JP2009139982A - Work management system, work management program and management server - Google Patents

Work management system, work management program and management server Download PDF

Info

Publication number
JP2009139982A
JP2009139982A JP2007312207A JP2007312207A JP2009139982A JP 2009139982 A JP2009139982 A JP 2009139982A JP 2007312207 A JP2007312207 A JP 2007312207A JP 2007312207 A JP2007312207 A JP 2007312207A JP 2009139982 A JP2009139982 A JP 2009139982A
Authority
JP
Japan
Prior art keywords
work
project
time
information
management server
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007312207A
Other languages
Japanese (ja)
Inventor
Hideaki Komai
英敬 駒井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Oki Electric Industry Co Ltd
Original Assignee
Oki Electric Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Oki Electric Industry Co Ltd filed Critical Oki Electric Industry Co Ltd
Priority to JP2007312207A priority Critical patent/JP2009139982A/en
Publication of JP2009139982A publication Critical patent/JP2009139982A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a work management system allowing reduction of a burden of a worker, for automatically totaling work man-hours performed by the worker in each project. <P>SOLUTION: This system for managing work in each project through computers 10 for the workers has: a project folder storage server 20 for storing a project folder provided in each project; and a man-hour management server 30 for performing registration of the project, new provision of the project folder to the project folder storage server 20, registration and management of the related worker in each project, and management of the man-hours. The computer 10 for the worker performs all creation and storage of material or data inside the project folder storage server 20, and the man-hour management server 30 calculates the work man-hours from an access situation to the project folder storage server 20 of the computer 10 for the worker sent from the project folder storage server 20. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、作業者の負担を少なくして、プロジェクト毎に作業者が行う作業工数を自動的に集計することができる作業管理システム、作業管理プログラム、および管理サーバに関する。   The present invention relates to a work management system, a work management program, and a management server that can reduce the burden on a worker and can automatically total the number of work steps performed by the worker for each project.

一般に、作業者用のコンピュータを用いたデスクワーク業務におけるプロジェクト毎の作業工数を管理して、人件費コストの算出や稼働率管理を行う従来の工数入力方法は、各作業者がコンピュータからWEB画面を用いて工数を入力する方法、各作業者用のコンピュータに工数管理ソフトウェアをインストールしておいて、このソフトウェアに工数を入力する方法が一般的であった。   In general, the conventional man-hour input method for calculating the labor cost and managing the operation rate by managing the work man-hours for each project in the desk work work using the computer for the worker is that each worker displays the WEB screen from the computer. A method of inputting man-hours by using the method, and a method of inputting man-hours to this software after installing man-hour management software on a computer for each worker.

しかし、このような従来の入力方法では、入力の頻度は、月次、週次、日次と管理形態によってさまざまであって、工数を入力するタイミングは、その日の作業終了時や、週末、月末となる。したがって、実際の作業開始、終了のタイミングとは異なっているため、どうしても、作業者の記憶や作業者が記録したノートなどに頼って、それを一定の期間毎に集計するなどの方法を採らざるを得なかった。また、休憩時間や雑務時間等も含まれることになり、正確な工数の入力ができないという問題があった。   However, in such a conventional input method, the frequency of input varies depending on the monthly, weekly, daily, and management type, and the timing for inputting the man-hours is at the end of work on the day, at the weekend, at the end of the month. It becomes. Therefore, it is different from the actual work start and end timings, so it is unavoidable to rely on the worker's memory or the notes recorded by the worker, and to add it up at regular intervals. Did not get. In addition, there is a problem that it is not possible to input man-hours accurately because it includes break times and work hours.

このような問題を解決するため、工数管理方法としてアプリケーションソフトウェアの実行時間を監視して工数を監視する方法(特許文献1参照)や、特定のプログラム名、ファイル名およびキーワードの出現を監視してプロジェクト毎の作業時間を自動的に累積する方法(特許文献2参照)などが報告されている。
特開2000−89982号公報 特開2002−24504号公報
In order to solve such problems, as a man-hour management method, a method of monitoring the man-hour by monitoring the execution time of the application software (see Patent Document 1), the appearance of a specific program name, file name, and keyword is monitored. A method of automatically accumulating work time for each project (see Patent Document 2) has been reported.
Japanese Unexamined Patent Publication No. 2000-89982 JP 2002-24504 A

しかしながら、特許文献1に示された方法では、工数の入力そのものは作業者自身が行う必要があるので手間がかかるという問題があり、また特許文献2に示された方法では、キーワードなどから時間の累積を具体的にどのように行うかが記載されていないという問題があった。   However, the method shown in Patent Document 1 has a problem that it takes time since the operator itself has to input the man-hours. In addition, the method shown in Patent Document 2 takes time from a keyword or the like. There was a problem that how to perform the accumulation was not described.

本発明は、前記の課題を解決するためになされたものであって、作業者の負担を少なくして、プロジェクト毎に作業者が行う作業工数を自動的に集計することができる作業管理システム、そのシステムで用いられる作業管理プログラム、および管理サーバを提供することを目的とする。   The present invention was made in order to solve the above-mentioned problems, and reduces the burden on the worker, and a work management system capable of automatically totaling the work man-hours performed by the worker for each project, An object is to provide a work management program and a management server used in the system.

前記目的を達成するため、1つ以上の作業用端末(例えば、作業者用コンピュータ10)と、作業用端末の作業時間を管理する処理部および記憶部を有する管理サーバ(例えば、プロジェクトフォルダ記憶サーバ20および工数管理サーバ30)とを備える作業管理システムにおいて、処理部は、作業用のプロジェクト毎に設けられたプロジェクトフォルダを記憶部に作成し、作業用端末からプロジェクトフォルダ内のファイルにアクセスがあると、ファイルへのアクセスの時刻情報を、プロジェクトの情報とを関連付けて記憶部に記憶することを特徴とする。   In order to achieve the object, a management server (for example, a project folder storage server) having one or more work terminals (for example, the computer 10 for workers), a processing unit for managing the work time of the work terminals, and a storage unit 20 and the man-hour management server 30), the processing unit creates a project folder provided for each work project in the storage unit, and accesses a file in the project folder from the work terminal. And time information of access to the file is stored in the storage unit in association with the project information.

また、処理部は、ファイルへの最初のアクセスの時刻情報を作業開始時刻情報とし、ファイルが閉じられた場合の時刻、または、ファイルへのアクセスが所定時間なかった場合の時刻を作業終了時刻情報として記憶部に記憶し、作業終了時刻情報と作業開始時刻情報とに基づいて作業時間を算出し管理することを特徴とする。   The processing unit uses the time information of the first access to the file as work start time information, and the time when the file is closed or the time when the file is not accessed for a predetermined time is the work end time information. And storing in the storage unit, and calculating and managing the work time based on the work end time information and the work start time information.

本発明の作業管理システムでは、作業者の負担を少なくしてプロジェクト毎に作業者が行う作業工数(作業時間)を自動的に集計することができる。   In the work management system of the present invention, it is possible to automatically add up the work man-hours (work time) performed by the worker for each project while reducing the burden on the worker.

以下、本発明を実施するための最良の形態(以下、「実施形態」という。)を図面に基づいて詳細に説明する。
《第1の実施形態》
図1は、本発明の第1の実施形態である作業管理システムを示すブロック図である。図1において、本実施形態の作業管理システムは、複数の作業者用コンピュータ10a(10),10b(10),10c(10)などと、プロジェクトフォルダ記憶サーバ20と、工数管理サーバ30と、これらを結ぶネットワーク40とで構成されている。
Hereinafter, the best mode for carrying out the present invention (hereinafter referred to as “embodiment”) will be described in detail with reference to the drawings.
<< First Embodiment >>
FIG. 1 is a block diagram showing a work management system according to the first embodiment of the present invention. In FIG. 1, the work management system of the present embodiment includes a plurality of workers' computers 10a (10), 10b (10), 10c (10), a project folder storage server 20, a man-hour management server 30, and the like. And a network 40 connecting the two.

