JP2007164580A - Production control system - Google Patents

Production control system Download PDF

Info

Publication number
JP2007164580A
JP2007164580A JP2005361760A JP2005361760A JP2007164580A JP 2007164580 A JP2007164580 A JP 2007164580A JP 2005361760 A JP2005361760 A JP 2005361760A JP 2005361760 A JP2005361760 A JP 2005361760A JP 2007164580 A JP2007164580 A JP 2007164580A
Authority
JP
Japan
Prior art keywords
lot
processing
evaluation
production
processes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005361760A
Other languages
Japanese (ja)
Inventor
Yoji Sakaguchi
洋二 阪口
Kazuhide Umewaka
一秀 梅若
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sharp Corp
Original Assignee
Sharp Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sharp Corp filed Critical Sharp Corp
Priority to JP2005361760A priority Critical patent/JP2007164580A/en
Publication of JP2007164580A publication Critical patent/JP2007164580A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

<P>PROBLEM TO BE SOLVED: To improve productivity/efficiency comprehensively by making a proper work instruction to each processing equipment in a production line adopting a job-shop production system. <P>SOLUTION: A flexible production control system having high overall efficiency is provided, which calculates an overall index that can weight a main index on the basis of a device state and a lot state for individual optimization but for improving the overall efficiency of a production line about items such as lead time, a device operating ratio, device efficiency and punctuality which are main efficiency indexes in a production line, and prepares a lot processing sequence corresponding to production status and index importance at that time and a process processing pattern. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、ジョブショップ型の多品種少量の生産形態をとる製造工場等の生産制御システムに関する。   The present invention relates to a production control system for a manufacturing factory or the like that takes a production form of a job shop type in a variety of small quantities.

一般に、あらゆる生産ラインにおいては、各ロットの納期を遵守することや、生産のリードタイムを可能な限り短縮することは、効率的な生産を行ううえで重要な項目である。生産ラインを効率的に稼動させるために、生産する対象製品の工程に合わせて、フローショップ型、ジョブショップ型、オープンショップ型など、各種の生産形態が実践されている。   In general, in every production line, complying with the delivery date of each lot and shortening the production lead time as much as possible are important items for efficient production. In order to operate the production line efficiently, various production forms such as a flow shop type, a job shop type, and an open shop type are practiced according to the process of the target product to be produced.

半導体生産ラインにおいては、生産する品種が多く、生産工程が複雑なため、単純なフローショップ型では効率的な生産は困難であるので、多種の機械で、多様な順番で半導体ウェハをロット単位で工程処理するジョブショップ型をとっている。ジョブショップ形態をとる生産形態の中でも、特に半導体生産ラインにおいては、処理装置としてスパッタ、ステッパ装置等、他の製品の生産ラインよりも高価な製造装置を使用する為、前記ロットの納期遵守、リードタイム短縮といった評価指標に加えて、装置の稼働率をあらわす評価指標が、生産ラインの効率を評価するうえで、大きな要因となる。したがって、半導体生産ラインにおいては、装置の稼働率は、生産ラインの総合的な効率を考えるうえでは、欠かすことにできない主要な評価指標となる。   In the semiconductor production line, there are many varieties to produce and the production process is complicated, so it is difficult to produce efficiently with a simple flow shop type. The job shop type is used for process processing. Among the production forms taking the job shop form, especially in the semiconductor production line, the manufacturing equipment that is more expensive than the production line of other products such as sputtering and stepper equipment is used as the processing equipment. In addition to an evaluation index such as time reduction, an evaluation index representing the operation rate of the apparatus is a major factor in evaluating the efficiency of the production line. Therefore, in the semiconductor production line, the operation rate of the apparatus is a main evaluation index that is indispensable when considering the overall efficiency of the production line.

このように、生産対象や生産設備等の要因により、生産ラインにおける評価指標の重み付けは異なる場合がある。また、評価指標毎に、その構成要素は夫々異なる。   Thus, the weighting of the evaluation index in the production line may differ depending on factors such as the production target and production equipment. In addition, the constituent elements are different for each evaluation index.

例えば、装置の稼働率については、その向上のために、装置のスループットの最大化を図る方法がある。これには、各装置の処理方法に応じたロット供給を行う必要があり、一般的には、同一レシピ(条件)で処理可能ロットを連続で供給することにより、レシピ切替により発生する時間ロスを削減、あるいはバッチ編成装置においては、フルバッチで処理させてスループットを向上させる。   For example, there is a method for maximizing the throughput of the apparatus in order to improve the operating rate of the apparatus. For this, it is necessary to supply lots according to the processing method of each device. Generally, by continuously supplying lots that can be processed under the same recipe (conditions), time loss caused by recipe switching is reduced. In the reduction or batch knitting apparatus, processing is performed in a full batch to improve throughput.

この他、各種の評価指標の構成要素の分析等をして、様々な評価指標改善の方法が考案され、実践されている。しかしながら、前述のように多品種少量生産をおこなう半導体生産ラインなど、生産ラインによって、評価指標の重み付けが異なったり、稼動する生産装置の様々な動作条件や納期など、多くの制約や考慮すべき要素があり、かつ評価指標は独立ではなく互いに影響しあっていること等もあって、総合的に生産ラインの効率化を図ることは非常に困難であるとされている。   In addition, various evaluation index improvement methods have been devised and practiced by analyzing components of various evaluation indices. However, as mentioned above, there are many restrictions and factors to be considered, such as semiconductor production lines that produce a variety of products in small quantities, such as the weighting of the evaluation index varies depending on the production line, and various operating conditions and delivery times of the production equipment that operates. In addition, it is said that it is very difficult to improve the efficiency of the production line comprehensively because the evaluation indicators are not independent but interact with each other.

こうしたなかで、生産ラインの効率化の為の生産制御システムやシミュレーション方法などが、数多く提案されており、以下の文献にその例を見ることができる。   Under these circumstances, many production control systems and simulation methods for improving the efficiency of production lines have been proposed, and examples thereof can be found in the following documents.

例えば、特許文献1では、フルバッチ処理をさせる為の方法として、装置での処理待ちロットと装置に未到着のロットの到着時刻を予測するリアルタイムスケジューリング装置を組み合わせることにより、フルバッチで処理させるスケジュールを作成する方法がある。また、特許文献2では、処理するロットの装置への投入タイミングを適切に設定すべく、各種状態のデータベースを作成し、これに基づいて、装置へのロット投入のスケジューリングをシミュレートし、スケジュール効率の向上を図ったものなどが提案されている。
特開平8−24115号公報 特開平8−31709号公報
For example, in Patent Document 1, as a method for performing full batch processing, a schedule for processing in a full batch is created by combining a processing waiting lot in the device and a real-time scheduling device that predicts the arrival time of an unarrived lot in the device. There is a way to do it. Further, in Patent Document 2, a database of various states is created in order to appropriately set the input timing of the lot to be processed into the apparatus, and on this basis, the scheduling of the lot input into the apparatus is simulated, and the schedule efficiency The thing etc. which aimed at the improvement of are proposed.
JP-A-8-24115 JP-A-8-31709

特許文献1の方法は、図14に示すように、バッチ編成工程においてバッチ編成待ちロットの最遅着手時刻と、バッチ編成可能ロットの到着予定時刻と現在時刻の関係によってバッチ編成可能ロットの到着を待って工程処理を開始するかどうかを判断するものであり、この仕組みは納期を守りつつバッチ編成数をあげるという点で効果はあるが、バッチ編成可能ロットの到着予定時刻はあらかじめスケジューラによって計算されたものであるために、バッチ編成可能ロットの処理順序を前倒しするなどの方法によりバッチ編成可能ロットの到着予定時刻を早める可能性を考慮していない点が不十分である。   As shown in FIG. 14, in the method of Patent Document 1, the batch knitting process determines the arrival of the batch knitted lot by the latest start time of the batch knitting waiting lot, the scheduled arrival time of the batch knitted lot, and the current time. This mechanism is used to determine whether or not to start process processing. This mechanism is effective in increasing the number of batch formations while keeping delivery times, but the scheduled arrival time of batch-formable lots is calculated in advance by the scheduler. Therefore, it is insufficient that the possibility of advancing the estimated arrival time of the batch knitted lot by a method such as advancing the processing order of the batch knitted lot is advanced.

また、こうした方式は、評価指標の1つの要素である装置効率を上げることを目的としており、その他の評価指標の向上や改善については考慮されていない。特許文献2についても、同様に装置効率の向上に重点を置いたものであるため、生産ライン全体としての効率向上を考慮したものとはいえない。   In addition, such a method is intended to increase apparatus efficiency, which is one element of the evaluation index, and does not take into consideration improvement or improvement of other evaluation indices. Since Patent Document 2 also focuses on improving the efficiency of the apparatus, it cannot be said that the improvement of the efficiency of the entire production line is taken into consideration.

総合的に生産ラインの効率向上を図るうえでは、各種の評価指標を個別に最適に調整するだけでは不十分であり、リードタイム長期化・稼働率低下・装置効率悪化・納期遅れなどの重要な要素に注目して、これらの評価指標を同時に考慮して、総合的な観点で評価しなければならない。つまり、複数の評価指標について相互にバランスを取ったうえで総合的に適正化することが重要である。また、一方、実際の生産ラインでは、在庫や、市場の動向に応じて、生産ラインにおける各種評価指標の重要度は変化するものであるので、これらの生産ラインの評価指標の重要度は常に一定とは限らず、状況に応じて、その重要度は変動するので、柔軟な対応ができることが望まれる。   In order to improve overall production line efficiency, it is not sufficient to optimally adjust each evaluation index individually. Important factors such as longer lead times, lower operating rates, lower equipment efficiency, and delayed delivery are important. Focusing on the elements, these evaluation indicators should be considered simultaneously and evaluated from a comprehensive perspective. In other words, it is important to optimize a plurality of evaluation indices in a comprehensive manner after balancing each other. On the other hand, in an actual production line, the importance of various evaluation indices in the production line changes according to inventory and market trends, so the importance of these production line evaluation indices is always constant. However, since the importance varies depending on the situation, it is desirable to be able to respond flexibly.

本発明は、生産ラインにおける各種の生産性・効率を評価する評価指標について、一方に偏ることなく、夫々の評価指標のバランスを取って、総合的に生産性・効率が向上するようなロット処理順序および、これに基づく工程処理パターンを選定しつつ、生産状況に応じて柔軟に対応することが可能な生産制御システムを提供することを目的とする。   The present invention relates to an evaluation index for evaluating various productivity / efficiency in a production line, and balances each evaluation index without biasing to one, so that lot processing that improves productivity / efficiency comprehensively is achieved. An object of the present invention is to provide a production control system capable of flexibly responding to a production situation while selecting an order and a process processing pattern based on the order.

上記目的を達成すべく、本発明は、複数の工程及び複数のロットを処理するジョブショップ形態を取る生産ラインにおいて、各ロットの状態データと、工程の各装置の状態データを取得し、各工程が取り得るロットの処理順序の組み合わせを作成して、各工程のロットの処理順序を組み合わせて、全工程の工程処理パターンを全て構成し、前記各ロットの状態データと、各装置の状態データを基に得られる評価点より、工程処理パターンの中から、評価点が最良となる工程処理パターンを選定し、評価点が最良である工程処理パターンを構成する各工程のロットの処理順序で各装置を制御することを特徴とする。   In order to achieve the above object, the present invention obtains the status data of each lot and the status data of each device of the process in a production line that takes a form of a job shop that processes a plurality of processes and a plurality of lots. Create a combination of lot processing order that can be taken, combine the processing order of lots of each process, configure all process processing patterns of all processes, state data of each lot, and status data of each device Based on the evaluation points obtained based on the process processing pattern, the process processing pattern with the best evaluation point is selected, and each device in the processing order of the lots of each process constituting the process processing pattern with the best evaluation point It is characterized by controlling.

また、例えば、複数の工程及び複数のロットを処理するジョブショップ形態を取る生産ラインにおいて、各ロットの状態データと、工程の各装置の状態データを取得し、各工程が取り得るロットの処理順序の組み合わせを作成して、各工程のロットの処理順序を組み合わせて、全工程の工程処理パターンを全て構成し、各ロットの状態データと、各装置の状態データを基に得られる評価点より、工程処理パターンの中から、評価点が最良となる工程処理パターンを選定する第1の計算装置と、第1の計算装置から得られた評価点が最良の工程処理パターンを構成する各工程のロットの処理順序に基づいて、各装置を制御し、各装置にロットを供給する第2の計算装置を備えることとしてもよい。   Also, for example, in a production line that takes the form of a job shop that processes a plurality of processes and a plurality of lots, the status data of each lot and the status data of each device of the process are acquired, and the processing order of lots that each process can take From the evaluation points obtained based on the status data of each lot and the status data of each device, all the process processing patterns of all the processes are configured by combining the lot processing order of each process. A first computing device that selects a process processing pattern with the best evaluation score from among the process processing patterns, and a lot of each process that makes up the best process processing pattern with the evaluation score obtained from the first computing device. It is good also as providing the 2nd calculation apparatus which controls each apparatus based on these processing orders and supplies a lot to each apparatus.

また、例えば、評価点は、ロット処理のリードタイム評価指標と、装置の稼働率評価指標と、装置の効率評価指標と、ロットの納期遅延率評価指標とに基づいて算出することとした構成でもよい。   Further, for example, the evaluation score may be calculated based on a lot processing lead time evaluation index, an apparatus operation rate evaluation index, an apparatus efficiency evaluation index, and a lot delivery date delay rate evaluation index. Good.

また、例えば、前記評価点は、評価点を構成する各評価指標に、夫々に重み付け係数を乗じたものに基づいて算出することとした構成でもよい。   Further, for example, the evaluation score may be calculated based on each evaluation index constituting the evaluation score multiplied by a weighting coefficient.

また、例えば、前記評価点の重み付け係数は、可変であることとしても良い。   For example, the weighting coefficient of the evaluation point may be variable.

本発明の構成によれば、複数の工程及び複数のロットを処理するジョブショップ形態を取る生産ラインにおいて、各ロットの状態データと、工程の各装置の状態データを取得し、各工程が取り得るロットの処理順序の組み合わせを作成して、各工程のロットの処理順序を組み合わせて、全工程の工程処理パターンを全て構成し、前記各ロットの状態データと、各装置の状態データを基に得られる評価点から、工程処理パターンの中から、評価点が最良となる工程処理パターンを選定し、評価点が最良である工程処理パターンを構成する各工程のロットの処理順序で各装置を制御することとした。   According to the configuration of the present invention, in a production line that takes a form of a job shop that processes a plurality of processes and a plurality of lots, the status data of each lot and the status data of each device in the process can be acquired, and each process can take Create a combination of lot processing order, combine lot processing order of each process, configure all process processing patterns of all processes, and obtain based on the status data of each lot and the status data of each device The process processing pattern with the best evaluation point is selected from the process processing patterns from the evaluation points to be controlled, and each device is controlled in the processing order of the lots of the respective processes constituting the process processing pattern with the best evaluation point. It was decided.

このように構成することで、ロットの状態と装置の状態との両方のデータから、各種評価指標に基づく総合的な評価を示す評価点が最も良い、全工程の工程処理パターンを抽出して、これに基づいて生産ラインの各装置にロットの処理順序を指示することができるので、スケジューリング時点で得られている各種条件を考慮された生産制御を行って、総合的に生産ラインの効率を上げることが可能となる。   By configuring in this way, from the data of both the state of the lot and the state of the device, the best evaluation point showing a comprehensive evaluation based on various evaluation indexes, the process processing pattern of all processes is extracted, Based on this, the lot processing order can be instructed to each device on the production line, and production control taking into account the various conditions obtained at the time of scheduling is performed to increase the efficiency of the production line comprehensively. It becomes possible.

また、複数の工程及び複数のロットを処理するジョブショップ形態を取る生産ラインにおいて、各ロットの状態データと、工程の各装置の状態データを取得し、各工程が取り得るロットの処理順序の組み合わせを作成して、各工程のロットの処理順序を組み合わせて、全工程の工程処理パターンを全て構成し、各ロットの状態データと、各装置の状態データを基に得られる評価点より、工程処理パターンの中から、評価点が最良となる工程処理パターンを選定する第1の計算装置と、第1の計算装置から得られた評価点が最良の工程処理パターンを構成する各工程のロットの処理順序に基づいて、各装置を制御し、各装置にロットを供給する第2の計算装置を備えることとした。   Also, in a production line that takes the form of a job shop that processes multiple processes and multiple lots, the status data of each lot and the status data of each device in the process are acquired, and combinations of lot processing orders that each process can take The process order of lots in each process is combined to form all process process patterns for all processes, and process processing is performed from the evaluation data obtained based on the status data of each lot and the status data of each device. A first computing device that selects a process processing pattern with the best evaluation point from among the patterns, and a lot processing for each process that makes up the best process processing pattern with the evaluation point obtained from the first computing device Based on the order, each apparatus is controlled, and a second calculation apparatus that supplies a lot to each apparatus is provided.

このように構成することで、第1の計算装置で、ロットの状態と装置の状態との両方のデータから、各種評価指標に基づく総合的な評価を示す評価点が最も良い、全工程の工程処理パターンを抽出して、第2の計算装置は、この結果を取得して、これに基づいて、各装置の制御、ロットの供給を行うので、機器等の情報取得およびスケジュール計算と生産制御を分担して行って、計算機の付加が分散できると共に、機能別に分かれているのでトラブル対応やメンテナンス対応が容易にしつつ、総合的に生産ラインの効率を上げることが可能となる。   By comprising in this way, the 1st calculation apparatus WHEREIN: From the data of both the state of a lot, and the state of an apparatus, the evaluation point which shows the comprehensive evaluation based on various evaluation indexes is the best process of all processes The processing pattern is extracted, and the second calculation device acquires this result, and based on this, performs control of each device and supply of lots, so information acquisition of equipment and the like, schedule calculation and production control are performed. By sharing, the addition of computers can be dispersed, and since it is divided by function, it is possible to improve the efficiency of the production line comprehensively while facilitating troubleshooting and maintenance.

また、例えば、評価点は、ロット処理のリードタイム評価指標と、装置の稼働率評価指標と、装置の効率評価指標と、ロットの納期遅延率評価指標とに基づいて算出することとした。   Further, for example, the evaluation score is calculated based on a lot processing lead time evaluation index, an apparatus operation rate evaluation index, an apparatus efficiency evaluation index, and a lot delivery date delay rate evaluation index.

このように構成されることで、評価点が、リードタイム評価指標と、装置の稼働率評価指標と、装置の効率評価指標と、納期遅延率評価指標といった生産ライン効率のための主要な評価指標に基づいて算出されるため、得られる評価点は、これら全ての評価指標が常に反映されたものになる。そして、この評価点の中から評価点が最も良い全工程の工程処理パターンを抽出するので、これに基づいて生産ラインの各装置にロットの処理順序を指示して、生産制御することにより、総合的に生産ラインの効率を上げることが可能となる。   By being configured in this way, the evaluation points are the main evaluation indexes for production line efficiency, such as lead time evaluation index, equipment operation rate evaluation index, equipment efficiency evaluation index, and delivery delay rate evaluation index. Therefore, the obtained evaluation points always reflect all these evaluation indexes. And since the process processing pattern of all the processes with the best evaluation score is extracted from these evaluation scores, the processing order of lots is instructed to each device of the production line based on this, and the production control is performed. It is possible to improve the efficiency of the production line.

また、評価点は、該評価点を構成する各評価指標に、夫々に重み付け係数を乗じたものに基づいて算出することとした。   In addition, the evaluation score is calculated based on each evaluation index constituting the evaluation score multiplied by a weighting coefficient.

このように構成することで、リードタイム評価指標、装置の稼働率評価指標、装置の効率評価指標、ロットの納期遅延率評価指標評価指標の各評価指標の重み付けを必要に応じて調整することができるので、各生産ラインにおいて重要度の高い評価指標に重点を置いて、生産ラインの各装置にロットの処理順序を指示して、夫々の生産ライン合わせて、総合的に効率を上げることができる。   By configuring in this way, the weight of each evaluation index of the lead time evaluation index, the device operation rate evaluation index, the device efficiency evaluation index, and the lot delivery date delay rate evaluation index evaluation index can be adjusted as necessary. As a result, it is possible to increase the overall efficiency of each production line by instructing the processing order of lots to each device on the production line with emphasis on highly important evaluation indexes in each production line. .

また、前記評価点の重み付け係数は、可変であることとした。   In addition, the weighting coefficient of the evaluation score is variable.

このように構成することで、リードタイム評価指標・装置の稼働率評価指標・装置の効率評価指標・納期遅延率評価指標といった主要な評価指標を生産状況、その時点での評価指標の重要度に応じて、その重み付けを柔軟に調整して生産ライン効率の総合評価を行い、これに基づき、ロット処理順序を作成するので、重要な評価指標に注目しつつ、総合的に適正化した生産制御をおこなうことができる。   By configuring in this way, the main evaluation indicators such as lead time evaluation index, equipment utilization rate evaluation index, equipment efficiency evaluation index, and delivery delay rate evaluation index are changed to the production status and the importance of the evaluation index at that time. Accordingly, the weighting is flexibly adjusted to comprehensively evaluate the production line efficiency, and based on this, the lot processing order is created. Therefore, comprehensively optimized production control is performed while paying attention to important evaluation indexes. Can be done.

以下、本発明の実施形態を図1〜図13に基づいて、説明する。最初に、本発明の実施形態に係る、生産制御システムの全体構成を示すブロック図について、図1を基に説明する。生産制御システムは第1の計算装置である生産管理コンピュータ1、第2の計算装置である装置制御コンピュータ2、搬送設備3、記録装置4、ロットを処理する工程である生産設備S1〜生産設備SNからなる。   Hereinafter, an embodiment of the present invention will be described with reference to FIGS. First, a block diagram showing an overall configuration of a production control system according to an embodiment of the present invention will be described with reference to FIG. The production control system includes a production management computer 1 that is a first computing device, a device control computer 2 that is a second computing device, a transport facility 3, a recording device 4, and production facilities S1 to SN that are processes for processing a lot. Consists of.

第1の計算装置としての生産管理コンピュータ1は、生産ラインの生産設備S1〜生産設備SN(以下、生産設備(S1〜SN))の各装置を管理するコンピュータであり、各生産設備(S1〜SN)の稼動状態や処理能力などをあらわす装置の状態データを取得し、記録装置4に記録・保存する。また、生産管理コンピュータ1は、処理予定または処理中の各ロットの処理状態や納期などをあらわすロットの状態データも取得し、記録装置4に記録・保存する。   The production management computer 1 as a first computing device is a computer that manages each device of production equipment S1 to production equipment SN (hereinafter referred to as production equipment (S1 to SN)) of a production line, and each production equipment (S1 to S1). (SN) status data of the device representing the operating status, processing capability, etc. is acquired, and recorded in the recording device 4 and stored. The production management computer 1 also acquires lot status data indicating the processing status or delivery date of each lot scheduled for processing or being processed, and records / stores it in the recording device 4.

そして生産管理コンピュータ1は、装置の状態データとロットの状態データを基に、各装置のロット処理順序を作成し、第2の計算装置としての装置制御コンピュータ2に送信する。装置制御コンピュータ2は、この処理順序に基づいて、各生産設備(S1〜SN)の装置が各ロットの処理を行うように制御する。また、装置制御コンピュータ2は、この処理順序に基づいて、各ロットを搬送設備3により、各生産設備(S1〜SN)に搬送させるように制御する。このようにして、各ロットは夫々対応する機種(製品)に応じて複数の工程で順番に処理され、完成品に至る。   Then, the production management computer 1 creates a lot processing order for each device based on the device status data and the lot status data, and transmits the lot processing order to the device control computer 2 as a second computing device. Based on this processing order, the apparatus control computer 2 controls the apparatus of each production facility (S1 to SN) to process each lot. Moreover, the apparatus control computer 2 controls each lot to be conveyed to each production facility (S1 to SN) by the conveyance facility 3 based on this processing order. In this way, each lot is sequentially processed in a plurality of steps in accordance with the corresponding model (product) to reach a finished product.

次に、各装置のロット処理順序および工程処理パターン作成の流れについて図2〜図5に基いて説明する。図2は、各工程のロット処理順序作成〜最良の工程処理パターンの決定までの流れを示す作成フロー図である。図3は、工程の流れを示す工程処理フロー図である。図4は、工程1におけるロット処理順序の組合せを示す図である。図5は各工程処理パターンの生産ラインの総合効率を示す評価点としての総合評価点を表す図である。   Next, the flow of lot processing sequence and process processing pattern creation of each apparatus will be described with reference to FIGS. FIG. 2 is a creation flowchart showing a flow from creation of a lot processing order of each process to determination of the best process processing pattern. FIG. 3 is a process flow chart showing a process flow. FIG. 4 is a diagram showing a combination of lot processing orders in step 1. FIG. 5 is a diagram showing total evaluation points as evaluation points indicating the total efficiency of the production line of each process processing pattern.

各装置のロット処理順序および工程処理パターン作成の流れは、以下のようである。まず、はじめに《手順1》として、工程処理パターンの候補を作成する。   The flow of lot processing order and process processing pattern creation for each device is as follows. First, a candidate for a process pattern is created as << Procedure 1 >>.

《手順1−1》各工程のロットの処理順序組み合わせ作成
各工程のロット処理順序の組み合わせ作成は、最初の工程である工程1を処理する生産設備から作成する。生産管理コンピュータ1は、記録装置4に記録されている工程1を処理する生産設備の処理待ちロットの処理順序の全ての組み合わせを計算し、生産管理コンピュータ1内のメモリに保持する。
<< Procedure 1-1 >> Lot Processing Order Combination Creation for Each Process A lot processing order combination creation for each process is created from a production facility that processes process 1 as the first process. The production management computer 1 calculates all combinations of the processing order of the processing waiting lots of the production facility that processes the process 1 recorded in the recording device 4 and holds them in the memory in the production management computer 1.

《手順1−2》各ロット処理順序の組合せについての処理開始時刻と処理終了時刻の見込算出
《手順1−1》で計算した工程1のロット処理順序の組み合わせ毎に、各ロットについて、処理順序に基づく工程1の処理時間を計算し、各ロットにおける見込処理開始時刻と見込処理完了時刻を得ることができる。これに次工程までの搬送時間を加えることにより、次工程(図3における工程2−1および工程2−2)夫々へのロット到着時刻を算出する。
<< Procedure 1-2 >> Expected calculation of process start time and process end time for each lot processing order combination For each lot processing order combination calculated in <Procedure 1-1 >>, the processing order for each lot The processing time of step 1 based on the above can be calculated, and the expected process start time and expected process completion time in each lot can be obtained. By adding the transport time to the next process to this, the lot arrival time at each of the next processes (process 2-1 and process 2-2 in FIG. 3) is calculated.

続いて、工程2−1と2−2のそれぞれについて、《手順1−1》と同様に、全てのロットについて、ロット処理順序の組み合わせを作成する。そして、《手順1−2》の流れに従い、工程2−1と2−2の夫々について各次工程への到着時刻を算出する。以降、最終工程までこの作業を繰り返すことにより、全ての工程におけるロット処理順序組み合わせを計算し、各ロットの各工程における見込処理開始時刻、見込処理完了時刻、ロット到着時間を算出できる。   Subsequently, for each of the steps 2-1 and 2-2, a combination of lot processing orders is created for all lots in the same manner as in <Procedure 1-1>. Then, according to the flow of << Procedure 1-2 >>, the arrival time at each next process is calculated for each of the processes 2-1 and 2-2. Thereafter, by repeating this operation until the final process, it is possible to calculate the combination of lot processing orders in all processes and calculate the expected process start time, expected process completion time, and lot arrival time in each process of each lot.

《手順1−3》工程処理パターンの組み合わせ作成と工程処理フローとの整合性がない工程処理パターンの削除   << Procedure 1-3 >> Deletion of Process Process Patterns with Inconsistency between Process Process Pattern Combination Creation and Process Process Flow

次に、上で計算した各工程のロット処理順序を、工程別に組み合わせて、全工程における工程処理パターンの組み合わせを全て作成する。そして、生産管理コンピュータ1は、記録装置4より工程処理フローを取り出し、上で作成した全ての工程処理パターンと比較して、時間的に矛盾が生じているものや、工程処理フローに記述されている処理順序と一致しない無効な工程処理パターンを除外する。   Next, the lot processing order of each process calculated above is combined for each process to create all combinations of process processing patterns in all processes. Then, the production management computer 1 takes out the process processing flow from the recording device 4 and is compared with all the process processing patterns created above, and there is a temporal contradiction or is described in the process processing flow. An invalid process pattern that does not match the existing process order is excluded.

《手順2》工程処理パターンの総合評価点の算出   << Procedure 2 >> Calculation of overall evaluation points for process pattern

《手順1》で作成された、夫々の有効な工程処理パターンにおいて、上記の結果、およびロットの状態データ、装置の状態データ等から、この工程処理パターンを構成するロット毎のリードタイム評価指標としてのリードタイム評価点・納期遅延率評価指標としての納期遅延評価点、またこの工程処理パターンを構成する装置毎の稼働率評価指標としての装置非稼働時間・効率評価指標としての装置効率を算出し、これを基にして、所定の演算をおこない、総合評価点を算出する   As the lead time evaluation index for each lot constituting this process processing pattern, from the above result, lot state data, apparatus state data, etc. in each effective process processing pattern created in << Procedure 1 >> The lead time evaluation point / delivery time delay rate evaluation index, and the equipment efficiency as the equipment non-working time / efficiency evaluation index as the operation rate evaluation index for each device that constitutes this process processing pattern are calculated. Based on this, a predetermined calculation is performed to calculate a comprehensive evaluation score.

《手順2−1》リードタイム評価点の算出   << Procedure 2-1 >> Calculation of Lead Time Evaluation Score

全ロットに対して、先頭工程の処理開始実績時刻と最終工程の完了予定時刻の差であるリードタイム求める。そして、各工程の処理時間である処理開始時刻と処理完了時刻の差を全工程の総和を求め、これを各ロットのリードタイム評価点とする。   The lead time, which is the difference between the actual process start time of the first process and the scheduled completion time of the final process, is obtained for all lots. Then, the difference between the processing start time and the processing completion time, which is the processing time of each process, is obtained as the sum of all processes, and this is used as the lead time evaluation point for each lot.

式1.リードタイム評価点算出式

Figure 2007164580
《手順2−2》納期遅延率評価点の算出 Formula 1. Lead time evaluation point calculation formula
Figure 2007164580
<< Procedure 2-2 >> Calculation of delay rate evaluation point for delivery

各ロットに定められている納期と出荷予定日との差を求め、出荷ロットの中の納期までに出荷できないと見込まれるロット数の比率を納期遅延評価点とする。   The difference between the delivery date set for each lot and the scheduled delivery date is obtained, and the ratio of the number of lots expected to be shipped by the delivery date in the shipment lot is set as the delivery delay evaluation point.

式2.納期遅延率評価点算出式   Formula 2. Delivery delay rate evaluation point calculation formula

Figure 2007164580
《手順2−3》装置非稼働時間の算出
各装置におけるロット処理見込時間(処理開始見込時刻−処理完了見込時刻)の総和を求め(稼働見込時間)、それを生産ライン稼働時間から減じて、装置非稼働時間を算出する。
Figure 2007164580
<< Procedure 2-3 >> Calculation of equipment non-operation time Obtain the total of lot processing expected time (processing start expected time-processing completion expected time) in each device (operation expected time) and subtract it from the production line operating time. The device non-operation time is calculated.

式3.装置非稼動時間算出式

Figure 2007164580
《手順2−4》装置効率の算出 Formula 3. Equipment non-operation time calculation formula
Figure 2007164580
<< Procedure 2-4 >> Calculation of apparatus efficiency

各装置における見込稼働時間と見込処理ロット数を求め、見込処理ロット数で見込稼働時間を割ったものを装置効率とする。即ち、この値が低いほど単位時間当たりの処理量が多いこととなり処理効率が高いといえる。   The expected operating time and the number of expected processing lots in each device are obtained, and the device efficiency is obtained by dividing the expected operating time by the number of expected processing lots. In other words, it can be said that the lower the value, the higher the processing amount per unit time and the higher the processing efficiency.

式4.装置効率算出式

Figure 2007164580
Formula 4. Equipment efficiency calculation formula
Figure 2007164580

そして、《手順2−1》〜《手順2−4》で算出した4つの評価点(指標)から夫々の工程処理パターンに基づいて、この工程処理パターンの全ロットのリードタイム評価点の合算、全ロットの納期評価点の合算、全装置の装置稼働率の合算、全装置の装置効率を計算し、夫々に重み付け係数としての重み付けパラメータを乗じたうえで、全て合算して、1つの工程処理パターンの総合評価点を算出する。   Then, based on the respective process processing patterns from the four evaluation points (indexes) calculated in << Procedure 2-1 >> to << Procedure 2-4 >>, the sum of the lead time evaluation points of all lots of this process processing pattern, Total process date for all lots, total operation rate of all devices, and device efficiency of all devices are calculated and multiplied by weighting parameters as weighting factors. The overall evaluation score of the pattern is calculated.

式5.総合評価点算出式

Figure 2007164580
但し、α・β・δ・εは重み付けパラメータとする。
《手順3》総合評価点が最良となる工程処理パターンの決定 Formula 5. Comprehensive score calculation formula
Figure 2007164580
However, α, β, δ, and ε are weighting parameters.
<< Procedure 3 >> Determination of process treatment pattern with the best overall evaluation score

《手順1》〜《手順2》で算出した全ての有効な工程処理パターンの総合評価点を比較し、総合評価点が最小となる点数を最良として、これを満たす工程処理パターンを抽出し、採用する。   Comparing the overall evaluation points of all effective process processing patterns calculated in << Procedure 1 >> to << Procedure 2 >>, extracting the process processing pattern that satisfies this as the best score that minimizes the overall evaluation score, and adopting it To do.

以上が、本発明における最適な工程処理パターンの計算の流れである。このようにして抽出した全工程の工程処理パターンは、生産ラインの主要な評価指標であるリードタイム、装置の稼働率、装置の効率、納期遅延に関する評価指標に基づく総合評価点により評価され、このうち最も総合評価点が良いものであるので、主要な評価指標が常に反映され、全ての評価指標について、総合的に優れたものになる。   The above is the flow of calculation of the optimum process processing pattern in the present invention. The process processing patterns of all the processes extracted in this way are evaluated by comprehensive evaluation points based on the evaluation indices related to lead time, equipment availability, equipment efficiency, and delivery delay, which are the main evaluation indices of the production line. Among them, since the overall evaluation score is the best, the main evaluation index is always reflected, and all the evaluation indexes are comprehensively excellent.

そして、この工程処理パターンに基づいて、生産ラインの各装置にロットの処理順序を指示することによって、スケジューリング時点で得られている各種条件を考慮して、総合的に効率の高い生産ラインの制御をおこなうことが可能となる。   Based on this process processing pattern, by instructing each device on the production line about the lot processing order, it is possible to control the production line with high efficiency in consideration of various conditions obtained at the time of scheduling. Can be performed.

また、このように構成することで、生産管理コンピュータ1で、ロットの状態と装置の状態との両方のデータから、各種評価指標に基づく総合的な評価を示す評価点が最も良い、全工程の工程処理パターンを計算・抽出して、装置制御コンピュータ2は、この結果を取得して、これに基づき各装置の制御、ロットの供給を行って、機器等の情報取得およびスケジュール計算と生産制御を分担して行うので、計算機の付加が分散できると共に、機能別に分かれているのでトラブル対応やメンテナンス対応が容易にしつつ、総合的に生産ラインの効率を上げることが可能となる。   Further, with this configuration, the production management computer 1 has the best evaluation score indicating the comprehensive evaluation based on various evaluation indexes from the data of both the lot state and the device state. The process control pattern 2 is calculated / extracted, and the apparatus control computer 2 acquires this result, controls each apparatus and supplies a lot based on this result, and acquires information on equipment, etc., schedule calculation and production control. Since it is shared, the addition of computers can be distributed, and since it is divided by function, it is possible to improve the efficiency of the production line comprehensively while facilitating troubleshooting and maintenance.

また、総合評価点を算出する式5において、右辺の各項にα・β・δ・εの重み付けパラメータを乗じているが、これは例えば、納期遵守に重きを置く場合はβを他のパラメータよりも小さくするという具合で調整することができ、このような重み付けパラメータを持つことにより、リードタイム評価点・装置非稼働時間・装置効率・納期遅延率評価点といった主要な評価指標を生産状況、その時点での評価指標の重要度に応じて、その重み付けを柔軟に調整して生産ライン効率の総合評価を行い、これに基づいて総合的に適正化した生産制御をおこなうことができる。   Also, in Equation 5 for calculating the overall evaluation score, each term on the right side is multiplied by a weighting parameter of α, β, δ, and ε. For example, when emphasizing on delivery date, β is replaced with other parameters. By having such a weighting parameter, the main evaluation indicators such as lead time evaluation point, equipment non-operation time, equipment efficiency, and delivery time delay rate evaluation point can be adjusted. In accordance with the importance of the evaluation index at that time, the weighting is flexibly adjusted to comprehensively evaluate the production line efficiency, and based on this, the production control can be comprehensively optimized.

なお、本実施形態では生産管理コンピュータ1および装置制御コンピュータ2を用いて、各種データ処理を行ったが、これらのデータ処理は、一括、あるいは分散して、任意のコンピュータで処理することができる。   In the present embodiment, various types of data processing are performed using the production management computer 1 and the apparatus control computer 2, but these data processing can be performed by any computer in a batch or distributed manner.

次に、これまでに説明した実施形態について、さらに具体的な例を示して、図6〜図13を用いて説明する。   Next, the embodiment described so far will be described with reference to FIGS. 6 to 13 by showing more specific examples.

ここでは、具体例として、図6に示すような3工程・5装置の工場において、機種(製品)AのLOT01、LOT03と機種(製品)BのLOT02の工程処理パターンの決定の流れを示す。   Here, as a specific example, a flow of determining process process patterns of LOT01 and LOT03 of the model (product) A and LOT02 of the model (product) B in the factory of the three processes and five apparatuses as shown in FIG.

機種A、機種Bは工程1の処理装置は共通であり、工程2、3については別の装置を用いて加工するものとする。また、装置2はバッチ編成装置であり、最大2ロットを同時に処理することが可能である。それ以外の装置は1ロットずつ処理する装置である。工程1、2、3の処理時間は夫々60分、120分,60分である。説明のため現時刻を0:00とする。LOT03は時刻0:00の時点で、既に工程1の処理を完了しており、工程2に仕掛かっているものとする。また各ロットには図7に示すような納期が設定されている。   The model A and the model B have the same processing apparatus for the process 1, and the processes 2 and 3 are processed using different apparatuses. The apparatus 2 is a batch knitting apparatus and can process a maximum of 2 lots simultaneously. Other devices are devices that process one lot at a time. The processing times of steps 1, 2, and 3 are 60 minutes, 120 minutes, and 60 minutes, respectively. For the sake of explanation, the current time is assumed to be 0:00. It is assumed that LOT03 has already completed the process of step 1 at the time of 0:00 and is already in process 2. In addition, a delivery date as shown in FIG. 7 is set for each lot.

上記の状況のもとで、全ての工程処理パターンの組み合わせは、工程1ではLOT01、LOT02のロット処理順序の組み合わせがあり、工程2−1にはLOT01、LOT02、LOT03において、2ロット同時に処理するロット処理順序の組み合わせと別々に処理するロット処理順序の組み合わせがあり、さらに工程2−2と工程3−1と工程3−2では夫々LOT01、LOT02、LOT03のロット処理順序の組み合わせがある。   Under the above circumstances, all process processing pattern combinations include a combination of lot processing orders of LOT01 and LOT02 in process 1, and two lots are processed simultaneously in LOT01, LOT02 and LOT03 in process 2-1. There are a combination of lot processing orders and a combination of lot processing orders to be processed separately. Further, there are combinations of lot processing orders of LOT01, LOT02, and LOT03 in step 2-2, step 3-1 and step 3-2, respectively.

これらの各工程におけるロットの処理順序の組み合わせから、機種Aの工程処理フロー(工程1→工程2−1→工程3−1)に合わせて当てはめ、機種Aにおける、全ての工程処理パターンを作成する。機種Bについても機種Aと同様に全ての工程処理パターンを作成する。そして、工程処理フロー(図6)と作成された機種A、Bについての全ての工程処理パターンを照合し、工程処理フローの処理順序と異なるものや、フローに存在しないもの(例えば、工程2−2でLOT01を処理するものが含まれている工程処理パターン)を除外する。   From the combination of the processing order of lots in each of these processes, it is applied according to the process processing flow of model A (process 1 → process 2-1 → process 3-1), and all process processing patterns for model A are created. . For the model B as well, as with the model A, all process processing patterns are created. Then, the process process flow (FIG. 6) and all process process patterns for the created models A and B are collated, and the process process flow has a different processing order or does not exist in the flow (for example, process 2- 2), a process pattern including a process for processing LOT01 is excluded.

このようにして、工程処理フローに適合する、有効な工程処理パターンが抽出され、これら夫々の工程処理パターンについて、式1〜式5を用いて総合評価点を算出する。   In this manner, effective process processing patterns that match the process processing flow are extracted, and a comprehensive evaluation score is calculated for each of these process processing patterns using Equations 1 to 5.

ここでは、簡単のため、搬送時間を省き、有効な工程処理パターンのうち、図8に示す4パターンを取り上げて、詳しく説明する。なお、パターン1、2は工程2−1を単独で流す場合であり、パターン3、4は工程2−1を2ロットバッチで流す場合である。   Here, for the sake of simplicity, the conveyance time is omitted, and four patterns shown in FIG. Patterns 1 and 2 are for the case where the process 2-1 is made to flow alone, and patterns 3 and 4 are cases where the process 2-1 is made to flow in two batches.

各パターンの処理開始見込時刻と完了見込時刻を図8に示す。この4パターンについて、式1〜式4を用いてリードタイム評価点・納期遅延評価点・装置非稼働時間・装置効率を算出した結果が夫々図9〜図12である。そして式5に基づき、各4パターンの総合評価点を合計したものが図13である。(ここでは、重み付けパラメータα・β・δ・εは全て1としている。)   FIG. 8 shows the expected processing start time and the expected completion time for each pattern. For these four patterns, the results of calculating the lead time evaluation point, the delivery delay evaluation point, the device non-operation time, and the device efficiency using Equations 1 to 4 are shown in FIGS. And based on Formula 5, what totaled the comprehensive evaluation score of each 4 patterns is FIG. (Here, the weighting parameters α, β, δ, and ε are all set to 1.)

こうして得られた4パターンの総合評価点のうち、その値が最小値をとるパターン2を総合的に生産効率が最良となる工程処理パターンとして抽出し、この工程処理パターンを構成する各工程のロット処理順序として採用する。   Of the four overall evaluation points obtained in this way, the pattern 2 having the minimum value is extracted as the process processing pattern that provides the best overall production efficiency, and the lots of each process constituting the process processing pattern. Adopt as processing order.

こうしたケースでは、従来技術では、工程1のLOT01とLOT02のどちらから着手するかを決定する際に、納期が迫っているLOT01を選択してしまうことが多い。その場合は、パターン1、3、4のケースとなり、リードタイム評価点の合計は3.25もしくは3.50となる。   In such a case, in the prior art, when deciding whether to start from LOT01 or LOT02 in step 1, LOT01 whose delivery date is approaching is often selected. In that case, the cases of patterns 1, 3, and 4 are obtained, and the total lead time evaluation score is 3.25 or 3.50.

または、装置2のバッチロット数を上げることを重視するあまり、パターン3、4を採用するとリードタイム評価点の合計は3.50となる。   Or, since emphasis is placed on increasing the number of batch lots of the apparatus 2, if the patterns 3 and 4 are employed, the total lead time evaluation score is 3.50.

ところが本発明に係る生産制御システムによると、重み付けパラメータを全て1とした場合、各パターンのリードタイム評価点は図9に示すとおりになり、パターン2のリードタイム評価点が3.00で、最も良く、図13の総合評価点においてもパターン2が最良ということが分る。   However, according to the production control system of the present invention, when all the weighting parameters are 1, the lead time evaluation points of each pattern are as shown in FIG. 9, and the lead time evaluation point of pattern 2 is 3.00, which is the most. It can be seen that the pattern 2 is the best in the overall evaluation point of FIG.

つまり、従来手法では選択されなかったパターン2のような納期には余裕のあるLOT02の処理を先に着手するようなパターンであっても、総合的な生産効率も高く、かつリードタイム評価点も高い結果となり、総合生産効率を重視しながら、リードタイムの短縮を重視する場合は、パターン2を採用することが最も適切であることがわかり、この生産制御システムの有効性が明らかである。   In other words, even with a pattern such as Pattern 2, which was not selected by the conventional method, a pattern in which LOT02 processing with sufficient time for delivery is started first, the overall production efficiency is high, and the lead time evaluation score is also high. The results are high, and when emphasizing the overall production efficiency and emphasizing the shortening of the lead time, it can be seen that the pattern 2 is most suitable, and the effectiveness of this production control system is clear.

以上、本発明の実施形態につき説明したが、本発明の範囲はこれに限定されるものではなく、発明の主旨を逸脱しない範囲で種々の変更を加えて実施することができる。   Although the embodiments of the present invention have been described above, the scope of the present invention is not limited to these embodiments, and various modifications can be made without departing from the spirit of the invention.

本発明の生産制御システム構成図Production control system configuration diagram of the present invention 各工程のロット処理順序作成の流れを示す作成フロー図Creation flow diagram showing the flow of creating lot processing sequence for each process 工程の流れを示す工程処理フロー図Process processing flow diagram showing process flow 工程1におけるロット処理順序の組合せを示す図The figure which shows the combination of the lot processing order in process 1 各工程処理パターンの評価点(総合評価点)を表す図The figure showing the evaluation point (total evaluation point) of each process processing pattern 本発明に基く具体的構成の1例(実施形態)Example of specific configuration based on the present invention (embodiment) 実施形態におけるロット別の納期を示す表Table showing delivery date by lot in the embodiment 実施形態におけるロットと工程処理パターンの関係を示す表Table showing the relationship between lots and process patterns in the embodiment 実施形態におけるリードタイム評価点を示す表Table showing lead time evaluation points in the embodiment 実施形態における納期遅延評価点を示す表Table showing delivery point delay evaluation points in the embodiment 実施形態における装置非稼働時間を示す表Table showing apparatus non-operation time in the embodiment 実施形態における装置効率を示す表Table showing apparatus efficiency in the embodiment 実施形態における総合評価点を示す表Table showing overall evaluation points in the embodiment 従来のバッチ編成工程Conventional batch knitting process

符号の説明Explanation of symbols

1 生産管理コンピュータ
2 装置制御コンピュータ
3 搬送設備
4 記録装置
S1〜SN 生産設備
DESCRIPTION OF SYMBOLS 1 Production management computer 2 Apparatus control computer 3 Conveying equipment 4 Recording apparatus S1-SN Production equipment

Claims (5)

複数の工程及び複数のロットを処理するジョブショップ形態を取る生産ラインにおいて、前記各ロットの状態データと、前記工程の各装置の状態データを取得し、
前記各工程が取り得る前記ロットの処理順序の組み合わせを作成して、前記各工程の前記ロットの処理順序を組み合わせて、全工程の工程処理パターンを全て構成し、
前記各ロットの状態データと、前記各装置の状態データを基に得られる評価点より、前記工程処理パターンの中から、前記評価点が最良となる前記工程処理パターンを選定し、前記評価点が最良である前記工程処理パターンを構成する前記各工程の前記ロットの処理順序で前記各装置を制御することを特徴とする生産制御システム。
In a production line that takes the form of a job shop that processes a plurality of processes and a plurality of lots, obtain the status data of each lot and the status data of each device of the process,
Create a combination of the processing order of the lot that each process can take, combine the processing order of the lot of each process, configure all the process processing pattern of all processes,
Based on the status data of each lot and the evaluation points obtained based on the status data of each device, the process processing pattern with the best evaluation score is selected from the process processing patterns, and the evaluation score is A production control system for controlling the respective devices in the processing order of the lots of the respective steps constituting the best process processing pattern.
複数の工程及び複数のロットを処理するジョブショップ形態を取る生産ラインにおいて、前記各ロットの状態データと、前記工程の各装置の状態データを取得し、
前記各工程が取り得る前記ロットの処理順序の組み合わせを作成して、前記各工程の前記ロットの処理順序を組み合わせて、全工程の工程処理パターンを全て構成し、
前記各ロットの状態データと、前記各装置の状態データを基に得られる評価点から、前記工程処理パターンの中から、前記評価点が最良となる前記工程処理パターンを選定する第1の計算装置と、
前記第1の計算装置から得られた前記評価点が最良の前記工程処理パターンを構成する前記各工程の前記ロットの処理順序に基づいて、前記各装置を制御し、前記各装置に前記ロットを供給する第2の計算装置を備えることを特徴とする生産制御システム。
In a production line that takes the form of a job shop that processes a plurality of processes and a plurality of lots, obtain the status data of each lot and the status data of each device of the process,
Create a combination of the processing order of the lot that each process can take, combine the processing order of the lot of each process, configure all the process processing pattern of all processes,
A first calculation device that selects the process processing pattern with the best evaluation point from the process processing patterns based on the state data of each lot and the evaluation points obtained based on the state data of each device. When,
Based on the processing order of the lots of the respective steps that constitute the process processing pattern having the best evaluation score obtained from the first calculation device, the respective devices are controlled, and the lots are assigned to the respective devices. A production control system comprising a second computing device for supply.
前記ロット処理のリードタイム評価指標と、前記装置の稼働率評価指標と、前記装置の効率評価指標と、前記ロットの納期遅延率評価指標とに基づいて、前記評価点を算出することを特徴とする請求項1または請求項2に記載の生産制御システム。   The evaluation score is calculated based on the lot processing lead time evaluation index, the operation rate evaluation index of the device, the efficiency evaluation index of the device, and the delivery date delay rate evaluation index of the lot, The production control system according to claim 1 or 2. 前記評価点を構成する各評価指標に夫々に重み付け係数を乗じたものに基づいて、前記評価点を算出することを特徴とする請求項4に記載の生産制御システム。   The production control system according to claim 4, wherein the evaluation score is calculated based on a value obtained by multiplying each evaluation index constituting the evaluation score by a weighting coefficient. 前記重み付け係数は、可変であることを特徴とする請求項4に記載の生産制御システム。   The production control system according to claim 4, wherein the weighting coefficient is variable.
JP2005361760A 2005-12-15 2005-12-15 Production control system Pending JP2007164580A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005361760A JP2007164580A (en) 2005-12-15 2005-12-15 Production control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005361760A JP2007164580A (en) 2005-12-15 2005-12-15 Production control system

Publications (1)

Publication Number Publication Date
JP2007164580A true JP2007164580A (en) 2007-06-28

Family

ID=38247385

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005361760A Pending JP2007164580A (en) 2005-12-15 2005-12-15 Production control system

Country Status (1)

Country Link
JP (1) JP2007164580A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7398132B2 (en) * 2006-01-06 2008-07-08 Gm Global Technology Operations, Inc. Method and system for analyzing throughput
JP2018063653A (en) * 2016-10-14 2018-04-19 ファナック株式会社 Information processor
JP7432448B2 (en) 2020-06-17 2024-02-16 株式会社日立製作所 Operation loss analysis system and operation loss analysis method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7398132B2 (en) * 2006-01-06 2008-07-08 Gm Global Technology Operations, Inc. Method and system for analyzing throughput
JP2018063653A (en) * 2016-10-14 2018-04-19 ファナック株式会社 Information processor
JP7432448B2 (en) 2020-06-17 2024-02-16 株式会社日立製作所 Operation loss analysis system and operation loss analysis method

Similar Documents

Publication Publication Date Title
Rahman et al. Real-time order acceptance and scheduling problems in a flow shop environment using hybrid GA-PSO algorithm
JPH10261122A (en) Work distribution optimization method
Ajorlou et al. Artificial bee colony algorithm for CONWIP production control system in a multi-product multi-machine manufacturing environment
CN111356988B (en) Method and system for scheduling semiconductor processing
Mirabedini et al. A scheduling model for serial jobs on parallel machines with different preventive maintenance (PM)
Godinho Filho et al. Assessing the impact of alternative continuous improvement programmes in a flow shop using system dynamics
US9575487B2 (en) Computer program, method, and system for optimized kit nesting
Wong et al. Decision-making on multi-mould maintenance in production scheduling
JP2010097506A (en) Schedule preparation system, schedule preparation method and schedule preparation program
JP2007164580A (en) Production control system
Zhang et al. Time‐selective integrated scheduling algorithm with backtracking adaptation strategy
CN110909917A (en) Data mining and process model based optimization scheduling method, system, medium and equipment
Weng et al. Realtime scheduling heuristics for just-in-time production in large-scale flexible job shops
JPWO2019064790A1 (en) Recommended order quantity determination device, recommended order quantity determination method and recommended order quantity determination program
Pfund et al. Extending the boundaries between scheduling and dispatching: hedging and rescheduling techniques
US11372396B2 (en) Control product flow of semiconductor manufacture process under time constraints
Talibi et al. The relevance study of adaptive kanban in a multicriteria constraints context using data-driven simulation method
Singh et al. Multicriteria dynamic scheduling by swapping of dispatching rules
Chen Scheduling of jobs and maintenance in a textile company
Kogan et al. Multi-period aggregate production planning in a news-vendor framework
JP5359311B2 (en) Workpiece manufacturing time prediction method, manufacturing date prediction method, arrival time prediction method, arrival date prediction method, workpiece manufacturing time prediction device, and arrival time prediction device
Ebrahimi et al. Determining the optimal performance of flexible manufacturing systems using network analysis and simulation process
WO2023176416A1 (en) Information processing method and information processing device
WO2006077930A1 (en) Production scheduling system
JP2003263213A (en) Production management system and production management method

Legal Events

Date Code Title Description
RD01 Notification of change of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7421

Effective date: 20071108