JP2013181921A - Method for dismantling radioactive contaminated facility - Google Patents

Method for dismantling radioactive contaminated facility Download PDF

Info

Publication number
JP2013181921A
JP2013181921A JP2012047266A JP2012047266A JP2013181921A JP 2013181921 A JP2013181921 A JP 2013181921A JP 2012047266 A JP2012047266 A JP 2012047266A JP 2012047266 A JP2012047266 A JP 2012047266A JP 2013181921 A JP2013181921 A JP 2013181921A
Authority
JP
Japan
Prior art keywords
building
slab
dismantling
facility
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2012047266A
Other languages
Japanese (ja)
Other versions
JP5787174B2 (en
Inventor
Kiyoshi Matsuo
浄 松尾
Kazuyoshi Torii
和敬 鳥居
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2012047266A priority Critical patent/JP5787174B2/en
Publication of JP2013181921A publication Critical patent/JP2013181921A/en
Application granted granted Critical
Publication of JP5787174B2 publication Critical patent/JP5787174B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method for dismantling a radioactive contaminated facility for dismantling the facility in short time without a worker entering a dismantlement area and securing safety against exposure.SOLUTION: In a method for dismantling a radioactive contaminated facility for newly installing a shelter 14 on the outer periphery of a building 12 of the radioactive contaminated facility so as to cover the building 12, installing lifting means 16 in the shelter 14, and performing a series of works of dismantlement, decontamination, shredding, container storage of a skeleton of the building 12 in the shelter 14, the skeleton of the building is segmented like a block by a remote operation to be sequentially dismantled downward from an upper part of the building 12, the segmented block-like skeleton of the building is lifted by the lifting means 16 and carried to a work area 18 with a degree of contamination lower than that of the building 12, which is provided in the shelter 14, to be decontaminated in the work area 18.

Description

本発明は、放射能汚染された原子力発電施設や核燃料施設などの放射能汚染施設の解体方法に関するものである。   The present invention relates to a method for dismantling radioactively contaminated facilities such as radioactively contaminated nuclear power generation facilities and nuclear fuel facilities.

従来の原子力発電施設の廃止措置計画に伴う解体方法では、発電所建屋を最終バウンダリーとするために、建屋内部に設置された機器・配管類の撤去が優先される。つまり、図18のフロー図に示すように、機器・配管類の撤去が終了した後に放射能汚染したコンクリート表面をはつり工法により除染し、サーベイ作業を経て管理区域を解除する。そして最終的に建屋は、一般の建築物と同様に上方から下方に順次解体されることになる。   In the dismantling method associated with the conventional decommissioning plan for nuclear power generation facilities, removal of equipment and piping installed in the building is given priority in order to make the power plant building the final boundary. That is, as shown in the flowchart of FIG. 18, after the removal of the equipment and piping is completed, the radioactively contaminated concrete surface is decontaminated by the suspension method, and the management area is released through the survey work. Finally, the building is demolished sequentially from top to bottom in the same way as ordinary buildings.

なお、原子力発電施設などの解体方法に関する従来の技術としては、例えば、特許文献1〜3が知られている。ここで、特許文献1は原子力設備の解体に関するものであり、原子炉格納容器の内壁面の放射性物質を除去した後、所定の大きさに解体して容器に収納してトンネルを通じてタービン建屋に運搬し、このタービン建屋の中で容器内の解体物を細断し除染作業を行うものである。   For example, Patent Documents 1 to 3 are known as conventional techniques related to a dismantling method for a nuclear power generation facility or the like. Here, Patent Document 1 relates to the dismantling of nuclear facilities, after removing radioactive material on the inner wall surface of the reactor containment vessel, dismantling it to a predetermined size, storing it in the vessel, and transporting it to the turbine building through the tunnel. The decontamination work is performed by chopping the dismantled material in the container in the turbine building.

また、特許文献2は原子炉建屋の解体に関するものであり、建屋の一部を下層階において解体していく工程と、その上方の建屋をリフトダウンさせる工程とを繰り返すことによって建屋を下方から上方に順次解体するものである。   Patent Document 2 relates to the dismantling of the reactor building, and the building is moved upward from below by repeating the step of dismantling a part of the building on the lower floor and the step of lifting down the building above it. Will be dismantled sequentially.

また、特許文献3はボイラー建屋の解体に関するものであり、建屋の一部の荷重を揚重手段で吊り支持して建屋の一部と残りの部分とを切り離した後、建屋の一部を下部から解体する工程と、揚重手段で建屋の一部を降下させる工程とを繰り返すことによって建屋の一部を下方から上方に向けて順次先行解体するものである。   Patent Document 3 relates to the dismantling of a boiler building. After a part of the building is lifted and supported by lifting means to separate a part of the building from the remaining part, the part of the building is moved to the lower part. The part of the building is sequentially dismantled sequentially from the bottom to the top by repeating the step of dismantling from the top and the step of lowering the part of the building by the lifting means.

特開2010−8091号公報JP 2010-8091 A 特開平11−270152号公報JP 11-270152 A 特開平10−46838号公報Japanese Patent Laid-Open No. 10-46838

ところで、放射能漏れ事故を起こした福島第一原子力発電所のように、建屋内外全体の機器・配管類および躯体表面がFP(核分裂生成物)およびU(ウラン)で汚染している施設では、建屋は最終バウンダリーとして機能しない。この場合、従来の機器・配管類を先行して解体し、その後に建屋を解体する手順の適用は、被曝に対する作業員の安全性の確保が難しいため適用困難である。   By the way, in facilities such as the Fukushima Daiichi nuclear power plant that caused the radioactive leak accident, equipment and piping throughout the building and the surface of the enclosure are contaminated with FP (fission products) and U (uranium). The building does not function as the final boundary. In this case, it is difficult to apply the procedure of dismantling the conventional equipment and piping in advance and then dismantling the building because it is difficult to ensure the safety of workers against exposure.

本発明は、上記に鑑みてなされたものであって、作業員が解体エリアに立ち入らずに施設を短期間で解体することができ、被曝に対する安全性の確保が可能な放射能汚染施設の解体方法を提供することを目的とする。   The present invention has been made in view of the above, and it is possible to dismantle a facility in a short period of time without an operator entering the dismantling area, and to dismantle a radioactive contamination facility capable of ensuring safety against exposure. It aims to provide a method.

