JP2004308220A - Retaining wall construction method - Google Patents
Retaining wall construction method Download PDFInfo
- Publication number
- JP2004308220A JP2004308220A JP2003102323A JP2003102323A JP2004308220A JP 2004308220 A JP2004308220 A JP 2004308220A JP 2003102323 A JP2003102323 A JP 2003102323A JP 2003102323 A JP2003102323 A JP 2003102323A JP 2004308220 A JP2004308220 A JP 2004308220A
- Authority
- JP
- Japan
- Prior art keywords
- retaining wall
- horizontal
- gauge
- upright
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Retaining Walls (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、コンクリート製擁壁の施工法に関する。
【0002】
【従来の技術】
従来のコンクリート擁壁の施工法として、コンクリート製基礎の施工に際して予め縦筋を埋め込んでおき、このコンクリート基礎の上に突出した縦筋に横筋を針金による結束などの手段で接続して縦横の鉄筋を構成し、この鉄筋を型枠工事、すなわち木板などのパネルで囲み、各パネルをセパレートボルトで連結固定した後、パネル内にコンクリートを打設し、コンクリートが固化した後、パネルを除去して擁壁を形成する方法が採用されている。
【0003】
【発明が解決しようとする課題】
しかしながら、上記従来の施工法は、擁壁を形成するに当たって、パネルの取付及び除去などの型枠工事に著しく手数がかかり、また、雨天はコンクリートを打設することができないなどの工期が遅延する欠点があり、それ故に施工コストが高くなる欠点がある。しかも、パネルを除去した後の擁壁の地肌に凹凸が生じることがあるため、その手直しにさらに手数とコストが必要であった。
【0004】
そこで、本発明者は、上記の課題を解決するために鋭意研究を重ね、一定の規格を定め、その規格に応じてブロック単位の擁壁を工場で製造し、かつ、擁壁を形成する場所において規格に併せた支柱を設置し、該支柱に擁壁ブロックを積み上げることにより、擁壁を形成するという擁壁施工法を発明した。
【0005】
【課題を解決するための手段】
本発明に係る擁壁施工法は、コンクリート製の基礎に固定される水平部と擁壁を支持する起立部とからなる鉄骨製の支柱と、支柱の起立部に填める複数の貫通穴を備えた直方体状のコンクリート製擁壁ブロックと、隣接する支柱の水平部間の距離を一定にするための水平部用ゲージと、隣接する支柱の起立部間の距離を一定にするための起立部用ゲージと、支柱の起立部を垂直に立設するための垂直測定具とを使用し、以下の手順によりコンクリート製の基礎に擁壁を立設することを特徴とするものである。
【0006】
1.基礎形成前に、各支柱の水平部が水平部用ゲージにより一定の距離をおいて、また各支柱の起立部が起立部用ゲージにより一定の距離をおいて、さらに各支柱の起立部が垂直測定具により垂直となるように、さらにまた擁壁ブロックの貫通穴に各支柱の起立部が合致するように支柱を設置する。
【0007】
2.各支柱の水平部が埋没するようにコンクリートを打設して基礎を形成する。
【0008】
3.基礎により各支柱が固定された時点で、各支柱の起立部に擁壁ブロックの貫通穴を填め、擁壁ブロックを積み上げて擁壁を形成する。
【0009】
4.擁壁ブロックの貫通穴にコンクリートを注入して擁壁ブロックと支柱の起立部とを固着する。
【0010】
上記の施工法によれば、基礎に支柱が水平部用ゲージ及び起立部用ゲージにより一定間隔をおいて、かつ、垂直測定具により起立部が垂直となるように固定されると共に、垂直に立設された起立部に擁壁ブロックの貫通穴が適合するので、該起立部に擁壁ブロックを填めていけば擁壁が形成される。
【0011】
また、上記の擁壁施工法において使用する水平部用ゲージとして、所定長さの水平バーと該水平バーの下面に所定間隔をおいて支柱の水平部に嵌合する嵌合部材とから構成したものを使用し、該嵌合部材を隣接する支柱の水平部に装着して架け渡すことにより、隣接する支柱の水平部が一定の間隔に配設されるようにしてもよい。
【0012】
上記の水平部用ゲージを使用すれば、隣接する支柱の水平部に嵌合部材を填め込めば、隣接する支柱の水平部が正確に一定の距離をおいて配置することができる。
【0013】
さらに、上記の擁壁施工法において使用する起立部用ゲージとして、所定長さの水平軸部と該水平軸部の両端に配した係合部とからなるゲージ本体と、支柱の起立部の頂部に着脱自在に配し、前記ゲージ本体の係合部と係合可能な係合受け部材とから構成したものを使用し、該係合受け部材を隣接する支柱の起立部にそれぞれ装着し、各支柱の係合受け部材間に前記ゲージ本体を架け渡すことにより、隣接する支柱の起立部が一定の間隔に立設されるようにしてもよい。
【0014】
上記の起立部用ゲージを使用すれば、隣接する支柱の起立部にそれぞれ係合受け部材を装着し、該係合受け部材にゲージ本体の係合部を係合させることにより係合受け部材間に前記ゲージ本体を架け渡すと、隣接する支柱の起立部が正確に一定の距離をおいて配置することができる。
【0015】
さらにまた、上記の擁壁施工法において使用する垂直測定具として、各支柱の起立部に沿って垂下する下げ振り装置と、支柱の起立部が垂直に立設しているときに前記の下げ振り装置が指し示す指標部とから構成したものを使用し、該垂直測定具により、各支柱の起立部が垂直に立設していることを確認できるようにしてもよい。
【0016】
上記の垂直測定具を使用すれば、支柱の起立部が垂直に立設されているか否かを即座に判断することができる。
【0017】
【発明の実施の形態】
以下に本発明の好適な実施例を図に基いて詳細に説明する。図1は擁壁ブロックの斜視図、図2は支柱の一部省略斜視図、図3は水平部用ゲージの斜視図、図4は起立部用ゲージの斜視図、図5〜図14は施工手順を示す概略図、図15は施工状態を示す参考斜視図である。
【0018】
[本発明の擁壁施工法に使用する器具]
図1において10はコンクリート製の擁壁ブロックであり、擁壁ブロック10はその内部に鉄筋11を備え、図において縦方向に貫通穴12a、12b、12c、12dが形成されたものである。この貫通穴12a、12b、12c、12dは、擁壁ブロック10を立設するために後述する支柱の起立部に填めるものであって、等間隔に設けられており、両端部の貫通穴12a、12dは断面半円状をなし、同一形状の擁壁ブロック10を隣接させることにより断面円形となる。該擁壁ブロック10はその全体が工場などにおいて型成形などにより製造され、工事現場などに移送されて使用されるものであり、そのため量産及び備蓄が可能であり、また壁面13は平滑なフラットに仕上げることも容易であり、さらに化粧仕上げなどの装飾を施すことも可能である。
【0019】
図2において20は鉄骨製の支柱であり、水平部21と起立部22とから構成される。水平部21は後述する擁壁施工の準備として行われるコンクリート製の基礎を構築する際に、この基礎に固定される部分であり、起立部22は擁壁を支持する部分である。支柱20は、その強度を保持するために水平部21と起立部22との交差部分に支え部材23が設けられている。また、支柱20は強度保持のために断面コの字型のいわゆるCチャンネルと呼ばれる鉄骨を直角に接合又は屈曲して形成し、さらに強度を高めるために断面T字型の補強部材24が支柱20の形状に沿ってその内側に添設されている。
【0020】
図3において30は水平部用ゲージを示し、該水平部用ゲージ30は前記支柱20を複数並列して立設したときに、隣接する支柱の水平部21が平行でその間隔を一定にするためのものである。該水平部用ゲージ30は水平バー31とこの水平バー31の下面の2箇所に設けられた嵌合部材32、33とから構成される。嵌合部材32と嵌合部材33との距離は、隣接する支柱間の距離であり、この距離は擁壁ブロック10の隣接する貫通穴間の距離である。前記嵌合部材32、33はそれぞれ支柱20の水平部21の太さに合致する間隔をあけた挟持片32a、32b、33a、33bから構成され、該挟持片32a、32bにより一方の支柱20の水平部21が挟み込まれ、挟持片33a、33bにより隣接する支柱20の水平部21が挟み込まれて、水平部用ゲージ30が支柱20の水平部21に架け渡されるように装着される。
【0021】
上記水平部用ゲージ30は、これを使用すれば、隣接する支柱20の水平部21に嵌合部材32、33を填め込むだけで、隣接する支柱20の水平部21が正確に一定の距離をおいて配置することができるので、簡単でかつ極めて便利でにある。また、この水平部用ゲージ30は、これを除去せずに後述するようにコンクリートを打設して支柱20の水平部21と共に基礎を形成するようにすれば、コンクリートの打設時のみならずコンクリート固着後において支柱全体を安定させる効果がある。
【0022】
図4において40は起立部用ゲージを示し、該起立部用ゲージ40は前記支柱20を複数並列して立設したときに、隣接する支柱の起立部22が平行でその間隔を一定にするためのものである。該起立部用ゲージ40は、ゲージ本体41と係合受け部材42、43とからなる。ゲージ本体41は所定長さの水平軸部41aと該水平軸部41aの両端に配した垂下曲板状の係合部41b、41cとから構成される。係合受け部材42、43は支柱の起立部22の頂部22aに着脱自在に配されるものであり、下部を開口した有天筒状をなし、その口径は起立部22の頂部22aに填る大きさであり、その側面には前記係合部41b、41cが係合する係合受け部42a、43aが設けられている。そして、該係合受け部材42、43を隣接する支柱の起立部22の頂部22aにそれぞれ装着し、各支柱の係合受け部材42、43の係合受け部42a、43aにゲージ本体41の係合部41b、41cを係合させることにより、各支柱の係合受け部材間に前記ゲージ本体41を架け渡すことができる。これにより、隣接する支柱の起立部22が一定の間隔に立設されるようになる。この起立部用ゲージ40は前記の水平部用ゲージ30と関連するものであり、前者は支柱の起立部22が平行でその間隔を一定にし、後者は支柱の水平部21を平行でその間隔を一定にするものであるから、水平部用ゲージ30により設定される支柱間の距離と起立部用ゲージ40により設定される支柱間の距離とは同一となり、また、起立部用ゲージ40及び水平部用ゲージ30は、そのように関連して設計される。
【0023】
上記の起立部用ゲージ40を使用すれば、隣接する支柱の起立部が正確に一定の距離をおいて配置することができるので、簡単でかつ極めて便利である。また、起立部用ゲージ40は支柱の起立部22に対して着脱自在であるから、起立部用ゲージ40を除去することができるので、後述するように擁壁用ブロック10を支柱の起立部22に填める際に邪魔にならない利点がある。
【0024】
上記したように、水平部用ゲージ30及び起立部用ゲージ40は、支柱20を平行に一定の間隔をおいて立設するためものであり、この支柱の20の起立部22は擁壁ブロック10の貫通穴に填めて擁壁ブロック10を垂直に立設するものであるから、擁壁ブロック10、支柱の20、水平部用ゲージ30及び起立部用ゲージ40は一定の規格に基づいて全て構成されるものであり、擁壁ブロック10の大きさが変化すれば、規格が変化し、その規格に基づいて支柱の20、水平部用ゲージ30及び起立部用ゲージ40の設計が変化する。例えば、擁壁ブロック10の大きさが大きくかつ厚くなれば、支柱20については、その太さを太く、長さを長く設計し、また、擁壁ブロック10については貫通穴の口径を大きく、間隔を変更し、個数を増加し、水平部用ゲージ30及び起立部用ゲージ40も擁壁ブロック10の貫通穴の間隔及び支柱20の太さに合わせて設計変更する。
【0025】
また、図4に示す50は垂直測定具であって、支柱20の起立部22を垂直に立設するためのものである。該垂直測定具50は、下げ振り装置51と指標部54とからなり、下げ振り装置51は係合受け部材43の側面に設けた下げ振り支持部材52と該下げ振り支持部材52から垂下する下げ振り53とから構成され、該下げ振り支持部材52は端部に垂直方向の垂直溝52bを形成した水平ピン52aから構成され、下げ振り53は下げ振り紐53aと下げ振り体53bとから構成される。そして、該水平ピン52aに下げ振り紐53aを巻き付け、垂直溝52bを通して下げ振り体53bを支柱の起立部22に沿って下方に垂下させる。指標部54は支柱の起立部22の図において前面側に垂直線をもって表示されており、指標部54に対して、水平ピン52aから下げ振り体53bまでの間の下げ振り紐53aが同一平面上において平行になっているときは、支柱の起立部22が垂直に立設していることが確認できる。また、指標部54に対して、水平ピン52aから下げ振り体53bまでの間の下げ振り紐53aがねじれの位置関係にあるときは、支柱の起立部22が垂直に立設していないことを示し、支柱の起立部22を傾動させて支柱の起立部22が垂直に立設するように修正する。
【0026】
上記の垂直測定具50を使用すれば、支柱の起立部22が垂直に立設されているか否かを即座に判断することができ、支柱の起立部22が垂直に立設されてない場合には、この垂直測定具50を確認しながら修正することができるので、簡単でかつ極めて便利である。
【0027】
[施工法の手順]
図5は、擁壁を構築する前の準備段階を表しており、地盤上に、コンクリートによる舗装Aがなされ、その舗装上の所定箇所にコンクリート製の敷き台Bが配設されている。この敷き台B上に図6に示すように2本の支柱20a、20bが立設される。この2本の支柱20a、20bの立設に当たり、まず、水平部21a、21bに2個の水平部用ゲージ30a、30bを填めて水平部21a、21bが平行で一定間隔になるように調整する。その状態において、起立部22a、22bの頂部に起立部用ゲージ40を填めて起立部22a、22bが平行で一定間隔になるように調整する。その際、起立部22a、22bの一方又は双方が垂直になるように垂直測定具50によって調整する。このようにして2本の支柱20a、20bが平行でかつ一定の間隔を維持し、起立部22a、22bが垂直になるように立設する。
【0028】
次に、図7に示すように、3番目の支柱20cを敷き台上に配置し、2番目の支柱20bの水平部21bと3番目の支柱20cの水平部21cとの間に2個の水平部用ゲージ30c、30dを填めて水平部21b、21cが平行で一定間隔になるように調整する。その状態において、1番目の支柱20aの起立部22aの頂部と2番目の支柱20bの起立部22bの頂部との間に架け渡した起立部用ゲージ40を起立部22b、22cの頂部に掛けかえ、この起立部用ゲージ40によって起立部22b、22cが平行で一定間隔になるように調整する。また、必要に応じて、起立部22b、22cの一方又は双方が垂直になるように垂直測定具50によって調整する。
【0029】
さらに、図8に示すように、4番目の支柱20dを敷き台上に配置し、3番目の支柱20cの水平部21cと4番目の支柱20dの水平部21dとの間に2個の水平部用ゲージ30e、30fを填めて水平部21c、21dが平行で一定間隔になるように調整する。その状態において、2番目の支柱20bの起立部22bの頂部と3番目の支柱20cの起立部22cの頂部との間に架け渡した起立部用ゲージ40を起立部22c、22dの頂部に掛けかえ、この起立部用ゲージ40によって起立部22c、22dが平行で一定間隔になるように調整する。また、前記と同様に、必要に応じて、起立部22b、22cの一方又は双方が垂直になるように垂直測定具50によって調整する。
【0030】
上記のような作業を繰り返して、所定本数の支柱20a、20b、20c、20d、・・を立設していく。本実施例においては、6本の支柱を立設することとし、支柱を立設した状態を図9に示す。この状態において、上記の支柱20a、20b、20c、20d、・・は、その水平部21a、21b、21c、21d、・・をそれぞれ跨ぐように填められた水平部用ゲージ30a、30b、30c、30d、30e、30f、・・により、ずれ動かないように固定される。なお、上記の支柱20a、20b、20c、20d、・・の立設において重要な点は、各支柱20a、20b、20c、20d、・・の水平部21a、21b、21c、21d、・・が水平部用ゲージ30a、30b、30c、30d、30e、30f、・・により一定の距離をおいて、また各支柱20a、20b、20c、20d、・・の起立部22a、22b、22c、22d、・・が起立部用ゲージ40により一定の距離をおいて、さらに各支柱20a、20b、20c、20d、・・の起立部22a、22b、22c、22d、・・が垂直測定具50により垂直となるように、さらにまた擁壁ブロック10の貫通穴12a、12b、12c、12d、・・に各支柱20a、20b、20c、20d、・・の起立部22a、22b、22c、22d、・・が合致するように支柱20a、20b、20c、20d、・・を設置する
次に、図10に示すように、上記の支柱20a、20b、20c、20d、・・の各水平部21a、21b、21c、21d、・・上に、水平部用ゲージ30a、30b、30c、30d、30e、30f、・・を挟んで、鉄筋を縦横に折り込んだネット状鉄筋Cを敷設する。その後、図11に示すように、前記のネット状鉄筋Cを含めて水平部21a、21b、21c、21d、・・及び水平部用ゲージ30a、30b、30c、30d、30e、30f、・・が埋没するように舗装A上にコンクリートを打設して基礎Dを形成し、支柱20a、20b、20c、20d、・・の起立部22a、22b、22c、22d、・・のみが直立して固定される状態にする。
【0031】
そして、基礎Dを形成するコンクリートが固まった時点において、図12に示すように、予め製作しておいた擁壁ブロック10を、その貫通穴12b、12c、12d、・・に前記の支柱20a、20b、20c、20d、・・の起立部22a、22b、22c、22d、・・が差し込まれるようにしてに填め込んで積み上げていくといくと、図13に示すように擁壁Eを形成する。そして、擁壁ブロック10の貫通穴12a、12b、12c、12d、・・にコンクリートを注入して擁壁ブロック10と支柱20a、20b、20c、20d、・・の起立部22a、22b、22c、22d、・・とを固着して、擁壁Eが完成する。
【0032】
上記に記載した手順による擁壁Eの施工法によれば、基礎に支柱が水平部用ゲージ及び起立部用ゲージにより一定間隔をおいて、かつ、垂直測定具により起立部が垂直となるように固定されると共に、垂直に立設された起立部に擁壁ブロックの貫通穴が適合するので、該起立部に擁壁ブロックを填めていくだけで擁壁を形成することができる。したがって、現場における擁壁形成のための型枠工事が不要となり、擁壁形成作業に手数を要しないものとなるので、工期の短縮が図れると共にコストの低減が図れる。また、擁壁ブロックは工場において製造されるため、工場において規格に適合した美麗な擁壁ブロックのみを選択して使用することができるので、現場における手直し作業が不要となる。なお、上記の実施例においては起立部用ゲージを、支柱を立設する毎に掛け替えていくようにしているが、複数の起立部用ゲージを用意して支柱の起立部頂部に掛けたままにしておき、基礎Dが形成された時点で起立部用ゲージを取り外すようにしてもよい。そのようにした場合には各支柱が水平部用ゲージと起立部用ゲージとで固定された状態で基礎Dにより支柱が固着するので、種々の影響による狂いなどが生じ難く、精度がより一層高くなる利点がある。
【0033】
[変更例]
図14は、擁壁ブロックにおける貫通穴を形成するパターンを示す斜視図であり、図14(a)は上記の実施例において採用した擁壁ブロック10であり、これは両端に断面半円形の貫通穴12a、12dを形成し、内方側に適宜間隔をおいて断面円形の貫通穴12b、12cを形成したものであり、上記実施例において説明したように支柱20を填め込む。また、図14(b)に示す擁壁ブロック110は、その両端のみに断面半円形の貫通穴112a、112bを形成し、断面半円形の貫通穴あるいは隣接する擁壁ブロックと合わせて断面円形に形成した貫通穴に支柱を填めて使用する。さらに図14(c)に示す擁壁ブロック210は、その内方のみに適宜の間隔をおいて断面円形の貫通穴212a、212bを形成したものであり、この貫通穴に支柱を填めて使用する。なお、擁壁ブロックの大きさは適宜選択可能であり、構築される擁壁の大きさ及び輸送の事情に合わせて設計すればよい。また、支柱を填める貫通穴の径及び数や間隔などは、擁壁の耐久性等を考慮して適宜設計すればよい。その場合、貫通穴の間隔が2種以上になったときには、水平部用ゲージ及び起立部用ゲージも2種以上の間隔のものを揃えておけばよい。
【0034】
図15は、起立部用ゲージの変更例であり、該起立部用ゲージ140は前記支柱20を複数並列して立設したときに、隣接する支柱の起立部22が平行でその間隔を一定にするためのものである。該起立部用ゲージ140は、ゲージ本体141と係合受け部材142、143とからなる。ゲージ本体141は所定長さの水平軸部141aと該水平軸部141aの両端に配した突起状の係合部141b、141cとから構成される。係合受け部材142、143は支柱の起立部22の頂部22aに着脱自在に配されるものであり、下部を開口した有天筒状をなし、その口径は起立部22の頂部22aに填る大きさであり、その頂部には前記係合部141b、141cが係合する凹状の係合受け部142a、143aが設けられている。そして、該係合受け部材142、143を隣接する支柱の起立部22の頂部22aにそれぞれ装着し、各支柱の係合受け部材142、143の係合受け部142a、143aにゲージ本体141の係合部141b、141cを係合させることにより、各支柱の係合受け部材間に前記ゲージ本体141を架け渡すことができる。これにより、隣接する支柱の起立部22が一定の間隔に立設されるようになる。
【0035】
なお、上記の実施例は、これに限定されるものではなく、特許請求の範囲に記載した広範囲な実施形態を包含するものである。
【0036】
【発明の効果】
本発明に係る擁壁施工法は、コンクリート製の基礎に固定される水平部と擁壁を支持する起立部とからなる鉄骨製の支柱と、支柱の起立部に填める複数の貫通穴を備えた直方体状のコンクリート製擁壁ブロックと、隣接する支柱の水平部間の距離を一定にするための水平部用ゲージと、隣接する支柱の起立部間の距離を一定にするための起立部用ゲージと、支柱の起立部を垂直に立設するための垂直測定具とを使用し、以下の手順によりコンクリート製の基礎に擁壁を立設することを特徴とするものである。
【0037】
1.基礎形成前に、各支柱の水平部が水平部用ゲージにより一定の距離をおいて、また各支柱の起立部が起立部用ゲージにより一定の距離をおいて、さらに各支柱の起立部が垂直測定具により垂直となるように、さらにまた擁壁ブロックの貫通穴に各支柱の起立部が合致するように支柱を設置する。
【0038】
2.各支柱の水平部が埋没するようにコンクリートを打設して基礎を形成する。
【0039】
3.基礎により各支柱が固定された時点で、各支柱の起立部に擁壁ブロックの貫通穴を填め、擁壁ブロックを積み上げて擁壁を形成する。
【0040】
4.擁壁ブロックの貫通穴にコンクリートを注入して擁壁ブロックと支柱の起立部とを固着する。
【0041】
上記の施工法によれば、基礎に支柱が水平部用ゲージ及び起立部用ゲージにより一定間隔をおいて、かつ、垂直測定具により起立部が垂直となるように固定されると共に、垂直に立設された起立部に擁壁ブロックの貫通穴が適合するので、該起立部に擁壁ブロックを填めていくだけで擁壁を形成することができる。したがって、現場における擁壁形成のための型枠工事が不要となり、擁壁形成作業に手数を要しないものとなるので、工期の短縮が図れると共にコストの低減が図れる。また、擁壁ブロックは工場において製造されるため、工場において規格に適合した美麗な擁壁ブロックのみを選択して使用することができるので、現場における手直し作業が不要となる。
【0042】
また、上記の擁壁施工法において使用する水平部用ゲージとして、所定長さの水平バーと該水平バーの下面に所定間隔をおいて支柱の水平部に嵌合する嵌合部材とから構成したものを使用し、該嵌合部材を隣接する支柱の水平部に装着して架け渡すことにより、隣接する支柱の水平部が一定の間隔に配設されるようにしてもよい。
【0043】
上記の水平部用ゲージを使用すれば、隣接する支柱の水平部に嵌合部材を填め込むだけで、隣接する支柱の水平部が正確に一定の距離をおいて配置することができるので、簡単でかつ極めて便利でにある。また、この水平部用ゲージは、これを除去せずにコンクリートを打設して支柱の水平部と共に基礎を形成するようにすれば、コンクリートの打設時のみならずコンクリート固着後において支柱全体を安定させる効果がある。
【0044】
さらに、上記の擁壁施工法において使用する起立部用ゲージとして、所定長さの水平軸部と該水平軸部の両端に配した係合部とからなるゲージ本体と、支柱の起立部の頂部に着脱自在に配し、前記ゲージ本体の係合部と係合可能な係合受け部材とから構成したものを使用し、該係合受け部材を隣接する支柱の起立部にそれぞれ装着し、各支柱の係合受け部材間に前記ゲージ本体を架け渡すことにより、隣接する支柱の起立部が一定の間隔に立設されるようにしてもよい。
【0045】
上記の起立部用ゲージを使用すれば、隣接する支柱の起立部にそれぞれ係合受け部材を装着し、該係合受け部材にゲージ本体の係合部を係合させることにより係合受け部材間に前記ゲージ本体を架け渡すと、隣接する支柱の起立部が正確に一定の距離をおいて配置することができるので、簡単でかつ極めて便利である。また、起立部用ゲージは支柱の起立部に対して着脱自在であるから、起立部用ゲージを除去することができるので、擁壁用ブロックを支柱の起立部に填める際に邪魔にならない利点がある。
【0046】
さらにまた、上記の擁壁施工法において使用する垂直測定具として、各支柱の起立部に沿って垂下する下げ振り装置と、支柱の起立部が垂直に立設しているときに前記の下げ振り装置が指し示す指標部とから構成したものを使用し、該垂直測定具により、各支柱の起立部が垂直に立設していることを確認できるようにしてもよい。
【0047】
上記の垂直測定具を使用すれば、支柱の起立部が垂直に立設されているか否かを即座に判断することができ、支柱の起立部が垂直に立設されてない場合には、この垂直測定具を確認しながら修正することができるので、簡単でかつ極めて便利である。
【図面の簡単な説明】
【図1】本発明の擁壁施工法に使用する擁壁ブロックの斜視図である。
【図2】本発明の擁壁施工法に使用する支柱の一部省略斜視図である。
【図3】本発明の擁壁施工法に使用する水平部用ゲー篠斜視図である。
【図4】本発明の擁壁施工法に使用する起立部用ゲージの一部切欠斜視図である。
【図5】擁壁を構築する前の準備段階を表す図であって、(a)は正面図、(b)は平面図、(c)は側面図である。
【図6】擁壁を構築するための第1及び第2の支柱を立設する状態を表す図であって、(a)は正面図、(b)は平面図、(c)は側面図である。
【図7】擁壁を構築するための第3の支柱を立設する状態を表す図であって、(a)は正面図、(b)は平面図、(c)はI−I線断面図である。
【図8】擁壁を構築するための第4の支柱を立設する状態を表す図であって、(a)は正面図、(b)は平面図、(c)はII−II線断面図である。
【図9】擁壁を構築するための支柱を立設した状態を表す図であって、(a)は正面図、(b)は平面図、(c)は側面図である。
【図10】擁壁を構築するための支柱の水平部上にネット状鉄筋を敷設した状態を表す図であって、(a)は正面図、(b)は平面図、(c)は側面図である。
【図11】擁壁を構築するための支柱の水平部に基礎を形成した状態を表す図であって、(a)は正面図、(b)は平面図、(c)は側面図である。
【図12】擁壁を構築する状態を示す斜視図である。
【図13】擁壁を構築した状態を表す図であって、(a)は正面図、(b)は平面図、(c)は側面図である。
【図14】擁壁ブロックに形成する貫通穴の3種類のパターン(a)、(b)、(c)を示す斜視図である。
【図15】起立部用ゲージの変更例を示す一部切欠斜視図である。
【符号の説明】
10・・・擁壁ブロック
11・・・擁壁ブロックに内在する鉄筋
12a・・擁壁ブロックの端部の貫通穴
12b・・擁壁ブロックの貫通穴
12c・・擁壁ブロックの貫通穴
12d・・擁壁ブロックの端部の貫通穴
13・・・擁壁ブロックの壁面
20・・・支柱
21・・・支柱の水平部
22・・・支柱の起立部
22a・・支柱起立部の頂部
23・・・支え部材
24・・・補強部材
30・・・水平部用ゲージ
31・・・水平バー
32・・・嵌合部材
32a・・嵌合部材32の挟持片
32b・・嵌合部材32の挟持片
33・・・嵌合部材
33a・・嵌合部材33の挟持片
33b・・嵌合部材33の挟持片
40・・・起立部用ゲージ
41・・・起立部用ゲージのゲージ本体
41a・・水平軸部
41b・・係合部
41c・・係合部
42・・・係合受け部材
42a・・係合受け部
43・・・係合受け部材
43a・・係合受け部
50・・・垂直測定具
51・・・下げ振り装置
52・・・下げ振り支持部材
52a・・水平ピン
52b・・垂直溝
53・・・下げ振り
53a・・下げ振り紐
53b・・下げ振り体
54・・・指標部
A・・・・舗装
B・・・・敷き台
C・・・・ネット状鉄筋
D・・・・基礎
E・・・・擁壁
110・・擁壁ブロック
112a・擁壁ブロックの端部の貫通穴
112b・擁壁ブロックの貫通穴
210・・擁壁ブロック
212a・擁壁ブロックの端部の貫通穴
212b・擁壁ブロックの貫通穴
140・・起立部用ゲージ
141・・起立部用ゲージのゲージ本体
141a・水平軸部
141b・係合部
141c・係合部
142・・係合受け部材
142a・係合受け部
143・・係合受け部材
143a・係合受け部[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method for constructing a concrete retaining wall.
[0002]
[Prior art]
As a conventional method for constructing concrete retaining walls, vertical bars are embedded in advance when constructing a concrete foundation, and horizontal bars are connected to the vertical bars protruding above the concrete foundation by means such as binding with wires, and vertical and horizontal reinforcing bars are used. Construct this rebar, formwork, that is, surround with a panel such as a wooden board, connect and fix each panel with separate bolts, pour concrete into the panel, remove the panel after the concrete solidifies, A method of forming a retaining wall is employed.
[0003]
[Problems to be solved by the invention]
However, the above-mentioned conventional construction method takes a lot of trouble in formwork such as installation and removal of panels when forming a retaining wall, and the construction period such as when it is impossible to cast concrete in rainy weather is delayed. It has drawbacks, and therefore has the drawback of high construction costs. In addition, irregularities may be formed on the ground of the retaining wall after the panel is removed.
[0004]
In order to solve the above-mentioned problems, the present inventor has conducted intensive studies, has set a certain standard, manufactures a retaining wall in block units at a factory according to the standard, and has a place where the retaining wall is formed. Invented a retaining wall construction method in which a supporting column was installed in accordance with the standard, and a retaining wall was formed by stacking a retaining wall block on the supporting column.
[0005]
[Means for Solving the Problems]
The retaining wall construction method according to the present invention includes a steel column including a horizontal portion fixed to a concrete foundation and an upright portion supporting the retaining wall, and a plurality of through holes that can be fitted into the upright portion of the post. Retaining wall block in the shape of a rectangular parallelepiped, a gauge for the horizontal part to keep the distance between the horizontal parts of the adjacent pillars constant, and a standing part to keep the distance between the standing parts of the adjacent pillars constant The present invention is characterized in that a retaining wall is erected on a concrete foundation by the following procedure using a gauge and a vertical measuring tool for erecting an upright portion of a column.
[0006]
1. Before the foundation is formed, the horizontal part of each pillar is kept at a fixed distance by the gauge for horizontal part, the upright part of each pillar is kept at a certain distance by the gauge for standing part, and the standing part of each pillar is vertical The columns are installed so that they are vertical by the measuring tool, and the uprights of the columns are aligned with the through holes of the retaining wall block.
[0007]
2. The foundation is formed by casting concrete so that the horizontal part of each column is buried.
[0008]
3. When each pillar is fixed by the foundation, the through hole of the retaining wall block is filled in the upright part of each pillar, and the retaining wall block is stacked to form a retaining wall.
[0009]
4. Concrete is poured into the through hole of the retaining wall block to fix the retaining wall block to the upright portion of the column.
[0010]
According to the above-mentioned construction method, the pillars are fixed to the foundation at regular intervals by the horizontal portion gauge and the upright portion gauge, and the upright portion is fixed by the vertical measuring tool so that the upright portion becomes vertical. Since the through-hole of the retaining wall block fits the provided standing portion, the retaining wall is formed by filling the standing wall block with the retaining wall block.
[0011]
Further, as the horizontal portion gauge used in the above retaining wall construction method, a horizontal bar of a predetermined length and a fitting member fitted to the horizontal portion of the column with a predetermined interval on the lower surface of the horizontal bar were configured. The horizontal parts of the adjacent columns may be arranged at a constant interval by using a member and attaching and fitting the fitting member to the horizontal parts of the adjacent columns.
[0012]
With the use of the above-described horizontal portion gauge, if the fitting member is fitted into the horizontal portion of the adjacent column, the horizontal portion of the adjacent column can be accurately arranged at a fixed distance.
[0013]
Further, as the standing portion gauge used in the above retaining wall construction method, a gauge body including a horizontal shaft portion having a predetermined length and engaging portions disposed at both ends of the horizontal shaft portion, and a top portion of the standing portion of the pillar. A detachable arrangement is used, and an engagement receiving member that can be engaged with the engagement portion of the gauge body is used, and the engagement reception member is attached to the upright portion of the adjacent column, respectively. By extending the gauge body between the engagement receiving members of the columns, the upright portions of the adjacent columns may be erected at regular intervals.
[0014]
If the above-described gauge for the upright portion is used, the engagement receiving members are attached to the upright portions of the adjacent columns, and the engagement portions of the gauge main body are engaged with the engagement receiving members. When the gauge main body is bridged over, the upright portions of the adjacent columns can be accurately arranged at a fixed distance.
[0015]
Furthermore, as a vertical measuring tool used in the above-mentioned retaining wall construction method, a down swing device that hangs down along the upright portion of each column, and the down swing device when the upright portion of the column is vertically erected. The vertical measuring device may be used to confirm that the upright portions of the respective columns are vertically erected, using an index portion indicated by the device.
[0016]
With the use of the above-described vertical measuring tool, it is possible to immediately determine whether or not the upright portion of the column is vertically erected.
[0017]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, a preferred embodiment of the present invention will be described in detail with reference to the drawings. 1 is a perspective view of a retaining wall block, FIG. 2 is a partially omitted perspective view of a support, FIG. 3 is a perspective view of a gauge for a horizontal portion, FIG. 4 is a perspective view of a gauge for an upright portion, and FIGS. FIG. 15 is a schematic perspective view showing a procedure, and FIG. 15 is a reference perspective view showing a construction state.
[0018]
[Apparatus used for the retaining wall construction method of the present invention]
In FIG. 1,
[0019]
In FIG. 2,
[0020]
In FIG. 3,
[0021]
If the
[0022]
In FIG. 4,
[0023]
The use of the above-mentioned
[0024]
As described above, the
[0025]
In addition,
[0026]
By using the above-described
[0027]
[Construction procedure]
FIG. 5 shows a preparatory stage before a retaining wall is constructed. A concrete pavement A is formed on the ground, and a concrete bed B is provided at a predetermined position on the pavement. As shown in FIG. 6, two
[0028]
Next, as shown in FIG. 7, the
[0029]
Further, as shown in FIG. 8, a
[0030]
By repeating the above operation, a predetermined number of
Next, as shown in FIG. 10, on the
[0031]
Then, when the concrete forming the foundation D is hardened, as shown in FIG. 12, the retaining
[0032]
According to the construction method of the retaining wall E according to the procedure described above, the pillars are arranged on the foundation at regular intervals by the horizontal portion gauge and the upright portion gauge, and the upright portion is made vertical by the vertical measuring tool. Since the through hole of the retaining wall block is fixed and fits upright in the upright portion, the retaining wall can be formed only by filling the upright portion with the retaining wall block. Therefore, the formwork for forming the retaining wall at the site is not required, and the labor for forming the retaining wall is not required, so that the construction period can be shortened and the cost can be reduced. In addition, since the retaining wall blocks are manufactured in the factory, only beautiful retaining wall blocks conforming to the standard can be selected and used in the factory, so that rework on site is unnecessary. In the above embodiment, the standing portion gauge is replaced every time the column is erected.However, a plurality of standing portion gauges are prepared and left standing on the column top. In this case, the upright portion gauge may be removed when the foundation D is formed. In such a case, since the columns are fixed by the foundation D in a state where each column is fixed by the horizontal portion gauge and the upright portion gauge, it is hard to cause disorder due to various influences, and the accuracy is further improved. There are advantages.
[0033]
[Example of change]
FIG. 14 is a perspective view showing a pattern for forming a through hole in the retaining wall block. FIG. 14A shows the retaining
[0034]
FIG. 15 shows a modified example of the upright portion gauge. When the upright portion gauges 140 are erected in parallel, the
[0035]
It should be noted that the above embodiments are not limited to this, but encompass a wide range of embodiments described in the claims.
[0036]
【The invention's effect】
The retaining wall construction method according to the present invention includes a steel column including a horizontal portion fixed to a concrete foundation and an upright portion supporting the retaining wall, and a plurality of through holes that can be fitted into the upright portion of the post. Retaining wall block in the shape of a rectangular parallelepiped, a gauge for the horizontal part to keep the distance between the horizontal parts of the adjacent pillars constant, and a standing part to keep the distance between the standing parts of the adjacent pillars constant The present invention is characterized in that a retaining wall is erected on a concrete foundation by the following procedure using a gauge and a vertical measuring tool for erecting an upright portion of a column.
[0037]
1. Before the foundation is formed, the horizontal part of each pillar is kept at a fixed distance by the gauge for horizontal part, the upright part of each pillar is kept at a certain distance by the gauge for standing part, and the standing part of each pillar is vertical The columns are installed so that they are vertical by the measuring tool, and the uprights of the columns are aligned with the through holes of the retaining wall block.
[0038]
2. The foundation is formed by casting concrete so that the horizontal part of each column is buried.
[0039]
3. When each pillar is fixed by the foundation, the through hole of the retaining wall block is filled in the upright part of each pillar, and the retaining wall block is stacked to form a retaining wall.
[0040]
4. Concrete is poured into the through hole of the retaining wall block to fix the retaining wall block to the upright portion of the column.
[0041]
According to the above-mentioned construction method, the pillars are fixed to the foundation at regular intervals by the horizontal portion gauge and the upright portion gauge, and the upright portion is fixed by the vertical measuring tool so that the upright portion becomes vertical. Since the through-hole of the retaining wall block fits the provided standing portion, the retaining wall can be formed only by inserting the retaining wall block into the standing portion. Therefore, the formwork for forming the retaining wall at the site is not required, and the labor for forming the retaining wall is not required, so that the construction period can be shortened and the cost can be reduced. In addition, since the retaining wall blocks are manufactured in the factory, only beautiful retaining wall blocks conforming to the standard can be selected and used in the factory, so that rework on site is unnecessary.
[0042]
Further, as the horizontal portion gauge used in the above retaining wall construction method, a horizontal bar of a predetermined length and a fitting member fitted to the horizontal portion of the column with a predetermined interval on the lower surface of the horizontal bar were configured. The horizontal parts of the adjacent columns may be arranged at a constant interval by using a member and attaching and fitting the fitting member to the horizontal parts of the adjacent columns.
[0043]
If the above-mentioned horizontal part gauge is used, the horizontal parts of the adjacent columns can be accurately arranged at a fixed distance simply by inserting the fitting members into the horizontal parts of the adjacent columns, so that it is easy to use. And very convenient. In addition, if this horizontal part gauge is used to cast concrete without removing it and form the foundation together with the horizontal part of the column, the whole column will be used not only when concrete is poured but also after concrete is fixed. Has the effect of stabilizing.
[0044]
Further, as the standing portion gauge used in the above retaining wall construction method, a gauge body including a horizontal shaft portion of a predetermined length and engaging portions disposed at both ends of the horizontal shaft portion, and a top portion of the standing portion of the column A detachable arrangement is used, and an engagement receiving member that can be engaged with the engagement portion of the gauge body is used, and the engagement reception member is attached to the upright portion of the adjacent column, respectively. By extending the gauge body between the engagement receiving members of the columns, the upright portions of the adjacent columns may be erected at regular intervals.
[0045]
If the above-described gauge for the upright portion is used, the engagement receiving members are attached to the upright portions of the adjacent columns, and the engagement portions of the gauge main body are engaged with the engagement receiving members. When the gauge main body is bridged, the upright portions of the adjacent columns can be accurately arranged at a fixed distance, which is simple and extremely convenient. In addition, since the standing portion gauge is detachable from the standing portion of the column, the standing portion gauge can be removed, so that it is not obstructed when the retaining wall block is inserted into the standing portion of the column. There is.
[0046]
Furthermore, as a vertical measuring tool used in the above-mentioned retaining wall construction method, a down swing device that hangs down along the upright portion of each column, and the down swing device when the upright portion of the column is vertically erected. The vertical measuring device may be used to confirm that the upright portions of the respective columns are vertically erected, using an index portion indicated by the device.
[0047]
By using the above vertical measuring tool, it is possible to immediately judge whether or not the upright portion of the column is standing upright, and if the upright portion of the column is not upright, Since the vertical measuring tool can be corrected while checking it, it is simple and extremely convenient.
[Brief description of the drawings]
FIG. 1 is a perspective view of a retaining wall block used in the retaining wall construction method of the present invention.
FIG. 2 is a partially omitted perspective view of a column used in the retaining wall construction method of the present invention.
FIG. 3 is a perspective view of a horizontal portion of the game used for the retaining wall construction method of the present invention.
FIG. 4 is a partially cutaway perspective view of an upright portion gauge used in the retaining wall construction method of the present invention.
5A and 5B are diagrams illustrating a preparation stage before a retaining wall is constructed, wherein FIG. 5A is a front view, FIG. 5B is a plan view, and FIG. 5C is a side view.
6A and 6B are diagrams showing a state in which first and second columns for constructing a retaining wall are erected, where FIG. 6A is a front view, FIG. 6B is a plan view, and FIG. It is.
7A and 7B are diagrams showing a state in which a third support for constructing a retaining wall is erected, wherein FIG. 7A is a front view, FIG. 7B is a plan view, and FIG. FIG.
8A and 8B are diagrams showing a state in which a fourth support for constructing a retaining wall is erected, wherein FIG. 8A is a front view, FIG. 8B is a plan view, and FIG. FIG.
9A and 9B are diagrams showing a state in which a support for constructing a retaining wall is erected, wherein FIG. 9A is a front view, FIG. 9B is a plan view, and FIG. 9C is a side view.
10A and 10B are diagrams illustrating a state in which a net-shaped reinforcing bar is laid on a horizontal portion of a pillar for constructing a retaining wall, wherein FIG. 10A is a front view, FIG. 10B is a plan view, and FIG. FIG.
11A and 11B are diagrams showing a state in which a foundation is formed on a horizontal portion of a support for constructing a retaining wall, wherein FIG. 11A is a front view, FIG. 11B is a plan view, and FIG. 11C is a side view. .
FIG. 12 is a perspective view showing a state in which a retaining wall is constructed.
13A and 13B are diagrams showing a state in which a retaining wall is constructed, wherein FIG. 13A is a front view, FIG. 13B is a plan view, and FIG. 13C is a side view.
FIG. 14 is a perspective view showing three types of patterns (a), (b), and (c) of through holes formed in the retaining wall block.
FIG. 15 is a partially cutaway perspective view showing a modified example of the upright portion gauge.
[Explanation of symbols]
10 ・ ・ ・ Retaining wall block
11 ・ ・ ・ Reinforcing bar inside the retaining wall block
12a: Through hole at the end of the retaining wall block
12b ・ ・ Through hole of retaining wall block
12c: Through hole in retaining wall block
12d ・ ・ Through hole at end of retaining wall block
13 ・ ・ ・ Wall surface of retaining wall block
20 ... prop
21 ... horizontal part of the support
22 ... standing part of the support
22a ... top of the upright section
23 Supporting member
24 ... Reinforcing member
30 ・ ・ ・ Gage for horizontal part
31 ・ ・ ・ Horizontal bar
32 ... fitting member
32a ··· Nipping piece of fitting
32b... Nipping piece of fitting
33 ... fitting member
33a ··· Nipping piece of fitting
33b... Nipping piece of fitting
40 ・ ・ ・ Standing gauge
41 ・ ・ ・ Gage body of gauge for standing part
41a ... horizontal shaft
41b ... engagement part
41c ... engaging part
42 ... engagement receiving member
42a ... engagement receiving part
43 ... engagement receiving member
43a... Engagement receiving part
50 ・ ・ ・ Vertical measuring tool
51 ・ ・ ・ Plumbing device
52 ... Plumbing support member
52a horizontal pin
52b ··· Vertical groove
53 ・ ・ ・ Plumb
53a ...
53b
54 ・ ・ ・ Indicator
A: Paving
B ... Sill
C ··· Net-shaped rebar
D ... Basic
E: Retaining wall
110 ... Retaining wall block
112a-Through hole at the end of the retaining wall block
112b ・ Through hole of retaining wall block
210 ... Retaining wall block
212a, through hole at end of retaining wall block
212b, through hole in retaining wall block
140 ・ ・ Gauge for standing part
141 ・ ・ Gage body of gauge for standing part
141a, horizontal shaft
141b / engagement part
141c / engagement part
142... Engagement receiving member
142a, engagement receiving portion
143... Engagement receiving member
143a, engagement receiving portion
Claims (4)
支柱の起立部に填める複数の貫通穴を備えた直方体状のコンクリート製擁壁ブロックと、
隣接する支柱の水平部間の距離を一定にするための水平部用ゲージと、
隣接する支柱の起立部間の距離を一定にするための起立部用ゲージと、
支柱の起立部を垂直に立設するための垂直測定具とを使用し、
以下の手順によりコンクリート製の基礎に擁壁を立設することを特徴とする擁壁施工法。
1.基礎形成前に、各支柱の水平部が水平部用ゲージにより一定の距離をおいて、また各支柱の起立部が起立部用ゲージにより一定の距離をおいて、さらに各支柱の起立部が垂直測定具により垂直となるように、さらにまた擁壁ブロックの貫通穴に各支柱の起立部が合致するように支柱を設置する。
2.各支柱の水平部が埋没するようにコンクリートを打設して基礎を形成する。
3.基礎により各支柱が固定された時点で、各支柱の起立部に擁壁ブロックの貫通穴を填め、擁壁ブロックを積み上げて擁壁を形成する。
4.擁壁ブロックの貫通穴にコンクリートを注入して擁壁ブロックと支柱の起立部とを固着する。A steel column consisting of a horizontal part fixed to a concrete foundation and a standing part supporting the retaining wall,
A cuboid concrete retaining wall block with a plurality of through holes that fit into the uprights of the columns,
A horizontal part gauge for keeping the distance between the horizontal parts of adjacent columns constant,
An upright gauge for keeping the distance between the uprights of adjacent struts constant;
Using a vertical measuring tool to erect the upright part of the column vertically,
A retaining wall construction method characterized by erecting a retaining wall on a concrete foundation by the following procedure.
1. Before the foundation is formed, the horizontal part of each pillar is kept at a fixed distance by the gauge for horizontal part, the upright part of each pillar is kept at a certain distance by the gauge for standing part, and the standing part of each pillar is vertical The columns are installed so that they are vertical by the measuring tool, and the uprights of the columns are aligned with the through holes of the retaining wall block.
2. The foundation is formed by casting concrete so that the horizontal part of each column is buried.
3. When each pillar is fixed by the foundation, the through hole of the retaining wall block is filled in the upright part of each pillar, and the retaining wall block is stacked to form a retaining wall.
4. Concrete is poured into the through hole of the retaining wall block to fix the retaining wall block to the upright portion of the column.
該嵌合部材を隣接する支柱の水平部に装着して架け渡すことにより、隣接する支柱の水平部が一定の間隔に配設されるようにしたことを特徴とする請求項1に記載の擁壁施工法。The horizontal portion gauge, a horizontal bar of a predetermined length and a fitting member that fits into the horizontal portion of the support column at a predetermined interval on the lower surface of the horizontal bar,
2. The holding member according to claim 1, wherein the fitting member is attached to a horizontal portion of the adjacent column and is bridged so that the horizontal portions of the adjacent column are arranged at a constant interval. Wall construction method.
該係合受け部材を隣接する支柱の起立部にそれぞれ装着し、各支柱の係合受け部材間に前記ゲージ本体を架け渡すことにより、隣接する支柱の起立部が一定の間隔に立設されるようにしたことを特徴とする請求項1又は2に記載の擁壁施工法。An erecting portion gauge, a gauge body including a horizontal shaft portion having a predetermined length and engaging portions disposed at both ends of the horizontal shaft portion, and a detachably disposed top portion of the upright portion of the support, and An engagement portion and an engageable engagement receiving member,
The engagement receiving members are mounted on the upright portions of the adjacent columns, and the gauge body is bridged between the engagement receiving members of the respective columns, so that the upright portions of the adjacent columns are erected at regular intervals. The retaining wall construction method according to claim 1, wherein:
該垂直測定具により、各支柱の起立部が垂直に立設していることを確認できるようにしたことを特徴とする請求項1〜3のいずれか1項に記載の擁壁施工法。A vertical measuring tool, a down swing device that hangs down along the upright portion of each column, and an index portion to which the down swing device points when the upright portion of the column is vertically erected,
The retaining wall construction method according to any one of claims 1 to 3, wherein the vertical measuring tool can confirm that the upright portions of the respective columns are vertically erected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003102323A JP2004308220A (en) | 2003-04-04 | 2003-04-04 | Retaining wall construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003102323A JP2004308220A (en) | 2003-04-04 | 2003-04-04 | Retaining wall construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004308220A true JP2004308220A (en) | 2004-11-04 |
Family
ID=33465782
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003102323A Pending JP2004308220A (en) | 2003-04-04 | 2003-04-04 | Retaining wall construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004308220A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101072512B1 (en) | 2011-03-11 | 2011-10-11 | 삼정건설 주식회사 | Multi-purpose resin block having sand |
KR101328438B1 (en) * | 2013-04-26 | 2013-11-14 | 전남대학교산학협력단 | Basis block for wall and constructing a wall using the same |
KR20160149676A (en) * | 2015-06-19 | 2016-12-28 | 홍지기술산업주식회사 | Reinforcing member for earth wall |
JP2021147996A (en) * | 2020-03-16 | 2021-09-27 | 株式会社ニッコン | Concrete secondary molding product and construction method of concrete secondary molding product |
WO2023272350A1 (en) * | 2021-06-30 | 2023-01-05 | Joshua Wilkinson | A method and apparatus for sleeper retaining wall post installation |
KR102665377B1 (en) * | 2024-01-22 | 2024-05-14 | (주) 대현이엔씨 | Structure Improved Concrete Panel Retaining Wall and Its Construction Method |
-
2003
- 2003-04-04 JP JP2003102323A patent/JP2004308220A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101072512B1 (en) | 2011-03-11 | 2011-10-11 | 삼정건설 주식회사 | Multi-purpose resin block having sand |
KR101328438B1 (en) * | 2013-04-26 | 2013-11-14 | 전남대학교산학협력단 | Basis block for wall and constructing a wall using the same |
KR20160149676A (en) * | 2015-06-19 | 2016-12-28 | 홍지기술산업주식회사 | Reinforcing member for earth wall |
JP2021147996A (en) * | 2020-03-16 | 2021-09-27 | 株式会社ニッコン | Concrete secondary molding product and construction method of concrete secondary molding product |
WO2023272350A1 (en) * | 2021-06-30 | 2023-01-05 | Joshua Wilkinson | A method and apparatus for sleeper retaining wall post installation |
KR102665377B1 (en) * | 2024-01-22 | 2024-05-14 | (주) 대현이엔씨 | Structure Improved Concrete Panel Retaining Wall and Its Construction Method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2006347260B2 (en) | Formwork and method for constructing rammed earth walls | |
US4337605A (en) | Concrete building blocks with looped securing rods for mortarless wall construction | |
US9091055B2 (en) | Wall assembly method | |
EP2215316B1 (en) | A block wall system | |
AU2006100463B4 (en) | Bricklayers pillar builder | |
JP2007070875A (en) | Upright support structure of strut and foundation block used for the structure | |
JP2004308220A (en) | Retaining wall construction method | |
CN113829493A (en) | Processing method of prefabricated greening retaining wall | |
JP5553947B1 (en) | Installation method of solar panel support column by cast-in percussion method | |
CN108951429A (en) | The method of frame and hollow pier pier construction built in hollow pier pier shaft | |
CN211007712U (en) | Portable pole is counted with skin to building a wall | |
JP2019065641A (en) | Rock fall guard fence | |
CN208777183U (en) | Frame and constructing device built in hollow pier pier shaft | |
KR20100092609A (en) | Precast form structure for gutter and construction method using the same | |
CN110185170A (en) | A kind of wall modular tile | |
JP2014173305A (en) | Arc form and structure of retaining wall | |
KR0172034B1 (en) | Device for supporting an anchor bolt | |
JP4808136B2 (en) | Metal fittings for simple foundation placement | |
JP6301989B2 (en) | Construction method of block fence | |
JPH0296024A (en) | Structuring foundation for building | |
JPH0352918Y2 (en) | ||
JP2779404B2 (en) | Foundation reinforcement | |
JP2001226981A (en) | Surveying gauge for individual footing form, and method for setting the same | |
JP4747020B2 (en) | Support structure for fence support | |
KR100733715B1 (en) | Forming apparatus for half precast concreat slab |