR20130133552A (en) Energy managing apparatus
Singh et al. Power quality related consumers rights in Indian electricity market
JP2019168806A (en) Management system
JP2017163746A (en) Power supply system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20161101

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170725

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170801

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170914

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20171010

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20180515