JP2003085133A - Batch control system of on-line compatible system, batch control program of on-line compatible system and recording medium for recording this program - Google Patents

Batch control system of on-line compatible system, batch control program of on-line compatible system and recording medium for recording this program

Info

Publication number
JP2003085133A
JP2003085133A JP2001271458A JP2001271458A JP2003085133A JP 2003085133 A JP2003085133 A JP 2003085133A JP 2001271458 A JP2001271458 A JP 2001271458A JP 2001271458 A JP2001271458 A JP 2001271458A JP 2003085133 A JP2003085133 A JP 2003085133A
Authority
JP
Japan
Prior art keywords
batch
processing
online
parameter
batch job
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001271458A
Other languages
Japanese (ja)
Other versions
JP5058416B2 (en
Inventor
Akihiro Mikami
昭弘 三上
Hidenobu Tatsumi
秀宜 巽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Soken Inc
Original Assignee
Nippon Soken Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Soken Inc filed Critical Nippon Soken Inc
Priority to JP2001271458A priority Critical patent/JP5058416B2/en
Publication of JP2003085133A publication Critical patent/JP2003085133A/en
Application granted granted Critical
Publication of JP5058416B2 publication Critical patent/JP5058416B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To avoid inconvenience such as the deterioration in a response of on-line processing without restricting a batch job more than necessary in a computer system for processing the on-line processing and the batch job in parallel. SOLUTION: This system executes the batch job by a batch processing part 11 and the on-line processing by an on-line processing part 12 in parallel to a common database DB, and is provided with a monitor 16 for monitoring an executing state of the on-line processing by the on-line processing part 12, and a batch control part 15 for setting a parameter being a control condition at batch job executing time by the batch processing part 11 on the basis of a monitoring result by the monitor 16, and promotes the on-line processing without restricting the batch job more than necessary by changing the parameter according to an occurrence state when a standby state of the on-line processing is caused.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明はコンピュータシステ
ム、特に共通のデータベースに対してオンライン処理と
バッチジョブとを並行して行うシステムにおけるバッチ
ジョブ制御システム、及びこの種のシステムに用いるプ
ログラム、並びにそのプログラムを記録した記録媒体に
関し、コンピュータを用いたデータ管理技術の分野に属
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a computer system, and more particularly to a batch job control system in a system for performing online processing and batch jobs in parallel on a common database, a program used for this type of system, and a program therefor. A recording medium in which is recorded belongs to the field of data management technology using a computer.

【0002】[0002]

【従来の技術】近年、銀行やクレジットカード会社等の
コンピュータを用いた管理システムにおいては、ATM
による夜間取引の普及やカード取引の国際化等に伴い、
オンライン処理の24時間化が要求されているところで
あり、また、これらの管理業務としてのバッチジョブが
増大する傾向にある。そこで、従来、共通のデータベー
スに対して時間帯を異ならせて行なっていたオンライン
処理とバッチジョブとを同時に並行処理することが試み
られ、その実用化が図られている。
2. Description of the Related Art In recent years, ATMs have been used in management systems using computers such as banks and credit card companies.
With the spread of nighttime transactions and internationalization of card transactions,
There is a demand for 24-hour on-line processing, and the number of batch jobs for managing these tasks tends to increase. Therefore, it has been attempted to simultaneously perform an online process and a batch job, which have been conventionally performed in a common database at different time zones, in parallel, and to put them into practical use.

【0003】[0003]

【発明が解決しようとする課題】ところで、バッチジョ
ブにおいては、例えば特定取引に関連する一連の処理を
終了した時点或いはそのような処理を所定回数実行した
時点、又は所定の処理時間が経過した時点等のインター
バルで、更新されたデーターベースの内容を確定する所
謂同期処理が行われるが、この同期処理はCPUに与え
る負荷が大きく、時間も要することから、従来において
は、バッチジョブの能率向上のため、上記インターバル
を比較的長くし、同期処理の回数を極力少なくするよう
に設定するのが通例であった。
By the way, in a batch job, for example, when a series of processes related to a specific transaction is completed, when such processes are executed a predetermined number of times, or when a predetermined processing time elapses. The so-called synchronous processing for fixing the contents of the updated database is performed at intervals such as, but this synchronous processing imposes a heavy load on the CPU and requires a lot of time. Therefore, it has been customary to set the interval relatively long and set the number of times of synchronization processing to be as small as possible.

【0004】しかし、上記のようなオンライン処理との
併用システムでは、バッチジョブの同期処理のインター
バルを長くすると、データベースの排他機能により、更
新し或いは読み込んだレコードが同期処理されるまでオ
ンライン処理の受け付けを拒否するので、オンライン処
理の迅速な処理が妨げられることになり、その結果、特
に昼間時等のオンライン処理が集中する時間帯は、オン
ライン処理のレスポンス時間が著しく長くなり、その処
理に支障を来すことになる。
However, in the combined system with the online processing as described above, if the interval of the synchronous processing of the batch job is lengthened, the online processing is accepted until the updated or read record is synchronously processed by the exclusive function of the database. As a result, the rapid processing of the online processing is hindered, and as a result, the response time of the online processing becomes significantly longer, especially during the daytime when the online processing is concentrated, which hinders the processing. Will come.

【0005】この問題に対しては、オンライン処理が集
中し易い昼間時等の所定の時間帯は、バッチジョブの同
期処理を行なうインターバルを短くすることにより、デ
ータベースの排他状態にあるレコードを早期に解放して
オンライン処理を促進し、そのレスポンス時間を短くす
るといった調整を行なうことが考えられる。
To solve this problem, in a predetermined time zone such as daytime when online processing is likely to be concentrated, by shortening the interval for performing batch job synchronous processing, the records in the exclusive state of the database can be processed early. It is conceivable to make adjustments such as releasing it to promote online processing and shortening its response time.

【0006】しかし、このように時間帯による画一的な
調整だけでは、オンライン処理が予想以上に集中したと
きに、これを十分に処理することができなくなってレス
ポンスの悪化が発生することになり、逆にオンライン処
理の発生が少ないときには、必要以上にバッチジョブを
制限することになって、ホストコンピュータの全体とし
ての処理能力を低下させることになる。
However, when the online processing is concentrated more than expected, it is impossible to sufficiently process the online processing only by the uniform adjustment according to the time zone, and the response is deteriorated. Conversely, when the occurrence of online processing is small, batch jobs are restricted more than necessary, and the overall processing capacity of the host computer is reduced.

【0007】そこで、本発明は、オンライン処理とバッ
チジョブとを並行処理するコンピュータシステムにおい
て、バッチジョブを必要以上に制限することなく、オン
ライン処理を効果的に促進して、ホストコンピュータの
高い処理能力を維持しながら、オンライン処理のレスポ
ンスの悪化等の不具合を回避することを課題とする。
Therefore, the present invention effectively promotes online processing in a computer system that processes online processing and batch jobs in parallel without unnecessarily limiting batch jobs, and increases the processing power of the host computer. It is an object to avoid problems such as deterioration of response of online processing while maintaining the above.

【0008】[0008]

【課題を解決するための手段】即ち、本発明は上記課題
の解決のため、次のように構成したことを特徴とする。
That is, the present invention is characterized by having the following constitution in order to solve the above problems.

【0009】まず、本願の請求項1に記載の発明は、オ
ンライン処理実行手段及びバッチジョブ実行手段によ
り、共通のデータベースに対してオンライン処理とバッ
チジョブとを並行して実行するシステムのバッチ制御シ
ステムに関するものであって、上記両実行手段によるオ
ンライン処理とバッチジョブの並行処理中におけるオン
ライン処理の待機状態の発生を検出する待機状態検出手
段と、該検出手段によりオンライン処理の待機状態の発
生が検出されたときに、その待機状態が軽減されるよう
に、上記バッチジョブ実行手段によるバッチジョブ実行
時の制御条件を変更するバッチジョブ制御手段とを有す
ることを特徴とする。
First, the invention according to claim 1 of the present application is a batch control system for a system that executes online processing and batch jobs in parallel to a common database by means of online processing execution means and batch job execution means. And a standby state detecting means for detecting the occurrence of the standby state of the online processing during the parallel processing of the batch processing and the online processing by the both executing means, and the detecting means for detecting the occurrence of the standby state of the online processing. And a batch job control means for changing the control condition when the batch job is executed by the batch job execution means so as to reduce the waiting state.

【0010】この発明によれば、オンライン処理とバッ
チジョブとが並行して実行されている場合に、バッチジ
ョブによって排他状態となっているレコードの増大によ
り、オンライン処理に所定限度以上の待機状態が発生し
た場合に、バッチジョブに対し、同期処理のインターバ
ル等の制御条件を変更することによって制限が加えられ
ることになる。これにより、オンライン処理が促進さ
れ、そのレスポンスが改善されることになる。
According to the present invention, when the online processing and the batch job are executed in parallel, the number of records in the exclusive state by the batch job is increased, so that the online processing has a waiting state of a predetermined limit or more. When it occurs, the batch job is limited by changing the control conditions such as the synchronization processing interval. This will facilitate online processing and improve its response.

【0011】また、請求項2に記載の発明は、上記請求
項1に記載のシステムにおいて、待機状態検出手段は、
所定件数のオンライン処理又は所定時間内に発生するオ
ンライン処理の平均レスポンス時間に基づいてオンライ
ン処理の待機状態の発生を検出することを特徴とする。
According to a second aspect of the present invention, in the system according to the first aspect, the standby state detecting means is
It is characterized in that the occurrence of a standby state of online processing is detected based on an average response time of a predetermined number of online processing or online processing that occurs within a predetermined time.

【0012】この発明によれば、オンライン処理の待機
状態の発生が、所定件数のオンライン処理又は所定時間
内に発生するオンライン処理の平均レスポンス時間に基
づいて検出されるので、オンライン処理の一時的、偶発
的なレスポンスの低下等に対してバッチジョブを不必要
に制限することが回避され、常に効果的で安定したバッ
チジョブの制御が行なわれることになる。
According to the present invention, the occurrence of the waiting state of the online processing is detected based on the average response time of the predetermined number of online processings or the online processings occurring within the predetermined time. Unnecessarily limiting the batch job against accidental deterioration of response is avoided, and effective and stable control of the batch job is always performed.

【0013】また、請求項3に記載の発明は、上記請求
項1又は請求項2に記載のシステム、特にバッチジョブ
実行手段が、所定の処理の所定実行回数ごと、又はジョ
ブ開始時もしくは前回の同期処理実行時からの所定経過
時間ごとの少なくとも一方のインターバルでデータベー
スに対する同期処理を行なうように構成され、かつ同期
処理実行後にバッチジョブの休止期間の設定が可能とさ
ているシステムにおいて、バッチジョブ制御手段は、バ
ッチジョブの制御条件として、上記同期処理のインター
バルとなる実行回数もしくは経過時間、又は上記バッチ
ジョブ休止期間の時間のうちの少なくとも一つのパラメ
ータを変更することを特徴とする。
According to a third aspect of the present invention, the system according to the first or second aspect, in particular, the batch job executing means is configured to perform a predetermined process every predetermined number of times, or at the time of starting a job or the last time. Batch job control in a system that is configured to perform a synchronous process on a database at least at intervals of a predetermined elapsed time after the synchronous process is executed, and is capable of setting a pause period for a batch job after the synchronous process is executed. The means is characterized in that, as the control condition of the batch job, at least one parameter of the number of times of execution or the elapsed time which is the interval of the synchronous processing or the time of the batch job suspension period is changed.

【0014】そして、請求項4に記載の発明は、上記請
求項3に記載のシステムにおいて、パラメータとして、
通常時のパラメータと、バッチジョブの実行を通常時よ
り所定量制限する1次制限パラメータと、さらに制限度
合いを高くする2次制限パラメータとが設定されてお
り、バッチジョブ制御手段は、通常時のパラメータから
1次制限パラメータに変更した後、オンライン処理の待
機状態が解消されないときに、2次制限パラメータを用
いることを特徴とする。
The invention according to claim 4 is, in the system according to claim 3 as a parameter,
A normal time parameter, a primary restriction parameter that restricts execution of a batch job by a predetermined amount from a normal time, and a secondary restriction parameter that further increases the restriction degree are set. After the parameter is changed to the primary limiting parameter, the secondary limiting parameter is used when the standby state of the online processing is not resolved.

【0015】これらの発明によれば、オンライン処理の
待機状態が発生したときに、バッチジョブの制御条件と
してのパラメータのうち、例えば同期処理のインターバ
ルとなる所定処理の実行回数が少なくされ、又は前回の
同期処理実行時等からの経過時間が短くされるなどによ
り、データベースにおける排他状態となっていたレコー
ドが早期に解放されることになり、また、同期処理実行
後にバッチジョブ休止期間が設けられ或いはその期間の
時間が長くされるなどにより、オンライン処理が促進さ
れることになる。その場合に、上記のインターバルとな
る回数又は時間、及びバッチジョブ休止時間等のパラメ
ータの2つ以上を同時に変更すれば、オンライン処理を
一層効果的に促進させることが可能となる。
According to these aspects of the invention, when the waiting state of the online processing occurs, the number of executions of the predetermined processing, which is the interval of the synchronous processing, of the parameters as the control condition of the batch job is reduced, or The records that were in the exclusive state in the database will be released early due to the shortening of the elapsed time from the execution of the synchronous processing of, and the batch job suspension period will be provided after the synchronous processing is executed, or Online processing will be promoted due to a longer period of time. In this case, if two or more parameters such as the number of times or the above interval and the batch job pause time are changed at the same time, online processing can be more effectively promoted.

【0016】そして、請求項4に記載の発明によれば、
オンライン処理の待機状態が発生している場合におい
て、上記パラメータを通常時のパラメータから1次制限
パラメータに変更しただけではその待機状態が十分に解
消されないときに、2次制限パラメータが用いられて、
バッチジョブに対する制限度合いが高められるので、当
初からバッチジョブに対する必要以上の制限を加えるこ
となく、オンライン処理の待機状態が確実に解消される
ことになる。
According to the invention described in claim 4,
In the case where a standby state for online processing has occurred, the secondary limit parameter is used when the standby state is not sufficiently resolved by simply changing the parameter from the normal parameter to the primary limit parameter.
Since the degree of limitation on the batch job is increased, the waiting state of the online processing can be reliably eliminated without imposing unnecessary limitation on the batch job from the beginning.

【0017】さらに、請求項5に記載の発明は、上記請
求項3又は請求項4に記載のシステム、特に複数のバッ
チジョブを処理するシステムにおいて、処理の優先度又
はオンライン処理を妨げる度合いの少なくとも一方の属
性に基づいて分類したバッチジョブのグループごとにパ
ラメータを記録したパラメータ記録手段が備えられ、か
つ、バッチジョブ制御手段は、上記パラメータ記録手段
から現在実行中のバッチジョブが属するグループについ
てのパラメータを読み出して用いることを特徴とする。
Further, according to the invention described in claim 5, in the system according to claim 3 or 4, particularly in the system for processing a plurality of batch jobs, at least the priority of processing or the degree of hindering online processing is provided. Parameter recording means for recording a parameter for each group of batch jobs classified based on one attribute is provided, and the batch job control means is configured to set parameters for the group to which the batch job currently being executed belongs from the parameter recording means. Is read out and used.

【0018】この発明によれば、種類の異なる複数のバ
ッチジョブが実行されるシステムの場合に、各バッチジ
ョブが、例えば処理が急がれているジョブか、そうでな
いジョブかといった優先度や、データベースの更新を伴
うジョブか参照のみのジョブかといったオンライン処理
を妨げる度合い等の属性に応じてグループ分けされると
共に、各グループごとに上記のような属性に応じてパラ
メータが設定されることになる。そして、このグループ
ごとのパラメータを記録したパラメータ記録手段から、
現在実行中のバッチジョブが属するグループについての
パラメータを読み出してバッチジョブが実行されること
になる。
According to the present invention, in the case of a system in which a plurality of batch jobs of different types are executed, the priority of each batch job is, for example, whether the processing is urgent or not, The jobs will be grouped according to attributes such as the degree of obstructing online processing, such as whether the job involves updating the database or only the reference, and parameters will be set for each group according to the above attributes. . Then, from the parameter recording means that records the parameters for each group,
The batch job will be executed by reading the parameters of the group to which the currently executing batch job belongs.

【0019】したがって、各バッチジョブに対する制限
が、そのバッチジョブの属性に応じたパラメータにより
適切に実行されると共に、このパラメータを設定し或い
は変更する場合に、各バッチジョブごとの設定、変更が
不要となって、同一グループのバッチジョブについての
設定、変更を一括して行うことが可能となる。
Therefore, the limitation on each batch job is appropriately executed by the parameter according to the attribute of the batch job, and when setting or changing this parameter, the setting or change for each batch job is not necessary. Therefore, it becomes possible to collectively set and change batch jobs of the same group.

【0020】一方、請求項6に記載の発明は、オンライ
ン処理実行手段及びバッチジョブ実行手段により、共通
のデータベースに対してオンライン処理とバッチジョブ
とが並行して実行され、かつ上記両実行手段によるオン
ライン処理とバッチジョブの並行処理中におけるオンラ
イン処理の実行状態を監視するオンライン処理監視手段
が備えられたシステムのバッチ制御用プログラムに関す
るものであって、コンピュータを、上記オンライン処理
監視手段による監視結果に基づいてオンライン処理に待
機状態が発生しているか否かを判定する待機状態判定手
段、及び該判定手段によりオンライン処理の待機状態の
発生が判定されたときに、その待機状態が軽減されるよ
うに、上記バッチジョブ実行手段によるバッチジョブ実
行時の制御条件を変更するバッチジョブ制御手段として
機能させることを特徴とする。
On the other hand, according to a sixth aspect of the present invention, the online processing execution means and the batch job execution means execute the online processing and the batch job in parallel on the common database, and both of the execution means. The present invention relates to a batch control program for a system having online processing monitoring means for monitoring the execution status of online processing during parallel processing of online processing and batch jobs, wherein a computer is used for monitoring results by the online processing monitoring means. Based on the standby state determining means for determining whether or not the standby state has occurred in the online processing based on the determination, and when the determination means determines that the standby state for the online processing has occurred, the standby state is reduced. , The control conditions at the time of batch job execution by the above batch job execution means Further, characterized in that to function as a batch job control means for.

【0021】また、請求項7に記載の発明は、上記請求
項6に記載のプログラムにおいて、コンピュータを待機
状態判定手段として機能させるときに、所定件数のオン
ライン処理又は所定時間内に発生するオンライン処理の
平均レスポンス時間に基づいてオンライン処理の待機状
態の発生を判定するように機能させることを特徴とす
る。
The invention according to claim 7 is the program according to claim 6, wherein a predetermined number of online processes or online processes that occur within a predetermined time when the computer functions as the standby state determination means. It is characterized by functioning to determine the occurrence of a standby state of online processing based on the average response time of.

【0022】また、請求項8に記載の発明は、上記請求
項6又は請求項7に記載のプログラムにおいて、バッチ
ジョブ実行手段が、所定の処理の所定実行回数ごと、又
はジョブ開始時もしくは前回の同期処理実行時からの所
定経過時間ごとの少なくとも一方のインターバルでデー
タベースに対する同期処理を行なうように構成され、か
つ同期処理実行後にバッチジョブの休止期間の設定が可
能とされたシステムに用いられる場合に、コンピュータ
をバッチジョブ制御手段として機能させるときに、バッ
チジョブの制御条件として、上記同期処理のインターバ
ルとなる実行回数もしくは経過時間、又は上記バッチジ
ョブ休止期間の時間のうちの少なくとも一つのパラメー
タを変更するように機能させることを特徴とする。
According to an eighth aspect of the present invention, in the program according to the sixth or seventh aspect, the batch job executing means performs the predetermined processing every predetermined number of times, or at the time of starting the job or the previous time. When used in a system that is configured to perform synchronization processing for a database at least at intervals of every predetermined elapsed time from the time when synchronization processing is executed, and that allows the setting of a pause period for batch jobs after execution of synchronization processing When the computer is caused to function as the batch job control means, as the control condition of the batch job, at least one parameter of the number of times of execution or the elapsed time which is the interval of the synchronous processing, or the time of the batch job suspension period is changed. It is characterized by making it function as.

【0023】また、請求項9に記載の発明は、上記請求
項8に記載のプログラムにおいて、パラメータとして、
通常時のパラメータと、バッチジョブの実行を通常時よ
り所定量制限する1次制限パラメータと、さらに制限度
合いを高くする2次制限パラメータとが設定されている
システムに用いられる場合に、コンピュータをバッチジ
ョブ制御手段として機能させるときに、通常時のパラメ
ータから1次制限パラメータに変更した後、オンライン
処理の待機状態が解消されないときに、2次制限パラメ
ータを用いるように機能させることを特徴とする。
The invention according to claim 9 is, in the program according to claim 8 as a parameter,
When the system is used in a system in which a normal time parameter, a primary restriction parameter that restricts execution of a batch job by a predetermined amount from the normal time, and a secondary restriction parameter that further increases the restriction degree are set, the computer is batched. When functioning as the job control means, after changing from the normal parameter to the primary limiting parameter, the secondary limiting parameter is used when the standby state of the online processing is not resolved.

【0024】そして、請求項10に記載の発明は、上記
請求項8又は9に記載のプログラムにおいて、複数のバ
ッチジョブが実行され、かつ、処理の優先度又はオンラ
イン処理を妨げる度合いの少なくとも一方の属性に基づ
いて分類したバッチジョブのグループごとにパラメータ
を記録したパラメータ記録手段が備えられたシステムに
用いられる場合に、コンピュータをバッチジョブ制御手
段として機能させるときに、上記パラメータ記録手段か
ら現在実行中のバッチジョブが属するグループについて
のパラメータを読み出して用いるように機能させること
を特徴とする。
According to a tenth aspect of the invention, in the program according to the eighth or ninth aspect, a plurality of batch jobs are executed, and at least one of the priority of processing and the degree of hindering online processing is set. When the computer is made to function as the batch job control means when used in a system provided with a parameter recording means for recording parameters for each group of batch jobs classified based on attributes, the parameter recording means is currently executing the data from the parameter recording means. It is characterized in that it functions so as to read and use the parameters of the group to which the batch job belongs.

【0025】この請求項6から請求項10に記載のプロ
グラムは、上記請求項1から請求項5に記載のシステム
にそれぞれ対応するもので、これらのプログラムをバッ
チジョブ実行手段やオンライン処理実行手段等が備えら
れたコンピュータシステムで用いることにより、請求項
1から請求項5に記載のバッチ制御システムと同様の作
用が得られる。
The programs described in claims 6 to 10 correspond to the systems described in claims 1 to 5, respectively, and these programs are executed by batch job execution means, online processing execution means, etc. When used in a computer system equipped with, the same operation as the batch control system according to the first to fifth aspects can be obtained.

【0026】そして、請求項11に記載の発明は、上記
請求項6から請求項10のいずれかに記載のプログラム
を記録したコンピュータ読み取り可能な記録媒体に関す
るものであり、この記録媒体によれば請求項6から請求
項10のいずれかに記載のプログラムが実行されること
になって、請求項1から請求項5に記載のバッチ制御シ
ステムと同様の作用が実現されることになる。
The invention described in claim 11 relates to a computer-readable recording medium in which the program according to any one of claims 6 to 10 is recorded. According to this recording medium, When the program according to any one of claims 6 to 10 is executed, the same operation as that of the batch control system according to claims 1 to 5 is realized.

【0027】[0027]

【発明の実施の形態】以下、本発明の実施の形態につい
て説明する。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiments of the present invention will be described below.

【0028】図1はこの実施の形態に係るシステムのハ
ード構成を示すもので、このシステムの中心となるホス
トコンピュータ10は、バッチ処理部11とオンライン
処理部12とを有し、両処理部11、12に各種コマン
ドの入力やバッチジョブの進行状況の監視等に用いられ
るオペレータ端末機21が接続されている。
FIG. 1 shows a hardware configuration of a system according to this embodiment. A host computer 10, which is the center of the system, has a batch processing unit 11 and an online processing unit 12, and both processing units 11 are provided. , 12 are connected to operator terminals 21 used for inputting various commands and monitoring the progress of batch jobs.

【0029】また、バッチ処理部11は、外部の入力フ
ァイルFL1からのデータの入力、出力ファイルFL2
へのデータの出力が可能とされていると共に、同期処理
のタイミングの設定等に用いられるカウンタ13とタイ
マ14とを備えており、また、オンライン処理部12
は、通信制御装置22を介して多数のユーザー端末機
(図示せず)と接続可能とされている。
Further, the batch processing section 11 inputs data from an external input file FL1 and outputs an output file FL2.
Data output to the online processing unit 12 is provided, and the online processing unit 12 includes a counter 13 and a timer 14 used for setting the timing of synchronization processing.
Can be connected to a large number of user terminals (not shown) via the communication control device 22.

【0030】さらに、このホストコンピュータ10に
は、上記バッチ処理部11によるバッチジョブの処理状
態を制御するためのバッチ制御部15が備えられてお
り、このバッチ制御部15に、上記オペレータ端末機2
1と、上記オンライン処理部12によるオンライン処理
の実行状況を監視するためのモニタ16と、クロック1
7とが接続されている。また、このバッチ制御部15に
は、属性に応じてグループ分けされた複数のバッチジョ
ブがそれぞれ属するグループを記録したジョブグループ
テーブルTB1と、バッチジョブ実行時の制御条件とな
るパラメータを記録したパラメータテーブルTB2とが
接続されている。
Further, the host computer 10 is provided with a batch control unit 15 for controlling the processing state of the batch job by the batch processing unit 11, and the batch control unit 15 has the operator terminal 2
1, a monitor 16 for monitoring the execution status of online processing by the online processing unit 12, and a clock 1
7 and 7 are connected. Further, the batch control unit 15 records a job group table TB1 in which a group to which each of a plurality of batch jobs grouped according to attributes belongs is recorded, and a parameter table in which parameters that are control conditions at the time of executing the batch job are recorded. TB2 is connected.

【0031】そして、バッチ制御部15は、本発明の実
施の形態に係るバッチ制御プログラムに従い、上記モニ
タ16からのオンライン処理の実行状況を示す信号と、
上記クロック17からの信号と、上記オペレータ端末機
21からのコマンド信号と、上記ジョブグループテーブ
ルTB1及びパラメータテーブルTB2からそれぞれ読
み出した情報とに基づき、上記バッチ処理部11による
バッチジョブの処理状態を制御するようになっている。
Then, the batch controller 15 follows the batch control program according to the embodiment of the present invention, and outputs a signal from the monitor 16 indicating the execution status of the online processing.
The processing status of the batch job by the batch processing unit 11 is controlled based on the signal from the clock 17, the command signal from the operator terminal 21, and the information read from the job group table TB1 and the parameter table TB2, respectively. It is supposed to do.

【0032】ここで、上記ジョブグループテーブルTB
1及びパラメータテーブルTB2について説明すると、
まずジョブグループテーブルTB1は、図2に示すよう
に、各バッチジョブを、専らデータベースDBの更新を
行なうジョブであってオンライン処理を妨げる度合いの
高いものと、データベースDBの参照が中心のジョブで
あって上記度合いの低いものと、データベースDBを使
用しないものとに区分し、それぞれ区分A、区分B、区
分Cとすると共に、各区分の複数のジョブに処理の緊急
性等に応じた優先度1、2…を設定し、この区分と優先
度とをパラメータとして各ジョブをグループ分けした構
成となっている。
Here, the job group table TB
1 and the parameter table TB2,
First, in the job group table TB1, as shown in FIG. 2, each batch job is a job that exclusively updates the database DB and has a high degree of obstruction to online processing, and a job that mainly refers to the database DB. Are divided into those having a low degree and those not using the database DB and are respectively divided into a division A, a division B, and a division C, and a plurality of jobs in each division have a priority 1 according to the urgency of processing or the like. 2 are set, and each job is divided into groups using the division and the priority as parameters.

【0033】また、上記パラメータテーブルTB2は、
図3に示すように、ジョブグループテーブルTB1によ
ってグループ分けされた各バッチジョブのうちの専らデ
ータベースDBの更新を行なうジョブのグループA1、
A2…、及びデータベースDBの参照が中心のジョブの
グループB1、B2…ごとに、同期処理を実行するイン
ターバルとなる所定の処理の所定実行回数(以下、「イ
ンターバル回数」という)及びジョブの開始時又は前回
の同期処理実行時からの所定経過時間(以下、「インタ
ーバル時間」という)と、同期処理実行後に設けるバッ
チジョブの休止期間の時間の3つのパラメータを、オン
ライン優先時間帯でのバッチ非制限時、バッチ1次制限
時及び2次制限時、並びにバッチ優先時間帯についてそ
れぞれ設定した構成となっている。
The parameter table TB2 is
As shown in FIG. 3, of the batch jobs grouped by the job group table TB1, a group A1 of jobs exclusively updating the database DB,
A2 ..., and for each group of jobs B1, B2 ... Of which reference is mainly made to the database DB, a predetermined number of times of execution of a predetermined process (hereinafter, referred to as “interval number”) and an interval at which the synchronous process is executed, and the start time of the job. Alternatively, three parameters, that is, a predetermined elapsed time from the previous execution of the synchronization processing (hereinafter, referred to as “interval time”) and a pause time of the batch job provided after the execution of the synchronization processing, are set as batch non-limitation in the online priority time zone. Time, batch primary restriction, secondary restriction, and batch priority time zone are set.

【0034】その場合に、オンライン優先時間帯では、
バッチジョブ非制限時に対して1次制限時はインターバ
ル回数は少なく、インターバル時間は短くされて、バッ
チジョブの実行により排他状態となっているデータベー
スDBのレコードを早期に解放するように設定されお
り、また、バッチジョブ休止時間が0より大きな値とさ
れて、同期処理実行後にバッチジョブを所定時間休止す
るように設定されている。
In that case, in the online priority time zone,
The number of intervals is small and the interval time is shortened when the primary job is restricted compared to when the batch job is not restricted, so that the records in the database DB that are in the exclusive state due to the execution of the batch job are set to be released early. Further, the batch job pause time is set to a value larger than 0, and the batch job is set to pause for a predetermined time after the synchronous processing is executed.

【0035】また、2次制限時の数値は、2次制限を1
回実施するたびに、バッチジョブに対する制限度合いを
高めるように1次制限時のパラメータの値に付加される
値であって、インターバル回数及びインターバル時間に
ついては所定量づつ減算されることにより、排他状態に
あるレコードを一層早期に解放するように設定され、同
期処理実行後のバッチ休止時間については所定量づつ加
算されて、この休止時間を長くするように設定されてい
る。
In addition, the numerical value at the time of the secondary restriction is 1 for the secondary restriction.
It is a value that is added to the value of the parameter at the time of primary limitation so as to increase the degree of limitation on the batch job each time it is executed. By subtracting the interval count and interval time by a predetermined amount, the exclusion status Is set to release the record at an earlier time, and the batch pause time after the execution of the synchronous processing is incremented by a predetermined amount to make the pause time longer.

【0036】また、バッチジョブの優先度については、
優先度が高いものほど、インターバル回数及びインター
バル時間が大きな値にされ、かつ休止時間が短くされ
て、優先度の低いものより制限を抑制した設定とされ、
また、バッチジョブの区分については、専らデータベー
スDBの更新を行なう区分(オンライン処理を妨げる度
合いの高い区分)Aのジョブが、データベースDBの参
照中心の区分(オンライン処理を妨げる度合いの低い区
分)Bのジョブより、インターバル回数及びインターバ
ル時間が小さな値に設定され、かつ休止時間が長くされ
て、バッチジョブに対する制限を強くした設定とされて
いる。
Regarding the priority of the batch job,
The higher the priority, the larger the number of intervals and the interval time, and the shorter the pause time.
As for the classification of batch jobs, the job of the section A that exclusively updates the database DB (the section having a high degree of hindering online processing) is the job of the reference center of the database DB (the section having a low degree of hindering online processing) The number of intervals and the interval time are set to values smaller than those of the job No., and the pause time is set to be longer, so that the limit for the batch job is set stronger.

【0037】なお、バッチジョブの制限制御を行なわな
いバッチ優先時間帯では、インターバル回数及びインタ
ーバル時間は、いずれもオンライン優先時間帯より大き
な値とされていると共に、同期処理実行後の休止時間は
0とされ、バッチジョブの処理を積極的に推進するよう
になっている。
In the batch priority time zone in which the batch job restriction control is not performed, both the number of intervals and the interval time are larger than the online priority time zone, and the pause time after the synchronous processing is 0. It is said that the processing of batch jobs is actively promoted.

【0038】次に、以上のシステムによるジョブの動
作、特にオンライン処理の実行状態に応じたバッチジョ
ブに対する制御動作について説明する。
Next, the job operation by the above system, particularly the control operation for the batch job according to the execution status of the online processing will be described.

【0039】まず、図1に示すバッチ処理部11を中心
としたバッチジョブ実行中の同期処理制御の動作を、図
4に示すフローチャートに従って説明する。
First, the operation of the synchronous processing control during the execution of a batch job centered on the batch processing section 11 shown in FIG. 1 will be described with reference to the flowchart shown in FIG.

【0040】この同期処理制御は、バッチジョブのメイ
ンルーチンで呼び出されるサブルーチンとして、例えば
入力ファイルFL1からのレコードの入力処理等、所定
の処理を行なうごとに実行されるものであって、まずス
テップS1で、当該サブルーチンの呼び出し回数、即ち
上記所定処理の実行回数を図1に示すカウンタ13によ
ってカウントする。そして、ステップS2で、その回数
が、前回の同期処理実行後、所定のインターバル回数に
達したか否かを判定し、達していない場合には、ステッ
プS3で、図1に示すタイマ14を用いて計測している
ジョブの開始時又は前回の同期処理実行時点からの経過
時間が所定のインターバル時間に達したか否かを判定す
る。
This synchronous processing control is executed as a subroutine called in the main routine of the batch job each time a predetermined processing such as the processing of inputting a record from the input file FL1 is performed. First, step S1 is executed. Then, the number of times the subroutine is called, that is, the number of times the predetermined process is executed is counted by the counter 13 shown in FIG. Then, in step S2, it is determined whether or not the number of times has reached a predetermined number of intervals after the execution of the previous synchronization process. If not, the timer 14 shown in FIG. 1 is used in step S3. It is determined whether the elapsed time from the start of the job being measured or the time of the previous execution of the synchronization process has reached a predetermined interval time.

【0041】上記インターバル回数及びインターバル時
間は、後述するバッチ制限制御により、バッチジョブの
属するグループ及びオンライン処理の実行状態に応じ
て、図3のパラメータテーブルTB2から予め読み出さ
れた値に設定されたものであるが、インターバル時間
は、ホストコンピュータ10への入出力ファイルFL
1、FL2のセット等に一定以上の時間を要する場合
や、上記の所定処理が大量のデータを扱う処理であっ
て、その実行に長時間を要する場合等に、上記インター
バル回数に達する前であっても同期処理を行なうために
設定されたものである。
The above-mentioned interval count and interval time are set to values read in advance from the parameter table TB2 of FIG. 3 according to the group to which the batch job belongs and the execution state of the online processing by the batch restriction control described later. The interval time is the input / output file FL to / from the host computer 10.
1, when the FL2 setting or the like requires a certain time or more, or when the predetermined process is a process for handling a large amount of data and it takes a long time to execute the process, etc., before the number of intervals is reached. However, it is set to perform the synchronization process.

【0042】そして、前回の同期処理実行後、所定処理
の実行回数がインターバル回数に達したとき、又はこの
インターバル回数に達する前であっても、バッチ開始時
又は前回の同期処理実行時からの経過時間が上記インタ
ーバル時間に達したときは、ステップS2又はステップ
S3からステップS4を実行し、データベースDBをそ
の時点の更新状態で同期処理する。
After execution of the previous synchronization processing, when the number of executions of the predetermined processing reaches the number of intervals, or even before reaching the number of intervals, the time elapsed from the start of the batch or the execution of the previous synchronization processing. When the time reaches the interval time, step S2 or step S3 to step S4 is executed, and the database DB is synchronously processed in the updated state at that time.

【0043】次に、ステップS5で、後述するバッチ制
限制御により、上記パラメータテーブルTB2から予め
読み出されて設定されている同期処理実行後のバッチ休
止期間の時間(以下、「休止時間」という)が経過する
のを待つ。この休止期間中はバッチジョブは休止され、
その間ホストコンピュータ10は専らオンライン処理を
実行することになる。なお、休止時間が0の場合、即ち
同期処理実行後のバッチ休止期間が設定されていないと
きは、ステップS5は直ちに終了する。
Next, in step S5, the batch pause period after the execution of the synchronous processing which is read out from the parameter table TB2 and set in advance by the batch restriction control described later (hereinafter referred to as "pause time"). Wait for. During this pause period, batch jobs are paused,
During that time, the host computer 10 exclusively executes online processing. When the pause time is 0, that is, when the batch pause period after the synchronous processing is not set, step S5 ends immediately.

【0044】そして、休止時間が経過すれば、ステップ
S6で、カウンタ13による上記所定処理の実行回数
(当該サブルーチンの呼び出し回数)のカウント値、及
びタイマ14による計測時間をクリアし、この同期処理
制御を終了する。
When the pause time has elapsed, the count value of the number of times the predetermined process is executed by the counter 13 (the number of times the subroutine is called) and the time measured by the timer 14 are cleared in step S6, and this synchronous process control is executed. To finish.

【0045】次に、上記インターバル回数、インターバ
ル時間及び休止時間等のバッチジョブの制御条件となる
パラメータをオンライン処理の実行状態に応じて設定す
るバッチ制限制御の動作を、図5に示すフローチャート
に従って説明する。なお、この制御は図1のバッチ制御
部15を中心として行なわれるものであり、その動作は
本発明の実施の形態に係るプログラムの作用に相当す
る。
Next, the operation of the batch limitation control for setting the parameters, which are the control conditions of the batch job, such as the number of intervals, the interval time and the pause time, according to the execution state of the online processing will be described with reference to the flowchart shown in FIG. To do. Note that this control is performed mainly by the batch control unit 15 in FIG. 1, and its operation corresponds to the operation of the program according to the embodiment of the present invention.

【0046】この制御は、通例、ホストコンピュータ1
0による毎日の作業開始時からスタートし、まず、所定
のイニシャライズの後、フローチャートのステップS1
1で、図1に示すクロック17からの信号により、現在
の時刻が所定のオンライン優先時間帯に属するか否かを
判定する。
This control is usually performed by the host computer 1.
It starts from the start of daily work by 0, first, after a predetermined initialization, step S1 of the flowchart.
In step 1, it is determined by the signal from the clock 17 shown in FIG. 1 whether or not the current time belongs to a predetermined online priority time zone.

【0047】そして、例えばこのオンライン優先時間帯
が午前9時から午後5時までとされており、ホストコン
ピュータ10の1日の作業開始が午前9時であるとする
と、作業開始時はオンライン優先時間帯に属することに
なる。この場合、まずステップS12で、同期処理を行
なうインターバル回数、インターバル時間、及び同期処
理実行後のバッチ休止時間の各パラメータとして、図3
のパラメータテーブルTB2から、現在実行しているバ
ッチジョブが属するジョブグループについてのオンライ
ン優先時間帯におけるバッチ非制限時の値を読み出し、
これらをバッチジョブ制御用パラメータに設定する。
If, for example, the online priority time zone is from 9 am to 5 pm, and the start of the day's work on the host computer 10 is 9 am, the online priority time is set at the start of work. Will belong to the belt. In this case, first, in step S12, as parameters of the number of intervals for performing the synchronization processing, the interval time, and the batch pause time after execution of the synchronization processing, as shown in FIG.
Value of the job group to which the currently executed batch job belongs is read out from the parameter table TB2 during the batch non-limit time period,
These are set in the parameters for batch job control.

【0048】ここで、現在実行中のバッチジョブの属す
るグループが例えばA1であるとすると、図3に示すよ
うに、上記各パラメータとして、インターバル回数は1
00回、インターバル時間は30秒、バッチ休止時間は
0、といった値に設定されることになり、前述のサブル
ーチンにより、これらのパラメータを用いてバッチジョ
ブに対する同期処理が行われる。
If the group to which the currently executed batch job belongs is A1, for example, as shown in FIG. 3, the number of intervals is 1 as each of the above parameters.
00 times, the interval time is set to 30 seconds, the batch pause time is set to 0, and the above-mentioned subroutine is used to perform the synchronous processing for the batch job using these parameters.

【0049】次に、ステップS13で、図1に示すモニ
タ16からの信号に基づいてオンライン処理のレスポン
ス時間を検出し、その時間が、図6に示すように、許容
限度もしくはこれに近い値であって、バッチジョブを制
限すべきかどうかの判断基準となる制限実施基準値T1
を超えているか否か、或いは一旦実施した制限を解除す
べきかどうかの判断基準であって上記制限実施基準値T
1より短い制限解除基準値T2未満であるか否か、さら
には、これらの時間T1、T2の間の値であるか否かの
判定を行なう。
Next, in step S13, the response time of the online processing is detected based on the signal from the monitor 16 shown in FIG. 1, and the time is at or below the allowable limit as shown in FIG. Therefore, the limit execution reference value T1 that is a reference for determining whether to limit the batch job
Which is a criterion for determining whether or not the limit is once exceeded, or whether or not the limit once implemented should be released.
It is determined whether or not it is less than the limit cancellation reference value T2 shorter than 1 and further whether or not it is a value between these times T1 and T2.

【0050】なお、オンライン処理の一時的、突発的な
レスポンスの遅れによるバッチジョブに対する不必要な
制限を回避するため、上記の判定は所定件数のオンライ
ン処理又は所定時間内に発生したオンライン処理の平均
レスポンス時間に基づいて行なうようになっており、し
たがって、上記ステップS13以下は、平均値が算出さ
れた時点で実行されることになる。
In order to avoid unnecessary restrictions on batch jobs due to temporary or sudden response delays in online processing, the above determination is made by averaging a predetermined number of online processings or online processings that have occurred within a predetermined time. It is designed to be performed based on the response time. Therefore, steps S13 and thereafter are executed when the average value is calculated.

【0051】そして、オンライン処理が順調に実行され
ており、そのレスポンス時間が上記制限実施基準値T1
以下のとき、即ち図6の領域B又はCに属するときは、
バッチジョブに対する積極的な制限は行なわれない。そ
の場合に、レスポンス時間が制限解除基準値T2未満で
あって領域Cに属するときは、ステップS14で、現在
バッチジョブに対する制限が実行されているか否かを判
定することになるが、作業開始直後は制限が行なわれて
いないから、そのまま制御を終了する。
Then, the online processing is executed smoothly, and the response time thereof is the above-mentioned limit execution reference value T1.
In the following cases, that is, when belonging to the area B or C in FIG. 6,
No aggressive restrictions are placed on batch jobs. In that case, if the response time is less than the restriction release reference value T2 and belongs to the area C, it is determined in step S14 whether or not the restriction on the batch job is currently executed. Is not restricted, the control ends as it is.

【0052】これに対し、オンライン処理の発生頻度が
高く、レスポンス時間が長くなって上記制限実施基準値
T1を超えて図6の領域Aに属することになったとき、
即ちオンライン処理のピーク(図7のピークA)が発生
したときは、ステップS13からステップS15を実行
して、オンラインピークの発生回数をカウントすると共
に、ステップS16で、今回の発生がオンライン優先時
間帯での制御開始後の1回目であるか否かを判定する。
そして、1回目であるときは、ステップS17で、図3
のパラメータテーブルTB2から当該ジョブグループに
ついての1次制限のためのパラメータを読み出し、以
後、このパラメータを用いて図4のサブルーチンによる
同期処理を実行する。
On the other hand, when the frequency of online processing is high and the response time becomes long and exceeds the above-mentioned limit enforcement reference value T1 to belong to the area A of FIG. 6,
That is, when a peak of online processing (peak A in FIG. 7) occurs, steps S13 to S15 are executed to count the number of occurrences of online peaks, and in step S16, the current occurrence is the online priority time zone. It is determined whether or not it is the first time after the start of control in.
If it is the first time, in step S17, as shown in FIG.
The parameter for primary restriction for the job group is read from the parameter table TB2, and thereafter, the synchronization process by the subroutine of FIG. 4 is executed using this parameter.

【0053】これにより、例えばジョブグループA1に
属するバッチジョブの場合、インターバル回数は50
回、インターバル時間は15秒にそれぞれ減少すると共
に、同期処理実行後に0.5秒のバッチ休止期間が設定
されることになり、このパラメータで同期処理が実行さ
れることにより、図7に符号aで示すように、バッチジ
ョブは第1次の制限状態となる。
Thus, for example, in the case of a batch job belonging to the job group A1, the interval count is 50.
The number of times and the interval time are reduced to 15 seconds respectively, and the batch pause period of 0.5 seconds is set after the synchronous processing is executed. By executing the synchronous processing with this parameter, the symbol a in FIG. As shown by, the batch job is in the first restricted state.

【0054】つまり、同期処理のインターバルが短くな
って、その回数が増加することにより、バッチジョブの
処理は抑制されることになるが、その反面、バッチジョ
ブの実行によって排他状態となったデータベースDBの
レコードが早期に解放されることになって、それだけオ
ンライン処理が促進され、また、同期処理実行後にバッ
チジョブの休止期間が設けられることにより、オンライ
ン処理がさらに促進されることになる。
That is, the batch processing is suppressed by shortening the interval of the synchronous processing and increasing the number of times, but on the other hand, the database DB which is in the exclusive state due to the execution of the batch job. Will be released earlier, and online processing will be promoted to that extent, and the online processing will be further promoted by providing the pause period of the batch job after the synchronous processing is executed.

【0055】そして、この1次制限を開始した後、ステ
ップS18で、次の制限制御のために、クロック17が
示す現時点の時刻を1次制限開始時刻として記録する。
After starting the primary restriction, the current time indicated by the clock 17 is recorded as the primary restriction start time in step S18 for the next restriction control.

【0056】以上のバッチジョブに対する制限制御によ
り、通例、オンライン処理のレスポンス時間は短くなる
のであるが、その一方でオンライン処理の発生頻度がさ
らに高くなって、平均レスポンス時間が制限解除基準値
T2未満に短縮されることなく、再び制限実施基準値T
1を超えることがある。この場合、上記ステップS13
からステップS15、S16を経てステップS19を実
行することになり、上記クロック17が示すその時点の
時刻と上記1次制限開始時刻とを比較することにより、
1次制限開始時からの経過時間を判定する。
Although the response time for online processing is usually shortened by the above-mentioned restriction control for batch jobs, the frequency of occurrence of online processing is further increased, and the average response time is less than the restriction release reference value T2. The limit enforcement reference value T
May exceed 1. In this case, the above step S13
From step S15 to step S16, step S19 is executed. By comparing the time at that time indicated by the clock 17 and the primary restriction start time,
The time elapsed from the start of the primary restriction is determined.

【0057】そして、この時間が15分未満のとき、即
ち図7のオンラインピークBのように、1次制限開始か
ら十分時間が経過していない間に平均レスポンス時間が
制限実施基準値T1を再び超えた場合は、しばらく様子
を見るために新たな制限を行なわず、1次制限の状態を
持続する。
Then, when this time is less than 15 minutes, that is, as shown in the online peak B in FIG. 7, the average response time is set to the restriction execution reference value T1 again while the sufficient time has not elapsed from the start of the primary restriction. When it exceeds, the new restriction is not made to see the situation for a while and the state of the primary restriction is maintained.

【0058】これに対し、図7のオンラインピークCの
ように、平均レスポンス時間が制限実施基準値T1を超
える状態が1次制限開始時から15分を経過した後、3
0分を経過する前に発生した場合は、ステップS20を
実行し、図7に符号bで示すように、バッチジョブに対
する第2次の制限を開始する。
On the other hand, as shown in the online peak C of FIG. 7, the state where the average response time exceeds the limitation execution reference value T1 is 3 minutes after 15 minutes have passed from the start of the primary limitation.
If it occurs before 0 minute has elapsed, step S20 is executed, and the secondary limitation on the batch job is started, as indicated by the symbol b in FIG.

【0059】この2次制限は、図3のパラメータテーブ
ルTB2から、当該ジョブが属するグループの各パラメ
ータの増分を読み出し、これを1次制限時の値に加算す
ることにより、バッチジョブに対する制限を強化するも
のである。例えば、現在処理中のバッチジョブがグルー
プA1に属するものとすれば、インターバル回数は、5
0に−5を加えることにより45回となり、インターバ
ル時間は、15に−2を加えることにより13秒とな
り、同期処理実行後のバッチ休止時間は0.5に0.2
を加えることにより、0.7となる。
The secondary restriction is read from the parameter table TB2 in FIG. 3 by reading out the increment of each parameter of the group to which the job belongs and adding this to the value at the time of primary restriction to strengthen the restriction on the batch job. To do. For example, if the batch job currently being processed belongs to the group A1, the interval count is 5
It becomes 45 times by adding -5 to 0, and the interval time becomes 13 seconds by adding -2 to 15 and the batch pause time after the synchronous processing is 0.5 to 0.2.
It becomes 0.7 by adding.

【0060】そして、このように補正された新たなパラ
メータで図4のサブルーチンによる同期処理制御が実行
されることにより、同期処理がより頻繁に行なわれるこ
とになると共に、同期処理実行後のバッチ休止期間の時
間が長くなり、その結果、バッチジョブの処理が一層制
限され、その分だけオンライン処理がさらに促進される
ことになる。
By executing the synchronous processing control by the subroutine of FIG. 4 with the new parameters thus corrected, the synchronous processing is performed more frequently and the batch pause after the synchronous processing is executed. The period of time becomes longer, and as a result, the processing of the batch job is further restricted, and the online processing is further accelerated accordingly.

【0061】なお、図7に示すオンラインピークDのよ
うに、1次制限開始時からの経過時間が15分から30
分までの間に、オンラインピークが複数回発生した場
合、上記各パラメータは、その都度、上記の増分だけ加
えられることになる。したがって、インターバルは次第
に短くなり、同期処理実行後のバッチ休止時間は次第に
長くなる。
As shown in the online peak D shown in FIG. 7, the elapsed time from the start of the primary restriction is 15 minutes to 30 minutes.
If an online peak occurs multiple times by the minute, the above parameters will be added by the above increments each time. Therefore, the interval is gradually shortened, and the batch pause time after execution of the synchronous processing is gradually lengthened.

【0062】また、以上の2次制限にもかかわらず、オ
ンライン処理の平均レスポンス時間が効果的に短縮され
ず、図7のオンラインピークEのように、1次制限開始
時から30分を経過した後に制限実施基準値T1を超え
る事態が発生したときは、このバッチ制限制御において
は、図5のフローチャートのステップS19からステッ
プS21を実行し、この制限制御を中断して、オペレー
タ端末機21にその状態を通知する。
In addition, despite the above-mentioned secondary restriction, the average response time of online processing was not effectively shortened, and 30 minutes had elapsed from the start of the primary restriction as shown by online peak E in FIG. When a situation in which the limit execution reference value T1 is exceeded later occurs, in this batch limit control, steps S19 to S21 of the flowchart of FIG. 5 are executed, the limit control is interrupted, and the operator terminal 21 is notified of that. Notify the status.

【0063】これにより、オペレータは、上記端末機2
1からバッチ処理部11に対してバッチジョブを一時停
止させるためのコマンドを発するなどの処理を行なうこ
とになり、その結果、オンライン処理のレスポンスの著
しい悪化が未然に回避されることになる。
As a result, the operator operates the terminal 2
From 1 to the batch processing unit 11, processing such as issuing a command for temporarily stopping the batch job is performed, and as a result, a significant deterioration in the response of the online processing is avoided.

【0064】また、上記のような1次制限又は2次制限
を実行したことにより、オンライン処理の平均レスポン
ス時間が制限解除基準値T2未満となったときは、ステ
ップS13、S14を経てステップS22を実行し、各
パラメータを図3のパラメータテーブルTB2のバッチ
非制限時の値にリセットする。これにより、図7に符号
cで示すように、バッチジョブの処理状態はオンライン
優先時間帯における非制限状態に復帰することになる。
When the average response time of the online processing becomes less than the limit release reference value T2 due to the execution of the above-described first-order limitation or second-order limitation, the steps S13 and S14 are followed by the step S22. Execution is performed, and each parameter is reset to the value when the batch is not restricted in the parameter table TB2 of FIG. As a result, the processing status of the batch job returns to the non-restricted status in the online priority time zone, as indicated by the symbol c in FIG.

【0065】そして、その後、ステップS23で、ステ
ップS15でカウントしているオンラインピークの発生
回数、及びステップS18で設定した1次制限開始時刻
をクリアし、再びオンラインピークが発生した場合の制
御に備える。
Then, in step S23, the number of times of occurrence of the online peak counted in step S15 and the primary restriction start time set in step S18 are cleared to prepare for the control when the online peak occurs again. .

【0066】また、1次制限又は2次制限の実行後、オ
ンラインピークの発生はなくなったが、平均レスポンス
時間が上記制限解除基準値T2未満に低下することもな
く、図6の領域Bに属する状態が持続する場合は、バッ
チジョブに対する制限は、その時点の状態を維持するこ
とになる。
Although the online peak does not occur after the primary restriction or the secondary restriction is executed, the average response time does not fall below the restriction cancellation reference value T2 and belongs to the area B in FIG. If the state persists, the limit for batch jobs will be to maintain the current state.

【0067】さらに、図1のクロック17で計時してい
る現在の時刻がバッチ優先時間帯(例えば午後5時〜翌
日の午前9時)に移行した場合は、ステップS11から
ステップ24を実行し、上記各パラメータの値として、
図3のパラメータテーブルTB2からバッチ優先時間帯
の値を読み出し、その値を用いてバッチジョブを実行す
る。
Further, when the current time measured by the clock 17 in FIG. 1 shifts to the batch priority time zone (for example, 5 pm to 9 am the next day), steps S11 to 24 are executed, As the value of each of the above parameters,
The value of the batch priority time zone is read from the parameter table TB2 of FIG. 3, and the batch job is executed using the value.

【0068】この場合の値は、オンライン処理のレスポ
ンスの悪化が問題となることは少ないので、インターバ
ル回数及びインターバル時間とも大きな値とされ、か
つ、同期処理実行後の休止期間の設定も行なわれない。
したがって、バッチジョブが連続的、集中的に実行さ
れ、その処理が促進されることになる。
In this case, since the deterioration of the response of the online processing is unlikely to be a problem, both the number of intervals and the interval time are set to a large value, and the pause period after the synchronous processing is not set. .
Therefore, batch jobs are executed continuously and intensively, and the processing thereof is promoted.

【0069】なお、以上の説明はグループA1に属する
バッチジョブを例にとって行なったが、図3のパラメー
タテーブルTB2では、各制御パラメータがバッチジョ
ブの属性に応じて設定され、例えば、優先度の高いバッ
チジョブは優先度の低いジョブより制限の度合いが低く
されることにより、その処理の著しい遅れが防止され、
また、オンライン処理に対する妨げとなる度合いが高い
ものは、その度合いが低いジョブより制限の度合いが高
くされることにより、オンライン処理の良好なレスポン
スが維持されるなど、バッチジョブに対する制限が、各
ジョブの属性に応じて木目細かく行われることになる。
Although the above description has been made by taking the batch job belonging to the group A1 as an example, in the parameter table TB2 of FIG. 3, each control parameter is set according to the attribute of the batch job, and for example, has a high priority. Batch jobs are less restricted than lower priority jobs, which prevents significant delays in their processing.
For jobs that have a high degree of obstruction to online processing, the degree of restriction is set higher than for jobs with a low degree to maintain a good response of online processing. It will be done finely according to the attribute.

【0070】そして、制御パラメータをバッチジョブの
グループごとに記録することにより、その設定や変更を
バッチジョブのグループごとに一括して行なうことが可
能とされている。
By recording the control parameters for each group of batch jobs, it is possible to collectively set or change them for each group of batch jobs.

【0071】[0071]

【発明の効果】以上のように本発明によれば、オンライ
ン処理とバッチジョブとが並行して処理されるシステム
において、レスポンス時間が所定値を超える等のオンラ
イン処理の待機状態が発生したときに、その発生状況に
応じてバッチジョブの制限制御が行なわれることにな
る。
As described above, according to the present invention, in a system in which online processing and batch jobs are processed in parallel, when a standby state for online processing occurs, such as when the response time exceeds a predetermined value. The batch job restriction control is performed according to the occurrence status.

【0072】これにより、バッチジョブを時間帯等に応
じて画一的に制限する場合のような必要以上の制限を回
避しながら、オンライン処理のレスポンスの悪化が効果
的に解消ないし回避されることになり、その結果、ホス
トコンピュータの全体としての処理能力を低下させるこ
となく、オンライン処理が常に良好に実行されることに
なる。
As a result, it is possible to effectively eliminate or avoid the deterioration of the response of the online processing while avoiding the unnecessary limitation such as the case where the batch job is uniformly limited according to the time zone or the like. As a result, the online processing is always executed well without deteriorating the overall processing capacity of the host computer.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本発明の実施の形態に係るシステムのハード
構成の説明図である。
FIG. 1 is an explanatory diagram of a hardware configuration of a system according to an embodiment of the present invention.

【図2】 同実施の形態におけるジョブグループテーブ
ルの構成図である。
FIG. 2 is a configuration diagram of a job group table in the embodiment.

【図3】 同じくパラメータテーブルの構成図である。FIG. 3 is also a configuration diagram of a parameter table.

【図4】 同じく同期処理制御の動作を示すフローチャ
ートである。
FIG. 4 is a flowchart showing an operation of synchronous processing control.

【図5】 同じくバッチ制限制御の動作を示すフローチ
ャートである。
FIG. 5 is a flow chart showing the operation of batch limitation control in the same manner.

【図6】 同じくオンライン処理のレスポンス時間の領
域図である。
FIG. 6 is a region diagram of a response time of online processing similarly.

【図7】 同じくバッチ制限制御の実行状態を示すタイ
ムチャートである。
FIG. 7 is a time chart showing an execution state of batch limitation control.

【符号の説明】[Explanation of symbols]

10 ホストコンピュータ 11 バッチ処理部(バッチ実行手段) 12 オンライン処理部(オンライン実行手段) 15 バッチ制御部(バッチ制御手段) DB データベース TB2 パラメータ記録手段(パラメータテーブ
ル)
10 Host Computer 11 Batch Processing Unit (Batch Execution Means) 12 Online Processing Unit (Online Execution Means) 15 Batch Control Unit (Batch Control Means) DB Database TB2 Parameter Recording Means (Parameter Table)

Claims (11)

【特許請求の範囲】[Claims] 【請求項1】 オンライン処理実行手段及びバッチジョ
ブ実行手段により、共通のデータベースに対してオンラ
イン処理とバッチジョブとを並行して実行するシステム
のバッチ制御システムであって、上記両実行手段による
オンライン処理とバッチジョブの並行処理中におけるオ
ンライン処理の待機状態の発生を検出する待機状態検出
手段と、該検出手段によりオンライン処理の待機状態が
検出されたときに、その待機状態が軽減されるように、
上記バッチジョブ実行手段によるバッチジョブ実行時の
制御条件を変更するバッチジョブ制御手段とを有するこ
とを特徴とするオンライン併用システムのバッチ制御シ
ステム。
1. A batch control system of a system for executing online processing and batch jobs in parallel to a common database by means of the online processing executing means and the batch job executing means, wherein the online processing is performed by both of the executing means. And a standby state detecting means for detecting the occurrence of the standby state of the online processing during the parallel processing of the batch job, and when the standby state of the online processing is detected by the detecting means, the standby state is reduced,
A batch control system for an online combination system, comprising: a batch job control means for changing a control condition when the batch job is executed by the batch job execution means.
【請求項2】 待機状態検出手段は、所定件数のオンラ
イン処理又は所定時間内に発生するオンライン処理の平
均レスポンス時間に基づいてオンライン処理の待機状態
の発生を検出することを特徴とする請求項1に記載のオ
ンライン併用システムのバッチ制御システム。
2. The standby state detection means detects the occurrence of a standby state of online processing based on an average response time of a predetermined number of online processes or online processing that occurs within a predetermined time. Batch control system of the online combination system described in.
【請求項3】 バッチジョブ実行手段が、所定の処理の
所定実行回数ごと、又はジョブ開始時もしくは前回の同
期処理実行時からの所定経過時間ごとの少なくとも一方
のインターバルでデータベースに対する同期処理を行な
うように構成され、かつ同期処理実行後にバッチジョブ
の休止期間の設定が可能とされているシステムにおい
て、バッチジョブ制御手段は、バッチジョブの制御条件
として、上記同期処理のインターバルとなる実行回数も
しくは経過時間、又は上記バッチジョブ休止期間の時間
のうちの少なくとも一つのパラメータを変更することを
特徴とする請求項1又は請求項2に記載のオンライン併
用システムのバッチ制御システム。
3. The batch job executing means performs the synchronization processing on the database at least once every predetermined number of times of predetermined processing, or at least one of every predetermined elapsed time from the start of the job or the previous execution of the synchronization processing. In the system configured as described above and capable of setting the pause period of the batch job after the synchronous processing is executed, the batch job control means uses the number of execution times or the elapsed time as the interval of the synchronous processing as the control condition of the batch job. Alternatively, at least one parameter of the batch job pause period is changed, and the batch control system of the online combination system according to claim 1 or 2.
【請求項4】 パラメータとして、通常時のパラメータ
と、バッチジョブの実行を通常時より所定量制限する1
次制限パラメータと、さらに制限度合いを高くする2次
制限パラメータとが設定されており、バッチジョブ制御
手段は、通常時のパラメータから1次制限パラメータに
変更した後、オンライン処理の待機状態が解消されない
ときに、2次制限パラメータを用いることを特徴とする
請求項3に記載のオンライン併用システムのバッチ制御
システム。
4. A parameter for a normal time as a parameter and a limit for executing a batch job by a predetermined amount from the normal time.
The next limit parameter and the second limit parameter for further increasing the limit degree are set, and the batch job control means does not cancel the standby state of the online processing after changing from the normal parameter to the first limit parameter. The batch control system of the online combination system according to claim 3, wherein a secondary limiting parameter is sometimes used.
【請求項5】 複数のバッチジョブが実行されるシステ
ムにおいて、処理の優先度又はオンライン処理を妨げる
度合いの少なくとも一方の属性に基づいて分類したバッ
チジョブのグループごとにパラメータを記録したパラメ
ータ記録手段が備えられ、かつ、バッチジョブ制御手段
は、上記パラメータ記録手段から現在実行中のバッチジ
ョブが属するグループについてのパラメータを読み出し
て用いることを特徴とする請求項3又は請求項4に記載
のオンライン併用システムのバッチ制御システム。
5. In a system in which a plurality of batch jobs are executed, there is provided a parameter recording means for recording parameters for each group of batch jobs classified based on at least one of the priority of processing and the degree of obstructing online processing. 5. The online combination system according to claim 3 or 4, wherein the batch job control means is provided and uses the parameter for the group to which the currently executing batch job belongs, read from the parameter recording means. Batch control system.
【請求項6】 オンライン処理実行手段及びバッチジョ
ブ実行手段により、共通のデータベースに対してオンラ
イン処理とバッチジョブとが並行して実行され、かつ上
記両実行手段によるオンライン処理とバッチジョブの並
行処理中におけるオンライン処理の実行状態を監視する
オンライン処理監視手段が備えられたシステムのバッチ
制御用プログラムであって、コンピュータを、上記オン
ライン処理監視手段による監視結果に基づいてオンライ
ン処理に待機状態が発生しているか否かを判定する待機
状態判定手段、及び該判定手段によりオンライン処理の
待機状態の発生が判定されたときに、その待機状態が軽
減されるように、上記バッチジョブ実行手段によるバッ
チジョブ実行時の制御条件を変更するバッチジョブ制御
手段として機能させることを特徴とするオンライン併用
システムのバッチ制御用プログラム。
6. The online processing execution means and the batch job execution means execute online processing and batch jobs in parallel with respect to a common database, and the online processing and batch jobs are executed in parallel by both execution means. Is a batch control program for a system provided with an online processing monitoring means for monitoring the execution status of online processing in a computer, in which a standby state occurs in the online processing based on the monitoring result by the online processing monitoring means. When the batch job is executed by the batch job executing means, the standby state determining means for determining whether or not the standby state is reduced when the online state waiting state is determined by the determining means Function as a batch job control unit that changes the control conditions of A program for batch control of an online combination system characterized by the following.
【請求項7】 コンピュータを待機状態判定手段として
機能させるときに、所定件数のオンライン処理又は所定
時間内に発生するオンライン処理の平均レスポンス時間
に基づいてオンライン処理の待機状態の発生を判定する
ように機能させることを特徴とする請求項6に記載のオ
ンライン併用システムのバッチ制御用プログラム。
7. When the computer functions as a standby state determination means, it is determined whether or not a standby state of online processing occurs based on an average response time of a predetermined number of online processes or online processing that occurs within a predetermined time. The program for batch control of the online combination system according to claim 6, which is made to function.
【請求項8】 バッチジョブ実行手段が、所定の処理の
所定実行回数ごと、又はジョブ開始時もしくは前回の同
期処理実行時からの所定経過時間ごとの少なくとも一方
のインターバルでデータベースに対する同期処理を行な
うように構成され、かつ同期処理実行後にバッチジョブ
の休止期間の設定が可能とされたシステムに用いられる
プログラムであって、コンピュータをバッチジョブ制御
手段として機能させるときに、バッチジョブの制御条件
として、上記同期処理のインターバルとなる実行回数も
しくは経過時間、又は上記バッチジョブ休止期間の時間
のうちの少なくとも一つのパラメータを変更するように
機能させることを特徴とする請求項6又は請求項7に記
載のオンライン併用システムのバッチ制御用プログラ
ム。
8. The batch job executing means performs synchronous processing on the database at least once every predetermined number of times of predetermined processing, or at least one of predetermined time elapsed from the start of the job or the previous synchronous processing execution. And a program used in a system capable of setting a pause period of a batch job after the synchronous processing is executed, wherein when the computer functions as a batch job control unit, 8. The online system according to claim 6 or 7, wherein at least one parameter of the number of times of execution or an elapsed time that is an interval of the synchronous processing or the time of the batch job suspension period is changed. Program for batch control of combined system.
【請求項9】 パラメータとして、通常時のパラメータ
と、バッチジョブの実行を通常時より所定量制限する1
次制限パラメータと、さらに制限度合いを高くする2次
制限パラメータとが設定されているシステムに用いられ
るプログラムであって、コンピュータをバッチジョブ制
御手段として機能させるときに、通常時のパラメータか
ら1次制限パラメータに変更した後、オンライン処理の
待機状態が解消されないときに、2次制限パラメータを
用いるように機能させることを特徴とする請求項8に記
載のオンライン併用システムのバッチ制御用プログラ
ム。
9. A parameter for a normal time as a parameter and a limit for executing a batch job by a predetermined amount from the normal time 1
A program used in a system in which a secondary restriction parameter and a secondary restriction parameter for further increasing the degree of restriction are set, and when the computer is made to function as batch job control means, the primary restriction is performed from the normal parameter. 9. The program for batch control of an online combination system according to claim 8, wherein the program is made to function so as to use the secondary restriction parameter when the standby state of the online processing is not resolved after changing to the parameter.
【請求項10】 複数のバッチジョブが実行され、か
つ、処理の優先度又はオンライン処理を妨げる度合いの
少なくとも一方の属性に基づいて分類したバッチジョブ
のグループごとにパラメータを記録したパラメータ記録
手段が備えられたシステムに用いられるプログラムであ
って、コンピュータをバッチジョブ制御手段として機能
させるときに、上記パラメータ記録手段から現在実行中
のバッチジョブが属するグループについてのパラメータ
を読み出して用いるように機能させることを特徴とする
請求項8又は請求項9に記載のオンライン併用システム
のバッチ制御用プログラム。
10. A parameter recording means for recording a parameter for each group of batch jobs in which a plurality of batch jobs are executed, and which are classified based on at least one of the priority of processing and the degree of obstructing online processing. A program used in the system described above, when the computer is caused to function as a batch job control unit, the parameter recording unit is caused to read and use a parameter for a group to which the currently executing batch job belongs. 10. The batch control program for the online combination system according to claim 8 or 9.
【請求項11】 請求項6から請求項10のいずれかに
記載のプログラムを記録したコンピュータ読み取り可能
な記録媒体。
11. A computer-readable recording medium in which the program according to any one of claims 6 to 10 is recorded.
JP2001271458A 2001-09-07 2001-09-07 Batch control system for online combination system, program for batch control of online combination system, and recording medium recording the program Expired - Fee Related JP5058416B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001271458A JP5058416B2 (en) 2001-09-07 2001-09-07 Batch control system for online combination system, program for batch control of online combination system, and recording medium recording the program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001271458A JP5058416B2 (en) 2001-09-07 2001-09-07 Batch control system for online combination system, program for batch control of online combination system, and recording medium recording the program

Publications (2)

Publication Number Publication Date
JP2003085133A true JP2003085133A (en) 2003-03-20
JP5058416B2 JP5058416B2 (en) 2012-10-24

Family

ID=19096963

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001271458A Expired - Fee Related JP5058416B2 (en) 2001-09-07 2001-09-07 Batch control system for online combination system, program for batch control of online combination system, and recording medium recording the program

Country Status (1)

Country Link
JP (1) JP5058416B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008092167A (en) * 2006-09-29 2008-04-17 Fuji Xerox Co Ltd Data processor
JP2008152542A (en) * 2006-12-18 2008-07-03 Hitachi Information Systems Ltd Batch job rerun control system
JP2010218268A (en) * 2009-03-17 2010-09-30 Nec Corp Parallel processing system, on-line processor, batch processor, parallel processing method, and parallel processing program
WO2013171854A1 (en) * 2012-05-16 2013-11-21 株式会社日立製作所 Calculator, thread allocation management method, and program

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01231160A (en) * 1988-03-11 1989-09-14 Hitachi Ltd Device for operating electronic computer system
JPH11102349A (en) * 1997-09-26 1999-04-13 Nec Corp Load control method for memory sharing multiprocessor system
JP2001134476A (en) * 1999-11-08 2001-05-18 Hitachi Ltd Method for updating data base in a batch

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01231160A (en) * 1988-03-11 1989-09-14 Hitachi Ltd Device for operating electronic computer system
JPH11102349A (en) * 1997-09-26 1999-04-13 Nec Corp Load control method for memory sharing multiprocessor system
JP2001134476A (en) * 1999-11-08 2001-05-18 Hitachi Ltd Method for updating data base in a batch

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008092167A (en) * 2006-09-29 2008-04-17 Fuji Xerox Co Ltd Data processor
JP2008152542A (en) * 2006-12-18 2008-07-03 Hitachi Information Systems Ltd Batch job rerun control system
JP2010218268A (en) * 2009-03-17 2010-09-30 Nec Corp Parallel processing system, on-line processor, batch processor, parallel processing method, and parallel processing program
WO2013171854A1 (en) * 2012-05-16 2013-11-21 株式会社日立製作所 Calculator, thread allocation management method, and program

Also Published As

Publication number Publication date
JP5058416B2 (en) 2012-10-24

Similar Documents

Publication Publication Date Title
Buttazzo et al. RED: Robust earliest deadline scheduling
US8959402B2 (en) Method for preemptively restarting software in a multi-subsystem mobile communication device to increase mean time between failures
JP2001318742A (en) Computer system and computer readable recording medium
JP4768354B2 (en) Job management apparatus, job management method, and job management program
US7120911B1 (en) Processor power-saving control method, storage medium, and processor power-saving control device
JP4387970B2 (en) Data I / O program, device, and method
KR20060008983A (en) Frequency control apparatus, information processing apparatus and program
WO2005106623A1 (en) Cpu clock control device, cpu clock control method, cpu clock control program, recording medium, and transmission medium
US20060248315A1 (en) Stack controller efficiently using the storage capacity of a hardware stack and a method therefor
EP3256951A1 (en) Scheduling volatile memory maintenance events in a multi-processor system
WO2022095862A1 (en) Thread priority adjusting method, terminal, and computer readable storage medium
JP2003085133A (en) Batch control system of on-line compatible system, batch control program of on-line compatible system and recording medium for recording this program
US20090138896A1 (en) Providing a computing system with real-time capabilities
CN113312235A (en) Service quality early warning power capping system with optimized throughput
JP2002073354A (en) Task control device and task contol method
JP2003223335A (en) Out-sourcing system, out-sourcing method, and program for out-sourcing
JP3127880B2 (en) Method of detecting abnormality of monitored device, device thereof, and machine-readable recording medium storing program
JPS63300326A (en) Transaction execution schedule system
JP2666732B2 (en) Load control method for computer system
JP3097873B2 (en) Transaction control method
JPH03118637A (en) Dynamic job multiplicity control system
JPH0721063A (en) Computer system monitoring device
JPH1091581A (en) Transaction processing system
JP3711642B2 (en) Processing management system
JP5718712B2 (en) Information processing device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080829

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20090907

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20111115

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20111129

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120104

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120724

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120801

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150810

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees