JP2002348813A - Method for constructing main tower of diagonal tensioning bridge - Google Patents

Method for constructing main tower of diagonal tensioning bridge

Info

Publication number
JP2002348813A
JP2002348813A JP2001158075A JP2001158075A JP2002348813A JP 2002348813 A JP2002348813 A JP 2002348813A JP 2001158075 A JP2001158075 A JP 2001158075A JP 2001158075 A JP2001158075 A JP 2001158075A JP 2002348813 A JP2002348813 A JP 2002348813A
Authority
JP
Japan
Prior art keywords
steel shell
main tower
bridge
concrete
diagonal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001158075A
Other languages
Japanese (ja)
Other versions
JP4387071B2 (en
Inventor
Jiro Iida
字朗 飯田
Hiroaki Nakayama
裕昭 中山
Akio Kasuga
昭夫 春日
Katsuhiko Mizuno
克彦 水野
Masaharu Kuwano
昌晴 桑野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Construction Co Ltd
Original Assignee
Sumitomo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Construction Co Ltd filed Critical Sumitomo Construction Co Ltd
Priority to JP2001158075A priority Critical patent/JP4387071B2/en
Publication of JP2002348813A publication Critical patent/JP2002348813A/en
Application granted granted Critical
Publication of JP4387071B2 publication Critical patent/JP4387071B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method for constructing a main tower of a diagonal tensioning bridge, which reduces the weight of a steel shell portion of the main tower, prevents stress to concentrate on a lower bed portion of the steel shell portion in a concrete portion, and improves the workability when the main tower is constructed. SOLUTION: According to the method, a plurality of steel shell units 24 are stacked on a main tower construction portion of the diagonal tensioning bridge to set the steel shell portion 20, and then concrete is lined along the steel shell portion 20 such that a bridge-axially central portion thereof is left like a belt, to thereby form a pre-cast concrete portion 22A. Thereafter, a diagonal member 14 is anchored to each anchoring structure 18 of the steel shell portion 20 via an anchor 16, and tension T is introduced to each diagonal member 14. Lastly, concrete is placed on the bridge-axially central portion of the steel shell portion 20. In this manner, the pre-cast concrete portion 22A is not formed at the bridge-axially central portion of the steel shell portion 20, and therefore a horizontal component (tensile force) of a diagonal tensile force T is borne only by the steel shell portion 20, while a vertical component (compressive force) of the diagonal tensile force T is borne by a composite cross section between the steel shell portion 20 and the pre-cast concrete portion 22A. As a result, the burden on the steel shell portion 20 is reduced.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本願発明は、斜張橋の主塔構
築方法に関するものであり、特に主塔側斜材定着部の構
築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a main tower of a cable-stayed bridge, and more particularly to a method of constructing a main tower side diagonal material fixing section.

【0002】[0002]

【従来の技術】一般に斜張橋は、主塔の橋軸方向両側に
複数対の斜材が上下複数段にわたって張設された構成と
なっており、その主塔側斜材定着部は、上記複数対の斜
材を定着するための複数対の定着構造を有する鋼殻部に
コンクリートが巻き立てられた構成となっている。
2. Description of the Related Art Generally, a cable-stayed bridge has a structure in which a plurality of pairs of diagonal members are stretched over a plurality of upper and lower stages on both sides in the bridge axis direction of a main tower. Concrete is wound around a steel shell having a plurality of pairs of fixing structures for fixing a plurality of pairs of diagonal members.

【0003】ただし従来の斜張橋においては、コンクリ
ート部に引張荷重が作用しないようにするため、主塔構
築時における斜材張力の導入を、鋼殻部にコンクリート
が巻き立てられる前の状態で行うようになっている。
However, in a conventional cable-stayed bridge, in order to prevent a tensile load from acting on the concrete part, the introduction of the diagonal material tension when constructing the main tower is performed in a state before the concrete is rolled around the steel shell part. It is supposed to do.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、このよ
うに斜材張力の導入をコンクリート巻き立て前の状態で
行うようにした場合には、斜材張力を鋼殻部ですべて受
け持つ必要があるので、その強度を確保するために鋼殻
部の重量が必然的に大きなものとなってしまい、これに
より架橋機材コストが高くついてしまう、という問題が
ある。
However, in the case where the introduction of the diagonal material tension is performed before the concrete is rolled up as described above, it is necessary to cover all of the diagonal material tension with the steel shell. In order to secure the strength, the weight of the steel shell is inevitably increased, which causes a problem that the cost of the cross-linking equipment increases.

【0005】また、斜材張力を鋼殻部ですべて受け持つ
ことから、コンクリート部における鋼殻部の下端部分に
応力集中が発生しやすくなる、という問題もある。
[0005] Further, since all of the diagonal material tension is taken up by the steel shell, there is also a problem that stress concentration tends to occur at the lower end of the steel shell in the concrete part.

【0006】さらに、鋼殻部の重量が大きなものとなっ
てしまうことから、架設・運搬に重量制限のあるような
場所においては施工が困難となる、という問題もある。
Further, since the weight of the steel shell becomes large, there is also a problem that it is difficult to perform the construction in a place where the construction and transportation have a weight limit.

【0007】本願発明は、このような事情に鑑みてなさ
れたものであって、主塔の鋼殻部を軽量化するととも
に、そのコンクリート部における鋼殻部の下端部分に応
力集中が発生するのを防止し、かつ主塔構築の際の施工
性向上を図ることができる斜張橋の主塔構築方法を提供
することを目的とするものである。
[0007] The present invention has been made in view of the above-mentioned circumstances, and reduces the weight of the steel shell of the main tower and causes stress concentration at the lower end of the steel shell in the concrete part. It is an object of the present invention to provide a method for constructing a main tower of a cable-stayed bridge, which can prevent the occurrence of the problem and improve the workability when constructing the main tower.

【0008】[0008]

【課題を解決するための手段】本願発明は、鋼殻部に対
してある程度コンクリートを巻き立てた状態で斜材張力
の導入を行うようにすることにより、上記目的達成を図
るようにしたものである。
The present invention achieves the above object by introducing diagonal tension in a state where concrete is wound up to a certain extent on a steel shell. is there.

【0009】すなわち、本願発明に係る斜張橋の主塔構
築方法は、主塔の橋軸方向両側に複数対の斜材が上下複
数段にわたって張設されてなる斜張橋の主塔構築方法で
あって、上記斜張橋の主塔構築部分に、上記複数対の斜
材を定着するための複数対の定着構造を有する鋼殻部を
設置した後、この鋼殻部に対して、該鋼殻部の橋軸方向
中央部分を残すようにしてコンクリートを巻き立て、そ
の後、上記各定着構造に定着された上記各斜材に張力を
導入し、最後に、上記鋼殻部の橋軸方向中央部分にコン
クリートを打設する、ことを特徴とするものである。
That is, the method for constructing a main tower of a cable-stayed bridge according to the present invention is a method for constructing a main tower of a cable-stayed bridge in which a plurality of pairs of diagonal members are stretched over a plurality of upper and lower stages on both sides in the bridge axis direction of the main tower. After installing a steel shell portion having a plurality of pairs of anchoring structures for anchoring the plurality of pairs of diagonal members on the main tower building portion of the cable stayed bridge, The concrete is rolled up so as to leave the central part of the steel shell in the bridge axis direction, and then tension is introduced into the respective diagonal members fixed to the respective anchoring structures. It is characterized by placing concrete in the central part.

【0010】上記「斜張橋」は、主塔の橋軸方向両側に
複数対の斜材が上下複数段にわたって張設されたもので
あれば、その種類は特に限定されるものではなく、通常
の斜張橋であってもよいし、主塔側斜材定着部が主塔上
部に集中的に配置された比較的主塔高さの低いエクスト
ラドーズド橋等の斜張橋であってもよい。
The type of the cable-stayed bridge is not particularly limited as long as a plurality of pairs of diagonal members are stretched over a plurality of upper and lower stages on both sides of the main tower in the bridge axis direction. Or a cable-stayed bridge, such as an extra-dosed bridge with a relatively low main tower height, in which the main tower side diagonal material anchoring section is concentrated at the top of the main tower. Good.

【0011】また、上記「鋼殻部」は、複数対の斜材を
定着するための複数対の定着構造を有するものであれ
ば、その具体的構成は特に限定されるものではない。
The specific configuration of the "steel shell" is not particularly limited as long as it has a plurality of pairs of fixing structures for fixing a plurality of pairs of diagonal members.

【0012】[0012]

【発明の作用効果】上記構成に示すように、本願発明に
係る斜張橋の主塔構築方法は、斜張橋の主塔構築部分
に、複数対の斜材を定着するための複数対の定着構造を
有する鋼殻部を設置した後、この鋼殻部に対してその橋
軸方向中央部分を残すようにしてコンクリートを巻き立
て、その後、各定着構造に定着された各斜材に張力を導
入し、最後に、鋼殻部の橋軸方向中央部分にコンクリー
トを打設するようになっているので、次のような作用効
果を得ることができる。
As described above, the method for constructing a main tower of a cable-stayed bridge according to the present invention comprises a plurality of pairs of fixing members for fixing a plurality of pairs of diagonal members to a main tower constructing portion of the cable-stayed bridge. After installing the steel shell having the anchoring structure, concrete is wrapped around the steel shell so as to leave the central part in the bridge axis direction, and then tension is applied to each diagonal material anchored to each anchoring structure. After the introduction, finally, concrete is poured into the central portion of the steel shell in the bridge axis direction, so that the following operation and effect can be obtained.

【0013】すなわち、鋼殻部に対してその橋軸方向中
央部分を残すようにしてコンクリートを巻き立てた後に
斜材張力の導入を行うことにより、斜材張力の水平成分
(引張力)については鋼殻部のみで受け持つ一方、斜材
張力の鉛直成分(圧縮力)については鋼殻部とコンクリ
ート部との合成断面で受け持つようにすることができ
る。
That is, by introducing the diagonal material tension after rolling up the concrete so as to leave the central part in the bridge axis direction with respect to the steel shell portion, the horizontal component (tensile force) of the diagonal material tension is obtained. The vertical component (compression force) of the diagonal material tension can be handled by the composite section of the steel shell and the concrete while the steel shell only takes charge.

【0014】このため、従来のように斜材張力を鋼殻部
ですべて受け持つ構造に比して、鋼殻部の負荷を軽減す
ることができ、その分だけ鋼殻部を軽量化することがで
きる。しかもその際、コンクリート部には引張荷重が作
用しないようにすることができる。
Therefore, the load on the steel shell can be reduced as compared with the conventional structure in which all the diagonal material tension is received by the steel shell, and the weight of the steel shell can be reduced accordingly. it can. Moreover, at that time, it is possible to prevent the tensile load from acting on the concrete portion.

【0015】また、圧縮力として作用する斜材張力の鉛
直成分を、鋼殻部とコンクリート部との合成断面で受け
持つことにより、鋼殻部下端に位置するコンクリート部
分に応力集中が発生してしまうのを未然に防止すること
ができる。
In addition, since the vertical component of the diagonal material tension acting as a compressive force is taken over by the composite cross section of the steel shell and the concrete, stress concentration occurs in the concrete portion located at the lower end of the steel shell. Can be prevented beforehand.

【0016】さらに、鋼殻部の軽量化を図ることができ
ることから、架橋機材のコスト低減を図ることができ、
また、架設・運搬に重量制限のあるような場所での施工
も行いやすくなる。
Furthermore, since the weight of the steel shell can be reduced, the cost of the cross-linking equipment can be reduced.
In addition, it is easy to perform construction in places where there is a limit on the weight of erection and transportation.

【0017】このように本願発明に係る斜張橋の主塔構
築方法を採用することにより、主塔の鋼殻部を軽量化す
ることができるとともに、そのコンクリート部における
鋼殻部の下端部分に応力集中が発生するのを防止するこ
とができ、かつ主塔構築の際の施工性向上を図ることが
できる。
As described above, by adopting the method for constructing the main tower of the cable-stayed bridge according to the present invention, it is possible to reduce the weight of the steel shell of the main tower, and at the lower end of the steel shell in the concrete part. The occurrence of stress concentration can be prevented, and the workability at the time of building the main tower can be improved.

【0018】上記「鋼殻部」の具体的構成が特に限定さ
れないことは上述したとおりであるが、この鋼殻部の設
置を、各対の定着構造毎に分割形成された複数の鋼殻ユ
ニットを積み重ねることにより行う構成とすれば、架設
・運搬を重量が十分に小さい鋼殻ユニットの単位で行う
ことができるので、架設・運搬に重量制限のあるような
場所での施工を極めて容易に行うことができる。
As described above, the specific configuration of the "steel shell" is not particularly limited. However, the installation of the steel shell is performed by a plurality of steel shell units divided for each pair of fixing structures. If the construction is carried out by stacking, construction and transportation can be performed in units of steel shell units whose weight is sufficiently small, so construction in places where the construction and transportation are limited by weight is extremely easy. be able to.

【0019】この場合において、各鋼殻ユニットの積み
重ねを、橋軸方向および橋軸直交方向いずれの方向に関
しても山切りカット面に設定された積層面を介して行う
構成とすれば、積み上げ時の施工誤差を最小限に抑える
ことができ、これにより施工性を一層向上させることが
できる。
[0019] In this case, if the stacking of the steel shell units is performed through the laminating plane set as the cleave cut plane in both the bridge axis direction and the bridge axis orthogonal direction, the stacking at the time of stacking is performed. Construction errors can be minimized, which can further improve the workability.

【0020】その際、予め工場等での表面加工により積
層面の面精度を高めておくようにすれば、各鋼殻ユニッ
トをメタルタッチ(高精度な面接触状態)で積み重ねる
ことが可能となるので、現場での溶接作業を不要とする
ことができ、これにより大幅な施工性向上を図ることが
できる。
At this time, if the surface accuracy of the lamination surface is increased in advance by surface processing in a factory or the like, it is possible to stack the steel shell units by metal touch (high-precision surface contact state). Therefore, welding work on site can be dispensed with, thereby greatly improving workability.

【0021】また、各鋼殻ユニットとして、その外周面
に複数のスタッドジベルが設けられたものを用いるよう
にすれば、鋼殻部に圧縮力として作用する斜材張力の鉛
直成分を、各鋼殻ユニットのスタッドジベルを介してコ
ンクリート部へ効率よく伝達することができるので、鋼
殻部とコンクリート部との合成断面での圧縮力負担を一
層効果的に行うことができる。
If each steel shell unit is provided with a plurality of stud dowels on its outer peripheral surface, the vertical component of the diagonal material tension acting as a compressive force on the steel shell can be reduced by each steel shell unit. Since the power can be efficiently transmitted to the concrete portion via the stud dowel of the shell unit, the compressive force can be more effectively applied to the composite cross section of the steel shell portion and the concrete portion.

【0022】[0022]

【発明の実施の形態】以下、図面を用いて、本願発明の
実施の形態について説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0023】図1は、本願発明の一実施形態に係る主塔
構築方法の対象となる斜張橋10の要部を、橋軸直交方
向から見て示す側面図であり、図2は、そのII-II 線矢
視図である。また、図3は、図1のIII 部詳細図であ
り、図4は、図3のIV-IV 線断面詳細図である。
FIG. 1 is a side view showing a main part of a cable-stayed bridge 10 to be subjected to a method for constructing a main tower according to an embodiment of the present invention, as viewed from a direction orthogonal to the bridge axis, and FIG. FIG. 2 is a view taken along line II-II. FIG. 3 is a detailed view of a part III in FIG. 1, and FIG. 4 is a detailed view of a cross section taken along line IV-IV of FIG.

【0024】これらの図に示すように、この斜張橋10
は、主塔高さが比較的低い(16m程度の)エクストラ
ドーズド橋であって、主塔12の橋軸方向両側に10対
の斜材14が上下10段にわたって張設されてなってい
る。これら各斜材14は、主塔12の上部に配置された
主塔側斜材定着部12Aと、主桁50における主塔12
の橋軸方向両側に配置された主桁側斜材定着部(図示せ
ず)との間に斜めに張設されている。その際、これら各
斜材14は、下段に位置するものほど大きな傾斜角で張
設されるようになっている。
As shown in these figures, this cable stayed bridge 10
Is an extradosed bridge having a relatively low height of the main tower (about 16 m), in which ten pairs of diagonal members 14 are stretched on both sides in the bridge axis direction of the main tower 12 in ten vertical steps. . Each of these diagonal members 14 is composed of a main tower side diagonal material fixing section 12 </ b> A arranged above the main tower 12 and a main tower 12
And a main girder-side diagonal material fixing portion (not shown) arranged on both sides in the bridge axis direction. At this time, each of the diagonal members 14 is stretched with a larger inclination angle as the lower one is located.

【0025】主塔側斜材定着部12Aは、上記10対の
斜材14の各々を、定着具16を介して定着するための
10対の定着構造18を有する鋼殻部20と、この鋼殻
部18に巻き立てられたコンクリート部22とからなっ
ている。
The main tower side diagonal material fixing section 12A is composed of a steel shell portion 20 having ten pairs of fixing structures 18 for fixing each of the ten pairs of diagonal members 14 through a fixing tool 16, The concrete part 22 is wound around the shell part 18.

【0026】鋼殻部20は、各対の定着構造18毎に分
割形成された10個の鋼殻ユニット24が積み重ねられ
てなっている(これについては後述する)。
The steel shell portion 20 is formed by stacking ten steel shell units 24 formed separately for each pair of fixing structures 18 (this will be described later).

【0027】一方、コンクリート部22は、先打ちコン
クリート部22Aと、後打ちコンクリート部22Bとか
らなっている。
On the other hand, the concrete section 22 is composed of a pre-cast concrete section 22A and a post-cast concrete section 22B.

【0028】先打ちコンクリート部22Aは、鋼殻部2
0の橋軸方向中央部分および橋軸直交方向中央部分を各
々帯状に残すようにしてコンクリートを巻き立てること
により形成されている。また、後打ちコンクリート部2
2Bは、鋼殻部20の橋軸方向中央部分の両側に帯状に
残された凹部空間に、コンクリートを打設することによ
り形成されている。これら各後打ちコンクリート部22
Bの表面は、先打ちコンクリート部22Aの表面に対し
て一段奥まった位置に形成されている。
The precast concrete portion 22A is made of steel shell 2
The bridge is formed by rolling up concrete so that the central portion of the bridge axis direction 0 and the central portion of the bridge axis direction are left in a strip shape. In addition, after-cast concrete part 2
2B is formed by pouring concrete into the concave space left in a strip shape on both sides of the central portion of the steel shell 20 in the bridge axis direction. Each of these post-cast concrete sections 22
The surface of B is formed at a position one step lower than the surface of the precast concrete portion 22A.

【0029】図5は、鋼殻部20を示す側面図であり、
図6は、この鋼殻部20を構成する10個の鋼殻ユニッ
ト24のうち、上から2段目の鋼殻ユニット24を例に
とって単品で示す側面図である。また、図7は、これら
鋼殻ユニット24を積み重ねる工程を示す斜視図であ
る。
FIG. 5 is a side view showing the steel shell 20.
FIG. 6 is a side view showing the steel shell unit 24 of the second stage from the top as an example out of the ten steel shell units 24 constituting the steel shell part 20. FIG. 7 is a perspective view showing a step of stacking the steel shell units 24.

【0030】これらの図に示すように、各鋼殻ユニット
24は、橋軸方向に延びる長尺の矩形枠26内に上記1
対の定着構造18が設けられてなっている。
As shown in these figures, each of the steel shell units 24 is accommodated in a long rectangular frame 26 extending in the bridge axis direction.
A pair of fixing structures 18 are provided.

【0031】矩形枠26は、1対の長尺壁面板28と、
これら長尺壁面板28の橋軸方向両端面に溶接固定され
た1対の短尺壁面板30とからなっている。
The rectangular frame 26 includes a pair of long wall plates 28,
The pair of short wall plates 30 are welded and fixed to both end surfaces of the long wall plates 28 in the bridge axis direction.

【0032】各長尺壁面板28は、その上端面28aお
よび下端面28bが、いずれも山切りカット面として形
成されている。すなわち、これら上端面28aおよび下
端面28bの中央部は水平面として形成されているが、
その橋軸方向両端部は、斜め下方へ傾斜した傾斜面とし
て形成されている。
Each of the long wall surfaces 28 has an upper end surface 28a and a lower end surface 28b formed as cut-away surfaces. That is, although the central portion of the upper end surface 28a and the lower end surface 28b is formed as a horizontal plane,
Both ends in the bridge axis direction are formed as inclined surfaces inclined obliquely downward.

【0033】また、各短尺壁面板30も、その上端面3
0aおよび下端面30bが、いずれも山切りカット面と
して形成されている。すなわち、これら上端面30aお
よび下端面30bは山形に形成されており、その橋軸直
交方向両端部が各長尺壁面板28の板厚分だけ水平面と
して形成されている。これら各短尺壁面板30の略中心
位置には、斜材14を挿通させるための斜材挿通孔30
cが形成されている。
Each short wall surface plate 30 also has an upper end surface 3.
0a and the lower end surface 30b are both formed as cut-away surfaces. That is, the upper end surface 30a and the lower end surface 30b are formed in a mountain shape, and both ends in the direction orthogonal to the bridge axis are formed as horizontal surfaces by the thickness of each long wall plate 28. At approximately the center of each of these short wall plates 30, a diagonal material insertion hole 30 for inserting the diagonal material 14 is provided.
c is formed.

【0034】矩形枠26の外周面には、多数のスタッド
ジベル32が設けられている。これらスタッドジベル3
2は、各長尺壁面板28における橋軸方向中央部以外の
部分および各短尺壁面板30における斜材挿通孔30c
の両側部分に、その全域にわたって所定配置で設けられ
ている。
A number of stud dowels 32 are provided on the outer peripheral surface of the rectangular frame 26. These stud dowels 3
2 is a portion of each long wall plate 28 other than the central portion in the bridge axis direction and a diagonal material insertion hole 30c in each short wall plate 30
Are provided in a predetermined arrangement over the entire area.

【0035】各定着構造18は、定着具16を受ける定
着用プレート34が、コ字状に配置された3枚の支持プ
レート36、38、40を介して矩形枠26に固定支持
されてなっている。
In each fixing structure 18, a fixing plate 34 for receiving the fixing tool 16 is fixedly supported by the rectangular frame 26 via three support plates 36, 38, and 40 arranged in a U-shape. I have.

【0036】定着用プレート34は、支持プレート36
における矩形枠26の中心寄りの表面中央部に溶接され
ている。この支持プレート36は、長尺壁面板28の上
端面28aおよび下端面28bの傾斜角と直交する傾斜
平面に沿って配置されており、その両側端面が両側の長
尺壁面板28に溶接されている。上下1対のプレート3
8、40は、長尺壁面板28の上端面28aおよび下端
面28bと略平行に配置されており、矩形枠26の中心
寄りの端面が支持プレート36に溶接されるとともに、
その両側端面が両側の長尺壁面板28に溶接されてい
る。定着用プレート34および支持プレート36には、
定着具固定孔34a、36aが形成されている。
The fixing plate 34 includes a support plate 36
Is welded to the center of the surface near the center of the rectangular frame 26. The support plate 36 is disposed along an inclined plane orthogonal to the inclination angles of the upper end surface 28a and the lower end surface 28b of the long wall plate 28, and both end surfaces are welded to the long wall plates 28 on both sides. I have. Upper and lower pair of plates 3
8, 40 are arranged substantially parallel to the upper end surface 28a and the lower end surface 28b of the long wall plate 28, and the end surface near the center of the rectangular frame 26 is welded to the support plate 36,
Both end surfaces are welded to the long wall plates 28 on both sides. The fixing plate 34 and the support plate 36 include
The fixing tool fixing holes 34a and 36a are formed.

【0037】図5に示すように、各鋼殻ユニット24に
おける長尺壁面板28の上端面28aおよび下端面28
bの橋軸方向両端部の下方傾斜角は、該鋼殻ユニット2
4に定着される斜材14の張設角度と同じ角度に設定さ
れている。このため、下段に位置する鋼殻ユニット24
ほど下方傾斜角が大きい値に設定されている。
As shown in FIG. 5, the upper end surface 28a and the lower end surface 28 of the long wall plate 28 in each steel shell unit 24 are formed.
The downward inclination angle of both ends in the bridge axis direction of the steel shell unit 2
The angle is set to be the same as the stretching angle of the diagonal member 14 fixed to the sheet 4. For this reason, the steel shell unit 24 located at the lower stage
The lower the inclination angle is, the larger the value is set.

【0038】これら各鋼殻ユニット24における長尺壁
面板28の上下両端面28a、28bおよび各短尺壁面
板30の上下両端面30a、30bは高精度に仕上げら
れており、これにより各鋼殻ユニット24相互間の積層
面20aはメタルタッチ(高精度な面接触状態)となっ
ている。
The upper and lower end surfaces 28a, 28b of the long wall plate 28 and the upper and lower end surfaces 30a, 30b of each short wall plate 30 in each of the steel shell units 24 are finished with high precision. The laminated surfaces 20a between the 24 are metal touch (high-precision surface contact state).

【0039】なお、最上段に位置する鋼殻ユニット24
における長尺壁面板28および各短尺壁面板30の上端
面28a、30a、ならびに最下段に位置する鋼殻ユニ
ット24における長尺壁面板28および各短尺壁面板3
0の下端面28b、30bは、水平面に沿って形成され
ている。そして、最下段に位置する鋼殻ユニット24の
下端面28bには、ベースプレート42が溶接固定され
ている。
The steel shell unit 24 located at the uppermost stage
, The upper end surfaces 28a and 30a of the short wall plates 30 and the long wall plate 28 and the short wall plates 3 of the steel shell unit 24 located at the lowermost stage.
The lower end surfaces 28b and 30b of 0 are formed along a horizontal plane. The base plate 42 is fixed by welding to the lower end surface 28b of the steel shell unit 24 located at the lowermost stage.

【0040】次に、本実施形態の主塔構築工程(より具
体的には、主塔12における主塔側斜材定着部12Aの
構築工程)について説明する。
Next, the main tower building process (more specifically, the main tower side diagonal material fixing section 12A in the main tower 12) of the present embodiment will be described.

【0041】まず、各鋼殻ユニット24を予め工場等で
製作しておく。その際、各鋼殻ユニット24の長尺壁面
板28および各短尺壁面板30の上下両端面28a、2
8bおよび30a、30bに表面加工を施して、その面
精度を十分に高めておく。
First, each steel shell unit 24 is manufactured in advance at a factory or the like. At this time, the upper and lower end surfaces 28a, 2a, 2b of the long wall plate 28 and the short wall plate 30 of each steel shell unit 24 are formed.
8b and 30a, 30b are subjected to surface processing to sufficiently enhance the surface accuracy.

【0042】次に、斜張橋10の主塔構築部分に10個
の鋼殻ユニット24を図7に示すように順次積み重ねて
鋼殻部20を設置した後、この鋼殻部20に対して、図
8および9に示すように、その橋軸方向中央部分および
橋軸直交方向中央部分を各々帯状に残すようにしてコン
クリートを巻き立て、先打ちコンクリート部22Aを形
成する。
Next, ten steel shell units 24 are sequentially stacked on the main tower building portion of the cable stayed bridge 10 as shown in FIG. As shown in FIGS. 8 and 9, concrete is rolled up so as to leave a central portion in the bridge axis direction and a central portion in the bridge axis orthogonal direction, respectively, to form a precast concrete portion 22A.

【0043】その後、各鋼殻ユニット24の各定着構造
18に定着具16を介して斜材14を定着した後、これ
ら各斜材14に張力T(図中矢印で示す)を導入する。
After that, the oblique members 14 are fixed to the fixing structures 18 of the respective steel shell units 24 via the fixing tools 16, and a tension T (indicated by an arrow in the drawing) is introduced to each of the oblique members 14.

【0044】そして最後に、鋼殻部20の橋軸方向中央
部分にコンクリートを打設し、図8および9に示すよう
な後打ちコンクリート部22Bを形成する。
Finally, concrete is poured into the central portion of the steel shell portion 20 in the bridge axis direction to form a post-cast concrete portion 22B as shown in FIGS.

【0045】この主塔構築工程において、鋼殻部20の
橋軸方向中央部分には先打ちコンクリート部22Aが形
成されないので、斜材張力Tの水平成分(引張力)は鋼
殻部20のみで受け持つこととなり、一方、斜材張力T
の鉛直成分(圧縮力)は鋼殻部20と先打ちコンクリー
ト部22Aとの合成断面で受け持つこととなる。
In the main tower building process, since the precast concrete portion 22A is not formed at the central portion of the steel shell portion 20 in the bridge axis direction, the horizontal component (tensile force) of the diagonal material tension T is only the steel shell portion 20. On the other hand, on the other hand, the diagonal material tension T
The vertical component (compression force) of the steel shell portion 20 and the pre-cast concrete portion 22A is covered by the composite section.

【0046】このため、従来のように斜材張力Tを鋼殻
部20ですべて受け持つ構造に比して、鋼殻部20の負
荷を軽減することができる。そして、その分だけ鋼殻部
20を軽量化することができ、これにより架橋機材のコ
スト低減を図ることができる。また、このように鋼殻部
20の軽量化を図ることができることから、架設・運搬
に重量制限のあるような場所での施工も行いやすくな
る。
Therefore, the load on the steel shell portion 20 can be reduced as compared with the conventional structure in which the steel shell portion 20 entirely receives the diagonal material tension T. In addition, the weight of the steel shell portion 20 can be reduced by that much, so that the cost of the cross-linking equipment can be reduced. Further, since the weight of the steel shell portion 20 can be reduced in this manner, it is easy to perform construction in a place where there is a weight limit in erection and transportation.

【0047】さらに、圧縮力として作用する斜材張力T
の鉛直成分を、鋼殻部20と先打ちコンクリート部22
Aとの合成断面で受け持つことにより、鋼殻部20下端
に位置するコンクリート部分に応力集中が発生してしま
うのを未然に防止することができる。
Further, the diagonal material tension T acting as a compressive force
Of the vertical component of the steel shell portion 20 and the pre-cast concrete portion 22
By taking charge of the composite cross section with A, it is possible to prevent stress concentration from occurring at the concrete portion located at the lower end of the steel shell portion 20 beforehand.

【0048】また上記主塔構築工程において、斜材張力
Tの導入により各鋼殻ユニット24には橋軸方向に多少
の伸びが生じるが、この伸びが生じた後に後打ちコンク
リート部22Bが形成されるので、コンクリート部22
には引張荷重が作用しないようにすることができる。
In the main tower building process, each steel shell unit 24 undergoes some elongation in the bridge axis direction due to the introduction of the diagonal material tension T. After this elongation, the post-cast concrete portion 22B is formed. So the concrete part 22
Can be prevented from being subjected to a tensile load.

【0049】このように本実施形態に係る斜張橋の主塔
構築方法を採用することにより、主塔12の鋼殻部20
を軽量化することができるとともに、そのコンクリート
部22における鋼殻部20の下端部分に応力集中が発生
するのを防止することができ、かつ主塔構築の際の施工
性向上を図ることができる。
As described above, by adopting the method for constructing the main tower of the cable-stayed bridge according to the present embodiment, the steel shell 20
Can be reduced in weight, stress concentration can be prevented from occurring at the lower end portion of the steel shell portion 20 in the concrete portion 22, and workability at the time of main tower construction can be improved. .

【0050】特に本実施形態においては、鋼殻部20の
設置を、各対の定着構造18毎に分割形成された複数の
鋼殻ユニット24を積み重ねることにより行う構成とな
っているので、架設・運搬を重量が十分に小さい鋼殻ユ
ニット24の単位(5tf程度以下の単位)で行うこと
ができ、これにより架設・運搬に重量制限のあるような
場所での施工を極めて容易に行うことができる。
In particular, in the present embodiment, the steel shell portion 20 is installed by stacking a plurality of steel shell units 24 formed separately for each pair of fixing structures 18. Carrying can be carried out in units of the steel shell unit 24 having a sufficiently small weight (a unit of about 5 tf or less), which makes it possible to extremely easily perform construction in places where there is a weight limit in erection and carrying. .

【0051】さらに本実施形態においては、各鋼殻ユニ
ット24の積み重ねを、橋軸方向および橋軸直交方向い
ずれの方向に関しても山切りカット面に設定された積層
面20aを介して行う構成となっているので、積み上げ
時の施工誤差を最小限に抑えることができ、これにより
施工性を一層向上させることができる。
Further, in this embodiment, the stacking of the steel shell units 24 is performed via the laminating surface 20a set as the cut-away surface in both the bridge axis direction and the bridge axis orthogonal direction. Therefore, the construction error at the time of stacking can be minimized, and thereby the workability can be further improved.

【0052】しかも本実施形態においては、積層面20
aを構成する各鋼殻ユニット24の上端面28a、30
aおよび下端面28b、30bの面精度を、予め工場等
での表面加工により十分に高めておき、各鋼殻ユニット
24をメタルタッチで積み重ねるようになっているの
で、現場での各鋼殻ユニット24相互間の溶接作業を不
要とすることができ、これにより大幅な施工性向上を図
ることができる。
Moreover, in the present embodiment, the lamination surface 20
a of upper end surfaces 28a, 30 of each of the steel shell units 24 constituting
a and the lower end surfaces 28b and 30b are sufficiently improved in advance by surface processing in a factory or the like, and the steel shell units 24 are stacked by metal touch. It is possible to eliminate the necessity of welding work between the 24 pieces, thereby greatly improving workability.

【0053】また本実施形態においては、各鋼殻ユニッ
ト24として、その外周面に複数のスタッドジベル32
が設けられたものを用いるようになっているので、鋼殻
部20に圧縮力として作用する斜材張力Tの鉛直成分
を、各鋼殻ユニット24のスタッドジベル32を介して
先打ちコンクリート部22Aへ効率よく伝達することが
できるので、鋼殻部20と先打ちコンクリート部22A
との合成断面での圧縮力負担を一層効果的に行うことが
できる。
In this embodiment, each of the steel shell units 24 has a plurality of stud dowels 32 on its outer peripheral surface.
The vertical component of the diagonal material tension T acting as a compressive force on the steel shell portion 20 is applied to the precast concrete portion 22A via the stud dowel 32 of each steel shell unit 24. Can be efficiently transmitted to the steel shell 20 and the precast concrete 22A.
And the compression force load on the combined cross section can be more effectively performed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本願発明の一実施形態に係る主塔構築方法の対
象となる斜張橋の要部を、橋軸直交方向から見て示す側
面図
FIG. 1 is a side view showing a main part of a cable-stayed bridge to be subjected to a method for constructing a main tower according to an embodiment of the present invention, as viewed from a direction orthogonal to a bridge axis.

【図2】図1のII-II 線矢視図FIG. 2 is a view taken along the line II-II in FIG.

【図3】図1のIII 部詳細図FIG. 3 is a detailed view of a part III in FIG. 1;

【図4】図3のIV-IV 線断面詳細図FIG. 4 is a detailed sectional view taken along line IV-IV of FIG. 3;

【図5】上記斜張橋における主塔の鋼殻部を示す側面図FIG. 5 is a side view showing a steel shell of a main tower in the cable stayed bridge.

【図6】上記鋼殻部を構成する10個の鋼殻ユニットの
うち、上から2段目の鋼殻ユニットを例にとって単品で
示す側面図
FIG. 6 is a side view showing, as an example, a steel shell unit in the second stage from the top of the ten steel shell units constituting the steel shell part.

【図7】上記各鋼殻ユニットを積み重ねる工程を示す斜
視図
FIG. 7 is a perspective view showing a step of stacking the above-mentioned steel shell units.

【図8】上記主塔構築方法における斜材張力導入の様子
を示す、図3と同様の図
FIG. 8 is a view similar to FIG. 3, showing a state of introduction of diagonal material tension in the main tower building method.

【図9】上記斜材張力導入の様子を示す、図4と同様の
FIG. 9 is a view similar to FIG. 4, showing how the diagonal member tension is introduced;

【符号の説明】[Explanation of symbols]

10 斜張橋(エクストラドーズド橋) 12 主塔 12A 主塔側斜材定着部 14 斜材 16 定着具 18 定着構造 20 鋼殻部 20a 積層面 22 コンクリート部 22A 先打ちコンクリート部 22B 後打ちコンクリート部 24 鋼殻ユニット 26 矩形枠 28 長尺壁面板 30 短尺壁面板 28a、30a 上端面 28b、30b 下端面 30c 斜材挿通孔 32 スタッドジベル 34 定着用プレート 34a、36a 定着具固定孔 36、38、40 支持プレート 42 ベースプレート 50 主桁 T 斜材張力 DESCRIPTION OF SYMBOLS 10 Cable stayed bridge (extra-dosed bridge) 12 Main tower 12A Main tower side diagonal material anchoring part 14 Diagonal material 16 Anchor 18 Anchor structure 20 Steel shell part 20a Stacking surface 22 Concrete part 22A Precast concrete part 22B Post-cast concrete part 24 Steel shell unit 26 Rectangular frame 28 Long wall plate 30 Short wall plate 28a, 30a Upper end surface 28b, 30b Lower end surface 30c Diagonal material insertion hole 32 Stud dowel 34 Fixing plate 34a, 36a Fixing device fixing hole 36, 38, 40 Support plate 42 Base plate 50 Main girder T Diagonal material tension

フロントページの続き (72)発明者 春日 昭夫 東京都新宿区荒木町13番地の4 住友建設 株式会社内 (72)発明者 水野 克彦 東京都新宿区荒木町13番地の4 住友建設 株式会社内 (72)発明者 桑野 昌晴 東京都新宿区荒木町13番地の4 住友建設 株式会社内 Fターム(参考) 2D059 AA27 AA41 BB08 CC25 DD28 GG55 GG61 Continuing from the front page (72) Inventor Akio Kasuga 13-4 Arakicho, Shinjuku-ku, Tokyo Sumitomo Construction Co., Ltd. (72) Inventor Katsuhiko Mizuno 13-13 Arakicho, Shinjuku-ku, Tokyo Sumitomo Construction Co., Ltd. (72 ) Inventor Masaharu Kuwano 13-4 Arakicho, Shinjuku-ku, Tokyo Sumitomo Construction F-term (reference) 2D059 AA27 AA41 BB08 CC25 DD28 GG55 GG61

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 主塔の橋軸方向両側に複数対の斜材が上
下複数段にわたって張設されてなる斜張橋の主塔構築方
法であって、 上記斜張橋の主塔構築部分に、上記複数対の斜材を定着
するための複数対の定着構造を有する鋼殻部を設置した
後、 この鋼殻部に対して、該鋼殻部の橋軸方向中央部分を残
すようにしてコンクリートを巻き立て、 その後、上記各定着構造に定着された上記各斜材に張力
を導入し、 最後に、上記鋼殻部の橋軸方向中央部分にコンクリート
を打設する、ことを特徴とする斜張橋の主塔構築方法。
1. A method for constructing a main tower of a cable-stayed bridge, comprising a plurality of pairs of diagonal members stretched over a plurality of upper and lower stages on both sides in the bridge axis direction of the main tower. After installing a steel shell portion having a plurality of pairs of anchoring structures for anchoring the plurality of pairs of diagonal members, the central portion of the steel shell portion in the bridge axis direction is left for the steel shell portion. Laying concrete, thereafter, introducing tension to each of the diagonal members fixed to each of the fixing structures, and finally pouring concrete to a central portion of the steel shell in the bridge axis direction. How to build the main tower of a cable-stayed bridge.
【請求項2】 上記鋼殻部の設置を、上記各対の定着構
造毎に分割形成された複数の鋼殻ユニットを積み重ねる
ことにより行う、ことを特徴とする請求項2記載の斜張
橋の主塔構築方法。
2. The cable-stayed bridge according to claim 2, wherein the installation of the steel shell portion is performed by stacking a plurality of steel shell units formed separately for each pair of the fixing structures. Main tower construction method.
【請求項3】 上記各鋼殻ユニットの積み重ねを、橋軸
方向および橋軸直交方向いずれの方向に関しても山切り
カット面に設定された積層面を介して行う、ことを特徴
とする請求項2記載の斜張橋の主塔構築方法。
3. The stacking of each of the steel shell units is performed via a lamination surface set as a mountain-cutting surface in both the bridge axis direction and the bridge axis orthogonal direction. The main tower construction method of the cable stayed bridge described.
【請求項4】 上記各鋼殻ユニットとして、該鋼殻ユニ
ットの外周面に複数のスタッドジベルが設けられたもの
を用いる、ことを特徴とする請求項2または3記載の斜
張橋の主塔構築方法。
4. The main tower of a cable-stayed bridge according to claim 2, wherein each of the steel shell units has a plurality of stud dowels provided on an outer peripheral surface of the steel shell unit. How to build.
JP2001158075A 2001-05-28 2001-05-28 Building a main tower of cable-stayed bridge Expired - Lifetime JP4387071B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001158075A JP4387071B2 (en) 2001-05-28 2001-05-28 Building a main tower of cable-stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001158075A JP4387071B2 (en) 2001-05-28 2001-05-28 Building a main tower of cable-stayed bridge

Publications (2)

Publication Number Publication Date
JP2002348813A true JP2002348813A (en) 2002-12-04
JP4387071B2 JP4387071B2 (en) 2009-12-16

Family

ID=19001848

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001158075A Expired - Lifetime JP4387071B2 (en) 2001-05-28 2001-05-28 Building a main tower of cable-stayed bridge

Country Status (1)

Country Link
JP (1) JP4387071B2 (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100614455B1 (en) 2004-08-30 2006-08-21 주식회사 진화기술공사 Extradosed Bridge and it's construction method
KR100779766B1 (en) 2006-07-11 2007-11-27 삼성물산 주식회사 Construction method for tower of bridge
KR100988670B1 (en) 2008-05-28 2010-10-18 주식회사 휴먼브릿지 The sidewalk suspension bridge in which separation constructing main cable at side-to-side of main tower
JP2014047489A (en) * 2012-08-30 2014-03-17 Sumitomo Mitsui Construction Co Ltd Anchorage structure of oblique cable
CN104727222A (en) * 2015-04-07 2015-06-24 林同棪国际工程咨询(中国)有限公司 Separated steel and concrete combined cable tower anchorage zone structure
CN105369736A (en) * 2015-12-15 2016-03-02 安徽省交通控股集团有限公司 Outer anchoring structure of cable-stayed bridge tower body
JP2016089579A (en) * 2014-11-11 2016-05-23 三井住友建設株式会社 Structure for fixing diagonal cables
JP2016204996A (en) * 2015-04-23 2016-12-08 三井住友建設株式会社 Fixation structure of oblique cable
CN108103949A (en) * 2017-12-29 2018-06-01 南通华凯重工有限公司 A kind of Cable stayed Bridge Main Tower composite steel anchor beam integral assembling process
CN108374323A (en) * 2018-04-04 2018-08-07 中铁第四勘察设计院集团有限公司 It is a kind of to be used to encircle the Sarasota boundling anchor structure for holding cable-stayed bridge
CN109267489A (en) * 2018-10-17 2019-01-25 中铁大桥局集团有限公司 A kind of Anchorage Zone of Cable-stayed Bridge Pylon construction method
CN109702387A (en) * 2018-09-28 2019-05-03 江苏中铁山桥重工有限公司 A kind of stayed bridge pylon cable inner lining steel construction manufacturing method
CN110184898A (en) * 2019-06-14 2019-08-30 中铁大桥局集团有限公司 The steel skeleton segment of Cable stayed Bridge Main Tower anchorage zone and king-post construction method
CN111005302A (en) * 2019-12-30 2020-04-14 中交路桥华南工程有限公司 Steel anchor beam mounting method
CN111119056A (en) * 2019-09-12 2020-05-08 中电建路桥集团有限公司 Construction method for steel-concrete combined section of inclined tower tip
CN113215985A (en) * 2021-05-28 2021-08-06 中铁二十局集团第三工程有限公司 Suspension bridge cable tower column anchor box mounting structure and method
CN113445433A (en) * 2021-08-13 2021-09-28 北京城建集团有限责任公司 Bridge tower construction method
CN113737661A (en) * 2021-10-11 2021-12-03 中铁二局集团有限公司 Construction method for steel-concrete combined section of tower base of cable-stayed bridge
CN114684624A (en) * 2022-03-29 2022-07-01 山东电力工程咨询院有限公司 Few-column sectional chimney-penetrating coal conveying trestle system and method

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100614455B1 (en) 2004-08-30 2006-08-21 주식회사 진화기술공사 Extradosed Bridge and it's construction method
KR100779766B1 (en) 2006-07-11 2007-11-27 삼성물산 주식회사 Construction method for tower of bridge
KR100988670B1 (en) 2008-05-28 2010-10-18 주식회사 휴먼브릿지 The sidewalk suspension bridge in which separation constructing main cable at side-to-side of main tower
JP2014047489A (en) * 2012-08-30 2014-03-17 Sumitomo Mitsui Construction Co Ltd Anchorage structure of oblique cable
JP2016089579A (en) * 2014-11-11 2016-05-23 三井住友建設株式会社 Structure for fixing diagonal cables
CN104727222B (en) * 2015-04-07 2017-01-18 林同棪国际工程咨询(中国)有限公司 Separated steel and concrete combined cable tower anchorage zone structure
CN104727222A (en) * 2015-04-07 2015-06-24 林同棪国际工程咨询(中国)有限公司 Separated steel and concrete combined cable tower anchorage zone structure
JP2016204996A (en) * 2015-04-23 2016-12-08 三井住友建設株式会社 Fixation structure of oblique cable
CN105369736A (en) * 2015-12-15 2016-03-02 安徽省交通控股集团有限公司 Outer anchoring structure of cable-stayed bridge tower body
CN105369736B (en) * 2015-12-15 2017-05-10 安徽省交通控股集团有限公司 Outer anchoring structure of cable-stayed bridge tower body
CN108103949A (en) * 2017-12-29 2018-06-01 南通华凯重工有限公司 A kind of Cable stayed Bridge Main Tower composite steel anchor beam integral assembling process
CN108374323A (en) * 2018-04-04 2018-08-07 中铁第四勘察设计院集团有限公司 It is a kind of to be used to encircle the Sarasota boundling anchor structure for holding cable-stayed bridge
CN108374323B (en) * 2018-04-04 2023-09-12 中铁第四勘察设计院集团有限公司 Cable tower bundling anchoring structure for arch-supporting cable-stayed bridge
CN109702387B (en) * 2018-09-28 2020-11-20 江苏中铁山桥重工有限公司 Method for manufacturing steel structure of tower column lining of cable-stayed bridge
CN109702387A (en) * 2018-09-28 2019-05-03 江苏中铁山桥重工有限公司 A kind of stayed bridge pylon cable inner lining steel construction manufacturing method
CN109267489A (en) * 2018-10-17 2019-01-25 中铁大桥局集团有限公司 A kind of Anchorage Zone of Cable-stayed Bridge Pylon construction method
CN110184898A (en) * 2019-06-14 2019-08-30 中铁大桥局集团有限公司 The steel skeleton segment of Cable stayed Bridge Main Tower anchorage zone and king-post construction method
CN111119056A (en) * 2019-09-12 2020-05-08 中电建路桥集团有限公司 Construction method for steel-concrete combined section of inclined tower tip
CN111005302A (en) * 2019-12-30 2020-04-14 中交路桥华南工程有限公司 Steel anchor beam mounting method
CN111005302B (en) * 2019-12-30 2021-07-30 中交路桥华南工程有限公司 Steel anchor beam mounting method
CN113215985A (en) * 2021-05-28 2021-08-06 中铁二十局集团第三工程有限公司 Suspension bridge cable tower column anchor box mounting structure and method
CN113445433A (en) * 2021-08-13 2021-09-28 北京城建集团有限责任公司 Bridge tower construction method
CN113737661A (en) * 2021-10-11 2021-12-03 中铁二局集团有限公司 Construction method for steel-concrete combined section of tower base of cable-stayed bridge
CN114684624A (en) * 2022-03-29 2022-07-01 山东电力工程咨询院有限公司 Few-column sectional chimney-penetrating coal conveying trestle system and method
CN114684624B (en) * 2022-03-29 2024-01-19 山东电力工程咨询院有限公司 Few-column sectional type chimney-penetrating coal conveying stack bridge system and method

Also Published As

Publication number Publication date
JP4387071B2 (en) 2009-12-16

Similar Documents

Publication Publication Date Title
JP2002348813A (en) Method for constructing main tower of diagonal tensioning bridge
US20120023858A1 (en) Truss-type shear reinforcement material having double anchorage functions at both top and bottom thereof
US8763333B1 (en) Method of making a dual panel composite truss
JP2005180162A (en) Connecting structure and connecting method of i-type prestressed concrete beam with steel bracket
WO2010051379A1 (en) Construction frame shear lug
JP6749673B1 (en) Joint structure of concrete columns and steel beams
TWI759947B (en) Method of introducing prestress to beam-column joint of pc structure in triaxial compression
JP2011196089A (en) Hybrid cogging and column-beam joint structure using the same
JP2004176482A (en) Construction method for non-buried column leg and structure of non-buried column leg
CN113356428B (en) Prestress superposed integral floor system applied to fabricated building and construction method
CN110725399A (en) Implementation method of longitudinal and transverse beam connecting node of fabricated building
JP4024449B2 (en) Seismic isolation method for existing buildings
JP2968952B2 (en) Column and beam joint structure and joining method
JP2000336769A (en) Truss structural body and construction method therefor
JP2002227425A (en) Temporary structure for setting base isolation device to existing building, and method for setting the same
JPH05195539A (en) Steel-framed column base
JP3028993B2 (en) Flat slab construction method
JP2005042491A (en) Prestressed concrete structure
JPH08226131A (en) Anchor bolt erection structure
JPH08284249A (en) Building frame structure
JP3146184B2 (en) Precast foundation beam joining method
JP2002339494A (en) Large-span floor slab
KR20240016761A (en) Reinforcement structure of section vulnerable to shear load of slab of piloti building and building equipped with it
JPH04222741A (en) Half precast concrete beam
JP2006118226A (en) Construction method of floor board with precast concrete slab

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071115

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090709

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090804

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090827

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090929

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090930

R150 Certificate of patent or registration of utility model

Ref document number: 4387071

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121009

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121009

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151009

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term