JP2013011976A - Train crew operation plan creation system - Google Patents

Train crew operation plan creation system Download PDF

Info

Publication number
JP2013011976A
JP2013011976A JP2011143234A JP2011143234A JP2013011976A JP 2013011976 A JP2013011976 A JP 2013011976A JP 2011143234 A JP2011143234 A JP 2011143234A JP 2011143234 A JP2011143234 A JP 2011143234A JP 2013011976 A JP2013011976 A JP 2013011976A
Authority
JP
Japan
Prior art keywords
crew
train
connection
temporary connection
fragment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2011143234A
Other languages
Japanese (ja)
Other versions
JP5718742B2 (en
Inventor
Hidetaka Shigeta
英貴 重田
Yasumitsu Fujiwara
寿光 藤原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NTT Data Sekisui Systems Corp
Japan Freight Railway Co
Original Assignee
NTT Data Sekisui Systems Corp
Japan Freight Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NTT Data Sekisui Systems Corp, Japan Freight Railway Co filed Critical NTT Data Sekisui Systems Corp
Priority to JP2011143234A priority Critical patent/JP5718742B2/en
Publication of JP2013011976A publication Critical patent/JP2013011976A/en
Application granted granted Critical
Publication of JP5718742B2 publication Critical patent/JP5718742B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a train crew operation plan creation system capable of creating a crew operation plan per day even if the scale of creating the plan becomes large.SOLUTION: The train crew operation plan creation system 1 for creating a train crew operation plan for a specified period by allocating each train travel section in a train operation diagram to a work unit of each crew includes: train operation conversion means 22 for creating a travel segment of each crew for each day on the basis of train operation data reflecting a suspension which is not scheduled when creating the train operation diagram; travel segment sort means 23 for sorting the travel segments by start time of each travel segment; provisional combination means 24 for provisionally combining one sorted travel segment with another sorted travel segment not overlapped with each other in time series; combination evaluation means 25 for evaluating for each provisional combination whether a new travel segment acquired through each provisional combination is over a prescribed evaluation reference; and definitive combination means 26 for changing a provisional combination having the highest evaluation value among provisional combinations over the evaluation reference to a definitive combination and creating a longer travel segment or work plan.

Description

本発明は、列車の乗務員の運用計画表を作成するに際して、需要の増減等によって既に作成された列車運行ダイヤが変化することに対応して日ごとに乗務員運用計画を作成することができる乗務員運用計画作成システムに関するものである。   The present invention, when creating an operation plan table for a train crew member, the crew member operation plan that can create a crew member operation plan every day in response to changes in the train schedule already created due to increase or decrease in demand, etc. It relates to a planning system.

従来、貨物列車や旅客列車等の運転士や車掌といった乗務員の運用計画作成において、乗務員が1回の出勤でこなす勤務内容の単位を仕業とした場合に、例えばこの仕業を30日分作成して1つの交番表を作成し、複数の乗務員が1つのグループ(交番組)を形成し、ローテーションで各仕業を順にこなしていく交番割による運用が行われている(特許文献1参照)。   Conventionally, in the operation plan creation of crew members such as drivers and conductors of freight trains and passenger trains, when the unit of work content that a crew member performs in one work is a work, for example, this work is created for 30 days. One alternating table is created, and a plurality of crew members form one group (an alternating program), and operations are carried out by an alternating number in which each work is sequentially performed by rotation (see Patent Document 1).

特許文献1では、横方向の実線で乗務員の乗務が示され、破線は乗務員の休憩時間を示している。そして、これらを繋ぎ合わせた一本の線が乗務員の1日の勤務内容(仕業)を示し、いくつかの仕業で1つの交番割が作成されている。   In Patent Document 1, a crew member's crew is shown by a horizontal solid line, and a broken line shows a crew member's rest time. A single line connecting them indicates the daily work contents (work) of the crew, and one alternation is created for several works.

特許文献1の発明は、列車運行ダイヤにみだれが発生した場合に、ダイヤみだれに対応した整理ダイヤを作成し、この整理ダイヤに乗務員を再割当するものである。   In the invention of Patent Document 1, when a drool occurs in a train operation diagram, an arrangement diagram corresponding to the diamond arrangement is created, and a crew member is reassigned to the arrangement diagram.

特開2006−79440号公報JP 2006-79440 A

特許文献1に開示された乗務員運用整理案作成装置は、一つの交番組がローテーションで各仕業を順にこなしていく交番割の運用計画を作成するものであり、日々の計画を作る手間や、勤務条件を一人ずつ考える手間が省けるというメリットがあるが、交番組がローテーションで各仕業を順にこなしていくため、1日単位で発生する需要の変動に柔軟に対応することができない。   The crew member operation arrangement plan creation device disclosed in Patent Document 1 creates an operation plan of an alternating rate in which one exchange program performs each work in turn, so that it takes time and effort to create a daily plan. Although there is an advantage that it is possible to save time and effort to think about the conditions one by one, it is not possible to respond flexibly to fluctuations in demand that occur on a daily basis because the exchange program performs each work in turn.

また、特許文献1のものは、ダイヤみだれが発生したときに、その日に予定されていた仕業を切り出し、これに対して乗務員を再割当しているものであり、日別の需要を反映したものではない。   Moreover, the thing of patent document 1 cuts out the work scheduled on the day when a diamond droop occurs, and reassigns a crew member to this, and reflects daily demand is not.

一般的な旅客列車や貨物列車の運用の場面では、土曜日、休日、祝日の場合には平日とは異なる列車運行ダイヤが用いられる。さらに、例えば冬場には石油列車による需要が日別に変動し、ゴールデンウィーク、お盆等の長期休暇の場合には工場等が閉まって原料製品の需要が低下し、突然の震災等による列車の増発や休止等で、1日単位で需要が変動する。   In general passenger train and freight train operations, a train schedule that is different from weekdays is used on Saturdays, holidays, and holidays. Furthermore, for example, the demand for oil trains fluctuates from day to day in the winter, and in the case of long holidays such as Golden Week and Bon Festival, the factories close and the demand for raw material products declines. Demand fluctuates on a daily basis due to a suspension or the like.

しかし、このような場合でも、交番割によって運用計画を作成する場合、例えば1年間を通して全ての列車が運行されることを前提に乗務員運用計画を作成して運用に必要な最低限の乗務員を割り付けておく必要がある。しかしながら、前述のように輸送量には波動があり、その運転された列車が運転されなければ、計画上割当があっても実際には勤務が発生しない場合があり、仮に最適化する計画ができたとしても、日々の休止の発生により非効率となることを免れない。   However, even in such a case, when creating an operation plan by alternating allocation, for example, a crew operation plan is created on the assumption that all trains operate throughout the year, and the minimum crew required for operation is assigned. It is necessary to keep. However, as mentioned above, there is a wave in the transport volume, and if the operated train is not operated, even if there is a plan allocation, work may not actually occur, and it is possible to plan to optimize it temporarily. Even so, it is inevitable that it will become inefficient due to daily outages.

そこで、1日単位で計画を作成することが考えられるが、この場合、例えば連日繰り返される仕業であっても、日ごとに異なる仕業と捉えるため、例えば30日分(約1ヶ月分)の計画を作成しようとした場合、計画作成対象のデータは約30倍となり、例えば計算量がデータ量の二乗に比例するような組み合わせ最適化アルゴリズムを使用した場合、約900倍の時間がかかることになってしまう。このため、運用計画作成の解を得るのに時間がかかったり、解が得られない場合がある。   Therefore, it is conceivable to create a plan in units of one day. In this case, for example, even if the work is repeated every day, for example, a plan for 30 days (about one month) is considered in order to regard it as a different work for each day. When creating a plan, the plan creation target data is about 30 times longer. For example, when a combinational optimization algorithm is used in which the calculation amount is proportional to the square of the data amount, it takes about 900 times longer. End up. For this reason, it may take time to obtain a solution for creating an operation plan, or a solution may not be obtained.

そこで、本発明は、上記事情に鑑みて、たとえ計画の作成規模が大きくなっても1日単位で乗務員の運用計画を作成することができる乗務員運用計画作成システムの提供をすることを目的としている。   Therefore, in view of the above circumstances, the present invention has an object to provide a crew member operation plan creation system that can create a crew member operation plan on a daily basis even if the plan creation scale is large. .

(1)前記目的を達成するために、本発明に係る乗務員運用計画作成システムは、列車運行ダイヤの各列車運行区間を乗務員の仕業単位に割り付けて所定期間の乗務員の運用計画を作成する乗務員運用計画作成システムにおいて、前記列車運行の休止を反映した列車運行データに基づいて乗務員の行程断片を生成する列車運行置換手段と、この行程断片をその開始時刻でソートする行程断片ソート手段と、ソートされた行程断片を時系列的に重複しない行程断片同士で順々に一対一の仮連結する仮連結処理を行う仮連結手段と、前記仮連結ごとに所定の評価を行ったときの評価値が、所定の評価基準値を超えるか否かを判断し、超えた場合には所定の評価基準値を当該評価値に置き換える連結評価手段と、前記仮連結処理後に得られる評価基準値の仮連結を本連結して、より長い行程断片又は仕業を生成する本連結手段と、を備えたことを特徴とする。   (1) In order to achieve the above object, the crew operation plan creation system according to the present invention assigns each train operation section of the train operation diagram to a crew unit of work and creates an operation plan for the crew for a predetermined period. In the plan creation system, the train operation replacement means for generating the crew fragment of the crew based on the train operation data reflecting the suspension of the train operation, the stroke fragment sorting means for sorting the journey fragment by its start time, Temporary connection means for performing temporary connection processing for temporarily connecting one-to-one temporary connection between the process fragments that do not overlap with each other in time series, and an evaluation value when performing a predetermined evaluation for each temporary connection, It is determined whether or not a predetermined evaluation reference value is exceeded, and if it exceeds, a connection evaluation unit that replaces the predetermined evaluation reference value with the evaluation value, and an evaluation base obtained after the temporary connection processing The temporary connection values and the connection, characterized by comprising the present connecting means for generating a longer stroke fragment or act, the.

(2)また、前記仮連結手段は、仮連結する対象の日の範囲を維持しつつ一日ずつずらしながら仮連結処理を行い、前記連結評価手段は、既行の仮連結処理の評価基準値に基づいて、連結打切基準値を算定し、現行の仮連結処理後の評価基準値が連結打切基準値を上回っているか否かについて判断し、前記評価値が前記連結打切基準値より上回っている場合に前記本連結させることを特徴とすることとしてもよい。   (2) Further, the temporary connection unit performs the temporary connection process while shifting the day by day while maintaining the range of the target date to be temporarily connected, and the connection evaluation unit is an evaluation reference value of the existing temporary connection process. Based on the above, the connection cutoff reference value is calculated, and it is determined whether or not the current evaluation reference value after provisional connection processing exceeds the connection cutoff reference value, and the evaluation value exceeds the connection cutoff reference value. In this case, the main connection may be used.

(3)さらに、前記仮連結手段は、前記ソートされた行程断片を仮連結する際に、任意に選択した一の行程断片と、この行程断片との開始時刻差が24時間以下の他の行程断片とを抽出して、仮連結をしてもよい。   (3) Furthermore, when the temporary connection means temporarily connects the sorted process fragments, the first process fragment arbitrarily selected and another process whose start time difference between the process fragments is 24 hours or less. The fragments may be extracted and temporarily connected.

(4)また、既出の仮連結の評価値と同じ評価値の仮連結が現れた場合、それ以降の少なくとも一部の仮連結を省略するバイパス手段を備えていてもよい。   (4) Moreover, when the temporary connection of the same evaluation value as the evaluation value of the temporary connection mentioned above appears, the bypass means which abbreviate | omits at least one part temporary connection after that may be provided.

(5)さらに、本発明に係る別の乗務員運用計画作成システムは、上記いずれかの乗務員運用計画作成システムにおいて、毎日運行した場合の列車の運転率を100%とした場合に各列車運行の運転率を算出する運転率算出手段と、運転率が基準値以上の列車運行グループと基準値未満の列車グループとに分ける列車グループ化手段とを備え、運転率が基準値未満の列車グループについて、日別に乗務員運用計画を作成することを特徴とする。   (5) Furthermore, another crew member operation plan creation system according to the present invention is the operation of each train operation in the above crew member operation plan creation system when the operation rate of the train when operated every day is 100%. For a train group with an operation rate less than the reference value, and a train grouping means for dividing the train operation group with the operation rate less than the reference value. Another feature is to create a crew operation plan.

(6)さらに、このシステムが、基準乗務時間に対する各乗務員の乗務時間の割合(乗務割合)を算出する乗務割合算出手段と、この乗務割合が基準値以上の乗務員グループと基準値未満の乗務員グループとに分ける乗務員グループ化手段と、前記基準値以上の乗務割合の乗務員グループを、前記基準値以上の運転率の列車グループに割り付け、前記基準値未満の乗務割合の乗務員グループを前記基準値未満の運転率の列車グループに割り付けるグループ紐付手段とを備え、前記列車の運転率が基準値以上の列車グループについて交番割を作成することとしてもよい。   (6) Further, this system calculates a crew ratio calculation means for calculating the ratio of each crew member's crew time to the standard crew time (a crew ratio), and a crew group whose crew ratio is equal to or greater than a reference value and a crew group whose standard value is less than the standard value And a crew group having a crew ratio equal to or higher than the reference value is assigned to a train group having an operation rate equal to or higher than the reference value, and a crew group having a crew ratio less than the reference value is less than the reference value. It is good also as preparing a police box allocation about the train group for which the operation rate of the said train is more than a reference value.

なお、本出願において、「行程」とは、例えばA→B→C駅の3駅を停車駅とする一の列車運行がある場合にA駅からC駅までの列車運行をいい、「行程断片」とは、上記の例でA−B駅間やB−C駅間の列車運行を担当する乗務員の乗務単位をいう。さらに、「仕業」とは、複数の「行程」からなる乗務員の約1日の乗務内容をいう。   In the present application, the “stroke” means, for example, a train operation from A station to C station when there is one train operation that stops at three stations A → B → C station. "" Means a crew unit of a crew member in charge of train operation between A-B stations and B-C stations in the above example. Furthermore, “work” refers to the crew's crew content for about one day consisting of a plurality of “strokes”.

また、「乗務割合」とは、基準乗務時間に対する各乗務員の乗務時間の割合を意味する。   “Crew ratio” means the ratio of the crew hours of each crew member to the standard crew hours.

このように構成された本発明の乗務員運用計画作成システムによれば、組み合わせ最適化問題として通常得ることが難しい又は得られない行程断片の連結解をより早く確実に得ることができるようになる。   According to the crew operation plan creation system of the present invention configured as described above, it is possible to quickly and surely obtain a connected solution of process fragments that are usually difficult or impossible to obtain as a combination optimization problem.

この結果、解が得られる時間が格段に短くなり、各乗務員の日々の仕業を1日毎の別々の予定として作成することができる。そのため、交番のように決められた仕業を順番にこなしていくだけのシステムでは対応が困難な事象、例えば需要の増加による増発、突然の震災による休止が発生した場合など、需要の変化にも柔軟に対応することができる。   As a result, the time for obtaining the solution is remarkably shortened, and the daily work of each crew member can be created as a separate schedule for each day. Therefore, it is flexible to changes in demand, such as events that are difficult to respond with a system that only performs tasks that are determined in order, such as police boxes, such as an increase in demand due to an increase in demand or a suspension due to a sudden earthquake disaster. It can correspond to.

