JP2004155246A - Starting device of train controller - Google Patents

Starting device of train controller Download PDF

Info

Publication number
JP2004155246A
JP2004155246A JP2002320870A JP2002320870A JP2004155246A JP 2004155246 A JP2004155246 A JP 2004155246A JP 2002320870 A JP2002320870 A JP 2002320870A JP 2002320870 A JP2002320870 A JP 2002320870A JP 2004155246 A JP2004155246 A JP 2004155246A
Authority
JP
Japan
Prior art keywords
logic unit
system device
predetermined
processing
system logic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2002320870A
Other languages
Japanese (ja)
Inventor
Takeshi Kawai
武 河合
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Signal Co Ltd
Original Assignee
Nippon Signal Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Signal Co Ltd filed Critical Nippon Signal Co Ltd
Priority to JP2002320870A priority Critical patent/JP2004155246A/en
Publication of JP2004155246A publication Critical patent/JP2004155246A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B61RAILWAYS
    • B61LGUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
    • B61L27/00Central railway traffic control systems; Trackside control; Communication systems specially adapted therefor
    • B61L27/04Automatic systems, e.g. controlled by train; Change-over to manual control
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B61RAILWAYS
    • B61LGUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
    • B61L1/00Devices along the route controlled by interaction with the vehicle or vehicle train, e.g. pedals
    • B61L1/20Safety arrangements for preventing or indicating malfunction of the device, e.g. by leakage current, by lightning

Abstract

<P>PROBLEM TO BE SOLVED: To prevent "windage" when a train controller of a standby double system type is started. <P>SOLUTION: In this starting device of the train controller of the standby double system type, a one-system device is set at a daily use device, a two-system device is set at a standby device, and the two-system device is used when a failure occurs in the one-system device. The starting device comprises a transmitting means for transmitting a predetermined starting information indicating on predetermined starting processing from the one-system device to the two-system device when the one-system device is performing the predetermined starting processing by power supply or reset processing, and an inhibiting means for inhibiting the completion of the predetermined starting processing of the two-system device when the two-system device receives the predetermined starting information from the one-system device. <P>COPYRIGHT: (C)2004,JPO

Description

【0001】
【発明の属する技術分野】
本発明は、ATCのような列車制御装置に組込まれる列車制御装置の立上装置に関する。
【0002】
【従来の技術】
従来、例えばATC地上装置のような列車制御用装置は、平成9年5月15日に(社)日本鉄道電気技術協会から発行された「鉄道技術者のための電気概論」信号シリーズ ATS・ATC P.76〜147(第4版)に示されるように、列車運転を可能な限り確保するために待機2重系方式の冗長構成とされている(特に、上記刊行物のP.106参照)。
【0003】
上記従来の待機2重系方式のATC地上装置から車上(列車)へ向けて所定のATC信号を送信するには、同一構成の1系装置及び2系装置に電源が供給されて駆動が開始されると、1系装置が常用系、すなわち主系装置となり、2系装置が待機系、すなわち従系装置となって使用され、1系装置に故障が発生したときは、2系装置から車上へ向けて所定のATC信号が送信されるように構成されている。
【0004】
【発明が解決しようとする課題】
しかしながら、上記従来の待機2従系方式のATC地上装置のような列車制御装置においては、1系装置及び2系装置に電源を供給して立ち上げる際、ATC信号を車上に向けて送信するための送信制御リレーがON,OFFを繰り返す、いわゆる「あおり」が生じることがあった。
【0005】
この「あおり」を本発明の実施の形態の説明の項で用いる図1を用いてさらに説明すると、2aは、上述の1系装置に相当する1系論理部であり、2bは、上述の2系装置に相当する2系論理部である。これら2つの論理部2a,2bを有するATC地上装置1を駆動させるためには、図示しない電源回路からスイッチS1 ,S2 をONにして両論理部2a,2bに電源が供給される。なお、この電源供給は、手動で行われるために各論理部2a,2bに対する電源投入に時間差が発生する。
【0006】
今、上述のスイッチS1 ,S2 のONにより各系論理部2a,2bに電源が供給されて駆動が開始されたとする。そして、2系論理部2bの方が1系論理部2aよりも少し早く所定の立上処理が終了したとする。この駆動開始時における両系論理部2a,2bの立上処理中、各系論理部2a,2bの正常リレー(COR,SKR)は、落下状態(OFF状態)にあるが、2系論理部2bが1系論理部2aより先に立ち上がると、その2系論理部2bは、1系論理部2aを故障と判定して2系論理部2bで生成された所定のATC信号を送信制御リレーSCRを介して車上に向けて送信を開始する。
【0007】
ところが、1系論理部2aは、故障ではないので、2系論理部2bの立上処理後に立ち上がる。この1系論理部2aの立上により1系論理部2aの正常リレーCORが動作(ON)して主系となり、その正常リレーCORの接点を介して2系論理部2bが従系におかれる。このように、1系論理部2aが主系におかれると、その1系論理部2aの正常リレーCORの接点が2系論理部2bを切り離すように作用するため、2系論理部2bから出力されていたATC信号が中断されて送信制御リレーSCRがOFFとされる。しかし、この送信制御リレーSCRは、1系論理部2aの正常リレーCORのONにより再びONとなって1系論理部2aで生成されたATC信号が車上に向けて送信される。このように、2系論理部2bが1系論理部2aよりも早く立上処理が終了すると、送信制御リレーSCRは、ON→OFF→ONの動作が行われて送信制御リレーSCRに「あおり」が発生してしまう。このような「あおり」は、1系論理部2a及び2系論理部2bがリセット処理されたときにも発生する。
【0008】
そこで、本発明は、上記欠点を解決するためになされたものであって、その目的は、「あおり」の発生しない列車制御装置の立上装置を提供することにある。
【0009】
【課題を解決するための手段】
本発明に係る列車制御装置の立上装置は、上記目的を達成するために、請求項1に記載の発明は、1系装置を常用系装置とするとともに、2系装置を待機系装置とし、その1系装置に故障が発生したときにその2系装置を使用する待機2重系方式の列車制御装置の立上装置であって、電源投入又はリセット処理により前記1系装置が所定の立上処理を行っているとき、その1系装置からその2系装置に対して所定の立上処理中である旨の所定の立上情報を送信する送信手段と、前記2系装置は、前記1系装置から所定の立上情報を受信しているとき、その2系装置の所定の立上処理の終了を禁止する禁止手段と、を有することを特徴としている。
本発明の請求項2に記載の列車制御装置の立上装置は、1系装置の立上処理中、その1系装置に故障が発生したとき、2系装置の立上処理の終了を許可する許可手段を設けたことを特徴としている。
本発明の請求項3に記載の列車制御装置の立上装置は、列車制御装置は、ATC地上装置であることを特徴としている。
【0010】
【発明の実施の形態】
以下、本発明の実施の形態を図面に基づいて説明する。図1は、本発明に係る列車制御装置の立上装置をATC地上装置に適用したときの概略構成図である。
【0011】
ATC地上装置1は、本発明の1系装置に相当する1系論理部2aと、本発明の2系装置に相当する2系論理部2bとからなる待機2重系方式の冗長構成とされている。各系論理部2a,2bは、CPUを中心に形成された同一構成からなる演算装置であり、入力される列車位置信号(本発明で「信号」というときは、「情報」と同じ意味で用いている。)や信号機の現示情報等の所定の入力信号に基づいて所定の演算処理を行い、所定のATC信号を出力するように構成されている。なお、1系論理部2a及び2系論理部2bに入力される上述の入力信号は、もちろん同一の入力信号である。
【0012】
図1中、S1 ,S2 はスイッチであって、図示しない電源回路から1系論理部2a及び2系論理部2bに所定の電源をそれぞれ供給するときにONされる。また、四角形のCORは、1系論理部2aが正常に動作しているときに扛上(ON)される正常リレーであり、四角形のSKRは、2系論理部2bが正常に動作しているときにONされる正常リレーである。
【0013】
図1中、四角形のSCRは、1系論理部2a又は2系論理部2bが所定のATC信号を出力しているときにONとなる送信制御リレーである。また、3は、増幅器を中心に形成された送信回路であって、1系論理部2a又は2系論理部2bから出力されるATC信号を増幅処理して列車イの走行するレールrを所定長さに区分して形成された軌道回路Tの始端側に接続トランスtを介して印加するように構成されている。
【0014】
なお、図1中のライン中に示されるCOR及びSCRは、各リレーの接点を示している。また、Rは、送信回路3からの出力(ATC信号)を軌道回路Tに印加しないときのダミー抵抗である。
【0015】
以下、図2のフローチャートを用いてATC地上装置1の立上時の制御動作を説明する。なお、このフローチャートは、2系論理部2bを中心に示されている。今、列車運転の開始に先立ってスイッチS1 ,S2 がONされて1系論理部2a及び2系論理部2bに電源が供給されたとする。
【0016】
各論理部2a,2bでは、電源の供給を受けると、所定の演算処理に先立って所定の初期化処理が行われる(ステップ100。以下、ステップを「ST」とする。)。この初期化終了後、各論理部2a,2bでは、所定の立上処理が行われる。この立上処理は、所定のプログラムに従って各種の照査処理によって実行される(ST102、ST104)。もちろん、この立上処理中に上述の初期化処理を含めることができる。そして、この立上処理中、1系論理部2aから2系論理部2bに対して1系論理部2aが立上処理中である旨の所定の立上情報が送信される(ST106。図1の矢印▲1▼参照。)。また、2系論理部2bから1系論理部2aに対して2系論理部2bが立上処理中である旨の所定の立上情報が送信される(図1の矢印▲2▼参照。)。
【0017】
2系論理部2bは、1系論理部2aから所定の立上情報を受信しているとき、自己の立上処理を終了を禁止して、1系論理部2aの立上処理終了を待つ状態におかれる。そして、この1系論理部2aの立上処理が終了し、その1系論理部2aの正常リレーがONとなった後に2系論理部2bの立上処理の終了が行われる。このように、1系論理部2aが2系論理部2bよりも先に立上処理が終了となるので、主系である1系論理部2aの正常リレーCORの接点及びその1系論理部2aが正常に動作していることによりONされる送信制御リレーSCRの接点を介して、その1系論理部2aで生成された所定のATC信号が軌道回路Tに印加される(ST108、ST110(1系正常)、ST112)。この立上処理開始からATC信号の軌道回路Tへの印加までの間に、1系論理部2aから2系論理部2bへ切替わる動作がないので、「あおり」は確実に防止される。
【0018】
上述の1系論理部2aの立上処理中、その1系論理部2aが故障であることが判明したとき(ST110(1系故障))、2系論理部2bは、1系論理部2aの立上終了を待つことなく、2系論理部2bの立上処理が終了することが許可され、このため、2系論理部2bの立上処理が終了すると、2系論理部2bの正常リレーSKRがONとされる。この正常リレーSKRのONにより、2系論理部2bで生成された所定のATC信号は、1系論理部2aの正常リレーCORの落下接点、送信回路3及び送信制御リレーSCRを介して軌道回路Tへ印加される(ST114)。もちろん、この場合も2系論理部2bから1系論理部2aに切替わることがないので、「あおり」は発生しない。
【0019】
なお、上述の例では、1系論理部2aに2系論理部2bから所定の立上情報(図1の矢印▲2▼参照)が入力されているが、これを省略することもできる。しかし、上述の例のようにすると、2系論理部2bを常用系、すなわち主系に容易に変更することが可能となる。また、上述の例では、ATC地上装置1の電源投入時の「あおり」防止を中心に説明したが、リセット処理時の「あおり」も同様に防止することができる。さらに、列車制御装置としてATC地上装置1を示したが、他の列車制御装置であってもよいことはもちろんである。
【0020】
【発明の効果】
本発明の請求項1に記載の列車制御装置の立上装置は、1系装置を常用系装置とするとともに、2系装置を待機系装置とし、その1系装置に故障が発生したときにその2系装置を使用する待機2重系方式の列車制御装置の立上装置であって、電源投入又はリセット処理により前記1系装置が所定の立上処理を行っているとき、その1系装置からその2系装置に対して所定の立上処理中である旨の所定の立上情報を送信する送信手段と、前記2系装置は、前記1系装置から所定の立上情報を受信しているとき、その2系装置の所定の立上処理の終了を禁止する禁止手段とを有するので、「あおり」を効果的に防止することができる。
本発明の請求項2に記載の列車制御装置の立上装置は、1系装置の立上処理中、その1系装置に故障が発生したとき、2系装置の立上処理の終了を許可する許可手段を設けたので、2系装置で所定の処理を行うことができる。
本発明の請求項3に記載の列車制御装置の立上装置は、列車制御装置は、ATC地上装置であるので、ATC地上装置の「あおり」を効果的に防止することができる。
【図面の簡単な説明】
【図1】本発明の列車制御装置の立上装置をATC地上装置に適用したときの概略構成図である。
【図2】制御動作を示すフローチャートである。
【符号の説明】
1 ATC地上装置
2a 1系論理部(1系装置)
2b 2系論理部(2系装置)
3 送信回路
COR,SKR 正常リレー
SCR 送信制御リレー
R ダミー抵抗
r レール
T 軌道回路
イ 列車
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a start-up device of a train control device incorporated in a train control device such as an ATC.
[0002]
[Prior art]
Conventionally, a train control device such as an ATC ground device, for example, is a signal series of "General Electricity for Railway Engineers" issued by the Japan Railway Electrical Engineers Association on May 15, 1997. ATS / ATC P. 76 to 147 (fourth edition), a redundant configuration of a standby dual system is used to ensure train operation as much as possible (especially, see P. 106 of the above publication).
[0003]
In order to transmit a predetermined ATC signal from the above-mentioned conventional standby dual system ATC ground device to the vehicle (train), power is supplied to the first system device and the second system device having the same configuration, and driving is started. When the system 1 is used as a normal system, that is, a main system, the system 2 is used as a standby system, that is, as a slave, and when a failure occurs in the system 1, the system 2 is used as a vehicle. A predetermined ATC signal is configured to be transmitted upward.
[0004]
[Problems to be solved by the invention]
However, in a conventional train control device such as the standby two-slave type ATC ground device, when power is supplied to the system 1 and the system 2 to start up, the ATC signal is transmitted toward the vehicle. So-called "tilt" may occur when the transmission control relay is repeatedly turned ON and OFF.
[0005]
This "tilt" will be further described with reference to FIG. 1 which is used in the description of the embodiment of the present invention. In FIG. 1, 2a is a 1-system logic unit corresponding to the 1-system device described above, and 2b is a 2-system logic unit. It is a system 2 logic unit corresponding to the system device. In order to drive the ATC ground equipment 1 having these two logic units 2a and 2b, power is supplied to both logic units 2a and 2b by turning on the switches S1 and S2 from a power supply circuit (not shown). Since the power supply is performed manually, there is a time difference between the power supply to the logic units 2a and 2b.
[0006]
Now, it is assumed that power is supplied to the respective system logic units 2a and 2b by turning on the switches S1 and S2, and the driving is started. Then, it is assumed that the predetermined start-up processing is completed slightly earlier in the second system logic unit 2b than in the first system logic unit 2a. During the start-up processing of both logical units 2a and 2b at the start of driving, the normal relays (COR, SKR) of each logical unit 2a and 2b are in the falling state (OFF state), but the second logical unit 2b Rises before the first-system logic unit 2a, the second-system logic unit 2b determines that the first-system logic unit 2a has failed and sends a predetermined ATC signal generated by the second-system logic unit 2b to the transmission control relay SCR. And start transmitting on the car.
[0007]
However, since the first-system logic unit 2a is not a fault, it starts up after the second-system logic unit 2b starts up. With the rise of the 1-system logic unit 2a, the normal relay COR of the 1-system logic unit 2a operates (ON) to become the master system, and the second-system logic unit 2b is set to the slave system via the contact of the normal relay COR. . As described above, when the first-system logical unit 2a is placed in the main system, the contact of the normal relay COR of the first-system logical unit 2a acts to separate the second-system logical unit 2b. The transmitted ATC signal is interrupted and the transmission control relay SCR is turned off. However, the transmission control relay SCR is turned on again by turning on the normal relay COR of the first system logic unit 2a, and the ATC signal generated by the first system logic unit 2a is transmitted toward the vehicle. As described above, when the start-up processing of the second-system logic unit 2b is completed earlier than that of the first-system logic unit 2a, the transmission control relay SCR performs an ON → OFF → ON operation, and the transmission control relay SCR “turns”. Will occur. Such a tilt also occurs when the first-system logic unit 2a and the second-system logic unit 2b are reset.
[0008]
Then, this invention is made in order to solve the said fault, The objective is to provide the start-up apparatus of the train control apparatus which does not generate "tilting."
[0009]
[Means for Solving the Problems]
In order to achieve the above object, the start-up device of the train control device according to the present invention is configured such that the invention according to claim 1 uses the first system device as a regular system device and the second system device as a standby system device, A start-up device for a standby dual-system train control device that uses the second system device when a failure occurs in the first system device. A transmitting means for transmitting predetermined start-up information indicating that predetermined start-up processing is being performed from the first system apparatus to the second system apparatus during the processing, and the second system apparatus comprises: Prohibiting means for prohibiting termination of the predetermined start-up processing of the second system device when receiving predetermined start-up information from the device.
The start-up device of the train control device according to claim 2 of the present invention permits the termination of the start-up process of the second system device when a failure occurs in the first system device during the start process of the first system device. It is characterized in that permission means is provided.
According to a third aspect of the present invention, the start-up device of the train control device is characterized in that the train control device is an ATC ground device.
[0010]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings. FIG. 1 is a schematic configuration diagram when a start-up device of a train control device according to the present invention is applied to an ATC ground device.
[0011]
The ATC terrestrial device 1 has a standby dual system type redundant configuration including a first system logic unit 2a corresponding to the first system device of the present invention and a second system logic unit 2b corresponding to the second system device of the present invention. I have. Each of the system logic units 2a and 2b is an arithmetic unit having the same configuration formed around a CPU, and receives an input train position signal (in the present invention, "signal" is used in the same meaning as "information"). ), And performs predetermined arithmetic processing based on predetermined input signals such as present information of a traffic light, and outputs a predetermined ATC signal. The above-mentioned input signals input to the first-system logic unit 2a and the second-system logic unit 2b are, of course, the same input signals.
[0012]
In FIG. 1, switches S1 and S2 are turned on when a predetermined power is supplied from a power supply circuit (not shown) to the first-system logic unit 2a and the second-system logic unit 2b. Further, the square COR is a normal relay that is lifted (ON) when the first-system logic unit 2a is operating normally, and the square SKR is that the second-system logic unit 2b is operating normally. It is a normal relay that is turned on at times.
[0013]
In FIG. 1, a square SCR is a transmission control relay that is turned on when the first-system logic unit 2a or the second-system logic unit 2b outputs a predetermined ATC signal. Reference numeral 3 denotes a transmission circuit formed mainly of an amplifier, which amplifies an ATC signal output from the first-system logic unit 2a or the second-system logic unit 2b to extend the rail r on which the train A travels by a predetermined length. It is configured to apply a voltage via the connection transformer t to the starting end side of the track circuit T formed separately.
[0014]
Note that COR and SCR shown in the line in FIG. 1 indicate the contacts of each relay. R is a dummy resistor when the output (ATC signal) from the transmission circuit 3 is not applied to the track circuit T.
[0015]
Hereinafter, the control operation of the ATC ground device 1 at the time of startup will be described with reference to the flowchart of FIG. This flowchart mainly shows the second-system logic unit 2b. It is assumed that switches S1 and S2 are turned on and power is supplied to the first-system logic unit 2a and the second-system logic unit 2b prior to the start of train operation.
[0016]
In the logic units 2a and 2b, when power is supplied, a predetermined initialization process is performed prior to a predetermined calculation process (step 100; hereinafter, the steps are referred to as "ST"). After completion of the initialization, the logic units 2a and 2b perform a predetermined start-up process. This start-up process is executed by various checking processes according to a predetermined program (ST102, ST104). Of course, the above-mentioned initialization processing can be included in this start-up processing. Then, during this start-up processing, predetermined start-up information indicating that the first-system logical unit 2a is performing the start-up processing is transmitted from the first-system logical unit 2a to the second-system logical unit 2b (ST106; FIG. 1). Arrow <1>). Also, predetermined start-up information indicating that the second-system logic unit 2b is performing a start-up process is transmitted from the second-system logic unit 2b to the first-system logic unit 2a (see arrow {circle around (2)} in FIG. 1). .
[0017]
The second-system logic unit 2b, when receiving predetermined start-up information from the first-system logic unit 2a, prohibits termination of its own start-up process and waits for the completion of the start-up process of the first-system logic unit 2a. Put in. Then, the start-up processing of the first-system logic unit 2a is completed, and after the normal relay of the first-system logic unit 2a is turned on, the start-up processing of the second-system logic unit 2b is completed. As described above, since the start-up processing of the first-system logical unit 2a is completed before the second-system logical unit 2b, the contact of the normal relay COR of the first-system logical unit 2a, which is the main system, and the first-system logical unit 2a A normal ATC signal generated by the first-system logic unit 2a is applied to the track circuit T via the contact point of the transmission control relay SCR that is turned on when the is operating normally (ST108, ST110 (1 System normal), ST112). Since there is no operation of switching from the first-system logic unit 2a to the second-system logic unit 2b between the start of the start-up processing and the application of the ATC signal to the track circuit T, "tilting" is reliably prevented.
[0018]
During the start-up processing of the first-system logic unit 2a, when it is determined that the first-system logic unit 2a is faulty (ST110 (first-system failure)), the second-system logic unit 2b is connected to the first-system logic unit 2a. The start-up process of the second-system logic unit 2b is allowed to end without waiting for the end of the start-up. Therefore, when the start-up process of the second-system logic unit 2b ends, the normal relay SKR of the second-system logic unit 2b is terminated. Is turned ON. When the normal relay SKR is turned on, a predetermined ATC signal generated by the second logical unit 2b is transmitted to the track circuit T via the falling contact of the normal relay COR of the first logical unit 2a, the transmission circuit 3 and the transmission control relay SCR. (ST114). Of course, in this case as well, there is no switching from the second-system logic unit 2b to the first-system logic unit 2a, so that "tilting" does not occur.
[0019]
In the above example, the predetermined start-up information (see the arrow {circle around (2)} in FIG. 1) is input to the first system logic unit 2a from the second system logic unit 2b, but this may be omitted. However, according to the above-described example, it is possible to easily change the second-system logic unit 2b to a normal system, that is, a main system. Further, in the above-described example, the description has been made mainly on the prevention of the "shift" when the power of the ATC ground apparatus 1 is turned on. However, the "shift" during the reset process can be similarly prevented. Further, although the ATC ground device 1 is shown as a train control device, it is a matter of course that another train control device may be used.
[0020]
【The invention's effect】
The start-up device of the train control device according to claim 1 of the present invention, wherein the first system device is used as a normal system device, the second system device is used as a standby system device, and when a failure occurs in the first system device, A start-up device for a standby dual-system train control device using a second-system device, wherein when the first-system device performs a predetermined start-up process by power-on or reset processing, Transmitting means for transmitting predetermined start-up information indicating that predetermined start-up processing is being performed to the second system apparatus; and the second system apparatus has received predetermined start-up information from the first system apparatus. At this time, since there is provided a prohibition unit for prohibiting the end of the predetermined start-up process of the second system device, it is possible to effectively prevent "tilting".
The start-up device of the train control device according to claim 2 of the present invention permits the termination of the start-up process of the second system device when a failure occurs in the first system device during the start process of the first system device. Since the permission means is provided, predetermined processing can be performed by the second apparatus.
Since the train control device according to the third aspect of the present invention is an ATC ground device, it is possible to effectively prevent the ATC ground device from being tilted.
[Brief description of the drawings]
FIG. 1 is a schematic configuration diagram when a start-up device of a train control device of the present invention is applied to an ATC ground device.
FIG. 2 is a flowchart showing a control operation.
[Explanation of symbols]
1 ATC ground equipment 2a 1 system logic unit (1 system device)
2b 2nd logic unit (2nd device)
3 Transmission circuit COR, SKR Normal relay SCR Transmission control relay R Dummy resistor r Rail T Track circuit A Train

Claims (3)

1系装置を常用系装置とするとともに、2系装置を待機系装置とし、その1系装置に故障が発生したときにその2系装置を使用する待機2重系方式の列車制御装置の立上装置であって、
電源投入又はリセット処理により前記1系装置が所定の立上処理を行っているとき、その1系装置からその2系装置に対して所定の立上処理中である旨の所定の立上情報を送信する送信手段と、
前記2系装置は、前記1系装置から所定の立上情報を受信しているとき、その2系装置の所定の立上処理の終了を禁止する禁止手段と、
を有することを特徴とする列車制御装置の立上装置。
Startup of a standby dual-system train control system that uses system 1 as a service system and system 2 as a standby system and uses the system 2 when a failure occurs in system 1 A device,
When the first system device is performing a predetermined start-up process by power-on or reset processing, predetermined start-up information indicating that a predetermined start-up process is being performed from the first system device to the second system device. Transmitting means for transmitting;
The second system device, when receiving predetermined start-up information from the first system device, prohibiting means for prohibiting termination of predetermined start-up processing of the second system device;
A start-up device for a train control device, comprising:
請求項1に記載の列車制御装置の立上装置において、1系装置の立上処理中、その1系装置に故障が発生したとき、2系装置の立上処理の終了を許可する許可手段を設けたことを特徴とする列車制御装置の立上装置。The start-up device of the train control device according to claim 1, wherein during start-up processing of the first system device, when a failure occurs in the first system device, a permission means for permitting termination of the start-up process of the second system device is provided. A start-up device for a train control device, which is provided. 請求項1又は2に記載の列車制御装置の立上装置において、列車制御装置は、ATC地上装置であることを特徴とする列車制御装置の立上装置。The start-up device for a train control device according to claim 1, wherein the train control device is an ATC ground device.
JP2002320870A 2002-11-05 2002-11-05 Starting device of train controller Pending JP2004155246A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002320870A JP2004155246A (en) 2002-11-05 2002-11-05 Starting device of train controller

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002320870A JP2004155246A (en) 2002-11-05 2002-11-05 Starting device of train controller

Publications (1)

Publication Number Publication Date
JP2004155246A true JP2004155246A (en) 2004-06-03

Family

ID=32801588

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002320870A Pending JP2004155246A (en) 2002-11-05 2002-11-05 Starting device of train controller

Country Status (1)

Country Link
JP (1) JP2004155246A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009051352A (en) * 2007-08-27 2009-03-12 Kyosan Electric Mfg Co Ltd Field control terminal and field instrument of net work system cooperative system
CN105109478A (en) * 2015-08-27 2015-12-02 华英汽车集团有限公司 Vehicle energy saving and emission reducing grouping system
CN111361607A (en) * 2018-12-25 2020-07-03 比亚迪股份有限公司 Train dormancy awakening system and method
JP2020144575A (en) * 2019-03-06 2020-09-10 日本信号株式会社 Railway control system
CN112706784A (en) * 2021-01-13 2021-04-27 中车青岛四方机车车辆股份有限公司 Full-automatic driving vehicle activation and interlocking control circuit, control method and vehicle

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009051352A (en) * 2007-08-27 2009-03-12 Kyosan Electric Mfg Co Ltd Field control terminal and field instrument of net work system cooperative system
CN105109478A (en) * 2015-08-27 2015-12-02 华英汽车集团有限公司 Vehicle energy saving and emission reducing grouping system
CN111361607A (en) * 2018-12-25 2020-07-03 比亚迪股份有限公司 Train dormancy awakening system and method
CN111361607B (en) * 2018-12-25 2021-08-10 比亚迪股份有限公司 Train dormancy awakening system and method
JP2020144575A (en) * 2019-03-06 2020-09-10 日本信号株式会社 Railway control system
JP7313845B2 (en) 2019-03-06 2023-07-25 日本信号株式会社 railway control system
CN112706784A (en) * 2021-01-13 2021-04-27 中车青岛四方机车车辆股份有限公司 Full-automatic driving vehicle activation and interlocking control circuit, control method and vehicle
CN112706784B (en) * 2021-01-13 2022-03-01 中车青岛四方机车车辆股份有限公司 Full-automatic driving vehicle activation and interlocking control circuit, control method and vehicle

Similar Documents

Publication Publication Date Title
JP2010068594A (en) Protection and control system
JP2004155246A (en) Starting device of train controller
JP2008099515A (en) Train safety onboard device, and inspection device thereof
JP2006323551A (en) Plant control system
KR20220163638A (en) Brake Apparatus for Vehicle and Control Method Therefor
JP2000201440A (en) Uninterruptible power supply system and its power supply method
JP2004175186A (en) Electronic interlock system
JP3839797B2 (en) Substation operation control device
JP2016142141A (en) Electronic control device for vehicle
JP5358343B2 (en) Power converter
JP2006105016A (en) Vehicular starting control device
JPH04265624A (en) Switching power supply circuit
JP2730356B2 (en) Standby redundant system
CN113830052B (en) Motor control switching circuit, redundancy backup electronic parking controller and parking system
JP3125864B2 (en) Redundant system
JP2508606B2 (en) Redundant device
JP2006279328A (en) Crossbar switch
JP2004058793A (en) Electronic interlocking device
JP3045748B2 (en) Power supply switching method
JP3798755B2 (en) Electric vehicle control device
CN117962839A (en) Power supply monitoring and failure processing method for parking system of vehicle
JP5523187B2 (en) Power switching method
JP2022159894A (en) Vehicle power supply control device
JP2004357423A (en) Uninterruptible power supply
RU2054780C1 (en) Power supply and distribution device for power supply systems