JP2004362187A - Project management system - Google Patents

Project management system Download PDF

Info

Publication number
JP2004362187A
JP2004362187A JP2003158790A JP2003158790A JP2004362187A JP 2004362187 A JP2004362187 A JP 2004362187A JP 2003158790 A JP2003158790 A JP 2003158790A JP 2003158790 A JP2003158790 A JP 2003158790A JP 2004362187 A JP2004362187 A JP 2004362187A
Authority
JP
Japan
Prior art keywords
task
project
management system
project management
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2003158790A
Other languages
Japanese (ja)
Other versions
JP4228786B2 (en
Inventor
Hiroyuki Konno
浩之 金野
Yasuhiro Hamazuka
康宏 濱塚
Junichi Hamano
順一 浜野
Yoshie Matsuzaki
吉衛 松崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2003158790A priority Critical patent/JP4228786B2/en
Publication of JP2004362187A publication Critical patent/JP2004362187A/en
Application granted granted Critical
Publication of JP4228786B2 publication Critical patent/JP4228786B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a project management system that assists in planning projects with accuracy. <P>SOLUTION: The project management system comprises: a WBS task registration means connected to the system of a project manager and the system of a project member via a network to register the operations of the project as tasks subdivided in the form of a tree; a ToDo list registration means for registering daily tasks for each operator; and a database for integrally managing and storing as task information the contents registered by the WBS task registration means and the ToDo list registration means. The schedule of each project and the schedule of each operator are integrally managed. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】
本発明はプロジェクトを効率良く運営するためのプロジェクト管理システムに関する。
【0002】
【従来の技術】
従来、プロジェクト管理システムとして、プロジェクト計画と進捗を基にプロジェクト管理するシステムが知られている(例えば、特許文献1参照)。
【0003】
この例では、プロジェクトの進捗が計画より遅れた場合に、その進捗遅れに伴う後続作業の作業期間を自動変更するものである。
【0004】
【特許文献1】
特開平10−240804号公報
【0005】
【発明が解決しようとする課題】
上記従来の技術で挙げた文献に記載された発明は、あらかじめ人手で作成するプロジェクト計画の日程が妥当な期間であれば、進捗に合わせ再スケジーリングできる為、有効である。しかし、プロジェクト計画の日程が、極端に短かった場合、進捗遅れが多発するため、再スケジューリングが繰り返し実施される。その結果、プロジェクトの終了時期がわからなくなる問題が発生する。
【0006】
本発明は、上記問題を解決するためになされたもので、精度の良いプロジェクト計画立案支援するプロジェクト管理システムを提供することを目的とする。
【0007】
【課題を解決するための手段】
上記課題を解決するために、本発明のプロジェクト管理システムは、ネットワークを介してプロジェクトマネジャのシステムとプロジェクトメンバのシステムと接続され、プロジェクトの作業をツリー状に細分化したタスクとして登録するWBSタスク登録手段と、作業者別に日々のタスクを登録するToDoリスト登録手段と、前記WBSタスク登録手段とToDoリスト登録手段で登録した内容をタスク情報として一元管理記憶するデータベースとを備えるようにしたもので、プロジェクト毎のスケジュールと作業者毎のスケジュールとを統合管理することで精度の良いスケジュール立案を可能としたシステムである。
【0008】
【発明の実施の形態】
以下、本発明のプロジェクト管理システムの一実施形態について図面を用いて説明する。
【0009】
まず、本発明のプロジェクト管理システムの全体構成を説明する。
【0010】
図1は、本発明のプロジェクト管理システムにおける一実施形態の全体構成を示すブロック図である。
【0011】
図1に示すように、プロジェクト管理システムは、プロジェクト管理システムのサーバ1に、少なくとも一つのプロジェクトマネジャが操作するコンピュータ3(以下、単にプロジェクトマネジャと称す)と少なくとも一つのプロジェクトメンバが操作するコンピュータ4(以下、単にプロジェクトメンバと称す)と少なくとも一つの請負企業が操作するコンピュータ5(以下、単に請負企業と称す)がネットワーク2を介して接続されて構成される。
【0012】
プロジェクト管理システムのサーバ1は、プロジェクトのタスクを記憶するタスク登録手段11と、タスク登録した登録の一部あるいは全部を請負企業4に委託するアウトソーシング手段12と、アウトソーシングによるサービス料を課金する課金手段13と、タスク登録手段11、アウトソーシング手段12、課金手段13の実行結果を記憶するデータベース18を有している。プロジェクトマネジャ3とプロジェクトメンバ4は、ネットワーク2を介して、タスク登録手段11を操作することができる。なお、タスク登録手段11は、プロジェクトの作業を細分化したWBS(Work Breakdown Structure)として登録するWBSタスク登録手段111と日毎の作業内容を登録するToDoリスト登録手段112とタスクの表示形式を切り替えるタスク切替表示手段とで構成される。
【0013】
また、プロジェクトマネジャ3と請負企業4は、ネットワーク2を介して、アウトソーシング手段12を操作することができる。
【0014】
次に、プロジェクト管理システムのハードウェア構成について説明する。
【0015】
図2は、プロジェクト管理システムの一実施形態におけるハードウェア構成を示したものである。
【0016】
プロジェクト管理システムは、プロジェクト管理システムのサーバ1の機能が搭載された電子計算機10と、プロジェクトマネジャが利用する電子計算機30と、プロジェクトメンバが利用する電子計算機40と、請負起業が利用する電子計算機50で構成される。ここで電子計算機は、モニタ、記憶装置、キーボード、LANカードなどの入出力装置が具備されている。また、電子計算機30、電子計算機40、電子計算機50は、ネットワーク2を介して電子計算機10に搭載されたプロジェクト管理機能を利用することができる。なお、ネットワーク2は、有線の通信ケーブルに限らず無線でもよい。
【0017】
以下、精度の良いプロジェクト計画の立案支援するタスク登録手段11のWBSタスク登録手段111とToDoリスト登録手段112を説明する。
【0018】
はじめに、プロジェクトの作業を細分化したタスクをデータベース18に登録するWBSタスク登録手段111について図3から図5を用いて説明する。
【0019】
図3は、プロジェクトのタスク情報をデータベース18に登録するための内容を説明する図である。
【0020】
図4は、プロジェクトのタスク情報をWBS形式にて登録・表示するための画面例である。
【0021】
図5は、プロジェクトのタスク情報の登録例である。
【0022】
図3の181にタスク情報の仕様を示す。タスク情報181には、プロジェクト名称、WBS No、WPフラグ、タスク名称、開始予定日、期限、工数、必要スキル、リソース(タスクの担当者)、先行WBS No、開始実績、終了実績、達成率、余裕期間などの項目がある。なお、プロジェクト名称とWBS Noとで、データの一意性を表現する。
【0023】
WBS登録画面は、例えば図4に示すようなものである。プロジェクトマネジャ3もしくはプロジェクトメンバ4の操作としては、WBS登録画面111aに従って、まず対象とするプロジェクトをメニュー111bより選択する。選択したプロジェクトに関連するデータが図3のタスク情報181に格納されている場合は、その内容がスプレッドシート111cに表示される。操作者は、スプレッドシート111cの追記したい項目にデータを入力する。
【0024】
図5は、図4に示したような情報を入力後、登録ボタン押下するとで、タスク情報181に登録される内容を表した図である。ここでWP(Work Package)フラグとは、登録されたタスクが詳細化された末端のタスクか否かを表すもので、Trueの場合は末端のタスクを、Falseの場合は、上位レベルのタスクを意味する。
また、WPフラグがTrueのタスクのみに、開始予定日、期限、工数、必要スキル、リソースなどの情報を登録する。
【0025】
次に、プロジェクトメンバ3が日毎のToDoリストをデータベース18に登録するToDoリスト登録手段112について図6と図7を用いて説明する。
【0026】
図6は、リソース(タスクの担当者)毎にプロジェクトのタスク情報をToDoリスト形式にて登録・表示するための画面例である。
【0027】
図7は、既に登録されているタスク情報181のデータを基に図6に示すToDo形式の画面の初期値を表示するためのフローチャート図である。
【0028】
ToDoリスト登録画面は、例えば、図6に示すようなものである。プロジェクトメンバ4の操作としては、ToDoリスト登録画面に従って、まず対象とするリソース(タスクの担当者)をメニュー112bより選択する。続いて、選択したリソースに関連するデータが、図7に示した処理フローに従ってスプレッドシート111cに表示される。ここで、ToDoリスト登録画面表示の処理フローについて図7を用いて説明する。
【0029】
タスク情報181のリソースフィールドがメニュー112bにて選択したリソース名称と一致するタスク情報を1件づつ読み込む(ステップ1、2)。読み込んだタスク情報のWPフラグがTrueの場合は、タスク名称にWBS Noの上位レベルのタスク名称を付加する(ステップ3、4)。次に、タスク情報を画面に表示する(ステップ5)。このタスクがクリティカルパスに該当する場合は、太字あるいは文字をカラーリングすることで強調表示する(ステップ6)。最後に、タスクの最遅開始日から最早開始日と当該タスク実行期間中の他のタスク実行工数を減算することで余裕期間を算出し、その結果を画面とタスク情報へ出力する(ステップ7、8)。これをレコード数繰り返す(ステップ9)。以上によりタスク情報181は、WBS登録画面111aからもToDoリスト登録画面112aからも登録できる単一の情報となる。
