JP2003041503A - Tool for increasing resistance of tie to ballast - Google Patents

Tool for increasing resistance of tie to ballast

Info

Publication number
JP2003041503A
JP2003041503A JP2001228815A JP2001228815A JP2003041503A JP 2003041503 A JP2003041503 A JP 2003041503A JP 2001228815 A JP2001228815 A JP 2001228815A JP 2001228815 A JP2001228815 A JP 2001228815A JP 2003041503 A JP2003041503 A JP 2003041503A
Authority
JP
Japan
Prior art keywords
plate
ballast
tie
sleeper
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001228815A
Other languages
Japanese (ja)
Inventor
Takashi Mitsuishi
孝 三石
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP2001228815A priority Critical patent/JP2003041503A/en
Publication of JP2003041503A publication Critical patent/JP2003041503A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To solve the problems of a tie 7; that train load causes repeating vertical and horizontal movements of the tie 7, causing the irregularity of the track and causing ballast below and besides the tie to move away, resulting in an increase in the irregularity of the track and the need to correct the track within a short period; that train vibration causes mud pumping from the ballast, also causing the irregularity of the track; and that the perpendicularity of the tie to the rails is lost by the creeping of the rails, etc. SOLUTION: Box shapes are attached to the tie 7 to prevent the settlement of the tie 7, each of the box shapes comprising a front plate 2a, a side plate 3a and a bottom face plate 5, all of which together surround the lower portion of the tie 7, and another front plate 2b, another side plate 3b, and a back plate 4b, all of which protrude into ballast 8 in the form of trumpets. A flat plate 4c is mounted on the lower surface of the bottom face plate 5 to maintain the straightness and the perpendicularity of the ties. A rubber plate 11 is inserted between the lower surface of the tie 7 and the bottom face plate 5 to reduce train vibration and prevent mud pumping from the ballast.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、鉄道においてマク
ラギ7下部を取り囲む正面板2a、側面板3a、底面板
5とバラスト8中に正面板2b、側面板3b、裏面板4
bがラッパ状に張り出すことからなる箱型を取り付け、
マクラギ7の沈下を押さえる。また、底面板5の下面に
平板4cを取り付けることで通り狂い、直角狂いを押さ
える。マクラギ7下面と底面板5間にゴム板11を挿入
することで列車振動を和らげ道床噴泥を押さえる用具に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a front plate 2a, a side plate 3a, a bottom plate 5 and a ballast 8 which surround a lower part of a sleeper 7 in a railway.
Attach a box shape that consists of b protruding into a trumpet shape,
Press down the sleepiness of sleeper 7. Further, by attaching the flat plate 4c to the lower surface of the bottom plate 5, it is possible to prevent the plate from passing through at a right angle. The present invention relates to a tool for suppressing train vibration by inserting a rubber plate 11 between the lower surface of the sleeper 7 and the bottom plate 5 to suppress the bed mud.

【0002】[0002]

【従来の技術】列車荷重がレールからマクラギに伝わ
り、マクラギ本体が繰り返しの上下・左右動を受け高低
・水準・通り狂い(以後:軌道狂いとする)が発生す
る。既設マクラギ敷設箇所で路盤が弱い箇所、大型機械
によるバラスト突き固めのできない箇所(踏切前後、橋
梁前後、分岐器前後その他電気設備等)ではバラスト突
き固め機械での補修では短期間しか維持できず、一般の
軌道箇所よりも早く軌道狂いが発生しやすい。特にレー
ル継目部とその付近では、繰り返しの衝撃荷重ためマク
ラギ本体が沈下して、軌道狂いを起こしていた。また、
列車の振動である期間を経過すると路盤から土砂が上昇
しバラスト内に混じり道床噴泥が発生しこれも軌道狂い
を引き起こしていた。なお、マクラギの下面は凹凸のな
い面でバラストと接しているため列車の左右動が働き通
り狂いを起こしていた。結果として、マクラギ下部、側
部のバラストが流出し軌道狂いも益々大きくなり、短期
間での軌道補修が必要であった。
2. Description of the Related Art A train load is transmitted from a rail to a sleeper, and the sleeper body is repeatedly moved up and down and left and right, causing height, level, and deviation (hereinafter referred to as track deviation). In the existing sleeper laying place where the roadbed is weak, where the ballast can not be compacted by a large machine (before and after the railroad crossing, before and after the bridge, before and after the turnout and other electrical equipment etc.), the ballast compaction machine can only maintain for a short period of time, Track deviations are likely to occur sooner than general track locations. In particular, at the rail joint and its vicinity, the sleeper main body sank due to repeated impact loads, causing track misalignment. Also,
After a certain period of train vibration, the soil and sand rose from the roadbed and mixed with the ballast to generate bed mud, which also caused track irregularity. In addition, since the underside of the sleeper is in contact with the ballast with a surface without irregularities, the lateral movement of the train worked and caused a deviation. As a result, the ballast in the lower and side parts of the sleeper spilled out and the orbital deviation became even greater, and it was necessary to repair the orbit in a short period of time.

【0003】レールのふく進等により、マクラギとレー
ルの直角狂いを起こしていた。これもマクラギ下面は、
バラストと面で接しているため道床抵抗力が弱い一因で
ある。
Due to the rolling of the rail and the like, the right angle between the sleeper and the rail was caused. This is also the underside of sleeper
This is one reason why the ballast resistance is weak because it is in contact with the ballast.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、路盤が
弱い箇所、大型機械によるバラスト突き固めのできない
箇所(踏切前後、橋梁前後、分岐器前後その他電気設備
等)での既設マクラギ敷設箇所では列車からの繰り返し
荷重を受けたマクラギ7本体の沈下による軌道狂い、及
びレール10のふく進等により、マクラギ7とレール1
0の直角狂い。また、列車振動での道床噴泥が発生して
の軌道狂い。結果として、短周期での軌道補修をする問
題があった。
However, if the existing sleeper is laid in a place where the roadbed is weak or where ballasts cannot be compacted by a large machine (before and after the railroad crossing, before and after the bridge, before and after the turnout, and other electrical equipment), The sleeper 7 and the rail 1 are damaged due to the track deviation due to the sinking of the sleeper 7 body subjected to repeated loading and the rail 10 moving forward.
0 right angle deviation. In addition, the track drifts due to the generation of roadbed mud due to train vibration. As a result, there was a problem of orbital repair in a short period.

【0005】[0005]

【課題を解決するための手段】上記問題を解決すべく本
発明は、マクラギ7下部に取り付けられた道床抵抗力増
強用具1である。正面板2a.2b、側面板3a.3
b、裏面板4a.4bと底面板5からなる箱型を取り付
ける。その開口部9が道床バラスト8の方向に下向きに
とし、正面板2b、側面板3b、裏面板4bがバラスト
8中にラッパ状に張り出す。そのことでマクラギ7下
部、側部のバラスト8の流出を押さえ、バラスト8を保
持する。そのバラスト8は列車荷重が加わるごとにラッ
パ状の上向きに開口部9内で密に締め固められるため列
車荷重での沈下による軌道狂いが非常に小さくなる。
In order to solve the above problems, the present invention is a roadbed resistance enhancing tool 1 attached to the lower part of the sleeper 7. Front plate 2a. 2b, side plate 3a. Three
b, back plate 4a. A box shape consisting of 4b and the bottom plate 5 is attached. The opening 9 is directed downward in the direction of the ballast ballast 8, and the front plate 2b, the side plate 3b, and the back plate 4b project into the ballast 8 in a trumpet shape. As a result, the outflow of the ballast 8 at the lower and side portions of the sleeper 7 is suppressed and the ballast 8 is held. Each time the train load is applied to the ballast 8, the ballast 8 is tightly compacted upward in the opening 9 so that the track deviation due to the subsidence due to the train load becomes extremely small.

【0006】また、正面板2b、側面板3b、裏面板4
bが取り付けられることでマクラギ7の下部の平面積が
以前のマクラギ7下面の平面積より大きくなるため道床
抵抗力の増強につながる。
Further, the front plate 2b, the side plate 3b, and the back plate 4
By attaching b, the flat area of the lower part of the sleeper 7 becomes larger than the flat area of the lower surface of the sleeper 7 before, which leads to the enhancement of the roadbed resistance force.

【0007】底面板5の下面に平板4cをマクラギ7長
手方向に対して直角に取り付けることで通り狂い、直角
狂いを押さえる。また、マクラギ7下面と底面板5間に
ゴム板11を挿入することで列車振動を和らげ道床噴泥
を押さえる。
The flat plate 4c is attached to the lower surface of the bottom plate 5 at a right angle to the longitudinal direction of the sleeper 7 so as to prevent the flat plate 4c from passing through and suppressing the right angle deviation. Further, by inserting the rubber plate 11 between the lower surface of the sleeper 7 and the bottom plate 5, the train vibration is softened and the bed mud is suppressed.

【0008】[0008]

【実施例】本発明の道床抵抗力増強用具1は、図1に示
すように、マクラギ7の左右端側下部に取り付ける。取
り付け方法は、図4(上部帯板6aと締め付けボルト6
c略す)に示すような道床肩(マクラギ7の長手方向で
マクラギ7端側のバラスト8部分)のバラスト8をマク
ラギ6下面位までバラスト8を掻きだす。ジャッキでマ
クラギ7を多少扛上させた状態で、マクラギ7下面とバ
ラスト8との隙間にX方向から道床抵抗力増強用具1を
挿入する。挿入後道床抵抗力増強用具1が取り付け位置
(正面板2aがマクラギ7端部に当たる位置)まで移動
後、上部帯板6aと側部帯板6bを締め付けボルト6c
で締結して取り付けを終わる。締結後バラスト突き固め
機械でバラスト8をラッパ状に張り出す開口部9内に突
き固めしジャッキを取り外す。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The trackbed resistance enhancing tool 1 of the present invention is attached to the lower part of the sleeper 7 on the left and right ends, as shown in FIG. The mounting method is shown in Fig. 4 (the upper strip 6a and the tightening bolts 6
The ballast 8 of the ballast shoulder (ballast 8 part on the end side of the sleeper 7 in the longitudinal direction of the sleeper 7) as shown in c) is scraped out to the lower surface of the sleeper 6. With the jackpot 7 slightly lifted up by the jack, the trackbed resistance enhancing tool 1 is inserted into the gap between the underside of the pillow 7 and the ballast 8 from the X direction. After the insertion, the trackbed resistance enhancing tool 1 moves to the attachment position (the position where the front plate 2a hits the end of the sleeper 7), and then the upper strip 6a and the side strip 6b are tightened with the bolts 6c.
Fasten with and finish the installation. After fastening, the ballast 8 is compacted into a trumpet-like opening 9 by a ballast compaction machine and the jack is removed.

【0009】裏面板4aは道床抵抗力増強用具1を挿入
時にバラスト8の抵抗を少なくするためとしている。側
板3aの斜面dはバラスト突き固め機械のツール(バラ
スト8をマクラギ7下に突き固める先端器具)が突き固
めの際容易に挿入できるため斜面としている。また、側
板2bと側板3bの斜面cは側板2bと側板3bがバラ
スト8中に容易に抵抗を受けることなく入りやすくする
ために斜面としている。
The back plate 4a is provided to reduce the resistance of the ballast 8 when the tool 1 for increasing roadbed resistance is inserted. The slope d of the side plate 3a is a slope because a tool of a ballast compaction machine (a tip tool for compacting the ballast 8 under the sleeper 7) can be easily inserted during compaction. The slopes c of the side plates 2b and 3b are sloped so that the side plates 2b and 3b can easily enter the ballast 8 without receiving resistance.

【0010】道床抵抗力増強用具1の使用個所として、
軌道狂いの発生が多い個所、レール継目部とその付近、
大型機械によることができないバラスト突き固め個所、
踏切橋梁の前後、その他電気設備また、路盤が弱い個所
等で取り付けることで相当の補修労力を省くことができ
る。
As a place where the roadbed resistance enhancing tool 1 is used,
Where there are many track deviations, rail joints and their vicinity,
Ballast compaction points, which cannot be done by large machines,
A considerable amount of repair work can be saved by installing it at the front and rear of the crossing bridge, other electrical equipment, or at a place where the roadbed is weak.

【0011】底面板5の下面に平板4cを取り付けるこ
とで、平板4cと平板4c間のバラスト8はラッパ状の
上向きに開口部9内で密に締め固められるため詰り底面
板5とバラスト8間及び、開口部9内側のバラスト8と
開口部9外側(正面板2b、側面板3b、裏面板4b先
端部分)のバラスト8と摩擦抵抗が充分増すため通り狂
い、それに直角狂いも押さえることができる。
By mounting the flat plate 4c on the lower surface of the bottom plate 5, the ballast 8 between the flat plates 4c and 4c is tightly compacted in the opening 9 upward in the trumpet shape, so that the space between the bottom plate 5 and the ballast 8 is blocked. Also, the ballast 8 inside the opening 9 and the ballast 8 outside the opening 9 (front end of the front plate 2b, the side plate 3b, the back plate 4b) and the frictional resistance are sufficiently increased so that the ballast 8 can be passed through and the right angle can be suppressed. .

【0012】軌道狂いの発生が多い箇所、レール継目部
とその付近、路盤が弱い箇所には図5でゴム板11をマ
クラギ7下面と底面板5間に挿入することで列車振動を
和らげ道床噴泥を押さえる。
At a place where the track is often misaligned, a rail joint and its vicinity, and a place where the roadbed is weak, a rubber plate 11 is inserted between the underside of the sleeper 7 and the bottom plate 5 in FIG. Hold down the mud.

【0013】道床抵抗力増強用具1は鋼材で正面板2
a.2b、側面板3a.3b、裏面板4a.4b、平板
4c、底面板5と側部帯板6bとは溶接で一体化してい
る。なお、本発明はコンクリートマクラギ7の使用時で
の説明であるが、木マクラギでもその形状に合わせるこ
とで道床抵抗力増強用具1を取り付けることができる。
The roadbed resistance enhancing tool 1 is a steel front plate 2
a. 2b, side plate 3a. 3b, back plate 4a. 4b, the flat plate 4c, the bottom plate 5 and the side strip 6b are integrated by welding. Although the present invention has been described when the concrete sleeper 7 is used, the road bed resistance enhancing tool 1 can be attached to a wood sleeper by matching its shape.

【0014】[0014]

【発明の効果】本発明は、以上説明したように構成され
ているので、以下に記載されるような効果が上げられ
る。
Since the present invention is configured as described above, the following effects can be obtained.

【0015】道床抵抗力増強用具1を取り付けることで
マクラギ7本体の道床抵抗力の増強につながるためマク
ラギ7本体の安定化(動かない)が図られ、軌道狂いの
発生を押さえ、軌道補修の周期を長期に伸ばすことがで
きる。
Since the roadbed resistance of the sleeper 7 main body is increased by attaching the roadbed resistance increasing tool 1, the sleeper 7 main body is stabilized (does not move), the occurrence of orbital deviation is suppressed, and the cycle of track repairing is suppressed. Can be extended in the long term.

【図面の簡単な説明】[Brief description of drawings]

【図1】マクラギに道床抵抗力増強用具1を取り付けた
実施例を示す斜視図である。
FIG. 1 is a perspective view showing an embodiment in which a roadbed resistance enhancing tool 1 is attached to a sleeper.

【図2】道床抵抗力増強用具1を示す斜視図である。FIG. 2 is a perspective view showing a roadbed resistance enhancing tool 1.

【図3】道床抵抗力増強用具1を示し、(A)は正面
図、(B)は側面図、(C)は裏面図、(D)は平面図 (E)はG−Gの断面図、(F)はH−Hの断面図であ
る。
3A and 3B show a roadbed resistance enhancing tool 1, where (A) is a front view, (B) is a side view, (C) is a rear view, (D) is a plan view, and (E) is a sectional view taken along line GG. , (F) are sectional views taken along line HH.

【図4】道床抵抗力増強用具1を取り付けする前の配置
図を示す。
FIG. 4 shows a layout of the trackbed resistance enhancement tool 1 before mounting.

【図5】(I)、(Z)は図3の(E)、(F)にゴム板
11を取り付けた断面図。(但し、図2、図4はゴム板
11を取り付けていない状態)
5 (I) and (Z) are cross-sectional views in which a rubber plate 11 is attached to (E) and (F) of FIG. (However, in FIGS. 2 and 4, the rubber plate 11 is not attached)

【符号の説明】[Explanation of symbols]

1 道床抵抗力増強用具 2a、2b 正面板 c 斜面 3a、3b 側面板 d 斜面 4a、4b 裏面板 5 底板 6a 上部帯板 6b 側部帯板 6c 締め付けボルト 7 マクラギ 8 バラスト 9 開口部 10 レール 11 ゴム板 1 Roadbed resistance enhancement tool 2a, 2b front plate c slope 3a, 3b Side plate d slope 4a, 4b Back plate 5 bottom plate 6a Upper strip 6b Side strip 6c tightening bolt 7 sleepers 8 ballasts 9 openings 10 rails 11 rubber plate

【手続補正書】[Procedure amendment]

【提出日】平成13年9月10日(2001.9.1
0)
[Submission date] September 10, 2001 (2001.9.1)
0)

【手続補正1】[Procedure Amendment 1]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】0008[Correction target item name] 0008

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【0008】[0008]

【実施例】 本発明の道床抵抗力増強用具1は、図1に
示すように、マクラギ7の左右端側下部に取り付ける。
取り付け方法は、図4(上部帯板6aと締め付けボルト
6c略す)に示すような道床肩(マクラギ7の長手方向
でマクラギ7端側のバラスト8部分)のバラスト8をマ
クラギ下面位までバラスト8を掻きだす。ジャッキで
マクラギ7を多少扛上させた状態で、マクラギ7下面と
バラスト8との隙間にX方向から道床抵抗力増強用具1
を挿入する。挿入後道床抵抗力増強用具1が取り付け位
置(正面板2aがマクラギ7端部に当たる位置)まで移
動後、上部帯板6aと側部帯板6bを締め付けボルト6
cで締結して取り付けを終わる。締結後バラスト突き固
め機械でバラスト8をラッパ状に張り出す開口部9内に
突き固めしジャッキを取り外す。
EXAMPLE As shown in FIG. 1, the roadbed resistance enhancing tool 1 of the present invention is attached to the lower part of the sleeper 7 on the left and right ends.
As shown in FIG. 4 (abbreviated to the upper strip 6a and the tightening bolts 6c), the ballast 8 on the roadbed shoulder (the ballast 8 part on the end of the sleeper 7 in the longitudinal direction of the sleeper 7) is moved to the bottom surface of the sleeper 7 and the ballast 8 is attached. Scratch out. With the jack sleeper 7 lifted up a little, the roadbed resistance enhancing tool 1 from the X direction in the gap between the underside of the sleeper 7 and the ballast 8.
Insert. After the insertion, the roadbed resistance enhancing tool 1 moves to the attachment position (the position where the front plate 2a hits the end of the sleeper 7), and then the upper band plate 6a and the side band plate 6b are fastened with the bolts 6.
Fasten with c and finish the installation. After fastening, the ballast 8 is compacted into a trumpet-like opening 9 by a ballast compaction machine and the jack is removed.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 マクラギ7下部に取り付けられた道床抵
抗力増強用具1である。正面板2a.2b、側面板3
a.3b、裏面板4a.4bと底面板5からなる箱型を
取り付け、正面板2b、側面板3b、裏面板4bがラッ
パ状にバラスト8中張り出すことでマクラギ7の沈下を
押さえる道床抵抗力増強用具。
1. A roadbed resistance enhancing tool 1 attached to a lower portion of a sleeper 7. Front plate 2a. 2b, side plate 3
a. 3b, back plate 4a. A roadbed resistance strengthening tool that attaches a box shape composed of 4b and a bottom plate 5 and presses down the sleep of the sleeper 7 by projecting the front plate 2b, the side plate 3b, and the back plate 4b into the ballast 8 in a trumpet shape.
【請求項2】 請求項1記載の道床抵抗力増強用具1に
おいて、底面板5の下面に平板4cを取り付けることで
通り狂い、直角狂いを押さえる道床抵抗力増強用具。
2. The trackbed resistance enhancing tool 1 according to claim 1, wherein a flat plate 4c is attached to the lower surface of the bottom plate 5 to prevent deviation and right angle deviation.
【請求項3】 請求項1記載の道床抵抗力増強用具1に
おいて、マクラギ7下面と底面板5間にゴム板11を挿
入することで列車振動を和らげ道床噴泥を押さえる道床
抵抗力増強用具。
3. The trackbed resistance enhancing tool 1 according to claim 1, wherein a rubber plate 11 is inserted between the lower surface of the sleeper 7 and the bottom plate 5 to reduce train vibration and suppress the trackbed sludge.
JP2001228815A 2001-07-30 2001-07-30 Tool for increasing resistance of tie to ballast Pending JP2003041503A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001228815A JP2003041503A (en) 2001-07-30 2001-07-30 Tool for increasing resistance of tie to ballast

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001228815A JP2003041503A (en) 2001-07-30 2001-07-30 Tool for increasing resistance of tie to ballast

Publications (1)

Publication Number Publication Date
JP2003041503A true JP2003041503A (en) 2003-02-13

Family

ID=19061255

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001228815A Pending JP2003041503A (en) 2001-07-30 2001-07-30 Tool for increasing resistance of tie to ballast

Country Status (1)

Country Link
JP (1) JP2003041503A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008095413A (en) * 2006-10-13 2008-04-24 Hokkaido Railway Co Ballast repairing method for ballasted track
JP5174985B1 (en) * 2012-09-21 2013-04-03 林総事株式会社 Rail joint vibration / impact noise reduction device
KR101807079B1 (en) * 2017-03-16 2018-01-18 (주)화승엑스윌 Rubber panel device for railroad crossing

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008095413A (en) * 2006-10-13 2008-04-24 Hokkaido Railway Co Ballast repairing method for ballasted track
JP5174985B1 (en) * 2012-09-21 2013-04-03 林総事株式会社 Rail joint vibration / impact noise reduction device
KR101807079B1 (en) * 2017-03-16 2018-01-18 (주)화승엑스윌 Rubber panel device for railroad crossing

Similar Documents

Publication Publication Date Title
KR20160001011U (en) Precast Concrete Panel for Concrete Ballast of the Railway
JP3925856B2 (en) Sleeper and sleeper height adjustment method
JP5410926B2 (en) Repair method for direct track
JP2003041503A (en) Tool for increasing resistance of tie to ballast
JPH07259001A (en) Strengthening construction method for existing ballast roadbed track
KR100319577B1 (en) Rubber panel device for crossing a railway
KR20030065897A (en) Structure of concrete ballast track and construction method thereof
CN110857544B (en) High-speed railway safety protection structure and construction method thereof
JP2006112215A (en) Safety rail device
KR100593194B1 (en) Railroad tie for using synthetic resins
KR200410824Y1 (en) Railway installation structure for tenderness ground
JP3349912B2 (en) Rail buckling prevention device
JP3077036B2 (en) Concrete paving slab for railway tracks
JP3943246B2 (en) Reinforcement girder mounting device
CN219410389U (en) Ballastless crossing plate and crossing structure with ballastless preventing function
JP2556666B2 (en) Bridge long rail method and roadbed resistance enhancement method
KR20020064623A (en) R.C Railroad Tie Assembly
CN216761759U (en) A switch ware mounting base for concrete sleeper
JP2003064601A (en) Under-road construction method and rigid floor slab used therefor
KR200370686Y1 (en) Structure of concrete ballast track
JP2003082601A (en) Ballast-resistance increase of concrete sleeper
KR20040000207A (en) Pandrolltype concrete vibration-proof sleeper for bridge
JPH0410242Y2 (en)
US1584056A (en) Railway tie
JP2003328302A (en) Connecting joint member for sleeper