JP2013019245A - Combination steel sheet pile, underground continuous wall, and method of removing combination steel sheet pile - Google Patents
Combination steel sheet pile, underground continuous wall, and method of removing combination steel sheet pile Download PDFInfo
- Publication number
- JP2013019245A JP2013019245A JP2011155709A JP2011155709A JP2013019245A JP 2013019245 A JP2013019245 A JP 2013019245A JP 2011155709 A JP2011155709 A JP 2011155709A JP 2011155709 A JP2011155709 A JP 2011155709A JP 2013019245 A JP2013019245 A JP 2013019245A
- Authority
- JP
- Japan
- Prior art keywords
- sheet pile
- steel sheet
- shaped steel
- hat
- web
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
本発明は、建築土木工事で主に土砂などの崩落を防ぐ土留め壁や地下構造物の壁、河川の仮締切などとして広く用いられる主として仮設用の組合せ鋼矢板及び地中連続壁並びに組合せ鋼矢板の撤去方法に関する。 The present invention mainly relates to a combination steel sheet pile and an underground continuous wall and a combination steel for temporary use, which are widely used as a retaining wall, a wall of an underground structure, a temporary cut-off of a river, etc. for preventing collapse of earth and sand in a civil engineering work. It relates to the method of removing the sheet pile.
一般に、地盤を掘削して地下に構造物を構築する際の工法は、仮設土留めを用いて掘削した後に本体壁を構築する工法や、仮設・本設兼用でソイルセメント壁、場所打ち鉄筋コンクリート壁を構築する工法が主流である。 In general, when excavating the ground and constructing a structure underground, the main wall is constructed after excavating with a temporary earth retaining, or a soil cement wall or cast-in-place reinforced concrete wall for temporary and permanent construction. The construction method is the mainstream.
しかしながら、仮設土留めを用いる工法のうち、ソイルセメント壁やコンクリート壁といったコンクリート系の壁体では、地下構造物構築後に仮設土留めを撤去できず、後発のプロジェクトへの影響が問題となる。 However, among the construction methods using temporary earth retaining, with concrete walls such as soil cement walls and concrete walls, the temporary earth retaining cannot be removed after the construction of the underground structure, and the effect on subsequent projects becomes a problem.
また、引抜きが可能な鋼材系の仮設土留めとしては親杭横矢板工法や鋼矢板が挙げられるが、掘削深度が10m程度以上となる場合には、断面剛性が不足することが多く、適用できないまたはタイロッドやアンカー等の付帯構造が必要となる。 Moreover, the steel pile-type temporary earth retaining that can be pulled out includes the parent pile sheet pile method and the steel sheet pile, but when the excavation depth is about 10 m or more, the cross-sectional rigidity is often insufficient and is not applicable. Or an incidental structure such as a tie rod or an anchor is required.
このような課題に対し、掘削深度10m程度以上の工事に適用可能な大断面の土留め部材として、500〜2000mm程度の鋼管に、直径165mm程度のスリット付き鋼管を継手として取付けた鋼管矢板が利用されている。 For such a problem, a steel pipe sheet pile in which a steel pipe with a slit of about 165 mm in diameter is attached as a joint to a steel pipe of about 500 to 2000 mm is used as a large cross-section retaining member applicable to construction with an excavation depth of about 10 m or more. Has been.
また、地中連続壁に用いる壁材として、鋼矢板とH形鋼を組合せた組合せ鋼矢板、例えば、鋼矢板にH形鋼を、連続又断続して溶接接合した組合せ鋼矢板も知られている。 Further, as a wall material used for the underground continuous wall, a combination steel sheet pile in which steel sheet piles and H-section steel are combined, for example, a combination steel sheet pile in which H-section steel is continuously or intermittently welded to a steel sheet pile, is also known. Yes.
例えば、特許文献1では、左右の継手形状が非対称な直線鋼矢板とH形鋼とを溶接接合した壁形鋼矢板とその製造方法の技術が開示されている。
For example,
また、特許文献2では、図25に示すように、左右の継手形状が非対称の略U字形状の鋼矢板27にH形鋼28を溶接Wあるいはボルト29及びナット30を用いて接合した組合せ鋼矢板24からなる地中連続壁用鋼材31が開示されている。
Further, in
さらに、特許文献3では、鋼矢板の表裏面の片面に加工治具を設け、補剛材としてH形鋼等の形鋼を嵌合できるようしたものが開示されている。
Furthermore,
また、幅方向の中央部にウェブを有し且つ両端部に継手を有する鋼矢板と、ウェブの端部にフランジを有するH形鋼とから形成され、鋼矢板のウェブと、H形鋼の片方のフランジとが、互いに重ね合わされて、H形鋼のフランジから突出するようにドリルねじにより接合して組合せ鋼矢板とする技術も知られている(例えば、特許文献4参照)。 Moreover, it is formed from a steel sheet pile having a web at the center in the width direction and joints at both ends, and an H-section steel having a flange at the end of the web, and the steel sheet pile web and one of the H-section steels There is also known a technique in which the flanges are combined with each other and joined with a drill screw so as to protrude from the flange of the H-shaped steel to form a combined steel sheet pile (for example, see Patent Document 4).
前記従来の技術における鋼管矢板の場合は、使用後にはこの鋼管が土水圧により変形することが多いため再利用できず、1回のみの使い切りとなり、コストが嵩むという問題がある。また、鋼管矢板は中空の形状であるため、その輸送・保管に嵩張るため、輸送・保管効率が悪いといった問題もあり、この面でもコストが嵩むという問題もある。 In the case of the steel pipe sheet pile in the prior art, the steel pipe is often deformed by earth water pressure after use, and thus cannot be reused. Moreover, since the steel pipe sheet pile has a hollow shape, it is bulky in transportation and storage, so that there is a problem that transportation and storage efficiency is poor, and there is also a problem that costs increase in this respect.
前記の組合せ鋼矢板は、ハット形鋼矢板のウェブとH形鋼のフランジとを隅肉溶接により接合しており、全体としてY型断面等の嵩む断面形態の組合せ鋼矢板となるため、輸送・保管が非効率になるという問題もある。また、このような組合せ鋼矢板でも、1回のみの使い切りとなるため建設コストが嵩むという問題がある。 The combination steel sheet pile has a hat-shaped steel sheet pile web and a H-shaped steel flange joined together by fillet welding, resulting in a combined steel sheet pile having a bulky cross-sectional shape such as a Y-shaped cross section as a whole. There is also the problem that storage becomes inefficient. Moreover, even such a combination steel sheet pile has a problem that the construction cost increases because it is used up only once.
また、都市内施工の場合は、騒音・振動に配慮しなければならないため圧入工法を必要とすることが多く、従来のU形鋼矢板等よりも断面積及び平面外径寸法が大きい全体としてY型断面等の嵩む断面形態の組合せ鋼矢板では、特殊な把持装置を備えた施工機械を用いなければならず、その施工に建設コストが増大する、または把持装置に鋼矢板が収まらず施工出来ないため、台数の少ない特殊な大型機械が必要になり、圧入施工・引き抜き撤去の両方にそのような大型施工機械が必要になると、コストが高くなるという問題がある。 In addition, in the case of construction in the city, a press-in method is often required because noise and vibration must be taken into account, and the overall cross-sectional area and planar outer diameter are larger than conventional U-shaped steel sheet piles. In combination steel sheet piles with a bulky cross-sectional shape such as a mold section, a construction machine with a special gripping device must be used, and the construction cost increases for that construction, or the steel sheet pile does not fit in the gripping device and construction is not possible Therefore, a special large-sized machine with a small number of units is required, and if such a large-sized construction machine is required for both press-fitting construction and pull-out removal, there is a problem that costs increase.
前記の特許文献1〜3に記載の組合せ鋼矢板は、通常の鋼矢板よりも表面積が大きくなるため地盤の摩擦抵抗が大きくなり、使用後に引き抜けない、または、引抜きに大がかりな施工機械を必要とするという問題がある。
The combined steel sheet piles described in
また、掘削深度10m超の仮設土留め(地盤を掘削し地下構造物を構築する際に用いる仮設の壁体。)に適用する場合、鋼矢板が長くなるため地盤の摩擦抵抗が大きくなり、組合せ鋼矢板が引き抜けない、または、引抜きに大がかりな施工機械を必要とするという問題がある。 In addition, when applied to temporary earth retaining with a depth of excavation of more than 10 m (temporary wall used when excavating the ground and constructing an underground structure), the steel sheet pile becomes longer, so the frictional resistance of the ground increases. There is a problem that the steel sheet pile cannot be pulled out, or that a construction machine requiring a large scale for drawing is required.
全体としてY型断面等の嵩む断面形態の組合せ鋼矢板24を引抜く場合には、図23(a)に示すように、ハット形鋼矢板10の両端の爪とH形鋼20のフランジ両端の先端を結ぶ線分の交点の三点を結ぶ三角形状に閉塞空間25が形成され、組合せ鋼矢板24と共に周辺地盤26も掘り出されて、沈下や傾斜といった問題が生じる。
When the combined
鋼矢板の片面にH形鋼を接合した組合せ鋼矢板を地盤に圧入等により貫入した場合、H型鋼と反対側の鋼矢板の裏面が地盤開削側となるが、H形鋼側から鋼矢板に溶接接合したり、又は鋼矢板の表裏からのボルト・ナットにより接合されている場合には、鋼矢板が掘削側に配置されている場合には、組合せ鋼矢板の引抜き後でなければ、鋼矢板とH形鋼とに別々に分離が出来ないという問題がある。 When a combined steel sheet pile in which H-shaped steel is joined to one side of the steel sheet pile is inserted into the ground by press-fitting etc., the reverse side of the steel sheet pile opposite to the H-shaped steel is the ground excavation side, but from the H-shaped steel side to the steel sheet pile If it is welded or joined by bolts and nuts from the front and back of the steel sheet pile, and if the steel sheet pile is placed on the excavation side, then the steel sheet pile must be There is a problem that it cannot be separated separately from H-shaped steel.
鋼矢板と補剛材を現場で別々に打設する場合に、引抜き前の分離が可能であるが、地中連続壁構築時にも別々に施工する必要があり、施工効率が落ちるといった問題がある。さらに、組合せ鋼矢板の上端のみを固定する構造である場合には、打設時に先端が開く恐れがあるとい問題がある。このような問題を回避すべく、先端を仮留めする方法も提案されているが、鋼矢板とH形鋼を分離することができず、引抜き後でなければ別々に分離できない。 When placing steel sheet piles and stiffeners separately on site, separation before drawing is possible, but it is necessary to construct them separately even when building underground continuous walls, resulting in a problem of reduced construction efficiency. . Furthermore, when it is a structure which fixes only the upper end of a combination steel sheet pile, there exists a problem that there exists a possibility that a front-end | tip may open at the time of placement. In order to avoid such a problem, a method of temporarily fixing the tip has also been proposed, but the steel sheet pile and the H-shaped steel cannot be separated, and cannot be separated separately unless after drawing.
また、図24に示すように、従来の鋼矢板27の片面にH形鋼を固定した分離不能な仮設用組合せ鋼矢板24からなる地中連続壁用鋼材31を地盤に貫入した仮設土留め壁では、仮設土留め壁間を開削後、地下構造物のコンクリートを打設する際の型枠の設置等のためには、仮設土留め壁31との間に、型枠・作業スペースGとして1m程度の離間を設けなければならず、敷地を有効利用できないとった問題がある。
Moreover, as shown in FIG. 24, the temporary earth retaining wall which penetrated into the ground the
ドリルねじ(ドリリングタッピングねじ)により鋼矢板とH形鋼を、H形鋼と反対側の鋼矢板側からH形鋼のフランジを貫通させて、しかも突出させる接合形態では、突出したドリルねじの先端部が地盤貫入時に石等の小障害物に衝突して曲がる恐れがあると共に、地盤貫入時及び引き抜き時に、ドリルねじのねじ部が損傷するため、1回のみの使用になり、このような形態では、そもそも、鋼矢板とH形鋼を分離して再利用するようなことは考慮されておらず、再利用しようとしても、ドリルねじにより先のねじ孔に合致するように接合することは困難であり、新たな雌ねじ孔が削孔されるために、先に設けたねじ孔が損傷部として残るようになるという問題がある。また、H形鋼と鋼矢板に貫通孔を設けるため水みちが形成され、漏水しやすい、或いはドリルねじが錆びやすいといった問題がある。 In the joining form in which the steel sheet pile and the H-shaped steel are passed through the flange of the H-shaped steel from the steel sheet pile side opposite to the H-shaped steel by the drill screw (drilling tapping screw), and the protruding form, the tip of the protruding drill screw Since the part may collide with a small obstacle such as a stone when it enters the ground and bends, the threaded part of the drill screw is damaged when the ground penetrates and when it is pulled out. In the first place, however, it is not considered that the steel sheet pile and the H-shaped steel are separated and reused, and it is difficult to join the steel sheet pile to match the previous screw hole by using a drill screw. Then, since a new female screw hole is drilled, there is a problem that the previously provided screw hole remains as a damaged portion. Further, since a through hole is provided in the H-shaped steel and the steel sheet pile, a water channel is formed, and there is a problem that the water leaks easily or the drill screw easily rusts.
そこで、本発明は、鋼矢板とH形鋼とを組み合わせた組合せ鋼矢板で、打設時には、一体に施工でき、地盤開削側から鋼矢板とH形鋼の接合部の解除が容易で、開削後の引き抜き時には、鋼矢板とH形鋼とに別々に分離して、選択して引き抜くことが可能な鋼矢板とH形鋼との組合せ鋼矢板及び地中連続壁並びに組合せ鋼矢板の撤去方法を提供することを目的とする。 Therefore, the present invention is a combined steel sheet pile combining a steel sheet pile and an H-shaped steel, which can be constructed integrally at the time of placing, and the joint between the steel sheet pile and the H-shaped steel can be easily released from the ground excavation side. Method of removing steel sheet pile and H-shaped steel combined steel sheet pile and underground continuous wall and combined steel sheet pile that can be separately separated into steel sheet pile and H-shaped steel at the time of subsequent drawing The purpose is to provide.
第1発明の組合せ鋼矢板においては、幅方向の中央部にウェブを有すると共に両端部に継手を有する鋼矢板の片面における前記ウェブに、H型鋼のフランジを重ね合わせて接合されている組合せ鋼矢板であって、鋼矢板のウェブとH型鋼のフランジとが、前記H型鋼と反対側の地盤開削側の面であって地中に位置される下部部分を除く上部部分で、H形鋼のフランジ部と前記鋼矢板のウェブが接する面でのみせん断抵抗を持たせた接合構造で接合され、かつ当該接合構造は、H形鋼のフランジ部よりも地盤側に突出していないボルト、ねじ若しくは隅肉溶接のいずれかによる接合構造であって取外し可能とされていることを特徴とする。 In the combined steel sheet pile of the first invention, the combined steel sheet pile having a web at the center in the width direction and a web of one side of the steel sheet pile having joints at both ends, and an H-shaped steel flange is overlapped and joined. The steel sheet pile web and the H-shaped steel flange are the upper part of the ground cutting side opposite to the H-shaped steel and excluding the lower part located in the ground. Bolts, screws or fillets that are joined with a joining structure having shear resistance only on the surface where the web of the sheet pile and the steel sheet pile contact, and the joining structure does not protrude from the flange side of the H-shaped steel It is a joining structure by any one of welding, and can be removed.
第2発明では、第1発明の組合せ鋼矢板において、前記鋼矢板は、ウェブの両端に一対のフランジが連設され、上記フランジの他端にアームが連設されていると共に、そのアームの先端部に継手を設けた断面ハット形のハット形鋼矢板であり、そのハット形鋼矢板のウェブに、上下方向に間隔をおいて多数の孔又は雌ねじ孔が設けられ、H形鋼のフランジに上下方向に間隔をおいて多数の雌ねじ孔が設けられ、前記ハット形鋼矢板のウェブの孔に挿通又はウェブの雌ねじ孔にねじ込まれる共にH形鋼のフランジの雌ねじ孔にねじ込まれた着脱自在なボルトにより接合されていることを特徴とする。 In the second invention, in the combined steel sheet pile of the first invention, the steel sheet pile has a pair of flanges connected to both ends of the web, an arm connected to the other end of the flange, and a tip of the arm. This is a hat-shaped steel sheet pile with a cross-section with joints in the section. The web of the hat-shaped steel sheet pile is provided with a number of holes or internal thread holes at intervals in the vertical direction, and the flange of the H-shaped steel is vertically A detachable bolt provided with a large number of internally threaded holes at intervals in the direction, inserted into the web hole of the hat-shaped steel sheet pile or screwed into the internally threaded hole of the web, and screwed into the internally threaded hole of the H-shaped steel flange It is characterized by being joined by.
第3発明では、第1発明の組合せ鋼矢板において、前記鋼矢板は、ウェブの両端に一対のフランジが連設され、上記フランジの他端にアームが連設されていると共に、そのアームの先端部に継手を設けた断面ハット形のハット形鋼矢板であり、そのハット形鋼矢板のウェブに、上下方向に間隔をおいて多数の孔が設けられ、前記ハット形鋼矢板のウェブの孔の内周面とH形鋼のフランジとが溶断撤去又は研削撤去可能な隅肉溶接により接合されていることを特徴とする。 In the third invention, in the combined steel sheet pile according to the first invention, the steel sheet pile has a pair of flanges connected to both ends of the web, an arm connected to the other end of the flange, and a tip of the arm. A hat-shaped steel sheet pile having a cross-section with a joint at the section, and a plurality of holes are provided in the hat-shaped steel sheet pile web at intervals in the vertical direction. The inner peripheral surface and the flange of the H-shaped steel are joined by fillet welding capable of fusing removal or grinding removal.
第4発明では、第1発明の組合せ鋼矢板において、前記鋼矢板は、ウェブの両端に一対のフランジが連設され、上記フランジの他端にアームが連設されていると共に、そのアームの先端部に継手を設けた断面ハット形のハット形鋼矢板であり、そのハット形鋼矢板のウェブとH形鋼のフランジとが、上下方向に間隔をおいてハット形鋼矢板側からの多数のドリルねじにより接合され、前記各ドリルねじの先端がH形鋼のフランジから突出していないことを特徴とする。 According to a fourth invention, in the combined steel sheet pile of the first invention, the steel sheet pile has a pair of flanges connected to both ends of the web, an arm connected to the other end of the flange, and a tip of the arm. A hat-shaped steel sheet pile having a hat-shaped cross-section with joints in the section, and a number of drills from the hat-shaped steel sheet pile side with the web of the hat-shaped steel sheet pile and the flange of the H-shaped steel spaced apart in the vertical direction It joins with a screw | thread, The front-end | tip of each said drill screw does not protrude from the flange of H-section steel, It is characterized by the above-mentioned.
第5発明では、第1発明〜第4発明のいずれか1つの組合せ鋼矢板において、組合せ鋼矢板の断面係数が、3,500cm3/m〜14,000cm3/mとされていることを特徴とする。 In the fifth invention, characterized in that in any one of the combination sheet pile of the first invention to the fourth invention, the section modulus of the combination sheet pile has been with 3,500cm 3 / m~14,000cm 3 / m And
第6発明の地中連続壁においては、第1発明〜第5発明のいずれかの複数枚の組合せ鋼矢板が、継手相互を嵌合して打設されて構築されていることを特徴とする。 In the underground continuous wall of the sixth invention, a plurality of the combined steel sheet piles of any one of the first invention to the fifth invention are constructed by fitting and fitting the joints to each other. .
第7発明の組合せ鋼矢板の撤去方法においては、第6発明の地中連続壁における組合せ鋼矢板の撤去方法であって、該地中連続壁におけるH形鋼と反対側の鋼矢板側の地盤を開削して開削溝を形成すると共に、開削溝側に地下構造物を構築した後、開削溝側の空間から鋼矢板とH形鋼との接合部を解除して分離し、H形鋼と鋼矢板を別々に引抜くことを特徴とする。 In the method for removing the combined steel sheet pile of the seventh invention, the method for removing the combined steel sheet pile in the underground continuous wall of the sixth invention, wherein the ground on the steel sheet pile side opposite to the H-shaped steel in the underground continuous wall To form an open groove, and after constructing an underground structure on the open groove side, the joint between the steel sheet pile and the H-section steel is released and separated from the space on the open groove side. The steel sheet pile is pulled out separately.
第8発明の組合せ鋼矢板の一部の撤去方法では、第6発明の地中連続壁における組合せ鋼矢板の一部の撤去方法であって、該地中連続壁におけるH形鋼と反対側の鋼矢板側の地盤を開削して開削溝を形成すると共に、鋼矢板を型枠として地下構造物を構築した後、開削溝側の空間から鋼矢板とH形鋼との接合部を解除して分離し、H形鋼のみを引抜くことを特徴とする。 In the method for removing a part of the combined steel sheet pile of the eighth invention, the method for removing a part of the combined steel sheet pile in the underground continuous wall of the sixth invention, After excavating the ground on the steel sheet pile side to form an open groove, and constructing an underground structure using the steel sheet pile as a formwork, release the joint between the steel sheet pile and the H-shaped steel from the space on the open groove side It separates and only H shape steel is pulled out.
第1発明の組合せ鋼矢板によると、幅方向の中央部にウェブを有すると共に両端部に継手を有する鋼矢板の片面における前記ウェブに、H型鋼のフランジを重ね合わせて接合されている組合せ鋼矢板であって、鋼矢板のウェブとH型鋼のフランジとが、前記H型鋼と反対側の地盤開削側の面であって地中に位置される下部部分を除く上部部分で、H形鋼のフランジ部と前記鋼矢板のウェブが接する面でのみせん断抵抗を持たせた接合構造で接合され、かつ当該接合構造は、H形鋼のフランジ部よりも地盤側に突出していない、ボルト、ねじ若しくは隅肉溶接のいずれかによる接合構造であって取外し可能とされているので、次の(1)〜(7)の効果が得られる。
(1)ハット形鋼矢板とH形鋼の接合部を開削溝側から解除して、ハット形鋼矢板とH形鋼を分離できるため、分離が容易になり、また、ハット形鋼矢板とH形鋼を別々に輸送・保管することが可能となるため、ハット形鋼矢板とH形鋼とが一体側の場合に比べて、輸送・保管コストを低減できる。
(2)ハット形鋼矢板とH形鋼を開削溝側からの接合部を解除して分離し、別々に引抜くことで地盤の周面抵抗を低減でき、大型で特殊な施工機械を用いることなく汎用の施工機械を用いて引抜き撤去を容易に行うことができる(従来では、ハット形鋼矢板とH形鋼の溶接接合箇所が背面土側に配置されている組合せ鋼矢板であるために、引抜き前にハット形鋼矢板とH形鋼を分離することは不可能で大型施工機械を用いる必要があったが、本発明の組合せ鋼矢板では、その必要がない。)。前記の周面摩擦は、引抜こうとする組合せ鋼矢板の表面積に依存するため、ハット形鋼矢板とH形鋼とを別々に引抜くことで、ハット形鋼矢板単体は組合せ鋼矢板の約4割の力で、H形鋼は約6割の力で引抜きが可能となる。したがって、組合せ鋼矢板を一体として引抜く場合よりも小さな施工機械で引抜きが可能となり施工コストを低減できる。例えば、バイブロハンマ等で打設・引抜きを行う場合でも、小型の施工機械で引抜きが可能となる。
(3)損耗し易いハット形鋼矢板のみを交換し再利用することが可能で、建設コストを低減できる。(従来は1回使い切りで全損する場合もあり、全体の鋼材重量の約6、7割を占めるH形鋼を本発明では、転用可能になる。)
(4)組合せ鋼矢板におけるH形鋼に代えて、サイズの異なるH形鋼を組み合わせることが可能で、異なる断面剛性を必要とする別の施工現場においても合理的な壁体仕様とすることができる。
(5)ハット形鋼矢板とH形鋼を別々に引抜くことが可能であるため、施工機械における把持機構に収まらなかったサイズの組合せ鋼矢板でも引抜き可能となる。この際、前面側のハット形鋼矢板を把持して反力を確保することも可能になるため、H形鋼の引抜きも容易になる。
(6)ハット形鋼矢板とH形鋼の接合部がH形鋼のフランジよりも地山側に突出していないので、打設時および仮設土留め供用時の接合部の損傷を避けることができ、容易に分離することができる。
(7)H形鋼のフランジ部とハット形鋼矢板のウェブ接する面でのみせん断抵抗を持たせる構造であるので、図示を省略するが、フランジ幅がハット形鋼矢板のウェブ幅を上回るH形鋼であっても接合が容易となる(なお、従来の溶接による接合方法(H形鋼のフランジ側面を隅肉溶接する方法)の場合は、V字状になった部分を溶接をしなければならないためフレア溶接となり、接合品質を保つことは容易ではない。)。
According to the combined steel sheet pile of the first invention, a combined steel sheet pile having a web at the center in the width direction and a web of one side of the steel sheet pile having joints at both ends and being joined by overlapping a flange of an H-shaped steel. The steel sheet pile web and the H-shaped steel flange are the upper part of the ground cutting side opposite to the H-shaped steel and excluding the lower part located in the ground. Bolts, screws or corners that are joined with a joining structure having shear resistance only at the surface where the web of the sheet pile and the steel sheet pile contact, and the joining structure does not protrude to the ground side from the flange part of the H-shaped steel Since it is a joining structure by any of the meat welding and can be removed, the following effects (1) to (7) can be obtained.
(1) Since the joint between the hat-shaped steel sheet pile and the H-shaped steel is released from the cut groove side and the hat-shaped steel sheet pile and the H-shaped steel can be separated, the separation becomes easy. Since the shaped steel can be transported and stored separately, the transportation and storage costs can be reduced compared to the case where the hat-shaped steel sheet pile and the H-shaped steel are integrated.
(2) Using a large and special construction machine, the ground surface resistance of the ground can be reduced by separating the hat-shaped steel sheet pile and H-shaped steel by releasing the joint from the cut groove and separating them separately. Can be easily pulled out and removed using a general-purpose construction machine (conventionally, because it is a combined steel sheet pile in which the welded joint of the hat-shaped steel sheet pile and the H-shaped steel is arranged on the back soil side, It is impossible to separate the hat-shaped steel sheet pile and the H-shaped steel before drawing and it was necessary to use a large construction machine, but this is not necessary in the combined steel sheet pile of the present invention.) Since the circumferential friction depends on the surface area of the combined steel sheet pile to be pulled out, the hat-shaped steel sheet pile alone is about 4 times the combined steel sheet pile by pulling out the hat-shaped steel sheet pile and the H-shaped steel separately. The H-shaped steel can be pulled out with a force of about 60%. Therefore, drawing can be performed with a smaller construction machine than when the combined steel sheet pile is pulled out as a unit, and the construction cost can be reduced. For example, even when performing placement and extraction with a vibro hammer or the like, extraction can be performed with a small construction machine.
(3) It is possible to replace and reuse only the hat-shaped steel sheet pile that is easily worn out, thereby reducing the construction cost. (Conventionally, there is a case in which a single use up causes a complete loss, and in the present invention, it becomes possible to divert H-section steel that occupies about 60 to 70% of the total steel weight.)
(4) In place of the H-section steel in the combined steel sheet pile, it is possible to combine H-section steels of different sizes, and to make rational wall body specifications even in other construction sites that require different cross-sectional rigidity. it can.
(5) Since the hat-shaped steel sheet pile and the H-shaped steel can be pulled out separately, even a combination steel sheet pile having a size that does not fit in the gripping mechanism in the construction machine can be pulled out. At this time, the hat-shaped steel sheet pile on the front side can be gripped to ensure a reaction force, so that the H-shaped steel can be easily pulled out.
(6) Since the joint between the hat-shaped steel sheet pile and the H-shaped steel does not protrude from the H-shaped steel flange to the natural ground side, damage to the joint at the time of driving and temporary earthing service can be avoided. It can be easily separated.
(7) Since the structure has a shear resistance only on the surface of the flange portion of the H-shaped steel and the web of the hat-shaped steel sheet pile, the illustration is omitted, but the flange shape has a flange width exceeding the web width of the hat-shaped steel sheet pile. Even steel can be easily joined (in the case of the conventional welding method (method of fillet welding the flange side of H-shaped steel), the V-shaped part must be welded) Because it does not become flare welding, it is not easy to maintain the joint quality.)
第2発明によると、第1発明の組合せ鋼矢板において、前記鋼矢板は、ウェブの両端に一対のフランジが連設され、上記フランジの他端にアームが連設されていると共に、そのアームの先端部に継手を設けた断面ハット形のハット形鋼矢板であり、そのハット形鋼矢板のウェブに、上下方向に間隔をおいて多数の孔又は雌ねじ孔が設けられ、H形鋼のフランジに上下方向に間隔をおいて多数の雌ねじ孔が設けられ、前記ハット形鋼矢板のウェブの孔に挿通又はウェブの雌ねじ孔にねじ込まれる共にH形鋼のフランジの雌ねじ孔にねじ込まれた着脱自在なボルトにより接合されているので、ハット形鋼矢板側からのボルトによる簡単な接合構造とすることができ、ハット形鋼矢板の組立及び接合解除も、電動工具或は手動工具を用いてボルトの脱着作業でよいため、容易に接合又は分離することができる等の効果が得られる。 According to the second invention, in the combined steel sheet pile of the first invention, the steel sheet pile has a pair of flanges connected to both ends of the web and an arm connected to the other end of the flange. It is a hat-shaped steel sheet pile having a hat-shaped cross section provided with a joint at the tip, and the web of the hat-shaped steel sheet pile is provided with a number of holes or internally threaded holes at intervals in the vertical direction. A large number of female screw holes are provided at intervals in the vertical direction, and are detachable that are inserted into the screw holes of the hat-shaped steel sheet pile or screwed into the female screw holes of the web and screwed into the female screw holes of the flange of the H-shaped steel. Since it is joined by bolts, it can be a simple joining structure using bolts from the hat-shaped steel sheet pile side, and assembly and release of the hat-shaped steel sheet piles can also be performed using electric tools or manual tools. For good in wearing work, the effect of such can be easily joined or separated is obtained.
第3発明によると、第1発明の組合せ鋼矢板において、前記鋼矢板は、ウェブの両端に一対のフランジが連設され、上記フランジの他端にアームが連設されていると共に、そのアームの先端部に継手を設けた断面ハット形のハット形鋼矢板であり、そのハット形鋼矢板のウェブに、上下方向に間隔をおいて多数の孔が設けられ、前記ハット形鋼矢板のウェブの孔の内周面とH形鋼のフランジとが溶断撤去又は研削撤去可能な隅肉溶接により接合されているので、ハット形鋼矢板側からの隅肉溶接による簡単な接合構造とすることができ、ハット形鋼矢板の組立及び接合解除も、溶接による接合又は溶断或はグラインダー等の電動研削工具を用いた接合解除作業となるため、容易に接合又は分離することができる等の効果が得られる。
また、本発明の場合は、ハット形鋼矢板のフランジとウェブの隅角部に近い箇所で溶接する従来技術に比べ、よりハット形鋼矢板のウェブの幅方向の中心側で溶接可能となるため、加工時の熱変形(ハット形鋼矢板の全幅の広がり)を抑えることができる(従来の溶接タイプでは、ハット形鋼矢板のフランジとウェブの隅角部に近い箇所での溶接であったので、溶接熱によって、図25(a)における左右の傾斜したフランジがさらに外側に拡開するように広がり、ハット形鋼矢板の全幅が広がるような変形が生じる。)。
According to a third invention, in the combined steel sheet pile of the first invention, the steel sheet pile has a pair of flanges connected to both ends of the web, and an arm connected to the other end of the flange. A hat-shaped steel sheet pile having a cross-section with a joint at the tip, and a plurality of holes are provided in the hat-shaped steel sheet pile web at intervals in the vertical direction. Since the inner peripheral surface and the flange of the H-shaped steel are joined by fillet welding that can be removed by cutting or grinding, a simple joining structure by fillet welding from the hat-shaped steel sheet pile side can be achieved. Assembling and debonding of the hat-shaped steel sheet piles are also performed by joining or fusing by welding or a debonding operation using an electric grinding tool such as a grinder, so that effects such as easy joining or separation can be obtained.
Moreover, in the case of this invention, since it becomes possible to weld at the center side of the width direction of the web of a hat-shaped steel sheet pile compared with the prior art which welds in the location near the flange of a hat-shaped steel sheet pile, and the corner of a web. , Thermal deformation during processing (expansion of the full width of the hat-shaped steel sheet pile) can be suppressed (in the conventional welding type, welding was performed at a location close to the flange of the hat-shaped steel sheet pile and the corner of the web) The welding heat causes the left and right inclined flanges in FIG. 25 (a) to expand further outwardly, causing a deformation in which the full width of the hat-shaped steel sheet pile is expanded.
第4発明によると、第1発明の組合せ鋼矢板において、前記鋼矢板は、ウェブの両端に一対のフランジが連設され、上記フランジの他端にアームが連設されていると共に、そのアームの先端部に継手を設けた断面ハット形のハット形鋼矢板であり、そのハット形鋼矢板のウェブとH形鋼のフランジとが、上下方向に間隔をおいてハット形鋼矢板側からの多数のドリルねじにより接合され、前記各ドリルねじの先端がH形鋼のフランジから突出していないので、組合せ鋼矢板を地盤に圧入又は引抜く時に、ドリルねじの先端が変形又は損傷する恐れがないので、組合せ鋼矢板におけるハット形鋼矢板とH形鋼を分離する場合に、ドリルねじを容易に引抜いて分離することができる等の効果が得られる。また、H形鋼と鋼矢板に貫通孔を設けないため水みちが形成されることはなく、漏水やドリルねじの腐食を防止することができる等の効果が得られる。 According to a fourth invention, in the combined steel sheet pile of the first invention, the steel sheet pile has a pair of flanges connected to both ends of the web and an arm connected to the other end of the flange. A hat-shaped steel sheet pile having a cross-section with a joint provided at the tip, and the web of the hat-shaped steel sheet pile and the flange of the H-shaped steel are spaced from each other in the vertical direction at a large number from the hat-shaped steel sheet pile side. Since it is joined by a drill screw and the tip of each drill screw does not protrude from the flange of the H-shaped steel, there is no possibility that the tip of the drill screw will be deformed or damaged when the combined steel sheet pile is press-fitted or pulled out from the ground. When the hat-shaped steel sheet pile and the H-shaped steel in the combined steel sheet pile are separated, effects such as being able to easily pull out the drill screw and separate them are obtained. In addition, since no through-hole is provided in the H-shaped steel and the steel sheet pile, no water channel is formed, and effects such as prevention of water leakage and drill screw corrosion can be obtained.
第5発明によると、第1発明〜第4発明のいずれか1つの組合せ鋼矢板において、組合せ鋼矢板の断面係数が、3,500cm3/m〜14,000cm3/mとされているので、深度が10mを越え、25m程度の深さの地中連続壁でも、対応可能な組合せ鋼矢板とすることができる等の効果が得られる。 According to a fifth invention, in any one of the combination sheet pile of the first invention to the fourth invention, the section modulus of the combination sheet pile is because there is a 3,500cm 3 / m~14,000cm 3 / m, Even if the depth exceeds 10 m and the underground continuous wall has a depth of about 25 m, it is possible to obtain an effect that the combined steel sheet pile can be handled.
第6発明の地中連続壁によると、第1発明〜第5発明のいずれかの複数枚の組合せ鋼矢板が、継手相互を嵌合して打設されて構築されているので、開削溝側から鋼矢板(ハット形鋼矢板)とH形鋼との接合を取り外した状態では、組合せ鋼矢板の全部又は一部を引抜くことができる組合せ鋼矢板を用いた地中連続壁とすることができる等の効果が得られる。 According to the underground continuous wall of the sixth invention, the combination steel sheet piles of any one of the first invention to the fifth invention are constructed by fitting and fitting the joints, so the cut groove side In a state in which the connection between the steel sheet pile (hat-shaped steel sheet pile) and the H-shaped steel is removed, the underground continuous wall using the combined steel sheet pile that can pull out all or part of the combined steel sheet pile can be used. The effect that it can do is acquired.
第7発明の組合せ鋼矢板の撤去方法によると、第6発明の地中連続壁における組合せ鋼矢板の撤去方法であって、該地中連続壁におけるH形鋼と反対側の鋼矢板側の地盤を開削して開削溝を形成すると共に、開削溝側に地下構造物を構築した後、開削溝側の空間から鋼矢板とH形鋼との接合部を解除して分離し、H形鋼と鋼矢板を別々に引抜くので、図23(a)に示すような閉塞空間25は形成されず、周辺地盤の乱れを低減可能となり、小型の施工機械を用いて施工できる等の効果が得られる。
According to the method for removing the combined steel sheet pile of the seventh invention, the method for removing the combined steel sheet pile in the underground continuous wall of the sixth invention, wherein the ground on the steel sheet pile side opposite to the H-shaped steel in the underground continuous wall To form an open groove, and after constructing an underground structure on the open groove side, the joint between the steel sheet pile and the H-section steel is released and separated from the space on the open groove side. Since the steel sheet piles are pulled out separately, the closed
第8発明の組合せ鋼矢板の一部の撤去方法によると、第6発明の地中連続壁における組合せ鋼矢板の一部の撤去方法であって、該地中連続壁におけるH形鋼と反対側の鋼矢板側の地盤を開削して開削溝を形成すると共に、鋼矢板を型枠として地下構造物用を構築した後、その施工完了後に、開削溝側の空間から鋼矢板とH形鋼との接合部を解除して分離し、H形鋼のみを引抜くので、組合せ鋼矢板における鋼矢板(ハット形鋼矢板)を本体壁の型枠として適用することが可能となり、型枠設置作業スペースを考慮しないでよいため、その分、敷地を有効に利用可能となる。 According to the method for removing a part of the combined steel sheet pile of the eighth invention, it is a method for removing a part of the combined steel sheet pile in the underground continuous wall of the sixth invention, and is the opposite side to the H-shaped steel in the underground continuous wall. After excavating the ground on the steel sheet pile side to form an open groove, the steel sheet pile was used as a formwork for building an underground structure, and after the construction was completed, the steel sheet pile and H-shaped steel Since the joint part is released and separated, and only the H-shaped steel is pulled out, it is possible to apply the steel sheet pile (hat-shaped steel sheet pile) in the combined steel sheet pile as a formwork for the main body wall, and formwork installation work space Therefore, the site can be used effectively.
次に、本発明を図示の実施形態に基づいて詳細に説明する。 Next, the present invention will be described in detail based on the illustrated embodiment.
最初に本発明における組合せ鋼矢板の実施形態において共通の構成部分について、第1実施形態の組合せ鋼矢板を参照して説明したのち、各実施形態の組合せ鋼矢板及びそれを用いた地中連続壁について説明する。 First, common components in the embodiment of the combined steel sheet pile of the present invention will be described with reference to the combined steel sheet pile of the first embodiment, and then the combined steel sheet pile of each embodiment and the underground continuous wall using the same Will be described.
図1及び同図(a)において用いられている組合せ鋼矢板を示す図2を参照して、本発明の組合せ鋼矢板1についての共通する構成に説明すると、組合せ鋼矢板1は、ハット形鋼矢板10からなる鋼矢板と、H形鋼20とを備えている。
With reference to FIG. 2 which shows the combination steel sheet pile used in FIG. 1 and the same figure (a), if it demonstrates to the common structure about the combination
前記のハット形鋼矢板10は、平面視で、ウェブ11の幅方向の両側に、ウェブの片面側で互に離反するように傾斜するフランジ12が一体に設けられ、そのフランジ12の先端からウェブ11に平行にアーム部13が設けられ、更にそのアーム部13の先端部に継手14が設けられている。この左右の継手14のうち、一方の継手14と、他方の継手14は、互いに点対称の形状となるように調整されている。この継手14は、隣接する他の組合せ鋼矢板1における他の継手14と互いに嵌合可能な形状で成形されており、特に嵌合時において継手14が相互に離脱しないように嵌合強度が高められている。
The hat-shaped
また、本発明で使用するハット形鋼矢板10は、熱間圧延加工による圧延鋼材であり、左右の継手14で嵌合溝及び係止爪を点対称の形状に成形され、継手14の強度が高められている鋼矢板である。
Moreover, the hat-shaped
H形鋼20は、圧延加工により製作されるものであって、ウェブ21と、当該ウェブ21の両端にそれぞれ設けられたフランジ22とから構成されている。このH形鋼20における一方のフランジ部22は、ハット形鋼矢板10における各フランジ12とウェブ11とにより形成される溝側におけるウェブ11に固定する形態と、前記溝側と反対側のウェブ11の外面に固定されている形態とがある。ハット形鋼矢板10におけるウェブ11と、H形鋼20のフランジ22との固定形態が各実施形態において相違している。いずれの形態でも、ハット形鋼矢板10側に設けた孔側からの接合手段としている。前記の接合手段による接合構造は、H形鋼20のフランジ部22と前記鋼矢板10のウェブ11が接する面でのみせん断抵抗を持たせた接合構造となっており、当該接合構造は、H形鋼20のフランジ部22よりも地盤側に突出していない、ボルト、ねじ若しくは隅肉溶接のいずれか1つによる接合構造とされ、しかも取外し可能な接合構造とされている。
The H-
前記ハット形鋼矢板10のウェブ11の片面にH形鋼20の一方のフランジ22が重ね合わされて、前記ハット形鋼矢板10における地中に位置される下部部分9を除く上部部分及びH形鋼20における地中に位置される下部部分を除く上部部分において、前記ハット形鋼矢板10のウェブ11とH形鋼20の一方のフランジ22とが、ハット形鋼矢板10側からのボルト、隅肉溶接、ドリルねじ等の接合手段により接合されている。ハット形鋼矢板10のH形鋼20側の面と反対の面は、組合せ鋼矢板1を地盤に貫入した後に開削された場合の開削溝側の面なることから、本発明の組合せ鋼矢板1では、開削溝側の面から、ハット形鋼矢板10とH形鋼20との接合を解除して分離可能な接合構造としている。前記のように、本発明では、組合せ鋼矢板1における下部部分9を除いた部分で、ハット形鋼矢板10におけるウェブ11とH形鋼20のフランジ22とが、ハット形鋼矢板10におけるウェブ11側から接合されている構造とされているので、地中連続壁(地中に構築される連続的な壁で、仮設、本仮設兼用の場合の両方を含む。)或は土留め壁(開削時に土を止める壁で、本設、仮設、本仮設兼用の場合を含む。切梁がある場合又はない場合を含む)を形成した場合に、下部部分9を除く上部側でハット形鋼矢板10におけるウェブ11の片面を露出させることで、図26(a)(b)に代表形態として示すように、接合部(ボルト3等)を取り外すことで、接合を解除して、分離可能な構造の組合せ鋼矢板1としている。また、ハット形鋼矢板10とH形鋼20とに分離することで、嵩張らないようにして、保管或は運搬可能にしている。前記の下部部分9は、開削溝を形成された状態で、各組合せ鋼矢板1における接合部分が取り外されて分離されるまで、地中に埋め込まれている部分である。本発明の組合せ鋼矢板1は、ハット形鋼矢板10とH形鋼20とを、現場で組立たてて構成したり、現場で分解することが容易な組合せ鋼矢板となっている。したがって、当然工場においても、組立、分解が容易な組合せ鋼矢板1である。
One side of the
以下、各実施形態についてさらに詳細に説明する。 Hereinafter, each embodiment will be described in more detail.
図1及び同図(a)において用いられている組合せ鋼矢板を示す図2を参照して、本発明の第1実施形態の組合せ鋼矢板1を説明すると、ハット形鋼矢板10におけるウェブ11の幅方向に間隔をおいて複数列(図示の場合は2列)上下方向に間隔をおいて多数のボルト挿通孔又は雌ねじ孔2を上部に備えている。H形鋼20の一方のフランジ22は、ハット形鋼矢板20におけるウェブ11と各フランジ12とにより形成される溝と反対側のウェブ11の外面に、部材長手方向に延長するように重ね合わされて配置されている。しかも、前記のボルト挿通孔又は雌ねじ孔2に対応して、H形鋼20のフランジ22には、幅方向に間隔をおくと共に上下方向に間隔をおいて多数の雌ねじ孔23を備えている。前記の雌ねじ孔23は、H形鋼20のフランジ22の板厚寸法内に納まるように設けることで、H形鋼と鋼矢板の貫通孔からの地下水の漏水や雌ねじ部の防錆を図るようにしている。また、ハット形鋼矢板10におけるウェブ11のボルト挿通孔又は雌ねじ孔2に挿通又はねじ込まれると共にH形鋼20のフランジ22の雌ねじ孔23にねじ込まれた多数の着脱可能なボルト3により、ハット形鋼矢板20にH形鋼20が固定されて、組合せ鋼矢板1の曲げ剛性が高められている。この形態では、H形鋼20のフランジ部22と前記鋼矢板10のウェブ11が接する面でのみボルト3軸部のせん断耐力によるせん断抵抗を持たせた接合構造となっておいる。また、ボルト3が、H形鋼20のフランジ部22よりも地盤側(地山側)に突出していない構造となっており、ボルト3の防錆が測られ、ボルト3の取り外し、組合せ鋼矢板1の分解、或いは再利用組立が容易になっている。
With reference to FIG. 2 which shows the combination steel sheet pile used in FIG. 1 and the same figure (a), when the combination
前記実施形態では、多数のボルト3の先端部もH形鋼20のフランジ22から突出していないため、地盤貫入時に、ボルト3の先端部が曲がったり、ねじ部が損傷するおそれがなく、又腐食する恐れがなく、後に、ハット形鋼矢板10とH形鋼20を分離する場合に、前記の着脱可能なボルト3を、ハット形鋼矢板10側のボルト頭部を回動工具(図示を省略)により回動することで、ハット形鋼矢板10とH形鋼20との接合を解除することができる。なお、図示を省略するが、H形鋼20のフランジ22に設ける雌ねじ孔23に代えて、H形鋼20のフランジ22に凹部を設けてその凹部にナットを収納すると共に溶接により固定するようにしたり、H形鋼20のフランジ22に大径の雌ねじ孔を設けて、外周面に雄ねじを有する雌ねじ部材をねじ込んで適宜溶接により固定してもよい。また、H形鋼20のフランジ22の幅寸法をハット形鋼矢板10のウェブ11の幅寸法よりも大きくして、H形鋼20のフランジ22をハット形鋼矢板10のウェブ11から張り出すようにしてもよい。このようにH形鋼20のフランジ22を広幅寸法とすると、接合用のボルト本数、雌ねじ孔、ナット等を増やすことができ、より接合強度を高めることができる。
In the above-described embodiment, since the tip portions of a large number of
図2に示す組合せ鋼矢板1における重心を通る左右方向の軸周りの断面係数は、例えば、3,500cm3/m〜14,000cm3/mとされている。このような断面係数とすることで、深度10m〜25m程度の仮設用等の土留め用の組合せ鋼矢板1としている。
Section modulus about the horizontal direction axis passing through the center of gravity in
図1に示すように、組合せ鋼矢板1を地盤に貫入し、隣り合う継手14相互を嵌合して地盤に貫入して、図21(a)又は図22(a)に示すように、地中連続壁15を構築した後、対向する地中連続壁15間の地盤を開削し、切梁を設置して地下構造物4を構築した後、ハット形鋼矢板10とH形鋼20の接合を解除すべく前記の全てのボルト3を取り外し、図21(b)又は図22(b)に示すように、地下構造物4と地中連続壁15との間を掘削土等により埋め戻すと共に切梁を撤去し、図21(c)に示すように、ハット形鋼矢板10とH形鋼20を、それぞれ別々に、汎用されている施工機械により引き抜き、同図右に示すように、複数枚のハット形鋼矢板10同士を5枚程度毎に積み重ねて保管又は、適宜桟木等のスペーサを介して、積み重ねて保管する。また、H形鋼20は複数並列配置して桟木等のスペーサを介して複数段積み重ねて保管する。また、損耗したハット形鋼矢板10を交換する必要がある場合には、図21(d)に示すように、新たなハット形鋼矢板10に置き換えた後、置き換え前の接合構造と同様な構造となるように接合して新たな組合せ鋼矢板1とする。また、より剛性の大きい(又は小さい)H形鋼に置き換える必要がある場合には、図21(e)に示すように、より桁高(梁せい)の大きい(又は小さい)H形鋼20に置き換えることで、現場において、より深度の深い(又は浅い)場所に打設する組合せ鋼矢板とする。このような場合に、置き換え前後の新旧のハット形鋼矢板10に設けるボルト挿通孔又は雌ねじ孔2の大きさ及び左右上下の間隔、及び置き換え前後の新旧のH形鋼20に設けてある雌ねじ孔23を、同じ大きさで左右上下のピッチを一定とすることで、位置ずれによる接合不能となることはない。前記の場合は、仮設用の組合せ鋼矢板1として用いた形態であるが、ハット形鋼矢板10を残置させて、地下構造物4における壁体の一部として残す形態が図22(c)に示されている。
As shown in FIG. 1, the combined
図22(c)に示すように、一部のハット形鋼矢板10を残してそのハット形鋼矢板10の地盤開削側にコンクリート壁を設ける場合には、H形鋼20のみを引き抜いて、前記と同様に積み重ねて保管する。また、残置させる以外のハット形鋼矢板10も同様に引き抜いて前記と同様に保管すると共に、必要に応じ、図22(d)又は(e)に示すように、適宜ハット形鋼矢板或はH形鋼20を置き換える。図21及び図22の形態は以下の実施形態でも同様に適用することができる。
As shown in FIG. 22 (c), when a concrete wall is provided on the ground cutting side of the hat-shaped
図3及び同図(a)において用いられている組合せ鋼矢板を示す図4を参照して、本発明の第2実施形態の組合せ鋼矢板1について説明すると、この形態では、ハット形鋼矢板10におけるウェブ11と各フランジ12とにより形成される溝側のウェブ11に、H形鋼20のフランジ22が、配置されている点で、前記の第1実施形態と相違し、図4における左右方向の図心を通る左右方向の軸周りの曲げ剛性が低下するが、その他の点では、前記第1実施形態の場合と同様である。この第2実施形態では、同じハット形鋼矢板10及びH形鋼20を用いて、断面積は同じでも、高さが低くなる分、剛性は、前記第1実施形態の場合に比べて、小さくなるが、敷地境界よりに設置でき、敷地を有効に利用できる。その他の点は、前記実施形態及び変形形態と同様である。
With reference to FIG. 4 which shows the combination steel sheet pile used in FIG. 3 and the same figure (a), when the combination
以下の実施形態でも同様であるが、前記のような本発明のハット形鋼矢板10では、次の(1)から(8)のような効果を発揮することができる。
The same applies to the following embodiments, but the hat-shaped
(1)ハット形鋼矢板とH形鋼の分離が容易になり、ハット形鋼矢板とH形鋼を別々に輸送・保管することが可能となるため、輸送・保管コストを低減できる。 (1) Separation of the hat-shaped steel sheet pile and the H-shaped steel is facilitated, and the hat-shaped steel sheet pile and the H-shaped steel can be separately transported and stored, so that transportation and storage costs can be reduced.
(2)ハット形鋼矢板とH形鋼を分離し別々に引抜くことで地盤の周面抵抗を低減でき、引抜きが容易となる。(従来は接合箇所(溶接部)が背面土側に配置されていたために、引抜き前にハット形鋼矢板とH形鋼を分離することは不可能であった。) (2) By separating the hat-shaped steel sheet pile and the H-shaped steel and pulling them separately, the peripheral surface resistance of the ground can be reduced, and the drawing becomes easy. (Conventionally, since the joining location (welded part) was arranged on the back soil side, it was impossible to separate the hat-shaped steel sheet pile and the H-shaped steel before drawing.)
(3)引き抜く場合の組合せ鋼矢板の周面摩擦は表面積に依存するため、ハット形鋼矢板とH形鋼を分離し別々に引抜くことで、ハット形鋼矢板単体は組合せ鋼矢板の約4割の力で、H形鋼は約6割の力で引抜きが可能となる。したがって、組合せ鋼矢板を一体として引抜く場合よりも小さな施工機械で引抜きが可能となり施工コストの低減につながる。 (3) Since the peripheral friction of the combined steel sheet pile when pulling depends on the surface area, the hat-shaped steel sheet pile alone is about 4 times the combined steel sheet pile by separating the hat-shaped steel sheet pile and the H-shaped steel separately. The H-shaped steel can be pulled out with a force of about 60%. Therefore, it is possible to pull out with a smaller construction machine than when the combined steel sheet pile is pulled out as a unit, leading to a reduction in construction cost.
(4)地盤に打設する場合に損耗し易いハット形鋼矢板のみを交換し再利用することが可能で、建設コストを低減できる。(従来は1回使い切りで全損になり不経済であるが、本発明の場合は、全体の鋼材重量の約6割、7割を占めるH形鋼を転用可能になるため、経済的である。) (4) It is possible to replace and reuse only the hat-shaped steel sheet pile that is easily worn when placing on the ground, and the construction cost can be reduced. (Conventionally, it is uneconomical because it is used up once and loses all, but in the case of the present invention, it is economical because it is possible to divert H-shaped steel, which accounts for about 60% and 70% of the total steel weight). .)
(5)サイズの異なるH形鋼を組み合わせることが可能で、異なる断面剛性を必要とする別のプロジェクトにおいても合理的な壁体仕様とすることができる。 (5) It is possible to combine H-shaped steels of different sizes, and it is possible to make a rational wall body specification in another project that requires different cross-sectional rigidity.
(6)ハット形鋼矢板とH形鋼を別々に引抜くことが可能であるため、汎用圧入機では把持機構に収まらなかったサイズの組合せ鋼矢板でも引抜き可能となる(この際、前面側のハット形鋼矢板を把持して反力を確保することも可能になる。)。 (6) Since the hat-shaped steel sheet pile and the H-shaped steel can be pulled out separately, even a combination steel sheet pile of a size that could not fit in the gripping mechanism with a general-purpose press-fitting machine can be pulled out. It is also possible to secure the reaction force by gripping the hat-shaped steel sheet pile.)
(7)ハット形鋼矢板とH形鋼を別々に引抜くため、閉塞空間は形成されず、周辺地盤の乱れを低減可能となる。 (7) Since the hat-shaped steel sheet pile and the H-shaped steel are pulled out separately, a closed space is not formed, and disturbance of the surrounding ground can be reduced.
(8)ハット形鋼矢板を本体壁の型枠として適用することが可能となり、敷地を最大限利用可能となる。 (8) The hat-shaped steel sheet pile can be applied as a formwork for the main body wall, and the site can be used to the maximum extent.
図5及び同図(a)において用いられている組合せ鋼矢板を示す図6を参照して、本発明の第3実施形態の組合せ鋼矢板1について説明する。この形態では、ハット形鋼矢板10におけるウェブ11と各フランジ12とにより形成される溝と反対側のウェブ11外面にH形鋼20のフランジ22が重ね合わされて隅肉溶接Wにより取り付けられている。この形態では、ハット形鋼矢板10のウェブ11に上下方向に間隔をおいて、H形鋼20のフランジ幅寸法より小さい多数の円形の貫通孔5を設けて、各円形孔内周面とH形鋼20のフランジ22とを隅肉溶接Wにより、ハット形鋼矢板10とH形鋼20の部材長手方向の上部側を固定した形態である。前記の円形の貫通孔5の直径寸法は、H形鋼20のフランジ幅寸法よりも小さい寸法とされている。前記の円形の貫通孔5の左右両側の内周面の部分で隅肉溶接するほうが、円形の貫通孔5の上下部内周面の部分で隅肉溶接するよりも、上下方向の応力伝達する上では有利である。前記の隅肉溶接Wは、溶断或はグラインダー等の電動式研削工具等の手段により撤去可能なようにされている。隅肉溶接Wののど厚寸法等については、設計により設定される。この形態では、H形鋼20のフランジ部22と前記鋼矢板10のウェブ11が接する面でのみせん断抵抗を持たせた接合構造として、H形鋼20のフランジ22よりも地盤側に突出していない隅肉溶接Wによる接合構造とされて、前記の隅肉溶接Wを撤去することで、取外し可能とされている。その他の形態は、前記実施形態と同様である。
With reference to FIG. 6 which shows the combination steel sheet pile used in FIG. 5 and the same figure (a), the combination
図7及び同図(a)において用いられている組合せ鋼矢板を示す図8を参照して、本発明の第4実施形態の組合せ鋼矢板1について説明すると、この形態では、ハット形鋼矢板10におけるウェブ11と各フランジ12とにより形成される溝側のウェブ11面に、H形鋼20におけるフランジ22が重ね合わさるように配置され、H形鋼20と反対のハット形鋼矢板10側から前記円形の貫通孔5の内周面と、H形鋼20のフランジ外面とが、隅肉溶接Wにより接合されて、H形鋼20のフランジ部22と前記鋼矢板10のウェブ11が接する面での隅肉溶接Wのみによりせん断抵抗を持たせた接合構造としている。この形態も、前記の隅肉溶接Wを撤去することで、取外し可能とされている。その他の形態は、図6に示す形態と同様である。
With reference to FIG. 8 which shows the combination steel sheet pile used in FIG. 7 and the same figure (a), when the combination
図9及び同図(a)において用いられている組合せ鋼矢板を示す図10を参照して、本発明の第5実施形態の組合せ鋼矢板1について説明すると、この形態では、ハット形鋼矢板10に設ける孔を、ウェブ11の長手方向に長孔の貫通孔5とした形態である。このように、長孔とすることで、ハット形鋼矢板10の部材長手方向に長い隅肉溶接Wが可能になり、溶接長が長くなるため、大きな応力を伝達することができる。また、溶接箇所が少なくなる分、溶接作業が容易になる。このような形態では、長孔の貫通孔5における直線状部分の内周面において直線状内周面に沿って隅肉溶接するのがよい。このように隅肉溶接することで、軸方向に作用する荷重に対して溶接部の長手方向にせん断力を作用させて抵抗させることができ、溶接部における引張残留応力が生じている方向に、荷重を作用させないので、溶接部の疲労性能を向上させることができる。その他の構成は前記実施形態の場合と同様である。
With reference to FIG. 10 which shows the combination steel sheet pile used in FIG.9 and the same figure (a), when the combination
図11及び同図(a)において用いられている組合せ鋼矢板を示す図12を参照して、本発明の第6実施形態の組合せ鋼矢板1について説明すると、ハット形鋼矢板10におけるウェブ11と各フランジ12とにより形成される溝側にH形鋼20が配置されて、ハット形鋼矢板10の下部を除く部分のウェブ11に設けた長孔の貫通孔5の部分で、前記実施形態と同様に隅肉溶接Wにより接合している形態である。
With reference to FIG. 12 which shows the combination steel sheet pile used in FIG.11 and the same figure (a), when the combination
図13及び同図(a)において用いられている組合せ鋼矢板を示す図14を参照して、本発明の第7実施形態の組合せ鋼矢板1について説明すると、この形態では、ハット形鋼矢板10におけるウェブ11と各フランジ12により形成される溝と反対側において、H形鋼20のフランジ22が、ハット形鋼矢板10のウェブ11に重ね合わされて、ハット形鋼矢板10側からのドリルねじ6が、H形鋼20のフランジ22にねじ込まれて、ハット形鋼矢板10のウェブ11がH形鋼20に固定されている。この形態では、前記ドリルねじ6の先端部は、H形鋼20のフランジ22の裏面から突出しないようにされている。ドリルねじ6の回動用係合部としての頭部を除いた長さ寸法は、ハット形鋼矢板10のウェブ11の板厚寸法と、H形鋼20のフランジ12の板厚寸法との合計寸法以下とされていることで、ドリルねじ6の先端部が、H形鋼20のフランジ22の裏面側に突出しないようにされている。ドリルねじ6による接合を容易にするために、ハット形鋼矢板10のウェブ11及びH形鋼20のフランジ22のいずれか一方又は両方に、ドリルねじ6の軸径よりも小さい先孔を予め設けた状態で、ハット形鋼矢板10のウェブ11からドリルねじ6により接合してもよいが、先孔を設けない状態でドリルねじ6により接合する形態であってもよい。図示の実施形態では、ハット形鋼矢板10におけるウェブ11の長手方向に間隔をおくと共に幅方向に間隔をおいて3列の多数のドリルねじ6により、ハット形鋼矢板10におけるウェブ11側からH形鋼20のフランジ22にねじ込まれて一体に接合された組合せ鋼矢板1とされている。
With reference to FIG. 14 which shows the combination steel sheet pile used in FIG. 13 and the same figure (a), when the combination
ドリルねじ6により、ハット形鋼矢板10におけるウェブ11とH形鋼20のフランジ22を接合している場合に、ドリルねじ6の先端部がH形鋼20のフランジ22の裏面に突出しないようにされているために、組合せ鋼矢板1を地盤に貫入する場合、又は引き抜く場合に、ドリルねじ6の先端部が変形することがない。また、H形鋼と鋼矢板にわたり貫通孔が形成されないため、地下水の漏水やドリルねじの腐食を防ぐことができる。そのため、土留め壁を構築すると共に土留め壁間を開削して開削溝を形成した場合、開削溝側からドリルねじ6を緩む方向に電動工具(図示を省略した)等により回動することで、ドリルねじ6を引き抜き、ドリルねじ6による接合部を解除することができ、ハット形鋼矢板10とH形鋼20の接合を開放して、H形鋼20を引き抜いたり、ハット形鋼矢板10とH形鋼20の両方を別々に小型の施工機械を使用して引き抜いたりすることができるようになっている。
When the
図15及び同図(a)において用いられている組合せ鋼矢板を示す図16を参照して、本発明の第8実施形態の組合せ鋼矢板1について説明すると、この形態では、ハット形鋼矢板10におけるウェブ11と各フランジ12により形成される溝側のウェブ11に、H形鋼20のフランジ22が重ね合わされて、ドリルねじ6により接合されている点で、前記の実施形態と相違しているがその他の点は、前記実施形態と同様である。
With reference to FIG. 16 which shows the combination steel sheet pile used in FIG.15 and the same figure (a), when the combination
図17及び同図(a)において用いられている組合せ鋼矢板を示す図18を参照して、本発明の第9実施形態の組合せ鋼矢板1について説明すると、この形態では、ハット形鋼矢板10におけるウェブ11に、ドリルねじ6の頭部を収容する截頭円錐状のボルト頭部収容溝7が形成されて、ドリルねじ6の頭部8が、ハット形鋼矢板10におけるウェブ11の外面から突出しないように、ドリルねじ6の頭部軸方向外面と、H形鋼20と反対側のハット形鋼矢板10におけるウェブ11の外面が面一となるようにして、ドリルねじ6の頭部の損傷を防止していると共に、ドリルねじ6の頭部8が、地盤貫入時、或は引き抜き時に、障害とならないようにした形態である。
With reference to FIG. 18 which shows the combination steel sheet pile used in FIG. 17 and the same figure (a), when the combination
図19及び同図(a)において用いられている組合せ鋼矢板を示す図20を参照して、本発明の第10実施形態の組合せ鋼矢板1について説明すると、この形態では、ハット形鋼矢板10におけるウェブ11と各フランジ12により形成される溝側のウェブ11に、H形鋼20のフランジ22が重ね合わされ、また、ハット形鋼矢板10におけるウェブ11に溝側に末広がりに開口する截頭円錐状のボルト頭部収容溝7が形成され、ハット形鋼矢板10におけるウェブ11側から多数のドリルねじ6により、H形鋼20のフランジ22にハット形鋼矢板10におけるウェブ11が接合されている点で、前記の実施形態と相違しているがその他の点は、前記実施形態と同様である。
19 and FIG. 20 showing the combined steel sheet pile used in FIG. 19A, the combined
前記各実施形態の組合せ鋼矢板1を用いて地中連続壁15を構築する場合には、前記各実施形態の組合せ鋼矢板1を、複数枚にわたり組合せ鋼矢板1の継手を介して嵌合して打設することで、H形鋼20側と反対側のハット形鋼矢板10におけるウェブ11側を開削することで、地中構造物構築後等に、開削溝側から、ハット形鋼矢板10におけるウェブ11とH形鋼20のフランジ22とを接合している金具等を取り外すことができる。そして、図21又は図22に示すように、H形鋼20を引き抜い抜いて、施工現場付近のヤード上で積み重ねて保管したり、H形鋼20及びハット形鋼矢板10を別々に引き抜き、積み重ねて効率よく保管したり、搬送する場合も効率よく搬送することができ、また、H形鋼20或はハット形鋼矢板10を新たな又は別個の部材に置き換え可能な形態としている。
