JP2007087259A - Road plan support program and road plan support apparatus - Google Patents

Road plan support program and road plan support apparatus Download PDF

Info

Publication number
JP2007087259A
JP2007087259A JP2005277488A JP2005277488A JP2007087259A JP 2007087259 A JP2007087259 A JP 2007087259A JP 2005277488 A JP2005277488 A JP 2005277488A JP 2005277488 A JP2005277488 A JP 2005277488A JP 2007087259 A JP2007087259 A JP 2007087259A
Authority
JP
Japan
Prior art keywords
road
brush
building
map
land
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2005277488A
Other languages
Japanese (ja)
Other versions
JP4972898B2 (en
Inventor
Hideki Uchikoshi
英樹 打越
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP2005277488A priority Critical patent/JP4972898B2/en
Publication of JP2007087259A publication Critical patent/JP2007087259A/en
Application granted granted Critical
Publication of JP4972898B2 publication Critical patent/JP4972898B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Instructional Devices (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To facilitate calculating a negotiation estimate relating to expropriation of land for a planned road. <P>SOLUTION: When the planned road as an object is designated, a road information acquisition means 1a acquires road relevant information including its road map. An object parcel retrieval means 1b puts a road map of residence display and a registry office map of lot number display one over the other to reflect a planned road figure on the registry office map and retrieves an object parcel. A parcel division means 1c divides the object parcel in accordance with the planned road figure and determines whether a building should be dismantled or not or the like and sets parcel management information to be stored in a parcel division information (a parcel management information storage means) 1f. A compensation calculating means 1d calculates the amount of compensation of a land to be expropriated, on the basis of parcel management information and adds dismantlement expenses to calculate the amount of compensation when the building should be dismantled, and sets the amount of compensation to parcel management information. A negotiation estimate output means 1e sets a difficulty level representation according to the amount of compensation onto a map showing a parcel boundary after parcel division to generate a negotiation estimate map. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は道路計画支援プログラムおよび道路計画支援装置に関し、特に道路計画に係る土地収用に関する交渉見込みの算出を支援する道路計画支援プログラムおよび道路計画支援装置に関する。   The present invention relates to a road planning support program and a road planning support device, and more particularly, to a road planning support program and a road planning support device that support calculation of negotiation prospects regarding land acquisition related to road planning.

行政が主導して進められる計画道路事業では、新たな道路の敷設や既存の道路の拡張などの道路計画が作成される計画決定段階を経て、事業が着手される事業決定段階に移る。計画道路とは、このような行政の事業対象となっている道路を言う。事業決定段階となると、計画道路に係る土地の収用交渉が開始され、登記所で管理される登記所地図や地積測量図などに基づいて計画道路に含まれる土地を分筆し、分筆された土地の対価として補償額が算出される。   In the planned road project led by the government, the project goes to the project decision stage where the project is started through the plan decision stage in which a road plan such as laying a new road or expanding an existing road is created. A planned road refers to a road that is the subject of such administrative work. At the project decision stage, negotiations for expropriation of the land on the planned road began, and the land included in the planned road was divided based on the registry map and area survey map managed by the registry office. A compensation amount is calculated as compensation.

ところで、計画道路地図は一般的な住居表示であるのに対し、登記所の登記所地図などは地番によって管理されている。このため、住居表示の計画道路地図と、地番表示の登記所地図とを重ね合わせ、登記所地図上に計画道路を反映した後、収用対象の筆の検索と分筆処理、および補償金の算出を行わなければならない。   By the way, while the planned road map is a general residence display, the registry map of the registry office is managed by lot number. For this reason, after overlaying the planned road map of the residential display and the registry map of the lot number display and reflecting the planned road on the registry map, search for the brushes to be expropriated and process the separation, and calculate the compensation money. It must be made.

住居表示の地図と地番表示の地図に関し、住居表示と地番表示の地図の座標系と単位を変換して重ね合わせて表示などをすることが可能な住居・地番表示方法が提案されている(たとえば、特許文献1参照)。   With regard to the map of house display and the map of lot number display, there has been proposed a house / lot number display method capable of displaying the map by converting the coordinate system and unit of the map of the house display and the lot number display and overlaying them (for example, , See Patent Document 1).

そこで、このような方法を用いて計画道路の地図と登記所地図とを重ね合わせ、登記所地図上に計画道路を反映した後、人手によって計画道路に含まれる対象筆を検出し、分筆処理を行って、その補償額を算出していた。
特開2002−139993号公報(段落番号〔0011〕〜〔0030〕、図1)
Therefore, using such a method, the map of the planned road and the registry map are overlaid, and after reflecting the planned road on the registry map, the target brush included in the planned road is detected manually, and the dividing process is performed. I went and calculated the compensation amount.
JP 2002-139993 A (paragraph numbers [0011] to [0030], FIG. 1)

しかしながら、計画道路に係る土地の収用費用の大部分を占める補償額は、分筆した収用地に対する補償額を単純に算出するだけでは十分ではないという問題がある。特に、対象となる土地に建物が建っている場合には、以下のような問題が生じる。   However, there is a problem that it is not sufficient to simply calculate the compensation amount for the land to be taken apart as the compensation amount that accounts for the majority of the land acquisition cost for the planned road. In particular, when a building is built on the target land, the following problems arise.

第1に、所有する土地の一部が削られた場合、収用部分を除く土地では、建物の建ぺい率(建物1階面積/土地面積)、または容積率(建物総面積/土地面積)が、基準値を下回ってしまうことがある。この場合、建物の全面解体が必要となるため、収用される土地の費用の他に建物解体費や建物新築費などがかかり、補償額も大きくなる。また、建ぺい率や容積率は、地域ごとに決められているため、解体が必要であるかどうかは、地域ごとに個別に検討しなければならない。   First, if a part of the land owned is scraped, the building coverage ratio (1st floor area / land area) or floor area ratio (total area of the building / land area) is the standard for the land excluding the expropriation part. May fall below the value. In this case, since the entire building needs to be demolished, a building demolition cost, a new building cost, etc. are in addition to the cost of the land to be expropriated, and the compensation amount also increases. In addition, since the building coverage ratio and floor area ratio are determined for each region, whether or not dismantling is necessary must be individually examined for each region.

第2に、収用対象の土地と残りの土地を分ける分筆線上に建物が存在する場合がある。この場合も、建物を全面解体する必要があり、上記と同様の費用が加算されるため、補償額を別途算出しなければならない。   Second, there may be a building on the dividing line that separates the land to be expropriated from the remaining land. In this case as well, the entire building must be dismantled, and the same costs as above are added, so the compensation amount must be calculated separately.

そして、第3に、分筆によって収用部分を除く土地が狭小地となり、資産価値が失われる場合がある。従来、残地については補償の対象外であったが、残地の資産価値が失われる場合には、所有者が何らかの補償を求め、交渉が長引くおそれがある。この問題は、土地に建物が建っていない場合にも同様に発生する。   Thirdly, the land excluding the expropriated portion is narrowed by the pen, and the asset value may be lost. Conventionally, the remaining land was not covered by compensation, but if the asset value of the remaining land is lost, the owner may seek some compensation and there is a risk that negotiations will be prolonged. This problem also occurs when there are no buildings on the land.

このように、計画道路に係る土地についての補償額を算出するだけでは、十分ではなく、他のさまざまな要素を加味して算出しなければならなかった。また、上記のようなケースでは対象者の同意を得ることが容易ではなく、交渉期間が長引く恐れもある。   Thus, it is not enough to calculate the compensation amount for the land related to the planned road, but it has to be calculated taking into account various other factors. In the above case, it is not easy to obtain the consent of the target person, and there is a possibility that the negotiation period will be prolonged.

しかしながら、上記のような地図の重ね合わせなど部分的な処理ではコンピュータを利用することはできたが、処理全体を通して支援する装置はなかった。この結果、見込みよりも補償金の額が大きくなったり、買収期間が長くなったりするという傾向にあった。   However, although a computer can be used for partial processing such as map superposition as described above, there is no device that supports the entire processing. As a result, there was a tendency for the amount of compensation to be larger than expected and the acquisition period to be longer.

このため、計画道路に係る土地収用に関する交渉見込みの算出を容易にする道路計画支援装置が要望されている。このような道路計画支援装置によって、たとえば、計画決定段階の前に、補償額の算出や、問題箇所の検討を行うことができれば、補償額を最小限とし、買収期間を短くすることが可能な計画道路の立案を支援することができる。   For this reason, there is a demand for a road planning support device that facilitates the calculation of negotiation prospects regarding land acquisition related to the planned road. With such a road planning support device, for example, if the compensation amount can be calculated and the problem area can be examined before the planning decision stage, the compensation amount can be minimized and the acquisition period can be shortened. Can support the planning of the planned road.

本発明はこのような点に鑑みてなされたものであり、計画道路に係る土地収用に関する交渉見込みの算出を容易にする道路計画支援プログラムおよび道路計画支援装置を提供することを目的とする。   The present invention has been made in view of the above points, and an object thereof is to provide a road planning support program and a road planning support device that facilitate the calculation of negotiation prospects regarding land acquisition related to a planned road.

本発明では上記課題を解決するために、図1に示すような処理をコンピュータに実行させるための道路計画支援プログラムが提供される。本発明に係る道路計画支援プログラムは、道路計画支援装置1に適用され、コンピュータを、道路情報取得手段1a、対象筆検索手段1b、分筆手段1c、補償額算出手段1dおよび交渉見込み出力手段1eとして機能させることができる。   In order to solve the above-described problems, the present invention provides a road planning support program for causing a computer to execute the process shown in FIG. The road planning support program according to the present invention is applied to the road planning support apparatus 1, and the computer is used as road information acquisition means 1a, target brush search means 1b, splitting means 1c, compensation amount calculation means 1d and negotiation prospect output means 1e. Can function.

道路情報取得手段1aは、道路関連情報(記憶手段)2aから、調査対象の計画道路に関する道路地図を含む道路関連情報を取得する。対象筆検索手段1bは、登記所が管理する登記所地図と道路地図とを重ね合わせ、道路地図上の計画道路図形を登記所地図の対応位置に反映し、計画道路図形に少なくとも一部が重なる対象筆を検索する。分筆手段1cは、対象筆を計画道路図形に応じて分筆するとともに、分筆を行った場合の建物解体の要否を判定し、筆管理情報として筆管理情報(記憶手段)1fに格納する。補償額算出手段1dは、筆管理情報に基づき、土地・建物取引価格を含む対象筆の属する地域の土地・建物関連情報を参照して、建物解体を行った場合を含む対象筆の補償額を算出する。交渉見込み出力手段1eは、分筆後の筆界線を示す地図上に補償額に応じた交渉見込みの難易度表示を重ねて、交渉見込み地図として出力する。   The road information acquisition unit 1a acquires road-related information including a road map related to the planned road to be investigated from the road-related information (storage unit) 2a. The target brush search means 1b superimposes the registration map and road map managed by the registration office, reflects the planned road graphic on the road map to the corresponding position of the registration map, and at least partly overlaps the planned road graphic. Search for the target brush. The dividing means 1c divides the target brush according to the planned road figure, determines whether or not the building must be dismantled when it is divided, and stores it in the brush management information (storage means) 1f as brush management information. Compensation amount calculation means 1d refers to the land / building related information of the region to which the target brush belongs, including the land / building transaction price, based on the brush management information, and calculates the compensation amount of the target brush including the case where the building was demolished. calculate. Negotiation prospect output means 1e superimposes the display of the difficulty level of the negotiation prospect according to the compensation amount on the map showing the stroke boundary line after the separation, and outputs it as a negotiation prospect map.

このような道路計画支援プログラムをコンピュータが実行することにより、コンピュータは、道路計画支援装置1として機能し、道路情報取得手段1aは、調査対象の計画道路が指定されると、この計画道路に関する道路地図を含む道路関連情報を、道路関連情報(記憶手段)2aから抽出する。対象筆検索手段1bは、計画道路に応じた登記所地図を登記所関連情報(記憶手段)2bから抽出し、この登記所地図と道路情報取得手段1aが抽出した道路地図とを重ね合わせ、位置の対応付けが可能な状態にする。そして、道路地図上の計画道路図形を、登記所地図の対応位置に反映して登記所地図上に計画道路図形を再現し、計画道路に少なくとも一部が重なる対象筆を検索する。分筆手段1cは、対象筆検索手段1bによって検索された対象筆を、計画道路図形に応じて分筆する。そして、分筆を行った場合に建物解体が必要になるかどうかを判定し、結果を筆管理情報に設定し、筆管理情報(記憶手段)1fに格納する。補償額算出手段1dは、筆管理情報に基づき、対象筆の周辺の土地・建物取引価格を含む対象筆の属する地域の土地・建物管理情報を参照して、対象筆の補償額を算出する。このとき、筆管理情報に基づき、建物解体が必要であれば、それに応じた額も加算して補償額を算出する。交渉見込み出力手段1eは、補償額に応じた交渉見込みの難易度を対象筆ごとに算出し、分筆が行われた後の計画道路との筆界線が示されている登記所地図上に交渉見込みの難易度表示を重ねて交渉見込み地図を作成する。   When the computer executes such a road planning support program, the computer functions as the road planning support device 1, and the road information acquisition unit 1 a specifies the road related to the planned road when the planned road to be investigated is designated. Road-related information including a map is extracted from the road-related information (storage means) 2a. The target brush search unit 1b extracts a registry map corresponding to the planned road from the registry related information (storage unit) 2b, and superimposes the registry map on the road map extracted by the road information acquisition unit 1a. It is in a state that can be associated. Then, the planned road graphic on the road map is reflected on the corresponding position of the registry map, the planned road graphic is reproduced on the registry map, and an object brush that at least partially overlaps the planned road is searched. The dividing means 1c divides the object brush searched by the object brush searching means 1b according to the planned road figure. Then, it is determined whether or not building dismantling is required when the pen is drawn, the result is set in the brush management information, and stored in the brush management information (storage means) 1f. Based on the brush management information, the compensation amount calculating means 1d refers to the land / building management information of the area to which the target brush belongs, including the land / building transaction price around the target brush, and calculates the compensation amount of the target brush. At this time, based on the brush management information, if the building dismantling is necessary, the amount corresponding thereto is also added to calculate the compensation amount. Negotiation prospect output means 1e calculates the degree of difficulty of the negotiation prospect according to the compensation amount for each target brush, and the negotiation prospect is displayed on the registry map showing the border line with the planned road after the separation is performed. Negotiation prospect maps are created by overlapping the difficulty levels.

また、本発明では、上記課題を解決するために、計画道路に係る土地の収用に関する交渉見込みの算出を支援する道路計画支援装置において、対象の計画道路に関する道路地図を含む道路関連情報を取得する道路情報取得手段と、登記所が管理する登記所地図と、道路地図とを重ね合わせ、道路地図上の計画道路図形を登記所地図の対応位置に反映し、計画道路図形に少なくとも一部が重なる対象筆を検索する対象筆検索手段と、対象筆に関する分筆情報、補償額および建物解体の有無を含む対象筆の筆管理情報を記憶する筆管理情報記憶手段と、対象筆を前記計画道路図形に応じて分筆するとともに、分筆を行った場合の建物解体の要否を判定し、筆管理情報に設定する分筆手段と、筆管理情報に基づき、土地・建物取引価格を含む対象筆の属する地域の土地・建物関連情報を参照して、建物解体を行った場合を含む対象筆の補償額を算出し、筆管理情報に設定する補償額算出手段と、分筆を行った対象筆の状態を示す地図上に補償額に応じた交渉見込みの難易度表示を重ね、交渉見込み地図として出力する交渉見込み出力手段と、を具備することを特徴とする道路計画支援装置が提供される。   Moreover, in this invention, in order to solve the said subject, in the road planning assistance apparatus which supports calculation of the negotiation prospect regarding land expropriation which concerns on a planned road, the road relevant information including the road map regarding a target planned road is acquired. The road information acquisition means, the registry map managed by the registry office, and the road map are overlaid, the planned road graphic on the road map is reflected in the corresponding position of the registry map, and at least partly overlaps the planned road graphic Target brush search means for searching for the target brush, brush management information storage means for storing the brush management information of the target brush including the information about the target brush, the amount of compensation for the target brush, the compensation amount, and the presence or absence of the building dismantling, and the target brush as the planned road figure In accordance with the brush management, it is determined whether or not the building should be dismantled, and the pen is set in the brush management information and the target brush including the land / building transaction price based on the brush management information. Calculate the compensation amount of the target brush including the case where the building was demolished by referring to the land / building related information of the area to which it belongs, and the compensation amount calculation means to be set in the brush management information, and the state of the target brush that performed the separation A road planning support device is provided, comprising: a negotiation prospect output means for displaying the difficulty level of the negotiation prospect according to the compensation amount on a map indicating the above and outputting as a negotiation prospect map.

