JP2007079994A - Construction work estimate support system, method and program - Google Patents

Construction work estimate support system, method and program Download PDF

Info

Publication number
JP2007079994A
JP2007079994A JP2005267575A JP2005267575A JP2007079994A JP 2007079994 A JP2007079994 A JP 2007079994A JP 2005267575 A JP2005267575 A JP 2005267575A JP 2005267575 A JP2005267575 A JP 2005267575A JP 2007079994 A JP2007079994 A JP 2007079994A
Authority
JP
Japan
Prior art keywords
construction
section
estimate
cost
contents
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005267575A
Other languages
Japanese (ja)
Inventor
Shoji Shintani
昌二 新谷
Yoshihiro Yokoyama
芳宏 横山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chugoku Electric Power Co Inc
Original Assignee
Chugoku Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chugoku Electric Power Co Inc filed Critical Chugoku Electric Power Co Inc
Priority to JP2005267575A priority Critical patent/JP2007079994A/en
Publication of JP2007079994A publication Critical patent/JP2007079994A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a system for deciding the propriety of the construction work contents of an electromagnetic induction fault measure and the estimate of a construction work cost. <P>SOLUTION: The construction work estimate support system comprises: a construction work cost database for dividing a transmission line section into a plurality of sections and preserving the construction work cost and the construction work contents required for each section; an estimate information analysis means for reading the section of a transmission line and the construction work contents from input information supplied as the data of a predetermined form and dividing them into the sections matched with the construction work cost database; an estimate prediction means for calculating the approximate amount of the construction work cost for the construction work contents of the specified section by comparing the construction work section and the construction work contents in the past stored in the construction work cost database with each of the construction work sections and the construction work contents decomposed in the estimate information analysis means; and an estimate comparison means for comparing the calculated approximate cost and the estimate cost and extracting the difference. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、送電線路における電磁誘導障害の発生が有線事業者に影響を与える場合に、有線事業者が行う電磁誘導障害対策工事に要する費用を見積もり、有線事業者が行った見積との差分を抽出し、さらに有線事業者が行った見積の妥当性を判断することを可能とする工事見積支援システム、方法、およびプログラムに関する。   The present invention estimates the cost required for electromagnetic induction failure countermeasure construction performed by the wire operator when the occurrence of electromagnetic induction failure in the transmission line affects the wire operator, and calculates the difference from the estimate made by the wire operator. The present invention relates to a construction estimation support system, method, and program that can extract and further determine the validity of an estimate made by a wired operator.

従来、電磁誘導障害対策が必要となる電力設備工事の計画提示資料として上記電力設備工事が完了する3年前に、起誘導電流曲線、インピーダンスマップ、送電線路系統図、送電線路経路図などを作成し、有線事業者に提示している。有線事業者は上記計画提示資料をもとに、電磁誘導の影響を受けないように必要な対策工事の洗い出しを行い、それらの工事に要する費用を電力会社と有線事業者で調整していた。   Conventionally, as a plan presentation material for power facility construction that requires countermeasures against electromagnetic induction troubles, three years before the completion of the above power facility construction, an induced current curve, impedance map, transmission line system diagram, transmission line route diagram, etc. are created. And present it to the cable operator. Based on the above-mentioned plan presentation materials, cable operators identified necessary work to avoid being affected by electromagnetic induction, and the costs required for such work were adjusted between the power company and the cable operator.

これまで、見積などを支援する技術として、特許文献1では、設備の修繕計画立案に関し、中期リスクに基づいた設備横断の修繕計画立案を支援する新規な技術を提案している。また、特許文献2は、業者が推奨する提案項目情報をオンラインでユーザである企業・団体等に提供し、企業・団体等からの発注を得やすくする環境を整備するとともに、企業・団体等における内部の関係部署間の調整及び業者への発注等の効率的な遂行を支援するプラントとその機器の発注及び受注支援システムを提供する技術を提案している。   To date, Patent Document 1 has proposed a new technology for supporting a repair plan for crossing equipment based on a medium-term risk as a technique for supporting an estimate or the like. In addition, Patent Document 2 provides suggested item information recommended by a company to a company or organization that is a user online, and provides an environment that makes it easy to obtain orders from companies and organizations. It proposes a technology that provides an ordering and ordering support system for a plant and its equipment that supports the efficient execution of the coordination between internal related departments and the ordering of contractors.

さらに、特許文献3は、販売効率や営業効率を向上させるために、複数の販売店とディストリビュータとの間をインターネット網で接続し、販売店からの注文に対して効率的に商品の見積処理を行う技術を提案している。
特開2005−11327号公報 特開2003―85413号公報 特開2002―7792号公報
Furthermore, in Patent Document 3, in order to improve sales efficiency and sales efficiency, a plurality of dealers and distributors are connected via an Internet network, and product quotation processing is efficiently performed for orders from dealers. Proposes technology to do.
JP 2005-11327 A JP 2003-85413 A Japanese Patent Laid-Open No. 2002-7792

ところで、送電線路の長さは数10Kmにも及び、その送電線路から半径5.0Km以内の工事箇所をピックアップした結果は膨大な量となり、その工事内容の正当性の判断や、間違い・問題点などのチェックに多大な工数と時間を要していた。また、電力会社の予測と有線事業者の見積額が大きく違っていることも多く、その調整にかなりの工数を使っていた。チェックなどに多大な工数および時間を要するため、充分な検証を行うことができないまま工事内容を承認してしまうことがあった。   By the way, the length of the power transmission line is several tens of kilometers, and the result of picking up the construction site within a radius of 5.0 km from the power transmission line is a huge amount. It took a lot of man-hours and time to check. In addition, the forecasts of electric power companies and the estimates of cable operators are often very different, and considerable man-hours were used for the adjustment. Since a lot of man-hours and time are required for checking and the like, the construction contents may be approved without being able to perform sufficient verification.

これに対応して、多大な量の電磁誘導障害対策工事の見積をチェックし、その工事の正当性を判断することのできるシステムが望まれている。   Correspondingly, a system capable of checking the estimate of a large amount of electromagnetic induction failure countermeasure construction and judging the validity of the construction is desired.

本発明は、上述のかかる事情に鑑みてなされたものであり、過去の工事のデータベースを参照しながら、新たな見積内容を精査し、また標準化された見積データベースを参照しながら、見積額の正当性を評価し、最適な金額で契約が結べるように支援する工事見積支援システム、方法、およびプログラムを提供することを目的とする。   The present invention has been made in view of the above-mentioned circumstances, and examines the new estimate contents while referring to the past construction database, and also confirms the validity of the estimate amount while referring to the standardized estimate database. The purpose is to provide a construction estimation support system, method, and program for evaluating the feasibility and assisting in making a contract with an optimal amount.

上記目的を達成するため、本発明に係わる工事見積支援システムは、送電線路区間を複数の区間に分け、その区間ごとに行った工事内容、および要した工事費用を保存する工事内容データベースと、予め定めた形式のデータとして与えられる見積情報から送電線路の区間と工事内容、および工事費用を読み取り、前記工事内容データベースと合致した区間に分ける見積情報分析手段と、前記工事内容データベースに蓄積された過去の工事区間および工事内容と、前記見積情報分析手段にて分解された工事区間および工事内容を工事区間ごとに比較することで、指定された区間の工事内容に対して工事費用の概算を算出する見積予測手段と、前記算出された概算費用と見積費用とを比較してその差分を抽出する見積比較手段とを備えたことを特徴とする。   In order to achieve the above object, a construction estimation support system according to the present invention divides a transmission line section into a plurality of sections, a construction content database for storing construction contents performed for each section, and necessary construction costs, Reads the section of the transmission line, the construction content, and the construction cost from the estimation information given as data in a predetermined format, and divides the section into a section that matches the construction content database, and the past information accumulated in the construction content database The construction cost of the designated section is calculated by comparing the construction section and construction contents of the construction section and the construction sections and construction contents disassembled by the estimate information analysis means for each construction section. And an estimated predicting means and an estimated comparing means for comparing the calculated estimated cost with the estimated cost and extracting the difference. To.

本発明によれば、有線事業者から受信した工事情報を用いて予め定めた区間における過去の工事内容を参照して見積内容を判断することができ、さらに見積予測を算出し、算出した見積予測との差分を抽出できるので、受信した見積情報との差分のみを検討することができ、工数削減を行うことができる。   According to the present invention, it is possible to determine the estimated content by referring to the past construction content in the predetermined section using the construction information received from the wire operator, further calculate the estimated prediction, and calculate the estimated prediction Therefore, only the difference from the received estimate information can be considered, and man-hours can be reduced.

上記工事見積支援システムにおいて好ましくは、前記見積予測手段にて算出された概算費用と、前記見積情報分析手段により分析された区間ごとの工事内容および工事費用とを比較することで、工事費用の見積額の妥当性を判断する見積妥当性判断手段とを備えると良い。   In the construction estimate support system, preferably, the estimated cost calculated by the estimated forecasting means is compared with the construction contents and construction costs for each section analyzed by the estimated information analyzing means, thereby estimating the construction cost. It is preferable to provide estimated validity judgment means for judging the validity of the forehead.

本発明によれば、受信した工事内容および工事区間を含む工事情報に妥当性があるのかを判断することができるので、妥当性が無い場合、有線事業者に対して再見積の指示および内容の詳細な説明を聞く機会を素早く電力会社に与えることができる。   According to the present invention, it is possible to determine whether the received construction information and the construction information including the construction section are valid or not. You can quickly give power companies the opportunity to hear detailed explanations.

また前記見積妥当性判断手段は、読み取られた工事費用の見積額が、対応する区間および工事内容の過去の平均値から予め指定可能に定めた範囲内である場合は妥当であると判断するように構成するのも好ましい。   Further, the estimated validity judging means judges that the estimated construction cost read is valid if it is within a range that can be designated in advance from the past average value of the corresponding section and construction contents. It is also preferable to configure.

本発明によれば、過去の平均値から予め定めた範囲以内は妥当と判断することができるので、コンピュータを用いて自動的に多量の妥当性を判断することができ、工数の削減につながる。   According to the present invention, since it can be determined that the value is within a predetermined range from the past average value, a large amount of validity can be automatically determined using a computer, leading to a reduction in man-hours.

さらに前記見積妥当性判断手段は、前記読み取られた工事費用の見積額が、対応する工事区間および工事内容の過去の平均価格に過去の傾向を加味した値から予め定めた範囲内である場合は妥当であると判断するように構成するのも好ましい。   Further, the estimated validity judgment means, when the estimated amount of the read construction cost is within a predetermined range from a value obtained by adding a past tendency to a past average price of the corresponding construction section and construction content. It is also preferable that the configuration is determined to be appropriate.

本発明によれば、過去の実績に最近の傾向を加えたものを加味して指標とし、その値から予め定めた範囲以内である場合は妥当であると判断できるので、見積の妥当性を判断する時の傾向を加味した現実に近い値を判断指標にできる。よって、より確度の高い判断を行うことができ、判断の間違いが減少する。   According to the present invention, an index obtained by adding a recent tendency to past results is used as an index, and if it is within a predetermined range from the value, it can be determined to be appropriate. It is possible to use a value close to reality taking into account the tendency to do so. Therefore, it is possible to make a determination with higher accuracy, and the number of determination errors is reduced.

さらに好ましくは、前記見積妥当性判断手段は、前記読み取られた工事区間の工事内容と、同送電線路の同工事区間の過去の工事内容とを比較し、同じ内容であった場合は、警告を行うように構成する。   More preferably, the estimated validity judgment means compares the read construction contents of the construction section with the past construction contents of the construction section of the transmission line, and gives a warning if the contents are the same. Configure to do.

本発明によれば、間違って以前と同じ工事を行う見積になっていた場合に、それを判断し矛盾点を有線事業者に通知できるので人的な見逃しがなく正確な見積の判断を行うことが可能となる。   According to the present invention, when it is wrong to estimate the same construction as before, it is possible to judge it and notify the wired operator of the contradiction, so that it is possible to make an accurate estimate judgment without human oversight. Is possible.

さらに、前記見積妥当性判断手段は、読み取られた工事内容が妥当でないと判断した場合、または読み取られた工事内容が、見積予測された工事内容よりもより高度で且つ工事費用がより高価な工事内容である場合は、警告を行うように構成するのも好ましい。   Further, the estimated validity determination means determines that the read construction content is not valid, or the read construction content is higher than the estimated construction content and the construction cost is higher. In the case of content, it is also preferable that a warning is given.

本発明によれば、電磁誘導障害対策として防磁シールドを行うことで問題が無い対処であるのに、工事内容として光ファイバーの工事を行うとした工事内容に指摘を行うことが可能となるので、余分なコストを負担する必要が無くなる。   According to the present invention, it is possible to point out to the construction content that the construction of the optical fiber is performed as the construction content, although there is no problem by performing the magnetic shielding as a countermeasure against the electromagnetic induction failure. No need to pay extra costs.

また、上記工事見積支援システムにおいて、前記見積情報分析手段が分析して作成した区間ごとの工事内容と要する工事費用と、見積予測手段が予測して作成した区間ごと工事内容と工事費用とを図示化する見積図示化手段とを備えるように構成するのも好ましい。   Also, in the construction estimate support system, the construction contents and required construction costs for each section analyzed and created by the estimate information analysis means, and the construction contents and construction costs for each section predicted and created by the estimate prediction means are shown in the figure. It is also preferable that the apparatus is configured so as to include an estimate plotting means to be converted.

本発明によれば、過去の工事の工事内容および工事費用などの実績と、新たな工事見積を視覚的に理解し易いように図式化するので、図式により新たに見積もられた工事内容および工事費用の妥当性を容易に判断することが可能になる。   According to the present invention, the actual contents of construction work and construction costs of the past construction and the new construction estimate are charted so that they can be easily understood visually. Therefore, the construction contents and construction newly estimated by the chart. It becomes possible to easily determine the appropriateness of the cost.

さらに、上記工事見積支援システムにおいて、前記複数の区間は変更可能に構成するのも好ましい。   Furthermore, in the construction estimate support system, it is preferable that the plurality of sections are configured to be changeable.

本発明によれば、予め定めた区間を変更して見積予測を色々な区間ごとに行うことが可能となるので、最初は大きな区間で見積予測の算出を行い、だんだんと小さく区切って計算することが可能となり、最適な区間を判断することも可能となり算出する概算費用の確度の高い見積予測を行うことが可能となる。   According to the present invention, since it is possible to perform estimation prediction for each of various sections by changing a predetermined section, first, the estimation prediction is calculated in a large section, and is calculated by gradually dividing into smaller sections. Therefore, it is possible to determine the optimum section, and it is possible to perform estimation prediction with high accuracy of the estimated cost to be calculated.

また、上記工事見積支援システムにおいて、電磁誘導障害対策を行う必要のある送電線路の有線事業者の顧客の総数または増加率を保存する通信経路データベースを備え、前記見積予測手段は、過去の工事内容および工事費用に拘わらず、対象の工事区間の総顧客数もしくは顧客の伸び率を加味した総顧客数が予め定めた数より大きい場合は、電磁誘導障害対策として光ファイバーを選択し、工事費用をある定めた割合で有線事業者と按分するように構成するのも良い。   The construction estimation support system further includes a communication path database that stores a total number or an increase rate of the wireline business customers of the transmission lines that need to take measures against electromagnetic induction disturbance, and the estimation prediction means includes past construction contents. Regardless of the construction cost, if the total number of customers in the target construction section or the total number of customers taking into account the customer growth rate is greater than the predetermined number, optical fiber is selected as a measure against electromagnetic induction interference, and there is a construction cost. It may be configured to apportion with cable operators at a fixed rate.

本発明によれば、電磁誘導障害対策を行う必要のある送電線路近辺の有線事業者の顧客の規模および増加率により、光ファイバーを選択し、互いに有益であるので、費用を折半することが可能となり、電力会社は費用の節約ができ、有線事業者も将来行うかもしれない工事を早めに電力会社から工事費用の一部負担を受けた上で行うことができるので互いに費用の節約を行うことができる。   According to the present invention, it is possible to halve the cost because the optical fiber is selected and beneficial to each other depending on the scale and increase rate of the customers of the cable operators in the vicinity of the transmission line that need to take measures against electromagnetic induction disturbance. , Electric power companies can save money, and wire operators can also carry out the construction that may be done in the future after receiving a part of the construction cost from the electric power company, so it is possible to save money each other it can.

さらに上記工事見積支援システムは、電磁誘導障害対策を行う必要のある送電線路近辺の有線事業者の通信経路の情報を保存する通信経路データベースを備え、前記見積予測手段は、前記通信経路データベースより電磁誘導障害対策を行う必要のある工事区間を判定し、前記工事内容データベースより前記判定した工事区間の工事費用を算出するように構成するのも好ましい。   The construction estimation support system further includes a communication path database that stores information on a communication path of a wire operator in the vicinity of a transmission line that needs to take countermeasures against electromagnetic induction failure. It is also preferable to determine a construction section where it is necessary to take a countermeasure against inductive failure, and calculate the construction cost of the determined construction section from the construction content database.

本発明によれば、過去の実績と有線事業者の通信経路から、工事区間と工事内容を予測し、自動的に工事費用を算出することが可能となるので、電磁誘導障害対策に要する工数の削減が可能となり、有線事業者との工事内容の詰めも行いやすくなる。   According to the present invention, it is possible to predict the construction section and the construction contents from the past results and the communication route of the wire operator, and to automatically calculate the construction cost. This will make it possible to reduce the amount of work and work with the cable operator.

上記工事見積支援システムは、さらに送電線路の区間ごとに工事内容と工事に要する費用を記憶する標準見積データベースを備え、前記見積予測手段は、前記標準見積データベースを用いて工事区間ごとに工事内容と工事費用の概算を算出するように構成するのも好ましい。   The construction estimation support system further includes a standard estimation database for storing construction contents and costs required for construction for each section of the transmission line, and the estimate prediction means uses the standard estimation database to construct the construction contents for each construction section. It is also preferable to configure to calculate an approximate construction cost.

本発明によれば、過去の実績とは無関係に外部から登録することのできるデータベースを用いて見積をチェックすることができるので、例えば過去のチェックで信憑性が得られた工事内容とその工事費用を決定して標準見積データベースとして記憶し、比較することができる、時間を要することなくチェックを行うことができる。また、標準見積データベースとして他社の工事内容およびその工事費用を登録しておくことで、見積内容を比較することができるので、さまざまな見積の比較を行うことができ、確からしい見積額に迫ることが可能となる。   According to the present invention, the estimate can be checked using a database that can be registered from the outside regardless of the past results. For example, the construction content and the construction cost for which credibility was obtained by the past check. Can be determined, stored as a standard estimate database, and compared. Also, by registering the construction contents and construction costs of other companies as a standard estimate database, it is possible to compare the contents of the estimate, so it is possible to compare various estimates and approach the probable estimate. Is possible.

上記目的を達成するため、本発明に係わる工事見積支援方法は、予め定めた形式のデータとして与えられる見積情報から送電線路の区間と工事内容、および工事費用を読み取り、送電線路区間を複数の区間に分け、その区間ごとに行った工事内容、および要した工事費用を保存する工事内容データベースと合致した区間に分ける第1のステップと、前記工事内容データベースに蓄積された過去の工事区間および工事内容と、前記第1のステップにて分解された工事区間および工事内容を工事区間ごとに比較することで、指定された区間の工事内容に対して工事費用の概算を算出する第2のステップと、前記算出された概算費用と見積費用とを比較してその差分を抽出する第3のステップとを含むことを特徴とする。   In order to achieve the above object, the construction estimation support method according to the present invention reads the transmission line section, the construction content, and the construction cost from the estimate information given as data in a predetermined format, and sets the transmission line section as a plurality of sections. The first step of dividing the section into the section that matches the construction contents database that stores the construction contents performed for each section and the construction cost database required, and the past construction sections and construction contents accumulated in the construction contents database And a second step of calculating an estimate of the construction cost for the construction content of the designated section by comparing the construction section and construction content disassembled in the first step for each construction section; A third step of comparing the calculated estimated cost with the estimated cost and extracting the difference.

上記目的を達成するため、本発明に係わる工事見積支援プログラムは、工事の見積を行うコンピュータ上で動作するプログラムであって、予め定めた形式のデータとして与えられる見積情報から送電線路の区間と工事内容、および工事費用を読み取り、送電線路区間を複数の区間に分け、その区間ごとに行った工事内容、および要した工事費用を保存する工事内容データベースと合致した区間に分ける第1の処理と、前記工事内容データベースに蓄積された過去の工事区間および工事内容と、前記第1の処理にて分解された工事区間および工事内容を工事区間ごとに比較することで、指定された区間の工事内容に対して工事費用の概算を算出する第2の処理と、前記算出された概算費用と見積費用とを比較してその差分を抽出する第3の処理とをコンピュータ上で動作させることを特徴とする。   In order to achieve the above object, a construction estimation support program according to the present invention is a program that runs on a computer that estimates construction, and is based on estimation information given as data in a predetermined format, and a section of a transmission line and construction Read the content and construction cost, divide the transmission line section into a plurality of sections, and the first processing to divide the construction contents performed for each section and the section that matches the construction contents database to save the required construction cost, By comparing the past construction sections and construction contents accumulated in the construction content database with the construction sections and construction contents disassembled in the first processing for each construction section, the construction contents of the designated section are obtained. A second process for calculating an approximate construction cost, and a third process for extracting the difference by comparing the calculated approximate cost with the estimated cost. And wherein operating the on the computer.

本発明によれば、有線事業者が行う電磁誘導障害対策の工事の見積を工事区間ごとに分けてコンピュータにて処理が行えるようにデータベース化し、過去の工事も同様にデータベース化するので、比較が容易となり、見積を比較することで見積の妥当性の判断を容易に行うことができ、行う必要が無い工事の指摘を行ったり、工事に要する費用が過去の例と比較してとても高い場合はその内容を知ることができたりすることが可能となる。さらに工事に関する人の工数を削減でき、工事費用として余計に支払うことを抑制し適切な工事費用を算出し支払うことが可能となる。   According to the present invention, the estimation of the electromagnetic induction failure countermeasure work performed by the cable operator is divided into work sections and created as a database so that it can be processed by a computer. When it becomes easy, it is easy to judge the validity of the estimate by comparing the estimates, and when the construction cost that is not necessary is pointed out or the cost required for the construction is very high compared to the past examples It is possible to know the contents. Furthermore, the number of man-hours related to the construction can be reduced, and it becomes possible to calculate and pay an appropriate construction cost while suppressing the extra payment as the construction cost.

以下、本発明の実施の形態を説明する。図1は本発明の第1の実施の形態に係わる工事見積支援システム及びこのシステムと通信を行う部門端末の機能ブロック図である。   Embodiments of the present invention will be described below. FIG. 1 is a functional block diagram of a construction estimate support system and a department terminal that communicates with the system according to the first embodiment of the present invention.

図1において、工事見積支援システムは、LAN(Local Area Network)4を介して部門端末3と繋がっている。   In FIG. 1, the construction estimate support system is connected to a department terminal 3 via a LAN (Local Area Network) 4.

ここで、工事見積支援システム1は受発注情報を管理する総務部門またはサービス事業者などにより管理、運営される。また、部門端末3は、システムの操作者である社員が属する部門の一または二以上の端末装置である。   Here, the construction estimation support system 1 is managed and operated by a general affairs department or a service provider who manages ordering information. The department terminal 3 is one or more terminal devices of departments to which employees who are operators of the system belong.

工事見積支援システム1は、LAN(Local Area Network)4を介してデータの送受信を行うための送受信部12、送受信部12から受け取ったデータの処理、およびその他のさまざまな処理を行う中央演算処理部13、データを記憶するための記憶部14、および、中央演算処理部13との間でデータの入出力を行う入力部15と表示部16から構成されている。   The construction estimation support system 1 includes a transmission / reception unit 12 for transmitting / receiving data via a LAN (Local Area Network) 4, a central processing unit for processing data received from the transmission / reception unit 12, and various other processes. 13 includes a storage unit 14 for storing data, an input unit 15 for inputting / outputting data to / from the central processing unit 13, and a display unit 16.

さらに、中央演算処理部13は、送受信部12との間でデータの受け渡しを行う送受信処理手段(機能)131、入力部15あるいは表示部16とデータの受け渡しを行う入出力処理手段(機能)132、入出力処理手段(機能)132または送受信処理手段131を介して受信した工事費用などの情報を登録する情報登録手段(機能)133、受信した見積から区間別に分けた送電線路に見積内容を展開する見積情報分析手段(機能)134、与えたれた工事区間の工事の見積を過去のデータベースを用いて行う見積予測手段(機能)135、受信した見積内容と、算出した見積予測内容とを比較してその結果を出力する見積比較手段136、受信した見積の妥当性を過去のデータベースなどを用いて判断する見積妥当性判断手段137、受信した見積内容と予測した見積予測内容とを図示化する見積図示化手段138から構成される。   Further, the central processing unit 13 is a transmission / reception processing means (function) 131 that exchanges data with the transmission / reception unit 12, and an input / output processing means (function) 132 that exchanges data with the input unit 15 or the display unit 16. , Information registration means (function) 133 for registering information such as construction costs received via the input / output processing means (function) 132 or the transmission / reception processing means 131, and expanding the estimate contents to the transmission lines divided by section from the received estimate Estimating information analyzing means (function) 134, estimating estimate means (function) 135 for performing construction estimation of a given construction section using a past database, comparing the received estimate content with the calculated estimate prediction content Estimate comparison means 136 for outputting the result, estimate validity judgment means 137 for judging the validity of the received estimate using a past database, etc. It consists estimate shown means 138 for the illustrating an estimated prediction contents predicted signal was estimated content.

また、記憶部14は、過去の工事内容を送電線路ごとに区間に分けて記憶する工事内容データベース(DB)151、受信した見積を見積対象の送電線路の区間ごとに展開した見積データベース(DB)152、対象となる送電線路の対象となる区間ごとに見積予測を行った結果を記憶する見積予測データベース(DB)153、受信した見積情報で見積DB152に展開された内容と、予測した見積予測情報で見積予測DB153に記憶された情報を比較して抽出した差分を記憶する見積比較結果データベース(DB)154、受信した見積情報により、工事が発生する区間を抽出した結果を記憶する見積路線データベース(DB)155から構成されている。   In addition, the storage unit 14 is a construction content database (DB) 151 that stores past construction content divided into sections for each transmission line, and an estimated database (DB) that expands the received estimate for each section of the transmission line to be estimated. 152, an estimate prediction database (DB) 153 that stores the result of estimate prediction for each target section of the target transmission line, the contents developed in the estimate DB 152 with the received estimate information, and estimated estimate prediction information An estimated comparison result database (DB) 154 for storing the difference extracted by comparing the information stored in the estimated prediction DB 153, and an estimated route database (for storing the result of extracting the section where the construction occurs based on the received estimated information) DB) 155.

端末3は、LAN(Local Area Network)4を介してデータの送受信を行うための送受信部32、送受信部32からのデータの処理を行う中央演算処理部33、中央演算処理部33との間でデータの入出力を行う入力部35および表示部36から構成されている。   The terminal 3 includes a transmission / reception unit 32 for transmitting / receiving data via a LAN (Local Area Network) 4, a central processing unit 33 for processing data from the transmission / reception unit 32, and the central processing unit 33. An input unit 35 for inputting / outputting data and a display unit 36 are included.

図2に、電磁誘導障害対策の対策について示す。防磁対策としては、項番ごとに、何も行う必要が無いことを表す「なし」、「防磁シールド」、「電柱への地絡線」、「光ファイバー化」などが登録されており、これから説明するデータベース内にはこの項番が登録される。   FIG. 2 shows countermeasures against electromagnetic induction disturbance. As anti-magnetic measures, “None”, “Magnetic shield”, “Earth line to power pole”, “Optical fiber”, etc. indicating that there is no need to do anything are registered for each item number. This item number is registered in the database.

図3に、見積DB152のデータ構成例を示す。この見積は、有線事業者から提出される見積情報を対象の送電線路の区間ごとに費用などを展開したものであり、変電所からの距離ごとに管理番号が付与され、その管理番号ごとにその区間が工事対象であるのか/無いのかを示すフラグと、工事内容として、図2で示している工事内容を表す項番と、見積もられた費用が保存されている。   FIG. 3 shows a data configuration example of the estimate DB 152. This estimate expands the cost for each section of the target transmission line based on the estimate information submitted by the cable operator, and a management number is assigned for each distance from the substation. A flag indicating whether the section is subject to construction or not, a construction number, an item number representing the construction content shown in FIG. 2, and an estimated cost are stored.

この区間は、例えば1Kmごともしくは2Kmごとなどと修正可能である。もしくは何らかの事情があれば不規則な距離の羅列(送電柱間の距離など)でも良い。図3においては、○○送電所から0〜1(Km)間は、工事対象(1)であり、工事の内容は「防磁シールド」(項番1)であり、工事費用として1,000を要することを示している。   This section can be corrected, for example, every 1 km or every 2 km. Or, if there are some circumstances, it may be an irregular distance (such as the distance between transmission poles). In Fig. 3, the area between 0 and 1 (Km) from the XX power transmission station is the construction object (1), the construction content is "magnetic shield" (item No. 1), and the construction cost is 1,000. It shows that it is necessary.

図4は、見積路線DB155のデータ構成例を示す。このデータベースは見積から有線事業者が工事を行うと判断した区間を抽出して記憶させるものであり、前記見積DB152において工事対象になっている区間を、○○変電所からの距離に応じて付与された管理番号に対して工事の有無を「工事対象」の欄に記載しているものである。本実施の形態では見積DB152から工事内容と見積費用の欄を削除した構成になっているが、その後の処理にとって便利なようにデータ構成を変更しても良い。   FIG. 4 shows a data configuration example of the estimated route DB 155. This database extracts and stores sections that are determined by the wireline operator to perform construction from estimates, and assigns sections that are subject to construction in the estimate DB 152 according to the distance from the XX substation. The presence or absence of construction for the assigned control number is described in the “Construction” column. In the present embodiment, the construction contents and the estimated cost columns are deleted from the estimate DB 152, but the data configuration may be changed so as to be convenient for the subsequent processing.

図5に、過去の防磁対策を記憶している工事内容DB151のデータ構成例を示す。工事内容DB151は、全ての電磁誘導障害対策の対象となる送電線路ごとにその変電所からの距離を基にして区間を定め管理番号を付与し、その管理番号ごとに過去に行った工事内容とその時に要した費用、工事日および担当した工事業者が年度順に並んで記憶されている。年度順、工事内容、費用ごとにソートする機能があることが望ましい。特に年度順に並んでいることは本発明の実施に当たって必要な条件ではない。   FIG. 5 shows a data configuration example of the construction content DB 151 that stores past magnetic-shielding measures. The construction content DB 151 determines a section based on the distance from the substation for each transmission line that is the target of all electromagnetic induction failure countermeasures, and assigns a management number. The expenses required at that time, the date of construction, and the contractor in charge were memorized in order of year. It is desirable to have a function that sorts by year, construction content, and cost. In particular, it is not a necessary condition for carrying out the present invention that they are arranged in order of year.

図6に、過去の情報により予測した見積予測DB153にデータ構成例を示す。本実施の形態ではみ見積DB152と類似した構成が分かりやすく説明しやすいため同じような構成にしているが、記憶される内容に違いが無ければ記憶の構成は異なっていても良い。図6では、見積予測DB153は見積根拠の項目が追加されているのが見積DB152と異なる点である。この見積根拠には参照するポイントが記憶されており、過去の工事内容とリンクしているものであり、見積予測値の根拠を容易に参照できるように記憶させるものである。   FIG. 6 shows a data configuration example in the estimated prediction DB 153 predicted based on past information. In the present embodiment, a configuration similar to the copy estimation DB 152 is easy to understand and easy to explain, and the same configuration is used. However, if there is no difference in the stored contents, the storage configuration may be different. In FIG. 6, the estimate prediction DB 153 is different from the estimate DB 152 in that an item of estimate basis is added. The points to be referred to are stored in the basis of this estimate, and are linked to the past construction contents, and are stored so that the basis of the estimated predicted value can be easily referred to.

また、見積費用の項目は見積DB152と同じであるが、この欄には過去の工事情報より見積予測手段135が予測した見積額が記憶される。   Moreover, although the item of estimated cost is the same as that of the estimate DB 152, the estimated amount predicted by the estimate predicting means 135 from the past construction information is stored in this column.

図7および図8に、見積比較結果DB154のデータ構成例を示す。図7のデータ構成例では、対象の送電線路の管理番号ごとに実際の見積と見積予測の工事内容と、それぞれの見積額、および見積額の差分が記憶される。このデータは見積比較手段136が作成するものである。また図8のデータ構成例では、図7で説明した項目に加えて、工事内容の「OK」、「NG」などの結果の欄と、見積額の結果の欄と、「重複工事」の有無の調査結果の欄と、「OK」、「NG」で表される最終的な結果を示す「最終結果」の欄が追加になっている。上記説明した欄は、見積妥当性判断手段137が見積の比較結果を参照して入力する欄である。   7 and 8 show data configuration examples of the estimated comparison result DB 154. FIG. In the data configuration example of FIG. 7, the actual estimate and the construction work of the estimate prediction, the estimated amount, and the difference between the estimated amounts are stored for each management number of the target transmission line. This data is created by the estimate comparison unit 136. In addition to the items described in FIG. 7, in the data configuration example of FIG. 8, a column of results such as “OK” and “NG” of the construction content, a column of the result of the estimated amount, and the presence of “duplicate construction” And a “final result” column indicating final results represented by “OK” and “NG” are added. The above-described column is a column that is input by the estimate validity determination unit 137 with reference to the comparison result of the estimate.

図9に、電磁誘導障害に対策するための電磁誘導障害対策工事の流れの概略を示す。まず電力会社は電磁誘導障害が発生する工事の予定情報を予め有線事業者に通知する(F91)。工事予定情報を受信した有線事業者は影響範囲などを見定め、見積情報を作成し、電力会社に送信する(F92)。本実施の形態では見積情報は印刷された文書でも良いが、電子化された文書である方が望ましい。
見積情報を受信した電力会社は、その見積情報より、有線事業者が工事しようとしている送電線路の工事の区間を特定し、見積路線DB155に記憶させる(F93)とともに、送電線路にて区間に分けて見積情報を展開する(F94)。見積情報の展開とは、区間ごとに工事内容およびその費用を特定し見積DB152の対応するエリアに記憶させることである。
FIG. 9 shows an outline of the flow of electromagnetic induction failure countermeasure construction for countermeasures against electromagnetic induction failures. First, the power company notifies the wireline company in advance of construction schedule information that causes an electromagnetic induction failure (F91). The cable operator who received the construction schedule information determines the influence range and the like, creates estimate information, and transmits it to the power company (F92). In this embodiment, the estimate information may be a printed document, but it is preferably a digitized document.
The power company that has received the estimate information identifies the section of the transmission line construction that the cable operator is going to construct from the estimate information, stores it in the estimated route DB 155 (F93), and divides the section into sections on the transmission line The estimate information is expanded (F94). The expansion of the estimate information is to identify the construction content and its cost for each section and store them in the corresponding area of the estimate DB 152.

次に、見積予測手段135は、見積情報分析手段134が抽出して区間ごとに工事の有無などを記憶させた見積路線DB155と、過去の工事内容および工事費用が区間ごとに記憶されている工事内容DB151とにアクセスして(F95、F96)、過去の実績にそった見積の予測を行い、その結果を見積予測DB153に記憶させる(F97)。   Next, the estimate predicting means 135 is an estimated route DB 155 extracted by the estimate information analyzing means 134 and storing the presence / absence of construction for each section, and a construction in which past construction contents and construction costs are stored for each section. The contents DB 151 is accessed (F95, F96), an estimate is predicted according to past results, and the result is stored in the estimate prediction DB 153 (F97).

次に、見積比較手段136は、区間ごとに展開された見積情報と、予測した見積予測情報とを比較して(F98、F99)その差分を抽出し、見積比較結果DB154に記憶させる(F9A)。それから見積妥当性判断手段137は、記憶された見積情報と見積予測情報との差分によりその見積の妥当性を判断し、見積が決定した際には、その見積を工事内容DB151に追記する(F9B)。   Next, the estimate comparison means 136 compares the estimated information developed for each section with the estimated estimate prediction information (F98, F99), extracts the difference, and stores it in the estimate comparison result DB 154 (F9A). . Then, the estimate validity determination means 137 determines the validity of the estimate based on the difference between the stored estimate information and the estimate prediction information. When the estimate is determined, the estimate is added to the construction content DB 151 (F9B). ).

工事見積支援システムは以上のように構成され、その動作の詳細について以下に説明する。   The construction estimation support system is configured as described above, and details of its operation will be described below.

[1.情報登録段階]
本工事見積支援システムの管理者は、入力部15に接続される、例えばキーボードまたはマウスなどの入力装置および表示部16に接続されているディスプレイなどの画面で確認しながら図2に示す電磁誘導障害対策の対策内容および有線事業者などの情報、および送電線路の区間の分け方などの情報を入力する。入力された電磁誘導障害対策の情報は情報登録手段133により記憶部14の内に保存される。
[1. Information registration stage]
The administrator of the construction estimation support system checks the electromagnetic induction failure shown in FIG. 2 while checking the input device 15 such as a keyboard or mouse connected to the input unit 15 and a screen such as a display connected to the display unit 16. Enter the details of the countermeasure, information on the cable operator, etc., and information on how to divide the section of the transmission line. The inputted information on countermeasures against electromagnetic induction failure is stored in the storage unit 14 by the information registration unit 133.

同様に図示してはいないが、有線事業者の社名や電話番号などの情報および送電線路の区間の分け方なども情報登録手段133により記憶部14の対応するエリアに保存される。   Similarly, although not shown in the figure, information such as the company name and telephone number of the wire operator and how to divide the section of the transmission line are also stored in the corresponding area of the storage unit 14 by the information registration unit 133.

[2.見積受信段階]
見積情報を受信した後の動作について図10のフローチャートを用いて説明する。図10の動作は見積情報分析手順134が行う動作である。
[2. Estimate reception stage]
The operation after receiving the estimate information will be described with reference to the flowchart of FIG. The operation in FIG. 10 is performed by the estimate information analysis procedure 134.

有線事業者から見積情報を受信する(S101)と、工事見積支援システム1の見積情報分析手段134は、受信した見積内容より、送電路線を確定し、確定した送電路線を予め定めた、例えば送電線からの距離などによる区間の分け方、または送電柱の間隔にて区間を分けるなどの方法を用いて送電路線を区間に分ける(S102)。図5に示す本実施の形態による工事内容DB151では、変電所から、例えば1Kmごとの等間隔で区間を分けている。次にその区間ごとに対応する区間が工事対象であるのかを判断し(S103)、工事対象であれば、見積路線DB155に工事対象であることを記載する(S104)。   When the estimate information is received from the wire operator (S101), the estimate information analysis means 134 of the construction estimate support system 1 determines the transmission line from the received estimate contents, and determines the determined transmission line in advance, for example, transmission The transmission line is divided into sections using a method of dividing the sections based on the distance from the electric wires or the like, or a method of dividing the sections based on the distance between the power transmission columns (S102). In the construction content DB 151 according to the present embodiment shown in FIG. 5, sections are divided from the substation at regular intervals, for example, every 1 km. Next, it is determined whether the section corresponding to each section is a construction target (S103), and if it is a construction target, the fact that it is a construction target is described in the estimated route DB 155 (S104).

本フローチャートでは工事対象で無い場合は何もしないことになるが、工事非対象であることを記載しても良い。   In this flowchart, nothing is done if it is not a construction target, but it may be described that it is not a construction target.

次に区間ごとに見積情報の内容を工事内容とその費用を見積DB152に登録する(S105)。次に全ての区間の処理を終了したかを判断し(S106)、終了していない場合は次の区間を指定して上記動作を繰り返す(S107)。対象の送電線路の全ての区間の処理がが終了した場合は動作を終了する(S106のyesのルート)。   Next, the contents of the estimate information for each section are registered in the estimate DB 152 with the contents of the construction and the cost (S105). Next, it is determined whether or not the processing for all the sections has been completed (S106). If not, the next section is designated and the above operation is repeated (S107). When the processing of all sections of the target transmission line is finished, the operation is finished (yes route in S106).

[3.見積予測段階]
対象の送電線路の対象の工事区間が判明した後に、それらの工事の費用の予測を行う処理を図11のフローチャートを用いて説明する。図11の動作は見積予測手段135が行う動作である。
[3. Estimated forecast stage]
After the target construction section of the target transmission line is found, a process for predicting the cost of the construction will be described with reference to the flowchart of FIG. The operation of FIG. 11 is an operation performed by the estimation prediction unit 135.

まず判明した工事対象区間を見積対象区間とする(S111)。次に見積対象区間の過去の工事内容を全ての送電路線の同一区間において統計を取り(S112)、一番頻度の高い工事内容を見積予測の工事内容とする(S113)。図5を用いて説明すると、各送電線路の変電所からのある位置での過去の工事内容が示されているが、これらの工事内容と、さらに次の送電線路の同一区間の工事内容についても同様に統計をとる。   First, the found construction target section is set as an estimation target section (S111). Next, the past construction contents of the section to be estimated are statistically taken in the same section of all the transmission lines (S112), and the construction frequency with the highest frequency is set as the construction contents for estimation prediction (S113). Referring to FIG. 5, the past construction contents at a certain position from the substation of each transmission line are shown. However, these construction contents and the construction contents of the same section of the next transmission line are also described. Take statistics as well.

次に過去の防磁対策を記憶している工事内容DB151を参照して、他の送電線路の同一区間を含む区間で、工事内容が見積予想工事内容と同一の場合の工事費用の平均値を算出する(S114)。算出した平均の工事費用を見積予測の工事内容における見積費用として見積予測DB153の対応欄に保存する(S115)。   Next, with reference to the construction content DB 151 storing past magnetic-shielding measures, the average value of construction costs is calculated when the construction content is the same as the estimated construction details in the section including the same section of other transmission lines. (S114). The calculated average construction cost is stored in the corresponding column of the estimate prediction DB 153 as an estimate cost in the estimate prediction work contents (S115).

次に全ての区間の処理を終了したか判断し(S116)、まだ処理する区間が残っている場合は、次の区間を指定して(S117)上記動作を繰り返す。全ての区間の処理が終了していた場合は処理を終了する(S116のyesのルート)。上記動作によって、過去の全送電線路の同一区間にて行っている工事内容で一番多かった工事内容とその工事における平均の費用を見積予想として決定することができる。   Next, it is determined whether the processing for all the sections has been completed (S116). If there are still sections to be processed, the next section is designated (S117) and the above operation is repeated. If all sections have been processed, the process ends (yes route in S116). By the above operation, it is possible to determine, as an estimated forecast, the construction content that has been most frequently performed in the same section of all transmission lines in the past and the average cost of the construction.

[4.見積比較段階]
次に見積もりの比較を行い、見積比較結果DB154を作成する動作について図12のフローチャートと図8に示す見積比較結果DB154を用いて説明する。本動作は見積比較手段136が行う動作である。
[4. Estimate comparison stage]
Next, the operation of comparing the estimates and creating the estimate comparison result DB 154 will be described using the flowchart of FIG. 12 and the estimate comparison result DB 154 shown in FIG. This operation is performed by the estimation comparison unit 136.

作成された見積DB152より、対象の送電線路の指定区間の工事内容を見積比較結果DB154の該当の欄に書き込む(S121)。同様に予測した見積において見積予測DB153より、対象の送電線路の指定区間の工事内容を見積比較結果DB154の該当の欄に書き込む(S122)。工事対象の区間について、見積DB152より工事費用を、見積予測DB153より工事見積費用を該当の欄に書き込む(S123、S124)。   From the created estimate DB 152, the construction details of the designated section of the target transmission line are written in the corresponding column of the estimate comparison result DB 154 (S121). Similarly, in the estimated prediction, the construction content of the designated section of the target transmission line is written in the corresponding column of the estimated comparison result DB 154 from the estimated prediction DB 153 (S122). For the section to be constructed, the construction cost is written from the estimated DB 152 and the construction estimated cost from the estimated prediction DB 153 into the corresponding columns (S123, S124).

次に対象送電線路の全ての区間の処理が終了したか判断し(S125)、終了していなければ、次の区間を指定して上記の動作を繰り返す(S126)。終了していれば動作を終了する(S125のyesのルート)。   Next, it is determined whether the processing of all sections of the target transmission line has been completed (S125). If not, the next section is designated and the above operation is repeated (S126). If completed, the operation is terminated (yes route of S125).

[5.見積妥当性判断段階]
次に受信した見積情報と予測した見積予測情報の妥当性を見積比較結果DB154を用いて判断する動作を図13のフローチャートおよび図8に示す見積比較結果DB154を用いて説明する。本動作は見積妥当性判断手段137が行う動作である。
[5. Estimate validity judgment stage]
Next, the operation of determining the validity of the received estimated information and the estimated estimated prediction information using the estimated comparison result DB 154 will be described using the flowchart of FIG. 13 and the estimated comparison result DB 154 shown in FIG. This operation is performed by the estimated validity determination unit 137.

まず指定された区間の工事内容について、見積と見積もり予測で異なっているかを判断する(S131)。同じであれば図8に示す見積比較結果DB154の工事内容の結果の欄に「OK」を書き込む(S132)。異なっていれば「NG」を書き込む(S133)。本実施形態では「OK」、「NG」の文字列を書き込むことにしているが、「OK」を「1」で、「NG」を「0」で表すなどは可能である。   First, it is determined whether the construction contents in the designated section are different between the estimate and the estimate prediction (S131). If they are the same, “OK” is written in the column of the result of construction in the estimate comparison result DB 154 shown in FIG. 8 (S132). If they are different, “NG” is written (S133). In the present embodiment, the character strings “OK” and “NG” are written, but “OK” can be represented by “1”, “NG” can be represented by “0”, and the like.

工事内容が同じであった場合は、次に工事の見積費用を比較する(S134)。本実施の形態の場合は、見積費用が見積予想費用額から、ある定めた、例えば10%を超えない場合は許容範囲であると判断し、見積比較結果DB154の見積額の結果の欄に「OK」を書き込む(S135)。この許容範囲については別途定め、記憶部14にデータとして保存し、その内容を取得した上で上記動作を行うことが可能である。許容範囲外であった場合は、見積比較結果DB154の上記該当欄「NG」を書き込む(S136)。   If the construction contents are the same, the estimated construction costs are then compared (S134). In the case of the present embodiment, it is determined that the estimated cost is within an allowable range if the estimated cost does not exceed 10%, for example, from the estimated estimated cost amount. "OK" is written (S135). The permissible range can be determined separately, stored as data in the storage unit 14, and the above operation can be performed after acquiring the contents. When it is out of the allowable range, the corresponding column “NG” in the estimated comparison result DB 154 is written (S136).

次に工事の重複を判断するため、前回と同じ工事を行っていないかを判断する(S137)。重複していた場合は、見積比較結果DB154の「重複工事」の欄に「NG」を書き込み(S138)、重複していない場合は、「OK」を書き込む(S139)。次に、全ての区間の処理を終了したかを判断し(S13A)、終了していない場合は、次の区間を指定して上記処理を繰り返す(S13B)。全区間の処理が終了していた場合は動作を終了する(S13Aのyesのルート)。
以上の動作により、受信した見積の妥当性を過去の実績を参照することで判断する。
Next, in order to determine the duplication of the construction, it is judged whether or not the same construction as the previous time has been performed (S137). If there is a duplication, “NG” is written in the “duplicate construction” column of the estimate comparison result DB 154 (S138), and if there is no duplication, “OK” is written (S139). Next, it is determined whether or not the processing for all the sections has been completed (S13A). If not, the next section is designated and the above processing is repeated (S13B). If the processing for all the sections has been completed, the operation ends (yes route of S13A).
With the above operation, the validity of the received estimate is determined by referring to the past results.

[6.見積、見積予測の図示化]
分析した見積内容である見積DB152と、区間ごとに過去の工事内容を参照して見積った見積予測DB153を用いて、操作者が判断しやすいように図示化を行う動作を図14に示すフローチャートを用いて説明する。本動作は見積図示化手段138が行う動作である。
[6. Illustrate estimates and estimate forecasts]
FIG. 14 is a flowchart showing an operation for performing illustration using the estimate DB 152 which is the analyzed estimate contents and the estimate prediction DB 153 estimated by referring to the past construction contents for each section so that the operator can easily judge. It explains using. This operation is an operation performed by the quotation plotting means 138.

まず、見積DB152より、指定区間の工事内容と工事費用を取得する(S141)。同様に見積予測DB153より、指定区間の予測した工事内容と工事費用を取得する(S142)。次に取得した見積の工事内容及び工事費用と、見積予測した工事内容および工事費用を指定の区間において図15に示すようにグラフ化する(S143)。次に全区間の処理が終了したか判断し(S144)、終了していない場合は次の項目を指定して上記動作を繰り返す(S145)。終了した場合は動作を終了する(S144のyesのルート)。
本発明による第1の実施の形態は以上のように構成され動作する。
First, the construction content and construction cost of the designated section are acquired from the estimate DB 152 (S141). Similarly, the construction content and construction cost predicted for the designated section are acquired from the estimate prediction DB 153 (S142). Next, the estimated construction content and construction cost obtained and the estimated construction content and construction cost estimated are graphed as shown in FIG. 15 in the designated section (S143). Next, it is determined whether or not the processing for all sections has been completed (S144). If not, the next item is designated and the above operation is repeated (S145). If completed, the operation ends (yes route in S144).
The first embodiment of the present invention is configured and operates as described above.

本実施の形態によれば、電磁誘導障害の対策工事の見積の予測を対象の送電線路の区間ごとに分類した過去の工事内容および工事費用により行うことが可能となり、受信した新たな見積情報を上記区間ごとに分けて展開することで、見積予測と比較することが可能となり、見積予測と合致しない部分について出力することが可能となるので、見積情報に間違いがあったり、予測と異なる見積もりを行っていた場合に指摘が可能となり支払う必要の無い工事費用の出費を抑制するができる。   According to the present embodiment, it is possible to predict the estimate of the electromagnetic induction failure countermeasure construction work based on the past construction contents and construction costs classified for each section of the target transmission line, and receive the received new estimate information. By expanding each section above, it is possible to compare with the estimated forecast, and it is possible to output the part that does not match the estimated forecast, so there is an error in the estimate information or an estimate different from the forecast If it has been done, it is possible to point out, and it is possible to reduce the cost of construction costs that do not need to be paid.

次に第2の実施の形態について以下に説明する。図16に、見積予測のフローチャートを示すが、第2の実施の形態では見積の傾向を加味して工事内容及び工事費用の見積額を算出するものである。   Next, a second embodiment will be described below. FIG. 16 shows a flowchart of the estimation prediction. In the second embodiment, the estimated contents of the construction contents and the construction cost are calculated in consideration of the tendency of the estimation.

図16は、本実施の形態による見積予測手段135が行う処理手順を示すフローチャートである。図16において、ステップS163と、ステップS164が既に説明を行った図11と異なる部分である。傾向を見るということで、最近の数件〜数10件の工事内容およびその時に要した工事費用を分析し、その変化率を算出し確からしいと判断される工事内容および工事に要する費用の見積を予測する。   FIG. 16 is a flowchart showing a processing procedure performed by the estimate predicting means 135 according to this embodiment. In FIG. 16, step S163 and step S164 are different from FIG. 11 already described. By looking at the trend, we analyze the recent several to several tens of work contents and the construction cost required at that time, calculate the rate of change, and estimate the construction contents and the cost required for construction Predict.

例えば、対象の工事区間において、過去最近の10件を抽出し、その工事内容と要した費用を取得し、工事内容の変化の度合いおよび工事内容が同じ工事費用の変化の度合いを判定し工事内容を決定し(S163)、その工事内容に合った工事見積費用を、最近の、例えば10件の工事費用の平均値を出すことで算出する(S164)。ステップS164において、工事費用の産出は、工事費用の変化率を求めて平均値からの差分を加算もしくは減算するようにしても良い。
本発明による第2の実施の形態は以上のように構成され動作する。
For example, in the target construction section, the latest 10 cases are extracted, the contents of the construction and the required costs are acquired, the degree of change in the construction contents and the degree of change in the construction costs with the same construction contents are determined, and the construction contents Is determined (S163), and a construction estimated cost suitable for the construction content is calculated by calculating an average value of, for example, 10 recent construction costs (S164). In step S164, the construction cost may be generated by calculating the rate of change of the construction cost and adding or subtracting the difference from the average value.
The second embodiment of the present invention is configured and operates as described above.

本実施の形態によれば、工事内容を過去最近の工事内容を鑑みて決定し、さらにその工事費用を過去最近の平均額もしくは過去最近の平均額に変化率を加えた額を算出することでより現実に近い見積もりの予測が可能となる。   According to this embodiment, the construction content is determined in view of the past recent construction content, and the construction cost is calculated by calculating the past recent average amount or the past recent average amount plus the rate of change. It is possible to predict a more realistic estimate.

次に第3の実施の形態について以下に説明する。図17に、過去の防磁対策が保存されている工事内容DB151の第3の実施の形態におけるデータ構成例を示す。本実施の形態では、工事内容DB151に記憶する内容として、変電所からの距離で区分された区間に加えて、その区間における工事が行われる箇所の送電線路からの距離を含めていることが異なる。   Next, a third embodiment will be described below. FIG. 17 shows a data configuration example in the third embodiment of the construction content DB 151 in which past magnetic-shielding measures are stored. In the present embodiment, the content stored in the construction content DB 151 is different from the section divided by the distance from the substation, in addition to the distance from the transmission line at the location where the construction is performed in that section. .

送電線路からの距離をパラメータとして含むことで、電磁誘導障害の発生が送電線路からの距離に依存していたり、距離によって障害の大きさが異なり、対策も異なる場合において、その送電線線路からの距離ごとに電磁誘導障害対策をより詳細に管理したりすることが可能となる。   By including the distance from the transmission line as a parameter, the occurrence of electromagnetic induction failure depends on the distance from the transmission line, or the magnitude of the failure differs depending on the distance and the countermeasures are different. It becomes possible to manage electromagnetic induction failure countermeasures in more detail for each distance.

この場合、図10に示す見積情報分析手段134のフローチャートにおいては、区間ごとにさらに距離ごとに見積DB152に工事内容と工事費用を登録する処理となる。また、図11に示す見積予測手段135のフローチャートにおいては、ステップS112において対象区間の工事内容の統計を取るに際してさらに送電線路からの距離に応じて統計を取るようにする。また、ステップS114において、工事費用の平均値も対象区間の送電線路の距離ごとに平均値を算出し、さらにステップS115において算出した工事費用の平均額も対象の工事区間ごとにさらに送電線路からの距離ごとに行うことになる。   In this case, in the flowchart of the estimate information analysis means 134 shown in FIG. 10, the construction content and construction cost are registered in the estimate DB 152 for each section and for each distance. Further, in the flowchart of the estimation predicting means 135 shown in FIG. 11, when statistics of the construction contents of the target section are obtained in step S112, statistics are further taken according to the distance from the transmission line. In step S114, the average construction cost is also calculated for each distance of the transmission line in the target section, and the average construction cost calculated in step S115 is further calculated from the transmission line for each target construction section. This is done for each distance.

また、図12に示す見積比較手段136のフローチャートにおいては、工事内容および見積費用および見積予測工事費用を送電線路の距離ごとに見積比較結果DB154に書き込む。   Further, in the flowchart of the estimate comparison unit 136 shown in FIG. 12, the construction content, the estimated cost, and the estimated predicted construction cost are written in the estimated comparison result DB 154 for each distance of the transmission line.

図13に示す見積妥当性判断手段137のフローチャートにおいては、ステップS131において、工事内容の比較は対象区間と距離に応じて行い、ステップS134において、見積額の差分が範囲内かを判断するに際しても、対象区間の対象の送電線路からの距離に応じて行い、ステップS137において、前回と同じ工事を行っているかの判断も対象区間の送電線路からの距離に応じて行う。   In the flowchart of the estimated validity determining means 137 shown in FIG. 13, the construction contents are compared in accordance with the target section and distance in step S131, and it is also determined in step S134 whether the difference in estimated amount is within the range. Depending on the distance from the target power transmission line of the target section, in step S137, whether the same construction as the previous work is being performed is also determined according to the distance from the power transmission line of the target section.

図14に示す見積もりの図示化についても、各対象区間に対してさらに送電線路からの距離に応じて図示化を行うこととなる。
本発明による第3の実施の形態は以上のように構成され動作する。
The illustration of the estimation shown in FIG. 14 is also illustrated for each target section according to the distance from the transmission line.
The third embodiment of the present invention is configured and operates as described above.

本実施の形態によれば、区間に加えてその区間の送電線路からの距離で工事を管理することで、より詳細な工事内容および工事費用を管理し、詳細な見積予測を行うことができる。特に電磁誘導障害が送電線路からの距離に依存する部分についてはより詳細にカバーできることになる。よって有線事業者の見積において過剰な対策を施そうとしていないかの判断が可能となる。   According to the present embodiment, in addition to a section, the construction is managed by the distance from the transmission line in the section, so that more detailed construction contents and construction costs can be managed and a detailed estimate can be predicted. In particular, the portion where the electromagnetic induction disturbance depends on the distance from the transmission line can be covered in more detail. Therefore, it is possible to determine whether or not excessive measures are being taken in the estimation of the wire operator.

次に第4の実施の形態について以下に説明する。図18に、送電線路に係わる有線事業者が有する通信経路の情報と、その区間での有線事業者の顧客の数およびその伸び率を保存する通信経路DB156の構成例を示す。この通信経路DB156は図1に示す工事見積支援システム1のブロック図内の記憶部14内に保存されるものであり、破線で示している。また、本情報は有線事業者から情報を入手して電力会社が作成する、もしくは有線事業者が作成したものを電力会社がデータベースに登録するようにする。   Next, a fourth embodiment will be described below. FIG. 18 shows a configuration example of the communication path DB 156 that stores information on the communication path possessed by the wired operator related to the power transmission line, the number of customers of the wired operator in the section, and the growth rate thereof. This communication path DB 156 is stored in the storage unit 14 in the block diagram of the construction estimation support system 1 shown in FIG. 1, and is indicated by a broken line. In addition, this information is obtained by the power company by obtaining information from the cable company, or the power company registers the information created by the cable company in the database.

本実施の形態では、見積予測手段135が行う動作にて、図19のフローチャートを用いて説明する。図19において図11と異なる部分はステップS191とステップS111の部分のみでありその他のステップに変更は無いのでステップS191についてのみ説明する。   In the present embodiment, the operation performed by the estimate prediction unit 135 will be described with reference to the flowchart of FIG. 19 is different from FIG. 11 only in steps S191 and S111, and the other steps are not changed, so only step S191 will be described.

図11のステップS111では工事区間を特定するのに、受信した見積から見積情報分析手段134が分析した工事区間を抽出してその後は工事区間ごとの処理を行っていたが、図19ではステップS191において、送電線路に対する通信経路DB156を用いて工事区間を予測してその予測した工事区間で以降の工事区間ごとの動作を行うものである。   In step S111 in FIG. 11, the construction section is specified, and the construction section analyzed by the estimate information analysis unit 134 is extracted from the received estimate. Thereafter, the processing for each construction section is performed, but in FIG. 19, step S191 is performed. , The construction route is predicted using the communication path DB 156 for the power transmission line, and the operation for each subsequent construction zone is performed in the predicted construction zone.

図18に示す通信経路DB156のデータ構成例において通信系DB156は、送電線路ごとの区間ごとに送電線路からの距離情報を有し、その距離の範囲内の通信経路の数、顧客の数および顧客の伸び率を保存している。ステップS191では、この通信経路の数により工事する区間を特定するものである。   In the data configuration example of the communication path DB 156 shown in FIG. 18, the communication system DB 156 has distance information from the power transmission line for each section of the power transmission line, and the number of communication paths, the number of customers, and the customers within the distance range. Preserved growth rate. In step S191, the construction section is specified by the number of communication paths.

本実施の形態によれば、通信経路DB156を有することで、電磁誘導障害対策が必要となる電力工事が発生する際に、有線事業者から見積を受信する以前に独自に過去の工事情報により工事区間を特定し、見積予測を行うことができる。   According to this embodiment, by having the communication path DB 156, when power construction that requires countermeasures against electromagnetic induction trouble occurs, the construction is independently performed based on past construction information before receiving an estimate from the wire operator. It is possible to specify an interval and perform estimation prediction.

次に第5の実施の形態について以下に説明する。第5の実施の形態は、見積の予測を行うに際し、対象の区間の有線事業者の顧客数またはその顧客数の伸び率がある定めた値以上になる場合は、光ファイバーを工事として選択するというものである。   Next, a fifth embodiment will be described below. In the fifth embodiment, when estimating the estimate, if the number of customers of the wireline operator in the target section or the growth rate of the number of customers exceeds a predetermined value, the optical fiber is selected as the construction. Is.

図20のフローチャートを用いて本実施の形態における見積予測手段135の動作を説明する。図11に示す見積予測手段135の動作と異なる部分はステップS111の部分がステップS201に変更となり、さらにステップS202〜S206が追加になっていることであり、過去の工事情報を参照して工事内容および工事費用の見積を決定する以前に以下の動作を行う部分が追加になっていることである。   The operation of the estimation predicting means 135 in this embodiment will be described using the flowchart of FIG. 11 differs from the operation of the estimate predicting means 135 shown in FIG. 11 in that the step S111 is changed to the step S201, and the steps S202 to S206 are further added. The construction contents are referred to the past construction information. And before deciding the estimate of the construction cost, the part that performs the following operations is added.

まず、見積情報分析にて特定した工事区間、もしくは通信経路を基にして予測した工事区間を対象区間とする(S201)。次に工事区間の顧客の数および顧客の伸び率を抽出し(S202)、顧客の数が予め定めた数以上である場合(S203のyesのルート)または、顧客の数と伸び率を演算した値が予め定めた値以上である場合(S204のyesのルート)は光ファイバーを工事として選択し(S205)、工事費用として有線事業者と按分した費用を見積予測DB153書き込み(S206)、次の区間の処理に進む(S116)。顧客の数が予め定めた数より少なく(S203のnoのルート)且つ顧客の数と伸び率の演算結果が予め定めた値より少ない場合(S204のnoのルート)はステップS112へ進み以前説明を行った動作を進めていく。   First, the construction section identified by the estimation information analysis or the construction section predicted based on the communication path is set as the target section (S201). Next, the number of customers in the construction section and the customer growth rate are extracted (S202). When the number of customers is greater than or equal to a predetermined number (yes route in S203), the number of customers and the growth rate are calculated. If the value is equal to or greater than the predetermined value (yes route in S204), the optical fiber is selected as the construction (S205), the cost apportioned with the wire operator as the construction cost is written in the estimated prediction DB 153 (S206), and the next section The process proceeds to (S116). If the number of customers is less than the predetermined number (no route of S203) and the calculation result of the number of customers and the growth rate is smaller than the predetermined value (no route of S204), the process proceeds to step S112 and the previous explanation is made. Proceed with the actions you have performed.

また、この通信経路情報の通信経路DB156への入力は、有線事業者が行ったり、もしくは電力会社が情報を入手した上で入力したり、さらにインターネットなどの通信ネットワークで接続されるようにして直接有線事業者がシステムにログインして情報を入力することも可能である。   In addition, the communication path information is input to the communication path DB 156 by a wired operator, or after an electric power company obtains the information, or directly connected to a communication network such as the Internet. It is also possible for a wireline operator to log into the system and enter information.

本実施の形態によれば、有線事業者の顧客の数および伸び率が高い地域を考慮して顧客が多い地域もしくは伸び率が高い地域で電磁誘導障害対策の必要性が発生した場合は、電磁誘導障害対策として電磁誘導障害影響を受けない上に、大量の顧客に対応できる光ファイバー回線を対策として選択し、お互いにメリットがあるので、その工事費用は有線事業者と電力会社で折半するということを行うことができる。   According to the present embodiment, when there is a need for electromagnetic induction failure countermeasures in an area where there are many customers or an area where the growth rate is high, considering the number of customers of the wireline operator and areas where the growth rate is high, As a countermeasure against inductive interference, an optical fiber line that can handle a large number of customers is selected as a countermeasure without being affected by electromagnetic inductive interference, and there is a mutual benefit, so that the construction cost will be split between the cable operator and the power company It can be performed.

次に第6の実施の形態について以下に説明する。第6の実施の形態は、見積の予測を行うに際し、区間ごとの標準の工事内容と工事費用を送電線路からの距離ごとに登録した標準見積データベース(DB)157を用いて見積の比較を行うものである。この標準見積DB157には、既に信憑性のある工事内容と工事費用を予め登録しておき、見積と比較する際に当該登録された標準見積DB157と比較するものである。   Next, a sixth embodiment will be described below. In the sixth embodiment, when estimating an estimate, an estimate is compared using a standard estimate database (DB) 157 in which standard construction contents and construction costs for each section are registered for each distance from the transmission line. Is. In this standard estimate DB 157, already credible construction contents and construction costs are registered in advance and compared with the registered standard estimate DB 157 when compared with the estimate.

標準見積DB157のデータ構成例を図21に示す。この標準見積DB157は図1に示す工事見積支援システム1のブロック図内の記憶部14内に保存されるものであり、破線で示している。図21にて分かるように、各送電線路は区間に分けられその区間ごとにさらに送電線路からの距離ごとに工事内容と工事費用が固定して登録されている。本実施の形態では見積情報分析手段134にて得られた見積情報を過去のデータベースを用いることなくチェックすることが可能となる。また、過去の工事内容DB151に登録されている工事内容と比較を行った後に、この標準見積DB157と比較を行うとしても良い。   A data configuration example of the standard estimate DB 157 is shown in FIG. The standard estimate DB 157 is stored in the storage unit 14 in the block diagram of the construction estimate support system 1 shown in FIG. 1 and is indicated by a broken line. As can be seen in FIG. 21, each transmission line is divided into sections, and the construction contents and construction costs are registered for each section and for each distance from the transmission line. In the present embodiment, it is possible to check the estimate information obtained by the estimate information analysis unit 134 without using a past database. Moreover, after comparing with the construction content registered in the past construction content DB 151, the comparison with the standard estimate DB 157 may be performed.

なお、上記の実施の形態では、LAN接続により組織内で利用する構成としたが、本発明による工事見積支援システムは、組織内で利用するのみならず、有線事業者に開放することで、有線事業者への工事見積に際しては、過去の見積を参照した上で新たな見積の作成を行うように指示することも可能である。このように、例えばインターネットを介してサービスを使用するに際してはユーザIDやパスワードの管理や、ネットワークを介したハッキングが行われないように情報を暗号化するなどの対策を取った上で行うのが望ましい。   In the above embodiment, the configuration is used in the organization by LAN connection. However, the construction estimation support system according to the present invention is not only used in the organization but also opened to the wire operator, so that It is possible to instruct a business operator to create a new estimate after referring to a past estimate. Thus, for example, when using a service via the Internet, it is necessary to take measures such as managing user IDs and passwords and encrypting information to prevent hacking via the network. desirable.

また、本発明は送電線路の電磁誘導障害対策の見積支援に限らず、何らかの距離を有し、その区間ごとに見積が行えるような工事について利用することができる。   In addition, the present invention is not limited to estimation support for countermeasures against electromagnetic induction disturbances in a transmission line, but can be used for constructions that have some distance and can be estimated for each section.

本発明の第1の実施の形態に係わる工事見積支援システムの機能ブロック図である。It is a functional block diagram of the construction estimate assistance system concerning the 1st Embodiment of this invention. 図1の電磁誘導障害対策の例を示す図である。It is a figure which shows the example of the electromagnetic induction failure countermeasure of FIG. 図1の見積DBのデータ構成例である。It is a data structural example of estimate DB of FIG. 図1の見積路線DBのデータ構成例である。It is a data structural example of estimated route DB of FIG. 図1の工事内容DBのデータ構成例である。It is an example of a data structure of construction content DB of FIG. 図1の見積予測DBのデータ構成例である。It is a data structural example of estimate prediction DB of FIG. 図1の見積比較結果DBのデータ構成例である。It is an example of a data structure of estimate comparison result DB of FIG. 図1の見積比較結果DBのデータ構成例である。It is an example of a data structure of estimate comparison result DB of FIG. 図1の工事見積支援システムの動作の概略を示す図である。It is a figure which shows the outline of operation | movement of the construction estimation assistance system of FIG. 図1の見積情報分析手段が行う処理手順を示すフローチャートである。It is a flowchart which shows the process sequence which the estimation information analysis means of FIG. 1 performs. 図1の見積予測手段が行う処理手順を示すフローチャートである。It is a flowchart which shows the process sequence which the estimation estimation means of FIG. 1 performs. 図1の見積比較手順が行う処理手順を示すフローチャートである。It is a flowchart which shows the process sequence which the estimate comparison procedure of FIG. 1 performs. 図1の見積妥当性判断手段が行う処理手順を示すフローチャートである。It is a flowchart which shows the process sequence which the estimation validity judgment means of FIG. 1 performs. 図1の見積図示化手段が行う処理手順を示すフローチャートである。It is a flowchart which shows the process sequence which the quote illustration means of FIG. 1 performs. 図1の見積図示化手段が行った図示化の例である。It is an example of the illustration which the estimation illustration means of FIG. 1 performed. 本発明の第2の実施の形態に係わる工事見積支援システムの見積予測手段が行う処理手順を示すフローチャートである。It is a flowchart which shows the process sequence which the estimation estimation means of the construction estimation assistance system concerning the 2nd Embodiment of this invention performs. 本発明の第3の実施の形態に係わる工事内容DBのデータ構成例である。It is an example of a data structure of construction content DB concerning the 3rd Embodiment of this invention. 本発明の第4および第5の実施の形態に係わる通信経路DBのデータ構成例である。It is a data structural example of communication path DB concerning the 4th and 5th embodiment of this invention. 本発明の第4の実施の形態に係わる見積予測手段が行う処理手順を示すフローチャートである。る。It is a flowchart which shows the process sequence which the estimation estimation means concerning the 4th Embodiment of this invention performs. The 本発明の第5の実施の形態に係わる見積予測手段が行う処理手順を示すフローチャートである。It is a flowchart which shows the process sequence which the estimation estimation means concerning the 5th Embodiment of this invention performs. 図1における標準見積DBのデータ構成例である。It is a data structural example of standard estimation DB in FIG.

符号の説明Explanation of symbols

1 工事見積支援システム
3 端末
4 LAN(Local Area Network)
12 33 送受信部
13 33 中央演算処理部
15 35 入力部
16 36 表示部
14 記憶部
131 送受信処理手段
132 入出力処理手段
133 情報登録手段
134 見積情報分析手段
135 見積予測手段
136 見積比較手段
137 見積妥当性判断手段
138 見積図示化手段
151 工事内容(データベース)DB
152 見積(データベース)DB
153 見積予測(データベース)DB
154 見積比較結果(データベース)DB
155 見積路線(データベース)DB
156 通信経路(データベース)DB
157 標準見積(データベース)DB
1 construction estimate support system
3 Terminal 4 LAN (Local Area Network)
12 33 Transmission / reception unit 13 33 Central processing unit 15 35 Input unit 16 36 Display unit 14 Storage unit 131 Transmission / reception processing unit 132 Input / output processing unit 133 Information registration unit 134 Estimation information analysis unit 135 Estimation prediction unit 136 Estimation comparison unit 137 Estimation validity Sex judging means 138 Estimating and displaying means 151 Construction contents (database) DB
152 Estimate (Database) DB
153 Estimated forecast (database) DB
154 Estimated comparison result (database) DB
155 Estimated route (database) DB
156 Communication path (database) DB
157 Standard quotation (database) DB

Claims (13)

送電線路区間を複数の区間に分け、その区間ごとに行った工事内容、および要した工事費用を保存する工事内容データベースと、
予め定めた形式のデータとして与えられる見積情報から送電線路の区間と工事内容、および工事費用を読み取り、前記工事内容データベースと合致した区間に分ける見積情報分析手段と、
前記工事内容データベースに蓄積された過去の工事区間および工事内容と、前記見積情報分析手段にて分解された工事区間および工事内容を工事区間ごとに比較することで、指定された区間の工事内容に対して工事費用の概算を算出する見積予測手段と、
前記算出された概算費用と見積費用とを比較してその差分を抽出する見積比較手段と、
を備えたことを特徴とする工事見積支援システム。
A transmission content section that divides the transmission line section into a plurality of sections, saves the construction details performed for each section, and the required construction costs,
An estimate information analyzing means that reads the section of the transmission line and the construction content and the construction cost from the estimate information given as data in a predetermined format, and divides the section into a section that matches the construction content database;
By comparing the past construction sections and construction contents accumulated in the construction contents database with the construction sections and construction contents disassembled by the estimation information analysis means for each construction section, the construction contents of the designated section are obtained. Estimating and predicting means for calculating the rough construction cost,
An estimated comparison means for comparing the calculated estimated cost with the estimated cost and extracting the difference;
A construction estimate support system characterized by comprising
前記見積予測手段にて算出された概算費用と、前記見積情報分析手段により分析された区間ごとの工事内容および工事費用とを比較することで、工事費用の見積額の妥当性を判断する見積妥当性判断手段と、
を備えたことを特徴とする請求項1に記載の工事見積支援システム。
By comparing the estimated cost calculated by the estimated forecasting means with the construction contents and construction costs for each section analyzed by the estimated information analyzing means, the validity of the estimated cost is judged. Sex judgment means,
The construction estimation support system according to claim 1, further comprising:
前記見積妥当性判断手段は、読み取られた工事費用の見積額が、対応する区間および工事内容の過去の平均値から予め指定可能に定めた範囲内である場合は妥当であると判断することを特徴とする請求項2に記載の工事見積支援システム。   The estimated validity judging means judges that the estimated construction cost read is valid if it falls within a predetermined range that can be designated in advance from the past average value of the corresponding section and construction content. The construction estimation support system according to claim 2, wherein the system is a construction estimation support system. 前記見積妥当性判断手段は、前記読み取られた工事費用の見積額が、対応する工事区間および工事内容の過去の平均価格に過去の傾向を加味した値から予め定めた範囲内である場合は妥当であると判断することを特徴とする請求項2に記載の工事見積支援システム。   The estimated validity judging means is valid when the estimated construction cost read is within a predetermined range from a value obtained by adding a past tendency to a past average price of a corresponding construction section and construction content. The construction estimation support system according to claim 2, wherein the construction estimation support system is determined. 前記見積妥当性判断手段は、前記読み取られた工事区間の工事内容と、同送電線路の同工事区間の過去の工事内容とを比較し、同じ内容であった場合は、警告を行うことを特徴とする請求項2ないし4のいずれか一に記載の工事見積支援システム。   The estimated validity judging means compares the construction contents of the read construction section with the past construction contents of the construction section of the transmission line, and gives a warning if the contents are the same. The construction estimation support system according to any one of claims 2 to 4. 前記見積妥当性判断手段は、読み取られた工事内容が妥当でないと判断した場合、または読み取られた工事内容が、見積予測された工事内容よりもより高度で且つ工事費用がより高価な工事内容である場合は、警告を行うことを特徴とする請求項2ないし5のいずれか一に記載の工事見積支援システム。   The estimated validity judging means determines that the read construction content is not valid, or the read construction content is higher than the estimated construction content and the construction cost is higher in construction cost. 6. The construction estimation support system according to any one of claims 2 to 5, wherein a warning is issued if there is any. 前記見積情報分析手段が分析して作成した区間ごとの工事内容と要する工事費用と、見積予測手段が予測して作成した区間ごと工事内容と工事費用とを図示化する見積図示化手段と、
を備えたことを特徴とする請求項1ないし6のいずれか一に記載の工事見積支援システム。
Estimate plotting means for illustrating the construction contents and required construction costs for each section analyzed and created by the estimate information analysis means, and the construction contents and construction costs for each section predicted and created by the estimate prediction means;
The construction estimation support system according to any one of claims 1 to 6, further comprising:
前記複数の区間は変更可能に構成されていることを特徴とする請求項1ないし7のいずれか一に記載の工事見積支援システム。   The construction estimation support system according to claim 1, wherein the plurality of sections are configured to be changeable. 電磁誘導障害対策を行う必要のある送電線路の有線事業者の顧客の総数または増加率を保存する通信経路データベースを備え、
前記見積予測手段は、過去の工事内容および工事費用に拘わらず、対象の工事区間の総顧客数もしくは顧客の伸び率を加味した総顧客数が予め定めた数より大きい場合は、電磁誘導障害対策として光ファイバーを選択し、工事費用をある定めた割合で有線事業者と按分することを特徴とする請求項2ないし8のいずれか一に記載の工事見積支援システム。
It has a communication path database that stores the total number or increase rate of wireline operators who need to take measures against electromagnetic induction disturbances.
If the total number of customers in the target construction section or the total number of customers taking into account the customer growth rate is greater than a predetermined number, regardless of the past construction contents and construction costs, the estimate prediction means The construction estimation support system according to claim 2, wherein an optical fiber is selected as the construction cost, and the construction cost is apportioned with the cable provider at a predetermined rate.
電磁誘導障害対策を行う必要のある送電線路近辺の有線事業者の通信経路の情報を保存する通信経路データベースを備え、
前記見積予測手段は、前記通信経路データベースより電磁誘導障害対策を行う必要のある工事区間を判定し、前記工事内容データベースより前記判定した工事区間の工事費用を算出することを特長とする請求項1ないし9のいずれか一に記載の工事見積支援システム。
It has a communication path database that stores information on the communication paths of cable operators in the vicinity of power transmission lines that need to take measures against electromagnetic induction disturbances.
2. The estimate prediction means determines a construction section that needs to be subjected to electromagnetic induction failure countermeasures from the communication path database, and calculates a construction cost of the determined construction section from the construction content database. The construction estimation support system according to any one of 1 to 9.
送電線路の区間ごとに工事内容と工事に要する費用を記憶する標準見積データベースを備え、
前記見積予測手段は、前記標準見積データベースを用いて工事区間ごとに工事内容と工事費用の概算を算出することを特徴とする請求項1または2に記載の工事見積支援システム。
A standard estimate database is stored for each section of the transmission line to store construction details and costs required for construction.
The construction estimation support system according to claim 1, wherein the estimate prediction means calculates an estimate of construction contents and construction costs for each construction section using the standard estimation database.
予め定めた形式のデータとして与えられる見積情報から送電線路の区間と工事内容、および工事費用を読み取り、送電線路区間を複数の区間に分け、その区間ごとに行った工事内容、および要した工事費用を保存する工事内容データベースと合致した区間に分ける第1のステップと、
前記工事内容データベースに蓄積された過去の工事区間および工事内容と、前記第1のステップにて分解された工事区間および工事内容を工事区間ごとに比較することで、指定された区間の工事内容に対して工事費用の概算を算出する第2のステップと、
前記算出された概算費用と見積費用とを比較してその差分を抽出する第3のステップと、を含むことを特徴とする工事見積支援方法。
Read the transmission line section, construction contents, and construction cost from the estimate information given as data in a predetermined format, divide the transmission line section into multiple sections, and the construction contents performed for each section and the construction cost required A first step of dividing the section that matches the construction content database to store
By comparing the past construction sections and construction contents accumulated in the construction content database with the construction sections and construction contents disassembled in the first step for each construction section, the construction contents of the designated section are obtained. A second step of calculating an approximate construction cost for
And a third step of extracting the difference by comparing the calculated approximate cost with the estimated cost.
工事の見積を行うコンピュータ上で動作するプログラムであって、
予め定めた形式のデータとして与えられる見積情報から送電線路の区間と工事内容、および工事費用を読み取り、送電線路区間を複数の区間に分け、その区間ごとに行った工事内容、および要した工事費用を保存する工事内容データベースと合致した区間に分ける第1の処理と、
前記工事内容データベースに蓄積された過去の工事区間および工事内容と、前記第1の処理にて分解された工事区間および工事内容を工事区間ごとに比較することで、指定された区間の工事内容に対して工事費用の概算を算出する第2の処理と、
前記算出された概算費用と見積費用とを比較してその差分を抽出する第3の処理と、
をコンピュータ上で動作させることを特徴とする工事見積支援プログラム。
A program that runs on a computer that estimates construction,
Read the transmission line section, construction contents, and construction cost from the estimate information given as data in a predetermined format, divide the transmission line section into multiple sections, and the construction contents performed for each section and the construction cost required The first process to divide the section that matches the construction content database to store
By comparing the past construction sections and construction contents accumulated in the construction content database with the construction sections and construction contents disassembled in the first processing for each construction section, the construction contents of the designated section are obtained. A second process for calculating a rough estimate of the construction cost,
A third process for comparing the calculated estimated cost with the estimated cost and extracting the difference;
A construction estimate support program characterized by operating a computer on a computer.
JP2005267575A 2005-09-14 2005-09-14 Construction work estimate support system, method and program Pending JP2007079994A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005267575A JP2007079994A (en) 2005-09-14 2005-09-14 Construction work estimate support system, method and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005267575A JP2007079994A (en) 2005-09-14 2005-09-14 Construction work estimate support system, method and program

Publications (1)

Publication Number Publication Date
JP2007079994A true JP2007079994A (en) 2007-03-29

Family

ID=37940228

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005267575A Pending JP2007079994A (en) 2005-09-14 2005-09-14 Construction work estimate support system, method and program

Country Status (1)

Country Link
JP (1) JP2007079994A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016103135A (en) * 2014-11-28 2016-06-02 三菱電機ビルテクノサービス株式会社 Air-conditioning equipment construction estimate preparation system and program
CN112669082A (en) * 2020-12-31 2021-04-16 大为国际工程咨询有限公司 Engineering cost analysis method and system for reducing repeated workload

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016103135A (en) * 2014-11-28 2016-06-02 三菱電機ビルテクノサービス株式会社 Air-conditioning equipment construction estimate preparation system and program
CN112669082A (en) * 2020-12-31 2021-04-16 大为国际工程咨询有限公司 Engineering cost analysis method and system for reducing repeated workload
CN112669082B (en) * 2020-12-31 2023-07-18 大为国际工程咨询有限公司 Construction cost analysis method and system for reducing repeated workload

Similar Documents

Publication Publication Date Title
US8620726B2 (en) Methods and apparatus for analyzing locate and marking operations by comparing locate information and marking information
US9208464B2 (en) Methods and apparatus for analyzing locate and marking operations with respect to historical information
CA2691780C (en) Management system, and associated methods and apparatus, for providing automatic assesment of a locate operation
CN110647522B (en) Data mining method, device and system
US20100250312A1 (en) System to Facilitate Pipeline Management, Program Product, and Related Methods
JP6264473B2 (en) Equipment maintenance management method
US20150193717A1 (en) Methods and apparatus for analyzing locate and marking operations
CN112016855B (en) User industry identification method and device based on relational network matching and electronic equipment
CN109858683A (en) Determine method, apparatus, electronic equipment and the storage medium of the business status in shop
US20160155079A1 (en) Apparatus and methods for evaluating a quality of a locate operation for underground utility
JP2007079994A (en) Construction work estimate support system, method and program
AU2016257766B2 (en) Methods and systems for use in monitoring the operations of a business
JP5111025B2 (en) System planning support system
JP5022857B2 (en) Pipeline information system
CN113641725A (en) Information display method, device, equipment and storage medium
JP2022138368A (en) Facility value estimate device, public equipment influence evaluation system, and public equipment influence evaluation method
US20170046791A1 (en) Systems and methods for budget analysis visualization
KR20150124357A (en) Apparatus and method for analyzing fluid stream in pipe network based gis
CN110705018A (en) Water supply pipeline pipe burst positioning method based on hot line work order and pipeline health assessment
Callanan Is the effect of high voltage transmission lines undervalued?
KR102530194B1 (en) Integration system for sewerage pipe asset management utilizing web applications
CN114418611B (en) Weak current construction cost calculation method and device, electronic equipment and storage medium
JP5013803B2 (en) Lightning strike frequency information providing apparatus, system, and method
WO2010039262A2 (en) Methods and apparatus for analyzing locate and marking operations with respect to environmental landmarks
US20220405670A1 (en) System and method for upstream interparty component supply chain control