上記した課題を解決し、目的を達成するために、本発明の請求項1に係る放射能汚染施設の解体方法は、放射能汚染された施設の建屋を覆うようにこの外周に上屋を新設するとともに、この上屋の中に揚重手段を設置し、この上屋の中で前記建屋躯体の解体、除染、細断、容器収納の一連の作業を行う放射能汚染施設の解体方法であって、遠隔操作により前記建屋躯体をブロック状に切り出して、前記建屋の上方から下方に向けて順次解体し、切り出したブロック状の前記建屋躯体を前記揚重手段で揚重して前記上屋内に設けた汚染度が前記建屋よりも低い作業エリアに運搬して、この作業エリアで除染するようにしたことを特徴とする。   In order to solve the above-described problems and achieve the object, the method for dismantling a radioactively contaminated facility according to claim 1 of the present invention provides a new roof on the outer periphery so as to cover the building of the radioactively contaminated facility. At the same time, a lifting means is installed in the shed, and the decontamination method of the radioactive contamination facility in which a series of operations of demolition, decontamination, shredding, and container storage of the building enclosure is performed in the shed. The building housing is cut into a block shape by remote operation, and the building is sequentially disassembled from the upper side to the lower side of the building, and the cut block building building is lifted by the lifting means. The degree of contamination provided in the building is transported to a work area lower than the building and decontaminated in this work area.

また、本発明の請求項2に係る放射能汚染施設の解体方法は、上述した請求項1において、前記建屋躯体と、前記建屋躯体に既設の機器・配管類とを一体的に切り出すことを特徴とする。   In addition, the method for dismantling a radioactive contamination facility according to claim 2 of the present invention is characterized in that, in claim 1 described above, the building housing and the existing equipment and piping are cut out integrally with the building housing. And

また、本発明の請求項3に係る放射能汚染施設の解体方法は、上述した請求項1または2において、前記建屋躯体をなすスラブ上に設けた穿孔手段を遠隔操作して前記スラブに貫通穴を設け、この貫通穴の上方から自動伸長手段および上部拡幅手段を備える柱状の支保工を挿入して前記スラブ下面と下階のスラブ上面との間に配置し、前記支保工を介して前記スラブの荷重を一時的に下階のスラブに支持させた後、前記スラブを切り出すことを特徴とする。   A method for dismantling a radioactive contamination facility according to claim 3 of the present invention is the method of disassembling a radioactive contamination facility according to claim 1 or 2, wherein a perforation means provided on the slab forming the building enclosure is remotely operated to penetrate the slab. A columnar support having automatic extension means and upper widening means is inserted from above the through hole, and is disposed between the lower surface of the slab and the upper surface of the lower slab, and the slab is inserted through the support work. After the load is temporarily supported by the slab on the lower floor, the slab is cut out.

また、本発明の請求項4に係る放射能汚染施設の解体方法は、上述した請求項3において、前記穿孔手段を遠隔操作して前記スラブに貫通穴を設け、この貫通穴の上方から下部拡幅手段を備える吊り治具を挿入して前記スラブに取り付けておき、切り出した前記スラブを前記吊り治具を介して前記揚重手段で揚重することを特徴とする。   According to a fourth aspect of the present invention, there is provided a method for dismantling a radioactive contamination facility according to the third aspect, wherein the piercing means is remotely operated to provide a through hole in the slab, and the lower widening from above the through hole. A hanging jig provided with means is inserted and attached to the slab, and the cut out slab is lifted by the lifting means through the hanging jig.

本発明によれば、放射能汚染された施設の建屋を覆うようにこの外周に上屋を新設するとともに、この上屋の中に揚重手段を設置し、この上屋の中で前記建屋躯体の解体、除染、細断、容器収納の一連の作業を行う放射能汚染施設の解体方法であって、遠隔操作により前記建屋躯体をブロック状に切り出して、前記建屋の上方から下方に向けて順次解体し、切り出したブロック状の前記建屋躯体を前記揚重手段で揚重して前記上屋内に設けた汚染度が前記建屋よりも低い作業エリアに運搬して、この作業エリアで除染するようにしたので、作業員が建屋躯体の解体エリアに立ち入らずに施設の建屋を短期間で解体することができ、作業員の被曝に対する安全性の確保が可能であるという効果を奏する。   According to the present invention, a new shed is installed on the outer periphery so as to cover the building of the radioactively contaminated facility, and a lifting means is installed in the shed, and the building skeleton in the shed. Is a method of dismantling a radioactive contamination facility that performs a series of operations of dismantling, decontamination, shredding, and container storage, by cutting out the building housing into a block shape by remote control, from the top to the bottom of the building Sequentially dismantled, the block-shaped building frame that has been cut out is lifted by the lifting means, transported to a work area with a lower degree of contamination than the building, and decontaminated in this work area Since it did in this way, an operator can dismantle the building of a facility in a short period of time without entering the dismantling area of the building frame, and there is an effect that it is possible to ensure safety against the exposure of the worker.

図1は、本発明に係る放射能汚染施設の解体方法の対象となる施設の正面断面図である。FIG. 1 is a front sectional view of a facility which is a target of a method for dismantling a radioactively contaminated facility according to the present invention. 図2は、本発明に係る放射能汚染施設の解体方法の対象となる施設の平面図である。FIG. 2 is a plan view of a facility that is a target of the method for dismantling a radioactively contaminated facility according to the present invention. 図3は、本発明に係る放射能汚染施設の解体方法による建屋解体手順を示す概略図である。FIG. 3 is a schematic view showing a building dismantling procedure according to the dismantling method of the radioactive contamination facility according to the present invention. 図4は、床と機器・配管類とを一体的に切り出す手順1を示す図である。FIG. 4 is a diagram showing a procedure 1 for integrally cutting a floor and equipment / piping. 図5は、床と機器・配管類とを一体的に切り出す手順2を示す図である。FIG. 5 is a diagram showing a procedure 2 for cutting out the floor and the equipment / pipings integrally. 図6は、床と機器・配管類とを一体的に切り出す手順3を示す図である。FIG. 6 is a diagram illustrating a procedure 3 for integrally cutting the floor and the equipment / piping. 図7は、床と機器・配管類とを一体的に切り出す手順4を示す図である。FIG. 7 is a diagram showing a procedure 4 for cutting out the floor and the equipment / pipings integrally. 図8は、躯体切り出し後の処理手順を例示するフロー図である。FIG. 8 is a flowchart illustrating an example of a processing procedure after the housing is cut out. 図9は、作業エリアの配置レイアウトを示す平面図である。FIG. 9 is a plan view showing the layout of the work area. 図10は、建物躯体を単独で切り出す手順1を示す図である。FIG. 10 is a diagram showing a procedure 1 for cutting out a building frame alone. 図11は、建物躯体を単独で切り出す手順2を示す図である。FIG. 11 is a diagram illustrating a procedure 2 for cutting out a building frame alone. 図12は、建物躯体を単独で切り出す手順3を示す図である。FIG. 12 is a diagram illustrating a procedure 3 for cutting out a building frame alone. 図13は、建物躯体を単独で切り出す手順4を示す図である。FIG. 13 is a diagram illustrating a procedure 4 for cutting out a building frame alone. 図14は、躯体切り出し後の処理手順を例示するフロー図である。FIG. 14 is a flowchart illustrating an example of a processing procedure after the body is cut out. 図15は、貫通穴の穿孔工程を示す図である。FIG. 15 is a diagram showing a through hole drilling process. 図16は、支保工の設置工程を示す図である。FIG. 16 is a diagram showing a support installation process. 図17は、吊り治具の取り付け工程を示す図である。FIG. 17 is a diagram illustrating a process of attaching the hanging jig. 図18は、従来の原子力発電施設の廃止措置計画に伴う解体手順を示す概略フロー図である。FIG. 18 is a schematic flowchart showing a dismantling procedure associated with a conventional nuclear power facility decommissioning plan.

