JP2004362187A - Project management system - Google Patents
Project management system Download PDFInfo
- Publication number
- JP2004362187A JP2004362187A JP2003158790A JP2003158790A JP2004362187A JP 2004362187 A JP2004362187 A JP 2004362187A JP 2003158790 A JP2003158790 A JP 2003158790A JP 2003158790 A JP2003158790 A JP 2003158790A JP 2004362187 A JP2004362187 A JP 2004362187A
- Authority
- JP
- Japan
- Prior art keywords
- task
- project
- management system
- project management
- information
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
【0001】
【発明の属する技術分野】
本発明はプロジェクトを効率良く運営するためのプロジェクト管理システムに関する。
【0002】
【従来の技術】
従来、プロジェクト管理システムとして、プロジェクト計画と進捗を基にプロジェクト管理するシステムが知られている(例えば、特許文献1参照)。
【0003】
この例では、プロジェクトの進捗が計画より遅れた場合に、その進捗遅れに伴う後続作業の作業期間を自動変更するものである。
【0004】
【特許文献1】
特開平10−240804号公報
【0005】
【発明が解決しようとする課題】
上記従来の技術で挙げた文献に記載された発明は、あらかじめ人手で作成するプロジェクト計画の日程が妥当な期間であれば、進捗に合わせ再スケジーリングできる為、有効である。しかし、プロジェクト計画の日程が、極端に短かった場合、進捗遅れが多発するため、再スケジューリングが繰り返し実施される。その結果、プロジェクトの終了時期がわからなくなる問題が発生する。
【0006】
本発明は、上記問題を解決するためになされたもので、精度の良いプロジェクト計画立案支援するプロジェクト管理システムを提供することを目的とする。
【0007】
【課題を解決するための手段】
上記課題を解決するために、本発明のプロジェクト管理システムは、ネットワークを介してプロジェクトマネジャのシステムとプロジェクトメンバのシステムと接続され、プロジェクトの作業をツリー状に細分化したタスクとして登録するWBSタスク登録手段と、作業者別に日々のタスクを登録するToDoリスト登録手段と、前記WBSタスク登録手段とToDoリスト登録手段で登録した内容をタスク情報として一元管理記憶するデータベースとを備えるようにしたもので、プロジェクト毎のスケジュールと作業者毎のスケジュールとを統合管理することで精度の良いスケジュール立案を可能としたシステムである。
【0008】
【発明の実施の形態】
以下、本発明のプロジェクト管理システムの一実施形態について図面を用いて説明する。
【0009】
まず、本発明のプロジェクト管理システムの全体構成を説明する。
【0010】
図1は、本発明のプロジェクト管理システムにおける一実施形態の全体構成を示すブロック図である。
【0011】
図1に示すように、プロジェクト管理システムは、プロジェクト管理システムのサーバ1に、少なくとも一つのプロジェクトマネジャが操作するコンピュータ3(以下、単にプロジェクトマネジャと称す)と少なくとも一つのプロジェクトメンバが操作するコンピュータ4(以下、単にプロジェクトメンバと称す)と少なくとも一つの請負企業が操作するコンピュータ5(以下、単に請負企業と称す)がネットワーク2を介して接続されて構成される。
【0012】
プロジェクト管理システムのサーバ1は、プロジェクトのタスクを記憶するタスク登録手段11と、タスク登録した登録の一部あるいは全部を請負企業4に委託するアウトソーシング手段12と、アウトソーシングによるサービス料を課金する課金手段13と、タスク登録手段11、アウトソーシング手段12、課金手段13の実行結果を記憶するデータベース18を有している。プロジェクトマネジャ3とプロジェクトメンバ4は、ネットワーク2を介して、タスク登録手段11を操作することができる。なお、タスク登録手段11は、プロジェクトの作業を細分化したWBS(Work Breakdown Structure)として登録するWBSタスク登録手段111と日毎の作業内容を登録するToDoリスト登録手段112とタスクの表示形式を切り替えるタスク切替表示手段とで構成される。
【0013】
また、プロジェクトマネジャ3と請負企業4は、ネットワーク2を介して、アウトソーシング手段12を操作することができる。
【0014】
次に、プロジェクト管理システムのハードウェア構成について説明する。
【0015】
図2は、プロジェクト管理システムの一実施形態におけるハードウェア構成を示したものである。
【0016】
プロジェクト管理システムは、プロジェクト管理システムのサーバ1の機能が搭載された電子計算機10と、プロジェクトマネジャが利用する電子計算機30と、プロジェクトメンバが利用する電子計算機40と、請負起業が利用する電子計算機50で構成される。ここで電子計算機は、モニタ、記憶装置、キーボード、LANカードなどの入出力装置が具備されている。また、電子計算機30、電子計算機40、電子計算機50は、ネットワーク2を介して電子計算機10に搭載されたプロジェクト管理機能を利用することができる。なお、ネットワーク2は、有線の通信ケーブルに限らず無線でもよい。
【0017】
以下、精度の良いプロジェクト計画の立案支援するタスク登録手段11のWBSタスク登録手段111とToDoリスト登録手段112を説明する。
【0018】
はじめに、プロジェクトの作業を細分化したタスクをデータベース18に登録するWBSタスク登録手段111について図3から図5を用いて説明する。
【0019】
図3は、プロジェクトのタスク情報をデータベース18に登録するための内容を説明する図である。
【0020】
図4は、プロジェクトのタスク情報をWBS形式にて登録・表示するための画面例である。
【0021】
図5は、プロジェクトのタスク情報の登録例である。
【0022】
図3の181にタスク情報の仕様を示す。タスク情報181には、プロジェクト名称、WBS No、WPフラグ、タスク名称、開始予定日、期限、工数、必要スキル、リソース(タスクの担当者)、先行WBS No、開始実績、終了実績、達成率、余裕期間などの項目がある。なお、プロジェクト名称とWBS Noとで、データの一意性を表現する。
【0023】
WBS登録画面は、例えば図4に示すようなものである。プロジェクトマネジャ3もしくはプロジェクトメンバ4の操作としては、WBS登録画面111aに従って、まず対象とするプロジェクトをメニュー111bより選択する。選択したプロジェクトに関連するデータが図3のタスク情報181に格納されている場合は、その内容がスプレッドシート111cに表示される。操作者は、スプレッドシート111cの追記したい項目にデータを入力する。
【0024】
図5は、図4に示したような情報を入力後、登録ボタン押下するとで、タスク情報181に登録される内容を表した図である。ここでWP(Work Package)フラグとは、登録されたタスクが詳細化された末端のタスクか否かを表すもので、Trueの場合は末端のタスクを、Falseの場合は、上位レベルのタスクを意味する。
また、WPフラグがTrueのタスクのみに、開始予定日、期限、工数、必要スキル、リソースなどの情報を登録する。
【0025】
次に、プロジェクトメンバ3が日毎のToDoリストをデータベース18に登録するToDoリスト登録手段112について図6と図7を用いて説明する。
【0026】
図6は、リソース(タスクの担当者)毎にプロジェクトのタスク情報をToDoリスト形式にて登録・表示するための画面例である。
【0027】
図7は、既に登録されているタスク情報181のデータを基に図6に示すToDo形式の画面の初期値を表示するためのフローチャート図である。
【0028】
ToDoリスト登録画面は、例えば、図6に示すようなものである。プロジェクトメンバ4の操作としては、ToDoリスト登録画面に従って、まず対象とするリソース(タスクの担当者)をメニュー112bより選択する。続いて、選択したリソースに関連するデータが、図7に示した処理フローに従ってスプレッドシート111cに表示される。ここで、ToDoリスト登録画面表示の処理フローについて図7を用いて説明する。
【0029】
タスク情報181のリソースフィールドがメニュー112bにて選択したリソース名称と一致するタスク情報を1件づつ読み込む(ステップ1、2)。読み込んだタスク情報のWPフラグがTrueの場合は、タスク名称にWBS Noの上位レベルのタスク名称を付加する(ステップ3、4)。次に、タスク情報を画面に表示する(ステップ5)。このタスクがクリティカルパスに該当する場合は、太字あるいは文字をカラーリングすることで強調表示する(ステップ6)。最後に、タスクの最遅開始日から最早開始日と当該タスク実行期間中の他のタスク実行工数を減算することで余裕期間を算出し、その結果を画面とタスク情報へ出力する(ステップ7、8)。これをレコード数繰り返す(ステップ9)。以上によりタスク情報181は、WBS登録画面111aからもToDoリスト登録画面112aからも登録できる単一の情報となる。
【0030】
次に、図5に示したタスク情報181を基に図6の余裕期間算出するまでの過程について図8を用いて説明する。
【0031】
図8は、ステップ7の余裕期間算出過程についてPERT図を用いて説明した図である。AからFまでの英字がタスクのイベントを表し、矢印がタスクを表す。また、最早開始日とは、タスクが一番早く実行できる日を、最遅開始日とは、プロジェクトの終了日に影響しないで開始できる最も遅い日を意味する。例えば、BとCの間にあるタスク(ドキュメント化)の最早開始日は、2/11で、最遅開始日は、2/12であることを意味する。また、このタスクの余裕期間は、1日であることを意味する。
【0032】
以上の処理結果のもと、図6のXに示す内容が画面に表示される。余裕期間を見ることで、緊急のタスクを識別することができる。また、操作者は、さらにスプレッドシート112cに追記したいデータを入力することができる。図6のYは、新規にタスクを追加した例である。このタスクは、WBS Noが1.2のタスクと実施期間が半日分(0.5日)重複する。このため、余裕期間のzの値は、1から0.5に変更される。これにより、他のタスクとの干渉を考慮したタスクの余裕期間を把握することができる。
【0033】
次に、タスク情報181のデータを基に図4に示すWBS形式の画面の初期値を表示するための方法について図15を用いて説明する。
【0034】
タスク情報181のプロジェクト名称フィールドがメニュー111bにて選択したプロジェクト名称と一致するタスク情報を1件づつ読み込む(ステップ1、2)。読み込んだタスク情報のWPフラグがFalseの場合は、WBS Noとタスク名称を除いたフィールドの値を空(”−”)に設定する(ステップ3、4)。続いて、読み込んだ情報を画面に表示する(ステップ5)。これをタスク情報181に登録されているレコード件数繰り返す(ステップ6)。
【0035】
なお、ここまで説明した図15と図7に示した2種類のフローチャートは、タスク切替表示手段113のアルゴリズムである。
【0036】
以下、本発明におけるタスク登録手段11を利用した事例であるプロジェクトのタスク委託サービスについて図9から図12を用いて説明する。
【0037】
図9は、プロジェクトのタスク委託サービスを実施する上で、あらかじめ登録するプロジェクト情報と請負企業情報を説明する図である。
【0038】
図10は、プロジェクト情報を登録する画面の表示例である。
【0039】
図11は、プロジェクトのタスク委託サービスの取引手順を説明する図である。
【0040】
図12は、プロジェクトのタスク委託サービスにおける発注予定タスク情報を説明する図である。
【0041】
図9の182にプロジェクト情報を、183に請負企業情報を示す。プロジェクト情報182には、企業ID、企業名、住所、担当者、パスワード、電話番号、メールアドレス、口座番号、プロジェクトID、プロジェクト名称、プロジェクト内容などの項目がある。
【0042】
プロジェクト情報登録画面は、例えば図10に示すようなものである。プロジェクトリーダの操作としては、まずプロジェクト情報登録画面182aに従って各項目を入力する。情報を入力後、登録ボタン押下すると、入力情報がプロジェクト情報182として登録される。そして、このプロジェクト情報の登録をもってシステム利用会員となり、会員ID(プロジェクトID)やパスワードなどの入会登録結果182bが入力したメールアドレスに通知される。なお、通知手段は、メールのほか手紙やFAXなどでもよい。
【0043】
請負企業情報の登録処理も同様である。データベース18に登録する請負企業情報を図3の請負企業情報183に示す。請負企業情報183は、企業ID、企業名、住所、担当者、パスワード、電話番号、メールアドレス、口座番号、企業概要、所有スキルなどの項目を含む。
【0044】
続いて、プロジェクトマネジャ3、請負企業4、プロジェクト管理システムのサーバ1との間で行われるタスクの委託サービスの流れについて図11を用いて説明する。
【0045】
図11において、まずプロジェクトマネジャ3が、プロジェクト情報登録画面で取得したプロジェクトIDとパスワードを基にプロジェクト管理システムのサーバ1にログインする(1)。プロジェクト管理システムのサーバ1では、プロジェクトIDとパスワードを基にプロジェクト情報182を参照し、合否を決定する認証処理を行い(2)、認証結果をプロジェクトマネジャ3に通知する(3)。ここで、プロジェクトIDやパスワードに誤りがあれば、認証不合格となり、プロジェクトマネジャ3は、次の手続き処理を行うことができない。認証結果が合格の場合、プロジェクトマネジャ3は、発注予定タスク登録作業を実施する(4)。ここでの主な発注予定タスク情報の登録項目について図12を用いて説明する。発注予定タスク情報184は、注文ID、注文ステータス、プロジェクト名称、WBS No、タスク名称、タスク内容、納期、予算、必要スキル、入札期限、入札条件などの項目からなる。注文IDは、他の注文と区別するための値で、プロジェクト管理システムのサーバ1に自動発行される。注文ステータスは、注文の状態を表すもので、見積もり回答待ち、委託先選択待ち、納品待ち、検収待ち、契約完了などの状態の内、現在の状態を表す。落札条件は、入札した請負企業の中から選定するための条件で、安値優先、請期優先、スキル優先、マニュアルなどがある。
【0046】
発注予定タスク登録が完了するとプロジェクト管理システムのサーバ1は、請負企業5に入札条件を通知する(5)。なお、通知する内容は、発注予定タスク情報184の注文ID、プロジェクト名称、WBS No、タスク名称、タスク内容、納期、必要スキル、入札期限である。入札したい請負企業5は、あらかじめ取得した企業IDとパスワードを基に、プロジェクト管理システムのサーバ1にログインする(6)。プロジェクト管理システムのサーバ1では、企業IDとパスワードを基に請負企業情報183を参照し、合否を決定する認証処理を行い(7)、認証結果を請負企業5に通知する(8)。企業IDやパスワードに誤りがあれば、認証不合格となり、請負企業5は、次の手続き処理を行うことができない。
認証結果が合格の場合、請負企業5は、入札情報登録をする(9)。ここで、入札情報を、図13に示す。入札情報185は、入札ID、請負企業5の企業ID、注文ID、納品可能な請期、見積もり金額、入札日の項目であるが、請負企業5の登録内容としては、注文IDに対する請期と見積もり金額の項目を入力する。
【0047】
プロジェクト管理システムのサーバ1は、入札日が入札期限日以前の場合、入札情報185に登録する(10)。この際、プロジェクト管理システムのサーバ1は、請負企業5のログインIDとシステムの日付を基に、入札ID、請負企業5の企業ID、入札日を追記する。
【0048】
プロジェクト管理システムのサーバ1は、発注予定タスク情報184の委託タスクの落札条件を参照し、マニュアルと設定されていた場合、入札情報185をプロジェクトマネジャ3に通知する(11)。プロジェクトマネジャ3は、入札情報より希望する請負企業5を1つ選択(落札)する(12)。また、落札条件が、安値優先、請期優先などが設定されている場合は、プロジェクト管理システムのサーバ1が、条件を満たす請負企業5を選定する(12a)。
【0049】
プロジェクト管理システムのサーバ1は、落札結果を請負企業5とプロジェクトマネジャ3に通知する(13)。落札できなかった請負企業5は、ここでサービスを終える。落札できた請負企業5は、委託されたタスクを実施し(14)、その成果を納品する(15)。プロジェクト管理システムのサーバ1は、プロジェクトマネジャ3に検収依頼を通知し(16)、プロジェクトマネジャ3は、検収結果を返す(17)。最後に、プロジェクト管理システムのサーバ1は、契約完了の旨をプロジェクトマネジャ3と請負企業5に通知する。
【0050】
最後に、本発明のプロジェクト管理システムのビジネスフローの一例を説明する。
【0051】
図14は、本発明のプロジェクト管理システムのビジネスフローの一例を説明する図である。
【0052】
プロジェクトマネジャ3と請負企業5は、プロジェクト管理システムのサーバ1に会員登録する。なお、会員登録完了をもって、守秘契約成立とする。
【0053】
サービスの内容としては、プロジェクト管理システムのサーバ1は、請負企業5に対して委託タスクの情報提供や発注(委託)サービスを提供する。また、プロジェクトマネジャ3に対しては、見積もり回答や、進捗状況の情報を提供する。
【0054】
タスクの委託契約が確定した後の納品物の流れは、請負企業5からプロジェクト管理システムのサーバ1を経由してプロジェクトマネジャ3に納品される。これに伴い、代金がプロジェクトマネジャ3よりプロジェクト管理システムのサーバ1に支払われ、プロジェクト管理システムのサーバ1より請負企業5へ委託料金が支払われる。また、プロジェクト管理システムのサーバ1は、プロジェクトマネジャ3から、手数料を課金する。手数料の金額は、例えば、予算よりも安く委託できた場合の差額または、その一部である。なお、これらの入出金処理は、図1における課金手段13にて実現する。
【0055】
【発明の効果】
本発明によれば、プロジェクト計画をWBS形式とToDo形式の2種類の方法にて登録することにより、余裕期間を考慮した精度の良いプロジェクト計画を作成することができる。また、アウトソーシング手段12によりクリティカルパスなどの余裕の無いプロジェクトのタスク、高いスキルを要するタスク、リソース不足のタスクなどを戦略的に請負企業に委託することを狙ったプロジェクト計画を立案することができる。
【図面の簡単な説明】
【図1】本発明の一実施形態のシステム構成を示すブロック図である。
【図2】本発明の一実施形態のハードウェア構成を示す図である。
【図3】タスク情報を説明する図である。
【図4】タスク情報登録画面の表示例である。
【図5】タスク情報のデータ登録例である。
【図6】ToDoリスト登録画面の表示例である。
【図7】ToDoリスト登録画面表示フローチャート図である。
【図8】余裕期間算出過程についてPERT図を用いて説明した図である。
【図9】プロジェクト情報と請負企業情報を説明する図である。
【図10】プロジェクト情報登録画面の表示例である
【図11】プロジェクトのタスク委託サービスの取引処理手順を説明する図である。
【図12】発注予定タスク情報を説明する図である。
【図13】入札情報を説明する図である。
【図14】プロジェクト管理システムのビジネスフローの一例を示す図である。
【図15】WBS登録画面表示フローチャート図である。
【符号の説明】
1…プロジェクト管理システムのサーバ、10…電子計算機、11…タスク情報登録手段、11…WBSタスク登録手段、111a…WBSタスク登録画面、111b…メニュー、111c…スプレッドシート、112…ToDoリスト登録手段、112a…ToDoリスト登録画面、112b…メニュー、112c…スプレッドシート、113…タスク切替表示手段、12…アウトソーシング手段、13…課金手段、18…データベース、181…タスク情報、182…プロジェクト情報、182a…プロジェクト情報登録画面、182b…プロジェクト情報登録結果、183…請負企業情報、184…発注予定タスク情報、185…入札情報、2…ネットワーク、3…プロジェクトマネジャ、30…電子計算機、4…プロジェクトメンバ、40…電子計算機、5…請負企業、50…電子計算機。[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a project management system for efficiently managing a project.
[0002]
[Prior art]
2. Description of the Related Art Conventionally, as a project management system, a system that manages a project based on a project plan and progress has been known (for example, see Patent Document 1).
[0003]
In this example, when the progress of the project is behind the plan, the work period of the subsequent work accompanying the progress delay is automatically changed.
[0004]
[Patent Document 1]
JP-A-10-240804
[Problems to be solved by the invention]
The invention described in the above-mentioned prior art is effective because the rescheduling can be performed in accordance with the progress as long as the schedule of the project plan created in advance by hand is appropriate. However, if the schedule of the project plan is extremely short, rescheduling is repeatedly performed because the progress is often delayed. As a result, there is a problem that the end time of the project cannot be known.
[0006]
The present invention has been made to solve the above problems, and has as its object to provide a project management system that supports accurate project planning.
[0007]
[Means for Solving the Problems]
In order to solve the above-mentioned problem, a project management system of the present invention is connected to a project manager system and a project member system via a network, and registers a work of a project as a task subdivided into a tree. Means, a ToDo list registration means for registering daily tasks for each worker, and a database for centrally storing the contents registered by the WBS task registration means and the ToDo list registration means as task information, This is a system that enables accurate schedule planning by integrally managing the schedule for each project and the schedule for each worker.
[0008]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, an embodiment of a project management system of the present invention will be described with reference to the drawings.
[0009]
First, the overall configuration of the project management system of the present invention will be described.
[0010]
FIG. 1 is a block diagram showing the overall configuration of an embodiment of the project management system of the present invention.
[0011]
As shown in FIG. 1, the project management system includes, in a
[0012]
The
[0013]
Further, the
[0014]
Next, the hardware configuration of the project management system will be described.
[0015]
FIG. 2 shows a hardware configuration in an embodiment of the project management system.
[0016]
The project management system includes a
[0017]
Hereinafter, the WBS task registering means 111 and the ToDo list registering means 112 of the task registering means 11 which support the preparation of a highly accurate project plan will be described.
[0018]
First, the WBS task registration means 111 for registering the tasks obtained by subdividing the work of the project into the
[0019]
FIG. 3 is a diagram for explaining contents for registering task information of a project in the
[0020]
FIG. 4 is an example of a screen for registering and displaying task information of a project in WBS format.
[0021]
FIG. 5 is an example of registration of task information of a project.
[0022]
The specification of the task information is shown at 181 in FIG. The task information 181 includes a project name, a WBS No, a WP flag, a task name, a scheduled start date, a deadline, man-hours, required skills, resources (person in charge of the task), a preceding WBS No, a start record, an end record, an achievement rate, There are items such as slack periods. The uniqueness of data is expressed by the project name and the WBS No.
[0023]
The WBS registration screen is, for example, as shown in FIG. As the operation of the
[0024]
FIG. 5 is a diagram showing the contents registered in the task information 181 by pressing the registration button after inputting the information as shown in FIG. Here, the WP (Work Package) flag indicates whether or not the registered task is a refined terminal task. In the case of True, the terminal task is set. In the case of False, the upper-level task is set. means.
In addition, information such as a scheduled start date, a deadline, man-hours, required skills, resources, and the like is registered only for tasks whose WP flag is True.
[0025]
Next, the ToDo list registration means 112 for the
[0026]
FIG. 6 is an example of a screen for registering and displaying task information of a project in a ToDo list format for each resource (person in charge of a task).
[0027]
FIG. 7 is a flowchart for displaying the initial values of the screen in the ToDo format shown in FIG. 6 based on the data of the task information 181 already registered.
[0028]
The ToDo list registration screen is, for example, as shown in FIG. As an operation of the
[0029]
The task information whose resource field in the task information 181 matches the resource name selected in the
[0030]
Next, a description will be given of a process up to the calculation of the allowance period in FIG. 6 based on the task information 181 shown in FIG. 5 with reference to FIG.
[0031]
FIG. 8 is a diagram illustrating the margin calculation process in
[0032]
Based on the above processing results, the content indicated by X in FIG. 6 is displayed on the screen. By looking at the slack, urgent tasks can be identified. Further, the operator can further input data to be added to the
[0033]
Next, a method for displaying the initial values of the screen in the WBS format shown in FIG. 4 based on the data of the task information 181 will be described with reference to FIG.
[0034]
The task information in which the project name field of the task information 181 matches the project name selected in the
[0035]
Note that the two types of flowcharts described so far and shown in FIGS. 15 and 7 are algorithms of the task switching
[0036]
Hereinafter, a task entrustment service for a project, which is an example of using the
[0037]
FIG. 9 is a diagram for explaining project information and contractor information registered in advance when implementing a task entrustment service for a project.
[0038]
FIG. 10 is a display example of a screen for registering project information.
[0039]
FIG. 11 is a diagram for explaining a transaction procedure of the task entrustment service of the project.
[0040]
FIG. 12 is a diagram for explaining scheduled order task information in the task consignment service of the project.
[0041]
In FIG. 9, 182 shows project information, and 183 shows contracted company information. The project information 182 includes items such as company ID, company name, address, person in charge, password, telephone number, e-mail address, account number, project ID, project name, and project contents.
[0042]
The project information registration screen is, for example, as shown in FIG. As an operation of the project leader, first, each item is input according to the project
[0043]
The same applies to the registration processing of the contracted company information. The contracted company information registered in the
[0044]
Next, the flow of a task consignment service performed between the
[0045]
In FIG. 11, first, the
[0046]
When the registration of the scheduled task is completed, the
If the authentication result passes, the contracting
[0047]
If the bidding date is before the bidding deadline, the
[0048]
The
[0049]
The
[0050]
Finally, an example of a business flow of the project management system of the present invention will be described.
[0051]
FIG. 14 is a diagram illustrating an example of a business flow of the project management system of the present invention.
[0052]
The
[0053]
As the contents of the service, the
[0054]
After the task outsourcing contract is confirmed, the flow of the delivered goods is delivered from the contracting
[0055]
【The invention's effect】
According to the present invention, by registering a project plan in two types, that is, a WBS format and a ToDo format, it is possible to create an accurate project plan in consideration of a margin period. In addition, the outsourcing means 12 can draft a project plan aiming at strategically outsourcing a task of a project with no margin such as a critical path, a task requiring high skills, a task with insufficient resources, etc. to a contractor.
[Brief description of the drawings]
FIG. 1 is a block diagram illustrating a system configuration according to an embodiment of the present invention.
FIG. 2 is a diagram showing a hardware configuration of an embodiment of the present invention.
FIG. 3 is a diagram illustrating task information.
FIG. 4 is a display example of a task information registration screen.
FIG. 5 is an example of data registration of task information.
FIG. 6 is a display example of a ToDo list registration screen.
FIG. 7 is a flowchart showing a ToDo list registration screen display.
FIG. 8 is a diagram illustrating a margin calculation process using a PERT diagram.
FIG. 9 is a diagram illustrating project information and contracted company information.
FIG. 10 is a display example of a project information registration screen. FIG. 11 is a diagram illustrating a transaction processing procedure of a task entrustment service of a project.
FIG. 12 is a diagram illustrating order scheduled task information.
FIG. 13 is a diagram illustrating bid information.
FIG. 14 is a diagram illustrating an example of a business flow of the project management system.
FIG. 15 is a WBS registration screen display flowchart.
[Explanation of symbols]
DESCRIPTION OF
Claims (6)
プロジェクトの運営管理をするプロジェクト管理システムであって、
前記プロジェクト管理システムは、
プロジェクトの作業をツリー状に細分化したタスクとして登録するWBSタスク登録手段と、
作業者別に日々のタスクを登録するToDoリスト登録手段と、
前記WBSタスク登録手段とToDoリスト登録手段で登録した内容をタスク情報として一元管理記憶するデータベースとで構成することを特徴とするプロジェクト管理システム。Connected to at least one project manager system and at least one project member system via a network;
A project management system that manages projects
The project management system,
WBS task registration means for registering the work of the project as a task subdivided in a tree shape,
ToDo list registration means for registering daily tasks for each worker,
A project management system comprising: a database for centrally storing the contents registered by the WBS task registration means and the ToDo list registration means as task information;
請求項3に記載の余裕期間算出方法で算出した余裕期間を表示することを特徴とする請求項1と請求項2に記載のプロジェクト管理システム。At the time of task registration in the WBS task registration means and the ToDo list registration means,
The project management system according to claim 1 or 2, wherein the margin period calculated by the margin period calculation method according to claim 3 is displayed.
プロジェクトの運営管理をするプロジェクト管理システムであって、
前記プロジェクト管理システムは、
少なくてもWBSタスク登録手段またはToDoリスト登録手段の一方を含んで構成するタスク登録手段と、
前記タスク登録手段で登録したタスクを前記請負企業に委託するアウトソーシング手段と、
前記委託に伴う費用を課金する課金手段と、
前記タスク登録手段とアウトソーシング手段と課金手段の実行結果を記憶するデータベースを有することを特徴とするプロジェクト管理システム。Connected to at least one project manager system and at least one contractor system via a network;
A project management system that manages projects
The project management system,
A task registration unit including at least one of a WBS task registration unit and a ToDo list registration unit;
Outsourcing means to outsource the task registered by the task registration means to the contractor,
A billing means for billing the cost associated with the consignment,
A project management system comprising a database for storing execution results of the task registration unit, the outsourcing unit, and the billing unit.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003158790A JP4228786B2 (en) | 2003-06-04 | 2003-06-04 | Project management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003158790A JP4228786B2 (en) | 2003-06-04 | 2003-06-04 | Project management system |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004362187A true JP2004362187A (en) | 2004-12-24 |
JP4228786B2 JP4228786B2 (en) | 2009-02-25 |
Family
ID=34052027
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003158790A Expired - Fee Related JP4228786B2 (en) | 2003-06-04 | 2003-06-04 | Project management system |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4228786B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007316999A (en) * | 2006-05-26 | 2007-12-06 | Sharp Corp | Email answering order decision system |
-
2003
- 2003-06-04 JP JP2003158790A patent/JP4228786B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007316999A (en) * | 2006-05-26 | 2007-12-06 | Sharp Corp | Email answering order decision system |
Also Published As
Publication number | Publication date |
---|---|
JP4228786B2 (en) | 2009-02-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7921405B2 (en) | Facilitation of multi-project management using throughput measurement | |
JP5025850B2 (en) | Cross application timesheet | |
US8271314B2 (en) | System and method of real-time homebuilding scheduling | |
US20060212323A1 (en) | Production management system | |
US20230032331A1 (en) | Systems and methods for converting sales opportunities to service tickets, sales orders, and projects | |
US20100257012A1 (en) | Lead management system | |
RU2642378C2 (en) | Automated system for making purchases and sales using interactive cloud system | |
US20130054294A1 (en) | Sales productivity system | |
JP2006277362A (en) | Lunch order system, method, and program | |
US20100205225A1 (en) | Method and Apparatus for Transforming a Process | |
US20150046355A1 (en) | Integrated temporary labor provisioning and monitoring | |
US20140278644A1 (en) | System and method for controlling the elements of parts and labor costs in a facilities management computing environment | |
US8386292B2 (en) | System and method for triggering a process on an enterprise system | |
WO2017024344A1 (en) | System and method for managing product installation and/or service delivery | |
JP4228786B2 (en) | Project management system | |
US20130282530A1 (en) | System and Method for Choosing a Contractor | |
EP2811434A1 (en) | Mobile terminal management server, and mobile terminal management program | |
EP2811436A1 (en) | Mobile terminal management server, and mobile terminal management program | |
JPH10187859A (en) | Business processing method, system and device, and storage medium storing business processing program | |
JP7115798B1 (en) | Delivery business consignment service server and delivery business management system | |
JP2014013481A (en) | Credit card settlement device, credit card settlement method and program | |
JP2007058253A (en) | Method of supporting estimation in system development, system for supporting estimation in system development, and program therefor | |
JP2009288886A (en) | Notification program and notification system | |
JP2023114988A (en) | Order reception/placement management device and order reception/placement management system | |
JP2023003788A (en) | Business management device and business management program |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060207 |
|
RD01 | Notification of change of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7421 Effective date: 20060420 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080814 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080819 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20081020 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20081111 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20081124 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111212 Year of fee payment: 3 |
|
LAPS | Cancellation because of no payment of annual fees |