JP2007082348A - Technique and structure for installing conduit tube in sc wall panel - Google Patents

Technique and structure for installing conduit tube in sc wall panel Download PDF

Info

Publication number
JP2007082348A
JP2007082348A JP2005268398A JP2005268398A JP2007082348A JP 2007082348 A JP2007082348 A JP 2007082348A JP 2005268398 A JP2005268398 A JP 2005268398A JP 2005268398 A JP2005268398 A JP 2005268398A JP 2007082348 A JP2007082348 A JP 2007082348A
Authority
JP
Japan
Prior art keywords
conduit
plate
offset
wall panel
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005268398A
Other languages
Japanese (ja)
Inventor
Kazufumi Terao
和史 寺尾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP2005268398A priority Critical patent/JP2007082348A/en
Publication of JP2007082348A publication Critical patent/JP2007082348A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Installation Of Indoor Wiring (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To improve bending accuracy tolerance for conduit tubes, efficiently install a conduit tube on a SC (Steel Plate-Concrete) wall panel by a simple procedure, and shorten the machining time and the installation time. <P>SOLUTION: The technique for installing conduit tubes in a SC wall panel is a method for installing an conduit tube 2 that penetrates opposite SC wall panels 1 between them. The method includes the steps of forming in each SC wall panel 1 a wide opening 4 whose bore is larger than the outside diameter of the conduit tube 6; fixing a plate 2 for closing each wide opening on each SC wall panel; forming in the plates a conduit tube insertion hole, whose diameter is substantially equal to the outside diameter of the conduit tube; and inserting the conduit tube into the conduit tube insertion holes and fixing it there. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、SC構造の壁内に埋設される電線管をSC鋼板に貫通させて取付固定するSC壁パネル内電線管の取付工法およびSC壁パネル内電線管の取付構造に関する。   The present invention relates to an SC wall panel inner conduit mounting method and an SC wall panel inner conduit mounting structure in which a conduit embedded in an SC structure wall is passed through and fixed to an SC steel plate.

近年、例えば発電プラント建屋の壁構造等に対し、RC(鉄筋コンクリート)構造に代ってSC(鋼板コンクリート)構造の適用が多くなっている。SC壁はスタッドを設けた複数枚の鋼板をスタッド側の面が対向する配置で設置し、各鋼板の間にコンクリートを打設して構成される。   In recent years, for example, an SC (steel concrete) structure has been increasingly applied in place of an RC (steel reinforced concrete) structure for a wall structure of a power plant building or the like. The SC wall is configured by installing a plurality of steel plates provided with studs in such a manner that the surfaces on the stud side face each other, and placing concrete between the steel plates.

このようなSC壁に電線管を取付ける場合、従来では、SC壁を構成する鋼板(以下、「SC壁パネル」という。)の内面に沿ってダクトを配置し、このダクト内に挿通した金属製の電線管の先端に可撓性電線管を接続し、この可撓性電線管をSC壁パネルに形成した貫通孔に通し、パネル外面側の開口部に導く工法が知られている(例えば、特許文献1参照)。   When attaching a conduit to such an SC wall, conventionally, a duct is disposed along the inner surface of a steel plate constituting the SC wall (hereinafter referred to as “SC wall panel”), and a metal made through the duct is inserted. There is known a construction method in which a flexible conduit is connected to the tip of the conduit, the flexible conduit is passed through a through hole formed in the SC wall panel, and led to the opening on the panel outer surface side (for example, Patent Document 1).

また、複数に分割された単位パネルに電線管の接続箱要素を取付けておき、単位パネルを接続する際に接続箱要素を組合せて接続箱を完成させ、接続箱により外部への電線管導出を行う工法も知られている(例えば、特許文献2参照)。   In addition, the connection box element of the conduit is attached to the unit panel divided into a plurality, and the connection box is completed by combining the connection box elements when connecting the unit panel, and the conduit is led out to the outside by the connection box. The construction method to perform is also known (for example, refer patent document 2).

ところで、SC壁内に挿入される金属製の電線管をSC壁パネルに直接貫通させる構成とすれば、比較的簡易な電線管構造となる。この場合、SC壁パネルを対向させてタイバーにより連結しておき、対向したSC壁パネル間にタイバーおよびスタッドを避けて電線管を配置し、この電線管をSC壁パネルに形成した貫通孔に挿通し、電線管の先端に形成したねじにナットを螺合することにより、SC壁パネルを挟み付ける形で固定することが行われる。この場合、従来ではSC壁パネルに形成する電線管挿通用の孔が、略電線管と同一径の孔とされていた。   By the way, if it is set as the structure which penetrates the metal conduit inserted in SC wall directly to SC wall panel, it will become a comparatively simple conduit structure. In this case, the SC wall panels are opposed to each other and connected by a tie bar, and a conduit is disposed between the opposing SC wall panels, avoiding the tie bars and studs, and the conduit is inserted into a through hole formed in the SC wall panel. Then, the SC wall panel is fixed in a sandwiched manner by screwing a nut into a screw formed at the tip of the conduit. In this case, conventionally, the hole for inserting the conduit formed in the SC wall panel has been substantially the same diameter as the conduit.

一般的に、SC壁パネルの組立ては、加工場で行われる。この組立ての際には、電線管の配置および径に対応して、SC壁パネルの表面にケガキが施され、所定の孔あけ加工が行われる。形成される孔の径および配置は、電線管に対応する径および配置に設定される。電線管がZ型等のオフセット電線管である場合には、このオフセット電線管のオフセット量に対応するオフセット寸法でSC壁パネルに電線管挿通用の孔が形成され、これらの孔にオフセット電線管が挿入され、ナット締め等による固定が行われる。
特開2003−328433号公報 特開2002−281639号公報
In general, the assembly of the SC wall panel is performed at a processing site. At the time of this assembly, the surface of the SC wall panel is marked according to the arrangement and diameter of the conduit tube, and a predetermined drilling process is performed. The diameter and arrangement of the holes to be formed are set to the diameter and arrangement corresponding to the conduit. When the conduit is an offset conduit such as a Z shape, holes for inserting the conduit are formed in the SC wall panel with an offset dimension corresponding to the offset amount of the offset conduit, and the offset conduit is formed in these holes. Is inserted and fixed by nut tightening or the like.
JP 2003-328433 A Japanese Patent Laid-Open No. 2002-281539

上述のように、対向する2枚のSC壁パネルに電線管の配置および径に対応してSC壁パネルの表面にケガキを施し、所定の孔あけ加工を行うことには、高精度が要求される。特にオフセット電線管を取付ける場合には、オフセット電線管と略同径の取付け用孔を高精度でオフセット位置に形成しなければならない。これらの孔に電線管を取付ける従来の技術においては、取付け用孔と電線管との取合い精度が厳しい。すなわち、金属製の電線管の曲げ加工を高精度で行うことには困難を伴い、曲げ加工時の弾性による戻り等が生じ、オフセット量が変化する。そして、上記のように鋼製等のSC壁パネルへの孔加工にも極めて高精度の加工が要求される。このため、従来では加工時間および取付け時間が多くなり、ロス工程が増加する等の問題が生じ、これらの問題によりSC壁パネル組立てを採用する高能率工法が十分に活用されていない。   As described above, high precision is required for marking two SC wall panels facing each other on the surface of the SC wall panel in accordance with the arrangement and diameter of the conduit and performing predetermined drilling. The In particular, when installing an offset conduit, a mounting hole having substantially the same diameter as the offset conduit must be formed at an offset position with high accuracy. In the conventional technology for attaching the conduits to these holes, the accuracy of fitting between the mounting holes and the conduits is severe. That is, it is difficult to bend metal metal pipes with high accuracy, and a return due to elasticity at the time of bending occurs, and the offset amount changes. As described above, extremely high-precision machining is also required for drilling holes in SC wall panels made of steel or the like. For this reason, conventionally, problems such as an increase in processing time and attachment time and an increase in the loss process occur, and due to these problems, the high-efficiency construction method employing SC wall panel assembly has not been fully utilized.

本発明はこのような事情に鑑みてなされたもので、電線管の曲げ加工精度の緩和等が図れるとともに、電線管をSC壁パネルに簡便な手順で能率よく取付けることができ、加工時間および取付け時間の短縮が図れ、ひいてはSC壁パネル組立ての採用による高能率工法を有効に活用することができるSC壁パネル内電線管の取付工法を提供することを目的とする。   The present invention has been made in view of such circumstances, and can reduce the bending accuracy of the conduit and can efficiently attach the conduit to the SC wall panel in a simple procedure. An object of the present invention is to provide a method for mounting a conduit in an SC wall panel, which can shorten the time and can effectively utilize the high efficiency method by adopting the SC wall panel assembly.

前記の目的を達成するために、本発明では、対向するSC壁パネル間にこれらを貫通する電線管を取付けるSC壁パネル内電線管の取付工法において、前記各SC壁パネルに前記電線管取付位置を設定して当該位置に前記電線管の外径よりも口径が大きい広口孔を形成する広口孔形成工程と、前記各SC壁パネルの各広口孔位置に当該広口孔を塞ぐプレートを位置決めするプレート位置決め工程と、前記プレートに前記電線管の外径と略等径の電線管挿通孔を形成する電線管挿通孔形成工程と、前記電線管挿通孔に前記電線管を挿通する電線管挿通工程と、前記プレートを前記各SC壁パネルに固定するプレート固定工程と、前記プレートに前記電線管を固定する電線管固定工程とを備えることを特徴とするSC壁パネル内電線管の取付工法を提供する。   In order to achieve the above-mentioned object, in the present invention, in the mounting method of the conduit in the SC wall panel for attaching the conduit passing therethrough between the opposing SC wall panels, the conduit mounting position on each SC wall panel. And a wide hole forming step for forming a wide hole having a larger diameter than the outer diameter of the conduit at the position, and a plate for positioning the plate closing the wide hole at each wide hole position of each SC wall panel A positioning step, a conduit insertion hole forming step for forming a conduit insertion hole of substantially the same diameter as the outer diameter of the conduit on the plate, and a conduit insertion step for inserting the conduit through the conduit insertion hole; A mounting method for a conduit in an SC wall panel, comprising: a plate fixing step for fixing the plate to each SC wall panel; and a conduit fixing step for fixing the conduit to the plate. To provide.

また、本発明では、対向するSC壁パネル間にこれらを貫通するオフセット電線管を取付けるSC壁パネル内電線管の取付工法において、前記各SC壁パネルに前記オフセット電線管取付位置を設定して当該位置に前記オフセット電線管の外径よりも口径が大きい広口孔を形成する広口孔形成工程と、前記各SC壁パネルの各広口孔位置に当該広口孔を塞ぐプレートを位置決めするプレート位置決め工程と、前記プレートに前記オフセット電線管の外径と略等径の電線管挿通孔を形成する電線管挿通孔形成工程と、前記電線管挿通孔に前記オフセット電線管を挿通する電線管挿通工程と、前記プレートを前記各SC壁パネルに固定するプレート固定工程と、前記プレートに前記オフセット電線管を固定する電線管固定工程とを備えることを特徴とするSC壁パネル内電線管の取付工法を提供する。   Further, in the present invention, in the mounting method of the SC wall panel inner conduit for attaching the offset conduit passing therethrough between the opposing SC wall panels, the offset conduit mounting position is set on each SC wall panel A wide hole forming step for forming a wide hole having a larger diameter than the outer diameter of the offset conduit at a position, and a plate positioning step for positioning a plate for closing the wide hole at each wide hole position of each SC wall panel; A conduit insertion hole forming step of forming a conduit insertion hole of substantially the same diameter as the outer diameter of the offset conduit in the plate, a conduit insertion step of inserting the offset conduit into the conduit insertion hole, and A plate fixing step of fixing the plate to each SC wall panel; and a conduit fixing step of fixing the offset conduit to the plate. To provide a mounting method of the SC wall panel conduit to.

また、本発明では、前記広口孔を塞ぐプレートを、前記電線管挿通孔が前記広口孔の範囲内でいずれの位置にずれる場合においても当該広口孔を塞ぐことが可能な面積を有する位置ずれ吸収代をもつ位置調整用大型プレートとする電線管取付工法を提供する。   In the present invention, the plate that closes the wide-mouth hole has a misalignment absorption that has an area that can close the wide-bore hole when the conduit insertion hole is displaced to any position within the wide-hole hole. A conduit mounting method that uses a large plate for position adjustment with a margin is provided.

さらに、本発明では、対向するSC壁パネル間にこれらを貫通するオフセット電線管を取付けるSC壁パネル内オフセット電線管取付構造であって、前記各SC壁パネルには前記オフセット電線管の外径よりも口径が大きい広口孔が前記オフセット電線管のオフセット量に対応する配置で形成されるとともに、前記各SC壁パネルには前記各広口孔を塞ぐプレートが固定されており、かつ前記各プレートには前記オフセット電線管の外径と略等径の電線管挿通孔が形成され、この電線管挿通孔には前記オフセット電線管が挿通して固定されていることを特徴とするSC壁パネル内オフセット電線管取付構造を提供する。   Furthermore, in the present invention, there is an offset conduit mounting structure in an SC wall panel for attaching an offset conduit that passes between the opposing SC wall panels, and each SC wall panel has an outer diameter of the offset conduit. A wide-bore hole having a large diameter is formed in an arrangement corresponding to the offset amount of the offset conduit, and a plate for closing the wide-bore hole is fixed to each SC wall panel. An offset wire in the SC wall panel, wherein a conduit tube insertion hole having an outer diameter substantially equal to the outer diameter of the offset conduit tube is formed, and the offset conduit tube is inserted and fixed in the conduit tube insertion hole. A tube mounting structure is provided.

本発明によれば、オフセット電線管を含む各種電線管をSC壁パネルに簡便な工程で能率よく取付けることができ、加工時間および取付け時間の短縮が図れ、ひいてはSC壁パネル組立ての採用による高能率の工法を有効に活用することができる。   According to the present invention, various conduits including offset conduits can be efficiently attached to the SC wall panel by a simple process, and the processing time and the attachment time can be shortened. As a result, high efficiency is achieved by adopting the SC wall panel assembly. This method can be used effectively.

以下、本発明に係るSC壁パネル内電線管の取付工法の実施形態について、図面を参照して説明する。   Hereinafter, an embodiment of an SC wall panel inner conduit mounting method according to the present invention will be described with reference to the drawings.

[第1実施形態(図1〜図6)]
本実施形態では、SC壁パネルにオフセット電線管を取付けるSC壁パネル内オフセット電線管取付工法について説明する。図1は同工法の手順を示す工程図であり、図2(a1)〜(d)は、取付工程に沿う手順を概略図によって示す工程説明図である。
[First Embodiment (FIGS. 1 to 6)]
In the present embodiment, an offset conduit mounting method in the SC wall panel for attaching the offset conduit to the SC wall panel will be described. FIG. 1 is a process diagram showing the procedure of the construction method, and FIGS. 2A to 2D are process explanatory diagrams schematically showing the procedure along the attachment process.

図1に示すように、本実施形態のSC壁パネル内オフセット電線管取付工法は、(1)電線管の加工を行う電線管加工工程aと、(2)対向するSC壁パネルにオフセット電線管取付位置を設定して当該位置にオフセット電線管の外径よりも口径が大きい広口孔を形成する広口孔形成工程bと、(3)各SC壁パネルの各広口孔位置に当該広口孔を塞ぐプレートを位置決めするプレート位置決め工程cと、(4)プレートにオフセット電線管の外径と略等径の電線管挿通孔を形成する電線管挿通孔形成工程dと、(5)電線管挿通孔にオフセット電線管を挿通する電線管挿通工程eと、(6)プレートを各SC壁パネルに溶接固定するプレート固定工程fと、(7)プレートにオフセット電線管を固定する電線管固定工程gと、(8)各SC壁パネル間にコンクリートを打設するコンクリート打設工程hを備える。以下、各工程a〜hについて詳述する。   As shown in FIG. 1, the SC wall panel offset conduit mounting method of this embodiment includes (1) a conduit processing step a for processing the conduit, and (2) an offset conduit on the opposing SC wall panel. A wide-bore forming step b for setting a mounting position and forming a wide-bore hole having a diameter larger than the outer diameter of the offset conduit at the position; and (3) closing the wide-bore hole at each wide-bore position of each SC wall panel. A plate positioning step c for positioning the plate; (4) a conduit insertion hole forming step d for forming a conduit insertion hole having a diameter substantially equal to the outer diameter of the offset conduit on the plate; and (5) the conduit insertion hole. A conduit insertion step e for inserting the offset conduit, (6) a plate fixing step f for fixing the plate to each SC wall panel by welding, and (7) a conduit fixing step g for fixing the offset conduit to the plate, (8) Each SC It comprises a concreting step h of concrete is between panels. Hereinafter, each process ah is explained in full detail.

(1)電線管加工工程a
電線管加工工程aでは、図2(a1)、(a2)、(a3)に順次に示すように、所定長さの金属製管材、例えば直線型の鋼管材6aをZ形に曲げ加工してオフセット電線管6とし、このオフセット電線管6の両端部にねじ切り加工を施して、両端にねじ部7を有するオフセット電線管6とする。
(1) Conduit processing step a
In the conduit processing step a, as shown in FIGS. 2 (a1), (a2), and (a3) sequentially, a predetermined length of a metal tube, for example, a straight steel tube 6a, is bent into a Z shape. An offset conduit 6 is formed, and both ends of the offset conduit 6 are threaded to form an offset conduit 6 having screw portions 7 at both ends.

(2)広口孔形成工程b
広口孔形成工程bでは、図2(b)に示すように、対向する1対のSC壁パネル1(1a,1b)にオフセット電線管6の外径よりも口径が大きい広口孔4(4a,4b)をオフセット電線管6のオフセット量に対応する配置で形成する。
(2) Wide-mouth hole forming step b
In the wide-mouth hole forming step b, as shown in FIG. 2 (b), a wide-bore hole 4 (4a, 4a, 4b) is formed in an arrangement corresponding to the offset amount of the offset conduit 6.

図3は、この広口孔形成工程bを詳細に示す説明図である。この図3には、事前に施すケガキ線11a,11bと、後の工程で取付けられるオフセット電線管6とが記載されている。図3に示すように、広口孔形成工程bでは、SC鋼壁パネル1aに、後の工程で取付けるオフセット電線管6の取付位置に対応して、縦横のケガキ線11a,11bを記し、これらのケガキ11a,11bの交点を中心として、SC壁パネル1aに例えば円形または楕円形の広口孔4aを形成する。なお、広口孔4aの形状は円、楕円の他、種々の形状とすることができる。また、特に形状を特定しない長孔等としてもよい。   FIG. 3 is an explanatory view showing the wide-mouth hole forming step b in detail. In FIG. 3, marking lines 11a and 11b to be applied in advance and an offset conduit 6 to be attached in a later process are described. As shown in FIG. 3, in the wide-mouth hole forming step b, the vertical and horizontal marking lines 11 a and 11 b are written on the SC steel wall panel 1 a corresponding to the mounting position of the offset conduit 6 to be mounted in a later step. For example, a circular or elliptical wide opening 4a is formed in the SC wall panel 1a with the intersection of the markings 11a and 11b as the center. The wide opening 4a may have various shapes other than a circle and an ellipse. Moreover, it is good also as a long hole etc. which do not specify a shape in particular.

(3)プレート位置決め工程c
プレート位置決め工程cでは、図2(c)に示すように、各SC壁パネル1a,1bに各広口孔4a,4bを塞ぐ位置調整用プレート2(2a,2b)の位置決めをし、仮固定等により取付ける。
(3) Plate positioning step c
In the plate positioning step c, as shown in FIG. 2 (c), the position adjustment plates 2 (2a, 2b) for closing the wide hole holes 4a, 4b in the SC wall panels 1a, 1b are positioned, temporarily fixed, etc. Install by.

図4は、このプレート位置決め工程cを詳細に示す説明図である。この図4には、縦横のケガキ線12a,12bが示されている。これらのケガキ線12a,12bは、広口孔4bを塞ぐ位置に位置調整用プレート2bを配置する基準線である。これらのケガキ線12a,12bに沿い、SC壁パネル1bの表面に、例えば四角形の位置調整用プレート2bが縦横の縁部を沿わせて配置する。この配置により、SC壁パネル1bに形成された広口孔4bが塞がれる。   FIG. 4 is an explanatory view showing the plate positioning step c in detail. FIG. 4 shows vertical and horizontal marking lines 12a and 12b. These marking lines 12a and 12b are reference lines for disposing the position adjusting plate 2b at positions where the wide opening 4b is closed. Along the surface of the SC wall panel 1b along the marking lines 12a and 12b, for example, a rectangular position adjusting plate 2b is arranged along the vertical and horizontal edges. With this arrangement, the wide opening 4b formed in the SC wall panel 1b is closed.

(4)電線管挿通孔形成工程d
電線管挿通孔形成工程dでは、図2(d)に示すように、各プレート2a,2bにオフセット電線管6の外径と略等径の電線管挿通孔5(5a,5b)を形成する。
(4) Conduit insertion hole forming step d
In the conduit insertion hole forming step d, as shown in FIG. 2D, the conduit insertion holes 5 (5a, 5b) having substantially the same diameter as the outer diameter of the offset conduit 6 are formed in the plates 2a, 2b. .

図5は、この電線管挿通孔形成工程dを詳細に示す説明図である。図5に示すように、電線管加工工程aで加工したオフセット電線管6のオフセット量に対応して、ケガキ線12c,12dにより位置調整用プレート孔加工芯13を設定する。この設定した位置調整用プレート孔加工芯13を中心として、位置調整用プレート孔としての電線管挿通孔5bを加工する。   FIG. 5 is an explanatory view showing in detail the conduit insertion hole forming step d. As shown in FIG. 5, the position adjusting plate hole processing core 13 is set by the marking lines 12 c and 12 d corresponding to the offset amount of the offset conduit 6 processed in the conduit processing step a. The conduit insertion hole 5b serving as the position adjusting plate hole is processed around the set position adjusting plate hole processing core 13.

(5)電線管挿通工程e
電線管挿通工程eでは、図2(d)に示すように、プレート2の電線管挿通孔5a,5bにオフセット電線管6を挿通する。
(5) Conduit insertion process e
In the conduit insertion step e, the offset conduit 6 is inserted into the conduit insertion holes 5a and 5b of the plate 2 as shown in FIG.

(6)プレート固定工程f
プレート固定工程fでは、図2(d)に示すように、プレート2bを位置調整してSC壁パネル1bに溶接部3により溶接固定する。この溶接部3としては、例えばプレート2bの周縁を一定の間隔で溶接する部分溶接として施す。
(6) Plate fixing process f
In the plate fixing step f, as shown in FIG. 2D, the position of the plate 2b is adjusted and the SC wall panel 1b is welded and fixed to the SC wall panel 1b. As the welded portion 3, for example, partial welding is performed in which the periphery of the plate 2b is welded at a constant interval.

(7)電線管固定工程g
電線管固定工程gでは、図2(d)に示すように、電線管挿通孔5a,5bに挿通したオフセット電線管6のねじ部7にロックナット8(8a,8b)を螺合してプレートに固定する。
(7) Conduit fixing process g
In the conduit fixing step g, as shown in FIG. 2 (d), the lock nut 8 (8a, 8b) is screwed into the screw portion 7 of the offset conduit 6 inserted into the conduit insertion holes 5a, 5b, and the plate To fix.

図6は、電線管挿通工程e〜電線管固定工程gを詳細に示す説明図である。図6に示すように、位置調整用プレート孔加工芯13を中心として形成された電線管挿通孔5bに、オフセット電線管6を挿通し、オフセット電線管6のねじ部7にロックナット8を螺合して、プレート2の内面、外面または両面に締結固定する。   FIG. 6 is an explanatory diagram showing in detail the conduit insertion step e to the conduit fixing step g. As shown in FIG. 6, the offset conduit 6 is inserted into the conduit insertion hole 5 b formed around the position adjusting plate hole processing core 13, and the lock nut 8 is screwed into the screw portion 7 of the offset conduit 6. Then, the plate 2 is fastened and fixed to the inner surface, the outer surface, or both surfaces of the plate 2.

(8)コンクリート打設工程h
以上の電線管加工工程a〜電線管固定工程gが終了した後に、本実施形態の最終工程として、コンクリート打設工程hを行う。このコンクリート打設工程hにより、オフセット電線管6が各SC壁パネル1a,1b間に完全固定される。
(8) Concrete placing process h
After the above-described conduit processing step a to conduit fixing step g are completed, a concrete placing step h is performed as the final step of the present embodiment. By this concrete placing process h, the offset conduit 6 is completely fixed between the SC wall panels 1a and 1b.

図7は、以上の工程により構成されたSC壁パネル内オフセット電線管取付構造を示している。この図7に示すように、本実施形態のSC壁パネル内オフセット電線管取付構造では、スタッド10が設けられた対向するSC壁パネル1a,1bがタイバー9によって連結されている。各SC壁パネル1a,1bには、オフセット電線管6の外径よりも口径が大きい広口孔4a,4bがオフセット電線管6のオフセット量に対応する配置で形成されている。各SC壁パネル1a,1bには、各広口孔4a,4bを塞ぐプレート2a,2bが溶接部3a,3bにより固定されている。各プレート2a,2bには、オフセット電線管6の外径と略等径の電線管挿通孔5a,5bが形成されている。これらの電線管挿通孔5a,5bには、オフセット電線管6が挿通されており、このオフセット電線管6の両端のねじ部7にロックナット8a,8bが螺合され、オフセット電線管6が固定されている。   FIG. 7 shows the SC wall panel offset conduit mounting structure constituted by the above steps. As shown in FIG. 7, in the SC wall panel offset conduit mounting structure of the present embodiment, opposed SC wall panels 1 a and 1 b provided with studs 10 are connected by tie bars 9. In each SC wall panel 1a, 1b, wide opening holes 4a, 4b having a diameter larger than the outer diameter of the offset conduit 6 are formed in an arrangement corresponding to the offset amount of the offset conduit 6. On each SC wall panel 1a, 1b, plates 2a, 2b for closing the wide opening holes 4a, 4b are fixed by welding portions 3a, 3b. In each of the plates 2a and 2b, conduit insertion holes 5a and 5b having substantially the same diameter as the outer diameter of the offset conduit 6 are formed. The offset conduit 6 is inserted into the conduit insertion holes 5a and 5b, and the lock nuts 8a and 8b are screwed into the screw portions 7 at both ends of the offset conduit 6 so that the offset conduit 6 is fixed. Has been.

以上の第1実施形態によれば、各SC壁パネル1a,1bにオフセット電線管6の径よりも大径な広口孔4a,4bを形成しておき、これらの広口孔4a,4bを位置調整用プレート2a,2bで塞いで位置決めし、この状態で電線管挿通孔5a,5bの形成およびこれらの電線管挿通孔5a,5bへのオフセット電線管6の挿通、各SC壁パネル1a,1bへのプレート2a,2bの溶接固定、およびプレート2a,2bへのオフセット電線管6の締付け固定を行うことにより、従来行われているSC壁パネルの孔へ直接にオフセット電線管を挿通する場合に比べて、曲げ加工精度の緩和等が大幅に図れる。そして、オフセット電線管6をSC壁パネル1a,1bに簡便な手順で能率よく取付けることができ、加工時間および取付け時間の短縮が図れる。したがって、SC壁パネル1a,1bの組立てを採用することによる高能率の工法を有効に活用することができるようになる。   According to the first embodiment described above, the wide opening holes 4a and 4b having a diameter larger than the diameter of the offset conduit 6 are formed in each SC wall panel 1a and 1b, and the positions of the wide opening holes 4a and 4b are adjusted. Are closed by the plates 2a and 2b, and in this state, the formation of the conduit insertion holes 5a and 5b, the insertion of the offset conduit 6 into the conduit insertion holes 5a and 5b, and the SC wall panels 1a and 1b. By fixing the plates 2a and 2b by welding and fastening the offset conduit 6 to the plates 2a and 2b, the offset conduit is directly inserted into the hole of the SC wall panel. As a result, the bending accuracy can be greatly reduced. The offset conduit 6 can be efficiently attached to the SC wall panels 1a and 1b by a simple procedure, and the processing time and the attachment time can be shortened. Therefore, it becomes possible to effectively utilize the highly efficient construction method by adopting the assembly of the SC wall panels 1a and 1b.

[第2実施形態(図8、図1〜図5)]
図8は、本発明の第2実施形態として、SC壁パネル1a,1bに直線型の電線管14を取付けた電線管取付構造を示している。
[Second Embodiment (FIGS. 8 and 1 to 5)]
FIG. 8 shows a conduit mounting structure in which a straight conduit 14 is attached to SC wall panels 1a and 1b as a second embodiment of the present invention.

この図8に示すように、本実施形態のSC壁パネル内直線型の電線管取付構造では,スタッド10が設けられた対向するSC壁パネル1a,1bがタイバー9によって連結されている。各SC壁パネル1a,1bには、直線型の電線管14の外径よりも口径が大きい広口孔4a,4bが対向配置で形成されている。各SC壁パネル1a,1bには、各広口孔4a,4bを塞ぐプレート2a,2bが溶接部3a,3bにより固定されている。各プレート2a,2bには、直線型の電線管14の外径と略等径の電線管挿通孔5a,5bが形成されている。これらの電線管挿通孔5a,5bには、直線型の電線管14が挿通されており、この直線型の電線管14の両端のねじ部7にロックナット8a,8bが螺合され、直線型の電線管14が固定されている。   As shown in FIG. 8, the SC wall panels 1 a and 1 b facing each other provided with the studs 10 are connected by a tie bar 9 in the SC wall panel linear conduit mounting structure of the present embodiment. In each of the SC wall panels 1a and 1b, wide opening holes 4a and 4b having a diameter larger than the outer diameter of the linear conduit 14 are formed so as to face each other. On each SC wall panel 1a, 1b, plates 2a, 2b for closing the wide opening holes 4a, 4b are fixed by welding portions 3a, 3b. In each of the plates 2a and 2b, conduit insertion holes 5a and 5b having substantially the same diameter as the outer diameter of the linear conduit 14 are formed. Straight conduits 14 are inserted into the conduit insertion holes 5a and 5b, and lock nuts 8a and 8b are screwed into the threaded portions 7 at both ends of the straight conduit 14 so that the linear The conduit 14 is fixed.

このような直線型の電線管14をSC壁パネル1a,1bに取付ける場合にも、第1実施形態と略同様の工程を行う。すなわち、(1)電線管の加工を行う電線管加工工程aと、(2)対向するSC壁パネルに直線型の電線管14の取付位置を設定して当該位置に直線型の電線管14の外径よりも口径が大きい広口孔を形成する広口孔形成工程bと、(3)各SC壁パネルの各広口孔位置に当該広口孔を塞ぐプレートを位置決めするプレート位置決め工程cと、(4)プレートに直線型の電線管14の外径と略等径の電線管挿通孔を形成する電線管挿通孔形成工程dと、(5)電線管挿通孔に直線型の電線管14を挿通する電線管挿通工程eと、(6)プレートを各SC壁パネルに溶接固定するプレート固定工程fと、(7)プレートに直線型の電線管14を固定する電線管固定工程gと、(8)各SC壁パネル間にコンクリートを打設するコンクリート打設工程hを備える。   Also when attaching such a linear conduit 14 to SC wall panel 1a, 1b, the process substantially the same as 1st Embodiment is performed. That is, (1) a conduit processing step a for processing a conduit, and (2) setting a mounting position of the straight conduit 14 on the opposing SC wall panel, and setting the straight conduit 14 at the position. A wide-bore forming step b for forming a wide-bore having a diameter larger than the outer diameter; (3) a plate positioning step c for positioning a plate that closes the wide-bore hole at each wide-bore position of each SC wall panel; A conduit insertion hole forming step d for forming a conduit insertion hole having a diameter substantially equal to the outer diameter of the linear conduit 14 in the plate; and (5) an electrical wire for inserting the linear conduit 14 into the conduit insertion hole. A pipe insertion step e, (6) a plate fixing step f for fixing the plate to each SC wall panel by welding, (7) a conduit fixing step g for fixing the linear conduit 14 to the plate, and (8) each Concrete placement to place concrete between SC wall panels Extent provided with a h.

