JP2013044126A - Track deviation repair method for track - Google Patents

Track deviation repair method for track Download PDF

Info

Publication number
JP2013044126A
JP2013044126A JP2011181461A JP2011181461A JP2013044126A JP 2013044126 A JP2013044126 A JP 2013044126A JP 2011181461 A JP2011181461 A JP 2011181461A JP 2011181461 A JP2011181461 A JP 2011181461A JP 2013044126 A JP2013044126 A JP 2013044126A
Authority
JP
Japan
Prior art keywords
track
anchor
ballast
filling layer
filler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2011181461A
Other languages
Japanese (ja)
Inventor
Takeshi Inoue
武 井上
Hajime Ozawa
元 小澤
Masao Nihei
正夫 仁瓶
Sadao Tsukano
定雄 塚野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KFC Ltd
Original Assignee
KFC Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KFC Ltd filed Critical KFC Ltd
Priority to JP2011181461A priority Critical patent/JP2013044126A/en
Publication of JP2013044126A publication Critical patent/JP2013044126A/en
Withdrawn legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To eliminate the need of heavy machines and wedges, to eliminate the need of installing/pulling out a mold form, to reduce work time/work days, and to efficiently and highly accurately correct track deviation.SOLUTION: A track deviation repair method for a track includes respective steps of: a) installing a plurality of anchors 28 for lift-up on an upper surface of a filling layer 4 for which a crosstie 2 and ballast 3 are solidified; b) installing a portal track lifting jig 10 which is supported at both ends by a ballast layer 3 on an outer side of the filling layer 4 and traverses a track 1 and the anchors 28; c) finely adjusting a track height by pulling up the anchors 28 with jacks 16 and 42 provided on the track lifting jig 10 and floating the filling layer 4 from the ballast 3; and d) packing a filler in a gap formed between the ballast 3 and the filling layer 4.

Description

この発明は、軌道狂い(沈下)した省力化軌道やスラブ軌道の軌道狂いを修正しかつ軌道を安定化させるための軌道の軌道狂い補修方法に関するものである。   The present invention relates to a trajectory error repair method for correcting a trajectory error of a labor-saving trajectory or a slab trajectory that has a trajectory error (sinking) and stabilizing the trajectory.

鉄道線路の保守作業を省力化するための省力化軌道が広く用いられている。既設の土路盤上又はコンクリート路盤上に道床バラストを敷き、その上にまくら木を敷設し、このまくら木にレール(軌道)を締結する構造となっている。しかし列車通過に伴ってレール面が沈下し、その結果生じた軌道狂いの修復に保守を要することが避けられない。そこでこの保守作業を省力化するため、省力化軌道とすることが従来から行われている。   Labor-saving tracks are widely used to save labor on maintenance work on railway tracks. A roadbed ballast is laid on an existing earth roadbed or a concrete roadbed, a sleeper is laid on the ballast, and a rail (track) is fastened to the sleeper. However, the rail surface sinks as the train passes, and it is inevitable that maintenance is required to repair the resulting track error. Therefore, in order to save labor for this maintenance work, it has been conventionally performed to use a labor saving track.

図23は従来の省力化軌道の断面構造の一例を示す図、図24は作業工程の一例を示す図である。この図23において符号1は左右一対のレール(軌道)、2はまくら木、3はバラストである。バラスト3はまくら木2の下方および周囲が固化剤など固めた填充層4となっている。すなわちこの省力化軌道では、旧道床バラストを所定厚さまで掘削して表面を転圧した後、その上面に不織布を敷いてその上に豆砕石を散布・転圧し、さらにその上にまくら木とレールとを固定してなる軌匡を組み、不織布から上部に硬化剤を注入して固めることによって填充層4とした構造を持つ。またバラスト3の表面と側部にアスコン舗装5を行っている。   FIG. 23 is a diagram illustrating an example of a cross-sectional structure of a conventional labor-saving track, and FIG. 24 is a diagram illustrating an example of a work process. In FIG. 23, reference numeral 1 is a pair of left and right rails (tracks), 2 is a sleeper, and 3 is a ballast. The ballast 3 is a filling layer 4 in which the lower part and the periphery of the sleeper tree 2 are hardened such as a solidifying agent. That is, in this labor-saving track, after excavating the old roadbed ballast to a predetermined thickness and rolling the surface, spread the non-woven fabric on the upper surface, spray and roll the crushed stone on it, and further sleeper trees and rails on it A structure in which the filler layer 4 is formed by assembling the rails formed by fixing and hardening and injecting a curing agent into the upper part from the nonwoven fabric. In addition, ascon pavement 5 is performed on the surface and side of the ballast 3.

特許文献1には、レールの沈下を防止するために、填充層の直下の道床バラストに安定化材を散布又は注入し固化することが記載されている。この安定化材の注入のために、不織布に前もって安定化材漏洩用の穴を空けておいたり、不織布の一部をメッシュ状にしたり、不織布直下のバラスト内に前もって孔あき管を挿入しておき仮軌道敷設後に安定化材を注入できるようにすることなどが提案されている。   Patent Document 1 describes that a stabilizing material is sprayed or injected into a roadbed ballast immediately below a filling layer in order to prevent the rail from sinking, and is solidified. In order to inject the stabilizer, a hole for leakage of the stabilizer is made in advance in the nonwoven fabric, a part of the nonwoven fabric is meshed, or a perforated tube is inserted in advance into the ballast directly under the nonwoven fabric. It has been proposed that the stabilizer can be injected after the temporary track has been laid.

また特許文献2には、特に新設軌道の場合に初期の軌道沈下を防止するために、まくら木と路盤の間に可撓性袋体を介在させ、この可撓性袋体に中詰め材を圧送充填することにより路盤に外圧を与え、この外圧によって路盤を先行的に圧密沈下させることが記載されている。この結果、その後に列車加重が加わっても路盤の沈下量を減少させることができるというものである。   Patent Document 2 discloses that a flexible bag is interposed between a sleeper and a roadbed in order to prevent initial settlement of the track, particularly in the case of a new track, and the filling material is pumped into the flexible bag. It is described that an external pressure is applied to the roadbed by filling and the roadbed is preliminarily consolidated by this external pressure. As a result, the subsidence amount of the roadbed can be reduced even if the train weight is applied thereafter.

またコンクリートスラブを用いるスラブ軌道においても、コンクリート路盤が地盤の変動などによって変位し、軌道補正が必要になることもある。この場合には従来は、コンクリートスラブの4隅と路盤との間に手動ジャッキを挿入し、全てのジャッキを同期させて駆動してコンクリートスラブを路盤からこう上させ、くさび(楔)などで高さを維持した状態でジャッキを外し、充填剤をコンクリートと路盤の間に充填していた。   Even in a slab track using a concrete slab, the concrete roadbed may be displaced due to changes in the ground and the track correction may be required. In this case, in the past, manual jacks were inserted between the four corners of the concrete slab and the roadbed, and all the jacks were driven in synchronism to drive the concrete slab above the roadbed. In this state, the jack was removed and the filler was filled between the concrete and the roadbed.

特開平6−108401JP-A-6-108401 特開平8−74202JP-A-8-74202

しかし特許文献1、2に記載されたものは、いずれもレールの沈下(軌道狂い)を防止するあるいは沈下量を減少させるものである。しかし実際の保守作業においては、レールを引き上げることが必要なことがある。大重量の列車が頻繁に通る範囲や、土路盤が柔軟な範囲、レールの継ぎ目付近で衝撃が大きい範囲などでは、隣接する他の範囲よりもレールの沈下が大きくなり、レールを引き上げる(こう上する、リフトアップする)ことが必要になる。   However, those described in Patent Documents 1 and 2 both prevent rail subsidence (track misalignment) or reduce the amount of subsidence. However, in actual maintenance work, it may be necessary to raise the rail. In areas where heavy trains frequently pass, areas where the roadbed is flexible, and where there is a large impact near the rail joints, rail subsidence will be larger than other adjacent areas, and the rails will be pulled up. To lift up).

そこで填充層の両側のバラストを掘り下げて(図24の工程A)、填充層の両側下方にジャッキを挿入し(工程B)、所定のレール高さに調整して填充層の高さを保持し、充填剤(フィルコン材、スラリー状セメント系注入剤、グラウトなど)を注入することが考えられる。しかしこの場合にはジャッキで高さ調整した後(工程B)、填充層の下にくさびを打ち込んで填充層を保持し(工程C)、さらに填充層の周囲に型枠を設置して(工程D)からフィルコン材などの充填材を注入する(工程E)必要がある。このため充填材の硬化まで型枠を設置したまま養生する必要がある(工程F)だけでなく、充填層の周囲の掘り下げ(工程A)や埋め戻し(工程G)にバックホーなどの重機が必要になり、型枠の設置・撤去(工程D、G)などに多くの作業時間・作業日数(通常3日程度)が必要になる。このため作業が大がかりで効率が悪いという問題がある。   Therefore, the ballast on both sides of the filling layer is dug down (step A in FIG. 24), jacks are inserted below both sides of the filling layer (step B), and the height of the filling layer is maintained by adjusting to a predetermined rail height. It is conceivable to inject a filler (such as a filcon material, a slurry-like cement-type injection agent, and grout). However, in this case, after adjusting the height with a jack (step B), a wedge is driven under the filling layer to hold the filling layer (step C), and a mold is installed around the filling layer (step). It is necessary to inject a filler such as a filcon material from (D) (step E). For this reason, it is necessary to cure with the formwork installed until the filler is cured (process F), and heavy equipment such as a backhoe is required for digging around the packed bed (process A) and backfilling (process G). Therefore, a lot of work time and work days (usually about 3 days) are required for installation and removal of the formwork (processes D and G). For this reason, there is a problem that the work is large and the efficiency is low.