作業者用コンピュータ10は、作業者がプロジェクトに関する作業を行うコンピュータであって、通常のコンピュータとしてのネットワークへのアクセス機能を有する。   The worker computer 10 is a computer on which a worker performs work related to a project, and has a function of accessing a network as a normal computer.

プロジェクトフォルダ記憶サーバ20には、プロジェクト毎に分類されたファイルが収められたフォルダ、すなわちプロジェクトPJ1に関するフォルダA(21)、プロジェクトPJ2に関するフォルダB(22)、プロジェクトPJ3に関するフォルダC(23)などが、それぞれ順番に整理されて保管されている。さらに、プロジェクトフォルダ記憶サーバ20は、作業者用コンピュータ10からのフォルダへのアクセスを監視して検出するフォルダ監視機能24と、フォルダ内のファイルへの作業者用コンピュータ10からのアクセスを監視して検出するファイル監視機能25とを備えている。   The project folder storage server 20 includes folders containing files classified for each project, that is, a folder A (21) related to the project PJ1, a folder B (22) related to the project PJ2, a folder C (23) related to the project PJ3, and the like. They are organized and stored in order. Further, the project folder storage server 20 monitors a folder monitoring function 24 for monitoring and detecting access to the folder from the worker computer 10 and monitors access from the worker computer 10 to files in the folder. And a file monitoring function 25 for detection.

作業者は、プロジェクトに関する作業を行う際には、すべて自己の作業者用コンピュータ10からプロジェクトフォルダ記憶サーバ20内の作業対象となるプロジェクト毎のフォルダにアクセスして、このフォルダ内のファイルに対し作業し、データの新規作成や変更を行うものとする。   When working on a project, a worker accesses the folder for each project to be worked in the project folder storage server 20 from his / her own computer 10 and works on files in this folder. The data is newly created or changed.

工数管理サーバ30は、作業者の工数管理をするデータベースサーバであり、記憶部39に、プロジェクトの情報、プロジェクトに従事する関連作業者の情報であるアカウント情報、プロジェクト毎の作業工数の情報を記憶し、プロジェクトの登録をするプロジェクト登録機能31、アカウントの管理をするアカウント管理機能32、作業工数を算出する作業工数算出機能33を備えている。各作業者が行った作業工数は、プロジェクト毎に作業工数算出機能33によって算出され、工数管理サーバ30内の記憶部39に保管される。   The man-hour management server 30 is a database server that manages the man-hours of workers, and stores information on projects, account information that is information on related workers engaged in the projects, and information on man-hours for each project in the storage unit 39. And a project registration function 31 for registering a project, an account management function 32 for managing an account, and a work man-hour calculating function 33 for calculating work man-hours. The work man-hours performed by each worker are calculated by the work man-hour calculating function 33 for each project and stored in the storage unit 39 in the man-hour management server 30.

作業者用コンピュータ10、プロジェクトフォルダ記憶サーバ20、および工数管理サーバ30は、すべてLANなどのネットワーク40で相互に接続されており、相互にデータやファイルのやり取りができるように構成されている。   The worker computer 10, the project folder storage server 20, and the man-hour management server 30 are all connected to each other via a network 40 such as a LAN, and are configured to exchange data and files with each other.

なお、工数管理サーバ30は、表示部、入力部、処理部である中央演算処理装置(CPU)、通信部、記憶部39、メモリなどから構成される。表示部は、ディスプレイなどで構成され、工数管理サーバ30による処理の実行状況や実行結果などの利用者への情報を表示する。入力部は、キーボードやマウスなどのコンピュータに指示を入力するための装置であり、管理者からの入力を受け付ける。中央演算処理装置は、メモリに格納される各種プログラムを実行する。通信部は、ネットワーク40を介して、他の装置と各種データやコマンドを交換する。記憶部39は、工数管理サーバ30が処理を実行するための各種データを保存する。メモリは、工数管理サーバ30が処理を実行する各種のプログラムおよび一時的なデータを保持する。   The man-hour management server 30 includes a display unit, an input unit, a central processing unit (CPU) that is a processing unit, a communication unit, a storage unit 39, a memory, and the like. The display unit is configured with a display or the like, and displays information to the user such as the execution status and execution result of the process by the man-hour management server 30. The input unit is a device for inputting an instruction to a computer such as a keyboard and a mouse, and receives an input from an administrator. The central processing unit executes various programs stored in the memory. The communication unit exchanges various data and commands with other devices via the network 40. The storage unit 39 stores various data for the man-hour management server 30 to execute processing. The memory holds various programs and temporary data that the man-hour management server 30 executes processing.

本実施形態においては、プロジェクトフォルダ記憶サーバ20と、工数管理サーバ30の2つのサーバの構成を示しているが、必ずしもこれに限定するものではない。記憶部39に、プロジェクト用のフォルダ、フォルダ監視機能24、ファイル監視機能25を備えていてもよい。   In the present embodiment, the configuration of the two servers of the project folder storage server 20 and the man-hour management server 30 is shown, but the present invention is not necessarily limited to this. The storage unit 39 may include a project folder, a folder monitoring function 24, and a file monitoring function 25.

次に、作業者が実施する作業の工数管理の処理について説明する。
図2は、作業者用コンピュータがプロジェクトフォルダ記憶サーバで作業する際のプロジェクトフォルダ記憶サーバおよび工数管理サーバとの相互通信関係の一例を示す説明図である。工数管理サーバ30は、予め、プロジェクト登録機能31およびアカウント管理機能32によってプロジェクトmの情報とプロジェクトmの関連作業者に関するアカウント情報をあわせて登録しておく(ステップS121)。そうして、プロジェクトフォルダ記憶サーバ20にプロジェクトm関連のフォルダを作成させ(ステップS111)、このフォルダとプロジェクトmとを関連付けておく(ステップS122)。
Next, the man-hour management process for the work performed by the worker will be described.
FIG. 2 is an explanatory diagram showing an example of a mutual communication relationship between the project folder storage server and the man-hour management server when the worker computer works on the project folder storage server. The man-hour management server 30 registers in advance the information on the project m and the account information on the workers related to the project m by using the project registration function 31 and the account management function 32 (step S121). Then, a folder related to the project m is created in the project folder storage server 20 (step S111), and this folder is associated with the project m (step S122).

作業者用コンピュータ10は、プロジェクトmの作業を開始する準備として、プロジェクトフォルダ記憶サーバ20のプロジェクトmのフォルダにアクセスする(ステップS101)。プロジェクトフォルダ記憶サーバ20のフォルダ監視機能24は、このアクセスを作業開始のアクセスとして検知する(ステップS112)。具体的には、プロジェクトフォルダ記憶サーバ20はアクセスを検知すると、作業者用コンピュータ10に作業者認証IDなどの要求をする。フォルダ監視機能24は、作業者認証IDなどを受理すると、作業者用コンピュータ10のアクセスを工数管理サーバ30に通知する(ステップS113)。   The worker computer 10 accesses the folder of the project m in the project folder storage server 20 as a preparation for starting the work of the project m (step S101). The folder monitoring function 24 of the project folder storage server 20 detects this access as a work start access (step S112). Specifically, when the project folder storage server 20 detects access, the project folder storage server 20 requests the worker computer 10 for the worker authentication ID and the like. Upon receiving the worker authentication ID and the like, the folder monitoring function 24 notifies the man-hour management server 30 of access to the worker computer 10 (step S113).

工数管理サーバ30は、このアクセスを受信し(ステップS123)、作業者がプロジェクトmの登録作業者であるか否かを判定する(ステップS124)。作業者がプロジェクトmの登録作業者である場合は(ステップS124,Yes)、プロジェクトフォルダ記憶サーバ20にフォルダの開放を許可する(ステップS125)。   The man-hour management server 30 receives this access (step S123), and determines whether the worker is a registered worker of the project m (step S124). When the worker is a registered worker of project m (step S124, Yes), the project folder storage server 20 is permitted to open the folder (step S125).

プロジェクトフォルダ記憶サーバ20は、工数管理サーバ30からの開放許可に応じてフォルダを開き、作業者用コンピュータ10にフォルダおよびフォルダ内のファイルへの作業を許可して作業を受け入れる(ステップS114)。作業者用コンピュータ10は、フォルダ内のファイルにアクセスしてプロジェクトmの作業を開始する(ステップS102)。   The project folder storage server 20 opens the folder in response to the release permission from the man-hour management server 30, and accepts the work by allowing the worker computer 10 to work on the folder and the files in the folder (step S114). The worker computer 10 accesses the file in the folder and starts work on the project m (step S102).

プロジェクトフォルダ記憶サーバ20は、作業者用コンピュータ10のファイルへのアクセスをファイル監視機能25で検出し、その旨を工数管理サーバ30に通知する(ステップS115)。工数管理サーバ30は、このファイルアクセスを認識し(ステップS126)、作業者用コンピュータ10のプロジェクトmの作業工数の算出を開始する(ステップS127)。   The project folder storage server 20 detects the access to the file of the worker computer 10 by the file monitoring function 25 and notifies the man-hour management server 30 to that effect (step S115). The man-hour management server 30 recognizes this file access (step S126), and starts calculating the man-hours for the project m of the worker computer 10 (step S127).

これ以降、作業者用コンピュータ10は、フォルダにアクセスしてプロジェクトmの作業を継続する(ステップS103)。プロジェクトフォルダ記憶サーバ20は、必要に応じ作業者用コンピュータ10からのアクセスを受け入れて作業継続を許可する(ステップS116)。   Thereafter, the worker computer 10 accesses the folder and continues the work of the project m (step S103). The project folder storage server 20 accepts access from the worker computer 10 as necessary, and permits work to be continued (step S116).

作業者がプロジェクトフォルダを閉じると(ステップS104)、プロジェクトフォルダ記憶サーバ20のフォルダ監視機能24では、作業の終了アクセスを検知して(ステップS117)、作業者用コンピュータ10の作業終了を工数管理サーバ30に通知する(ステップS118)。   When the worker closes the project folder (step S104), the folder monitoring function 24 of the project folder storage server 20 detects the work end access (step S117), and determines the work end of the worker computer 10 as the man-hour management server. 30 is notified (step S118).

工数管理サーバ30は、この通知を受信し、作業者用コンピュータ10のプロジェクトmの作業工数の算出を終了する(ステップS128)。それとともに、どの作業者がどのプロジェクトの作業を何時開始して何時終了したかを記憶部39に記憶する。   The man-hour management server 30 receives this notification and ends the calculation of the man-hours for the project m of the worker computer 10 (step S128). At the same time, it is stored in the storage unit 39 which worker started and when finished which project.

作業工数の算出は、各種の方法が考えられるが、ここでは、ファイルへの最初のアクセスの時刻情報を作業開始時刻情報とし、ファイルが閉じられた場合、または、ファイルへのアクセスが所定時間がなかった場合に作業終了時刻情報として記憶部に記憶し、作業終了時刻情報と作業開始時刻情報とに基づいて作業時間を算出し管理している。   There are various methods for calculating the work man-hours. Here, the time information of the first access to the file is used as the work start time information, and when the file is closed or the file is accessed for a predetermined time. If not, the work end time information is stored in the storage unit, and the work time is calculated and managed based on the work end time information and the work start time information.

なお、ステップS124で作業者がプロジェクトmの登録作業者で無かった場合は(ステップS124、No)、プロジェクトフォルダ記憶サーバ20にフォルダの開放を許可せず(ステップS129)、プロジェクトフォルダ記憶サーバ20はプロジェクトmのフォルダを開かない(ステップS119)。そして、作業者用コンピュータ10は、非該当プロジェクトであることを受信する(ステップS120)。   If the worker is not a registered worker of project m in step S124 (No in step S124), the project folder storage server 20 does not allow the project folder storage server 20 to release the folder (step S129). The folder of project m is not opened (step S119). Then, the worker computer 10 receives that the project is not applicable (step S120).

図3は、工数管理サーバでの作業実績の収集データの一覧の例を示す説明図である。収集データは、ステップS126での作業者用コンピュータ10のファイルアクセスの認識時刻およびステップS128での作業者用コンピュータ10の作業終了の認識時刻を、時刻経過順に、作業をした作業者用コンピュータ番号、プロジェクト番号および作業開始(O)と作業終了(E)の区別をつけて示している。なお、作業者用コンピュータ番号は、ステップS112およびステップS117において、IP(Internet Protocol)アドレス(アクセスの端末を識別するアドレス情報)などで特定することができる。   FIG. 3 is an explanatory diagram showing an example of a list of collected data of work results in the man-hour management server. The collected data includes the recognition time of the file access of the worker computer 10 in step S126 and the recognition time of the work completion of the worker computer 10 in step S128 in the order of time passage, the computer number of the worker who worked. The project number and the work start (O) and work end (E) are distinguished from each other. The worker computer number can be specified in step S112 and step S117 by an IP (Internet Protocol) address (address information for identifying an access terminal) or the like.

図4は、プロジェクト毎の作業実績の結果データの一覧の例を示す説明図である。図3に示した収集データを並び替えて、プロジェクト毎に、一連の作業の作業時間と作業をした作業者用コンピュータ番号および現在までの工数集計時間を示したプロジェクト別の作業実績収集結果データである。この集計により作業工数が集積される。   FIG. 4 is an explanatory diagram showing an example of a list of result data of work results for each project. The collected data shown in Fig. 3 is rearranged, and for each project, work result collection result data for each project showing the work time of a series of work, the computer number for the worker who performed the work, and the total man-hours up to now is there. The operation man-hour is accumulated by this aggregation.

本実施形態の工数管理システムは、作業者用コンピュータ10のプロジェクトフォルダ記憶サーバ20内の各フォルダへのアクセスを、プロジェクトフォルダ記憶サーバ20が監視して工数管理サーバ30に通知することにより、自動的にプロジェクト毎の作業の開始・終了が記憶でき、工数も自動的に計数できる。したがって、作業者は特別な処理をすることなく、記憶に頼ることが無いので、正確な工数計算が自動的に実行できる。   The man-hour management system of the present embodiment automatically monitors the project folder storage server 20 by monitoring the access to each folder in the project folder storage server 20 of the worker computer 10 and notifies the man-hour management server 30 of the access. The start / end of work for each project can be memorized, and man-hours can be automatically counted. Therefore, since the worker does not depend on memory without performing special processing, accurate man-hour calculation can be automatically executed.

また、プロジェクトフォルダ記憶サーバ20のフォルダ内のファイルへのアクセスをトリガにして工数管理サーバ30で工数計算を行っているため、作業者用コンピュータ10内に工数計算用のアプリケーションソフトが必要でなく、工数計算用のアプリケーションソフトを立ち上げる必要も無いので操作が容易になる。なお、プロジェクトフォルダ記憶サーバ20内の各フォルダで作業できないような工数、例えば、紙に手書きの作業や打ち合わせなどについては、別途、工数管理サーバ30に手入力できるようにしてもよい。   In addition, since the man-hour calculation is performed by the man-hour management server 30 triggered by access to the files in the folder of the project folder storage server 20, no application software for man-hour calculation is required in the worker computer 10, Operation is easy because there is no need to launch application software for calculating man-hours. It should be noted that man-hours that cannot be performed in each folder in the project folder storage server 20, for example, hand-written work or meetings on paper, may be manually input to the man-hour management server 30.

この第1の実施形態の変形例として、作業者用コンピュータ10に作業工数算出機能を含め、工数管理サーバ30には作業工数算出機能を含めず、作業者用コンピュータ10が求めた作業工数を集計する機能を設けるようにすることもできる。これにより、各作業者が行った作業工数は、プロジェクト毎に作業者用コンピュータ10によって算出され、各作業者用コンピュータ10毎に記憶され保管されることになる。プロジェクト毎の複数作業者の工数を集計する場合は、工数管理サーバ30が適当な時期に作業工数集計機能で各作業者用コンピュータ10から読み出して集計する。この実施形態では、各作業者が自分の行った作業工数を、いつでもプロジェクト毎に容易に確かめることができるという利点がある。   As a modified example of the first embodiment, the work man-hour calculation function is included in the worker computer 10 and the work man-hour calculation function is not included in the man-hour management server 30, and the work man-hours obtained by the worker computer 10 are tabulated. It is also possible to provide a function to do this. As a result, the man-hours performed by each worker are calculated by the worker computer 10 for each project, and are stored and stored for each worker computer 10. When totaling the man-hours of a plurality of workers for each project, the man-hour management server 30 reads out the data from each worker's computer 10 and totals it at an appropriate time by the work man-hour totaling function. In this embodiment, there is an advantage that each worker can easily check the work man-hours performed by each worker every project.

《第2の実施形態》
図5は、本発明の第2の実施形態である作業管理システムを示すブロック図である。図5において、本実施形態の作業管理システムは、複数の作業者用コンピュータ10a(10)、10b(10)、10c(10)などと、工数管理サーバ30Aと、これらを結ぶネットワーク40から構成される。第2の実施形態は、第1の実施形態と比較して、プロジェクトフォルダ記憶サーバ20を用いないで、プロジェクトの作業は、作業者用コンピュータ10で実施する場合である。図5において、図1に記載の同一構成品については同一符号を付しており、説明を省略する。
<< Second Embodiment >>
FIG. 5 is a block diagram showing a work management system according to the second embodiment of the present invention. In FIG. 5, the work management system of this embodiment includes a plurality of workers' computers 10a (10), 10b (10), 10c (10), a man-hour management server 30A, and a network 40 connecting them. The Compared to the first embodiment, the second embodiment is a case where the project folder storage server 20 is not used and the project work is performed by the worker computer 10. In FIG. 5, the same components as those shown in FIG.

作業者用コンピュータ10は、作業者がプロジェクトに関する作業を行うコンピュータであって、通常のコンピュータとしての機能に加えて、工数管理サーバ30から送られるキーワードを含んだアプリケーションソフトをインストールするアプリケーションソフトインストール機能12a(12)、入力手段から入力される単語のうち出現頻度が高いものであってすでにキーワードとして選ばれていないものをキーワード候補として抽出するキーワード候補抽出機能13a(13)、抽出されたキーワード候補を所定の時点に工数管理サーバ30へ送信するキーワード候補送信機能14a(14)と、工数管理サーバ30で決定されたキーワードを検出した場合に工数管理サーバ30へ通知するキーワード検出通知機能15a(15)を備えている。   The worker computer 10 is a computer on which a worker performs work related to a project, and in addition to a function as a normal computer, an application software installation function that installs application software including a keyword sent from the man-hour management server 30 12a (12), a keyword candidate extraction function 13a (13) that extracts words that have a high appearance frequency and are not already selected as keywords from among the words input from the input means, and extracted keyword candidates Is transmitted to the man-hour management server 30 at a predetermined time, and a keyword detection notification function 15a (15) for notifying the man-hour management server 30 when a keyword determined by the man-hour management server 30 is detected. ) To have.

アプリケーションソフトインストール機能12によってインストールされるアプリケーションソフトには、プロジェクト毎に決められたキーワードを示すリストが含まれている。このリストは、例えば、図6に示すようにプロジェクト毎にそのプロジェクトに属するキーワードが分類され、プロジェクト毎に別々の異なるキーワードが示されて、検索が容易なように構成されている。   The application software installed by the application software installation function 12 includes a list indicating keywords determined for each project. For example, as shown in FIG. 6, the list is configured so that keywords belonging to the project are classified for each project, and different keywords are shown for each project, so that the search is easy.

図5に戻って、工数管理サーバ30Aは、プロジェクトを登録しプロジェクトの情報を管理するプロジェクト登録機能31、プロジェクトに従事する関連作業者の情報であるアカウント情報を管理するアカウント管理機能32、プロジェクト毎の作業工数を算出して管理する作業工数算出機能33、作業者用コンピュータ10から送られるキーワード候補を記憶するキーワード候補記憶機能34、複数のキーワード候補からプロジェクト毎のキーワードを選定するキーワード選定機能35、作業者用コンピュータ10にアプリケーションソフトを配信するアプリケーションソフト配信機能36を備えている。   Returning to FIG. 5, the man-hour management server 30 </ b> A registers a project and manages project information, a project registration function 31, an account management function 32 that manages account information that is information of related workers engaged in the project, and for each project. The work man-hour calculating function 33 for calculating and managing the work man-hours, the keyword candidate storing function 34 for storing the keyword candidates sent from the operator computer 10, and the keyword selecting function 35 for selecting keywords for each project from a plurality of keyword candidates. An application software distribution function 36 for distributing application software to the worker computer 10 is provided.

特に、アプリケーションソフト配信機能36は、プロジェクトに特有の少なくとも1つのキーワードと、逐次入力される入力信号に含まれる単語情報とキーワードの何れかとが一致したことを示す一致情報を工数管理サーバ30Aに送信するアプリケーションプログラムとを前記作業用端末に送信する機能を有する。なお、作業者用コンピュータ10、工数管理サーバ30AはすべてLANなどのネットワーク40で接続されており、相互にデータやファイルのやり取りができるようになっている。   In particular, the application software distribution function 36 transmits to the man-hour management server 30A coincidence information indicating that at least one keyword specific to the project matches one of the keyword and the word information included in the sequentially input signal. And an application program to be transmitted to the work terminal. Note that the operator computer 10 and the man-hour management server 30A are all connected by a network 40 such as a LAN, and can exchange data and files with each other.

次に、作業者が実施する作業の工数管理の処理について説明する。
図7および図8は、作業者用コンピュータで作業する際の作業者用コンピュータおよび工数管理サーバとの相互通信関係の一例を示す説明図である。図7において、工数管理サーバ30Aは、予め、プロジェクト登録機能31およびアカウント管理機能32によってプロジェクトの情報とプロジェクト毎の関連作業者に関するアカウント情報をあわせて登録しておく(ステップS230)。そうして、現在がキーワード候補を収集する作業を行うキーワード学習期間か、通常の作業期間かを、作業者用コンピュータ10側(ステップS201)と工数管理サーバ30A側(ステップS231)とでそれぞれ判定する。作業者用コンピュータ10は、工数管理サーバ30Aにアクセスし、WEB画面などを用いて、作業者が所定項目について入力する。作業者用コンピュータ10から学習期間でないと入力されると(ステップS201,No)、図8のステップS210へ進む。工数管理サーバ30A側で学習期間でないと判定した場合は(ステップS231,No)、図8のステップS241へ進む。一方、工数管理サーバ30A側で学習期間であると判定した場合は(ステップS231,Yes)、ステップS232へ進む。
Next, the man-hour management process for the work performed by the worker will be described.
7 and 8 are explanatory diagrams illustrating an example of a mutual communication relationship between the worker computer and the man-hour management server when working with the worker computer. In FIG. 7, the man-hour management server 30A registers in advance the project information and the account information regarding the related workers for each project by the project registration function 31 and the account management function 32 (step S230). Thus, it is determined on the worker computer 10 side (step S201) and the man-hour management server 30A side (step S231) whether the keyword learning period for performing the task of collecting keyword candidates or the normal work period. To do. The worker computer 10 accesses the man-hour management server 30A, and the worker inputs a predetermined item using a WEB screen or the like. If it is input from the operator computer 10 that it is not the learning period (step S201, No), the process proceeds to step S210 in FIG. If the man-hour management server 30A determines that it is not the learning period (step S231, No), the process proceeds to step S241 in FIG. On the other hand, when it is determined on the man-hour management server 30A side that it is the learning period (step S231, Yes), the process proceeds to step S232.

作業者用コンピュータ10側で学習期間の場合は(ステップS201,Yes)、実行する可能性のある複数の作業プロジェクトを工数管理サーバ30A側に指定する(ステップS202)。工数管理サーバ30A側ではアクセスを受けて(ステップS232)、作業者が指定されたプロジェクトの作業者であるか否かを判定する(ステップS233)。指定プロジェクトの作業者でない場合は(ステップS233,No)、該当しないプロジェクトである旨を作業者用コンピュータ10に通知し(ステップS234)、作業者用コンピュータ10側では非該当プロジェクトである旨の通知を受けとる(ステップS203)。実際には、この場合、該当するプロジェクトのフォルダを開かせないなどの方法で作業者用コンピュータ10のアクセスを禁止する。   In the case of the learning period on the worker computer 10 side (step S201, Yes), a plurality of work projects that may be executed are designated on the man-hour management server 30A side (step S202). The man-hour management server 30A side receives access (step S232), and determines whether or not the worker is a worker of the designated project (step S233). If it is not the worker of the designated project (step S233, No), the worker computer 10 is notified that the project is not applicable (step S234), and the worker computer 10 is notified that the project is not applicable. Is received (step S203). Actually, in this case, access to the worker computer 10 is prohibited by a method such as not opening the folder of the corresponding project.

一方、作業者が指定プロジェクトの作業者である場合は(ステップS233,Yes)、工数管理サーバ30Aは、アプリケーションソフト配信機能36を用いて学習期間用のアプリケーションプログラムを作業者用コンピュータ10側に送り(ステップS235)、作業者用コンピュータ10は、アプリケーションソフトインストール機能12を用いてこれを受信して立ち上げる(ステップS204)。そうして、作業者用コンピュータ10は、このアプリケーションプログラムを用いてプロジェクト作業を開始し、プロジェクト作業の開始を工数管理サーバ30Aへ通知する(ステップS205)。工数管理サーバ30Aは、この作業の通知を受信して作業工数算出機能33で作業者用コンピュータ10の作業工数算出を開始する(ステップS236)。   On the other hand, when the worker is a worker of the designated project (step S233, Yes), the man-hour management server 30A uses the application software distribution function 36 to send the application program for the learning period to the worker computer 10 side. (Step S235), the worker computer 10 receives the application software installation function 12 and starts it (Step S204). Then, the worker computer 10 starts the project work using this application program, and notifies the man-hour management server 30A of the start of the project work (step S205). The man-hour management server 30A receives the notification of the work, and starts the work man-hour calculation of the worker computer 10 by the work man-hour calculating function 33 (step S236).

ここで、作業者用コンピュータ10では2つの作業が並行して行われる。1つはプロジェクトの作業であり、もう1つはキーワード候補抽出機能13によりステップS205で開始される入力手段から入力される単語の出現頻度からのキーワード候補の抽出である(ステップS206)。プロジェクト作業が終了するまでこれらの作業は並行して進められる。キーワードの抽出方法は、一般的に使われるキーワード検索エンジンやキーロガーの仕組みを適用することができる。なお、入力手段は、キーボードやマイクなどである。例えば、入力信号は、作業者用コンピュータ10のキーボード信号となる。   Here, in the computer 10 for workers, two work is performed in parallel. One is the work of the project, and the other is the extraction of keyword candidates from the appearance frequency of words input from the input means started in step S205 by the keyword candidate extraction function 13 (step S206). These work will proceed in parallel until the project work is completed. As a keyword extraction method, a commonly used keyword search engine or keylogger mechanism can be applied. The input means is a keyboard or a microphone. For example, the input signal is a keyboard signal of the operator computer 10.

プロジェクト作業の終了は、工数管理サーバ30Aに通知され(ステップS207)、工数管理サーバ30Aはこれを受信して作業工数算出機能33での作業者用コンピュータ10の作業工数算出を終了する(ステップS237)。そうして、作業者用コンピュータ10でのキーワード候補の抽出も終了する。プロジェクト作業が終了した時点などの所定の時点で抽出されたキーワード候補は、キーワード候補送信機能14によって工数管理サーバ30Aへ送信される(ステップS208)。なお、キーワード候補の送信は、プロジェクト作業終了のときに抽出結果をまとめて送信しているが、抽出したときに、随時送信してもよい。   The completion of the project work is notified to the man-hour management server 30A (step S207), and the man-hour management server 30A receives this and finishes the work man-hour calculation of the worker computer 10 by the work man-hour calculation function 33 (step S237). ). Thus, the extraction of keyword candidates on the operator computer 10 is also completed. The keyword candidates extracted at a predetermined time such as when the project work is completed are transmitted to the man-hour management server 30A by the keyword candidate transmission function 14 (step S208). In addition, although the keyword candidate is transmitted together with the extraction result at the end of the project work, it may be transmitted at any time when it is extracted.

プロジェクト作業が終了し、キーワード候補の送信が終了した時点で、キーワード学習期間を終了するか否かが判定され、改めて別なプロジェクトについてキーワード学習期間を継続する場合は(ステップS209,No)、ステップS202へ戻り、キーワード学習期間を終了する場合は(ステップS209,Yes)、図8のステップS210へ進む。   When the project work is finished and the transmission of keyword candidates is finished, it is determined whether or not to end the keyword learning period, and if the keyword learning period is continued for another project again (No in step S209), step Returning to S202, if the keyword learning period is to be ended (step S209, Yes), the process proceeds to step S210 in FIG.

工数管理サーバ30Aでは、キーワード候補記憶機能34によって複数の作業者用コンピュータ10からキーワード候補を受信して保存する(ステップS238)。そうして、こうして保存された複数のキーワード候補からキーワード選定機能35によってキーワードを選定する(ステップS239)。選定の方法は、使用頻度順である閾値以上のものを選定する。複数のプロジェクトで頻繁に用いられる単語は一般の単語としてキーワードには選定しない。予めプロジェクトで使用される単語が特定できる場合には、別途登録しておくこともできる。そうして、新たに選定したキーワードをアプリケーションプログラムに含める(ステップS240)。その後、図8のステップS241に進む。   In the man-hour management server 30A, keyword candidates are received from the plurality of workers' computers 10 by the keyword candidate storage function 34 and stored (step S238). Then, keywords are selected by the keyword selection function 35 from the plurality of keyword candidates thus saved (step S239). As a selection method, a method that is equal to or higher than a threshold value in order of use frequency is selected. Words frequently used in multiple projects are not selected as keywords as general words. If the words used in the project can be specified in advance, they can be registered separately. Then, the newly selected keyword is included in the application program (step S240). Thereafter, the process proceeds to step S241 in FIG.

キーワード学習期間を終了した後、あるいはキーワード学習期間でなく通常のプロジェクト作業の場合には、作業者用コンピュータ10は、実行する作業プロジェクトを指定して、工数管理サーバ30Aに通知する(ステップS210)。   After the keyword learning period ends, or in the case of normal project work instead of the keyword learning period, the worker computer 10 designates the work project to be executed and notifies the man-hour management server 30A (step S210). .

工数管理サーバ30Aは、このプロジェクトの指定通知を受信して(ステップS241)、作業者が指定されたプロジェクトの作業者であるか否かをアカウント管理機能32で判定する(ステップS242)。作業者が指定されたプロジェクトの作業者である場合は(ステップS242,Yes)、アプリケーションソフト配信機能36を用いて、ステップS240で更新した各プロジェクトのキーワードを含むアプリケーションプログラムを作業者用コンピュータ10に送信する(ステップS243)。   The man-hour management server 30A receives this project designation notification (step S241), and determines whether or not the worker is a worker of the designated project by the account management function 32 (step S242). If the worker is a worker of the designated project (step S242, Yes), the application program including the keyword of each project updated in step S240 is stored in the worker computer 10 using the application software distribution function 36. Transmit (step S243).

作業者用コンピュータ10は、工数管理サーバ30Aから送られたキーワードを含むアプリケーションプログラムをアプリケーションソフトインストール機能12を用いて受信し、立ち上げる(ステップS211)。そうして、プロジェクトの作業を開始する(ステップS212)。作業者用コンピュータ10のキーワード検出通知機能15は、作業を開始後、入力装置から入力される単語の中に、実行しているプロジェクトのキーワードを検出した場合、その旨を工数管理サーバ30Aに通知する(ステップS213)。   The worker computer 10 receives the application program including the keyword sent from the man-hour management server 30A using the application software installation function 12 and starts it (step S211). Then, the project work is started (step S212). When the keyword detection notification function 15 of the worker computer 10 starts the work and detects the keyword of the project being executed in the words input from the input device, it notifies the man-hour management server 30A to that effect. (Step S213).

工数管理サーバ30Aは、作業者用コンピュータ10からのキーワード検出の通知を受信すると、作業工数算出機能33を用いて作業者用コンピュータ10の作業工数算出を開始する。また、すでに作業工数算出を行っている場合はその作業を継続する(ステップS244)。   When the man-hour management server 30 </ b> A receives the keyword detection notification from the worker computer 10, the man-hour management server 30 </ b> A starts the work man-hour calculation of the worker computer 10 using the work man-hour calculating function 33. If the work man-hour has already been calculated, the work is continued (step S244).

プロジェクトの作業を実行中に、入力装置から入力される単語の中に、実行しているプロジェクトとは異なる他のプロジェクトのキーワードが検出されたか否か判定する(ステップS214)。検出した場合(ステップS214,Yes)、その旨を工数管理サーバ30Aに通知し(ステップS215)、他のプロジェクトの作業に移り(ステップS219)、ステップS210に戻る。あるいは、直ちにステップS213に戻るようにしてもよい。   While executing the project work, it is determined whether or not a keyword of another project different from the project being executed is detected in the words input from the input device (step S214). If it is detected (step S214, Yes), the fact is notified to the man-hour management server 30A (step S215), and the operation moves to another project (step S219), and the process returns to step S210. Or you may make it return to step S213 immediately.

作業者用コンピュータ10は、他のプロジェクトのキーワードを検出しない場合(ステップS214,No)実行しているプロジェクトに属するキーワードを所定時間にわたって検出しないか否かを判定する(ステップS216)。所定時間検出しなかった場合(ステップS216,Yes)、所定時間キーワード検出なしの旨を工数管理サーバ30Aに通知し(ステップS217)、特に要求がない限り作業を終了する。実行しているプロジェクトに属するキーワードの検出に大幅な途切れがない場合は(ステップS216,No)、実行しているプロジェクトの作業を継続(続行)して(ステップS218)、ステップS213に戻る。   When the operator computer 10 does not detect a keyword of another project (step S214, No), it determines whether or not a keyword belonging to the project being executed is not detected for a predetermined time (step S216). If it is not detected for a predetermined time (step S216, Yes), the fact that no keyword is detected for a predetermined time is notified to the man-hour management server 30A (step S217), and the operation is terminated unless otherwise requested. If there is no significant interruption in the detection of keywords belonging to the project being executed (No in step S216), the operation of the project being executed is continued (continue) (step S218), and the process returns to step S213.

一方、工数管理サーバ30Aは、ステップS244ののち、作業者用コンピュータ10からのプロジェクトのキーワード検出の通知あるいはをキーワードを所定時間にわたって検出しない通知を受け取ると、作業工数算出機能33での作業者用コンピュータ10の作業工数算出を終了する(ステップS245)。   On the other hand, when the man-hour management server 30A receives the notification of the keyword detection of the project from the operator computer 10 or the notification that the keyword is not detected for a predetermined time after the step S244, the man-hour management server 30A The calculation of the work man-hour of the computer 10 is finished (step S245).

ステップS242で、作業者が指定されたプロジェクトの作業者でない場合は(ステップS242,No)、該当しないプロジェクトであることを作業者用コンピュータ10に通知して(ステップS246)、処理を終了する。   If it is determined in step S242 that the worker is not a worker of the designated project (step S242, No), the worker computer 10 is notified that the project is not applicable (step S246), and the process is terminated.

本実施形態の工数管理システムは、作業の開始終了をキーワードの出現をトリガにして判定しているので、自動的に作業の開始・終了を記録することができる。したがって、工数も自動的に記録管理でき、作業者の記憶やメモに頼らないため、正確な工数の記録が可能になる。また、作業者用コンピュータ10に工数管理用のアプリケーションプログラムをインストールし、このアプリケーションプログラムによるキーワード検出によって工数管理を行っているので、作業対象のフォルダ、ファイルの格納位置に依存することなく工数管理が可能になる。   Since the man-hour management system according to the present embodiment determines the start / end of work by using the appearance of a keyword as a trigger, the start / end of work can be automatically recorded. Accordingly, man-hours can be automatically recorded and managed, and since it does not depend on the memory or memo of the worker, accurate man-hours can be recorded. In addition, since an application program for man-hour management is installed in the worker computer 10 and man-hour management is performed by keyword detection using this application program, man-hour management can be performed without depending on the storage location of the folder or file to be worked on. It becomes possible.

本発明は、上記した実施形態に限定されるものではなく、本発明の趣旨に反しない範囲で種々の変形が可能である。例えば、第2の実施形態で、作業工数の算出を工数管理サーバで行う代わりに、作業者用コンピュータ10で行うようにし、作業者用コンピュータ10はキーワードが検出されると作業工数の算出を開始するようにし、作業工数の終了時など適当な時期に集計した作業工数を工数管理サーバに通知するようにしてもよい。これによって、ネットワーク上の通信の輻輳を緩和することができる効果がある。   The present invention is not limited to the above-described embodiment, and various modifications can be made without departing from the spirit of the present invention. For example, in the second embodiment, the work man-hour is calculated by the worker computer 10 instead of by the man-hour management server, and the worker computer 10 starts calculating the man-hour when the keyword is detected. It is also possible to notify the man-hour management server of the man-hours collected at an appropriate time such as when the man-hours are completed. This has the effect of reducing communication congestion on the network.

第2の実施形態で使用される工数管理サーバ30Aの作業管理プログラムは、プロジェクトに特有の少なくとも1つのキーワードと、逐次入力される入力信号に含まれる単語情報とキーワードの何れかとが一致したことを示す一致情報を工数管理サーバ30Aに送信するアプリケーションプログラムとを、作業者用コンピュータ10に送信するアプリケーションソフト配信機能36と、一致情報を作業者用コンピュータ10から受信した時刻である作業開始時刻と、所定時間にわたって一致情報を受信できなくなったときの時刻である作業終了時刻とに基づいて作業時間を算出する作業工数算出機能33と、を有している。   The work management program of the man-hour management server 30A used in the second embodiment confirms that at least one keyword specific to the project matches one of the keyword and the word information included in the input signal sequentially input. An application program for transmitting the matching information to the man-hour management server 30A to the worker computer 10, an application software distribution function 36 for transmitting to the worker computer 10, and a work start time that is the time when the matching information is received from the worker computer 10. And a work man-hour calculating function 33 that calculates a work time based on a work end time that is a time when the coincidence information cannot be received for a predetermined time.

また、アプリケーションプログラムは、他のプロジェクトに属する少なくとも1つの他のキーワードを含めて送信し、他のプロジェクトに属するキーワードの何れかを検出したときの検出時刻の情報を工数管理サーバ30Aに送信させ、作業工数算出機能33は、作業用端末から受信した検出時刻を作業終了時刻として作業時間を算出することができる。   In addition, the application program transmits including at least one other keyword belonging to another project, and causes the man-hour management server 30A to transmit information on the detection time when any of the keywords belonging to the other project is detected, The work man-hour calculating function 33 can calculate the work time using the detection time received from the work terminal as the work end time.

本発明の第1の実施形態である作業管理システムを示すブロック図である。It is a block diagram which shows the work management system which is the 1st Embodiment of this invention. 作業者用コンピュータがプロジェクトフォルダ記憶サーバで作業する際のプロジェクトフォルダ記憶サーバおよび工数管理サーバとの相互通信関係の一例を示す説明図である。It is explanatory drawing which shows an example of the mutual communication relationship with the project folder storage server and man-hour management server at the time of the computer for workers working with a project folder storage server. 工数管理サーバでの作業実績の収集データの一覧の例を示す説明図である。It is explanatory drawing which shows the example of the list of the collection data of the work results in a man-hour management server. プロジェクト毎の作業実績の結果データの一覧の例を示す説明図である。It is explanatory drawing which shows the example of the list of the result data of the work results for every project. 本発明の第2の実施形態である作業管理システムを示すブロック図である。It is a block diagram which shows the work management system which is the 2nd Embodiment of this invention. アプリケーションソフトに含まれるキーワードリストの一例を示す説明図である。It is explanatory drawing which shows an example of the keyword list contained in application software. 作業者用コンピュータで作業する際の作業者用コンピュータおよび工数管理サーバとの相互通信関係の一例を示す説明図である。It is explanatory drawing which shows an example of the mutual communication relationship with the computer for workers at the time of working with the computer for workers, and a man-hour management server. 作業者用コンピュータで作業する際の作業者用コンピュータおよび工数管理サーバとの相互通信関係の一例を示す説明図である。It is explanatory drawing which shows an example of the mutual communication relationship with the computer for workers at the time of working with the computer for workers, and a man-hour management server.

符号の説明Explanation of symbols

10 作業者用コンピュータ(作業用端末)
12 アプリケーションソフトインストール機能
13 キーワード候補抽出機能
14 キーワード候補送信機能
15 キーワード検知通知機能
20 プロジェクトフォルダ記憶サーバ(ファイルサーバ)
21 フォルダA
22 フォルダB
23 フォルダC
24 フォルダ監視機能
25 ファイル監視機能
30,30A 工数管理サーバ(管理サーバ)
31 プロジェクト登録機能
32 アカウント管理機能
33 作業工数算出機能
34 キーワード候補記憶機能
35 キーワード選定機能
36 アプリケーションソフト配信機能
39 記憶部
40 ネットワーク
10 Computer for workers (working terminal)
12 Application software installation function 13 Keyword candidate extraction function 14 Keyword candidate transmission function 15 Keyword detection notification function 20 Project folder storage server (file server)
21 Folder A
22 Folder B
23 Folder C
24 Folder monitoring function 25 File monitoring function 30, 30A Man-hour management server (management server)
31 Project Registration Function 32 Account Management Function 33 Work Effort Calculation Function 34 Keyword Candidate Storage Function 35 Keyword Selection Function 36 Application Software Distribution Function 39 Storage Unit 40 Network

Claims (11)

1つ以上の作業用端末と、前記作業用端末の作業時間を管理する処理部および記憶部を有する管理サーバとを備える作業管理システムであって、
前記処理部は、作業用のプロジェクト毎に設けられたプロジェクトフォルダを前記記憶部に作成し、前記作業用端末から前記プロジェクトフォルダ内のファイルにアクセスがあると、前記ファイルへのアクセスの時刻情報と、前記プロジェクトの情報とを関連付けて前記記憶部に記憶する
ことを特徴とする作業管理システム。
A work management system comprising one or more work terminals, and a management server having a processing unit and a storage unit for managing work times of the work terminals,
The processing unit creates a project folder provided for each work project in the storage unit, and when a file in the project folder is accessed from the work terminal, time information of access to the file and The work management system is characterized in that the information on the project is associated with and stored in the storage unit.
前記処理部は、前記ファイルへの最初のアクセスの時刻情報を作業開始時刻情報とし、前記ファイルが閉じられた場合の時刻、または、前記ファイルへのアクセスが所定時間なかった場合の時刻を作業終了時刻情報として前記記憶部に記憶し、前記作業終了時刻情報と前記作業開始時刻情報とに基づいて作業時間を算出し管理する
ことを特徴とする請求項1に記載の作業管理システム。
The processing unit uses the time information of the first access to the file as work start time information, and ends the time when the file is closed or when the file is not accessed for a predetermined time. The work management system according to claim 1, wherein time information is stored in the storage unit, and a work time is calculated and managed based on the work end time information and the work start time information.
1つ以上の作業用端末と、作業用のファイルを格納するプロジェクト毎に設けられたプロジェクトフォルダを有するファイルサーバと、前記作業用端末の作業時間を管理する管理サーバとを備える作業管理システムであって、
前記ファイルサーバは、前記作業用端末から、前記プロジェクトフォルダ内のファイルにアクセスがあると、前記ファイルへのアクセスの時刻情報および前記プロジェクトの情報とを含むアクセス監視情報を前記管理サーバに送信し、
前記管理サーバは、受信した前記アクセス監視情報を記憶部に記憶する
ことを特徴とする作業管理システム。
A work management system comprising one or more work terminals, a file server having a project folder provided for each project for storing work files, and a management server for managing work time of the work terminals. And
When the file in the project folder is accessed from the work terminal, the file server transmits access monitoring information including time information of access to the file and information of the project to the management server,
The management server stores the received access monitoring information in a storage unit.
1つ以上の作業用端末と、前記作業用端末で行われるプロジェクト毎の作業の管理をする管理サーバとを備える作業管理システムであって、
前記作業用端末は、前記プロジェクト毎の入力信号に含まれる単語情報から前記単語情報の出現回数によって複数のキーワード候補を選択して前記管理サーバに送信するとともに、前記入力信号中に前記プロジェクト毎に予め前記管理サーバによって設定された複数のキーワードのうちのいずれかを検出した時刻を作業開始時刻情報として、また、所定時間にわたって前記複数のキーワードのいずれをも検出できなくなった時刻および他のプロジェクトに属する複数のキーワードのうちのいずれかを検出した時刻を作業終了時刻情報として、前記管理サーバに通知し、
前記管理サーバは、受信した前記通知を記憶部に記憶し、前記通知に基づいて作業時間を算出し管理する
ことを特徴とする作業管理システム。
A work management system comprising one or more work terminals and a management server that manages work for each project performed on the work terminals,
The work terminal selects a plurality of keyword candidates from the word information included in the input signal for each project according to the number of appearances of the word information and transmits the selected keyword candidates to the management server, and for each project in the input signal The time when any one of the plurality of keywords set in advance by the management server is detected as work start time information, and the time when any of the plurality of keywords cannot be detected over a predetermined time and other projects Notifying the management server of the time at which one of the plurality of keywords belonging is detected as work end time information,
The said management server memorize | stores the received said notification in a memory | storage part, and calculates and manages work time based on the said notification. The work management system characterized by the above-mentioned.
前記管理サーバは、前記作業用端末から送られた前記複数のキーワード候補から前記プロジェクト毎に複数のキーワードを決定して登録するとともに、前記作業用端末のプロジェクト作業の開始にあたり前記作業用端末に前記登録したキーワードを送信する
ことを特徴とする請求項4に記載の作業管理システム。
The management server determines and registers a plurality of keywords for each project from the plurality of keyword candidates sent from the work terminal, and at the start of the project work of the work terminal, the work terminal The registered keyword is transmitted. The work management system according to claim 4, wherein the registered keyword is transmitted.
前記管理サーバは、前記作業用端末から送られた前記複数のキーワード候補から前記プロジェクト毎に複数のキーワードを決定して登録するとともに、前記作業用端末に前記登録したキーワードを含むキーワードを検出するアプリケーションソフトを送信する
ことを特徴とする請求項4に記載の作業管理システム。
The management server determines and registers a plurality of keywords for each project from the plurality of keyword candidates sent from the work terminal, and detects a keyword including the registered keyword in the work terminal The work management system according to claim 4, wherein software is transmitted.
作業用端末の作業時間を管理する管理サーバであるコンピュータの作業管理プログラムであって、
前記コンピュータに、
作業用のプロジェクト毎に設けられたプロジェクトフォルダを作成し登録するプロジェクト登録機能と、
前記作業用端末からの前記プロジェクトフォルダ内のファイルへのアクセスを監視し、前記ファイルへの最初のアクセス時刻を作業開始時刻情報とし、前記ファイルが閉じられた場合の時刻、または、前記ファイルへのアクセスが所定時間がなかった場合の時刻を作業終了時刻情報とし、前記作業開始時刻情報または前記作業終了時刻情報と、前記プロジェクトの情報とを関連付けて記憶部に記憶するファイル監視機能と、
前記作業終了時刻情報と前記作業開始時刻情報とに基づいて作業時間を算出し管理する作業工数算出機能と、
を実現させることを特徴とする作業管理プログラム。
A work management program for a computer, which is a management server for managing the work time of a work terminal,
In the computer,
A project registration function that creates and registers a project folder for each work project;
The access to the file in the project folder from the work terminal is monitored, the first access time to the file is set as work start time information, the time when the file is closed, or the file A file monitoring function for storing the work start time information or the work end time information and the information of the project in a storage unit in association with the time when the access has not been performed for a predetermined time as work end time information,
A work man-hour calculating function for calculating and managing a work time based on the work end time information and the work start time information;
The work management program characterized by realizing.
作業用端末で行われるプロジェクト毎の作業を管理する管理サーバであるコンピュータの作業管理プログラムであって、
前記コンピュータに、
前記プロジェクトに特有の少なくとも1つのキーワードと、逐次入力される入力信号に含まれる単語情報と前記キーワードのいずれかとが一致したことを示す一致情報を前記管理サーバに送信するアプリケーションプログラムとを前記作業用端末に送信するアプリケーションソフト配信機能と、
前記一致情報を前記作業用端末から受信した時刻である作業開始時刻と、所定時間にわたって前記一致情報を受信できなくなったときの時刻である作業終了時刻とに基づいて作業時間を算出する作業工数算出機能と、
を実現させることを特徴とする作業管理プログラム。
A work management program for a computer that is a management server that manages work for each project performed on a work terminal,
In the computer,
An application program for transmitting to the management server at least one keyword specific to the project and matching information indicating that word information included in an input signal sequentially input matches any of the keywords Application software distribution function to send to the terminal,
Man-hour calculation for calculating a work time based on a work start time that is a time when the match information is received from the work terminal and a work end time that is a time when the match information cannot be received for a predetermined time. Function and
The work management program characterized by realizing.
前記アプリケーションプログラムは、他のプロジェクトに属する少なくとも1つの他のキーワードを含めて送信し、前記他のプロジェクトに属するキーワードの何れかを検出したときの検出時刻の情報を前記管理サーバに送信させ、
前記作業工数算出機能は、前記作業用端末から受信した検出時刻を前記作業終了時刻として前記作業時間を算出することを特徴とする請求項8に記載の作業管理プログラム。
The application program is transmitted including at least one other keyword belonging to another project, causing the management server to transmit information on a detection time when any of the keywords belonging to the other project is detected,
The work management program according to claim 8, wherein the work man-hour calculation function calculates the work time using the detection time received from the work terminal as the work end time.
前記入力信号は、前記作業用端末のキーボード信号であることを特徴とする請求項8または請求項9に記載の作業管理プログラム。   The work management program according to claim 8 or 9, wherein the input signal is a keyboard signal of the work terminal. 処理部および記憶部を有する管理サーバであって、
前記処理部は、
作業用のプロジェクト毎に設けられたプロジェクトフォルダを前記記憶部に作成し、
前記プロジェクトフォルダ内のファイルにアクセスがあると、前記ファイルへのアクセスの時刻情報と、前記アクセスの端末を識別するアドレス情報と、前記プロジェクトの情報とを関連付けて前記記憶部に記憶し、
前記ファイルへの最初のアクセスの時刻情報を作業開始時刻情報とし、前記ファイルが閉じられた場合の時刻、または、前記ファイルへのアクセスが所定時間なかった場合の時刻を作業終了時刻情報として前記記憶部に記憶し、前記作業終了時刻情報と前記作業開始時刻情報とに基づいて作業時間を算出し管理する
ことを特徴とする管理サーバ。
A management server having a processing unit and a storage unit,
The processor is
Create a project folder for each working project in the storage unit,
When there is access to a file in the project folder, time information of access to the file, address information for identifying the terminal of the access, and information on the project are stored in the storage unit in association with each other,
The time information of the first access to the file is set as work start time information, and the time when the file is closed or the time when the file is not accessed for a predetermined time is stored as the work end time information. A management server that stores the work time and calculates and manages the work time based on the work end time information and the work start time information.
JP2007312207A 2007-12-03 2007-12-03 Work management system, work management program and management server Pending JP2009139982A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007312207A JP2009139982A (en) 2007-12-03 2007-12-03 Work management system, work management program and management server

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007312207A JP2009139982A (en) 2007-12-03 2007-12-03 Work management system, work management program and management server

Publications (1)

Publication Number Publication Date
JP2009139982A true JP2009139982A (en) 2009-06-25

Family

ID=40870563

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007312207A Pending JP2009139982A (en) 2007-12-03 2007-12-03 Work management system, work management program and management server

Country Status (1)

Country Link
JP (1) JP2009139982A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016045672A (en) * 2014-08-22 2016-04-04 株式会社日立製作所 Design assistance device
JP2018055265A (en) * 2016-09-27 2018-04-05 株式会社オービック Expense calculation device, expense calculation method and expense calculation program

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016045672A (en) * 2014-08-22 2016-04-04 株式会社日立製作所 Design assistance device
JP2018055265A (en) * 2016-09-27 2018-04-05 株式会社オービック Expense calculation device, expense calculation method and expense calculation program

Similar Documents

Publication Publication Date Title
JP5972121B2 (en) Application management system, management apparatus, application execution terminal, application management method, application execution terminal control method, and program
JP5966270B2 (en) System and device management program
US20110153748A1 (en) Remote forensics system based on network
JP5370478B2 (en) Name identification device, name identification method and name identification program
JP5600277B2 (en) Cloud service relocation system, method and program
US20080072225A1 (en) Information processing apparatus, information processing method, program, and recording medium
WO2013183115A1 (en) Log management system and program
CN103984891A (en) Network security systems and methods
US9740865B2 (en) System and method for configuring antivirus scans
US8266178B2 (en) Management apparatus, information processing apparatus, and method therefor
RU2449360C1 (en) System and method for creating antivirus databases in accordance with personal computer parameters
JP2006350464A (en) Data collection system, data extraction server, data collection method and data collection program
EP3188022B1 (en) System monitoring device
US10033737B2 (en) System and method for cross-cloud identity matching
JP2009139982A (en) Work management system, work management program and management server
JP4240001B2 (en) Data collection apparatus and program
US20070214192A1 (en) Change monitoring program for computer resource on network
JP6375679B2 (en) Server information management apparatus, server information management program, and server information management method
JP5851311B2 (en) Application inspection device
US20180020075A1 (en) Apparatus and method for providing data based on cloud service
US9092431B2 (en) Document management system and document management method for determining whether at least one managed document was printed and updating print information of the at least one managed document based on the determination
WO2013114830A1 (en) Process prediction execution device and process prediction execution method
JPH0863352A (en) Virus check system
JP6102459B2 (en) Device management apparatus, information processing system, information processing method, and program
JP2017211722A (en) Application support program, application support device and application support method

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090617