JP2009032097A - Management system, management method, and program - Google Patents

Management system, management method, and program Download PDF

Info

Publication number
JP2009032097A
JP2009032097A JP2007196389A JP2007196389A JP2009032097A JP 2009032097 A JP2009032097 A JP 2009032097A JP 2007196389 A JP2007196389 A JP 2007196389A JP 2007196389 A JP2007196389 A JP 2007196389A JP 2009032097 A JP2009032097 A JP 2009032097A
Authority
JP
Japan
Prior art keywords
time
action
date
instruction
department
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007196389A
Other languages
Japanese (ja)
Inventor
Tetsuo Nishishige
哲雄 西重
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2007196389A priority Critical patent/JP2009032097A/en
Publication of JP2009032097A publication Critical patent/JP2009032097A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To reduce deviation between object management and action management in a hierarchized organization which consists of two or more divisions. <P>SOLUTION: A management system which manages an activity of the hierarchized organization which consists of two or more divisions, includes: a memory unit (a data storage device 1201) which memorizes the action management information which stores a last action completion planed date which is the action completion planed date with respect to the last instruction, and the newest action instruction planed date which is the newest action instruction planed date, in every division; an arithmetic operation unit (an arithmetic operation unit 1202) which compares the last action completion planed date with the newest action instruction planed date for a predetermined division, by referring to the action management information in the memory unit, and outputs a first risk display signal if the action completion planed date is later; and a display element (a display 11) which performs a display of possibility to which the newest action instruction planed date may not be reasonable, when the first risk display signal is received from the arithmetic operation unit. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、複数階層からなる組織の活動状況のマイルストン日時(行動開始日、行動完了日など)を管理する際に、組織活動のリスクを計算して表示する技術に関する。   The present invention relates to a technique for calculating and displaying the risk of organizational activity when managing milestone dates and times (action start date, action completion date, etc.) of an activity status of an organization consisting of a plurality of hierarchies.

従来、予実算(予定と実績)による目標管理と日々の現場の行動管理との乖離を防ぐことができる進捗管理支援装置については、例えば特許文献1に開示されているものがある。特許文献1の進捗管理支援装置は、管理者の「力量」や「勘所・経験」に頼らなくても、現場に対し目標値(「製品Aを100個販売」など)と実績値、補正目標値、予測値を設定し、これらの差分に基づいて、現場へ所定の行動をとるように告知できる機能を備えている。
特開2006−323787号公報
Conventionally, for example, Patent Document 1 discloses a progress management support device that can prevent a deviation between target management based on actual prediction (scheduled and actual) and daily site behavior management. The progress management support apparatus disclosed in Patent Document 1 can be used for target values (such as “sell 100 products A”), actual values, and correction targets without relying on the manager's “capability” and “consideration / experience”. A value and a predicted value are set, and based on the difference between them, a function that can notify the site to take a predetermined action is provided.
JP 2006-323787 A

しかし、現場へ目標値が変わったことを告知(A-1)し、現場がそれに基づいて行動(B-1)を調整する場合、現場は、その行動プロセスの変更有無(リソース(人、機械、資金など)の調整で目標値を達成できるか、業務の流れを変える必要があるか)を検討する期間(C-1)と、検討に基づいて調整する期間(D-1)が必要となる。従って、この期間(C-1)(D-1)は検討期間あるいは調整期間であり正しく目標値と実績値の差分を取れないため、特許文献1の技術では、目標管理と行動管理との乖離を防ぐことはできない。   However, when the target is changed (A-1) and the site adjusts the action (B-1) based on it, the site changes the behavior process (resource (human, machine) , Funding, etc.) (requires whether the target value can be achieved or whether the flow of work needs to be changed) (C-1) and the period (D-1) to be adjusted based on the review Become. Therefore, since this period (C-1) (D-1) is an examination period or an adjustment period and the difference between the target value and the actual value cannot be obtained correctly, the technique of Patent Document 1 has a difference between target management and behavior management. Cannot be prevented.

また、この期間(C-1)は、告知先の現場でも同様現象(現場が関連部門へ告知)が発生するため、管理が及ばない告知が発生し、正確に期間(C-1)を把握することは事実上不可能である。   In addition, during this period (C-1), the same phenomenon (notification to the relevant department) occurs at the site of the notification destination, so an announcement that cannot be managed occurs, and the period (C-1) is accurately grasped. It is virtually impossible to do.

特に、告知(A-1)に基づいて行動(B-1)を調整し、行動(B-1)の調整中に別の告知(A-2)があった場合、行動(B-1)の調整が完了できないまま、行動(B-2)を検討開始するため、行動(B-1)に費やした期間(C-1)(D-1)の作業が無駄になるとともに、期間(D-1)に行った作業を元に戻して、新たに期間(C-2)で検討し、期間(D-2)で行動を行うため、調整がさらに煩雑となる。   In particular, if the action (B-1) is adjusted based on the notice (A-1) and there is another notice (A-2) during the adjustment of the action (B-1), the action (B-1) Since the study of action (B-2) is started without completing the adjustment, the work of period (C-1) (D-1) spent on action (B-1) is wasted and period (D -1) The work performed in 1) is returned to the original state, and it is newly examined in the period (C-2), and the action is performed in the period (D-2), so the adjustment becomes more complicated.

以上から、現場では、行動(B-2)の調整が麻痺(調整不能)する場合、及び期間(C-2)に行われる検討内容、及び期間(D-2)の行動内容が不十分となる場合が発生し、目標管理と行動管理の乖離がより拡大する可能性がある。   Based on the above, in the field, when the adjustment of behavior (B-2) is paralyzed (unadjustable), and the examination content performed in period (C-2) and the behavior content in period (D-2) are insufficient May occur, and the gap between goal management and behavior management may be further expanded.

そこで、本発明は、上記問題点に鑑みてなされたものであり、階層化された複数の部署からなる組織における目標管理と行動管理の乖離を低減することを目的とする。   Therefore, the present invention has been made in view of the above problems, and an object thereof is to reduce the difference between target management and behavior management in an organization composed of a plurality of hierarchized departments.

前記課題を解決するために、本発明は、階層化された複数の部署からなる組織の活動を管理する管理システムであって、部署ごとに、前回の行動指示に対する行動終了の予定日時である前回行動終了予定日時、及び、最新の行動指示の予定日時である最新行動指示予定日時を格納する行動管理情報を記憶する記憶部と、記憶部の行動管理情報を参照し、所定の部署に関して、前回行動終了予定日時と最新行動指示予定日時を比較し、前回行動終了予定日時のほうが遅い日時であったときに第1のリスク表示信号を出力する演算部と、演算部から第1のリスク表示信号を受信すると、最新行動指示予定日時が妥当ではない可能性がある旨の表示を行う表示部と、を備える。その他の手段については後記する。   In order to solve the above-mentioned problem, the present invention is a management system for managing the activity of an organization composed of a plurality of hierarchical departments, and for each department, the previous time is the scheduled end date of the action for the previous action instruction. The storage unit that stores the action management information that stores the scheduled action end date and time and the latest action instruction scheduled date and time that is the latest action instruction scheduled date, and the action management information in the storage unit, The operation end scheduled date and time and the latest action instruction scheduled date and time are compared, and a calculation unit that outputs a first risk display signal when the previous action end scheduled date and time is later, and a first risk display signal from the calculation unit A display unit that displays that there is a possibility that the latest action instruction scheduled date and time may not be valid. Other means will be described later.

本発明によれば、階層化された複数の部署からなる組織における目標管理と行動管理の乖離を低減することができる。   ADVANTAGE OF THE INVENTION According to this invention, the divergence of target management and action management in the organization which consists of several hierarchized departments can be reduced.

以下、本発明を実施するための最良の形態(以下、「実施形態」という。)について詳細に説明する。なお、以下において、「最短時間」とは、現場が管理者から指示を受けてから行動方針(行動内容)を調整(決定)するのに要する最短の時間のことである。つまり、最短時間は、リソースの投入などによっても短縮することができない、という性質を有する。また、「最短日時」とは、現場が管理者から指示を受けてから最短時間が経過したときの日時のことを指す。さらに、「行動」とはその部署における活動のことを指す。   Hereinafter, the best mode for carrying out the present invention (hereinafter referred to as “embodiment”) will be described in detail. In the following, the “minimum time” is the shortest time required for the site to adjust (determine) the action policy (action content) after receiving an instruction from the manager. In other words, the shortest time has the property that it cannot be shortened by resource input or the like. The “shortest date and time” refers to the date and time when the shortest time has elapsed since the site received an instruction from the manager. Furthermore, “behavior” refers to an activity in the department.

まず、図1を参照しながら、本実施形態のシステム構成を説明する。図1は、本実施形態の目標管理システムの構成図である。
目標管理システムSは、ディスプレイ11(表示部)及びディスク装置12から構成される。ディスプレイ11とディスク装置12は、インタネット/イントラネットを介してデータ通信が可能である。
First, the system configuration of this embodiment will be described with reference to FIG. FIG. 1 is a configuration diagram of a target management system according to the present embodiment.
The target management system S includes a display 11 (display unit) and a disk device 12. The display 11 and the disk device 12 can perform data communication via the Internet / Intranet.

ディスプレイ11(クライアント)は、キーボード、マウスなどから構成される入力装置1101と、表示インタフェースであるWebブラウザ(不図示)を備え、インタネット/イントラネットを介して、ユーザの入力に基づいた情報を、ディスク装置12へ送信することができ、インタネット/イントラネットを介してディスク装置12から受信した情報をWebブラウザへ表示することができる。また、ディスプレイ11上には、目標管理システムSを起動指示できるアイコンをあらかじめ配置している。   The display 11 (client) includes an input device 1101 composed of a keyboard, a mouse, and the like, and a Web browser (not shown) as a display interface, and stores information based on user input via the Internet / intranet. The information can be transmitted to the device 12 and the information received from the disk device 12 via the Internet / intranet can be displayed on the Web browser. On the display 11, an icon for instructing activation of the target management system S is arranged in advance.

ディスク装置12は、例えばサーバであり、ハードディスクから構成されるデータ格納装置1201(記憶部)と、CPU(Central Processing Unit)とメモリから構成される演算装置1202(演算部)を備え、インタネット/イントラネットを介して、ディスプレイ11から得られた情報に基づいて演算し、インタネット/イントラネットを介して、演算結果をディスプレイ11へ送ることができる。   The disk device 12 is, for example, a server, and includes a data storage device 1201 (storage unit) configured from a hard disk, and an arithmetic device 1202 (calculation unit) configured from a CPU (Central Processing Unit) and a memory. The calculation result can be calculated based on the information obtained from the display 11 and the calculation result can be sent to the display 11 via the Internet / intranet.

ディスク装置12のデータ格納装置1201には、目標管理プログラム13が格納されている。目標管理プログラム13は、入出力部14、データ管理部15、及びデータ分析部16から構成される。   A target management program 13 is stored in the data storage device 1201 of the disk device 12. The target management program 13 includes an input / output unit 14, a data management unit 15, and a data analysis unit 16.

入出力部14は、入力解析処理部17と出力解析処理部18から構成され、目標管理プログラム13とディスプレイ11との入出力の役割を担う。
入力解析処理部17は、ディスプレイ11から送られたデータをデータ分析部16へ引き継ぐ処理を行う。
出力解析処理部18は、初期画面表示処理部113と活動リスク判定処理部116で生成されたデータをディスプレイ11へ出力する処理を行う。
The input / output unit 14 includes an input analysis processing unit 17 and an output analysis processing unit 18 and plays a role of input / output between the target management program 13 and the display 11.
The input analysis processing unit 17 performs processing for taking over the data sent from the display 11 to the data analysis unit 16.
The output analysis processing unit 18 performs processing for outputting the data generated by the initial screen display processing unit 113 and the activity risk determination processing unit 116 to the display 11.

データ管理部15は、データ分析部16でリスク計算する際の元情報を管理・格納するものであり、行動管理テーブル19(行動管理情報)と、告知(行動指示)情報管理テーブル110(行動指示情報管理情報)、告知方法管理テーブル111(行動指示方法管理情報)、及びリスク判定テーブル112を備えている。   The data management unit 15 manages and stores the original information when the data analysis unit 16 performs risk calculation, and includes a behavior management table 19 (behavior management information) and a notification (behavior instruction) information management table 110 (behavior instruction). Information management information), a notification method management table 111 (behavior instruction method management information), and a risk determination table 112.

行動管理テーブル19は、ディスプレイ11に表示する組織の活動状況のマイルストン日時(行動開始日、行動完了日など)を管理し、この日時を組織単位に複数格納するテーブルである(詳細は図2で後記)。
告知情報管理テーブル110は、本実施形態の特徴を示す告知内容(告知方法、告知先組織など)を管理し、この内容を組織単位に複数格納するテーブルである(詳細は図3で後記)。
The behavior management table 19 is a table that manages the milestone date and time (behavior start date, behavior completion date, etc.) of the activity status of the organization displayed on the display 11 and stores a plurality of such dates and times in organizational units (details are shown in FIG. 2). (Postscript).
The notification information management table 110 is a table that manages notification contents (notification method, notification destination organization, etc.) indicating the features of the present embodiment, and stores a plurality of these contents in organizational units (details will be described later in FIG. 3).

告知方法管理テーブル111は、告知に要する時間、及び告知先組織の理解度の重み値を管理し、この重み値を告知方法単位に複数格納するテーブルである(詳細は図4で後記)。
リスク判定テーブル112は、リスクの内容を示す文字列を管理し、この文字列をリスク内容単位に複数格納するテーブルである(詳細は図5で後記)。
The notification method management table 111 is a table that manages the time required for notification and the weight value of the understanding level of the notification destination organization, and stores a plurality of weight values for each notification method (details will be described later in FIG. 4).
The risk determination table 112 is a table that manages a character string indicating the content of risk and stores a plurality of character strings in units of risk contents (details will be described later in FIG. 5).

データ分析部16は、本実施形態の特徴の一つであり、初期画面表示処理部113、活動リスク度計算処理部114、最短日時計算処理部115、及び活動リスク判定処理部116から構成される。
初期画面表示処理部113は、入力解析処理部17で受信した組織を起点に、その組織と結びつく組織を行動管理テーブル19から特定し、特定した内容を出力解析処理部18へ出力する処理を行う。
The data analysis unit 16 is one of the features of this embodiment, and includes an initial screen display processing unit 113, an activity risk degree calculation processing unit 114, a shortest date and time calculation processing unit 115, and an activity risk determination processing unit 116. .
The initial screen display processing unit 113 starts the organization received by the input analysis processing unit 17, identifies the organization associated with the organization from the behavior management table 19, and outputs the identified content to the output analysis processing unit 18. .

活動リスク度計算処理部114は、本実施形態の特徴の一つであり、告知情報管理テーブル110の組織が告知する回数、告知に要する時間、及び告知先組織の理解度の重み値をもとに組織の活動リスク度を計算し、その結果を告知情報管理テーブル110へ格納する処理を行う。   The activity risk level calculation processing unit 114 is one of the features of this embodiment, and is based on the number of notifications by the organization of the notification information management table 110, the time required for notification, and the weight value of the understanding level of the notification destination organization. The activity risk level of the organization is calculated, and the result is stored in the notification information management table 110.

最短日時計算処理部115は、本実施形態の特徴の一つであり、告知情報管理テーブル110の活動リスク度と行動管理テーブル19の告知日をもとに、組織活動の最短日時を計算し、その結果を行動管理テーブル19へ格納する処理を行う。
活動リスク判定処理部116は、行動管理テーブル19の組織活動の最短日時、告知日、行動完了日をもとに、リスク判定テーブル112におけるリスク内容を示す文字列を特定し、特定した文字列を出力解析処理部18へ出力する処理を行う。
The shortest date and time calculation processing unit 115 is one of the features of this embodiment, and calculates the shortest date and time of organizational activity based on the activity risk level of the notification information management table 110 and the notification date of the behavior management table 19. A process of storing the result in the behavior management table 19 is performed.
The activity risk determination processing unit 116 specifies a character string indicating the risk content in the risk determination table 112 based on the shortest date and time of the organizational activity in the behavior management table 19, the notification date, and the action completion date. Processing to output to the output analysis processing unit 18 is performed.

次に、図2〜図5を参照しながら、データ構成について説明する(適宜図1参照)。図2は、行動管理テーブルの構成図である。
行動管理テーブル19は、活動のマイルストン日時を格納(管理)するデータベース(テーブル)であり、No.22、部署名23、前回(告知)24、前回(最短日時)25(前回行動終了予定日時)、前回(行動完了)26、現在(告知)27(最新行動指示予定日時)、現在(最短日時)28(最新行動終了予定日時)、及び現在(行動完了)29(現実の行動終了日時)のカラム(以下、「のカラム」の記載は省略。他図についても同様)から構成される。
行動管理テーブル19は、部署名23をキーデータとして、1レコード単位にデータを管理している。
Next, the data structure will be described with reference to FIGS. 2 to 5 (see FIG. 1 as appropriate). FIG. 2 is a configuration diagram of the behavior management table.
The behavior management table 19 is a database (table) for storing (managing) milestone dates and times of activities. 22, department name 23, last time (notification) 24, last time (shortest date and time) 25 (previous action end scheduled date and time), last time (action completion) 26, current (notification) 27 (latest action instruction scheduled date and time), current (shortest date and time) ) 28 (latest action end scheduled date and time) and present (behavior completion) 29 (actual action end date and time) columns (hereinafter, “no column” is omitted. The same applies to other figures).
The behavior management table 19 manages data in units of records using the department name 23 as key data.

No.22には、行動管理テーブル19で管理されるレコードの識別番号が格納される。部署名23には、部署の名前である文字列が格納される。前回(告知)24には、活動のサイン(告知)を受け取った一世代前の日付が格納される。前回(最短日時)25には、本実施形態の特徴の一つである最短日時の日付が格納される。前回(行動完了)26には、行動を完了した一世代前の日付が格納される。現在(告知)27には、活動のサイン(告知)を受け取った最新の日付が格納される。現在(最短日時)28には、本実施形態の特徴の一つである最短日時の最新の日付が格納される。現在(行動完了)29には、行動を完了した最新の日付が格納される。   No. 22 stores an identification number of a record managed by the behavior management table 19. The department name 23 stores a character string that is the name of a department. The previous (notification) 24 stores the date one generation before the sign of the activity (notification) was received. The previous (shortest date and time) 25 stores the date of the shortest date and time, which is one of the features of the present embodiment. The previous (action completion) 26 stores the date one generation before the completion of the action. The current date (notification) 27 stores the latest date when the signature (notification) of the activity is received. The current (shortest date and time) 28 stores the latest date of the shortest date and time, which is one of the features of the present embodiment. The current (action complete) 29 stores the latest date when the action is completed.

また、行動管理の対象とならない部署(「第1部」のような管理部門)については、行210のように、各セルに情報がないことを意味する「−」が格納される。なお、「−」の代わりにNULL値を使用してもよい。
さらに、前回(最短日時)25、及び現在(最短日時)28の日付は、本実施形態にて計算後に値が格納されるため、その計算前は「−」となっている。
For a department that is not subject to behavior management (a management department such as “Part 1”), as shown in row 210, “−”, which means that there is no information in each cell, is stored. Note that a NULL value may be used instead of “-”.
Furthermore, the values of the previous (shortest date and time) 25 and the current (shortest date and time) 28 are “−” before the calculation because values are stored after the calculation in this embodiment.

また、前回(行動完了)26については、情報がない場合(例えば、行動が完了していない場合)があり、その場合は符号220のセル(以下、単に「符号220」という。他も同様)のように「−」となる。
なお、行動管理テーブル19は、部署名23を指定することで、符号24から符号29の各日付を取り出すことができるインタフェースを備えている。なお、行動管理テーブル19の各データは、表計算ソフトにて、登録・編集が可能となっている。
In addition, there is a case where there is no information about the previous time (behavior completion) 26 (for example, a case where the action is not completed), and in this case, a cell denoted by reference numeral 220 (hereinafter simply referred to as “reference numeral 220”, and so on). It becomes "-" like.
Note that the behavior management table 19 includes an interface that can extract dates 24 to 29 by designating the department name 23. Each data of the behavior management table 19 can be registered and edited with spreadsheet software.

図3は、告知情報管理テーブルの構成図である。告知情報管理テーブル110は、本実施形態の特徴の一つである告知方法などを格納するデータベースであり、No.32、部署名33、告知元部署34、告知先へ告知する方法35、告知する回数36(指示回数)、浸透時間(計)37、及び最短日数38(指示消化に必要な時間)から構成される。
告知情報管理テーブル110は、部署名33をキーデータとして、1レコード単位にデータを管理している。
FIG. 3 is a configuration diagram of the notification information management table. The notification information management table 110 is a database that stores a notification method that is one of the features of this embodiment. 32, department name 33, notification source department 34, notification method 35 to notification destination, number of notifications 36 (number of instructions), penetration time (total) 37, and minimum number of days 38 (time required for instruction digestion) The
The notification information management table 110 manages data for each record using the department name 33 as key data.

No.32には、告知情報管理テーブル110で管理されるレコードの識別番号が格納される。部署名33には、部署の名前である文字列が格納される。告知元部署34には、部署名33へ告知した部署名が格納される。告知先へ告知する方法35には、部署名33に格納された部署が他部署へ告知する方法が格納される。告知する回数36は、部署名33に格納された部署が他部署へ告知する回数を示す数値が格納される。浸透時間(計)37には、本実施形態で計算された活動リスクを示す数値が格納される。最短日数38には、本実施形態で計算された最短日数(最短時間)が格納される。   No. 32 stores an identification number of a record managed by the notification information management table 110. The department name 33 stores a character string that is the name of a department. In the notification source department 34, the department name notified to the department name 33 is stored. In the method 35 of notifying the notification destination, a method in which the department stored in the department name 33 notifies other departments is stored. The number of notifications 36 stores a numerical value indicating the number of times the department stored in the department name 33 notifies the other departments. The infiltration time (total) 37 stores a numerical value indicating the activity risk calculated in the present embodiment. The shortest days 38 stores the shortest days (shortest time) calculated in the present embodiment.

また、情報がないセル(符号39の行の告知元部署34)には、行動管理テーブル19と同様、該当セルに情報がないことを意味する「−」が格納される。
さらに、浸透時間(計)37、及び最短日数38には、本実施形態における計算後に値が格納されるため、その計算の実行前は「−」となっている。
また、告知情報管理テーブル110には、部署名33の値及び告知元部署34の値を相互に比較することにより関連する部署をたどることができるインタフェースが備えられている。例えば、符号310の行(レコード)の符号312の「第1部」と符号39の行の部署名33の「第1部」が一致するので、符号311の「A課」は符号39の行の部署名33の「第1部」の下組織とみなすことができる。
Further, as in the behavior management table 19, “−” indicating that there is no information in the corresponding cell is stored in the cell having no information (notification source department 34 in the row of reference numeral 39).
Furthermore, since values are stored in the penetration time (total) 37 and the shortest number of days 38 after the calculation in the present embodiment, the value is “−” before the calculation is executed.
Further, the notification information management table 110 is provided with an interface that can trace the related departments by comparing the value of the department name 33 and the value of the notice source department 34 with each other. For example, since “first part” of reference numeral 312 in the row (record) of reference numeral 310 matches “first part” of the department name 33 of the reference numeral 39, “section A” of reference numeral 311 is changed to the reference numeral 39. It can be regarded as a subordinate organization of the “part 1” of the department name 33.

なお、告知情報管理テーブル110には、部署名33を指定することで、部署名33から最短日数38の各情報を取り出すことができるインタフェースが備えられている。また、告知情報管理テーブル110の各データは、表計算ソフトにて、登録・編集が可能となっている。   The notification information management table 110 is provided with an interface that can extract each piece of information of the shortest number of days 38 from the department name 33 by designating the department name 33. Each data of the notification information management table 110 can be registered and edited by spreadsheet software.

図4は、告知方法管理テーブルの構成図である。告知方法管理テーブル111は、告知方法に対する活動の重み値を格納するデータベースであり、No.42、告知内容43、浸透レベル44(理解度レベル)、及び告知時間45(必要時間)から構成される。
告知方法管理テーブル111は、告知内容43をキーデータとして、1レコード単位にデータを管理している。
FIG. 4 is a configuration diagram of the notification method management table. The notification method management table 111 is a database that stores activity weight values for the notification method. 42, notification content 43, penetration level 44 (understanding level), and notification time 45 (required time).
The notification method management table 111 manages data for each record using the notification contents 43 as key data.

No.42には、告知方法管理テーブル111で管理されるレコードの識別番号が格納される。告知内容43には、告知内容を示す文字列が格納される。浸透レベル44には、告知が部署へ浸透する際の効果を示す重み値である「1」以上の数値が格納される。告知時間45には、告知が部署へ浸透する際の時間を示す重み値である「1」以上の数値が格納される。   No. 42 stores an identification number of a record managed by the notification method management table 111. The notification content 43 stores a character string indicating the notification content. The penetration level 44 stores a numerical value of “1” or more, which is a weight value indicating an effect when the notification penetrates the department. In the notification time 45, a numerical value of “1” or more, which is a weight value indicating the time when the notification penetrates into the department, is stored.

なお、浸透レベル44及び告知時間45の重み値は、数値が小さくなるほど効果的な告知となるような値とし、あらかじめ告知内容43の各文字列から関係者によって判断された数値が相対的に定義されている。例えば、告知内容43における「メール」と「説明会」を比較すると、総じて「メール」はネットワークを介して同時に送信できるため告知に要する時間は少なく、「説明会」は資料や質疑応答などにより理解度が高まると考えられる。従って、「メール」の告知時間45を相対的に「1」と定義し、「説明会」の浸透レベル44を相対的に「1」と定義し、その他の数値を「2」以上で相対的に定義している。   Note that the weight values of the penetration level 44 and the notification time 45 are such that the smaller the numerical value, the more effective the notification, and the numerical values determined in advance by the parties concerned from each character string of the notification content 43 are relatively defined. Has been. For example, when comparing “mail” and “explanation” in the announcement content 43, “mail” can be sent simultaneously via the network, so the time required for the announcement is small. The degree is expected to increase. Therefore, the notification time 45 of “mail” is relatively defined as “1”, the penetration level 44 of “explanation” is relatively defined as “1”, and other numerical values are relative to “2” or more. Is defined.

また、告知方法管理テーブル111は、告知内容43の文字列と告知先へ告知する方法35(図3参照。以下同様)の文字列を比較するインタフェースを備えている。例えば、符号310の行の符号313の「説明会」は、符号46の行の符号47の「説明会」と一致するので、符号48の浸透レベル「1」及び符号49の告知時間「4」を特定することができる。
なお、告知方法管理テーブル111は、告知内容43を指定することで、浸透レベル44と告知時間45の各情報を取り出すことができるインタフェースを備えている。また、告知方法管理テーブル111の各データは、表計算ソフトにて、登録・編集が可能となっている。
The notification method management table 111 includes an interface for comparing the character string of the notification content 43 and the character string of the method 35 (see FIG. 3; the same applies hereinafter) for notifying the notification destination. For example, the “description meeting” of reference numeral 313 in the row of reference numeral 310 matches the “description meeting” of reference numeral 47 in the row of reference numeral 46, so that the penetration level “1” of reference numeral 48 and the announcement time “4” of reference numeral 49 Can be specified.
The notification method management table 111 is provided with an interface that can extract each information of the penetration level 44 and the notification time 45 by designating the notification content 43. Each data of the notification method management table 111 can be registered and edited by spreadsheet software.

図5は、リスク判定テーブルの構成図である。リスク判定テーブル112は、リスクの内容を格納するデータベースであり、判定結果52、リスク内容53から構成される。
リスク判定テーブル112は、判定結果52をキーデータとして、1レコード単位にデータを管理している。
FIG. 5 is a configuration diagram of the risk determination table. The risk determination table 112 is a database that stores risk content, and includes a determination result 52 and a risk content 53.
The risk determination table 112 manages data for each record using the determination result 52 as key data.

判定結果52には、リスク判定テーブル112で管理されるレコードの識別番号が格納される。リスク内容53には、リスクの内容を示す文字列が格納される。
また、リスク判定テーブル112は、判定結果52を指定することで、リスク内容53の文字列を取り出すことができるインタフェースを備えている。なお、リスク判定テーブル112の各データは、表計算ソフトにて、登録・編集が可能となっている。
In the determination result 52, the identification number of the record managed in the risk determination table 112 is stored. The risk content 53 stores a character string indicating the risk content.
In addition, the risk determination table 112 includes an interface that can extract the character string of the risk content 53 by designating the determination result 52. Each data of the risk determination table 112 can be registered and edited with spreadsheet software.

次に、図6を参照しながら、ディスプレイに表示される画面構成について説明する(適宜他図参照)。図6は、本実施形態の特徴の一つであるリスクに関する表示を行う画面の構成図である。目標管理システムSは、入力装置1101を使用してディスプレイ11のディスクトップ上に配置されたアイコンをクリックすることで起動され、そのクリック後、Webブラウザ61が開き、Webブラウザ61上のウインドウの中に目標管理モニタ62と題する画面(以下、単に「目標管理モニタ62」ともいう。)が表示される。   Next, a screen configuration displayed on the display will be described with reference to FIG. 6 (refer to other figures as appropriate). FIG. 6 is a configuration diagram of a screen that displays a risk that is one of the features of the present embodiment. The target management system S is activated by clicking on an icon arranged on the desktop of the display 11 using the input device 1101. After that, the web browser 61 is opened and is displayed in the window on the web browser 61. A screen entitled “Target management monitor 62” (hereinafter also simply referred to as “target management monitor 62”) is displayed.

目標管理モニタ62は、行動管理テーブル19に格納された情報をもとに、活動マイルストン日時を部署単位に表示する表である。目標管理システムSの利用者は、この目標管理モニタ62を閲覧することで、各部署の活動の進捗を把握し、リスクを監視することで、リスクへの対応策を検討することができる。   The target management monitor 62 is a table that displays the activity milestone date and time for each department based on the information stored in the behavior management table 19. The user of the target management system S can view the progress of the activity of each department by browsing the target management monitor 62 and monitor the risk to examine countermeasures against the risk.

また、最新内容64にこの画面を表示した日付を表示することにより、表66に表示されたリスク内容と照らし合わせて対応する際の行動の優先順位等を検討できるようになっている。
また、目標管理モニタ62は、告知元の部署を基点に、関連する部署を絞り込んで表示する機能を備えており、プルダウン63から基点となる部署を選択することで、表66に関連する部署に関する情報が表示される。本実施形態の場合、プルダウン63では「第1部」となっているため、この部署と関連する部署の情報が告知情報管理テーブル110の内容をもとに絞り込まれ、表66へ表示されている。
Further, by displaying the date when this screen is displayed in the latest content 64, it is possible to examine the priority order of actions when responding to the risk content displayed in the table 66.
The target management monitor 62 has a function of narrowing down and displaying related departments based on the department of the notification source. By selecting the department as the base from the pull-down 63, the target management monitor 62 relates to the departments related to Table 66. Information is displayed. In the case of the present embodiment, since it is “Part 1” in the pull-down 63, information on the department related to this department is narrowed down based on the contents of the notification information management table 110 and displayed in the table 66. .

本実施形態の特徴の一つである活動のリスクの評価結果は表66に表示される。表66は、部署名67、前回68、現在69、及びリスク内容610を列とする表形式で表示され、プルダウン63で部署を指定したタイミングで、指定された部署の情報が表示される。プルダウン63の項目の候補は、告知情報管理テーブル110の部署名33に格納された文字列である。   The evaluation result of the risk of activity, which is one of the features of this embodiment, is displayed in Table 66. The table 66 is displayed in a table format with the department name 67, the previous time 68, the current 69, and the risk content 610 as columns, and information on the designated department is displayed at the timing when the department is designated by the pull-down 63. Candidate items for the pull-down 63 are character strings stored in the department name 33 of the notification information management table 110.

なお、本実施形態の特徴の一つである活動のリスクの評価結果は、リスク計算ボタン65をクリックすることにより計算される。従って、リスク計算ボタン65がクリックされる前は、最短日時612、最短日時615、及びリスク内容610の各セルは空欄となっており(「−」が表示され)、リスク計算ボタン65がクリックされた後、最短日時612、最短日時615、及びリスク内容610の列に値が表示される。   It should be noted that an activity risk evaluation result that is one of the features of the present embodiment is calculated by clicking the risk calculation button 65. Therefore, before the risk calculation button 65 is clicked, the cells of the shortest date and time 612, the shortest date and time 615, and the risk content 610 are blank ("-" is displayed), and the risk calculation button 65 is clicked. After that, values are displayed in the columns of the shortest date and time 612, the shortest date and time 615, and the risk content 610.

部署名67には、プルダウン63で指定された部署名に関連する部署名が表示される。具体的には、告知情報管理テーブル110の告知元部署34の列からプルダウン63の文字列と一致する文字列を特定し、特定した文字列を含む行のすべての部署名33の情報を表示する。例えば、符号617の「B課」については、プルダウン63で「第1部」が指定されているため、告知元部署34の列から「第1部」と一致する文字列を特定し、特定した文字列について、部署名33の列から、「B課」を抽出している(「A課」と「C課」についても同様)。   In the department name 67, a department name related to the department name designated by the pull-down 63 is displayed. Specifically, a character string that matches the character string in the pull-down 63 is specified from the column of the notification source department 34 in the notification information management table 110, and information on all the department names 33 in the line including the specified character string is displayed. . For example, for “Section B” of reference numeral 617, since “Part 1” is specified in the pull-down 63, a character string that matches “Part 1” is identified from the column of the notification source department 34 and identified. As for the character string, “Section B” is extracted from the column of the department name 33 (the same applies to “Section A” and “Section C”).

前回68は、告知611、最短日時612、行動完了613から構成される。告知611、最短日時612、行動完了613は行動管理テーブル19を参照し表示され、前記の部署名67を表示する際と同様に実行される。例えば、符号617の「B課」の符号618の「2007/04/01」は、行動管理テーブル19の部署名23の「B課」の行の前回(告知)24である符号218の「2007/04/01」を参照している。また、符号617の「B課」の符号619の「2007/05/10」は、行動管理テーブル19の部署名23の「B課」の行の前回(最短日時)25である符号219の「2007/05/10」を参照している。さらに、符号617の「B課」の符号620「−」は、行動管理テーブル19の部署名23の「B課」の行の前回(行動完了)26である符号220の「−」を参照している。   The previous time 68 includes a notification 611, a shortest date and time 612, and an action completion 613. Announcement 611, shortest date and time 612, and action completion 613 are displayed with reference to the action management table 19, and are executed in the same manner as when the department name 67 is displayed. For example, “2007/04/01” of reference numeral 618 of “section B” of reference numeral 617 is “2007” of reference numeral 218 which is the previous (notification) 24 of the row of “section B” of the department name 23 of the action management table 19. / 04/01 ". In addition, “2007/05/10” of the reference numeral 619 of the “section B” of the reference numeral 617 is “last” (the shortest date and time) 25 of the line “section B” of the department name 23 of the action management table 19 “ 2007/05/10 ". Further, the reference numeral 620 “−” of the “section B” of the reference numeral 617 refers to the “−” of the reference numeral 220 that is the previous (action completion) 26 in the row of the “section B” of the department name 23 of the action management table 19. ing.

現在69は、告知614、最短日時615、行動完了616から構成される。告知614、最短日時615、行動完了616も前記と同様に、行動管理テーブル19を参照される、つまり、「B課」の場合は、それぞれ、図2の行動管理テーブル19における符号221、符号222、符号223が参照され、表示される。   The current 69 includes an announcement 614, a shortest date and time 615, and an action completion 616. The notification 614, the shortest date and time 615, and the action completion 616 are also referred to the action management table 19 as described above, that is, in the case of “Section B”, reference numerals 221 and 222 in the action management table 19 of FIG. Reference numeral 223 is referred to and displayed.

リスク内容610には、本実施形態にて計算されたリスク内容が表示される。例えば、「現在の告知時期が早すぎます。現在の告知時期を後ろにずらす必要があります。」の文字列は、リスク判定テーブル112(図5参照)の符号55の「現在の告知時期が早すぎます。現在の告知時期を後ろにずらす必要があります。」を参照している。   The risk content 610 displays the risk content calculated in the present embodiment. For example, the character string “Current notification time is too early. The current notification time needs to be shifted backward.” Is the character string “55. The current notification time is early” in the risk determination table 112 (see FIG. 5). It is too much. You need to shift the current announcement time back. "

なお、部署名67の情報の数が多くて表示しきれない場合、スクロールバー629を利用してスクロールできる。
また、リスク計算ボタン65のクリック後、リスクの内容に応じて、リスクに関連するセルを表66に網掛けをつけて(着色をして)強調表示する。なお、本実施形態では、2種類のリスクについて表示するようになっている。1つ目は告知タイミングのリスクであり、2つ目は行動品質のリスクである。1つ目のリスク表示の狙いは、管理者が告知を乱発することを警告(抑制)するものであり、2つ目のリスク表示の狙いは、現場の活動の検討不十分を警告するものである。
If the information of the department name 67 is large and cannot be displayed, the scroll bar 629 can be used to scroll.
In addition, after the risk calculation button 65 is clicked, cells related to the risk are shaded (colored) and highlighted in the table 66 according to the content of the risk. In the present embodiment, two types of risks are displayed. The first is a notification timing risk, and the second is a behavioral quality risk. The purpose of the first risk indication is to warn (suppress) that the administrator makes announcing notifications, and the purpose of the second risk indication is to warn that the on-site activities are not sufficiently examined. is there.

符号624のリスク内容は1つ目のリスク表示に該当し、最短日時612、告知614、リスク内容610の該当セルに網掛け表示する。符号628のリスク内容は2つ目のリスク表示であり、最短日時615、行動完了616の該当セルに網掛け表示する。すなわち、本実施形態の場合、符号624のリスク内容の場合、符号619、621、624に網掛けをつけて表示されて、符号628のリスク内容の場合、符号625の行の符号626、627、628のセルに網掛け表示する。   The risk content indicated by reference numeral 624 corresponds to the first risk display, and is shaded and displayed on the corresponding cells of the shortest date and time 612, the notification 614, and the risk content 610. The risk content indicated by reference numeral 628 is a second risk display, and is shaded and displayed in the corresponding cell of the shortest date and time 615 and action completion 616. That is, in the case of the present embodiment, in the case of the risk content of reference numeral 624, the reference numerals 619, 621, and 624 are shaded and displayed, and in the case of the risk content of reference numeral 628, reference numerals 626, 627, 628 cells are shaded.

次に、図7を参照しながら、目標管理システムの処理について説明する(適宜他図参照)。図7は、目標管理システムの処理の流れの概要を示すフロー図である。
まず、初期画面表示処理部113が、目標管理システムの起動と目標管理モニタの表示を行う(ステップ71)。次に、活動リスク度計算処理部114が、活動リスク度計算と計算結果の格納を行う(ステップ72)。続いて、最短日時計算処理部115が、最短日時の足しこみと計算結果の格納を行う(ステップ73)。最後に、活動リスク判定処理部116が、リスク内容の判定と表示を行う(ステップ74)。
各処理について、図8〜11を参照しながら詳述する(適宜他図参照)。図8〜11は、図7における各ステップの詳細処理フロー図である。
Next, the process of the target management system will be described with reference to FIG. 7 (refer to other figures as appropriate). FIG. 7 is a flowchart showing an outline of the processing flow of the target management system.
First, the initial screen display processing unit 113 activates the target management system and displays a target management monitor (step 71). Next, the activity risk level calculation processing unit 114 calculates the activity risk level and stores the calculation result (step 72). Subsequently, the shortest date and time calculation processing unit 115 adds the shortest date and time and stores the calculation result (step 73). Finally, the activity risk determination processing unit 116 determines and displays the risk content (step 74).
Each process will be described in detail with reference to FIGS. 8 to 11 are detailed processing flowcharts of the steps in FIG.

図8に示すように、まず、目標管理システムSの利用者は、入力装置1101を使用してディスプレイ11のディスクトップ上に配置された起動用のアイコン(起動アイコン)をクリックする。これにより、ディスプレイ11は、目標管理システムSを起動する情報を生成し、ディスク装置12にこの情報を送り、目標管理プログラム13の入力解析処理部17は、この情報の受信と同時に目標管理プログラム13を起動し、Webブラウザ61を生成し、ディスプレイ11に画面表示する。起動直後は、プルダウン63、最新内容64、及び表66(枠のみ)が表示されている(ステップ81)。
プルダウン63から任意の部署名を選択する(ステップ82)と、本実施形態の初期画面表示処理が起動する。
As shown in FIG. 8, first, the user of the target management system S uses the input device 1101 to click an activation icon (activation icon) arranged on the desktop of the display 11. As a result, the display 11 generates information for starting the target management system S and sends this information to the disk device 12, and the input analysis processing unit 17 of the target management program 13 simultaneously receives the information, and the target management program 13 To generate a Web browser 61 and display it on the display 11. Immediately after activation, a pull-down 63, the latest content 64, and a table 66 (only the frame) are displayed (step 81).
When an arbitrary department name is selected from the pull-down 63 (step 82), the initial screen display process of this embodiment is started.

続いて、初期画面表示処理部113は、選択したプルダウン63の部署名の文字列が告知情報管理テーブル110の告知元部署34の列に存在するかを判断し(ステップ83)、その部署名が存在しない場合は(No)処理を終了し、その部署名が存在する場合は(Yes)一致する文字列の行に含まれる部署名33を特定(抽出)する(ステップ84)。   Subsequently, the initial screen display processing unit 113 determines whether or not the character string of the department name of the selected pull-down 63 exists in the column of the notification source department 34 of the notice information management table 110 (step 83). If it does not exist (No), the process ends. If the department name exists (Yes), the department name 33 included in the line of the matching character string is specified (extracted) (step 84).

次に、初期画面表示処理部113は、前記で特定した(当該)部署名の文字列を行動管理テーブル19の部署名23の列から検索し(ステップ85)、一致する文字列の行から前回(告知)24、前回(行動完了)26、現在(告知)27、現在(行動完了)29の列にあたるセルを特定し(ステップ86)、特定したセルの内容、及び部署名23を表66の該当セルへ検索順に配置し(ステップ87)、ステップ83に戻る。上記の処理をプルダウン63に表示された部署名がなくなるまで(ステップ83でNoになるまで)行う。   Next, the initial screen display processing unit 113 searches for the character string of the department name specified above from the column of the department name 23 of the action management table 19 (step 85), and starts from the line of the matching character string last time. (Notification) 24, previous (action completion) 26, current (notification) 27, current (action completion) 29 cells are identified (step 86), the contents of the identified cells and the department name 23 are listed in Table 66. Arrange the cells in the search order (step 87), and return to step 83. The above processing is performed until the department name displayed on the pull-down 63 disappears (until No in step 83).

本実施形態の例の場合、プルダウン63で「第1部」が選択されているため、この文字列で告知情報管理テーブル110の告知元部署34を検索する。検索の結果、部署名33として「A課」「B課」「C課」がヒットし、「A課」「B課」「C課」と行動管理テーブル19の部署名23を比較し、一致する行の前回(告知)24、前回(行動完了)26、現在(告知)27、現在(行動完了)29を表66の該当セルへ配置する。例えば、「B課」の場合、前回(告知)24は符号218の「2007/04/01」、前回(行動完了)26は符号220の「−」、現在(告知)27は符号221の「2007/4/20」、現在(行動完了)29は符号223の「−」となり、それぞれ符号618、620、621、623に表示し、「B課」の文字列を符号617に表示する。   In the example of this embodiment, since “Part 1” is selected from the pull-down 63, the notification source department 34 of the notification information management table 110 is searched using this character string. As a result of the search, “Section A”, “Section B”, “Section C” is hit as the department name 33, and “Section A”, “Section B”, “Section C” are compared with the department name 23 of the behavior management table 19, and they match. The previous (notification) 24, the previous (action completion) 26, the current (notification) 27, and the current (action completion) 29 of the row to be performed are arranged in the corresponding cells in Table 66. For example, in the case of “section B”, the previous (announcement) 24 is “2007/04/01” at 218, the previous (action completion) 26 is “−” at 220, and the current (announcement) 27 is “221” 2007/4/20 ", present (action complete) 29 is"-"of reference numeral 223, which is displayed at reference numerals 618, 620, 621 and 623, respectively, and a character string of" B section "is displayed at reference numeral 617.

次に、図9に示すように、目標管理システムSの利用者は、リスク計算ボタン65をクリックし(ステップ91)、リスク計算の開始を指示する。この開始指示後、活動リスク度計算処理部114は、本実施形態の特徴である活動の最短日数を部署ごとに計算し、告知情報管理テーブル110へ格納する処理を次のように行う。   Next, as shown in FIG. 9, the user of the target management system S clicks the risk calculation button 65 (step 91), and instructs the start of risk calculation. After the start instruction, the activity risk level calculation processing unit 114 calculates the minimum number of days of activity for each department, which is a feature of the present embodiment, and stores the information in the notification information management table 110 as follows.

活動リスク度計算処理部114は、告知元部署34の列にプルダウン63の部署名が存在するか判断し(ステップ911)、当該部署名が存在しない場合は(No)処理を終了し、当該部署名が存在する場合は(Yes)ステップ92に進む。
活動リスク度計算処理部114は、該当する部署名67の情報を抽出し(ステップ92)、その部署名67の情報と告知情報管理テーブル110の部署名33の情報と一致する行を特定する(ステップ93)。
The activity risk level calculation processing unit 114 determines whether or not the department name of the pull-down 63 exists in the column of the notification source department 34 (step 911). If the department name does not exist (No), the process ends. If the name exists (Yes), go to step 92.
The activity risk level calculation processing unit 114 extracts information of the corresponding department name 67 (step 92), and identifies a line that matches the information of the department name 67 and the information of the department name 33 of the notification information management table 110 ( Step 93).

次に、活動リスク度計算処理部114は、特定した行のうち告知する回数36を抽出(特定)し、告知先へ告知する方法35の文字列を特定する(ステップ94)。さらに、活動リスク度計算処理部114は、特定した告知先へ告知する方法35の文字列と告知方法管理テーブル111の告知内容43の列と一致する文字列を特定し(ステップ95)、特定した行の浸透レベル44、告知時間45を抽出する(ステップ96)。   Next, the activity risk degree calculation processing unit 114 extracts (specifies) the number of notifications 36 from the specified lines, and specifies the character string of the method 35 that notifies the notification destination (step 94). Furthermore, the activity risk level calculation processing unit 114 specifies the character string that matches the character string of the notification method 43 and the notification content 43 column of the notification method management table 111 (step 95). The row penetration level 44 and the notification time 45 are extracted (step 96).

次に、活動リスク度計算処理部114は、抽出した浸透レベル44と告知時間45を乗算し、さらに乗算した数値と抽出した告知する回数36を乗算(ステップ97)する(所定の算出式で計算する)。次に、活動リスク度計算処理部114は、乗算した数値(算出値)を浸透時間(計)37に格納し(ステップ98)、格納した浸透時間(計)の数値に係数「1」を乗算(ステップ99)し、その数値を最短日数38に格納し(ステップ910)、ステップ911に戻る。   Next, the activity risk level calculation processing unit 114 multiplies the extracted penetration level 44 and the notification time 45, and further multiplies the extracted value by the extracted number of notifications 36 (step 97) (calculated by a predetermined calculation formula). To do). Next, the activity risk degree calculation processing unit 114 stores the multiplied value (calculated value) in the infiltration time (total) 37 (step 98), and multiplies the stored infiltration time (total) value by a coefficient “1”. (Step 99), the numerical value is stored in the shortest number of days 38 (Step 910), and the process returns to Step 911.

なお、浸透レベル44と告知時間45の重み値、ステップ97及びステップ99における計算式は、管理者の経験則などから変更してもかまわない。特に、ステップ99では、係数として「1」を使用したが、浸透時間の値を日数の値に適切に変換するために、浸透レベル44と告知時間45の重み値を考慮して、「1」以外の係数(例えば「1.2」など)を適宜使用してよい。   It should be noted that the weight values of the penetration level 44 and the notification time 45 and the calculation formulas in step 97 and step 99 may be changed based on the manager's empirical rules. In particular, in step 99, “1” is used as the coefficient. However, in order to appropriately convert the value of the infiltration time into the value of the number of days, the weight value of the infiltration level 44 and the notification time 45 is taken into consideration. A coefficient other than (for example, “1.2”) may be used as appropriate.

本実施形態の例の場合、符号617の「B課」と一致する告知情報管理テーブル110の部署名33は符号317のセルであり、このセルの行から告知先へ告知する方法35は符号319の「メール」、告知する回数36は符号320の「1」となる。また、告知方法管理テーブル111の告知内容43において符号319の「メール」と一致する文字列の行の浸透レベル44は符号410の「10」となり、告知時間45は符号411の「2」となる。上記の浸透レベル44の符号410の「10」と告知時間45の符号411の「2」を乗算すると「20」となり、この結果を浸透時間(計)37の符号321のセルに「20」として格納する。格納した符号321の「20」に係数「1」を乗算した結果は「20」となるので、この値を最短日数38の符号322のセルに「20(日)」として格納する。符号312の行も同様にして符号314と符号48と符号49の値をもとに計算すると、その結果が符号321のセルに「4(日)」として格納される。   In the case of the example of the present embodiment, the department name 33 of the notification information management table 110 that coincides with “B section” of reference numeral 617 is a cell of reference numeral 317, and the method 35 of notifying the notification destination from the row of this cell is reference numeral 319. “Mail”, the number of notifications 36 is “1” of 320. Further, in the notification content 43 of the notification method management table 111, the penetration level 44 of the line of the character string that matches the “mail” of the reference numeral 319 is “10” of the reference numeral 410, and the notification time 45 is “2” of the reference numeral 411. . Multiplying “10” of the infiltration level 44 by the reference numeral 410 and “2” of the informing time 45 by the numeral 411 gives “20”, and this result is set as “20” in the cell 321 of the infiltration time (total) 37. Store. Since the result of multiplying the stored code 321 “20” by the coefficient “1” is “20”, this value is stored as “20 (day)” in the cell 322 with the shortest number of days 38. Similarly, when the row of reference numeral 312 is calculated based on the values of reference numerals 314, 48, and 49, the result is stored in the cell of reference numeral 321 as “4 (day)”.

次に、図10に示すように、最短日時計算処理部115は、格納された最短日数38を関連する組織単位に加算し、告知日に加算することで最短日時を計算し行動管理テーブル19へ格納する処理を次のように行う。
最短日時計算処理部115は、まず、告知情報管理テーブル110の告知元部署34の列にプルダウン63の部署名が存在するか否か判断し(ステップ100)、その部署名が存在しない場合は(No)処理を終了し、その部署名が存在する場合は(Yes)その行の部署名33を特定する(ステップ101)。
Next, as shown in FIG. 10, the shortest date and time calculation processing unit 115 calculates the shortest date and time by adding the stored shortest number of days 38 to the related organizational unit and adds it to the announcement date, and then to the behavior management table 19. The storing process is performed as follows.
The shortest date and time calculation processing unit 115 first determines whether or not the pull-down 63 department name exists in the column of the notification source department 34 in the notice information management table 110 (step 100). No) The process is terminated, and if the department name exists (Yes), the department name 33 of the line is specified (step 101).

最短日時計算処理部115は、さらに、特定した部署名の文字列が告知情報管理テーブル110の告知元部署34の列に存在するか判断し(ステップ102)、存在しない場合は(No)ステップ104に進み、存在する場合は(Yes)その告知元部署34に対応する部署名33を特定して(ステップ103)ステップ102に戻る。これにより、関連する組織名をすべて特定することができる。   The shortest date calculation processing unit 115 further determines whether or not the character string of the specified department name exists in the column of the notification source department 34 of the notification information management table 110 (step 102). If it exists (Yes), the department name 33 corresponding to the notification source department 34 is specified (step 103), and the process returns to step 102. Thereby, all the related organization names can be specified.

次に、最短日時計算処理部115は、特定した組織のすべての部署名、及びプルダウン63で指定した組織の部署名の行を部署名33から特定し、特定した行の最短日数38を抽出し(ステップ104)、その抽出した最短日数38をすべて加算する(ステップ105)。次に、最短日時計算処理部115は、ステップ105で加算した値に前回(告知)24の値、現在(告知)27の値を加算し(ステップ106、108)、その加算した値をそれぞれ、行動管理テーブル19の前回(最短日時)25、現在(最短日時)28に格納する(ステップ107、109)。ステップ109の後、ステップ100に戻る。これにより、プルダウン63で選択された部署名に関し、告知元部署34の列におけるすべての該当部署名について、その関連する部署を考慮した前回(最短日時)25、現在(最短日時)28の値を算出し格納することができる。   Next, the shortest date and time calculation processing unit 115 identifies all department names of the identified organization and the department name of the organization specified by the pull-down 63 from the department name 33, and extracts the minimum number of days 38 of the identified line. (Step 104), all the extracted shortest days 38 are added (Step 105). Next, the shortest date and time calculation processing unit 115 adds the value of the previous (notification) 24 and the value of the current (notification) 27 to the value added in step 105 (steps 106 and 108). They are stored in the previous (shortest date and time) 25 and the current (shortest date and time) 28 of the behavior management table 19 (steps 107 and 109). After step 109, the process returns to step 100. As a result, the values of the previous (shortest date and time) 25 and the current (shortest date and time) 28 in consideration of the related departments for all the department names in the column of the notification source department 34 regarding the department names selected from the pull-down 63 are obtained. Can be calculated and stored.

本実施形態の場合、プルダウン63で指定した組織の部署名である「第1部」に関して、特定した組織は「A課」「B課」「C課」となり、「A課」に関連する部門は「D関連部門」となる。表66の「A課」については、符号316の「4日」と符号323の「6日」と符号324の「20日」を加算し、最短日数は「30日」となる。また、符号211の行の「A課」の前回(告知)24の値は符号212の「2007/03/01」であり、これに「30日」を加算した値である「2007/03/30」を前回(最短日時)25である符号213に「2007/03/30」として格納する。同様にして、現在(告知)27の値(符号215)に「30日」を加算し、符号216に「2007/04/30」を格納する。   In the case of this embodiment, regarding the “first part” that is the department name of the organization specified in the pull-down 63, the specified organizations are “A section”, “B section”, and “C section”, and the sections related to “Section A”. Becomes "D-related department". For “section A” in Table 66, “4 days” of reference numeral 316, “6 days” of reference numeral 323, and “20 days” of reference numeral 324 are added, and the shortest number of days becomes “30 days”. In addition, the value of the previous (notification) 24 of “section A” in the row of reference numeral 211 is “2007/03/01” of reference numeral 212, which is a value obtained by adding “30 days” to “2007/03 /”. “30” is stored as “2007/03/30” in the reference numeral 213 which is the previous (shortest date and time) 25. Similarly, “30 days” is added to the value (reference numeral 215) of the current (notification) 27, and “2007/04/30” is stored in the reference numeral 216.

次に、図11に示すように、活動リスク判定処理部116は、格納された行動管理テーブル19の前回(最短日時)25、現在(告知)27、現在(最短日時)28、及び現在(行動完了)29の値を比較演算し、演算結果からリスクの内容をリスク判定テーブル112から選択し、選択したリスクの内容と前回(最短日時)25、現在(告知)27、現在(最短日時)28、及び現在(行動完了)29の値を表66の該当するセルへ表示するとともに、比較演算に使用したセルを網掛け表示する処理を次のように行う。   Next, as shown in FIG. 11, the activity risk determination processing unit 116 stores the previous (shortest date / time) 25, the current (notification) 27, the current (shortest date / time) 28, and the current (action) in the stored behavior management table 19. Completion) The value 29 is compared and the risk content is selected from the risk determination table 112 based on the calculation result. The selected risk content and the previous (shortest date) 25, current (notification) 27, current (shortest date) 28 In addition, the current (action complete) 29 value is displayed in the corresponding cell of Table 66, and the cell used for the comparison operation is displayed in a shaded manner as follows.

まず、活動リスク判定処理部116は、現在(告知)27から前回(最短日時)25を減算し(ステップ111)、その値が「0」より小さくなる場合は判定結果を「2」として取得し、現在(行動完了)29から現在(最短日時)28を減算し(ステップ112)、その値が「0」より小さくなる場合は判定結果を「3」として取得する。上記の判定以外の場合は判定結果を「1」とする。   First, the activity risk determination processing unit 116 subtracts the previous (shortest date and time) 25 from the current (notification) 27 (step 111), and if the value is smaller than “0”, acquires the determination result as “2”. The current (shortest date and time) 28 is subtracted from the current (action complete) 29 (step 112), and if the value is smaller than “0”, the determination result is acquired as “3”. In cases other than the above determination, the determination result is “1”.

活動リスク判定処理部116は、その判定結果とリスク判定テーブル112から判定結果52を特定し(ステップ113)、該当する判定結果52の行のリスク内容53を特定する(ステップ114)。活動リスク判定処理部116は、前記で判定に利用したセル(前回(最短日時)25の値、現在(告知)27の値、現在(最短日時)28の値、現在(行動完了)29の値)のうち、判定結果52が「2」または「3」のセルを網掛け(着色)表示するセルとして特定する(ステップ115)。   The activity risk determination processing unit 116 specifies the determination result 52 from the determination result and the risk determination table 112 (step 113), and specifies the risk content 53 of the row of the corresponding determination result 52 (step 114). The activity risk determination processing unit 116 uses the cell (the value of the previous (shortest date / time) 25, the value of the current (notification) 27, the value of the current (shortest date / time) 28, the value of the current (action complete) 29 used in the above determination. ), A cell having a determination result 52 of “2” or “3” is specified as a cell to be shaded (colored) (step 115).

また、活動リスク判定処理部116は、そのリスク内容53と着色するセルに関するデータが表66の符号612、614、615、616、610のセルへ反映するように出力解析処理部18へ出力する(ステップ116)。これらの処理を、部署名67に表示されている部署数分実施する。なお、判定結果が複数となる場合は、対象のリスク内容53の文字列を結合して出力解析処理部18へ出力するようにしてもよい。   In addition, the activity risk determination processing unit 116 outputs the risk content 53 and the data related to the colored cell to the output analysis processing unit 18 so that the data is reflected in the cells 612, 614, 615, 616, and 610 in Table 66 ( Step 116). These processes are performed for the number of departments displayed in the department name 67. When there are a plurality of determination results, the character strings of the target risk contents 53 may be combined and output to the output analysis processing unit 18.

本実施形態の例において、「A課」の場合、符号215の「2007/04/01」から符号213の「2007/03/30」を減算すると「0」以上となり、符号217の「−」から符号216「2007/04/30」を減算すると「0」以上(減算元が「−」の場合は減算結果が「0」以上であることとすると定義しておけばよい)となるため、判定結果は「1」となる。従って、リスク判定テーブル112の判定結果52が「1」となるリスク内容53は「リスクはありません」となり、この文字列「リスクはありません」を符号632のセルに表示するように出力解析処理部18へ出力する。この場合、網掛け(着色)するセルに関する情報を出力解析処理部18へ出力する必要はない。   In the example of the present embodiment, in the case of “section A”, subtraction of “2007/03/30” of reference numeral 213 from “2007/04/01” of reference numeral 215 results in “0” or more, and “−” of reference numeral 217. Since the code 216 “2007/04/30” is subtracted from “0” or more (if the subtraction source is “−”, it may be defined that the subtraction result is “0” or more), The determination result is “1”. Therefore, the risk content 53 for which the determination result 52 of the risk determination table 112 is “1” is “no risk”, and the output analysis processing unit 18 displays the character string “no risk” in the cell indicated by reference numeral 632. Output to. In this case, it is not necessary to output information related to the cells to be shaded (colored) to the output analysis processing unit 18.

また、「B課」の場合、符号221の「2007/04/20」から符号219の「2007/05/10」を減算すると「0」未満となり、符号223の「−」から符号222の「2007/05/30」を減算すると「0」以上となるため、判定結果は「2」となる。従って、リスク判定テーブル112の判定結果52が「2」となる行は符号54となり、そのリスク内容53は「現在の告知時期が早すぎます。現在の告知時期を後ろにずらす必要があります。」(符号55)となる。そして、この文字列「現在の告知時期が早すぎます。現在の告知時期を後ろにずらす必要があります。」、符号219の「2007/05/10」、及び符号221の「2007/04/20」をそれぞれ符号624、619、621のセルへ表示し、網掛け(着色)するように出力解析処理部18へ第1のリスク表示信号を出力する。   Further, in the case of “section B”, subtracting “2007/05/10” of reference numeral 219 from “2007/04/20” of reference numeral 221 results in less than “0”, and from “−” of reference numeral 223 to “ When "2007/05/30" is subtracted, it becomes "0" or more, so the determination result is "2". Therefore, the line in which the determination result 52 of the risk determination table 112 is “2” is denoted by reference numeral 54, and the risk content 53 is “the current notification time is too early. The current notification time needs to be shifted backward.” (Reference numeral 55). This character string “current notification time is too early. The current notification time needs to be shifted backward.”, “219/05/10” of reference numeral 219, and “2007/04/20 of reference numeral 221” "Is displayed in cells 624, 619, and 621, respectively, and a first risk display signal is output to the output analysis processing unit 18 so as to be shaded (colored).

「C課」の場合、「B課」の場合と同様であるので詳細な説明を省略するが、図11のステップ112における判定結果が「3」となり、第2のリスク表示信号が出力解析処理部18へ出力され、符号626、627、628のセルに図示したような情報と網掛け(着色)による表示がなされる。   The case of “section C” is the same as the case of “section B” and will not be described in detail. However, the determination result in step 112 in FIG. 11 is “3”, and the second risk display signal is output analysis processing. The information is output to the unit 18, and the information shown in the cells 626, 627, and 628 and the display by shading (coloring) are performed.

このように、本実施形態の目標管理システムSは、目標変更に対する現場の行動を管理する際に、組織や現場の状態によって現場の追従度合いを予測するシステムである。これにより、告知した総数、部門のまたがり数、告知方法によって調整可能な最短日時を計算し、計算した最短日時と告知日(あるいは行動完了日)を比較することにより、管理者の告知タイミングの妥当性や現場の行動の品質レベルを把握することができる。   As described above, the target management system S according to the present embodiment is a system that predicts the degree of follow-up on the site according to the state of the organization and the site when managing the action on the site for the target change. By calculating the shortest date and time that can be adjusted according to the total number of notifications, the number of divisions across the department, and the notification method, and comparing the calculated shortest date and time with the date of notification (or the date of completion of the action) It is possible to understand the quality level of gender and on-site behavior.

また、目標管理システムSにより、管理者は、告知のタイミングの妥当性(前回の告知内容が組織に浸透していないにもかかわらず、新しい告知を発信し、現場で情報が錯綜する可能性があるか否か)、及び、現場の行動の品質(例えば、告知内容が組織に浸透していないにもかかわらず、現場が行動完了していることは、現場は活動内容を十分に検討していない可能性がある)を予測できる。従って、管理者の告知乱発による現場の混乱や、現場の検討不十分による目標値との乖離を防ぐことができるため、現場は管理者が設定した目標値に追従した行動をすることができる。   In addition, the target management system S allows the administrator to determine the appropriateness of the timing of the notification (even though the content of the previous notification has not penetrated the organization, there is a possibility that information will be confused at the site by sending a new notification. And the quality of the action at the site (for example, the fact that the action has been completed despite the fact that the notification content has not penetrated the organization) Can be predicted). Therefore, since the site can be prevented from being confused due to the misuse of notification by the manager and the deviation from the target value due to insufficient examination of the site, the site can behave according to the target value set by the manager.

また、本発明は、組織が多くあり社内通達などの告知が組織間で多数飛び交う企業全般に利用可能である。特に、現業務と平行して事業構造を改革している企業(グローバル改革において現地と国内で改革中)など、告知が錯綜し現場活動が混乱しやすい企業に対して高い効果が期待できる。また、2006年6月に成立した金融商品取引法(内部統制報告制度)の1要素である「情報と伝達」について、親会社と子会社間の伝達リスクを把握する用途でも利用可能である。   In addition, the present invention can be used for all companies where there are many organizations and a large number of notifications such as in-house notifications fly between the organizations. In particular, companies that are reforming their business structure in parallel with current operations (reforming local and domestic companies in global reforms) can be expected to be highly effective for companies that are confused with on-site activities. In addition, “information and transmission”, which is one element of the Financial Instruments and Exchange Act (internal control reporting system) enacted in June 2006, can also be used to grasp the transmission risk between the parent company and the subsidiary.

以上で実施形態の説明を終えるが、本発明の態様はこれらに限定されるものではない。
ハードウェア、プログラム、表示画面などの具体的な構成について、本発明の主旨を逸脱しない範囲で適宜変更が可能である。
This is the end of the description of the embodiments, but the aspects of the present invention are not limited to these.
Specific configurations of hardware, programs, display screens, and the like can be changed as appropriate without departing from the spirit of the present invention.

本実施形態の目標管理システムの構成図である。It is a block diagram of the target management system of this embodiment. 行動管理テーブルの構成図である。It is a block diagram of an action management table. 告知情報管理テーブルの構成図である。It is a block diagram of a notification information management table. 告知方法管理テーブルの構成図である。It is a block diagram of a notification method management table. リスク判定テーブルの構成図である。It is a block diagram of a risk determination table. リスク表示画面の構成図である。It is a block diagram of a risk display screen. 目標管理システムの処理の流れの概要を示すフロー図である。It is a flowchart which shows the outline | summary of the flow of a process of a target management system. 図7におけるステップ71の詳細処理フロー図である。FIG. 8 is a detailed process flowchart of step 71 in FIG. 7. 図7におけるステップ72の詳細処理フロー図である。FIG. 8 is a detailed process flowchart of step 72 in FIG. 7. 図7におけるステップ73の詳細処理フロー図である。FIG. 8 is a detailed process flow diagram of step 73 in FIG. 7. 図7におけるステップ74の詳細処理フロー図である。FIG. 8 is a detailed process flow diagram of step 74 in FIG. 7.

符号の説明Explanation of symbols

11 ディスプレイ(表示部)
19 行動管理テーブル(行動管理情報)
110 告知情報管理テーブル(行動指示情報管理情報)
111 告知方法管理テーブル(行動指示方法管理情報)
1201 データ格納装置(記憶部)
1202 演算装置(演算部)
S 目標管理システム(管理システム)
11 Display (display unit)
19 Behavior management table (Behavior management information)
110 Notification information management table (action instruction information management information)
111 Notification Method Management Table (Behavior Instruction Method Management Information)
1201 Data storage device (storage unit)
1202 Arithmetic unit (calculation unit)
S target management system (management system)

Claims (9)

階層化された複数の部署からなる組織の活動を管理する管理システムであって、
前記部署ごとに、前回の行動指示に対する行動終了の予定日時である前回行動終了予定日時、及び、最新の行動指示の予定日時である最新行動指示予定日時を格納する行動管理情報を記憶する記憶部と、
前記記憶部の行動管理情報を参照し、所定の部署に関して、前記前回行動終了予定日時と前記最新行動指示予定日時を比較し、前記前回行動終了予定日時のほうが遅い日時であったときに第1のリスク表示信号を出力する演算部と、
前記演算部から第1のリスク表示信号を受信すると、前記最新行動指示予定日時が妥当ではない可能性がある旨の表示を行う表示部と、
を備えたことを特徴とする管理システム。
A management system that manages the activities of an organization consisting of multiple departments,
A storage unit that stores behavior management information for storing the previous action end scheduled date and time that is the scheduled end date and time of the last action instruction and the latest action instruction scheduled date and time that is the scheduled date and time of the latest action instruction for each department When,
With reference to the action management information in the storage unit, the previous action end scheduled date and time are compared with the latest action instruction scheduled date and time for a predetermined department, and the first action end date and time is later than the first date. A calculation unit that outputs a risk display signal of
When receiving the first risk display signal from the calculation unit, a display unit that displays that the latest action instruction scheduled date and time may not be valid;
A management system characterized by comprising:
前記記憶部は、前記部署ごとに、行動指示元部署からの指示回数、及び、その指示消化に必要な時間のそれぞれ相対的な重み値を格納する行動指示情報管理情報を、さらに記憶し、
前記演算部は、前記行動指示情報管理情報を参照し、前記所定の部署に関して、前記指示回数の重み値と前記指示消化に必要な時間の重み値と所定の算出式に基づいて行動指示伝達必要時間を算出し、前回の行動指示の日時からその関連部署のそれぞれの前記行動指示伝達必要時間を加算した値に対応する時間が経過した日時を前記前回行動終了予定日時として前記行動管理情報に格納する
ことを特徴とする請求項1に記載の管理システム。
The storage unit further stores, for each of the departments, action instruction information management information for storing the number of instructions from the action instruction source department, and a relative weight value of each time required for instruction digestion,
The arithmetic unit refers to the action instruction information management information and needs to transmit an action instruction with respect to the predetermined department based on a weight value of the number of instructions, a weight value of time required for digesting the instruction, and a predetermined calculation formula. The time is calculated, and the date and time when the time corresponding to the value obtained by adding the time required to transmit the action instructions of each related department from the date and time of the previous action instruction has elapsed is stored in the action management information as the previous action end scheduled date and time. The management system according to claim 1, wherein:
前記記憶部は、行動指示の方法ごとに、理解度レベル及び必要時間のそれぞれ相対的な重み値を格納する行動指示方法管理情報を、さらに記憶し、
前記演算部は、前記行動指示方法管理情報を参照し、前記所定の部署に関して、前記理解度レベルの重み値、必要時間の重み値、及び前記指示回数の重み値を乗算することで前記指示消化に必要な時間を算出し、前記行動指示情報管理情報に格納する
ことを特徴とする請求項2に記載の管理システム。
The storage unit further stores behavior instruction method management information for storing a relative weight value of an understanding level and a required time for each method of behavior instruction,
The calculation unit refers to the action instruction method management information, and multiplies the instruction level by multiplying the weight value of the understanding level, the weight value of the required time, and the weight value of the instruction count for the predetermined department. The management system according to claim 2, wherein a time required for the calculation is calculated and stored in the action instruction information management information.
前記行動管理情報は、前記部署ごとに、最新の行動指示の日時から前記関連部署のそれぞれ行動指示伝達必要時間を加算した値に対応する時間が経過した日時を最新行動終了予定日時として保持し、
前記演算部は、前記所定の部署に関して、入力された現実の行動終了日時と、前記行動管理情報に格納された最新行動終了予定日時を比較し、前記最新行動終了予定日時のほうが遅い日時であったときに第2のリスク表示信号を出力し、
前記表示部は、前記演算部から前記第2のリスク表示信号を受信すると、前記現実の行動終了日時が妥当ではない可能性がある旨の表示を行う
ことを特徴とする請求項2に記載の管理システム。
The behavior management information holds, as the latest action end scheduled date and time, for each of the departments, the date and time when the time corresponding to the value obtained by adding the action instruction transmission required time of the related department from the date and time of the latest action instruction has elapsed,
The calculation unit compares the input actual action end date and time with the latest action end scheduled date and time stored in the action management information for the predetermined department, and the latest action end scheduled date and time is later. Outputs a second risk indication signal when
3. The display according to claim 2, wherein when the second risk display signal is received from the calculation unit, the display unit displays that the actual action end date may be invalid. Management system.
階層化された複数の部署からなる組織の活動を管理する管理システムによる管理方法であって、
前記管理システムは、
前記部署ごとに、前回の行動指示に対する行動終了の予定日時である前回行動終了予定日時、及び、最新の行動指示の予定日時である最新行動指示予定日時を格納する行動管理情報を記憶する記憶部と、演算部と、表示部と、を備え、
前記演算部は、前記記憶部の行動管理情報を参照し、所定の部署に関して、前記前回行動終了予定日時と前記最新行動指示予定日時を比較し、前記前回行動終了予定日時のほうが遅い日時であったときに第1のリスク表示信号を出力し、
前記表示部は、前記演算部から第1のリスク表示信号を受信すると、前記最新行動指示予定日時が妥当ではない可能性がある旨の表示を行う
ことを特徴とする管理方法。
A management method using a management system that manages the activities of an organization consisting of a plurality of hierarchized departments,
The management system includes:
A storage unit that stores behavior management information for storing the previous action end scheduled date and time that is the scheduled end date and time of the last action instruction and the latest action instruction scheduled date and time that is the scheduled date and time of the latest action instruction for each department And a calculation unit and a display unit,
The calculation unit refers to the behavior management information in the storage unit, compares the scheduled last action end date and time with the latest scheduled action instruction date and time for a predetermined department, and the last scheduled action end date and time is later. Output a first risk indication signal when
When the display unit receives the first risk display signal from the calculation unit, the display unit displays that the latest action instruction scheduled date and time may be invalid.
前記記憶部は、前記部署ごとに、行動指示元部署からの指示回数、及び、その指示消化に必要な時間のそれぞれ相対的な重み値を格納する行動指示情報管理情報を、さらに記憶し、
前記演算部は、前記行動指示情報管理情報を参照し、前記所定の部署に関して、前記指示回数の重み値と前記指示消化に必要な時間の重み値と所定の算出式に基づいて行動指示伝達必要時間を算出し、前回の行動指示の日時からその関連部署のそれぞれの前記行動指示伝達必要時間を加算した値に対応する時間が経過した日時を前記前回行動終了予定日時として前記行動管理情報に格納する
ことを特徴とする請求項5に記載の管理方法。
The storage unit further stores, for each of the departments, action instruction information management information for storing the number of instructions from the action instruction source department, and a relative weight value of each time required for instruction digestion,
The arithmetic unit refers to the action instruction information management information and needs to transmit an action instruction with respect to the predetermined department based on a weight value of the number of instructions, a weight value of time required for digesting the instruction, and a predetermined calculation formula. The time is calculated, and the date and time when the time corresponding to the value obtained by adding the time required to transmit the action instructions of each related department from the date and time of the previous action instruction has elapsed is stored in the action management information as the previous action end scheduled date and time. The management method according to claim 5, wherein:
前記記憶部は、行動指示の方法ごとに、理解度レベル及び必要時間のそれぞれ相対的な重み値を格納する行動指示方法管理情報を、さらに記憶し、
前記演算部は、前記行動指示方法管理情報を参照し、前記所定の部署に関して、前記理解度レベルの重み値、必要時間の重み値、及び前記指示回数の重み値を乗算することで前記指示消化に必要な時間を算出し、前記行動指示情報管理情報に格納する
ことを特徴とする請求項6に記載の管理方法。
The storage unit further stores behavior instruction method management information for storing a relative weight value of an understanding level and a required time for each method of behavior instruction,
The calculation unit refers to the action instruction method management information, and multiplies the instruction level by multiplying the weight value of the understanding level, the weight value of the required time, and the weight value of the instruction count for the predetermined department. The management method according to claim 6, further comprising: calculating a time required for the management and storing the time in the action instruction information management information.
前記行動管理情報は、前記部署ごとに、最新の行動指示の日時から前記関連部署のそれぞれ行動指示伝達必要時間を加算した値に対応する時間が経過した日時を最新行動終了予定日時として保持し、
前記演算部は、前記所定の部署に関して、入力された現実の行動終了日時と、前記行動管理情報に格納された最新行動終了予定日時を比較し、前記最新行動終了予定日時のほうが遅い日時であったときに第2のリスク表示信号を出力し、
前記表示部は、前記演算部から前記第2のリスク表示信号を受信すると、前記現実の行動終了日時が妥当ではない可能性がある旨の表示を行う
ことを特徴とする請求項6に記載の管理方法。
The behavior management information holds, as the latest action end scheduled date and time, for each of the departments, the date and time when the time corresponding to the value obtained by adding the action instruction transmission required time of the related department from the date and time of the latest action instruction has elapsed,
The calculation unit compares the input actual action end date and time with the latest action end scheduled date and time stored in the action management information for the predetermined department, and the latest action end scheduled date and time is later. Outputs a second risk indication signal when
The said display part, when receiving the said 2nd risk display signal from the said calculating part, displays that the said actual action end date may not be appropriate. Management method.
請求項5から請求項8までのいずれか1項に記載の管理方法をコンピュータに実行させることを特徴とするプログラム。   A program that causes a computer to execute the management method according to any one of claims 5 to 8.
JP2007196389A 2007-07-27 2007-07-27 Management system, management method, and program Pending JP2009032097A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007196389A JP2009032097A (en) 2007-07-27 2007-07-27 Management system, management method, and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007196389A JP2009032097A (en) 2007-07-27 2007-07-27 Management system, management method, and program

Publications (1)

Publication Number Publication Date
JP2009032097A true JP2009032097A (en) 2009-02-12

Family

ID=40402521

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007196389A Pending JP2009032097A (en) 2007-07-27 2007-07-27 Management system, management method, and program

Country Status (1)

Country Link
JP (1) JP2009032097A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018096856A1 (en) * 2016-11-25 2018-05-31 株式会社日立製作所 Company information system and company information providing method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018096856A1 (en) * 2016-11-25 2018-05-31 株式会社日立製作所 Company information system and company information providing method

Similar Documents

Publication Publication Date Title
US20230236805A1 (en) Systems and Methods for Development and Deployment of Software Platforms Having Advanced Workflow and Event Processing Components
US8543527B2 (en) Method and system for implementing definable actions
US8209669B2 (en) System and method for supporting software
US10970114B2 (en) Systems and methods for task scheduling
US8799796B2 (en) System and method for generating graphical dashboards with drill down navigation
US20070106577A1 (en) Apparatus and method for facilitating trusted business intelligence
US20100138268A1 (en) Progress management platform
US10007951B2 (en) IT asset management trend charting for compliance over time
WO2004021147A9 (en) Decision analysis system and method
US20040128357A1 (en) Method for tracking responses to a forum topic
US9311385B2 (en) Indicating level of confidence in digital content
US10324951B1 (en) Tracking and viewing model changes based on time
US20220292006A1 (en) System for Automatically Generating Insights by Analysing Telemetric Data
Karkhanis et al. Improving the effectiveness of root cause analysis in hospitals
US8843882B1 (en) Systems, methods, and algorithms for software source code analytics and software metadata analysis
JP4714130B2 (en) Risk analysis method, risk analysis system, and risk analysis program
US8731982B2 (en) System and methodology for sequential navigation and monitoring in a business process or complex task
JP2009032097A (en) Management system, management method, and program
Kulkarni et al. Authoring a periodic adverse drug experience report… here's what you need to know!
US20100107049A1 (en) Dynamic Generation of Data Entry Metadata
JP2017509940A (en) Systems, devices and methods for exchanging and processing data scales and objects
US10515330B2 (en) Real time visibility of process lifecycle
US20110276912A1 (en) Automating internal controls assessments for outsourced operations
CN112236786A (en) Future prediction simulation device, method, and computer program
US20070260983A1 (en) Method for providing a summary of user activities