JP2003036287A - Building material distribution support device, building material distribution support method, building material distribution support program, and computer readable recording medium - Google Patents

Building material distribution support device, building material distribution support method, building material distribution support program, and computer readable recording medium

Info

Publication number
JP2003036287A
JP2003036287A JP2001222013A JP2001222013A JP2003036287A JP 2003036287 A JP2003036287 A JP 2003036287A JP 2001222013 A JP2001222013 A JP 2001222013A JP 2001222013 A JP2001222013 A JP 2001222013A JP 2003036287 A JP2003036287 A JP 2003036287A
Authority
JP
Japan
Prior art keywords
work
date
building materials
building
building material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001222013A
Other languages
Japanese (ja)
Inventor
Toshimi Dobashi
稔美 土橋
Tetsuro Uenami
鉄郎 上浪
Hirosuke Kenmotsu
宏輔 監物
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2001222013A priority Critical patent/JP2003036287A/en
Publication of JP2003036287A publication Critical patent/JP2003036287A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a building material distribution support device, building material distribution support method, building material distribution support program, and computer readable recording medium that can streamline, and increase the efficiency of, overall building material distribution. SOLUTION: A distribution planning determination unit 21 determines a carry-in date, which is set on material data stored in a material database 13a and on which building material required for a corresponding operation is to be carried in, such that the carry-in date becomes a predetermined period earlier than the operation start date, based on operation start date information included in process data stored in a process database 11a in a process data storage unit 11, material data stored in a material database 13a in a material data storage unit 13, predetermined-period information stored in an allocation database 15a in an allocation data storage unit 15. The distribution planning determination unit 21 also determines a conveyance (lift) date, on which a building material required for an operation is to be conveyed (lifted) in the workplace, such that the conveyance data becomes a predetermined period earlier than the operation start date.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、建築資材を作業所
に搬入し、搬入された建築資材を作業所内にて搬送する
物流計画を立案するための建築資材の物流支援装置、建
築資材の物流支援方法、建築資材の物流支援プログラ
ム、及びコンピュータ読み取り可能な記録媒体に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction material distribution support device for constructing a distribution plan for carrying a construction material into a work place and transporting the carried construction material in the work place, and a distribution of the construction material. The present invention relates to a support method, a building material distribution support program, and a computer-readable recording medium.

【0002】[0002]

【従来の技術】建築の生産行為は部材の加工、物流、組
立の3要素で概ね成立している。この中で、部材の加工
はプレハブ化・ユニット化等により合理化が図られ、組
立は合理化工法の開発や機械化・自動化等が進められて
いるものの、物流については合理化の可能性が多く残さ
れている。
2. Description of the Related Art A building production activity is generally established by three elements: processing, distribution and assembly of parts. Among these, although the processing of parts has been streamlined by prefabricating and unitizing, and the assembly is being developed with rationalization method, mechanization, automation, etc., there is a lot of possibility of streamlining in logistics. There is.

【0003】建築資材の物流は、トラック等による作業
所への搬入(輸配送)と、作業所内における揚重(垂直
方向での搬送)、間配り(水平方向での搬送)等の搬送
からなる。現在、物流の合理化としては、輸配送、搬送
毎に合理化に向けての取り組みが進められている。たと
えば、輸配送の合理化としては、電子データ交換(Elec
tronic Data Interchange)を利用してゼネコン複数社
で建築資材を共同配送し、輸配送の効率化とコストダウ
ンを図るものがある。また、揚重(搬送)の合理化とし
ては、揚重作業の機械化・自動化、パレットの標準化、
揚重専門チームの採用、揚重計画の合理化等について取
り組まれている。
[0003] The distribution of building materials is carried in by a truck or the like into a work place (transportation / delivery), lifted in the work place (transportation in the vertical direction), and distributed (transportation in the horizontal direction). . Currently, as the rationalization of physical distribution, efforts are being made to rationalize each of transportation and delivery. For example, to streamline transportation, electronic data exchange (Elec
There are some companies that jointly deliver building materials by using tronic Data Interchange) to improve the efficiency and cost of transportation. For rationalization of lifting (transportation), mechanization and automation of lifting work, standardization of pallets,
Efforts are being made to recruit specialized lifting teams and rationalize lifting plans.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、従来の
取り組みは、輸配送の合理化、揚重(搬送)の合理化と
いったように、輸配送と搬送(揚重)とで独立したもの
すぎず、建築資材の物流をトータルで合理化、効率化し
ようとするものではない。
However, the conventional approaches are not independent of transportation and transportation (lifting), such as rationalization of transportation and delivery, rationalization of lifting (transportation), and construction materials. It is not intended to totally streamline and streamline the logistics.

【0005】本発明は上述の点に鑑みてなされたもの
で、建築資材の物流をトータルで合理化、効率化するこ
とが可能な建築資材の物流支援装置、建築資材の物流支
援方法、建築資材の物流支援プログラム及びコンピュー
タ読み取り可能な記録媒体を提供することを課題とす
る。
The present invention has been made in view of the above-mentioned points, and is a building material distribution support device, a building material distribution support method, and a building material distribution support apparatus capable of totally rationalizing and streamlining the distribution of building materials. An object is to provide a distribution support program and a computer-readable recording medium.

【0006】[0006]

【課題を解決するための手段】本発明者らは、建築資材
の物流全体での合理化、効率化を可能とする物流支援装
置等について鋭意研究を行った結果、以下のような事実
を新たに見出した。
[Means for Solving the Problems] As a result of earnest research on a distribution support device or the like that enables rationalization and efficiency in the distribution of building materials as a whole, the present inventors newly found the following facts. I found it.

【0007】建築資材を工場出荷から作業所内での組立
(取付)までの流れを一つのシステムとして捉えると、
その基本構成機能は輸配送、在庫、搬送の3機能とな
る。ここで、輸配送は、工場や物流センター(配送セン
ター)と作業所との間での建築資材の運送のことであ
る。在庫は、作業所内での保管場所、物流センター等に
おける建築資材の一時保管のことである。搬送は、作業
所内での建築資材の搬送のことであり、揚重、間配り等
を含んでいる。これらの基本構成機能間の関連は、建築
資材を工場から作業所内で組立(取付)るまでの建築資
材の供給連鎖であるサプライチェーンと、このサプライ
チェーンをマネジメントするための需要情報の連鎖であ
るデマンドチェーンの2系統存在する。
If the flow from the factory shipment of building materials to the assembly (installation) in the work place is regarded as one system,
Its basic constituent functions are three functions: transportation / delivery, inventory, and transportation. Here, the transportation and delivery is transportation of building materials between a factory or a distribution center (delivery center) and a work place. Inventory refers to temporary storage of building materials in storage areas such as workplaces and distribution centers. Transportation refers to the transportation of building materials within the workplace, including lifting and distribution. The relationship between these basic constituent functions is the supply chain, which is the supply chain of building materials from the factory to the assembly (installation) of building materials, and the chain of demand information for managing this supply chain. There are two demand chain systems.

【0008】サプライチェーンにおける資材の流れは、
輸配送→在庫→揚重→工程の流れとなり、また、建築資
材の搬入後直ちに搬送する場合は、輸配送→揚重→工程
の流れとなる。ここで、工程とは、運ばれた建築資材を
組立(取付)作業や工事工程ののことである。サプライ
チェーンのトリガーは、デマンドチェーンの起点である
工程であり、工程から発信される情報はサプライチェー
ンとは逆方向に流れるのが基本である。すなわち、組立
(取付)等の作業時期が決まると、以下の需要情報の連
鎖が発生する。 工程から発信される需要情報は、作業の開始日と作業
に必要とされる建築資材である。 作業の開始日に応じて作業に必要とされる建築資材の
搬送日を決定する。なお、建築資材の搬送は、作業所内
での保管場所に一次保管された建築資材(在庫)から出
庫する場合と、搬入後に搬送する場合とがある。 搬送日の決定とともに、作業の開始日に応じて作業に
必要とされる建築資材の搬入日を決定する。 建築資材の在庫予定数は、搬送日と搬入日との関係か
ら、出庫数と入庫数との差分により求まる。 このように、工程(作業の開始日)は、サプライチェー
ンの最終点であるが、建築資材の移動のトリガーとなる
需要情報の発生源でもあり、物流システム自体には含ま
れないものの建築資材の移動を計画し円滑に実施する上
で重要な役割となる。
The flow of materials in the supply chain is
The flow is as follows: transportation / delivery → inventory → lifting → process. In addition, when the building material is conveyed immediately after it is carried in, the flow is as follows. Here, the process means an assembly (attachment) work or a construction process of the transported building material. The trigger of the supply chain is the process that is the starting point of the demand chain, and the information transmitted from the process basically flows in the opposite direction to the supply chain. That is, when the work time for assembly (attachment) or the like is determined, the following chain of demand information occurs. The demand information transmitted from the process is the start date of the work and the building materials required for the work. Determine the delivery date of the building materials required for the work according to the start date of the work. The building material may be transported from the building material (inventory) temporarily stored in the storage location in the work place, or may be transported after being loaded. Along with the determination of the delivery date, the delivery date of the building materials required for the work is determined according to the start date of the work. The planned inventory quantity of building materials can be obtained from the difference between the number of deliveries and the number of receipts from the relationship between the delivery date and the delivery date. In this way, the process (start date of work) is the final point of the supply chain, but it is also the source of demand information that triggers the movement of building materials, and is not included in the distribution system itself, but It plays an important role in planning and smoothly implementing the movement.

【0009】かかる研究結果を踏まえ、本発明に係る建
築資材の物流支援装置は、建築資材を作業所に搬入し、
搬入された建築資材を作業所内にて搬送する物流計画を
立案するための建築資材の物流支援装置であって、少な
くとも作業の開始日に関する情報を含む工程データを格
納する工程データ格納手段と、作業に必要とされる建築
資材に関するデータを格納する資材データ格納手段と、
工程データ格納手段に格納された工程データに含まれる
作業の開始日に関する情報と資材データ格納手段に格納
された建築資材に関するデータとに基づいて、作業に必
要とされる建築資材の作業所への搬入日を作業の開始日
よりも所定期間前となるように決定するとともに、作業
に必要とされる建築資材の作業所内での搬送日を作業の
開始日よりも所定期間前となるように決定する物流計画
立案手段と、を備えていることを特徴としている。
On the basis of the above research results, the building material distribution support apparatus according to the present invention carries the building material into a work place,
A distribution support device for building materials for planning a distribution plan for transporting a delivered building material in a work place, the process data storing means storing at least process data including information on a start date of the work, and the work. Material data storage means for storing data related to building materials required for
Based on the information about the start date of the work included in the process data stored in the process data storage means and the data about the building material stored in the material data storage means, The delivery date is determined to be a predetermined period before the work start date, and the construction material transportation date within the workplace is determined to be a predetermined period before the work start date. And a physical distribution planning means for carrying out.

【0010】一方、本発明に係る建築資材の物流支援方
法は、建築資材を作業所に搬入し、搬入された建築資材
を作業所内にて搬送する物流計画を立案するための建築
資材の物流支援方法であって、少なくとも作業の開始日
に関する情報を含む工程データを格納する工程データ格
納手段と、作業に必要とされる建築資材に関するデータ
を格納する資材データ格納手段と、を用い、物流計画立
案手段が、工程データ格納手段に格納された工程データ
に含まれる作業の開始日に関する情報と資材データ格納
手段に格納された建築資材に関するデータとに基づい
て、作業に必要とされる建築資材の作業所への搬入日を
作業の開始日よりも所定期間前となるように決定すると
ともに、作業に必要とされる建築資材の作業所内での搬
送日を作業の開始日よりも所定期間前となるように決定
する物流計画立案ステップを備えていることを特徴とし
ている。
On the other hand, the method of supporting distribution of building materials according to the present invention is a method of supporting distribution of building materials for carrying in building materials to a work place and planning a distribution plan for carrying the carried building materials within the work place. A method for planning a physical distribution using at least a process data storage means for storing process data including information on a work start date and a material data storage means for storing data on a building material required for the work. The means performs the work of the building material required for the work based on the information about the start date of the work included in the process data stored in the process data storage means and the data about the building material stored in the material data storage means. The delivery date to the place is set to be a predetermined period before the work start date, and the construction material required for the work is delivered to the work place within the work place. Remote it is characterized in that it comprises a determining logistics planning step so that the predetermined period before.

【0011】これら本発明に係る建築資材の物流支援装
置及び建築資材の物流支援方法それぞれによれば、物流
計画立案手段により、工程データ格納手段に格納された
工程データに含まれる作業の開始日に関する情報と資材
データ格納手段に格納された建築資材に関するデータと
に基づいて、作業に必要とされる建築資材の作業所への
搬入日が作業の開始日よりも所定期間前となるように決
定されるとともに、作業に必要とされる建築資材の作業
所内での搬送日が作業の開始日よりも所定期間前となる
ように決定される。このように、作業の開始日を基準に
して搬入日及び搬送日が決定されるので、建築資材の物
流計画が建築資材の作業所への搬入及び作業所内での搬
送という物流全体と実際の作業とが関連付けられた状態
で立案されることになり、建築資材の物流全体において
合理化、効率化を図ることができる。また、本発明によ
れば、搬入日及び搬送日が暦日ではなく、作業の開始日
に対して相対的に決定されるので、作業の開始日が変更
された場合でも搬入日及び搬送日の変更が容易となり、
作業日程の変更に対して柔軟に対応することができる。
According to each of the building material physical distribution support apparatus and the building material physical distribution support method of the present invention, the physical distribution planning means relates to the start date of the work included in the process data stored in the process data storage means. Based on the information and the data on the building materials stored in the material data storage means, the date of delivery of the building materials required for the work to the work place is determined to be a predetermined period before the start date of the work. In addition, the construction material required for the work is determined to be transported within the work place by a predetermined period before the start date of the work. In this way, the delivery date and the delivery date are determined based on the start date of the work, so the distribution plan of the building material is the entire logistics and actual work of delivering the building material to the work place and transporting it in the work place. Since it will be planned in a state where and are associated with each other, rationalization and efficiency can be achieved in the entire distribution of building materials. Further, according to the present invention, since the carry-in date and the carry-in date are not calendar days but are relatively determined with respect to the work start date, even when the work start date is changed, the carry-in date and the carry-in date are Change is easy,
It is possible to flexibly respond to changes in work schedules.

【0012】また、本発明に係る建築資材の物流支援装
置においては、物流計画立案手段にて搬入日及び搬送日
を決定するために必要とされる所定期間に関するデータ
を格納する割振データ格納手段を更に備えていることが
好適である。
Further, in the construction material physical distribution support apparatus according to the present invention, an allocation data storage means for storing data relating to a predetermined period required for determining the delivery date and the transportation date by the physical distribution planning means. Further, it is preferable to further include.

【0013】一方、本発明に係る建築資材の物流支援方
法においては、物流計画立案手段にて搬入日及び搬送日
を決定するために必要とされる所定期間に関するデータ
を格納する割振データ格納手段を更に用い、物流計画立
案ステップにおいて、物流計画立案手段は、更に割振デ
ータ格納手段に格納された所定期間に関するデータに基
づいて、搬入日及び搬送日を決定することが好適であ
る。
On the other hand, in the distribution support method for building materials according to the present invention, the allocation data storage means for storing the data regarding the predetermined period required for determining the carry-in date and the transport date by the distribution planning means is provided. Further, it is preferable that, in the physical distribution planning step, the physical distribution planning means further determines the carry-in date and the transportation date based on the data regarding the predetermined period stored in the allocation data storage means.

【0014】このように構成した場合、それぞれにおい
て、物流計画立案手段にて搬入日及び搬送日を決定する
ために必要とされる所定期間に関するデータを適切に管
理することができるとともに、データの変更を容易に行
うことができる。
In the case of such a configuration, in each case, the data relating to the predetermined period required for determining the carry-in date and the carry-in date by the distribution planning means can be appropriately managed, and the data can be changed. Can be done easily.

【0015】また、本発明に係る建築資材の物流支援装
置においては、資材データ格納手段に格納される建築資
材に関するデータは、作業に必要とされる建築資材の種
類、数量、作業所内での搬送回数、及び作業に必要とさ
れる建築資材を搬入するための搬入車両の台数を含んで
いることが好適である。
Further, in the building material physical distribution support apparatus according to the present invention, the data on the building material stored in the material data storage means includes the type and quantity of the building material required for the work, and the transportation within the work place. It is preferable to include the number of times and the number of loading vehicles for loading the building materials required for the work.

【0016】一方、本発明に係る建築資材の物流支援方
法においては、資材データ格納手段に格納される建築資
材に関するデータは、作業に必要とされる建築資材の種
類、数量、作業所内での搬送回数、及び作業に必要とさ
れる建築資材を搬入するための搬入車両の台数を含んで
いることが好適である。
On the other hand, in the building material physical distribution support method according to the present invention, the data on the building materials stored in the material data storage means includes the type and quantity of the building materials required for the work, and the transportation within the work place. It is preferable to include the number of times and the number of loading vehicles for loading the building materials required for the work.

【0017】このように構成した場合、それぞれにおい
て、搬入日及び搬送日毎における物流の負荷状態を適切
に決定することができる。
With this configuration, the load condition of the physical distribution can be appropriately determined for each of the carry-in date and the carry-in date.

【0018】また、本発明に係る建築資材の物流支援装
置においては、物流計画立案手段は、搬入日における搬
入車両の台数と、搬送日における搬送回数とを決定する
ことが好適である。
Further, in the construction material physical distribution support apparatus according to the present invention, it is preferable that the physical distribution planning means determines the number of incoming vehicles on the incoming date and the number of times of transportation on the incoming date.

【0019】一方、本発明に係る建築資材の物流支援方
法においては、物流計画立案ステップにおいて、物流計
画立案手段は、搬入日における搬入車両の台数と、搬送
日における搬送回数とを決定することが好適である。
On the other hand, in the construction material physical distribution support method according to the present invention, in the physical distribution planning step, the physical distribution planning means can determine the number of vehicles to be carried in on the carrying-in date and the number of times of carrying on the carrying day. It is suitable.

【0020】このように構成した場合、それぞれにおい
て、搬入日及び搬送日毎の物流の負荷状態を適切に確認
することができる。
In the case of such a configuration, it is possible to properly confirm the load state of the physical distribution on each of the carry-in date and the carry-in date.

【0021】また、本発明に係る建築資材の物流支援装
置においては、物流計画立案手段は、搬入日に搬入され
る建築資材の数量と、搬送日に搬送される建築資材の数
量とを決定することが好適である。
In the building material physical distribution support apparatus according to the present invention, the physical distribution planning means determines the number of building materials carried in on the carrying-in date and the number of building materials carried on the carrying day. Is preferred.

【0022】一方、本発明に係る建築資材の物流支援方
法においては、物流計画立案ステップにおいて、物流計
画立案手段は、搬入日に搬入される建築資材の数量と、
搬送日に搬送される建築資材の数量とを決定することが
好適である。
On the other hand, in the distribution support method for building materials according to the present invention, in the distribution planning step, the distribution planning means determines the number of building materials carried in on the carrying-in date,
It is preferable to determine the number of building materials to be delivered on the delivery date.

【0023】このように構成した場合、それぞれにおい
て、搬入日及び搬送日毎の物流の負荷状態を適切に確認
することができる。
In the case of such a configuration, it is possible to properly confirm the load state of the physical distribution on each of the carry-in date and the carry-in date.

【0024】また、本発明に係る建築資材の物流支援装
置においては、物流計画立案手段は、作業所に搬入され
た建築資材のうち作業所内に設置された保管場所に在庫
として一時保管される建築資材の数量を算出することが
好適である。
Further, in the distribution support apparatus for building materials according to the present invention, the distribution planning means is a building material that is temporarily stored as an inventory in the storage place installed in the working place among the building materials carried into the working place. It is preferable to calculate the quantity of materials.

【0025】一方、本発明に係る建築資材の物流支援方
法においては、物流計画立案ステップにおいて、物流計
画立案手段は、作業所に搬入された建築資材のうち作業
所内に設置された保管場所に在庫として一時保管される
建築資材の数量を算出することが好適である。
On the other hand, in the construction material distribution support method according to the present invention, in the distribution planning step, the distribution planning means stores the stock in the storage place installed in the working place among the building materials carried into the working place. It is preferable to calculate the number of building materials temporarily stored as.

【0026】このように構成した場合、それぞれにおい
て、搬入日及び搬送日毎の物流の負荷状態を適切に確認
することができる。
In the case of such a configuration, it is possible to appropriately confirm the load state of the physical distribution on each of the carry-in date and the carry-in date.

【0027】また、上記課題を解決するために、本発明
に係る建築資材の物流支援プログラムは、建築資材を作
業所に搬入し、搬入された建築資材を作業所内にて搬送
する物流計画を立案するためにコンピュータを、少なく
とも作業の開始日に関する情報を含む工程データを格納
する工程データ格納手段、作業に必要とされる建築資材
に関するデータを格納する資材データ格納手段、及び工
程データ格納手段に格納された工程データに含まれる作
業の開始日に関する情報と資材データ格納手段に格納さ
れた建築資材に関するデータとに基づいて、作業に必要
とされる建築資材の作業所への搬入日を作業の開始日よ
りも所定期間前となるように決定するとともに、作業に
必要とされる建築資材の作業所内での搬送日を作業の開
始日よりも所定期間前となるように決定する物流計画立
案手段、として機能させることを特徴としている。
In order to solve the above problems, the building material physical distribution support program according to the present invention formulates a physical distribution plan in which the building material is carried into a work place and the carried building material is transported within the work place. In order to do so, a computer is stored in a process data storage means for storing process data including at least information regarding the start date of the work, a material data storage means for storing data related to construction materials required for the work, and a process data storage means. Based on the information about the start date of the work included in the process data and the data about the building material stored in the material data storage means, the start date of the work to bring the building material required for the work to the work place is started. It is decided to be a predetermined period before the day, and the date of delivery of the building materials required for the work within the work place is the predetermined period from the start date of the work. Is characterized in that is before and so as to determine that the logistics planning unit functions as a.

【0028】本発明に係る建築資材の物流支援プログラ
ムによれば、コンピュータを用いて上述したプログラム
を実行することで、コンピュータが工程データ格納手
段、資材データ格納手段、及び物流計画立案手段として
機能し、物流計画立案手段により、工程データ格納手段
に格納された工程データに含まれる作業の開始日に関す
る情報と資材データ格納手段に格納された建築資材に関
するデータとに基づいて、作業に必要とされる建築資材
の作業所への搬入日が作業の開始日よりも所定期間前と
なるように決定されるとともに、作業に必要とされる建
築資材の作業所内での搬送日が作業の開始日よりも所定
期間前となるように決定される。このように、作業の開
始日を基準にして搬入日及び搬送日が決定されるので、
建築資材の物流計画が建築資材の作業所への搬入及び作
業所内での搬送という物流全体と実際の作業とが関連付
けられた状態で立案されることになり、建築資材の物流
全体において合理化、効率化を図ることができる。ま
た、本発明によれば、搬入日及び搬送日が暦日ではな
く、作業の開始日に対して相対的に決定されるので、作
業の開始日が変更された場合でも搬入日及び搬送日の変
更が容易となり、作業日程の変更に対して柔軟に対応す
ることができる。
According to the building material physical distribution support program of the present invention, the computer functions as a process data storing means, a material data storing means, and a physical distribution planning means by executing the above-mentioned program using a computer. Required by the physical distribution planning means on the basis of the information on the start date of the work contained in the process data stored in the process data storage means and the data on the building material stored in the material data storage means The delivery date of the building material to the work place is determined to be a predetermined period before the work start date, and the delivery date of the building material required for the work in the work place is earlier than the work start date. It is determined to be before the predetermined period. In this way, the carry-in date and transport date are determined based on the start date of the work,
The logistics plan for building materials will be drafted in a state where the entire logistics of delivering building materials to and from the workplace are associated with the actual work. Can be realized. Further, according to the present invention, since the carry-in date and the carry-in date are not calendar days but are relatively determined with respect to the work start date, even when the work start date is changed, the carry-in date and the carry-in date are Changes can be facilitated, and it is possible to flexibly respond to changes in work schedules.

【0029】また、本発明に係る信号機を用いた建築資
材の物流支援プログラムにおいては、物流計画立案手段
にて搬入日及び搬送日を決定するために必要とされる所
定期間に関するデータを格納する割振データ格納手段を
更に備えていることが好適である。このように構成した
場合、搬入日及び搬送日毎における物流の負荷状態を適
切に決定することができる。
Further, in the distribution support program for building materials using the traffic light according to the present invention, the allocation for storing the data relating to the predetermined period required for determining the carry-in date and the transport date by the distribution planning means. It is preferable to further include data storage means. With such a configuration, it is possible to appropriately determine the load state of the physical distribution on each of the carry-in date and the transport day.

【0030】また、本発明に係る信号機を用いた建築資
材の物流支援プログラムにおいては、資材データ格納手
段に格納される建築資材に関するデータは、作業に必要
とされる建築資材の種類、数量、作業所内での搬送回
数、及び作業に必要とされる建築資材を搬入するための
搬入車両の台数を含んでいることが好適である。このよ
うに構成した場合、搬入日及び搬送日毎の物流の負荷状
態を適切に確認することができる。
Further, in the building material distribution support program using the traffic light according to the present invention, the data on the building materials stored in the material data storage means is the type, quantity, and work of the building materials required for the work. It is preferable to include the number of times of transportation in the place and the number of loading vehicles for loading the building materials required for the work. With such a configuration, it is possible to appropriately confirm the load state of the physical distribution on each of the carry-in date and the transport day.

【0031】また、本発明に係る信号機を用いた建築資
材の物流支援プログラムにおいては、物流計画立案手段
は、搬入日における搬入車両の台数と、搬送日における
搬送回数とを決定することが好適である。このように構
成した場合、搬入日及び搬送日毎の物流の負荷状態を適
切に確認することができる。
In the distribution support program for building materials using the traffic light according to the present invention, it is preferable that the distribution planning means determines the number of vehicles to be carried in on the carry-in date and the number of times of carrying on the carry-on day. is there. With such a configuration, it is possible to appropriately confirm the load state of the physical distribution on each of the carry-in date and the transport day.

【0032】また、本発明に係る信号機を用いた建築資
材の物流支援プログラムにおいては、物流計画立案手段
は、搬入日に搬入される建築資材の数量と、搬送日に搬
送される建築資材の数量とを決定することが好適であ
る。このように構成した場合、搬入日及び搬送日毎の物
流の負荷状態を適切に確認することができる。
Further, in the building material physical distribution support program using the traffic light according to the present invention, the physical distribution planning means has the quantity of the building material carried in on the carry-in date and the quantity of the building material carried on the carrying day. It is preferred to determine With such a configuration, it is possible to appropriately confirm the load state of the physical distribution on each of the carry-in date and the transport day.

【0033】また、本発明に係る信号機を用いた建築資
材の物流支援プログラムにおいては、物流計画立案手段
は、作業所に搬入された建築資材のうち作業所内に設置
された保管場所に在庫として一時保管される建築資材の
数量を算出することが好適である。このように構成した
場合、搬入日及び搬送日毎の物流の負荷状態を適切に確
認することができる。
Further, in the building material distribution support program using the traffic light according to the present invention, the distribution planning means temporarily stores the building materials carried into the work place in stock at a storage location installed in the work place. It is preferable to calculate the quantity of building materials to be stored. With such a configuration, it is possible to appropriately confirm the load state of the physical distribution on each of the carry-in date and the transport day.

【0034】また、上記課題を解決するために、本発明
に係るコンピュータ読み取り可能な記録媒体は、請求項
13〜請求項18のいずれか一項に記載の建築資材の物
流支援プログラムを記録したことを特徴としている。
In order to solve the above-mentioned problems, the computer-readable recording medium according to the present invention records the building material physical distribution support program according to any one of claims 13 to 18. Is characterized by.

【0035】本発明に係るコンピュータ読み取り可能な
記録媒体では、作業の開始日を基準にして搬入日及び搬
送日が決定されるので、建築資材の物流計画が建築資材
の作業所への搬入及び作業所内での搬送という物流全体
と実際の作業とが関連付けられた状態で立案されること
になり、建築資材の物流全体において合理化、効率化を
図ることができる。また、本発明によれば、搬入日及び
搬送日が暦日ではなく、作業の開始日に対して相対的に
決定されるので、作業の開始日が変更された場合でも搬
入日及び搬送日の変更が容易となり、作業日程の変更に
対して柔軟に対応することができる。
In the computer-readable recording medium according to the present invention, the carry-in date and the carry-in date are determined on the basis of the start date of the work. Since the whole physical distribution of transportation in the office is associated with the actual work, the rationalization and efficiency of the entire physical distribution of the building material can be achieved. Further, according to the present invention, since the carry-in date and the carry-in date are not calendar days but are relatively determined with respect to the work start date, even when the work start date is changed, the carry-in date and the carry-in date are Changes can be facilitated, and it is possible to flexibly respond to changes in work schedules.

【0036】[0036]

【発明の実施の形態】本発明の実施形態に係る建築資材
の物流支援装置について図面を参照して説明する。な
お、本実施形態は、建築資材、特に、マンション等の集
合住宅工事における仕上・設備材の物流計画を立案する
物流支援装置に適用したものである。
BEST MODE FOR CARRYING OUT THE INVENTION A distribution support apparatus for building materials according to an embodiment of the present invention will be described with reference to the drawings. The present embodiment is applied to a physical distribution support device that formulates a physical distribution plan for building materials, particularly finishing / equipment materials in the construction of apartments such as condominiums.

【0037】まず、本実施形態に係る建築資材の物流支
援装置1の構成について説明する。図1は、本実施形態
に係る建築資材の物流支援装置の構成図である。物流支
援装置1は、建築資材を作業所に搬入し、搬入された建
築資材を作業所内にて搬送(揚重、間配り等)する物流
計画を立案するためのものであって、物理的には、CP
U(中央処理装置)、メモリ、マウスやキーボードなど
の入力装置、ディスプレイなどの表示装置、ハードディ
スクなどの格納装置、通信ユニットなどの送受信装置な
どを備えたコンピュータシステム(たとえば、パーソナ
ルコンピュータ)として構成される。物流支援装置1
は、機能的な構成要素として、図1に示されるように、
工程データ格納手段としての工程データ格納部11と、
資材データ格納手段としての資材データ格納部13と、
割振データ格納手段としての割振データ格納部15と、
保管場所設定データ格納部17と、物流計画立案手段と
しての物流計画立案部19とを備えて構成される。
First, the construction of the construction material physical distribution support apparatus 1 according to this embodiment will be described. FIG. 1 is a block diagram of a construction material physical distribution support apparatus according to the present embodiment. The physical distribution support device 1 is for physically delivering a building material to a work place and for transporting (lifting, distributing, etc.) the loaded building material in the work place, and physically Is CP
A computer system (for example, a personal computer) including a U (central processing unit), a memory, an input device such as a mouse and a keyboard, a display device such as a display, a storage device such as a hard disk, and a transmission / reception device such as a communication unit. It Logistics support device 1
Is a functional component as shown in FIG.
A process data storage unit 11 as process data storage means,
A material data storage unit 13 as a material data storage means,
An allocation data storage unit 15 as allocation data storage means,
The storage location setting data storage unit 17 and a physical distribution plan planning unit 19 as a physical distribution planning unit are provided.

【0038】工程データ格納部11は、少なくとも作業
の開始日に関する情報を含む工程データを格納するもの
であり、工程データベース11aを含んでいる。工程デ
ータベース11aは、図2に示されるように、工程デー
タとして、作業名(工区及び作業の種類)と、作業の開
始日と、作業の終了日と、所要期間とが対応づけられて
格納、記憶されている。図2は、工程データベース11
aの構成図である。工程データベース11aにおいて
は、図2に示されるように、たとえば「工区」に「工区
A」が記憶され、「作業の種類」に「作業a」が記憶さ
れ、「作業の開始日」に「○月○日」が記憶され、「作
業の終了日」に「○月×日」が記憶され、「所要期間」
に「△日」が記憶されている。なお、工程データ格納部
11(工程データベース11a)に格納される工程デー
タは、基準とする工区を作るための工程表を含む基準工
程データと、建築物全体を作るためのマスター工程表を
含む概略工程データとを用いて、基準工程データに基づ
いて概略工程データを展開する、すなわち概略工程デー
タに基準工程データの中身を差し込むことにより得るよ
うにしてもよい。
The process data storage unit 11 stores process data including at least information regarding the start date of the work, and includes a process database 11a. As shown in FIG. 2, the process database 11a stores, as process data, a work name (construction section and work type), a work start date, a work end date, and a required period in association with each other, Remembered FIG. 2 shows the process database 11
It is a block diagram of a. In the process database 11a, as shown in FIG. 2, for example, "work zone A" is stored in "work zone", "work a" is stored in "work type", and "○" is stored in "start date of work". "○○" is stored, "End date of work" is stored as "X month x day", and "Required period" is stored.
Is stored in. In addition, the process data stored in the process data storage unit 11 (process database 11a) is an outline including standard process data including a process table for making a reference work section and a master process table for making the entire building. The process data may be used to develop the general process data based on the standard process data, that is, the contents of the standard process data may be inserted into the general process data.

【0039】資材データ格納部13は、作業に必要とさ
れる建築資材に関するデータ(資材データ)を格納する
ものであり、資材データベース13aを含んでいる。資
材データベース13aは、図3に示されるように、資材
データとして、作業名(工区及び作業の種類)と、建築
資材と、作業所内での搬送(揚重)回数と、搬入車両と
が対応づけられて格納、記憶されている。図3は、資材
データベース13aの構成図である。建築資材として
は、対応する作業に必要とされる建築資材の種類、数量
がデータとして含まれる。また、搬入車両としては、対
応する作業に必要とされる建築資材を搬入するための搬
入車両の台数、種類(たとえば、積載量)がデータとし
て含まれる。資材データベース13aにおいては、図3
に示されるように、たとえば「工区」に「工区A」が記
憶され、「作業の種類」に「作業a」が記憶され、「建
築資材の種類」に「資材a」が記憶され、「建築資材の
数量」に「32」が記憶され、「搬送(揚重)回数」に
「4」が記憶されている。「搬入車両」には搬入車両の
台数として「1」が記憶されている。
The material data storage unit 13 stores data (material data) relating to building materials required for work, and includes a material database 13a. As shown in FIG. 3, the material database 13a associates, as material data, a work name (construction section and work type), a building material, the number of times of transportation (lifting) in a work place, and a loading vehicle. Stored and stored. FIG. 3 is a configuration diagram of the material database 13a. As the building material, the type and quantity of the building material required for the corresponding work are included as data. Further, as the loading vehicle, the number and type (for example, the loading amount) of the loading vehicle for loading the building materials required for the corresponding work are included as data. In the material database 13a, FIG.
As shown in, for example, “work area A” is stored in “work area”, “work a” is stored in “work type”, “material a” is stored in “building material type”, and “building material” is stored. "32" is stored in the "quantity of materials", and "4" is stored in the "number of times of transportation (lifting)". “1” is stored in the “carry-in vehicle” as the number of carried-in vehicles.

【0040】割振データ格納部15は、物流計画立案部
19にて搬入日及び搬送(揚重)日を決定するために必
要とされる所定期間に関するデータを格納するものであ
り、割振データベース15aを含んでいる。所定期間に
関するデータは、搬入日及び搬送(揚重)日を作業の開
始日を基準として相対的に決定するためのものであり、
搬入日に対する所定期間及び搬送(揚重)日に対する所
定期間を含む。割振データベース15aは、図4に示さ
れるように、作業の種類と、搬入日に対する所定期間
と、搬送(揚重)日に対する所定期間とが対応づけられ
て格納、記憶されている。図4は、割振データベース1
5aの構成図である。割振データベース15aにおいて
は、図4に示されるように、たとえば「作業の種類」に
「作業a」が記憶され、「搬入日に対する所定期間」に
「−1」が記憶され、「搬送(揚重)日に対する所定期
間」に「−1」が記憶されている。ここで、所定期間は
作業の開始日の何日前に対応する作業に必要な建築資材
を搬入あるいは搬送(揚重)するかを表すものであり、
たとえば「−1」は作業の開始日の前日に建築資材を搬
入あるいは搬送(揚重)することを表している。なお、
本実施形態において、搬入日に対する所定期間及び搬送
(揚重)日に対する所定期間は日単位にて設定されてい
るが、時間単位にて設定するようにしてもよい。
The allocation data storage unit 15 stores data concerning a predetermined period required for the distribution plan planning unit 19 to determine a delivery date and a transportation (lifting) date, and stores the allocation database 15a. Contains. The data regarding the predetermined period is for relatively determining the carry-in date and the transport (lifting) date based on the start date of the work,
Includes a specified period for the carry-in date and a specified period for the transport (lift) date. As shown in FIG. 4, the allocation database 15a stores and stores the types of work, a predetermined period for a carry-in date, and a predetermined period for a transport (lift) date in association with each other. Figure 4 shows the allocation database 1
It is a block diagram of 5a. In the allocation database 15a, as shown in FIG. 4, for example, “work a” is stored in “kind of work”, “−1” is stored in “predetermined period for carry-in date”, and “transport (lifting)” is stored. ) "-1" is stored in the "predetermined period for day". Here, the predetermined period indicates how many days before the start date of the work to carry in or carry (lift) the building materials necessary for the corresponding work,
For example, "-1" indicates that the building material is loaded or transported (lifted) on the day before the start date of the work. In addition,
In the present embodiment, the predetermined period for the carry-in date and the predetermined period for the transport (lifting) day are set on a daily basis, but may be set on an hourly basis.

【0041】保管場所設定データ格納部17は、作業所
に搬入された建築資材を在庫として一時保管する保管場
所に関するデータを格納するものであり、保管場所設定
データベース17aを含んでいる。これは、建築資材の
搬入日と搬送(揚重)日が異なる場合、搬入された建築
資材を在庫として一時保管する必要があり、この在庫
(建築資材)の保管場所を決めておくことが必要となる
ためである。図5は、保管場所設定データベース17a
の構成図である。保管場所設定データベース17aにお
いては、図5に示されるように、たとえば「作業の種
類」に「作業a」が記憶され、「保管場所」に「101
号室」が記憶され、「保管可能数量」に「100」が記
憶されている。「保管可能数量」は、対応する「保管場
所」に保管可能な建築資材の数量を表している。なお、
「保管可能数量」の代わりに、対応する「保管場所」の
最大容量(面積)を用いるようにしてもよい。
The storage location setting data storage unit 17 stores data relating to a storage location where the building materials carried into the work place are temporarily stored as an inventory, and includes a storage location setting database 17a. This is because if the date of delivery of building materials and the date of transportation (lifting) are different, it is necessary to temporarily store the delivered building materials as an inventory, and it is necessary to determine the storage location of this inventory (building materials). This is because FIG. 5 shows the storage location setting database 17a.
It is a block diagram of. In the storage location setting database 17a, as shown in FIG. 5, for example, "work a" is stored in "work type", and "101" is stored in "storage location".
The "room" is stored, and "100" is stored in the "storable quantity". The “storable quantity” represents the quantity of the building material that can be stored in the corresponding “storage location”. In addition,
The maximum capacity (area) of the corresponding "storage location" may be used instead of the "storable quantity".

【0042】再び、図1を参照する。物流計画立案部1
9は、物流計画として作業に必要とされる建築資材の作
業所への搬入日及び作業に必要とされる建築資材の作業
所内での搬送(揚重)日を決定するためのものであり、
物流計画決定部21と、物流計画出力部23とを含んで
いる。
Referring again to FIG. Logistics Planning Department 1
9 is for determining a delivery date of the building material required for the work to the work place and a transportation (lifting) date of the building material required for the work in the work place as a logistics plan,
The physical distribution plan determining unit 21 and the physical distribution plan output unit 23 are included.

【0043】物流計画決定部21は、工程データ格納部
11の工程データベース11aに格納された工程データ
に含まれる作業の開始日に関する情報、資材データ格納
部13の資材データベース13aに格納された資材デー
タ、及び割振データ格納部15の割振データベース15
aに格納された所定期間に関する情報に基づいて、資材
データベース13aに格納された資材データに設定さ
れ、対応する作業に必要とされる建築資材を作業所に搬
入する搬入日を作業の開始日よりも所定期間前となるよ
うに決定する。また、物流計画決定部21は、同様に、
資材データベース13aに格納された資材データに設定
され、対応する作業に必要とされる建築資材を作業所内
において搬送(揚重)する搬送(揚重)日を作業の開始
日よりも所定期間前となるように決定する。物流計画決
定部21は、たとえば、割振データベース15aの「搬
入日に対する所定期間」に「−1」が格納され、同じく
「搬送(揚重)日に対する所定期間」に「−1」が格納
されている場合、対応する作業の開始日の前日に資材デ
ータベース13aに格納された資材データによる建築資
材が搬入及び搬送(揚重)されるように、搬入日及び搬
送日を相対指定し、決定する。
The physical distribution plan determining unit 21 has information about the start date of the work included in the process data stored in the process database 11a of the process data storage unit 11 and the material data stored in the material database 13a of the material data storage unit 13. , And the allocation database 15 of the allocation data storage unit 15.
Based on the information about the predetermined period stored in a, the carry-in date, which is set in the material data stored in the material database 13a and carries in the building material required for the corresponding work to the work place, is from the start date of the work. Is also determined to be before the predetermined period. Further, the distribution plan determination unit 21 similarly
The building material set in the material data stored in the material database 13a, and carrying (lifting) the building material required for the corresponding work in the work place, is the carrying (lifting) date before the start date of the work by a predetermined period. Decide to be. The physical distribution plan determination unit 21 stores, for example, "-1" in the "predetermined period for the carry-in date" and "-1" in the "predetermined period for the transport (lift) day" of the allocation database 15a. When there is a corresponding work, the carry-in date and the carry-in date are relatively designated and determined so that the building material according to the material data stored in the material database 13a is carried in and carried (lifted) on the day before the start date of the corresponding work.

【0044】また、物流計画決定部21は、物流の負荷
状態として、搬入日における搬入車両の台数と、搬送
(揚重)日における搬送(揚重)回数と、搬入日に搬入
される建築資材の数量と、搬送(揚重)日に搬送(揚
重)される建築資材の数量とを決定する。
Further, the physical distribution plan determining unit 21 determines, as the physical distribution load state, the number of vehicles to be carried in on the carrying-in day, the number of times of carrying (hoisting) on the carrying (lifting) day, and the building material carried on the carrying-in day And the number of building materials transported (lifted) on the transportation (lifting) day.

【0045】また、物流計画決定部21は、物流の負荷
状態として、作業所に搬入された建築資材のうち作業所
内に設置された保管場所に在庫として一時保管される建
築資材の数量(在庫数量)を算出する。在庫数量の算出
は、下記(1)式に基づいて行われる。 在庫数量=前日の在庫数量+当日の入庫数量−当日の出庫数量 … (1) 入庫数量:保管場所に一時保管される建築資材の数量 出庫数量:保管場所から搬送(揚重)のため運び出され
る建築資材の数量
Further, the physical distribution plan determining unit 21 determines, as the physical load, the quantity of the building material temporarily stored as an inventory in the storage place installed in the working place (the stock quantity). ) Is calculated. The inventory quantity is calculated based on the following equation (1). Inventory quantity = Inventory quantity on the previous day + Receipt quantity on the day-Deposit quantity on the current day (1) Receipt quantity: Quantity of building materials temporarily stored in the storage location Issue quantity: Delivered from the storage location for transportation (lifting) Quantity of building materials

【0046】(1)式は、日毎の終了時における在庫数
量の予定を算出するものであり、1日の中では、在庫数
量が保管場所の保管可能数量を超過する可能性もある。
このため、下記(2)式に基づいて、日毎の最大保有数
量を算出するようにしてもよい。 在庫数量=前日の在庫数量−前日の出庫数量+当日の入庫数量 … (2)
The expression (1) calculates the schedule of the stock quantity at the end of each day, and the stock quantity may exceed the storable quantity in the storage location within one day.
For this reason, the maximum holding quantity for each day may be calculated based on the following equation (2). Stock quantity = stock quantity on the previous day-stock quantity on the previous day + received quantity on the day… (2)

【0047】更に、物流計画決定部21は、保管場所設
定データ格納部17の保管場所設定データベース17a
に格納された保管場所に関するデータに基づいて、建築
資材の保管場所を決定する。このとき、物流計画決定部
21は、保管場所に在庫として一時保管される建築資材
の数量が保管場所設定データベース17aに格納された
保管可能数量以下となるように管理する。
Further, the physical distribution plan determination unit 21 stores the storage location setting database 17a in the storage location setting data storage unit 17.
The storage location of the building material is determined based on the storage location data stored in. At this time, the distribution plan determination unit 21 manages the quantity of the building material temporarily stored as stock in the storage location so that it is less than or equal to the storable quantity stored in the storage location setting database 17a.

【0048】物流計画決定部21は、決定した建築資材
の搬入日、建築資材の搬送(揚重)日、物流の負荷状
態、保管場所等に関する情報を物流計画出力部23に送
出する。
The physical distribution plan determination unit 21 sends information on the determined construction material carry-in date, construction material transportation (lifting) date, physical distribution load state, storage location, etc. to the physical distribution plan output unit 23.

【0049】物流計画出力部23は、物流計画決定部2
1にて決定された建築資材の搬入日、建築資材の搬送
(揚重)日、物流の負荷状態、保管場所等に関する情報
を受領し、これらの情報に基づいて物流計画を示すため
の画像データ等を作成して出力する。なお、物流計画出
力部23は、物流計画を示すための画像データ等を作成
する代わりに、物流計画決定部21にて決定されて送出
された建築資材の搬入日、建築資材の搬送(揚重)日、
物流の負荷状態、保管場所等に関する情報をデータベー
ス等の記憶装置に格納、記憶させるようにしてもよい。
The distribution plan output unit 23 is the distribution plan determination unit 2
Image data for receiving the delivery date of building materials, delivery (lifting) date of building materials, load condition of logistics, storage location, etc. determined in 1 and showing the logistics plan based on these information Etc. are created and output. Note that the physical distribution plan output unit 23 does not create image data or the like for indicating the physical distribution plan, but instead of the delivery date of the building material determined and sent out by the physical distribution plan determination unit 21 and the transportation (lifting) of the building material. )Day,
Information on the load state of the physical distribution, the storage location, etc. may be stored and stored in a storage device such as a database.

【0050】物流計画出力部23から出力される画像デ
ータは、たとえば図6に示されるような物流計画画面P
を生成するものである。図6に示された物流計画画面P
には、「工程」として各作業の内容(工区、作業の種
類)が、時間軸(日単位)に沿って示されている。ま
た、「搬送(揚重)日程」及び「搬入日程」として、物
流計画決定部21にて決定された搬入日及び搬送日(各
作業の開始日を基準にして相対指定)に対応する時間軸
位置に搬送(揚重)回数及び搬入車両台数の値が時間軸
(日単位)に沿って示されている。物流計画画面Pに
は、たとえば、「工区A:作業a」に必要とされる建築
資材(資材a)を「工区A:作業a」の開始日の前日に
一台の車両にて作業所に搬入し、4回の搬送(揚重)に
より工区Aに対して運び込む旨が示されている。
The image data output from the physical distribution plan output unit 23 is, for example, a physical distribution plan screen P as shown in FIG.
Is generated. Physical distribution plan screen P shown in FIG.
Shows the content of each work (construction section, work type) as a “process” along the time axis (day unit). Further, as the “transportation (lifting) schedule” and the “delivery schedule”, a time axis corresponding to the delivery date and the transport date (relatively designated based on the start date of each work) determined by the distribution plan determination unit 21. The values of the number of times of transportation (lifting) and the number of loaded vehicles are shown along the time axis (day unit) at the position. In the physical distribution plan screen P, for example, a building material (material a) required for “work area A: work a” is delivered to a work place by one vehicle on the day before the start day of “work area A: work a”. It is shown that it is carried in and carried into the work area A by four times of transportation (lifting).

【0051】そして、物流計画画面Pには、「在庫予
定」として各作業に必要とされる建築資材の数量(必要
数量)、作業所に搬入される建築資材の数量(入庫数
量)、在庫として一時保管される建築資材の数量(在庫
数量)、保管場所が、時間軸(日単位)に沿って示され
ている。物流計画画面Pには、たとえば、「工区A:作
業a」に必要とされる建築資材(資材a)の数量が「3
2」であり、「工区A:作業a」の開始日の前日に作業
所に搬入される建築資材(資材a)の数量が「32」で
ある旨が示されている。なお、この場合、搬入日と搬送
日とが同日であるため、「在庫数量」は「0」となり、
「保管場所」についての表示はなされていない。
Then, on the physical distribution plan screen P, the quantity (building quantity) of building materials required for each work as "planned stock", the quantity (building quantity) of building materials carried into the work place, and the stock The quantity (stock quantity) of the building materials temporarily stored and the storage location are shown along the time axis (day unit). In the physical distribution plan screen P, for example, the quantity of the building material (material a) required for “construction area A: work a” is “3.
2 ”, which indicates that the quantity of the building material (material a) carried into the work site on the day before the start date of“ work area A: work a ”is“ 32 ”. In this case, since the carry-in date and the transport date are the same day, the "inventory quantity" is "0",
There is no indication of "storage location".

【0052】続いて、図7に示すフローチャートを参照
しながら、本実施形態に係る建築資材の物流支援装置1
の動作(建築資材の物流支援方法)について説明する。
図7は、本実施形態に係る建築資材の物流支援装置1の
動作(建築資材の物流支援方法)を示すフローチャート
である。
Subsequently, referring to the flow chart shown in FIG. 7, the construction material distribution support apparatus 1 according to the present embodiment.
Operation (method of supporting distribution of building materials) will be described.
FIG. 7 is a flowchart showing the operation of the building material distribution support apparatus 1 according to the present embodiment (building material distribution support method).

【0053】まず、物流計画決定部21は、工程データ
格納部11の工程データベース11aから格納された工
程データ(作業の開始日に関する情報)を読み込む(S
101)。そして、物流計画決定部21は、資材データ
格納部13の資材データベース13aから格納された資
材データを読み込み(S103)、割振データ格納部1
5の割振データベース15aから格納された所定期間に
関する情報を読み込み(S105)、保管場所設定デー
タ格納部17の保管場所設定データベース17aから格
納された保管場所に関するデータを読み込む(S10
7)。
First, the physical distribution plan determination unit 21 reads the stored process data (information on the start date of the work) from the process database 11a of the process data storage unit 11 (S).
101). Then, the physical distribution plan determination unit 21 reads the stored material data from the material database 13a of the material data storage unit 13 (S103), and the allocation data storage unit 1
The information about the predetermined period stored from the allocation database 15a of No. 5 is read (S105), and the data about the storage location stored from the storage location setting database 17a of the storage location setting data storage unit 17 is read (S10).
7).

【0054】次に、物流計画決定部21は、読み込んだ
データに基づいて、上述したように、対応する作業に必
要とされる建築資材の作業所への搬入日を作業の開始日
よりも所定期間前となるように決定するとともに、対応
する作業に必要とされる建築資材の作業所内での搬送
(揚重)日を作業の開始日よりも所定期間前となるよう
に決定する(S109:物流計画立案ステップ)。
Then, based on the read data, the physical distribution plan deciding unit 21 determines the delivery date of the building material required for the corresponding work to the work place more than the start date of the work, as described above. It is determined that it is before the period, and the transportation (lifting) date of the building material required for the corresponding work in the work place is determined by a predetermined period before the start date of the work (S109: Logistics planning step).

【0055】続いて、物流計画決定部21は、読み込ん
だデータに基づいて、物流の負荷状態として、搬入日に
おける搬入車両の台数と、搬送(揚重)日における搬送
(揚重)回数と、搬入日に搬入される建築資材の数量
と、搬送(揚重)日に搬送(揚重)される建築資材の数
量とを決定し、ステップS109にて決定した搬入日あ
るいは搬送(揚重)日と対応付ける(S111:物流計
画立案ステップ)。
Then, the physical distribution plan determining section 21 determines the load state of physical distribution based on the read data, as the number of vehicles to be carried in on the day of carrying in, the number of times of carrying (lifting) on the day of carrying (lifting), The quantity of the building material to be carried in on the carry-in day and the quantity of the building material to be carried (lifted) on the carrying (lifting) day are determined, and the carrying-in date or the carrying (lifting) day determined in step S109. (S111: physical distribution planning step).

【0056】また、物流計画決定部21は、物流の負荷
状態として、作業所に搬入された建築資材のうち作業所
内に設置された保管場所に在庫として一時保管される建
築資材の数量(在庫数量)を算出し、ステップS109
にて決定した搬入日と対応付ける。このとき、搬入日と
搬送(揚重)日とが異なる場合等在庫が発生する場合に
は、在庫として発生した建築資材の保管場所を決定する
(S113:物流計画立案ステップ)。
Further, the physical distribution plan deciding unit 21 determines, as the physical load state, the quantity of the building materials (stock quantity) which is temporarily stored as an inventory in the storage place installed in the working place among the building materials carried into the working place. ) Is calculated, and step S109
Correspond with the delivery date determined in. At this time, when inventory occurs such as when the carry-in date is different from the transportation (lifting) date, the storage location of the building material generated as inventory is determined (S113: physical distribution planning step).

【0057】この後、物流計画決定部21は、決定した
建築資材の搬入日、建築資材の搬送(揚重)日、物流の
負荷状態、保管場所等に関する情報を物流計画出力部2
3に送出する(S115)。そして、物流計画決定部2
1は、物流計画を示すための画像データ等を作成して出
力する(S117)。
After that, the physical distribution plan deciding section 21 provides information on the decided construction material delivery date, construction material transportation (lifting) date, physical distribution load state, storage location, etc. to the physical distribution plan output section 2.
3 (S115). And the distribution plan determination unit 2
1 creates and outputs image data or the like for showing the physical distribution plan (S117).

【0058】以上のことから、本実施形態によれば、物
流計画立案部19の物流計画決定部21により、工程デ
ータ格納部11(工程データベース11a)に格納され
た工程データに含まれる作業の開始日に関する情報と資
材データ格納部13(資材データベース13a)に格納
された建築資材に関するデータとに基づいて、作業に必
要とされる建築資材の作業所への搬入日が作業の開始日
よりも所定期間前となるように決定されるとともに、作
業に必要とされる建築資材の作業所内での搬送(揚重)
日が作業の開始日よりも所定期間前となるように決定さ
れる。このように、作業の開始日を基準にして搬入日及
び搬送(揚重)日が相対的に決定されるので、建築資材
の物流計画が建築資材の作業所への搬入及び作業所内で
の搬送(揚重)という物流全体と実際の作業とが関連付
けられた状態で立案されることになり、建築資材の物流
全体において合理化、効率化を図ることができる。
From the above, according to the present embodiment, the distribution plan decision unit 21 of the distribution plan planning unit 19 starts the work included in the process data stored in the process data storage unit 11 (process database 11a). Based on the information on the date and the data on the building materials stored in the material data storage unit 13 (material database 13a), the date of bringing in the building materials required for the work to the work place is more predetermined than the start date of the work. It is decided to be before the period, and the building materials required for the work are transported (lifted) in the workplace.
The date is determined to be a predetermined period before the work start date. In this way, the delivery date and the transportation (lifting) date are relatively determined based on the start date of the work, so that the distribution plan of the building materials is carried in the building materials to the work place and the transportation inside the work place. Since the whole physical distribution of (lifting) is associated with the actual work, it is possible to rationalize and improve the efficiency of the entire physical distribution of the building material.

【0059】また、本実施形態によれば、搬入日及び搬
送(揚重)日が暦日ではなく、作業の開始日に対して相
対的に決定されるので、作業の開始日が変更された場合
でも搬入日及び搬送(揚重)日の変更が容易となり、作
業日程の変更に対して柔軟に対応することができる。
Further, according to the present embodiment, since the carry-in date and the carrying (lifting) date are not determined by the calendar date but by the work start date, the work start date is changed. Even in this case, it is easy to change the carry-in date and the carrying (lifting) date, and it is possible to flexibly deal with the change in the work schedule.

【0060】また、本実施形態においては、物流計画決
定部21にて搬入日及び搬送(揚重)日を決定するため
に必要とされる所定期間に関するデータを格納する割振
データ格納部15(割振データベース15a)を更に備
え、物流計画決定部21は、搬入日及び搬送(揚重)日
を決定する際に割振データ格納部15(割振データベー
ス15a)に格納された所定期間に関するデータを更に
用いている。これにより、物流計画決定部21にて搬入
日及び搬送(揚重)日を決定するために必要とされる所
定期間に関するデータを適切に管理することができると
ともに、データの変更等を容易に行うことができる。
Further, in the present embodiment, the allocation data storage unit 15 (allocation unit) for storing the data regarding the predetermined period required for the distribution plan determination unit 21 to determine the delivery date and the transportation (lifting) date. The distribution plan determination unit 21 further includes a database 15a), and further uses the data regarding the predetermined period stored in the allocation data storage unit 15 (allocation database 15a) when determining the carry-in date and the transportation (lifting) date. There is. As a result, it is possible to appropriately manage the data relating to the predetermined period required for determining the carry-in date and the transport (lift) date in the physical distribution plan determining unit 21, and easily change the data. be able to.

【0061】また、本実施形態においては、資材データ
格納部13(資材データベース13a)に格納される建
築資材に関するデータは、作業に必要とされる建築資材
の種類、数量、作業所内での搬送(揚重)回数、及び作
業に必要とされる建築資材を搬入するための搬入車両の
台数を含んでいる。これにより、搬入日及び搬送(揚
重)日毎における物流の負荷状態を適切に決定すること
ができる。
Further, in the present embodiment, the data regarding the building materials stored in the material data storage unit 13 (material database 13a) includes the types and quantities of the building materials required for the work, and the transportation within the work place ( It includes the number of times of loading and unloading and the number of loading vehicles for loading building materials required for the work. As a result, it is possible to appropriately determine the load state of the physical distribution on each of the carry-in date and the carrying (lifting) date.

【0062】また、本実施形態においては、物流計画決
定部21は、搬入日における搬入車両の台数と、搬送
(揚重)日における搬送(揚重)回数とを決定し、搬入
日あるいは搬送(揚重)日に対応付けている。これによ
り、搬入日及び搬送(揚重)日毎の物流の負荷状態を適
切に確認することができる。
Further, in the present embodiment, the physical distribution plan determination unit 21 determines the number of vehicles to be carried in on the carry-in date and the number of times of carrying (lifting) on the carrying (lifting) day, and the carrying-in date or carrying (carrying) It corresponds to the date. As a result, it is possible to appropriately confirm the load state of the physical distribution on each of the carry-in date and the carrying (lifting) date.

【0063】また、本実施形態においては、物流計画決
定部21は、搬入日に搬入される建築資材の数量と、搬
送(揚重)日に搬送(揚重)される建築資材の数量とを
決定し、搬入日あるいは搬送(揚重)日に対応付けてい
る。これにより、搬入日及び搬送(揚重)日毎の物流の
負荷状態を適切に確認することができる。
Further, in the present embodiment, the physical distribution plan determining unit 21 determines the quantity of the building material carried in on the carry-in day and the quantity of the building material carried (lifted) on the carrying (lifting) day. It is determined and associated with the date of delivery or the date of transportation (lifting). As a result, it is possible to appropriately confirm the load state of the physical distribution on each of the carry-in date and the carrying (lifting) date.

【0064】また、本実施形態においては、物流計画決
定部21は、作業所に搬入された建築資材のうち作業所
内に設置された保管場所に在庫として一時保管される建
築資材の数量を算出している。これにより、搬入日及び
搬送(揚重)日毎の物流の負荷状態を適切に確認するこ
とができる。
Further, in the present embodiment, the physical distribution plan determining unit 21 calculates the number of building materials temporarily stored as inventory in the storage place installed in the work place among the building materials carried into the work place. ing. As a result, it is possible to appropriately confirm the load state of the physical distribution on each of the carry-in date and the carrying (lifting) date.

【0065】続いて、本発明の実施形態に係る建築資材
の物流支援プログラム及びこの取引関連情報提示プログ
ラムを記録したコンピュータ読み取り可能な記録媒体
(以下、単に記録媒体という)について説明する。ここ
で、記録媒体とは、コンピュータのハードウェア資源に
備えられている読み取り装置に対して、プログラムの記
述内容に応じて、磁気、光、電気等のエネルギーの変化
状態を引き起こして、それに対応する信号の形式で、読
み取り装置にプログラムの記述内容を伝達できるもので
ある。係る記録媒体としては、たとえば、磁気ディス
ク、光ディスク、CD−ROM、コンピュータに内蔵さ
れるメモリなどが該当する。
Next, a computer-readable recording medium (hereinafter, simply referred to as a recording medium) recording the distribution support program for building materials and the transaction-related information presenting program according to the embodiment of the present invention will be described. Here, the recording medium responds to a reading device provided in a computer hardware resource by causing a change state of energy such as magnetism, light, and electricity in accordance with the description content of a program. The description content of the program can be transmitted to the reading device in the form of a signal. As such a recording medium, for example, a magnetic disk, an optical disk, a CD-ROM, a memory built in a computer, or the like is applicable.

【0066】図8は、本発明の実施形態に係る記録媒体
の構成図である。記録媒体30は、図8に示すように、
プログラムを記録するプログラム領域30aを備えてお
り、このプログラム領域30aには、物流支援プログラ
ム32が記録されている。物流支援プログラム32は、
処理を統括するメインモジュール32aと、コンピュー
タシステムとして構成された物流支援装置1を工程デー
タ格納部11(工程データベース11a)として機能さ
せて、少なくとも作業の開始日に関する情報を含む工程
データを格納する工程データ格納モジュール32bと、
同じく物流支援装置1を資材データ格納部13(資材デ
ータベース13a)として機能させて、作業に必要とさ
れる建築資材に関するデータ(資材データ)を格納する
資材データ格納モジュール32cと、同じく物流支援装
置1を割振データ格納部15(割振データベース15
a)として機能させて、物流計画立案部19にて搬入日
及び搬送(揚重)日を決定するために必要とされる所定
期間に関するデータを格納する割振データ格納モジュー
ル32dと、同じく物流支援装置1を保管場所設定デー
タ格納部17(保管場所設定データベース17a)とし
て機能させて、作業所に搬入された建築資材を在庫とし
て一時保管する保管場所に関するデータを格納する保管
場所設定データ格納モジュール32eを備えて構成され
る。また、物流支援プログラム32は、物流支援装置1
を物流計画決定部21とし機能させて、建築資材の搬入
日、建築資材の搬送(揚重)日、物流の負荷状態、保管
場所等の物流計画を決定する物流計画決定モジュール3
2fと、同じく物流支援装置1を物流計画出力部23と
して機能させて、物流計画決定部21にて決定された物
流計画(建築資材の搬入日、建築資材の搬送(揚重)
日、物流の負荷状態、保管場所等)に関する情報に基づ
いて物流計画を示すための画像データ等を作成して出力
する物流計画出力モジュール32gとを更に備えて構成
される。
FIG. 8 is a block diagram of a recording medium according to the embodiment of the present invention. The recording medium 30, as shown in FIG.
A program area 30a for recording a program is provided, and a distribution support program 32 is recorded in this program area 30a. The logistics support program 32
A process of causing the main module 32a that supervises the process and the physical distribution support device 1 configured as a computer system to function as the process data storage unit 11 (process database 11a) to store process data including at least information regarding the start date of the work. A data storage module 32b,
Similarly, the physical distribution support device 1 is caused to function as the material data storage unit 13 (material database 13a), and a material data storage module 32c for storing data (material data) relating to building materials required for work, and also the physical distribution support device 1 Allocation data storage unit 15 (allocation database 15
Allocation data storage module 32d that functions as a) and stores data relating to a predetermined period required for determining a carry-in date and a transport (lift) date in logistics planning unit 19, and also a logistics support device. 1 to function as the storage location setting data storage unit 17 (storage location setting database 17a) to store a storage location setting data storage module 32e that stores data relating to the storage location where the building materials carried into the work place are temporarily stored as inventory. It is equipped with. Further, the distribution support program 32 includes the distribution support device 1
The distribution plan determination module 3 that functions as the distribution plan determination unit 21 to determine a distribution plan such as a construction material delivery date, a construction material transportation (lifting) date, a distribution load state, and a storage location.
Similarly to 2f, the physical distribution support device 1 is made to function as the physical distribution plan output unit 23, and the physical distribution plan determined by the physical distribution plan determination unit 21 (the date of delivery of building materials, the transportation of building materials (lifting)).
And a physical distribution plan output module 32g for creating and outputting image data and the like for showing a physical distribution plan on the basis of information on the date, physical distribution load state, storage location, etc.).

【0067】記録媒体30のプログラム領域30aに記
録された物流支援プログラム32は、フレキシブルディ
スクドライブ装置又はCD−ROMドライブ装置等の読
取装置等をコンピュータシステムに接続してこれらの読
取装置からコンピュータシステムに読み出して、コンピ
ュータシステムの記憶装置に格納されることにより実行
可能となる。そして、記憶装置に格納された物流支援プ
ログラム32がコンピュータシステムのCPU等にて実
行されることにより、コンピュータシステムが工程デー
タ格納部11(工程データベース11a)、資材データ
格納部13(資材データベース13a)、割振データ格
納部15(割振データベース15a)、保管場所設定デ
ータ格納部17(保管場所設定データベース17a)、
及び物流計画立案部19(物流計画決定部21、物流計
画出力部23)として機能することになる。
The physical distribution support program 32 recorded in the program area 30a of the recording medium 30 is connected to a computer system by a reading device such as a flexible disk drive device or a CD-ROM drive device, and the reading device changes from the reading device to the computer system. It can be executed by being read and stored in the storage device of the computer system. Then, the computer system causes the computer system to execute the physical distribution support program 32 stored in the storage device by the CPU or the like of the computer system, and the process data storage unit 11 (process database 11a) and the material data storage unit 13 (material database 13a). , Allocation data storage unit 15 (allocation database 15a), storage location setting data storage unit 17 (storage location setting database 17a),
And the physical distribution plan planning unit 19 (the physical distribution plan determination unit 21 and the physical distribution plan output unit 23).

【0068】本発明は、前述した実施形態に限定される
ものではない。たとえば、本実施形態においては、各作
業に必要とされる建築資材の搬送(揚重)日数を「1」
としているが、対応する作業の所要期間にわたって複数
日に分けて建築資材を均等搬送(揚重)するようにして
もよい。また、作業所内での建築資材の搬送は、垂直方
向での搬送である揚重だけでなく、水平方向での搬送で
ある間配りを含んでいてもよい。
The present invention is not limited to the above embodiment. For example, in this embodiment, the number of days of transportation (lifting) of building materials required for each work is “1”.
However, the building material may be evenly transported (lifted) in a plurality of days over the required period of the corresponding work. Further, the transportation of the building material in the work place may include not only the lifting which is the transportation in the vertical direction but also the distribution which is the transportation in the horizontal direction.

【0069】また、物流計画立案部19は、物流計画立
案部19にて決定された物流計画を利用者の操作に基づ
いて調整するように構成してもよい。たとえば、図6の
物流計画画面Pとして示された物流計画において、工区
Bの作業aにて必要される建築資材(資材a)を工区A
の作業aにて必要とされる建築資材(資材a)と合わせ
て一台の車両で運送しようとして、利用者が工区Bの作
業aにて必要される建築資材(資材a)の搬入日を工区
Bの作業aの開始日前日から工区Aの作業aにて必要と
される建築資材(資材a)の搬入日に変更入力すると、
物流計画立案部19(物流計画決定部21)は、続い
て、物流計画決定部21は、読み込んだデータに基づい
て、物流の負荷状態として、搬入日における搬入車両の
台数と、搬送(揚重)日における搬送(揚重)回数と、
搬入日に搬入される建築資材の数量と、搬送(揚重)日
に搬送(揚重)される建築資材の数量、作業所に搬入さ
れた建築資材のうち作業所内に設置された保管場所に在
庫として一時保管される建築資材の数量(在庫数量)等
の物流の負荷状態を再度決定し直す。このとき、工区B
の作業aにて必要される建築資材(資材a)は在庫とし
て保管場所に保管されることから、在庫予定による保管
場所の占有状態を確認し、保管が可能な場合に、物流の
負荷状態を変更可能としてもよい。
The physical distribution planning unit 19 may be configured to adjust the physical distribution plan determined by the physical distribution planning unit 19 based on the operation of the user. For example, in the physical distribution plan shown as the physical distribution plan screen P in FIG.
In order to transport the building material (material a) together with the building material (material a) required in work a, the user sets the delivery date of the building material (material a) required in work a in work area B. If you change the input date of the construction material (material a) required for work a in work area A from the day before the start date of work a in work area B,
Based on the read data, the distribution plan planning unit 19 (distribution plan determination unit 21) then determines the distribution load state based on the read data, such as the number of vehicles to be carried in on the carry-in date and transportation (lifting). ) Number of transportation (lifting) times per day,
The number of building materials carried in on the delivery date, the quantity of building materials transported (lifted) on the transportation (lifting) day, and the storage location installed in the workplace among the building materials transported to the workplace The load status of physical distribution such as the quantity of building materials (stock quantity) temporarily stored as inventory is decided again. At this time, work area B
Since the building material (material a) required for work a) is stored in the storage location as inventory, check the occupancy status of the storage location according to the inventory plan, and if the storage is possible, check the distribution load state. It may be changeable.

【0070】[0070]

【発明の効果】以上、詳細に説明したように、本発明に
よれば、建築資材の物流をトータルで合理化、効率化す
ることが可能な建築資材の物流支援装置、建築資材の物
流支援方法、建築資材の物流支援プログラム及びコンピ
ュータ読み取り可能な記録媒体を提供することができ
る。
As described above in detail, according to the present invention, a construction material distribution support device, a construction material distribution support method, which can totally streamline and streamline the distribution of construction materials, A building material distribution support program and a computer-readable recording medium can be provided.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施形態に係る建築資材の物流支援装
置の構成図である。
FIG. 1 is a configuration diagram of a building material physical distribution support apparatus according to an embodiment of the present invention.

【図2】工程データ格納部に含まれる工程データベース
の構成図である。
FIG. 2 is a configuration diagram of a process database included in a process data storage unit.

【図3】資材データ格納部に含まれる資材データベース
の構成図である。
FIG. 3 is a configuration diagram of a material database included in a material data storage unit.

【図4】割振データ格納部に含まれる割振データベース
の構成図である。
FIG. 4 is a configuration diagram of an allocation database included in an allocation data storage unit.

【図5】保管場所設定データ格納部に含まれる保管場所
設定データベースの構成図である。
FIG. 5 is a configuration diagram of a storage location setting database included in a storage location setting data storage unit.

【図6】物流計画出力部23から出力される画像データ
に基づく物流計画画面の一例を示す図である。
FIG. 6 is a diagram showing an example of a physical distribution plan screen based on image data output from a physical distribution plan output unit 23.

【図7】本発明の実施形態に係る建築資材の物流支援装
置の動作(建築資材の物流支援方法)を示すフローチャ
ートである。
FIG. 7 is a flowchart showing the operation of the building material distribution support apparatus according to the embodiment of the present invention (building material distribution support method).

【図8】本発明の実施形態に係る記録媒体の構成図であ
る。
FIG. 8 is a configuration diagram of a recording medium according to an embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1…物流支援装置、11…工程データ格納部、11a…
工程データベース、13…資材データ格納部、13a…
資材データベース、15…割振データ格納部、15a…
割振データベース、17…保管場所設定データ格納部、
17a…保管場所設定データベース、19…物流計画立
案部、21…物流計画決定部、23…物流計画出力部、
30…記録媒体、32…物流支援プログラム、32b…
工程データ格納モジュール、32c…資材データ格納モ
ジュール、32d…割振データ格納モジュール、32e
…保管場所設定データ格納モジュール、32f…物流計
画決定モジュール、32g…物流計画出力モジュール、
P…物流計画画面。
1 ... Logistics support device, 11 ... Process data storage unit, 11a ...
Process database, 13 ... Material data storage, 13a ...
Material database, 15 ... Allocation data storage unit, 15a ...
Allocation database, 17 ... Storage location setting data storage unit,
Reference numeral 17a ... Storage location setting database, 19 ... Logistics planning unit, 21 ... Logistics plan determination unit, 23 ... Logistics plan output unit,
30 ... Recording medium, 32 ... Logistics support program, 32b ...
Process data storage module, 32c ... Material data storage module, 32d ... Allocation data storage module, 32e
... storage location setting data storage module, 32f ... physical distribution plan determination module, 32g ... physical distribution plan output module,
P ... Logistics planning screen.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 監物 宏輔 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内   ─────────────────────────────────────────────────── ─── Continued front page    (72) Inventor Kosuke             Kashima-ken, 1-2-7 Moto-Akasaka, Minato-ku, Tokyo             Inside the corporation

Claims (19)

【特許請求の範囲】[Claims] 【請求項1】 建築資材を作業所に搬入し、搬入された
前記建築資材を前記作業所内にて搬送する物流計画を立
案するための建築資材の物流支援装置であって、 少なくとも作業の開始日に関する情報を含む工程データ
を格納する工程データ格納手段と、 前記作業に必要とされる建築資材に関するデータを格納
する資材データ格納手段と、 前記工程データ格納手段に格納された前記工程データに
含まれる前記作業の開始日に関する情報と前記資材デー
タ格納手段に格納された前記建築資材に関するデータと
に基づいて、前記作業に必要とされる建築資材の前記作
業所への搬入日を前記作業の開始日よりも所定期間前と
なるように決定するとともに、前記作業に必要とされる
建築資材の前記作業所内での搬送日を前記作業の開始日
よりも所定期間前となるように決定する物流計画立案手
段と、を備えていることを特徴とする建築資材の物流支
援装置。
1. A building material distribution support device for carrying in a building material to a work place and planning a distribution plan for transporting the carried in building material within the work place, at least the start date of the work. Included in the process data stored in the process data storage unit, a process data storage unit that stores process data including information about the material, a material data storage unit that stores data related to building materials required for the work Based on the information on the start date of the work and the data on the building material stored in the material data storage means, the date of bringing in the building material required for the work to the work place is the start date of the work. It is determined to be before a predetermined period of time, and the transport date of the building material required for the work in the work place is a predetermined period from the start date of the work. A logistics support device for building materials, comprising: a logistics planning means for determining as before.
【請求項2】 前記物流計画立案手段にて前記搬入日及
び前記搬送日を決定するために必要とされる前記所定期
間に関するデータを格納する割振データ格納手段を更に
備えていることを特徴とする請求項1に記載の建築資材
の物流支援装置。
2. The allocation data storage means for storing data relating to the predetermined period required for determining the carry-in date and the transport date by the physical distribution planning means, is further provided. The building material physical distribution support apparatus according to claim 1.
【請求項3】 前記資材データ格納手段に格納される前
記建築資材に関するデータは、前記作業に必要とされる
建築資材の種類、数量、前記作業所内での搬送回数、及
び前記作業に必要とされる建築資材を搬入するための搬
入車両の台数を含んでいることを特徴とする請求項1に
記載の建築資材の物流支援装置。
3. The data regarding the building material stored in the material data storage means is the type and quantity of the building material required for the work, the number of times of transportation in the work place, and the data required for the work. The distribution support apparatus for building materials according to claim 1, wherein the distribution supporting apparatus for building materials includes the number of loading vehicles for loading building materials.
【請求項4】 前記物流計画立案手段は、前記搬入日に
おける前記搬入車両の台数と、前記搬送日における搬送
回数とを決定することを特徴とする請求項3に記載の建
築資材の物流支援装置。
4. The distribution support apparatus for building materials according to claim 3, wherein the physical distribution planning means determines the number of the carried-in vehicles on the carrying-in date and the number of times of carrying on the carrying day. .
【請求項5】 前記物流計画立案手段は、前記搬入日に
搬入される建築資材の数量と、前記搬送日に搬送される
建築資材の数量とを決定することを特徴とする請求項3
に記載の建築資材の物流支援装置。
5. The physical distribution planning means determines a quantity of building materials carried in on the carrying-in date and a quantity of building materials carried on the carrying day.
The distribution support device for building materials described in.
【請求項6】 前記物流計画立案手段は、前記作業所に
搬入された建築資材のうち前記作業所内に設置された保
管場所に在庫として一時保管される建築資材の数量を算
出することを特徴とする請求項3に記載の建築資材の物
流支援装置。
6. The physical distribution planning means calculates the number of building materials temporarily stored as an inventory in a storage place installed in the work place among the building materials carried into the work place. The logistics support device for building materials according to claim 3.
【請求項7】 建築資材を作業所に搬入し、搬入された
前記建築資材を前記作業所内にて搬送する物流計画を立
案するための建築資材の物流支援方法であって、 少なくとも作業の開始日に関する情報を含む工程データ
を格納する工程データ格納手段と、 前記作業に必要とされる建築資材に関するデータを格納
する資材データ格納手段と、を用い、 物流計画立案手段が、前記工程データ格納手段に格納さ
れた前記工程データに含まれる前記作業の開始日に関す
る情報と前記資材データ格納手段に格納された前記建築
資材に関するデータとに基づいて、前記作業に必要とさ
れる建築資材の前記作業所への搬入日を前記作業の開始
日よりも所定期間前となるように決定するとともに、前
記作業に必要とされる建築資材の前記作業所内での搬送
日を前記作業の開始日よりも所定期間前となるように決
定する物流計画立案ステップを備えていることを特徴と
する建築資材の物流支援方法。
7. A method of supporting distribution of building materials for delivering a building material to a work place and devising a distribution plan for transporting the received building material within the work place, at least the start date of the work. Using the process data storage means for storing the process data including the information on the above, and the material data storage means for storing the data on the building materials required for the work, the physical distribution planning means is used as the process data storage means. Based on the information about the start date of the work included in the stored process data and the data about the building material stored in the material data storage means, to the work place of the building material required for the work The delivery date of the work is determined to be a predetermined period before the start date of the work, and the delivery date of the building materials required for the work in the work place is set A logistics support method for building materials, comprising a logistics planning step of determining a predetermined period before the start date of the work.
【請求項8】 前記物流計画立案手段にて前記搬入日及
び前記搬送日を決定するために必要とされる前記所定期
間に関するデータを格納する割振データ格納手段を更に
用い、 前記物流計画立案ステップにおいて、前記物流計画立案
手段は、更に前記割振データ格納手段に格納された前記
所定期間に関するデータに基づいて、前記搬入日及び前
記搬送日を決定することを特徴とする請求項7に記載の
建築資材の物流支援方法。
8. The physical distribution planning means further comprises allocation data storage means for storing data relating to the predetermined period required for determining the carrying-in date and the carrying date, in the physical distribution planning step. The building material according to claim 7, wherein the physical distribution planning means further determines the carry-in date and the carrying date based on the data relating to the predetermined period stored in the allocation data storage means. Logistics support method.
【請求項9】 前記資材データ格納手段に格納される前
記建築資材に関するデータは、前記作業に必要とされる
建築資材の種類、数量、前記作業所内での搬送回数、及
び前記作業に必要とされる建築資材を搬入するための搬
入車両の台数を含んでいることを特徴とする請求項7に
記載の建築資材の物流支援方法。
9. The data regarding the building material stored in the material data storage means is the type and quantity of the building material required for the work, the number of times of transportation in the work place, and the data required for the work. The method of supporting distribution of a building material according to claim 7, wherein the method includes the number of vehicles for carrying in the building material.
【請求項10】 前記物流計画立案ステップにおいて、
前記物流計画立案手段は、前記搬入日における前記搬入
車両の台数と、前記搬送日における搬送回数とを決定す
ることを特徴とする請求項9に記載の建築資材の物流支
援方法。
10. In the logistics planning step,
10. The distribution support method for building materials according to claim 9, wherein the distribution planning means determines the number of the carried-in vehicles on the carrying-in date and the number of times of carrying on the carrying day.
【請求項11】 前記物流計画立案ステップにおいて、
前記物流計画立案手段は、前記搬入日に搬入される建築
資材の数量と、前記搬送日に搬送される建築資材の数量
とを決定することを特徴とする請求項9に記載の建築資
材の物流支援方法。
11. In the physical distribution planning step,
10. The distribution of building materials according to claim 9, wherein the distribution planning means determines a quantity of building materials carried in on the carrying-in date and a quantity of building materials carried on the carrying day. How to help.
【請求項12】 前記物流計画立案ステップにおいて、
前記物流計画立案手段は、前記作業所に搬入された建築
資材のうち前記作業所内に設置された保管場所に在庫と
して一時保管される建築資材の数量を算出することを特
徴とする請求項9に記載の建築資材の物流支援方法。
12. In the logistics planning step,
10. The physical distribution planning means calculates the number of building materials temporarily stored as an inventory in a storage place installed in the working place among the building materials carried into the working place. Logistics support method for the listed building materials.
【請求項13】 建築資材を作業所に搬入し、搬入され
た前記建築資材を前記作業所内にて搬送する物流計画を
立案するためにコンピュータを、 少なくとも作業の開始日に関する情報を含む工程データ
を格納する工程データ格納手段、 前記作業に必要とされる建築資材に関するデータを格納
する資材データ格納手段、及び前記工程データ格納手段
に格納された前記工程データに含まれる前記作業の開始
日に関する情報と前記資材データ格納手段に格納された
前記建築資材に関するデータとに基づいて、前記作業に
必要とされる建築資材の前記作業所への搬入日を前記作
業の開始日よりも所定期間前となるように決定するとと
もに、前記作業に必要とされる建築資材の前記作業所内
での搬送日を前記作業の開始日よりも所定期間前となる
ように決定する物流計画立案手段、として機能させるこ
とを特徴とする建築資材の物流支援プログラム。
13. A computer for carrying a building material into a work place and planning a physical distribution plan for carrying the carried building material in the work place, wherein process data including at least information on a start date of the work is stored. Process data storage means for storing, material data storage means for storing data on building materials required for the work, and information on the start date of the work included in the process data stored in the process data storage means, Based on the data on the building material stored in the material data storage means, the date of bringing in the building material required for the work to the work place is a predetermined period before the start date of the work. In addition, the transportation date of the building materials required for the work in the work place should be a predetermined period before the start date of the work. Constant for logistics planning means, is characterized in that to function as a building material logistics support program.
【請求項14】 前記物流計画立案手段にて前記搬入日
及び前記搬送日を決定するために必要とされる前記所定
期間に関するデータを格納する割振データ格納手段を更
に備えていることを特徴とする請求項13に記載の建築
資材の物流支援プログラム。
14. The distribution data planning means further comprises an allocation data storage means for storing data relating to the predetermined period required for determining the carry-in date and the transport date. The logistics support program for building materials according to claim 13.
【請求項15】 前記資材データ格納手段に格納される
前記建築資材に関するデータは、前記作業に必要とされ
る建築資材の種類、数量、前記作業所内での搬送回数、
及び前記作業に必要とされる建築資材を搬入するための
搬入車両の台数を含んでいることを特徴とする請求項1
3に記載の建築資材の物流支援プログラム。
15. The data on the building material stored in the material data storage means includes the type and quantity of the building material required for the work, the number of times of transportation in the work place,
And the number of loading vehicles for loading building materials required for the work.
The logistics support program for building materials described in 3.
【請求項16】 前記物流計画立案手段は、前記搬入日
における前記搬入車両の台数と、前記搬送日における搬
送回数とを決定することを特徴とする請求項15に記載
の建築資材の物流支援プログラム。
16. The logistics support program for building materials according to claim 15, wherein the physical distribution planning means determines the number of the input vehicles on the import date and the number of transfers on the import date. .
【請求項17】 前記物流計画立案手段は、前記搬入日
に搬入される建築資材の数量と、前記搬送日に搬送され
る建築資材の数量とを決定することを特徴とする請求項
15に記載の建築資材の物流支援プログラム。
17. The physical distribution planning means determines the number of building materials carried in on the carrying-in date and the number of building materials carried on the carrying day. Building materials logistics support program.
【請求項18】 前記物流計画立案手段は、前記作業所
に搬入された建築資材のうち前記作業所内に設置された
保管場所に在庫として一時保管される建築資材の数量を
算出することを特徴とする請求項15に記載の建築資材
の物流支援プログラム。
18. The distribution planning means calculates the number of building materials temporarily stored as inventory in a storage place installed in the work place among the building materials carried into the work place. The logistics support program for building materials according to claim 15.
【請求項19】 請求項13〜請求項18のいずれか一
項に記載の建築資材の物流支援プログラムを記録したこ
とを特徴とするコンピュータ読み取り可能な記録媒体。
19. A computer-readable recording medium on which the distribution support program for building materials according to any one of claims 13 to 18 is recorded.
JP2001222013A 2001-07-23 2001-07-23 Building material distribution support device, building material distribution support method, building material distribution support program, and computer readable recording medium Pending JP2003036287A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001222013A JP2003036287A (en) 2001-07-23 2001-07-23 Building material distribution support device, building material distribution support method, building material distribution support program, and computer readable recording medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001222013A JP2003036287A (en) 2001-07-23 2001-07-23 Building material distribution support device, building material distribution support method, building material distribution support program, and computer readable recording medium

Publications (1)

Publication Number Publication Date
JP2003036287A true JP2003036287A (en) 2003-02-07

Family

ID=19055575

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001222013A Pending JP2003036287A (en) 2001-07-23 2001-07-23 Building material distribution support device, building material distribution support method, building material distribution support program, and computer readable recording medium

Country Status (1)

Country Link
JP (1) JP2003036287A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112270522A (en) * 2020-10-14 2021-01-26 广东博智林机器人有限公司 Steel bar operation method and system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112270522A (en) * 2020-10-14 2021-01-26 广东博智林机器人有限公司 Steel bar operation method and system

Similar Documents

Publication Publication Date Title
US8655736B2 (en) Buyer-side consolidation of compatible purchase orders
US8219503B2 (en) Estimated time of arrival (ETA) systems and methods
US7668727B2 (en) System and method for building loads from requisitions
KR102447337B1 (en) Systems and methods for automated delivery worker scheduling
JP2009286502A (en) Transportation scheduling system
JP2010168205A (en) System, apparatus, method and program for optimum vehicle assignment
Hill et al. Reducing vendor delivery uncertainties in a JIT environment
De Koster Warehouse assessment in a single tour
JP2002203158A (en) Work planning method and work planning device
JP4030465B2 (en) Product inventory management system
JP2006312546A (en) Physical distribution support system for construction site and physical distribution support method for construction site using this system
CN111401800A (en) Vehicle dispatching system suitable for ceramic industry
JP2003036287A (en) Building material distribution support device, building material distribution support method, building material distribution support program, and computer readable recording medium
JP3239980B2 (en) Logistics management system
JP3303293B2 (en) Automatic warehouse and its control method
JP2910219B2 (en) Distribution method and distribution system
JP2002193450A (en) Physical distribution control method and physical distribution control system for transported cargo
JP3163286B2 (en) Vehicle dispatch system
US20040117230A1 (en) Recalculating planned requests
JP4263496B2 (en) Shipping management method and computer
WO2019039605A1 (en) Information processing device
US7487120B1 (en) Methods and system for continuous replenishment planning of consignment inventory
WO2019039604A1 (en) Information processing device
JP2003141675A (en) System for vehicle allocation plan
CN112613807B (en) Optimization method for finished cigarette delivery scheduling

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20041224

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070710

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070907

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20071113