JP2004027544A - Joint part of press-in shaft - Google Patents
Joint part of press-in shaft Download PDFInfo
- Publication number
- JP2004027544A JP2004027544A JP2002182771A JP2002182771A JP2004027544A JP 2004027544 A JP2004027544 A JP 2004027544A JP 2002182771 A JP2002182771 A JP 2002182771A JP 2002182771 A JP2002182771 A JP 2002182771A JP 2004027544 A JP2004027544 A JP 2004027544A
- Authority
- JP
- Japan
- Prior art keywords
- shaft
- block
- collar
- shaft block
- blocks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、立坑や管渠を推進工法により構築するのに好適なマンホール構築用を兼ねた立坑ブロックを使用した圧入立坑において、前記立坑ブロックを接続する継手部に関する。さらに詳しくは、互いに接続する立坑ブロックをそれらの端部において接続し、互いに固定し、回転トルクを伝達する継手部に関する。
【0002】
【従来の技術】
上下水道用の管渠やその他各種の配管を地中に敷設するに当たり、地面を開削せずに非開削で施工する方法として、推進工法が用いられている。この推進工法は、地面の適当な個所に立坑を構築し、この立坑を起点または中間点として推進管を推進するものである。
【0003】
従来、このような推進工法を施工するための立坑は、鋼矢板等の仮設土留め材を使用して周囲を土留めしながら、地盤を縦方向に掘削することにより構築されていた。そして、推進管の推進工事を完了した後は、この立坑にマンホールを施工していた。例えば、立坑の底部に基礎を施した後、その上にマンホールブロックを設置し、これに前記推進管を接続すると共に、マンホールブロックの底部に底盤(インバート)を施工し、その後マンホールの周囲の土砂を埋め戻す等の工事が行われていた。
【0004】
近年、都市部では比較的小口径の管渠を推進工法により施工する工事が多くなっているが、前述のような工事では、立坑を掘削する工事が大がかりとなり、その立坑を掘削するための開削面積も大きい。また、別途マンホールを施工し、その周囲の立坑を埋め戻さなければならないため、立坑施工からマンホール施工までの全体としての工事の手数、期間がかかるという欠点がある。
【0005】
そこで例えば、特開平6−117176号公報に示されたように、円筒形のコンクリートからなる立坑ブロックを使用し、これを地面に縦に押し込んで圧入すると共に、その内部の土砂を排除しなから立坑を構築し、その後、立坑ブロックの周壁に開設した推進管発進口となる坑口から推進管を地中に推進し、敷設する施工技術とそれに使用される立坑ブロックが提案されている。推進管の敷設の後は、立坑ブロックをそのままマンホールの周壁を形成するブロックとして使用し、マンホールを構築する。すなわち水路工事中は立坑となり、その後はマンホールとなる立坑兼用のマンホールである。
【0006】
この施工方法では、立坑ブロックの周面に予め推進管を発進する穴や隣接する立坑から推進されてくる推進管を受け入れる穴、いわゆる坑口を穿孔しておき、これを塞いだ状態で立坑ブロックを地中に圧入し、立坑完成後に坑口を開く。或いは立坑ブロックの圧入により、立坑が出来上がった後コアドリル等で坑口を現場で穿孔する。そしてその後、坑口から推進管を地中に圧入し、推進を行う。推進管の推進を完了した後、立坑ブロックを使用してマンホールを施工すると共に、立坑ブロックの坑口に推進管の端部をモルタル等で固定し、接続を完了する。
【0007】
このような工事において、立坑を構築する場合は、円筒形の鉄筋コンクリートからなる立坑ブロックを地面から縦に圧入し、地面を縦に掘り進むと共に、その中の土砂を排除しながら立坑ブロックを地中に埋め込んでいく。そのために立坑ブロックの下端縁から先に鋸歯状の刃先を有する鋼管等からなる推進刃を取り付け、立坑ブロックの中心軸を垂直にした状態で、同立坑ブロックをその中心軸の周りに回転しながら、前記の推進刃で地中を掘り進んでいく。そして、立坑ブロックの上に別の立坑ブロックを強固に継ぎ合わせながらそれらの推進を続け、所要の深さの立坑を構築する。
【0008】
比較的浅い立坑を構築する場合は、立坑ブロックが1つだけ使用されることもあるが、殆どの場合、2つ以上の立坑ブロックを接続して使用する。そのため接続する立坑ブロックの上端と立坑ブロックの下端に断面L字形の鋼製のリング状の継手を取り付けておく。より具体的には、前記の継手をアンカー鉄筋の一部に溶接した状態で立坑ブロックを遠心成型する型枠の中に配置し、この状態で立坑ブロックを遠心成型することにより、継手を立坑ブロック端部の周面と端面にわたって埋め込む。そしてこれらの立坑ブロックを接続するに当たっては、上側の立坑ブロックの下端面と下側の立坑ブロックの上端面とを突き当た状態で継手を重ね合わせ、その状態で全周にわたって溶接により互いに固定され、2つの立坑ブロックが互いに接続される。
【0009】
【発明が解決しようとしている課題】
しかしながら、前述のようにして継手を溶接して立坑ブロックを接続する場合、現場に溶接機材を持ち込んで溶接しなければならず、また溶接の技能を身につけた溶接技能者の存在が不可欠となる。また、いかに溶接技能に優れた溶接技能者であっても、垂直に立てた状態で端部を突き合わせた立坑ブロックの継ぎ目を横に向かって円周方向に溶接していかなければならず、溶接に手数と時間がかかる。例えば、外径1164〜2560mmの立坑ブロックの場合、2人の溶接技能者で溶接しても20〜60分程かかる。
【0010】
本発明は、このような従来の立坑ブロックを接続する継手部における課題に鑑み、溶接機材や溶接技能の存在無しに、しかも短時間で現場で立坑ブロックを接続することが出来、さらに回転圧入時のトルクを伝達する。立坑ブロックの継手部を提供することを目的とする。
【0011】
【課題を解決するための手段】
本発明では、前記の目的を達成するため、立坑ブロック2、3の端部に設けた凹状の接続片嵌合部19とそれに嵌まり込む接続片17、17’とにより、立坑ブロック2、3の端部でそれらの回り止めをすると共に、前記接続片17、17’を立坑ブロック2、3の端部にボルト20とナット21とで固定することが出来るようにした。これにより、接続片嵌合部19への接続片17、17’の嵌め込み及びボルト20とナット21とのねじ込みと締め付け作業によって立坑ブロック2、3の接続を可能とした。
【0012】
すなわち、本発明による推進立坑の継手部は、立坑ブロック2、3を地面の中に圧入し、且つその内部の土砂を排除して立坑1を構築する推進立坑の前記立坑ブロック2、3を接続するものであって、接続する一方の立坑ブロック2の端部外周に円筒リング状のカラー14を嵌め込んで固定し、このカラー14から接続片17を突設している。また、この立坑ブロック2の端部に接続すべき他方の立坑ブロック3の端部外周にも円筒リング状のカラー15を嵌め込んで固定するが、このカラー15には凹状の接続片嵌合部19を設けておく。前記立坑ブロック2、3の接続すべき端部を互いに突き合わせた状態で、一方の立坑ブロック2のカラー14から突設された接続片17を前記他の立坑ブロック3のカラー15の接続片嵌合部19に嵌め込み、且つこの接続片17をボルト20とナット21によりその接続片嵌合部19の部分で立坑ブロック3の端部に固定する。これにより立坑ブロックを互いに接続するものである。
【0013】
このような推進立坑の継手では、一方の立坑ブロック2の端部に設けた突状の接続片17が他方の立坑ブロック3の端部に設けた接続片嵌合部19に嵌合することで接続されているため、双方の立坑ブロック2、3は互いに回り止めされた状態で接続される。また接続片17が接続片嵌合部19の部分において他方の立坑ブロック2、3の端部にボルト20とナット21により固定されるため、双方の立坑ブロック2、3の端部が完全に固定される。
【0014】
前記の推進立坑の継手部では、接続片14を突片状として一方の立坑ブロック2の端部に固定したカラー14から突設している。これに対し、接続片14を双方の立坑ブロック2、3の端部に固定したカラー14、15とは別体とする形態もある。この場合は、互いに接続すべき双方の立坑ブロック2、3の端部外周に嵌め込んで固定したカラー14、15にそれぞれ凹状の接続片嵌合部19、19を設け、前記立坑ブロック2、3の接続すべき端部を互いに突き合わせた状態で、カラー14、15に設けた接続片嵌合部19、19を位置合わせする。そして、それら双方の接続片嵌合部19、19にわたって前記の接続片17’を嵌め込み、且つこの接続片17’をボルト20とナット21によりその接続片嵌合部19、19の部分で立坑ブロック2、3の端部に固定する。
【0015】
この場合もまた、接続片17’が双方の立坑ブロック2、3の端部に設けた接続片嵌合部19、19にわたって嵌合することで、双方の立坑ブロック3、4は互いに回り止めされた状態で接続される。また接続片17’が双方の立坑ブロック2、3の接続片嵌合部19の部分においてそれぞれの立坑ブロック2、3の端部にボルト20とナット21により固定されるため、双方の立坑ブロック2、3の端部が完全に固定される。
【0016】
なお、ボルト20とナット21の何れか一方を、カラー14、15の接続片嵌合部19、19においてコンクリート躯体に埋め込まれたアンカーボルト20またはアンカーナット21とすると、ボルト20やナット21が立坑ブロック2、3の内周面側に突出せず、またそれらのねじ込みや締め付けもしやすい。好ましくはナット21をアンカーナット21とするのがよい。
【0017】
【発明の実施の形態】
次に、図面を参照しながら、本発明の実施の形態について、具体的且つ詳細に説明する。
図3は、立坑1を構築するための立坑ブロック2、3を示しており、2つの円筒状の立坑ブロック2、3を接続した状態である。この立坑ブロック2は、例えば遠心成型されたコンクリートの円筒状の管体からなる。
【0018】
下側の立坑ブロック2の周壁の所定の位置に、後述する推進管13を推進し、或いは隣接する別の立坑1から推進された推進管13を受け入れるための坑口9が穿孔されている。この坑口9は、立坑ブロック2の周壁を同立坑ブロック2の径方向に穿孔して形成したものである。この坑口9は、工場において立坑ブロック2を成型した後、削孔機等を使用して穿孔されるか、或いは予め型枠内に後述する坑口リング10を配置し、立坑ブロック2の成型時に坑口9を同時成型する。
【0019】
この坑口9は、立坑ブロック2の周壁に1個所だけ穿孔されることもあるが、マンホールに接続される推進管13の数に応じて同じ高さ或いは高さを変えて2個所或いはそれ以上の個所に穿孔されることが多い。図1と図3に示した立坑ブロック2の例では、立坑ブロック2の径方向に90゜の角度で周壁の同じ高さに2個所の坑口9が穿孔されている。坑口9には、パッキング等のシール材を取り付けたり、或いは推進管13を推進する前に坑口9を塞いでおく蓋を固定するための坑口リング10が嵌め込まれている。
【0020】
なお、この坑口リング10には、管挿入孔11が穿孔されている。この管挿入孔11は、立坑1を構築したとき、その外側の坑口9付近の地盤を改良するための薬液を注入する注入管(図示せず)を挿入するためのものである。
下側の立坑ブロック2の下端部からは、継手等を介して固定された推進刃5が延設されている。この推進刃5は円筒状の鋼製のもので、その外径は、前記立坑ブロック2の外径よりやや大きい。この推進刃5の下端縁には、鋸歯状の掘削刃14が形成されている。
【0021】
比較的浅い立坑1及びマンホールを構築する場合は、立坑ブロック2が1つだけ使用されることもあるが、殆どの場合、立坑ブロック2の1つ分の高さより深い立坑1及びマンホールを構築する場合が多い。このような場合は図1に示すように、2つ以上の立坑ブロック2、3をその端部の継手7により接続して使用する。
【0022】
この継手7の構成について図3〜図4により説明すると、接続する立坑ブロック2の上端外周と立坑ブロック3の下端外周には、円筒鋼製のリング状のカラー14、15をそれぞれ埋め込んで取り付ける。これらのカラー14、15は、立坑ブロック2、3を遠心成型する型枠の中に配置されたアンカー鉄筋16の端部に溶接された状態で型枠内に配置され、この状態で立坑ブロック2、3が遠心成型される。これにより、カラー14、15は、立坑ブロック2、3の端部の外周面に埋め込まれた状態で取り付けられる。この状態では、カラー14、15の外周面は、立坑ブロック2、3の端部の外周面とほぼ面一となる。
【0023】
一方の立坑ブロック2の上端のカラー14からは、立坑ブロック2の端面より上に突出させて接続片17が一体に突設されている。図示の例では、カラー14の円周方向に90゜間隔で4つの接続片17が突設されているが、立坑ブロック2の径が大きい場合は、4つ以上の接続片17を突設することもある。この接続片17は、横に長い矩形で、両側に45゜の面取を施した突片状のものである。この接続片17には横に並んで二つのねじ孔が設けられている。なお、図4には図示ていないが、上側の立坑ブロック3の上にさらに他の立坑ブロックを接続する場合、上側の立坑ブロック3の上端側も、前述した下側の立坑ブロック2の上端と同じ構造にする。
【0024】
他方、立坑ブロック3の下端のカラー15の下辺側には、前記接続片17の位置と形状とに対応して接続片嵌合部19が設けられている。従って図示の例では、カラー15の円周方向に90゜間隔で4つの接続片嵌合部19が設けられている。接続片17の配置や数が異なれば、それに対応して接続片嵌合部19の配置や数も異なることは言うまでもない。
この接続片嵌合部19は、接続片17の形状に対応しておりは、横に長い矩形で、両側に45゜の面取を施した凹欠状のものであり、ここに接続片17が遊びが小さい状態で嵌め込むことが出来る。
【0025】
この接続片嵌合部19の奥側を塞ぐように、カラー15の内周に鋼製の板片からなるアンカー固定片18が溶接され、このアンカー固定片18には前記接続片17のねじ孔に対応して横に並んで二つのねじ孔が設けられている。さらこのねじ孔に位置合わせされた状態で、その内周側にそれぞれアンカーナット21が溶接されている。前述のようにして立坑ブロック3を成型する段階で、これらのアンカー固定片18とアンカーナット21は、立坑ブロック3を成型するための型枠の内側に配置され、成型された立坑ブロック3のコンクリート躯体の中に埋め込まれる。なお、図4には図示ていないが、上側立坑ブロック3の上にさらに別の立坑ブロックを接続する場合、その立坑ブロックの下端側も、前述した立坑ブロック3の下端と同じ構造とする。
【0026】
次に前記の継手7による立坑ブロック2、3の接続工程も含めて、立坑1と推進管により水路を構築する施工方法について説明すると、まず、立坑ブロック2を地面に圧入して推進し、立坑1を構築する。舗装面に立坑1を掘削する場合は、まず舗装を切断し、撤去し、路面から1.5m程の深さまで試掘する。マンホールを設置する平面位置を芯出しするため測量し、その芯出した位置を基準として立坑を推進するための立坑推進機を設置する。
【0027】
立坑ブロック2は、通常の場合、予め推進刃5が取り付けられない状態で現場に搬入され、図3に示すように、推進刃5が工事現場で取り付けられる。また、坑口9は、前記の管挿入孔11を含めて予め鋼板等で閉じておく。
このようにして推進刃5を取り付けた立坑ブロック2を前記立坑圧入機に取り付け、立坑ブロック2をその中心軸の周りに旋回或いは反転旋回させながら地面に垂直に圧入する。これと同時に、立坑ブロック2内の土砂を排出する。
【0028】
こうして立坑ブロック2を圧入し、推進した後、立坑1の深さに応じて別の立坑ブロック3を接続する。まず、上の立坑ブロック3をクレーン等で吊り上げ、既に土中に垂直に圧入した下側の立坑ブロック2の上に移動させる。そのまま上側の立坑ブロック3を下降させ、図3に示すように、その下端部のカラー15の接続片嵌合部19と下側の立坑ブロック2の上端部のカラー14の接続片14との位置を合わせる。さらに立坑ブロック3を下降させ、4つの接続片14を接続片嵌合部19に同時に嵌合する。その後、接続片14の外側からそのねじ孔にボルト20を通し、図4(B)に示すようにこのボルト20をアンカー固定片18に溶接したアンカーナット21にねじ込み、締め付ける。これを4箇所の継手7の全てに行うことにより、立坑ブロック2の上に立坑ブロック3が接続され、固定される。
【0029】
この状態でさらに接合した立坑ブロック2、3を、その中心軸の周りに旋回或いは反転旋回させながら地面に垂直に圧入する。これと同時に、立坑ブロック2、3内の土砂を排出する。
立坑ブロック3の上にさらに別の立坑ブロックを接続する場合は、前述と同様にして接続する。
【0030】
図1と図6に示すように、所定の深さまで掘削し、立坑1を構築した後は、マンホールの底壁となるべき部分、すなわち立坑ブロック2の下端内周面に囲まれた部分に、生コンクリートを打ち込み、表面を仕上げて、底盤6を成型する。この状態では図1や図6に示すような蓋8を閉めることが出来る斜壁である上部立坑ブロック4は設置しておらず、その代わりに上側の立坑ブロック3の上端部に円筒鋼板等からなる架設ケーシング(図示せず)が取り付けられている。
【0031】
次に、図1に仮装線で示したように、前記の立坑ブロック2の坑口9を開き、そこから推進管13を推進する。このとき、坑口9付近の地盤が水分を多く含むため、軟弱であるときは、坑口9を開いた途端に土砂が坑口9から立坑1内に流入してしまう。
【0032】
このような状態のときは、坑口9を開く前に、坑口9付近の地盤に薬液を注入し、水分を含む地盤が凝固して水分が出ないように改良する。
【0033】
地上から立坑1を通してその坑口9側に推進管13を導入し、この推進管13を坑口9から立坑1の外に押し出す。さらに、地上から立坑1の中に次の推進管13を導入し、これを立坑1の中で順次継ぎ合わせながら、押し出す。これにより、推進管13を立坑1の坑口9から地山に圧入する。このとき、立坑1内に設置した図示してない推進ジャッキにより、立坑1の壁面で反力を取りながら推進管13を推進していく。推進管13の推進と同時にその中の土砂を排除し、立坑1から地上に排出する。
【0034】
地山に推進した推進管13は、隣接する他の立坑1の坑口から受け入れ、立坑1、1の間が推進管13で接続される。この状態を図6に示す。これにより、一対の立坑1、1の間で推進が完了する。その後、推進管13と坑口9との間をシールする。
【0035】
次に、図1と図6に示すようにして、立坑ブロック3の上に、一部にテーパを有する上部立坑ブロック4、いわゆる斜壁を接続し、固定する。この上部立坑ブロック4は回転して推進しないので、前述のように立坑ブロック2と立坑ブロック3とを接続したのと異なる適宜の手段により接続することが出来る。前述のように立坑ブロック2と立坑ブロック3とを接続したのと同様にして接続するときは、この立坑ブロック4の下端にも、前述した立坑ブロック3の下端と同じように、接続片嵌合部19を有するカラー15を設ける。
【0036】
この上部立坑ブロック4は、その上部に金属製リング状の蓋受け金具14が埋め込まれた状態で成型されており、ここに金属製、コンクリート製或いは強化プラスチック製等の蓋8が嵌め込まれる。立坑ブロック2、3は、この蓋29の上面が地面GLと面一になるようの埋設される。
【0037】
図5は、前記と異なる推進立坑の継手部の形態を示すものである。図4により前述した推進立坑の継手部では、接続片14を突片状として一方の立坑ブロック2の上端部に固定したカラー14から一体に突設している。これに対し、図5に示した実施形態では、接続片17’を双方の立坑ブロック2、3の端部に固定したカラー14、15とは別体とする一方で、双方の立坑ブロック2、3のカラー14、15にそれぞれ凹状の接続片嵌合部19、19を設けている。
【0038】
接続片嵌合部19、19の形状やその部分に固定したアンカー固定片18とアンカーナット21等の構造は、前述した上側の立坑ブロック3の下端に設けたカラー15の接続片嵌合部19と同様である。但し、下側で突き合わせられるカラー14の接続片嵌合部19は、上側で突き合わせられるカラー15の接続片嵌合部19と向きが上下逆で、上側に開いている。
【0039】
既に述べた通り、接続片17’は、固定したカラー14、15とは別体である。この接続片17’は、前記カラー14、15の接続片嵌合部19、19を上下に突き合わせた状態の形状と対応しており、角部を45゜に面取りした正方形または矩形である。また、上下に2個ずつのねじ孔が設けられている。
【0040】
この例では、下の立坑ブロック2に上に上側の立坑ブロック3を接続するとき、上下の立坑ブロック2、3の接続すべき端部を互いに突き合わせた状態で、カラー14、15に設けた接続片嵌合部19、19が正対するように位置合わせして付き合わせる。そして、それら双方の接続片嵌合部19、19を突き合わせことにより形成された四角形の凹部にそれら接続片嵌合部19、19の双方にわたって前記の接続片17’を嵌め込む。さらに図5(B)に示すように、接続片17’のねじ孔からボルト20を差し込み、これをアンカー固定片18、18に溶接したアンカーナット21、21にねじ込み、締め付ける。これを4箇所の継手7の全てに行うことにより、立坑ブロック2の上に立坑ブロック3が接続され、固定される。
【0041】
【発明の効果】
以上説明した通り、本発明によれば、溶接によらず接続片14と接続片嵌合部19との嵌合及びボルト20とナット21のねじ込みと締め付けだけで立坑ブロック2、3の接続が行えるので、溶接機材や溶接技能者が不要になると共に、簡単で短時間に立坑ブロック2、3の接続が行える。これにより、工事の効率化と工期の短縮が図れる。
【図面の簡単な説明】
【図1】本発明による立坑ブロックと推進刃を使用して立坑を推進、構築する状態を示す縦断側面図である。
【図2】同立坑ブロックと推進刃を使用して立坑を推進、構築する状態を示す横断平面図である。
【図3】本発明による立坑ブロックを接続するときのそれらの状態の例を示す半断面斜視図である。
【図4】本発明による立坑ブロックを接続する継手部を示す要部側面図とそのA−A部拡大断面図である。
【図5】本発明による立坑ブロックを接続する継手部の他の実施形態を示す要部側面図とそのB−B部拡大断面図である。
【図6】本発明による立坑ブロックにより水路とマンホールを構築した例を示す縦断側面断面図である。
【符号の説明】
1 立坑
2 立坑ブロック
3 立坑ブロック
14 カラー
15 カラー
17 接続片
19 接続片嵌合部
20 ボルト
21 ナット[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a joint for connecting a vertical shaft block in a press-fitting vertical shaft using a vertical shaft block also serving as a manhole suitable for constructing a vertical shaft or a sewer by a propulsion method. More particularly, the present invention relates to a joint for connecting shaft shafts to be connected to each other at their ends, fixing each other, and transmitting rotational torque.
[0002]
[Prior art]
2. Description of the Related Art When laying pipes for water supply and sewerage and other various pipes underground, a propulsion method is used as a method of constructing the ground without excavating the ground without excavating the ground. In this propulsion method, a shaft is constructed at an appropriate place on the ground, and the propulsion pipe is propelled from the shaft as a starting point or an intermediate point.
[0003]
Conventionally, shafts for constructing such a propulsion method have been constructed by excavating the ground in the vertical direction while retaining the surrounding area using temporary earth retaining materials such as steel sheet piles. After the completion of the propulsion pipe propulsion work, a manhole was being constructed in this shaft. For example, after laying a foundation on the bottom of a shaft, a manhole block is installed on it, and the propulsion pipe is connected to the manhole block, and a bottom plate (invert) is constructed on the bottom of the manhole block. Construction such as backfilling was performed.
[0004]
In recent years, the construction of relatively small-diameter sewers by the propulsion method has been increasing in urban areas.However, in the above-mentioned construction, excavation of shafts has become extensive, and excavation to excavate the shaft The area is also large. In addition, since a manhole must be separately constructed and the shaft around the manhole must be backfilled, there is a disadvantage in that it takes time and effort to perform the entire construction from the construction of the shaft to the construction of the manhole.
[0005]
Therefore, for example, as shown in Japanese Patent Application Laid-Open No. 6-117176, a vertical shaft block made of cylindrical concrete is used, and is vertically pushed into the ground and pressed into the ground, and the sediment inside is removed. Construction techniques for constructing a shaft, then propelling the propulsion pipe into the ground from a tunnel opening at the peripheral wall of the shaft and serving as a launching port for the propulsion pipe, and laying the shaft, and a shaft block used for the construction technique have been proposed. After the installation of the propulsion pipe, the manhole is constructed by using the shaft block as it is as a block forming the peripheral wall of the manhole. In other words, the shaft becomes a shaft during the construction of the canal, and then becomes a manhole.
[0006]
In this construction method, a hole for starting a propulsion pipe or a hole for receiving a propulsion pipe propelled from an adjacent shaft, a so-called wellhead is drilled in advance on the peripheral surface of the shaft block, and the shaft block is Press into the ground and open the pit after the shaft is completed. Alternatively, after the shaft has been completed by press-fitting the shaft block, a pit is drilled on site with a core drill or the like. After that, the propulsion pipe is pressed into the ground from the wellhead and propelled. After the propulsion of the propulsion pipe is completed, the manhole is constructed using the shaft block, and the end of the propulsion pipe is fixed to the entrance of the shaft block with mortar or the like, and the connection is completed.
[0007]
In such construction, when constructing a shaft, a shaft block made of cylindrical reinforced concrete is pressed vertically from the ground, digging the ground vertically, and removing the earth and sand inside the shaft while placing the shaft in the ground. Embed. For this purpose, a propulsion blade made of a steel pipe or the like having a serrated cutting edge is attached to the lower end edge of the shaft block, and while the center axis of the shaft block is vertical, the shaft is rotated around the center axis. Digging underground with the aforementioned propulsion blade. Then, while continuing to propel another shaft shaft while firmly splicing it on the shaft block, a shaft with a required depth is constructed.
[0008]
When constructing a relatively shallow shaft, only one shaft block may be used, but in most cases two or more shaft blocks are connected and used. Therefore, a steel ring-shaped joint having an L-shaped cross section is attached to the upper end of the shaft block and the lower end of the shaft block to be connected. More specifically, the joint is welded to a part of the anchor rebar, and the shaft is placed in a mold for centrifugally molding the shaft, and the shaft is centrifugally molded in this state, whereby the joint is connected to the shaft. Embed over the peripheral surface and the end surface of the end. In connecting these shaft blocks, the joints are overlapped in a state where the lower end surface of the upper shaft block and the upper end surface of the lower shaft block are abutted, and are fixed to each other by welding over the entire circumference in this state. The two shaft blocks are connected to each other.
[0009]
[Problems to be solved by the invention]
However, when connecting a shaft block by welding joints as described above, welding equipment must be brought to the site to perform welding, and the presence of welding technicians who have acquired welding skills is indispensable. . Also, no matter how good the welding skill is, even the welding technician must weld the seam of the shaft block whose ends are abutted vertically in the circumferential direction to the side. It takes time and effort. For example, in the case of a shaft block having an outer diameter of 1164 to 2560 mm, it takes about 20 to 60 minutes even if welding is performed by two welding technicians.
[0010]
The present invention has been made in view of the above-mentioned problems in the joint portion for connecting the shaft shaft, and it is possible to connect the shaft block on-site in a short time without the use of welding equipment and welding skills, and furthermore, when rotating press-fitting, Of torque. An object of the present invention is to provide a joint portion of a shaft block.
[0011]
[Means for Solving the Problems]
In the present invention, in order to achieve the above object, the vertical shaft blocks 2 and 3 are formed by the concave connection piece
[0012]
That is, the joint portion of the propulsion shaft according to the present invention connects the shaft blocks 2 and 3 of the propulsion shaft for press-fitting the shaft blocks 2 and 3 into the ground and removing the sediment therein to construct the shaft 1. A cylindrical ring-shaped
[0013]
In such a joint of the propulsion shaft, the protruding
[0014]
In the joint portion of the above-described propelling shaft, the connecting
[0015]
Also in this case, since the connecting piece 17 'is fitted over the connecting piece
[0016]
When one of the
[0017]
BEST MODE FOR CARRYING OUT THE INVENTION
Next, embodiments of the present invention will be described specifically and in detail with reference to the drawings.
FIG. 3 shows the shaft blocks 2 and 3 for constructing the shaft 1, in a state where the two cylindrical shaft blocks 2 and 3 are connected. The
[0018]
At a predetermined position on the peripheral wall of the
[0019]
The
[0020]
The
A propulsion blade 5 fixed via a joint or the like extends from a lower end of the
[0021]
When building a relatively shallow shaft 1 and manhole, only one
[0022]
The configuration of the joint 7 will be described with reference to FIGS. 3 and 4. Ring-shaped
[0023]
From the
[0024]
On the other hand, on the lower side of the
The connection piece
[0025]
An
[0026]
Next, a construction method for constructing a water channel with the shaft 1 and the propulsion pipe, including the step of connecting the shaft blocks 2 and 3 by the joint 7, will be described. First, the
[0027]
Normally, the
The
[0028]
After press-fitting and propelling the
[0029]
In this state, the vertical shaft blocks 2 and 3 further joined are vertically pressed into the ground while being swiveled or inverted around their central axes. At the same time, the sediment in the shaft blocks 2 and 3 is discharged.
When connecting another shaft block on the
[0030]
As shown in FIGS. 1 and 6, after digging to a predetermined depth and constructing the shaft 1, the portion to be the bottom wall of the manhole, that is, the portion surrounded by the lower peripheral inner peripheral surface of the
[0031]
Next, as shown by the temporary wire in FIG. 1, the
[0032]
In such a state, before opening the
[0033]
The
[0034]
The
[0035]
Next, as shown in FIGS. 1 and 6, on the
[0036]
The upper shaft block 4 is molded with a metal ring-shaped
[0037]
FIG. 5 shows a form of a joint part of a driving shaft different from the above. In the joint part of the propulsion shaft described above with reference to FIG. 4, the
[0038]
The shape of the connection piece
[0039]
As already mentioned, the connecting piece 17 'is separate from the fixed
[0040]
In this example, when connecting the
[0041]
【The invention's effect】
As described above, according to the present invention, the vertical shaft blocks 2 and 3 can be connected only by fitting the connecting
[Brief description of the drawings]
FIG. 1 is a longitudinal sectional side view showing a state where a shaft is propelled and constructed using a shaft block and a propulsion blade according to the present invention.
FIG. 2 is a cross-sectional plan view showing a state where a shaft is propelled and constructed using the same shaft block and a propulsion blade.
FIG. 3 is a half sectional perspective view showing an example of those states when connecting a shaft block according to the present invention.
FIG. 4 is a side view of a main part showing a joint part for connecting a shaft block according to the present invention, and an enlarged sectional view of AA part thereof.
FIG. 5 is a side view of an essential part showing another embodiment of a joint part for connecting a shaft block according to the present invention, and an enlarged sectional view of a BB part thereof.
FIG. 6 is a vertical sectional side view showing an example in which a waterway and a manhole are constructed by the shaft block according to the present invention.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002182771A JP2004027544A (en) | 2002-06-24 | 2002-06-24 | Joint part of press-in shaft |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002182771A JP2004027544A (en) | 2002-06-24 | 2002-06-24 | Joint part of press-in shaft |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004027544A true JP2004027544A (en) | 2004-01-29 |
Family
ID=31179181
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002182771A Pending JP2004027544A (en) | 2002-06-24 | 2002-06-24 | Joint part of press-in shaft |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004027544A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6244996U (en) * | 1985-09-05 | 1987-03-18 | ||
JPS6285595U (en) * | 1985-11-20 | 1987-06-01 | ||
JPH0673982A (en) * | 1992-08-28 | 1994-03-15 | Osaka Gas Co Ltd | Pipe laying method in ground and laid pipe in ground |
JPH10114954A (en) * | 1997-10-30 | 1998-05-06 | Chiken Kogyo Kk | Manhole body block applied to small-bore pipe jacking and method of manhole construction |
JPH1130092A (en) * | 1997-07-10 | 1999-02-02 | Aichi Kogyo Kk | Cut-off device for tunnel opening |
-
2002
- 2002-06-24 JP JP2002182771A patent/JP2004027544A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6244996U (en) * | 1985-09-05 | 1987-03-18 | ||
JPS6285595U (en) * | 1985-11-20 | 1987-06-01 | ||
JPH0673982A (en) * | 1992-08-28 | 1994-03-15 | Osaka Gas Co Ltd | Pipe laying method in ground and laid pipe in ground |
JPH1130092A (en) * | 1997-07-10 | 1999-02-02 | Aichi Kogyo Kk | Cut-off device for tunnel opening |
JPH10114954A (en) * | 1997-10-30 | 1998-05-06 | Chiken Kogyo Kk | Manhole body block applied to small-bore pipe jacking and method of manhole construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH11181790A (en) | Execution method of building foundation | |
JP3177468B2 (en) | Standing block, standing excavation method and sewer propulsion method | |
JP4440497B2 (en) | Construction method of underground continuous wall and construction method of underground structure | |
JP4086400B2 (en) | Propulsion shaft, its construction method and propulsion method | |
JP2004027544A (en) | Joint part of press-in shaft | |
JP2005264446A (en) | Method of joining cast-in place pile and steel pipe column | |
JP3893052B2 (en) | Joint structure of manhole for propulsion pipe and its construction method | |
JP2007308951A (en) | Method of constructing outer peripheral column by inverted construction method | |
JP3944005B2 (en) | Chemical injection method to press-fit shaft and its excavation ground | |
JP3776987B2 (en) | Vertical shaft construction method using a manhole wall combined tubular body | |
JPH0828195A (en) | Lining of tunnel | |
JP3221895B2 (en) | Construction method of large-diameter underground wall body and excavation equipment for burying pipes | |
JPH1130092A (en) | Cut-off device for tunnel opening | |
JPH10114954A (en) | Manhole body block applied to small-bore pipe jacking and method of manhole construction | |
JP2004027542A (en) | Advancing shaft and chemical injection method to ground in the vicinity of its pit mouth | |
JP2003155887A (en) | Immersion construction method of shaft | |
JP2014005590A (en) | Coupling device for cylindrical member forming unit | |
JP2006037633A (en) | Foundation structure and construction method thereof | |
JP2003328357A (en) | Steel pipe sheet pile method | |
JPH0390705A (en) | Joining method for steel pipe pile | |
JP2000248548A (en) | Removal method of continuous wall core pile and device thereof | |
JPH07292858A (en) | Structure for connecting pc member | |
KR20220089017A (en) | the degree structure of the steel pipe for the work equipment in which the dismantlement facilitates | |
JPH09195274A (en) | Driving method for precast pile and guide pile | |
JPH11172708A (en) | Method for forming pile penetrating existing underground structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050202 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070328 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070410 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070522 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20070807 |