JP2009503294A - Tunnel construction method - Google Patents

Tunnel construction method Download PDF

Info

Publication number
JP2009503294A
JP2009503294A JP2008523536A JP2008523536A JP2009503294A JP 2009503294 A JP2009503294 A JP 2009503294A JP 2008523536 A JP2008523536 A JP 2008523536A JP 2008523536 A JP2008523536 A JP 2008523536A JP 2009503294 A JP2009503294 A JP 2009503294A
Authority
JP
Japan
Prior art keywords
tunnel
roof
mountain
lock block
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2008523536A
Other languages
Japanese (ja)
Inventor
ユーガー,モアデチャイ
リーベルマン,シュロモ
Original Assignee
ネイアマン,オファ
ボッザー,ハシダ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ネイアマン,オファ, ボッザー,ハシダ filed Critical ネイアマン,オファ
Publication of JP2009503294A publication Critical patent/JP2009503294A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

山又は丘(12)の斜面(10)のハーフトンネルの区域を建設する方法を提供し、掘削されるハーフトンネルの上端部の上方で前記区域(16)に沿ってロックブロック(18)を形成する段階と、前記ロックブロックを横切ってロックエレメントを挿入し、前記山に伸ばす段階と、前記ロックブロックの向こう且つ下方の前記山の部分に穴を掘り、前記ハーフトンネルの屋根部分と底部分を画定する段階と、前記ハーフトンネルの全区域が形成されるまで前記掘削処理を繰り返す段階とを備えている。  Providing a method of constructing a half-tunnel area on the slope (10) of a mountain or hill (12), forming a rock block (18) along said area (16) above the upper end of the excavated half-tunnel Inserting a locking element across the lock block and extending it into the mountain; digging a hole in the mountain part beyond and below the lock block; Defining and repeating the excavation process until the entire area of the half tunnel is formed.

Description

本発明は、トンネルの建設に関し、特に、典型的には丘陵の斜面や山腹の土にハーフトンネルを建設又は広げる方法に関する。   The present invention relates to the construction of tunnels, and more particularly to a method of constructing or spreading a half-tunnel, typically on a hillside or mountainside soil.

山又は丘の斜面に沿って道路を造ったり又は広げたりする場合には、とりわけ、森林を含む環境に引き起こされる損害に関して、重大な問題があり、当業者に周知で理解されるように、不安定性及び地すべりを引き起こすことがある。その問題を克服するために、ハーフトンネルの建造が開発されているが、ここまでは、少なくとも、そのようなハーフトンネルの屋根を支持する必要性の実質面から、最善の解決策が提供されていない。図1に示されているように、標準のトンネル2が建設される時、矢印F,Fで示される2つの対向する圧縮力がトンネルの屋根に発生し、この力は釣り合っている。したがって、トンネルが掘削される地盤のタイプにより、強化する土壌くぎ6を地盤に挿入することが要求されることがある。そのようなくぎ6が使用される時、図示のようにそれらはアーチ形のトンネルの屋根に関して放射状に地盤に挿入される。そのため、ハーフトンネルはその屋根で中央の対向する力を有していないから、トンネル建設の上述した方法は適用できない。使用される明らかな解決策はトンネルの基礎、例えば道路と屋根の間に延びる圧縮材又は柱の形式で屋根の自由端を支持することである。そのような支持柱の不利益は直ちに明らかである。 When building or extending roads along mountain or hillsides, there are significant problems, particularly with respect to damage caused to the environment, including forests, as anxiety is well known and understood by those skilled in the art. May cause qualitative and landslides. To overcome that problem, construction of half-tunnels has been developed, but so far the best solution has been provided, at least in real terms of the need to support the roof of such a half-tunnel. Absent. As shown in FIG. 1, when the standard of the tunnel 2 will be constructed, arrow F, compressive force two opposite represented by F 1 is generated on the roof of the tunnel, this force is balanced. Therefore, depending on the type of ground from which the tunnel is excavated, it may be required to insert a strengthening soil nail 6 into the ground. When such nails 6 are used, they are inserted radially into the ground with respect to the arched tunnel roof as shown. Therefore, since the half tunnel does not have a central opposing force on its roof, the above-described method of tunnel construction cannot be applied. The obvious solution used is to support the free end of the roof in the form of a tunnel foundation, for example a compression or a column extending between the road and the roof. The disadvantage of such support pillars is immediately obvious.

そのため、従来技術のハーフトンネル建設の不利益を克服すると共に、トンネルの開放側に支持柱を有しないハーフトンネルの建設方法を提供することを本発明の主要な目的とする。   Therefore, the main object of the present invention is to provide a half tunnel construction method that overcomes the disadvantages of the prior art half tunnel construction and does not have a support column on the open side of the tunnel.

屋根の上方の地盤に挿入されるロックエレメントにより屋根が確実に支持されるハーフトンネルの建設方法を提供することを本発明のさらなる目的とする。   It is a further object of the present invention to provide a method for constructing a half tunnel in which the roof is securely supported by a locking element inserted into the ground above the roof.

本発明は、山又は丘の斜面にハーフトンネルの区域を建設する方法を提供し、a)掘削されるハーフトンネルの上端部の上方で前記区域に沿ってロックブロックを形成する段階と、b)前記ロックブロックを横切ってロックエレメントを挿入し、前記山に伸ばす段階と、c)前記ロックブロックの向こう且つ下方の前記山の部分を掘削し、前記ハーフトンネルの屋根部分と底部分を画定する段階と、d)前記ハーフトンネルの全区域が形成されるまで段階c)を繰り返す段階とを備えている。   The present invention provides a method for constructing an area of a half tunnel on a slope of a mountain or hill, a) forming a lock block along the area above the upper end of the excavated half tunnel; b) Inserting a locking element across the lock block and extending it to the mountain; c) excavating the mountain portion beyond and below the lock block to define a roof portion and a bottom portion of the half tunnel. And d) repeating step c) until the entire area of the half tunnel is formed.

本発明はより十分に理解されるように以下の例示する図面を参照しつつ好適な実施例に関連させて説明されるだろう。   The present invention will be described in connection with a preferred embodiment with reference to the following illustrative drawings so that it may be more fully understood.

詳細に図面を参照すると、詳細な説明は本発明の好適な実施例の例示のためだけに示され、本発明の原理及び概念の説明を最も有用且つ容易に理解されるものと信じられているものを提供するために示される。この点に関しては、本発明の基本的な理解のために必要とされるものより詳細に本発明の構造の詳細を示すためになされるものではなく、図面と共に詳細な説明は本発明の幾つかの方法が実際にどのように具現化されるのかを当業者に明確にさせるためにある。   DETAILED DESCRIPTION Referring to the drawings in detail, the detailed description is set forth only for the purpose of illustrating a preferred embodiment of the invention and is believed to be the most useful and easily understood explanation of the principles and concepts of the invention. Shown to provide things. This is not to be construed as showing details of the structure of the present invention in more detail than is required for a basic understanding of the present invention. This is to make it clear to those skilled in the art how this method is actually implemented.

本発明による山又は丘の斜面にトンネルの区域を建設する方法は、建設段階に関連させて説明される。第1段階は図2に示されており、丘又は山12の斜面10を示している。平地14、例えば建設されるトンネル区域の道路からの高さhを決定した後、例えば、L形状の凹所が形成され、ロックブロック18が凹所16の基部20に配置される。ロックブロック18はプリズム体が都合良く、例えば、組み立て式鉄筋コンクリートスラブである。代わりに、そのような鉄筋コンクリートロックブロックが自然位で配置されてもよい。ロックエレメント22は、典型的には特別丈夫な土壌くぎ又は圧縮応力を与えられたアンカーであり、その後、ロックブロック18により丘又は山12の斜面に打ち込み又は穴をあけられる。ロックエレメント22は支持するために掘り起こされるトンネルの幅の上方に十分延びるように計画された実際の長さを有している。また、図面に見られるように、ロックエレメントはロックブロック18の平面に関して斜面10の通常の角度より僅かに小さい角度から90°より僅かに大きい角度までの異なる角度で扇形に広がっている。これらのロックエレメント22は釣り合いを保つために掘削されるハーフトンネルを釣り合わせるために必要な要求圧縮力を供給し、図1に示されているように、標準トンネルが建設されている時、この圧縮力は通常「対向するハーフトンネル」により供給される。   The method of constructing a tunnel area on the slope of a mountain or hill according to the present invention will be described in connection with the construction phase. The first stage is shown in FIG. 2 and shows the slope 10 of the hill or mountain 12. After determining the height h from the road in the flat ground 14, for example the tunnel area to be constructed, for example, an L-shaped recess is formed, and the lock block 18 is arranged at the base 20 of the recess 16. The lock block 18 is conveniently a prism body, for example, an assembled reinforced concrete slab. Alternatively, such a reinforced concrete lock block may be placed in a natural position. The lock element 22 is typically a special strong soil nail or compressively stressed anchor, which is then driven or drilled into the slope of the hill or mountain 12 by the lock block 18. The locking element 22 has an actual length that is designed to extend well above the width of the tunnel that is dug up to support it. Also, as can be seen in the drawing, the locking elements fan out at different angles with respect to the plane of the locking block 18 from slightly less than the normal angle of the ramp 10 to slightly greater than 90 °. These locking elements 22 provide the required compressive force required to balance the half tunnels that are excavated to maintain balance, and this is shown when a standard tunnel is being constructed as shown in FIG. The compressive force is usually supplied by “opposing half tunnels”.

ハーフトンネルが形成される丘又は山12の斜面10の地盤は破砕された又は風雨にさらされた石、代わりの土等のような不安定な材料から構成されており、硬化薬品又は土壌強化材料の注入、又はさらに別の手段のような公知の技術により、格子状パターンのアンカー又は土壌くぎを打ち込むことにより、地盤を最初に安定させることが推奨される。   The ground on the slope 10 of the hill or mountain 12 where the half tunnel is formed is composed of unstable materials such as crushed or weathered stones, alternative soils, etc., hardened chemicals or soil strengthening materials It is recommended to stabilize the ground first by driving in a grid pattern anchor or soil nail by known techniques such as injection or other means.

計画されたハーフトンネルの上方の地面がロックブロック18及びロックエレメント22により一旦固められると、矢印Eにより示されるように頂部から底部へのハーフトンネルの掘削は図3に示されているように開始可能である。屋根部分24が形成される時、地盤のタイプにより、ロックエレメント22の方向を横切る土壌くぎ26が付加されてもよく、ハーフトンネルの上方の強化格子を形成する。ショットクリート28は土壌くぎ26の挿入の前又は後に屋根に塗られてもよい。図4に見られるように、この掘削処理及びその後のハーフトンネルの屋根を覆いながら土壌くぎの挿入は全体のハーフトンネルが掘削され、形成されるまで繰り返される。その後、ショットクリート28は適当な外装材により覆われ、ハーフトンネルの屋根により大きな強度を与えることができる。   Once the ground above the planned half-tunnel is solidified by the lock block 18 and the lock element 22, excavation of the half-tunnel from top to bottom as shown by arrow E begins as shown in FIG. Is possible. When the roof portion 24 is formed, depending on the type of ground, a soil nail 26 across the direction of the lock element 22 may be added, forming a reinforced grid above the half tunnel. The shot cleat 28 may be applied to the roof before or after insertion of the soil nail 26. As can be seen in FIG. 4, this excavation process and subsequent insertion of the soil nails while covering the roof of the half tunnel is repeated until the entire half tunnel is excavated and formed. Thereafter, the shot cleat 28 is covered with a suitable exterior material, and the half-tunnel roof can be provided with greater strength.

図5を参照すると、山12の斜面10に形成された拡張道路30を構成するハーフトンネルが見られる。岩石の落下の危険や土が滑り落ちる可能性がある場合、庇状の突出物32がロックブロック18の前部に取り付けられ、突出物32は異なる形状をしていてもよい。それは落下する岩石が道路30を越えて斜面10の他の部分34へ移動し続けるよう誘導するように構成され、及び又は滑って落下する土や岩石を保有可能な樋として構成されてもよい。   Referring to FIG. 5, the half tunnel constituting the extended road 30 formed on the slope 10 of the mountain 12 can be seen. If there is a risk of falling rocks or there is a possibility that the soil will slide down, a hook-like protrusion 32 is attached to the front part of the lock block 18, and the protrusion 32 may have a different shape. It may be configured to guide the falling rock to continue to move across the road 30 to the other portion 34 of the slope 10 and / or may be configured as a cage capable of holding soil and rock falling down.

本発明は上記した詳細な実施例に限定されるものではなく、本発明はその精神又は本質的特性から逸脱することなく他の特定の形式で具体化されてもよいことは当業者にとって明らかであろう。そのため、本発明はすべての点において例示としてであり制限的でないと考えられ、本発明の範囲は上述した説明よりむしろ添付した請求項により示され、そのため、請求項と同等の意味及び範囲内にあるすべての変形がそこに包含されることを意図している。   It will be apparent to those skilled in the art that the present invention is not limited to the detailed embodiments described above and that the present invention may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. I will. Thus, the present invention is considered in all respects to be illustrative and not restrictive, and the scope of the present invention is defined by the appended claims rather than the foregoing description, and thus, within the meaning and scope equivalent to the claims. All certain variations are intended to be included therein.

(従来例)標準のトンネル建設の概略図である。(Conventional example) Schematic of standard tunnel construction. 本発明によるハーフトンネル建設方法の第1段階の概略断面図である。It is a schematic sectional drawing of the 1st step of the half tunnel construction method by this invention. 本発明によるハーフトンネルの建設方法の第2段階の概略断面図である。It is a schematic sectional drawing of the 2nd step of the construction method of the half tunnel by this invention. 本発明によるハーフトンネルの建設方法の第3段階の概略断面図である。It is a schematic sectional drawing of the 3rd step of the construction method of the half tunnel by this invention. 本発明によるハーフトンネルの建設方法の第4段階の概略断面図であり、岩石の落下保護をさらに有している。FIG. 6 is a schematic cross-sectional view of the fourth stage of the half tunnel construction method according to the present invention, further comprising rock fall protection.

Claims (8)

山又は丘の斜面にハーフトンネルの区域を建設する方法であって、
a)掘削されるハーフトンネルの上端部の上方で前記区域に沿ってロックブロックを形成する段階と、
b)前記ロックブロックを横切ってロックエレメントを挿入し、前記山に伸ばす段階と、
c)前記ロックブロックの向こう且つ下方の前記山の部分を掘削し、前記ハーフトンネルの屋根部分と底部分を画定する段階と、
d)前記ハーフトンネルの全区域が形成されるまで段階c)を繰り返す段階と、
を備えていることを特徴とする方法。
A method of constructing a half-tunnel area on the slope of a mountain or hill,
a) forming a lock block along said area above the upper end of the half tunnel to be excavated;
b) inserting a locking element across the locking block and extending it into the pile;
c) excavating the portion of the mountain beyond and below the lock block to define a roof portion and a bottom portion of the half tunnel;
d) repeating step c) until the entire area of the half tunnel is formed;
A method characterized by comprising:
掘削される前記ハーフトンネルの上端部の上方の斜面に凹所を形成する段階をさらに備えている請求項1に記載の方法。   The method according to claim 1, further comprising forming a recess in a slope above the upper end of the half tunnel to be excavated. 前記ハーフトンネルの屋根に実質的に垂直な方向に延びる前記屋根部分に土壌くぎを挿入することをさらに備えている請求項1に記載の方法。   The method of claim 1, further comprising inserting a soil nail into the roof portion that extends in a direction substantially perpendicular to the roof of the half tunnel. 前記段階c)の後に前記屋根部分にショットクリートを塗る段階をさらに備えている請求項1に記載の方法。   The method of claim 1, further comprising applying shot cleats to the roof portion after step c). 前記段階d)の後に前記ハーフトンネルの全区域の屋根にショットクリートを塗る段階をさらに備えている請求項1に記載の方法。   The method of claim 1, further comprising the step of applying shotcrete to the roof of the entire area of the half tunnel after step d). 前記段階a)の前又は後に、硬化可能薬品又は土壌強化材料を注入し、又は格子状パターンのアンカー又は土壌くぎを打ち込む段階をさらに備えている請求項1に記載の方法。   The method according to claim 1, further comprising the step of injecting hardenable chemicals or soil strengthening materials or driving in a grid pattern of anchors or soil nails before or after said step a). 前記ハーフトンネルの屋根に外装材をつける段階をさらに備えている請求項1に記載の方法。   The method of claim 1, further comprising attaching an exterior material to the roof of the half tunnel. 前記ロックブロックの露出面に突出部を取り付け、落下する土と岩石を保護することをさらに備えている請求項1に記載の方法。   The method of claim 1, further comprising attaching a protrusion to an exposed surface of the lock block to protect falling soil and rock.
JP2008523536A 2005-07-26 2006-07-26 Tunnel construction method Pending JP2009503294A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
IL169878A IL169878A (en) 2005-07-26 2005-07-26 Method for tunnel construction
PCT/IL2006/000867 WO2007013074A1 (en) 2005-07-26 2006-07-26 A method for tunnel construction

Publications (1)

Publication Number Publication Date
JP2009503294A true JP2009503294A (en) 2009-01-29

Family

ID=37229059

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008523536A Pending JP2009503294A (en) 2005-07-26 2006-07-26 Tunnel construction method

Country Status (8)

Country Link
US (1) US20080205989A1 (en)
EP (1) EP1910625A1 (en)
JP (1) JP2009503294A (en)
CN (1) CN101228322B (en)
CA (1) CA2615102A1 (en)
EA (1) EA200800409A1 (en)
IL (1) IL169878A (en)
WO (1) WO2007013074A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110259455B (en) * 2019-05-14 2021-01-22 中铁十八局集团有限公司 High mountain valley steep stream tunnel snake winding type surrounding pavement construction method
CN113047846A (en) * 2021-03-10 2021-06-29 北京永创众信建筑设计有限公司 Construction method for tunneling tunnel through slope

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2528374B2 (en) * 1990-04-09 1996-08-28 株式会社フジタ How to build a mountain road
FR2663666B1 (en) * 1990-06-22 1996-08-30 Marcel Matiere STRUCTURE COVERED IN PREFABRICATED ELEMENTS.
JPH0786240B2 (en) * 1990-11-28 1995-09-20 株式会社藤井基礎設計事務所 Half tunnel structure and half tunnel construction method
JPH0718174B2 (en) * 1990-12-14 1995-03-01 富山県 Construction method of tunnel entrance
JP3138950B2 (en) * 1992-12-17 2001-02-26 大成建設株式会社 Roadway construction method on slope
JP3355414B2 (en) * 1992-12-17 2002-12-09 大成建設株式会社 Roadway construction method on slope
JP3100922B2 (en) * 1997-05-28 2000-10-23 株式会社宮地鐵工所 Steel-concrete composite rockshed
ITGE20030005A1 (en) * 2003-01-24 2004-07-25 Ferrari De Nobili S R L CONTINUOUS METHOD OF REALIZATION OF UNDERGROUND WORKS,

Also Published As

Publication number Publication date
WO2007013074A1 (en) 2007-02-01
US20080205989A1 (en) 2008-08-28
CA2615102A1 (en) 2007-02-01
EA200800409A1 (en) 2009-12-30
IL169878A (en) 2010-06-16
CN101228322B (en) 2010-12-22
EP1910625A1 (en) 2008-04-16
CN101228322A (en) 2008-07-23

Similar Documents

Publication Publication Date Title
US5551810A (en) Retaining wall with an outer face and method of forming the same
CN107060803B (en) Tunnel construction method by utilizing pipe curtain grouting
US7600948B2 (en) Micropile retaining wall
JP2007154413A (en) Soldier pile type earth retaining anchor type retaining wall and its construction method
KR101244257B1 (en) Method for digging tunnel
EP0070659A1 (en) Retaining wall and in situ method of construction
CN108884652A (en) For consolidating the interlocking stabilisation system in side slope, unfettered soil etc.
JP5615236B2 (en) Shaft construction method and shaft structure of inclined ground
CN107044293A (en) A kind of construction method in tunnel
US5395185A (en) Method of temporarily shoring and permanently facing and excavated slope with a retaining wall
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
Bergmann et al. Design and construction of a composite nailed and mechanically stabilized embankment structure across a talus slope
JP2009503294A (en) Tunnel construction method
KR101017979B1 (en) Environment garden-stone retaining wall
KR100984040B1 (en) Method of reinforced earth retaining wall for cutting face through double reinforcing execution
KR100556668B1 (en) Structure of a slop reinforced of carrying out by physical environment
KR101183955B1 (en) Composite retaining wall construction method
JPH11256596A (en) Reinforcement structure and reinforcement construction method for foundation structure in building
JPH10121489A (en) Building structure utilizing pile as pillar
KR102421636B1 (en) method for installing a retaining wall using landscape rock
KR101283985B1 (en) Fixing apparatus using double pressure panel for retaining wall block and method for making retaining wall using the same
KR100689080B1 (en) A method of construction for reinforcement and landscape architecture to an incline plane
KR100479500B1 (en) The slope tree-planting structure using socket type steel pipe, and his construction method
JP2000314143A (en) Retaining wall execution method and retaining wall device
JP2003336254A (en) Concrete pile and construction method of foundation structure by use thereof