このような道路計画支援装置では、調査対象の計画道路が指定されると、道路情報取得手段は、その道路地図を含む道路関連情報を取得し、対象筆検索手段は、道路地図と登記所地図とを重ね合わせて登記所地図に計画道路図形を反映し、対象筆を検索する。分筆手段は、対象筆を計画道路図形に応じて分筆し、建物解体の有無などを判定し、筆管理情報記憶手段に格納される筆管理情報に設定する。補償額算出手段は、筆管理情報に基づき、収用地の補償金と建物解体がある場合にはその費用を算出して加算し、補償額を算出して筆管理情報に設定する。交渉見込み出力手段は、補償額に応じた難易度表示を分筆後の筆界線を示した地図上に設定した交渉見込み地図を生成し、出力する。   In such a road planning support device, when a planned road to be investigated is designated, the road information acquisition means acquires road related information including the road map, and the target brush search means includes a road map and a registry map. And the planned road figure is reflected on the registry map, and the target brush is searched. The dividing means divides the target brush according to the planned road figure, determines the presence / absence of building dismantling, etc., and sets the brush management information stored in the brush management information storage means. The compensation amount calculation means calculates and adds the compensation amount of the land to be collected and the cost of dismantling the building based on the brush management information, calculates the compensation amount, and sets it in the brush management information. The negotiation prospect output means generates and outputs a negotiation prospect map in which the difficulty level display corresponding to the compensation amount is set on the map showing the stroke line after the separation.

本発明では、登記所地図上に計画道路図形を反映させた後、分筆を行って建物解体の要否などを判定し、収用地の補償額とともに、建物解体などが必要な場合はその費用を加算して対象筆に対する補償額を算出する。そして、補償額に応じた交渉見込みの難易度表示を分筆後の状態を示す地図上に設定し、交渉見込み地図を作成する。   In the present invention, after reflecting the planned road figure on the registry map, it is determined whether or not the building needs to be demolished by dividing it. Add up to calculate the compensation amount for the target brush. Then, the negotiation difficulty level display corresponding to the compensation amount is set on the map indicating the state after the separation, and a negotiation probability map is created.

このように、建物解体の要否などの要素を自動的に加味して補償額を算出するので、交渉に要する費用を正確、かつ容易に算出することができるという利点がある。また、出力時、交渉見込みの難易度も表示されるので、買収期間の予測なども容易に行うことができるようになる。   In this way, since the compensation amount is calculated by automatically taking into account factors such as the necessity of building dismantling, there is an advantage that the cost required for negotiation can be calculated accurately and easily. In addition, since the difficulty level of the negotiation is displayed at the time of output, the acquisition period can be easily predicted.

以下、本発明の実施の形態を図面を参照して説明する。まず、実施の形態に適用される発明の概念について説明し、その後、実施の形態の具体的な内容を説明する。
図1は、実施の形態に適用される発明の概念図である。
Hereinafter, embodiments of the present invention will be described with reference to the drawings. First, the concept of the invention applied to the embodiment will be described, and then the specific contents of the embodiment will be described.
FIG. 1 is a conceptual diagram of the invention applied to the embodiment.

本発明に係る道路計画支援装置1は、道路情報取得手段1a、対象筆検索手段1b、分筆手段1c、補償額算出手段1d、交渉見込み出力手段1eおよび筆管理情報(記憶手段)1fを有する。また、道路関連情報(記憶手段)2a、登記所関連情報(記憶手段)2bおよび土地・建物関連情報(記憶手段)2cに接続し、それぞれの記憶手段が格納する情報を読み出すことができる。   The road planning support apparatus 1 according to the present invention includes road information acquisition means 1a, target brush search means 1b, splitting means 1c, compensation amount calculation means 1d, negotiation prospect output means 1e, and brush management information (storage means) 1f. Further, it is possible to connect to road-related information (storage means) 2a, registry office-related information (storage means) 2b, and land / building related information (storage means) 2c, and to read information stored in the respective storage means.

ここで、道路関連情報(記憶手段)2aは、計画道路および現状道路に関する道路情報や道路地図などを格納する記憶手段である。なお、計画道路が建設予定の道路であるのに対し、現状道路は、道路地図および登記所地図に記載されている既存の道路である。登記所関連情報(記憶手段)2bは、登記所が保有する不動産に関する地図、地積測量図、建物図面、登記日時などを格納する記憶手段である。なお、登記所とは法務局、地方法務局、その支所・出張所を指し、ここでは、主として不動産に関する登記情報(登記所(法務省)地図、地積測量図、建物図面など)を保有する機関の意で用いる。土地・建物関連情報(記憶手段)2cは、登記所情報を除く土地や建物に関する情報で、たとえば、所定の地域の建ぺい率や容積率の基準、土地の取引価格、建物価格、狭小地の判断基準などの情報を格納する記憶手段である。   Here, the road related information (storage means) 2a is storage means for storing road information, road maps, and the like regarding the planned road and the current road. The planned road is a road that is planned to be constructed, whereas the current road is an existing road described in a road map and a registry map. The registry related information (storage unit) 2b is a storage unit that stores a map, a land survey map, a building drawing, a registration date and time, etc., related to real estate owned by the registry. The registration office refers to the Legal Affairs Bureau, the Geographical Affairs Bureau, its branch offices and branch offices, and is used here mainly to mean the registration information (registration office (Ministry of Justice) map, land survey map, building drawings, etc.) relating to real estate. . Land / building-related information (memory means) 2c is information on land and buildings excluding registry information. For example, the building coverage ratio and floor area standard for a given area, land transaction price, building price, and narrow land judgment standard Storage means for storing information such as.

道路情報取得手段1aは、道路番号や路線名など、調査対象の計画道路の指定情報を入力すると、これを検索キーとして道路関連情報(記憶手段)2aを検索し、対象の計画道路に関する道路地図を含む道路関連情報を取得する。この道路地図は、住居表示の地図である。また、計画道路が現状道路の拡張である場合は、現状道路に関する道路関連情報も同様に取得し、計画道路の幅員と現状道路の幅員とから幅員増分を算出しておく。   When the road information acquisition means 1a inputs the designation information of the planned road to be investigated such as the road number and the route name, the road information acquisition means 1a searches the road related information (storage means) 2a using this as a search key, and the road map relating to the target planned road Get road related information including This road map is a map of residence display. When the planned road is an extension of the current road, road-related information regarding the current road is acquired in the same manner, and the width increment is calculated from the width of the planned road and the width of the current road.

対象筆検索手段1bは、登記所関連情報(記憶手段)2bから調査対象の地域の登記所地図を取得する。この登記所地図は、地番表示であるので、道路情報取得手段1aで獲得した住居表示の道路地図と重ね合わせ、道路地図上の現状道路図形および計画される計画道路図形を登記所地図上に反映させる。そして、計画道路図形が設定される登記所地図から、現状道路の図形を除く計画道路図形の領域と少なくとも一部が重なる筆を検索する。そして、検索された筆は、対象筆として、地番などの筆を識別する情報を筆管理情報に設定し、筆管理情報(記憶手段)1fに格納する。また、このとき、必要であれば、実際の計画値に基づく幅員増分から計画道路図形を補正する。そして、対象筆の筆図形に対する分筆線となる計画道路図形の筆界線と、対象筆の筆図形の筆界線との距離を算出し、筆界線の移動距離として筆管理情報(記憶手段)1fに格納する。   The target brush search unit 1b acquires a registry map of the area to be investigated from the registry related information (storage unit) 2b. Since this registry map is a lot number display, it is superimposed with the road map of the residence display acquired by the road information acquisition means 1a, and the current road pattern and the planned planned road pattern on the road map are reflected on the registry map. Let Then, a brush that at least partially overlaps the area of the planned road graphic excluding the current road graphic is searched from the registry map where the planned road graphic is set. The retrieved brush sets, as the target brush, information identifying the brush such as a lot number in the brush management information and stores it in the brush management information (storage means) 1f. At this time, if necessary, the planned road figure is corrected from the width increment based on the actual planned value. Then, the distance between the boundary line of the planned road figure that becomes a parting line for the brush pattern of the target brush and the brush boundary line of the brush pattern of the target brush is calculated, and the movement distance of the brush line is stored in the brush management information (storage means) 1f. Store.

分筆手段1cは、対象筆検索手段1bによって検索された対象筆ごとに分筆を行うとともに、この分筆によって建物解体が必要となるかどうかを判定する。まず、筆管理情報を読み出し、筆管理情報に登録された対象筆の地番などからその筆の地積測量図を取得し、筆界線の移動距離に基づき、地積測量図上に分筆線を描画して分筆を行う。次に、分筆線によって分けられる現状道路側の収用部分の土地面積を算出し、筆管理情報に設定する。また、収用部分を除く土地の面積を算出し、対象筆の建物図面情報の建物の建築面積と延床面積とから、分筆後の建ぺい率と容積率を算出する。そして、対象筆の地域に設定される建ぺい率・容積率を取得し、取得した建ぺい率・容積率を基準として、分筆後の建ぺい率・容積率が基準を満たしているかどうかを判定する。基準を満たしていない場合、建物解体要を筆管理情報に設定する。また、分筆線上に建物が存在するかどうかを判定し、存在する場合も建物解体要を筆管理情報に設定する。さらに、必要であれば、交渉時の補償額や交渉期間に影響を与えると思われる事項について、同様の判定を行い、結果を筆管理情報に設定する。たとえば、収用部分を除く土地の面積が狭小地となり、利用価値がなくなってしまうような事態が発生するか否かを判定し、その結果を筆管理情報に設定する。なお、建ぺい率・容積率による建物解体要否の判定など、補償額に関連する項目についての判定は、後段の補償額算出手段1dで行ってもよい。   The splitting means 1c performs the splitting for each target brush searched by the target brush searching means 1b, and determines whether the building dismantling is required by this splitting. First, read the brush management information, get the area survey map of the brush from the lot number etc. of the target brush registered in the brush management information, draw the pen line on the area survey map based on the movement distance of the brush border line Make a pen. Next, the land area of the expropriated portion on the current road side divided by the stroke line is calculated and set in the brush management information. Further, the area of the land excluding the expropriated portion is calculated, and the building coverage ratio and the floor area ratio after the separation are calculated from the building area and the total floor area of the building drawing information of the target brush. Then, the building coverage ratio and the floor area ratio set in the area of the target brush are acquired, and it is determined whether or not the building coverage ratio and the floor area ratio after the separation satisfy the standard, based on the acquired building coverage ratio and the floor area ratio. If the standard is not satisfied, the building dismantling requirement is set in the brush management information. In addition, it is determined whether or not a building exists on the dividing line, and if it exists, the building dismantling point is set in the brush management information. Further, if necessary, the same determination is made for matters that may affect the compensation amount at the time of negotiation and the negotiation period, and the result is set in the brush management information. For example, it is determined whether or not a situation occurs in which the area of the land excluding the expropriation portion becomes narrow and the utility value is lost, and the result is set in the brush management information. It should be noted that the determination regarding items related to the compensation amount, such as the necessity of building dismantling based on the building coverage ratio and the floor area ratio, may be performed by the compensation amount calculating means 1d at the subsequent stage.

補償額算出手段1dは、分筆手段1cによって設定された筆管理情報に基づき、対象筆の補償額を算出して筆管理情報に設定する。土地・建物関連情報(記憶手段)2cから該当地域の土地の取引価格情報を読み出し、筆管理情報に設定される収用対象の土地面積から、その補償額を算出する。そして、筆管理情報に建物解体要が設定されていた場合には、土地・建物関連情報(記憶手段)2cから建物価格基準情報を読み出し、おおよその建物補償額の基準値を取得し、建物解体要否の判定で用いた建物の建築面積と延床面積から建物補償額を算出する。なお、分筆手段1cにおいて建物解体要否の判定が行われていない場合には、建物補償額の算出前に判定を実行する。以上のようにして得られた、土地の補償額と建物の補償額とを合算し、対象筆の補償額とする。また、他の要因に対する補償額が必要である場合には、これらの補償額も加算して対象筆の補償額を算出する。たとえば残地が狭小地であれば補償費を支払うという場合には、狭小地判定の結果に応じて、該当する補償費を加算する。最終的に算出された補償額は、筆管理情報に設定する。   The compensation amount calculation means 1d calculates the compensation amount of the target brush based on the brush management information set by the brush writing means 1c, and sets it in the brush management information. The transaction price information of the land in the corresponding area is read from the land / building related information (storage means) 2c, and the compensation amount is calculated from the land area to be expropriated set in the brush management information. Then, if the building dismantling requirement is set in the brush management information, the building price standard information is read from the land / building related information (storage means) 2c, the reference value of the approximate building compensation amount is obtained, and the building dismantling is obtained. The building compensation amount is calculated from the building area and total floor area used in the determination of necessity. In addition, when the necessity determination of building dismantling is not performed in the dividing means 1c, determination is performed before calculation of a building compensation amount. The compensation amount for land and the compensation amount for buildings obtained as described above are added together to obtain the compensation amount for the target brush. Further, when compensation amounts for other factors are necessary, these compensation amounts are also added to calculate the compensation amount for the target brush. For example, if the remaining land is narrow, if the compensation fee is paid, the corresponding compensation cost is added according to the result of the narrow land determination. The finally calculated compensation amount is set in the brush management information.

交渉見込み出力手段1eは、筆管理情報に基づき、分筆手段1cによって作成された分筆後の筆界線が描画された登記所地図上の対応位置に、補償額に応じた交渉見込みの難易度表示を示すアイコンを付加する。たとえば、額に応じて大きさ・数が変わるお金アイコンを定義しておき、対象筆の補償額に応じたアイコンを地図上に設定することによって、対象筆の補償額の大きさが一目でわかる表示を実現する。また、建物解体が必要な筆に対しては、建物解体要を示すアイコンを付与し、表示させる。   Based on the brush management information, the negotiation prospect output means 1e displays the difficulty level of the negotiation prospect according to the compensation amount at the corresponding position on the registry map where the stroke boundary line created by the dividing means 1c is drawn. Add an icon to indicate. For example, by defining a money icon that changes in size and number according to the amount, and setting an icon according to the compensation amount of the target brush on the map, you can see the amount of compensation for the target brush at a glance Realize the display. In addition, an icon indicating the necessity of building demolition is assigned to a brush that requires building demolition and displayed.

筆管理情報(記憶手段)1fは、対象筆検索手段1bによって検索された対象筆に関する筆管理情報を記憶する記憶手段である。
なお、上記の各処理手段は、コンピュータが道路計画支援プログラムを実行することによって、その機能を実現する。
The brush management information (storage unit) 1f is a storage unit that stores brush management information related to the target brush searched by the target brush search unit 1b.
Each processing unit described above realizes its function by the computer executing the road planning support program.

このような道路計画支援装置1の動作について説明する。
道路計画支援装置1に調査対象の計画道路を指定する道路番号が入力されると、道路情報取得手段1aは、指定された道路番号に対応する計画道路に関する道路地図、道路属性(幅員や道路名称、種別など)を、道路関連情報(記憶手段)2aから読み出す。対象筆検索手段1bは、登記所地図を登記所関連情報(記憶手段)2bから読み出し、道路情報取得手段1aで読み出された道路地図と登記所地図を重ね合わせ、道路地図上の計画道路図形を登記所地図上に反映する。住居表示の道路地図と地番表示の登記所地図の重ね合わせは、同じ場所であることが明白な基準点を複数設定し、この基準点が一致するようにいずれかの地図の座標値を補正して行う。さらに、対象筆検索手段1bは、登記所地図上の計画道路図形に基づき、収用対象の筆を検索する。すなわち、現状道路の筆界線と、計画道路の筆界線との間に含まれる筆図形をすべて抽出する。そして、地番など、抽出された対象筆を識別する情報と、現状道路の筆界線と計画道路の筆界線との差分である筆界線移動距離を筆管理情報に設定する。
The operation of the road planning support apparatus 1 will be described.
When the road number for designating the planned road to be surveyed is input to the road planning support device 1, the road information acquisition means 1a reads the road map and road attributes (width and road name) for the planned road corresponding to the designated road number. , Type, etc.) are read from the road related information (storage means) 2a. The target brush search means 1b reads the registry map from the registry related information (storage means) 2b, superimposes the road map read by the road information acquisition means 1a and the registry map, and creates a planned road figure on the road map. Is reflected on the registry map. Overlaying the road map with residence display and the registry map with lot number display sets multiple reference points that are clearly the same location, and corrects the coordinate values of either map so that these reference points match. Do it. Furthermore, the target brush search means 1b searches for a brush for expropriation based on the planned road figure on the registry map. That is, all the brush figures included between the current road brush border and the planned road brush border are extracted. Then, the stroke management distance is set in the brush management information, which is the difference between the information identifying the extracted target brush, such as the lot number, and the stroke line of the current road and the stroke line of the planned road.

分筆手段1cは、対象筆ごとに筆管理情報を読み出し、対象筆の地積測量図上に、筆界線の移動距離に基づいて分筆線を描画して分筆を行い、現状道路側の収用部分の土地面積を算出し、筆管理情報に設定する。また、収用部分を除く土地の面積を算出し、対象筆の建物図面情報の建物の建築面積と延床面積とから、分筆後の建ぺい率と容積率を算出し、対象地域の建ぺい率・容積率の基準を満たしているかどうかを判定する。基準を満たしていない場合は、建物解体要を筆管理情報に設定する。さらに、分筆線上に建物が存在するかどうかを判定し、存在する場合も建物解体要を筆管理情報に設定する。次に、補償額算出手段1dは、筆管理情報に設定される収用対象の土地面積と、土地・建物関連情報(記憶手段)2cの取引価格から、その筆の収用地に対する補償額を算出する。さらに、筆管理情報に建物解体要が設定されていた場合には、おおよその建物補償額の基準値を取得し、建物の建築面積と延床面積から建物補償額を算出する。そして、土地と建物の補償額を合算し、対象筆の補償額とする。また、他の要因に対する補償額が必要である場合には、これらの補償額も加算して対象筆の補償額を算出する。   The dividing means 1c reads out the brush management information for each target brush, draws a dividing line on the area survey map of the target brush based on the movement distance of the boundary line, and performs the dividing, and the land of the expropriation part on the current road side The area is calculated and set in the brush management information. In addition, the land area excluding the expropriated portion is calculated, and the building coverage ratio and floor area ratio after partitioning are calculated from the building area and total floor area of the building drawing information of the target brush, and the building area ratio and floor area ratio of the target area are calculated. Determine whether the criteria are met. If the standard is not satisfied, the building dismantling requirement is set in the brush management information. Further, it is determined whether or not a building exists on the dividing line, and if it exists, the building disassembly requirement is set in the brush management information. Next, the compensation amount calculation means 1d calculates the compensation amount for the collection place of the brush from the land area to be collected set in the brush management information and the transaction price of the land / building related information (storage means) 2c. . Further, when the building dismantling requirement is set in the brush management information, an approximate reference value of the building compensation amount is acquired, and the building compensation amount is calculated from the building area and the total floor area of the building. Then, the compensation amount for the land and building is added together to obtain the compensation amount for the target brush. Further, when compensation amounts for other factors are necessary, these compensation amounts are also added to calculate the compensation amount for the target brush.

交渉見込み出力手段1eは、筆管理情報に基づき、分筆後の筆界線が描画された登記所地図上の対応位置に、補償額に応じた交渉見込みの難易度を示すアイコンを付加し、表示させる。   Based on the brush management information, the negotiation prospect output means 1e adds and displays an icon indicating the difficulty level of the negotiation prospect according to the compensation amount at the corresponding position on the registry map where the stroke line after the separation is drawn. .

このように、調査対象の計画道路が指定されると、登記所地図上に指定された計画道路図形を反映させた後、分筆を行って建物解体の要否などを判定し、収用地の補償額とともに、建物解体などが必要な場合はその費用を加算して対象筆に対する補償額を算出するので、交渉に要する費用を正確かつ容易に算出することができる。   In this way, when the planned road to be surveyed is designated, the designated road figure on the registry map is reflected, and then a pen is drawn to determine the necessity of building dismantling, etc. When the building dismantling is required together with the amount, the cost is added to calculate the compensation amount for the target brush, so the cost required for negotiation can be calculated accurately and easily.

また、補償額に応じた交渉見込みの難易度をアイコンによって表し、このアイコンを計画道路が描画される交渉見込み地図上の筆に対応して表示させるので、買収期間の予測なども容易に行うことができるようになる。   In addition, the difficulty level of the negotiation prospect according to the compensation amount is indicated by an icon, and this icon is displayed corresponding to the brush on the negotiation prospect map where the planned road is drawn, so that the acquisition period can be easily predicted. Will be able to.

以下、実施の形態を、既存の道路の幅員を拡張する道路計画についての交渉見込みを算出する場合を例にとり、図面を参照して詳細に説明する。
図2は、本発明の実施の形態の道路計画支援装置を含むシステムの構成図である。
Hereinafter, an embodiment will be described in detail with reference to the drawings, taking as an example the case of calculating a negotiation probability for a road plan for expanding the width of an existing road.
FIG. 2 is a configuration diagram of a system including the road planning support apparatus according to the embodiment of this invention.

実施の形態の道路計画支援装置100は、図示しないネットワークによって、道路関連情報管理装置200、登記所関連情報管理装置300、土地・建物関連情報管理装置400および利用者端末500a、500bに接続している。   The road planning support apparatus 100 according to the embodiment is connected to a road related information management apparatus 200, a registry office related information management apparatus 300, a land / building related information management apparatus 400, and user terminals 500a and 500b through a network (not shown). Yes.

道路関連情報管理装置200は、計画道路に関する道路情報属性や道路・土地情報地図などが格納されるデータベース200aを管理する。登記所関連情報管理装置300は、登記所が管理する登記所地図、地積測量図、建物図面などが格納されるデータベース300aを管理する。土地・建物関連情報管理装置400は、建ぺい率・容積率基準、取引価格、建物価格基準、狭小地判断などの土地・建物関連情報が格納されるデータベース400aを管理する。道路関連情報管理装置200、登記所関連情報管理装置300および土地・建物関連情報管理装置400は、道路計画支援装置100から要求された情報データを提供する。また、図2では、ネットワークを介して接続する各情報管理装置を介してデータを取得するとしたが、各データベースが直接道路計画支援装置100に接続する構成とすることもできる。   The road related information management apparatus 200 manages a database 200a in which road information attributes, road / land information maps, etc. relating to the planned road are stored. The registry office-related information management device 300 manages a database 300a in which registry maps, land survey maps, building drawings, and the like managed by the registry office are stored. The land / building related information management device 400 manages a database 400a in which land / building related information such as building coverage ratio / floor ratio standard, transaction price, building price standard, and narrow land judgment are stored. The road-related information management device 200, the registry office-related information management device 300, and the land / building-related information management device 400 provide information data requested from the road planning support device 100. In FIG. 2, data is acquired via each information management device connected via a network, but each database may be directly connected to the road planning support device 100.

利用者端末500a、500bは、利用者による交渉見込み算出対象の計画道路の指定を道路計画支援装置100に送信するとともに、道路計画支援装置100が作成した交渉見込み地図を取得し、表示画面に表示する。   The user terminals 500a and 500b transmit the designation of the planned road to be calculated by the user to the negotiation plan calculation target to the road planning support apparatus 100, acquire the negotiation prospect map created by the road planning support apparatus 100, and display it on the display screen. To do.

なお、以上の構成は一例であり、データの所在などに応じて適宜変更される。
ここで、道路計画支援装置100のハードウェア構成について説明する。図3は、本実施の形態の道路計画支援装置のハードウェア構成例を示すブロック図である。
The above configuration is an example, and is changed as appropriate according to the location of data.
Here, the hardware configuration of the road planning support apparatus 100 will be described. FIG. 3 is a block diagram illustrating a hardware configuration example of the road planning support apparatus according to the present embodiment.

道路計画支援装置100は、CPU(Central Processing Unit)101によって装置全体が制御されている。CPU101には、バス107を介してRAM(Random Access Memory)102、ハードディスクドライブ(HDD:Hard Disk Drive)103、グラフィック処理装置104、入力インタフェース105、通信インタフェース106が接続されている。   The entire road planning support apparatus 100 is controlled by a CPU (Central Processing Unit) 101. A random access memory (RAM) 102, a hard disk drive (HDD) 103, a graphic processing device 104, an input interface 105, and a communication interface 106 are connected to the CPU 101 via a bus 107.

RAM102には、CPU101に実行させるOS(Operating System)のプログラムやアプリケーションプログラムの少なくとも一部が一時的に格納される。また、RAM102には、CPU101による処理に必要な各種データが格納される。HDD103には、OSやアプリケーションプログラムが格納される。グラフィック処理装置104には、モニタ108が接続されており、CPU101からの命令に従って画像をモニタ108の画面に表示させる。入力インタフェース105には、キーボード109aやマウス109bが接続されており、キーボード109aやマウス109bから送られてくる信号を、バス107を介してCPU101に送信する。通信インタフェース106は、ネットワーク600に接続されており、ネットワーク600を介して利用者の端末装置やデータサーバとの間でデータの送受信を行う。   The RAM 102 temporarily stores at least part of an OS (Operating System) program and application programs to be executed by the CPU 101. The RAM 102 stores various data necessary for processing by the CPU 101. The HDD 103 stores an OS and application programs. A monitor 108 is connected to the graphic processing device 104, and an image is displayed on the screen of the monitor 108 in accordance with a command from the CPU 101. A keyboard 109 a and a mouse 109 b are connected to the input interface 105, and signals transmitted from the keyboard 109 a and the mouse 109 b are transmitted to the CPU 101 via the bus 107. The communication interface 106 is connected to the network 600 and transmits / receives data to / from a user terminal device or a data server via the network 600.

このようなハードウェア構成によって、本実施の形態の処理機能を実現することができる。また、利用者端末500a、500bも同様のハードウェア構成をとる。
なお、図3では、モニタ108、キーボード109a、マウス109bなどのユーザインタフェースが道路計画支援装置100に接続するとしたが、図2に示したように利用者端末500a、500bとネットワーク600を介して接続し、ユーザインタフェース処理は、利用者端末側で行うとし、ユーザインタフェースを持たない構成としてもよい。
With such a hardware configuration, the processing functions of the present embodiment can be realized. The user terminals 500a and 500b also have the same hardware configuration.
In FIG. 3, the user interface such as the monitor 108, the keyboard 109 a, and the mouse 109 b is connected to the road planning support apparatus 100, but is connected to the user terminals 500 a and 500 b via the network 600 as shown in FIG. 2. However, the user interface processing may be performed on the user terminal side and may be configured without a user interface.

次に、道路計画支援装置100のソフトウェア構成について説明する。図4は、本実施の形態の道路計画支援装置のソフトウェア構成を示すブロック図である。図2と同じものには同じ番号を付し、説明は省略する。なお、説明を簡単にするため、道路計画支援装置100は、直接各データベースにアクセスできるとする。   Next, the software configuration of the road planning support apparatus 100 will be described. FIG. 4 is a block diagram showing a software configuration of the road planning support apparatus according to the present embodiment. The same components as those in FIG. 2 are denoted by the same reference numerals, and description thereof is omitted. In order to simplify the description, it is assumed that the road planning support apparatus 100 can directly access each database.

道路計画支援装置100は、幅員増分算出モジュール111、道路情報取得モジュール112、対象筆検索モジュール113、登記所関連情報取得モジュール114、建ぺい率・容積率算出モジュール115、分筆モジュール116、対象筆管理ワークテーブル(記憶部)117、分筆線上の建物検索モジュール118、補償額地図出力モジュール119、補償額算出モジュール120および土地・建物関連情報取得モジュール121を有する。   The road planning support device 100 includes a width increment calculation module 111, a road information acquisition module 112, a target brush search module 113, a registry office related information acquisition module 114, a building coverage ratio / flood ratio calculation module 115, a pen writing module 116, and a target brush management work table. (Storage unit) 117, a building search module 118 on a stroke line, a compensation map output module 119, a compensation calculation module 120, and a land / building related information acquisition module 121.

幅員増分算出モジュール111は、道路情報取得モジュール112を介して調査対象の計画道路に関する道路関連情報を取得し、現状道路から計画道路へ拡張する幅員増分を算出する。道路情報取得モジュール112は、道路関連情報を格納する道路情報属性データベース210を検索して指定された計画道路および計画道路に対応する現状道路に関する道路情報属性を取得するとともに、道路・土地情報地図データベース220を検索して道路・土地情報地図を取得する。   The width increase calculation module 111 acquires road related information related to the planned road to be investigated via the road information acquisition module 112, and calculates a width increase to be expanded from the current road to the planned road. The road information acquisition module 112 searches the road information attribute database 210 that stores road related information, acquires road information attributes related to the designated road and the current road corresponding to the road, and road / land information map database. A road / land information map is acquired by searching 220.

対象筆検索モジュール113は、登記所関連情報取得モジュール114を介して調査対象の地域の登記所地図を取得し、道路情報取得モジュール112が取得した道路地図と重ね合わせ、計画道路図形を描画して対象筆を検索する。検索された対象筆の識別情報と筆界線移動距離は、対象筆管理ワークテーブル(記憶部)117に格納する。登記所関連情報取得モジュール114は、登記所が管理する登記所関連情報を格納する登記所地図データベース310、地積測量図データベース320、建物図面データベース330および登記データベース340を検索し、それぞれ調査対象の登記所地図、対象筆の地積測量図、建物図面および登記情報を取得する。建ぺい率・容積率算出モジュール115は、対象筆の地積測量図と建物図面を読み出し、分筆モジュール116によって分筆された対象筆の収用地を除く残地の面積に基づき分筆後の建ぺい率と容積率を算出する。分筆モジュール116は、対象筆の筆界線移動距離に基づき、対象筆の地積測量図上に分筆線を描画する。分筆線上の建物検索モジュール118は、分筆モジュール116の描画した分筆線上に建物が存在する対象筆を検索する。   The target brush search module 113 acquires a registry map of the area to be surveyed via the registry related information acquisition module 114, superimposes it with the road map acquired by the road information acquisition module 112, and draws a planned road figure. Search for the target brush. The identification information and the stroke line movement distance of the searched target brush are stored in the target brush management work table (storage unit) 117. The registry-related information acquisition module 114 searches the registry map database 310, the land survey map database 320, the building drawing database 330, and the registry database 340 that store registry-related information managed by the registry, and registers each of the survey targets. Get the location map, the area survey map of the target brush, the building drawing, and the registration information. The building coverage ratio / floor ratio calculation module 115 reads the area survey map and building drawing of the target brush, and calculates the building coverage ratio and the floor ratio after the separation based on the area of the remaining land excluding the collection area of the target brush divided by the distribution module 116. To do. The dividing module 116 draws a dividing line on the area survey map of the target brush based on the movement distance of the target brush. The building search module 118 on the stroke line searches for a target brush whose building exists on the stroke line drawn by the stroke module 116.

補償額地図出力モジュール119は、補償額算出モジュール120が算出した補償額に応じた交渉の難易度を示すアイコンを分筆後の対象筆を示した登記所地図上に設定し、交渉見込み地図(補償額に関する見込みが主であるので、以下、補償額地図とする)を出力する。補償額算出モジュール120は、土地・建物関連情報取得モジュール121を介して読み出した建ぺい率・容積率基準、取引価格、建物価格基準および狭小地マスタテーブルに基づき、対象筆ごとの補償額を算出する。土地・建物関連情報取得モジュール121は、土地・建物関連情報を格納する建ぺい率・容積率基準データベース410、取引価格データベース420、建物価格基準データベース430および狭小地判断マスタテーブル440を検索し、調査対象の筆に対応する建ぺい率・容積率基準、取引価格、建物価格基準および狭小地マスタテーブルを取得する。   The compensation amount map output module 119 sets an icon indicating the difficulty level of negotiation according to the compensation amount calculated by the compensation amount calculation module 120 on the registry map indicating the target brush after the separation, and sets the negotiation prospect map (compensation). Since the prospects for the amount are mainly, the compensation amount map will be output below. The compensation amount calculation module 120 calculates a compensation amount for each target brush on the basis of the building coverage ratio / volume ratio standard, transaction price, building price standard, and narrow land master table read out via the land / building related information acquisition module 121. The land / building related information acquisition module 121 searches the building coverage ratio / flood ratio reference database 410, the transaction price database 420, the building price reference database 430, and the narrow land determination master table 440 for storing the land / building related information, Get the building coverage ratio / floor area standard, transaction price, building price standard, and narrow land master table corresponding to the brush.