さらに填充層をジャッキで持ち上げる際には、填充層の両端が押し上げられるので、その中央付近が低くなるように湾曲するのが避けられない。このため、レール高さが補修終了後に変化することになり、軌道狂いが不正確になりやすいという問題もある。   Further, when the filling layer is lifted with a jack, both ends of the filling layer are pushed up, so that it is inevitable that the vicinity of the center is lowered. For this reason, the rail height changes after completion of repair, and there is also a problem that the track error tends to be inaccurate.

一方、スラブ軌道ではスラブと路盤との間に入れる複数のジャッキを同期駆動する必要があるため多数の作業者が必要で作業能率も悪い。また充填材を注入するためには、スラブの側面を型枠などで囲む必要があり、作業能率は一層悪くなる。さらにコンクリートスラブは弾性がないので全体を同時にこう上する必要があり、作業が大規模になる。   On the other hand, in the slab track, it is necessary to synchronously drive a plurality of jacks inserted between the slab and the roadbed, so that a large number of workers are required and the work efficiency is poor. Further, in order to inject the filler, it is necessary to surround the side surface of the slab with a mold or the like, and the work efficiency is further deteriorated. Furthermore, since the concrete slab is not elastic, it is necessary to raise the whole at the same time, and the work becomes large-scale.

この発明はこのような事情に鑑みなされたものであり、バックホーなどの重機やくさびが不要であり、型枠の設置・撤収が不要であり、作業時間・作業日数は減らして能率良くかつ高精度に軌道狂いを修正することができる省力化軌道の軌道狂い補修方法を提供することを目的とする。またスラブ軌道における軌道狂い補修方法を提供することを目的とする。   The present invention has been made in view of such circumstances, and does not require a heavy machine such as a backhoe or a wedge, does not require installation / removal of a formwork, reduces work time and work days, and is efficient and highly accurate. It is an object of the present invention to provide a labor-saving track trajectory repair method that can correct track trajectory. It is another object of the present invention to provide a method for repairing a track error in a slab track.

この発明によれば省力化軌道における前記の目的は、バラストとまくら木を固結した構造の省力化軌道の軌道狂い補修方法において、a)前記まくら木とバラストを固めた填充層の上面にリフトアップ用の複数のアンカーを設置する;b)前記填充層の外側でバラスト層に両端が支持され軌道および前記アンカーを横断する門型のこう上治具を設置する;c)前記アンカーを前記こう上治具に設けたジャッキによって引き上げ、前記填充層をバラストから浮かせることによって軌道高さを微調整する;d)バラストと填充層との間にできる間隙に充填材を充填する;以上の各工程を有する省力化軌道の軌道狂い補修方法、により達成される。   According to the present invention, the above-described object in the labor-saving track is a method for repairing the track error in the labor-saving track of the structure in which the ballast and the sleeper are consolidated, and a) for lifting up on the upper surface of the filling layer in which the sleeper and the ballast are consolidated B) installing a portal-type raising jig that is supported at both ends by the ballast layer outside the filling layer and traverses the track and the anchor; c) The height of the orbit is finely adjusted by pulling up with a jack provided on the tool and floating the filling layer from the ballast; d) filling the filler in the gap formed between the ballast and the filling layer; This is achieved by a labor-saving track trajectory repair method.

またスラブ軌道における前記の目的は、コンクリートスラブに軌道を固定したスラブ軌道の軌道狂い補修方法において、
a′)前記コンクリートスラブの上面にリフトアップ用の複数のアンカーを設置する;
b′)前記コンクリートスラブの外側で路盤に両端が支持され軌道および前記アンカーを横断する門型のこう上治具を設置する;
c′)前記アンカーを前記こう上治具に設けたジャッキによって引き上げ、前記コンクリートスラブを路盤から浮かせることによって軌道高さを微調整する;
d′)路盤とコンクリートスラブとの間にできる間隙に充填材を充填する;
以上の各工程を有するスラブ軌道の軌道狂い補修方法、により達成される。
In addition, the above-mentioned purpose in the slab track is a method for repairing the track error of the slab track in which the track is fixed to the concrete slab.
a ') installing a plurality of lift-up anchors on the upper surface of the concrete slab;
b ') installing a portal-type uplifting jig that is supported by the roadbed outside the concrete slab and that crosses the track and the anchor;
c ′) The anchor is lifted by a jack provided on the upper jig, and the concrete slab is lifted from the roadbed to finely adjust the track height;
d ') Filling the gap created between the roadbed and the concrete slab;
This is achieved by a method for repairing a track slab track having the above steps.

省力化軌道の場合には、填充層にリフト用のアンカーを固定し、このアンカーを填充層の外側に支持するこう上治具に設けたジャッキによって引き上げるので、填充層をバラストから浮かせることによってこの間にできる間隙に充填材を充填するので、填充層の外側でバラストを掘り下げたりバラストを埋め戻す必要が無い。このため大型重機が不要である。また、充填材を注入する際に型枠が不要であるから、型枠の設置・撤収の作業が不要で作業時間・作業日数を短縮できる。さらに填充層は両端だけでなく適宜の複数の位置(例えば3箇所)で引き上げれば填充層の湾曲が防止でき、高精度な軌道狂いの修正が可能である。   In the case of a labor-saving track, a lift anchor is fixed to the filler layer, and this anchor is lifted by a jack provided on the upper jig that supports the outer side of the filler layer, so that the filler layer is lifted from the ballast during this time. Since the filling material is filled in the gap that can be made, there is no need to dig up the ballast or backfill the ballast outside the filling layer. For this reason, large heavy machinery is unnecessary. In addition, since a mold is not required when injecting the filler, work for installing and removing the mold is unnecessary, and the work time and the number of work days can be shortened. Furthermore, if the filling layer is pulled up not only at both ends but also at a plurality of appropriate positions (for example, three locations), the bending of the filling layer can be prevented, and a highly accurate trajectory deviation can be corrected.

スラブ軌道の場合には、複数のジャッキを同期駆動する作業者の人数を減らし、作業能率を向上させることができる。   In the case of a slab track, the number of workers that drive a plurality of jacks synchronously can be reduced, and work efficiency can be improved.

本発明を省力化軌道に適用した一実施例を示す平面図The top view which shows one Example which applied this invention to the labor-saving track | orbit その填充層を引き上げる準備工程を示すレール直交方向の断面図Cross-sectional view in the direction perpendicular to the rail showing the preparation process for pulling up the filling layer 同じくレール引き上げた状態を示す断面図Sectional view showing the state where the rail is also lifted アンカー定着部の形成工程を示す断面図Sectional view showing formation process of anchor fixing part 同じくアンカー定着部の拡大断面図Similarly, an enlarged cross-sectional view of the anchor fixing part 充填材の注入管を設置する工程の説明図Explanatory drawing of the process of installing the filler injection pipe こう上治具の他の実施例を示す図The figure which shows the other Example of a raising jig このこう上治具を用いたリフトアップ用ジャッキセットの説明図Explanatory drawing of jack set for lift up using this upper jig 同じくリフトアップ工程の説明図Similarly explanatory drawing of lift-up process 同じく周辺地盤の改良のため充填材注入工程の説明図Explanatory drawing of filling material injection process for improvement of surrounding ground 同じく充填材の充填注入工程を示す図The figure which shows the filling injection process of a filler similarly 地盤補強完了状態を示す図The figure which shows the ground reinforcement completion state 図7のこう上治具の使用状態を示す正面図The front view which shows the use condition of the upper jig | tool of FIG. 同じく平面図Same top view 同じく右側面図Same right side view 上部ジャッキの断面図Cross section of upper jack 本発明の作業工程を示す図The figure which shows the work process of this invention 注入管打設用削孔装置を示す図The figure which shows the drilling device for the injection pipe placement 注入管の逆止弁を示すための一部断面図Partial sectional view to show the check valve of the injection pipe パッカーの動作説明図Illustration of packer operation 充填材のステップ注入工程の説明図Explanatory drawing of step injection process for filler 本発明をスラブ軌道に適用した実施例を示すレール直交方向の断面図Sectional view of rail orthogonal direction showing an embodiment in which the present invention is applied to a slab track 省力化軌道の断面図Cross section of labor saving track 従来考えられている軌道狂い補修方法の一例を示す作業工程図Work process diagram showing an example of a conventional method of repairing a track error

アンカーは、填充層にドリル形成したアンカー孔に接着系アンカー(例えばケミカルアンカー、「ケミカルアンカー」は日本デコラック社の商品名)を固着したアンカー定着部に螺入されて着脱可能に固着することができる(請求項2)。この場合接着系アンカーは、例えば低温速硬型のポリエステル樹脂アンカーを使用することができ、ここに固着された埋め込みナットにネジを形成したアンカーを螺入して固定することができる。アンカー孔は、アンカーを取り外した状態では防護蓋で塞いでおけるようにするのがよい。次の軌道狂い調整時に利用することができるからである。アンカーは、填充層の上面に密着する真空チャックであってもよい。   The anchor may be screwed into an anchor fixing portion in which an adhesive anchor (for example, a chemical anchor, “Chemical Anchor” is a trade name of Nippon Decorac Co., Ltd.) is fixed to the anchor hole drilled in the filling layer so as to be detachably fixed. (Claim 2). In this case, for example, a low-temperature fast-hardening type polyester resin anchor can be used as the adhesive anchor, and an anchor formed with a screw can be screwed into an embedded nut fixed to the anchor. The anchor hole is preferably closed with a protective lid when the anchor is removed. This is because it can be used at the time of the next trajectory adjustment. The anchor may be a vacuum chuck that is in close contact with the upper surface of the filling layer.

アンカーおよびアンカー定着部は、軌道横断方向の直線上で軌道の外側と軌道の間の合計3箇所に設けるのが望ましい(請求項3)。軌道間(填充層の中間付近)にアンカー、アンカー定着部を設けることにより、填充層の湾曲を防ぐことができ、またアンカー定着部の数を4以上に増やすと作業能率が低下するからである。こう上治具は、軌道の長手方向に複数台所定間隔ごとに配置し、填充層の所定範囲をこう上するようにするのがよい。充填層はその弾性によりその一部をこう上してもよいが、複数台のこう上治具で広い範囲を同時にこう上しても良く、この場合は作業精度の向上と作業能率の向上が図れる。   The anchors and anchor fixing portions are preferably provided at a total of three locations between the outer side of the track and the track on a straight line in the traverse direction. This is because by providing anchors and anchor fixing portions between the tracks (near the middle of the filling layer), it is possible to prevent the filling layer from being curved, and when the number of anchor fixing portions is increased to 4 or more, the work efficiency decreases. . It is preferable that a plurality of the raising jigs are arranged at predetermined intervals in the longitudinal direction of the track so as to rise above the predetermined range of the filling layer. Part of the packed bed may be raised due to its elasticity, but a wide range may be raised simultaneously with multiple raising jigs. In this case, work accuracy and work efficiency are improved. I can plan.

こう上治具は、一対の支持部と、両支持部に掛け渡された梁部と、両支持部に設けられ前記梁部の高さ調整用下部ジャッキとを備え、前記工程b)では前記下部ジャッキによってアンカーの高さを粗調整し、前記工程c)では前記梁部に保持した微調整用の上部ジャッキによって軌道高さを微調整するようにするのがよい(請求項4)。上部ジャッキと下部ジャッキとに分けて引き上げ量を設定すれば、調整がし易くなり、能率が向上する(請求項5)。   The upper jig includes a pair of support portions, a beam portion spanned between both support portions, and a lower jack for adjusting the height of the beam portion provided on both support portions, and in the step b), The height of the anchor is roughly adjusted by the lower jack, and in the step c), the track height is finely adjusted by the upper jack for fine adjustment held on the beam portion (Claim 4). If the lifting amount is set separately for the upper jack and the lower jack, the adjustment becomes easier and the efficiency is improved (claim 5).

充填材(フィルコン材など)の注入は種々の方法により行うことが可能である。填充層に開けた注入孔から注入してもよいが、バラストと填充層の間の空隙に確実に注入しかつその下方(バラストやその下の土路盤)まで達する深い範囲まで注入できればバラストやその下の土路盤の補強(道床安定化、下地盤改質)を同時に行って軌道狂いを一層確実に減少または防止することができる。   Injection of a filler (such as a filcon material) can be performed by various methods. It may be injected from the injection hole opened in the filler layer, but if it can be injected into the gap between the ballast and the filler layer and it can be injected deeply down to the bottom (ballast and the underlying roadbed), the ballast and its It is possible to more reliably reduce or prevent trajectory error by simultaneously reinforcing the bottom road bed (stabilizing the road bed and modifying the ground bed).

そのためには、次のようにするのがよい。すなわち、工程a)では、充填層にアンカー定着部を形成すると共に、填充層を貫通してバラストおよびその下方に達する注入管を設置しておき、工程d)では、前記注入管から空隙とその下方に充填材(フィルコン材)を注入するようにすれば、空隙だけでなくその下のバラストや土路盤(下地盤)にも充填材を円滑に注入できる(請求項6)。この場合注入管は、削孔機で形成した削孔に挿入され多数の小孔が形成された鋼管であり、この注入管から充填材、すなわちフィルコン材やグラウト(セメントミルク又はモルタルなど)を注入して、バラストと填充層の間にできる間隙に充填すると共に、バラストや土路盤に注入して路盤強度の向上(路盤改良)を連続工程で行うのがよい。この場合その上端開口には防護蓋を着脱可能に設けておけばアンカーで填充層を引き上げる工程中にマイクロパイルに異物が入るのを防ぐことができる(請求項7)。   For that purpose, it is better to do as follows. That is, in step a), an anchor fixing part is formed in the packed bed, and a ballast and an injection pipe reaching the lower side are installed through the packed bed, and in step d), a void and its By injecting the filler (filcon material) downward, the filler can be smoothly injected not only into the gap but also into the ballast and earth roadbed (underground board) thereunder (Claim 6). In this case, the injection pipe is a steel pipe that is inserted into a drilling hole formed by a drilling machine and formed with a large number of small holes. From this injection pipe, a filler, that is, filcon material or grout (such as cement milk or mortar) is injected. Then, it is preferable that the gap formed between the ballast and the filling layer is filled and injected into the ballast or the earth roadbed to improve the roadbed strength (roadbed improvement) in a continuous process. In this case, if a protective lid is detachably provided at the upper end opening, it is possible to prevent foreign matter from entering the micropile during the process of pulling up the filling layer with an anchor.

注入管の小孔には逆止弁を取り付けておき、削孔装置による削孔形成時の削り屑や充填材が注入管内に入る(逆流する)のを防止するのがよい(請求項8)。また注入管には、注入管の途中に固定位置可変でかつ充填材が通過可能なパッカーを挿入し、このパッカーを間隙より下方に固定した状態で充填材をこのパッカーを通してその下に注入し、その後パッカーを間隙より上方に移動して固定した後充填材を間隙に注入するのがよい(請求項9)。すなわち下方から段階的に注入していくものである(ステップ注入方式)。   A check valve is attached to the small hole of the injection pipe to prevent shavings and filler from entering the injection pipe (reverse flow) when forming a hole by the drilling device (Claim 8). . Also, in the injection tube, a packer is inserted in the middle of the injection tube, the fixed position of which can be changed and the filler can pass through, and the filler is injected below through the packer with the packer fixed below the gap, After that, after the packer is moved and fixed above the gap, the filler is preferably injected into the gap. That is, the injection is performed stepwise from below (step injection method).

アンカー定着部は、ドリルによる削孔に接着系アンカーを挿入し、これに先端を尖らせた全ネジあるいは異形鋼棒を打ち込むことによって接着系アンカーの容器を破壊し化学反応を起こさせて固定したものであり、ここに固着した前記全ネジあるいは異形鋼棒の上端にリフトアップ用接続ナットを固着してこのナットに長ネジを螺入してアンカーとしてもよい(請求項10)。   The anchor fixing part inserts the adhesive anchor into the drilling hole, and drives the fixed anchor rod by destroying the container of the adhesive anchor by driving all screws or deformed steel bars with a sharpened tip into it. A lift-up connection nut may be fixed to the upper end of the all screws or deformed steel rods fixed thereto, and a long screw may be screwed into the nut to form an anchor (claim 10).

スラブ軌道の場合には、アンカーはスラブ表面に真空吸着される真空チャックが適する(請求項12)。スラブは鉄筋入りのコンクリート製であるためドリル孔を加工することが困難であるから接着系アンカーは使えないからである。またこう上機は軌道長手方向に所定間隔ごとに複数台設置し、これらを同時に駆動してスラブ全体を同時にこう上させるようにすれば、作業能率が良く軌道狂いの修正精度が向上する(請求項13)。   In the case of a slab track, the anchor is preferably a vacuum chuck that is vacuum-adsorbed on the slab surface. This is because slabs are made of concrete with reinforcing bars, so it is difficult to drill holes and adhesive anchors cannot be used. In addition, if a plurality of hoisting machines are installed at predetermined intervals in the longitudinal direction of the track and these are driven simultaneously so that the entire slab is lifted simultaneously, the work efficiency is improved and the accuracy of the track error is improved. Item 13).

図1においては、図23の対応する部分に同一符号を付したので、その説明は繰り返さない。この図1において符号10はこう上治具であり、図2、3に示すように、レール1、1を横断する略門型に作られている。すなわちこのこう上治具10は、一対の支持部12、12に梁部14を掛け渡したものであり、各支持部12には油圧式の下部ジャッキ16が設けられている。各支持部12は、レール1、1の外側でバラスト3の上面に支持され、この上端に梁部14の両端が支持されている。ここに梁部14はレール1、1にほぼ直交している。   In FIG. 1, since the same code | symbol was attached | subjected to the corresponding part of FIG. 23, the description is not repeated. In FIG. 1, reference numeral 10 denotes an upper jig, which is formed in a substantially gate shape that crosses the rails 1 and 1 as shown in FIGS. That is, the upper jig 10 has a pair of support portions 12, 12 with a beam portion 14 spanned between them, and each support portion 12 is provided with a hydraulic lower jack 16. Each support portion 12 is supported on the upper surface of the ballast 3 on the outside of the rails 1 and 1, and both ends of the beam portion 14 are supported on this upper end. Here, the beam portion 14 is substantially orthogonal to the rails 1 and 1.

このこう上治具10を設置する前に、填充層4にアンカー定着部18と充填材注入用注入管(パイル)20を設置しておく(図17の工程a、b)。アンカー定着部18は、レール1を横断する直線に沿って3箇所に設けられている。すなわち、レール1、1と外側と中央付近との合計3箇所に設けられ、この上方に前記こう上治具10の梁部14が位置するようにこう上治具10が設置される。なおこう上治具10は、レール1の長さ方向の適宜間隔ごとに設置されるので、1つのこう上治具10に対応する3箇一組の前記アンカー定着部18も、これに合わせてレール1の長手方向に所定の間隔を空けて設置される。   Before installing the upper jig 10, an anchor fixing portion 18 and a filler injection pipe (pile) 20 are installed in the filling layer 4 (steps a and b in FIG. 17). The anchor fixing portions 18 are provided at three locations along a straight line that crosses the rail 1. In other words, the upper jig 10 is provided at a total of three locations of the rails 1, 1, the outer side, and the vicinity of the center, and the beam jig 14 of the upper jig 10 is positioned above this. Since the upper jig 10 is installed at appropriate intervals in the length direction of the rail 1, three sets of the anchor fixing portions 18 corresponding to one upper jig 10 are also adjusted accordingly. The rails 1 are installed at predetermined intervals in the longitudinal direction.

アンカー定着部18は、図1では、隣接する2本のまくら木2の間を通る直線に沿って設けるのが望ましい。後記するアンカー28による引き上げ力が全て填充層4に直接作用するからである。しかし枕木2を貫通して填充層4に達するように設けてもよい。   In FIG. 1, the anchor fixing unit 18 is preferably provided along a straight line passing between two adjacent sleepers 2. This is because all the pulling force by the anchor 28 described later directly acts on the filling layer 4. However, it may be provided so as to penetrate the sleepers 2 and reach the filling layer 4.

このアンカー定着部18は、図4、5に示すようにケミカルアンカー(商品名)などの接着系アンカーによって形成される。すなわち図4に示すように、まず填充層4にアンカー孔22をハンマードリルなどを用いる人力施工によって削孔する(図4のA)。このアンカー孔22をブロワーで切り粉を除去し、さらにケミカルブラシで孔内壁の粉塵を除去し、さらにブロワーや集塵機で掃除したあと、接着剤を装填したカプセルを挿入する。そしてこのアンカー孔22に先端が尖った表面にネジや凹凸を設けた鋼棒24を打ち込むことによってカプセルを破壊し、化学反応により鋼棒24を固定するものである(図4のB)。   The anchor fixing portion 18 is formed by an adhesive anchor such as a chemical anchor (trade name) as shown in FIGS. That is, as shown in FIG. 4, the anchor hole 22 is first drilled in the filling layer 4 by manual work using a hammer drill or the like (A in FIG. 4). The anchor hole 22 is cut with a blower, dust on the inner wall of the hole is removed with a chemical brush, further cleaned with a blower or a dust collector, and then a capsule loaded with an adhesive is inserted. Then, the capsule is broken by driving a steel rod 24 provided with a screw or irregularities on the surface of the anchor hole 22 having a sharp tip, and the steel rod 24 is fixed by a chemical reaction (B in FIG. 4).

この鋼棒24の上端には接続用ナット26が設けられ、この接続用ナット26がアンカー孔22内に入るようにアンカー孔22の深さと鋼棒24の長さが設定されている(図5のA)。この接続用ナット26にアンカー28が螺入され、このアンカー28を介して填充層4が引き上げられる(図5のB)。なお填充層4のこう上(リフトアップ)により軌道狂いの補修が完了したあとでは、このアンカー28が取り外され、接続用ナット26に防護蓋30を螺入しておく(図5のC)。防護蓋30は接続用ナット26に異物が入るのを防止し、将来同じアンカー定着部18を用いて軌道狂いの補修を行う際に利用できるようにするものである。   A connecting nut 26 is provided at the upper end of the steel rod 24, and the depth of the anchor hole 22 and the length of the steel rod 24 are set so that the connecting nut 26 enters the anchor hole 22 (FIG. 5). A). An anchor 28 is screwed into the connecting nut 26, and the filling layer 4 is pulled up via the anchor 28 (B in FIG. 5). In addition, after the repair of the trajectory error is completed by raising (lifting up) the filling layer 4, the anchor 28 is removed, and the protective lid 30 is screwed into the connecting nut 26 (C in FIG. 5). The protective lid 30 prevents foreign matter from entering the connecting nut 26 and can be used when repairing the track error using the same anchor fixing portion 18 in the future.

前記充填材注入用注入管20は図6に示すように、小型の削孔機32を用いて填充層4の適宜の位置に形成した削孔34に(図6のA)挿入する鋼管(パイル)であり、この鋼管には小孔が多数形成されている。ここに削孔機32は、レール1と干渉しない位置で枕木2に載せた鋼製架台38、38に載せられて、図1に示すように枕木2の間などの適宜の位置に削孔34を加工し、ここに鋼管を挿入して注入管20とする。この注入管20には防護蓋40が着脱可能に固定され、アンカー28により填充層4を引き上げる際などに異物が鋼管内に入るのを防ぐ(図6のB)。   As shown in FIG. 6, the filling material injection pipe 20 is a steel pipe (pile) to be inserted into a hole 34 (A in FIG. 6) formed at an appropriate position of the filling layer 4 using a small hole drill 32. In this steel pipe, a large number of small holes are formed. Here, the hole drilling machine 32 is placed on steel mounts 38 and 38 mounted on the sleeper 2 at a position where it does not interfere with the rail 1, and the hole drilling 34 is placed at an appropriate position such as between the sleepers 2 as shown in FIG. Then, a steel pipe is inserted into the injection pipe 20. A protective lid 40 is detachably fixed to the injection pipe 20 to prevent foreign matter from entering the steel pipe when the filling layer 4 is pulled up by the anchor 28 (B in FIG. 6).

以上のように、填充層4にアンカー定着部18とフィルコン材注入管20の設置が完了してから、こう上治具10を設置する(図17の工程c)。すなわち、一対の支持部12をバラスト3に立て、この上に梁部14を掛け渡す(図2のAおよびB)。この時こう上治具10の梁部14が3つのアンカー定着部18の上方に位置するようにする。また梁部14の高さがほぼ適切で水平になるように、左右の下部ジャッキ16を粗調整しておく。   As described above, after the installation of the anchor fixing portion 18 and the fillcon material injection pipe 20 is completed in the filling layer 4, the upper jig 10 is installed (step c in FIG. 17). That is, the pair of support portions 12 are erected on the ballast 3 and the beam portion 14 is hung thereon (A and B in FIG. 2). At this time, the beam portion 14 of the upper jig 10 is positioned above the three anchor fixing portions 18. In addition, the left and right lower jacks 16 are roughly adjusted so that the height of the beam portion 14 is substantially appropriate and horizontal.

梁部14には、各アンカー定着部18の上方に油圧式のセンターホールジャッキからなる上部ジャッキ42を載せる。このジャッキ42は、図16に示すように中央を上下方向に貫通する貫通孔を持つ構造である。この図16において、44は円筒状のボディであって、その下端には筒状のガイド46がボディ44内へ同心に伸びるように固定されている。このガイド46の外周面とボディ44の内周面との間にはピストン48が摺動自在に装填されている。ボディ44の上端面には、このピストン48の上部外周面とボディ42内周面との間に進入した円筒状の蓋ブロック50が固定されている。   On the beam portion 14, an upper jack 42 made of a hydraulic center hole jack is placed above each anchor fixing portion 18. As shown in FIG. 16, the jack 42 has a structure having a through hole penetrating the center in the vertical direction. In FIG. 16, reference numeral 44 denotes a cylindrical body, and a cylindrical guide 46 is fixed to the lower end thereof so as to extend concentrically into the body 44. A piston 48 is slidably loaded between the outer peripheral surface of the guide 46 and the inner peripheral surface of the body 44. A cylindrical lid block 50 that has entered between the upper outer peripheral surface of the piston 48 and the inner peripheral surface of the body 42 is fixed to the upper end surface of the body 44.

ボディ44の内底には、その底部内面とガイド46の外周とピストン48の下面とで囲まれる油圧室52が形成される。この油圧室52には油圧ユニット(図示せず)から油圧が供給され、この油圧によってピストン48が上昇する。なおピストン48の外周面とボディ44の内周面と蓋ブロック50の下面とで大気圧に連通する低圧室54が形成されている。ピストン48には、ガイド46と同軸にガイド46の内径と同径の上下方向に貫通する貫通孔56が形成されている。   A hydraulic chamber 52 surrounded by the inner surface of the bottom portion, the outer periphery of the guide 46 and the lower surface of the piston 48 is formed on the inner bottom of the body 44. The hydraulic chamber 52 is supplied with hydraulic pressure from a hydraulic unit (not shown), and the piston 48 is raised by the hydraulic pressure. A low pressure chamber 54 communicating with the atmospheric pressure is formed by the outer peripheral surface of the piston 48, the inner peripheral surface of the body 44, and the lower surface of the lid block 50. The piston 48 is formed with a through hole 56 that is coaxial with the guide 46 and penetrates in the vertical direction and has the same diameter as the guide 46.

この上部ジャッキ42のガイド46とピストン48の貫通孔56には前記アンカー28を上方から通し、その下端を前記アンカー定着部18の接続用ナット26に螺入する。またアンカー28には上方からアンカー28の高さ調節用のナット58が螺合されている。すなわちこのナット58の回転によってナット58の下面を前記ピストン48の上端に当接させ、上部ジャッキ42とアンカー28とに遊びが無くなるように設定する。3つの上部ジャッキ42が同様に設定される。図2のCはこの状態を示している。   The anchor 28 is passed through the guide 46 of the upper jack 42 and the through hole 56 of the piston 48 from above, and the lower end thereof is screwed into the connecting nut 26 of the anchor fixing portion 18. A nut 58 for adjusting the height of the anchor 28 is screwed onto the anchor 28 from above. In other words, the lower surface of the nut 58 is brought into contact with the upper end of the piston 48 by the rotation of the nut 58 so that the upper jack 42 and the anchor 28 are free from play. Three upper jacks 42 are similarly set. FIG. 2C shows this state.

この状態で3つの上部ジャッキ42の油圧室52に油圧を供給すると、各上部ジャッキ42の各ピストン48の上面がナット58とアンカー28とを一体として上昇させる。このためアンカー28の下端が結合された填充層4がバラスト3から引き上げられる(図17の工程d)。各上部ジャッキ42の油圧を個別に制御することによって、レール1、1の高さを微調整することができる。またレール1、1のカント(傾き)を同時に微調整する。   When hydraulic pressure is supplied to the hydraulic chambers 52 of the three upper jacks 42 in this state, the upper surfaces of the pistons 48 of the upper jacks 42 raise the nuts 58 and the anchors 28 together. For this reason, the filling layer 4 to which the lower ends of the anchors 28 are coupled is pulled up from the ballast 3 (step d in FIG. 17). By individually controlling the hydraulic pressure of each upper jack 42, the height of the rails 1 and 1 can be finely adjusted. Further, the cant (tilt) of the rails 1 and 1 is finely adjusted simultaneously.

このレール高さとカントの微調整が済んだ状態では、填充層4とバラスト3の間に間隙60が形成される(図3)。この間隙60には前記注入管20から充填材(フィルコン材が適する。)が注入される(図17の工程e)。すなわち空隙60に充填材を注入して充填すると共に、その下のバラスト3と土路盤にも充填材(グラウトが適する。)を注入して填充して基礎の土質改善を行う。この状態で充填材の硬化を待つ(図17の工程f)。すなわち養生する。 In the state where the rail height and the cant are finely adjusted, a gap 60 is formed between the filling layer 4 and the ballast 3 (FIG. 3). A filling material (fillcon material is suitable) is injected into the gap 60 from the injection tube 20 (step e in FIG. 17). In other words, the filler 60 is injected and filled in the gap 60, and the base material is improved by injecting and filling the filler (grouting is suitable) into the ballast 3 and the soil roadbed below. In this state, the hardening of the filler is awaited (step f in FIG. 17). In other words, it is cured.

この養生が終わるとこう上治具10を撤去する(図17の工程g)。すなわち上部ジャッキ42の油圧を抜いてアンカー28に加わっている引き上げ力を除去し、ナット58を弛めて取り外し、さらにアンカー28の下端を、アンカー定着部18の接続用ナット26から外す。この状態でアンカー28は上方に抜けることになる。アンカー28を抜いてからこう上治具10を分解して撤去する。そしてアンカー定着部18と注入口に防護蓋30、40を装着し、次の軌道狂い補修箇所に移動する。   When this curing is finished, the upper jig 10 is removed (step g in FIG. 17). That is, the lifting force applied to the anchor 28 is removed by removing the hydraulic pressure of the upper jack 42, the nut 58 is loosened and removed, and the lower end of the anchor 28 is removed from the connection nut 26 of the anchor fixing portion 18. In this state, the anchor 28 is pulled upward. After the anchor 28 is pulled out, the upper jig 10 is disassembled and removed. Then, the protective lids 30 and 40 are attached to the anchor fixing portion 18 and the injection port, and moved to the next place where the trajectory is repaired.

図7〜15は他の実施例を示すものである。この実施例は前記実施例1のこう上治具10の構造が異なるものであって、工法自体は異ならない。従って図1〜6などで説明した実施例1と対応する部分には同一符号を付してその説明は繰り返さない。ここで用いるこう上治具100には図13〜15に示すように、左右にそれぞれ2本ずつの支持部102があって、合計4本の支持部102を持つ。4本の支持部102の上端には、四角枠型に組んだ梁部となる形鋼104が載せられ、この形鋼104の上に、軌道1と平行に3組の小梁106が掛け渡されている。小梁106の中央付近は3個のアンカー定着部18の上方に位置する。   7 to 15 show other embodiments. In this embodiment, the structure of the upper jig 10 of the first embodiment is different, and the construction method itself is not different. Accordingly, portions corresponding to those in the first embodiment described with reference to FIGS. 1 to 6 are denoted by the same reference numerals, and the description thereof will not be repeated. As shown in FIGS. 13 to 15, the upper jig 100 used here has two support portions 102 on each of the left and right sides, and has a total of four support portions 102. On the upper ends of the four support portions 102, a section steel 104 is mounted as a beam portion assembled in a square frame shape, and three sets of small beams 106 hang over the shape steel 104 in parallel with the track 1. Has been. The vicinity of the center of the beam 106 is located above the three anchor fixing portions 18.

小梁106は一対のI形鋼を間隙を開けて対向配置したものであり、この間隙にはアンカー28が通る。各小梁106の上面には前記上部ジャッキ42(図16に示すものと同じもの)が万力(図示せず)などによって固定される。ここに上部ジャッキ42は、それぞれアンカー定着部18の上方に位置させる。図7は上部ジャッキ42の設置前のこの状態を示している。この実施例では、支持部102にキリンジャッキからなる下部ジャッキ16を用いている。このキリンジャッキは送りネジを手動のナットリング108(図7参照)を回転することによって上下動させることによって高さを粗調整し、その後全ての(9個の)上部ジャッキ42の高さあるいは傾き(カント)を調節(粗調整)するものである。   The small beam 106 is a pair of I-beams arranged opposite each other with a gap therebetween, and an anchor 28 passes through this gap. The upper jack 42 (same as shown in FIG. 16) is fixed to the upper surface of each beam 106 by a vise (not shown) or the like. Here, the upper jacks 42 are respectively positioned above the anchor fixing unit 18. FIG. 7 shows this state before the upper jack 42 is installed. In this embodiment, the lower jack 16 made of a giraffe jack is used for the support portion 102. This giraffe jack adjusts the height roughly by moving the feed screw up and down by rotating the manual nut ring 108 (see FIG. 7), and then the height or inclination of all (9) upper jacks 42. (Kant) is adjusted (coarse adjustment).

このこう上治具100は図7に示すように、予めアンカー定着部18と充填材注入口となる削孔34およびここに挿入した鋼管(パイル)20からなる注入管の施工が済ませてある填充層4の上方に設置される(図17の工程a、b、c)。小梁106には上部ジャッキ42を固定しておく。そしてアンカー28を上部ジャッキ42に通して、下端をアンカー定着部18に接続する。図8はこの状態を示している。   As shown in FIG. 7, the upper jig 100 is filled with an anchor pipe 18 and an injection pipe made of a steel pipe (pile) 20 inserted therein and a drill hole 34 serving as a filler inlet. It is installed above the layer 4 (steps a, b and c in FIG. 17). The upper jack 42 is fixed to the beam 106. Then, the anchor 28 is passed through the upper jack 42, and the lower end is connected to the anchor fixing unit 18. FIG. 8 shows this state.

そして全ての上部ジャッキ42にそれぞれ個別に調整ながら所定圧力の油圧を油圧ユニットから供給し、アンカー28と填充層4と鋼管20とを一体に引き上げる。このため填充層4とバラスト3との間に間隙60が形成される(図17の工程d)。図9はこの状態を示している。   Then, a hydraulic pressure of a predetermined pressure is supplied from the hydraulic unit while individually adjusting all the upper jacks 42, and the anchor 28, the filling layer 4 and the steel pipe 20 are pulled up integrally. Therefore, a gap 60 is formed between the filling layer 4 and the ballast 3 (step d in FIG. 17). FIG. 9 shows this state.

このように準備した後、鋼管20からグラウト(鋼管内および削孔壁部に充填されるスラリー状のセメント系注入材料)などの充填材を注入する(図17の工程e)。この時グラウト流体に圧力が加わるよう、鋼管内にパッカー110を入れて栓をする(図10のA)。このパッカー110は膨張可能なワイヤー入りのゴム体、注入用器具であり、これを膨張させてからグラウトを加圧注入することによって先端から順に段階的(ステップアップ)な圧力注入を行う(図10のB)。この時パッカー110は、間隙60付近に位置させてこの間隙60より下方だけにグラウトを供給する。図10はグラウトの注入前(A)と注入後(B)とを示している。   After the preparation as described above, a filler such as grout (slurry cement-based injection material filled in the steel pipe and the hole wall) is injected from the steel pipe 20 (step e in FIG. 17). At this time, the packer 110 is put in the steel pipe so as to apply pressure to the grout fluid (A in FIG. 10). This packer 110 is an inflatable wire-filled rubber body and an injection device, and after inflating it, the grout is pressurized and injected step by step (step-up) in order from the tip (FIG. 10). B). At this time, the packer 110 is positioned near the gap 60 and supplies the grout only below the gap 60. FIG. 10 shows before (A) and after (B) injection of grout.

空隙60より下にグラウトを注入した後、パッカー110の位置を空隙60より上方に移動し(図11のA)、さらにグラウトを加圧注入して空隙60に注入する(図11のB)。図11はこの状態を示している。そしてグラウトの硬化を待ち(図17の工程f、養生)、硬化したらこう上治具100などを除去する(図17の工程g)。図12はこの状態を示す。   After the grout is injected below the gap 60, the position of the packer 110 is moved above the gap 60 (A in FIG. 11), and the grout is injected under pressure and injected into the gap 60 (B in FIG. 11). FIG. 11 shows this state. Then, the hardening of the grout is awaited (step f in FIG. 17, curing), and when it is cured, the upper jig 100 and the like are removed (step g in FIG. 17). FIG. 12 shows this state.

図18〜21は、充填材を下から順に注入(ステップ注入)する実施例を説明するものであり、この実施例では充填材とは別系統の圧力によって任意の位置に固定可能なパッカー150を用いる。このパッカー150は、その中央に膨張可能なゴム体152を持ち、このゴム体152は充填材とは別系統の加圧チューブ154によって導かれる水圧や空気圧によって膨張し、注入管34の任意の位置にしっかりと固定可能である。またこのパッカー150は上下に貫通する充填材通路156が形成されている。   18 to 21 illustrate an embodiment in which fillers are sequentially injected from the bottom (step injection). In this embodiment, a packer 150 that can be fixed at an arbitrary position by a pressure of a system different from the filler is used. Use. The packer 150 has an expandable rubber body 152 at the center thereof, and the rubber body 152 is expanded by water pressure or air pressure guided by a pressure tube 154 of a system different from the filler, so that an arbitrary position of the injection pipe 34 is obtained. It can be firmly fixed to. The packer 150 is formed with a filler passage 156 penetrating vertically.

図18は注入管打設用削孔装置を示し、削孔ロッド158の先端にダウンザホールハンマー160を接続して注入管20に上方から挿入し、削孔ロッド158を回転することによって削孔34を形成しつつ注入管20を所定の深さまで進入させるものである。すなわちダウンザホールハンマー160の先端には拡径ビット162が取り付けられ、削孔ロッド158を一方向に回転する時に拡径ビット162が拡径して填充層4やバラスト層3を掘削し、削孔34が形成される。この時、拡径ビット162と共に注入管20も下降していく。所定の深さまで下降したら削孔ロッド158を逆転させれば、拡径ビット162が縮径して削孔ロッド158および削径ビット162は上方に抜き取ることができ、注入管20を削孔34内に設置することができる。   18 shows a drilling device for injecting the injection tube. A down-the-hole hammer 160 is connected to the tip of the drilling rod 158 and inserted into the injection tube 20 from above, and the drilling rod 158 is rotated to rotate the drilling hole 34. The injection tube 20 is advanced to a predetermined depth while forming. That is, the diameter-expanding bit 162 is attached to the tip of the down-the-hole hammer 160, and when the drilling rod 158 is rotated in one direction, the diameter-expanding bit 162 expands to excavate the filling layer 4 and the ballast layer 3 and drill the hole 34. Is formed. At this time, the injection pipe 20 is also moved down together with the diameter expanding bit 162. When the drilling rod 158 is reversed when the drilling rod is lowered to a predetermined depth, the diameter expanding bit 162 is reduced in diameter so that the drilling rod 158 and the drilling bit 162 can be extracted upward, and the injection tube 20 is inserted into the drilling hole 34. Can be installed.

ここに注入管20には、多数の小孔164が形成され、各小孔164にはそれぞれ逆止弁166が取り付けられている。逆止弁166は、注入管20の管壁に設けた小孔164に管壁の外側から嵌合された硬質ゴムなどの弁板で構成され、管内圧(充填材圧)が所定圧になると弁板が管壁の外側に押し出されて開弁するものである。削孔ビット162の進入に伴って削孔ビット162が填充層3やバラスト4を削った削り屑(繰り粉)が注入管20と削孔34の間隙を通って上昇するので、この削り屑が注入管20の中に入ったり、小孔164を塞ぐのを防ぐためである。   Here, a large number of small holes 164 are formed in the injection tube 20, and a check valve 166 is attached to each small hole 164. The check valve 166 is configured by a valve plate made of hard rubber or the like fitted into a small hole 164 provided in the pipe wall of the injection pipe 20 from the outside of the pipe wall, and when the pipe internal pressure (filler pressure) becomes a predetermined pressure. The valve plate is pushed out of the pipe wall and opened. As the drill bit 162 enters, the shavings (milled powder) that the drill bit 162 scrapes the filling layer 3 and the ballast 4 rises through the gap between the injection tube 20 and the drill hole 34, so that the shavings are This is for preventing the injection tube 20 from entering or closing the small hole 164.

この実施例では、パッカー150は注入管20の中に挿入し(図21の工程ア)、図9に示した間隙60よりも下の所定の高さに位置させ(図20(A)参照)、加圧チューブ154に水圧あるいは空気圧を供給することによってゴム体152を膨張させるて固定する(図20(B)参照、図21の工程イ)。そして充填材通路156に上方から(外から)第1の充填材であるグラウト材を注入し(工程ウ)、充填材をパッカー15を貫通してその下方に注入する。充填材の注入圧力を所定圧に上げれば、パッカー150より下方の逆止弁166が開き充填材が注入管20の外側、すなわち注入管20と削孔34の間の間隙に流出する。この充填材は、バラスト3に注入されて、填充層4を支持している部分を強固に固めて地盤改良する。   In this embodiment, the packer 150 is inserted into the injection tube 20 (step A in FIG. 21) and positioned at a predetermined height below the gap 60 shown in FIG. 9 (see FIG. 20A). Then, the rubber body 152 is expanded and fixed by supplying water pressure or air pressure to the pressurizing tube 154 (see FIG. 20B, step a in FIG. 21). Then, a grout material, which is the first filler, is injected into the filler passage 156 from above (from outside) (step c), and the filler is injected through the packer 15 and below. If the injection pressure of the filler is increased to a predetermined pressure, the check valve 166 below the packer 150 opens and the filler flows out of the injection pipe 20, that is, into the gap between the injection pipe 20 and the drilling hole 34. This filler is injected into the ballast 3 to firmly solidify the portion supporting the filling layer 4 and improve the ground.

所定量の充填材の注入が終わると、加圧チューブ154から圧力を抜き、ゴム体152を収縮させてパッカー150を間隙60より上方に移動させる(工程エ)。そしてパッカー150を再び膨張させて固定してから(工程オ)、第2の充填材であるフィルコン材を注入し、間隙60に流入させる(工程カ)。このため余分な箇所に充填材が漏れ出て(リークして)必要な箇所が未注入のままに残ることを防止して、確実かつ効果的なリフトアップができる。注入が終わると加圧チューブ154から圧力を抜き、パッカー150を注入管20から抜き取る(工程キ)か、パッカー150を上方へ移動させながら、注入管の20の上端開口までフィルコン材を追加注入する(工程ク)。   When the injection of the predetermined amount of filler is completed, the pressure is released from the pressure tube 154, the rubber body 152 is contracted, and the packer 150 is moved above the gap 60 (step D). Then, after the packer 150 is expanded and fixed again (step (e)), a fillcon material as the second filler is injected and flows into the gap 60 (step (f)). For this reason, it is possible to prevent the filler from leaking (leakage) to an extra portion and to leave a necessary portion uninjected, thereby reliably and effectively lifting up. When the injection is completed, the pressure is released from the pressure tube 154, and the packer 150 is extracted from the injection tube 20 (step K), or the filler material is additionally injected to the upper end opening of the injection tube 20 while moving the packer 150 upward. (Process K).

この実施例は以上のように、グラウト圧を調整しながら段階的に注入するものである。従って、この時パッカー150はグラウト注入圧と別系統で加圧膨張させておくことができるので、グラウト圧にパッカー150が負けて移動するのを防ぐことができ、常に良好な注入作業を安定して行うことが可能になる。   In this embodiment, as described above, the grouting pressure is adjusted in stages while being adjusted. Therefore, the packer 150 can be pressurized and expanded separately from the grout injection pressure at this time, so that the packer 150 can be prevented from losing and moving due to the grout pressure. Can be performed.

図22はコンクリートスラブ軌道の軌道補正を示す。この図において、符号200はコンクリート路盤、202はこの上に載せたコンクリートスラブであり、両者の間にはアスファルト樹脂などの充填材204が充填されている。軌道206は、このコンクリートスラブ202の上面に図示しない締結具によって固定されている。充填材204の厚さを調整することによって軌道206の高さが設定されている。   FIG. 22 shows the track correction of the concrete slab track. In this figure, reference numeral 200 denotes a concrete roadbed, 202 denotes a concrete slab placed thereon, and a filler 204 such as asphalt resin is filled therebetween. The track 206 is fixed to the upper surface of the concrete slab 202 by a fastener (not shown). The height of the track 206 is set by adjusting the thickness of the filler 204.

208はこう上治具であり、左右一対の下部ジャッキ210と、下部ジャッキ210の上端に上部ジャッキ212を介して掛け渡された梁部214とを有する。下部ジャッキ210と上部ジャッキ212は、梁部214を支持する支持部となる。下部ジャッキ210は4本の送りネジからなり、それぞれの下端はコンクリート路盤200に支持されている。上部ジャッキ212は油圧式のものであり、油圧により梁部214の高さを微調整することができる。   Reference numeral 208 denotes an upper jig, which has a pair of left and right lower jacks 210 and a beam portion 214 spanned through an upper jack 212 on the upper end of the lower jack 210. The lower jack 210 and the upper jack 212 serve as a support portion that supports the beam portion 214. The lower jack 210 includes four feed screws, and the lower ends of the lower jacks 210 are supported by the concrete roadbed 200. The upper jack 212 is a hydraulic type, and the height of the beam portion 214 can be finely adjusted by hydraulic pressure.

梁部214はFRPなどの繊維強化樹脂で中央が高くなるように湾曲している。この梁部214の下方には、左右の軌道206、206を跨ぐ小梁216、216が有り、小梁216、216の両端にアンカー218、218の上端が保持されている。このアンカー218、218の下端には、逆碗状(カップ状)の吸着部220、220が固定され、この吸着部220、220はコンクリートスラブ202の上面に真空吸着される。なおこの吸着部220、220には、真空ポンプが接続されているが、ここではこの真空排気系は省いてある。また吸着部220には空気を導入することによって吸着を解除できる。   The beam portion 214 is made of a fiber reinforced resin such as FRP and is curved so that the center becomes higher. Below the beam 214, there are small beams 216 and 216 straddling the left and right tracks 206 and 206, and the upper ends of the anchors 218 and 218 are held at both ends of the small beams 216 and 216, respectively. At the lower ends of the anchors 218, 218, inverted saddle-shaped (cup-shaped) suction portions 220, 220 are fixed, and the suction portions 220, 220 are vacuum-sucked on the upper surface of the concrete slab 202. A vacuum pump is connected to the adsorbing portions 220 and 220, but the evacuation system is omitted here. Adsorption can be released by introducing air into the adsorption unit 220.

小梁216、216の中央は連結棒222、222によって、前記梁部214に連結されている。すなわち連結棒222、222は上部が梁部214を下方から貫通して上方からナットが螺入され、下部が小梁216、216を下方に向かって貫通してナットが螺入されている。このため、これらのナットにより梁部214と小梁216の間隔を調整することにより、小梁216の高さを調整可能である。   The centers of the small beams 216 and 216 are connected to the beam portion 214 by connecting rods 222 and 222. That is, the connecting rods 222 and 222 have an upper portion that penetrates the beam portion 214 from below and a nut that is threaded from above, and a lower portion that penetrates the small beams 216 and 216 downward and are nut-threaded. Therefore, the height of the small beam 216 can be adjusted by adjusting the distance between the beam portion 214 and the small beam 216 with these nuts.

下部ジャッキ210と上部ジャッキ212を使って、梁部214を引き上げると、これに連結された小梁216が上昇し、また小梁216に連結されたアンカー218に上向きの力が加わる。アンカー218の下端は吸着部220でコンクリートスラブ202に固着されているので、結局コンクリートスラブ202が上方に引き上げられる。このようにして軌道206の軌道狂いが修正される。この時コンクリートスラブ202とコンクリート路盤200との間隔が変化するので、充填材204はコンクリートスラブ202あるいはコンクリート路盤200から剥がれることになる。   When the beam portion 214 is pulled up using the lower jack 210 and the upper jack 212, the small beam 216 connected thereto is raised, and an upward force is applied to the anchor 218 connected to the small beam 216. Since the lower end of the anchor 218 is fixed to the concrete slab 202 by the adsorption part 220, the concrete slab 202 is eventually pulled upward. In this way, the trajectory error of the trajectory 206 is corrected. At this time, since the distance between the concrete slab 202 and the concrete roadbed 200 changes, the filler 204 is peeled off from the concrete slab 202 or the concrete roadbed 200.

従ってこの間隙に新たに充填材を注入すればよい。例えば、この間隙をコンクリートスラブ202の外周を型枠で囲んだり、他のシール材を詰めて注入する充填材が外へ流出しないように対策した上で充填材を注入すればよい。この時、間隙にくさびなどを用いて高さを固定しておけば、こう上治具208を外して別の場所での作業に使用できるので、作業能率が向上する。   Therefore, a new filler may be injected into this gap. For example, the filler may be injected after measures are taken so that the outer periphery of the concrete slab 202 is surrounded by a mold or the filler to be injected after filling with another sealing material is prevented from flowing out. At this time, if the height is fixed using a wedge or the like in the gap, the upper jig 208 can be removed and used for work in another place, so that work efficiency is improved.

この実施例では、アンカー218を各軌道206の両側にそれぞれ配置しているので、左右の軌道206ごとに別々に軌道狂いを行うことができることになり、軌道狂いを精度高く補正するのに適する。   In this embodiment, since the anchors 218 are arranged on both sides of each track 206, the track misalignment can be performed separately for each of the left and right tracks 206, which is suitable for correcting the track misalignment with high accuracy.

1、206 軌道(レール)
2 枕木
3 バラスト
4 填充層
10、100、208 こう上治具
12、102 支持部
14、104、214 梁部
16、210 下部ジャッキ
18 アンカー定着部
20 充填材注入用注入管である鋼管(パイル)
28、218 アンカー
34 注入管挿入用の削孔
42、212 上部ジャッキ
60 間隙
102 支持部
104 形鋼(梁部)
108 下部ジャッキのナットリング
110、150 パッカー
164 小孔
166 逆止弁
1,206 Track (rail)
2 Sleeper 3 Ballast 4 Filling layer 10, 100, 208 Raising jig 12, 102 Supporting part 14, 104, 214 Beam part 16, 210 Lower jack 18 Anchor fixing part 20 Steel pipe (pile) which is an injection pipe for filling material injection
28, 218 Anchor 34 Injection hole insertion hole 42, 212 Upper jack 60 Gap 102 Support part 104 Shape steel (beam part)
108 Nut ring of lower jack 110, 150 Packer 164 Small hole 166 Check valve

Claims (13)

バラストとまくら木を固結した構造の省力化軌道の軌道狂い補修方法において、
a)前記まくら木とバラストを固めた填充層の上面にリフトアップ用の複数のアンカーを設置する;
b)前記填充層の外側でバラスト層に両端が支持され軌道および前記アンカーを横断する門型のこう上治具を設置する;
c)前記アンカーを前記こう上治具に設けたジャッキによって引き上げ、前記填充層をバラストから浮かせることによって軌道高さを微調整する;
d)バラストと填充層との間にできる間隙に充填材を充填する;
以上の各工程を有する省力化軌道の軌道狂い補修方法。
In the labor-saving track orbit repair method of the structure that consolidated ballast and sleepers,
a) installing a plurality of lift-up anchors on the upper surface of the filling layer in which the sleeper tree and ballast are hardened;
b) installing a portal-type rising jig that is supported at both ends by the ballast layer outside the filling layer and traverses the track and the anchor;
c) The anchor is lifted up by a jack provided on the upper jig, and the orbital height is finely adjusted by lifting the filling layer from the ballast;
d) filling the gap formed between the ballast and the filling layer with a filler;
A method of repairing the track error of the labor-saving track having the above steps.
アンカーは、填充層にドリル加工したアンカー孔に接着系アンカーを固着したアンカー定着部に着脱可能に固定され、アンカーを取り外した状態でアンカー孔に防護蓋が着脱可能である請求項1の省力化軌道の軌道狂い補修方法。   2. The labor saving according to claim 1, wherein the anchor is detachably fixed to an anchor fixing portion in which an adhesive anchor is fixed to an anchor hole drilled in a filling layer, and a protective cover is detachable to the anchor hole in a state where the anchor is removed. How to repair the track error. アンカーおよびアンカー定着部は、軌道横断方向の直線上で軌道の外側と軌道の間の複数箇所に設けている請求項1又は2の省力化軌道の軌道狂い補修方法。   3. The track error correcting method for a labor-saving track according to claim 1 or 2, wherein the anchor and the anchor fixing portion are provided at a plurality of locations between the outside of the track and the track on a straight line in the traverse direction. こう上治具は、一対の支持部と、両支持部に掛け渡された梁部と、両支持部に設けられ前記梁部の高さ調整用下部ジャッキとを備え、前記工程b)では前記下部ジャッキによってアンカーの高さを粗調整し、前記工程c)では前記梁部に保持した微調整用の上部ジャッキによって軌道高さを微調整する請求項1の省力化軌道の軌道狂い補修方法。   The upper jig includes a pair of support portions, a beam portion spanned between both support portions, and a lower jack for adjusting the height of the beam portion provided on both support portions, and in the step b), 2. The track error correcting method for a labor-saving track according to claim 1, wherein the height of the anchor is roughly adjusted by a lower jack, and the track height is finely adjusted by an upper jack for fine adjustment held in the beam portion in the step c). 下部ジャッキおよび上部ジャッキは油圧式ジャッキである請求項4の省力化軌道の軌道狂い補修方法。   The method for repairing a track error of a labor-saving track according to claim 4, wherein the lower jack and the upper jack are hydraulic jacks. 工程a)では、填充層にアンカーを設置すると共に、填充層を貫通してバラストおよびその下方土路盤に達する注入管を設置しておき、
工程d)では、前記注入管から空隙とそのその下方に充填材を注入する請求項1の省力化軌道の軌道狂い補修方法。
In step a), an anchor is installed in the filling layer, and an injection pipe that penetrates the filling layer and reaches the ballast and the lower ground bed is installed.
In step d), the labor-saving trajectory repair method of the labor-saving trajectory according to claim 1, wherein a gap and a filler are injected from the injection pipe into the gap and below the gap.
注入管は、削孔機で形成した削孔に挿入され多数の小孔が形成された鋼管であり、その上端開口には防護蓋が着脱可能である請求項6の省力化軌道の軌道狂い補修方法。   The injection pipe is a steel pipe inserted into a drilling hole formed by a drilling machine and formed with a large number of small holes, and a protective lid is detachable at the upper end opening thereof. Method. 小孔には逆止弁が取り付けられ、削孔形成時の削り屑や充填材が注入管内に入るのを防止している請求項7の省力化軌道の軌道狂い補修方法。   The method of repairing a track error in a labor-saving track according to claim 7, wherein a check valve is attached to the small hole to prevent swarf and filler during the formation of the hole from entering the injection pipe. 注入管には、注入管の途中に固定位置可変でかつ充填材が通過可能なパッカーが挿入され、このパッカーを間隙より下方に固定した状態で充填材をこのパッカーを通してその下に注入し、その後パッカーを間隙より上方に移動して固定した後充填材を間隙に注入する請求項7の省力化軌道の軌道狂い補修方法。   In the injection tube, a packer is inserted in the middle of the injection tube, the fixing position of which is variable and the filler can pass through. The filler is injected below through the packer while the packer is fixed below the gap. 8. The method of repairing a track error of a labor-saving track according to claim 7, wherein after the packer is moved and fixed above the gap, the filler is injected into the gap. アンカー定着部は、ドリルによる削孔に接着系アンカーを挿入し、これに先端を尖らせた全ネジあるいは異形鋼棒を打ち込むことによって接着系アンカーの容器を破壊し化学反応を起こさせて固定したものであり、ここに固着した前記全ネジあるいは異形鋼棒の上端に固着したリフトアップ用接続ナットに螺入した着脱可能な長ネジをアンカーとしたものである請求項2の省力化軌道の軌道狂い補修方法。   The anchor fixing part inserts the adhesive anchor into the drilling hole, and drives the fixed anchor rod by destroying the container of the adhesive anchor by driving all screws or deformed steel bars with a sharpened tip into it. 3. The track of the labor-saving track according to claim 2, wherein the whole screw fixed here or the detachable long screw screwed into the connection nut for lift-up fixed to the upper end of the deformed steel bar is used as an anchor. Crazy repair method. コンクリートスラブに軌道を固定したスラブ軌道の軌道狂い補修方法において、
a′)前記コンクリートスラブの上面にリフトアップ用の複数のアンカーを設置する;
b′)前記コンクリートスラブの外側で路盤に両端が支持され軌道および前記アンカーを横断する門型のこう上治具を設置する;
c′)前記アンカーを前記こう上治具に設けたジャッキによって引き上げ、前記コンクリートスラブを路盤から浮かせることによって軌道高さを微調整する;
d′)路盤とコンクリートスラブとの間にできる間隙に充填材を充填する;
以上の各工程を有するスラブ軌道の軌道狂い補修方法。
In the method of repairing the track deviation of the slab track with the track fixed to the concrete slab,
a ') installing a plurality of lift-up anchors on the upper surface of the concrete slab;
b ') installing a portal-type uplifting jig that is supported by the roadbed outside the concrete slab and that crosses the track and the anchor;
c ′) The anchor is lifted by a jack provided on the upper jig, and the concrete slab is lifted from the roadbed to finely adjust the track height;
d ') Filling the gap created between the roadbed and the concrete slab;
A method for repairing a slab track trajectory that has the above steps.
アンカーは、スラブ表面に吸着された真空チャックである請求項11のスラブ軌道の軌道狂い補修方法。   12. The method of repairing a slab track trajectory error according to claim 11, wherein the anchor is a vacuum chuck adsorbed on the slab surface. こう上機は、1つのコンクリートスラブに対して軌道長さ方向に所定間隔ごとに複数台設置され、これらが同期して駆動されて1つのコンクリートスラブ全体が同時にこう上される請求項11のスラブ軌道の軌道狂い補修方法。   The slab according to claim 11, wherein a plurality of the raising machines are installed at predetermined intervals in the track length direction with respect to one concrete slab, and these are driven synchronously so that one whole concrete slab is simultaneously raised. How to repair the track error.
JP2011181461A 2011-08-23 2011-08-23 Track deviation repair method for track Withdrawn JP2013044126A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011181461A JP2013044126A (en) 2011-08-23 2011-08-23 Track deviation repair method for track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011181461A JP2013044126A (en) 2011-08-23 2011-08-23 Track deviation repair method for track

Publications (1)

Publication Number Publication Date
JP2013044126A true JP2013044126A (en) 2013-03-04

Family

ID=48008253

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011181461A Withdrawn JP2013044126A (en) 2011-08-23 2011-08-23 Track deviation repair method for track

Country Status (1)

Country Link
JP (1) JP2013044126A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105064149A (en) * 2015-08-13 2015-11-18 中铁十一局集团有限公司 Track skeleton adjusting device
JP2016172970A (en) * 2015-03-17 2016-09-29 東日本旅客鉄道株式会社 Subgrade raising method
CN106400622A (en) * 2016-05-31 2017-02-15 中铁第四勘察设计院集团有限公司 Repair structure for plate type ballastless track in turnout zone
KR102378945B1 (en) * 2022-01-06 2022-03-28 주식회사 브리텍 Rail bed repair and reinforcement construction method for railway

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016172970A (en) * 2015-03-17 2016-09-29 東日本旅客鉄道株式会社 Subgrade raising method
CN105064149A (en) * 2015-08-13 2015-11-18 中铁十一局集团有限公司 Track skeleton adjusting device
CN106400622A (en) * 2016-05-31 2017-02-15 中铁第四勘察设计院集团有限公司 Repair structure for plate type ballastless track in turnout zone
KR102378945B1 (en) * 2022-01-06 2022-03-28 주식회사 브리텍 Rail bed repair and reinforcement construction method for railway

Similar Documents

Publication Publication Date Title
CN110924961B (en) Construction method for starting shield tunneling machine to pass through existing station
CN106437737B (en) Pipe jacking type coal mine small-section roadway tunneling method
CN110846967B (en) Method and apparatus for reconstructing a road surface for highway construction
JP2013044126A (en) Track deviation repair method for track
CN105821835A (en) Water injection type rotary drilling construction method for cast-in-situ bored pile
JP5554176B2 (en) Method for reinforcing bearing capacity of track
CN111608192A (en) Method and device for installing steel sheet pile in large-diameter boulder and sandstone stratum
CN109931077B (en) Support system for tunnel repair and construction method thereof
KR20170118640A (en) Restoration construction method of road subsided by weak ground
CN100523389C (en) Ballastless track steel reinforced concrete pile-net construction method
CN107989042B (en) Construction method of pile planting machine
KR100963880B1 (en) Excavating method for underground plaza using steel casing retaining wall
CN110258191B (en) Deviation rectifying and reinforcing method for transverse displacement of high-speed railway roadbed
JP5472878B2 (en) Labor-saving track lift-up device and lift-up method
CN109024670B (en) Underground comprehensive pipe gallery protection and reinforcement system penetrating through buried high-voltage cable and reinforcement method
CN104153355B (en) The constructing device of concrete-pile and construction method thereof
CN113266019B (en) Construction method of foundation pit steel pipe support system
CN110985017B (en) Construction method for shield tunneling of rainwater box culvert under expansive soil stratum
RU2334839C1 (en) Method of tunnel railway base repair
CN107869139B (en) Pile planting machine with monitoring function
JP2874573B2 (en) Rail foundation and its repair method
JP5348781B2 (en) Repair method of substructure
JP4049467B2 (en) How to correct uneven settlement of soil concrete
CN113322936B (en) Soil body reinforcing construction method and construction auxiliary device for thick sand layer karst area
CN112267893B (en) Construction method of large-section tunnel

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20141104