【0030】
次に、図5に示したタスク情報181を基に図6の余裕期間算出するまでの過程について図8を用いて説明する。
【0031】
図8は、ステップ7の余裕期間算出過程についてPERT図を用いて説明した図である。AからFまでの英字がタスクのイベントを表し、矢印がタスクを表す。また、最早開始日とは、タスクが一番早く実行できる日を、最遅開始日とは、プロジェクトの終了日に影響しないで開始できる最も遅い日を意味する。例えば、BとCの間にあるタスク(ドキュメント化)の最早開始日は、2/11で、最遅開始日は、2/12であることを意味する。また、このタスクの余裕期間は、1日であることを意味する。
【0032】
以上の処理結果のもと、図6のXに示す内容が画面に表示される。余裕期間を見ることで、緊急のタスクを識別することができる。また、操作者は、さらにスプレッドシート112cに追記したいデータを入力することができる。図6のYは、新規にタスクを追加した例である。このタスクは、WBS Noが1.2のタスクと実施期間が半日分(0.5日)重複する。このため、余裕期間のzの値は、1から0.5に変更される。これにより、他のタスクとの干渉を考慮したタスクの余裕期間を把握することができる。
【0033】
次に、タスク情報181のデータを基に図4に示すWBS形式の画面の初期値を表示するための方法について図15を用いて説明する。
【0034】
タスク情報181のプロジェクト名称フィールドがメニュー111bにて選択したプロジェクト名称と一致するタスク情報を1件づつ読み込む(ステップ1、2)。読み込んだタスク情報のWPフラグがFalseの場合は、WBS Noとタスク名称を除いたフィールドの値を空(”−”)に設定する(ステップ3、4)。続いて、読み込んだ情報を画面に表示する(ステップ5)。これをタスク情報181に登録されているレコード件数繰り返す(ステップ6)。
【0035】
なお、ここまで説明した図15と図7に示した2種類のフローチャートは、タスク切替表示手段113のアルゴリズムである。
【0036】
以下、本発明におけるタスク登録手段11を利用した事例であるプロジェクトのタスク委託サービスについて図9から図12を用いて説明する。
【0037】
図9は、プロジェクトのタスク委託サービスを実施する上で、あらかじめ登録するプロジェクト情報と請負企業情報を説明する図である。
【0038】
図10は、プロジェクト情報を登録する画面の表示例である。
【0039】
図11は、プロジェクトのタスク委託サービスの取引手順を説明する図である。
【0040】
図12は、プロジェクトのタスク委託サービスにおける発注予定タスク情報を説明する図である。
【0041】
図9の182にプロジェクト情報を、183に請負企業情報を示す。プロジェクト情報182には、企業ID、企業名、住所、担当者、パスワード、電話番号、メールアドレス、口座番号、プロジェクトID、プロジェクト名称、プロジェクト内容などの項目がある。
【0042】
プロジェクト情報登録画面は、例えば図10に示すようなものである。プロジェクトリーダの操作としては、まずプロジェクト情報登録画面182aに従って各項目を入力する。情報を入力後、登録ボタン押下すると、入力情報がプロジェクト情報182として登録される。そして、このプロジェクト情報の登録をもってシステム利用会員となり、会員ID(プロジェクトID)やパスワードなどの入会登録結果182bが入力したメールアドレスに通知される。なお、通知手段は、メールのほか手紙やFAXなどでもよい。
【0043】
請負企業情報の登録処理も同様である。データベース18に登録する請負企業情報を図3の請負企業情報183に示す。請負企業情報183は、企業ID、企業名、住所、担当者、パスワード、電話番号、メールアドレス、口座番号、企業概要、所有スキルなどの項目を含む。
【0044】
続いて、プロジェクトマネジャ3、請負企業4、プロジェクト管理システムのサーバ1との間で行われるタスクの委託サービスの流れについて図11を用いて説明する。
【0045】
図11において、まずプロジェクトマネジャ3が、プロジェクト情報登録画面で取得したプロジェクトIDとパスワードを基にプロジェクト管理システムのサーバ1にログインする(1)。プロジェクト管理システムのサーバ1では、プロジェクトIDとパスワードを基にプロジェクト情報182を参照し、合否を決定する認証処理を行い(2)、認証結果をプロジェクトマネジャ3に通知する(3)。ここで、プロジェクトIDやパスワードに誤りがあれば、認証不合格となり、プロジェクトマネジャ3は、次の手続き処理を行うことができない。認証結果が合格の場合、プロジェクトマネジャ3は、発注予定タスク登録作業を実施する(4)。ここでの主な発注予定タスク情報の登録項目について図12を用いて説明する。発注予定タスク情報184は、注文ID、注文ステータス、プロジェクト名称、WBS No、タスク名称、タスク内容、納期、予算、必要スキル、入札期限、入札条件などの項目からなる。注文IDは、他の注文と区別するための値で、プロジェクト管理システムのサーバ1に自動発行される。注文ステータスは、注文の状態を表すもので、見積もり回答待ち、委託先選択待ち、納品待ち、検収待ち、契約完了などの状態の内、現在の状態を表す。落札条件は、入札した請負企業の中から選定するための条件で、安値優先、請期優先、スキル優先、マニュアルなどがある。
【0046】
発注予定タスク登録が完了するとプロジェクト管理システムのサーバ1は、請負企業5に入札条件を通知する(5)。なお、通知する内容は、発注予定タスク情報184の注文ID、プロジェクト名称、WBS No、タスク名称、タスク内容、納期、必要スキル、入札期限である。入札したい請負企業5は、あらかじめ取得した企業IDとパスワードを基に、プロジェクト管理システムのサーバ1にログインする(6)。プロジェクト管理システムのサーバ1では、企業IDとパスワードを基に請負企業情報183を参照し、合否を決定する認証処理を行い(7)、認証結果を請負企業5に通知する(8)。企業IDやパスワードに誤りがあれば、認証不合格となり、請負企業5は、次の手続き処理を行うことができない。
認証結果が合格の場合、請負企業5は、入札情報登録をする(9)。ここで、入札情報を、図13に示す。入札情報185は、入札ID、請負企業5の企業ID、注文ID、納品可能な請期、見積もり金額、入札日の項目であるが、請負企業5の登録内容としては、注文IDに対する請期と見積もり金額の項目を入力する。
【0047】
プロジェクト管理システムのサーバ1は、入札日が入札期限日以前の場合、入札情報185に登録する(10)。この際、プロジェクト管理システムのサーバ1は、請負企業5のログインIDとシステムの日付を基に、入札ID、請負企業5の企業ID、入札日を追記する。
【0048】
プロジェクト管理システムのサーバ1は、発注予定タスク情報184の委託タスクの落札条件を参照し、マニュアルと設定されていた場合、入札情報185をプロジェクトマネジャ3に通知する(11)。プロジェクトマネジャ3は、入札情報より希望する請負企業5を1つ選択(落札)する(12)。また、落札条件が、安値優先、請期優先などが設定されている場合は、プロジェクト管理システムのサーバ1が、条件を満たす請負企業5を選定する(12a)。
【0049】
プロジェクト管理システムのサーバ1は、落札結果を請負企業5とプロジェクトマネジャ3に通知する(13)。落札できなかった請負企業5は、ここでサービスを終える。落札できた請負企業5は、委託されたタスクを実施し(14)、その成果を納品する(15)。プロジェクト管理システムのサーバ1は、プロジェクトマネジャ3に検収依頼を通知し(16)、プロジェクトマネジャ3は、検収結果を返す(17)。最後に、プロジェクト管理システムのサーバ1は、契約完了の旨をプロジェクトマネジャ3と請負企業5に通知する。
【0050】
最後に、本発明のプロジェクト管理システムのビジネスフローの一例を説明する。
【0051】
図14は、本発明のプロジェクト管理システムのビジネスフローの一例を説明する図である。
【0052】
プロジェクトマネジャ3と請負企業5は、プロジェクト管理システムのサーバ1に会員登録する。なお、会員登録完了をもって、守秘契約成立とする。
【0053】
サービスの内容としては、プロジェクト管理システムのサーバ1は、請負企業5に対して委託タスクの情報提供や発注(委託)サービスを提供する。また、プロジェクトマネジャ3に対しては、見積もり回答や、進捗状況の情報を提供する。
【0054】
タスクの委託契約が確定した後の納品物の流れは、請負企業5からプロジェクト管理システムのサーバ1を経由してプロジェクトマネジャ3に納品される。これに伴い、代金がプロジェクトマネジャ3よりプロジェクト管理システムのサーバ1に支払われ、プロジェクト管理システムのサーバ1より請負企業5へ委託料金が支払われる。また、プロジェクト管理システムのサーバ1は、プロジェクトマネジャ3から、手数料を課金する。手数料の金額は、例えば、予算よりも安く委託できた場合の差額または、その一部である。なお、これらの入出金処理は、図1における課金手段13にて実現する。
【0055】
【発明の効果】
本発明によれば、プロジェクト計画をWBS形式とToDo形式の2種類の方法にて登録することにより、余裕期間を考慮した精度の良いプロジェクト計画を作成することができる。また、アウトソーシング手段12によりクリティカルパスなどの余裕の無いプロジェクトのタスク、高いスキルを要するタスク、リソース不足のタスクなどを戦略的に請負企業に委託することを狙ったプロジェクト計画を立案することができる。
【図面の簡単な説明】
【図1】本発明の一実施形態のシステム構成を示すブロック図である。
【図2】本発明の一実施形態のハードウェア構成を示す図である。
【図3】タスク情報を説明する図である。
【図4】タスク情報登録画面の表示例である。
【図5】タスク情報のデータ登録例である。
【図6】ToDoリスト登録画面の表示例である。
【図7】ToDoリスト登録画面表示フローチャート図である。
【図8】余裕期間算出過程についてPERT図を用いて説明した図である。
【図9】プロジェクト情報と請負企業情報を説明する図である。
【図10】プロジェクト情報登録画面の表示例である
【図11】プロジェクトのタスク委託サービスの取引処理手順を説明する図である。
【図12】発注予定タスク情報を説明する図である。
【図13】入札情報を説明する図である。
【図14】プロジェクト管理システムのビジネスフローの一例を示す図である。
【図15】WBS登録画面表示フローチャート図である。
【符号の説明】
1…プロジェクト管理システムのサーバ、10…電子計算機、11…タスク情報登録手段、11…WBSタスク登録手段、111a…WBSタスク登録画面、111b…メニュー、111c…スプレッドシート、112…ToDoリスト登録手段、112a…ToDoリスト登録画面、112b…メニュー、112c…スプレッドシート、113…タスク切替表示手段、12…アウトソーシング手段、13…課金手段、18…データベース、181…タスク情報、182…プロジェクト情報、182a…プロジェクト情報登録画面、182b…プロジェクト情報登録結果、183…請負企業情報、184…発注予定タスク情報、185…入札情報、2…ネットワーク、3…プロジェクトマネジャ、30…電子計算機、4…プロジェクトメンバ、40…電子計算機、5…請負企業、50…電子計算機。
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a project management system for efficiently managing a project.
[0002]
[Prior art]
2. Description of the Related Art Conventionally, as a project management system, a system that manages a project based on a project plan and progress has been known (for example, see Patent Document 1).
[0003]
In this example, when the progress of the project is behind the plan, the work period of the subsequent work accompanying the progress delay is automatically changed.
[0004]
[Patent Document 1]
JP-A-10-240804
[Problems to be solved by the invention]
The invention described in the above-mentioned prior art is effective because the rescheduling can be performed in accordance with the progress as long as the schedule of the project plan created in advance by hand is appropriate. However, if the schedule of the project plan is extremely short, rescheduling is repeatedly performed because the progress is often delayed. As a result, there is a problem that the end time of the project cannot be known.
[0006]
The present invention has been made to solve the above problems, and has as its object to provide a project management system that supports accurate project planning.
[0007]
[Means for Solving the Problems]
In order to solve the above-mentioned problem, a project management system of the present invention is connected to a project manager system and a project member system via a network, and registers a work of a project as a task subdivided into a tree. Means, a ToDo list registration means for registering daily tasks for each worker, and a database for centrally storing the contents registered by the WBS task registration means and the ToDo list registration means as task information, This is a system that enables accurate schedule planning by integrally managing the schedule for each project and the schedule for each worker.
[0008]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, an embodiment of a project management system of the present invention will be described with reference to the drawings.
[0009]
First, the overall configuration of the project management system of the present invention will be described.
[0010]
FIG. 1 is a block diagram showing the overall configuration of an embodiment of the project management system of the present invention.
[0011]
As shown in FIG. 1, the project management system includes, in a server 1 of the project management system, a computer 3 (hereinafter simply referred to as a project manager) operated by at least one project manager and a computer 4 operated by at least one project member. (Hereinafter simply referred to as a project member) and a computer 5 (hereinafter simply referred to as a contractor) operated by at least one contractor are connected via a network 2.
[0012]
The server 1 of the project management system includes a task registration unit 11 for storing project tasks, an outsourcing unit 12 for outsourcing part or all of the registered tasks to the contracting company 4, and a charging unit for charging a service fee for outsourcing. 13 and a database 18 for storing execution results of the task registration unit 11, the outsourcing unit 12, and the billing unit 13. The project manager 3 and the project members 4 can operate the task registration means 11 via the network 2. The task registration means 11 includes a WBS task registration means 111 for registering a work of a project as a WBS (Work Breakdown Structure), a ToDo list registration means 112 for registering daily work contents, and a task for switching a task display format. And switching display means.
[0013]
Further, the project manager 3 and the contracting company 4 can operate the outsourcing means 12 via the network 2.
[0014]
Next, the hardware configuration of the project management system will be described.
[0015]
FIG. 2 shows a hardware configuration in an embodiment of the project management system.
[0016]
The project management system includes a computer 10 having the functions of the server 1 of the project management system, a computer 30 used by the project manager, a computer 40 used by the project members, and a computer 50 used by the contractor. It consists of. Here, the computer is provided with input / output devices such as a monitor, a storage device, a keyboard, and a LAN card. The computer 30, the computer 40, and the computer 50 can use the project management function mounted on the computer 10 via the network 2. The network 2 is not limited to a wired communication cable, but may be wireless.
[0017]
Hereinafter, the WBS task registering means 111 and the ToDo list registering means 112 of the task registering means 11 which support the preparation of a highly accurate project plan will be described.
[0018]
First, the WBS task registration means 111 for registering the tasks obtained by subdividing the work of the project into the database 18 will be described with reference to FIGS.
[0019]
FIG. 3 is a diagram for explaining contents for registering task information of a project in the database 18.
[0020]
FIG. 4 is an example of a screen for registering and displaying task information of a project in WBS format.
[0021]
FIG. 5 is an example of registration of task information of a project.
[0022]
The specification of the task information is shown at 181 in FIG. The task information 181 includes a project name, a WBS No, a WP flag, a task name, a scheduled start date, a deadline, man-hours, required skills, resources (person in charge of the task), a preceding WBS No, a start record, an end record, an achievement rate, There are items such as slack periods. The uniqueness of data is expressed by the project name and the WBS No.
[0023]
The WBS registration screen is, for example, as shown in FIG. As the operation of the project manager 3 or the project member 4, first, a target project is selected from the menu 111b according to the WBS registration screen 111a. When the data related to the selected project is stored in the task information 181 of FIG. 3, the content is displayed on the spreadsheet 111c. The operator inputs data to an item to be added to the spreadsheet 111c.
[0024]
FIG. 5 is a diagram showing the contents registered in the task information 181 by pressing the registration button after inputting the information as shown in FIG. Here, the WP (Work Package) flag indicates whether or not the registered task is a refined terminal task. In the case of True, the terminal task is set. In the case of False, the upper-level task is set. means.
In addition, information such as a scheduled start date, a deadline, man-hours, required skills, resources, and the like is registered only for tasks whose WP flag is True.
[0025]
Next, the ToDo list registration means 112 for the project member 3 to register the daily ToDo list in the database 18 will be described with reference to FIGS.
[0026]
FIG. 6 is an example of a screen for registering and displaying task information of a project in a ToDo list format for each resource (person in charge of a task).
[0027]
FIG. 7 is a flowchart for displaying the initial values of the screen in the ToDo format shown in FIG. 6 based on the data of the task information 181 already registered.
[0028]
The ToDo list registration screen is, for example, as shown in FIG. As an operation of the project member 4, first, a target resource (person in charge of a task) is selected from the menu 112b according to the ToDo list registration screen. Subsequently, data related to the selected resource is displayed on the spreadsheet 111c according to the processing flow shown in FIG. Here, the processing flow of displaying the ToDo list registration screen will be described with reference to FIG.
[0029]
The task information whose resource field in the task information 181 matches the resource name selected in the menu 112b is read one by one (steps 1 and 2). If the WP flag of the read task information is True, the task name of the upper level of the WBS No is added to the task name (steps 3 and 4). Next, the task information is displayed on the screen (step 5). If this task corresponds to a critical path, it is highlighted by coloring bold letters or characters (step 6). Finally, a margin is calculated by subtracting the earliest start date from the latest start date of the task and other task execution steps during the task execution period, and outputs the result to the screen and task information (step 7, 8). This is repeated for the number of records (step 9). As described above, the task information 181 is a single piece of information that can be registered from both the WBS registration screen 111a and the ToDo list registration screen 112a.
[0030]
Next, a description will be given of a process up to the calculation of the allowance period in FIG. 6 based on the task information 181 shown in FIG. 5 with reference to FIG.
[0031]
FIG. 8 is a diagram illustrating the margin calculation process in step 7 using a PERT diagram. Letters from A to F represent task events, and arrows represent tasks. The earliest start date means the day when the task can be executed earliest, and the latest start date means the latest day that can be started without affecting the end date of the project. For example, the earliest start date of a task (documentation) between B and C is 2/11, and the latest start date is 2/12. Also, the spare time of this task means one day.
[0032]
Based on the above processing results, the content indicated by X in FIG. 6 is displayed on the screen. By looking at the slack, urgent tasks can be identified. Further, the operator can further input data to be added to the spreadsheet 112c. Y in FIG. 6 is an example in which a new task is added. This task overlaps with the task whose WBS No. is 1.2 for a half day (0.5 days). Therefore, the value of z in the margin period is changed from 1 to 0.5. As a result, it is possible to grasp the margin of the task in consideration of interference with other tasks.
[0033]
Next, a method for displaying the initial values of the screen in the WBS format shown in FIG. 4 based on the data of the task information 181 will be described with reference to FIG.
[0034]
The task information in which the project name field of the task information 181 matches the project name selected in the menu 111b is read one by one (steps 1 and 2). If the WP flag of the read task information is False, the value of the field excluding the WBS No and the task name is set to empty ("-") (steps 3 and 4). Subsequently, the read information is displayed on the screen (step 5). This is repeated for the number of records registered in the task information 181 (step 6).
[0035]
Note that the two types of flowcharts described so far and shown in FIGS. 15 and 7 are algorithms of the task switching display unit 113.
[0036]
Hereinafter, a task entrustment service for a project, which is an example of using the task registration unit 11 in the present invention, will be described with reference to FIGS.
[0037]
FIG. 9 is a diagram for explaining project information and contractor information registered in advance when implementing a task entrustment service for a project.
[0038]
FIG. 10 is a display example of a screen for registering project information.
[0039]
FIG. 11 is a diagram for explaining a transaction procedure of the task entrustment service of the project.
[0040]
FIG. 12 is a diagram for explaining scheduled order task information in the task consignment service of the project.
[0041]
In FIG. 9, 182 shows project information, and 183 shows contracted company information. The project information 182 includes items such as company ID, company name, address, person in charge, password, telephone number, e-mail address, account number, project ID, project name, and project contents.
[0042]
The project information registration screen is, for example, as shown in FIG. As an operation of the project leader, first, each item is input according to the project information registration screen 182a. When the registration button is pressed after inputting the information, the input information is registered as project information 182. Then, by registering this project information, the user becomes a system user and is notified to the e-mail address to which the enrollment registration result 182b such as a member ID (project ID) and a password is input. The notification means may be a letter, a facsimile or the like in addition to the mail.
[0043]
The same applies to the registration processing of the contracted company information. The contracted company information registered in the database 18 is shown as contracted company information 183 in FIG. The contracted company information 183 includes items such as a company ID, a company name, an address, a person in charge, a password, a telephone number, an e-mail address, an account number, a company profile, and a possession skill.
[0044]
Next, the flow of a task consignment service performed between the project manager 3, the contractor 4, and the server 1 of the project management system will be described with reference to FIG.
[0045]
In FIG. 11, first, the project manager 3 logs in to the server 1 of the project management system based on the project ID and the password acquired on the project information registration screen (1). The server 1 of the project management system refers to the project information 182 on the basis of the project ID and the password, performs an authentication process for deciding whether to pass or fail (2), and notifies the project manager 3 of the authentication result (3). Here, if there is an error in the project ID or the password, the authentication fails, and the project manager 3 cannot perform the next procedure. If the authentication result is successful, the project manager 3 performs the task of registering the scheduled task (4). Here, the registration items of the main task information to be ordered will be described with reference to FIG. The scheduled task information 184 includes items such as order ID, order status, project name, WBS No, task name, task content, delivery date, budget, required skills, bid deadline, and bid conditions. The order ID is a value for distinguishing it from other orders, and is automatically issued to the server 1 of the project management system. The order status indicates the status of the order, and indicates the current status among the statuses such as waiting for an estimate response, waiting for selection of a contractor, waiting for delivery, waiting for acceptance, and completing a contract. The successful bid condition is a condition for selecting from the contracting companies that have bid, and includes a low price priority, a contract period priority, a skill priority, and a manual.
[0046]
When the registration of the scheduled task is completed, the server 1 of the project management system notifies the contracting company 5 of the bidding condition (5). The contents to be notified are the order ID, the project name, the WBS No, the task name, the task contents, the delivery date, the required skills, and the bid deadline of the scheduled task information 184. The contracting company 5 who wants to bid logs in to the server 1 of the project management system based on the company ID and password obtained in advance (6). The server 1 of the project management system refers to the contracted company information 183 based on the company ID and the password, performs an authentication process for deciding whether or not to pass / fail (7), and notifies the contracted company 5 of the authentication result (8). If there is an error in the company ID or the password, the authentication fails, and the contracting company 5 cannot perform the next procedure.
If the authentication result passes, the contracting company 5 registers the bid information (9). Here, the bid information is shown in FIG. The bid information 185 includes items of a bid ID, a company ID of the contracting company 5, an order ID, a contractable delivery period, an estimated amount, and a bid date. Enter the item of the estimated amount.
[0047]
If the bidding date is before the bidding deadline, the server 1 of the project management system registers the bidding information in the bidding information 185 (10). At this time, the server 1 of the project management system additionally writes the bid ID, the company ID of the contracting company 5, and the bidding date based on the login ID of the contracting company 5 and the date of the system.
[0048]
The server 1 of the project management system refers to the successful bid condition of the entrusted task in the scheduled order task information 184, and notifies the project manager 3 of the bidding information 185 if it is set to manual (11). The project manager 3 selects (contracts) one desired contracting company 5 from the bid information (12). Further, when the successful bid condition is set to the low price priority, the contract date priority, or the like, the server 1 of the project management system selects a contract company 5 that satisfies the condition (12a).
[0049]
The server 1 of the project management system notifies the contract company 5 and the project manager 3 of the successful bid result (13). The contracting company 5 that failed to make a successful bid ends the service here. The contracted company 5 that has won the bid carries out the task entrusted (14) and delivers the result (15). The server 1 of the project management system notifies the project manager 3 of the acceptance request (16), and the project manager 3 returns the acceptance result (17). Finally, the server 1 of the project management system notifies the project manager 3 and the contracting company 5 that the contract has been completed.
[0050]
Finally, an example of a business flow of the project management system of the present invention will be described.
[0051]
FIG. 14 is a diagram illustrating an example of a business flow of the project management system of the present invention.
[0052]
The project manager 3 and the contract company 5 register as members in the server 1 of the project management system. The confidentiality agreement will be concluded upon completion of member registration.
[0053]
As the contents of the service, the server 1 of the project management system provides the contracting company 5 with information provision of commissioned tasks and ordering (consignment) service. In addition, the project manager 3 is provided with an estimate response and information on the progress.
[0054]
After the task outsourcing contract is confirmed, the flow of the delivered goods is delivered from the contracting company 5 to the project manager 3 via the server 1 of the project management system. Along with this, the price is paid from the project manager 3 to the server 1 of the project management system, and the commission fee is paid from the server 1 of the project management system to the contracting company 5. The server 1 of the project management system charges a fee from the project manager 3. The amount of the commission is, for example, a difference or a part of the difference when the commission can be outsourced lower than the budget. These depositing and withdrawing processes are realized by the charging unit 13 in FIG.
[0055]
【The invention's effect】
According to the present invention, by registering a project plan in two types, that is, a WBS format and a ToDo format, it is possible to create an accurate project plan in consideration of a margin period. In addition, the outsourcing means 12 can draft a project plan aiming at strategically outsourcing a task of a project with no margin such as a critical path, a task requiring high skills, a task with insufficient resources, etc. to a contractor.
[Brief description of the drawings]
FIG. 1 is a block diagram illustrating a system configuration according to an embodiment of the present invention.
FIG. 2 is a diagram showing a hardware configuration of an embodiment of the present invention.
FIG. 3 is a diagram illustrating task information.
FIG. 4 is a display example of a task information registration screen.
FIG. 5 is an example of data registration of task information.
FIG. 6 is a display example of a ToDo list registration screen.
FIG. 7 is a flowchart showing a ToDo list registration screen display.
FIG. 8 is a diagram illustrating a margin calculation process using a PERT diagram.
FIG. 9 is a diagram illustrating project information and contracted company information.
FIG. 10 is a display example of a project information registration screen. FIG. 11 is a diagram illustrating a transaction processing procedure of a task entrustment service of a project.
FIG. 12 is a diagram illustrating order scheduled task information.
FIG. 13 is a diagram illustrating bid information.
FIG. 14 is a diagram illustrating an example of a business flow of the project management system.
FIG. 15 is a WBS registration screen display flowchart.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Server of a project management system, 10 ... Computer, 11 ... Task information registration means, 11 ... WBS task registration means, 111a ... WBS task registration screen, 111b ... Menu, 111c ... Spreadsheet, 112 ... ToDo list registration means, 112a ToDo list registration screen, 112b menu, 112c spreadsheet, 113 task switching display means, 12 outsourcing means, 13 billing means, 18 database, 181 task information, 182 project information, 182a project Information registration screen, 182b Project information registration result, 183 Contracting company information, 184 Task information to be ordered, 185 Bid information, 2 Network, 3 Project manager, 30 Computer, 4 Project member 40 ... computer, 5 ... contractors, 50 ... computer.

Claims (6)

ネットワークを介して少なくとも一つのプロジェクトマネジャのシステムおよび少なくとも一つのプロジェクトメンバのシステムと接続され、
プロジェクトの運営管理をするプロジェクト管理システムであって、
前記プロジェクト管理システムは、
プロジェクトの作業をツリー状に細分化したタスクとして登録するWBSタスク登録手段と、
作業者別に日々のタスクを登録するToDoリスト登録手段と、
前記WBSタスク登録手段とToDoリスト登録手段で登録した内容をタスク情報として一元管理記憶するデータベースとで構成することを特徴とするプロジェクト管理システム。
Connected to at least one project manager system and at least one project member system via a network;
A project management system that manages projects
The project management system,
WBS task registration means for registering the work of the project as a task subdivided in a tree shape,
ToDo list registration means for registering daily tasks for each worker,
A project management system comprising: a database for centrally storing the contents registered by the WBS task registration means and the ToDo list registration means as task information;
前記データベースの前記タスク情報を基にして、WBSタスク表示とTo Doリスト表示の切り替え表示を行うタスク切替表示手段を備えたことを特徴とする請求項1に記載のプロジェクト管理システム。2. The project management system according to claim 1, further comprising: a task switching display unit configured to perform a switching display between a WBS task display and a To Do list display based on the task information in the database. 3. タスクの余裕期間を、同じリソースで異なるタスクが同時期に重なった場合に、前記タスクのクリティカルパスから算出した余裕期間から重複期間の工数を減算することで算出する余裕期間算出方法。A method for calculating a slack period of a task by subtracting a man-hour of an overlap period from a slack period calculated from a critical path of the task when different tasks of the same resource overlap at the same time. 前記WBSタスク登録手段および前記ToDoリスト登録手段でのタスク登録時に、
請求項3に記載の余裕期間算出方法で算出した余裕期間を表示することを特徴とする請求項1と請求項2に記載のプロジェクト管理システム。
At the time of task registration in the WBS task registration means and the ToDo list registration means,
The project management system according to claim 1 or 2, wherein the margin period calculated by the margin period calculation method according to claim 3 is displayed.
ネットワークを介して少なくとも一つのプロジェクトマネジャのシステムおよび少なくとも一つの請負企業のシステムと接続され、
プロジェクトの運営管理をするプロジェクト管理システムであって、
前記プロジェクト管理システムは、
少なくてもWBSタスク登録手段またはToDoリスト登録手段の一方を含んで構成するタスク登録手段と、
前記タスク登録手段で登録したタスクを前記請負企業に委託するアウトソーシング手段と、
前記委託に伴う費用を課金する課金手段と、
前記タスク登録手段とアウトソーシング手段と課金手段の実行結果を記憶するデータベースを有することを特徴とするプロジェクト管理システム。
Connected to at least one project manager system and at least one contractor system via a network;
A project management system that manages projects
The project management system,
A task registration unit including at least one of a WBS task registration unit and a ToDo list registration unit;
Outsourcing means to outsource the task registered by the task registration means to the contractor,
A billing means for billing the cost associated with the consignment,
A project management system comprising a database for storing execution results of the task registration unit, the outsourcing unit, and the billing unit.
前記課金手段は、プロジェクトマネジャが登録したプロジェクトのタスク委託予算よりも、請負企業の見積もり金額が安い場合、その差額、または、差額にあらかじめ設定した率の積の金額を前記プロジェクトマネジャより課金する請求項5に記載のプロジェクト管理システム。When the estimated amount of the contracting company is lower than the task commission budget of the project registered by the project manager, the charging means requests the project manager to charge the difference or the product of the product of the rate set in advance to the difference. Item 6. The project management system according to Item 5.
JP2003158790A 2003-06-04 2003-06-04 Project management system Expired - Fee Related JP4228786B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003158790A JP4228786B2 (en) 2003-06-04 2003-06-04 Project management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003158790A JP4228786B2 (en) 2003-06-04 2003-06-04 Project management system

Publications (2)

Publication Number Publication Date
JP2004362187A true JP2004362187A (en) 2004-12-24
JP4228786B2 JP4228786B2 (en) 2009-02-25

Family

ID=34052027

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003158790A Expired - Fee Related JP4228786B2 (en) 2003-06-04 2003-06-04 Project management system

Country Status (1)

Country Link
JP (1) JP4228786B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007316999A (en) * 2006-05-26 2007-12-06 Sharp Corp Email answering order decision system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007316999A (en) * 2006-05-26 2007-12-06 Sharp Corp Email answering order decision system

Also Published As

Publication number Publication date
JP4228786B2 (en) 2009-02-25

Similar Documents

Publication Publication Date Title
US7921405B2 (en) Facilitation of multi-project management using throughput measurement
JP5025850B2 (en) Cross application timesheet
US8271314B2 (en) System and method of real-time homebuilding scheduling
US20060212323A1 (en) Production management system
US20230032331A1 (en) Systems and methods for converting sales opportunities to service tickets, sales orders, and projects
US20100257012A1 (en) Lead management system
RU2642378C2 (en) Automated system for making purchases and sales using interactive cloud system
US20130054294A1 (en) Sales productivity system
JP2006277362A (en) Lunch order system, method, and program
US20100205225A1 (en) Method and Apparatus for Transforming a Process
US20150046355A1 (en) Integrated temporary labor provisioning and monitoring
US20140278644A1 (en) System and method for controlling the elements of parts and labor costs in a facilities management computing environment
US8386292B2 (en) System and method for triggering a process on an enterprise system
WO2017024344A1 (en) System and method for managing product installation and/or service delivery
JP4228786B2 (en) Project management system
US20130282530A1 (en) System and Method for Choosing a Contractor
EP2811434A1 (en) Mobile terminal management server, and mobile terminal management program
EP2811436A1 (en) Mobile terminal management server, and mobile terminal management program
JPH10187859A (en) Business processing method, system and device, and storage medium storing business processing program
JP7115798B1 (en) Delivery business consignment service server and delivery business management system
JP2014013481A (en) Credit card settlement device, credit card settlement method and program
JP2007058253A (en) Method of supporting estimation in system development, system for supporting estimation in system development, and program therefor
JP2009288886A (en) Notification program and notification system
JP2023114988A (en) Order reception/placement management device and order reception/placement management system
JP2023003788A (en) Business management device and business management program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060207

RD01 Notification of change of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7421

Effective date: 20060420

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080814

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080819

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081020

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20081111

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20081124

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111212

Year of fee payment: 3

LAPS Cancellation because of no payment of annual fees