JP2004110102A - Project management method and process definition device - Google Patents
Project management method and process definition device Download PDFInfo
- Publication number
- JP2004110102A JP2004110102A JP2002268052A JP2002268052A JP2004110102A JP 2004110102 A JP2004110102 A JP 2004110102A JP 2002268052 A JP2002268052 A JP 2002268052A JP 2002268052 A JP2002268052 A JP 2002268052A JP 2004110102 A JP2004110102 A JP 2004110102A
- Authority
- JP
- Japan
- Prior art keywords
- work
- wbs
- work process
- information
- definition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims description 84
- 238000007726 management method Methods 0.000 title claims description 63
- 238000011161 development Methods 0.000 claims description 7
- 238000012217 deletion Methods 0.000 claims description 2
- 230000037430 deletion Effects 0.000 claims description 2
- 238000012545 processing Methods 0.000 description 26
- 238000010586 diagram Methods 0.000 description 13
- 238000013461 design Methods 0.000 description 10
- 230000001419 dependent effect Effects 0.000 description 8
- 239000004381 Choline salt Substances 0.000 description 5
- 238000012360 testing method Methods 0.000 description 5
- 238000012356 Product development Methods 0.000 description 2
- 230000015556 catabolic process Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Stored Programmes (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、本発明は、プロジェクト管理において、プロジェクトの作業情報の管理方法および工程定義装置に関する。
【0002】
【従来の技術】
従来のプロジェクト管理に関するものとしては、例えば特開2000−215038号公報に記載の『情報管理装置および記録媒体』がある。これは、プロジェクト管理者がそのプロジェクトで実施すべき作業工程を定義し、それらの作業工程の定義に、作業の進捗、成果物などを関連付けてプロジェクトの管理を一元的に行うことで、プロジェクト管理の効率を向上させるシステムである。
【0003】
この装置は、最初に基本的なプロセス定義を記述しておけば、複数の処理手段によりそのプロセス定義の内容に沿ってプロジェクト情報を正しい順序で順次生成していくことが可能であり、一元管理によりプロジェクト情報間に矛盾が生じないという利点がある。
しかし、このようなシステムにおいて、プロジェクト管理者が定義すべき作業工程を組織として共通化することで、開発効率の向上を実現するという試みは一般的に行われており、特に目新しいものではない。
【0004】
また、他の提案としては、例えば特開2001−42915号公報に記載の『製品開発工程管理システム、方法、およびこの方法を記録した記録媒体』がある。これは、プロジェクトの進行中に必要な段階で開発工程に作業を追加したり、修正したりする手段を提供することで、プロジェクト管理者がそのプロジェクトを円滑に遂行させることを目的としている。
【0005】
このシステムによれば、既存のシステムのデータを外部から参照するだけであるため、一般的な製品開発環境において構築して利用されている業務支援システムを改造することなく、開発対象となる製品や、部品についての属性データ間の関連を保持することが可能である。
【0006】
【発明が解決しようとする課題】
共通化された作業工程に従っている場合、各プロジェクトで実際に行うべき、より詳細な作業は、そのプロジェクトで開発すべき対象(コンポーネント)の構成によって様々である。そのため、このような詳細な作業に関しては、プロジェクトの管理者が逐次必要な作業を追加したり、修正したりする必要がある。この結果、プロジェクト管理者は、プロジェクトの進行中に作業工程の修正を行うための管理コストが必要となる。この管理コストを低減させることが望ましい。
【0007】
本発明の目的は、このような問題点を解決し、プロジェクト固有の詳細な作業項目を自動的に定義可能とし、プロジェクト管理者の管理コストを低減させ、また、作業工程の定義の矛盾や漏れなどプロジェクト管理者によるミスをなくし、精度の高いプロジェクト管理を実現することが可能なプロジェクト管理方法および工程定義装置を提供することである。
【0008】
【課題を解決するための手段】
本発明のプロジェクト管理方法は、各プロジェクトの開発対象である構成情報をコンポーネント構成管理部に入力し、かつ共通WBS(Work Breakdown Structure)管理部にも入力し、コンポーネント構成管理部は、開発対象(コンポーネント)の構成情報を管理するとともに、共通WBS管理部は、共通して利用可能な作業工程を定義し、該作業工程の各項目を詳細化するパターンを表すWBS詳細化レベルを管理し、WBS詳細化装置とWBS管理部は、上記2つの管理部で管理されている情報を受けてWBSを詳細化し、また、WBSを管理することを特徴としている。
【0009】
また、本発明の工程定義装置は、各プロジェクトの開発対象の構成を入力情報として、開発対象(コンポーネント)の構成情報を管理するコンポーネント構成管理部と、共通して利用可能な作業工程(WBS)の定義と、それらの各項目を詳細化するパターンをあらわすWBS詳細化レベルを管理する共通WBS管理部と、これら2つの管理部で管理された情報から自動的にWBSを詳細化するWBS詳細化装置と、詳細化されたWBSを管理するWBS管理部を備えることを特徴としている。
【0010】
【発明の実施の形態】
以下、本発明の実施の形態について図面により説明する。
(第1の実施形態)
図1は、本発明の第1の実施形態を示す工程定義装置のシステム構成図である。
工程定義装置101は、各プロジェクト固有のコンポーネント構成情報103を管理するコンポーネント構成管理部102(図3で詳細を説明)と、共通WBS情報105とWBS詳細化レベル情報106を管理する共通WBS管理部104(図4で詳細に説明)と、WBS詳細化装置107(図6で詳細を説明)と、詳細化WBS情報109を管理するWBS管理部108(図5で詳細を説明)から構成される。WBS詳細化装置107は、コンポーネント構成情報103と共通WBS情報105とWBS詳細化レベル情報106を入力情報としてWBSの詳細化を行い、その結果を詳細化WBS情報109に格納する。
【0011】
図2は、図1に示すシステムにおいて実現されるWBS詳細化の例を示した図である。
コンポーネント構成管理部102では、開発対象のコンポーネントとしてコンポーネント(A)201、コンポーネント(B)202、コンポーネント(C)203、コンポーネント(D)204が定義されており、コンポーネント(D)204はコンポーネント(B)202、コンポーネント(C)203に、コンポーネント(B)202とコンポーネント(C)203はコンポーネント(A)201に依存する依存関係205が定義されている。以上が、第1の作業定義と、第2の作業である依存関係が定められる。
【0012】
次に、共通WBS管理部104では、WBSの共通部分が定義されており、内部仕様設計207は外部仕様設計206に、コーディング208は内部仕様設計207に、モジュールテスト209は内部仕様設計207とコーディング208に、総合テスト210は外部仕様設計206とコーディング208に、それぞれ依存する依存関係211が定義されており、内部仕様設計207は2、総合テスト210には0といったように、各作業にはWBS詳細化レベル212が定義されている。WBS詳細化装置107は、これらの情報からWBSを詳細化し、その結果をWBS管理部108に格納する。以上が第2の作業の依存関係の定義と、WBS(作業工程)の詳細化である。
【0013】
WBS管理部108では、WBSの詳細化の結果として、共通WBS管理部104で定義された作業206,207,208,209,210などと同じ定義を持ち、さらにWBS詳細化装置107によって詳細化された作業213,214,215が定義される。また、共通WBS管理部104で定義されている依存関係211も、WBS詳細化装置107によってWBS詳細化レベル212に従って、WBS管理部108に依存関係216,217,218,219が定義される。尚、これらの依存関係216,217,218,219は、図中で線の種類が異なっているが、これは線の区別を明確にするためであり、依存関係としてまったく同じ種類の情報を表わしている。
【0014】
図3(a)(b)は、コンポーネント構成管理部102におけるコンポーネント構成情報103の管理方法を示した図である。
コンポーネント(A)201、コンポーネント(B)202、コンポーネント(C)203、コンポーネント(D)204が図のような依存関係205を持っているという情報は、コンポーネント構成情報103では、コンポーネント名301と依存関係302の2列を持った表で管理される。例えば、コンポーネント名301がAの依存関係302の列は値がないため、コンポーネント(A)201は依存する他のコンポーネントを持たないとなる。また、コンポーネント名301がDの依存関係302の列はBとCという2つの値があるため、コンポーネント(D)204はコンポーネント(B)202とコンポーネント(C)203の2つのコンポーネントに依存することとなる。
【0015】
図4(a)(b)は、共通WBS管理部104における共通WBS情報105とWBS詳細化レベル情報106の管理方法を示した図である。
共通WBS管理部104は、共通WBS情報105を作業定義401と依存関係定義404の2つの表で管理する。作業定義401は作業名402と親作業403の2つの列を持った表である。例えば、作業名402がコーディングの親作業403は製造となっているので、コーディング208の作業は製造409の親作業を持ち、作業名402が製造の親作業403は値がないため、製造409の作業は親作業を持たないこととなる。
【0016】
依存関係定義404は、作業名405と依存関係406の2つの列を持った表である。例えば、作業名405がモジュールテストの依存関係406は内部仕様設計とコーディングのため、モジュールテスト209は内部仕様設計207とコーディング208に依存していることになる。WBS詳細化レベル情報106は、作業名407とWBS詳細化レベル408の2つの列を持った表で管理される。例えば、作業名407が外部仕様設計のWBS詳細化レベル408が0であるので、開部仕様設計206のWBS詳細化レベル212は0となる。
【0017】
図5(a)(b)は、WBS詳細化装置107によって詳細化されたWBSを管理するWBS管理部108における詳細化WBS情報109の管理方法を示した図である。
WBS管理部108は、詳細化WBS情報109を作業定義501と依存関係定義502の2つの表で管理する。作業定義501は、共通WBS情報105の作業定義401と同様の構造を持った表であり、詳細化された作業213,214,215の定義も管理する。依存関係定義502も共通WBS情報105の依存関係定義404と同様の構造を持った表であり、詳細化された作業213,214,215の依存関係216,217,218,219の定義も管理する。
【0018】
図6は、WBS詳細化装置107が実行する処理全体の流れを表したフローチャートである。
WBS詳細化装置107は、共通WBS情報105の作業定義401に定義された作業を詳細化WBS情報109の作業定義501にコピーする(ステップ601)。次に、WBS詳細化レベル情報106でWBS詳細化レベル212が1以上に定義されている作業について、コンポーネント構成情報103に定義されたコンポーネントに対応した詳細な作業として、詳細化WBS情報109の作業定義501に定義を追加する(ステップ602)。共通WBS情報105の作業定義401から順に作業を取得する(ステップ603)。
【0019】
取得した作業の親作業403が定義されているかをチェックし(ステップ604)、定義されていない場合は、その作業が親作業なので、作業定義401にまだ処理を実行していない次の作業が存在するか否かを確認し(ステップ610)、次の作業があればステップ603の処理から再び実行する。処理を実行していない次の作業が存在しない場合は、WBS詳細化装置は処理を終了する。ステップ604のチェックにおいて、親作業が定義されている場合は、WBS詳細化レベル情報106からその作業のWBS詳細化レベル212を取得する(ステップ605)。取得したWBS詳細化レベルによって処理が異なり(ステップ606)、0の場合(ステップ607)、1の場合(ステップ608)、2の場合(ステップ609)のそれぞれの処理を実行した後、前述したステップ610以降の処理を実行する。
【0020】
各WBS詳細化レベルにおける処理(ステップ607,608,609)の流れについてフローチャートを使用して順番に説明する。
図7は、WBS詳細化レベル212が0の場合の図6のフローチャートにおけるステップ607の処理の詳細を示したフローチャートである。
まず、処理対象の作業について、共通WBS情報105の依存関係定義404から依存関係定義が存在するか否かをチェックする(ステップ701)。依存関係定義が存在しない場合は、レベル0の詳細化処理部分の処理を終了する。一方、依存関係が存在する場合、その依存先の作業すべてについて、そのWBS詳細化レベル202をWBS詳細化レベル情報106より取得し(ステップ702)、その値によって以下の処理を実行する。
【0021】
取得したWBS詳細化レベルの値が1以上の場合、依存先の作業もコンポーネントに対応して詳細化されているため、それらの詳細化された作業すべてと、現在処理対象の作業との依存関係を新たに詳細化WBS情報109の依存関係定義502に定義する(ステップ703)。取得したWBS詳細化レベルの値が1以上でない場合、共通WBS情報105の依存関係定義404に定義された依存関係を詳細化WBS情報109の依存関係定義502にコピーして(ステップ704)、レベル0の詳細化処理部分の処理を終了する。
【0022】
図8は、WBS詳細化レベル212が1の場合の図6のフローチャートにおけるステップ608の処理の詳細を示したフローチャートである。
まず、処理対象の作業について、共通WBS情報105の依存関係定義404から依存関係定義が存在するか否かをチェックする(ステップ801)。依存関係定義が存在しない場合は、レベル1の詳細化処理部分の処理を終了する。依存関係が存在する場合、その依存先の作業すべてについて、そのWBS詳細化レベル202をWBS詳細化レベル情報106より取得し(ステップ802)、その値によって以下の処理を実行する。
【0023】
取得したWBS詳細化レベルの値が1以上の場合、依存先の作業もコンポーネントに対応して詳細化されているため、それらの詳細化された作業と現在処理対象の作業から詳細化された作業同士について、依存関係を新たに詳細化WBS情報109の依存関係定義502に定義する(ステップ803)。取得したWBS詳細化レベルの値が1以上でない場合、すべての詳細化した作業と、依存先作業について、詳細化WBS情報109の依存関係定義502にレコードを追加する(804)。そして、レベル0の詳細化処理部分の処理を終了する。
【0024】
図9は、WBS詳細化レベル212が2の場合の図6のフローチャートにおけるステップ609の処理の詳細を示したフローチャートである。
まず、コンポーネント構成情報103で定義された依存関係と同じ依存関係を、詳細化された作業間に対して新たに詳細化WBS情報109の依存関係定義502に定義する(ステップ901)。次に、処理対象の作業について、共通WBS情報105の依存関係定義404から依存関係定義が存在するか否かをチェックする(ステップ902)。依存関係定義が存在しない場合は、レベル0の詳細化処理部分の処理を終了する。
【0025】
依存関係が存在する場合、その依存先の作業すべてについて、そのWBS詳細化レベル202をWBS詳細化レベル情報106より取得し(ステップ903)、その値によって以下の処理を実行する。取得したWBS詳細化レベルの値が1以上の場合、依存先の作業もコンポーネントに対応して詳細化されているため、それらの詳細化された作業と現在処理対象の作業から詳細化された作業同士について、依存関係を新たに詳細化WBS情報109の依存関係定義502に定義する(ステップ904)。取得したWBS詳細化レベルの値が1以上でない場合、現在処理対象の作業から詳細化された作業すべてと依存先の作業に依存関係を、新たに詳細化WBS情報109の依存関係定義502に定義して(ステップ905)、レベル0の詳細化処理部分の処理を終了する。
【0026】
(第2の実施の形態)
次に、プロジェクトの進行中に開発対象となるコンポーネントの構成が変更された場合について、WBS詳細化装置107による変更の反映方法について説明する。すなわち、第2の実施形態は、プロジェクトの進行中にコンポーネントの構成が変更になった場合の例である。
図10は、本発明の第2の実施形態を示すものであって、開発対象となるコンポーネントの構成が変更された場合のコンポーネント構成情報103の管理方法を表した図である。
ここでは、一例として新たにコンポーネントE1001が追加され、コンポーネントB202がコンポーネントE1001に依存し、コンポーネントE1001がコンポーネントA201に依存している。この変更に伴って、コンポーネント構成情報103にレコードを追加する。すなわち、ここでは、コンポーネント名Eに対する依存関係A、コンポーネント名Bに対する依存関係Eが、コンポーネント構成情報として追加されている。
【0027】
図11は、開発対象となるコンポーネントの構成が変更された場合のWBS詳細化処理後の詳細化WBS情報109の管理方法を表した図である。
新たに追加されたコンポーネントE1001に対応する作業1101,1102,1103が追加され、それぞれ他の作業との依存関係216,217,218,219が定義される。なお、図11では、コンポーネントE1001に関連する依存関係のみ記している。
【0028】
図12は、開発対象となるコンポーネントの構成が変更された場合について、WBS詳細化装置107の処理の流れを示すフローチャートである。
まず、最初にコンポーネント構成情報103より、更新された情報を取得する(ステップ1201)。削除されたコンポーネントもしくはその依存関係が存在した場合、詳細化WBS情報109の作業定義501、依存関係定義506より、削除対象に関連するレコードすべてを削除する(ステップ1202)。
【0029】
次に、追加されたコンポーネントもしくはその依存関係が存在した場合、WBS詳細化レベル情報106でWBS詳細化レベル212が1以上に定義されている作業について、追加されたコンポーネントに対応した詳細な作業として、詳細化WBS情報109の作業定義501に定義を追加する(ステップ1203)。次に、更新されたコンポーネントに関連する作業定義401を順に取得し(ステップ1204)、共通WBS管理部104のWBS詳細化レベル情報106からその作業のWBS詳細化レベル212を取得する(ステップ1205)。
【0030】
以降、新規にWBS詳細化処理を実行する場合と同様に、取得したWBS詳細化レベルによって処理が異なり(ステップ1206)、0の場合(ステップ607)、1の場合(ステップ608)、2の場合(ステップ609)のそれぞれの処理を更新された詳細化作業について実行する。更新されたコンポーネントに関連する作業定義401のすべてについて処理が終了すれば(ステップ1207)、WBS詳細化装置107による詳細化WBS情報109の更新処理が終了する。
【0031】
【発明の効果】
以上説明したように、本発明によれば、各プロジェクトが共通化されたWBSを使用し、かつ各プロジェクト固有の詳細な作業を開発対象のコンポーネント構成情報から自動的に生成することで、プロジェクト管理者の管理コストを低減し、作業の詳細化における定義の矛盾や漏れなどの人為的なミスを削滅し、結果として高品質なプロジェクト管理を容易に実現することが可能となる。
【図面の簡単な説明】
【図1】本発明の第1の実施形態を示す工程定義装置の全体の構成図である。
【図2】図1におけるサンプルデータによる工程定義装置の作業工程の詳細化の概要をあらわす図である。
【図3】コンポーネント構成管理部で管理されるコンポーネント構成情報のデータ形式の図である。
【図4】共通WBS管理部で管理される共通WBS情報とWBS詳細化レベル情報のデータ形式の図である。
【図5】WBS管理部で管理される詳細化WBS情報のデータ形式の図である。
【図6】WBS詳細化処理の全体をあらわすフローチャート図である。
【図7】WBS詳細化レベルが0の場合の詳細化処理部分のフローチャート図である。
【図8】WBS詳細化レベルが1の場合の詳細化処理部分のフローチャート図である。
【図9】WBS詳細化レベルが2の場合の詳細化処理部分のフローチャート図である。
【図10】本発明の第2の実施形態を示すもので、コンポーネント構成情報が変更された場合のコンポーネント構成情報のデータ形式の図である。
【図11】図10において、コンポーネント構成情報が変更された場合のWBS詳細化処理後の詳細化WBS情報のデータ形式の図である。
【図12】コンポーネント構成情報が変更された場合のWBS詳細化処理の全体をあらわすフローチャート図である。
【符号の説明】
101:工程定義装置
102:コンポーネント構成管理部
103:コンポーネント構成情報
104:共通WBS管理部
105:共通WBS情報
106:WBS詳細化レベル情報
107:WBS詳細化装置
108:WBS管理部
109:詳細化WBS情報
201,202,203,204,1001:コンポーネント
205,211,216,217,218,219:依存関係
206,207,208,209,210,213,214,215,1101,1102,1103:WBSを構成する作業
212:WBS詳細化レベル
301:コンポーネント名の列
302,406:依存関係の列
401,501:作業定義
402,405,407,503,505:作業名の列
403,504:親作業の列
404,502,506:依存関係定義
408:WBS詳細化レベルの列
1001:追加されたコンポーネント[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method for managing work information of a project and a process definition device in project management.
[0002]
[Prior art]
As an example related to the conventional project management, there is, for example, "Information Management Apparatus and Recording Medium" described in JP-A-2000-215038. This is because the project manager defines the work process to be performed in the project, and associates the work process definition, work progress, deliverables, etc. with the project management by centrally managing the project. This is a system that improves the efficiency of the system.
[0003]
With this device, if a basic process definition is described first, project information can be sequentially generated in a correct order by a plurality of processing means in accordance with the contents of the process definition. Therefore, there is an advantage that no contradiction occurs between project information.
However, in such a system, attempts are generally made to improve the development efficiency by standardizing the work process to be defined by the project manager as an organization, and it is not particularly novel.
[0004]
Another proposal is, for example, a “product development process management system and method, and a recording medium on which the method is recorded” described in JP-A-2001-42915. This is intended to make it possible for a project manager to smoothly carry out the project by providing a means for adding or modifying work in the development process at a necessary stage while the project is in progress.
[0005]
According to this system, since the data of the existing system is only referred to from the outside, the product or product to be developed can be developed without modifying the business support system built and used in the general product development environment. , It is possible to hold the relationship between the attribute data of the parts.
[0006]
[Problems to be solved by the invention]
When the standardized work process is followed, more detailed work to be actually performed in each project varies depending on the configuration of an object (component) to be developed in the project. Therefore, with regard to such detailed work, the project manager needs to add or modify necessary work sequentially. As a result, the project manager needs a management cost for correcting the work process while the project is in progress. It is desirable to reduce this management cost.
[0007]
An object of the present invention is to solve such a problem, to enable a project-specific detailed work item to be automatically defined, reduce the management cost of a project manager, and to contradict or omit the definition of a work process. It is an object of the present invention to provide a project management method and a process definition device capable of realizing highly accurate project management by eliminating mistakes by a project manager.
[0008]
[Means for Solving the Problems]
According to the project management method of the present invention, configuration information to be developed for each project is input to a component configuration management unit, and also to a common WBS (Work Breakdown Structure) management unit. In addition to managing the configuration information of the components, the common WBS management unit defines a work process that can be commonly used, manages a WBS detailing level representing a pattern for detailing each item of the work process, and manages the WBS. The refinement device and the WBS management unit are characterized in that they receive information managed by the two management units, refine the WBS, and manage the WBS.
[0009]
In addition, the process definition device of the present invention uses a component configuration management unit that manages configuration information of a development target (component) using a configuration of a development target of each project as input information, and a work process (WBS) that can be commonly used. And a common WBS management unit that manages a WBS refinement level that represents a pattern that refines each of those items, and a WBS refinement that automatically refines the WBS from information managed by these two management units It is characterized by comprising a device and a WBS management unit for managing the detailed WBS.
[0010]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
(1st Embodiment)
FIG. 1 is a system configuration diagram of a process definition device according to the first embodiment of the present invention.
The
[0011]
FIG. 2 is a diagram showing an example of WBS refinement realized in the system shown in FIG.
In the component
[0012]
Next, in the common WBS
[0013]
The WBS
[0014]
FIGS. 3A and 3B are diagrams illustrating a method of managing the
The information that the component (A) 201, the component (B) 202, the component (C) 203, and the component (D) 204 have the
[0015]
FIGS. 4A and 4B are diagrams illustrating a method of managing the
The common
[0016]
The dependency relationship definition 404 is a table having two columns of a work name 405 and a
[0017]
FIGS. 5A and 5B are diagrams illustrating a method of managing the
The
[0018]
FIG. 6 is a flowchart showing the flow of the entire processing executed by
The
[0019]
It is checked whether the
[0020]
The flow of processing (
FIG. 7 is a flowchart showing details of the processing of
First, it is checked whether or not a dependency definition exists from the dependency definition 404 of the
[0021]
If the value of the obtained WBS detail level is 1 or more, the dependent work is also refined corresponding to the component, and thus the dependency relationship between all the refined work and the currently processed work Is newly defined in the
[0022]
FIG. 8 is a flowchart showing details of the processing of
First, it is checked whether a dependency definition exists from the dependency definition 404 of the
[0023]
If the value of the acquired WBS detail level is 1 or more, the dependent work is also refined corresponding to the component, so the refined work from those refined work and the work currently being processed The dependency is newly defined in the
[0024]
FIG. 9 is a flowchart showing details of the processing of
First, the same dependency as the dependency defined in the
[0025]
If there is a dependency, the
[0026]
(Second embodiment)
Next, a method of reflecting the change by the
FIG. 10 illustrates the second embodiment of the present invention, and illustrates a method of managing the
Here, as an example, the component E1001 is newly added, the component B202 depends on the component E1001, and the component E1001 depends on the component A201. Along with this change, a record is added to the
[0027]
FIG. 11 is a diagram illustrating a management method of the
[0028]
FIG. 12 is a flowchart showing the flow of processing of the
First, updated information is obtained from the component configuration information 103 (step 1201). If the deleted component or its dependency exists, all records related to the deletion target are deleted from the
[0029]
Next, when the added component or its dependency exists, the work in which the
[0030]
Thereafter, as in the case of newly executing the WBS detailing process, the process differs depending on the acquired WBS detailing level (step 1206), 0 (step 607), 1 (step 608), 2 Each process of (Step 609) is executed for the updated detailed work. When the process is completed for all the
[0031]
【The invention's effect】
As described above, according to the present invention, project management is performed by using a common WBS for each project and automatically generating detailed work unique to each project from component configuration information of a development target. This reduces human management costs and eliminates human errors such as inconsistencies and omissions in definition in detailed work, and as a result, high-quality project management can be easily realized.
[Brief description of the drawings]
FIG. 1 is an overall configuration diagram of a process definition device according to a first embodiment of the present invention.
FIG. 2 is a diagram showing an outline of detailing a work process of a process definition device based on sample data in FIG. 1;
FIG. 3 is a diagram illustrating a data format of component configuration information managed by a component configuration management unit.
FIG. 4 is a diagram illustrating a data format of common WBS information and WBS detail level information managed by a common WBS management unit.
FIG. 5 is a diagram illustrating a data format of detailed WBS information managed by a WBS management unit;
FIG. 6 is a flowchart showing the whole WBS detailing process.
FIG. 7 is a flowchart of a detailing processing portion when the WBS detailing level is 0;
FIG. 8 is a flowchart of a detailing process portion when the WBS detail level is 1.
FIG. 9 is a flowchart of a detailing process portion when the WBS detailing level is 2.
FIG. 10 is a diagram illustrating a data format of component configuration information when component configuration information is changed according to the second embodiment of this invention.
FIG. 11 is a diagram showing a data format of the refined WBS information after the WBS refinement processing in a case where component configuration information is changed in FIG.
FIG. 12 is a flowchart showing the whole WBS detailing process when the component configuration information is changed.
[Explanation of symbols]
101: process definition device 102: component configuration management unit 103: component configuration information 104: common WBS management unit 105: common WBS information 106: WBS detail level information 107: WBS detail device 108: WBS management unit 109:
Claims (5)
該コンポーネント構成管理部は、開発対象であるコンポーネントの構成情報を管理し、
該共通作業工程管理部は、共通して利用可能な作業工程を定義し、かつ該作業工程の各項目を詳細化するパターンを表す作業工程の詳細化レベルを管理し、
作業工程詳細化装置は、上記2つの管理部で管理されている情報を受けて作業工程を詳細化し、
作業工程管理部は、上記作業工程詳細化装置で詳細化された作業工程を管理することを特徴とするプロジェクト管理方法。Input the configuration information to be developed for each project to the component configuration management section and also to the common work process management section,
The component configuration management unit manages configuration information of a component to be developed,
The common work process management unit defines work processes that can be used in common, and manages a detail level of a work process that represents a pattern that details each item of the work process,
The work process detailing device receives the information managed by the above two management units, details the work process,
A project management method, wherein a work process management unit manages work processes detailed by the work process detailing device.
共通して利用可能な作業工程の定義、および該作業工程の各項目を詳細化するパターンをあらわす作業工程詳細化レベルを管理する共通作業工程管理部と、
これら2つの管理部で管理された情報から、自動的に作業工程を詳細化する作業工程詳細化装置と、
該作業工程詳細化装置により詳細化された作業工程を管理する作業工程管理部を備えることを特徴とする工程定義装置。A component configuration management unit that manages the configuration information of the development target using the configuration of the development target of each project as input information;
A common work process management unit that manages a definition of a work process that can be used in common, and a work process detailing level that represents a pattern for detailing each item of the work process;
A work process detailing device for automatically detailing work processes from information managed by these two management units;
A process definition device comprising: a work process management unit that manages a work process refined by the work process refinement device.
作業工程詳細化レベル情報で作業工程詳細化レベルが定義されている作業について、追加されたコンポーネントに対応した詳細な作業として、詳細化作業工程情報の作業定義に該当する定義を追加し、次に、更新されたコンポーネントに関連する作業定義を順に取得し、共通作業工程管理部の作業工程詳細化レベル情報からその作業の作業工程詳細化レベルを取得することを特徴とする請求項1記載のプロジェクト管理方法。During the progress of the project, if the configuration of the component to be developed is changed, obtain updated information, and if there is a deleted component or its dependency, the work definition of the detailed work process information, Delete all records related to the deletion target from the dependency definition,
For the work for which the work process refinement level is defined in the work process refinement level information, add a definition corresponding to the work definition of the refined work process information as a detailed work corresponding to the added component, and then 2. The project according to claim 1, wherein a work definition related to the updated component is obtained in order, and a work process detail level of the work is obtained from work process detail level information of the common work process management unit. Management method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002268052A JP2004110102A (en) | 2002-09-13 | 2002-09-13 | Project management method and process definition device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002268052A JP2004110102A (en) | 2002-09-13 | 2002-09-13 | Project management method and process definition device |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004110102A true JP2004110102A (en) | 2004-04-08 |
Family
ID=32266381
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002268052A Pending JP2004110102A (en) | 2002-09-13 | 2002-09-13 | Project management method and process definition device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004110102A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006277745A (en) * | 2005-03-25 | 2006-10-12 | Microsoft Corp | Work item rule for work item tracking system |
JP2009176010A (en) * | 2008-01-24 | 2009-08-06 | Internatl Business Mach Corp <Ibm> | System for performing process management, process management method and program |
JP2014123249A (en) * | 2012-12-21 | 2014-07-03 | International Business Maschines Corporation | Information processor, program, and information processing method |
-
2002
- 2002-09-13 JP JP2002268052A patent/JP2004110102A/en active Pending
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006277745A (en) * | 2005-03-25 | 2006-10-12 | Microsoft Corp | Work item rule for work item tracking system |
US8554599B2 (en) | 2005-03-25 | 2013-10-08 | Microsoft Corporation | Work item rules for a work item tracking system |
JP2009176010A (en) * | 2008-01-24 | 2009-08-06 | Internatl Business Mach Corp <Ibm> | System for performing process management, process management method and program |
US8655696B2 (en) | 2008-01-24 | 2014-02-18 | International Business Machines Corporation | System for performing schedule management, schedule management method and program |
JP2014123249A (en) * | 2012-12-21 | 2014-07-03 | International Business Maschines Corporation | Information processor, program, and information processing method |
US9891911B2 (en) | 2012-12-21 | 2018-02-13 | International Business Machines Corporation | Software development work item management system |
US10768928B2 (en) | 2012-12-21 | 2020-09-08 | International Business Machines Corporation | Software development work item management system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10558642B2 (en) | Mechanism for deprecating object oriented data | |
US7509327B2 (en) | Business data migration using metadata | |
US20030105843A1 (en) | Input/output device information management system for multi-computer system | |
US7971178B1 (en) | System to merge custom and synthesized digital integrated circuit design data | |
US20060150178A1 (en) | Method and system for updating application design | |
US7665014B2 (en) | Method and apparatus for generating forms using form types | |
US20140040791A1 (en) | Development platform for software as a service (saas) in a multi-tenant environment | |
JP2004280829A (en) | Customization of metadata describing object in computing environment | |
US11693873B2 (en) | Systems and methods for using entity/relationship model data to enhance user interface engine | |
US20110126171A1 (en) | Dynamic native editor code view facade | |
US7296038B2 (en) | Context resolution | |
JP3577400B2 (en) | System design equipment and data warehouse design system | |
US20120005645A1 (en) | Metaobject enhancement objects | |
JP3186117B2 (en) | Automatic program generation system using data-centric software components | |
US20070136325A1 (en) | Database schema for content managed data | |
JP2013020437A (en) | Requirements management support device | |
US20080155495A1 (en) | Methods and apparatus for modeling a workflow process in an offline environment | |
US20060069679A1 (en) | System for creating associative records | |
US20110218979A1 (en) | Document revision control | |
JP2004110102A (en) | Project management method and process definition device | |
JP2004272911A (en) | Customization of field in object in computing environment | |
KR100337373B1 (en) | A method for Managing Design Information in CAD system | |
US20210294966A1 (en) | Systems and methods for binding lookup controls | |
US20080270985A1 (en) | Database application assembly and preparation | |
KR100428710B1 (en) | A modeling system and method by modeling-object assembling |