以下に、本発明に係る放射能汚染施設の解体方法の実施の形態を図面に基づいて詳細に説明する。なお、以下では、建屋内外全体の機器・配管類および表面が放射能漏れ事故などによりFP(核分裂生成物)およびU(ウラン)で汚染されている原子力発電施設を例にとり説明するが、この実施例によりこの発明が限定されるものではない。   Embodiments of a method for dismantling a radioactive contamination facility according to the present invention will be described below in detail with reference to the drawings. In the following, we will explain an example of a nuclear power generation facility where the entire equipment and piping inside and outside the building and the surface are contaminated with FP (fission products) and U (uranium) due to a radioactive leak accident, etc. The invention is not limited to the examples.

図1および図2に示すように、本発明に係る放射能汚染施設の解体方法は、放射能汚染された施設10の建屋12を覆うようにこの外周に上屋14を新設するとともに、この上屋14の中に天井クレーン16(揚重手段)、汚染度が建屋12よりも低い作業エリア18を設置し、この上屋14の中で建屋躯体の解体、除染、細断、容器収納の一連の作業を行うことを前提とするものである。なお、図1において点線部2は爆発事故等により消失した建屋の天井部分である。   As shown in FIG. 1 and FIG. 2, the method for dismantling a radioactively contaminated facility according to the present invention newly installs a roof 14 on the outer periphery so as to cover the building 12 of the radioactively contaminated facility 10. An overhead crane 16 (lifting means) and a work area 18 having a pollution level lower than that of the building 12 are installed in the store 14, and the building housing is dismantled, decontaminated, shredded, and stored in the container 14 It is premised on a series of operations. In FIG. 1, a dotted line portion 2 is a ceiling portion of the building that has disappeared due to an explosion accident or the like.

上屋14は、複数の鉄骨柱20と、これを支えるSC壁(鋼板コンクリート構造壁)22と、トラス構造の天井屋根15とを有する略直方体状の構造物であり、鉄骨柱20間をシート状物で被覆することにより建屋12を外部から遮蔽する。   The roof 14 is a substantially rectangular parallelepiped structure having a plurality of steel columns 20, an SC wall (steel plate concrete structure wall) 22 that supports the steel columns 20, and a truss-structured ceiling roof 15. The building 12 is shielded from the outside by covering it with the object.

SC壁22は、2枚の鋼板間にコンクリートを充填した壁構造であり、その基礎は地表面GL以下に根入れされる。SC壁22の基礎下には地盤改良体26を構築し、上屋14の外周地下には止水壁24を構築する。   The SC wall 22 is a wall structure in which concrete is filled between two steel plates, and the foundation is embedded below the ground surface GL. A ground improvement body 26 is constructed under the foundation of the SC wall 22, and a water blocking wall 24 is constructed in the outer periphery underground of the roof 14.

また、天井屋根15下の天井クレーン16は、鉄骨柱20に設けたレール21に沿って上屋14内を走行可能に構成する。   The overhead crane 16 under the ceiling roof 15 is configured to be able to travel in the roof 14 along rails 21 provided on the steel column 20.

建屋12の解体方法としては、図3(1)〜(5)に示すように、上屋14の中で天井クレーン16を用いて建屋躯体の上方から下方に向けて順次解体撤去していく。   As a method of dismantling the building 12, as shown in FIGS. 3 (1) to (5), the dismantling and removal are sequentially performed from the upper side to the lower side of the building frame using the overhead crane 16 in the upper building 14.

より具体的には、建屋躯体をなす床、梁、壁等のコンクリートは、後述する手順により遠隔操作でブロック状に切り出される。そして、切り出したブロック状の建屋躯体を天井クレーン16で揚重して上屋14内の作業エリア18に運搬し、この作業エリア18で除染作業等の後工程の作業を行うことになる。   More specifically, concrete such as a floor, a beam, and a wall constituting the building frame is cut out in a block shape by remote operation according to a procedure described later. Then, the cut-out block-shaped building frame is lifted by the overhead crane 16 and transported to the work area 18 in the roof 14, and post-process work such as decontamination work is performed in the work area 18.

(建屋躯体の切り出し手順)
次に、建屋躯体をなす床等のコンクリートの切り出し手順について、床と機器・配管類とを一体的に切り出す場合と、機器・配管類が既に撤去されている建屋躯体を単独で切り出す場合とに分けて説明する。
(Procedure for cutting out the building frame)
Next, regarding the procedure of cutting concrete such as the floor that forms the building frame, when cutting the floor and equipment / piping together, and when cutting out the building frame from which equipment / piping has already been removed. Separately described.

[床と機器・配管類とを一体的に切り出す場合]
まず、機器・配管類が床に付いた状態で、床と機器・配管類とを一体的に切り出す場合について図4〜図7を参照しながら説明する。なお、図4〜図7の各図において(1)は平面断面図、(2)は正面断面図である。
[When cutting the floor and equipment / piping together]
First, a case where the floor and the equipment and piping are cut out integrally with the equipment and piping attached to the floor will be described with reference to FIGS. In addition, in each figure of FIGS. 4-7, (1) is a plane sectional view, (2) is a front sectional view.

図4に示すように、梁38を有する床36(スラブ)の下面側には配管類30やレール34が取り付けてある。下階の床37にはタンク28(機器類)が据え付けられ、壁40の側面には配管類32が取り付けてある。まず、配管類30、レール34を切断するための複数の開口42を床36に開ける。この開口42は、床36上に配置した図示しないコアボーリング装置、ワイヤーソー装置またはダイヤモンドブレード装置などを遠隔操作することで穿孔することができる。   As shown in FIG. 4, piping 30 and rails 34 are attached to the lower surface side of a floor 36 (slab) having beams 38. A tank 28 (equipment) is installed on the floor 37 of the lower floor, and piping 32 is attached to the side surface of the wall 40. First, a plurality of openings 42 for cutting the piping 30 and the rail 34 are opened in the floor 36. The opening 42 can be drilled by remotely operating a core boring device, a wire saw device, a diamond blade device, or the like (not shown) disposed on the floor 36.

次に、図5に示すように、開口42を通じて床36の下側にある配管類30、レール34を切断面30a、34aにて切断する。   Next, as shown in FIG. 5, the piping 30 and the rail 34 below the floor 36 are cut through the openings 42 at the cut surfaces 30a and 34a.

次に、図6に示すように、床36上の複数個所にエポキシアンカーなどのアンカーボルト44を取り付け、アンカーボルト44を介して天井クレーン16で吊り上げた状態にする。次いで、床36と壁40および梁38との境界部分36aを切断位置として、図示しないワイヤーソー装置等を遠隔操作して床36を切断する。そして、配管類30やレール34とともに切り出したブロック状の床36を天井クレーン16で揚重して撤去する。同様に、梁38を切断後、揚重して撤去する。   Next, as shown in FIG. 6, anchor bolts 44 such as epoxy anchors are attached to a plurality of locations on the floor 36 and are lifted by the overhead crane 16 via the anchor bolts 44. Next, the floor 36 is cut by remotely operating a wire saw device (not shown) with the boundary portion 36a between the floor 36 and the wall 40 and the beam 38 as a cutting position. Then, the block-shaped floor 36 cut out together with the piping 30 and the rail 34 is lifted by the overhead crane 16 and removed. Similarly, after cutting the beam 38, it is lifted and removed.

最後に、図7に示すように、床36や梁38が撤去された青天井の状態でタンク28、壁40に設置された配管類32を揚重して撤去する。この後、上記と同様に壁40を切断後、揚重して撤去する。   Finally, as shown in FIG. 7, the pipes 32 installed on the tank 28 and the wall 40 are lifted and removed in the state of the blue ceiling from which the floor 36 and the beam 38 have been removed. Thereafter, the wall 40 is cut and lifted and removed in the same manner as described above.

このように、本発明によれば、床の下側に設置された機器・配管類を部屋内部に作業員が進入することなく床上より安全に撤去することができる。また、床上や壁に設置された機器・配管類は天井スラブ(上階の床)が無い青天井の状態で遠隔性、揚重性に優れた解体ができる。   Thus, according to the present invention, equipment and piping installed under the floor can be safely removed from the floor without an operator entering the room. In addition, the equipment and piping installed on the floor and on the wall can be dismantled with excellent remoteness and liftability in a blue ceiling without a ceiling slab (floor on the upper floor).

撤去された大判のブロック状の床36(スラブ)、梁38、壁40、タンク28、配管類30、32、レール34等は、それぞれ天井クレーン16により作業エリア18に運搬された後、除染、細断、容器収納される。この作業エリア18におけるこの後の処理手順については、図8に例示するように、ステップS1、S2、S3の各工程を経たものとなる。このように、本発明によれば、床等の躯体を大判のブロック状に切り出し、建屋外部の安全な作業エリアで除染、細断、容器収納等を行うため、並行作業が可能であり、工期の短縮が図れる。   The removed large block floor 36 (slab), beams 38, walls 40, tanks 28, pipes 30, 32, rails 34, etc. removed are transported to the work area 18 by the overhead crane 16 and then decontaminated. Shredded and containerized. The subsequent processing procedure in the work area 18 is performed through steps S1, S2, and S3 as illustrated in FIG. In this way, according to the present invention, a frame such as a floor is cut into a large block shape, and decontamination, shredding, container storage, etc. are performed in a safe work area of the building outdoor part, so that parallel work is possible. The construction period can be shortened.

ここで、図8の処理手順においては、以下の(1)〜(5)を前提条件としている。
(1)解体対象部位のスラブ(床)等のコンクリートは放射化していないものとし、表面に付着したFP、Uを除染すればCL(放射性物質として扱う必要のないもの)になるものとする。
(2)機器・配管類がスラブ(床)に付いた状態でスラブ(床)と機器・配管類とを一体的に切り出し、上屋内の作業エリアで機器・配管類を取り外すものとする。
(3)ブロック状に切り出されたスラブ(床)等のコンクリートは、細断時のクロスコンタミネーションを避けるために表面除染を行った後に細断するものとする。
(4)コンクリート表面のはつり片、粉体は、局所集塵およびはつりエリアのバリア内換気によりほぼ100%回収できるものとする。
(5)はつり作業時の浸透によるクロスコンタミネーション回避のため、液体を用いたはつりは行わないものとする。
Here, in the processing procedure of FIG. 8, the following (1) to (5) are preconditions.
(1) It is assumed that concrete such as slab (floor) in the part to be dismantled has not been activated, and if FP and U adhering to the surface are decontaminated, it will become CL (thing that does not need to be treated as radioactive material). .
(2) With the equipment / piping attached to the slab (floor), the slab (floor) and the equipment / piping are integrally cut out, and the equipment / piping is removed in the indoor work area.
(3) Concrete such as slab (floor) cut out in blocks should be shredded after surface decontamination to avoid cross-contamination during shredding.
(4) The suspended pieces and powder on the concrete surface can be recovered almost 100% by local dust collection and ventilation within the suspended area.
(5) In order to avoid cross-contamination due to permeation at the time of the fishing work, the liquid is not used.

図8のステップS1は、スラブ(床)をブロック状に切断した後、天井クレーンにより揚重し、コンテナ(上屋)内の作業スペース(作業エリア)に移動し、架台上に載せ、スラブ(床)から配管類を撤去するものである。なお、撤去した配管類は後述するステップS3の工程により処理される。   In step S1 of FIG. 8, the slab (floor) is cut into blocks, and then lifted by an overhead crane, moved to a work space (work area) in a container (shed), placed on a gantry, Piping is removed from the floor. The removed piping is processed by the process of step S3 described later.

配管類が撤去されたコンクリートは、架台より地面作業床に降ろされる。続いて、ここにバリアを設置し、コンクリート表側表面をスパイキーハンマーなどのはつり装置ではつる。表裏を反転して裏側表面をはつる。なお、このコンクリート表面のはつり除染により生じる粉体は後述するステップS2の工程により処理される。   The concrete from which the pipes have been removed is lowered from the mount onto the ground work floor. Subsequently, a barrier is installed here, and the surface of the concrete surface is suspended by a lifting device such as a spiky hammer. Flip the front and back sides of the backside surface. In addition, the powder produced by the suspension decontamination of the concrete surface is processed by the step S2 described later.

表面がはつられたコンクリートを細断エリアに移動して、CL検認用容器の収納形状に細断した後、CL検認用容器に収納してCL検認を行う。この後、破砕、粒度調整等の再生処理を行ってから路盤材などに再利用する。   The concrete with the surface moved is moved to a shredding area and shredded into a storage shape for a CL verification container, and then stored in a CL verification container for CL verification. After this, after recycling processing such as crushing and particle size adjustment, it is reused for roadbed materials.

ステップS2は、コンクリート表面の除染により生じたFP、U等の粉体の処理に関するものである。FP、U等の粉体は処分容器に収納され、モルタルを充てんした後、表面線量を測定して一時保管され、最終的に埋設処分される。   Step S2 relates to processing of powders such as FP and U generated by decontamination of the concrete surface. Powders such as FP and U are stored in a disposal container, filled with mortar, temporarily measured by measuring the surface dose, and finally buried.

ステップS3は、汚染配管類の除染処理に関するものであり、ブラストなどの物理的手法や化学的手法により汚染配管類を除染した後、ステップS31、S32の工程に分かれて処理される。ステップS31では、FP、Uの粉体、スラッジを処分容器に収納し、モルタル・砂を充てんした後、表面線量を測定して一時保管され、最終的に埋設処分される。   Step S3 relates to the decontamination processing of the contaminated piping. After decontamination of the contaminated piping by a physical method such as blasting or a chemical method, the processing is divided into steps S31 and S32. In step S31, FP, U powder and sludge are stored in a disposal container, filled with mortar and sand, surface dose is measured, temporarily stored, and finally buried.

ステップS32では、金属母材をガス切断などにより細断し、放射能レベルが比較的低いもの(L2)、放射能レベルが極めて低いもの(L3)、放射性物質として扱う必要のないもの(CL)に分けて処理する。L2については容器収納後、ステップS31に移行してモルタル・砂を充てんした後、表面線量を測定して一時保管され、最終的に埋設処分される。L3については、フレコン(フレキシブルコンテナバッグ)に収納して素堀トレンチ内等に処分される。CLについては、検認容器に収納して検認後、再利用に供される。   In step S32, the metal base material is shredded by gas cutting or the like, and the radioactive level is relatively low (L2), the radioactive level is extremely low (L3), or the radioactive material is not required to be handled (CL) It is divided and processed. About L2, after storing a container, it transfers to step S31 and is filled with mortar and sand, then the surface dose is measured and temporarily stored, and finally buried. About L3, it accommodates in a flexible container (flexible container bag), and is disposed of in an underground trench. The CL is stored in a verification container and reused after verification.

なお、作業エリア18は、図9に示すように、はつりエリア18a、細断エリア18b、容器収納・充てんエリア18c、配管類撤去エリア18d、配管類細断エリア18e、金属容器収納・充てんエリア18fからなる。作業エリア18には、天井クレーン16とは別に作業エリア専用の門型クレーン18gを設けている。また、上屋14の外側の敷地には、充てんモルタルなどを製造するエリア46を設けている。   As shown in FIG. 9, the work area 18 includes a fishing area 18a, a shredding area 18b, a container storage / filling area 18c, a piping removal area 18d, a piping shredding area 18e, a metal container storing / filling area 18f. Consists of. In addition to the overhead crane 16, a portal crane 18g dedicated to the work area is provided in the work area 18. Further, an area 46 for producing filling mortar and the like is provided on the site outside the roof 14.

このように、本発明によれば、建屋からコンクリートを大判のブロック状で切り出した後にはつり除染し、その後に細断するため、クロスコンタミネーションの発生が抑制される。これにより、FPおよびUの汚染廃棄物低減が図れる。   As described above, according to the present invention, since concrete is cut out from a building in a large block shape, it is decontaminated and then shredded, so that occurrence of cross contamination is suppressed. Thereby, the contaminated waste of FP and U can be reduced.

[建屋躯体を単独で切り出す場合]
次に、機器・配管類が既に撤去された状態で建屋躯体(床、梁、壁)を単独で切り出す場合について図10〜図13を参照しながら説明する。なお、図10〜図12の各図において(1)は平面断面図、(2)は正面断面図である。
[When cutting out the building frame alone]
Next, a case where a building frame (floor, beam, wall) is cut out alone with the devices and piping already removed will be described with reference to FIGS. In addition, in each figure of FIGS. 10-12, (1) is a plane sectional view, (2) is a front sectional view.

まず、図10に示すように、床36上の複数個所にエポキシアンカーなどのアンカーボルト44を取り付け、アンカーボルト44を介して天井クレーン16で吊り上げた状態にする。次いで、床36と壁40および梁38との境界部分36aを切断位置として、図示しないワイヤーソー装置等を遠隔操作して床36を切断する。そして、切り出したブロック状の床36を天井クレーン16で揚重して撤去する。   First, as shown in FIG. 10, anchor bolts 44 such as epoxy anchors are attached to a plurality of locations on the floor 36 and are lifted by the overhead crane 16 via the anchor bolts 44. Next, the floor 36 is cut by remotely operating a wire saw device (not shown) with the boundary portion 36a between the floor 36 and the wall 40 and the beam 38 as a cutting position. Then, the block-shaped floor 36 cut out is lifted by the overhead crane 16 and removed.

同様にして、図11に示すように、梁38を天井クレーン16で吊り上げた状態としておき、前後端部38aを切断位置として切断後、揚重して撤去する。   Similarly, as shown in FIG. 11, the beam 38 is lifted by the overhead crane 16, and the front and rear end portions 38 a are cut at the cutting position, and then lifted and removed.

次に、図12に示すように、壁40を天井クレーン16で吊り上げた状態としておき、下端部および側端部40aを切断位置として切断後、揚重して撤去する。   Next, as shown in FIG. 12, the wall 40 is lifted by the overhead crane 16, and the lower end and the side end 40a are cut at the cutting position, and then lifted and removed.

撤去したブロック状の床36(スラブ)、梁38、壁40は、それぞれ天井クレーン16により作業エリア18のはつりエリア18aに運搬され、そのコンクリート表面はスパイキーハンマーなどのはつり装置48ではつり取られる。このエリアにおけるこの後の処理手順については、図14に例示するように、ステップS1、S2の各工程を経たものとなる。   The removed block-like floor 36 (slab), beam 38, and wall 40 are respectively transported to the suspension area 18a of the work area 18 by the overhead crane 16, and the concrete surface thereof is suspended by a suspension device 48 such as a spiky hammer. Subsequent processing procedures in this area are performed through steps S1 and S2, as illustrated in FIG.

ここで、図14の処理手順においては、以下の(1)〜(4)を前提条件としている。
(1)解体対象部位のスラブ(床)等のコンクリートは放射化していないものとし、表面に付着したFP、Uを除染すればCL(放射性物質として扱う必要のないもの)になるものとする。
(2)ブロック状に切り出されたスラブ(床)等のコンクリートは、細断時のクロスコンタミネーションを避けるために表面除染を行った後に細断するものとする。
(3)コンクリート表面のはつり片、粉体は、局所集塵およびはつりエリアのバリア内換気によりほぼ100%回収できるものとする。
(4)はつり作業時の浸透によるクロスコンタミネーション回避のため、液体を用いたはつりは行わないものとする。
Here, in the processing procedure of FIG. 14, the following (1) to (4) are preconditions.
(1) It is assumed that concrete such as slab (floor) in the part to be dismantled has not been activated, and if FP and U adhering to the surface are decontaminated, it will become CL (thing that does not need to be treated as radioactive material). .
(2) Concrete such as slab (floor) cut out in blocks should be shredded after surface decontamination to avoid cross-contamination during shredding.
(3) The suspended pieces and powder on the concrete surface can be recovered almost 100% by local dust collection and ventilation within the suspended area.
(4) In order to avoid cross-contamination due to permeation during the suspending operation, suspending using liquid is not performed.

図14のステップS1では、スラブ(床)をブロック状に切断した後、天井クレーンにより揚重し、コンテナ(上屋)内の作業スペース(作業エリア)に移動し、ここにバリアを設置し、コンクリート表側表面をスパイキーハンマーなどのはつり装置ではつる。表裏を反転して裏側表面をはつる。なお、このコンクリート表面のはつり除染により生じる粉体は後述するステップS2の工程により処理される。   In step S1 of FIG. 14, after cutting the slab (floor) into blocks, the slab is lifted by an overhead crane, moved to a work space (work area) in a container (shed), and a barrier is installed here. The surface of the concrete is suspended by a lifting device such as a spiky hammer. Flip the front and back sides of the backside surface. In addition, the powder produced by the suspension decontamination of the concrete surface is processed by the step S2 described later.

表面がはつられたコンクリートを細断エリアに移動して、CL検認用容器の収納形状に細断した後、CL検認用容器に収納してCL検認を行う。この後、破砕、粒度調整等の再生処理を行ってから路盤材などに再利用する。   The concrete with the surface moved is moved to a shredding area and shredded into a storage shape for a CL verification container, and then stored in a CL verification container for CL verification. After this, after recycling processing such as crushing and particle size adjustment, it is reused for roadbed materials.

ステップS2は、コンクリート表面の除染により生じたFP、U等の粉体の処理に関するものである。FP、U等の粉体は処分容器に収納され、モルタルを充てんした後、表面線量を測定して一時保管され、最終的に埋設処分される。   Step S2 relates to processing of powders such as FP and U generated by decontamination of the concrete surface. Powders such as FP and U are stored in a disposal container, filled with mortar, temporarily measured by measuring the surface dose, and finally buried.

(建屋躯体を切り出す際の支保工および吊り治具)
次に、建屋躯体を切り出す際に用いる支保工および吊り治具の構成および作用について図15〜図17を参照しながら説明する。なお、図15〜図17の各図において(1)は平面図、(2)は正面断面図である。
(Support and hanging jig when cutting out the building frame)
Next, the structure and operation of the support and suspension jig used when cutting out the building frame will be described with reference to FIGS. In addition, in each figure of FIGS. 15-17, (1) is a top view, (2) is front sectional drawing.

図15に示すように、床36(スラブ)上にコアボーリング装置50(穿孔手段)を配置し、床36の外周側に複数の貫通穴52を設ける。この貫通穴52は支保工設置用のものであり、その径は例えばφ200mm程度、設置ピッチは例えば2m程度としてよい。なお、コアボーリング装置50は建屋12の外部から遠隔操作する。   As shown in FIG. 15, the core boring device 50 (perforating means) is disposed on the floor 36 (slab), and a plurality of through holes 52 are provided on the outer peripheral side of the floor 36. The through holes 52 are for support installation, and the diameter thereof may be about φ200 mm and the installation pitch may be about 2 m, for example. The core boring device 50 is remotely operated from outside the building 12.

次に、図16(1)、(2)に示すように、柱状の支保工54を貫通穴52の上方から天井クレーン16で挿入し床36下面と下階の床37上面との間に配置する。この支保工54の径は、例えば貫通穴52よりも小径のφ150mm程度としてよい。   Next, as shown in FIGS. 16 (1) and (2), a columnar support 54 is inserted from above the through hole 52 with the overhead crane 16 and placed between the lower surface of the floor 36 and the upper surface of the floor 37 of the lower floor. To do. The diameter of the support work 54 may be, for example, about φ150 mm, which is smaller than the through hole 52.

ここで、支保工54は、遠隔操作により自身の長さを自動的に伸長する図示しない自動伸長手段と、上部拡幅手段とが備わっており、自動で床36、37間に固定される。図16(3)の要部拡大図に示すように、上部拡幅手段は、棒状部54aに設けた軸部54bと、軸部54bに頂点を回転自在に取り付けられた直角三角形状のロック片54cとからなり、ロック片54cは貫通穴52を通り抜けた際に開いて床36下面と当接状態となる。なお、この上部拡幅手段は、傘における止め金等の他の手段で構成してもよい。また、支保工54の上端には、貫通穴52より大径の突起部54dが設けてあり貫通穴52に入らないようになっている。支保工54を壁40近辺に複数配置することで、床36の荷重は支保工54を介して一時的に下階の床37に伝達されることになる。   Here, the support work 54 is provided with an automatic extension means (not shown) that automatically extends its length by a remote operation and an upper widening means, and is automatically fixed between the floors 36 and 37. As shown in the enlarged view of the main part of FIG. 16 (3), the upper widening means includes a shaft portion 54b provided on the rod-shaped portion 54a and a right-triangular lock piece 54c whose vertex is rotatably attached to the shaft portion 54b. The lock piece 54c opens when passing through the through hole 52 and comes into contact with the lower surface of the floor 36. In addition, you may comprise this upper widening means with other means, such as a clasp in an umbrella. Further, a protrusion 54 d having a diameter larger than that of the through hole 52 is provided at the upper end of the support work 54 so that the support work 54 does not enter the through hole 52. By arranging a plurality of support works 54 in the vicinity of the wall 40, the load on the floor 36 is temporarily transmitted to the floor 37 on the lower floor via the support work 54.

次に、図17(1)、(2)に示すように、床36(スラブ)の中央側に複数の貫通穴56を設ける。この貫通穴56は吊り治具設置用のものであり、その径は例えばφ100mm程度としてよい。なお、貫通穴56は貫通穴52と同時期に設けてもよい。そして、天井クレーン16を用いて貫通穴56に吊り治具58を挿入し、床36に取り付ける。   Next, as shown in FIGS. 17 (1) and (2), a plurality of through holes 56 are provided on the center side of the floor 36 (slab). The through hole 56 is for installing a lifting jig, and the diameter thereof may be about φ100 mm, for example. The through hole 56 may be provided at the same time as the through hole 52. Then, the suspension jig 58 is inserted into the through hole 56 using the overhead crane 16 and attached to the floor 36.

ここで、吊り治具58は、図17(3)の正面図、(4)の側面図に示すように、胴部58aと、胴部58aの下部に設けられ、軸58d周りに回転するアゴ部58bを進退自在に格納する長孔58cとを備える。また、胴部58aの上部には天井クレーン用のフック係合孔58eと、突起部58fとが設けてある。アゴ部58bが吊り治具58の下部を拡幅する下部拡幅手段として機能する。   Here, as shown in the front view of FIG. 17 (3) and the side view of FIG. 17 (4), the suspension jig 58 is provided on the barrel portion 58a and the lower portion of the barrel portion 58a and rotates around the shaft 58d. And a long hole 58c for retracting and retracting the portion 58b. A hook engaging hole 58e for an overhead crane and a protrusion 58f are provided on the upper portion of the body portion 58a. The jaw portion 58b functions as a lower widening means for widening the lower portion of the hanging jig 58.

図17(3)は、アゴ部58bが回転して長孔58cから突出した状態を示している。通常時にこの状態でバランスするようにバネ等を用いて構成しておけば、長孔58c内にアゴ部58bを格納した状態で吊り治具58を貫通穴56に挿入すると、アゴ部58bは自動的に回転および突出して吊り治具58の下部を拡幅する。これにより、アゴ部58bが床36下面に当接した状態となり床荷重を物理的に受けることができる。このため、アンカーを用いた場合のように引抜けるおそれはない。   FIG. 17 (3) shows a state in which the jaw portion 58b rotates and protrudes from the long hole 58c. If it is configured using a spring or the like so as to balance in this state at normal time, when the hanging jig 58 is inserted into the through hole 56 with the jaw portion 58b stored in the elongated hole 58c, the jaw portion 58b is automatically Thus, the lower part of the hanging jig 58 is widened by rotating and projecting. Thereby, it becomes the state which the jaw part 58b contact | abutted to the floor 36 lower surface, and can receive a floor load physically. For this reason, there is no possibility of pulling out unlike the case where an anchor is used.

続いて、図17(1)、(2)に示すように、床36と壁40および梁38との境界部分36aを切断位置として、図示しないワイヤーソー装置等を遠隔操作して床36を切断する。切り出した床36を吊り治具58を介して天井クレーン16で揚重して運搬する。このような手順により、天井クレーン16を支保工として占有することなく床36(スラブ)を撤去することができる。   Subsequently, as shown in FIGS. 17 (1) and 17 (2), the floor 36 is cut by remotely operating a wire saw device (not shown) with the boundary portion 36a between the floor 36 and the wall 40 and the beam 38 as a cutting position. To do. The cut out floor 36 is lifted and transported by the overhead crane 16 through the hanging jig 58. By such a procedure, the floor 36 (slab) can be removed without occupying the overhead crane 16 as a supporting work.

なお、本発明では、作業員が解体エリアに長時間滞在できない、あるいは、アクセスが困難な建屋を対象としており、基本的に建屋で行う全ての作業は遠隔装置に対する遠隔操作による。ここで、遠隔装置を採用しない場合には、例えば解体エリアの空間線量が下がるまで極めて長期間放置する必要があり現実的ではない。また、人が近寄れるようにするために躯体表面や機器表面・内部の除染作業が必要となるが、この除染作業も遠隔装置によらなければ工期が長期化しコストが膨大になるおそれがあるという問題がある。   In the present invention, the building is intended for a building where workers cannot stay in the dismantling area for a long time or is difficult to access, and basically all work performed in the building is performed by remote control of a remote device. Here, when the remote device is not employed, it is necessary to leave the apparatus for a very long time until the air dose in the dismantling area is lowered, which is not practical. In addition, decontamination work on the housing surface, equipment surface, and inside is required to allow people to approach, but if this decontamination work is not performed by a remote device, the construction period may be prolonged and the cost may be enormous. There is a problem that there is.

以上説明したように、本発明によれば、放射能汚染された施設の建屋を覆うようにこの外周に上屋を新設するとともに、この上屋の中に揚重手段を設置し、この上屋の中で前記建屋躯体の解体、除染、細断、容器収納の一連の作業を行う放射能汚染施設の解体方法であって、遠隔操作により前記建屋躯体をブロック状に切り出して、前記建屋の上方から下方に向けて順次解体し、切り出したブロック状の前記建屋躯体を前記揚重手段で揚重して前記上屋内に設けた汚染度が前記建屋よりも低い作業エリアに運搬して、この作業エリアで除染するようにしたので、作業員が建屋躯体の解体エリアに立ち入らずに施設の建屋を短期間で解体することができ、作業員の被曝に対する安全性の確保が可能である。   As described above, according to the present invention, a new shed is installed on the outer periphery so as to cover the building of the radioactively contaminated facility, and a lifting means is installed in the shed. A decontamination method of a radioactive contamination facility that performs a series of operations of dismantling, decontamination, shredding, and container storage of the building enclosure, cutting the building enclosure into a block shape by remote operation, Dismantled sequentially from the top to the bottom, the cut block-shaped building frame is lifted by the lifting means and transported to a work area having a lower pollution level than the building, Since decontamination is performed in the work area, the facility building can be dismantled in a short period of time without the worker entering the building demolition area, and safety against exposure of the worker can be ensured.

以上のように、本発明に係る放射能汚染施設の解体方法は、作業員が解体エリアに立ち入らずに施設を短期間で解体するのに有用であり、特に、作業員の被曝に対する安全性を確保するのに適している。   As described above, the method for dismantling a radioactive contamination facility according to the present invention is useful for dismantling the facility in a short period of time without the worker entering the dismantling area. Suitable for securing.

10 原子力発電施設(放射能汚染施設)
12 建屋
14 上屋
16 天井クレーン(揚重手段)
18 作業エリア
20 鉄骨柱
22 SC壁
24 止水壁
26 地盤改良体
28 タンク(機器類)
30,32 配管類
34 レール
36 床(建屋躯体、スラブ)
37 下階の床(下階のスラブ)
38 梁(建屋躯体)
40 壁(建屋躯体)
42 開口
44 アンカーボルト
46 エリア
48 はつり装置
50 コアボーリング装置(穿孔手段)
52,56 貫通穴
54 支保工
54c ロック片(上部拡幅手段)
58 吊り治具
58b アゴ部(下部拡幅手段)
GL 地表面
10 Nuclear power generation facilities (radioactive contamination facilities)
12 building 14 roof 16 overhead crane (lifting means)
18 Work area 20 Steel column 22 SC wall 24 Water blocking wall 26 Ground improvement body 28 Tank (equipment)
30, 32 Piping 34 Rail 36 Floor (Building frame, slab)
37 Lower floor (lower slab)
38 Liang (building enclosure)
40 walls (building enclosure)
42 Opening 44 Anchor bolt 46 Area 48 Lifting device 50 Core boring device (drilling means)
52, 56 Through hole 54 Support work 54c Lock piece (upper widening means)
58 Suspension jig 58b Jaw part (lower widening means)
GL Ground surface

Claims (4)

放射能汚染された施設の建屋を覆うようにこの外周に上屋を新設するとともに、この上屋の中に揚重手段を設置し、この上屋の中で前記建屋躯体の解体、除染、細断、容器収納の一連の作業を行う放射能汚染施設の解体方法であって、
遠隔操作により前記建屋躯体をブロック状に切り出して、前記建屋の上方から下方に向けて順次解体し、切り出したブロック状の前記建屋躯体を前記揚重手段で揚重して前記上屋内に設けた汚染度が前記建屋よりも低い作業エリアに運搬して、この作業エリアで除染するようにしたことを特徴とする放射能汚染施設の解体方法。
In addition to installing a new shed on the outer periphery to cover the building of the radioactively contaminated facility, a lifting means is installed in the shed, and the building housing is dismantled, decontaminated, A method of dismantling a radioactive contamination facility that performs a series of operations such as shredding and container storage,
The building housing was cut out into a block shape by remote operation, and was sequentially disassembled from the top to the bottom of the building, and the cut-out building housing was lifted by the lifting means and provided in the upper indoor area. A method for dismantling a radioactively contaminated facility, characterized in that it is transported to a work area having a pollution level lower than that of the building and decontaminated in this work area.
前記建屋躯体と、前記建屋躯体に既設の機器・配管類とを一体的に切り出すことを特徴とする請求項1に記載の放射能汚染施設の解体方法。   The method for dismantling a radioactive contamination facility according to claim 1, wherein the building housing and the equipment and piping existing in the building housing are cut out integrally. 前記建屋躯体をなすスラブ上に設けた穿孔手段を遠隔操作して前記スラブに貫通穴を設け、この貫通穴の上方から自動伸長手段および上部拡幅手段を備える柱状の支保工を挿入して前記スラブ下面と下階のスラブ上面との間に配置し、前記支保工を介して前記スラブの荷重を一時的に下階のスラブに支持させた後、前記スラブを切り出すことを特徴とする請求項1または2に記載の放射能汚染施設の解体方法。   A piercing means provided on the slab constituting the building frame is remotely operated to provide a through hole in the slab, and a columnar supporter having an automatic extension means and an upper widening means is inserted from above the through hole to insert the slab. 2. It arrange | positions between a lower surface and the slab upper surface of a lower floor, The load of the said slab is temporarily supported by the slab of a lower floor via the said support work, The said slab is cut out, It is characterized by the above-mentioned. Or the dismantling method of the radioactive contamination facility of 2. 前記穿孔手段を遠隔操作して前記スラブに貫通穴を設け、この貫通穴の上方から下部拡幅手段を備える吊り治具を挿入して前記スラブに取り付けておき、切り出した前記スラブを前記吊り治具を介して前記揚重手段で揚重することを特徴とする請求項3に記載の放射能汚染施設の解体方法。   The piercing means is remotely operated to provide a through hole in the slab, a suspension jig having a lower widening means is inserted from above the penetration hole and attached to the slab, and the cut slab is attached to the suspension jig. The method for dismantling a radioactively contaminated facility according to claim 3, wherein the lifting is performed by the lifting means.
JP2012047266A 2012-03-02 2012-03-02 How to dismantle radioactive contamination facilities Active JP5787174B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012047266A JP5787174B2 (en) 2012-03-02 2012-03-02 How to dismantle radioactive contamination facilities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012047266A JP5787174B2 (en) 2012-03-02 2012-03-02 How to dismantle radioactive contamination facilities

Publications (2)

Publication Number Publication Date
JP2013181921A true JP2013181921A (en) 2013-09-12
JP5787174B2 JP5787174B2 (en) 2015-09-30

Family

ID=49272651

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012047266A Active JP5787174B2 (en) 2012-03-02 2012-03-02 How to dismantle radioactive contamination facilities

Country Status (1)

Country Link
JP (1) JP5787174B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017067754A (en) * 2015-09-29 2017-04-06 日立Geニュークリア・エナジー株式会社 Demolition method of reactor building

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6229676A (en) * 1985-07-29 1987-02-07 清水建設株式会社 Method and apparatus for disassembling wall like structure
JPS6466370A (en) * 1987-09-07 1989-03-13 Kajima Corp Method of removing contaminated piping of nuclear reactor facility
JPS6466599A (en) * 1987-09-07 1989-03-13 Kajima Corp Method for disassembling reactor building
JPH0673899A (en) * 1992-08-24 1994-03-15 Toda Constr Co Ltd Wrecking method of radioactive contaminated nuclear facility
JP2006225949A (en) * 2005-02-17 2006-08-31 Takenaka Komuten Co Ltd Demolition method of building

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6229676A (en) * 1985-07-29 1987-02-07 清水建設株式会社 Method and apparatus for disassembling wall like structure
JPS6466370A (en) * 1987-09-07 1989-03-13 Kajima Corp Method of removing contaminated piping of nuclear reactor facility
JPS6466599A (en) * 1987-09-07 1989-03-13 Kajima Corp Method for disassembling reactor building
JPH0673899A (en) * 1992-08-24 1994-03-15 Toda Constr Co Ltd Wrecking method of radioactive contaminated nuclear facility
JP2006225949A (en) * 2005-02-17 2006-08-31 Takenaka Komuten Co Ltd Demolition method of building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017067754A (en) * 2015-09-29 2017-04-06 日立Geニュークリア・エナジー株式会社 Demolition method of reactor building

Also Published As

Publication number Publication date
JP5787174B2 (en) 2015-09-30

Similar Documents

Publication Publication Date Title
Jeong et al. A qualitative identification and analysis of hazards, risks and operating procedures for a decommissioning safety assessment of a nuclear research reactor
JP5787174B2 (en) How to dismantle radioactive contamination facilities
RU2444796C1 (en) Method for removing channel uranium-graphite nuclear reactor from service
KR101473711B1 (en) Underground excavation method of constructing underground structure for radioactive waste storage
Baumgartner et al. Engineering for a disposal facility using the in-room emplacement method
EP1517337B1 (en) Method for disposing of power station facility directly below the original location
Laraia Case studies and lessons learned from decontamination, demolition, and managing the produced wastes
JP6480365B2 (en) Reactor building demolition method
Kirby Brookhaven Graphite Research Reactor (BGRR) D&D Project—11243
KR102116379B1 (en) Method for processing a nuclear reactor
JPS6231144B2 (en)
Laraia Entombment: A Viable Decommissioning Strategy for Research Reactors?
JP6975676B2 (en) Dismantling method of reactor containment vessel and biological shielding wall
Kuznetsov et al. Decommissioning of Research Building B at VNIINM: Main Results
Heystee Proposed deep geologic repository for low and intermediate-level radioactive waste at the Bruce site, Tiverton, Ontario
JP2001116876A (en) Nuclear reactor building structure
Laraia Dismantling and demolition techniques for cementitious systems
Wall et al. Retrieval of Intermediate Level Waste at Trawsfyndd Nuclear Power Station
Engovatov et al. Providing rationale for the possibility of decommissioning Bilibino nuclear cogeneration plant based on the onsite disposal option
Tachibana Experiences on Research Reactors Decommissioning in the NSRI of the JAEA
Brown et al. Completion of the decommissioning of a former active handling building at UKAEA Winfrith
JP2020180821A (en) Disposal tunnel structure of radioactive waste, manufacturing method for disposal tunnel structure, and maintenance method for disposal tunnel structure
Miller et al. Development of decommissioning techniques on a major nuclear facility at UKAEA Winfrith
Endsley Saxton Nuclear Experimental Corporation, Containment Vessel (CV) Concrete Removal: Decommissioning in a Flood Plan
Villagran et al. Used Fuel Container Retrieval from a Deep Geological Repository in

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140730

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20150526

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150527

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20150608

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150623

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150715

R150 Certificate of patent or registration of utility model

Ref document number: 5787174

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150