JP2010168879A - Reinforcement construction method of caisson type pile, and reinforcement unit body for the same - Google Patents
Reinforcement construction method of caisson type pile, and reinforcement unit body for the same Download PDFInfo
- Publication number
- JP2010168879A JP2010168879A JP2009034505A JP2009034505A JP2010168879A JP 2010168879 A JP2010168879 A JP 2010168879A JP 2009034505 A JP2009034505 A JP 2009034505A JP 2009034505 A JP2009034505 A JP 2009034505A JP 2010168879 A JP2010168879 A JP 2010168879A
- Authority
- JP
- Japan
- Prior art keywords
- reinforcing bar
- bars
- unit body
- reinforcement
- deep foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Foundations (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
本発明は、橋梁及び送電線鉄塔などの基礎用に使用する深礎杭の鉄筋組立体を鉄筋ユニット体で構成し、その鉄筋ユニット体を予め地上にて組立て、吊支体で深礎杭に吊支移送して鉄筋組立体を構築する、その深礎杭の鉄筋構築施工法及びその鉄筋ユニット体に関する。In the present invention, a reinforcing bar assembly of a deep foundation pile used for foundations such as bridges and transmission line towers is constituted by a reinforcing bar unit body, the reinforcing bar unit body is pre-assembled on the ground in advance, and a deep foundation pile is formed with a suspension support. The present invention relates to a reinforcing bar construction method for a deep pile and a reinforcing bar unit body which is constructed by transferring a suspended support and constructing a reinforcing bar assembly.
従来、橋梁及び送電線鉄塔などを構築する場合の基礎として深礎杭基礎が構築され、該深礎杭基礎は、まず地盤に深礎立坑を掘削した後、土留め用コンクリート若しくはライナープレートなど防御壁を形成し、次に作業用足場を地上まで構設し、その状態で該深礎立坑内に筒状の鉄筋組立体を所定高さのブロック単位(4.8〜6.5m若しくは現場状況により他の高さも選ばれる。)で構築し、該構築された鉄筋組立体を各ブロック単位で埋設する形で前記立坑内にコンクリートを充填するようにして深礎杭基礎が構築され、地上までの所定高さまで施工される。 Conventionally, a deep foundation pile foundation has been constructed as a foundation for constructing bridges, transmission line towers, etc., and the deep foundation pile foundation is first constructed by excavating a deep foundation shaft in the ground, and then a defense concrete such as earth retaining concrete or liner plate. A wall is formed, and then a working scaffold is constructed up to the ground, and in that state, a cylindrical reinforcing bar assembly is placed in the deep foundation shaft in blocks of a predetermined height (4.8 to 6.5 m or site conditions). Other heights are also selected)), and the foundation pile foundation is constructed by filling the shaft with concrete in the form of embedding the constructed rebar assembly in units of blocks. It is constructed to a predetermined height.
その鉄筋組立体の構築は、上記作業用足場を構設後、該立坑壁面に沿って垂直方向に段取り筋を立設すると共に円周方向に帯筋と、径方向で格子状に剪断補強筋をそれぞれ配筋結束又は溶接し、その後縦主筋を配設して上述したように各ブロック単位で順次地上まで、鉄筋構築とコンクリート打設を繰り返し、該立坑内に各ブロック単位で深礎杭基礎が一般的に構築施工されている。 The rebar assembly is constructed by setting up the above-mentioned working scaffold, setting up setup bars in the vertical direction along the wall surface of the shaft, and reinforcing bars in the circumferential direction and shear reinforcement bars in the grid pattern in the radial direction. Reinforcing bar laying or welding, and then placing the longitudinal main bars and repeating the construction of the reinforcing bars and placing concrete concretely in units of each block as described above, and deep foundation pile foundation in units of each block in the shaft Is generally constructed and constructed.
また、先行技術として、「深礎杭用鉄筋ユニット及びそれを使用した深礎杭の構築方法」があり、そのユニット及び深礎杭の構築方法は、所定ピッチで水平配置された円弧状の横配力筋12を適当間隔で配置された複数の縦捨筋14で連結した外鉄筋ユニット10及び内鉄筋ユニット11を、複数の外縦主筋64及び内縦主筋70を固着すると共にトラス構造の外スペーサー22及び内スペーサー24を縦方向に複数取付けた深礎杭用鉄筋ユニットを使用して、防御壁40内で各工程に沿って連結する深礎杭の構築方法がある。(例えば、特許文献1参照) Further, as a prior art, there is a “reinforcement unit for deep foundation piles and a construction method of deep foundation piles using the same”, and the construction method of the unit and deep foundation piles is an arc-shaped laterally arranged horizontally at a predetermined pitch. The outer
さらに、本出願人が特許登録した「仮組鉄筋ユニットの載せ換え移載による鉄筋施工方法」があり、その鉄筋施工方法は、地上にて予め仮組治具体に仮組鉄筋ユニットを仮組みし、該仮組鉄筋ユニットを仮組治具体から移載治具体に載せ換え、建て込み位置に釣支移送して該建て込み位置の縦筋に、該仮組治具体の仮組鉄筋ユニットを結束又は溶着固定して施工する鉄筋施工方法がある。(例えば、特許文献2参照) Furthermore, there is a “rebar construction method by transfer and transfer of temporary assembly rebar unit” patented by the present applicant, which reinforces the temporary assembly rebar unit on a temporary assembly jig body in advance on the ground. The temporary assembly rebar unit is transferred from the temporary assembly jig body to the transfer jig body, and the fishing rod is transferred to the built-in position, and the temporary assembled rebar unit of the temporary assembly jig body is bound to the vertical reinforcement at the built-in position. Alternatively, there is a reinforcing bar construction method in which welding is performed and fixed. (For example, see Patent Document 2)
在来の深礎杭基礎の鉄筋組立体は、作業用足場を構設してから縦方向の縦主筋を深礎立坑内の外周のがぶり厚も考慮して二重に立設して構築されるが、この縦主筋立設の前に、要所箇所に段取り筋を立設し、該段取り筋に円弧状の複数の帯筋を順次配筋して環状に形成し、この状態では段取り筋が支持されず、(なお、施工者の多くは作業用足場に段取り筋を一時的または、本願で言う鉄筋ブロック体を数段構築するまで、支持または仮止めさせる事を実施している。)、またこの段取り筋の支持は、[0013]の後述するように縦主筋を支持固定すると剪断補強筋の施工に支障が出るため代わりに段取り筋を用いて支持させず、不安定の状態で構築すると共に径方向に複数の剪断補強筋を格子状に配筋して、所定ブロック単位で鉄筋組立体を構築し、そのほとんどの作業が深礎立坑内で行なわれ、地上での作業は、深礎立坑内に資材を降ろす作業に止まり、その深礎立坑内の作業においては、後述するような様々な課題が有ることから、地上での作業に振り返られる施工技術が求められていた。Reinforcement assemblies for conventional deep foundation pile foundations are constructed by constructing a working scaffold and then standing vertically with vertical main bars in consideration of the thickness of the outer periphery of the deep foundation shaft However, before this vertical main bar is erected, a setup line is erected at an important point, and a plurality of arc-shaped band bars are sequentially arranged on the set-up line to form an annular shape. The reinforcement is not supported. (It is noted that many installers are temporarily or temporarily fixing the setup reinforcement in the working scaffold until several stages of reinforcing bar blocks are constructed in this application. ) In addition, the support of the set-up bars is not supported by using the set-up bars instead because the construction of the shear reinforcement bars will be hindered if the longitudinal main bars are supported and fixed as described later in [0013]. and Haisuji multiple shear reinforcement in a lattice Rutotomoni radially to build, rebar assembly in a predetermined block unit Most of the work is carried out in the deep foundation shaft, and the work on the ground is limited to the work of dropping materials into the deep foundation shaft. challenges from the fact that there is, construction technology that is looking back to work on the ground has been demanded.
そして、上述施工される鉄筋組立体の環径は、非常に大きなものとなるため(後述する。)、所要長さの帯筋を円弧状に形成したものと直線の剪断補強筋を、深礎立坑内の狭い作業用足場で環状と格子状に構築するのは、後述するように高重量の鉄筋の結束又は溶着作業をするのに、非常に人員と手間が掛かり、鉄筋の結束又は溶着作業で効率化が求められ、また特に狭い作業用足場での安全性と身体的疲労の改善も求められていた。 And since the ring diameter of the rebar assembly constructed as described above becomes very large (described later), a steel strip having a required length is formed into an arc shape and a straight shear reinforcement bar is a deep foundation. Narrow work scaffolds in the shaft are constructed in a ring and lattice form, as will be described later, in order to bind or weld heavy rebars, it takes a lot of work and labor to bind or reinforce rebars. There was also a need to improve efficiency and to improve safety and physical fatigue, especially on a narrow work platform.
また、従来の深礎杭基礎の構築は、上述の鉄筋構築からコンクリート打設まで所定の高さ(過去例として、4.8mから6.8m)の各ブロック単位で積み上げ構築され、そのとき鉄筋構築に使用された作業用足場の撤去とコンクリート打設、そしてその後、新たに次段ブロック用の作業用足場の構設する方法または作業用足場をそのままコンクリートの打設で埋め込んでしまう施工法もあり、その何れの施工法も、作業時間若しくは作業用足場が無駄になっており、改善が求められていた。In addition, the construction of a conventional deep foundation pile foundation is built up in units of blocks of a predetermined height (4.8 to 6.8 m as a past example) from the above-mentioned reinforcing bar construction to concrete placement. removal and concreting of work platform that was used to construct, and then, also construction methods newly become embedded in pouring neat concrete methods or work platform to構設the work platform for the next stage block In any of the construction methods, work time or work scaffolding was wasted, and improvement was demanded.
さらに、その各ブロック単位での構築は、コンクリートの打設後、凝固した後次のコンクリート打設の打ち継ぎの継ぎ目の密着度を増すためのレイタンス処理で、固まったそのコンクリート表面の不純物を取り除くために洗浄する必要があり、その洗浄後の洗浄水をポンプで汲み出し作業など時間と手間を要し、レイタンス処理などの期間は状況により5日程度を要し、ブロック単位の構築回数分がその期間の人員配置の無駄となり、改善が求められていた。 Furthermore, the construction of each block unit is to remove impurities on the solidified concrete surface by a latency process to increase the adhesion of the joint of the next concrete casting after solidification after solidification. For this reason, it takes time and labor to pump the wash water after the washing, such as pumping work, and the period of the latency treatment etc. takes about 5 days depending on the situation, and the number of times of construction in block units is It was a waste of staffing during the period, and improvements were required.
加えて、該ブロック単位で深礎杭基礎の構築のさらなる課題は、地盤に深礎立坑を掘削して深礎立坑内の深礎抗底及び側壁に土留め用のコンクリート壁を形成するが、必ずしも該周壁が円形で底面も平坦に形成されず歪みが存在し、その状態で作業用足場と縦筋の段取り筋を配置し、その段取り筋に帯筋を深礎立坑内で環状に配筋、結束又は溶着して構築されるため、ブロック単位での鉄筋組立体が、環状で水平レベルを保っているかどうかは、数段の帯筋を構築するまで、その鉄筋組立体の水平レベルをトランシットなどの計測器で正確に計測しにくかった。 In addition, the further problem of construction of deep foundation pile foundation in the block unit is to excavate deep foundation shafts in the ground to form concrete walls for earth retaining on the deep foundation bottom and side walls in the deep foundation shafts. The peripheral wall is not necessarily circular and the bottom surface is not formed flat, and there is distortion. In this state, the work scaffolding and the vertical streak are placed, and the stirrup is placed in a ring in the deep foundation shaft. Because it is constructed by tying or welding, whether the rebar assembly in the block unit is circular and keeps the horizontal level, the horizontal level of the rebar assembly is transited until a several level of rebar is built. It was difficult to measure accurately with such measuring instruments.
そして、その水平レベルを調整も煩雑で、特に大径と高重量となるとそれが顕著であり、また上述した鉄筋構築の最初の段階では、段取り筋(本来構築する縦主筋より細い鉄筋が使われる。)で構築し、その後で縦主筋を配設して構築するが、その当初の段取り筋は特に支持されておらず不安定の状態で鉄筋組立体が構築され、現実、そのような水平レベルの不完全な構築状況で地上まで構築したとき、鉄筋組立体が崩壊する事故が発生し(雑誌、日経コンストラクション、2008年12月号、26頁から29頁に「事故の原因と再発防止策、29頁」が掲載されている。)、報告では、原因として決定づけられていないが、段取り筋の座屈が原因ではないか、その座屈の原因として段取り筋に偏心が生じていたことが指摘され、鉄筋組立体を構築するときの水平レベルを低い位置で正確に出せない在来工法の大きな課題となり、安全性にも課題を残し、低い位置で水平計測と容易に水平レベルが調整でき、且つ立設固定ができるものが求められていた。 Adjustment of the horizontal level is also complicated, especially when the diameter and weight are large, and in the first stage of building the above-mentioned reinforcing bar, a set-up bar (a reinforcing bar thinner than the longitudinal main bar to be originally built is used). )), And then arrange the longitudinal main bars, but the initial set-up bars are not particularly supported and the rebar assembly is built in an unstable state. When building up to the ground in an incomplete construction situation, an accident occurred in which the rebar assembly collapsed (Magazine, Nikkei Construction, December 2008 issue,
また、上述問題点は縦主筋(上述では段取り筋として使用している。)そのものの課題でもあり、つまりその縦主筋と円弧状の帯筋の構築において、並列する縦主筋に、帯筋両端のフックでそれぞれ掛け渡すように施工されるが、そのフックを掛けることが問題で、太い両縦主筋が垂直に立った状態で一方のフックは、縦主筋に容易に掛けられるが、その掛けた状態でもう一方のフックを掛けようとすると、そのフックの曲った部分が邪魔となり、両縦主筋を近づけるように撓ませてフックの先端を迂回するように掛けない限り該縦主筋に掛けられず、それは通常フックの曲げ部分から先端までの長さが一例で290ミリあり、このことはそのフックの先端が290ミリを迂回させなければ該縦主筋に掛ける事ができず、現実、縦筋は太く容易に歪ませることができず、また次々と掛止して環状になった最後の一箇所に掛けようとすると、その環状にすべて掛止された縦主筋は、もう撓むことは全くできないので、該フックが縦主筋を越せず、在来施工の縦主筋が配置された状態では、帯筋の両フックを該縦主筋の上部先端から挿入して所定の位置の下方に送り、帯筋両端の該両縦主筋にそのフックが掛かるように施工しており、非常に手間が掛かることから改善が求められていた。 In addition, the above-mentioned problem is also a problem of the longitudinal main bar (used as a set-up bar in the above) itself, that is, in the construction of the vertical main bar and the arc-shaped band, It is constructed so as to be hung with hooks, but it is a problem to hang the hooks, and one hook can be easily hung on the vertical main bars with the thick vertical main bars standing vertically, but the hooked state If you try to hang the other hook, the bent part of that hook will be in the way, and it will not be hung on the vertical main bar unless it is bent so that both vertical main bars are bent closer to bypass the tip of the hook, It is usually 290 mm in length from the bent part of the hook to the tip. This means that the tip of the hook cannot be hooked on the vertical main muscle unless it bypasses 290 mm. Yong Can not be distorted, and if you try to hang on the last one place that is looped and looped one after another, the vertical main bars that are all hooked on the ring can no longer flex, When the hook does not pass through the longitudinal main bar and the longitudinal main bar of the conventional construction is arranged, both hooks of the strap are inserted from the upper end of the longitudinal main bar and sent below the predetermined position, Since the construction is made so that the hooks are applied to both the longitudinal main bars, it takes a lot of time and effort.
上述の帯筋の在来施工から分かるように、縦主筋若しくは段取り筋に帯筋を掛止しにくく、該縦主筋若しくは段取り筋を固定せず一時的に作業用足場に保持させたり、揺動可能な状態とすることで、帯筋を段取り筋に掛けやすく施工していることから円弧状の帯筋の施工は、制約が多く時間を要し、また配筋施工の最初の段階の手間と煩雑性と上述した水平レベル調整の煩雑性とその施工の安全性もあり、改善が求められていた。 As can be seen from the conventional construction of the above-mentioned band reinforcement, it is difficult to hook the band reinforcement on the vertical main bar or the set-up bar, and the vertical main bar or the set-up bar is not fixed and temporarily held on the work scaffold or swings. By making it possible, it is easy to lay the straps on the set-up bars, so the construction of the arc-shaped strips is time-consuming and time consuming, and the effort of the first stage of bar arrangement construction Improvements have been sought due to the complexity, the above-described horizontal level adjustment complexity, and the safety of the construction.
さらに、在来工法の立坑内での鉄筋構築作業は、帯筋及び剪断補強筋などの資材を絶えずクレーン等で降ろして貰い、特に帯筋は、両縦主筋の上部端からフック部を掛け渡すようにして挿入し一本一本降ろす必要があり非常に手間で、そしてそれらを段取り筋及び縦主筋に結束又は溶着する作業の繰り返しで、狭い作業用足場に立っての穴底から上を見上げるなど体のバランスを取りながらの作業が多く、注意力と体力を使い、心身共に非常に疲労を来たし、そして肩こりなど多くの人が経験し、それら疲労による安全性にも問題があり、さらにその作業者は、一日中深礎立坑内の空気環境の悪い場所での作業となる事が多く、それらの改善が求められていた。 Furthermore, rebar construction work in a conventional construction shaft is to continuously unload materials such as reinforced bars and shear reinforcement bars with a crane, etc., especially for the reinforced bars, hooks are hooked from the upper ends of both longitudinal main bars. Thus, it is necessary to insert and take down one by one very much, and look up from the bottom of the hole standing in a narrow work scaffold by repeating the work of tying or welding them to the setup and longitudinal main bars There are many work while balancing the body, using attention and physical strength, both the mind and body got very tired, and many people such as stiff shoulders have experienced safety problems due to fatigue, Workers often work in places with poor air environment in deep foundation shafts throughout the day, and improvements were required.
加えて、上述在来工法の立坑内での作業は、通常でも危険が伴い、さらに上からの落下物、例えば、風などの影響によるホコリ、小石などの落下、またすべての資材が地上に貯蔵され、それらが絶えず降ろされてくることから、作業用足場等の関係もあり逃げ場が限られ待避できないこともあり、また地上側も含めて絶えず注意が必要で、通常の工事現場以上の注意力が要求され、加えて深い立坑内で長時間の作業であることから換気設備も必要とし、これらのことから作業員の疲労もはげしく、改善が求められ、危険が伴う深礎立坑内での作業をできるだけ少なくし、地上での作業に極力振り替える事で、作業の効率化と危険作業の短縮を図り、作業の軽減と安全性を確保する事とし、また換気設備も必要としないなど上述した数々の課題の解決を図ることを目的としている。In addition, the work in the above-mentioned conventional method shafts is usually dangerous, and the fallen objects from above, for example, the fall of dust and pebbles due to the influence of wind, etc., and all materials are stored on the ground. Since they are constantly lowered, there is a relationship with scaffolding for work, etc., and there are cases where the escape area is limited and cannot be saved, and attention is required constantly including the ground side. In addition, it requires long-term work in deep shafts and requires ventilation equipment. These factors also lead to excessive fatigue, demand for improvements , and work in deep foundation shafts that are dangerous. to reduce as much as possible, in as much as possible reclassified it to work on the ground, working to shorten the dangerous work and efficiency of work, and that to ensure the reduction and safety of the work, also numerous described above, such as does not require ventilation equipment Challenges Resolution are intended to be achieved.
なお、上述施工される深礎杭の多くは、直径で8mから29mで、深さ19m程度(現場状況により他の寸法も選ばれる。)の規模であり、その施工で多く使用される鉄筋サイズにおいて、縦主筋はD51の規格サイズの重量は15.9kg/mであり、例えば、定尺12mの長さで約191kgの総重量で、また帯筋及び剪断補強筋でよく使用されるサイズのD29は5.04kg/mであり、定尺12mの長さで約60kgと相当の高重量で、このような重量物を、上述した在来工法ように、深礎立坑内で狭い作業用足場の上での手作業で鉄筋を結束又は溶着するのは、安全性と作業の効率化に課題を多く残すものであった。 Most of the above-mentioned deep foundation piles are 8m to 29m in diameter and about 19m in depth (other dimensions are selected depending on the site conditions). The vertical main bar has a D51 standard size weight of 15.9 kg / m, for example, a length of 12 m, a total weight of about 191 kg, and a size often used for band bars and shear reinforcement bars. D29 is 5.04kg / m, and the length is 12m, and the weight is about 60kg. The weight of such a heavy work is narrow in the deep foundation shaft as in the conventional construction method described above. Bonding or welding the reinforcing bars by hand manually left many problems in safety and work efficiency.
また、特許文献1の「深礎杭用鉄筋ユニット及びそれを使用した深礎杭の構築方法」は、深礎杭の防御壁40内で、その防御壁40にトラス構造の外スペーサー22を取り付け、次に外鉄筋ユニット10を外スペーサー22の波形ラチス筋28に引っかけ、外鉄筋ユニット10を結束し、次に内スペーサー24を取り付ける各工程で順次、組み上げることが開示されていますが、上述したように各鉄筋、単体の重量が非常に重く、それをユニット化したときの重量は過大で、その重量に耐える状態に補強、組み立てされているユニットでないので、その取り扱い、移動に於いては、クレー等で且つ移動させるための治具等が必要で、開示された内容のように、防御壁40に単純に降ろすという事が効率よくできなかった。 In addition, “Reinforcement unit for deep foundation pile and method for constructing deep foundation pile using the same” in
つまり、開示された深礎杭用鉄筋ユニットは、鉄筋を円弧状の横配力筋12を適当間隔で配置された複数の縦捨筋14で連結した外鉄筋ユニット10及び内鉄筋ユニット11を溶接構造で筒状に各段、製造されるが、(特許文献1の[0012]に記載されている。)上述したように、深礎杭で使用される鉄筋の重量が過大で、上述のような立体構造のユニットでは形状が安定せず、また防御壁40内に降ろす段階でも形状が保てず、課題が多かった。 That is, the disclosed reinforcing bar unit for deep foundation piles welds the outer
さらに、特許文献2の「仮組鉄筋ユニットの載せ換え移載による鉄筋施工方法」は、仮組治具体に仮組鉄筋ユニットを仮組みし、該仮組鉄筋ユニットを仮組治具体から移載治具体に載せ換え、建て込み位置に釣支移送して該建て込み位置の縦筋に、該仮組治具体の仮組鉄筋ユニットを結束固定して施工することから、深礎杭用基礎の縦主筋は、固定立設された状態で施工されないので、特許文献2の仮組鉄筋ユニットをそのまま釣支移送しても、該ユニットを縦主筋に結束して鉄筋組立体の構築する施工ができず、また数多くの該縦主筋にそれぞれ結束するまで移載治具体から該仮組鉄筋ユニットを切り離すことができず、よってこの特許文献2の工法では、深礎立坑内の施工のスピード化及び安全性が得られず、このことから鉄筋のユニット化と該鉄筋ユニットの釣支移送の概念は類似でも、構築する対象物及びその条件が相違すると課題が多く全く対応できず、深礎杭用の施工法に適した鉄筋ユニット及び吊支体とその深礎杭鉄筋の施工法の改良が求められていた。 Furthermore, “Rebar construction method by transfer and transfer of temporary assembly reinforcing bar unit” in
本発明は、上記課題を有効に達成するために、第1の解決手段として、該深礎立坑内に鉄筋組立体を構築する鉄筋構築施工法において、予め地上で梯子筋を所定位置に位置出し、該梯子筋の支持受け筋に、円弧状で両端にフックが形成される帯筋を環状に所要数連結形成すると共に該環状の帯筋に、剪断補強筋を径方向に格子状に配筋して鉄筋ブロック体を形成し、該鉄筋ブロック体を梯子筋の該支持受け筋に所要段数支持させて鉄筋ユニット体として構築する第一の行程と、
該構築された所要段数の鉄筋ユニット体を吊支体で、深礎立坑に吊支移送する第二の行程と、
深礎立坑壁面の壁面に沿ってガイド筋を立設すると共にガイド筋支持用刺し筋で該壁面より支持してガイド体とし、該ガイド体を案内として上記吊支移送された該鉄筋ユニット体を深礎立坑内の所定位置まで移送降下させる第三の行程と、
上記降下された鉄筋ユニット体を水平レベル出しすると共にガイド体と鉄筋ユニット体を結束又は溶着し、該二段目以降は、前記第一から第三の行程を繰り返し、該鉄筋ユニット体の各梯子筋同士を直線状に溶着して各段連結し、該重装された鉄筋ユニット体を各ガイド体に結束又は溶着する第四の行程と、
該二段目以降、該鉄筋ユニット体同士を重装連結した後、作業用足場を直近一段低い段まで順次構設する第五の行程と、
鉄筋ユニット体が構築された後、縦主筋を該鉄筋ユニット体の各所要位置にそれぞれ配設すると共にその縦主筋と鉄筋ユニット体を結束又は溶着する行程を第六の行程とする鉄筋構築施工法で、
各工程によって鉄筋組立体を深礎立坑内に構築する事としている。In order to effectively achieve the above-mentioned problems, the present invention provides, as a first solution, in a reinforcing bar construction method for constructing a reinforcing bar assembly in the deep foundation shaft, a ladder bar is previously positioned at a predetermined position on the ground. In addition, a required number of strips that are arc-shaped and hooks are formed on both ends are connected to the ladder support support bars in a ring shape, and shear reinforcement bars are radially arranged in a lattice pattern in the ring straps. Forming a reinforcing bar block body, and supporting the reinforcing bar block body to the support receiving bars of the ladder bars in a required number of steps to construct a reinforcing bar unit body;
A second step of transferring the rebar unit body of the required number of steps constructed to the deep foundation shaft with a suspension support,
A guide bar is erected along the wall surface of the deep foundation shaft and is supported from the wall surface by a guide bar supporting stab bar to form a guide body. A third step of transporting and dropping to a predetermined position in the deep foundation shaft,
The lowered rebar unit body is leveled and the guide body and the rebar unit body are bound or welded, and after the second stage, the first to third steps are repeated, and each ladder of the rebar unit body is repeated. A fourth step of welding the reinforcing bars in a straight line and connecting each step, and binding or welding the stacked reinforcing bar unit bodies to each guide body;
After the second stage, after connecting the rebar unit bodies together, a fifth step of sequentially constructing the work scaffold to the next lower stage,
After the reinforcing bar unit body is constructed, a reinforcing bar construction method in which the longitudinal main bar is disposed at each required position of the reinforcing bar unit body and the process of binding or welding the longitudinal main bar and the reinforcing bar unit body is the sixth process. so,
Reinforcement assemblies will be built in the deep foundation shaft by each process .
また、第2の解決手段として、ガイド筋支持用刺し筋は、深礎立坑壁面に埋め込み状に穿入し、且つ壁面より所定量突設させ、後に構築された鉄筋組立体が正確に所定位置に支持できるように、ガイド筋を該壁面と所定間隔で支持することでガイド体として構成し、該ガイド体を案内として、鉄筋ユニット体を深礎立坑内の所定位置まで移送降下させると共に該鉄筋ユニット体を深礎立坑内の所定位置に保持固定させる鉄筋構築施工法で、
ガイド体を案内として、鉄筋ユニット体を深礎立坑内の所定位置まで移送降下させ、所定位置に保持固定させる事としている。As a second solution, the stab bars for supporting the guide bars are embedded in the deep foundation wall surface and protruded by a predetermined amount from the wall surface, so that the rebar assembly constructed later can be accurately positioned at a predetermined position. The guide bars are configured as a guide body by supporting the guide bars at a predetermined distance from the wall surface, and the reinforcing bar unit is transported and lowered to a predetermined position in the deep shaft while using the guide bodies as guides. Reinforcement construction method to hold and fix the unit body in a predetermined position in the deep foundation shaft ,
Using the guide body as a guide, the rebar unit body is transported and lowered to a predetermined position in the deep foundation shaft and is held and fixed at the predetermined position .
また、第3の解決手段として、鉄筋ユニット体において、支持受け筋を所定間 隔で所要段数設けて梯子筋とし、また円弧状で両端にフックが形成される帯筋を、環状に連結形成すると共に剪断補強筋を径方向に格子状に形成する鉄筋ブロック体を一段とし、該鉄筋ブロック体の所定位置に上記梯子筋を複数、配置すると共に該梯子筋の各支持受け筋と該鉄筋ブロック体を結束又は溶着支持することで、
鉄筋ブロック体で鉄筋ユニット体を構築すると共に深礎立坑内に移送し、該鉄筋ユニット体を各重装して鉄筋組立体を構築すること事としている。Further, a third aspect of the invention, the reinforcing bar unit body, the support receiving muscle and ladder muscle provided the required number of stages in a predetermined interval and a hoop hook at both ends in the arc shape is formed, connecting annular shape In addition, a reinforcing bar block body in which shear reinforcing bars are formed in a grid pattern in the radial direction is made one stage, a plurality of the ladder bars are arranged at predetermined positions of the reinforcing bar block body, and each support receiving bar of the ladder bars and the reinforcing bar block body By binding or welding support ,
A rebar unit body is constructed with a rebar block body and transferred into a deep foundation shaft, and the rebar unit body is constructed by building up the rebar unit bodies in layers.
地盤に基礎用の深礎立坑を掘削して土留め施工された該深礎立坑内に鉄筋組立体を構築する鉄筋構築施工法において、予め地上で、鉄筋ユニット体が正確に形成できるように、先ず梯子筋を予め位置出しされた所定位置に所要数配置し、該梯子筋の支持受け筋に、円弧状で両端にフックが形成される帯筋を内外二重の環状に所要数連結形成すると共に該環状の帯筋に、剪断補強筋を径方向に格子状に配筋して鉄筋ブロック体を形成すると共に該鉄筋ブロック体を、梯子筋に所定間隔で所要段数、横設される該支持受け筋に結束又は溶着支持させて所定の鉄筋ユニット体として構築する第一の行程と、
該構築された所定の鉄筋ユニット体を吊支体で、深礎立坑に吊支移送する第二の行程と、
該吊支移送された該鉄筋ユニット体を、深礎立坑内の所定位置までガイド体に沿って移送降下させる第三の行程と、
上記移送降下された一段目の鉄筋ユニット体を該深礎立坑内底面で水平レベル出しすると共にその状態で、壁面に沿って立設されたそれぞれのガイド体と該鉄筋ユニット体とを結束又は溶着し、また該底面から二段目以降は、前記第一から第三の行程を繰り返し、降下重装された該鉄筋ユニット体の各梯子筋同士を各段、順次、直線状となるように重装させると共に溶着して各段連結し、該重装各段連結された鉄筋ユニット体を上記と同様に各ガイド体に結束又は溶着する第四の行程と、
そして該二段目以降、鉄筋ユニット体の各梯子筋同士を重装連結した後、剪断補強筋が格子状に配筋されたその格子状の所定空間に、該鉄筋ユニット体の直近一段低い段まで順次、作業用足場を構設する第五の行程と、
深礎立坑内に鉄筋ユニット体が所定段数、構築された後、縦主筋を該鉄筋ユニット体の各所要位置にそれぞれ配設すると共にその縦主筋と鉄筋ユニット体を結束又は溶着する第六の行程よりなり、前記各工程によって鉄筋組立体を深礎立坑内に構築する第1の解決手段により、
上記第一の行程から、地上で梯子筋に各鉄筋ブロック体単位で鉄筋ユニット体を構築するので、最も時間を要する鉄筋ユニット体の構築が地上で行なえ、上述した危険要素が多く存在する深礎立坑内の作業が大幅に減らすことができ、最良の安全対策となり、また従来のように高重量で数多くの資材をクレーンでその都度降ろす必要が無く、すべて構築現場近くに置いておけることで、作業性が良く効率化できることから、鉄筋組立体の工期の大幅な短縮とコストの低減が図れ、さらに、鉄筋ユニット体を結束又は溶着して所定形状に形成しているので、型く ずれすることなく安全に素早く吊支移送が可能となる。 In the reinforcing bar construction method that constructs a reinforcing bar assembly in the deep foundation shaft that has been earthed by excavating a foundation deep shaft for foundation, so that the reinforcing bar unit body can be accurately formed on the ground beforehand, First, a required number of ladder bars are arranged in a predetermined position, and a required number of band bars that are arc-shaped and hooks are formed at both ends are connected to the support bars of the ladder bars in a required manner. In addition, a reinforcing bar block is formed by arranging shear reinforcement bars in a lattice pattern in the radial direction on the annular band, and the reinforcing bar block is horizontally arranged at a predetermined number of steps on the ladder bars. A first step of constructing as a predetermined reinforcing bar unit body by binding or welding support to the receiving bar;
A second step of suspending and transferring the constructed predetermined reinforcing bar unit body to a deep foundation shaft with a suspension support;
A third step of transporting and lowering the rebar unit body transported by the suspension support along the guide body to a predetermined position in the deep foundation shaft;
The transported and lowered first-stage rebar unit body is leveled at the bottom of the deep foundation shaft, and in this state, each guide body erected along the wall surface and the rebar unit body are bound or welded together. In the second and subsequent steps from the bottom surface, the first to third steps are repeated, and the ladder bars of the rebar unit body that are lowered and stacked are overlapped in stages so as to be linear. And a fourth step of binding or welding the rebar unit bodies connected to each stage in the same manner as described above,
After the second stage, after the ladder bars of the reinforcing bar unit body are overlaid and connected, the lower level of the reinforcing bar unit body is the next lower level in the grid-like predetermined space where the shear reinforcement bars are arranged in a grid pattern. Until the fifth step of constructing a work scaffold,
After the reinforcing bar unit body has been built in the deep foundation shaft, the longitudinal main bars are arranged at the required positions of the reinforcing bar unit body, and the longitudinal main bar and the reinforcing bar unit body are bound or welded. The first solving means for constructing the reinforcing bar assembly in the deep foundation shaft by the above steps ,
From the first step above, the reinforcing bar unit body is constructed on the ladder on the ground in each rebar block body, so the most time-consuming rebar unit body can be constructed on the ground, and there are many risk factors mentioned above. Work in the shaft can be greatly reduced, it is the best safety measure, and there is no need to unload many heavy materials each time with a crane as in the past, and all can be placed near the construction site, because it can better efficiency workability, Hakare is significantly reduced and cost reduction of the construction period rebar assembly, further, since the reinforcing bar unit body by tying or welding to form into a predetermined shape, the mold rather be shifted The suspension support can be transferred safely and quickly.
また、第二及び第三の行程から、鉄筋ユニット体を深礎立坑に吊支移送して、該地上から深礎立坑内の所定重装位置へ降下するとき、ガイド体に沿って降下できるので、深礎立坑内で各鉄筋ユニット体を重装固定する位置出しが容易となると共に該ガイド体に鉄筋ユニット体を結束又は溶着することができ、よって鉄筋組立体の崩れなどに繋がることなく各鉄筋ユニット体を重装できる。Also, from the second and third strokes, the rebar unit body can be suspended and transferred to the deep foundation shaft, and when it descends from the ground to the predetermined heavy load position in the deep foundation shaft, it can descend along the guide body In addition, it is easy to position and fix each reinforcing bar unit body in the deep foundation shaft, and the reinforcing bar unit body can be bound or welded to the guide body, so that each rebar assembly is not broken. Reinforcement unit can be loaded.
さらに、その所定位置へ移送降下するとき、ガイド体に沿って降下させるので、該立坑内の設置場所で作業員による誘導作業も必要ないので、鉄筋ユニット体を降下させるまでその場で待機する必要も無く、安全に鉄筋ユニット体を降下させることができ、よって鉄筋ユニット体の移送降下作業が安全に捗り、吊支移送の時間短縮となる。Furthermore, since it is lowered along the guide body when transporting and lowering to the predetermined position, it is not necessary to perform guidance work by an operator at the installation location in the shaft, so it is necessary to wait on the spot until the rebar unit body is lowered. Therefore, the rebar unit body can be safely lowered , so that the transfer and lowering operation of the rebar unit body can proceed safely and the time for the suspension support transfer can be shortened.
また、第四の行程から、水平レベル調整を深礎立坑内の底面と該連結体で上記のように調整できるので、水平レベルを保ち鉄筋組立体が崩れるようなこともなく、正確に安定した鉄筋組立体が安全に早く施工ができる。 In addition, from the fourth stroke, the horizontal level adjustment can be adjusted as described above with the bottom of the deep foundation shaft and the connection body, so that the horizontal level is maintained and the rebar assembly is not destroyed, and it is accurately stable. The rebar assembly can be safely and quickly constructed.
また、第五の行程から、鉄筋ユニット体を作業用足場より後で順次構設するので、地上からクレーなどで深礎立坑内に吊支移送降下させるとき、作業用足場が邪魔になってその降下する鉄筋ユニット体が見え辛くなることもなく、確認しながら降下と作業員が深礎立坑内で補助することなく位置合わせができるので、安全に位置合わせができ、且つ移送降下作業が捗り施工時間の短縮にも繋がる。 Further, the fifth step, since the later sequentially構設than work platform rebar unit body, Rutoki is Tsu支transferred lowered into caisson shafts like clay from the ground, and work platform are in the way The descending rebar unit body does not become difficult to see, and while confirming, the descent and the operator can align without assistance in the deep foundation shaft, so the alignment can be done safely and the transfer descent work is progressing It leads to shortening of construction time.
そして、常に作業者が目線以下の楽な姿勢で作業が行なえるので、腕及び肩に掛かる負担が軽減でき、また後述する深礎立坑内で鉄筋ユニット体の各梯子筋に重装固定する溶接作業などの作業性も、不安定な作業用足場の上でも、上述のように目線以下の楽な姿勢で行なえ、作業姿勢のバランスが取りやすく、安全に効率よく作業ができる。 And because the worker can always work in an easy posture below the line of sight , the burden on the arms and shoulders can be reduced, and welding that is fixed to each ladder of the reinforcing bar unit in the deep foundation shaft described later As described above, workability such as work can be performed in an easy posture below the line of sight even on an unstable work scaffold, and it is easy to balance the work posture, enabling safe and efficient work.
さらに、深礎立坑内で鉄筋ユニット体の各梯子筋に重装固定する溶接などの作業性は、地上の溶接作業と違って、深礎立坑内の作業用足場と言う狭く危険を伴う作業場所での作業から特に重要で、上述のように目線以下の楽な姿勢で作業が行なえると言うことは、作業姿勢のバランスが取りやすく作業員の安全性と疲労が少なく、作業環境衛生と安全で効率よく作業ができる。In addition, the workability such as welding that is fixed to each ladder bar of the reinforcing bar unit in the deep foundation shaft is different from the ground welding work, and it is a work place with a narrow danger called the work scaffold in the deep foundation shaft. It is especially important from the work at work, and the fact that work can be performed in an easy posture below the line of sight as described above means that the work posture is easily balanced and the worker's safety and fatigue are low, and the work environment is hygienic and safe. Can work efficiently.
また、第六の行程から、深礎立坑内に鉄筋ユニット体が構築された後、縦主筋と鉄筋ユニット体を結束又は溶着することから、従来のように縦主筋の上端から挿通する手間の掛かる作業が無く、また上述したように鉄筋を一気に地上まで構築すると起こる可能性がある座屈崩壊を防止するため各ブロック単位で鉄筋構築とコンクリート打設を繰り返すと言う時間を要する行程が無く、鉄筋組立体の上部から縦主筋を挿通して該鉄筋組立体に結束又は溶着することで完成するので施工が容易で、さらに鉄筋構築を地上まで一気に完成させることができ、短時間に施工完了となる。 Further, the sixth step, after the rebar unit body is constructed in the shinso vertical shaft, the longitudinal main reinforcement and reinforcement unit bodies since the tying or welding, laborious inserting from the upper end of the vertical main reinforcement as in the conventional There is no work, and there is no time-consuming process of repeating rebar construction and concrete placement for each block to prevent buckling collapse that may occur if the rebar is built up to the ground as described above. Construction is easy because it is completed by inserting the vertical main bar from the top of the assembly and binding or welding to the rebar assembly , and construction of the rebar can be completed to the ground at once, and construction is completed in a short time .
これらのことから、上述した多くの課題を取り除き、鉄筋構築のほとんどの作業を地上に振り替えることで深礎立坑内での作業を最小限に止め、作業員の作業環境衛生と疲労が比較的少なく安全で、作業の一元化による効率化で施工が早く、これを実証するため、施工規模において立杭抗径が14m、深さ19m規模の鉄筋組立体を構築する実証施工に使用した時、在来工法の過去実績では、平均約13人/日の人員で、約40日程度の施工期間を要するが、本発明の深礎杭の鉄筋構築施工法では、平均約7人/日の人員で、11日間で完了することができ、改めて施工期間の早さが実証できた。 For these reasons, many of the problems described above are eliminated, and most of the work of building reinforcing bars is transferred to the ground to minimize the work in the deep foundation shaft. It is safe and efficient due to the unification of work, so that construction can be done quickly. In order to verify this, when used for demonstration construction to construct a reinforcing bar assembly with a pile pile diameter of 14m and a depth of 19m on the construction scale, it is conventional. In the past results of the construction method, it takes an average of about 13 people / day, and it takes about 40 days of construction. However, in the method for constructing reinforcing bars for deep foundation piles of the present invention, the average is about 7 people / day. It could be completed in 11 days and once again proved the speed of the construction period.
しかして、ガイド体は、鉄筋ユニット体を移送降下の案内と後に構築された鉄筋組立体が正確に所定位置に支持できるように、深礎立坑壁周面に沿って所定位置でガイド筋を立設させ、一方、該壁面に差し込み状に埋設し、且つ壁面より所定量突設させて所要数のガイド筋支持用刺し筋を設け、該所要数の各ガイド筋支持用刺し筋の突設部と該立設されたガイド筋を溶着支持し、その立設支持されたガイド筋に沿って鉄筋ユニット体を深礎立坑内の所定位置まで移送降下の案内とすると共に該鉄筋ユニット体を深礎立坑内の所定位置に保持固定させる第2の解決手段により、
地上からクレーなどで深礎立坑内に吊支移送降下させるとき、ガイド体に沿って降下できるので、作業員が深礎立坑内で補助することなく位置合わせができることで移送降下作業が捗り、さらにそれにより重装固定する位置出しも容易となり、また該ガイド体に鉄筋ユニット体を結束又は溶着することで、鉄筋組立体の崩れなどに繋がることなく各鉄筋ユニット体を重装できる。 Thus, the guide member is so constructed after the guide of the transfer drop Rebar unit body reinforcing bar assembly can be supported in precisely predetermined position, the guide muscle at a predetermined position location along the shinso pit wall peripheral surface On the other hand, a required number of stab bars for supporting the guide muscles are provided by being embedded in the wall surface and inserted in a predetermined amount from the wall surface to project the required number of stab bars for supporting each of the guide muscles. The reinforcing bar unit is welded and supported along the guide bar, and the rebar unit body is guided along the guide bar supported upright to the predetermined position in the deep foundation shaft. By the second solving means for holding and fixing at a predetermined position in the foundation shaft ,
When suspended and transported from the ground to the deep foundation shaft with clay, etc., it can be lowered along the guide body. Accordingly, the positioning of the reinforcing unit is facilitated, and the reinforcing bar unit bodies are bound or welded to the guide body, so that the reinforcing bar unit bodies can be mounted without causing the collapse of the reinforcing bar assembly.
また第一の行程で鉄筋ユニット体を所定形状に正確に構築しているのとガイド筋支持用刺し筋で正確にガイド筋を立設支持しているので、そのガイド筋に沿って鉄筋組立体を構築することでガブリが手間を要することなく正確に設定でき、これは上述した在来の掘削と土留め施工により形成される深礎立坑が正確な円筒状に形成できないので、鉄筋組立体の設置位置と水平レベルを正確に出すのに非常に手間が掛かり困難で時間を要し、施工期間の遅延となっていたことが解決できた。In addition, since the reinforcing bar unit body is accurately constructed in the first step and the guide bar is accurately set up and supported by the guide bar supporting stab bars, the reinforcing bar assembly along the guide bars By constructing the structure, it is possible to accurately set the gabri without the need for labor, and this is because the deep foundation shaft formed by the above-mentioned conventional excavation and earth retaining work cannot be formed into an accurate cylindrical shape. It was very difficult and time consuming to accurately set the installation position and horizontal level, and it was possible to solve the problem that the construction period was delayed.
しかして、深礎立坑内に鉄筋組立体を構築する鉄筋ユニット体において、所定長さの型材などの支持本体の一側面から突設させた棒状の支持受け筋を所定間隔で所要段数設けて梯子筋とし、また円弧状で両端にフックが形成される帯筋を、所要数で内外二重の環状に連結形成すると共に該環状の帯筋に剪断補強筋を径方向に格子状に配筋して形成する鉄筋ブロック体を一段とし、該鉄筋ブロック体の帯筋及び剪断補強筋の所定位置に上記梯子筋を複数、配置すると共に該梯子筋の 各支持受け筋と該鉄筋ブロック体を各所定段数、結束又は溶着支持する第3の解決手段により、
予め正確な鉄筋ユニット体構築していることから、該鉄筋ユニット体の重装連結により、正確に鉄筋組立体を構築することができ、また深礎立坑内の壁面と鉄筋組立体とのガブリも正確に設定でき、さらに鉄筋ユニット体が歪み無く正確に重装できることから、鉄筋組立体の座屈を防ぐことができ、該鉄筋組立体が崩れるようなこともなく、安全に早く施工ができ、コスト削減にもなる。 Thus, in a reinforcing bar unit body that constructs a reinforcing bar assembly in a deep foundation shaft, a ladder is provided with a predetermined number of rod-shaped support receiving bars protruding from one side surface of a supporting body such as a mold material of a predetermined length at a predetermined interval. A strip with a circular arc and hooks formed at both ends is connected to the required number of inner and outer double loops, and shear reinforcement bars are arranged radially in a grid pattern on the ring strips. A plurality of ladder bars are arranged at predetermined positions of the reinforcing bar block body and the shear reinforcement bars, and each support receiving bar of the ladder bars and the reinforcing bar block body are arranged in predetermined stages. By the third solution means for supporting the number of steps, bundling or welding ,
Since an accurate rebar unit body has been constructed in advance, it is possible to construct a rebar assembly accurately by overlapping connection of the rebar unit bodies, and there is also a gamble between the wall surface in the deep foundation shaft and the rebar assembly. Since it can be set accurately and the rebar unit body can be accurately loaded without distortion, buckling of the rebar assembly can be prevented, and the rebar assembly can be safely and quickly constructed, It will also reduce costs.
また、鉄筋ユニット体の梯子筋により、従来の段取り筋使用による座屈崩壊もなく、さらに従来のように座屈崩壊防止のため、ブロックごとのコンクリート打設を行うことなく鉄筋組立体を一気に地上まで構築しても座屈による崩壊もなく、工期の短縮が図れる。In addition, due to the ladder bars of the reinforcing bar unit body, there is no buckling collapse due to the use of conventional setup bars, and in order to prevent buckling collapse as in the past, the reinforcing bar assembly can be grounded at once without performing concrete placement for each block. Even if it is constructed up to, it will not collapse due to buckling, and the construction period can be shortened.
さらに、梯子筋を上下で連結できるように連結体を設けているので、該梯子筋を重装して鉄筋組立体を構築するとき、該梯子筋を重装したときの傾きを連結体の厚さ若しくは間にプレートを挟み入れる等によって傾き調節ができ、また深礎立坑内に最初の段階の鉄筋構築で、その水平レベル調整を深礎立坑内の底面と該連結体で上記のように調整できるので、水平レベルを保ち鉄筋組立体が崩れるようなこともなく、正確に安定した鉄筋組立体が安全に早く施工ができ、さらに梯子筋の連結体を溶着して重装することで、鉄筋ユニット体が素早く重装構築できるので重装施工が容易となり、施工工期も短縮できる。
よって、本発明は、実用上著大な効果を奏する。 Further, since the connecting body is provided so that the ladder bars can be connected up and down, when constructing a reinforcing bar assembly by overlapping the ladder bars, the inclination when the ladder bars are mounted is determined by the thickness of the connecting body. Inclination can be adjusted by inserting a plate between them, or the first level of reinforcing bar construction in the deep foundation shaft, and the horizontal level adjustment is adjusted as described above with the bottom surface of the deep foundation shaft and the connecting body. It is possible to maintain a horizontal level and the rebar assembly does not collapse, and an accurate and stable rebar assembly can be constructed safely and quickly. Since the unit body can be quickly constructed with heavy equipment, heavy equipment construction is facilitated and the construction period can be shortened.
Therefore, the present invention has a remarkable effect in practice.
深礎立坑内に鉄筋組立体を構築する鉄筋構築施工法であって、円弧状で両端フック形状を有する帯筋を環状に連結すると共に該帯筋に剪断補強筋を径方向に格子状に配筋して鉄筋ブロック体を形成し、該鉄筋ブロック体を梯子筋の複数の各支持受け筋にそれぞれ結束又は溶着すると共に該帯筋及び剪断補強筋の所要位置に複数配置し、且つ該梯子筋は、予め位置出しされて配置される第一の行程と、
該鉄筋ユニット体を吊支体で吊支移送すると共に該深礎立坑内の壁面のガイド体に沿って移送降下させ、該ガイド体と鉄筋ユニット体を結束又は溶着する第二、第三の行程と、
前記移送降下により該鉄筋ユニット体の各梯子筋に重装固定すると共にその鉄筋ユニット体移送後、その後追いで作業用足場を順次、構設する第四、第五の行程と、
深礎立坑内に鉄筋ユニット体が構築された後、縦主筋を配置すると共にその縦主筋と鉄筋ユニット体を結束又は溶着する第六の行程で鉄筋組立体を構築する施工法と、
ガイド筋支持用刺し筋により深礎立坑内にガイド筋を立設支持するガイド体により鉄筋ユニット体の移送降下を案内ガイドして所定位置に降下、重装固定させて鉄筋組立体を構築する施工法と、
鉄筋組立体を構築するのに、帯筋及び剪断補強筋を有する鉄筋ブロック体を梯子筋に所定段数結束又は溶着した鉄筋ユニット体で構築することより、
時間を要する鉄筋組立体の構築を、鉄筋ユニット体として分割して地上で構築することで安全に、且つ容易に組立でき、施工工期の短縮を実現させた。This is a reinforcing bar construction method for building a reinforcing bar assembly in a deep foundation shaft, in which circular bars and hooks with hooks on both ends are connected in a ring, and shear reinforcement bars are radially arranged on the band bars in a grid pattern. Reinforcing bar to form a reinforcing bar block, and the reinforcing bar block is bound or welded to each of a plurality of support receiving bars of the ladder, and a plurality of the reinforcing bars are arranged at required positions of the band reinforcing bars and the shear reinforcing bars. Is a first step that is pre-positioned and arranged;
Second and third strokes in which the rebar unit body is suspended and transferred by a suspension support body and is transported and lowered along the guide body on the wall surface in the deep foundation shaft, and the guide body and the rebar unit body are bound or welded . When,
Fourth and fifth steps of constructing work scaffolds sequentially after the rebar unit body is transported and fixed to each ladder bar of the rebar unit body by the transport descent ,
After the rebar unit body is built in the deep foundation shaft, the construction method of constructing the rebar assembly in the sixth process of placing the vertical main bar and binding or welding the vertical main bar and the rebar unit body,
Construction that constructs a rebar assembly by guiding the transport descent of the rebar unit body to guide and lowering it to a predetermined position and fixing it with a guide body that supports and guides the guide bar in the deep foundation shaft by the stab bars for supporting the guide bars Law and
To construct a reinforcing bar assembly, constructing a reinforcing bar block body having band bars and shear reinforcing bars with a reinforcing bar unit body bonded or welded to a ladder bar with a predetermined number of steps,
By building a rebar assembly that requires time into a rebar unit and building it on the ground, it can be assembled safely and easily, and the construction period can be shortened.
本発明の実施例を図面に基づいて説明すると、図1において、1は鉄筋ユニット体で、該鉄筋ユニット体1は、深礎立坑2内に吊支体3で吊支移送され、該深礎立坑2内のガイド筋4に沿って移送降下して深礎立坑2内の底面から積み上げ構築される。 An embodiment of the present invention will be described with reference to the drawings. In FIG. 1,
そこで、上記深礎立坑2は、橋梁及び送電線鉄塔などの基礎として構築され、該深礎杭基礎は、図1に示すように、まず地盤を掘削して深礎立坑2を形成し、該深礎立坑2周壁面を土留め用コンクリート若しくはライナープレートなど防御壁5を構築すると共に該防御壁5の周壁に、鉄筋ユニット体1の移送下降を容易にするため上部端が外側に若干曲げられて形成されたガイド筋4,4,…を立設し、該ガイド筋4,4,…を支持するガイド筋用刺し筋6,6,…を防御壁5の周壁より突設させると共に地上から底面まで所定間隔で設けている。Therefore, the
また、鉄筋ユニット体1は、図2に示すように、深礎立坑径に対応した円弧状で両端フック形状を形成した帯筋7,7,…を環状に所定のラップ長で連結すると共に内外二重の環状に連結形成し、該環状の帯筋7,7,…に剪断補強筋8,8,…を上述同様所定のラップ長で連結すると共に径方向に格子状に配筋して鉄筋ブロック体9として形成すると共に後述する該鉄筋ブロック体9を両受け梯子筋10と片受け梯子筋11により複数段支持することで形成される。 In addition, as shown in FIG. 2, the reinforcing
そこで、両受け梯子筋10は、図3に示すように断面略コの字状の支持本体10aとその下端に板状の連結体12を設けると共に棒状の支持受け筋13,13,…を該支持本体10aの左右側に突出するようにその下部から所定間隔で六箇所設けている。なお、上述断面略コの字状は、角パイプ状などでも良く、特に形状には拘らない。 Therefore, as shown in FIG. 3, the two receiving ladder bars 10 are provided with a
また、片受け梯子筋11は、図4に示すように、断面略L字状の支持本体11aと下端に板状の連結体12aを設けると共に棒状で一方側に突出する支持受け筋14,14,…をその下部から所定間隔で六箇所設けている。なお、上述断面略L字状は、角パイプ状などでも良く、特に形状には拘らない。 Further, as shown in FIG. 4, the one-piece ladder muscle 11 is provided with a support body 11 a having a substantially L-shaped cross section and a plate-like connecting body 12 a at the lower end, and is supported in a bar shape and protrudes to one side. Are provided at predetermined intervals from the lower part thereof. The substantially L-shaped cross section may be a square pipe shape or the like, and is not particularly limited to the shape.
そして、該両受け梯子筋10は、図2に示すように、環状に構築された帯筋7,7,…の内外二重のその間であって、また図5に示すように帯筋7,7,…を支持受け筋13,13,…で支持受けすると共に剪断補強筋8,8,…の先端のフック部15,15,…で該帯筋7,7,…を掛止して、さらにクロスして重ねるように該剪断補強筋8,8,…を掛止支持受けし、結束又は溶着して構築される。
なお、図2に示す該両受け梯子筋10の配置は、八箇所それぞれ配設されているが特に配置数は限定されることなく鉄筋ユニット体1の環状径に対応して決められる。The receiving
In addition, although the arrangement | positioning of this both receiving
また、該片受け梯子筋11は、図2に示すように、剪断補強筋8,8,…が格子状にクロスした近傍の所定位置、図示では十二箇所配置し、また図6に示すように剪断補強筋8,8,…を支持受け筋14,14,…で支持受けすると共にその上にクロスして重ねるように剪断補強筋8,8,…を支持受けすると共に結束又は溶着して構築される。
なお、該片受け梯子筋11の配置位置と配置数は鉄筋ユニット体1の環状径に対応して決められる。Further, as shown in FIG. 2, the one-piece ladder bars 11 are arranged at predetermined positions in the vicinity where the
In addition, the arrangement position and the number of arrangement of the piece receiving ladder bars 11 are determined corresponding to the annular diameter of the reinforcing
そして、上述両受け梯子筋10または片受け梯子筋11であって、その所定段の支持受け筋13または該支持受け筋14に、帯筋7,7,…と剪断補強筋8,8,…が支持受けされて一段の鉄筋ブロック体9として形成される。Then, a ladder muscle 11 receives
なお、上述のように円弧状の帯筋7,7,…と直線状の剪断補強筋8,8,…には、それぞれ先端側にフック部15,15が形成され、該フック部15,15の部分で所定の重なりのラップ長で連結されて、それぞれ所定の環径又は長さに連結形成される。As described above, hook portions 15 and 15 are formed on the distal ends of the arc-shaped
しかして、鉄筋ユニット体1として構築する手順において、図7に示すように、該鉄筋ユニット体1が所定形状となるように、予め仮組治具16,16,…を所定位置に配置固定すると共に両受け梯子筋10,10,…及び片受け梯子筋11,11,…もそれぞれ所定位置に移送可能に配置する。 Thus, in the procedure for constructing the reinforcing
そこで、仮組治具16は、図8に示すように、横断面略T字状の支柱本体17とその下部に支柱保持ベース18を形成し、該支柱保持ベース18で立設支持された支柱本体17の前面側に、回動支持体19,19,…を上述支持受け筋13,14と同様の間隔と配置数を持って回動可能に枢着突設され、また該回動支持体19,19,…は、その突出部分の上部側に凹状の支持受け部20を形成すると共に水平から後方へ反転可能に支持され、なお図中21は、各回動支持体19,19,…の回動止めのストッパー21である。 Therefore, as shown in FIG. 8, the temporary assembly jig 16 includes a column main body 17 having a substantially T-shaped cross section and a
そして、上述仮組治具16,16,…は、鉄筋ユニット体1として構築されるその外径より外側の所定位置に予め固定して配設し、また両受け梯子筋10,10,…は、その二重の環状の中間位置で移動可能に配置され、そして片受け梯子筋11,11,…も、環状の内側の所定位置にそれぞれ移動可能に配置すると共にそれぞれその配置状態で、円弧状の帯筋7,7,…を該仮組治具16,16,…の回動支持体19,19,…で仮受け支持させ、また両受け梯子筋10,10,…の支持受け筋13,13,…では支持させると共に該支持受け筋13,13,…に結束または溶着して所定のラップ長で連結してそれぞれ環状に形成し、また二重に形成される内側の環状に配置する該帯筋7,7,…も同様に該支持受け筋13,13,…に結束または溶着して内外二重の環状として形成する。 The above temporary assembly jig 16, 16, ..., from the outer diameter to be constructed as a
また、剪断補強筋8,8,…は、図6及び図7に示すように、上記環状径に合わせて所定のラップ長で直線状に連結し、その両端部のフック部15,15は該環状に形成された外側の帯筋7に掛止させて所定の格子状に配設すると共に片受け梯子筋11,11,…の支持受け筋14,14,…で支持受させて結束または溶着し、該環状の帯筋7と剪断補強筋8,8,…にて鉄筋ブロック体9として構築し、また該鉄筋ブロック体9を、それぞれ仮組治具16,16,…にも支持させると共に両受け梯子筋10,10,…及び片受け梯子筋11,11,…に所定の六段分支持させて溶着又は結束して鉄筋ユニット体1を構築している。Further, the
しかして、図1に示すように、地上に構築された鉄筋ユニット体1を、吊支体3を介してクレーン22などで吊支移送すると共に深礎立坑2内に降下させて、深礎立坑2の底面より該鉄筋ユニット体1を積み上げ構築して鉄筋組立体23として構築する。As shown in FIG. 1, the
そこでその移送に於いて、図7に示すように、吊支体3は、角パイプなどで、例えば平面八角形状に形成される吊り枠体3aと直線状の直線吊支枠3bを有し、該吊支体3をクレーン22等で吊支移送するが、該吊支体3は、図7及び図9に示すように、移送治具体24を所定位置に垂下状に設けている。Therefore, in the transfer, as shown in FIG. 7, the
該移送治具体24は、図9及び図10に示すように、縦長の支持本体25に帯筋7,7,…と同位置に支持金具26,26,…を回動可能に、図示ではそれぞれ六ヶ所枢着配置し、該支持金具26は、図10に示すように、支持本体25の前面側より回動可能に突設させ、且つその突出部分の上部側に凹状の支持受け部27を形成すると共に水平から後方へ反転可能に枢着され、また該支持金具26に帯筋7を保持する押さえ保持金具28を回動可能に枢着している。該移oct Specifically 24, as shown in FIGS. 9 and 10,
なお、図7に図示する直線状の直線吊支枠3bに垂下支持されている移送治具体24は、上述と同様のもので、且つ同様に作用することから、特に配置位置を図7に示すことで、特に、説明は省略し、また、図中29,30は、支持金具26及び押さえ保持金具28の回動止めのストッパー29,30である。In addition, since the
そして、上述したように地上で構築された鉄筋ユニット体1を、吊支体3にて移送するとき、まず、図9に示すように、吊支体3に設けられた移送治具体24を、環状の帯筋7,7,…の内側に降下させ、その時、支持金具26,26,…及び押さえ保持金具28,28,…が該帯筋7,7,…に当接すると共に後方に反転状に揺動しながら、帯筋7,7,…をやり過ごし、図中矢視で示すように最下段まで下降させる。And when transferring the
そして、その下まで降下させた時、図10に示すように支持金具26が回動状に後方から揺動して元の水平位置に戻り、静止したとき若干、吊支体3を持ち上げることで、図示のように帯筋7を支持受けし、そして押さえ保持金具28を回動させて該帯筋7を押さえ保持し、回動止めのストッパー29,30で止め、該帯筋7が保持されることで、鉄筋ユニット体1が移送治具体24に保持され、吊支体3にて移送可能となる。 Then, when lowered to the bottom, as shown in FIG. 10, the
また、該仮組治具16,16,…から移送治具体24,24,…に移載される状況は、鉄筋ユニット体1を吊支移送する時、吊支体3で鉄筋ユニット体1を吊り上げると、該鉄筋ユニット体1の帯筋7,7,…が、上述仮組治具16,16,…の回動支持体19,19,…の下側から当接押し上げ、水平から後方へ反転することで、仮組治具16,16,…から離れ、移送治具体24,24,…に移載吊支される。Further, the situation where the temporary assembly jigs 16, 16,... Are transferred to the
なお、上述した支持金具26,26,…及び押さえ保持金具28,28,…で、帯筋7,7,…を押さえ保持した状態で該鉄筋ユニット体1を吊支移送するが、仮組治具16,16,…は、該鉄筋ユニット体1を移送治具体24に移載された後、そのまま残された状態で立設している。 The
そして、図1に示すように、吊支体3で鉄筋ユニット体1を深礎立坑2内に移送し、該鉄筋ユニット体1の帯筋7,7,…がガイド筋4,4,…に沿うように降下させる。
なお、最初の一段目は、該深礎立坑2内の底面に載置すると共に鉄筋ユニット体1の水平レベルを設定するため、トランシットなどの計測器で正確に計測して、該鉄筋ユニット体1の両受け梯子筋10,10,…及び片受け梯子筋11,11,…の連結体12,12aで、底面との高さ調節を底上げ用の板状のものを介し又は連結体12,12aの厚さを代えて高さを調節して水平レベルを設定する。Then, as shown in FIG. 1, the reinforcing
The first stage is placed on the bottom surface of the
そして、図11に示すように、鉄筋ユニット体1の両受け梯子筋10,10,…及び片受け梯子筋11,11,…の連結体12,12aを二段重装して各溶着固定すると共にガイド筋4,4,…と帯筋7,7,…も溶着固定した後、一段目の作業用足場31を構設し、そしてさらに次の鉄筋ユニット体1を重装構築するとき、作業員はその鉄筋ユニット体1を地上で構築し、そしてそれを降下させた後に、その一段目の作業用足場31まで降りてきて、該鉄筋ユニット体1の両受け梯子筋10,10,…及び片受け梯子筋11,11,…の上部と、該連結体12,12aを重装させると共に位置出しと水平レベル出しを行なった後、溶着固定する。 As shown in FIG. 11, the two receiving ladder bars 10, 10,... Of the reinforcing
以上のように、鉄筋ユニット体1を構築、移送、重装固定を繰り返し、地上まで該鉄筋ユニット体1を積み上げ構築した後、図12に示すように、最後に深礎立坑2内の所定の帯筋7,7,…に縦主筋32,32,…を挿入して底面から立設させると共に該帯筋7,7,…に溶着又は結束して鉄筋組立体23を構築する。
その構築完了後、深礎立坑2内にコンクリートを打設して、深礎杭基礎が完成する。As described above, after the
After the construction is completed, concrete is cast in the
なお、第三の行程で一気に地上まで組み上げ、鉄筋組立体23を構築後、最後にまとめてコンクリート打設する実施例を示しているが、鉄筋施工の途中でコンクリート打設の実施をする事については、深礎杭の規模と近隣の生コン業者の製造能力に応じて適宜変更、実施される。 In addition, although the example which assembles to the ground at a stretch in the 3rd process, constructs the reinforcing bar assembly 23 and puts concrete at the end is shown, it is about performing concrete placing in the middle of reinforcing bar construction Will be changed and implemented as appropriate depending on the scale of the deep foundation pile and the manufacturing capacity of the nearby ready-mixed concrete contractors.
また、吊支体3の移送治具体24で移送しているが、吊支体3の吊り枠体3aで直接、両受け梯子筋10,10,…及び片受け梯子筋11,11,…を吊支して移送しても良いが、特に図示は省略した。 Moreover, although it has transferred with the transfer jig |
さらに、深礎杭基礎が構築される場所の自然環境及び施工仕様によって、本発明で使用される各部材は、大きく左右されるので、各部材の形状、使用数などは、適宜設計変更される。 Furthermore, since each member used in the present invention greatly depends on the natural environment and construction specifications of the place where the deep foundation pile foundation is constructed, the shape, number of use, etc. of each member are appropriately changed in design. .
本発明は、橋梁及び送電線鉄塔などを構築する場合の深礎杭基礎用に使用する鉄筋組立体の構築施工及び鉄筋組立体を構成する鉄筋ユニット体とその移送に利用することができる。 INDUSTRIAL APPLICABILITY The present invention can be used for building construction of a reinforcing bar assembly used for a foundation pile foundation when building a bridge, a transmission line tower, and the like, and a reinforcing bar unit body constituting the reinforcing bar assembly and its transfer.
1 鉄筋ユニット体
2 深礎立坑
3 吊支体
4 ガイド筋
7 帯筋
8 剪断補強筋
9 鉄筋ブロック体
10 両受け梯子筋
11 片受け梯子筋
12,12a 連結体
13,14 支持受け筋
15 フック部
16 仮組治具
19 回動支持体
23 鉄筋組立体
24 移送治具体
26 支持金具
31 作業用足場
32 縦主筋DESCRIPTION OF
Claims (7)
該深礎立坑壁面の所要位置に、ガイド体を所要本数少なくとも壁面より立設支持させ、該鉄筋ユニット体を吊支体で深礎立坑に吊支移送すると共に該ガイド体に沿って深礎立坑内の所定位置まで移送降下させて、該鉄筋ユニット体をガイド体に結束又は溶着する第二の行程と、
移送された該鉄筋ユニット体の各梯子筋同士を重装溶着すると共にその重装溶着後、後追いで作業用足場を鉄筋ユニット体構築と共に順次構設する第三の行程と、
深礎立坑内に所定の鉄筋ユニット体が構築された後、縦主筋を該鉄筋ユニット体の各所要位置にそれぞれ配設すると共にその縦主筋と鉄筋ユニット体を結束又は溶着して鉄筋組立体として構築することを特徴とした深礎杭の鉄筋構築施工法。In a reinforcing bar construction method for constructing a reinforcing bar assembly in a deep foundation shaft excavated for foundation by excavating a foundation deep foundation shaft in the ground, an arc-shaped double-sided hook with internal and external double A reinforcing bar block body formed by connecting and forming a desired number of annular reinforcing bars in a grid pattern in the radial direction on the annular band bars, and supporting or binding and supporting the reinforcing bar block bodies. Reinforcing bars are provided with a predetermined number of steps on the ladder bars, and a reinforcing bar block body is bound or welded to the supporting receiving bars to form a reinforcing bar unit body. The ladder bars are arranged in an annular band and shear reinforcement bars. The ladder bars and / or temporary assembly jigs are pre-positioned to construct a reinforcing bar unit body on the ground so that a plurality of the reinforcing bar block bodies are accurately formed in a predetermined shape. The first step to do
At least the required number of guide bodies are erected and supported from the wall surface at the required position on the wall surface of the deep foundation shaft, and the rebar unit body is suspended and transferred to the deep foundation shaft by the suspension support body, and the deep foundation shaft along the guide body. A second step of transferring and lowering the reinforcing bar unit body to a predetermined position, and binding or welding the reinforcing bar unit body to the guide body;
A third step of sequentially welding the ladder bars of the transferred reinforcing bar unit body together with the reinforcing bar unit body construction in succession after the heavy welding,
After a certain reinforcing bar unit body is built in the deep foundation shaft, the longitudinal main bars are arranged at the required positions of the reinforcing bar unit bodies, and the longitudinal main bars and the reinforcing bar unit bodies are bound or welded to form a reinforcing bar assembly. Reinforcement construction method of deep foundation pile characterized by construction.
また梯子筋の支持受け筋を所定間隔で所要段数設け、該支持受け筋に上記鉄筋ブロック体を結束又は溶着支持すると共に該梯子筋の配設を鉄筋ブロック体の該帯筋及び剪断補強筋の所要位置にそれぞれ複数配設して結束又は溶着したことを特徴とする鉄筋ユニット体。In a reinforcing bar unit body that constructs a reinforcing bar assembly in a deep foundation shaft, an arc-shaped and double-ended hook shape is connected to the inner and outer double rings in the required number, and shear reinforcing bars are connected to the annular band bars. Reinforcing bar block body formed by arranging the bars in a grid pattern in the radial direction,
In addition, a required number of support bars for the ladder bars are provided at a predetermined interval, and the reinforcing bar block body is bound or welded and supported on the support bar, and the ladder bars are arranged for the band bars and the shear reinforcement bars of the reinforcing bar block body. A reinforcing bar unit having a plurality of pieces arranged at a required position and bound or welded.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009034505A JP4385236B1 (en) | 2009-01-24 | 2009-01-24 | Reinforcement construction method for deep pile and its reinforcing bar unit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2009034505A JP4385236B1 (en) | 2009-01-24 | 2009-01-24 | Reinforcement construction method for deep pile and its reinforcing bar unit |
Publications (2)
Publication Number | Publication Date |
---|---|
JP4385236B1 JP4385236B1 (en) | 2009-12-16 |
JP2010168879A true JP2010168879A (en) | 2010-08-05 |
Family
ID=41549796
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2009034505A Active JP4385236B1 (en) | 2009-01-24 | 2009-01-24 | Reinforcement construction method for deep pile and its reinforcing bar unit |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4385236B1 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4883462B1 (en) * | 2011-08-22 | 2012-02-22 | 昌之 宗清 | Reinforcement construction method for deep foundation piles and ladder reinforcement of the reinforcing bar unit. |
JP5527750B1 (en) * | 2013-03-01 | 2014-06-25 | 山本建設 株式会社 | Suspension frame connecting bracket combined use hanging bracket |
JP2017186863A (en) * | 2016-04-07 | 2017-10-12 | 東海メタル株式会社 | Movable jig |
CN109183964A (en) * | 2018-09-05 | 2019-01-11 | 中铁贵州工程有限公司 | A kind of storage pond construction method |
CN109183965A (en) * | 2018-09-05 | 2019-01-11 | 中铁贵州工程有限公司 | A kind of storage pond construction technology |
JP2022054519A (en) * | 2020-09-28 | 2022-04-07 | 東急建設株式会社 | Reinforcing bar unit and reinforcing bar assembly method |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113738120B (en) * | 2021-10-11 | 2022-07-29 | 北京好运达智创科技有限公司 | Portable reinforcement device |
-
2009
- 2009-01-24 JP JP2009034505A patent/JP4385236B1/en active Active
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4883462B1 (en) * | 2011-08-22 | 2012-02-22 | 昌之 宗清 | Reinforcement construction method for deep foundation piles and ladder reinforcement of the reinforcing bar unit. |
JP5527750B1 (en) * | 2013-03-01 | 2014-06-25 | 山本建設 株式会社 | Suspension frame connecting bracket combined use hanging bracket |
JP2014169181A (en) * | 2013-03-01 | 2014-09-18 | Yamamoto Kensetsu Co Ltd | Connection hanging bracket used also as hanging frame connection bracket |
JP2017186863A (en) * | 2016-04-07 | 2017-10-12 | 東海メタル株式会社 | Movable jig |
CN109183964A (en) * | 2018-09-05 | 2019-01-11 | 中铁贵州工程有限公司 | A kind of storage pond construction method |
CN109183965A (en) * | 2018-09-05 | 2019-01-11 | 中铁贵州工程有限公司 | A kind of storage pond construction technology |
JP2022054519A (en) * | 2020-09-28 | 2022-04-07 | 東急建設株式会社 | Reinforcing bar unit and reinforcing bar assembly method |
JP7053750B1 (en) | 2020-09-28 | 2022-04-12 | 東急建設株式会社 | Reinforcing bar unit and rebar assembly method |
Also Published As
Publication number | Publication date |
---|---|
JP4385236B1 (en) | 2009-12-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4385236B1 (en) | Reinforcement construction method for deep pile and its reinforcing bar unit | |
CN105756356B (en) | A kind of steel pipe column casing mounting and adjusting alignment methods | |
CN110629932B (en) | High-rise steel pipe concrete composite column construction method | |
JP4883462B1 (en) | Reinforcement construction method for deep foundation piles and ladder reinforcement of the reinforcing bar unit. | |
CN105649348B (en) | A kind of steel pipe column casing handling installation method | |
CN110778116B (en) | Construction method of complex curved surface giant concrete beam tube structure | |
JP2012036584A (en) | Arrangement method of reinforced concrete column | |
CN103866982B (en) | A kind of petal art framework construction method | |
JP5453172B2 (en) | Floor reinforcement arrangement method | |
CN106836948B (en) | A kind of construction technology of reinforced concrete structure | |
JP6871728B2 (en) | Prefabricated structure | |
CN110080455A (en) | A kind of precast shear wall, connecting node and its construction method | |
JP6431232B1 (en) | Rebar assembly method | |
CN112663636B (en) | Non-panel reinforced soil ecological slope protection system and construction method thereof | |
CN112195913B (en) | Positioning device for reinforcement cage in mountain construction process and construction method thereof | |
CN105604248B (en) | A kind of steel pipe column casing docking protection welding method of steel pipe column | |
CN211142831U (en) | Suspension bridge anchorage front anchor chamber top cover plate | |
CN211499464U (en) | Steel pipe concrete composite column for high-rise building and reinforcing system thereof | |
CN110593124A (en) | Suspension bridge anchorage front anchor chamber top cover plate and construction method thereof | |
CN210530854U (en) | Assembled steel reinforcement cage for rapid lining of tunnel | |
JP4017143B2 (en) | Shaft rebar assembly method and assembly apparatus | |
CN204401648U (en) | Circular Pit inwall reinforcing cage binding stand | |
CN105178594B (en) | A kind of hollow column template and its construction method for exempting from scaffold construction | |
CN113005910B (en) | Construction method of adjustable cable saddle integral high-precision positioning structure | |
CN110821040B (en) | Steel ladle beam supporting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20090318 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20090318 |
|
A975 | Report on accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A971005 Effective date: 20090507 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090519 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090615 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20090908 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20090914 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4385236 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20181009 Year of fee payment: 9 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313113 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313113 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |