Publication number
JP2009215848A
JP2009215848A JP2008063379A JP2008063379A JP2009215848A JP 2009215848 A JP2009215848 A JP 2009215848A JP 2008063379 A JP2008063379 A JP 2008063379A JP 2008063379 A JP2008063379 A JP 2008063379A JP 2009215848 A JP2009215848 A JP 2009215848A
Authority
JP
Japan
Prior art keywords
building equipment
members
layout sheet
sheet
marking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008063379A
Other languages
Japanese (ja)
Other versions
JP5318438B2 (en
Inventor
Mitsugu Naka
貢 仲
Hiroyasu Yamada
弘康 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takasago Thermal Engineering Co Ltd
Original Assignee
Takasago Thermal Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takasago Thermal Engineering Co Ltd filed Critical Takasago Thermal Engineering Co Ltd
Priority to JP2008063379A priority Critical patent/JP5318438B2/en
Publication of JP2009215848A publication Critical patent/JP2009215848A/en
Application granted granted Critical
Publication of JP5318438B2 publication Critical patent/JP5318438B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Panels For Use In Building Construction (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To enable the accurate and smooth arrangement of building equipment members. <P>SOLUTION: A layout sheet 1 where the arrangement state of piping, ducts and the like are illustrated in a full size, and marking holes 13 are formed at embedded positions of inserts, sleeves and the like is drafted. The layout sheet 1 is disposed on the concrete receiving material side, and marking is performed on a concrete receiving material through the marking holes 13. Subsequently, inserts, sleeves and the like are placed on the concrete receiving material based on the marking, and concrete is placed. Necessary piping and joints are prepared based on the layout sheet 1 and arranged. <P>COPYRIGHT: (C)2009,JPO&amp;INPIT

Description

この発明は、配管やダクトなどの建築設備部材を配設する建築設備部材の配設方法および、建築設備部材を配設するための建築設備部材のレイアウトシートに関する。   The present invention relates to a method for arranging building equipment members such as pipes and ducts, and a layout sheet for building equipment members for arranging the building equipment members.

例えば、建築設備部材を支持する天井吊りボルトを取り付けるためのインサートや、コンクリート製の梁や壁などに貫通孔を形成するためのインサートやスリーブなどの埋設部材は、次のようにして、コンクリート製の躯体に埋設される。すなわち、コンクリートを打設する前に、型枠を形成するコンパネ板(合板、ベニヤ板)やデッキプレート(鉄骨造の床を構成する波状のプレート)などのコンクリート受け材に、埋設部材の埋設位置をマーキング(墨出し)する。このとき、配管やダクトなどの施工図にインサートの配設位置が図示された縮尺のインサート図などを現場に持参して参照し、通り芯などの基準線からスケールなどで埋設部材の埋設位置を測定して、コンクリート受け材にその測定位置をマーキングする。そして、マーキングした位置に埋設部材を配置した状態で、コンクリート受け材にコンクリートを打設することで、埋設部材を躯体に埋設するものである。   For example, inserts for attaching ceiling suspension bolts that support building equipment members, embedded members such as inserts and sleeves for forming through holes in concrete beams and walls, etc., are made of concrete as follows. It is buried in the frame. In other words, before placing concrete, place the embedded member on the concrete receiving material such as a control panel (plywood, plywood) or deck plate (corrugated plate that forms a steel-framed floor) that forms the formwork. Mark (mark out). At this time, refer to the drawing of the scale where the position of the insert is shown on the construction drawing of piping and ducts, etc. Measure and mark the measurement position on the concrete receiver. Then, in the state where the embedded member is arranged at the marked position, the embedded member is embedded in the housing by placing concrete in the concrete receiving material.

しかしながら、埋設部材の数は非常に多く、上記のようにしてすべての埋設部材の埋設位置をマーキングするには、多大な時間と労力とを要する。一方、学校の各教室やホテルの各客室などは、建築設備部材が同じパターンで配設され、埋設部材の埋設位置も同じパターンで配設されている場合が多い。このようなことから、同じパターンで配設される埋設部材の埋設位置を容易にマーキングすることを可能にする位置出し作業方法が知られている(例えば、特許文献1参照。)。この方法は、建物内で繰り返される基準平面パターンに対応する大きさの位置出しシートを用意し、このシートに基準平面パターン内での埋設部材の埋設位置に合致する位置出し孔を予め形成する。そして、基準平面パターンに合致する部分のコンクリート受け材に位置出しシートを敷いて、コンクリート受け材に位置出し孔を利用して埋設部材の埋設位置をマーキングするものである。
特開平07−054493号公報
However, the number of embedded members is very large, and it takes a lot of time and labor to mark the embedded positions of all the embedded members as described above. On the other hand, in each classroom of a school and each guest room of a hotel, building equipment members are often arranged in the same pattern, and the buried positions of the buried members are often arranged in the same pattern. For this reason, there is known a positioning operation method that makes it possible to easily mark the embedded position of the embedded member arranged in the same pattern (see, for example, Patent Document 1). In this method, a positioning sheet having a size corresponding to a reference plane pattern repeated in a building is prepared, and a positioning hole that matches the embedded position of the embedded member in the reference plane pattern is formed in the sheet in advance. Then, a positioning sheet is laid on a portion of the concrete receiving material that matches the reference plane pattern, and the embedded position of the embedded member is marked using the positioning hole in the concrete receiving material.
Japanese Patent Application Laid-Open No. 07-054493

ところで、配管やダクトなどの建築設備部材の配設は、施工図に基づいて行われる。例えば、施工の元請会社で作図した施工図が下請会社に交付され、下請会社では、この施工図に基づいて継手の選定や、定尺管を必要長さに切断したり、接続フランジを取り付けたりする配管加工などを行う。このとき、交付される施工図は、1フロアの全体施工図を複数に分割した図である場合が多いため、隣接する図とのつながり関係を確認しながら、継手の選定や配管加工などを行う必要があった。   By the way, arrangement | positioning of construction equipment members, such as piping and a duct, is performed based on a construction drawing. For example, a construction drawing drawn by the construction contractor is delivered to the subcontracting company, and the subcontracting company selects joints based on this construction drawing, cuts the length pipe to the required length, and attaches a connection flange. Or pipe processing. At this time, the construction drawings to be delivered are often divided into a plurality of construction drawings of one floor, so the joint selection and piping processing are performed while checking the connection relationship with the adjacent drawings. There was a need.

しかも、交付される施工図は縮尺図であるため、例えば、調整用の単管を製作する場合に、施工図のみで差込代やねじ込み代を検討しながら、単管の長さを適正に決定することが困難であった。このため、長さが異なる単管を複数用意し、現場で適正な長さの単管を選定しなければならかった。また、インサートを用いてダクトを吊ったり、スリーブに配管を貫通させたりする場合にも、現物(現場)との寸法が著しく異なる縮尺された工区ごとの施工図を見ながら施工しなければならない。このため、円滑かつ適正な施工や部材点数の計上(拾い出し)が困難で、あるいは熟練を要し、作業員などによる個人差が生じていた。   Moreover, since the construction drawing to be delivered is a scale drawing, for example, when manufacturing a single pipe for adjustment, the length of the single pipe is appropriately adjusted while examining the insertion allowance and screwing allowance only with the construction drawing. It was difficult to decide. For this reason, it was necessary to prepare a plurality of single pipes with different lengths and to select a single pipe with an appropriate length on site. In addition, when a duct is hung using an insert or a pipe is passed through a sleeve, it must be constructed while looking at the construction drawings for each scaled work area that is significantly different from the actual product (site). For this reason, it was difficult to perform smooth and proper construction and counting (picking up) the number of members, or skill was required, and individual differences among workers and the like occurred.

さらに、施工図には、多種の工事区分(職種)の建築設備部材が図示されている場合があり、例えば、衛生設備の空調配管を配設する場合に、施工図から空調配管のみを正確に読み取ることが困難で、施工に長時間を要したり、読み間違いや施工ミスをしたりするおそれがあった。また、インサートやスリーブを埋設する場合に、配管の施工図とは別に、インサート図やスリーブ図といった図が作成される場合があるが、この場合には各図に差異が生じるおそれがあり、施工ミスを防止するには各図を確認する必要などがあった。   Furthermore, there are cases where construction equipment members of various construction categories (job types) are shown in the construction drawings. For example, when air conditioning piping for sanitary facilities is installed, only the air conditioning piping is accurately shown from the construction drawings. It was difficult to read, and there was a risk that it would take a long time for construction, or could result in reading errors or construction errors. In addition, when embedding inserts and sleeves, drawings such as insert diagrams and sleeve diagrams may be created separately from the piping construction drawings. In order to prevent mistakes, it was necessary to check each figure.

このように、従来の建築設備部材の配設方法では、多大な労力と時間とを要し、しかも施工ミスを招くおそれがあった。これに対し、上記特許文献1に記載された方法では、埋設部材の埋設位置のマーキングを容易にするのみであり、このような問題を解決することができない。しかも、建物内で繰り返される基準平面パターンにおけるマーキングを容易にするものであり、多種の平面パターンや埋設部材の埋設位置パターンに対しては、適用することができない。つまり、このような場合には従来のように、基準線からスケールなどで埋設部材の埋設位置を測定して、コンクリート受け材にマーキングしなければならない。   As described above, the conventional method for arranging building equipment members requires a great deal of labor and time, and may cause construction errors. On the other hand, the method described in Patent Document 1 only facilitates marking of the embedded position of the embedded member, and cannot solve such a problem. In addition, the marking in the reference plane pattern repeated in the building is facilitated, and cannot be applied to various types of plane patterns and embedded position patterns of the embedded members. That is, in such a case, as in the prior art, the embedding position of the embedding member must be measured from the reference line with a scale or the like to mark the concrete receiving material.

そこでこの発明は、正確(適正)かつ円滑(容易)に建築設備部材を配設することを可能にする建築設備部材の配設方法およびレイアウトシートを提供することを目的とする。   Then, this invention aims at providing the arrangement | positioning method and layout sheet | seat of a building equipment member which makes it possible to arrange | position a building equipment member correctly (proper) and smoothly (easy).

上記目的を達成するために請求項1に記載の発明は、配管やダクトなどの建築設備部材を配設する建築設備部材の配設方法であって、前記建築設備部材の配設状態が原寸大で図示され、インサートやスリーブなどの埋設部材の埋設位置が示されたレイアウトシートを、CAD(Computer Aided Design)装置を使用して作成するシート作成ステップと、前記レイアウトシートをコンクリート受け材側に配設し、前記埋設部材の埋設位置に形成された墨付け孔を介して、前記コンクリート受け材に前記埋設位置をマーキングするマーキングステップと、前記マーキングに基づいて前記コンクリート受け材に前記埋設部材を配置して、コンクリートを打設する打設ステップと、前記レイアウトシートに基づいて必要な建築設備部材を準備する設備部材準備ステップと、前記レイアウトシートに基づいて、前記埋設部材を介して前記必要な建築設備部材を配設する設備部材配設ステップと、を有することを特徴とする。   In order to achieve the above object, the invention described in claim 1 is a method for arranging building equipment members such as pipes and ducts, wherein the arrangement state of the building equipment members is full scale. A sheet creation step for creating a layout sheet using a CAD (Computer Aided Design) device, in which a layout sheet showing an embedding position of an embedding member such as an insert or a sleeve is shown, and the layout sheet is arranged on the concrete receiving material side. A marking step for marking the burying position on the concrete receiving material via a marking hole formed at the burying position of the burying member, and arranging the burying member on the concrete receiving material based on the marking And placing the concrete, and necessary building equipment based on the layout sheet An equipment member preparing step for preparing a member, and an equipment member arranging step for arranging the necessary building equipment member via the embedded member based on the layout sheet.

この発明によれば、シート作成ステップで原寸大のレイアウトシートが作成され、マーキングステップでコンクリート受け材に埋設部材の埋設位置がマーキングされ、打設ステップでコンクリート躯体に埋設部材が埋設され、設備部材準備ステップで必要な建築設備部材が準備され、設備部材配設ステップで必要な建築設備部材が配設される。   According to the present invention, a full-size layout sheet is created in the sheet creating step, the embedding position of the embedding member is marked in the concrete receiving material in the marking step, and the embedding member is embedded in the concrete frame in the placing step. Necessary building equipment members are prepared in the preparation step, and necessary building equipment members are arranged in the equipment member arranging step.

請求項2に記載の発明は、請求項1に記載の建築設備部材の配設方法において、前記シート作成ステップにおいて、前記必要な建築設備部材に関する情報を記したレイアウトシートを作成する、ことを特徴とする。ここで、必要な建築設備部材に関する情報とは、設備部材準備ステップで準備する必要な建築設備部材の種類や寸法に関する情報や、設備部材配設ステップで配設する建築設備部材の位置情報などを意味する。   Invention of Claim 2 is the layout method of the construction equipment member of Claim 1, The layout sheet which described the information regarding the said required construction equipment member is created in the said sheet creation step. And Here, the information related to the necessary building equipment members includes information on the types and dimensions of necessary building equipment members prepared in the equipment member preparation step, position information on the building equipment members arranged in the equipment member arranging step, and the like. means.

請求項3に記載の発明は、請求項1または2のいずれか1項に記載の建築設備部材の配設方法において、前記シート作成ステップにおいて、所定の建築設備部材の配設状態が識別可能に図示されたレイアウトシートを作成する、ことを特徴とする。ここで、所定の建築設備部材とは、所定の業者が加工、配設(施工)を行う建築設備部材や、同一の系統・工事区分に属する建築設備部材などを意味し、識別可能とは、色分けによる識別や、所定の建築設備部材のみを図示することによる識別などが可能なことを意味する。   According to a third aspect of the present invention, in the construction equipment member arranging method according to any one of the first or second aspects, in the sheet creating step, a predetermined construction equipment member placement state can be identified. The illustrated layout sheet is created. Here, the predetermined building equipment member means a building equipment member that is processed and arranged (constructed) by a predetermined contractor, a building equipment member that belongs to the same system / construction division, and the like is identifiable. This means that identification by color coding, identification by illustrating only predetermined building equipment members, and the like are possible.

請求項4に記載の発明は、請求項1から3のいずれか1項に記載の建築設備部材の配設方法において、前記マーキングステップにおいて、前記埋設部材の種類や大きさなどが識別可能に前記マーキングをする、ことを特徴とする。   Invention of Claim 4 is the arrangement | positioning method of the construction equipment member of any one of Claim 1 to 3, In the marking step, the kind, magnitude | size, etc. of the said embedded member can be identified. It is characterized by marking.

請求項5に記載の発明は、配管やダクトなどの建築設備部材を配設するための建築設備部材のレイアウトシートであって、CAD装置を使用して、前記建築設備部材の配設状態が原寸大で図示され、インサートやスリーブなどの埋設部材の埋設位置が示され、前記建築設備部材に関する情報が記されている、ことを特徴とする。   The invention according to claim 5 is a layout sheet of building equipment members for arranging building equipment members such as pipes and ducts, and the arrangement state of the building equipment members is an original size using a CAD device. It is illustrated at a large size, the burying position of the burying member such as an insert or a sleeve is shown, and information on the building equipment member is written.

請求項1に記載の発明によれば、個々の埋設部材の埋設位置が図示されたレイアウトシートに基づいて埋設位置をマーキングする。このため、マーキングステップにおいて、埋設位置が繰り返される標準的なパターンでなくても、埋設部材の埋設位置をコンクリート受け材に容易かつ適正にマーキングすることができる。また、設備部材準備ステップにおいて、建築設備部材の配設状態が原寸大で図示されたレイアウトシートに基づいて必要な建築設備部材を準備する。このため、例えば、差込代やねじ込み代を検討しながら、単管の長さを適正に決定することや、部材点数の計上を正確に行うことなどが可能となる。さらに、設備部材配設ステップにおいて、建築設備部材の配設状態が原寸大で図示されたレイアウトシートに基づいて必要な建築設備部材を配設するため、円滑かつ適正な配設施工が可能となる。このようにして、正確かつ円滑に建築設備部材を配設することが可能となる。   According to the first aspect of the present invention, the embedded position of each embedded member is marked based on the illustrated layout sheet. For this reason, even if it is not the standard pattern in which a burying position is repeated in a marking step, the burying position of a burying member can be marked easily and appropriately on a concrete receiving material. Further, in the equipment member preparation step, necessary construction equipment members are prepared based on the layout sheet in which the arrangement state of the construction equipment members is illustrated in full size. For this reason, for example, it is possible to appropriately determine the length of the single pipe and accurately count the number of members while considering the insertion allowance and the screw allowance. Furthermore, in the equipment member placement step, the necessary construction equipment members are placed based on the layout sheet shown in the drawing in which the placement state of the building equipment members is full-scale, so that smooth and proper placement work is possible. . In this way, building equipment members can be arranged accurately and smoothly.

請求項2に記載の発明によれば、レイアウトシートに必要な建築設備部材の種類や寸法に関する情報や、位置情報などが記されているため、必要な建築設備部材を正確かつ容易に準備し、さらには、建築設備部材を正確かつ円滑に配設することが可能となる。   According to invention of Claim 2, since the information regarding the kind and dimension of a building equipment member required for a layout sheet, the position information, etc. are written, the necessary building equipment member is prepared accurately and easily, Furthermore, it becomes possible to arrange | position a building equipment member correctly and smoothly.

請求項3に記載の発明によれば、レイアウトシートに所定の建築設備部材の配設状態が識別可能に図示されているため、施工業者(作業者)などは自己が加工、配設すべき建築設備部材の配設状態を正確かつ容易に読み取ることができ、その結果、正確かつ円滑に建築設備部材を配設することが可能となる。   According to invention of Claim 3, since the arrangement | positioning state of a predetermined | prescribed building equipment member is illustrated in the layout sheet so that identification is possible, the construction contractor (operator) etc. should be processed and arranged by himself / herself The arrangement state of the equipment member can be read accurately and easily, and as a result, the construction equipment member can be arranged accurately and smoothly.

請求項4に記載の発明によれば、埋設部材の種類や大きさなどが識別可能にマーキングされるため、種類や大きさなどが適正な埋設部材を正確かつ円滑にコンクリート受け材に配置することができる。   According to the invention described in claim 4, since the type and size of the buried member are marked so as to be identifiable, the buried member having the appropriate type and size can be accurately and smoothly placed on the concrete receiving material. Can do.

請求項5に記載の発明によれば、このレイアウトシートを使用することで、請求項1、2と同様にして、正確かつ円滑に建築設備部材を配設することが可能となる。   According to the fifth aspect of the invention, by using this layout sheet, it is possible to arrange the building equipment members accurately and smoothly in the same manner as in the first and second aspects.

以下、この発明を図示の実施の形態に基づいて説明する。   The present invention will be described below based on the illustrated embodiments.

(実施の形態1)
図1は、この実施の形態に係る建築設備部材の配設方法を示すフローチャートである。この建築設備部材の配設方法は、配管やダクトなどの建築設備部材を配設する方法であり、主として、シート作成ステップと、マーキングステップと、打設ステップと、設備部材準備ステップと、設備部材配設ステップとを有している。
(Embodiment 1)
FIG. 1 is a flowchart showing a method for arranging building equipment members according to this embodiment. This building equipment member arranging method is a method of arranging building equipment members such as pipes and ducts, mainly a sheet creating step, a marking step, a placing step, a facility member preparing step, and a facility member. A disposing step.

シート作成ステップは、建築設備部材の配設状態が原寸大で図示され、インサートやスリーブなどの埋設部材の埋設位置が図示されたレイアウトシートを作成するステップである。具体的には、まず、CAD装置(CADシステム)などを使用して建築設備部材の配設状態図を作成する(ステップS1)。ここで、建築設備部材の配設状態図とは、配管やダクトなどが配設された最終状態を示す図であり、すべての建築設備部材の大きさ、形状、曲げ状態、傾きなどが正確に図示されたものである。また、建築設備部材にはバルブや継手などの付属品も含まれ、バルブのハンドルの位置などの施工情報(配設状態)も含む。   The sheet creating step is a step of creating a layout sheet in which the arrangement state of the building equipment members is illustrated in full size and the embedding positions of the embedding members such as inserts and sleeves are illustrated. Specifically, an arrangement state diagram of building equipment members is first created using a CAD device (CAD system) or the like (step S1). Here, the arrangement state diagram of building equipment members is a diagram showing the final state in which pipes and ducts are arranged, and the size, shape, bending state, inclination, etc. of all building equipment members are accurate. It is what was illustrated. Building equipment members also include accessories such as valves and joints, and also include construction information (arrangement state) such as the position of the handle of the valve.

さらに、埋設部材の埋設位置、つまり、インサートの打ち込み位置やスリーブの配置位置などを含み、埋設部材の種類に応じて色分けして図示する。例えば、インサートの打ち込み位置には赤丸(後述する図3、4では破線の円)で図示し、スリーブの配置位置には青丸(後述する図3、4では二点鎖線の円)で図示する。ここで、埋設部材の埋設位置は、すべての建築設備部材の配設状態や作業性などを考慮して設定する。例えば、インサートの打ち込み位置は、配管の大きさに適した吊りボルトのピッチ(間隔)や、配管の納まり具合(安定性)などを考慮して設定する。また、スリーブの配置位置は、床コンクリートの上層階と下層階の設備の配置(例えば、他の配管やケーブル、ダクトなどとの干渉)や、スリーブを貫通する配管の納まり具合などを考慮して設定する。   Furthermore, it includes the embedded position of the embedded member, that is, the position where the insert is driven, the position where the sleeve is disposed, etc., and is shown in different colors according to the type of the embedded member. For example, the insertion position of the insert is indicated by a red circle (dotted circle in FIGS. 3 and 4 to be described later), and the arrangement position of the sleeve is indicated by a blue circle (circle of a two-dot chain line in FIGS. 3 and 4 to be described later). . Here, the burying position of the burying member is set in consideration of the arrangement state and workability of all the building equipment members. For example, the insertion position of the insert is set in consideration of the pitch (interval) of the suspension bolts suitable for the size of the pipe, the degree of fitting (stability) of the pipe, and the like. In addition, the layout of the sleeves takes into account the layout of the upper and lower floors of the floor concrete (for example, interference with other pipes, cables, ducts, etc.) and the degree of fitting of the pipes that penetrate the sleeve. Set.

このような配設状態図に、さらに、必要な建築設備部材に関する情報を記入する。ここで、必要な建築設備部材に関する情報とは、後述する設備部材準備ステップで準備する必要な建築設備部材の種類や寸法に関する情報や、設備部材配設ステップで配設する建築設備部材の位置情報などを意味する。具体的には、配管の口径や長さ、スリーブの開口径など、建築設備部材や埋設部材などの必要部材の拾い出しや加工に必要な情報や、配管の天井面からの高さ位置などの位置情報などを記入する。また、配設状態図には、躯体の通り芯(基準線)の番号に対応した通り芯の番号を記入する。   In addition, information relating to necessary building equipment members is entered in such an arrangement state diagram. Here, the information on the necessary building equipment members is information on the types and dimensions of the necessary building equipment members prepared in the equipment member preparation step described later, and the position information on the building equipment members arranged in the equipment member arranging step. Means. Specifically, the pipe diameter and length, the opening diameter of the sleeve, etc., information necessary for picking up and processing necessary members such as building equipment members and buried members, and the height position from the ceiling surface of the pipe Enter location information. Also, in the arrangement state diagram, the number of the core corresponding to the number of the core (reference line) of the casing is entered.

次に、作図した配設状態図を原寸大でプロッタ等から印刷出力する(ステップS2)。ここで、一般に原寸大の配設状態図が大きいため、プロッタが出力可能な大きさの用紙に分割して、複数の分割図面を出力する。分割は、通り芯(図3参照)を境にして分割する。そして、後述するように、通り芯に合わせてコンクリート受け材側に配設する。これにより、分割図面の貼り合わせを正確かつ容易に行うことが可能となる。ただし、障害物のために通り芯を境にして分割することができない場合や、配設状態図が大きい場合などには、分割図面に通り芯までの距離、位置関係を記入する(図4参照)こともできる。また、所定の建築設備部材の配設状態を識別可能に図示して出力する。ここで、所定の建築設備部材とは、所定の業者が加工、配設(施工)を行う建築設備部材や、同一の系統・工事区分に属する建築設備部材などを意味し、識別可能とは、色分けによる識別や、所定の建築設備部材のみを図示することによる識別などが可能なことを意味する。具体的には、この実施の形態では、衛生設備の空調配管を配設すること(衛生工事の配管)を目的とし、衛生設備の配管とその埋設部材などの関連部材のみの図と、これらの部材に関する情報のみを残し、その他の部材については削除した図を出力する。また、CAD装置のプロッタにセットされるロール紙は、幅が約60cm〜1mで、1巻きの長さは例えば50mである。このようなロール紙を3〜4mに切断すると、機械室や便所などの室に好適である。   Next, the drawn arrangement state diagram is printed out from the plotter or the like in full size (step S2). Here, since the full-scale arrangement state diagram is generally large, it is divided into sheets of a size that can be output by the plotter, and a plurality of divided drawings are output. The division is performed with the street core (see FIG. 3) as a boundary. And it arrange | positions to the concrete receiving material side according to a core as so that it may mention later. As a result, it is possible to accurately and easily paste the divided drawings. However, if it is not possible to divide by the boundary due to an obstacle, or if the arrangement state diagram is large, enter the distance to the core and the positional relationship on the division drawing (see Fig. 4). You can also In addition, the arrangement state of a predetermined building equipment member is illustrated and output so as to be identifiable. Here, the predetermined building equipment member means a building equipment member that is processed and arranged (constructed) by a predetermined contractor, a building equipment member that belongs to the same system / construction division, and the like is identifiable. This means that identification by color coding, identification by illustrating only predetermined building equipment members, and the like are possible. Specifically, in this embodiment, for the purpose of arranging air-conditioning pipes for sanitary facilities (plumbing for sanitary work), a diagram of only sanitary equipment pipes and related members such as buried members thereof, Only the information about the member is left, and other members are deleted. Further, the roll paper set on the plotter of the CAD apparatus has a width of about 60 cm to 1 m, and the length of one roll is, for example, 50 m. When such roll paper is cut into 3 to 4 m, it is suitable for rooms such as machine rooms and toilets.

続いて、出力した複数の分割図面を貼り合わせて、1枚の配設状態図面とする(ステップS3)。ここで、図面の貼り合わせには、図や数字などが判読できるように透明または半透明で、しかも、湿気などによる伸縮で剥れるのを防止するために、伸縮性が図面の用紙と同等なテープを使用するのが好ましい。例えば、基材が和紙で接着材がゴム系の養生テープを使用する。また、屋外で雨天などでも使用できるように、このようにして貼り合わせた図面にラミネート加工したり、図面の上に透明なゴムシートを敷いてもよい。図3は、配設状態図面の一例を示し、この実施の形態では、左端に通り芯の番号(「6」〜「9」)が記入されている。   Subsequently, the plurality of divided drawings that have been output are pasted together to form a single arrangement drawing (step S3). Here, the drawings are pasted together so that the figures and numbers are transparent or translucent so that they can be read, and in order to prevent peeling due to expansion and contraction due to moisture etc., the stretchability is equivalent to the drawing paper. It is preferable to use a tape. For example, a curing tape whose base material is Japanese paper and whose adhesive is rubber is used. In addition, the drawings attached in this way may be laminated so that they can be used outdoors even in rainy weather, or a transparent rubber sheet may be laid on the drawings. FIG. 3 shows an example of the arrangement state drawing. In this embodiment, the core numbers (“6” to “9”) are written on the left end.

次に、配設状態図面に、埋設部材の埋設位置に墨付け孔を形成する(ステップS4)。すなわち、ステップS1でインサートの打ち込み位置として図示された赤丸や、スリーブの配置位置として図示された青丸の中心と同心上に、円形の墨付け孔を開ける。ここで、例えば、円筒状のステンレス鋼管の先端を尖らせたものを配設状態図面に押し付けることで、墨付け孔を開ける。図4は、墨付け孔が形成された状態を示す一例であり、図中符号11が上記赤丸(図中破線の円)、符号12が上記青丸(図中二点鎖線の円)で、符号13が墨付け孔である。以上のようにして、レイアウトシート1が作成される。このように、この実施の形態では、墨付け孔13が形成された状態をレイアウトシート1としているが、墨付け孔13が形成される前の状態(ステップS3の状態)をレイアウトシートとし、このレイアウトシートを後述するようにコンクリート受け材に貼り付けた後に、墨付け孔13を形成してもよい。   Next, a marking hole is formed in the placement state drawing at the buried position of the buried member (step S4). That is, in step S1, a circular marking hole is formed concentrically with the center of the red circle shown as the insert placement position and the blue circle shown as the sleeve placement position. Here, for example, a sharpened hole is opened by pressing a cylindrical stainless steel tube with a sharpened tip against the arrangement state drawing. FIG. 4 is an example showing a state in which a marking hole is formed. In the figure, reference numeral 11 is the red circle (dotted circle in the figure), and reference numeral 12 is the blue circle (two-dot chain circle in the figure). Reference numeral 13 is a marking hole. As described above, the layout sheet 1 is created. As described above, in this embodiment, the state in which the marking hole 13 is formed is the layout sheet 1, but the state before the marking hole 13 is formed (the state in step S3) is the layout sheet. The marking hole 13 may be formed after the layout sheet is attached to the concrete receiving material as will be described later.

マーキングステップは、レイアウトシート1をコンクリート受け材側に配設し、埋設部材の埋設位置に形成された墨付け孔13を介して、コンクリート受け材に埋設位置をマーキングするステップである。具体的には、上記のレイアウトシート1をコンパネ板やデッキプレートなどのコンクリート受け材の上に配置して、仮固定する(ステップS5)。このとき、コンクリート受け材の通り芯の番号とレイアウトシート1の通り芯の番号とを合わせることで、位置合わせを行う。または、梁面などにレイアウトシート1の一端を合わせることで、位置合わせを行う。   The marking step is a step in which the layout sheet 1 is disposed on the concrete receiving material side and the embedding position is marked on the concrete receiving material through the marking hole 13 formed at the embedding position of the embedding member. Specifically, the layout sheet 1 is placed on a concrete receiving material such as a panel board or deck plate and temporarily fixed (step S5). At this time, alignment is performed by matching the number of the core of the concrete receiving material with the number of the core of the layout sheet 1. Alternatively, alignment is performed by aligning one end of the layout sheet 1 to a beam surface or the like.

次に、墨付け孔13の中心に向けてカラーインキを噴き付け、カラーインキをコンクリート受け材に付着させることで、埋設部材の埋設位置をコンクリート受け材にマーキングする(ステップS6)。このとき、赤丸11の墨付け孔13、つまりインサートの打ち込み位置には赤インキを噴き付け、青丸12の墨付け孔13、つまりスリーブの配置位置には青インキを噴き付ける。これにより、埋設部材の種類に応じてマーキングが色分けされ、後述するようにレイアウトシート1を取り除いても、埋設部材の種類を識別できる。さらに、レイアウトシート1の墨付け孔13の周りにもカラーインキが付着され、後述する設備部材準備ステップや設備部材配設ステップにおいて、埋設部材の埋設位置や種類を確認したりするのに役立つものである。   Next, color ink is sprayed toward the center of the marking hole 13 and the color ink is adhered to the concrete receiving material, thereby marking the embedded position of the embedded member on the concrete receiving material (step S6). At this time, red ink is sprayed to the marking hole 13 of the red circle 11, that is, the position where the insert is driven, and blue ink is sprayed to the marking hole 13 of the blue circle 12, that is, the position where the sleeve is arranged. Thereby, the marking is color-coded according to the type of the embedded member, and the type of the embedded member can be identified even if the layout sheet 1 is removed as described later. Further, color ink is also attached around the marking hole 13 of the layout sheet 1, which is useful for confirming the burying position and type of the burying member in the equipment member preparing step and the equipment member arranging step described later. It is.

打設ステップは、上記のマーキングに基づいてコンクリート受け材に埋設部材を配置して、コンクリートを打設するステップである。具体的には、まず、レイアウトシート1をコンクリート受け材から取り除き(ステップS7)、マーキングした部位に、埋設部材の寸法を書き写す(ステップS8)。つまり、各スリーブの寸法をレイアウトシート1から読み取り、例えば図5に示すように、青インキの上に白インキでスリーブの寸法を書き込む。ここで、図中符号2は、コンクリート受け材としてのコンパネ板、符号21は赤インキ(インサートの打ち込み位置)、符号22は青インキ(スリーブの配置位置)である。また、インサートの寸法はすべて同一であるため、インサートの寸法は書き写す必要がない。   The placing step is a step of placing concrete by placing an embedded member on the concrete receiving material based on the above marking. Specifically, first, the layout sheet 1 is removed from the concrete receiving material (step S7), and the dimensions of the embedded member are copied to the marked site (step S8). In other words, the dimensions of each sleeve are read from the layout sheet 1, and for example, as shown in FIG. 5, the dimensions of the sleeve are written with white ink on blue ink. Here, reference numeral 2 in the drawing is a panel board as a concrete receiving material, reference numeral 21 is red ink (insert placement position), and reference numeral 22 is blue ink (sleeve placement position). Moreover, since all the dimensions of the insert are the same, it is not necessary to copy the dimensions of the insert.

次に、マーキングに従って、コンパネ板2に埋設部材を配置する(ステップS9)。すなわち、赤インキの上にインサートを配置し、青インキの上に、書き込まれた寸法のスリーブを配置する。続いて、コンパネ板2で構成された型枠にコンクリートを打設する(ステップS10)。そして、コンクリートが固まることで、コンクリート躯体にインサートやスリーブが埋設、配設される。   Next, an embedded member is arranged on the panel 2 according to the marking (step S9). That is, the insert is placed on the red ink and the sleeve of the written size is placed on the blue ink. Subsequently, concrete is placed on the mold formed by the panel 2 (step S10). Then, as the concrete hardens, inserts and sleeves are embedded and disposed in the concrete frame.

設備部材準備ステップは、レイアウトシートに基づいて必要な建築設備部材を準備するステップである。具体的には、まず、打設されたコンクリート床の下層階に、通り芯を合わせて上記のレイアウトシート1を敷く(ステップS11)。そして、このレイアウトシート1を見ながら必要な建築設備部材を拾い出す(ステップS12)。すなわち、レイアウトシート1に図示された配管の大きさ、形状、配設状態や、レイアウトシート1に記入された上記の必要な建築設備部材に関する情報に基づいて、必要な配管の径、長さや形状、継手のネジ径や長さ、あるいは調整用の単管の長さを拾い出し、さらにはこれらの部材の必要数を拾い出す(計上する)。   The equipment member preparation step is a step of preparing necessary building equipment members based on the layout sheet. Specifically, first, the layout sheet 1 is laid on the lower floor of the placed concrete floor with the cores aligned (step S11). Then, a necessary building equipment member is picked up while looking at the layout sheet 1 (step S12). That is, based on the information regarding the size, shape, arrangement state of the piping illustrated in the layout sheet 1 and the above-described necessary building equipment members written in the layout sheet 1, the diameter, length and shape of the necessary piping Then, the screw diameter and length of the joint or the length of the single pipe for adjustment are picked up, and further, the necessary number of these members is picked up (calculated).

続いて、これらの必要な建築設備部材を入手して、必要な加工を行う(ステップS13)。例えば、配管の切断、配管や継手のネジ切りや、フランジの取り付け、曲げ加工などを行う。ここで、建築設備部材には、配管やダクトの他に、バルブや継手などの付属品も含まれる。また、この実施の形態では、打設ステップの後に設備部材準備ステップを行っているが、打設ステップの前に、あるいは打設ステップと並行して、設備部材準備ステップを行ってもよい。さらに、必ずしもレイアウトシート1はコンクリート床の下層階に敷かなくてもよく、レイアウトシート1から必要な情報が読み取れる状態であればよい。   Subsequently, these necessary building equipment members are obtained, and necessary processing is performed (step S13). For example, cutting pipes, threading pipes and joints, attaching flanges, and bending. Here, building equipment members include accessories such as valves and joints in addition to pipes and ducts. In this embodiment, the equipment member preparation step is performed after the placement step. However, the equipment member preparation step may be performed before or in parallel with the placement step. Furthermore, the layout sheet 1 does not necessarily have to be laid on the lower floor of the concrete floor as long as necessary information can be read from the layout sheet 1.

設備部材配設ステップは、レイアウトシートに基づいて、埋設部材を介して必要な建築設備部材を配設するステップである。すなわち、上記のレイアウトシート1を見ながら、設備部材準備ステップで拾い出し、加工した建築設備部材を配設する(ステップS14)。具体的には、インサートに吊りボルトを取り付けて、この吊りボルトで所定の配管やダクトを吊って配設したり、スリーブに所定の配管やダクトを貫通させたり、あるいは、所定の継手やバルブなどを所定の位置、方向に取り付けたりする。   The facility member disposing step is a step of disposing necessary building facility members via the embedded member based on the layout sheet. That is, while looking at the layout sheet 1, the building equipment member picked up and processed in the equipment member preparation step is arranged (step S14). Specifically, a hanger bolt is attached to the insert, and a predetermined pipe or duct is hung by the hanger bolt, a predetermined pipe or duct is passed through the sleeve, or a predetermined joint or valve, etc. Is attached in a predetermined position and direction.

そして、レイアウトシート1を撤去して、配設作業を終了する(ステップS15)。ここで、建築設備部材の配設後に、配管やダクトなどに断熱材を被覆する作業などの後続作業を行う場合や、配設後の検査を行う場合などには、レイアウトシート1を撤去しないで、レイアウトシート1を見ながら後続作業や検査などを行ってもよい。   And the layout sheet 1 is removed and arrangement | positioning work is complete | finished (step S15). Here, the layout sheet 1 should not be removed when a subsequent operation such as an operation of covering a pipe or duct with a heat insulating material is performed after the installation of the building equipment member or when an inspection after the installation is performed. Subsequent work or inspection may be performed while viewing the layout sheet 1.

以上のように、この建築設備部材の配設方法およびレイアウトシート1によれば、設備部材準備ステップにおいて、建築設備部材の配設状態が原寸大で図示され、しかも建築設備部材の種類や寸法に関する情報が記入されたレイアウトシート1を見ながら必要な建築設備部材を準備する。このため、例えば、差込代による配管の伸び縮みを検討しながら、単管の長さを適正に決定することや、必要な部材を必要数正確に拾い出すことを、円滑に行える。また、設備部材配設ステップにおいても、建築設備部材の配設状態が原寸大で図示され、しかも建築設備部材の位置情報などが記入されたレイアウトシート1を見ながら配設を行うため、円滑かつ適正な配設が可能となる。例えば、取り付けるべき配管や継手、あるいはバルブなどを付け間違えたり、接続向きや取付方向などを間違えることなどを削減できる。   As described above, according to the arrangement method and layout sheet 1 of the building equipment member, the arrangement state of the building equipment member is illustrated in full size in the equipment member preparation step, and further, it relates to the type and size of the building equipment member. Necessary building equipment members are prepared while looking at the layout sheet 1 in which information is written. For this reason, for example, it is possible to smoothly determine the length of the single pipe and to pick out necessary members accurately as many times as necessary while considering the expansion and contraction of the pipe due to the insertion allowance. Also, in the equipment member placement step, the placement state of the construction equipment members is illustrated in full scale, and the placement is performed while looking at the layout sheet 1 in which the location information of the construction equipment members is written, so Proper arrangement is possible. For example, it is possible to reduce a mistake in attaching a pipe, a joint, a valve, or the like to be attached or a mistake in a connection direction or an attachment direction.

さらに、レイアウトシート1には、所定の建築設備部材の図および情報のみが図示、記入されている。つまり、この実施の形態では、衛生設備の空調配管とその関連部材の図と、これらの部材に関する情報のみが図示、記入されている、このため、多くの系統・工事区分(多業種・多職種)の配管やダクトなどが複雑に交錯する図面を見る場合に比べて、配管業者などは、自己が配設すべき建築設備部材の配設状態や情報を、迷うことなく正確かつ容易に読み取ることができる。また、マーキングステップにおいて、埋設部材の種類に応じてマーキングが色分けされるため、打設ステップにおいて、適正な種類の埋設部材を正確かつ円滑にコンクリート受け材に配置することができる。ここで、埋設部材の種類だけではなく、大きさや形状などが識別できるようにマーキングを色分けや模様分けなどすることで、多種、多様な埋設部材を正確かつ円滑に配置することが可能となる。   Furthermore, the layout sheet 1 is shown and filled with only the drawings and information of predetermined building equipment members. In other words, in this embodiment, only the air conditioning piping of sanitary facilities and related members and information about these members are shown and filled in. Therefore, many systems and construction categories (multi-industry / Compared with the case of looking at drawings where pipes and ducts are complicatedly crossed), plumbers etc. can read the installation status and information of building equipment members that should be installed accurately and easily without hesitation. Can do. In the marking step, since the marking is color-coded according to the type of the embedded member, an appropriate type of embedded member can be accurately and smoothly placed on the concrete receiving material in the placing step. Here, not only the type of the embedded member but also the markings are color-coded or patterned so that the size, shape, etc. can be identified, so that various and various embedded members can be accurately and smoothly arranged.

以上のことから、構造体の変更などの大規模な対応を要することなく、正確かつ円滑に建築設備部材を配設することが可能となり、その結果、施工での無駄をなくし、かつ、品質向上や作業員数の削減を図ることが可能となる。さらに、上記のように、レイアウトシート1を見ながら後続作業や検査などを行うことで、円滑かつ正確に作業や検査などを行うことが可能となる。   From the above, it is possible to arrange building equipment members accurately and smoothly without requiring large-scale measures such as changing the structure. As a result, construction waste is eliminated and quality is improved. And the number of workers can be reduced. Further, as described above, by performing the subsequent operation or inspection while looking at the layout sheet 1, the operation or inspection can be performed smoothly and accurately.

(実施の形態2)
この実施の形態では、レイアウトシート1を配設状態図面とゴムシートとから構成する点で、実施の形態1と構成が異なる。
(Embodiment 2)
This embodiment is different from the first embodiment in that the layout sheet 1 is composed of an arrangement state drawing and a rubber sheet.

ここで、ゴムシートとしては、衛生工事の水パッキンなどに使用され厚みが3mm程度のゴムシートを用い、このゴムシートの上に、上記のようにして作成した配設状態図面を貼り付ける。次に、上記と同様にして、埋設部材の埋設位置に墨付け孔を形成する。このとき、配設状態図面とゴムシートとを貫通するように墨付け孔を形成して、レイアウトシート1とする。そして、このようなレイアウトシート1を用いて、埋設部材の埋設位置をコンクリート受け材にマーキングする(上記のステップS6)ものである。   Here, as the rubber sheet, a rubber sheet having a thickness of about 3 mm used for water packing for sanitary work is used, and the arrangement state drawing prepared as described above is pasted on the rubber sheet. Next, in the same manner as described above, a marking hole is formed at the embedded position of the embedded member. At this time, a marking hole is formed so as to penetrate the arrangement state drawing and the rubber sheet, and the layout sheet 1 is obtained. Then, using such a layout sheet 1, the burying position of the burying member is marked on the concrete receiving material (step S6 above).

このようなレイアウトシート1によれば、マーキングに際して繰り返し使用することができる。このため、マンションやホテルの室などのように、設備や配管などの配設位置が同じパターンの室に対して、より円滑、短時間に、かつ正確に複数のマーキングを行うことが可能となる。また、高層階の建物のように室数が多数あっても、それぞれにレイアウトシート1を作成する必要がないため、マーキングのし忘れ(施工漏れ)などが起こり難くなる。   Such a layout sheet 1 can be used repeatedly for marking. For this reason, it is possible to perform a plurality of markings more smoothly, in a short time, and accurately on a room having the same arrangement position of equipment, piping, etc., such as an apartment or a hotel room. . Further, even if there are a large number of rooms as in a high-rise building, it is not necessary to create a layout sheet 1 for each of them, so that it is difficult to forget to perform marking (work leakage).

以上、この発明の実施の形態について説明したが、具体的な構成は、上記の実施の形態に限られるものではなく、この発明の要旨を逸脱しない範囲の設計の変更等があっても、この発明に含まれる。例えば、上記の実施の形態では、ステップS1において、つまりCAD装置などにおいて必要な建築設備部材に関する情報を記入しているが、必要に応じて、それ以降に手書きなどによって記入してもよい。また、ステップS2において、衛生設備の空調配管とその埋設部材などの関連部材のみを図示して出力しているが、当該レイアウトシートの交付を受ける配管業者が担当する工事区分(職種)の建築設備部材やその埋設部材のみを図示して出力したり、衛生設備の空調配管とその埋設部材などの関連部材を他の部材と色分けして出力したりしてもよい。   Although the embodiment of the present invention has been described above, the specific configuration is not limited to the above embodiment, and even if there is a design change or the like without departing from the gist of the present invention, Included in the invention. For example, in the above-described embodiment, information regarding building equipment members required in step S1, that is, in a CAD apparatus or the like is entered, but if necessary, it may be entered later by handwriting or the like. In step S2, only the air-conditioning piping of the sanitary equipment and the related members such as the buried members are illustrated and outputted, but the construction equipment of the construction category (job type) in charge of the piping contractor receiving the layout sheet is output. Only the member and the embedded member may be illustrated and output, or the air-conditioning piping of the sanitary facility and the related member such as the embedded member may be output by being color-coded with other members.

また、コンクリート受け材がコンパネ板2の場合について説明したが、波状のプレートであるデッキプレートなどであってもよく、デッキプレートの場合には、複数の山の頂面上にレイアウトシート1を張った状態で配置すればよい。さらに、屋上や土間などの結露しやすい部位には、コンパネ板の上に断熱材を敷く場合があるが、このような場合にも適用することができる。すなわち、上記のステップS5、S6と同様にして、レイアウトシート1を断熱材の上に配置してマーキングし、断熱材を貫通する孔を形成してこの孔にスリーブとボイド蓋(紙製のスリーブを塞ぐ蓋)を配置したり、断熱材を貫通するようにインサートを打ち込んだりする。   Moreover, although the case where the concrete receiving material is the panel board 2 has been described, it may be a deck plate which is a corrugated plate. In the case of the deck plate, the layout sheet 1 is stretched on the top surface of a plurality of mountains. It may be arranged in the state. Furthermore, there is a case where a heat insulating material is laid on the panel board in a portion where condensation is likely to occur, such as on the roof or between soils, but this can also be applied to such a case. That is, in the same manner as in the above steps S5 and S6, the layout sheet 1 is arranged and marked on the heat insulating material, a hole penetrating the heat insulating material is formed, and a sleeve and a void lid (paper sleeve) are formed in the hole. A lid that closes the cover) is placed, or an insert is driven so as to penetrate the heat insulating material.

以上のように、この発明に係る建築設備部材の配設方法およびレイアウトシートは、正確かつ円滑に建築設備部材を配設することを可能にするものとして極めて有用である。   As described above, the building equipment member disposing method and the layout sheet according to the present invention are extremely useful for enabling the building equipment member to be disposed accurately and smoothly.

この発明の実施の形態1に係る建築設備部材の配設方法を示すフローチャートである。It is a flowchart which shows the arrangement | positioning method of the building equipment member which concerns on Embodiment 1 of this invention. 図1の続きを示すフローチャートである。It is a flowchart which shows the continuation of FIG. 図1のフローチャートのステップS3において貼り合わせた配設状態図面の一例を示す図である。It is a figure which shows an example of the arrangement | positioning state drawing bonded together in step S3 of the flowchart of FIG. 図1のフローチャートのステップS4において配設状態図面に墨付け孔を形成した状態の一例を示す図である。It is a figure which shows an example of the state which formed the marking hole in arrangement | positioning state drawing in step S4 of the flowchart of FIG. 図1のフローチャートのステップS8において、コンクリート受け材のマーキング部位に埋設部材の寸法を書き写した状態を示す図である。It is a figure which shows the state which copied the dimension of the burying member in the marking site | part of a concrete receiving material in step S8 of the flowchart of FIG.

符号の説明Explanation of symbols

1 レイアウトシート
11 赤丸(インサート位置)
12 青丸(スリーブ位置)
13 墨付け孔
2 コンパネ板(コンクリート受け材)
21 赤インキ(インサート位置)
22 青インキ(スリーブ位置)
1 Layout sheet 11 Red circle (insert position)
12 Blue circle (sleeve position)
13 Marking hole 2 Panel board (concrete receiving material)
21 Red ink (insert position)
22 Blue ink (sleeve position)

Claims (5)

配管やダクトなどの建築設備部材を配設する建築設備部材の配設方法であって、
前記建築設備部材の配設状態が原寸大で図示され、インサートやスリーブなどの埋設部材の埋設位置が示されたレイアウトシートを、CAD装置を使用して作成するシート作成ステップと、
前記レイアウトシートをコンクリート受け材側に配設し、前記埋設部材の埋設位置に形成された墨付け孔を介して、前記コンクリート受け材に前記埋設位置をマーキングするマーキングステップと、
前記マーキングに基づいて前記コンクリート受け材に前記埋設部材を配置して、コンクリートを打設する打設ステップと、
前記レイアウトシートに基づいて必要な建築設備部材を準備する設備部材準備ステップと、
前記レイアウトシートに基づいて、前記埋設部材を介して前記必要な建築設備部材を配設する設備部材配設ステップと、
を有することを特徴とする建築設備部材の配設方法。
It is an arrangement method of building equipment members for arranging building equipment members such as pipes and ducts,
A sheet creation step of creating a layout sheet using the CAD device, wherein the layout state of the building equipment member is illustrated in full size, and the embedded position of the embedded member such as an insert or a sleeve is indicated;
A marking step for arranging the layout sheet on the concrete receiving material side and marking the embedded position on the concrete receiving material through a marking hole formed at the embedded position of the embedded member;
Placing the buried member in the concrete receiving material based on the marking, placing the concrete; and
Facility member preparation step of preparing necessary building facility members based on the layout sheet;
Based on the layout sheet, a facility member disposing step of disposing the necessary building facility member via the embedded member;
A method for arranging building equipment members, comprising:
前記シート作成ステップにおいて、前記必要な建築設備部材に関する情報を記したレイアウトシートを作成する、ことを特徴とする請求項1に記載の建築設備部材の配設方法。   The layout method according to claim 1, wherein, in the sheet creation step, a layout sheet describing information on the necessary building equipment member is created. 前記シート作成ステップにおいて、所定の建築設備部材の配設状態が識別可能に図示されたレイアウトシートを作成する、ことを特徴とする請求項1または2のいずれか1項に記載の建築設備部材の配設方法。   3. The building equipment member according to claim 1, wherein, in the sheet creating step, a layout sheet is created so that an arrangement state of a predetermined building equipment member can be identified. Arrangement method. 前記マーキングステップにおいて、前記埋設部材の種類や大きさなどが識別可能に前記マーキングをする、ことを特徴とする請求項1から3のいずれか1項に記載の建築設備部材の配設方法。   The arrangement method according to any one of claims 1 to 3, wherein in the marking step, the marking is performed so that the type and size of the embedded member can be identified. 配管やダクトなどの建築設備部材を配設するための建築設備部材のレイアウトシートであって、
CAD装置を使用して、前記建築設備部材の配設状態が原寸大で図示され、インサートやスリーブなどの埋設部材の埋設位置が示され、前記建築設備部材に関する情報が記されている、ことを特徴とする建築設備部材のレイアウトシート。
A layout sheet for building equipment members for arranging building equipment members such as pipes and ducts,
Using a CAD device, the arrangement state of the building equipment member is illustrated in full size, the embedded position of the embedded member such as an insert or a sleeve is shown, and information on the building equipment member is written. A layout sheet for building equipment members.
JP2008063379A 2008-03-12 2008-03-12 Arrangement method and layout sheet for building equipment members Expired - Fee Related JP5318438B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008063379A JP5318438B2 (en) 2008-03-12 2008-03-12 Arrangement method and layout sheet for building equipment members

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008063379A JP5318438B2 (en) 2008-03-12 2008-03-12 Arrangement method and layout sheet for building equipment members

Publications (2)

Publication Number Publication Date
JP2009215848A true JP2009215848A (en) 2009-09-24
JP5318438B2 JP5318438B2 (en) 2013-10-16

Family

ID=41187970

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008063379A Expired - Fee Related JP5318438B2 (en) 2008-03-12 2008-03-12 Arrangement method and layout sheet for building equipment members

Country Status (1)

Country Link
JP (1) JP5318438B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015082059A (en) * 2013-10-24 2015-04-27 京セラドキュメントソリューションズ株式会社 Positioning sheet and image forming apparatus
JP2019196988A (en) * 2018-05-10 2019-11-14 株式会社日立プラントサービス Inking method or inking system

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0754493A (en) * 1993-08-18 1995-02-28 Takasago Thermal Eng Co Ltd Positioning method for insert or the like, and positioning sheet therefor
JP2005271134A (en) * 2004-03-24 2005-10-06 Panac Co Ltd Installation position pattern sheet and machining system installation method using it

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0754493A (en) * 1993-08-18 1995-02-28 Takasago Thermal Eng Co Ltd Positioning method for insert or the like, and positioning sheet therefor
JP2005271134A (en) * 2004-03-24 2005-10-06 Panac Co Ltd Installation position pattern sheet and machining system installation method using it

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015082059A (en) * 2013-10-24 2015-04-27 京セラドキュメントソリューションズ株式会社 Positioning sheet and image forming apparatus
JP2019196988A (en) * 2018-05-10 2019-11-14 株式会社日立プラントサービス Inking method or inking system
JP7105101B2 (en) 2018-05-10 2022-07-22 株式会社日立プラントサービス inking method or inking system

Also Published As

Publication number Publication date
JP5318438B2 (en) 2013-10-16

Similar Documents

Publication Publication Date Title
US7444270B2 (en) Method, apparatus and banner for structure layout
US20090277031A1 (en) Construction layout method and template
US6360448B1 (en) System for laying out an installation of components and method of use
US5755072A (en) Construction method
US7373731B2 (en) Construction templates and methods of use
US8533927B2 (en) Full-scale architectural template and method for installing construction elements for exhibitions, trade shows, conventions and events without damaging carpet or floor
US20030061722A1 (en) Polygrid
JP5318438B2 (en) Arrangement method and layout sheet for building equipment members
JP2018526656A (en) Mounting system and method for mapping building components
CN115758554A (en) ALC (autoclaved lightweight concrete) slab lean construction method based on BIM (building information modeling) technology
US7685734B1 (en) Pipe fitting template
US20210262221A1 (en) System and Method of Installing System of Sheets of Sheathing having Laser Engraved and/or Rasterbated Image of Building Information
JPWO2019123909A1 (en) Gypsum board
Lee et al. Willis's elements of quantity surveying
Kiong et al. An overview of precast concrete system for building maintenance: malaysian perspective
JP5602042B2 (en) Separation distance measuring device
TWI767764B (en) The modeling method of csd and sem
JP2009155797A (en) MARKING METHOD FOR PCa MEMBER BY USE OF SHEET
JP7445512B2 (en) Display material for floor slab construction and floor slab construction method
JPH01316589A (en) Method and jig for pipe construction
US20240118066A1 (en) Tape measuring strap with custom markings showing the positioning of various components for construction application
JP7289175B1 (en) architectural system
JP5016358B2 (en) Building materials
JPH07286849A (en) Method and device for confirming gradient of pipeline
JP2549286Y2 (en) Concrete formwork made of paper tube

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110214

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120912

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120918

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20121113

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130709

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130710

R150 Certificate of patent or registration of utility model

Ref document number: 5318438

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees