JP2003048116A - Cutting equipment and cutting method for steel pipe - Google Patents

Cutting equipment and cutting method for steel pipe

Info

Publication number
JP2003048116A
JP2003048116A JP2001239738A JP2001239738A JP2003048116A JP 2003048116 A JP2003048116 A JP 2003048116A JP 2001239738 A JP2001239738 A JP 2001239738A JP 2001239738 A JP2001239738 A JP 2001239738A JP 2003048116 A JP2003048116 A JP 2003048116A
Authority
JP
Japan
Prior art keywords
cutting
steel pipe
pipe
product
axial direction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001239738A
Other languages
Japanese (ja)
Inventor
Yuzuru Monno
譲 門野
Junichiro Murakami
純一郎 村上
Masahiko Iwamoto
理彦 岩本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Nippon Steel Corp
Original Assignee
Mitsubishi Heavy Industries Ltd
Sumitomo Metal Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd, Sumitomo Metal Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP2001239738A priority Critical patent/JP2003048116A/en
Publication of JP2003048116A publication Critical patent/JP2003048116A/en
Pending legal-status Critical Current

Links

Landscapes

  • Shearing Machines (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide cutting equipment and cutting method for a steel pipe, capable of reducing the equipment cost and operation cost. SOLUTION: In this steel pipe cutting equipment adapted to discharge a steel pipe product in the same direction as in the carry-in direction, one or more cutters are arranged in series to constitute one cutting line, in which one steel pipe is carried in the axial direction, crops at both ends of the steel pipe are removed, and the steel pipe is cut in an arbitrary length into the maximum number n of steel pipe products. One cutting line has the minimum number of cutters, which is equal to or larger than (n+1)/2, and one gauge stopper provided to be movable in the axial direction of the steel pipe on the discharge side of the steel pipe product rather from the cutter and be retreated from the discharged steel pipe product. Among the plural cutters, the cutter closest to the gauge stopper is fixed in the axial direction of the steel pipe, and the other cutters are provided movably in the axial direction of the steel pipe. This cutting method for the steel pipe adopts the above cutting equipment.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、製造された1本の
鋼管の両端のクロップを切断除去し複数本の任意の長さ
の製品鋼管に切断する鋼管の切断設備および切断方法に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a steel pipe cutting facility and a cutting method for cutting and removing the crops at both ends of a single manufactured steel pipe to cut into a plurality of product steel pipes having an arbitrary length.

【0002】[0002]

【従来の技術】図3および図4に基づき、従来の鋼管の
切断設備および切断方法を説明する。図3は、製造され
た1本の鋼管の両端のクロップを切断除去し複数本の任
意の長さの製品鋼管に切断する鋼管の切断設備の配置の
説明図であり、図4は図3に示す切断設備を使用する鋼
管の切断方法の説明図である。
2. Description of the Related Art A conventional steel pipe cutting equipment and cutting method will be described with reference to FIGS. FIG. 3 is an explanatory view of the arrangement of a steel pipe cutting facility for cutting and removing the crops at both ends of one manufactured steel pipe to cut into a plurality of product steel pipes having an arbitrary length, and FIG. 4 is shown in FIG. It is explanatory drawing of the cutting method of the steel pipe which uses the cutting equipment shown.

【0003】一般に、ミルで製造されたシ―ムレス鋼管
等の鋼管(以下、「パイプ」という)2を高能率で所定
の長さにミーリングにより切断し製品鋼管(以下、「製
品パイプ」という。)にする鋼管の切断設備(以下、
「切断ライン」という)03には、メタルソーを備えた
切断ヘッド5とパイプクランプ装置6とを搭載した切断
装置4がパイプ2の軸方向に複数台が直列に設置され切
断ラインを構成しており、パイプ2はその軸方向に搬入
される。
Generally, a steel pipe (hereinafter referred to as "pipe") 2 such as a seamless steel pipe manufactured by a mill is cut into a predetermined length with high efficiency by milling, and a product steel pipe (hereinafter referred to as "product pipe"). ) Steel pipe cutting equipment (hereinafter,
A cutting device 4 equipped with a cutting head 5 equipped with a metal saw and a pipe clamp device 6 is installed in series in the axial direction of the pipe 2 to form a cutting line. The pipe 2 is loaded in the axial direction.

【0004】切断装置4のうちの1台は固定式で、他の
切断装置4はパイプ2の任意の切断長に対応するためパ
イプ2の搬入の方向、すなわちパイプ2の軸方向に移動
可能に設置されている。そして、上記のような切断ライ
ン03はミルの製造能力に対応して1ラインまたは複数
ラインが設けられている。
One of the cutting devices 4 is of a fixed type, and the other cutting device 4 is movable in the carrying-in direction of the pipe 2, that is, the axial direction of the pipe 2, since it corresponds to an arbitrary cutting length of the pipe 2. is set up. The cutting line 03 as described above is provided with one line or a plurality of lines corresponding to the manufacturing capacity of the mill.

【0005】図3は示されるものは、従来の切断ライン
03の配置の1例であり、1本のパイプ2の両端のクロ
ップ除去と、パイプ2を最大5本の製品パイプ2−1〜
2−5に切断する切断ラインを2ライン設けた例であ
る。
FIG. 3 shows an example of the arrangement of the conventional cutting line 03. The removal of crops at both ends of one pipe 2 and the pipe 2 having a maximum of 5 product pipes 2-1 to 2-1.
This is an example in which two cutting lines for cutting into 2-5 are provided.

【0006】図3において、1はミル出側テーブル、2
は切断されるパイプ、03は切断ラインでパイプ2の両
端のクロップを除去して5本に切断する6台の切断装置
4−1〜4−6が設置されている。(以下、個々の切断
装置を特に区別しないときは符号「4」を用い、個々の
切断装置をいうときは符号「4−1」〜「4−6」を用
いる。)各切断装置4にはメタルソーを備えた切断ヘッ
ド5とパイプクランプ装置6とが搭載されている。8は
切断された製品パイプ2−1〜2−5を排出する切断ラ
イン出側テーブルである。
In FIG. 3, 1 is a mill exit side table, 2
Is a pipe to be cut, and 03 is a cutting line, and six cutting devices 4-1 to 4-6 are installed to remove the crops at both ends of the pipe 2 and cut into five. (Hereinafter, when the individual cutting devices are not particularly distinguished, the reference numeral "4" is used, and when referring to the individual cutting devices, the reference numerals "4-1" to "4-6" are used.) A cutting head 5 equipped with a metal saw and a pipe clamp device 6 are mounted. Reference numeral 8 is a cutting line delivery side table for discharging the cut product pipes 2-1 to 2-5.

【0007】03’、8’はもう一方の切断ラインおよ
び切断ライン出側テーブルで、ミルの製造能力に対応し
て上記切断ライン03、切断ライン出側テーブル8と並
列に配置されている。
Reference numerals 03 'and 8'represent the other cutting line and the cutting line delivery side table, which are arranged in parallel with the cutting line 03 and the cutting line delivery side table 8 in correspondence with the manufacturing capacity of the mill.

【0008】上記のように配置された従来の切断ライン
03による鋼管の切断方法を図4に基づき説明する。図
4(a)に示すように、ミルにより製造されたパイプ2
は、ミル出側テーブル1から切断ライン03へ搬入され
ると、パイプ2の先頭のクロップ9の切断位置を、パイ
プ2の進行方向最下流側に配置された固定切断装置4−
1の切断位置に合わせ、パイプ2は固定切断装置4−1
に搭載されたパイプクランプ装置6でクランプされる。
A method of cutting a steel pipe by the conventional cutting line 03 arranged as described above will be described with reference to FIG. As shown in FIG. 4 (a), the pipe 2 manufactured by a mill
Is carried into the cutting line 03 from the mill outlet table 1, the cutting position of the leading crop 9 of the pipe 2 is fixed to the fixed cutting device 4-positioned on the most downstream side in the traveling direction of the pipe 2.
According to the cutting position of 1, the pipe 2 is a fixed cutting device 4-1.
It is clamped by the pipe clamp device 6 mounted on the.

【0009】他の切断装置はパイプ2の軸方向に移動可
能な移動切断装置4−2、4−3、4−4、4−5、4
−6であり、それぞれ予め定められた製品パイプ2−1
〜2−5の長さにしたがって所定の位置へ移動してお
り、固定切断装置4−1の動作と同時にそれぞれの移動
切断装置4−2〜4−6に搭載されたパイプクランプ装
置6でパイプ2をクランプする。
The other cutting devices are movable cutting devices 4-2, 4-3, 4-4, 4-5, 4 which are movable in the axial direction of the pipe 2.
-6, each of which is a predetermined product pipe 2-1
2-5 are moved to a predetermined position according to the length, and at the same time as the operation of the fixed cutting device 4-1, the pipes are clamped by the pipe clamp devices 6 mounted on the respective moving cutting devices 4-2-4-6. Clamp 2

【0010】次いで図4(b)に示すように、6台の切
断装置4は切断ヘッド5を一斉に作動させパイプ2を両
側から切断する。
Next, as shown in FIG. 4B, the six cutting devices 4 actuate the cutting heads 5 simultaneously to cut the pipe 2 from both sides.

【0011】切断されたパイプ2は図4(c)に示すよ
うに、クロップ9、10を分離除去し、製品パイプ2−
1〜2−5として、パイプ2の搬入の方向と同方向で切
断ライン03から排出され、切断ライン出側テーブル8
で搬送されていく。
As shown in FIG. 4 (c), the cut pipe 2 has the crops 9 and 10 separated and removed, and the product pipe 2-
1 to 2-5 are discharged from the cutting line 03 in the same direction as the loading direction of the pipe 2, and the cutting line exit side table 8
Will be transported in.

【0012】[0012]

【発明が解決しようとする課題】以上説明した従来の鋼
管の切断装置および切断方法の場合、切断ラインでは1
本のパイプを両端のクロップ除去とn本の製品パイプに
切断する場合には必ずn+1台の切断装置が必要とな
り、パイプを1度に切断できる点では能率的であるが設
備費が高くなる問題がある。
In the case of the conventional steel pipe cutting apparatus and cutting method described above, the number of the cutting lines is 1
When cropping two pipes at both ends and cutting into n product pipes, n + 1 cutting devices are always required, which is efficient in that the pipes can be cut at one time, but the equipment cost is high. There is.

【0013】本発明は、上記のような従来の鋼管の切断
装置および切断方法の問題点を解消し、設備費と運転コ
ストを低減できる鋼管の切断設備および切断方法を提供
することを目的とするものである。
It is an object of the present invention to provide a steel pipe cutting equipment and a cutting method which can solve the above problems of the conventional steel pipe cutting device and cutting method and can reduce the equipment cost and the operating cost. It is a thing.

【0014】[0014]

【課題を解決するための手段】(1)本発明は、上記の
課題を解決するためになされたものであって、その第1
の手段として、複数の切断装置を直列に配置して1列の
切断ラインを構成し、1本の鋼管をその軸方向に搬入し
同鋼管の両端のクロップを除去し最大n本の任意の長さ
の製品鋼管に切断し、同製品鋼管を前記搬入の方向と同
方向に排出する鋼管の切断設備において、前記1列の切
断ラインが、(n+1)/2以上で最小の台数の切断装
置と、同切断装置より前記製品鋼管の排出側に前記鋼管
の軸方向に移動可能かつ排出される前記製品鋼管から退
避可能に設けられた1台のゲージストッパとを有し、前
記複数の切断装置のうち前記ゲージストッパに最も近い
側の切断装置を前記鋼管の軸方向に固定して設け、他の
切断装置を前記鋼管の軸方向に移動可能に設けてなるこ
とを特徴とする鋼管の切断設備を提供する。
(1) The present invention has been made in order to solve the above-mentioned problems.
As a means of arranging, a plurality of cutting devices are arranged in series to form one line of cutting line, one steel pipe is carried in the axial direction, the crops at both ends of the steel pipe are removed, and a maximum of n arbitrary lengths are removed. In a steel pipe cutting facility for cutting into the product steel pipe of No. 1 and discharging the product steel pipe in the same direction as the carrying-in direction, the one line of the cutting line is (n + 1) / 2 or more and the minimum number of cutting devices. , A single gauge stopper provided on the discharge side of the product steel pipe from the cutting device so as to be movable in the axial direction of the steel pipe and retractable from the product steel pipe discharged, Among them, a cutting device on the side closest to the gauge stopper is fixedly provided in the axial direction of the steel pipe, and another cutting device is provided so as to be movable in the axial direction of the steel pipe. provide.

【0015】従来設備においては1本の鋼管の両端のク
ロップを除去しn本の製品鋼管に切断する場合には必ず
(n+1)台の切断装置4が必要となり、鋼管を1度に
切断できる点では能率的であるが設備費が高くなったと
ころを、第1の手段によれば、上記構成により、1本の
鋼管の両端のクロップを除去しn本の製品鋼管に切断す
る場合には(n+1)/2以上で最小の台数の切断装置
と1台のゲージストッパで対応できる。
In the conventional equipment, when removing the crops at both ends of one steel pipe and cutting into n product steel pipes, (n + 1) cutting devices 4 are necessarily required, and the steel pipes can be cut at one time. According to the first means, when the cost is high but the equipment cost is high, when the crops at both ends of one steel pipe are removed to cut into n product steel pipes, ( A minimum number of cutting devices (n + 1) / 2 or more and one gauge stopper can be used.

【0016】(2)第2の手段としては、第1の手段の
鋼管の切断設備において、前記製品鋼管の最大本数nが
5または4であり、前記1列の切断ラインが3台の前記
切断装置と1台の前記ゲージストッパとを有してなるこ
とを特徴とする鋼管の切断設備を提供する。
(2) As a second means, in the steel pipe cutting equipment of the first means, the maximum number n of the product steel pipes is 5 or 4, and the one line of the cutting line has three cutting lines. There is provided a steel pipe cutting facility comprising a device and one gauge stopper.

【0017】第2の手段によれば、採用されることが多
い製品鋼管の最大本数nが5または4の鋼管の切断設備
において、第1の手段の作用を奏するものとなる。
According to the second means, the function of the first means can be obtained in the cutting equipment for steel pipes in which the maximum number n of product steel pipes which is often adopted is 5 or 4.

【0018】(3)また、第3の手段として、1本の鋼
管の両端のクロップを除去しn本の任意の長さの製品鋼
管に切断する鋼管の切断方法において、第1の手段また
は第2の手段の鋼管の切断設備を用いて、前記台数の前
記切断装置で同鋼管を切断し、次いで同鋼管の残部の先
頭を前記ゲージストッパに当接させて前記台数の切断装
置で切断することを特徴とする鋼管の切断方法を提供す
る。
(3) As a third means, in the method for cutting a steel pipe in which the crops at both ends of one steel pipe are removed to cut into n product steel pipes of arbitrary length, the first means or Using the steel pipe cutting equipment of the second means, the steel pipe is cut by the cutting device of the number, and then the leading end of the rest of the steel pipe is brought into contact with the gauge stopper to cut by the cutting device of the number. A method for cutting a steel pipe is provided.

【0019】第3の手段によれば、第1の手段または第
2の手段の作用により、1本の鋼管の両端のクロップを
除去し複数の製品鋼管に切断する場合に従来方法より少
ない台数の切断装置と1台のゲージストッパで対応でき
る。
According to the third means, by the action of the first means or the second means, when the crops at both ends of one steel pipe are removed and a plurality of product steel pipes are cut, a smaller number of units than the conventional method is used. A cutting device and one gauge stopper can be used.

【0020】[0020]

【発明の実施の形態】図1および図2に基づき本発明の
実施の一形態に係る鋼管の切断装置および切断方法を説
明する。図1は、本実施の形態の鋼管の切断設備の配置
の説明図であり、図2は図1に示す切断設備を使用する
鋼管の切断方法の説明図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A steel pipe cutting apparatus and a cutting method according to an embodiment of the present invention will be described with reference to FIGS. 1 and 2. FIG. 1 is an explanatory diagram of an arrangement of a steel pipe cutting equipment according to the present embodiment, and FIG. 2 is an explanatory diagram of a steel pipe cutting method using the cutting equipment shown in FIG. 1.

【0021】図1においては、製造された1本のパイプ
の両端のクロップを切断除去し複数本の任意の長さの製
品パイプに切断する本実施の形態の鋼管の切断設備(切
断ライン)3を、2ライン設けたものを示している。な
お、図1、図2において前述の図3、図4におけるもの
と同じ機能のものには同じ符号を付している。
In FIG. 1, a steel pipe cutting facility (cutting line) 3 of the present embodiment for cutting and removing the crops at both ends of one manufactured pipe to cut into a plurality of product pipes of arbitrary length. Is provided with two lines. In FIGS. 1 and 2, the same functions as those in FIGS. 3 and 4 described above are denoted by the same reference numerals.

【0022】本実施の形態の切断ライン3は、1本のパ
イプ2を両端クロップ除去と最大n本の製品パイプに切
断する場合、1ラインの構成を、(n+1)/2以上で
最小の台数(すなわち、(n+1)/2の端数を切上げ
た台数)の切断装置と1台のゲージストッパとで構成す
るものであり、図1は採用されることが多い製品パイプ
の最大本数nが5の鋼管の切断設備の例である。
In the cutting line 3 of this embodiment, when one pipe 2 is cut at both ends and cut into a maximum of n product pipes, the configuration of one line is (n + 1) / 2 or more and the minimum number of pipes. (I.e., (n + 1) / 2 fractions are rounded up) and one gauge stopper. In FIG. 1, the maximum number n of product pipes that is often adopted is 5. It is an example of a steel pipe cutting facility.

【0023】図1において、1はミル出側テーブル、2
は切断されるパイプ、3は切断ラインであり、切断ライ
ン3には3台の切断装置4と、切断装置4よりパイプ2
の搬入の方向で下流側、すなわち製品パイプ2−1〜2
−5の排出側にゲージストッパ7が設置されている。ゲ
ージストッパ7はパイプ2の搬入の方向、すなわちパイ
プ2の軸方向に移動可能かつ切断した製品パイプ2−1
〜2−5の排出時には製品パイプから退避可能に設置さ
れている。
In FIG. 1, 1 is a mill outlet table, 2
Is a pipe to be cut, 3 is a cutting line, and the cutting line 3 has three cutting devices 4 and the pipe 2 from the cutting device 4.
Of the product pipes 2-1 to 2 in the downstream direction of the loading
A gauge stopper 7 is installed on the discharge side of -5. The gauge stopper 7 is movable in the carrying-in direction of the pipe 2, that is, the axial direction of the pipe 2 and is a cut product pipe 2-1.
It is installed so that it can be retracted from the product pipe at the time of discharge of 2-5.

【0024】切断装置4はそれぞれメタルソーを備えた
切断ヘッド5とパイプクランプ装置6とが搭載されてお
り、下流側から、固定切断装置4−1、移動切断装置4
−2、移動切断装置4−3の順に3台設けられている。
固定切断装置4−1はパイプ2の搬入の方向、すなわち
パイプ2の軸方向に固定されて設けられており、移動切
断装置4−2、4−3はパイプ2の搬入の方向、すなわ
ちパイプ2の軸方向に移動可能に設けられている。
The cutting device 4 is equipped with a cutting head 5 and a pipe clamp device 6 each equipped with a metal saw. From the downstream side, a fixed cutting device 4-1 and a moving cutting device 4 are installed.
-2, three moving cutting devices 4-3 are provided in this order.
The fixed cutting device 4-1 is provided so as to be fixed in the carrying-in direction of the pipe 2, that is, the axial direction of the pipe 2, and the moving cutting devices 4-2 and 4-3 are provided in the carrying-in direction of the pipe 2, that is, the pipe 2. It is provided so as to be movable in the axial direction.

【0025】8は切断された製品パイプ2−1〜2−5
を切断ライン3から排出する切断ライン出側テーブルで
ある。
8 is a cut product pipe 2-1 to 2-5
Is a cutting line delivery side table that discharges from the cutting line 3.

【0026】3’、8’はもう一方の切断ラインおよび
切断ライン出側テーブルであり、ミルの製造能力に対応
して上記切断ライン3、切断ライン出側テーブル8と並
列に配置されている。
Reference numerals 3'and 8'represent the other cutting line and the cutting line delivery side table, which are arranged in parallel with the cutting line 3 and the cutting line delivery side table 8 in accordance with the manufacturing capacity of the mill.

【0027】上記のように配置された従来の上記切断ラ
イン3による鋼管の切断方法を図2に基づき説明する。
図2(a)に示すように、ミルにより製造されたパイプ
2がミル出側テーブル1からその軸方向に切断ライン3
へ搬入されると、まず、パイプ2の先頭のクロップ9の
切断位置を固定切断装置4−1の切断位置に合わせ、固
定切断装置4−1に搭載されたパイプクランプ装置6で
クランプし、他の移動切断装置4−2、4−3は予め定
められた製品パイプ2−1、2−2の切断パイプ長にし
たがって所定の位置へ移動しており、固定切断装置4−
1のパイプクランプ装置6の動作と同時にパイプ2をそ
れぞれの移動切断装置に搭載されたパイプクランプ装置
6でクランプする。
A method of cutting a steel pipe by the conventional cutting line 3 arranged as described above will be described with reference to FIG.
As shown in FIG. 2 (a), a pipe 2 manufactured by a mill has a cutting line 3 extending in the axial direction from a mill outlet table 1.
When it is carried in, first, the cutting position of the leading crop 9 of the pipe 2 is aligned with the cutting position of the fixed cutting device 4-1, and is clamped by the pipe clamp device 6 mounted on the fixed cutting device 4-1. The moving cutting devices 4-2 and 4-3 of FIG. 4 are moved to predetermined positions according to the cutting pipe lengths of the product pipes 2-1 and 2-2 which are predetermined, and the fixed cutting device 4-
Simultaneously with the operation of the first pipe clamp device 6, the pipe 2 is clamped by the pipe clamp device 6 mounted on each moving and cutting device.

【0028】次いで、図2(b)に示すように、3台の
切断装置4−1〜4−3は一斉に切断ヘッド5を作動さ
せパイプ2を切断する。
Next, as shown in FIG. 2 (b), the three cutting devices 4-1 to 4-3 actuate the cutting heads 5 simultaneously to cut the pipe 2.

【0029】切断された製品パイプ2−1、2−2は先
端側のクロップ9を分離除去し、図2(c)に示すよう
に、切断ライン3からパイプ2の搬入の方向と同じ方向
に排出され切断ライン出側テーブル8で搬送されてい
く。この時、ゲージストッパ7は予め固定切断装置4−
1から製品パイプ2−3のパイプ長だけ下流側へ移動し
た位置で製品パイプ2−1、2−2から退避している。
The cut product pipes 2-1 and 2-2 have the crop 9 on the tip side separated and removed, and as shown in FIG. 2 (c), in the same direction as the carrying-in direction of the pipe 2 from the cutting line 3. The sheet is discharged and conveyed on the cutting line output side table 8. At this time, the gauge stopper 7 is previously fixed to the cutting device 4-.
It retreats from the product pipes 2-1 and 2-2 at a position moved to the downstream side by the length of the product pipe 2-3 from 1.

【0030】この排出動作と同時に図2(d)に示すよ
うに、残りのパイプ2を進行させ、製品パイプ2−3と
なる残りのパイプ2の先頭をゲージストッパ7に当接さ
せるとともに、移動切断装置4−2、4−3を予め定め
られた製品パイプ2−4、2−5の長さにしたがって所
定の位置へ移動し、3台の切断装置4それぞれに搭載の
パイプクランプ装置6でパイプ2をクランプする。
At the same time as this discharging operation, as shown in FIG. 2 (d), the remaining pipe 2 is advanced, and the leading end of the remaining pipe 2 to be the product pipe 2-3 is brought into contact with the gauge stopper 7 and moved. The cutting devices 4-2 and 4-3 are moved to predetermined positions according to the predetermined lengths of the product pipes 2-4 and 2-5, and the pipe clamp device 6 mounted on each of the three cutting devices 4 is used. Clamp the pipe 2.

【0031】次いで、図2(e)に示すように、再び上
記3台の切断装置4は切断ヘッド5を一斉に作動させパ
イプ2の残部を切断する。
Then, as shown in FIG. 2 (e), the three cutting devices 4 again actuate the cutting heads 5 simultaneously to cut the remaining part of the pipe 2.

【0032】しかる後、図2(f)に示すように、切断
された製品パイプ2−3、2−4、2−5は後端側のク
ロップ10を分離除去し、パイプ2の搬入の方向と同じ
方向に切断ライン3から排出され、切断ライン出側テー
ブル8で搬送されていく。
After that, as shown in FIG. 2 (f), the cut product pipes 2-3, 2-4, 2-5 are separated and removed from the rear end side crop 10, and the pipe 2 is carried in the direction. It is discharged from the cutting line 3 in the same direction as and is conveyed by the cutting line exit side table 8.

【0033】以上は最大n=5で、n=5本に切断する
場合であるが、n=4または3本の時は2回目のパイプ
の後端を切断しないこととなる。また、n=2または1
本の時は1回目の切断のみで完了する。
The above is the case of cutting n = 5 at maximum and cutting n = 5. However, when n = 4 or 3, the rear end of the second pipe is not cut. Also, n = 2 or 1
In the case of a book, only the first cutting is completed.

【0034】本実施の形態の鋼管の切断設備と切断方法
の効果を、図3、図4に示した従来技術と比べたものを
表1に示す。
Table 1 shows the effects of the steel pipe cutting equipment and the cutting method according to the present embodiment as compared with the prior art shown in FIGS. 3 and 4.

【0035】[0035]

【表1】 [Table 1]

【0036】ミルと切断ライン等の精整設備は、それぞ
れの能力が整合性ある仕様とするため、表1では切断ラ
イン3単独で評価する。設備費、切断時間、比較の数値
は、上記の図1、図2に示した設備構成と切断方法によ
って求めた。なお、比較して示す値は1ラインについて
である。
In the table, the cutting line 3 alone is evaluated in order to make the specifications of the mill and the cutting line, etc., such that the respective capacities are consistent. The equipment cost, the cutting time, and the numerical value for comparison were obtained by the equipment configuration and the cutting method shown in FIGS. 1 and 2 above. The values shown in comparison are for one line.

【0037】表1に示すように切断装置4の単価を1.
0a、ゲージストッパ7の単価を0.2aとすると、従
来技術では設備費は6.0aとなるが、本実施の形態の
設備費は、ゲージストッパ7を1台余分に設置したが切
断装置4の台数を半減させたため設備費は3.2aとな
り、従来技術を1.00とすると本実施の形態の設備費
は0.53となる。
As shown in Table 1, the unit price of the cutting device 4 is 1.
If the unit price of the gauge stopper 7 is 0.2a and the unit cost of the gauge stopper 7 is 0.2a, the equipment cost is 6.0a in the conventional technique. The equipment cost is 3.2a because the number of units has been halved, and the equipment cost of the present embodiment is 0.53 when the conventional technique is 1.00.

【0038】また、従来技術の場合、パイプ2を1本処
理するのにパイプ搬入20秒、切断20秒、パイプ排出
20秒で合計60秒を要するが、本実施の形態の場合、
パイプ搬入20秒、切断20秒、中間排出10秒、切断
20秒、パイプ排出10秒で合計80秒を要する。
Further, in the case of the prior art, it takes a total of 60 seconds for 20 seconds for pipe loading, 20 seconds for cutting, and 20 seconds for pipe discharging to process one pipe 2, but in the case of the present embodiment,
Pipe loading 20 seconds, cutting 20 seconds, intermediate discharge 10 seconds, cutting 20 seconds, pipe discharging 10 seconds, totaling 80 seconds.

【0039】すなわち、切断能率は従来技術を1.00
とすれば本実施の形態は0.75となる。この設備費と
切断能率の関係より、設備費/切断能率は従来技術を
1.00とすれば本実施の形態は0.71となり、約3
0%経済的となる。
That is, the cutting efficiency is 1.00 in the conventional technique.
If so, the present embodiment will be 0.75. From the relationship between the equipment cost and the cutting efficiency, the equipment cost / cutting efficiency is 0.71 in this embodiment when the conventional technology is 1.00, which is about 3
It becomes 0% economical.

【0040】上記の従来技術の切断ライン03では、1
本のパイプ2を両端のクロップ9、10を除去しn本の
製品パイプに切断する場合には必ず(n+1)台の切断
装置4が必要となり、パイプ2を1度に切断できる点で
は能率的であるが設備費が高くなる。しかし、本発明の
上記実施の形態のような切断ライン3の構成にすると、
1本のパイプ2を両端のクロップ9、10を除去しn本
の製品パイプに切断する場合には(n+1)/2(端数
は繰り上げ)台の切断装置4と1台のゲージストッパ7
で対応でき、設備費を低減できる。また、本実施の形態
の設備構成は、両端のクロップ9、10を除去しない切
断方法にも適用することが可能である。
In the above-mentioned prior art cutting line 03, 1
When removing the crops 9 and 10 on both ends of the pipe 2 to cut into n product pipes, (n + 1) cutting devices 4 are necessarily required, which is efficient in that the pipe 2 can be cut at one time. However, the equipment cost is high. However, when the cutting line 3 is configured as in the above embodiment of the present invention,
When cutting one pipe 2 into n product pipes by removing the crops 9 and 10 at both ends, (n + 1) / 2 (fractions are rounded up) cutting devices 4 and one gauge stopper 7
It is possible to deal with, and the equipment cost can be reduced. Further, the equipment configuration of the present embodiment can be applied to a cutting method in which the crops 9 and 10 at both ends are not removed.

【0041】なお、上記の説明はシームレス鋼管につい
て行ったが、溶接鋼管についても本発明を適用すること
が可能であり、同様の効果が得られる。
Although the above description has been made on the seamless steel pipe, the present invention can be applied to a welded steel pipe and the same effect can be obtained.

【0042】以上本発明の実施の形態を説明したが、上
記実施の形態に限定されるものではなく、本発明の範囲
内でその具体的構造に種々の変更を加えてもよいことは
言うまでもない。
Although the embodiments of the present invention have been described above, it is needless to say that the present invention is not limited to the above-mentioned embodiments, and various modifications may be made to the concrete structure within the scope of the present invention. .

【0043】[0043]

【発明の効果】(1)請求項1の発明によれば、鋼管の
切断設備を、複数の切断装置を直列に配置して1列の切
断ラインを構成し、1本の鋼管をその軸方向に搬入し同
鋼管の両端のクロップを除去し最大n本の任意の長さの
製品鋼管に切断し、同製品鋼管を前記搬入の方向と同方
向に排出する鋼管の切断設備において、前記1列の切断
ラインが、(n+1)/2以上で最小の台数の切断装置
と、同切断装置より前記製品鋼管の排出側に前記鋼管の
軸方向に移動可能かつ排出される前記製品鋼管から退避
可能に設けられた1台のゲージストッパとを有し、前記
複数の切断装置のうち前記ゲージストッパに最も近い側
の切断装置を前記鋼管の軸方向に固定して設け、他の切
断装置を前記鋼管の軸方向に移動可能に設けてなるよう
に構成したので、従来設備においては1本の鋼管の両端
のクロップを除去しn本の製品鋼管に切断する場合には
必ず(n+1)台の切断装置が必要となり設備費が高く
なったところを、(n+1)/2以上で最小の台数の切
断装置と1台のゲージストッパで対応でき、設備費を低
減でき、設備費/切削能率も向上して運転コストを低減
できる鋼管の切断設備となる。
(1) According to the invention of claim 1, the steel pipe cutting equipment comprises a plurality of cutting devices arranged in series to form a row of cutting lines, and one steel pipe is arranged in the axial direction thereof. In the cutting equipment for steel pipes, the steel pipes are carried into a pipe and the crops at both ends of the steel pipes are removed to cut up to n product steel pipes of arbitrary length, and the product steel pipes are discharged in the same direction as the carry-in direction. The cutting line of (n + 1) / 2 or more is the minimum number of cutting devices, and is movable from the cutting device to the discharge side of the product steel pipe in the axial direction of the steel pipe and can be retracted from the discharged product steel pipe. One gauge stopper provided, and the cutting device closest to the gauge stopper among the plurality of cutting devices is fixedly provided in the axial direction of the steel pipe, and another cutting device is provided for the steel pipe. Since it is configured to be movable in the axial direction, In the conventional equipment, when removing the crops at both ends of one steel pipe and cutting into n product steel pipes, (n + 1) cutting devices are always required and the equipment cost becomes (n + 1) / With a minimum of two or more cutting devices and a single gauge stopper, the equipment cost can be reduced and the equipment cost / cutting efficiency can be improved to reduce the operating cost.

【0044】(2)請求項2の発明によれば、請求項1
に記載の鋼管の切断設備において、前記製品鋼管の最大
本数nが5または4であり、前記1列の切断ラインが3
台の前記切断装置と1台の前記ゲージストッパとを有し
てなるように構成したので、採用されることが多い製品
鋼管の最大本数nが5または4の鋼管の切断設備におい
て、請求項1に発明の効果を奏するものが得られる。
(2) According to the invention of claim 2, claim 1
In the cutting equipment for steel pipes according to [4], the maximum number n of the product steel pipes is 5 or 4, and the cutting line in one row is 3
A cutting equipment for steel pipes having a maximum number n of product steel pipes of 5 or 4 which is often adopted because it is configured to have one cutting device and one gauge stopper. What has the effect of the invention is obtained.

【0045】(3)請求項3の発明によれば、鋼管の切
断方法を、1本の鋼管の両端のクロップを除去しn本の
任意の長さの製品鋼管に切断する鋼管の切断方法におい
て、請求項1または請求項2に記載の鋼管の切断設備を
用いて、前記台数の前記切断装置で同鋼管を切断し、次
いで同鋼管の残部の先頭を前記ゲージストッパに当接さ
せて前記台数の切断装置で切断するように構成したの
で、請求項1または請求項2の発明の効果により、1本
の鋼管の両端のクロップを除去し複数の製品鋼管に切断
する場合に従来方法より少ない台数の切断装置と1台の
ゲージストッパで対応でき、設備費/切削能率が向上し
て運転コストを低減できる鋼管の切断方法となる。
(3) According to the invention of claim 3, the method for cutting a steel pipe is a method for cutting steel pipes by removing the crops at both ends of one steel pipe and cutting into n product steel pipes of arbitrary length. Using the steel pipe cutting equipment according to claim 1 or 2, the steel pipe is cut by the cutting device of the number of units, and then the leading end of the rest of the steel pipe is brought into contact with the gauge stopper. Since it is configured to cut with the cutting device of claim 1, due to the effect of the invention of claim 1 or claim 2, when the crops at both ends of one steel pipe are removed and a plurality of product steel pipes are cut, a smaller number of units than the conventional method is used. The cutting device and one gauge stopper can be used to improve the equipment cost / cutting efficiency and reduce the operating cost.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施の一形態に係る鋼管の切断設備の
配置の説明図である。
FIG. 1 is an explanatory diagram of an arrangement of a steel pipe cutting facility according to an embodiment of the present invention.

【図2】図1の鋼管の切断設備を使用する鋼管の切断方
法の説明図である。
2 is an explanatory view of a method for cutting a steel pipe using the steel pipe cutting equipment of FIG. 1. FIG.

【図3】従来の鋼管の切断設備の配置の説明図である。FIG. 3 is an explanatory view of the arrangement of conventional steel pipe cutting equipment.

【図4】図3の鋼管の切断設備を使用する鋼管の切断方
法の説明図である。
4 is an explanatory view of a method of cutting a steel pipe using the steel pipe cutting equipment of FIG.

【符号の説明】[Explanation of symbols]

1 ミル出側テーブル 2 パイプ 2−1、2−2、2−3、2−4、2−6製品パイプ 3、3’ 切断ライン 4 切断装置 4−1 固定切断装置 4−2、4−3、4−5、4−6移動切断装置 5 切断ヘッド 6 パイプクランプ装置 7 ゲージストッパ 8、8’ 切断ライン出側テーブル 9、10 クロップ 1 mil outlet table 2 pipes 2-1, 2-2, 2-3, 2-4, 2-6 Product pipe 3,3 'cutting line 4 cutting device 4-1 Fixed cutting device 4-2, 4-3, 4-5, 4-6 moving cutting device 5 cutting head 6 Pipe clamp device 7 gauge stopper 8, 8'Cutting line outlet table 9, 10 crops

───────────────────────────────────────────────────── フロントページの続き (72)発明者 村上 純一郎 広島県三原市糸崎町5007番地 三菱重工業 株式会社三原機械・交通システム工場内 (72)発明者 岩本 理彦 和歌山県和歌山市湊1850番地 住友金属工 業株式会社和歌山製鉄所内 Fターム(参考) 3C039 EA12    ─────────────────────────────────────────────────── ─── Continued front page    (72) Inventor Junichiro Murakami             Hiroshima Prefecture Mihara City Itozakicho 5007 Mitsubishi Heavy Industries             Mihara Machinery & Transportation Systems Factory (72) Inventor Norihiko Iwamoto             Sumitomo Metal Works, 1850 Minato, Wakayama, Wakayama Prefecture             Wakayama Steel Works Co., Ltd. F-term (reference) 3C039 EA12

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 複数の切断装置を直列に配置して1列の
切断ラインを構成し、1本の鋼管をその軸方向に搬入し
同鋼管の両端のクロップを除去し最大n本の任意の長さ
の製品鋼管に切断し、同製品鋼管を前記搬入の方向と同
方向に排出する鋼管の切断設備において、前記1列の切
断ラインが、(n+1)/2以上で最小の台数の切断装
置と、同切断装置より前記製品鋼管の排出側に前記鋼管
の軸方向に移動可能かつ排出される前記製品鋼管から退
避可能に設けられた1台のゲージストッパとを有し、前
記複数の切断装置のうち前記ゲージストッパに最も近い
側の切断装置を前記鋼管の軸方向に固定して設け、他の
切断装置を前記鋼管の軸方向に移動可能に設けてなるこ
とを特徴とする鋼管の切断設備。
1. A plurality of cutting devices are arranged in series to form one row of cutting lines, one steel pipe is loaded in the axial direction thereof, and the crops at both ends of the steel pipe are removed to remove a maximum of n arbitrary pipes. In a steel pipe cutting facility that cuts a product steel pipe of a length and discharges the same product steel pipe in the same direction as the loading direction, the one row cutting line has a minimum number of cutting devices of (n + 1) / 2 or more. And one gauge stopper provided on the discharge side of the product steel pipe from the cutting device so as to be movable in the axial direction of the steel pipe and retractable from the discharged product steel pipe. Among them, a cutting device closest to the gauge stopper is fixedly provided in the axial direction of the steel pipe, and another cutting device is provided so as to be movable in the axial direction of the steel pipe. .
【請求項2】 請求項1に記載の鋼管の切断設備におい
て、前記製品鋼管の最大本数nが5または4であり、前
記1列の切断ラインが3台の前記切断装置と1台の前記
ゲージストッパとを有してなることを特徴とする鋼管の
切断設備。
2. The steel pipe cutting equipment according to claim 1, wherein the maximum number n of the product steel pipes is 5 or 4, and the one cutting line has three cutting devices and one gauge. A steel pipe cutting facility having a stopper.
【請求項3】 1本の鋼管の両端のクロップを除去しn
本の任意の長さの製品鋼管に切断する鋼管の切断方法に
おいて、請求項1または請求項2に記載の鋼管の切断設
備を用いて、前記台数の前記切断装置で同鋼管を切断
し、次いで同鋼管の残部の先頭を前記ゲージストッパに
当接させて前記台数の切断装置で切断することを特徴と
する鋼管の切断方法。
3. A steel pipe is provided with n-crop at both ends.
In a method for cutting a steel pipe for cutting a product steel pipe of an arbitrary length of a book, the steel pipe cutting equipment according to claim 1 or 2 is used to cut the steel pipe with the cutting device of the number, A method for cutting a steel pipe, characterized in that the leading end of the remaining portion of the same steel pipe is brought into contact with the gauge stopper, and the steel pipe is cut by the above-mentioned number of cutting devices.
JP2001239738A 2001-08-07 2001-08-07 Cutting equipment and cutting method for steel pipe Pending JP2003048116A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001239738A JP2003048116A (en) 2001-08-07 2001-08-07 Cutting equipment and cutting method for steel pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001239738A JP2003048116A (en) 2001-08-07 2001-08-07 Cutting equipment and cutting method for steel pipe

Publications (1)

Publication Number Publication Date
JP2003048116A true JP2003048116A (en) 2003-02-18

Family

ID=19070440

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001239738A Pending JP2003048116A (en) 2001-08-07 2001-08-07 Cutting equipment and cutting method for steel pipe

Country Status (1)

Country Link
JP (1) JP2003048116A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06277932A (en) * 1993-03-30 1994-10-04 Ube Ind Ltd Fixed dimension sawing method for long material
JPH11277328A (en) * 1998-03-26 1999-10-12 Kawasaki Steel Corp Cutting method of strip steel product and cutting device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06277932A (en) * 1993-03-30 1994-10-04 Ube Ind Ltd Fixed dimension sawing method for long material
JPH11277328A (en) * 1998-03-26 1999-10-12 Kawasaki Steel Corp Cutting method of strip steel product and cutting device

Similar Documents

Publication Publication Date Title
KR960008869B1 (en) Multiple outlet finishing mill
US9199387B2 (en) Method and apparatus for a rules based utilization of a minimum-slit-head configuration plunge slitter
CN109129670A (en) A kind of diced system of sponge block
TW570854B (en) Equipment and method for cutting pipe
CN101870035B (en) Machine method and device for processing plate-shaped workpieces, in particular sheet metal
CN114406352A (en) Online sizing and segmenting device and method for hot-rolled bar
JP2003048116A (en) Cutting equipment and cutting method for steel pipe
CN210616763U (en) Cross cutting die and sheet product production line
JPS6158268B2 (en)
EP2431339A1 (en) Glass sheet cutting method and system
CN101412040A (en) Method for scaling steel rolling rolled piece
JPH08187615A (en) Device for cutting and collecting/stacking plate
JP2639869B2 (en) Method and apparatus for sizing long materials
JP2008105071A (en) Method and device for cutting thick steel plate
DE19930757C2 (en) Dividing saw system
KR20140093343A (en) A Method for Nesting a Flat Bar
JP2003145341A (en) Strip material cutting method
CN107971755A (en) A kind of bar detection device and its method
JP3112856B2 (en) Semi-product removal device in steel strip hot rolling plant
CN220051021U (en) Combined production line for strips with different specifications and different lengths
CN212147060U (en) Ingot slicing device capable of improving efficiency
US20220226950A1 (en) Method and processing assembly for processing profile beam parts each extending along a longitudinal axis
JPS5890301A (en) Rolling method
JPH08215920A (en) Method for cutting-off pipe material and its manufacture
JPS5951873B2 (en) Sorting device for random length steel bars

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080418

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20090330

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20090428

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110405

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20110906