以下、各データベースの構成を順に説明する。
図5は、本実施の形態の道路情報属性データベースの構成を示した図である。
道路情報属性データベース210に格納される道路情報属性は、道路を識別する道路番号211a、その道路名称211b、道路の幅員211c、種別211dなどの情報項目から構成される。種別211dは、該当する道路が既存の現状道路、または計画されている計画道路のいずれであるかを示す。たとえば、道路番号「331」によって識別される道路「Cの丘線」は、現状道路で、幅員が「19」である。そして、道路番号「333」によって識別される同じ道路は計画道路で、幅員を「30」に拡張する計画がされていることが設定されている。
Hereinafter, the configuration of each database will be described in order.
FIG. 5 is a diagram showing the configuration of the road information attribute database of the present embodiment.
The road information attribute stored in the road information attribute database 210 includes information items such as a road number 211a for identifying a road, a road name 211b, a road width 211c, and a type 211d. The type 211d indicates whether the corresponding road is an existing current road or a planned road that is planned. For example, the road “C hill line” identified by the road number “331” is a current road and has a width of “19”. The same road identified by the road number “333” is a planned road, and it is set that the width is planned to be expanded to “30”.

図6は、本実施の形態の道路・土地情報地図データベースの構成を示した図である。
道路・土地情報地図データベース220は、道路結線テーブル221、土地結線テーブル222、座標値テーブル223から構成される。これらは、道路・土地情報地図をデータ化した情報であり、道路結線テーブル221は、道路番号と、道路図形を描画する2点の番号の情報項目を有する。点番号は、地図上に道路図形を描画するため、道路図形上の任意の点を結ぶ結線の開始と終了点を示している。同様に、土地結線テーブル222には、土地の住居表示と、地図上に土地図形を描画するため、土地図形上の任意の点を結ぶ結線の開始と終了点を示す点番号の情報項目がある。座標値テーブル223は、道路結線テーブル221と土地結線テーブル222の点番号の座標を示している。たとえば、道路番号「131」の道路図形は、点番号「S1」と「S2」によって結ばれる線分を有し、「S1」の地図座標は(Xs1,Ys1)、「S2」の座標は(Xs2,Ys2)であることが示されている。これにより、地図上に道路番号「131」の道路図形を描画することができる。同様に、「千葉県松戸市八ヶ崎・・・」で表される土地図形は、点番号「U1」、「U2」を結ぶ線から点番号「U4」、「U1」を結ぶ線によって表すことができる。土地図形の点番号も、同様に座標値テーブル223に設定されており、地図上に土地図形を描画することができる。
FIG. 6 is a diagram showing a configuration of a road / land information map database according to the present embodiment.
The road / land information map database 220 includes a road connection table 221, a land connection table 222, and a coordinate value table 223. These are information obtained by converting the road / land information map into data, and the road connection table 221 has information items of road numbers and two numbers for drawing road figures. The point numbers indicate the start and end points of the connection connecting arbitrary points on the road graphic in order to draw the road graphic on the map. Similarly, in the land connection table 222, there is a point number information item indicating the start and end points of the connection connecting arbitrary points on the land figure in order to draw the land figure on the map and the land dwelling display. . The coordinate value table 223 indicates the coordinates of the point numbers of the road connection table 221 and the land connection table 222. For example, the road figure of road number “131” has a line segment connected by point numbers “S1” and “S2”, the map coordinates of “S1” are (Xs1, Ys1), and the coordinates of “S2” are ( Xs2, Ys2). Thereby, the road figure of the road number “131” can be drawn on the map. Similarly, a land figure represented by “Yatsuzaki, Matsudo-shi, Chiba Prefecture” is represented by a line connecting point numbers “U4” and “U1” from a line connecting point numbers “U1” and “U2”. be able to. Similarly, the point number of the land figure is also set in the coordinate value table 223, and the land figure can be drawn on the map.

図7は、本実施の形態の登記所地図データベースの構成を示した図である。
登記所地図データベース310は、結線テーブル311と座標値テーブル312から構成される。結線テーブル311は、地番区域311aと、地番311bおよび結線の点番号311c、311dから構成される。座標値テーブル312は、結線テーブル311の点番号311c、311dの座標を示している。たとえば、地番区域「千葉県松戸市八ヶ崎」の地番「10」の土地図形は、点番号「T1」、「T2」を結ぶ線から点番号「T4」、「T1」を結ぶ線によって表すことができる。土地図形の点番号は、座標値テーブル312に設定されており、地図上に土地図形を描画することができる。
FIG. 7 is a diagram showing a configuration of the registry map database according to the present embodiment.
The registry map database 310 includes a connection table 311 and a coordinate value table 312. The connection table 311 includes a lot number area 311a, a lot number 311b, and connection point numbers 311c and 311d. The coordinate value table 312 indicates the coordinates of the point numbers 311c and 311d in the connection table 311. For example, the land figure of the lot number “10” in the lot number area “Yatsuzaki, Matsudo City, Chiba Prefecture” is represented by a line connecting the point numbers “T4” and “T1” from the line connecting the point numbers “T1” and “T2”. be able to. The point number of the land figure is set in the coordinate value table 312, and the land figure can be drawn on the map.

図8は、本実施の形態の地積測量図データベースの構成を示した図である。
地積測量図データベース320は、一筆単位の地図をデータ化した情報で、結線テーブル321と座標値テーブル322とから構成される。結線テーブル321は、登記所地図の結線テーブル311と同様に、地番区域321a、地番321bおよび結線の点番号321c、321dから構成される。なお、座標値テーブル322が示す点番号の座標は、所定の基準点からの位置を示した公共座標値によって表される。分筆処理は、この地積測量図に基づいて行われる。
FIG. 8 is a diagram showing the structure of the land survey map database according to the present embodiment.
The land survey map database 320 is information obtained by converting a map of one stroke to data, and includes a connection table 321 and a coordinate value table 322. The connection table 321 includes a lot number area 321a, a lot number 321b, and connection point numbers 321c and 321d, similarly to the connection table 311 of the registry map. Note that the coordinates of the point numbers indicated by the coordinate value table 322 are represented by public coordinate values indicating positions from a predetermined reference point. The pen-drawing process is performed based on this area survey map.

図9は、本実施の形態の建物図面データベースの構成を示した図である。
建物図面データベース330は、建物の図面をデータ化した情報で、結線テーブル331、座標値テーブル332および属性テーブル333から構成される。結線テーブル331は、建物のある地番区域331a、地番331b、家屋番号331cおよびその建物図形上の線分を示す点番号331d、331eが設定される。また、座標値テーブル332には、点番号に対応する座標値が設定されている。また、属性テーブル333は、家屋ごとの建築面積と延床面積が格納されている。たとえば、地番「6」の家屋番号「あいう」は、建築面積が「50」で、延床面積が「80」であることが示されている。
FIG. 9 is a diagram showing a configuration of a building drawing database according to the present embodiment.
The building drawing database 330 is information obtained by converting building drawings into data, and includes a connection table 331, a coordinate value table 332, and an attribute table 333. In the connection table 331, a lot number area 331a, a lot number 331b, a house number 331c, and point numbers 331d and 331e indicating line segments on the building figure are set. In the coordinate value table 332, coordinate values corresponding to the point numbers are set. The attribute table 333 stores the building area and the total floor area for each house. For example, the house number “Ayu” of the lot number “6” indicates that the building area is “50” and the total floor area is “80”.

図10は、本実施の形態の登記データベースの構成を示した図である。
登記データベース340は、土地・建物の登記に関する情報であり、地番区域341a、地番341b、家屋番号341c、種類341d、構造341eおよび登記原因とその日付341fなどの情報項目を有する。地番区域341a、地番341bおよび家屋番号341cは、建物図面データベース330の結線テーブル331の地番区域331a、地番331bおよび家屋番号331cと同じである。種類341dは家屋の用途、構造341eは家屋の構造体および登記原因とその日付341fは登記の理由と登記日時を示している。
FIG. 10 is a diagram showing a configuration of the registration database according to the present embodiment.
The registration database 340 is information regarding land / building registration, and includes information items such as a lot number area 341a, a lot number 341b, a house number 341c, a type 341d, a structure 341e, a registration cause, and a date 341f thereof. The lot number area 341a, lot number 341b, and house number 341c are the same as the lot number area 331a, lot number 331b, and house number 331c of the connection table 331 of the building drawing database 330. The type 341d indicates the usage of the house, the structure 341e indicates the structure of the house and the registration cause, and the date 341f indicates the reason for registration and the date and time of registration.

図11は、本実施の形態の建ぺい率・容積率基準データベースの構成を示した図である。
建ぺい率・容積率基準データベース410には、自治体などが保有する建ぺい率・容積率基準情報が格納され、所定の住居区域を示す住居表示411a、その住居区域における建ぺい率411bおよび容積率411cの基準値などの情報項目がある。
FIG. 11 is a diagram showing the configuration of the building coverage ratio / volume ratio reference database according to the present embodiment.
The building coverage ratio / floor ratio reference database 410 stores building coverage ratio / floor ratio reference information held by local governments and the like, such as a house display 411a indicating a predetermined residential area, and a reference value of the building coverage ratio 411b and the floor area ratio 411c in the residential area. There is an information item.

図12は、本実施の形態の取引価格データベースの構成を示した図である。
取引価格データベース420には、取引価格情報が格納され、住居表示421aと、その住居地域の土地の1m2当たりの取引価格421bなどの情報項目がある。
FIG. 12 is a diagram showing a configuration of a transaction price database according to the present embodiment.
The transaction price database 420 stores transaction price information, and includes information items such as a housing display 421a and a transaction price 421b per 1 m 2 of land in the residential area.

図13は、本実施の形態の建物価格基準データベースの構成を示した図である。
建物価格基準データベース430は、床面積431、築年数432およびその他係数433から構成される。これらの情報は、建物の価値を見積もるための情報で、床面積431は、床面積の広さに応じた取引価格、築年数432は、築年数に応じた補償金の減額係数、およびその他係数433は、その他の条件に応じた補償額係数を示している。
FIG. 13 is a diagram showing a configuration of a building price reference database according to the present embodiment.
The building price reference database 430 includes a floor area 431, a building age 432, and other coefficients 433. These pieces of information are information for estimating the value of the building. The floor area 431 is a transaction price corresponding to the size of the floor area, the building age 432 is a reduction factor of compensation according to the building age, and other factors. Reference numeral 433 denotes a compensation amount coefficient according to other conditions.

図14は、本実施の形態の狭小地判断マスタテーブルの構成を示した図である。
狭小地判断マスタテーブル440には、狭小地と判断する面積範囲、下限を示す狭小地判断面積1(441a)と上限を示す狭小地判断面積2(441b)、該当する狭小地における価格低下比率441cが示されている。
FIG. 14 is a diagram showing a configuration of the narrow land determination master table of the present embodiment.
The narrow area determination master table 440 includes an area range to be determined as a narrow area, a narrow area determination area 1 (441a) indicating a lower limit, a narrow area determination area 2 (441b) indicating an upper limit, and a price reduction ratio 441c in the corresponding narrow area. It is shown.

たとえば、収用外の土地の面積が「8」であった場合、「No.2」の範囲となり、価値低下比率は、該当する土地の取引価格の50%となる。
ここで、対象筆管理ワークテーブルの構成について説明する。
For example, when the area of land that is not expropriated is “8”, it is in the range of “No.
Here, the configuration of the target brush management work table will be described.

図15は、本実施の形態の対象筆管理ワークテーブルの構成を示した図である。
対象筆管理ワークテーブル(記憶部)117に格納される対象筆管理ワークテーブルは、地番117a、筆界線移動距離117b、建ぺい率117c、容積率117d、建物解体フラグ117e、補償額(土地)117f、補償額(建物)117g、補償額(計)117hおよび残地補償額117iを有する。
FIG. 15 is a diagram showing the configuration of the target brush management work table of the present embodiment.
The target brush management work table stored in the target brush management work table (storage unit) 117 includes a lot number 117a, a brush stroke moving distance 117b, a building coverage ratio 117c, a floor area ratio 117d, a building dismantling flag 117e, a compensation amount (land) 117f, and a compensation. It has a forehead (building) 117g, a compensation amount (total) 117h, and a remaining site compensation amount 117i.

地番117aには、対象筆検索モジュール113によって検索された対象筆の地番が登録される。筆界線移動距離117bには、対象筆検索モジュール113によって算出された対象筆の筆界線移動距離が登録される。建ぺい率117cおよび容積率117dには、建ぺい率・容積率算出モジュール115によって算出された対象筆の建ぺい率と容積率がそれぞれ登録される。建物解体フラグ117eには、分筆線上の建物検索モジュール118または補償額算出モジュール120によって解体が必要と判定された対象筆についてフラグがセットされる。補償額(土地)117fには、補償額算出モジュール120が算出した収用地に関する補償額が登録される。補償額(建物)117gには、建物解体フラグ117eがセットされている対象筆について、補償額算出モジュール120が算出した建物に関する補償額が登録される。補償額(計)117hには、補償額(土地)117fと補償額(建物)117gとを合算した補償額が登録される。残地補償額117iには、補償額算出モジュール120によって狭小地と判断された残地に関する補償額が登録される。   The lot number of the target brush searched by the target brush search module 113 is registered in the lot number 117a. In the brush stroke moving distance 117b, the brush stroke moving distance of the target brush calculated by the target brush search module 113 is registered. In the building coverage ratio 117c and the volume ratio 117d, the building coverage ratio and the volume ratio of the target brush calculated by the building coverage ratio / volume ratio calculation module 115 are registered, respectively. In the building dismantling flag 117e, a flag is set for a target brush that is determined to be dismantling by the building search module 118 or the compensation amount calculation module 120 on the dividing line. In the compensation amount (land) 117f, the compensation amount related to the land acquired by the compensation amount calculation module 120 is registered. In the compensation amount (building) 117g, the compensation amount related to the building calculated by the compensation amount calculation module 120 is registered for the target brush in which the building dismantling flag 117e is set. In the compensation amount (total) 117h, a compensation amount obtained by adding the compensation amount (land) 117f and the compensation amount (building) 117g is registered. In the remaining area compensation amount 117i, a compensation amount related to the remaining area determined to be a narrow area by the compensation amount calculation module 120 is registered.

以下、このような構成の道路計画支援装置100の処理動作について説明する。最初に処理全体の流れについて説明し、続いて個々の処理について説明する。
図16は、本実施の形態の道路支援装置の処理手順を示したフローチャートである。
Hereinafter, the processing operation of the road planning support apparatus 100 having such a configuration will be described. First, the flow of the entire process will be described, and then each process will be described.
FIG. 16 is a flowchart showing a processing procedure of the road support apparatus according to the present embodiment.

[ステップS01] 調査対象の計画道路の指定情報(道路番号、路線名など)を入力する。指定情報は、ネットワークを介して接続する利用者端末500a、500bなどから取得する。   [Step S01] The designation information (road number, route name, etc.) of the planned road to be investigated is input. The designation information is acquired from the user terminals 500a and 500b connected via the network.

[ステップS02] ステップS01で取得した指定情報に基づき、道路情報属性データベース210および道路・土地情報地図データベース220を検索し、調査対象の計画道路に関する道路情報属性と道路・土地情報地図を取得する。そして、得られた道路情報属性に基づき、現状道路から計画道路に拡張する際の幅員増分を算出する。   [Step S02] Based on the designation information acquired in step S01, the road information attribute database 210 and the road / land information map database 220 are searched, and road information attributes and road / land information maps relating to the planned road to be investigated are acquired. Then, based on the obtained road information attribute, the width increase when expanding from the current road to the planned road is calculated.

[ステップS03] 登記所地図データベース310を検索して該当する登記所地図を取得し、ステップS02で取得した道路・土地情報地図と重ね合わせる。必要であれば、幅員増分で道路図形を補正する。そして、登記所地図に調査対象の道路図形を描画し、道路図形の筆界線に接面する筆図形および影響を受ける筆を検索し、これらをすべて抽出する。また、筆界線の移動距離を対象筆管理ワークテーブルに登録しておく。   [Step S03] The registry map database 310 is searched to obtain a corresponding registry map, and is superimposed on the road / land information map acquired in step S02. If necessary, correct the road figure in increments of width. Then, the road figure to be surveyed is drawn on the registry map, the brush figure in contact with the brush border of the road figure and the affected brush are searched, and all of them are extracted. Also, the movement distance of the brush stroke line is registered in the target brush management work table.

[ステップS04] ステップS03によって抽出された対象筆について、地積測量図データベース320から地積測量図を抽出し、分筆線を新たに描画して分筆処理を行う。また、建物図面データベース330を検索して対象筆の建物情報を取得し、収用対象でない方の筆に対して建ぺい率および容積率を算出する。算出された建ぺい率および容積率は、対象筆管理ワークテーブルに登録する。   [Step S04] With respect to the target brush extracted in step S03, a geodetic survey map is extracted from the geodetic survey map database 320, and a pen stroke line is newly drawn to perform a pen stroke process. Further, the building drawing database 330 is searched to acquire the building information of the target brush, and the building coverage ratio and the floor area ratio are calculated with respect to the brush that is not subject to expropriation. The calculated building coverage ratio and floor area ratio are registered in the target brush management work table.

[ステップS05] 各対象筆の分筆線上に建物があるかどうかを調べる。すなわち、ステップS04において分筆された対象筆の筆図形と建物図形を重畳させ、分筆線と建物図形に交点があるかどうかを調べ、交点がある筆を特定する。分筆線上に建物がある場合は、該当筆の建物解体フラグ117eをセットする。   [Step S05] It is checked whether there is a building on the dividing line of each target brush. That is, the brush figure and the building figure of the target brush divided in step S04 are superimposed, and it is checked whether or not there is an intersection between the dividing line and the building figure, and the brush with the intersection is specified. If there is a building on the dividing line, the building disassembly flag 117e of the corresponding brush is set.

[ステップS06] 対象筆管理ワークテーブルに基づいて補償額算出処理を行って補償額地図を作成し、出力する。取引価格データベース420を検索して、該当路線の基準価格を取得して対象筆の収用地の補償額を算出する。また、ステップS04で算出された建ぺい率・容積率を建ぺい率・容積率基準データベース410から抽出した該当路線の基準と比較し、建物解体が必要であるかどうかを判断する。必要と判断された場合およびステップS05によって建物解体フラグ117eがセットされていた場合は、建物価格基準データベース430や登記データベース340の該当データを参照して建物に関する補償額を算出する。さらに、残地の面積を狭小地判断マスタテーブル440と照らし合わせ、狭小地と判断される場合には、残地補償額を算出する。これらが合算され、全体の補償額見込みが算出される。こうして算出された補償額に応じたアイコンを分筆後の状態が描画された登記所地図上に設定して補償額地図を作成し、出力する。   [Step S06] A compensation amount calculation process is performed based on the target brush management work table to create and output a compensation amount map. The transaction price database 420 is searched, the reference price of the corresponding route is acquired, and the compensation amount of the destination area for the target brush is calculated. Further, the building coverage ratio / floor ratio calculated in step S04 is compared with the reference of the corresponding route extracted from the building coverage ratio / volume ratio reference database 410, and it is determined whether or not building dismantling is necessary. If it is determined that it is necessary and if the building dismantling flag 117e is set in step S05, the compensation amount for the building is calculated with reference to the corresponding data in the building price standard database 430 and the registration database 340. Further, the remaining area is compared with the narrow area determination master table 440, and when it is determined that the area is narrow, the remaining area compensation amount is calculated. These are added together to calculate the total compensation estimate. An icon corresponding to the compensation amount calculated in this way is set on the registry map on which the state after the division is drawn, and a compensation amount map is created and output.

次に、各ステップにおける処理について詳細に説明する。
(1)道路情報取得と幅員増分算出処理
道路情報取得モジュール112は、調査対象として指定された計画道路の「道路番号」もしくは「道路名称」と、「種別=現状」を検索キーとして道路情報属性データベース210を検索し、現状道路の幅員を抽出する。続いて、同じ「道路番号」もしくは「道路名称」と、「種別=計画」を検索キーとして道路情報属性データベース210を検索し、計画道路の幅員を抽出する。そして、幅員増分算出モジュール111は、それぞれの幅員から拡張される幅員増分を算出する。算出は、
幅員増分= 計画道路の幅員 − 現状道路の幅員 ・・・(1)
によって行う。たとえば、図5の「Cの丘線」の場合、幅員増分は、30−19=11mとなる。また、道路情報取得モジュール112は、道路・土地情報地図データベース220を検索し、調査対象の計画道路に関する道路・土地情報地図を取得しておく。
Next, processing in each step will be described in detail.
(1) Road Information Acquisition and Width Increment Calculation Processing The road information acquisition module 112 uses the “road number” or “road name” and “type = current” of the planned road designated as the survey target as road information attributes. The database 210 is searched and the width of the current road is extracted. Subsequently, the road information attribute database 210 is searched using the same “road number” or “road name” and “type = plan” as search keys, and the width of the planned road is extracted. Then, the width increment calculation module 111 calculates the width increment expanded from each width. The calculation is
Width increase = Plan road width-Current road width (1)
Do by. For example, in the case of “C hill line” in FIG. 5, the width increase is 30−19 = 11 m. The road information acquisition module 112 searches the road / land information map database 220 to acquire a road / land information map related to the planned road to be investigated.

(2)登記所地図情報取得と対象筆検索処理
登記所関連情報取得モジュール114は、登記所地図データベース310を検索し、調査対象の計画道路に関連する登記所地図を取得する。(1)道路情報取得処理で取得した道路・土地情報地図は、図6に示したように住居表示であるが、登記所地図は図7に示したように地番表示であるため、重ね合わせ処理を行う。重ね合わせ処理では、双方の地図上で、明らかに同じ場所と認識できる筆界点を基準点として複数指定する。たとえば、道路交差点などが基準点として指定される。そして、基準点に基づき、どちらかの地図の座標値を補正し、登記所地図と道路・土地情報地図を重ね合わせる。
(2) Registry Map Information Acquisition and Target Brush Search Process The registry related information acquisition module 114 searches the registry map database 310 and acquires a registry map related to the planned road to be investigated. (1) Although the road / land information map acquired in the road information acquisition process is a residence display as shown in FIG. 6, the registration map is a lot number display as shown in FIG. I do. In the superimposition processing, a plurality of brush boundary points that can be clearly recognized as the same place on both maps are designated as a reference point. For example, a road intersection is designated as the reference point. Then, based on the reference point, the coordinate value of either map is corrected, and the registry map and the road / land information map are superimposed.

図17は、本実施の形態の対象筆検索における道路・土地情報地図と登記所地図との重ね合わせ処理を示した図である。
調査対象の道路に係る道路情報属性データと道路・土地情報地図データから、道路・土地情報地図601上の現状道路601aの境界線を幅員増分601bずらすことにより、計画道路601cの図形を特定することができる。道路・土地情報地図601と登記所地図602とは、上記の重ね合わせが行われており、たとえば、登記所地図602の地番10の筆図形を特定する点T1、T2、T3、T4と、道路・土地情報地図601上の区分U1、U2、U3、U4とが一致する。これにより、道路・土地情報地図601上の計画道路図形を登記所地図602に反映させることができる。
FIG. 17 is a diagram showing an overlay process of the road / land information map and the registry map in the target brush search according to the present embodiment.
The figure of the planned road 601c is specified by shifting the boundary line of the current road 601a on the road / land information map 601 by the width increment 601b from the road information attribute data and road / land information map data relating to the road to be investigated. Can do. The road / land information map 601 and the registry map 602 are overlaid as described above. For example, the points T1, T2, T3, T4 that specify the brush figure of the lot number 10 of the registry map 602, and the road -The divisions U1, U2, U3, U4 on the land information map 601 match. Thereby, the planned road figure on the road / land information map 601 can be reflected in the registry map 602.

図18は、本実施の形態の計画道路が反映された登記所地図を示した図である。登記所地図と道路・土地情報地図を重ね合わせた地図(以下、重ね合わせ地図とする)603には、登記所地図602に、筆界線TaTcと、筆界線TbTdとによって表される計画道路が描画される。   FIG. 18 is a diagram showing a registry office map in which the planned road of the present embodiment is reflected. In a map (hereinafter referred to as an overlay map) 603 in which a registry map and a road / land information map are superimposed, a planned road represented by a brush border line TaTc and a brush border line TbTd is drawn on the registry map 602. Is done.

以下、対象筆検索モジュール113は、重ね合わせ地図603に基づき、計画道路に係る筆を検索する。まず、重ね合わせ地図603の現状道路図形に接面するすべての筆を抽出する。すなわち、現状道路図形と同じ筆界線を一部でも共有する筆図形を検索する。図の例では、筆界線T5T1を共有する地番6、筆界線T1T2を共有する地番10、筆界線T2T7を共有する地番8、筆界線T14T10を共有する地番9、筆界線T10T11を共有する地番7、および筆界線T11T21を共有する地番11が検索される。検索された筆図形の地番は、対象筆管理ワークテーブルに格納する。なお、この処理は、登記所地図を取得した時点で行われてもよい。そして、検索された筆ごとに、接面する筆の境界線と平行する計画道路の筆界線TaTcとTbTdのうち、分筆線になる筆界線を特定する。ここでは、筆を構成する筆界線と交点を持つほうの筆界線を検索する。たとえば、筆界線TbTdは、地番10の筆界線T1T4や、T2T3と交点を持つため、地番10の分筆線になる筆界線である。一方、筆界線TaTcは、地番10のすべての筆界線と交点を持たないため、地番10の分筆線にはならない。   Hereinafter, the target brush search module 113 searches for a brush related to the planned road based on the overlay map 603. First, all the brushes that touch the current road graphic of the overlay map 603 are extracted. That is, a brush figure that shares at least part of the same brush stroke as the current road figure is searched. In the example of the figure, a lot number 6 sharing the writing boundary line T5T1, a lot number 10 sharing the writing boundary line T1T2, a lot number 8 sharing the writing boundary line T2T7, a lot number 9 sharing the writing boundary line T14T10, and a lot number sharing the writing boundary line T10T11. And the lot number 11 which shares the brush stroke line T11T21 is searched. The lot number of the searched brush figure is stored in the target brush management work table. This process may be performed when the registry map is acquired. Then, for each retrieved brush, the stroke line that becomes the dividing line is specified from the stroke boundaries TaTc and TbTd of the planned road parallel to the boundary line of the brush that touches. In this case, the one that has an intersection with the brush border constituting the brush is searched. For example, the writing boundary line TbTd is a writing boundary line that becomes the dividing line of the lot number 10, since it has an intersection with the writing line T1T4 of the lot number 10 and T2T3. On the other hand, the writing line TaTc does not have an intersection with all the writing lines of the lot number 10, and therefore, does not become the dividing line of the lot number 10.

次に、筆界線の移動距離、すなわち、分筆線となる筆界線TaTcまたはTbTdと現状道路と共有される筆の筆界線との距離を算出する。この際、重ね合わせ地図603上で描画した計画道路図形が、道路情報属性データより得られる実際の計画に基づく幅員増分と一致しない場合が考えられるので、図面上の計画道路図形を実際の計画値に合うように補正する。まず、道路の片側に接面するすべての筆に対して接面する境界線と上記処理によって分筆線と特定された筆界線との距離、すなわち幅員増分を算出し、平均値を出す。たとえば、地番6、地番10および地番8における幅員増分を算出し、平均値を出す。それぞれの幅員増分は、たとえば、筆界線TbTdと筆界線T1T4の交点と、T1の間の距離を算出することによって得られる。もう一方(地番9、地番7、地番11)についても同様に、幅員増分の平均値を算出する。そして、筆界線TaTcについて算出された幅員増分の平均値と、筆界線TbTdについて算出された幅員増分の平均値とを合算し、道路情報属性データより得られた幅員増分と比較する。一致しない場合は、道路情報属性データより得られた幅員増分となるように、幅員増分の平均値を補正する。   Next, the movement distance of the brush boundary line, that is, the distance between the brush boundary line TaTc or TbTd serving as the dividing line and the brush boundary line shared with the current road is calculated. At this time, the planned road graphic drawn on the overlay map 603 may not match the width increment based on the actual plan obtained from the road information attribute data. Correct to fit. First, the distance between the boundary line that is in contact with all the brushes that are in contact with one side of the road and the stroke line identified by the above processing, that is, the width increment, is calculated, and the average value is calculated. For example, the width increments at lot number 6, lot number 10 and lot number 8 are calculated, and an average value is obtained. Each width increment is obtained by, for example, calculating the distance between the intersection point of the writing line TbTd and the writing line T1T4 and T1. Similarly, the average value of the width increment is calculated for the other (lot number 9, lot number 7, lot number 11). And the average value of the width | variety increment calculated about the stroke line TaTc and the average value of the width | variety increment calculated about the brush stroke line TbTd are added together, and it compares with the width | variety increment obtained from road information attribute data. If they do not match, the average value of the width increment is corrected so as to be the width increment obtained from the road information attribute data.

たとえば、図面より得られる筆界線TaTcに係る幅員増分の平均値が12m、筆界線TbTdに係る幅員増分の平均値が10mになり、計画値が11mであったとする。図面上の幅員増分の合計は、11mとならないため、補正を行う。   For example, it is assumed that the average value of the width increment related to the border line TaTc obtained from the drawing is 12 m, the average value of the width increment related to the brush line TbTd is 10 m, and the planned value is 11 m. The total width increment on the drawing is not 11 m, so correction is performed.

TaTcに係る幅員増分= 12m×11m/22m =6m、
TbTdに係る幅員増分= 10m×11m/22m =5m ・・・(2)
と算出することができる。補正された幅員増分に基づき、計画道路の筆界線TaTcとTbTdを修正する。
Width increment related to TaTc = 12 m × 11 m / 22 m = 6 m
Width increment related to TbTd = 10 m × 11 m / 22 m = 5 m (2)
Can be calculated. Based on the corrected width increment, the stroke boundaries TaTc and TbTd of the planned road are corrected.

さらに、現状道路に接面していないが、道路が拡張することにより影響を受ける筆を抽出する。式(2)によって修正された計画道路の筆界線TaTcおよびTbTdと、現状道路の筆界線との間に含まれる筆をすべて抽出する。抽出した筆の地番は、対象筆管理ワークテーブルの地番117aに格納する。また、修正後の筆界線を分筆線とする筆の筆界線と分筆線間の距離を算出し、対象筆管理ワークテーブルの筆界線移動距離117bに格納する。このとき、現状道路に接面するとして既に抽出された筆図形は、を対象筆管理ワークテーブルの地番117aに検索された地番を上書きし、式(2)により得られた該当の幅員増分値を筆界線移動距離117bに格納する。   Furthermore, a brush that is not in contact with the current road but is affected by the expansion of the road is extracted. All brushstrokes included between the stroke boundaries TaTc and TbTd of the planned road corrected by Expression (2) and the stroke boundaries of the current road are extracted. The extracted brush lot number is stored in the lot number 117a of the target brush management work table. In addition, the distance between the brush stroke line and the stroke line of the brush with the corrected brush stroke line as the split stroke line is calculated and stored in the brush stroke moving distance 117b of the target brush management work table. At this time, the brush graphic already extracted as being in contact with the current road overwrites the searched lot number in the lot number 117a of the target brush management work table, and the corresponding width increment value obtained by Expression (2) is used. Stored in the brush stroke moving distance 117b.

(3)分筆処理と建ぺい率・容積率算出処理
対象筆管理ワークテーブルに格納されたすべての筆について、順次、以下の処理を行う。まず、建ぺい率・容積率算出モジュール115は、分筆モジュール116を起動し、分筆処理を行う。分筆モジュール116は、登記所関連情報取得モジュール114によって、それぞれの地番117aを読み出し、その地番に基づいて地積測量図データベース320を検索し、該当する地積測量図を抽出する。そして、地積測量図図形上に、現状道路の筆界線を描画し、その筆界線を対象筆管理ワークテーブルの筆界線移動距離117b分だけ道路とは反対方向に平行移動し、新たな分筆線を作成する。
(3) Separation processing and building coverage ratio / volume ratio calculation processing The following processing is sequentially performed for all brushes stored in the target brush management work table. First, the building coverage ratio / volume ratio calculation module 115 activates the drawing module 116 to perform a drawing process. The writing module 116 reads each lot number 117a by the registry related information acquisition module 114, searches the lot survey database 320 based on the lot number, and extracts the corresponding lot survey map. Then, the stroke line of the current road is drawn on the land survey map figure, and the stroke line is translated in the direction opposite to the road by the stroke line movement distance 117b of the target brush management work table, and a new stroke line is drawn. create.

一例を挙げて説明する。図19は、本実施の形態における分筆線の設定処理の一例を示した図である。
図の例では、地番10の筆の地積測量図610aが検索されたとする。地番10は、地番Bによって表される現状道路に接面し、筆界線T1T2、T2T3、T3T4およびT4T1によって描画される筆図形を有している。まず、筆界線T1T2と共有される現状道路筆界線(TeTf)611を地積測量図610aに描画する。
An example will be described. FIG. 19 is a diagram showing an example of the setting process of the stroke line in the present embodiment.
In the example shown in the figure, it is assumed that the area survey diagram 610a of the brush of the lot number 10 is retrieved. The lot number 10 is in contact with the current road represented by the lot number B, and has a brush figure drawn by the stroke boundaries T1T2, T2T3, T3T4, and T4T1. First, the current road brush border (TeTf) 611 shared with the brush border T1T2 is drawn on the land survey map 610a.

続く分筆処理では、対象筆管理ワークテーブルから地番10の筆界線移動距離117b、ここでは「5m」を抽出し、現状道路筆界線(TeTf)611を道路とは反対方向に平行移動させた位置に、分筆線(TgTh)612を新たに描画する。これにより、地積測量図610bが作成される。   In the subsequent separation process, the stroke boundary movement distance 117b of the lot number 10 is extracted from the target brush management work table, in this case, "5m", and the current road boundary line (TeTf) 611 is translated to the position opposite to the road. , A new stroke line (TgTh) 612 is drawn. As a result, a land survey map 610b is created.

こうして、分筆処理が行われると、建ぺい率・容積率算出モジュール115は、分筆線(TgTh)612が描画された地積測量図610bに基づき、建ぺい率と容積率を算出する。まず、登記所関連情報取得モジュール114によって、対象筆管理ワークテーブルに格納される地番117aに基づいて建物図面データベース330を検索し、建築面積と延床面積を抽出する。そして、分筆線(TgTh)612で分筆された土地のうち、道路とは反対側の残地613の面積を算出し、抽出された建築面積と延床面積から建ぺい率と容積率を算出する。なお、建ぺい率と容積率は、
建ぺい率= 建築面積/土地面積、
容積率= 延床面積/土地面積 ・・・(3)
によって算出される。算出された建ぺい率と容積率は、対象筆管理ワークテーブルの該当筆の建ぺい率117cと容積率117dに格納する。
Thus, when the separation process is performed, the building coverage ratio / volume ratio calculation module 115 calculates the building coverage ratio and the volume ratio based on the area survey diagram 610b in which the dividing line (TgTh) 612 is drawn. First, the registry related information acquisition module 114 searches the building drawing database 330 based on the lot number 117a stored in the target brush management work table, and extracts the building area and the total floor area. And the area of the remaining land 613 on the opposite side to the road is calculated from the land divided by the dividing line (TgTh) 612, and the building coverage ratio and the floor area ratio are calculated from the extracted building area and total floor area. The building coverage ratio and floor area ratio are
Coverage ratio = building area / land area,
Floor area ratio = total floor area / land area (3)
Is calculated by The calculated building coverage ratio and floor area ratio are stored in the building coverage ratio 117c and the volume ratio 117d of the corresponding brush in the target brush management work table.

(4)分筆線上の建物検索処理
分筆線上の建物検索モジュール118は、対象筆管理ワークテーブルに格納されたすべての筆について、順次、以下の処理を行う。まず、対象筆管理ワークテーブルの地番117aに基づいて、建物図面データベース330を検索し、対象筆の建物図面を抽出する。また、上記処理によって分筆された該当筆の地積測量図を読み出し、抽出された建物図面の座標を地積測量図に合うように変換した後、建物図形を地積測量図に重畳させる。
(4) Building Search Processing on the Pencil Line The building search module 118 on the pen stroke line sequentially performs the following processing for all the brushes stored in the target brush management work table. First, the building drawing database 330 is searched based on the house number 117a of the target brush management work table, and the building drawing of the target brush is extracted. Further, after reading the area survey map of the corresponding brush divided by the above processing, and converting the coordinates of the extracted building drawing so as to match the area survey map, the building figure is superimposed on the area survey map.

一例を挙げて説明する。図20は、本実施の形態における分筆線上の建物検索処理の一例を示した図である。
図の例では、分筆処理が施された地番10の地積測量図610bに基づき、建物検索処理が行われる。まず、建物図面データベース330を検索し、地番10の建物図面620を抽出する。そして、建物図面620の座標を地積測量図610bに合わせ、地積測量図610bに建物図面620の建物図形を重畳させる。
An example will be described. FIG. 20 is a diagram showing an example of a building search process on the stroke line in the present embodiment.
In the example shown in the figure, the building search process is performed based on the land area survey map 610b of the lot number 10 that has been subjected to the separation process. First, the building drawing database 330 is searched, and the building drawing 620 of the lot number 10 is extracted. Then, the coordinates of the building drawing 620 are aligned with the land surveying map 610b, and the building figure of the building drawing 620 is superimposed on the land surveying map 610b.

こうして作成される地積測量図と建物図形の合成図630によって、分筆線上に建物があるかどうかを判定する。すなわち、分筆線(TgTh)612と、建物図形の交点があるかどうかを調べ、交点が検出された場合には、建物が分筆線上にあると判定する。図の例では、分筆線(TgTh)612上に交点631a、631bが検出されるので、地番10の建物「あいう」は分筆線(TgTh)612上にあると判定される。   It is determined whether or not there is a building on the dividing line based on the composition survey map 630 created in this manner and the composite figure 630 of the building figure. That is, it is checked whether there is an intersection between the stroke line (TgTh) 612 and the building graphic, and if the intersection is detected, it is determined that the building is on the stroke line. In the example shown in the figure, the intersection points 631a and 631b are detected on the dividing line (TgTh) 612, and therefore it is determined that the building “Aoi” of the lot number 10 is on the dividing line (TgTh) 612.

このように、分筆線と建物図形に交点が検出された場合は、対象筆管理ワークテーブルの該当筆の建物解体フラグ117eをオンにする。
(5)補償額算出処理と補償額地図出力処理
対象筆管理ワークテーブルに格納されたすべての筆について、順次、以下の処理を行う。補償額地図出力モジュール119は、補償額算出モジュール120を起動し、対象筆の補償額を算出する。補償額算出モジュール120では、対象筆の地番117aに対応付けられた住居表示情報に基づき、土地・建物関連情報取得モジュール121によって取引価格データベース420を検索し、該当路線の土地の基準価格を取得する。そして、分筆後の地積測量図に基づき、分筆後に道路になる側の筆の土地面積に応じて補償額を算出する。算出した収用地の補償額は、対象筆管理ワークテーブルの該当筆の補償額(土地)117fに格納する。
As described above, when an intersection point is detected between the stroke line and the building graphic, the building disassembly flag 117e of the corresponding brush in the target brush management work table is turned on.
(5) Compensation amount calculation processing and compensation amount map output processing The following processing is sequentially performed for all the brushes stored in the target brush management work table. The compensation amount map output module 119 activates the compensation amount calculation module 120 and calculates the compensation amount of the target brush. The compensation amount calculation module 120 searches the transaction price database 420 by the land / building related information acquisition module 121 based on the housing display information associated with the lot number 117a of the target brush, and acquires the reference price of the land on the corresponding route. . Then, the compensation amount is calculated according to the land area of the brush on the side that becomes the road after the division based on the area survey map after the division. The calculated compensation amount of the land to be collected is stored in the compensation amount (land) 117f of the corresponding brush in the target brush management work table.

次に、これまでの処理で抽出された地番区域に基づき、土地・建物関連情報取得モジュール121によって建ぺい率・容積率基準データベース410を検索し、該当地域の建ぺい率と容積率の基準を取得する。そして、対象筆管理ワークテーブルに格納される対象筆の分筆処理で算出された建ぺい率117cと容積率117dを読み出し、基準と比較する。分筆処理後の建ぺい率と容積率が基準に達していない場合は、建物の解体が必要であるので、対象筆管理ワークテーブルの該当筆の建物解体フラグ117eをオンする。この処理により、分筆後の建物が、建ぺい率・容積率が基準を満たさない場合、または分筆線上に存在する場合に、建物解体フラグ117eがオンになる。補償額算出モジュール120は、建物解体フラグ117eがオンになっている筆について、順に、登記所関連情報取得モジュール114を介して登記データベース340を検索して該当建物の築年数と構造を抽出する。また、建物図面データベース330から該当建物の延床面積を抽出する。さらに、地番区域に基づき、土地・建物関連情報取得モジュール121によって建物価格基準データベース430を検索し、床面積に対する取引価格や築年数に応じた係数などを得る。そして、該当建物に関する延床面積の単位あたりの取引価格(円/m2)、築年数および構造などから、おおよその取引価格(円/m2)を取得し、該当建物の延床面積を乗算することにより、補償額(建物)を算出する。算出した建物の補償額は、対象筆管理ワークテーブルの該当筆の補償額(建物)117gに格納する。さらに、補償額(土地)117fと、補償額(建物)117gの値を加算して合計補償額を算出し、補償額(計)117hに格納する。 Next, the land / building related information acquisition module 121 searches the building coverage ratio / flood ratio reference database 410 based on the lot number area extracted in the above processing, and acquires the building coverage ratio and the floor ratio reference of the corresponding area. Then, the building coverage ratio 117c and the volume ratio 117d calculated in the target brush separation process stored in the target brush management work table are read and compared with the reference. If the building coverage ratio and the floor area ratio after the separation process have not reached the standard, the building must be disassembled, so the building disassembly flag 117e of the corresponding brush in the target brush management work table is turned on. With this process, the building dismantling flag 117e is turned on when the building after partitioning does not satisfy the criteria for the building coverage ratio / volume ratio, or exists on the dividing line. The compensation amount calculation module 120 sequentially searches the registration database 340 via the registry office related information acquisition module 114 for the brush whose building dismantling flag 117e is turned on, and extracts the building age and structure of the building. Further, the total floor area of the building is extracted from the building drawing database 330. Further, based on the lot number area, the building price reference database 430 is searched by the land / building related information acquisition module 121 to obtain a transaction price for the floor area, a coefficient corresponding to the building age, and the like. Then, obtain the approximate transaction price (yen / m 2 ) from the transaction price (yen / m 2 ) per unit of the total floor area for the building, age and structure, and multiply by the total floor area of the building. By doing so, the compensation amount (building) is calculated. The calculated compensation amount of the building is stored in the compensation amount (building) 117g of the corresponding brush in the target brush management work table. Further, the total compensation amount is calculated by adding the compensation amount (land) 117f and the compensation amount (building) 117g, and stored in the compensation amount (total) 117h.

最後に、分筆後の地積測量図に基づき、分筆後に残る側の筆(残地)の土地面積が狭小地であるかどうかの判断を行う。補償額算出モジュール120は、分筆後の地積測量図に基づいて残地の面積を検出し、土地・建物関連情報取得モジュール121を介して読み出した狭小地判断マスタテーブル440に格納される判断基準と照合する。残地が狭小地判断マスタテーブル440の判断面積に該当する場合は、対応する価格低下比率を読み出し、残地補償額を算出する。残地補償額は、
残地補償額= [該当筆(残地)の面積]×[取引価格データベースから検索された取引価格]×[価格低下比率] ・・・(4)
によって算出することができる。算出された残地補償額は、対象筆管理ワークテーブルの残地補償額117iに格納する。
Finally, it is determined whether the land area of the brush (residual land) that remains after the separation is narrow or narrow based on the area survey map after the separation. The compensation amount calculation module 120 detects the area of the remaining land based on the area survey map after the separation, and stores the determination criteria stored in the narrow land determination master table 440 read out via the land / building related information acquisition module 121. Match. When the remaining area corresponds to the determination area of the narrow area determination master table 440, the corresponding price reduction ratio is read and the remaining area compensation amount is calculated. Remaining area compensation amount is
Remaining land compensation amount = [area of applicable brush (remaining land)] x [transaction price retrieved from transaction price database] x [price reduction ratio] (4)
Can be calculated. The calculated residual compensation amount is stored in the residual compensation amount 117i of the target brush management work table.

以上の処理により、すべての筆の補償額が算出される。続いて補償額地図出力モジュール119は、算出された補償額に基づき、補償額地図を作成する。補償額地図は、分筆後の筆界線を示した登記所地図上に、補償額に応じた難易度を示すアイコンを設定して作成する。   Through the above processing, the compensation amount for all brushes is calculated. Subsequently, the compensation amount map output module 119 creates a compensation amount map based on the calculated compensation amount. The compensation amount map is created by setting an icon indicating the degree of difficulty corresponding to the compensation amount on the registry map showing the stroke boundaries after the separation.

一例を挙げて説明する。図21は、本実施の形態の補償額地図の表示例を示した図である。図は、重ね合わせ地図603に基づいて作成されている。
図では、実線で表される筆界線702によって表される計画道路701の道路図形(斜線部)と、2点鎖線によって表された現状道路の筆界線703と、現状道路近辺の地番の筆(地番6、6−1、7、8、9、10、11)が表示されている。なお、筆界線(計画道路)702は、補正が行われた後の筆界線である。
An example will be described. FIG. 21 is a diagram showing a display example of the compensation amount map of the present embodiment. The figure is created based on the overlay map 603.
In the figure, a road figure (shaded portion) of the planned road 701 represented by a brush border 702 represented by a solid line, a brush border 703 of a current road represented by a two-dot chain line, and a brush of a lot number in the vicinity of the current road ( The lot numbers 6, 6-1, 7, 8, 9, 10, 11) are displayed. The stroke line (plan road) 702 is a stroke line after the correction is performed.

このような計画道路による分筆後の登記所地図上の筆ごとに、お金アイコン704、建物解体アイコン705および狭小地アイコン706が設定される。お金アイコン704は、対象筆管理ワークテーブルの補償額(計)117hの金額の大きさに応じて該当する筆の位置に設定されるアイコンで、図の例では、1コインが1000万円を表している。たとえば、地番9は、2000万円、地番7は3000万円の補償額になる。建物解体アイコン705は、対象筆管理ワークテーブルの建物解体フラグ117eがオンの筆に対応する位置に設定される。図の例では、地番10と地番8の筆の建物解体が必要であることがわかる。そして、狭小地アイコン706は、対象筆管理ワークテーブルの残地補償額117iが0でない筆に対応する位置に設定される。図の例では、地番6が狭小地であり、狭小地補償額として1000万円が追加される可能性があることがわかる。   A money icon 704, a building dismantling icon 705, and a narrow land icon 706 are set for each brush on the registry map after dividing by such a planned road. The money icon 704 is an icon set at the position of the corresponding brush according to the amount of compensation amount (total) 117h in the target brush management work table. In the example in the figure, one coin represents 10 million yen. ing. For example, the lot number 9 is 20 million yen, and the lot number 7 is 30 million yen. The building dismantling icon 705 is set at a position corresponding to a brush whose building dismantling flag 117e in the target brush management work table is on. In the example of the figure, it can be seen that the building dismantling of the lot number 10 and the lot number 8 brush is necessary. The narrow land icon 706 is set at a position corresponding to a brush whose remaining area compensation amount 117i of the target brush management work table is not 0. In the example of the figure, it is understood that the lot number 6 is a narrow land, and there is a possibility that 10 million yen may be added as the narrow ground compensation amount.

以上のように、本発明の実施の形態では、住居表示の道路・土地情報地図に設定される計画道路と、地番表示の登記所地図を重ねあわせて、登記所地図上に計画道路図形を反映させ、対象となる筆を特定する。このとき、登記所地図上に描画された計画道路図形を道路情報属性より得られる実際の計画値に合うように補正する。これは、図面上で描画した計画道路が、実際の計画に基づく幅員増分とずれてしまう場合が考えられるため、図面上の計画道路図形を実際の計画値に合うように補正するものであり、より正確に補償額を見積もることができるようになる。この地図に基づき、対象筆ごとに、分筆線が建物上に引かれていないかどうか、分筆後の建ぺい率・容積率が基準を満たしているかどうか、残地が資産価値が低減される狭小地であるかどうかなど、交渉見込みの難易度に影響する項目をチェックする。建物が分筆線上にある場合、および分筆後の建ぺい率・容積率が基準を満たさない場合は、建物解体などが必要となり、そのための費用を加算して対象筆に対する補償額を算出する。また、残地が狭小地となる場合に、補償額に加算される恐れのある残地補償額も算出しておく。このように、収用地の買収に必要な要素を加味して、その補償額を加算することにより、補償額をより正確に算出することができるようになる。   As described above, in the embodiment of the present invention, the planned road figure is reflected on the registry map by overlapping the planned road set in the road / land information map with the residence display and the registry map with the lot number display. And specify the target brush. At this time, the planned road figure drawn on the registry map is corrected to match the actual planned value obtained from the road information attribute. This is because the planned road drawn on the drawing may deviate from the width increment based on the actual plan, so the planned road figure on the drawing is corrected to match the actual planned value, The amount of compensation can be estimated more accurately. Based on this map, for each target brush, whether or not a pen line is drawn on the building, whether the building coverage and floor area ratio after the pen meets the standard, and the remaining land is a narrow area where the asset value is reduced Check items that affect the difficulty of negotiation prospects, such as whether or not there is. If the building is on the dividing line, and if the building coverage ratio and floor area ratio after dividing the line do not meet the standards, the building must be dismantled, and the cost for that is added to calculate the compensation amount for the target brush. In addition, when the remaining area is narrow, a remaining area compensation amount that may be added to the compensation amount is calculated. In this way, the compensation amount can be calculated more accurately by adding the compensation amount in consideration of the elements necessary for the acquisition of the land for acquisition.

また、補償額に応じた交渉見込みの難易度をアイコンによって表し、このアイコンを計画道路が描画される補償額地図上の筆に対応して表示させるので、補償額見込みの大きさを正確かつ容易に把握することができるとともに、これに応じて買収期間の予測精度も向上する。   In addition, the degree of difficulty of the negotiation estimate according to the compensation amount is indicated by an icon, and this icon is displayed corresponding to the brush on the compensation amount map on which the planned road is drawn, so the size of the compensation amount estimate is accurate and easy As a result, the forecast accuracy of the acquisition period will be improved accordingly.

たとえば、図21の場合、お金アイコン704によって、おおよその補償額の大きさを容易に把握することができる。また、建物解体アイコン705によって、建物解体が必要となるため補償額が大きくなる筆や、狭小地アイコン706も把握することができる。このように、交渉見込みに影響を与える要素が視覚的に表示されるため、交渉期間の予測も容易に行うことができるようになる。   For example, in the case of FIG. 21, the approximate amount of compensation can be easily grasped by the money icon 704. Further, the building demolition icon 705 can also grasp a brush and a narrow ground icon 706 that require a building demolition to increase the compensation amount. In this way, since elements that affect negotiation prospects are visually displayed, it is possible to easily predict the negotiation period.

さらに、補償額地図の出力までの処理を道路計画支援装置が自動で行うことができるため、計画道路の条件を変えて補償額地図をいくつか出力することにより、最適な計画道路を決定することができる。たとえば、図21の例では、地番8および地番10で建物の解体が必要となり、地番6は狭小地となるので、計画道路を狭める、もしくはその位置を地番9、地番7および地番11側にずらした場合の補償額地図を作成し、当初の補償額地図と比較検討することができる。計画道路の位置をずらすことにより、地番10および地番8の建物解体が必要なくなれば、補償の総額を減らすことができる。   Furthermore, since the road planning support device can automatically perform processing up to the output of the compensation amount map, the optimum planned road can be determined by outputting several compensation amount maps by changing the conditions of the planned road. Can do. For example, in the example of FIG. 21, the dismantling of the building is required at the lot number 8 and the lot number 10, and the lot number 6 is a narrow land, so the planned road is narrowed or the position is shifted to the lot numbers 9, 7, and 11 side. A compensation amount map can be created and compared with the initial compensation amount map. By shifting the location of the planned road, the total amount of compensation can be reduced if the dismantling of the lot numbers 10 and 8 is not necessary.

なお、上記の処理機能は、コンピュータによって実現することができる。その場合、道路計画支援装置が有すべき機能の処理内容を記述したプログラムが提供される。そのプログラムをコンピュータで実行することにより、上記処理機能がコンピュータ上で実現される。処理内容を記述したプログラムは、コンピュータで読み取り可能な記録媒体に記録しておくことができる。コンピュータで読み取り可能な記録媒体としては、磁気記録装置、光ディスク、光磁気記録媒体、半導体メモリなどがある。磁気記録装置には、ハードディスク装置(HDD)、フレキシブルディスク(FD)、磁気テープなどがある。光ディスクには、DVD(Digital Versatile Disc)、DVD−RAM(Random Access Memory)、CD−ROM(Compact Disc Read Only Memory)、CD−R(Recordable)/RW(ReWritable)などがある。光磁気記録媒体には、MO(Magneto-Optical disk)などがある。   The above processing functions can be realized by a computer. In that case, a program describing the processing contents of the functions that the road planning support apparatus should have is provided. By executing the program on a computer, the above processing functions are realized on the computer. The program describing the processing contents can be recorded on a computer-readable recording medium. Examples of the computer-readable recording medium include a magnetic recording device, an optical disk, a magneto-optical recording medium, and a semiconductor memory. Examples of the magnetic recording device include a hard disk device (HDD), a flexible disk (FD), and a magnetic tape. Examples of the optical disc include a DVD (Digital Versatile Disc), a DVD-RAM (Random Access Memory), a CD-ROM (Compact Disc Read Only Memory), and a CD-R (Recordable) / RW (ReWritable). Magneto-optical recording media include MO (Magneto-Optical disk).

プログラムを流通させる場合には、たとえば、そのプログラムが記録されたDVD、CD−ROMなどの可搬型記録媒体が販売される。また、プログラムをサーバコンピュータの記憶装置に格納しておき、ネットワークを介して、サーバコンピュータから他のコンピュータにそのプログラムを転送することもできる。   When distributing the program, for example, portable recording media such as a DVD and a CD-ROM in which the program is recorded are sold. It is also possible to store the program in a storage device of a server computer and transfer the program from the server computer to another computer via a network.

プログラムを実行するコンピュータは、たとえば、可搬型記録媒体に記録されたプログラムもしくはサーバコンピュータから転送されたプログラムを、自己の記憶装置に格納する。そして、コンピュータは、自己の記憶装置からプログラムを読み取り、プログラムに従った処理を実行する。なお、コンピュータは、可搬型記録媒体から直接プログラムを読み取り、そのプログラムに従った処理を実行することもできる。また、コンピュータは、サーバコンピュータからプログラムが転送されるごとに、逐次、受け取ったプログラムに従った処理を実行することもできる。   The computer that executes the program stores, for example, the program recorded on the portable recording medium or the program transferred from the server computer in its own storage device. Then, the computer reads the program from its own storage device and executes processing according to the program. The computer can also read the program directly from the portable recording medium and execute processing according to the program. Further, each time the program is transferred from the server computer, the computer can sequentially execute processing according to the received program.

(付記1) 計画道路に係る土地の収用に関する交渉見込みの算出を支援する道路計画支援プログラムにおいて、
コンピュータを、
対象の計画道路に関する道路地図を含む道路関連情報を取得する道路情報取得手段、
登記所が管理する登記所地図と、前記道路地図とを重ね合わせ、前記道路地図上の計画道路図形を前記登記所地図の対応位置に反映し、前記計画道路図形に少なくとも一部が重なる対象筆を検索する対象筆検索手段、
前記対象筆を前記計画道路図形に応じて分筆するとともに、分筆を行った場合の建物解体の要否を判定し、筆管理情報として筆管理情報記憶手段に格納する分筆手段、
前記筆管理情報に基づき、土地・建物取引価格を含む前記対象筆の属する地域の土地・建物関連情報を参照して、建物解体を行った場合を含む前記対象筆の補償額を算出する補償額算出手段、
分筆後の筆界線を示す地図上に前記補償額に応じた交渉見込みの難易度表示を重ね、交渉見込み地図として出力する交渉見込み出力手段、
として機能させることを特徴とする道路計画支援プログラム。
(Supplementary note 1) In the road planning support program that supports the calculation of negotiation prospects for land acquisition related to the planned road,
Computer
Road information acquisition means for acquiring road-related information including a road map relating to the target planned road;
A target brush that overlaps the road map with the registry map managed by the registry office, reflects the planned road graphic on the road map to the corresponding position of the registry map, and at least partially overlaps the planned road graphic Object brush search means to search,
While dividing the target brush according to the planned road figure, determining whether or not the building must be dismantled when it is divided, and storing the brush management information in the brush management information storage means,
Based on the brush management information, the compensation amount for calculating the compensation amount of the target brush including the case where the building was demolished with reference to the land / building related information of the area to which the target brush belongs including the land / building transaction price Calculation means,
Negotiation prospect output means for displaying the negotiation prospect difficulty level according to the compensation amount on the map showing the stroke boundary line after the division and outputting as a negotiation prospect map,
Road planning support program characterized by functioning as

(付記2) 前記分筆手段では、前記コンピュータを、
前記対象筆の地積測量図に前記計画道路図形に応じた分筆線を描画して収用部分を除く残地面積を算出するとともに、前記対象筆の建物図面情報から建物の建築面積と延床面積を取得し、前記残地面積、前記建築面性および前記延床面積から前記対象筆を分筆した後の建ぺい率と容積率を算出する建ぺい率・容積率算出手段、
前記対象筆の地域に設定される建ぺい率・容積率を取得し、取得した前記建ぺい率・容積率を基準として分筆後の前記建ぺい率・容積率が基準に適合していない場合には、建物解体が必要であることを前記筆管理情報に設定する基準適合判定手段、
前記建物図面情報に基づき、前記分筆線上に建物が存在する場合には建物解体が必要であることを前記筆管理情報に設定する分筆線上建物検索手段、
として機能させることを特徴とする付記1記載の道路計画支援プログラム。
(Supplementary Note 2) In the above-mentioned dividing means, the computer is
The remaining area excluding the expropriated portion is calculated by drawing a dividing line corresponding to the planned road figure on the area survey map of the target brush, and the building area and the total floor area of the building are calculated from the building drawing information of the target brush. A building coverage ratio / volume ratio calculating means for obtaining and calculating a building coverage ratio and a floor area ratio after dividing the target brush from the remaining area, the building surface property and the total floor area;
The building coverage ratio / floor ratio set for the area of the target brush is acquired, and if the building coverage ratio / floor ratio after separation is not based on the acquired building coverage ratio / floor ratio, building dismantling is required. A standard conformity determination means for setting the brush management information to be,
Based on the building drawing information, if there is a building on the dividing line, the building management unit on the dividing line that sets in the brush management information that building dismantling is necessary,
The road planning support program according to appendix 1, wherein the road planning support program is made to function as:

(付記3) 前記道路情報取得手段では、前記計画道路が予定される現時の道路状況を示す現状道路と前記計画道路を比較し、前記計画道路によって増分される幅員増分を算出し、
前記対象筆検索手段では、前記登記所地図上に反映された前記計画道路の筆界線と、前記登記所地図上の前記現状道路の筆界線との間の距離の平均値を算出し、前記幅員増分に応じて前記計画道路の筆界線の位置を補正する、
ことを特徴とする付記1記載の道路計画支援プログラム。
(Additional remark 3) In the said road information acquisition means, the present road which shows the present road condition where the said planned road is planned, and the said planned road are compared, The width increment incremented by the said planned road is calculated,
In the target brush search means, an average value of a distance between a stroke boundary line of the planned road reflected on the registry map and a stroke boundary line of the current road on the registry map is calculated, and the width Correct the position of the stroke line of the planned road according to the increment;
The road planning support program according to supplementary note 1, characterized by that.

(付記4) 前記対象筆検索手段では、前記計画道路が予定される現時の現状道路に接面し、前記現状道路と筆界線を共有する筆と、筆図形の筆界線が前記現状道路の筆界線と前記計画道路の筆界線との間にある筆と、を前記対象筆として特定する、
ことを特徴とする付記1記載の道路計画支援プログラム。
(Additional remark 4) In the said target brush search means, the brush which touches the present present road where the said planned road is planned, and shares a brush border with the said present road, and the brush border of a brush figure are the brushes of the said current road A brush located between a border line and a brush border of the planned road is identified as the target brush;
The road planning support program according to supplementary note 1, characterized by that.

(付記5) 前記交渉見込み出力手段では、
前記筆管理情報に基づき、前記補償額の大きさ、前記建物解体の要否を含む前記交渉見込みの難易度を規定する要素を表すアイコンを前記交渉見込み地図上の対応する前記対象筆位置に設定させる、
ことを特徴とする付記1記載の道路計画支援プログラム。
(Supplementary Note 5) In the negotiation prospect output means,
Based on the brush management information, an icon representing an element that defines the degree of difficulty of the negotiation prospect including the size of the compensation amount and the necessity of the building dismantling is set to the corresponding target brush position on the negotiation prospect map. Let
The road planning support program according to supplementary note 1, characterized by that.

(付記6) 前記補償額算出手段では、
前記対象筆を分筆した後の残地の筆の面積を算出し、前記残地の筆の面積が予め決められた狭小地に該当する場合には、前記狭小地の面積に応じた残地補償額を算出する、
ことを特徴とする付記1記載の道路計画支援プログラム。
(Supplementary Note 6) In the compensation amount calculation means,
Calculate the area of the remaining brush after dividing the target brush, and if the area of the remaining brush corresponds to a predetermined narrow area, the residual area compensation according to the area of the narrow area Calculate the amount,
The road planning support program according to supplementary note 1, characterized by that.

(付記7) 前記交渉見込み出力手段では、
残地が前記狭小地である場合には、前記狭小地を表すアイコンを前記交渉見込み地図上の対応する前記対象筆位置に設定させる、
ことを特徴とする付記7記載の道路計画支援プログラム。
(Appendix 7) In the negotiation prospect output means,
If the remaining land is the narrow land, the icon representing the narrow land is set to the corresponding target brush position on the negotiation prospect map,
The road planning support program according to appendix 7, characterized in that

(付記8) 計画道路に係る土地の収用に関する交渉見込みの算出を支援する道路計画支援装置において、
対象の計画道路に関する道路地図を含む道路関連情報を取得する道路情報取得手段と、
登記所が管理する登記所地図と、前記道路地図とを重ね合わせ、前記道路地図上の計画道路図形を前記登記所地図の対応位置に反映し、前記計画道路図形に少なくとも一部が重なる対象筆を検索する対象筆検索手段と、
前記対象筆に関する分筆情報、補償額および建物解体の有無を含む前記対象筆の筆管理情報を記憶する筆管理情報記憶手段と、
前記対象筆を前記計画道路図形に応じて分筆するとともに、分筆を行った場合の建物解体の要否を判定し、前記筆管理情報に設定する分筆手段と、
前記筆管理情報に基づき、土地・建物取引価格を含む前記対象筆の属する地域の土地・建物関連情報を参照して、建物解体を行った場合を含む前記対象筆の補償額を算出し、前記筆管理情報に設定する補償額算出手段と、
分筆後の筆界線を示す地図上に前記補償額に応じた交渉見込みの難易度表示を重ね、交渉見込み地図として出力する交渉見込み出力手段と、
を具備することを特徴とする道路計画支援装置。
(Supplementary Note 8) In a road planning support device that supports calculation of negotiation prospects regarding land acquisition related to a planned road,
Road information acquisition means for acquiring road related information including a road map relating to the target planned road;
A target brush that overlaps the road map with the registry map managed by the registry office, reflects the planned road graphic on the road map to the corresponding position of the registry map, and at least partially overlaps the planned road graphic An object brush search means for searching for,
Brush management information storage means for storing the brush management information of the target brush including the separation information on the target brush, the compensation amount, and the presence or absence of building dismantling,
While dividing the target brush according to the planned road figure, determining whether or not the building must be dismantled when the pen is drawn, and a writing means for setting the brush management information;
Based on the brush management information, with reference to the land / building related information of the area to which the target brush belongs, including the land / building transaction price, calculate the compensation amount of the target brush including the case of building demolition, Compensation amount calculation means set in the brush management information;
Negotiation prospect output means for overlaying the difficulty level of the negotiation prospect according to the compensation amount on the map showing the stroke line after the separation, and outputting as a negotiation prospect map;
A road planning support apparatus comprising:

実施の形態に適用される発明の概念図である。It is a conceptual diagram of the invention applied to embodiment. 本発明の実施の形態の道路計画支援装置を含むシステムの構成図である。1 is a configuration diagram of a system including a road planning support apparatus according to an embodiment of the present invention. 本実施の形態の道路計画支援装置のハードウェア構成例を示すブロック図である。It is a block diagram which shows the hardware structural example of the road planning assistance apparatus of this Embodiment. 本実施の形態の道路計画支援装置のソフトウェア構成を示すブロック図である。It is a block diagram which shows the software structure of the road planning assistance apparatus of this Embodiment. 本実施の形態の道路情報属性データベースの構成を示した図である。It is the figure which showed the structure of the road information attribute database of this Embodiment. 本実施の形態の道路・土地情報地図データベースの構成を示した図である。It is the figure which showed the structure of the road and land information map database of this Embodiment. 本実施の形態の登記所地図データベースの構成を示した図である。It is the figure which showed the structure of the registry map database of this Embodiment. 本実施の形態の地積測量図データベースの構成を示した図である。It is the figure which showed the structure of the land survey map database of this Embodiment. 本実施の形態の建物図面データベースの構成を示した図である。It is the figure which showed the structure of the building drawing database of this Embodiment. 本実施の形態の登記データベースの構成を示した図である。It is the figure which showed the structure of the registration database of this Embodiment. 本実施の形態の建ぺい率・容積率基準データベースの構成を示した図である。It is the figure which showed the structure of the building coverage ratio / volume ratio reference | standard database of this Embodiment. 本実施の形態の取引価格データベースの構成を示した図である。It is the figure which showed the structure of the transaction price database of this Embodiment. 本実施の形態の建物価格基準データベースの構成を示した図である。It is the figure which showed the structure of the building price reference | standard database of this Embodiment. 本実施の形態の狭小地判断マスタテーブルの構成を示した図である。It is the figure which showed the structure of the narrow land determination master table of this Embodiment. 本実施の形態の対象筆管理ワークテーブルの構成を示した図である。It is the figure which showed the structure of the object brush management work table of this Embodiment. 本実施の形態の道路支援装置の処理手順を示したフローチャートである。It is the flowchart which showed the process sequence of the road assistance apparatus of this Embodiment. 本実施の形態の対象筆検索における道路・土地情報地図と登記所地図との重ね合わせ処理を示した図である。It is the figure which showed the superimposition process with the road and land information map and registry office map in the object brush search of this Embodiment. 本実施の形態の計画道路が反映された登記所地図を示した図である。It is the figure which showed the registry office map in which the planned road of this Embodiment was reflected. 本実施の形態における分筆線の設定処理の一例を示した図である。It is the figure which showed an example of the setting process of a stroke line in this Embodiment. 本実施の形態における分筆線上の建物検索処理の一例を示した図である。It is the figure which showed an example of the building search process on a dividing line in this Embodiment. 本実施の形態の補償額地図の表示例を示した図である。It is the figure which showed the example of a display of the compensation amount map of this Embodiment.

符号の説明Explanation of symbols

1 道路計画支援装置
1a 道路情報取得手段
1b 対象筆検索手段
1c 分筆手段
1d 補償額算出手段
1e 交渉見込み出力手段
1f 筆管理情報(記憶手段)
2a 道路関連情報(記憶手段)
2b 登記所関連情報(記憶手段)
2c 土地・建物関連情報(記憶手段)
DESCRIPTION OF SYMBOLS 1 Road planning support apparatus 1a Road information acquisition means 1b Target brush search means 1c Separation means 1d Compensation amount calculation means 1e Negotiation prospect output means 1f Brush management information (storage means)
2a Road-related information (memory means)
2b Registry office related information (memory means)
2c Land / building related information (memory)

Claims (5)

計画道路に係る土地の収用に関する交渉見込みの算出を支援する道路計画支援プログラムにおいて、
コンピュータを、
対象の計画道路に関する道路地図を含む道路関連情報を取得する道路情報取得手段、
登記所が管理する登記所地図と、前記道路地図とを重ね合わせ、前記道路地図上の計画道路図形を前記登記所地図の対応位置に反映し、前記計画道路図形に少なくとも一部が重なる対象筆を検索する対象筆検索手段、
前記対象筆を前記計画道路図形に応じて分筆するとともに、分筆を行った場合の建物解体の要否を判定し、筆管理情報として筆管理情報記憶手段に格納する分筆手段、
前記筆管理情報に基づき、土地・建物取引価格を含む前記対象筆の属する地域の土地・建物関連情報を参照して、建物解体を行った場合を含む前記対象筆の補償額を算出する補償額算出手段、
分筆後の筆界線を示す地図上に前記補償額に応じた交渉見込みの難易度表示を重ね、交渉見込み地図として出力する交渉見込み出力手段、
として機能させることを特徴とする道路計画支援プログラム。
In the road planning support program that supports the calculation of the negotiation prospects for land acquisition related to the planned road,
Computer
Road information acquisition means for acquiring road-related information including a road map relating to the target planned road;
A target brush that overlaps the road map with the registry map managed by the registry office, reflects the planned road graphic on the road map to the corresponding position of the registry map, and at least partially overlaps the planned road graphic Object brush search means to search,
While dividing the target brush according to the planned road figure, determining whether or not the building must be dismantled when it is divided, and storing the brush management information in the brush management information storage means,
Based on the brush management information, the compensation amount for calculating the compensation amount of the target brush including the case where the building was demolished with reference to the land / building related information of the area to which the target brush belongs including the land / building transaction price Calculation means,
Negotiation prospect output means for displaying the negotiation prospect difficulty level according to the compensation amount on the map showing the stroke boundary line after the division and outputting as a negotiation prospect map,
Road planning support program characterized by functioning as
前記分筆手段では、前記コンピュータを、
前記対象筆の地積測量図に前記計画道路図形に応じた分筆線を描画して収用部分を除く残地面積を算出するとともに、前記対象筆の建物図面情報から建物の建築面積と延床面積を取得し、前記残地面積、前記建築面性および前記延床面積から前記対象筆を分筆した後の建ぺい率と容積率を算出する建ぺい率・容積率算出手段、
前記対象筆の地域に設定される建ぺい率・容積率を取得し、取得した前記建ぺい率・容積率を基準として分筆後の前記建ぺい率・容積率が基準に適合していない場合には、建物解体が必要であることを前記筆管理情報に設定する基準適合判定手段、
前記建物図面情報に基づき、前記分筆線上に建物が存在する場合には建物解体が必要であることを前記筆管理情報に設定する分筆線上建物検索手段、
として機能させることを特徴とする請求項1記載の道路計画支援プログラム。
In the dividing means, the computer is
The remaining area excluding the expropriated portion is calculated by drawing a dividing line corresponding to the planned road figure on the area survey map of the target brush, and the building area and the total floor area of the building are calculated from the building drawing information of the target brush. A building coverage ratio / volume ratio calculating means for obtaining and calculating a building coverage ratio and a floor area ratio after dividing the target brush from the remaining area, the building surface property and the total floor area;
The building coverage ratio / floor ratio set for the area of the target brush is acquired, and if the building coverage ratio / floor ratio after separation is not based on the acquired building coverage ratio / floor ratio, building dismantling is required. A standard conformity determination means for setting the brush management information to be,
Based on the building drawing information, if there is a building on the dividing line, the building management unit on the dividing line that sets in the brush management information that building dismantling is necessary,
The road planning support program according to claim 1, wherein
前記交渉見込み出力手段では、
前記筆管理情報に基づき、前記補償額の大きさ、前記建物解体の要否を含む前記交渉見込みの難易度を規定する要素を表すアイコンを前記交渉見込み地図上の対応する前記対象筆位置に設定させる、
ことを特徴とする請求項1記載の道路計画支援プログラム。
In the negotiation prospect output means,
Based on the brush management information, an icon representing an element that defines the degree of difficulty of the negotiation prospect including the size of the compensation amount and the necessity of the building dismantling is set to the corresponding target brush position on the negotiation prospect map. Let
The road planning support program according to claim 1, wherein:
前記補償額算出手段では、
前記対象筆を分筆した後の残地の筆の面積を算出し、前記残地の筆の面積が予め決められた狭小地に該当する場合には、前記狭小地の面積に応じた残地補償額を算出する、
ことを特徴とする請求項1記載の道路計画支援プログラム。
In the compensation amount calculating means,
Calculate the area of the remaining brush after dividing the target brush, and if the area of the remaining brush corresponds to a predetermined narrow area, the residual area compensation according to the area of the narrow area Calculate the amount,
The road planning support program according to claim 1, wherein:
計画道路に係る土地の収用に関する交渉見込みの算出を支援する道路計画支援装置において、
対象の計画道路に関する道路地図を含む道路関連情報を取得する道路情報取得手段と、
登記所が管理する登記所地図と、前記道路地図とを重ね合わせ、前記道路地図上の計画道路図形を前記登記所地図の対応位置に反映し、前記計画道路図形に少なくとも一部が重なる対象筆を検索する対象筆検索手段と、
前記対象筆に関する分筆情報、補償額および建物解体の有無を含む前記対象筆の筆管理情報を記憶する筆管理情報記憶手段と、
前記対象筆を前記計画道路図形に応じて分筆するとともに、分筆を行った場合の建物解体の要否を判定し、前記筆管理情報に設定する分筆手段と、
前記筆管理情報に基づき、土地・建物取引価格を含む前記対象筆の属する地域の土地・建物関連情報を参照して、建物解体を行った場合を含む前記対象筆の補償額を算出し、前記筆管理情報に設定する補償額算出手段と、
分筆後の筆界線を示す地図上に前記補償額に応じた交渉見込みの難易度表示を重ね、交渉見込み地図として出力する交渉見込み出力手段と、
を具備することを特徴とする道路計画支援装置。
In a road planning support device that supports the calculation of negotiation prospects for land acquisition related to a planned road,
Road information acquisition means for acquiring road related information including a road map relating to the target planned road;
A target brush that overlaps the road map with the registry map managed by the registry office, reflects the planned road graphic on the road map to the corresponding position of the registry map, and at least partially overlaps the planned road graphic An object brush search means for searching for,
Brush management information storage means for storing the brush management information of the target brush including the separation information on the target brush, the compensation amount, and the presence or absence of building dismantling,
While dividing the target brush according to the planned road figure, determining whether or not the building must be dismantled when the pen is drawn, and a writing means for setting the brush management information;
Based on the brush management information, with reference to the land / building related information of the area to which the target brush belongs, including the land / building transaction price, calculate the compensation amount of the target brush including the case of building demolition, Compensation amount calculation means set in the brush management information;
Negotiation prospect output means for overlaying the difficulty level of the negotiation prospect according to the compensation amount on the map showing the stroke line after the separation, and outputting as a negotiation prospect map;
A road planning support apparatus comprising:
JP2005277488A 2005-09-26 2005-09-26 Road planning support program and road planning support device Expired - Fee Related JP4972898B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005277488A JP4972898B2 (en) 2005-09-26 2005-09-26 Road planning support program and road planning support device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005277488A JP4972898B2 (en) 2005-09-26 2005-09-26 Road planning support program and road planning support device

Publications (2)

Publication Number Publication Date
JP2007087259A true JP2007087259A (en) 2007-04-05
JP4972898B2 JP4972898B2 (en) 2012-07-11

Family

ID=37974161

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005277488A Expired - Fee Related JP4972898B2 (en) 2005-09-26 2005-09-26 Road planning support program and road planning support device

Country Status (1)

Country Link
JP (1) JP4972898B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014026316A (en) * 2012-07-24 2014-02-06 Tamano Consultants Co Ltd Total acquisition cost calculation system of site and site acquisition management support method for site acquisition task
CN111949682A (en) * 2020-07-02 2020-11-17 广州仓实信息科技有限公司 Compensation protocol generation method and device, computer equipment and storage medium

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH042002A (en) * 1990-04-19 1992-01-07 Koito Mfg Co Ltd Head lamp for car
JPH11272746A (en) * 1998-03-18 1999-10-08 Misawa Homes Co Ltd Real property information management system
JP2002140474A (en) * 2000-11-02 2002-05-17 Takaha Toshi Kagaku Kenkyusho:Kk System for supporting automatic estimation of street value and automatic evaluation of lot and automatic interruption in arrangement action of land in urban development business
JP2002318835A (en) * 2001-04-19 2002-10-31 Kansai Electric Power Co Inc:The Cutting plan management system for trees nearby transmission line
JP2003038336A (en) * 2001-07-26 2003-02-12 Sekisui House Ltd Home delivery box
JP2003067539A (en) * 2001-08-27 2003-03-07 Toshiba Corp Site compensation management system and compensation ledger data registration program
JP2003167884A (en) * 2001-11-28 2003-06-13 Jekku:Kk Real estate register information retrieving system for public work projects

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH042002A (en) * 1990-04-19 1992-01-07 Koito Mfg Co Ltd Head lamp for car
JPH11272746A (en) * 1998-03-18 1999-10-08 Misawa Homes Co Ltd Real property information management system
JP2002140474A (en) * 2000-11-02 2002-05-17 Takaha Toshi Kagaku Kenkyusho:Kk System for supporting automatic estimation of street value and automatic evaluation of lot and automatic interruption in arrangement action of land in urban development business
JP2002318835A (en) * 2001-04-19 2002-10-31 Kansai Electric Power Co Inc:The Cutting plan management system for trees nearby transmission line
JP2003038336A (en) * 2001-07-26 2003-02-12 Sekisui House Ltd Home delivery box
JP2003067539A (en) * 2001-08-27 2003-03-07 Toshiba Corp Site compensation management system and compensation ledger data registration program
JP2003167884A (en) * 2001-11-28 2003-06-13 Jekku:Kk Real estate register information retrieving system for public work projects

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014026316A (en) * 2012-07-24 2014-02-06 Tamano Consultants Co Ltd Total acquisition cost calculation system of site and site acquisition management support method for site acquisition task
CN111949682A (en) * 2020-07-02 2020-11-17 广州仓实信息科技有限公司 Compensation protocol generation method and device, computer equipment and storage medium
CN111949682B (en) * 2020-07-02 2024-04-16 广州仓实信息科技有限公司 Compensation protocol generation method, device, computer equipment and storage medium

Also Published As

Publication number Publication date
JP4972898B2 (en) 2012-07-11

Similar Documents

Publication Publication Date Title
Shojaei et al. Visualization requirements for 3D cadastral systems
Bastem et al. Development of historic building information modelling: A systematic literature review
Rajabifard et al. BIM and urban land administration
JP5841934B2 (en) Location-based data service apparatus and method
KR102184048B1 (en) System and method for checking of information about estate development plan based on geographic information system
JP5365254B2 (en) Area check program, area check method and area check apparatus
Aien et al. Utilising data modelling to understand the structure of 3D cadastres
CN113780475B (en) Mountain tunnel model fusion method based on GIS environment
Aringer et al. Bavarian 3D building model and update concept based on LiDAR, image matching and cadastre information
Hagemans et al. The new, LADM inspired, data model of the Dutch cadastral map
JP2004145874A (en) Fixed asset lot measurement/calculation/information management system
KR20100025144A (en) Architectural structure management system based on geographic information system and architecture drawing and method thereof
Sami et al. On the Prospects of Developing Khartoum Sustainable Geospatial System
JP4972898B2 (en) Road planning support program and road planning support device
Kara et al. Requirements and opportunities for web-based 3D visualization and dissemination of property valuation information
Blankenbach et al. Building Information Modelin
Boria et al. A protocol to convert infrastructure data from computer-aided design (CAD) to geographic information systems (GIS)
JP4946095B2 (en) Information processing method and apparatus related to special green space conservation area
JP3673504B2 (en) Geographic information retrieval system and geographic information retrieval program
Brisaboa et al. Collecting and publishing large multiscale geographic datasets
CN112489177A (en) Point cloud data rendering and displaying method and system
Konecny Cadastral mapping with earth observation technology
EP3889859A1 (en) Information processing device, information processing system, and information processing method
Hajji 3D Cadastre for Land Administration: Some issues about the Moroccan context
CN117668993A (en) BIM and GIS-based method and system for positioning route points of bridge full-component

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080619

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110712

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110909

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120313

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120326

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150420

Year of fee payment: 3

LAPS Cancellation because of no payment of annual fees