本発明に係る実施の形態の乗務員運用計画作成システムの構成を説明するブロック図である。It is a block diagram explaining the structure of the crew member operation plan creation system of embodiment which concerns on this invention. 1日の列車運行ダイヤを示した図である。It is the figure which showed the daily train operation schedule. 本発明に係る実施の形態の乗務員運用計画作成システムの全体的な処理の流れを説明するフローチャートである。It is a flowchart explaining the flow of the whole process of the crew member operation plan creation system of embodiment which concerns on this invention. 図3の行程断片の連結処理の主な流れを説明するフローチャートである。It is a flowchart explaining the main flows of the connection process of the process fragment | piece of FIG. 図4の行程断片の部分連結処理の主な流れを説明するフローチャートである。It is a flowchart explaining the main flows of the partial connection process of the process fragment | piece of FIG. 図5の行程断片の仮連結処理の流れを説明するフローチャートである。It is a flowchart explaining the flow of the temporary connection process of the process fragment | piece of FIG. 図3の仕業の改善の処理の主な流れを説明するフローチャートである。It is a flowchart explaining the main flows of the process of the work improvement of FIG. 図7の行程断片の部分交換処理の主な流れを説明するフローチャートである。It is a flowchart explaining the main flows of the partial exchange process of the process fragment | piece of FIG. 図8の行程断片の仮交換処理の主な流れを説明するフローチャートである。It is a flowchart explaining the main flows of the temporary replacement | exchange process of the process fragment | piece of FIG. 図2の1日の列車運行ダイヤから日々の休止を反映して作成した日別の列車運行ダイヤを示す図である。It is a figure which shows the daily train operation diagram created reflecting the daily stop from the daily train operation diagram of FIG. 図10の日別の列車運行ダイヤに基づいて生成された行程断片のプールを示す図である。It is a figure which shows the pool of the process fragment | piece produced | generated based on the daily train operation diagram of FIG. 図11の行程断片を時系列的に並べて日別に示した図である。なお、ここでの日付は列車運行数が最少となる時刻(図2,図10の白抜矢印参照)を日付変更としている。It is the figure which arranged the process fragment | piece of FIG. Note that the date here is the date change at the time when the number of train operations is minimized (see the white arrows in FIGS. 2 and 10). (a)〜(c)は、乗務員運用計画作成システムによる連結処理の具体例を説明する図である。(A)-(c) is a figure explaining the specific example of the connection process by a crew member operation plan creation system. 時刻と列車運行数との関係を示す一般例を示し、列車運行数が最少となる時刻を日付変更とする処理を説明するための図である。It is a figure for showing the general example which shows the relationship between time and the number of train operations, and explaining the process which makes the date change the time when the number of train operations becomes the minimum. 日別の乗務員運用表を示す図である。It is a figure which shows a crew member operation table according to day. 本発明に係る実施例の乗務員運用計画作成システムの構成を示すブロック図である。It is a block diagram which shows the structure of the crew member operation plan preparation system of the Example which concerns on this invention. (a)各列車の運転率と、運転率により分けた各列車グループを示す。(b)乗務員の乗務割合と、乗務割合により分けた各乗務員グループを示す。(A) The operation rate of each train and each train group divided according to the operation rate are shown. (B) The crew ratio of the crew and each crew group divided by the crew percentage are shown. 実施例の乗務員運用計画作成システムにより乗務員運用表を作成する全体的な処理の流れを説明するフローチャートである。It is a flowchart explaining the flow of the whole process which produces a crew member operation | movement table by the crew member operation plan creation system of an Example. 図17の列車のグループ分け処理の流れを説明するフローチャートである。It is a flowchart explaining the flow of the grouping process of the train of FIG. 図17の乗務員のグループ分け処理の流れを説明するフローチャートである。It is a flowchart explaining the flow of the crew member grouping process of FIG.

以下、本発明の実施の形態について図面を参照して説明する。図1では、本実施の形態の乗務員運用計画作成システム1の構成を説明している。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. FIG. 1 illustrates the configuration of a crew member operation plan creation system 1 according to the present embodiment.

乗務員運用計画作成システム1は、列車運行データ2aと乗務員データ2bが記憶されたデータベース2と、データベース2に記憶された情報を以下に説明する各手段により処理して乗務員運用計画を作成する処理部3と、作成した乗務員運用計画を出力する出力手段4を有している。   The crew operation plan creation system 1 includes a database 2 in which train operation data 2a and crew data 2b are stored, and a processing unit that creates a crew operation plan by processing the information stored in the database 2 by means described below. 3 and output means 4 for outputting the created crew member operation plan.

この乗務員運用計画作成システム1は、処理部3の読込手段21により需要を反映した日別の列車運行ダイヤを読込み、これに基づいて「行程断片」を複数作成し、これらを好適に連結して各乗務員の仕業を日別に作成することにより、日別の乗務員運用計画表を作成するものである。   This crew member operation plan creation system 1 reads daily train schedules reflecting demand by means of the reading means 21 of the processing unit 3, creates a plurality of “stroke fragments” based on this, and suitably links them. By creating work for each crew member by day, a crew member operation plan table for each day is created.

ここで、上述したように「行程断片」とは、乗務員の乗務単位をいう。例えば、図2に示す列車運行N1からは、A駅からB駅に列車運行N1を行う乗務内容の行程断片n1が生成される。   Here, as described above, the “stroke fragment” means a crew unit of a crew member. For example, from the train operation N1 shown in FIG. 2, a journey fragment n1 of the crew content for performing the train operation N1 from the A station to the B station is generated.

ここで、図示していないが、仮にA駅からC駅の列車運行であってB駅にて停車する列車運行があるとすると、A駅からC駅までの行程にはA−B駅間とB−C駅間との2つの行程断片が含まれることとなる。   Here, although not shown, if there is a train service from A station to C station and a train service that stops at B station, the distance from A station to C station is between A and B stations. It will include two journey fragments between B and C stations.

図2の列車運行ダイヤは、運行される貨物列車を時刻別(横軸参照)に示し、列車運行ダイヤの縦軸は各駅名及び駅間距離を簡略的に示している。符号M1,M2,N1,N2,Q1,Q2,X1,Y1は列車運行を示し、往路と復路で「列車」が異なるため、異なる列車運行「M1」、「M2」、・・・となっている。   The train operation diagram of FIG. 2 shows the freight trains operated by time (see horizontal axis), and the vertical axis of the train operation diagram simply shows the names of stations and the distances between stations. Symbols M1, M2, N1, N2, Q1, Q2, X1, and Y1 indicate train operations. Since the “train” is different between the forward route and the return route, different train operations are “M1”, “M2”, and so on. Yes.

図2に示す一般的な1日の列車運行ダイヤは、時刻別に運行される全ての列車を示しているが、例えば6月12日は列車運行Q1,Q2が休止というように当初運行する設定であった列車であっても、需要の減少により列車が運行しない場合がある。   The general daily train operation diagram shown in FIG. 2 shows all trains operated by time, but for example, on June 12, the train operations Q1 and Q2 are initially set to stop. Even if there was a train, the train may not operate due to a decrease in demand.

そのため、日別に運用計画を作成する場合には、図10に示すように、休止情報を反映させた日別の列車運行ダイヤを生成する必要がある。図10の日別の列車運行ダイヤは、図2に示す1日の列車運行ダイヤを休止情報を反映して日別に横に展開したものである。本システムにおいては、この日別の列車運行ダイヤは、列車運行データ2aに含まれているものとする。   Therefore, when creating an operation plan for each day, it is necessary to generate a daily train operation diagram reflecting the suspension information, as shown in FIG. The daily train operation diagram of FIG. 10 is obtained by expanding the daily train operation diagram of FIG. 2 side by side reflecting the stop information. In this system, it is assumed that this daily train operation schedule is included in the train operation data 2a.

以下、乗務員運用計画作成システム1の処理部3について説明する。   Hereinafter, the processing unit 3 of the crew member operation plan creation system 1 will be described.

処理部3は、日別の列車運行ダイヤを読み込むための読込手段21と、日別の各列車運行を行程断片に置き換える列車運行置換手段22と、置換した乗務員の行程断片をその開始時刻でソートする行程断片ソート手段23と、ソートされた行程断片を仮連結する仮連結手段24と、各仮連結の削減コスト量を評価する連結評価手段25と、最大の削減コスト量となる最良の仮連結を本連結する本連結手段26と、仮連結処理において既出の最良の仮連結と同じ評価値の行程断片が出現した場合に、その後の仮連結処理の少なくとも一部をバイパスするバイパス手段27と、行程断片に必要な便乗を付加して仕業にする仕業作成手段28と、仕業内の行程断片を交換して仕業を改善する仕業改善手段29と、行程断片および仕業が労働規定に違反していないかどうかをチェックする労働規定チェック手段30とを主に備えている。   The processing unit 3 sorts the daily train operation schedule by reading means 21, train operation replacement means 22 for replacing each daily train operation with a journey fragment, and the replaced crew members' journey fragments by their start times. The process fragment sorting means 23, the temporary connection means 24 for temporarily connecting the sorted process fragments, the connection evaluation means 25 for evaluating the reduction cost amount of each temporary connection, and the best temporary connection with the maximum reduction cost amount. And a bypass means 27 for bypassing at least a part of the subsequent temporary connection process when a process fragment having the same evaluation value as the best temporary connection already appeared in the temporary connection process, A work creation means 28 for adding a necessary piggyback to a work piece and performing work, a work improvement means 29 for improving work by exchanging work pieces within the work, and the work piece and work are different from the labor regulations. And labor provisions check means 30 to check whether or not mainly equipped.

ここで、「仮連結」とは、行程断片同士を一対一で仮に連結することをいい、実際に行程断片同士を連結した場合に人件費等のコストがどの程度削減されるか評価するために行われるものである。   Here, “temporary connection” means that the process fragments are temporarily connected on a one-to-one basis, and in order to evaluate how much costs such as labor costs are reduced when the process fragments are actually connected. Is to be done.

また「本連結」とは、仮連結を実際に連結して、より長い行程断片を生成することをいう。さらに、「仮連結処理」とは、複数の行程断片同士を総当りで仮連結させる処理をいう。   The “main connection” means that the temporary connection is actually connected to generate a longer stroke fragment. Furthermore, the “temporary connection process” refers to a process of temporarily connecting a plurality of process fragments together.

<列車運行置換手段>
列車運行置換手段22は、日別の列車運行を行程断片に置き換えるものである。この置換により生成される各行程断片は、少なくとも開始時刻の情報を伴った形で生成される(図11参照)。
<Train operation replacement means>
The train operation replacement means 22 replaces daily train operations with stroke fragments. Each stroke fragment generated by this replacement is generated with at least information on the start time (see FIG. 11).

<日付変更時刻>
貨物列車の運行は深夜に行われることが多いので、日付変更時刻を24時(午前0時)に合わせた場合、日を跨いだ列車の運行が不自然に分割される場合がある(例えば、A駅を出発してB駅に午後11時に着き、翌日の午前1時にB駅から出発してC駅に着くような列車があった場合、A−B駅間の運行と、B−C駅間の運行が別々に分割された計画作成対象となってしまう)。
<Date change time>
Freight trains are often operated at midnight, so if the date change time is set to 24:00 (midnight), train operations across days may be unnaturally divided (for example, If there is a train that departs from station A and arrives at station B at 11:00 pm, then arrives at station B at 1:00 am the next day, trains between stations A and B and station C The operation between them will be the target of creating a plan divided separately).

そこで、運行列車数が最少の時間帯を日付変更時刻として設定するのが望ましい。例えば、図13に示す一般例では設定した時刻(白抜矢印)が日付変更時刻となる。これにより運行列車数が多い時間帯が同一日付として探索範囲になるため、連結対象が見つかるのが早くなる効果がある。該当時刻に列車が運行されている場合もあるが、本システムは連続した日付同士を併せて探索範囲にする仕組みを有し、結局は本連結されるため問題とはならない。   Therefore, it is desirable to set the time zone with the smallest number of trains as the date change time. For example, in the general example shown in FIG. 13, the set time (open arrow) is the date change time. As a result, the time zone with a large number of operating trains becomes the search range as the same date, so that there is an effect that the connection target is found earlier. There are cases where trains are operated at the corresponding time, but this system has a mechanism that makes consecutive search dates together into a search range, and since it is finally connected, there is no problem.

日付変更時刻は、列車運行数が最少の時刻であればよく、夜間に限らず日中に設定することもできる。また、貨物列車に限らず他の乗務員運用計画について本システムにより計画を作成する場合でも同様に日付変更時刻を設定することができる。   The date change time only needs to be the time when the number of train operations is the smallest, and can be set not only at night but also during the day. In addition, the date change time can be set in the same manner even when a plan is created by this system for other crew operation plans, not limited to freight trains.

<行程断片ソート手段>
行程断片ソート手段23は、生成された各行程断片のプール(図11参照)につき、各行程断片の開始時刻を指標にして各行程断片を時系列的に並び替えるソートを行うものである。図12にソートされた日付別の行程断片を示す。なお、図12の各行程断片は、図11と同様に、図10の各列車運行に対応した小文字のアルファベットで示されている。
<Process fragment sorting means>
The process fragment sorting means 23 performs sorting that rearranges each process fragment in time series using the start time of each process fragment as an index for the generated pool of each process fragment (see FIG. 11). FIG. 12 shows the process fragments sorted by date. In addition, each process fragment of FIG. 12 is shown by the small letter alphabet corresponding to each train operation of FIG. 10 similarly to FIG.

<仮連結手段>
仮連結手段24は、1回の仮連結処理で対象とする連続日分(例えば連続3日分、図12の探索範囲参照)の行程断片を、図12に示すように日別に展開された行程断片の中から抽出し、さらに、そのうちの一の行程断片を基礎断片として選択し、基礎断片と時系列的に重複しない他の行程断片とで仮連結を行うものである。
<Temporary connection means>
The temporary connection means 24 is a process in which process fragments for consecutive days (for example, for three consecutive days, see the search range in FIG. 12) targeted in one temporary connection process are expanded on a daily basis as shown in FIG. Extracting from the fragments, further selecting one of the stroke fragments as a basic fragment, and temporarily connecting the basic fragment with another stroke fragment that does not overlap in time series.

仮連結手段24は、基礎断片の開始時刻の前後24時間以内の時点を開始時刻とする他の行程断片を抽出して仮連結する。これは、開始時刻差が24時間を越える行程断片との連結が労働規定等により制約されることによる。この例では、1回の仮連結処理の対象を連続3日分としている。これは一日の途中から始まる24時間の仕業を作成するためには2日間を探索対象にする必要があること、列車運用の周期性を利用するためにはさらにもう一つの仕業が入る範囲を対象とする必要があるためである。   The temporary connection means 24 extracts and temporarily connects other process fragments whose start time is within 24 hours before and after the start time of the basic fragment. This is because the connection with a process fragment whose start time difference exceeds 24 hours is restricted by labor regulations and the like. In this example, the target of one temporary connection process is set to three consecutive days. This means that it is necessary to search for two days in order to create a 24-hour work starting from the middle of the day, and in order to use the periodicity of train operation, another work can be included. This is because it is necessary to target.

しかし、乗務員が連泊で行う等の仕業を考慮して24時間を越える行程断片と仮連結するようにしてもよく、この場合、1回の仮連結処理の対象とする連続日分(探索範囲)を連続4日分以上としてもよい。   However, it may be possible to temporarily link with a travel fragment exceeding 24 hours in consideration of work performed by the crew for consecutive nights. In this case, consecutive days (search range) to be subjected to one temporary connection process. ) May be four consecutive days or more.

<連結評価手段>
連結評価手段25は、仮連結手段24による一対一の仮連結で得られる行程断片についての評価値が所定の評価基準値を超えるか否かを仮連結ごとに判断するものである。例えば、この評価値は仮連結した場合の評価基準値を削減コスト量とすることができる。
<Consolidation evaluation means>
The connection evaluation unit 25 determines, for each temporary connection, whether or not the evaluation value for the stroke fragment obtained by the one-to-one temporary connection by the temporary connection unit 24 exceeds a predetermined evaluation reference value. For example, for this evaluation value, an evaluation reference value when provisionally connected can be used as a reduction cost amount.

この場合、図12に示す例では、3日目の行程断片q1,q2と1日目の行程断片n1,n2を比較すると行程断片q1,q2の方が行程断片同士の間隔が狭くコスト削減されることから、仮連結時の評価値が高いものとなる。したがって、1〜3日目を仮連結処理する場合、3日目の行程断片q1,q2の仮連結が最良の仮連結ということになる。   In this case, in the example shown in FIG. 12, when the third-day process fragments q1 and q2 are compared with the first-day process fragments n1 and n2, the process fragments q1 and q2 have a narrower interval between the process fragments and the cost is reduced. Therefore, the evaluation value at the time of provisional connection is high. Accordingly, when temporary connection processing is performed on the first to third days, the temporary connection of the process fragments q1 and q2 on the third day is the best temporary connection.

また、連結評価手段25は、一連の仮連結を試行している最中は、仮連結の評価基準値としての、その時点での連結時最良削減コストを常に更新し続ける。そして、一連の仮連結が終了した時点で、連結時最良削減コストの情報、つまり最もコスト削減がされた最良の仮連結と、その評価値の情報を後述の本連結手段26に渡す。   Further, the connection evaluation means 25 always keeps updating the connection-time best reduction cost as the evaluation reference value of the temporary connection while trying a series of temporary connections. Then, when a series of temporary connections are completed, the information on the best reduction cost at the time of connection, that is, the best temporary connection in which the cost has been reduced and the evaluation value information are passed to the main connection means 26 described later.

また、連結評価手段25は、本連結手段26に渡した評価値が、既に行なった仮連結処理における最高の評価値から計算された、連結打切基準値としての連結打切用削減コストより上回っているか否かについても判断し、上回っていない場合には後述の本連結をさせないようにする。   Whether the evaluation value given to the connection means 26 exceeds the reduction cost for connection termination as the connection termination reference value calculated from the highest evaluation value in the temporary connection processing that has already been performed. It is also judged whether or not, and if it does not exceed, it will not be connected as described later.

これは、最もコスト削減される仮連結であっても、連結打切用削減コストを上回っていなければ、十分なコスト削減が達成されていないものとして、本連結の対象から除くものである。これにより、コスト削減の低い行程断片同士を本連結せず、他の探索範囲内にある行程断片との連結ができるようにする。   This is excluded from the scope of this consolidation, even if the temporary cost reduction is the most cost-reduced, as long as it does not exceed the reduction cost for closing the connection, sufficient cost reduction has not been achieved. As a result, stroke fragments with low cost reduction are not linked to each other, but can be linked to stroke fragments in other search ranges.

<本連結手段>
本連結手段26は、最良の仮連結を本連結して、より長い行程断片又は仕業を作成するものである。本連結された行程断片は、新たな行程断片として再び仮連結処理に供される。
<This connection means>
The main connecting means 26 is for main connecting the best temporary connection to create a longer stroke fragment or work. The main linked process fragment is again used for the temporary connection process as a new process fragment.

<バイパス手段>
バイパス手段27は、既に本連結された仮連結と同じ条件の仮連結が出現した場合に、それ以降に予定されている仮連結を省略して、その現在試行している1回分の仮連結処理を終了させるものである。
<Bypass means>
The bypass means 27 omits the temporary connection scheduled after that when the temporary connection of the same condition as the already temporarily connected temporary connection appears, and temporarily performs the temporary connection process for the current trial. Is to end.

具体的には、一の基礎断片と他の行程断片について一対一の仮連結を行っている最中に、既に本連結された最良の仮連結の削減コスト量と同じ仮連結が現れた場合、既出の仮連結と同じ条件のものと判断して、それ以降の仮連結は行わないようにするものである。   Specifically, when one-to-one temporary connection is performed for one basic fragment and another process fragment, the same temporary connection as the reduction cost of the best temporary connection that has already been fully connected appears. It is determined that the conditions are the same as those of the temporary connection described above, and the subsequent temporary connection is not performed.

<仕業作成手段>
仕業作成手段28は、上記条件を満たす本連結をそれ以上することができない本連結後の行程断片について解析を行い、仕業が基地駅で開始および終了しているか否かを判断する。仕業が基地駅で開始していない、あるいは、基地駅で終了していない場合には、基地駅から開始して基地駅に戻る仕業となるように本連結後の行程断片に対して旅客便乗を付加したり適切な位置で切断を行ったりする。
<Work creation method>
The work creation means 28 analyzes the process fragment after the main connection that cannot further perform the main connection that satisfies the above conditions, and determines whether the work has started and ended at the base station. If the work has not started at the base station or has not ended at the base station, passengers can be boarded on the post-consolidated journey fragment so that the work starts at the base station and returns to the base station. Add or cut at an appropriate position.

仕業の基地駅については、任意の手段で決めることとしてもよいが、どの基地駅に仕業が所属するものであるかは仕業作成時に決定されている必要がある。   The base station for the work may be determined by any means, but the base station to which the work belongs needs to be determined when the work is created.

基地駅が一つの場合には基地駅は自明であるが、二以上の基地駅がある場合、各仕業について基地駅を決定する必要がある。基地駅を決定する方法としては、例えば業務ルールとして定めたり、行程断片の駅に近い基地駅を選択することができる。   When there is one base station, the base station is self-explanatory, but when there are two or more base stations, it is necessary to determine the base station for each operation. As a method for determining the base station, for example, business rules can be set, or a base station close to the station of the process fragment can be selected.

A駅が基地駅である乗務員の場合、同じ基地駅Aを開始地点と終了地点とする行程断片は、何ら修正をしなくとも、それだけで一つの仕業となる。これに対して、行程断片の開始地点又は終了地点が同じ基地駅Aでない場合は、便乗や行程断片を付加することで基地駅Aに戻る仕業に修正しなければならない。   In the case of a crew member whose station A is a base station, a process fragment having the same base station A as a start point and an end point is only one work without any modification. On the other hand, if the starting point or the ending point of the journey fragment is not the same base station A, it is necessary to correct the operation to return to the base station A by adding the flight boarding or the journey fragment.

<仕業改善手段>
仕業改善手段29は、仕業同士で一部行程断片を仮交換して評価値が改善できる場合に、本交換を行うものである。
<Work improvement measures>
The work improvement means 29 performs this exchange when the evaluation value can be improved by temporarily exchanging partial process fragments between works.

ここで「仮交換」とは、対象とする複数の仕業にそれぞれ含まれる行程断片同士を異なる仕業間で、一対一で仮に交換することをいい、実際に行程断片同士を交換した場合に人件費等のコストがどの程度削減されるか評価するために行われるものである。   Here, “provisional exchange” means to temporarily exchange one-to-one process fragments included in each of a plurality of targeted operations, and personnel expenses when actual process fragments are exchanged. It is performed in order to evaluate how much the cost is reduced.

また「本交換」とは、仕業同士間で実際に行程断片を組換える交換をして新たな仕業を再生成することをいう。さらに、「仮交換処理」とは、複数の行程断片同士を総当りで仮交換させる処理をいう。   Also, “main exchange” means that a new work is regenerated by exchanging the actual process fragments between the works. Further, the “temporary exchange process” refers to a process of temporarily exchanging a plurality of stroke fragments with a round robin.

仕業改善手段29は、仮交換する前の各仕業の評価値の和と仮交換した後の各仕業の評価値の和を比較し、交換の前後で評価値の合計が改善される場合には本交換を行う。   The work improvement means 29 compares the sum of the evaluation values of each work before provisional exchange with the sum of the evaluation values of each work after provisional exchange. When the sum of the evaluation values is improved before and after the exchange, Perform this exchange.

また、仕業改善手段29は、仮連結処理と同様、所定の連続日分(例えば連続3日分)を探索範囲として仮交換処理することで、仮交換対象を時系列に限られた範囲に限定することができる。   Also, the work improvement means 29 limits the provisional replacement target to a range limited to a time series by performing a provisional exchange process using a predetermined continuous day (for example, three consecutive days) as a search range, similarly to the provisional connection process. can do.

加えて、一の仮交換処理中に、既出の最良の仮交換時の評価値と同値の評価値が出現した場合には、前記バイパス手段27によって、それ以降の仮交換を省略させてもよい。   In addition, when an evaluation value equal to the evaluation value at the time of the best temporary replacement that has already appeared appears during one temporary replacement process, the subsequent temporary replacement may be omitted by the bypass means 27. .

<労働規定チェック手段>
労働規定チェック手段30は、仮連結手段24で仮連結された行程断片、仕業作成手段28で作成された仕業、仕業改善手段で行程断片の仮交換が行われた仕業が労働規定を満たしているかをチェックする。
<Labor regulation check method>
The labor regulation checking means 30 determines whether the work piece temporarily connected by the temporary connection means 24, the work created by the work creation means 28, or the work in which the work piece is temporarily exchanged by the work improvement means satisfy the labor regulations. Check.

例えば、作成された仕業が長すぎて1回の乗務時間の制限を超えていれば、その仕業は成り立たない。また、継続して乗務することができる距離や時間に制限がある場合は、それを超える乗務を含む仕業は成り立たない。さらに、乗務時間にその他の必要業務時間を加えた労働時間が制限を超えるような仕業も成り立たない。   For example, if the created work is too long and exceeds the limit of one flight time, the work is not realized. In addition, if there is a limit to the distance or time during which you can continue to ride, work that includes more than that will not work. Furthermore, work that exceeds the limit of working hours by adding the other required work hours to the crew hours cannot be realized.

このような仕業あるいは行程断片は、労働規定チェック手段30により検出され、コストの削減が不可能と判断されたり、交換の候補から外したりされる。   Such a work or process fragment is detected by the labor regulation checking means 30, and it is determined that the cost cannot be reduced, or is excluded from replacement candidates.

<出力手段>
出力手段4は、乗務員運用計画作成システム1の処理部3によって生成された乗務員運用表を出力する処理を行う。この出力手段4は、記録媒体にデータを書き込む手段、プリンター又はモニタなどのいずれの構成であってもよい。
<Output means>
The output unit 4 performs a process of outputting the crew member operation table generated by the processing unit 3 of the crew member operation plan creation system 1. The output unit 4 may be any configuration such as a unit for writing data on a recording medium, a printer, or a monitor.

<行程断片の連結処理>
次に、図3〜図6のフローチャートを参照しながら、本実施の形態の乗務員運用計画作成システム1の処理の流れについて説明する。
<Concatenation of process fragments>
Next, the flow of processing of the crew member operation plan creation system 1 according to the present embodiment will be described with reference to the flowcharts of FIGS.

ステップS1−1において、処理部3の読込手段21により日別の列車運行のデータを有する列車運行データ2aの読込みを行う。   In step S1-1, the train operation data 2a having daily train operation data is read by the reading means 21 of the processing unit 3.

上述したように、この列車運行データ2aは、需要の増減等により予定が変わることにより、日々異なったものとなっている。   As described above, the train operation data 2a is different every day due to a change in schedule due to an increase or decrease in demand or the like.

図2の1日の列車運行ダイヤ中の列車運行M1,M2,N1,N2,Q1,Q2,X1,Y1の全列車が日々繰り返し運行される予定であった場合に、図10の日別の列車運行ダイヤに示すように、例えば6月12日では列車運行N1,N2,Q1,Q2,X1,Y1が休止して列車運行N1,N2のみが運行するように、日々異なったものとなっている。   When all trains M1, M2, N1, N2, Q1, Q2, X1, and Y1 are scheduled to be repeatedly operated every day in the daily train schedule of FIG. As shown in the train schedule, for example, on June 12th, train operations N1, N2, Q1, Q2, X1, and Y1 are stopped and only train operations N1 and N2 are operated. Yes.

ステップS1−2では、日別の列車運行ダイヤの列車運行に対応した、日別の行程断片を生成する。具体的には、図10に示す6月12日の列車運行N1に基づいて、6月12日の行程断片n1(図11、図12参照)が生成されるというように、それぞれ行程断片が生成される。   In step S1-2, a daily process fragment corresponding to the train operation of the daily train operation diagram is generated. Specifically, based on the train operation N1 on June 12 shown in FIG. 10, the journey fragment n1 (see FIG. 11 and FIG. 12) is generated on June 12, and each journey fragment is generated. Is done.

これにより、運用表の作成対象期間の日付分の行程断片によりなる行程断片のプールが作成される(図11参照)。図11に示すプールに含まれる各行程断片は、外見上は同じような行程断片があるが、それぞれの行程断片は、少なくとも異なる開始時刻を有しているため、互いに異なる行程断片となる。   As a result, a pool of stroke fragments composed of the stroke fragments for the date of the operation table creation target period is created (see FIG. 11). Each process fragment included in the pool shown in FIG. 11 has a similar process fragment in appearance, but each process fragment has a different start time, and thus is a different process fragment.

図3を参照して、ステップS1−3では、行程断片のプールに含まれる行程断片同士を、具体的に後述するサブステップS2〜S4系(図4〜図6参照)により、時系列的に重複しないように好適に連結させて乗務員の仕業を生成する。   Referring to FIG. 3, in step S1-3, the process fragments included in the process fragment pool are time-sequentially processed by sub-steps S2 to S4 (see FIGS. 4 to 6) which will be described later. A crew member's work is generated by suitably connecting them so as not to overlap.

ステップS1−4では、行程断片から各乗務員の仕業を生成する。上述したように、便乗を付加等して乗務員の発駅と着駅を同じ基地駅とする処理を行う。   In step S1-4, the work of each crew member is generated from the process fragment. As described above, a process is performed in which a crew member's departure station and arrival station are set to the same base station by adding a flight.

ステップS1−5では、生成した乗務員の仕業のそれぞれに含まれる行程断片を相互に交換して仕業の改善を行う。この具体的な処理は、ステップS5〜S7(図7〜図9参照)にて後述するが、仕業に含まれる行程断片を他の仕業の行程断片と仮交換及び本交換することにより、仕業の改善を行うものである。   In step S1-5, the process fragments included in each of the generated crew member's work are mutually exchanged to improve the work. This specific process will be described later in steps S5 to S7 (see FIG. 7 to FIG. 9). However, by replacing the process fragment included in the work with the process fragments of other work, It is an improvement.

ステップS1−6では、改善された仕業に各列車運行を割り付けるとともに、さらにステップS1−7にて乗務員を各仕業に割り付ける。   In step S1-6, each train operation is assigned to the improved work, and a crew member is assigned to each work in step S1-7.

ステップS1−8では、割り付けて生成した乗務員運用表を出力手段4により出力する(図14参照)。なお、乗務員「高橋」と「中田」の基地駅はA駅であり、乗務員「江藤」と「馬込」の基地駅はB駅である。   In step S1-8, the crew member operation table generated by assignment is output by the output means 4 (see FIG. 14). The base stations for the crew members “Takahashi” and “Nakada” are the A stations, and the base stations for the crew members “Eto” and “Magome” are the B stations.

<行程断片の連結処理>
図4〜図6を参照しながら、行程断片の部分連結処理について以下に説明する。
<Concatenation of process fragments>
The process fragment partial linking process will be described below with reference to FIGS.

ステップS2−1では、図11に示す行程断片のプールに含まれる行程断片を、その開始時刻を指標にして日別の各群(日別リスト)に仕分けする。   In step S2-1, the process fragments included in the pool of process fragments shown in FIG. 11 are sorted into daily groups (daily lists) using the start time as an index.

ステップS2−2では、行程断片の部分連結処理を行う。ここで示す例では、図12に示すように、連続する3つの群(連続3日分の行程断片)を部分連結処理の対象としている(図12の「探索範囲」参照)。   In step S2-2, the process fragment partial connection process is performed. In the example shown here, as shown in FIG. 12, three consecutive groups (stroke fragments for three consecutive days) are the targets of the partial connection process (see “search range” in FIG. 12).

この部分連結処理は、主として後述の仮連結から本連結までの一連の連結処理を内容とするものである(図5,図6参照)。この部分連結処理により、処理対象の複数群に含まれる行程断片のうち、最も高い削減コスト量であり且つ既出の仮連結の最高の評価値から計算された連結打切用削減コストを上回る仮連結が本連結されることとなる。   This partial connection process mainly includes a series of connection processes from the temporary connection described later to the main connection (see FIGS. 5 and 6). With this partial connection process, temporary connection that exceeds the reduction cost for connection termination that is the highest reduction cost amount among the process fragments included in the plurality of groups to be processed and that is calculated from the highest evaluation value of the temporary connection that has already been issued. This will be connected.

続いて、ステップS2−3では、ステップS2−2の部分連結処理において本連結があったか否かを判断し、本連結があった場合(Yes)はステップS2−4に進む。逆に、本連結がなかった場合(No)はステップS2−7に進む。   Subsequently, in step S2-3, it is determined whether or not there is a main connection in the partial connection process in step S2-2. If there is a main connection (Yes), the process proceeds to step S2-4. Conversely, if there is no main connection (No), the process proceeds to step S2-7.

ステップS2−4では、本連結情報を「有」に設定する。ここで、「本連結情報」とは、例えば30日分の計画を作成する場合に、当該30日分の部分連結処理において、少なくとも1回、本連結がなされたか否かの情報を示すものである。   In step S2-4, this connection information is set to “present”. Here, “mainly connected information” indicates, for example, information on whether or not the main connection has been made at least once in the partial connection process for 30 days when a plan for 30 days is created. is there.

これにより、もし30日分の部分連結処理が終了した時点で「本連結情報」が「有」であれば、条件を満たす部分連結がさらになされる余地があるということが分かる。一方、「本連結情報」が「無」であれば、それ以上、条件を満たす部分連結がなされる余地がないことが分かる。   As a result, it is understood that if the “main link information” is “present” at the time when the partial link process for 30 days is completed, there is a room for further partial link that satisfies the condition. On the other hand, if “main link information” is “none”, it can be understood that there is no room for partial connection that satisfies the conditions.

ステップS2−5では、部分連結前の行程断片を日別リストから削除する。これは、部分連結処理で生成した新たな行程断片と部分連結前の2つの行程断片とが重複することを避けるために行う。   In step S2-5, the process fragment before partial connection is deleted from the daily list. This is performed in order to avoid the overlap between the new process fragment generated by the partial connection process and the two process fragments before the partial connection.

ステップS2−6では、部分連結処理で生成した新たな行程断片を日別リストに追加して日別リストを更新する。   In step S2-6, the new process fragment generated by the partial connection process is added to the daily list to update the daily list.

ステップS2−7では、運用計画を作成する対象の期間(例えば30日分)について、部分連結に関する一連の処理が完了したか否かを判断し、完了した場合(Yes)はステップS2−10に進む。   In step S2-7, it is determined whether or not a series of processing relating to partial connection has been completed for a period for which an operation plan is to be created (for example, for 30 days), and if completed (Yes), the process proceeds to step S2-10. move on.

一方、計画対象期間(例えば30日分)の部分連結処理が完了していない場合(No)は、本連結情報を「無」に設定し(ステップS2−8)、部分連結処理の対象を1日分ずらす探索範囲の変更処理(ステップS2−9)をしてステップS2−2に戻る。   On the other hand, when the partial connection process for the plan target period (for example, 30 days) is not completed (No), this connection information is set to “None” (step S2-8), and the target of the partial connection process is set to 1. The search range changing process (step S2-9) shifted by the day is performed, and the process returns to step S2-2.

ステップS2−10では、上述した「本連結情報」が「有」であると判断された場合には、さらに条件を満たす部分連結がなされる余地があると判断して、本連結情報を「無」に設定し(ステップS2−8)、部分連結処理の対象を1日分ずらす探索範囲の変更処理(ステップS2−9)をしてステップS2−2に戻る。   In step S2-10, when it is determined that the “main link information” described above is “present”, it is determined that there is a room for partial connection that satisfies a further condition, and the main link information is set to “none”. "(Step S2-8), the search range changing process (step S2-9) for shifting the target of the partial connection process by one day is performed, and the process returns to step S2-2.

一方、「本連結情報」が「有」でないと判断された場合(No)は、それ以上、条件を満たす部分連結がなされる余地がないものと判断して、メインルーチンに戻ってステップS1−4に進む(図3参照)。   On the other hand, if it is determined that the “main connection information” is not “present” (No), it is determined that there is no room for further partial connection that satisfies the condition, and the process returns to the main routine to return to step S1- Go to 4 (see FIG. 3).

<部分連結処理>
図5,6に部分連結処理のフローチャートを示す。
<Partial consolidation processing>
5 and 6 are flowcharts of the partial connection process.

部分連結処理は、仮連結処理と本連結処理とからなり、例えば30日分の乗務員運用計画を作成する場合、部分的な連続3日分(例えば1〜3日目)の範囲に含まれる行程断片(例えば図12の行程断片n1,n2,n1,n2,x1,q1,q2)について、仮連結処理を試行する。この仮連結処理では、行程断片同士が連結した場合の評価値(ここでは削減コスト量)を算出するために行程断片同士を仮に連結し、実際の連結(本連結)は行わない。   The partial connection process consists of a temporary connection process and a main connection process. For example, when creating a crew operation plan for 30 days, a process included in a range of partial three consecutive days (for example, the first to third days). For the fragments (for example, the process fragments n1, n2, n1, n2, x1, q1, q2 in FIG. 12), a temporary connection process is tried. In this temporary connection process, the process fragments are temporarily connected to calculate an evaluation value (here, a reduction cost amount) when the process fragments are connected, and actual connection (main connection) is not performed.

このうち一の行程断片(例えば1日目の行程断片n1)を固定して、他の行程断片(この例では行程断片n2(1日目),n1,n2,x1(2日目),q1,q2(3日目))と順に一対一の仮連結していく。その後、固定する行程断片を交換して同様に仮連結し、結果として総当りの仮連結を行なう。そして、各仮連結の削減コスト量を算出し、削減コスト量が最も多い最良の仮連結(例えば3日目の行程断片q1とq2の仮連結)を返す(ここまでが1回分の仮連結処理となる)。   One of the stroke fragments (for example, the stroke fragment n1 of the first day) is fixed, and the other stroke fragments (in this example, the stroke fragments n2 (first day), n1, n2, x1 (second day), q1 , Q2 (3rd day)) and one-to-one temporary connection. Thereafter, the process pieces to be fixed are exchanged and temporarily connected in the same manner. As a result, the round robin temporary connection is performed. Then, the reduction cost amount of each temporary connection is calculated, and the best temporary connection with the largest reduction cost amount (for example, the temporary connection of the process pieces q1 and q2 on the third day) is returned (the temporary connection processing up to here is one time). Becomes).

そして、この最良の仮連結によって既出の仮連結の最高の評価値から計算された連結打切用削減コストを超えるコスト削減が可能であるとき、これを本連結する。その後、本連結により行程断片が1つ減少した状態で、再び仮連結処理からの試行を繰り返す。この一連の処理より、一定の条件を満たしたより長い行程断片が作成される。   Then, when the best temporary connection can reduce the cost exceeding the connection cutting reduction cost calculated from the highest estimated value of the temporary connection, the main connection is performed. After that, the trial from the temporary connection process is repeated again in a state where the stroke fragment is reduced by one by the main connection. By this series of processing, a longer stroke fragment that satisfies a certain condition is created.

前述の削減コスト量は、所定の評価関数に基づいて算出されるものであり、この評価関数を構成する要素としては、例えば、行程断片同士の開始時刻の時間差(時間差が大きいほど削減コスト量小)や、便乗数(便乗を伴うほど削減コスト量小)などのコストに纏わるものである。   The above-described reduction cost amount is calculated based on a predetermined evaluation function. As an element constituting this evaluation function, for example, the time difference between the start times of the process fragments (the larger the time difference, the smaller the reduction cost amount). ) And the number of flight multipliers (the amount of reduction cost decreases as the flight increases).

以下、図5を参照しながら、3日単位で行う部分連結処理S3系の各ステップについて説明する。なお、スタートの段階では、後述の削減コスト量および連結時最良削減コストが「−1」の値にリセットされる。   Hereinafter, each step of the partial connection processing S3 system performed in units of three days will be described with reference to FIG. Note that, at the start stage, a reduction cost amount, which will be described later, and a concatenation best reduction cost are reset to a value of “−1”.

ステップS3−1では、行程断片のプールに含まれる各行程断片の開始時刻を指標にして行程断片を開始時刻の順にソートする。   In step S3-1, the process fragments are sorted in the order of the start time using the start time of each process fragment included in the pool of process fragments as an index.

この開始時刻は、行程断片同士を仮連結する際(後述のステップS4−3)に用いられ、一の行程断片に対する連結対象を限定するために用いられる。   This start time is used when temporarily connecting the stroke fragments (step S4-3, which will be described later), and is used to limit the connection target for one stroke fragment.

ステップS3−2では、ステップS3−1でソートしたもののうち、連続日分(ここでは連続3日分)の行程断片同士の仮連結処理を行う。仮連結処理では、上述したように削減コスト量が最も高い仮連結を最良の仮連結として返すとともにその削減コスト量を返す。   In step S3-2, temporary concatenation processing is performed between the process fragments for consecutive days (here, for three consecutive days) among those sorted in step S3-1. In the temporary connection process, as described above, the temporary connection having the highest reduction cost is returned as the best temporary connection and the reduction cost is returned.

ステップS3−3では、この削減コスト量が正の値であるか、つまり、最良の仮連結によりコスト削減されるか否かを判断する。正の値であってコスト削減される場合(Yes)は、ステップS3−4へ進む。逆にコスト増で負の値となる場合(No)は、リターンしてステップS2−3へ進む。   In step S3-3, it is determined whether this reduction cost amount is a positive value, that is, whether the cost is reduced by the best temporary connection. When it is a positive value and the cost is reduced (Yes), the process proceeds to step S3-4. Conversely, if the cost increases and becomes a negative value (No), the process returns and proceeds to step S2-3.

なお、ステップS3−3で示す「削減コスト」は、図6に示す仮連結処理からリターンした時点の「連結時最良削減コスト」と同じ値である。   The “reduction cost” shown in step S3-3 is the same value as the “best reduction cost at connection” when returning from the temporary connection process shown in FIG.

この削減コスト量については隣接する行程断片との開始時刻の差が大きくコスト増となって負の値となる場合もある(例えば、図12の行程断片n2とq1参照)。   With respect to this reduced cost amount, the difference in start time between adjacent process fragments may be large, resulting in a cost increase and a negative value (see, for example, process fragments n2 and q1 in FIG. 12).

ステップS3−4では、削減コスト量の連結打切用削減コストが設定されているか否かを判断し、設定されていない場合(No)はステップS3−6に進み、設定されている場合(Yes)はステップS3−5に進む。   In step S3-4, it is determined whether or not a reduction cost for connection termination of the reduction cost amount is set. If not set (No), the process proceeds to step S3-6, and is set (Yes). Advances to step S3-5.

この連結打切用削減コストは、ステップS3−6で算定される基準の値である。最初の段階では、どの程度コスト削減できるか不明であるため、一回目の仮連結処理(図12では、1〜3日目の行程断片n1,n2(1日目),n1,n2,x1(2日目),q1,q2(3日目)の総当りの仮連結)を行い、そこで得られた最良の仮連結の削減コスト量を用いて連結打切用削減コストを定める。   This reduction cost for connection termination is the standard value calculated in step S3-6. Since it is unclear how much the cost can be reduced at the first stage, the first temporary connection process (in FIG. 12, the process fragments n1, n2 (first day), n1, n2, x1 on the first to third days) 2nd day), q1, q2 (3rd day) round-robin provisional connection), and using the best temporary connection reduction cost amount obtained there, the reduction cost for connection termination is determined.

ステップS3−6では、削減コスト量の連結打切用削減コストの算定を行う。例えば、最良の仮連結の削減コスト量に0.95を乗じて得た値を連結打切用削減コストとして定める。この連結打切用削減コストの設定を低く設定すると、削減コスト量が少ない行程断片同士が本連結されやすくなるために調節する必要がある。   In step S3-6, the reduction cost for the connection termination of the reduction cost amount is calculated. For example, a value obtained by multiplying the best temporary connection reduction cost amount by 0.95 is determined as the connection cutoff reduction cost. If the connection cut-off reduction cost is set to a low value, it is necessary to adjust the process fragments so that the process fragments having a small reduction cost amount are easily connected to each other.

一方、ステップS3−5では、2回目以降の仮連結処理で得られた最良の仮連結の削減コスト量が、ステップS3−6で設定した削減コスト量の連結打切用削減コストより高いか否かを判断する。連結打切用削減コストより高い場合(No)は、隣接する他の探索範囲にある行程断片との接続と比べて十分にコスト削減される最良の仮連結と判断して、ステップS3−7に進む。   On the other hand, in Step S3-5, whether the reduction cost amount of the best temporary connection obtained in the second and subsequent temporary connection processes is higher than the reduction cost for connection termination set in the reduction cost amount set in Step S3-6. Judging. If it is higher than the connection cut-off reduction cost (No), it is determined as the best temporary connection that is sufficiently cost-reduced compared to the connection with the process fragment in another adjacent search range, and the process proceeds to step S3-7. .

逆に、削減コスト量の連結打切用削減コストより低い場合(Yes)は、十分なコスト削減がなされない最良の仮連結と判断し、リターンしてステップS2−3に進む。   On the other hand, if the reduction cost amount is lower than the connection cutting reduction cost (Yes), it is determined that the best temporary connection is not made with sufficient cost reduction, and the process returns to step S2-3.

ステップS3−7では、各部分連結処理において「初回の」仮連結処理で出現した削減コスト量を後述するステップS4−9のバイパス連結用削減コストとして設定する。このバイパス連結用削減コストについては、ステップS4−9にて後述する。   In step S3-7, the reduction cost amount that appears in the “first” provisional connection process in each partial connection process is set as a reduction cost for bypass connection in step S4-9 described later. This bypass connection reduction cost will be described later in step S4-9.

ステップS3−8では、ステップS3−2で返された最良の仮連結となる2つの行程断片を本連結して新たな行程断片を生成する。   In step S3-8, the two stroke fragments that are the best temporary links returned in step S3-2 are fully linked to generate a new stroke fragment.

ステップS3−9では、本連結する前の2つの行程断片を削除する。   In step S3-9, the two stroke fragments before the main connection are deleted.

ステップS3−10では、本連結した新たな行程断片を、ステップS3−1で開始時刻順にソートした他の行程断片の時系列的に正しい位置に挿入する。   In step S3-10, the newly connected new process fragment is inserted into the correct position in time series of the other process fragments sorted in the order of the start time in step S3-1.

以下、図6を参照しながら仮連結処理について具体的に説明する。   Hereinafter, the temporary connection process will be specifically described with reference to FIG.

ステップS4−1では、ステップS3−1でソートされた行程断片の中から基礎断片としての一の行程断片を選択する。この基礎断片の選択は、ステップS4−1に来るごとに開始時刻でソートされている行程断片のプールを一つずつ移動する(また、最後に到達した場合は最初に戻る)。これにより時刻順に仮連結処理が行われ、周期性を利用した探索を行うことができる。   In step S4-1, one stroke fragment as a basic fragment is selected from the stroke fragments sorted in step S3-1. The selection of the basic fragment moves the pool of the stroke fragments sorted by the start time one by one every time it comes to step S4-1 (and returns to the beginning when it reaches the end). Thereby, temporary connection processing is performed in order of time, and a search using periodicity can be performed.

ステップS4−2では、行程断片のプールの中から他の一の行程断片を選択する。   In step S4-2, another stroke fragment is selected from the pool of stroke fragments.

ステップS4−3では、ステップS4−1で選択した一の行程断片とステップS4−2の他の一の行程断片との開始時刻差が24時間以内か否か判断する。   In step S4-3, it is determined whether the start time difference between the one stroke fragment selected in step S4-1 and the other stroke fragment in step S4-2 is within 24 hours.

24時間を超えている場合は、他の一の行程断片の選択を打ち切ってよい。これは、行程断片は開始時刻でソートされており、以降の選択では必ず24時間を超えることが分かるためである。24時間という値は、労働規定等に基づいて任意に設定することができる。   If it exceeds 24 hours, the selection of the other one stroke fragment may be discontinued. This is because the stroke fragments are sorted by the start time, and it can be seen that subsequent selections always exceed 24 hours. The value of 24 hours can be arbitrarily set based on labor regulations.

ステップS4−4では、一の行程断片と他の一の行程断片の仮連結を行い、次いでステップS4−5では、この仮連結について、本連結したとしたならば削減される削減コスト量を評価値として所定の評価関数により算出する。   In step S4-4, one stroke fragment and one other stroke fragment are temporarily connected, and then in step S4-5, if this temporary connection is assumed to be the main connection, the reduction cost amount to be reduced is evaluated. The value is calculated by a predetermined evaluation function.

この削減コスト量については、労働規定チェック手段30でチェックを行った結果、違反が検出された場合にはコスト増すなわち負の値を用いる。また、用いる評価関数にもよるが、開始時刻が極端に離れているような行程断片同士を仮連結した場合には、コスト増となって負の値となる場合もある。   With respect to this reduction cost amount, if a violation is detected as a result of checking by the labor regulation checking means 30, a cost increase, that is, a negative value is used. Further, although depending on the evaluation function to be used, when the process fragments whose start times are extremely far apart are temporarily connected, the cost may increase and become a negative value.

ステップS4−6では、この削減コスト量が現行の仮連結処理において最も高い削減コスト量(連結時最良削減コスト)を超えるか否かを判断する。超える場合(Yes)はステップS4−7に進み、超えない場合(No)はステップS4−8に進む。   In step S4-6, it is determined whether this reduction cost amount exceeds the highest reduction cost amount (the best reduction cost at the time of connection) in the current temporary connection process. When exceeding (Yes), it progresses to step S4-7, and when not exceeding (No), it progresses to step S4-8.

ステップS4−7では、ステップS4−5で算出した削減コスト量を連結時最良削減コストに設定又は更新する。また、同時にそのときの仮連結の情報(行程断片の情報等)を保存する。このようにすることで、より高い削減コスト量の情報とその時の仮連結の情報が更新・保持される。   In step S4-7, the reduction cost amount calculated in step S4-5 is set or updated to the best reduction cost at the time of connection. At the same time, temporary connection information (process fragment information, etc.) at that time is stored. By doing so, information on a higher reduction cost amount and information on temporary connection at that time are updated and held.

ステップS4−8では、ステップS4−1で選択した一の行程断片に対して、連結対象に含まれる、その他の行程断片との一連の仮連結が完了したか判断する。完了した場合(Yes)はステップS4−9に進み、未完の場合(No)はステップS4−2に戻る。   In step S4-8, it is determined whether or not a series of provisional connections with other process fragments included in the connection target is completed for the one process fragment selected in step S4-1. If completed (Yes), the process proceeds to step S4-9. If not completed (No), the process returns to step S4-2.

ステップS4−9では、現在の連結時最良削減コストが、ステップS3−7で設定したバイパス連結用削減コストと同値か否かを判断する。同値の場合(Yes)は周期性があると判断してS4−1〜S4−9のループを脱してリターンし、ステップS3−3に進む。異値の場合(No)はステップS4−10に進む。   In step S4-9, it is determined whether or not the current best connection reduction cost is the same as the bypass connection reduction cost set in step S3-7. In the case of the same value (Yes), it is determined that there is periodicity, the loop of S4-1 to S4-9 is exited, and the process returns to Step S3-3. If the value is different (No), the process proceeds to step S4-10.

バイパス連結用削減コストは、上述したように連続日分(ここでは連続3日分)の現行回より前に行った本連結時のコスト削減量である。   The reduction cost for bypass connection is a cost reduction amount at the time of the main connection performed before the current round of continuous days (here, for three consecutive days) as described above.

例えば、図12に示すように1〜3日目の行程断片について仮連結処理する場合、1日目の行程断片n1と行程断片n2とが最良の仮連結がなされて、この値がバイパス連結用削減コストに設定されたと仮定した場合、その後に2日目の行程断片n1を基礎断片として固定して他の行程断片と仮連結をしていくとき、2日目の行程断片n2との仮連結の削減コスト量がバイパス連結用削減コストと同値となる。このように、もともと交番で実施されていたような行程断片の周期性を利用して仮連結処理の一部を省略するものである。   For example, as shown in FIG. 12, when temporary connection processing is performed for the first to third-day process fragments, the first-day process fragment n1 and the process fragment n2 are optimally connected, and this value is used for bypass connection. If it is assumed that the reduction cost is set, then when the second day's process fragment n1 is fixed as a basic fragment and temporarily connected with another process fragment, the temporary connection with the second day's process fragment n2 The reduction cost amount is equivalent to the reduction cost for bypass connection. In this way, a part of the provisional connection process is omitted by using the periodicity of the process fragment as originally performed in the police box.

ステップS4−10では、連続日分(ここでは連続3日分)の行程断片それぞれについて仮連結を行ったか否かを判断する。行った場合(Yes)は、最良の仮連結の情報とその削減コスト量をリターンしてステップS3−3に進み、行っていない場合(No)は、ステップS4−1に戻る。   In step S4-10, it is determined whether or not provisional concatenation has been performed for each of the process fragments for consecutive days (here, for three consecutive days). If yes (Yes), return the information of the best temporary connection and the reduction cost amount, and go to Step S3-3. If not (No), return to Step S4-1.

以下、ステップS1−5における仕業改善処理(図3参照)について、図7〜図9を参照しながら説明する。   Hereinafter, the work improvement process (see FIG. 3) in step S1-5 will be described with reference to FIGS.

ここで、「仕業改善処理」とは、既に生成された仕業に含まれる行程断片を他の仕業に含まれる行程断片と交換することにより、より良い条件の(ここでは、よりコスト削減された)仕業を生成する処理をいう。   Here, the “work improvement process” means that the process fragment included in the already generated work is replaced with the process fragment included in the other work, and the better condition (here, the cost is reduced). A process that generates work.

まず、ステップS5−1では、ステップS1−4で生成した各仕業を日別に分ける処理をする。   First, in step S5-1, processing for dividing each work generated in step S1-4 by day is performed.

そして、ステップS5−2では、各仕業に含まれる行程断片について部分交換処理を行う。この部分交換処理は基本的に既に説明した部分連結処理(図5参照)と似た処理の流れとなる(図8参照)。   In step S5-2, partial replacement processing is performed for the process fragments included in each work. This partial replacement processing basically has a flow of processing similar to the partial connection processing (see FIG. 5) already described (see FIG. 8).

ステップS5−3では、ステップS5−2の行程断片の部分交換処理で本交換があったか否かを判断し、本交換があった場合(Yes)はステップS5−4へ進む。逆に本交換がなかった場合(No)は、ステップS5−7へ進む。   In step S5-3, it is determined whether or not there has been a real exchange in the process fragment partial exchange process in step S5-2. If there has been a real exchange (Yes), the process proceeds to step S5-4. On the other hand, if there is no real exchange (No), the process proceeds to step S5-7.

ステップS5−4では、本交換情報を「有」に設定する。この「本交換情報」は、既に説明した「本連結情報」と似た情報であり、計画作成対象期間について部分交換処理を行なった後に、少なくとも1回本交換された場合には「有」に設定される。   In step S5-4, the exchange information is set to “present”. This “main exchange information” is information similar to the “main connection information” already described. If the main exchange is performed at least once after the partial exchange process is performed for the period for which the plan is created, “present” is set. Is set.

ステップS5−5では、本交換前の行程断片を日別リストから削除し、ステップS5−6にて本交換後の行程断片を日別リストに追加する。   In step S5-5, the process fragment before the main exchange is deleted from the daily list, and in step S5-6, the process fragment after the main exchange is added to the daily list.

ステップS5−7では、改善対象の計画期間について処理が完了したか否かを判断する。例えば仕業の改善対象が30日分であれば、その30日分について部分交換処理を主とする一連の処理が完了したか否かを判断して、完了した場合(Yes)はステップS5−10に進む。   In step S5-7, it is determined whether or not the process is completed for the plan period to be improved. For example, if the work improvement target is for 30 days, it is determined whether or not a series of processing mainly for partial replacement processing has been completed for 30 days, and if completed (Yes), step S5-10. Proceed to

未完の場合(No)はステップS5−8にて、本交換情報を「無」に設定するとともに、ステップS5−9にて部分交換対象を1日分ずらす探索範囲の変更処理を行なってステップS5−2に戻る。   If it is not completed (No), in step S5-8, the exchange information is set to "None", and in step S5-9, the search range is changed by shifting the partial exchange target by one day, and step S5 is executed. Return to -2.

一方、ステップS5−10にて本交換情報が「有」と判断された場合(Yes)は、条件を満たす、さらなる仕業の改善の余地があるものと判断して、上記同様にステップS5−8、S5−9を介してステップS5−2に戻る。逆に、本交換情報が「有」でないと判断された場合には、これ以上、条件を満たす仕業の改善の余地がないと判断してリターンし、ステップS1−7に進む(図3参照)。   On the other hand, if it is determined that the exchange information is “Yes” in step S5-10 (Yes), it is determined that there is room for further work improvement that satisfies the condition, and step S5-8 is performed as described above. , Return to step S5-2 via S5-9. On the other hand, if it is determined that the exchange information is not “present”, it is determined that there is no room for improvement of the work that satisfies the conditions, and the process returns to step S1-7 (see FIG. 3). .

以下、ステップS5−2の行程断片の部分交換処理について、図8を参照しながら説明する。   Hereinafter, the process fragment partial replacement process in step S5-2 will be described with reference to FIG.

ステップS6−1では、各仕業を開始時刻でソートする。   In step S6-1, each work is sorted by start time.

ステップS6−2では、ソートした各仕業に含まれる行程断片について仮交換処理を行い、最良の行程断片の仮交換についての情報と、その際の削減コスト量の情報を得る。   In step S6-2, provisional exchange processing is performed on the process fragments included in each sorted work, and information on the provisional exchange of the best process fragments and information on the reduction cost amount at that time are obtained.

ステップS6−3では、最良の仮交換の削減コスト量が正の値か判断する。削減コスト量が正の値であってコスト削減される場合(Yes)は、ステップS6−4へ進む。逆にコスト増で負の値となる場合(No)は、リターンしてステップS5−3へ進む。   In step S6-3, it is determined whether the best temporary replacement reduction cost amount is a positive value. When the reduction cost amount is a positive value and the cost is reduced (Yes), the process proceeds to step S6-4. Conversely, if the cost increases and becomes a negative value (No), the process returns and proceeds to step S5-3.

なお、ステップS6−3で示す「削減コスト」は、図9に示す仮交換処理からリターンした時点の「交換時最良削減コスト」と同値である。   The “reduction cost” shown in step S6-3 is equivalent to the “best reduction cost at the time of replacement” at the time of returning from the provisional replacement process shown in FIG.

ステップS6−4では、削減コスト量の交換打切用削減コストが設定されているか否かを判断し、設定されていない場合(No)はステップS6−6に進み、設定されている場合(Yes)はステップS6−5に進む。   In step S6-4, it is determined whether or not a reduction cost for replacement termination is set. If not set (No), the process proceeds to step S6-6, and if set (Yes). Advances to step S6-5.

なお、この交換打切用削減コストは、ステップS6−6で算定される値である。   Note that the replacement cutoff reduction cost is a value calculated in step S6-6.

最初の段階では、どの程度コスト削減できるか不明であるため、一回目の仮交換処理を行い、そこで得られた最良の仮交換の削減コスト量を用いて交換打切用削減コストを定める。   Since it is unclear how much the cost can be reduced at the first stage, the first temporary replacement process is performed, and the reduction cost for replacement abortion is determined by using the best temporary replacement reduction cost amount obtained there.

ステップS6−6では、削減コスト量の交換打切用削減コストの算定を行う。例えば、最良の仮交換の削減コスト量に0.95を乗じて得た値を交換打切用削減コストとして定める。この交換打切用削減コストの設定を低く設定すると、削減コスト量が少ない行程断片同士が本交換されやすくなるために調節する必要がある。   In step S6-6, the reduction cost for replacement termination of the reduction cost amount is calculated. For example, a value obtained by multiplying the best temporary replacement reduction cost amount by 0.95 is determined as the replacement cutoff reduction cost. If the reduction cost for replacement abortion is set low, it is necessary to adjust the process fragments so that the process fragments having a small reduction cost amount are easily exchanged.