このような第2実施形態によれば、各SC壁パネル1a,1bに直線型電線管14の径よりも大径な広口孔4a,4bを形成しておき、これらの広口孔4a,4bを位置調整用プレート2a,2bで塞いで位置決めし、この状態で電線管挿通孔5a,5bの形成およびこれらの電線管挿通孔5a,5bへの直線型電線管14の挿通、各SC壁パネル1a,1bへのプレート2a,2bの溶接固定、およびプレート2a,2bへの直線型電線管14の締付け固定を行うことにより、曲げ加工精度の緩和等が図れるとともに、電線管14をSC壁パネル1a,1bに簡便な手順で能率よく取付けることができ、加工時間および取付け時間の短縮が図れる。したがって、SC壁パネル1a,1bの組立てを採用することによる高能率の工法を有効に活用することができる。   According to the second embodiment, the wide-wall holes 4a and 4b having a diameter larger than the diameter of the straight conduit 14 are formed in each SC wall panel 1a and 1b, and the wide-hole holes 4a and 4b are formed. Positioning is performed by closing the position adjusting plates 2a and 2b. In this state, formation of the conduit insertion holes 5a and 5b, insertion of the linear conduit 14 into the conduit insertion holes 5a and 5b, and each SC wall panel 1a , 1b by welding and fixing the straight conduit 14 to the plates 2a, 2b, the bending accuracy can be eased, and the conduit 14 is connected to the SC wall panel 1a. , 1b can be efficiently attached by a simple procedure, and the processing time and the attachment time can be shortened. Therefore, the highly efficient construction method by adopting the assembly of the SC wall panels 1a and 1b can be effectively utilized.

[第3実施形態(図9〜図13、図3、図5)]
本実施形態では、広口孔を塞ぐプレートとして、電線管挿通孔が広口孔の範囲内でいずれの位置・方向にずれる場合においても、当該広口孔を塞ぐことが可能な面積を有する位置ずれ吸収代をもつ位置調整用大型プレートを適用する電線管取付工法電線管取付構造について説明する。
[Third Embodiment (FIGS. 9 to 13, FIG. 3, FIG. 5)]
In the present embodiment, as the plate for closing the wide opening, even if the conduit insertion hole is displaced in any position and direction within the range of the wide opening, the misalignment absorption margin having an area capable of closing the wide opening is provided. A conduit mounting structure for applying a large-sized plate for position adjustment with a conduit mounting structure will be described.

図9は同工法の手順を示す工程図であり、図10(a1)〜(d)は、取付工程に沿う手順を概略図によって示す工程説明図である。   FIG. 9 is a process diagram showing the procedure of the construction method, and FIGS. 10A to 10D are process explanatory diagrams schematically showing the procedure along the attachment process.

図9に示すように、本実施形態のSC壁パネル内オフセット電線管取付工法は、(1)電線管の加工を行う電線管加工工程aと、(2)対向するSC壁パネルにオフセット電線管取付位置を設定して当該位置にオフセット電線管の外径よりも口径が大きい広口孔を形成する広口孔形成工程bと、(3)電線管挿通孔が広口孔の範囲内で、いずれの位置にずれる場合においても広口孔を塞ぐことができる面積を有する位置ずれ吸収代をもつ位置調整用大型プレートを位置決めして、各SC壁パネルの各広口孔位置に当該広口孔を塞ぐプレート位置決め工程cと、(4)位置調整用大型プレートにオフセット電線管の外径と略等径の電線管挿通孔を形成する電線管挿通孔形成工程dと、(5)電線管挿通孔にオフセット電線管を挿通する電線管挿通工程eと、(6)位置調整用大型プレートを各SC壁パネルに溶接固定するプレート固定工程fと、(7)位置調整用大型プレートにオフセット電線管を固定する電線管固定工程gと、(8)各SC壁パネル間にコンクリートを打設するコンクリート打設工程hとを備える。以下、各工程a〜hについて詳述する。   As shown in FIG. 9, the SC wall panel offset conduit mounting method of this embodiment includes (1) a conduit processing step a for processing the conduit, and (2) an offset conduit on the opposing SC wall panel. A wide-bore forming step b for setting a mounting position and forming a wide-bore hole having a larger diameter than the outer diameter of the offset conduit at the position; and (3) any position within the range of the wide-bore hole Positioning step c for positioning a large plate for position adjustment having a misalignment absorption margin having an area capable of closing the wide-mouth hole even in the case of shifting to the wide-hole position of each SC wall panel And (4) a conduit insertion hole forming step d for forming a conduit insertion hole having a substantially equal diameter to the outer diameter of the offset conduit on the large plate for position adjustment, and (5) an offset conduit in the conduit insertion hole. Insertion of conduit Step e, (6) a plate fixing step f for fixing the large plate for position adjustment to each SC wall panel by welding, and (7) a conduit fixing step g for fixing the offset conduit tube to the large plate for position adjustment. 8) A concrete placing step h for placing concrete between each SC wall panel. Hereinafter, each process ah is explained in full detail.

(1)電線管加工工程a
電線管加工工程aでは、図10(a1)、(a2)、(a3)に順次に示すように、所定長さの金属製管材、例えば直線型の鋼管材6aをZ形に曲げ加工してオフセット電線管6とし、このオフセット電線管6の両端部にねじ切り加工を施して、両端にねじ部7を有するオフセット電線管6とする。
(1) Conduit processing step a
In the conduit processing step a, as shown in order in FIGS. 10 (a1), (a2), and (a3), a predetermined length of metal pipe, for example, a straight steel pipe 6a, is bent into a Z shape. An offset conduit 6 is formed, and both ends of the offset conduit 6 are threaded to form an offset conduit 6 having screw portions 7 at both ends.

(2)広口孔形成工程b
広口孔形成工程bでは、図10(b)に示すように、対向する1対のSC壁パネル1(1a,1b)にオフセット電線管6の外径よりも口径が大きい広口孔4(4a,4b)をオフセット電線管6のオフセット量に対応する配置で形成する。
(2) Wide-mouth hole forming step b
In the wide-mouth hole forming step b, as shown in FIG. 10 (b), a wide-bore hole 4 (4a, 4a, 4b) is formed in an arrangement corresponding to the offset amount of the offset conduit 6.

本実施形態の広口孔形成工程bにおいても、図3に示した方法を適用して広口孔の形成を行う。すなわち、SC鋼壁パネル1aに、後の工程で取付けるオフセット電線管6の取付位置に対応して、縦横のケガキ線11a,11bを記し、これらのケガキ11a,11bの交点を中心として、SC壁パネル1aに例えば円形または楕円形の広口孔4aを形成する。なお、広口孔4aの形状は円、楕円の他、種々の形状とすることができる。また、特に形状を特定しない長孔等としてもよい。   Also in the wide-mouth hole forming step b of this embodiment, the wide-hole hole is formed by applying the method shown in FIG. That is, on the SC steel wall panel 1a, vertical and horizontal marking lines 11a and 11b are written corresponding to the mounting positions of the offset conduit 6 to be mounted in a later process, and the SC wall is centered on the intersection of these markings 11a and 11b. For example, a circular or elliptical wide opening 4a is formed in the panel 1a. The wide opening 4a may have various shapes other than a circle and an ellipse. Moreover, it is good also as a long hole etc. which do not specify a shape in particular.

(3)プレート位置決め工程c
本実施形態のプレート位置決め工程cでは、各SC壁パネル1a,1bの各広口孔4a,4bを塞ぐプレートとして、第1実施形態の位置調整用プレート2a,2bに代え、図10(c)に示すように、位置調整用大型プレート16(16a,16b)を適用する。
(3) Plate positioning step c
In the plate positioning step c of the present embodiment, instead of the position adjusting plates 2a and 2b of the first embodiment as plates for closing the wide opening holes 4a and 4b of the SC wall panels 1a and 1b, FIG. As shown, a large plate 16 (16a, 16b) for position adjustment is applied.

この位置調整用大型プレート16a,16bは、図10(c)に示すように、第1実施形態の位置調整用プレート2a,2bに比して面積が大きく設定されている。位置調整用大型プレート16a,16bの面積は、この位置調整用大型プレート16a,16bに形成される電線管挿通孔5(5a,5b)がSC壁パネル1a,1bに形成される各広口孔4a,4bの範囲内でいずれの方向・位置に対して位置調整される場合においても、当該広口孔4a,4bを塞ぐことが可能な面積を有する位置ずれ吸収代をもつ構成とされている。   As shown in FIG. 10C, the position adjusting large plates 16a and 16b have a larger area than the position adjusting plates 2a and 2b of the first embodiment. The area of the large plates 16a, 16b for position adjustment is such that the wide hole 4a in which the conduit insertion hole 5 (5a, 5b) formed in the large plates 16a, 16b for position adjustment is formed in the SC wall panels 1a, 1b. , 4b, even when the position is adjusted with respect to any direction / position, the misalignment absorption margin has an area capable of closing the wide opening 4a, 4b.

図11および図12は、この位置調整用大型プレート16a,16bの面積を設定する場合の概念を示す説明図である。図11には簡便化のため広口孔4a,4bを示す円と、電線管挿通孔5a,5bの中心点20とが示されている。この電線管挿通孔5a,5bの中心点20が図11の紙面上に沿って縦横に最大限位置ずれした場合、仮想線で示した広口孔4a,4bの半径相当領域18の変位量は、同図に仮想線で示した変位領域(取付位置ずれの吸収代)15として示した範囲まで拡大される。   FIG. 11 and FIG. 12 are explanatory diagrams showing the concept in the case of setting the area of the large plates for position adjustment 16a, 16b. For the sake of simplicity, FIG. 11 shows a circle indicating the wide opening holes 4a and 4b and a center point 20 of the conduit insertion holes 5a and 5b. When the center point 20 of the conduit insertion holes 5a and 5b is displaced to the maximum in the vertical and horizontal directions along the paper surface of FIG. 11, the amount of displacement of the radius equivalent region 18 of the wide-mouth holes 4a and 4b indicated by phantom lines is In the same figure, it is expanded to a range shown as a displacement area (absorption margin of attachment position deviation) 15 shown by a virtual line.

そこで、図12に示すように、矩形状として例示した位置調整用大型プレート16a,16bには、図11で示した位置ずれ時に拡大される変位領域15相当の縦横寸法が設定されている。   Therefore, as shown in FIG. 12, the vertical and horizontal dimensions corresponding to the displacement region 15 enlarged at the time of the positional deviation shown in FIG. 11 are set in the large plates 16a and 16b for position adjustment exemplified as a rectangular shape.

図13は、このような概念に基づいて構成された位置調整用大型プレート16a,16bと、各SC壁パネル1a,1bに形成される広口孔4a,4b(この図13の例では広口孔4a,4bが楕円状の長孔として形成されている)とが示され、さらに位置調整用大型プレート16a,16bに形成される円形の電線管挿通孔5a,5bが仮想線および実線により2つの位置でずれた様子が示されている。このような位置ずれが生じても、本実施形態では隙間が生じることがなく、電線管挿通孔5a,5bが各広口孔4a,4bの範囲内でいずれの方向・位置に対して位置調整される場合においても、上述した領域15,18が位置ずれ吸収代となり、広口孔4a,4bが常に位置調整用大型プレート16a,16bにより塞がれる。   FIG. 13 shows a large plate for position adjustment 16a, 16b constructed based on such a concept, and wide opening holes 4a, 4b formed in each SC wall panel 1a, 1b (in this example of FIG. 13, wide opening hole 4a). , 4b are formed as elliptical long holes), and circular conduit insertion holes 5a, 5b formed in the large plates 16a, 16b for position adjustment are arranged at two positions by virtual lines and solid lines. It is shown that the position is shifted. Even if such misalignment occurs, no gap is produced in the present embodiment, and the conduit insertion holes 5a and 5b are adjusted with respect to any direction and position within the range of the wide opening holes 4a and 4b. Even in this case, the above-described regions 15 and 18 serve as misalignment absorption margins, and the wide-mouth holes 4a and 4b are always closed by the large plates 16a and 16b for position adjustment.

すなわち、本実施形態では、プレート位置決め工程cとして、図10(c)に示すように、電線管挿通孔5a,5bが広口孔4a,4bの範囲内でいずれの位置にずれる場合においても当該広口孔4a,4bを塞ぐことが可能な面積を有する位置ずれ吸収代をもつ位置調整用大型プレート16a,16bが各SC壁パネル1a,1bに位置決めされ、取付けられる。   That is, in this embodiment, as shown in FIG. 10C, the plate positioning step c is performed even when the conduit insertion holes 5a and 5b are shifted to any position within the range of the wide opening holes 4a and 4b. Position adjusting large plates 16a, 16b having a displacement absorption margin having an area capable of closing the holes 4a, 4b are positioned and attached to the SC wall panels 1a, 1b.

(4)電線管挿通孔形成工程d
電線管挿通孔形成工程dでは、図10(d)に示すように、位置調整用大型プレート16a,16bにオフセット電線管6の外径と略等径の電線管挿通孔5a,5bを形成する。この電線管挿通孔5a,5bを形成については、第1実施形態における図5と同様の方法が適用される。すなわち、電線管加工工程aで加工したオフセット電線管6のオフセット量に対応して、ケガキ線12c,12dにより位置調整用プレート孔加工芯13を設定する。この設定した位置調整用プレート孔加工芯13を中心として、位置調整用プレート孔としてオフセット電線管6の外径と略等径の電線管挿通孔5a,5bを、位置調整用大型プレート16a,16bに形成する。なお、本実施形態では、位置調整用大型プレート16a,16bのいずれの位置に電線管挿通孔5a,5bを形成しても広口孔4a,4bが常に位置調整用大型プレート16a,16bにより塞がれる構成となるので、広口孔4a,4bの形成は第1実施形態と異なり、電線管挿通孔形成工程d以前に形成することができる。
(4) Conduit insertion hole forming step d
In the conduit insertion hole forming step d, as shown in FIG. 10D, the conduit insertion holes 5a and 5b having substantially the same diameter as the outer diameter of the offset conduit 6 are formed in the position adjusting large plates 16a and 16b. . For the formation of the conduit insertion holes 5a and 5b, the same method as in FIG. 5 in the first embodiment is applied. That is, the position adjusting plate hole processing core 13 is set by the marking lines 12c and 12d corresponding to the offset amount of the offset conduit 6 processed in the conduit processing step a. Centering on the set position adjusting plate hole processing core 13, as the position adjusting plate hole, the conduit pipe insertion holes 5 a and 5 b having substantially the same diameter as the outer diameter of the offset conduit 6, and large position adjusting plates 16 a and 16 b are provided. To form. In this embodiment, the wide opening 4a, 4b is always closed by the position adjusting large plates 16a, 16b even if the conduit insertion holes 5a, 5b are formed at any position of the position adjusting large plates 16a, 16b. Therefore, the wide-mouth holes 4a and 4b can be formed before the conduit insertion hole forming step d, unlike the first embodiment.

(5)電線管挿通工程e
電線管挿通工程eでは、図10(d)に示すように、位置調整用大型プレート16a,16bの電線管挿通孔5a,5bにオフセット電線管6を挿通する。
(5) Conduit insertion process e
In the conduit insertion step e, as shown in FIG. 10 (d), the offset conduit 6 is inserted into the conduit insertion holes 5a and 5b of the large plates 16a and 16b for position adjustment.

(6)プレート固定工程f
プレート固定工程fでは、図10(d)に示すように、位置調整用大型プレート16a,16bを位置調整してSC壁パネル1bに溶接部3により溶接固定する。この溶接部3としては、例えば位置調整用大型プレート16a,16bの周縁を一定の間隔で溶接する部分溶接として施す。
(6) Plate fixing process f
In the plate fixing step f, as shown in FIG. 10 (d), the position adjusting large plates 16a and 16b are adjusted and welded and fixed to the SC wall panel 1b by the welding portion 3. As the welded portion 3, for example, partial welding is performed in which the peripheral edges of the position adjusting large plates 16a and 16b are welded at regular intervals.

(7)電線管固定工程g
電線管固定工程gでは、図10(d)に示すように、電線管挿通孔5a,5bに挿通したオフセット電線管6のねじ部7にロックナット8(8a,8b)を螺合して位置調整用大型プレート16a,16bに固定する。
(7) Conduit fixing process g
In the conduit fixing step g, as shown in FIG. 10 (d), the lock nut 8 (8a, 8b) is screwed into the threaded portion 7 of the offset conduit 6 inserted into the conduit insertion holes 5a, 5b. It fixes to the adjustment large plates 16a and 16b.

この電線管固定工程gにおいては、図6に示した第1実施形態の方法を適用することができる。すなわち、位置調整用プレート孔加工芯13を中心として形成された電線管挿通孔5bに、オフセット電線管6を挿通し、オフセット電線管6のねじ部7にロックナット8を螺合して、プレート2の内面、外面または両面に締結固定する。   In the conduit fixing step g, the method of the first embodiment shown in FIG. 6 can be applied. That is, the offset conduit 6 is inserted into the conduit insertion hole 5b formed around the position adjusting plate hole processing core 13, and the lock nut 8 is screwed into the threaded portion 7 of the offset conduit 6 to form the plate. Fastened and fixed to the inner surface, outer surface, or both surfaces of 2.

(8)コンクリート打設工程h
以上の電線管加工工程a〜電線管固定工程gが終了した後に、本実施形態の最終工程として、コンクリート打設工程hを行う。このコンクリート打設工程hにより、オフセット電線管6が各SC壁パネル1a,1b間に完全固定される。
(8) Concrete placing process h
After the above-described conduit processing step a to conduit fixing step g are completed, a concrete placing step h is performed as the final step of the present embodiment. By this concrete placing process h, the offset conduit 6 is completely fixed between the SC wall panels 1a and 1b.

以上の工程により構成されるSC壁パネル内オフセット電線管取付構造では、スタッド10が設けられた対向するSC壁パネル1a,1bがタイバー9によって連結される。各SC壁パネル1a,1bには、オフセット電線管6の外径よりも口径が大きい広口孔4a,4bがオフセット電線管6のオフセット量に対応する配置で形成される。各SC壁パネル1a,1bには、各広口孔4a,4bを塞ぐプレート2a,2bが溶接部3a,3bにより固定される。位置調整用大型プレート16a,16bには、オフセット電線管6の外径と略等径の電線管挿通孔5a,5bが形成されている。これらの電線管挿通孔5a,5bには、オフセット電線管6が挿通され、このオフセット電線管6の両端のねじ部7にロックナット8a,8bが螺合され、オフセット電線管6が固定される。   In the SC wall panel offset conduit mounting structure constituted by the above steps, the opposing SC wall panels 1 a and 1 b provided with the studs 10 are connected by a tie bar 9. In each SC wall panel 1a, 1b, wide opening holes 4a, 4b having a diameter larger than the outer diameter of the offset conduit 6 are formed in an arrangement corresponding to the offset amount of the offset conduit 6. Plates 2a and 2b for closing the wide-mouth holes 4a and 4b are fixed to the SC wall panels 1a and 1b by welds 3a and 3b, respectively. On the large plates 16a and 16b for position adjustment, conduit insertion holes 5a and 5b having substantially the same diameter as the outer diameter of the offset conduit 6 are formed. The offset conduit 6 is inserted into the conduit insertion holes 5a and 5b, and the lock nuts 8a and 8b are screwed to the screw portions 7 at both ends of the offset conduit 6 so that the offset conduit 6 is fixed. .

以上の第3実施形態によれば、取付位置ずれの吸収代15をカバーする大きさの位置調整用大型プレート16を適用することにより、SC鋼板パネル1の広口孔4のいずれの位置にオフセット電線管6が取付けられていても、位置調整用大型プレート16の取付位置ズレの吸収代15によりSC鋼板パネル1の広口孔SC鋼板長孔4が確実に塞がれる。   According to the third embodiment described above, by applying the position adjusting large plate 16 having a size that covers the absorption margin 15 of the mounting position deviation, the offset electric wire can be placed at any position of the wide opening 4 of the SC steel plate panel 1. Even if the pipe 6 is attached, the wide opening hole SC steel plate long hole 4 of the SC steel plate panel 1 is reliably closed by the absorption margin 15 of the attachment position shift of the large plate 16 for position adjustment.

したがって、位置調整用大型プレート16を使用することにより、オフセット電線管6を通す位置調整用プレート孔5を先行加工することができ、第1実施形態と同様の効果に加えて、更なる工程短縮が図れる。   Therefore, by using the large plate for position adjustment 16, the position adjustment plate hole 5 through which the offset conduit 6 passes can be processed in advance, and in addition to the same effect as the first embodiment, further process shortening Can be planned.

本発明の第1実施形態による工法の手順を示す工程図。Process drawing which shows the procedure of the construction method by 1st Embodiment of this invention. (a1)〜(d)は、本発明の第1実施形態による取付工程に沿う手順を概略図によって示す工程説明図。(A1)-(d) is process explanatory drawing which shows the procedure in alignment with the attachment process by 1st Embodiment of this invention with a schematic diagram. 本発明の第1実施形態による工法を示す詳細説明図。Detailed explanatory drawing which shows the construction method by 1st Embodiment of this invention. 本発明の第1実施形態による工法を示す詳細説明図。Detailed explanatory drawing which shows the construction method by 1st Embodiment of this invention. 本発明の第1実施形態による工法を示す詳細説明図。Detailed explanatory drawing which shows the construction method by 1st Embodiment of this invention. 本発明の第1実施形態による工法を示す詳細説明図。Detailed explanatory drawing which shows the construction method by 1st Embodiment of this invention. 本発明の第1実施形態による構造を示す詳細説明図。Detailed explanatory drawing which shows the structure by 1st Embodiment of this invention. 本発明の第2実施形態による工法を示す詳細説明図。Detailed explanatory drawing which shows the construction method by 2nd Embodiment of this invention. 本発明の第3実施形態による同工法の手順を示す工程図。Process drawing which shows the procedure of the construction method by 3rd Embodiment of this invention. (a1)〜(d)は、本発明の第3実施形態による取付工程に沿う手順を概略図によって示す工程説明図。(A1)-(d) is process explanatory drawing which shows the procedure in alignment with the attachment process by 3rd Embodiment of this invention with a schematic diagram. 本発明の第3実施形態による工法を示す詳細説明図。Detailed explanatory drawing which shows the construction method by 3rd Embodiment of this invention. 本発明の第3実施形態による工法を示す詳細説明図。Detailed explanatory drawing which shows the construction method by 3rd Embodiment of this invention. 本発明の第3実施形態による工法を示す詳細説明図。Detailed explanatory drawing which shows the construction method by 3rd Embodiment of this invention.

符号の説明Explanation of symbols

1 SC鋼板パネル(SC壁パネル)
2 位置調整用プレート
3 位置調整用プレートの定溶接部
4 広口孔
5 電線管挿通孔
6 オフセット電線管
7 ねじ部
8 ロックナット
9 タイバー
10 スタッド
11 電線管ケガキ線
12 位置調整用プレートケガキ線
13 位置調整用プレート孔加工芯
14 直線型電線管
15 取付位置ずれの吸収代
16 位置調整用大型プレート
17 SC鋼板孔
1 SC steel panel (SC wall panel)
2 Position adjustment plate 3 Position weld plate constant weld 4 Wide opening 5 Conduit insertion hole 6 Offset conduit 7 Threaded portion 8 Lock nut 9 Tie bar 10 Stud 11 Conduit marking wire 12 Position adjustment plate marking wire 13 Position Adjustment plate hole machining core 14 Straight conduit 15 Absorption allowance for mounting position deviation 16 Position adjustment large plate 17 SC steel plate hole

Claims (4)

対向するSC壁パネル間にこれらを貫通する電線管を取付けるSC壁パネル内電線管の取付工法において、前記各SC壁パネルに前記電線管取付位置を設定して当該位置に前記電線管の外径よりも口径が大きい広口孔を形成する広口孔形成工程と、前記各SC壁パネルの各広口孔位置に当該広口孔を塞ぐプレートを位置決めするプレート位置決め工程と、前記プレートに前記電線管の外径と略等径の電線管挿通孔を形成する電線管挿通孔形成工程と、前記電線管挿通孔に前記電線管を挿通する電線管挿通工程と、前記プレートを前記各SC壁パネルに固定するプレート固定工程と、前記プレートに前記電線管を固定する電線管固定工程とを備えることを特徴とするSC壁パネル内電線管の取付工法。 In the mounting method of the conduit in the SC wall panel for attaching the conduit passing therethrough between the opposing SC wall panels, the conduit mounting position is set on each SC wall panel, and the outer diameter of the conduit is at the position. A wide hole forming step for forming a wide hole having a larger diameter than that, a plate positioning step for positioning a plate that closes the wide hole hole at each wide hole position of each SC wall panel, and the outer diameter of the conduit on the plate A conduit insertion hole forming step for forming a conduit insertion hole of substantially the same diameter, a conduit insertion step for inserting the conduit through the conduit insertion hole, and a plate for fixing the plate to each SC wall panel An SC wall panel conduit mounting method comprising a fixing step and a conduit fixing step of fixing the conduit to the plate. 対向するSC壁パネル間にこれらを貫通するオフセット電線管を取付けるSC壁パネル内電線管の取付工法において、前記各SC壁パネルに前記オフセット電線管取付位置を設定して当該位置に前記オフセット電線管の外径よりも口径が大きい広口孔を形成する広口孔形成工程と、前記各SC壁パネルの各広口孔位置に当該広口孔を塞ぐプレートを位置決めするプレート位置決め工程と、前記プレートに前記オフセット電線管の外径と略等径の電線管挿通孔を形成する電線管挿通孔形成工程と、前記電線管挿通孔に前記オフセット電線管を挿通する電線管挿通工程と、前記プレートを前記各SC壁パネルに固定するプレート固定工程と、前記プレートに前記オフセット電線管を固定する電線管固定工程とを備えることを特徴とするSC壁パネル内電線管の取付工法。 In the mounting method of the conduits in the SC wall panel for mounting the offset conduits penetrating between the opposing SC wall panels, the offset conduits are set at the respective SC wall panels, and the offset conduits are set at the positions. A wide hole forming step for forming a wide hole having a diameter larger than the outer diameter of the plate, a plate positioning step for positioning a plate closing the wide hole at each wide hole position of each SC wall panel, and the offset electric wire on the plate A conduit insertion hole forming step for forming a conduit insertion hole having a diameter approximately equal to the outer diameter of the tube, a conduit insertion step for inserting the offset conduit tube into the conduit insertion hole, and the plate for each SC wall. An SC wall panel comprising: a plate fixing step for fixing to a panel; and a conduit fixing step for fixing the offset conduit to the plate. Mounting method of the inner conduit. 前記広口孔を塞ぐプレートを、前記電線管挿通孔が前記広口孔の範囲内でいずれの位置にずれる場合においても当該広口孔を塞ぐことが可能な面積を有する位置ずれ吸収代をもつ位置調整用大型プレートとする請求項1または2記載の電線管の取付工法。 The plate for closing the wide hole is for position adjustment having a misalignment absorption margin having an area capable of closing the wide hole even when the conduit insertion hole is shifted to any position within the range of the wide hole. 3. The method for mounting a conduit according to claim 1 or 2, wherein the large plate is used. 対向するSC壁パネル間にこれらを貫通するオフセット電線管を取付けるSC壁パネル内オフセット電線管取付構造であって、前記各SC壁パネルには前記オフセット電線管の外径よりも口径が大きい広口孔が前記オフセット電線管のオフセット量に対応する配置で形成されるとともに、前記各SC壁パネルには前記各広口孔を塞ぐプレートが固定されており、かつ前記各プレートには前記オフセット電線管の外径と略等径の電線管挿通孔が形成され、この電線管挿通孔には前記オフセット電線管が挿通して固定されていることを特徴とするSC壁パネル内オフセット電線管の取付構造。 An offset conduit mounting structure in an SC wall panel for attaching an offset conduit passing therethrough between opposing SC wall panels, each SC wall panel having a wide opening having a diameter larger than the outer diameter of the offset conduit Is formed in an arrangement corresponding to the offset amount of the offset conduit, and each SC wall panel is fixed with a plate that closes each of the wide-mouth holes, and each plate has an outer periphery of the offset conduit. A mounting structure for an offset conduit in an SC wall panel, wherein a conduit insertion hole having a diameter substantially equal to the diameter is formed, and the offset conduit is inserted and fixed in the conduit insertion hole.
JP2005268398A 2005-09-15 2005-09-15 Technique and structure for installing conduit tube in sc wall panel Pending JP2007082348A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005268398A JP2007082348A (en) 2005-09-15 2005-09-15 Technique and structure for installing conduit tube in sc wall panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005268398A JP2007082348A (en) 2005-09-15 2005-09-15 Technique and structure for installing conduit tube in sc wall panel

Publications (1)

Publication Number Publication Date
JP2007082348A true JP2007082348A (en) 2007-03-29

Family

ID=37942029

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005268398A Pending JP2007082348A (en) 2005-09-15 2005-09-15 Technique and structure for installing conduit tube in sc wall panel

Country Status (1)

Country Link
JP (1) JP2007082348A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018003957A (en) * 2016-07-01 2018-01-11 積水化学工業株式会社 Cap, cap forming member, covering method and partition penetration structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018003957A (en) * 2016-07-01 2018-01-11 積水化学工業株式会社 Cap, cap forming member, covering method and partition penetration structure

Similar Documents

Publication Publication Date Title
JP2009228276A (en) Vibration control damper and mounting structure thereof
JP2007198066A (en) Beam junction structure of rectangular steel pipe pillar and its construction method
JP2007270511A (en) Reinforcement structure and steel plate for reinforcement of structure
JP2007082348A (en) Technique and structure for installing conduit tube in sc wall panel
JP6340645B1 (en) Splice plate holding jig
KR20150142752A (en) Jig for preventing thermal deformation
JP2010065478A (en) Method of manufacturing steel pipe with stiffener
JP2013087439A (en) Template position correcting implement
JP2007231522A (en) Bendable and joinable sheet panel, and tunnel reinforcing method
CN110226047B (en) Fastening structure and fastening method
JP2006046007A (en) Joint member
RU169354U1 (en) THERMAL INSULATING DRILLING HOUSING
JP2008274651A (en) Alc burying anchor metal fitting, alc panel and alc panel installing structure
JP2010090570A (en) Pile head joining structure
JP5442336B2 (en) Joint structure of reinforced concrete beam and steel beam
JP5208820B2 (en) Beam joint structure
JP5358004B2 (en) Beam joint structure
JP4398234B2 (en) Piping connection structure and angle adjusting pipe used therefor
JP2009114759A (en) Building unit jointing device
AU2020101546A4 (en) The reinforcement structure of rectangular steel column and beam connecting node in prefabricated steel structure building
JP2009142881A (en) Positioner face plate and core connecting tool
JP5661419B2 (en) Beam joint forming method
JPH07324506A (en) Connection of module
JP2003313816A (en) Construction method of bridge falling prevention device and temporary fixing sheath assembly
JP2006121823A (en) Supporting member and internal instrument supporting frame

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071217

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090507

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090616

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20091020