When the underground
例えば、地中連続壁15を撤去する場合に、前記のように、該地中連続壁におけるH形鋼と反対側の鋼矢板側の地盤を開削して開削溝を形成すると共に、開削溝側に地下構造物を構築した後、開削溝側の空間から鋼矢板とH形鋼との接合部を解除して分離し、H形鋼と鋼矢板を別々に引抜く地中連続壁における組合せ鋼矢板の撤去方法によると、図23(b)に示すように、周囲地盤に対する影響が小さいため、小型の引き抜き施工機械を用いて別々に引き抜くことができるため、また、組合せ鋼矢板1の場合に比べて嵩張らないように積み重ねて保管することができる。また、ハット形鋼矢板10におけるウェブ11とH形鋼20のフランジ22との接合を解除した後、H形鋼のみを引抜いて、ハット形鋼矢板10のみを残置させて、そのハット形鋼矢板10を壁部コンクリートを形成する場合の型枠として利用したりできるので、効率よく利用することができる組合せ鋼矢板1となっている。
For example, when the underground
本発明を実施する場合、ハット形鋼矢板10以外の鋼矢板とH形鋼あるいはI形鋼を用いた組合せ鋼矢板としてもよい。また、本発明を実施する場合、ハット形鋼矢板10等の鋼矢板の上端部とH形鋼あるいはI形鋼の上端部とは、上下方向で同じ位置とし、ハット形鋼矢板10等の鋼矢板の下端部とH形鋼あるいはI形鋼の下端部とは、図示のように上下方向で同じ位置としてもよく、ハット形鋼矢板10等の鋼矢板の下端部を突出させるようにしても、H形鋼あるいはI形鋼を突出させるようにしてもよい。また、図示を省略するが、本発明を実施する場合に、H形鋼のフランジ幅がハット形鋼矢板のウェブ幅より広い形態とし、H形鋼のフランジがハット形鋼矢板のウェブから突出している形態の組合せ鋼矢板としてもよい。
When practicing the present invention, a steel sheet pile other than the hat-shaped
1 組合せ鋼矢板
2 ボルト挿通孔又は雌ねじ孔
3 ボルト
4 地下構造物
5 貫通孔
6 ドリルねじ
7 ボルト頭部収容溝
8 ドリルねじの頭部
9 下部部分
10 ハット形鋼矢板
11 ウェブ(ハット形鋼矢板の)
12 フランジ(ハット形鋼矢板の)
13 アーム部
14 継手
15 地中連続壁
20 H形鋼
21 ウェブ(H形鋼の)
22 フランジ(H形鋼の)
23 雌ねじ孔
24 組合せ鋼矢板
25 閉塞空間
26 周囲地盤
27 鋼矢板
28 H形鋼
29 ボルト
30 ナット
31 地中連続壁用鋼材
DESCRIPTION OF
12 Flange (for hat-shaped steel sheet pile)
13
22 Flange (H-shaped steel)
23 Female threaded
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2011155709A JP2013019245A (en) | 2011-07-14 | 2011-07-14 | Combination steel sheet pile, underground continuous wall, and method of removing combination steel sheet pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2011155709A JP2013019245A (en) | 2011-07-14 | 2011-07-14 | Combination steel sheet pile, underground continuous wall, and method of removing combination steel sheet pile |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2013019245A true JP2013019245A (en) | 2013-01-31 |
Family
ID=47690929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2011155709A Withdrawn JP2013019245A (en) | 2011-07-14 | 2011-07-14 | Combination steel sheet pile, underground continuous wall, and method of removing combination steel sheet pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2013019245A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2015183475A (en) * | 2014-03-25 | 2015-10-22 | Jfeスチール株式会社 | Steel earth retaining wall member and synthesized wall with steel earth retaining wall member |
JP2020116877A (en) * | 2019-01-25 | 2020-08-06 | 株式会社奥村組 | Plant for concrete production |
JP2021161745A (en) * | 2020-03-31 | 2021-10-11 | Jfeエンジニアリング株式会社 | Water proof wall, and construction method of water proof wall |
-
2011
- 2011-07-14 JP JP2011155709A patent/JP2013019245A/en not_active Withdrawn
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2015183475A (en) * | 2014-03-25 | 2015-10-22 | Jfeスチール株式会社 | Steel earth retaining wall member and synthesized wall with steel earth retaining wall member |
JP2020116877A (en) * | 2019-01-25 | 2020-08-06 | 株式会社奥村組 | Plant for concrete production |
JP7181106B2 (en) | 2019-01-25 | 2022-11-30 | 株式会社奥村組 | Concrete production plant |
JP2021161745A (en) * | 2020-03-31 | 2021-10-11 | Jfeエンジニアリング株式会社 | Water proof wall, and construction method of water proof wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9512590B2 (en) | Combined steel sheet pile, diaphragm wall, and method of disassembling combined steel sheet pile | |
JP5413541B2 (en) | Combination steel sheet pile, underground continuous wall, and reuse method of combination steel sheet pile | |
JP2018024982A (en) | Reinforcement method and reinforcement structure of existing pile foundation | |
JP5235748B2 (en) | Wall metal fittings and underground continuous wall construction method | |
JP5268732B2 (en) | Wall member for underground continuous wall, underground continuous wall construction method, and underground continuous wall | |
JP2013019245A (en) | Combination steel sheet pile, underground continuous wall, and method of removing combination steel sheet pile | |
JP2007291682A (en) | Structure and method for jointing wide flange shapes together | |
JP2014051843A (en) | Steel pipe sheet pile installation method and steel pipe sheet pile joint | |
JP6317122B2 (en) | Yamazushi support work | |
JP4912726B2 (en) | Connection structure between segment rings | |
JP6085240B2 (en) | Core material and upper core material removal method | |
JP4844477B2 (en) | Synthetic wall structure and its construction method | |
JP2011063957A (en) | Method for removing upper portion of pile | |
JP2011089372A (en) | Socket type connecting member for continuous underground wall core pile, and method of removing the same | |
JP6905813B2 (en) | Synthetic segment and ring | |
JP6095832B1 (en) | Reinforcement method before repairing retaining wall structure | |
JP6997671B2 (en) | Pile, how to join piles and how to remove upper piles | |
JP5348197B2 (en) | Synthetic wall structure | |
JP5420429B2 (en) | Joint structure and joint method of reinforcing ring for liner plate and joint plate | |
JP2003328357A (en) | Steel pipe sheet pile method | |
JP6559998B2 (en) | Pipe roof construction method | |
JP5486931B2 (en) | Joint structure of reinforcing ring for liner plate and joint method | |
JP2020165287A (en) | Combination structure of steel material, construction method of earth retaining wall, and removal method of upper pile for earth retaining wall | |
JP6002348B1 (en) | Retaining method of retaining wall structure | |
KR200454383Y1 (en) | Fastening reinforcement ball for reinforcing joints of temporary earthquake construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Withdrawal of application because of no request for examination |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 20141007 |