JP2006350832A - Work distribution device, work distribution system and work distribution method - Google Patents

Work distribution device, work distribution system and work distribution method Download PDF

Info

Publication number
JP2006350832A
JP2006350832A JP2005178244A JP2005178244A JP2006350832A JP 2006350832 A JP2006350832 A JP 2006350832A JP 2005178244 A JP2005178244 A JP 2005178244A JP 2005178244 A JP2005178244 A JP 2005178244A JP 2006350832 A JP2006350832 A JP 2006350832A
Authority
JP
Japan
Prior art keywords
master
production
workers
repair
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005178244A
Other languages
Japanese (ja)
Inventor
Akihiro Furusawa
昭宏 古澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sharp Corp
Original Assignee
Sharp Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sharp Corp filed Critical Sharp Corp
Priority to JP2005178244A priority Critical patent/JP2006350832A/en
Publication of JP2006350832A publication Critical patent/JP2006350832A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To always accurately perform personnel distribution of a production site by taking into consideration the personnel distribution including transfer between direct workers and indirect workers. <P>SOLUTION: Personnel distribution between direct workers and indirect workers is changed. For example, when the number of defective products increases, indirect workers are increased to instruct a distribution so as not to accumulate the defective products. When production is delayed, direct workers are increased to recover actual production. Consequently, it is possible to perform personnel distribution and work distribution without having to change production conditions such as to add workers or lower the number of planned products on that day to perform adjustment in a monthly plan or to force workers to work overtime as in the conventional practice. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、生産ラインにおける複数の作業者を適宜に配置するための作業配分装置、作業配分システム、及び作業配分方法に関する。   The present invention relates to a work distribution device, a work distribution system, and a work distribution method for appropriately arranging a plurality of workers on a production line.

従来、生産現場においては、複数の作業を作業者に適宜に配分して、作業効率の向上を図るために、チームリーダー等の管理監督者が、経験則などに基づいて作業工程に見合った適正な作業手順と作業時間を設定し、生産計画を作成していた。   Conventionally, in order to improve work efficiency by appropriately allocating multiple operations to workers at production sites, team leaders and other supervisors are appropriate to work processes based on empirical rules. The production plan was created by setting a proper work procedure and working time.

また、特許文献1の作業配分表作成支援システムでは、生産計画、人員計画から組立を行う複数種の製品を、同一の組立ラインに順次混流して流し、その組立ラインに沿って、それぞれ配置した作業員が、設定サイクルタイム内で順次要素作業を行って製品を組立てることを前提としており、組立てられる製品の種類毎に、それぞれの作業者の配置と配置人数とその各作業者が行う要素作業の手順と標準要素時間とその標準要素時間を積算した標準作業工程とを予め定めた作業分析表を作成し、他方、生産計画から混流する製品の種類の生産台数比率と種類別の工程時間とを乗じた加重平均配分表を作成するとともにその加重平均配分表の加重平均データを、それぞれ製品の種類毎に対応した各工程の加重平均サイクルタイムを求め、かつ、これらを積算した合計サイクルタイムが上記設定サイクルタイム以内になるようにしている。
特開2002−215860号公報(第3〜4、6〜7頁、図1、2参照)
Further, in the work distribution table creation support system of Patent Document 1, a plurality of types of products to be assembled from production plans and personnel plans are sequentially mixed and flowed to the same assembly line, and are arranged along the assembly lines. It is assumed that the workers will assemble the products by sequentially performing the element work within the set cycle time, and for each type of product to be assembled, the arrangement and number of each worker and the element work performed by each worker Create a work analysis table that pre-determines the procedure, standard element time, and standard work process obtained by accumulating the standard element time. On the other hand, the ratio of the number of products mixed from the production plan A weighted average allocation table multiplied by the weighted average distribution table, and the weighted average data for each process corresponding to each type of product, The total cycle time obtained by integrating these is set to be within the set cycle time.
JP 2002-215860 A (refer to FIGS. 3 and 4, pages 6 to 7, FIGS. 1 and 2)

しかしながら、チームリーダー等の管理監督者が、経験則などに基づいて生産計画を作成する場合は、生産計画が複雑化すると、ライン落ちした製品の個数等の変動に応じて生産計画を適確かつ迅速に修正することが困難であった。   However, when a supervisor such as a team leader creates a production plan based on a rule of thumb, etc., if the production plan becomes complicated, the production plan can be accurately confirmed according to changes in the number of products that have fallen on the line. It was difficult to correct quickly.

また、特許文献1のシステムにおいては、作業配分の結果が設定サイクルタイムを越えた場合、混流する製品の比率を変更するか、または前後工程の作業者に作業を割振るという方法により設定サイクルタイム内で収まるように解決していた。   Further, in the system of Patent Document 1, when the result of work distribution exceeds the set cycle time, the set cycle time is changed by changing the ratio of the mixed products or allocating the work to the workers in the preceding and following processes. It was settled to fit within.

ところが、最近では効率を最大限に追求していく中で、前後工程の作業者のみによる作業配分では設定サイクルタイム内で収めることができないことがあり、その場合には作業者を追加するか、当日の計画台数を下げて、月度の計画で調整するか、作業者に残業を課すといった生産条件の変更が必要になり、特許文献1のシステムでは解決することができなかった。   However, recently, while pursuing maximum efficiency, work distribution by only the workers in the front and back processes may not be able to fit within the set cycle time, in which case additional workers may be added, It is necessary to change the production conditions such as reducing the planned number of the day and adjusting with the monthly plan, or imposing overtime on the worker, and the system of Patent Document 1 cannot solve the problem.

また、生産現場においては、作業者区分があって、工程内において製品に対し直接的に作業を実施する直接作業者と、部品供給や製品の修理といった生産に対して間接的な作業を実施する間接作業者との二者が存在している。直接作業者の作業は連続的であり、このために作業の空き時間がほとんど存在しない。一方、間接作業者の作業は主に断続的に発生する傾向にあり、このために間接作業の合間に空き時間が発生し、この空き時間を1日のトータル時間として見ると多大なロス時間となっているのが実情である。特に、間接作業者は、製品の修理作業がないときに大きなロスを生んだ。また、修理作業が頻繁に発生したときには、間接作業者の処理能力を超え、修理が必要なライン落ちの製品が作業工程に溢れて、過剰な仕掛品を持つことになった。   In addition, there are worker divisions at the production site, and direct workers who work directly on products in the process and indirect work on production such as parts supply and product repair. There are two indirect workers. The direct operator's work is continuous, so there is almost no work free time. On the other hand, the work of indirect workers tends to occur mainly intermittently. For this reason, idle time occurs between the indirect work, and when this idle time is viewed as the total time of the day, It is the actual situation. In particular, indirect workers caused significant losses when there was no product repair work. Moreover, when repair work frequently occurred, the capacity of the indirect worker exceeded the capacity of the indirect worker, and the line-off products that needed repair overflowed into the work process, resulting in excessive work in progress.

しかしながら、従来は、関節作業者の必要作業時間の変動に着眼点を置き、直接作業者と間接作業者間の移動を含めた人員配置を考慮するまでには至らず、このために人員配置に無駄や不足が生じることがあった。   However, in the past, it was not enough to focus on the fluctuations in the required work time of joint workers, and consider the staffing including movement between direct workers and indirect workers. Waste and shortage sometimes occurred.

そこで、本発明は、上記従来の問題点に鑑みてなされたものであり、直接作業者と間接作業者間の移動を含めた人員配置を考慮して、生産現場の人員配置を常に適確に行うことが可能な作業配分装置、作業配分システム、及び作業配分方法を提供することを目的とする。   Therefore, the present invention has been made in view of the above-described conventional problems, and always considers personnel assignment on the production site in consideration of personnel assignment including movement between direct workers and indirect workers. An object is to provide a work distribution device, a work distribution system, and a work distribution method that can be performed.

上記課題を解決するために、本発明の作業配分装置は、製品を生産する生産ラインの工程間で人員入れ替えを迅速に行う為の作業配分装置であって、製品の生産実績データを収集する生産実績収集部と、不良製品のデータを収集するライン落ち実績収集部と、修理された製品のデータを収集する修理実績収集部と、製品の生産計画を格納した生産計画マスタと、前記生産実績収集部で収集された生産実績データを格納した生産実績マスタと、前記ライン落ち実績収集部で収集されたデータを格納したライン落ちマスタと、前記修理実績収集部で収集されたデータを格納した修理実績マスタと、製品の不良要因別にかかる修理時間を格納した不良要因別修理時間マスタと、製品を組立てる直接作業者及び不良製品を修理する間接作業者の管理データを格納した人員マスタと、少なくとも生産ラインの最遅残業時刻を管理する就業時間マスタと、前記生産実績マスタ、前記ライン落ちマスタ、及び前記修理実績マスタに対するデータの書き込み及び読み出しを管理する管理部と、前記生産計画マスタ、前記生産実績マスタ、前記ライン落ちマスタ、前記修理実績マスタ、前記不良要因別修理時間マスタ、前記人員マスタ、及び前記就業時間マスタのそれぞれのデータに基づいて、直接作業者及び間接作業者を入れ替え、人員配置及び作業配分を求める演算部と、前記演算部により求められた人員配置及び作業配分結果を出力する結果出力部とを備えている。   In order to solve the above-mentioned problems, the work distribution device of the present invention is a work distribution device for quickly changing personnel between processes of a production line for producing products, and is a production collecting data for production results of products. A performance collection unit, a line drop result collection unit that collects defective product data, a repair result collection unit that collects data of repaired products, a production plan master that stores product production plans, and the production result collection Production record master storing the production record data collected by the department, line drop master storing the data collected by the line drop record collection part, and repair record storing the data collected by the repair record collection part The master, the repair time master by defect factor that stores the repair time for each defect factor of the product, and the management data of the direct worker who assembles the product and the indirect worker who repairs the defective product A management master for managing the writing and reading of data with respect to the production master, the line failure master, and the repair performance master And a direct worker based on the data of the production plan master, the production record master, the line drop master, the repair record master, the repair time master by defect factor, the personnel master, and the work time master. And an indirect worker to replace the indirect workers and obtain a staff assignment and work distribution, and a result output section for outputting the staff assignment and work distribution results obtained by the computation section.

この様な本発明の装置によれば、製品の生産実績データ、不良製品のデータ、修理された製品のデータ、製品の生産計画、生産実績データ、製品の不良要因別にかかる修理時間、直接作業者及び間接作業者の管理データ、及び生産ラインの最遅残業時刻に基づいて、直接作業者及び間接作業者を入れ替え、人員配置及び作業配分を求めているので、直接作業者と間接作業者間の移動を含めた人員配置を考慮して、生産現場の人員配置を常に適確に行うことができる。   According to such an apparatus of the present invention, product production result data, defective product data, repaired product data, product production plan, production result data, repair time for each cause of product failure, direct worker Indirect workers and indirect workers are replaced based on the management data of the indirect workers and the latest overtime time of the production line, and personnel allocation and work distribution are requested. Considering personnel allocation including movement, personnel allocation at production sites can always be performed accurately.

また、本発明の作業配分システムは、上記本発明の作業配分装置における生産実績収集部の機能を果たすために、組立工程における製品のバーコードを読み取るバーコードリーダー、及びバーコードリーダーにより読み取られたデータを収集するコンピュータを少なくとも含む投入実績収集装置と、上記本発明の作業配分装置におけるライン落ち実績収集部の機能を果たすために、検査工程における製品のバーコードを読み取るバーコードリーダー、及びバーコードリーダーにより読み取られたデータを収集するコンピュータを少なくとも含むライン落ち実績収集装置と、上記本発明の作業配分装置における修理実績収集部の機能を果たすために、修理工程における製品のバーコードを読み取るバーコードリーダー、及びバーコードリーダーにより読み取られたデータを収集するコンピュータを少なくとも含む修理実績収集装置と、上記本発明の作業配分装置における生産計画マスタ、生産実績マスタ、ライン落ちマスタ、修理実績マスタ、不良要因別修理時間マスタ、人員マスタ、就業時間マスタ、管理部、及び演算部のそれぞれの機能を果たすコンピュータと、上記本発明の作業配分装置における結果出力部の機能を果たすプリンターと、ターゲットタクトタイム、人員配置、及び作業配分等を表示する生産管理モニターとを備えている。   In addition, the work distribution system of the present invention was read by a barcode reader that reads the barcode of a product in the assembly process and the barcode reader in order to fulfill the function of the production result collection unit in the work distribution device of the present invention. A bar code reader for reading a bar code of a product in an inspection process and a bar code in order to perform the function of an input result collecting unit including at least a computer for collecting data, and a line drop result collecting unit in the work distribution apparatus of the present invention. A bar code for reading a bar code of a product in a repair process in order to perform the function of a line drop record collecting device including at least a computer for collecting data read by a reader and a repair record collecting unit in the work distribution device of the present invention. Reader and barcode reader A repair result collecting device including at least a computer that collects data read from, and a production plan master, a production result master, a line drop master, a repair result master, a repair time master by defect factor, and personnel in the work distribution device of the present invention. A computer that functions as a master, a working time master, a management unit, and a calculation unit, a printer that functions as a result output unit in the work distribution device of the present invention, a target tact time, personnel allocation, work distribution, and the like And a production management monitor for displaying.

この様に本発明のシステムは、コンピュータ、バーコードリーダー、プリンター、モニター等を組み合わせて構築することができる。   In this way, the system of the present invention can be constructed by combining a computer, a barcode reader, a printer, a monitor, and the like.

更に、本発明の作業配分方法は、不良製品の台数を算出するステップと、前記不良製品の台数に基づいて、不良製品を修理する間接作業者の人数を算出するステップと、作業者総人数から前記間接作業者の人数を差し引いて、製品を組立てる直接作業者の人数を算出するステップと、前記直接作業者の人数に基づいてターゲットタクトタイムを算出するステップと、前記ターゲットタクトタイムに基づいて、生産予測が生産計画を達成するか否かを判定するステップと、生産予測が生産計画を達成できないと判定された場合に、生産計画を達成し得る様にターゲットタクトタイムを再算出するステップと、前記再算出されたターゲットタクトタイムから直接作業者の人数を再算出するステップと、作業者総人数から前記再算出された直接作業者の人数を差し引いて、間接作業者の人数を再算出するステップとを含んでいる。   Further, the work distribution method of the present invention includes a step of calculating the number of defective products, a step of calculating the number of indirect workers repairing the defective products based on the number of defective products, and the total number of workers. Subtracting the number of indirect workers to calculate the number of direct workers to assemble the product, calculating the target tact time based on the number of direct workers, and based on the target tact time, Determining whether the production forecast achieves the production plan, recalculating the target tact time so that the production plan can be achieved if it is determined that the production forecast cannot achieve the production plan, Recalculating the number of workers directly from the recalculated target tact time; and recalculating the direct work from the total number of workers. By subtracting the number of persons, and a step of re-calculating the number of indirect workers.

この様な本発明の方法によれば、まず、不良製品を修理する間接作業者の人数を求めてから、製品を組立てる直接作業者の人数を求めて、この直接作業者の人数に基づいてターゲットタクトタイムを算出している。そして、このターゲットタクトタイムに基づいて、生産予測が生産計画を達成するか否かを判定し、生産計画を達成することができるのであれば、間接作業者の人数と直接作業者の人数が変更されることなく設定される。また、生産計画を達成することができなければ、生産計画を達成し得るターゲットタクトタイムを再算出し、この再算出されたターゲットタクトタイムから直接作業者の人数及び間接作業者の人数を逆算して求めている。これにより、直接作業者と間接作業者間の移動を含めた人員配置を考慮して、生産現場の人員配置を常に適確に行うことができる。   According to such a method of the present invention, first, the number of indirect workers who repair a defective product is obtained, then the number of direct workers who assemble the product is obtained, and the target is determined based on the number of direct workers. Tact time is calculated. Then, based on this target tact time, it is determined whether the production forecast achieves the production plan. If the production plan can be achieved, the number of indirect workers and the number of direct workers are changed. It is set without being done. If the production plan cannot be achieved, the target tact time that can achieve the production plan is recalculated, and the number of direct workers and the number of indirect workers are calculated backward from the recalculated target tact time. Looking for. Thereby, it is possible to always and appropriately perform the personnel assignment on the production site in consideration of the personnel assignment including the movement between the direct worker and the indirect worker.

この様な本発明によれば、常に、増減する不良製品を処理するのに適正な間接作業者を配置することができる。不良製品が少ない時は、間接作業者を少なくして過剰配置による手待ちロスを防ぐ。また、不良製品が頻繁に発生した時は、間接作業者を増やしてライン落ち在庫を増やすことなく工程内を常に整理させることができる。   According to the present invention as described above, it is possible to always arrange an indirect worker who is appropriate for processing defective products that increase or decrease. When there are few defective products, the number of indirect workers is reduced to prevent waiting loss due to excessive placement. In addition, when defective products frequently occur, the process can always be organized without increasing the number of indirect workers and increasing the line drop stock.

当日の生産計画が急遽増加した時、修理工程から組立工程へ応援に行かせ、増加人員を考慮した最適な作業配分表を作成し、効率的な生産を行うことができる。   When the production plan for the day suddenly increases, you can go from the repair process to the assembly process, create an optimal work distribution table that takes into account the increased personnel, and perform efficient production.

以下、本発明の実施形態を添付図面を参照しつつ詳細に説明する。   Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

図1は、本発明の作業配分装置の一実施形態を示す機能ブロック図である。本実施形態の作業配分装置は、組立工程で組立てられた製品の生産実績データを収集する生産実績収集部1、検査工程で撥ねられた不良製品を示すライン落ちデータを収集するライン落ち実績収集部2、修理工程で修理された製品を示す修理実績データを収集する修理実績収集部3、製品の生産計画を格納した生産計画マスタ10、生産実績収集部1で収集された生産実績データを格納した生産実績マスタ11、ライン落ち実績収集部2で収集されたライン落ちデータを格納したライン落ちマスタ12、修理実績収集部3で収集された修理実績データを格納した修理実績マスタ13、製品の不良要因別に求められた修理時間を格納した不良要因別修理時間マスタ14、直接作業者及び間接作業者の在籍人員の名簿を格納管理する人員マスタ15、始業時刻、休憩時刻、終業時刻、及び就業可能な最遅残業時刻を格納管理する就業時間マスタ16、各マスタに対するデータの書き込みや読み出し等を行う管理部4、各マスタのデータに基づいて生産現場の人員配置及び作業配分等を算出する演算部5、及び演算部5により算出された人員配置及び作業配分等を出力する結果出力部6を備えている。   FIG. 1 is a functional block diagram showing an embodiment of the work distribution apparatus of the present invention. The work distribution apparatus according to the present embodiment includes a production result collecting unit 1 that collects production result data of products assembled in the assembly process, and a line drop result collecting unit that collects line drop data indicating defective products rejected in the inspection process. 2. Stored repair result collection unit 3 for collecting repair result data indicating products repaired in the repair process, production plan master 10 for storing product production plans, and production result data collected by production result collection unit 1 Production record master 11, line drop master 12 storing line drop data collected by line drop record collecting unit 2, repair record master 13 storing repair record data collected by repair record collecting unit 3, cause of product failure Defect factor-specific repair time master 14 storing separately obtained repair time, and personnel master 1 for storing and managing a list of registered employees of direct workers and indirect workers , Work time master 16 for storing and managing start time, break time, end time, and latest overtime time available for work, management unit 4 for writing and reading data to and from each master, production based on data of each master A calculation unit 5 that calculates the personnel allocation and work distribution on the site, and a result output unit 6 that outputs the personnel allocation and work distribution calculated by the calculation unit 5 are provided.

図2は、図1の作業配分装置を実現するシステムを示す図である。このシステムでは、ホストコンピュータ20をシステムの中枢とし、プリンター31、生産管理モニター装置24、組立工程の投入実績収集装置21、検査工程のライン落ち実績収集装置25、及び修理工程の修理実績収集装置28等をネットワークを通じてホストコンピュータ20に接続している。   FIG. 2 is a diagram illustrating a system that implements the work distribution device of FIG. In this system, the host computer 20 is the center of the system, and a printer 31, a production management monitor device 24, an assembly process input result collection device 21, an inspection process line drop result collection device 25, and a repair process repair result collection device 28. Are connected to the host computer 20 through a network.

尚、プリンター31、生産管理モニター装置24、各装置21、25、28を複数設けても良い。また、ホストコンピュータ20の役目をネットワーク上の複数の端末装置に分散させても構わない。   A plurality of printers 31, production management monitor devices 24, and devices 21, 25, and 28 may be provided. Further, the role of the host computer 20 may be distributed to a plurality of terminal devices on the network.

組立工程の投入実績収集装置21は、図1の生産実績収集部1に対応しており、コンピュータ及びモニター等からなる端末装置22と、バーコードリーダー23とを備えている。バーコードリーダー23は、組立工程の先頭に投入された製品のバーコードを逐一読み取って、このバーコードによって示される製品の経歴書等を端末装置22に出力する。端末装置22は、複数の製品の経歴書等を収集して、各製品の経歴書等から生産実績データを生成し、この生産実績データをモニターに表示したり、この生産実績データをホストコンピュータ20に送信する。   The assembly process input result collection device 21 corresponds to the production result collection unit 1 of FIG. 1, and includes a terminal device 22 including a computer and a monitor, and a barcode reader 23. The bar code reader 23 reads the bar code of the product input at the beginning of the assembly process one by one, and outputs the product history and the like indicated by the bar code to the terminal device 22. The terminal device 22 collects resumes and the like of a plurality of products, generates production result data from the resumes and the like of each product, displays the production result data on a monitor, and displays the production result data on the host computer 20. Send to.

検査工程のライン落ち実績収集装置25は、図1のライン落ち実績収集部2に対応しており、コンピュータ及びモニター等からなる端末装置26と、バーコードリーダー27とを備えている。バーコードリーダー27は、検査工程で撥ねられた不良製品のバーコードを読み取って、このバーコードによって示される製品の経歴書等を端末装置26に出力する。端末装置26は、不良製品の経歴書等をライン落ちデータとして収集し、このライン落ちデータをモニターに表示したり、このライン落ちデータをホストコンピュータ20に送信する。   The line drop record collection device 25 in the inspection process corresponds to the line drop record collection unit 2 in FIG. 1 and includes a terminal device 26 including a computer and a monitor, and a barcode reader 27. The bar code reader 27 reads the bar code of the defective product repelled in the inspection process, and outputs a product history document or the like indicated by the bar code to the terminal device 26. The terminal device 26 collects resumes and the like of defective products as line drop data, displays the line drop data on a monitor, and transmits the line drop data to the host computer 20.

修理工程の修理実績収集装置28は、図1の修理実績収集部3に対応しており、コンピュータ及びモニター等からなる端末装置29と、バーコードリーダー30とを備えている。バーコードリーダー30は、修理工程で修理された製品のバーコードを読み取って、このバーコードによって示される製品の経歴書等を端末装置29に出力する。端末装置29は、不良製品の経歴書等をライン落ちデータとして収集し、このライン落ちデータをモニターに表示したり、このライン落ちデータをホストコンピュータ20に送信する。   The repair result collection device 28 in the repair process corresponds to the repair result collection unit 3 in FIG. 1 and includes a terminal device 29 including a computer and a monitor, and a barcode reader 30. The bar code reader 30 reads the bar code of the product repaired in the repair process, and outputs the product history and the like indicated by the bar code to the terminal device 29. The terminal device 29 collects a resume of defective products as line drop data, displays the line drop data on a monitor, and transmits the line drop data to the host computer 20.

システムの中枢となるホストコンピュータ20は、図1の生産計画マスタ10、生産実績マスタ11、ライン落ちマスタ12、修理実績マスタ13、不良要因別修理時間マスタ14、人員マスタ15、就業時間マスタ16、管理部4、及び演算部5に対応しており、各マスタ10〜16を記憶装置に記憶し、管理部4と演算部5の役目を果たす。また、プリンター31は、図1の結果出力部6に対応している。   The host computer 20 serving as the center of the system includes a production plan master 10, a production record master 11, a line drop master 12, a repair record master 13, a repair factor master 14, a personnel master 15, a working time master 16, Corresponding to the management unit 4 and the calculation unit 5, the masters 10 to 16 are stored in the storage device, and serve as the management unit 4 and the calculation unit 5. The printer 31 corresponds to the result output unit 6 in FIG.

生産管理モニター装置24は、組立工程の全ステーション(作業場所)にそれぞれ設けられており、ホストコンピュータ20から生産ラインに関する各種の情報を受け取って表示する。例えば、ターゲットタクトタイム、ライン落ち台数、直接作業者の人数、間接作業者の人数、生産予測、及び配員マップ等を表示して、これらを作業者が確認することを可能にする。   The production management monitor device 24 is provided at each station (work place) in the assembly process, and receives and displays various information about the production line from the host computer 20. For example, the target tact time, the number of dropped lines, the number of direct workers, the number of indirect workers, the production prediction, the staffing map, and the like are displayed, and these can be confirmed by the worker.

次に、図3に示す組立工程の作業配分を行うための元データとなる作業標準時間見積書について説明する。この作業標準時間見積書は、図1の各マスタ10〜16と同様に、ホストコンピュータ20の記憶装置に記憶されている。   Next, a work standard time estimate which is the original data for performing work distribution in the assembly process shown in FIG. 3 will be described. The work standard time estimate is stored in the storage device of the host computer 20 in the same manner as the masters 10 to 16 in FIG.

この作業標準時間見積書の標準時間とは、所定の標準作業条件のもとで、一定の作業方法で習熟期間を経た一人前の作業者が、標準の作業速度で作業を成し遂げるに要する時間である。   The standard time in this work standard time estimate is the time required for a single worker who has gone through a proficiency period with a certain work method to complete the work at the standard work speed under the prescribed standard work conditions. is there.

作業標準時間見積書は、製品の機種名40毎に作成されるものであり、作業項目の番号41と、作業項目42と、作業項目の繰り返し回数43と、標準の作業速度で作業項目1回に要する正味時間(単)44と、前記正味時間(単)に前記回数43を積算した正味時間(計)45とを対応付けて示している。また、各作業項目の正味時間(計)45を加算してなる合計46をも示している。   The work standard time estimate is created for each product model name 40. The work item number 41, the work item 42, the work item repetition count 43, and the work item once at a standard work speed. The net time (unit) 44 required for the above and the net time (total) 45 obtained by adding the number of times 43 to the net time (unit) are shown in association with each other. Further, a total 46 obtained by adding the net time (total) 45 of each work item is also shown.

次に、図4に示すライン落ち台数に対して適正とされる間接作業者を表記した修理工程適正人員表について説明する。この修理工程適正人員表は、図1の各マスタ10〜16と同様に、ホストコンピュータ20の記憶装置に記憶されている。   Next, a repair process appropriate personnel table showing indirect workers appropriate for the number of dropped lines shown in FIG. 4 will be described. The repair process appropriate personnel table is stored in the storage device of the host computer 20 in the same manner as the masters 10 to 16 in FIG.

この修理工程適正人員表は、検査工程で撥ねられた不良製品を修理するのに要する作業時間50と、間接作業者の人数51とを対応付けて示している。作業時間50は、図5の不良要因別修理時間マスタ14に基づいて見積もられる。不良要因別修理時間マスタ14は、先に述べた様に製品の不良要因別に求められた修理時間を格納したものであり、図5に示す様に不良症状と、不良原因と、一人前の作業者が不良製品を修理するのに要する修理時間とを対応付けて示すものである。   This repair process appropriate personnel table shows the work time 50 required to repair a defective product repelled in the inspection process and the number of indirect workers 51 in association with each other. The work time 50 is estimated based on the failure factor-specific repair time master 14 of FIG. As described above, the repair time master 14 for each defect factor stores the repair time obtained for each defect factor of the product. As shown in FIG. 5, the defect symptom, the cause of the defect, and the work for one person are stored. This indicates the repair time required for the person to repair the defective product in association with each other.

例えば、不良症状が“ファン回らず”で、不良原因が“コネクタ挿入忘れ“というの不良製品が10台あったとすると、不良要因別修理時間マスタ14を参照して、一人前の作業者が該不良製品を修理するのに要する修理時間として“6(分)”が求められ、作業時間50が60(分)(=修理時間“6(分)”×10台)と見積もられ、図3の修理工程適正人員表を参照して、作業時間50の60(分)に対応する間接作業者の人数51“2(名)”が求められる。   For example, if there are 10 defective products whose failure symptom is “no fan rotation” and the cause of failure is “forgetting to insert a connector”, referring to the repair time master 14 by failure cause, As the repair time required for repairing the defective product, “6 (minutes)” is obtained, and the work time 50 is estimated to be 60 (minutes) (= repair time “6 (minutes)” × 10 units). The number of indirect workers 51 “2 (name)” corresponding to 60 (minutes) of the work time 50 is obtained with reference to the appropriate repair process personnel table.

尚、本実施形態では、図6に示す様に修理工程の作業テーブルTの設置台数を6台としているので、修理工程適正人員表における間接作業者の最大人数を6名としている。   In the present embodiment, as shown in FIG. 6, the number of work tables T for the repair process is set to six, so the maximum number of indirect workers in the repair process appropriate personnel table is six.

次に、本実施形態の作業配分装置による人員配置の処理過程を、図7及び図8のフローチャートを参照しつつ説明する。   Next, the process of staffing by the work distribution device of this embodiment will be described with reference to the flowcharts of FIGS.

まず、図7のフローチャートに従って、人員配置の変更が必要であるか否かが判定される。演算部5は、任意設定された時刻になると、管理部4を通じて、生産計画マスタ10内の生産計画と生産実績マスタ11内の生産実績データとを比較し、生産実績が生産計画台数を満たすか否かを判定する(ステップS101)。例えば、生産計画台数を満たすのであれば(ステップS101で「Yes」)、演算部5は、生産ラインを停止させて、製品の生産作業を終了する。   First, in accordance with the flowchart of FIG. 7, it is determined whether or not the personnel assignment needs to be changed. The arithmetic unit 5 compares the production plan in the production plan master 10 with the production result data in the production result master 11 through the management unit 4 at an arbitrarily set time, and whether the production result satisfies the number of production plans. It is determined whether or not (step S101). For example, if the planned production quantity is satisfied (“Yes” in step S101), the calculation unit 5 stops the production line and ends the product production work.

また、生産計画台数を満たさないのであれば(ステップS101で「No」)、演算部5は、管理部4を通じて、就業時間マスタ16内の就業可能な最遅残業時刻を参照し、現在の時刻が就業可能な最遅残業時刻に達しているかどうかを判定する(ステップS102)。最遅残業時刻に達しているのであれば(ステップS102で「Yes」)、ラインを停止させ作業を終了する。   If the planned production quantity is not satisfied (“No” in step S101), the calculation unit 5 refers to the latest overtime time at which work can be performed in the work time master 16 through the management unit 4, and the current time It is determined whether or not the latest overtime time at which work is possible has been reached (step S102). If the latest overtime time has been reached (“Yes” in step S102), the line is stopped and the operation is terminated.

また、就業可能な最遅残業時刻に達していないのではあれば(ステップS102で「No」)、演算部5は、就業可能な最遅残業時刻に達するまでには生産計画台数が満たされる様に人員配置を変更する必要があるとみなし、この人員配置の変更を行うために図2のフローチャートの処理を実行する。   In addition, if the latest overtime time at which work is possible has not been reached (“No” in step S102), the calculation unit 5 may ensure that the planned number of production is satisfied before the latest overtime time at which work can be reached. 2 is executed, and the process of the flowchart of FIG. 2 is executed to change the personnel assignment.

尚、ステップS101の判定が行われる任意設定された時刻は、例えば休憩前の時刻に設定される。これにより、人員配置を変更する必要があるとみなされたとしても、休憩直後に人員配置が変更されることになり、作業中の変更が行われず、作業者の配置変更に伴う時間的なロスが軽減される。   Note that the arbitrarily set time at which the determination in step S101 is performed is set to, for example, the time before the break. As a result, even if it is deemed necessary to change the personnel allocation, the personnel allocation will be changed immediately after the break, and no changes will be made during the work, resulting in a time loss associated with the operator's allocation change. Is reduced.

次に、図8のフローチャートに従って、人員配置の変更処理を説明する。まず、演算部5は、管理部4を通じて、ライン落ちマスタ12内のライン落ちデータと修理実績マスタ13内の修理実績データを参照し、現在の不良製品の台数と不良症状を求める(ステップS110)。   Next, according to the flowchart of FIG. First, the calculation unit 5 refers to the line drop data in the line drop master 12 and the repair record data in the repair record master 13 through the management unit 4 to obtain the current number of defective products and defect symptoms (step S110). .

例えば、ライン落ちマスタ12内のライン落ちデータは、図9に示す様に検査工程における不良製品の検査日時と、機種コードと、経歴書Noと、不良症状とを対応付けたものである。また、修理実績マスタ13内の修理実績データは、図10に示す様に修理工程での不良製品の修理開始時刻並びに終了時刻と、機種コードと、経歴書Noと、不良原因とを対応付けたものである。演算部5は、ライン落ちデータの経歴書Noと修理実績データの経歴書Noとを比較参照して、発生した全ての不良製品のうちから既に修理された不良製品を取り除いて、未だに修理されていない不良製品の台数を求め、これを現在の不良製品の台数とし、現在の不良製品の不良症状を求める。   For example, the line drop data in the line drop master 12 is associating an inspection date / time of a defective product, a model code, a resume number, and a defective symptom in the inspection process as shown in FIG. Further, the repair record data in the repair record master 13 correlates the repair start time and end time of the defective product in the repair process, the model code, the resume No., and the cause of the defect as shown in FIG. Is. The arithmetic unit 5 compares and refers to the resume No of the line omission data and the resume No of the repair record data, removes the defective products that have already been repaired from all the defective products that have occurred, and is still being repaired. The number of non-defective products is obtained, and this is set as the current number of defective products, and the defective symptoms of the current defective product are obtained.

次に、演算部5は、管理部4を通じて、図5に示す様な不良要因別修理時間マスタ14を参照して、ステップS111で求めた現在の不良製品毎に、一人前の作業者が不良製品を修理するのに要する修理時間を求め、現在の不良製品全てを修理するのに要する合計の修理時間を作業時間50として求める。そして、演算部5は、管理部4を通じて、図3の修理工程適正人員表を参照し、この作業時間50に対応する間接作業者の人数51を求める(ステップS111)。   Next, the calculation unit 5 refers to the defect factor-specific repair time master 14 as shown in FIG. 5 through the management unit 4 and determines that a single worker is defective for each current defective product obtained in step S111. The repair time required for repairing the product is obtained, and the total repair time required for repairing all currently defective products is obtained as the work time 50. And the calculating part 5 calculates | requires the number 51 of the indirect worker corresponding to this work time 50 with reference to the repair process appropriate personnel table of FIG. 3 through the management part 4 (step S111).

尚、現在の不良製品の不良症状を引き起こした不良原因が複数種類である場合は、例えば各不良原因のうちの最大の修理時間を選択して、合計の修理時間を求めれば良い。あるいは、各不良原因の修理時間の平均を用いても良い。   In addition, when there are a plurality of types of failure causes that cause a failure symptom of the current defective product, for example, the maximum repair time of each failure cause may be selected to obtain the total repair time. Or you may use the average of the repair time of each defect cause.

更に、演算部5は、管理部4を通じて、人員マスタ15内の在籍人員の名簿を参照し、直接作業者と間接作業者を合わせた作業者総人数から間接作業者の人数51を差し引いて、その残りの人員全てを組立工程に配置される直接作業者とする(ステップS112)。更に、演算部5は、管理部4を通じて、図3の作業標準時間見積書を参照し、各作業項目の正味時間(計)45を加算してなる合計46を求め、この合計46をステップS112で求めた直接作業者の人数で除算した値をターゲットタクトタイムとする(ステップS113)。   Furthermore, the calculation unit 5 refers to the list of registered personnel in the personnel master 15 through the management unit 4, and subtracts the number 51 of indirect workers from the total number of workers including the direct workers and indirect workers, All the remaining personnel are direct workers arranged in the assembly process (step S112). Furthermore, the calculation unit 5 refers to the work standard time estimate in FIG. 3 through the management unit 4 to obtain a total 46 obtained by adding the net time (total) 45 of each work item, and this total 46 is obtained in step S112. The value obtained by dividing by the number of direct workers obtained in step S5 is set as the target tact time (step S113).

次に、演算部5は、生産計画マスタ10内の生産計画、生産実績マスタ11内の生産実績データ、及びステップS113で求めたターゲットタクトタイム等に基づいて、生産予測を求め、この生産予測で生産計画を達成することが可能であるか否かを判定する(ステップS114)。   Next, the calculation unit 5 obtains a production prediction based on the production plan in the production plan master 10, the production result data in the production result master 11, the target tact time obtained in step S113, and the like. It is determined whether or not the production plan can be achieved (step S114).

例えば、図11(a)に示す様に生産計画が600台であり、生産実績が現在の時刻12時10分の時点で239台であるとする。そして、時刻12時10分の時点での直行率が95%であり、ステップS113で求めたターゲットタクトタイムが53秒であるとする。直行率とは、一度も不良になることなく、組立工程から外されることなく、ストレートで組立てられた製品の台数を、生産ラインへの投入台数で除算し、その商に100を乗算した値である。   For example, as shown in FIG. 11A, it is assumed that the production plan is 600 units, and the production performance is 239 units at the current time 12:10. The direct rate at the time of 12:10 is 95%, and the target tact time obtained in step S113 is 53 seconds. The straight line rate is a value obtained by dividing the number of products assembled in a straight line by the number of products put into the production line and multiplying the quotient by 100 without causing any defects or removing from the assembly process. It is.

このとき、生産予測、すなわち生産実績が生産計画に達するのに要する必要時間は、次の式(1)で示される。   At this time, the production prediction, that is, the time required for the production performance to reach the production plan is expressed by the following equation (1).

必要時間=(生産計画−生産実績)×ターゲットタクトタイム÷直行率 …(1)
上記式(1)に、図11(a)に示す生産計画600台、生産実績239台、直行率95%、及びターゲットタクトタイム53秒を代入すると、必要時間が336分となる。
Necessary time = (Production plan-Actual production) x Target tact time ÷ Direct rate ... (1)
If 600 production plans, 239 production results, a direct production rate of 95%, and a target tact time of 53 seconds shown in FIG. 11A are substituted into the above equation (1), the required time becomes 336 minutes.

そして、演算部5は、管理部4を通じて、就業時間マスタ16内の休憩時刻、終業時刻、及び最遅残業時刻等を参照し、休憩時間80分(12:10〜13:00、15:00〜15:10及び17:40〜18:00)を求め、必要時間336分と休憩時間80分の和416分を求め、現在の時刻12時10分から416分後の時刻19時06分を生産終了予定時刻として求める。更に、演算部5は、生産終了予定時刻19時06分が最遅残業時刻以前であれば、生産計画を達成できると判定し(ステップS114で「Yes」)、また生産終了予定時刻19時06分が最遅残業時刻を超えれば、生産計画を達成できないと判定する(ステップS114で「No」)。   Then, the calculation unit 5 refers to the break time, the end work time, the latest overtime time, and the like in the working time master 16 through the management unit 4, and the break time is 80 minutes (12:10 to 13:00, 15:00). ~ 15: 10 and 17: 40 ~ 18: 00), the required time of 336 minutes and the rest time of 80 minutes, the sum of 416 minutes, and the current time of 12:10 to 416 minutes later, 19:06 Obtained as the scheduled end time. Further, the calculation unit 5 determines that the production plan can be achieved if the scheduled production end time 19:06 is before the latest overtime time (“Yes” in step S114), and the scheduled production end time 19:06. If the minute exceeds the latest overtime time, it is determined that the production plan cannot be achieved (“No” in step S114).

例えば、図11(b)に示す様に生産終了予定時刻19時06分が最遅残業時刻20時30分以前であって、生産計画を達成できる場合は(ステップS114で「Yes」)、演算部5は、組立工程の人員配置と作業配分を算出する(ステップS118)。演算部5は、例えば図12の組立工程配員マップ60を用いて、組立工程の各ステーション(作業場所)の先頭から順に人員を配置していく。図12の組立工程配員マップ60は、図1の各マスタ10〜16と同様に、ホストコンピュータ20の記憶装置に記憶されており、演算部5から管理部4を通じて参照することができる。また、演算部5は、管理部4を通じて、図3の作業標準時間見積書を参照し、各作業者の作業標準時間がステップS113で求めたターゲットタクトタイムに最も近くなる様に作業配分を割振る。   For example, as shown in FIG. 11B, when the scheduled production end time 19:06 is before the latest overtime time 20:30 and the production plan can be achieved (“Yes” in step S114), the calculation is performed. The unit 5 calculates the personnel allocation and work distribution in the assembly process (step S118). The calculation unit 5 arranges personnel in order from the head of each station (work place) in the assembly process using, for example, the assembly process dispatch map 60 of FIG. The assembly process assignment map 60 of FIG. 12 is stored in the storage device of the host computer 20 as with the masters 10 to 16 of FIG. Further, the calculation unit 5 refers to the work standard time estimate in FIG. 3 through the management unit 4 and allocates the work distribution so that the work standard time of each worker is closest to the target tact time obtained in step S113. shake.

この作業配分について、図13の具体例を用いて説明する。No1の作業者には、“バーコード読み取り”から“LCDユニットを取る”までの作業を割振り、その作業標準時間を52秒に設定する。仮に、“バックライト組品にLCDユニットを位置決め”までの作業をNo1の作業者に割振ると、作業標準時間が56.1秒となり、ステップS113で求めたターゲットタクトタイム53秒との差が大きくなる。よって、“バックライト組品にLCDユニットを位置決め”からの作業がNo2の作業者に割振られる。以降同様に、No2の作業者、No3の作業者、…に対して、作業標準時間がターゲットタクトタイム53秒に近くなる様に作業を順次割振って行く。   This work distribution will be described using a specific example of FIG. For the No. 1 worker, work from “bar code reading” to “take LCD unit” is assigned, and the work standard time is set to 52 seconds. If the work up to “positioning the LCD unit on the backlight assembly” is allocated to the No. 1 worker, the work standard time is 56.1 seconds, and the difference from the target tact time 53 seconds obtained in step S113 is growing. Therefore, the work from “positioning the LCD unit to the backlight assembly” is allocated to the No. 2 worker. In the same manner, the work is sequentially assigned to the No. 2 worker, No. 3 worker,... So that the standard work time is close to the target tact time of 53 seconds.

最後に、管理部4は、ステップS110〜ステップS114、及びステップS118で求められた結果を生産管理モニター装置24及びプリンター31に出力し(ステップS119)、この処理を終了する。図14は、生産管理モニター装置24による表示例を示している。   Finally, the management unit 4 outputs the results obtained in steps S110 to S114 and step S118 to the production management monitor device 24 and the printer 31 (step S119), and ends this process. FIG. 14 shows a display example by the production management monitor device 24.

また、生産予測が生産計画を達成しない場合は(ステップS114で「No」)、演算部5は、生産予測が計画台数を最遅残業時刻までに達成できる様にターゲットタクトタイムを変更する(S115)。すなわち、ターゲットタクトタイムを短くして、最遅残業時刻以前の生産終了予定時刻を設定する。このターゲットタクトタイムは、次式(2)にから求められる。   When the production prediction does not achieve the production plan (“No” in step S114), the calculation unit 5 changes the target tact time so that the production prediction can achieve the planned number of vehicles by the latest overtime time (S115). ). That is, the target tact time is shortened and the scheduled production end time before the latest overtime time is set. This target tact time is obtained from the following equation (2).

ターゲットタクトタイム(秒)=
(現時刻から最遅残業時刻までの稼動可能時間)÷(生産計画−生産実績)×直行率…(2)
このターゲットタクトタイムの変更について、図15の具体例を用いて説明する。図15(a)に示す様に生産計画600台、12時10分の時点での生産実績130台、及び直行率95%であるとすると、ステップS113でターゲットタクトタイムが56秒と設定される。この場合、図15(b)に示す様な生産予測となり、生産実績が生産計画600台に達するときには最遅残業時刻20:30を過ぎてしまう。従って、ステップS114においてターゲットタクトタイム56秒では生産予測が生産計画を達成しないと判定され、ステップS115に移行することになる。ステップS115においては、上記式(2)を用いて、ターゲットタクトタイムが再算出される。生産計画600台、現在の時刻12時10分の時点での生産実績130台、直行率95%、及び該現在の時刻から最値残業時刻までの稼動可能時間420分を上記式(2)に代入すると、ターゲットタクトタイム51秒が算出される。
Target tact time (seconds) =
(Operating time from the current time to the latest overtime) ÷ (Production plan-Actual production) x Direct rate ... (2)
The change of the target tact time will be described using a specific example of FIG. As shown in FIG. 15A, assuming that the production plan is 600 units, the production result is 130 units at 12:10, and the direct rate is 95%, the target tact time is set to 56 seconds in step S113. . In this case, the production prediction is as shown in FIG. 15B, and the latest overtime 20:30 is passed when the production performance reaches 600 production plans. Therefore, in step S114, it is determined that the production prediction does not achieve the production plan at the target tact time of 56 seconds, and the process proceeds to step S115. In step S115, the target tact time is recalculated using the above equation (2). Production plan 600 units, production results 130 units at the current time 12:10, direct rate 95%, and operation time 420 minutes from the current time to the maximum overtime time in the above formula (2) When substituted, a target tact time of 51 seconds is calculated.

次に、演算部5は、変更されたターゲットタクトタイムを設定するのに必要な直接作業者の人数を再算出する(ステップS116)。この直接作業者の人数は、次式(3)から再算出される。   Next, the computing unit 5 recalculates the number of direct workers necessary to set the changed target tact time (step S116). The number of direct workers is recalculated from the following equation (3).

直接作業者の人数=
(組立工程における作業標準時間の合計)÷ターゲットタクトタイム …(3)
ターゲットタクトタイムが51秒であり、図3の作業標準時間見積書を参照すると、合計46が1479秒であることから、上記式(3)に基づいて直接作業者の人数が29名と算出される。
Number of direct workers =
(Total work standard time in assembly process) ÷ Target tact time (3)
Since the target tact time is 51 seconds and the work standard time estimate in FIG. 3 is referred to, the total 46 is 1479 seconds, so the number of direct workers is calculated as 29 based on the above formula (3). The

次に、演算部5は、管理部4を通じて、人員マスタ15内の在籍人員の名簿を参照し、直接作業者と間接作業者を合わせた作業者総人数から直接作業者の人数を減算して、間接作業者の人数を設定し(ステップS117)、組立工程の人員配置と作業配分を算出する(ステップS118)。人員配置は、先に述べた様に図12の組立工程配員マップ60を用いて、組立工程の各ステーション(作業場所)の先頭から順に人員を配置していくというものである。また、作業配分は、図3の作業標準時間見積書を参照しつつ、各作業者の作業標準時間がステップS115で求めたターゲットタクトタイム51秒に最も近くなる様に作業配分を割振るというものである。   Next, the calculation unit 5 refers to the list of registered personnel in the personnel master 15 through the management unit 4 and subtracts the number of workers directly from the total number of workers including the direct workers and indirect workers. Then, the number of indirect workers is set (step S117), and the personnel allocation and work distribution in the assembly process are calculated (step S118). As described above, the personnel allocation uses the assembly process allocation map 60 of FIG. 12 to allocate personnel in order from the beginning of each station (work place) in the assembly process. In addition, the work allocation is performed by allocating the work distribution so that the work standard time of each worker is closest to the target tact time 51 seconds obtained in step S115 while referring to the work standard time estimate in FIG. It is.

この結果として、図15(c)、(d)に示す様な生産計画を満たす生産予測が成り立つ。   As a result, production prediction that satisfies the production plan as shown in FIGS. 15C and 15D is established.

最後に、管理部4は、ステップS110〜ステップS118で求められた結果を生産管理モニター装置24及びプリンター31に出力し(ステップS119)、この処理を終了する。   Finally, the management unit 4 outputs the results obtained in steps S110 to S118 to the production management monitor device 24 and the printer 31 (step S119), and ends this process.

この様に本実施形態では、直接作業者と間接作業者との人員配置の入れ替えを行っている。例えば、不良製品の台数が増えたときには、間接作業者を増やして、不良製品を溜め込まないような配置指示を行う。また、生産が遅れている時は、直接作業者を増やして、生産実績を挽回させている。これにより、従来の様に作業者を追加するか、当日の計画台数を下げて、月度の計画で調整するか、作業者に残業を課すといった生産条件の変更を必要とせず、人員配置および作業配分が可能になる。   As described above, in the present embodiment, the personnel assignment between the direct worker and the indirect worker is changed. For example, when the number of defective products increases, the number of indirect workers is increased and a placement instruction is given so as not to store defective products. In addition, when production is delayed, the number of workers is increased directly and production performance is recovered. As a result, it is not necessary to change the production conditions such as adding workers as before, reducing the planned number of days on the day, adjusting according to the monthly plan, or imposing overtime on workers. Allocation is possible.

尚、本発明は、上記実施形態に限定されるものではなく、多様に変形することができる。例えば、バーコードの代わりに、ICタグ等を製品に付加し、ICタグを通じて、製品のデータを読み書き及び収集する様にしても良い。   In addition, this invention is not limited to the said embodiment, It can deform | transform variously. For example, instead of a bar code, an IC tag or the like may be added to a product, and product data may be read / written and collected through the IC tag.

本発明は、生産現場等において、有効利用されることなくロスの要因となっていた過剰な間接作業者の配置をなくし、ライン落ち在庫に対して適正な間接作業者を配置することにより、生産現場の更なる生産性向上のための解決策の1つとして適用することができる。   The present invention eliminates the placement of excessive indirect workers that have been a factor of loss without being effectively used at production sites, etc. It can be applied as one of the solutions for further on-site productivity improvement.

本発明の作業配分装置の一実施形態を示す機能ブロック図である。It is a functional block diagram which shows one Embodiment of the work distribution apparatus of this invention. 図1の作業配分装置を実現するシステムを示す図である。It is a figure which shows the system which implement | achieves the work distribution apparatus of FIG. 図1の作業配分装置における作業標準時間見積書を例示する図である。It is a figure which illustrates the work standard time estimate in the work distribution apparatus of FIG. 図1の作業配分装置における修理工程適正人員表を例示する図である。It is a figure which illustrates the repair process appropriate personnel table in the work distribution apparatus of FIG. 図1の作業配分装置における不良要因別修理時間マスタを例示する図である。It is a figure which illustrates the repair time master classified by defect factor in the work distribution apparatus of FIG. 修理工程の作業テーブルの設置態様を例示する図である。It is a figure which illustrates the installation aspect of the work table of a repair process. 図1の作業配分装置による人員配置の変更が必要であるか否かの判定処理を示すフローチャートである。It is a flowchart which shows the determination processing whether the personnel allocation change by the work distribution apparatus of FIG. 1 is required. 図1の作業配分装置による人員配置の変更処理を示すフローチャートである。It is a flowchart which shows the personnel allocation change process by the work distribution apparatus of FIG. 図1の作業配分装置におけるライン落ちマスタを例示する図である。It is a figure which illustrates the line drop master in the work distribution apparatus of FIG. 図1の作業配分装置における修理実績マスタを例示する図である。It is a figure which illustrates the repair performance master in the work distribution apparatus of FIG. (a)は生産予測に用いられるデータを示す図表であり、(b)は生産予測の結果を示すグラフである。(A) is a chart which shows the data used for production prediction, (b) is a graph which shows the result of production prediction. 図1の作業配分装置における組立工程配員マップを例示する図である。It is a figure which illustrates the assembly process staffing map in the work distribution apparatus of FIG. 図1の作業配分装置による作業配分を例示する図表である。It is a chart which illustrates work distribution by the work distribution device of FIG. 図1の作業配分装置における生産管理モニター装置の表示例を示す図である。It is a figure which shows the example of a display of the production management monitor apparatus in the work distribution apparatus of FIG. (a)は生産予測に用いられるデータを示す図表であり、(b)は生産予測の結果を示すグラフであり、(c)は(a)のデータにおけるターゲットタイムを変更して示す図表であり、(d)は変更されたターゲットタイムに基づく生産予測の結果を示すグラフである。(A) is a chart showing data used for production prediction, (b) is a chart showing the result of production prediction, and (c) is a chart showing a change in target time in the data of (a). (D) is a graph which shows the result of the production prediction based on the changed target time.

符号の説明Explanation of symbols

1 生産実績収集部
2 ライン落ち実績収集部
3 修理実績収集部
4 管理部
5 演算部
6 結果出力部
10 生産計画マスタ
11 生産実績マスタ
12 ライン落ちマスタ
13 修理実績マスタ
14 不良要因別修理時間マスタ
15 人員マスタ
16 就業時間マスタ
20 ホストコンピュータ
21 投入実績収集装置
22 端末装置
23 バーコードリーダー
24 生産管理モニター
25 ライン落ち実績収集装置
26 端末装置
27 バーコードリーダー
28 修理実績収集装置
29 端末装置
30 バーコードリーダー
31 プリンター
40 機種名
41 No
42 作業項目
43 回数
44 正味時間(単)
45 正味時間(計)
46 合計
50 作業時間(分)
51 人員(名)
60 組立工程配員マップ
DESCRIPTION OF SYMBOLS 1 Production result collection part 2 Line drop result collection part 3 Repair result collection part 4 Management part 5 Calculation part 6 Result output part 10 Production plan master 11 Production result master 12 Line drop master 13 Repair result master 14 Repair time master 15 by defect factor Personnel master 16 Working time master 20 Host computer 21 Input result collection device 22 Terminal device 23 Bar code reader 24 Production management monitor 25 Line drop result collection device 26 Terminal device 27 Bar code reader 28 Repair result collection device 29 Terminal device 30 Bar code reader 31 Printer 40 Model name 41 No
42 work items 43 times 44 net time (single)
45 Net time (total)
46 Total 50 Working hours (minutes)
51 people
60 Assembly process staffing map

Claims (3)

製品を生産する生産ラインの工程間で人員入れ替えを迅速に行う為の作業配分装置であって、
製品の生産実績データを収集する生産実績収集部と、
不良製品のデータを収集するライン落ち実績収集部と、
修理された製品のデータを収集する修理実績収集部と、
製品の生産計画を格納した生産計画マスタと、
前記生産実績収集部で収集された生産実績データを格納した生産実績マスタと、
前記ライン落ち実績収集部で収集されたデータを格納したライン落ちマスタと、
前記修理実績収集部で収集されたデータを格納した修理実績マスタと、
製品の不良要因別にかかる修理時間を格納した不良要因別修理時間マスタと、
製品を組立てる直接作業者及び不良製品を修理する間接作業者の管理データを格納した人員マスタと、
少なくとも生産ラインの最遅残業時刻を管理する就業時間マスタと、
前記生産実績マスタ、前記ライン落ちマスタ、及び前記修理実績マスタに対するデータの書き込み及び読み出しを管理する管理部と、
前記生産計画マスタ、前記生産実績マスタ、前記ライン落ちマスタ、前記修理実績マスタ、前記不良要因別修理時間マスタ、前記人員マスタ、及び前記就業時間マスタのそれぞれのデータに基づいて、直接作業者及び間接作業者を入れ替え、人員配置及び作業配分を求める演算部と、
前記演算部により求められた人員配置及び作業配分結果を出力する結果出力部と
を備えることを特徴とする作業配分装置。
A work distribution device for quickly changing personnel between processes on a production line that produces products,
A production performance collection unit that collects product production data;
A line drop record collection unit that collects data on defective products,
A repair performance collection unit that collects data on repaired products;
A production plan master that stores the production plan for the product,
A production record master storing production record data collected by the production record collection unit;
A line drop master storing data collected by the line drop record collection unit;
A repair record master that stores data collected by the repair record collection unit;
A repair time master by defect factor that stores the repair time for each defect factor of the product,
A personnel master that stores management data for direct workers who assemble products and indirect workers who repair defective products,
A working hour master that manages at least the latest overtime on the production line;
A management unit that manages writing and reading of data with respect to the production record master, the line drop master, and the repair record master;
Based on the respective data of the production plan master, the production record master, the line failure master, the repair record master, the repair factor master by defect factor, the personnel master, and the working time master, direct workers and indirect An operator that replaces workers and obtains personnel allocation and work distribution; and
A work distribution apparatus comprising: a result output unit that outputs a staff assignment and a work distribution result obtained by the calculation unit.
請求項1に記載の作業配分装置における生産実績収集部の機能を果たすために、組立工程における製品のバーコードを読み取るバーコードリーダー、及びバーコードリーダーにより読み取られたデータを収集するコンピュータを少なくとも含む投入実績収集装置と、
請求項1に記載の作業配分装置におけるライン落ち実績収集部の機能を果たすために、検査工程における製品のバーコードを読み取るバーコードリーダー、及びバーコードリーダーにより読み取られたデータを収集するコンピュータを少なくとも含むライン落ち実績収集装置と、
請求項1に記載の作業配分装置における修理実績収集部の機能を果たすために、修理工程における製品のバーコードを読み取るバーコードリーダー、及びバーコードリーダーにより読み取られたデータを収集するコンピュータを少なくとも含む修理実績収集装置と、
請求項1に記載の作業配分装置における生産計画マスタ、生産実績マスタ、ライン落ちマスタ、修理実績マスタ、不良要因別修理時間マスタ、人員マスタ、就業時間マスタ、管理部、及び演算部のそれぞれの機能を果たすコンピュータと、
請求項1に記載の作業配分装置における結果出力部の機能を果たすプリンターと、
ターゲットタクトタイム、人員配置、及び作業配分等を表示する生産管理モニターと
を備えることを特徴とする作業配分システム。
In order to fulfill the function of the production result collecting unit in the work distribution device according to claim 1, at least a barcode reader for reading a barcode of a product in an assembly process and a computer for collecting data read by the barcode reader are included. Input record collection device,
In order to perform the function of the line drop record collection unit in the work distribution device according to claim 1, at least a barcode reader that reads a barcode of a product in an inspection process, and a computer that collects data read by the barcode reader Including line drop record collection device,
In order to fulfill the function of the repair result collecting unit in the work distribution device according to claim 1, at least a bar code reader for reading a bar code of a product in a repair process and a computer for collecting data read by the bar code reader are included. Repair results collection device,
The functions of the production plan master, production result master, line failure master, repair result master, repair factor master by defect factor, personnel master, working time master, management unit, and calculation unit in the work distribution device according to claim 1 A computer that fulfills
A printer that functions as a result output unit in the work distribution device according to claim 1;
A work distribution system comprising: a production management monitor for displaying target tact time, personnel assignment, work distribution, and the like.
不良製品の台数を算出するステップと、
前記不良製品の台数に基づいて、不良製品を修理する間接作業者の人数を算出するステップと、
作業者総人数から前記間接作業者の人数を差し引いて、製品を組立てる直接作業者の人数を算出するステップと、
前記直接作業者の人数に基づいてターゲットタクトタイムを算出するステップと、
前記ターゲットタクトタイムに基づいて、生産予測が生産計画を達成するか否かを判定するステップと、
生産予測が生産計画を達成できないと判定された場合に、生産計画を達成し得る様にターゲットタクトタイムを再算出するステップと、
前記再算出されたターゲットタクトタイムから直接作業者の人数を再算出するステップと、
作業者総人数から前記再算出された直接作業者の人数を差し引いて、間接作業者の人数を再算出するステップと、
を含むことを特徴とする作業配分方法。
Calculating the number of defective products;
Calculating the number of indirect workers repairing the defective product based on the number of defective products;
Subtracting the number of indirect workers from the total number of workers to calculate the number of direct workers to assemble the product;
Calculating a target tact time based on the number of direct workers;
Determining whether the production forecast achieves a production plan based on the target tact time; and
Recalculating the target tact time so that the production plan can be achieved if it is determined that the production forecast cannot achieve the production plan;
Recalculating the number of workers directly from the recalculated target tact time;
Subtracting the recalculated number of direct workers from the total number of workers to recalculate the number of indirect workers;
A work distribution method characterized by including:
JP2005178244A 2005-06-17 2005-06-17 Work distribution device, work distribution system and work distribution method Pending JP2006350832A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005178244A JP2006350832A (en) 2005-06-17 2005-06-17 Work distribution device, work distribution system and work distribution method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005178244A JP2006350832A (en) 2005-06-17 2005-06-17 Work distribution device, work distribution system and work distribution method

Publications (1)

Publication Number Publication Date
JP2006350832A true JP2006350832A (en) 2006-12-28

Family

ID=37646575

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005178244A Pending JP2006350832A (en) 2005-06-17 2005-06-17 Work distribution device, work distribution system and work distribution method

Country Status (1)

Country Link
JP (1) JP2006350832A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012068848A (en) * 2010-09-22 2012-04-05 Honda Motor Co Ltd Production management device
JPWO2011055601A1 (en) * 2009-11-04 2013-03-28 株式会社エヌ・ティ・ティ・ドコモ Information analysis apparatus and information analysis method
JP2014235495A (en) * 2013-05-31 2014-12-15 株式会社日立製作所 Work instruction system and method
CN103886440B (en) * 2012-12-20 2017-06-27 上海华虹宏力半导体制造有限公司 The distribution system and distribution method of a kind of wafer
CN107966964A (en) * 2016-10-19 2018-04-27 村田机械株式会社 Management system of spinning and spinning management method
JP2018097801A (en) * 2016-12-16 2018-06-21 富士通株式会社 Determination device, determination method and determination program for allocated personnel number
JP2021105864A (en) * 2019-12-26 2021-07-26 株式会社日立製作所 Computer system and method for determining resource arrangement

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPWO2011055601A1 (en) * 2009-11-04 2013-03-28 株式会社エヌ・ティ・ティ・ドコモ Information analysis apparatus and information analysis method
JP5468084B2 (en) * 2009-11-04 2014-04-09 株式会社Nttドコモ Information analysis apparatus and information analysis method
JP2012068848A (en) * 2010-09-22 2012-04-05 Honda Motor Co Ltd Production management device
CN103886440B (en) * 2012-12-20 2017-06-27 上海华虹宏力半导体制造有限公司 The distribution system and distribution method of a kind of wafer
JP2014235495A (en) * 2013-05-31 2014-12-15 株式会社日立製作所 Work instruction system and method
CN107966964A (en) * 2016-10-19 2018-04-27 村田机械株式会社 Management system of spinning and spinning management method
JP2018097801A (en) * 2016-12-16 2018-06-21 富士通株式会社 Determination device, determination method and determination program for allocated personnel number
JP2021105864A (en) * 2019-12-26 2021-07-26 株式会社日立製作所 Computer system and method for determining resource arrangement
US11416302B2 (en) 2019-12-26 2022-08-16 Hitachi, Ltd. Computer system and method for determining of resource allocation

Similar Documents

Publication Publication Date Title
JP2006350832A (en) Work distribution device, work distribution system and work distribution method
US8577712B2 (en) Assessing risk
WO2019056710A1 (en) Supplier recommendation method and apparatus, and computer readable storage medium
US20090157458A1 (en) Supply chain evaluation system, method, and program
WO2020016451A1 (en) Optimized patient schedules based on patient workflow and resource availability
JPH02155067A (en) Method for warning inventory and system using such method
Bokhorst et al. Lean production control at a high-variety, low-volume parts manufacturer
US20110093365A1 (en) System and Process for Monitoring, Control and Withdrawal of Consumable Items in a Production Environment
JP4982196B2 (en) Replacement part order processing apparatus, replacement part order processing method, and replacement part order processing program
US20150142494A1 (en) System and method for scheduling temporary resources
US20150242782A1 (en) Interactive Planning Method And Tool
Huang Information architecture for effective Workload Control: an insight from a successful implementation
JP2018206000A (en) Production planning system, production planning method and personnel ability calculation method
CN116502830A (en) Scheduling plan generation method, scheduling plan generation system and scheduling plan generation product
JP6265871B2 (en) Sales operation support system and sales operation support method
EP1983477A1 (en) Apparatus and method for processing management information
JPH11353368A (en) Profit management system, profit managing method, and record medium
JP2018169684A (en) Business support device
JP2010272068A (en) Facility managing apparatus
JP2000067111A (en) Scheduling device and ordered production planning system
US20080065458A1 (en) Method and system for reducing total transactional lead time and enhancing quality of a process within a healthcare environment
JP2728450B2 (en) Project management diagnostic system
Mendibil et al. Measuring and improving business process reliability
JP2003330523A (en) System for production loss reduction, method therefor and computer readable recording medium
RU65264U1 (en) AUTOMATED CONTROL SYSTEM INFORMATION FLOWS MODEL