一方、ステップS6−5では、2回目以降の仮交換処理で得られた最良の仮交換の削減コスト量が、ステップS6−6で設定した削減コスト量の交換打切用削減コストより高いか否かを判断する。交換打切用削減コストより高い場合(No)は、隣接する他の探索範囲にある行程断片との交換と比べて十分にコスト削減される最良の仮交換と判断して、ステップS6−7に進む。   On the other hand, in step S6-5, whether the reduction cost amount of the best temporary replacement obtained in the second and subsequent temporary replacement processing is higher than the reduction cost for replacement termination set in the reduction cost amount set in step S6-6. Judging. If it is higher than the reduction cost for replacement termination (No), it is determined as the best temporary replacement that is sufficiently cost-reduced compared to the replacement with the process fragment in another adjacent search range, and the process proceeds to step S6-7. .

逆に、削減コスト量の交換打切用削減コストより低い場合(Yes)は、十分なコスト削減がなされない最良の仮交換と判断し、リターンしてステップS5−3に進む。   On the contrary, if the reduction cost amount is lower than the reduction cost for replacement termination (Yes), it is determined that the temporary replacement is not the best temporary replacement that is not sufficiently cost-reduced, and the process returns to step S5-3.

ステップS6−7では、初回の仮交換処理で出現した削減コスト量を後述するステップS7−9で使用されるバイパス交換用削減コストとして設定する。このバイパス交換用削減コストについては、ステップS7−9にて後述する。   In step S6-7, the reduction cost amount that appears in the initial temporary replacement process is set as a reduction cost for bypass replacement used in step S7-9, which will be described later. This reduction cost for bypass replacement will be described later in step S7-9.

ステップS6−8では、ステップS6−2で返された最良の仮交換となる2つの行程断片を本交換して新たな仕業をそれぞれ生成する。   In step S6-8, the two stroke fragments that are the best temporary exchanges returned in step S6-2 are fully exchanged to generate new works.

以下、ステップS6−2の仮交換処理について図9を参照しながら説明する。   Hereinafter, the temporary replacement process in step S6-2 will be described with reference to FIG.

ステップS7−1では、仕業の一を基礎仕業として選択する。この基礎仕業の選択は、ステップS7−1に来るごとにステップS6−1において開始時刻でソートされている仕業のプール(図示省略)を一つずつ移動する(また、最後に到達した場合は最初に戻る)。これにより時刻順に仮交換処理が行われ、周期性を利用した探索を行うことができる。   In step S7-1, one of the works is selected as the basic work. The selection of the basic work is performed by moving the work pool (not shown) sorted by the start time in step S6-1 one by one each time it comes to step S7-1 (and the first when it reaches the end) Back to). Thereby, the provisional exchange process is performed in order of time, and a search using periodicity can be performed.

ステップS7−2では、仕業プールの中から他の一の仕業を選択する。   In step S7-2, another work is selected from the work pool.

ステップS7−3では、ステップS7−1で選択した一の仕業とステップS7−2の他の一の仕業との開始時刻差が24時間以内か否か判断する。24時間を超えている場合については、ステップS4−3と同様である。   In step S7-3, it is determined whether or not the start time difference between the one operation selected in step S7-1 and the other operation in step S7-2 is within 24 hours. The case where it exceeds 24 hours is the same as step S4-3.

ステップS7−4では、一の仕業と他の一の仕業の交換可能な行程断片の仮交換を行い、次いでステップS7−5にて仮交換の削減コスト量を所定の評価関数により算出する。ただし、交換可能かどうかは労働規定チェック手段30でチェックする。   In step S7-4, temporary exchange of exchangeable process fragments between one work and another work is performed, and then in step S7-5, a reduction cost amount of the temporary exchange is calculated by a predetermined evaluation function. However, the labor regulation checking means 30 checks whether the exchange is possible.

ステップS7−6では、削減コスト量が現行の仮交換処理において最も高い削減コスト量(交換時最良削減コスト)を超えるか否かを判断する。超える場合(Yes)はステップS7−7に進み、超えない場合(No)はステップS7−8に進む。   In step S7-6, it is determined whether or not the reduction cost amount exceeds the highest reduction cost amount (the best reduction cost at the time of replacement) in the current temporary replacement process. When exceeding (Yes), it progresses to step S7-7, and when not exceeding (No), it progresses to step S7-8.

ステップS7−7では、ステップS7−5で算出した削減コスト量を交換時最良削減コストに設定又は更新する。また、同時にそのときの仮交換の情報(行程断片の情報等)を保存する。このようにすることで、より高い削減コスト量の情報とその時の仮交換の情報が更新・保持される。   In step S7-7, the reduction cost amount calculated in step S7-5 is set or updated to the best reduction cost at the time of replacement. At the same time, provisional exchange information (process fragment information, etc.) at that time is stored. By doing so, information of a higher reduction cost amount and information of provisional exchange at that time are updated and held.

ステップS7−8では、ステップS7−1で選択した一の仕業に対して、探索範囲に含まれる、その他の仕業との仮交換が完了したか判断する。完了した場合(Yes)はステップS7−9に進み、未完の場合(No)はステップS7−2に戻る。   In step S7-8, it is determined whether the provisional exchange with the other work included in the search range is completed for the one work selected in step S7-1. If completed (Yes), the process proceeds to step S7-9. If not completed (No), the process returns to step S7-2.

ステップS7−9では、現在の交換時最良削減コストが、ステップS6−7で設定したバイパス交換用削減コストと同値か否かを判断する。同値の場合(Yes)は周期性があると判断してステップS7−1〜S7−9のループを脱してリターンし、ステップS6−3に進む。異値の場合(No)はステップS7−10に進む。   In step S7-9, it is determined whether or not the current best replacement reduction cost is equivalent to the reduction cost for bypass replacement set in step S6-7. If the values are the same (Yes), it is determined that there is periodicity, the process returns from step S7-1 to S7-9, and the process proceeds to step S6-3. If the value is different (No), the process proceeds to step S7-10.

バイパス交換用削減コストは、上述したように連続日分(ここでは連続3日分)の現行回より前に行った本交換時のコスト削減量である。   The reduction cost for bypass replacement is the amount of cost reduction at the time of the main replacement performed before the current round of continuous days (here, for three consecutive days) as described above.

ステップS7−10では、連続日分(ここでは連続3日分)の仕業それぞれについて仮交換を行ったか否かを判断する。行った場合(Yes)は、最良の仮交換の情報とその削減コスト量をリターンしてステップS6−3に進み、行っていない場合(No)は、ステップS7−1に戻る。   In step S7-10, it is determined whether or not provisional exchange has been performed for each of the operations for consecutive days (here, for three consecutive days). If yes (Yes), return the information of the best temporary exchange and its reduction cost amount and proceed to Step S6-3. If not (No), return to Step S7-1.

以下、本発明に係る乗務員運用計画作成システムの効果を説明する。   Hereinafter, the effect of the crew member operation plan creation system according to the present invention will be described.

本発明に係る乗務員運用計画作成システムによれば、組み合わせ最適化問題として通常得ることが難しい又は得られない行程断片の連結解を、少なくとも以下の構成(1)とすることにより得ることができる。このため、日々異なる需要に対応して日ごとに異なる乗務員運用計画を作成することができる(図14参照)。   According to the crew member operation plan creation system according to the present invention, it is possible to obtain a connected solution of stroke fragments that is usually difficult to obtain or cannot be obtained as a combination optimization problem by at least the following configuration (1). For this reason, it is possible to create different crew operation plans for each day corresponding to different demands (see FIG. 14).

その結果、日々の需要の変動を考慮した日別の乗務員運用計画を作成することができる。また、従来手法の交番割の乗務員運用計画で発生していた計画の見直しにかかる手間が大幅に削減されることで、計画作成業務の効率化も図ることができる。   As a result, it is possible to create a daily crew member operation plan that takes into account daily demand fluctuations. In addition, it is possible to improve the efficiency of the plan creation work by drastically reducing the trouble of reviewing the plan that has occurred in the crew operation plan of the alternating method of the conventional method.

(1)最も有利な連結から順に行程断片を連結していくため、連結処理が迅速となる。
行程断片同士を仮連結していき、それぞれの仮連結について有利な連結となるかどうかその都度評価する。そして、それらの仮連結の中で最も削減コスト量が多い有利な仮連結を最良の仮連結として本連結を行う。この本連結した行程断片を含めて同じ処理を繰り返すことにより最も削減コスト量が多いものから順に行程断片の連結が行われ、削減コスト量が低い行程断片同士を手当たり次第に連結するよりも、連結処理が適正且つ迅速となる。
(1) Since the process fragments are connected in order from the most advantageous connection, the connection process is quick.
The process fragments are temporarily connected to each other, and it is evaluated each time whether or not each temporary connection is advantageous. Then, the main connection is performed with the advantageous temporary connection having the largest reduction cost among the temporary connections as the best temporary connection. By repeating the same process including the main linked process fragments, the process fragments are connected in order from the largest reduction cost amount, and the connection processing is performed rather than connecting the process fragments with the lowest reduction cost amount by hand. Is appropriate and quick.

さらに、以下の構成(2)〜(6)とすることで、上記連結解をさらに早く確実に得ることができるようになる。   Furthermore, by using the following configurations (2) to (6), the above connected solution can be obtained more quickly and reliably.

(2)仮連結処理の対象日の範囲を限定(ここでは連続3日分に限定)するので、一の行程断片と連結される可能性が高い、時系列に近接した行程断片との間で仮連結処理がなされ、連結処理が迅速となる。   (2) Since the range of the target date of the provisional connection process is limited (here, limited to three consecutive days), there is a high possibility of being connected to one stroke fragment, between the stroke fragments close to the time series Temporary connection processing is performed, and the connection processing becomes quick.

さらに、削除コスト量の連結打切用削減コスト(ステップS3−6参照)の存在により、対象日範囲内の最良の仮連結であっても連結打切用削減コストを超えなければ本連結されないので、当該最良の仮連結を構成する行程断片と、隣接する対象範囲外の行程断片であって前記連結打切用削減コストを超えるものとの仮連結や本連結の可能性が奪われず、より適正な連結がなされる。   Furthermore, due to the existence of a reduction cost for connection termination of the deletion cost amount (see step S3-6), even if the best provisional connection within the target date range is not exceeded unless the reduction cost for connection termination is exceeded, The connection between the process fragment that constitutes the best temporary connection and the process fragment that is outside the adjacent target range and exceeds the reduction cost for the connection termination is not deprived of the possibility of temporary connection or main connection, and more appropriate connection is possible. Made.

具体的な例として、図12A(a)の1〜3日目に含まれる各行程断片についての仮連結処理を考える。まず、連結処理がある程度進み、1日目と2日目のn1とn2がそれぞれ連結された行程断片、3日目のq1とq2が連結された行程断片となっているとする。また、2日目にx1、4日目にy1という行程断片があり、それぞれ3日目の行程断片(q1とq2が連結されたもの)に連結可能であると仮定する。   As a specific example, consider provisional connection processing for each process fragment included in the first to third days of FIG. 12A (a). First, it is assumed that the linking process has progressed to some extent, and it is a stroke fragment in which n1 and n2 on the first day and the second day are connected, respectively, and a stroke fragment in which q1 and q2 on the third day are connected. Further, it is assumed that there is a stroke fragment of x1 on the second day and y1 on the fourth day, and that each can be linked to a stroke fragment (concatenated q1 and q2) of the third day.

連結打切用削減コストを考慮しない場合、探索範囲1(1〜3日目)では2日目の行程断片x1と3日目の行程断片(q1とq2が連結されたもの)は連結可能であり、わずかでもコスト削減が可能であれば連結が行われる(図12A(b)参照)。   If the reduction cost for connection termination is not taken into account, in the search range 1 (1st to 3rd days), the process fragment x1 on the second day and the process fragment (combined q1 and q2) on the third day can be connected. If the cost can be reduced even slightly, the connection is performed (see FIG. 12A (b)).

この後、連結の範囲が探索範囲2に移動しても4日目の行程断片y1は3日目の行程断片(x1、q1、q2が連結されたもの)と連結されることはない。これは行程断片の開始時刻が24時間以上離れている、あるいは労働規程違反(仕業は24時間以下の長さでなければならない)という理由による。   Thereafter, even if the range of connection moves to the search range 2, the process fragment y1 on the fourth day is not connected to the process fragment on the third day (what is connected to x1, q1, and q2). This is due to the fact that the start time of the process fragment is more than 24 hours away or the labor regulations are violated (the work must be 24 hours or less in length).

連結打切用削減コストを導入すると、探索範囲1(1〜3日目)では2日目の行程断片x1と3日目の行程断片(q1とq2が連結されたもの)は連結可能であるもののコスト削減はわずかである。連結打切用削減コストよりコスト削減が少なければ、この連結は行われずに連結の範囲が探索範囲2に移動する。この結果、よりコスト削減が可能である連結が行われ、3日目のq1とq2、4日目のy1が連結された行程断片を作成することができる(図12(c)参照)。   When the reduction cost for connection termination is introduced, in the search range 1 (1st to 3rd days), it is possible to connect the process fragment x1 of the second day and the process fragment of the third day (concatenated q1 and q2). Cost savings are negligible. If the cost reduction is less than the connection cutoff reduction cost, this connection is not performed and the connection range moves to the search range 2. As a result, concatenation capable of further cost reduction is performed, and it is possible to create a process fragment in which q1 and q2 on the third day and y1 on the fourth day are concatenated (see FIG. 12C).

(3)仮連結する際に、一の行程断片と、この行程断片と開始時刻差が24時間以下の他の行程断片とを抽出して仮連結対象とするため、連結処理が迅速となる。   (3) At the time of provisional connection, one process fragment and another process fragment with a start time difference of 24 hours or less are extracted and used as a provisional connection target, so that the connection process is accelerated.

もともと労働規定等の制約で開始時刻差が24時間を越える行程断片同士の連結はできない場合に、あらかじめ条件から外れるものを連結対象からはずすことで処理が迅速となる。   When it is not possible to connect process fragments whose start time difference exceeds 24 hours due to restrictions on labor regulations or the like, the processing can be speeded up by removing those that do not meet the conditions from the connection target.

(4)上記の連結打切用削減コストを超え且つ最良の仮連結時の評価値と同値となる行程断片が再び現れたとき、既に行われた最良の仮連結と同条件の行程断片として捉えて、残りの行程断片との一対一の仮連結をバイパスするため処理が迅速となる。   (4) When a process fragment that exceeds the above-mentioned reduction cost for connection termination and becomes the same value as the evaluation value at the time of the best temporary connection appears again, it is regarded as a process fragment of the same condition as the best temporary connection that has already been made. Since the one-to-one temporary connection with the remaining stroke fragments is bypassed, the processing becomes quick.

具体的な例としては、図12に示すように1〜3日目の各行程断片について仮連結処理をしていくとき、1日目の行程断片n1,n2同士の仮連結が最もコスト削減されたとした場合、この削減コスト量がステップS3−7でバイパス連結用削減コストとして保存される。   As a specific example, as shown in FIG. 12, when temporary connection processing is performed for each process fragment on the first to third days, the temporary connection between the process fragments n1 and n2 on the first day is the most cost-reduced. If this is the case, this reduction cost amount is stored as a reduction cost for bypass connection in step S3-7.

その後の仮連結処理にて、2日目の行程断片n1について仮連結処理をする際に、2日目の行程断片n1,n2の仮連結の削減コスト量がバイパス連結用削減コストと同値となるため、この2日目の行程断片n1,n2が1日目の行程断片n1,n2と同条件の行程断片と判断されて、それ以降の仮連結はスキップされ、連結処理が迅速となる。   In the subsequent temporary connection process, when the temporary connection process is performed for the process fragment n1 on the second day, the reduction cost amount of the temporary connection of the process fragments n1 and n2 on the second day is equal to the reduction cost for bypass connection. Therefore, it is determined that the process fragments n1 and n2 on the second day are the process fragments having the same conditions as the process fragments n1 and n2 on the first day, and the subsequent temporary connection is skipped, so that the connection process becomes quick.

次に、本発明に係る別の乗務員運用計画作成システムについて説明する。   Next, another crew member operation plan creation system according to the present invention will be described.

日々の需要の変化は、全ての列車運行で一律に発生するわけではなく、列車運行ごとに異なる。それらの列車運行に対して、日別に乗務員運用計画を作成することによって、効率よく運転率と乗務割合とを結びづけることが可能となる。   Changes in daily demand do not occur uniformly for all train operations, but differ for each train operation. By creating a crew operation plan for each train operation on a daily basis, it becomes possible to efficiently link the operation rate and the crew ratio.

このようにすることで、交番割で対応可能な乗務員運用計画部分について日別に作成するよりも、より迅速な処理が可能となる。   By doing in this way, a quicker process is possible rather than producing every day about the crew operation plan part which can respond by police box percent.

図15に実施例の乗務員運用計画作成システム10の構成を示し、図16にグループ分けした結果の表を示す。   FIG. 15 shows the configuration of the crew member operation plan creation system 10 of the embodiment, and FIG. 16 shows a table of the results of grouping.

乗務員運用計画作成システム10は、図15に示すように、読込手段3Aを有している。この読込手段3Aは、既に説明した乗務員運用計画作成システム1の処理部3に加えて、各乗務員の乗務割合を算出する乗務割合算出手段31と、各列車運行の運転率を算出する運転率算出手段32と、運転率により列車運行をグループ化する列車グループ化手段33と、乗務員を前記乗務割合により列車グループと同数のグループに分ける乗務員グループ化手段34と、列車グループと乗務員グループとを紐付けするグループ紐付手段35とを有しているものである。   The crew member operation plan creation system 10 includes a reading unit 3A as shown in FIG. In addition to the processing unit 3 of the crew member operation plan creation system 1 described above, the reading unit 3A includes a crew ratio calculation unit 31 that calculates the crew ratio of each crew member, and a driving rate calculation that calculates the driving rate of each train operation. The means 32, the train grouping means 33 for grouping train operations according to the driving rate, the crew grouping means 34 for dividing the crew members into the same number of groups as the train groups by the crew ratio, and the train group and the crew group are linked. Group linking means 35 to be used.

<乗務割合算出手段>
乗務割合算出手段31は、基準乗務時間に対する各乗務員の乗務時間の割合を算出する手段である。例えば、乗務割合=各乗務員が1箇月間に乗務する時間/正社員Aの乗務員が1箇月間に乗務する時間×100(%)とすることができる。
<Crew ratio calculation means>
The crew ratio calculation means 31 is a means for calculating the ratio of each crew member's crew time to the standard crew time. For example, crew ratio = time spent by each crew member during one month / time spent by a crew member of regular employee A during one month × 100 (%).

<運転率算出手段>
運転率算出手段32は、毎日運行する列車の運転率を100%とした場合の各列車の運転率を計算するものである。
<列車グループ化手段>
列車グループ化手段33は、運転率算出手段32により算出された各列車の運転率を指標にして、各列車を所定の運転率範囲の列車グループにそれぞれ仕分けする手段である。
<Driving rate calculation means>
The operation rate calculation means 32 calculates the operation rate of each train when the operation rate of the train that operates every day is 100%.
<Train grouping means>
The train grouping unit 33 is a unit that sorts each train into train groups in a predetermined operation rate range using the operation rate of each train calculated by the operation rate calculation unit 32 as an index.

<乗務員グループ化手段>
乗務員グループ化手段34は、乗務割合算出手段31により算出された各乗務員の乗務割合を指標にして、各乗務員を所定の乗務割合の範囲の乗務員グループにそれぞれ仕分けする手段である。
<Crew grouping means>
The crew grouping means 34 is a means for sorting each crew member into a crew group within a predetermined crew ratio range, using the crew ratio calculated by the crew ratio calculation means 31 as an index.

<グループ紐付手段>
グループ紐付手段35は、列車の運転率により列車グループを運転率の順にソートするとともに、乗務員の乗務割合により乗務員グループを乗務割合の順にソートして、列車グループと乗務員グループとを当該ソート順で対応するように関連付ける手段である。
<Group linking means>
The group linking means 35 sorts the train groups in the order of the driving rate according to the driving rate of the train, sorts the crew group in the order of the riding rate according to the crew rate of the crew, and corresponds the train group and the crew group in the sorting order. It is a means of associating.

以下、実施例の乗務員運用計画作成システム10について詳述する。   Hereinafter, the crew member operation plan creation system 10 according to the embodiment will be described in detail.

まず、運転率算出手段32により、各列車運行R1,R2,U1,U2,T1,T2に対して、毎日運転された場合を100%とした場合の各列車運行の運転率を計算する(図16(a)参照)。   First, the operation rate calculation means 32 calculates the operation rate of each train operation when the daily operation is 100% for each train operation R1, R2, U1, U2, T1, T2 (see FIG. 16 (a)).

そして、列車グループ化手段33により、列車運行の運転率に応じて列車をグループ分けする(図16(a)参照)。   Then, the trains are grouped by the train grouping means 33 according to the operation rate of the train operation (see FIG. 16A).

一方、乗務員についても、乗務割合算出手段31により各乗務員の乗務割合を算出し、乗務員グループ化手段34により、乗務割合に応じたグループ分けを実施する(図16(b)のグループI〜III参照)。   On the other hand, with respect to crew members, the crew ratio of each crew member is calculated by the crew ratio calculation means 31, and the grouping according to the crew ratio is performed by the crew grouping means 34 (see groups I to III in FIG. 16B). ).

そして、既に実施の形態で説明した各手段によって、運転率が所定未満の列車のグループB,Cについて、日別の乗務員運用計画を作成し、グループ紐付手段35により、乗務割合が所定未満の乗務員グループII,IIIをそれぞれ同順でグループB,Cに紐付ける。   Then, by each means already described in the embodiment, a daily crew member operation plan is created for the groups B and C of the train whose driving rate is less than a predetermined value, and a crew member whose crew ratio is less than a predetermined value is determined by the group linking means 35. Group II and III are linked to groups B and C in the same order.

一方、運転率が所定以上の列車のグループAについては、従来の循環する交番割を適用して部分的な乗務員運用計画を作成し、勤務における乗務の割合が所定以上のグループIの乗務員をグループAに紐付ける。   On the other hand, for group A of trains with an operation rate of more than a predetermined value, a partial crew operation plan is created by applying the conventional circulating police box, and the crew members of group I with a duty ratio of greater than or equal to a predetermined value are grouped. Tie to A.

このようにすることで、需要が変化しやすく交番割では対応不可能な列車についてのみ日別に計画が作成され、人員配置の効率化も図ることができ、計画作成処理もより迅速化する。   By doing in this way, a plan is created every day only for trains that are likely to change in demand and cannot be handled by police box allocation, the efficiency of staffing can be improved, and the plan creation process is further accelerated.

以下、乗務員運用計画作成システム10の処理の流れについて、図17〜図19のフローチャートを参照しながら説明する。   Hereinafter, the processing flow of the crew member operation plan creation system 10 will be described with reference to the flowcharts of FIGS. 17 to 19.

ステップS8−1では、読込手段21により列車運行データ2cと乗務員データ2dを読み込む。この列車運行データ2cには、運用計画を作成する対象期間の休止情報が反映された日別の列車運行ダイヤが含まれている。また、乗務員データ2dには乗務員の氏名や乗務時間等の情報(図16(b)参照)が含まれている。   In step S8-1, the train operation data 2c and the crew data 2d are read by the reading means 21. The train operation data 2c includes a daily train operation diagram in which the suspension information of the target period for creating the operation plan is reflected. The crew data 2d includes information such as the crew name and crew hours (see FIG. 16B).

ステップS8−2では、当初運行予定の各列車の運転率を計算し、この運転率に基づいて各列車を2以上の列車グループに分ける。運転率の計算とグループ化については、後述のステップS9系で説明する。   In step S8-2, the operation rate of each train scheduled to be initially operated is calculated, and each train is divided into two or more train groups based on this operation rate. The calculation and grouping of the operation rate will be described in the later-described step S9 system.

ステップS8−3では、乗務員データに記録されている乗務員の乗務時間から、各乗務員の乗務割合を計算し、この乗務割合に基づいて列車グループと同数の2以上の乗務員グループに分ける。乗務割合の計算とグループ化については、後述のステップS10系で説明する。   In step S8-3, the crew ratio of each crew member is calculated from the crew hours recorded in the crew data, and is divided into two or more crew groups equal to the number of train groups based on this crew ratio. The calculation and grouping of the crew ratio will be described in the later-described step S10 system.

ステップS8−4では、列車グループと乗務員グループとをそれぞれ紐付けする。この紐付けでは、列車グループを運転率で降順にソートするとともに乗務員グループを乗務割合で降順にソートし、降順に対応するように列車グループと乗務員グループが紐付けられる。   In step S8-4, the train group and the crew group are associated with each other. In this linking, the train groups are sorted in descending order by the operation rate, the crew groups are sorted in descending order by the crew ratio, and the train groups and crew groups are linked to correspond to the descending order.

ステップS8−5では、運転率が所定未満の列車グループについて、実施の形態で説明したように日別の乗務員運用計画を作成する。   In step S8-5, as described in the embodiment, a daily crew member operation plan is created for a train group having an operation rate of less than a predetermined value.

この例では、運転率が90%以下の列車グループB,Cについて日別の乗務員運用計画を作成している(図16(a)参照)。   In this example, a daily crew member operation plan is created for train groups B and C with an operation rate of 90% or less (see FIG. 16A).

ステップS8−6では、運転率が所定以上の列車グループについて、列車運行データ2cに基づいて、従来の通りに循環する交番割を適用して乗務員運用計画を作成する。基本的には、1日分の列車ダイヤから交番割を作成する(図示省略)。   In step S8-6, a crew member operation plan is created for train groups with an operation rate equal to or greater than a predetermined value by applying an alternating rate circulating as usual based on the train operation data 2c. Basically, a police box is created from train schedules for one day (not shown).

ステップS8−7では、ステップS8−5およびS8−6で作成した乗務員運用表を合成出力する(図示省略)。   In step S8-7, the crew member operation table created in steps S8-5 and S8-6 is synthesized and output (not shown).

以下、図18を参照して運転率により列車のグループ分けをする処理を説明する。   Hereinafter, the process of grouping trains according to the operation rate will be described with reference to FIG.

ステップS9−1では、列車運行データ2cから列車別に所定期間(ここでは1年間)の運転日数を導出する。   In step S9-1, the operation days of a predetermined period (here 1 year) are derived for each train from the train operation data 2c.

ステップS9−2では、各列車の運転率を算出する。この運転率は、運転日数/365(閏年は366)×100(%)により算出する。   In step S9-2, the operation rate of each train is calculated. This operation rate is calculated by the number of operation days / 365 (366 for leap years) × 100 (%).

ステップS9−3では、各列車をグループに分けるための運転率の閾値を設定する。この閾値は、ユーザにより設定できるようになっている。また、この閾値の設定により、日別に作成される運用計画の対象列車が決まるので、設定により最終的な乗務員の運用コストが変化する。従って、最終的な乗務員の運用コストとの兼ね合いで閾値を決定することが望ましい。   In step S9-3, an operation rate threshold for dividing each train into groups is set. This threshold value can be set by the user. In addition, since the target train of the operation plan created for each day is determined by the setting of the threshold, the final operation cost of the crew changes depending on the setting. Therefore, it is desirable to determine the threshold value in consideration of the final crew operating cost.

この例では、
グループAの運転率(%)>90
90≧グループBの運転率(%)>50
50≧グループCの運転率(%)> 0
となるように閾値を設定している。
In this example,
Group A operation rate (%)> 90
90 ≧ Group B operation rate (%)> 50
50 ≧ Group C operation rate (%)> 0
The threshold is set so that

ステップS9−4では、導出した運転率と設定した閾値に基づいて各列車をグループに分ける。その後、リターンしてステップS8−3(S10−1)に進む。   In step S9-4, each train is divided into groups based on the derived operation rate and the set threshold value. Then, it returns and progresses to step S8-3 (S10-1).

この例では、図16(a)に示すように、運転率100%の列車運行R1,R2はグループAに分類され、運転率85%の列車運行U1,U2はグループBに分類され、運転率43%の列車運行T1,T2はグループCに分類されている。   In this example, as shown in FIG. 16 (a), train operations R1 and R2 with an operation rate of 100% are classified into group A, train operations U1 and U2 with an operation rate of 85% are classified into group B, and the operation rate 43% of train operations T1 and T2 are classified into Group C.

以下、図19を参照して、乗務割合により乗務員をグループ分けする処理を説明する。   Hereinafter, with reference to FIG. 19, the process of grouping crew members according to the crew ratio will be described.

ステップS10−1では、乗務員データ2dから、基準乗務時間として、乗務割合100%の正社員Aについて、計画作成対象とする1箇月間の勤務時間を算出するとともに、各乗務員の同勤務時間を算出する。   In step S10-1, for the regular employee A with a crew ratio of 100%, the working hours for one month to be planned are calculated from the crew data 2d, and the same working hours for each crew member are calculated. .

ここでの、勤務時間は運転士としての業務を行なっている時間とする。   Here, the working time is the time during which the operation as a driver is performed.

ステップS10−2では、各乗務員についてそれぞれ乗務割合を算出する。   In step S10-2, a crew ratio is calculated for each crew member.

この乗務割合は、各乗務員の1箇月間に乗務する時間/正社員Aの乗務員が1箇月間に乗務する時間×100(%)により算出する。   This crew ratio is calculated by the time spent for each crew member during one month / the time when the crew member of regular employee A is crewed during one month × 100 (%).

ステップS10−3では、乗務員をグループ分けするための乗務割合の閾値を設定する。この閾値により各乗務員がグループ分けされる。この乗務割合の閾値についても削減コスト量を決定する一要素としてユーザにより設定できるようになっている。   In step S10-3, a crew ratio threshold for grouping crew members is set. Each crew member is grouped by this threshold value. The crew ratio threshold can also be set by the user as an element for determining the reduction cost amount.

この例では、
グループIの乗務割合(%)>80、
80≧グループIIの乗務割合(%)>40
40≧グループIIIの乗務割合(%)>0
となるように閾値を設定している。
In this example,
Group I crew ratio (%)> 80,
80 ≥ Group II crew ratio (%)> 40
40 ≧ Group III crew ratio (%)> 0
The threshold is set so that

ステップS10−4では、導出した乗務割合と設定した閾値に基づいて各乗務員を各グループに分ける。その後、リターンしてステップS8−4に進む。   In step S10-4, the crew members are divided into groups based on the derived crew ratio and the set threshold value. Then, it returns and progresses to step S8-4.

この例では、図16(b)に示すように、正社員Aで乗務割合100%の「狭山」と「鈴木」がグループIに分類され、正社員Bで乗務割合71%の「高橋」と「中田」がグループIIに分類され、正社員Cで乗務割合28%の「馬込」と「江藤」がグループIIIに分類される。   In this example, as shown in FIG. 16 (b), “Sayama” and “Suzuki” who are 100% crew members are classified into Group I, while “Takahashi” and “Nakada” who are 71% crew members. ”Is classified as Group II, and“ Mamagome ”and“ Eto ”who are full-time employees C and have a crew ratio of 28% are classified as Group III.

グループIの乗務員である「狭山」又は「鈴木」がグループAの列車運行R1,R2に乗務し、グループIIの乗務員である「高橋」又は「中田」がグループBの列車運行U1,U2に乗務し、グループIIIの乗務員である「馬込」又は「江藤」がグループCの列車運行T1,T2に乗務することとなる。   Group I crew “Sayama” or “Suzuki” is on board Group A train operations R1 and R2, and Group II crew “Takahashi” or “Nakada” is on Group B train services U1 and U2. Then, “Magome” or “Eto” who is a crew member of Group III will be in charge of train operations T1 and T2 of Group C.

以下、本発明に係る実施例の乗務員運用計画作成システム10の効果を説明する。   Hereinafter, the effect of the crew member operation plan creation system 10 according to the embodiment of the present invention will be described.

列車の運転率に応じて日別の運用計画を作成する対象の列車を限定するので、作成対象が減少して、計画作成の処理が迅速となる。   Since the target trains for creating daily operation plans are limited according to the operation rate of the train, the number of creation targets is reduced, and the plan creation process becomes quick.

さらに、運転率が低い列車について日別の運用計画を作成することができることから、乗務割合別に乗務員を割り付けることが可能となり、従来の交番割では非常に達成が困難な勤務体系の乗務員が混在した乗務員運用計画を作成することができる。例えば、育児等の短縮勤務への適用も可能である(図16(b)の正社員B,C参照)。   Furthermore, because it is possible to create a daily operation plan for trains with low operation rates, it is possible to assign crew members by crew ratio, and there are a mix of crew members who are very difficult to achieve with the conventional police box assignment. A crew operation plan can be created. For example, it can be applied to shortened work such as childcare (see full-time employees B and C in FIG. 16B).

以上、本発明に係る乗務員運用計画作成システムについて、実施の形態及び実施例に基づき説明してきたが、具体的な構成については、これらの実施の形態や実施例に限られるものではなく、特許請求の範囲の各請求項に係る発明の要旨を逸脱しない限り、設計の変更や追加等は許容される。   As mentioned above, although the crew member operation plan creation system according to the present invention has been described based on the embodiments and examples, the specific configuration is not limited to these embodiments and examples. Modifications and additions of the design are permitted without departing from the spirit of the invention according to each claim in the scope of the above.

例えば、日別の列車運行ダイヤは、基本の運行ダイヤに加えて休止情報や臨時列車の情報といった差分の情報を用いて列車運行置換手段22によって生成されることとしてもよい。   For example, the daily train operation schedule may be generated by the train operation replacement means 22 using difference information such as stop information and information on temporary trains in addition to the basic operation schedule.

1,10 乗務員運用計画作成システム
2 データベース
21 読込手段
22 列車運行置換手段
23 行程断片ソート手段
24 仮連結手段
25 連結評価手段
26 本連結手段
27 バイパス手段
28 仕業作成手段
29 仕業改善手段
30 労働規定チェック手段
31 運転率算出手段
32 乗務割合算出手段
33 列車グループ化手段
34 乗務員グループ化手段
35 グループ紐付手段
2a,2c 列車運行データ
2b,2d 乗務員データ
3,3A 処理部
4 出力手段
n1,n2,n1,n2,q1,q2 行程断片
N1,N2,M1,M2,Q1,Q2 列車運行
R1,R2,U1,U2,T1,T2 列車運行
1,10 Crew member operation plan creation system 2 Database 21 Reading means 22 Train operation replacement means 23 Process fragment sorting means 24 Temporary connection means 25 Connection evaluation means 26 Main connection means 27 Bypass means 28 Work preparation means 29 Work improvement means 30 Labor regulations check Means 31 Operation rate calculation means 32 Crew ratio calculation means 33 Train grouping means 34 Crew grouping means 35 Group linking means 2a, 2c Train operation data 2b, 2d Crew data 3, 3A Processing section 4 Output means
n1, n2, n1, n2, q1, q2 travel segment N1, N2, M1, M2, Q1, Q2 train operation R1, R2, U1, U2, T1, T2 train operation

Claims (6)

列車運行ダイヤの各列車運行区間を乗務員の仕業単位に割り付けて所定期間の乗務員の運用計画を作成する乗務員運用計画作成システムにおいて、
前記列車運行の休止を反映した列車運行データに基づいて乗務員の日毎の行程断片を生成する列車運行置換手段と、
この行程断片をその開始時刻でソートする行程断片ソート手段と、
ソートされた行程断片を時系列的に重複しない行程断片同士で順々に一対一の仮連結する仮連結処理を行う仮連結手段と、
前記仮連結ごとに所定の評価を行ったときの評価値が、所定の評価基準値を超えるか否かを判断し、超えた場合には所定の評価基準値を当該評価値に置き換える連結評価手段と、
前記仮連結処理後に得られる評価基準値の仮連結を本連結して、より長い行程断片又は仕業を生成する本連結手段と、を備えたことを特徴とする乗務員運用計画作成システム。
In the crew operation plan creation system that assigns each train operation section of the train operation diagram to the crew's work unit and creates the crew's operation plan for a predetermined period,
Train operation replacement means for generating daily journey fragments of crew based on train operation data reflecting the suspension of the train operation,
A process fragment sorting means for sorting the process fragments by their start times;
Temporary connection means for performing temporary connection processing for temporarily connecting one-to-one temporary connection between the process pieces that do not overlap in time series with the sorted process pieces;
Connection evaluation means for determining whether or not an evaluation value when a predetermined evaluation is performed for each temporary connection exceeds a predetermined evaluation reference value, and replacing the predetermined evaluation reference value with the evaluation value if it exceeds When,
A crew member operation plan creation system comprising: a main connection means for generating a longer process fragment or work by main connection of temporary connection of evaluation reference values obtained after the temporary connection processing.
前記仮連結手段は、仮連結する対象の日の範囲を維持しつつ一日ずつずらしながら仮連結処理を行い、
前記連結評価手段は、
既行の仮連結処理の評価基準値に基づいて連結打切基準値を算定し、
現行の仮連結処理後の評価基準値が連結打切基準値を上回っているか否かについて判断し、
前記評価値が前記連結打切基準値より上回っている場合に前記本連結させることを特徴とする請求項1に記載の乗務員運用計画作成システム。
The temporary connection means performs the temporary connection process while shifting the day by day while maintaining the range of the target date to be temporarily connected,
The connection evaluation means includes
Based on the evaluation standard value of the existing temporary consolidation process, the consolidated termination standard value is calculated,
Judge whether the evaluation standard value after the current provisional consolidation process exceeds the standard value for termination of consolidation,
The crew member operation plan creation system according to claim 1, wherein the main connection is made when the evaluation value is higher than the connection cutoff reference value.
前記仮連結手段は、前記ソートされた行程断片を仮連結する際に、任意に選択した一の行程断片と、この行程断片との開始時刻差が24時間以下の他の行程断片とを抽出して、仮連結をすること特徴とする請求項1又は2に記載の乗務員運用計画作成システム。   When temporarily connecting the sorted process fragments, the temporary connection unit extracts one process fragment arbitrarily selected and another process fragment whose start time difference between the process fragments is 24 hours or less. The crew member operation plan creation system according to claim 1, wherein temporary connection is performed. 既出の仮連結の評価値と同じ評価値の仮連結が現れた場合、それ以降の少なくとも一部の仮連結を省略するバイパス手段を備えたことを特徴とする請求項1〜3いずれか1項に記載の乗務員運用計画作成システム。   The bypass means which abbreviate | omits at least one part temporary connection after that when the temporary connection of the same evaluation value as the evaluation value of the temporary connection mentioned above appears was provided. A crew management plan creation system described in 1. 毎日運行した場合の列車の運転率を100%とした場合に各列車運行の運転率を算出する運転率算出手段と、
運転率が基準値以上の列車運行グループと基準値未満の列車グループとに分ける列車グループ化手段とを備え、
運転率が基準値未満の列車グループについて、日別に乗務員運用計画を作成することを特徴とする請求項1〜4いずれか1項に記載の乗務員運用計画作成システム。
An operation rate calculating means for calculating the operation rate of each train operation when the operation rate of the train when operating daily is 100%,
A train grouping means that divides the train operation group with an operation rate equal to or higher than a reference value and a train group with a driving rate lower than the reference value
The crew member operation plan creation system according to any one of claims 1 to 4, wherein a crew member operation plan is created on a daily basis for a train group having an operation rate less than a reference value.
基準乗務時間に対する各乗務員の乗務時間の割合である乗務割合を算出する乗務割合算出手段と、
この乗務割合が基準値以上の乗務員グループと基準値未満の乗務員グループとに分ける乗務員グループ化手段と、
前記基準値以上の乗務割合の乗務員グループを、前記基準値以上の運転率の列車グループに割り付け、
前記基準値未満の乗務割合の乗務員グループを前記基準値未満の運転率の列車グループに割り付けるグループ紐付手段とを備え、前記列車の運転率が基準値以上の列車グループについて交番割を作成することを特徴とする請求項5に記載の乗務員運用計画作成システム。
A crew ratio calculation means for calculating a crew ratio that is a ratio of each crew member's crew time to the standard crew time;
A crew grouping means for dividing the crew ratio into a crew group having a standard value or more and a crew group having a standard value or less;
Assign a crew group with a crew ratio greater than or equal to the reference value to a train group with an operation rate greater than or equal to the reference value,
A group linking means for allocating a crew group having a crew ratio less than the reference value to a train group having an operation rate less than the reference value, and creating an alternating allocation for a train group having an operation rate of the train equal to or greater than the reference value. 6. The crew member operation plan creation system according to claim 5,
JP2011143234A 2011-06-28 2011-06-28 Crew operation plan creation system Expired - Fee Related JP5718742B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011143234A JP5718742B2 (en) 2011-06-28 2011-06-28 Crew operation plan creation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011143234A JP5718742B2 (en) 2011-06-28 2011-06-28 Crew operation plan creation system

Publications (2)

Publication Number Publication Date
JP2013011976A true JP2013011976A (en) 2013-01-17
JP5718742B2 JP5718742B2 (en) 2015-05-13

Family

ID=47685821

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011143234A Expired - Fee Related JP5718742B2 (en) 2011-06-28 2011-06-28 Crew operation plan creation system

Country Status (1)

Country Link
JP (1) JP5718742B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016006014A1 (en) * 2014-07-08 2016-01-14 株式会社 東芝 Crew member path task creating system and crew member path task creating method
JP2018185639A (en) * 2017-04-25 2018-11-22 株式会社構造計画研究所 Scheduling system, scheduling method and program

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05298593A (en) * 1992-04-24 1993-11-12 Mitsubishi Electric Corp Device for supporting crew operation schedule preparation
JP2004224290A (en) * 2003-01-27 2004-08-12 Toshiba Corp Crew scheduling and arrangement plan preparation support device for recovering train schedule and crew scheduling and arrangement plan preparation support program for recovering train schedule
JP2010285053A (en) * 2009-06-11 2010-12-24 Hitachi Ltd Device and method for re-preparing operation plan

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05298593A (en) * 1992-04-24 1993-11-12 Mitsubishi Electric Corp Device for supporting crew operation schedule preparation
JP2004224290A (en) * 2003-01-27 2004-08-12 Toshiba Corp Crew scheduling and arrangement plan preparation support device for recovering train schedule and crew scheduling and arrangement plan preparation support program for recovering train schedule
JP2010285053A (en) * 2009-06-11 2010-12-24 Hitachi Ltd Device and method for re-preparing operation plan

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JPN6015005623; 野末 尚次: '鉄道における計画支援システムの現状と課題' 電気学会論文誌C Vol.115 No.5, 1995, pp.628-633 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016006014A1 (en) * 2014-07-08 2016-01-14 株式会社 東芝 Crew member path task creating system and crew member path task creating method
KR20160148666A (en) 2014-07-08 2016-12-26 가부시끼가이샤 도시바 Crew member path task creating system and crew member path task creating method
JPWO2016006014A1 (en) * 2014-07-08 2017-04-27 株式会社東芝 Crew route course creation system and crew route course creation method
KR101871622B1 (en) 2014-07-08 2018-06-26 가부시끼가이샤 도시바 Crew member path task creating system and crew member path task creating method
JP2018185639A (en) * 2017-04-25 2018-11-22 株式会社構造計画研究所 Scheduling system, scheduling method and program

Also Published As

Publication number Publication date
JP5718742B2 (en) 2015-05-13

Similar Documents

Publication Publication Date Title
Hyer Education: MRP/GT: a framework for production planning and control of cellular manufacturing
US8082071B2 (en) System and method of multi-generation positive train control system
CN106991495B (en) Method and system for uniformly compiling freight train marshalling plan on railways across China
Keller et al. Energy supply orientation in production planning systems
JP5718742B2 (en) Crew operation plan creation system
JP2018185639A (en) Scheduling system, scheduling method and program
Voß et al. Computer-aided scheduling of public transport
KR101871622B1 (en) Crew member path task creating system and crew member path task creating method
CN115907332A (en) Two-layer optimization method and device for oil-gas well maintenance task scheduling
Kisielewski The system of IT support for logistics in the rail transport
Kim et al. The influence of an autonomous driving car operation on commuters’ departure times
Clausen et al. Combining simulation and optimization to improve LTL traffic
Mancera et al. Single wagonload production schemes improvements using GüterSim (agent-based simulation tool)
JP2013011975A (en) Train crew operation plan creation system
Ceder Transit scheduling
Feng et al. Uncertain demand based integrated optimisation for train timetabling and coupling on the high-speed rail network
CN111222660B (en) Rail transit traffic road generation method and system based on full-line two-dimensional cutting
AU2008307181A1 (en) Method for creating timetables for transportation systems taking into account time limits
CN103198370A (en) Method and device of automatic schedule information processing of periodic use and maintenance schedules of bullet trains
CN112598262A (en) Oil-gas well maintenance task scheduling processing method and device
CN202495087U (en) Bullet train weekly use and maintenance plan automatic scheduling information processing device
JP2012010501A (en) Automatic facility deactivation planning device
Marton Villon–a tool for simulation of operation of transportation terminals
Mueller et al. Procedure of modular green factory planning to enhance collaboration and decision making
Hou et al. Optimization of Passenger and Freight Collaborative Transportation for Urban Rail Transit under Virtual Coupling Condition.

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20140627

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150205

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150217

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150319

R150 Certificate of patent or registration of utility model

Ref document number: 5718742

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees