JP2002227413A - Method and device for managing work progress of structure and recording medium used for these method and device - Google Patents

Method and device for managing work progress of structure and recording medium used for these method and device

Info

Publication number
JP2002227413A
JP2002227413A JP2001023156A JP2001023156A JP2002227413A JP 2002227413 A JP2002227413 A JP 2002227413A JP 2001023156 A JP2001023156 A JP 2001023156A JP 2001023156 A JP2001023156 A JP 2001023156A JP 2002227413 A JP2002227413 A JP 2002227413A
Authority
JP
Japan
Prior art keywords
data
management
creating
schedule
processing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001023156A
Other languages
Japanese (ja)
Inventor
Harusada Azuma
晴貞 東
Seiichiro Yamagiri
清一郎 山切
Shigemi Harada
成美 原田
Koichiro Wakayama
紘一郎 若山
Koji Moriya
弘司 守屋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
JFE Systems Inc
Original Assignee
Kawasaki Steel Systems R&D Corp
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Systems R&D Corp, Kawasaki Steel Corp filed Critical Kawasaki Steel Systems R&D Corp
Priority to JP2001023156A priority Critical patent/JP2002227413A/en
Publication of JP2002227413A publication Critical patent/JP2002227413A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Information Retrieval, Db Structures And Fs Structures Therefor (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To easily and accurately manage a work progress at a time when a structure such as a bridge is manufactured. SOLUTION: Process order and linkages among processes are registered while referring to a part table in which required information required for preparing a minimum unit member constituting at least the bridge and a combination member in which the minimum unit member is combined, a production management database, in which the quantity of treatment working from a treatment process is registered regarding each minimum unit member and combination member on the basis of the part table and which has at least a task table as the unit of a work indication, and the task table for the production management database, process plan data are prepared automatically on the basis of the process order and the linkages among the processes and manday data and part data, and work-progress management plan data are transmitted to a process scheduler and a process schedule is prepared. The prepared process schedule is adjusted on the basis of result data displaying a progress state, and a process plan reflecting result data is conducted.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、橋梁、建築物、人
口地盤、護岸設備等の大型構造物を製作する際に設計情
報が作成される前後で工程計画を行う構造物の工程管理
方法、工程管理装置及びこれらに使用する記憶媒体に関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a process management method for a structure, which performs a process plan before and after design information is created when manufacturing a large structure such as a bridge, a building, an artificial ground, a seawall, etc. The present invention relates to a process management device and a storage medium used for the same.

【0002】[0002]

【従来の技術】依頼主から構造物例えば橋梁の引き合い
があったときに、橋梁を受注するか否かを判断するため
に、引き合いのあった橋梁についての工程計画を作成す
る必要があると共に、実際に橋梁を受注して、生産開始
する際にも設計データに基づく工程計画を作成する必要
がある。このように工程計画を作成する際に、従来は、
ガントチャート等を作成する市販のアプリケーションソ
フトで構成された工程スケジューラを適用することによ
り、工程計画の作成を行うようにしている。
2. Description of the Related Art When there is an inquiry from a client for a structure such as a bridge, it is necessary to prepare a process plan for the inquired bridge in order to determine whether or not to accept an order for the bridge. When actually receiving an order for a bridge and starting production, it is necessary to create a process plan based on the design data. Conventionally, when creating a process plan like this,
A process plan is created by applying a process scheduler composed of commercially available application software for creating a Gantt chart or the like.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上記従
来例にあっては、工程スケジューラを適用することによ
り、工程計画を作成することができるが、この工程スケ
ジューラで工程計画を作成するために、橋梁を構成する
最小基本単位部材及びこれを組み合わせた組合せ部材の
数量、処理工程、工程順、工程間繋がり等を表す工程計
画データを入力する必要があり、橋梁のように、多数の
部材で構成されている場合には、その入力に多くの人手
と作業時間を要し、工程計画の作成を容易に行うことが
できないという未解決の課題がある。
However, in the above-mentioned conventional example, a process plan can be created by applying a process scheduler. However, in order to create a process plan with this process scheduler, a bridge is required. It is necessary to input the process plan data representing the number of the minimum basic unit members and the combined members that combine them, the process steps, the order of the processes, the connection between the processes, etc., and it is composed of many members like a bridge. In such a case, there is an unsolved problem that the input requires a lot of manpower and work time, and it is not easy to create a process plan.

【0004】そこで、本発明は、上記従来例の未解決の
課題に着目してなされたものであり、工程スケジューラ
で必要とする工程計画データの作成を容易に且つ自動的
に行うことができる橋梁生産における工程管理方法、工
程管理装置及びこれらに使用する記憶媒体を提供するこ
とを目的としている。
Accordingly, the present invention has been made in view of the above-mentioned unsolved problems of the prior art, and is a bridge capable of easily and automatically creating process plan data required by a process scheduler. It is an object of the present invention to provide a process management method and a process management device in production and a storage medium used for the same.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するため
に、請求項1に係る構造物の工程管理方法は、橋梁等の
構造物を製作する際の工程管理スケジュールを作成する
工程管理手段を使用した構造物の工程管理方法におい
て、少なくとも前記構造物を構成する最小単位部材及び
当該最小単位部材を組み合わせた組合せ部材の作成に必
要とする部材データ及び処理工程データを生産管理デー
タベースに登録するステップと、前記生産管理データベ
ースに登録された前記部材データ及び処理工程データに
基づいて工程順及び工程間つながりを設定して工程計画
データを作成し、これを前記工程管理手段に送出するス
テップとを備えていることを特徴としている。
According to a first aspect of the present invention, there is provided a process management method for a structure, comprising: a process management unit for creating a process management schedule for manufacturing a structure such as a bridge; In the process control method for a used structure, a step of registering at least a minimum unit member constituting the structure and member data and processing process data necessary for creating a combined member combining the minimum unit members in a production management database. And setting a process order and a connection between processes based on the member data and the process process data registered in the production management database to create process plan data, and sending the process plan data to the process management means. It is characterized by having.

【0006】この請求項1に係る発明では、橋梁等の構
造物を構成する最小単位部材及びこの最小単位部材を組
み合わせた組合せ部材の作成に必要とする部材データ及
び処理工程データを生産管理データベースに登録するこ
とにより、この生産管理データベースを参照して部材デ
ータと処理工程データとから工程順及び工程間つながり
を設定して工程計画データを作成し、これを工程管理手
段に送出することにより、工程管理に必要なガントチャ
ート等の工程管理スケジュールを作成する。
According to the first aspect of the present invention, member data and processing process data required for creating a minimum unit member constituting a structure such as a bridge and a combination member combining the minimum unit members are stored in a production management database. By registering, by referring to the production management database, the process order and the connection between processes are set from the member data and the process process data to create process plan data, and the process plan data is sent to the process management means. Create a process management schedule such as a Gantt chart required for management.

【0007】また、請求項2に係る構造物の工程管理方
法は、橋梁等の構造物を製作する際の工程管理スケジュ
ールを作成する工程管理手段を使用した構造物の工程管
理方法において、少なくとも前記構造物を構成する最小
単位部材及び当該最小単位部材を組み合わせた組合せ部
材の作成に必要とする部材データ及び処理工程データを
生産管理データベースに登録するステップと、前記生産
管理データベースに登録された前記部材データ及び処理
工程データに基づいて工程順及び工程間つながりを設定
して工程計画データを作成し、これを前記工程管理手段
に送出するステップと、前記工程管理手段で作成された
工程管理スケジュールと実際の進捗状況とに基づいて当
該工程管理スケジュールを調整するステップとを備えて
いることを特徴としている。
According to a second aspect of the present invention, there is provided a process control method for a structure using a process control means for creating a process control schedule for manufacturing a structure such as a bridge. Registering, in a production management database, member data and processing process data necessary for creating a minimum unit member constituting the structure and a combined member combining the minimum unit members, and the member registered in the production management database Setting the process order and the connection between processes based on the data and the process process data to create process plan data and sending the process plan data to the process management means; Adjusting the process management schedule based on the progress of the process. To have.

【0008】この請求項2に係る発明では、請求項1に
係る発明の作用に加えて、工程管理手段で工程管理を行
っているときに、工程管理スケジュールと実際の進捗状
況とに基づいて工程管理スケジュールを調整することに
より、進捗状況に応じた最適な工程管理スケジュールを
作成することができる。さらに、請求項3に係る構造物
の工程管理装置は、橋梁等の構造物を製作する際の工程
管理スケジュールを作成する工程管理手段を備えた構造
物の工程管理装置において、前記構造物を構成する最小
単位部材及び当該最小単位部材を組み合わせた組合せ部
材の作成に必要とする必要情報を登録した部品テーブル
と、該部品テーブルに基づいて個々の最小単位部材及び
組合せ部材について処理工程からみた処理加工量を登録
し、作業指示の単位となるタスクテーブルとを少なくと
も備えた生産管理データベースと、該生産管理データベ
ースのタスクテーブルを参照して工程順及び工程間つな
がりを登録して工程計画データを作成し、当該工程管理
計画データを前記工程管理手段に送出する工程計画デー
タ作成手段とを少なくとも備えていることを特徴として
いる。
According to the second aspect of the present invention, in addition to the operation of the first aspect of the invention, when the process management is performed by the process management means, the process is performed based on the process management schedule and the actual progress. By adjusting the management schedule, an optimal process management schedule according to the progress can be created. Furthermore, the structure process management device according to claim 3 is a structure process management device provided with a process management unit that creates a process management schedule for manufacturing a structure such as a bridge. Table that registers the minimum unit members to be created and necessary information required to create a combined member combining the minimum unit members, and processing based on the component table for each of the minimum unit members and the combined members as viewed from the processing step. A production management database having at least a task table serving as a unit of a work instruction, and registering a process order and a connection between processes with reference to the task table of the production management database to create process plan data. At least a process plan data creating means for sending the process management plan data to the process management means. It is characterized.

【0009】この請求項3に係る発明では、請求項1に
係る発明と同様に、工程計画作成手段で、生産管理デー
タベースにおける部品テーブルに登録された各部材につ
いての処理工程で処理する分をまとめた単位で作成され
るタスクテーブルを参照して、工程順及び工程間つなが
りを登録することにより、自動的に工程計画データを作
成し、これを例えば工程スケジューラで構成される工程
管理手段に送出して、工程管理スケジュールを作成す
る。
According to the third aspect of the present invention, similarly to the first aspect of the invention, the process plan creating means collects the amount of processing for each member registered in the parts table in the production management database. By referring to a task table created in units of steps, and registering the process order and the connection between processes, process plan data is automatically created and sent to a process management means composed of, for example, a process scheduler. To create a process management schedule.

【0010】さらにまた、請求項4に係る構造物の工程
管理装置は、橋梁等の構造物を製作する際の工程管理ス
ケジュールを作成する工程管理手段を備えた構造物の工
程管理装置において、前記構造物を構成する最小単位部
材及び当該最小単位部材を組み合わせた組合せ部材の作
成に必要とする必要情報を登録した部品テーブルと、該
部品テーブルに基づいて個々の最小単位部材及び組合せ
部材について処理工程からみた処理加工量を登録し、作
業指示の単位となるタスクテーブルとを少なくとも備え
た生産管理データベースと、該生産管理データベースの
タスクテーブルを参照して工程順及び工程間つながりを
登録して工程計画データを作成し、当該工程管理計画デ
ータを前記工程管理手段に送出する工程計画データ作成
手段と、前記工程管理手段で設定された工程の進捗状態
を検出する進捗状態検出手段と、前記工程管理手段で確
定された工程管理スケジュールと前記進捗状態検出手段
で検出した進捗状態とに基づいて工程管理調整データを
作成し、当該工程計画調整データを前記工程管理手段に
送出する工程計画調整データ作成手段とを少なくとも備
えたことを特徴としている。
Further, the structure process management apparatus according to a fourth aspect of the present invention is the structure process management apparatus comprising a process management means for creating a process management schedule for manufacturing a structure such as a bridge. A parts table in which necessary information necessary for creating a minimum unit member constituting the structure and a combination member combining the minimum unit members is registered, and a processing step is performed for each of the minimum unit member and the combination member based on the part table. A production management database having at least a task table serving as a unit of work instruction, and registering a process order with reference to the task table of the production management database to register a process order and a connection between processes. A process plan data creating unit for creating data and sending the process management plan data to the process management unit; Progress detection means for detecting the progress of the process set by the control means, and process management adjustment data based on the process management schedule determined by the process management means and the progress detected by the progress detection means. And at least a process plan adjustment data creating means for creating and sending the process plan adjustment data to the process management means.

【0011】この請求項4に係る発明では、請求項2に
係る発明と同様に、生産管理データベースのタスクテー
ブルを参照して、工程計画データを作成し、これに基づ
いて工程計画手段で工程管理スケジュールを作成したと
きに、進捗状態検出手段で検出した実際の進捗状態と工
程管理スケジュールとに基づいて工程計画調整データを
作成し、この工程計画調整データを再度工程管理手段に
送出して、工程管理スケジュールを進捗状態に対応させ
て修正する。
In the invention according to the fourth aspect, similarly to the invention according to the second aspect, the process planning data is created by referring to the task table of the production management database, and the process management is performed by the process planning means based on the data. When the schedule is created, process plan adjustment data is created based on the actual progress status detected by the progress status detection means and the process management schedule, and the process plan adjustment data is sent back to the process management means, and the process Modify the management schedule according to the progress status.

【0012】なおさらに、請求項5に係る記憶媒体は、
少なくとも構造物を構成する最小単位部材及び当該最小
単位部材を組み合わせた組合せ部材の作成に必要とする
部材データ及び処理工程データを生産管理データベース
に登録する手順と、前記生産管理データベースに登録さ
れた前記部材データ及び処理工程データに基づいて工程
順及び工程間つながりを設定して工程計画データを作成
し、これを前記工程管理手段に送出する手順とを実行す
るためのプログラムをコンピュータ読み取り可能に記憶
したことを特徴としている。
Still further, a storage medium according to claim 5 is
A procedure for registering at least a minimum unit member constituting the structure and member data and processing step data necessary for creating a combined member combining the minimum unit member in a production management database; and Based on the member data and the process step data, a process order and a connection between processes are set to create process plan data, and a procedure for sending the process plan data to the process management means is stored in a computer-readable manner. It is characterized by:

【0013】また、請求項6に係る記憶媒体は、少なく
とも構造物を構成する最小単位部材及び当該最小単位部
材を組み合わせた組合せ部材の作成に必要とする部材デ
ータ及び処理工程データを生産管理データベースに登録
する手順と、前記生産管理データベースに登録された前
記部材データ及び処理工程データに基づいて工程順及び
工程間つながりを設定して工程計画データを作成し、こ
れを前記工程管理手段に送出する手順と、前記工程管理
手段で作成された工程管理スケジュールと実際の進捗状
況とに基づいて当該工程管理スケジュールを調整する手
順とを実行するためのプログラムをコンピュータ読み取
り可能に記憶したことを特徴としている。
According to a sixth aspect of the present invention, in a production management database, at least a member data and a processing step data necessary for creating at least a minimum unit member constituting a structure and a combination member combining the minimum unit member are stored in a production management database. A procedure for registering, a procedure for setting a process order and a connection between processes based on the member data and the process process data registered in the production management database, creating process plan data, and sending the process plan data to the process management means. And a program for executing a procedure for adjusting the process management schedule based on the process management schedule created by the process management means and the actual progress, and stored in a computer-readable manner.

【0014】これら請求項5又は6に係る発明では、記
憶媒体に工程管理に必要とする所定手順を実行するため
のプログラムがコンピュータ読み取り可能に記憶されて
いるので、携帯が容易であり、この記憶媒体に記憶され
ているプログラムをコンピュータにインストールするか
又はコンピュータで読み取ることにより、構造物の工程
管理を容易に行うことができる。
In the invention according to claim 5 or 6, since a program for executing a predetermined procedure required for process management is stored in a storage medium in a computer-readable manner, it is easy to carry around. By installing the program stored in the medium on the computer or reading the program on the computer, the process control of the structure can be easily performed.

【0015】[0015]

【発明の実施の形態】以下、本発明の実施の形態を図面
に基づいて説明する。図1は本発明を構造物として橋梁
を適用した場合の一実施形態を示す橋梁製作工場の概略
構成図であって、図中、1は橋梁の生産管理を行う生産
管理システムや工場全体を管理する生産制御兼評価シス
テム、原価管理システム、調達管理システム等の管理シ
ステムが配設された総合管理事務所、2は部材仕分ヤー
ド、3は自動溶接機を有するフランジパネルラインFP
Lを備え、鋼製の箱桁橋を製作する箱桁製作ヤード、4
は自動溶接機を有するウェブパネルラインWPL及びI
桁製作ラインを備え、鋼製のI桁橋を製作するI桁製作
ヤード、5はプレス機、H型鋼キャンバー矯正機、NC
マーキング機、門型NC孔明機(SCOM)、テーブル
型NC孔明機(BV)、NCプラズマ切断機等が配設さ
れた部材加工ヤード、6は屋外組立場である。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a schematic configuration diagram of a bridge manufacturing factory showing an embodiment in which a bridge is applied as a structure according to the present invention. In the drawing, reference numeral 1 denotes a production management system for performing bridge production management and a whole factory management. Management office with management systems such as production control and evaluation system, cost management system, procurement management system, etc., 2 is a material sorting yard, 3 is a flange panel line FP with an automatic welding machine.
L, and a box girder manufacturing yard for manufacturing a steel box girder bridge, 4
Are web panel lines WPL and I with automatic welding machines
Equipped with a girder manufacturing line, I-girder manufacturing yard for manufacturing steel I-girder bridge, 5 for press machine, H-shaped steel camber straightening machine, NC
A member processing yard provided with a marking machine, a gate type NC drilling machine (SCOM), a table type NC drilling machine (BV), an NC plasma cutting machine, etc., and 6 is an outdoor assembly site.

【0016】この橋梁製作工場で、受注した複数の橋梁
がその箱桁、鈑桁、鋼床版箱桁、鋼床版鈑桁等の橋種
と、架設まで、塗装まで、輸送まで等の施工範囲とに応
じて順次製作され、これら橋梁の製作時の工程管理及び
受注の際に必要とする基本構造情報に基づく簡易物量計
算を工程管理システムで実行する。ここで、橋梁を生産
する場合の概要を例えば箱桁鋼橋をステージ生産方式で
生産する場合を例にとって説明する。このステージ生産
方式は、図2に示すように、自動化ラインの個々の設備
を、1つの管理区分としてのステージとし、非自動化工
程についてもライン概念を導入し、生産工程の流れに沿
って管理を行うようにした生産方式である。
At this bridge manufacturing plant, a plurality of bridges that have received orders are classified into bridge types, such as box girders, sheet girders, steel deck slab box girders, steel deck slab girders, and construction ranges from erection to painting to transportation. And a simple physical quantity calculation based on the basic structure information required for the production of these bridges and for receiving orders. Here, an outline of a case where a bridge is produced will be described by taking a case where a box girder steel bridge is produced by a stage production method as an example. In this stage production system, as shown in FIG. 2, individual equipment of an automation line is set as a stage as one management division, and a line concept is introduced for non-automated processes, and management is performed according to the flow of the production process. It is a production method that is performed.

【0017】先ず、鋼板や型鋼の素材に対して仕分、外
注切板、外注加工、1次加工の4つのステージで構成さ
れる切板加工作業を行うことにより、部材用切板や組部
材用切板等のピースを形成する。このピースは、素材を
切板した状態で最小単位部材を表している。そして、ピ
ースに対して細巾板継ライン、広巾板継ライン、部材加
工の3つのステージで構成される部材加工作業を行うこ
とにより、フランジ、デッキプレート、ウェブ縦リブ、
スティフナー、ガゼット、ソールプレート、スラブアン
カー、スタッドジベル、対傾構部材、塗装金物、検査路
金物、排水装置金物、添接板等の部材を形成する。この
部材は、切板に加工をした状態又はピースとピースとを
平面的に溶接した状態を表している。
[0017] First, by performing a plate processing operation including four stages of sorting, outsourced cutting plate, outsourced processing, and primary processing on a steel plate or a shape steel material, a member cut plate or an assembled member is processed. A piece such as a cutting board is formed. This piece represents the minimum unit member in a state where the material is cut. Then, by performing a member processing operation composed of three stages of the narrow plate connecting line, the wide plate connecting line, and the member processing on the piece, a flange, a deck plate, a web vertical rib,
Forming members such as stiffeners, gussets, sole plates, slab anchors, stud dowels, tilting members, painted hardware, inspection hardware, drainage hardware, attachment plates, etc. This member represents a state in which a cut plate is processed or a state in which pieces are welded two-dimensionally.

【0018】次いで、部材に対して小物組、I桁ライン
(IBL)、ウェブパネルライン(WPL)及びフラン
ジパネルライン(FPL)の4つのステージで構成され
る部材組立作業を行うことにより、I桁パネル、ウェブ
パネル、フランジパネル、横リブ、ダイヤフラム、横桁
用仕口、縦桁用仕口、張出ブラケット用仕口、中床板用
仕口、側床板用仕口、吊りピース等の組部材又はパネル
を形成する。ここで、組部材とはピースとピース、ピー
スと部材、部材と部材を立体的に溶接した状態を表し、
この組部材と部材とは形状により部材は組部材に、組部
材は部材となることがある。
Next, the member is assembled with four stages of a small set, an I-girder line (IBL), a web panel line (WPL), and a flange panel line (FPL) on the member, thereby obtaining an I-girder. Assembled members such as panels, web panels, flange panels, horizontal ribs, diaphragms, horizontal girder connections, vertical girder connections, overhang bracket connections, middle floor plate connections, side floor plate connections, hanging pieces, etc. Alternatively, a panel is formed. Here, the assembled member represents a state in which a piece and a piece, a piece and a member, a member and a member are three-dimensionally welded,
Depending on the shape of the assembled member and the member, the member may be an assembled member and the assembled member may be a member.

【0019】そして、形成された組部材又はパネルに対
してブロック組の1つのステージで構成されるブロック
組立作業を行うことにより、主桁、横桁、縦桁、張出ブ
ラケット、中床板、側床板、対傾構、横構、耐震連結、
検査路、排水装置、伸縮装置、製作高欄等のブロックを
形成し、形成されたブロックを仮組及び塗装の2つのス
テージで構成される仮組立作業を行うことにより、2つ
の箱桁を横桁で連接したグループ製品を製作し、製作さ
れたグループ製品を出荷及び現地工事の2つのステージ
で構成される製品としての橋梁が完成する。なお、受注
形態によっては、仮組立作業まで、塗装まで、出荷まで
で作業を打ち切ることがある。
Then, by performing a block assembling operation composed of one stage of the block assembly on the formed assembly member or panel, the main girder, the horizontal girder, the vertical girder, the overhang bracket, the middle floor plate, and the side girder. Floorboard, anti-tilt structure, horizontal structure, seismic connection,
By forming blocks such as inspection paths, drainage devices, telescopic devices, and manufacturing rails, and performing the temporary assembly work consisting of two stages, temporary assembly and painting, on the formed blocks, two box girders are crossed. Then, a bridge is completed as a product composed of two stages of shipping and on-site construction. It should be noted that, depending on the form of the order, the work may be terminated until the temporary assembly work, the painting, and the shipment.

【0020】そして、ステージと作業指示工程との関係
は、仕分ステージでは、受入、配材、次工程送の3つの
作業指示工程が含まれ、外注切断ステージでは罫書、切
断、糸面取、次工程送の4つの作業指示工程が含まれ、
外注加工ステージでは曲げ、孔明、機械加工、鉄工加
工、次工程送の5つの作業指示工程が含まれ、一次加工
ステージでは、罫書、切断及び次工程送の3つの作業指
示工程が含まれ、細巾板継ラインステージでは組立、溶
接、歪取、ベーダー、孔明及び次工程送の6つの作業指
示工程が含まれ、広巾板継ラインステージでは、組立、
溶接、歪取、ベーダー及び次工程送の5つの作業指示工
程が含まれ、部材加工ステージでは罫書機(MAM)、
ベーダー、切断、孔明機(SCOM)、孔明機(B
V)、ラジアル端面切削、曲げ、次工程送りの8つの作
業指示工程が含まれている。
The relationship between the stage and the work instruction process is as follows. The sorting stage includes three work instruction processes of receiving, distributing, and sending the next process. Includes four work instruction steps for sending the process,
The outsourcing processing stage includes five work instruction steps of bending, drilling, machining, iron work, and sending the next process. The primary processing stage includes three work instruction steps of scribing, cutting, and sending the next process. The wide board joint line stage includes six work instruction steps of assembling, welding, straightening, vader, drilling and sending the next process.
Includes five work instruction steps of welding, straightening, vader, and next process, and a scribe machine (MAM),
Vader, cutting, drilling machine (SCOM), drilling machine (B
V), eight operation instruction steps of radial end face cutting, bending, and next step feed are included.

【0021】また、小物組ステージ、I桁ラインステー
ジ、ウェブパネルラインステージ、フランジパネルライ
ンステージ及びブロック組ステージでは、夫々組立、溶
接、歪取及び次工程送の4つの作業指示工程が含まれ、
仮組ステージでは仮組立、解体及び次工程送の3つの作
業指示工程が含まれ、塗装ステージでは塗装準備、塗装
及び次工程送の3つの作業指示工程が含まれ、出荷ステ
ージでは横持、保管、梱包及び発送の4つの作業指示工
程が含まれている。
Each of the accessory set stage, the I-girder line stage, the web panel line stage, the flange panel line stage, and the block set stage includes four work instruction steps of assembling, welding, straightening, and sending the next step, respectively.
The temporary assembly stage includes three work instruction steps of temporary assembly, disassembly, and next process transfer. The painting stage includes three work instruction steps of paint preparation, painting, and next process transfer. , Packing and shipping.

【0022】このように、ステージ生産方式で箱桁鋼橋
が生産されるのであるが、この間の生産管理を生産管理
システムで行う。この生産管理システムは、図3に示す
ように、基本構造情報に基づいて簡易物量計算を行う簡
易物量算出システム11と、工程計画を行う工程管理シ
ステム12と、簡易物量算出システム11及び工程管理
システム12から入力される工数計算パラメータに基づ
いて工数管理を行う工数管理システム13と、受注した
橋梁の設計データを作成し、この設計データに基づいて
構造情報及び原板情報を工程管理システム12に出力す
る自動原寸システム14と、工程管理システム12から
出力される計画データ、工程手順、工程手順ネットワー
ク、部品情報に基づいてガントチャートを作成する工程
管理手段としての工程スケジューラ15と、各ヤード2
〜5及び屋外組立場6での実際の工数実績情報を収集す
る生産制御兼評価システム16とを備えている。
As described above, the box girder steel bridge is produced by the stage production system, and the production management during this is performed by the production management system. As shown in FIG. 3, the production management system includes a simple physical quantity calculation system 11 that performs a simple physical quantity calculation based on basic structure information, a process management system 12 that performs a process plan, a simple physical quantity calculation system 11, and a process management system. A man-hour management system 13 that manages man-hours based on man-hour calculation parameters input from 12 and design data of a bridge that has been ordered, and outputs structural information and original sheet information to the process management system 12 based on the design data. An automatic full-scale system 14, a process scheduler 15 as a process management means for creating a Gantt chart based on plan data, a process procedure, a process procedure network, and component information output from the process management system 12, and each yard 2
5 and a production control and evaluation system 16 for collecting actual man-hour performance information at the outdoor assembling facility 6.

【0023】また、生産管理システムのハードウェア構
成は、図4に示すように、簡易物量算出システム11、
工程管理システム12及び工数管理システム13を構築
する総合管理事務所1に配設された管理用サーバ21
と、この管理用サーバ21に例えばイーサネット(登録
商標)で構成されローカルエリアネットワークLANを
介して接続された製作現場に配設された複数台のパーソ
ナルコンピュータPCF及び総合管理事務所1に配設さ
れた複数台のパーソナルコンピュータPCOと、ローカ
ルエリアネットワークLANに接続されたプリンタPR
とで構成されている。
As shown in FIG. 4, the hardware configuration of the production management system includes a simple physical quantity calculation system 11,
A management server 21 provided in the integrated management office 1 for constructing the process management system 12 and the man-hour management system 13
And a plurality of personal computers PCF and a general management office 1 which are arranged at a production site and which are connected to the management server 21 by, for example, Ethernet (registered trademark) and connected via a local area network LAN. And a plurality of personal computers PCO and a printer PR connected to a local area network LAN
It is composed of

【0024】管理用サーバ21には、例えば箱桁橋、鈑
桁橋及び鋼床版箱桁橋でなる3つの橋種に応じて予め設
定されたブロック物量算出モデル及び部材物量算出モデ
ルを格納したモデルデータベースと、橋梁を生産する場
合の管理を行う生産管理データベースとが形成されてい
る。モデルデータベースには、図5に示す橋種に応じた
橋を構成する主桁、横桁等のブロック単位の物量を算出
するブロック物量算出モデルと、図6に示す橋種に応じ
たブロックを構成する上フランジ、下フランジ、ウェブ
等の部材単位の物量を算出する部材物量算出モデルとが
格納されている。
In the management server 21, a model storing a block physical quantity calculation model and a member physical quantity calculation model preset according to three bridge types, for example, a box girder bridge, a sheet girder bridge and a steel deck slab girder bridge. A database and a production management database for managing bridge production are formed. The model database includes a block physical quantity calculation model for calculating physical quantities in block units, such as a main girder and a horizontal girder, which form a bridge corresponding to the bridge type shown in FIG. 5 and a block corresponding to the bridge type shown in FIG. And a member physical quantity calculation model for calculating the physical quantity of each member such as an upper flange, a lower flange, and a web.

【0025】ここで、ブロック物量算出モデルは、図5
に示すように、箱桁橋、鈑桁橋及び鋼床版箱桁橋の橋種
毎に、主桁の1ブロック長を表すブロック長、橋長、支
承間の長さを表す支間長、同一橋梁が重連する場合の重
連数、契約重量に基づく総重量,鋼材重量,主構造重
量,素材重量,切板重量でなる重量、主桁数に対応する
ライン数、主桁以外のライン数を表す列数、1主桁のジ
ョイント間数を表す連数、主桁,横桁,対傾構等の主構
造ブロック数、主構造ブロックに対応するジョイント
数、支承,伸縮装置等の主要付属品数、ソールプレー
ト,その補強リブ,落橋防止取付板等のブロック組、主
桁,支承,伸縮装置等の仮組立、プライマー種類及び製
品ブラストの有無を表す塗装等の各項目が計算式と共に
記述され、これらの計算式の演算が基本情報としての契
約重量に基づいて行われる。
The block physical quantity calculation model is shown in FIG.
As shown in the figure, for each bridge type of box girder bridge, sheet girder bridge and steel deck slab girder bridge, the block length representing one block length of the main girder, the bridge length, the span length representing the length between bearings, and the same bridge The number of cascades, the total weight based on the contract weight, the steel weight, the main structure weight, the material weight, the weight consisting of the cutting plate weight, the number of lines corresponding to the main girder, and the number of lines other than the main girder The number of columns to represent, the number of joints to represent the number of joints of the main girder, the number of main structural blocks such as the main girder, the horizontal girder, and the inclined structure; Each item such as a sole plate, its reinforcing ribs, a block assembly such as a fall prevention mounting plate, a temporary assembly of a main girder, a bearing, a telescopic device, a primer type and a coating indicating the presence or absence of a product blast is described together with a calculation formula. Is calculated based on the contract weight as basic information. .

【0026】また、部材物量算出モデルは、図6に示す
ように、1ブロック当たりの橋種、ブロック名称、ブロ
ックを形成するための部材名称毎に、幅及び長さを設定
する寸法、部材数、タイプ、箇所、最大板厚等の板継作
業、NC罫書による罫書作業、添接孔、添接板の孔明
数、開先形状,開先加工等の溶接作業、外注,対傾構ラ
イン,吊金具,塗装用手摺取付ピース等のブロック組作
業について設定値が選定されている。
As shown in FIG. 6, the model for calculating the material quantity of a member includes a bridge type, a block name, a dimension for setting a width and a length for each member name for forming a block, and the number of members. , Type, location, maximum sheet thickness, etc., joining work by NC scoring, welding work such as contact holes, number of holes in contact plate, groove shape, groove processing, outsourcing, anti-tilt line, hanging Set values are selected for the work of assembling the blocks such as metal fittings and painting handrail mounting pieces.

【0027】また、生産管理データベースは、図7に示
すように、自動原寸システム14から入力される原寸情
報に基づいて作成される5つの構造階層を有する部品テ
ーブルと、この部品テーブルにおける各階層の登録デー
タに対応する処理工程を登録した処理工程テーブルと、
この処理工程テーブルの各階層における工程で処理する
分をまとめた単位で作成されるタスクテーブルとで構成
されている。
Further, as shown in FIG. 7, the production management database includes a parts table having five structural hierarchies created based on the actual size information input from the automatic actual size system 14, and each of the hierarchies in the parts table. A processing step table in which processing steps corresponding to the registration data are registered,
The processing table includes a task table that is created in a unit that summarizes the processing performed in the process in each layer.

【0028】部品テーブルは、橋梁を構成する各部品の
加工、組立等の状態により、部品をピース、部材、パネ
ル、ブロックの各構成要素に分け、各構成要素を図7に
示すツリー構造に配置することにより、5つの構造階層
を形成する。そして、第1の構造階層となる物件テーブ
ルには物件の物件情報「○○橋」が登録され、第2の構
造階層となるブロックテーブルには物件を構成する主
桁、横桁等のブロックのブロック情報が登録され、第3
の構造階層となるパネルテーブルにはブロックを構成す
る主桁上フランジ、主桁下フランジ、主桁ウェブ等のパ
ネルのパネル情報が登録され、第4の構造階層となる部
材テーブルにはパネルを構成する部材の部材情報が登録
され、第5の構造階層となるピーステーブルには部材を
構成する最小単位部材となるピースのピース情報が登録
されている。
The parts table divides the parts into pieces, members, panels, and blocks according to the state of processing, assembling, and the like of the parts constituting the bridge, and arranges the respective constituents in a tree structure shown in FIG. By doing so, five structural hierarchies are formed. The property table “XX Bridge” of the property is registered in the property table serving as the first structural hierarchy, and the block information such as the main girder and the horizontal girder constituting the property is stored in the block table serving as the second structural hierarchy. The block information is registered and the third
Panel information of panels such as a main girder upper flange, a main girder lower flange, and a main girder web constituting a block are registered in a panel table which is a structural hierarchy of the table, and a panel is formed in a member table which is a fourth structural hierarchy. The piece information of the piece which is the minimum unit member constituting the member is registered in the piece table which is the fifth structural hierarchy.

【0029】ここで、物件情報としては、物件毎に設定
される物件ID、契約番号、装置番号、物件名、橋種I
Dが設定されている。また、ブロック情報としては、物
件ID、ブロックID、ブロックマーク、台数、代表ブ
ロックID、ブロック種IDが設定されている。さら
に、パネル情報としては、物件ID、パネルID、パネ
ルマーク、所属ブロックID、台数、代表パネルID、
パネル種IDが設定されている。さらにまた、部材情報
としては、物件ID、部材ID、部材マーク、所属ブロ
ックID、所属パネルID、員数、代表部材IDが設定
されている。なおさらに、ピース情報としては、物件I
D、ピースID、ピースマーク、所属ブロックID、所
属パネルID、所属部材ID、代表ピースID、所属素
材IDが設定されている。
Here, the property information includes a property ID, a contract number, a device number, a property name, and a bridge type I set for each property.
D is set. As the block information, a property ID, a block ID, a block mark, a number, a representative block ID, and a block type ID are set. Further, the panel information includes a property ID, a panel ID, a panel mark, an affiliation block ID, the number, a representative panel ID,
The panel type ID is set. Furthermore, as the member information, a property ID, a member ID, a member mark, a belonging block ID, a belonging panel ID, the number of members, and a representative member ID are set. Still further, as piece information, the property I
D, piece ID, piece mark, belonging block ID, belonging panel ID, belonging member ID, representative piece ID, and belonging material ID are set.

【0030】そして、設計情報に基づく構造情報を出力
する自動原寸システムから例えば原板単位で入力される
部品マーク及び員数に基づいてピーステーブル、部材テ
ーブル、パネルテーブル、ブロックテーブル及び物件テ
ーブルで構成される部品データベースを自動的に作成す
ると共に、作成した部品データベースに基づいて個々の
部品を作成するために必要処理工程を表す処理工程テー
ブルを作成し、且つ自動原寸システムからの原寸展開情
報に基づいて孔数、罫書長、溶接長等の加工量を表す加
工量テーブルを作成し、さらに作成した処理工程テーブ
ルに基づいて部品データベースの各階層において、部品
毎、工程毎に加工量を集計して、作業指示の単位となる
タスクテーブルを作成し、なおさらに自動原寸システム
から入力される材料情報に基づいて素材情報を設定した
原板テーブルを作成し、素材情報をもとに部品テーブル
のピースを検索してマッチした素材情報が登録されたピ
ースとリンク付けを行う。原板テーブルに登録された素
材情報とピーステーブルに登録された素材情報とが一致
しない場合には、両者間のリンク付けを行うことなく開
放原板となる。
The automatic full scale system that outputs structural information based on the design information is composed of a piece table, a member table, a panel table, a block table, and a property table based on, for example, part marks and the number of members input in units of original plates. In addition to automatically creating a parts database, a processing step table representing processing steps required to create individual parts is created based on the created parts database, and holes are created based on full-scale development information from an automatic full-scale system. Create a machining amount table indicating the machining amount such as the number, ruled line length, welding length, etc., and further summarize the machining amount for each part and process in each layer of the parts database based on the created processing process table. Create a task table as a unit of instruction, and further input materials from the automatic full-scale system Create an original plate table set the material information based on the information, matched material information was to perform the piece and the link with that is registered by searching the piece of parts table on the basis of material information. If the material information registered in the original table and the material information registered in the piece table do not match, an open original is obtained without linking the two.

【0031】さらに、設計完了時点での原寸展開情報が
得られる以前の引き合い時、予算作成時等に工数管理シ
ステムで使用する物量データを簡易物量算出システム1
1で算出する。この簡易物量算出システムは、橋種毎に
作成された図5に示すブロック物量算出モデル及び図6
に示す部材物量算出モデルを使用して、橋種に応じたブ
ロック物量算出モデル及び部材物量算出モデルを選択
し、選択された各モデルに従って、先ず、ブロック物量
算出モデルにおける原単位迄の主構造情報を算出し、次
いで、ブロック物量算出モデルにおける残りの重量、ラ
イン数、列数、連数、主構造ブロック数等を算出し、さ
らに部材物量算出モデルに従って、ブロックを構成する
部材に対する寸法、部材数、タイプ、板継、曲げ、孔明
け、溶接、ブロック組等の物量を算出し、これらに基づ
いて部品テーブル、処理工程テーブル及びタスクテーブ
ルを作成する。
Further, the quantity data used in the man-hour management system at the time of inquiries before obtaining the original size development information at the time of completion of the design, at the time of creating a budget, etc., is calculated by the simplified quantity calculation system 1.
Calculate with 1. The simplified physical quantity calculation system includes a block physical quantity calculation model shown in FIG.
The block physical quantity calculation model and the component physical quantity calculation model corresponding to the bridge type are selected using the component physical quantity calculation model shown in (1), and the main structural information up to the basic unit in the block physical quantity calculation model is firstly determined according to each selected model. Is calculated, and then the remaining weight, the number of lines, the number of columns, the number of stations, the number of main structural blocks, and the like in the block physical quantity calculation model are calculated. , Types, plate joints, bending, drilling, welding, block assembly, etc., and a component table, a processing step table and a task table are created based on these.

【0032】また、管理用サーバ21には、工数管理シ
ステムが構築されている。この工数管理システムは、物
件毎に生産管理データベースに格納されている簡易物量
データ、設計完了時の物量データ、手動原寸の板取情報
及びNC情報作成時の物量データに基づいて工数計算を
行う。この工数管理システムでは、鈑桁、箱桁、鋼床版
箱桁等の橋種毎に工数計算モデルを登録しておく。この
工数計算モデルの登録は、生産管理システムを起動する
ことにより行う。
The man-hour management system is constructed in the management server 21. The man-hour management system calculates man-hours based on simple physical quantity data stored in the production management database, physical quantity data at the time of design completion, manual original board drawing information, and physical quantity data at the time of creating NC information for each property. In this man-hour management system, a man-hour calculation model is registered for each bridge type such as a sheet girder, a box girder, and a steel deck slab box girder. The registration of the man-hour calculation model is performed by activating the production management system.

【0033】この生産管理システムは、起動されると、
図8に示す処理を実行し、先ず、ステップS301で、
図9に示す生産管理システム初期画面をディスプレイに
表示する。この生産管理システム初期画面は、図9に示
すように、物件管理ボタン81、実績情報ボタン82、
進捗把握ボタン83、モデル登録ボタン84、マスタ登
録ボタン85、計算モデルボタン86、工程計画ボタン
87及び終了ボタン88が形成され、これらボタンをマ
ウス又はキーボードで選択することにより、対応する処
理が実行される。
When this production management system is started,
The processing shown in FIG. 8 is executed, and first, in step S301,
The production management system initial screen shown in FIG. 9 is displayed on the display. As shown in FIG. 9, the production management system initial screen includes a property management button 81, a performance information button 82,
A progress grasp button 83, a model registration button 84, a master registration button 85, a calculation model button 86, a process plan button 87, and an end button 88 are formed. By selecting these buttons with a mouse or a keyboard, corresponding processes are executed. You.

【0034】次いで、ステップS302に移行して、物
件管理ボタン81が選択されたか否かを判定し、物件管
理ボタン81が選択されたときにはステップS303に
移行して、物件基本情報の作成、原板情報の登録、作業
情報の登録及び工数計算式を含む工数計算基本モデルを
使用した工数計算処理等の作業を行う物件管理処理を行
ってからステップS304に移行して、終了ボタン88
が選択されたか否かを判定し、終了ボタン88が選択さ
れていないときには前記ステップS301に戻り、終了
ボタン88が選択されているときには生産管理システム
を終了する。
Next, the process proceeds to step S302, where it is determined whether or not the property management button 81 has been selected. When the property management button 81 has been selected, the process proceeds to step S303 to generate the basic property information, , Registration of work information, and property management processing for performing work such as man-hour calculation processing using a man-hour calculation basic model including a man-hour calculation formula.
Is determined, the process returns to step S301 when the end button 88 is not selected, and ends the production management system when the end button 88 is selected.

【0035】また、前記ステップS302の判定結果
が、物件管理ボタン81が選択されていないときにはス
テップS305に移行して、実績情報ボタン82が選択
されているか否かを判定し、実績情報ボタン82が選択
されているときには、ステップS306に移行して、ピ
ース納品情報の登録、出来高チェックシートの作成及び
工数実績情報の登録等の作業を行う実績情報処理を行っ
てから前記ステップS304に移行し、実績情報ボタン
82が選択されていないときにはステップS307に移
行する。
If the result of the determination in step S302 is that the property management button 81 has not been selected, the flow shifts to step S305 to determine whether or not the performance information button 82 has been selected. If it is selected, the process proceeds to step S306 to perform actual information processing for performing operations such as registration of piece delivery information, creation of a work volume check sheet, and registration of man-hour actual information, and then proceeds to step S304. If the information button 82 has not been selected, the process moves to step S307.

【0036】このステップS307では、進捗把握ボタ
ン83が選択されているか否かを判定し、進捗把握ボタ
ン83が選択されているときには、ステップS308に
移行して、ピース調達状況確認、出来高進捗確認及び工
数実績進捗率ファイル作成等を行う進捗把握処理を実行
してから前記ステップS304に移行し、進捗把握ボタ
ン83が選択されていないときにはステップS309に
移行する。
In this step S307, it is determined whether or not the progress grasp button 83 has been selected. If the progress grasp button 83 has been selected, the flow shifts to step S308 to confirm the piece procurement status, the volume progress confirmation, and the like. After executing a progress grasping process for creating a man-hour actual progress rate file or the like, the process proceeds to step S304. If the progress grasping button 83 is not selected, the process proceeds to step S309.

【0037】このステップS309では、モデル登録ボ
タン84が選択されているか否かを判定し、モデル登録
ボタン84が選択されているときには、ステップS31
0に移行して、モデル関係の各テーブルの登録・更新を
行うモデル登録処理を行ってから前記ステップS304
に移行し、モデル登録ボタン84が選択されていないと
きにはステップS311に移行する。
In this step S309, it is determined whether or not the model registration button 84 has been selected. If the model registration button 84 has been selected, the process proceeds to step S31.
0, and a model registration process for registering / updating each table of the model relation is performed.
When the model registration button 84 has not been selected, the process proceeds to step S311.

【0038】このステップS311では、マスタ登録ボ
タン85が選択されているか否かを判定し、マスタ登録
ボタン85が選択されているときには、ステップS31
2に移行して、マスタ関係の各テーブルの登録・更新を
行うマスタ登録処理を実行してから前記ステップS30
4に移行し、マスタ登録ボタン85が選択されていない
ときにはステップS313に移行する。
In this step S311, it is determined whether or not the master registration button 85 has been selected. If the master registration button 85 has been selected, the process proceeds to step S31.
Then, the process proceeds to step S30, where a master registration process for registering / updating each table related to the master is executed, and
The process proceeds to step S313, and if the master registration button 85 has not been selected, the process proceeds to step S313.

【0039】このステップS313では、計算モデルボ
タン86が選択されているか否かを判定し、計算モデル
ボタン86が選択されているときにはステップS314
に移行して、工数計算式を含む工数計算モデルの登録・
更新を行う工数計算モデル処理を行ってから前記ステッ
プS304に移行し、計算モデルボタン86が選択され
ていないときにはステップS315に移行する。
In step S313, it is determined whether or not the calculation model button 86 has been selected. If the calculation model button 86 has been selected, step S314 is performed.
And register the tact calculation model including tact formula
After performing the man-hour calculation model process for updating, the process proceeds to step S304. If the calculation model button 86 is not selected, the process proceeds to step S315.

【0040】このステップS315では、工程計画ボタ
ン87が選択されているか否かを判定し、工程計画ボタ
ン87が選択されているときにはステップS316に移
行して、タスクテーブルに登録された組部材の各工程に
ついて工程順・工程間繋がりを登録して工程計画を行う
工程計画処理を行ってから前記ステップS304に移行
し、工程計画ボタン87が選択されていないときには直
接前記ステップS304に移行する。
In this step S315, it is determined whether or not the process plan button 87 has been selected. If the process plan button 87 has been selected, the flow shifts to step S316, where each of the assembly members registered in the task table has been selected. The process goes to step S304 after performing a process planning process for registering the process sequence and the connection between the processes and performing a process plan. If the process plan button 87 is not selected, the process directly goes to step S304.

【0041】ここで、ステップS314の工数計算モデ
ル処理は、図10に示すように、先ず、ステップS32
1で、工数計算基本モデルを工数計算モデルテーブルに
登録する。この工数計算基本モデルテーブルの登録は、
新規に作成してもよいし、既登録の基本モデルを選択し
て、これに登録されている組部材及び組部材の各物量パ
ラメータを複写するようにしてもよい。
Here, as shown in FIG. 10, the man-hour calculation model processing in step S314 is performed first in step S32.
In step 1, the man-hour calculation basic model is registered in the man-hour calculation model table. Registration of this man-hour calculation basic model table,
A new model may be created, or a registered basic model may be selected, and a set member registered in this basic model and each material parameter of the set member may be copied.

【0042】次いで、ステップS322に移行して、工
数計算モデルテーブルに登録されている工数計算モデル
を選択し、次いでステップS323に移行して、図11
に示すように、フランジ、主桁ウェブ等の組部材名を組
番号と共に登録する。次いで、ステップS324に移行
して、各組部材についての工数計算パラメータを定義す
る。この工数計算パラメータの定義は、図12に示すよ
うに、各組部材についてパラメータ番号、例えば主構造
鋼重、主構造部材数、総孔数等の組部材名で一意の物量
パラメータ名、モデル内で一意の定義名、整数、実数、
3択等の属性、単位、表示桁文字列、アドレス、自動計
算するか否かを選択するチェックボックス、自動計算式
を表形式で工数計算パラメータ定義テーブルに登録す
る。
Then, the flow shifts to step S322 to select a man-hour calculation model registered in the man-hour calculation model table, and then shifts to step S323, where FIG.
As shown in (1), the names of the assembly members such as the flange and the main girder web are registered together with the assembly numbers. Next, the process proceeds to step S324 to define man-hour calculation parameters for each set member. As shown in FIG. 12, the definition of the man-hour calculation parameters is a parameter number unique to each group member, such as a parameter number such as a main structural steel weight, the number of main structural members, a total number of holes, and the like. , Unique definition names, integers, real numbers,
Attributes such as three options, units, display digit character strings, addresses, check boxes for selecting whether or not to perform automatic calculation, and automatic calculation formulas are registered in a table format in the man-hour calculation parameter definition table.

【0043】次いで、ステップS325に移行して、パ
ラメータ定義に選択型項目が含まれているか否かを判定
し、パラメータ定義に選択型項目がある場合には、ステ
ップS326に移行して、選択型項目の項目名を選択型
項目テーブルに登録してからステップS327に移行し
て、パラメータ定義に選択型項目がない場合には直接ス
テップS327に移行する。
Next, the process proceeds to step S325 to determine whether or not the parameter definition includes a selection type item. If the parameter definition includes a selection type item, the process proceeds to step S326 to select the selection type item. After registering the item name of the item in the selectable item table, the process proceeds to step S327. If there is no selectable item in the parameter definition, the process directly proceeds to step S327.

【0044】このステップS327では、図13に示す
ように、工数、数量、単位工数、段取時間、効率化係数
及び段取効率化係数で構成される各タスク(工程)パラ
メータについて各々工数計算式を入力し、この工数計算
式を工数計算式テーブルに登録する。各タスクパラメー
タとしては、箱桁の主桁ダイヤフラムである場合に、図
14に示すように、ステージ名「5機械加工」で工程名
「65NC切断」である場合に、数量は「=〔ダイヤフ
ラム枚数〕」、単位工数は「=((〔フランジ幅〕*
〔ウェブ高さ〕/1000))*2*1.5*2*2)
/12/60+((〔ウェブ高さ〕/1000/2+
〔フランジ幅〕/2)*2*2)/2.5/60+
((〔フランジ幅〕+(〔ウェブ高さ〕……」、段取時
間は「=0.4〔ダイヤフラム枚数〕」、効率化係数は
「1.5」、段取効率化係数は「1.0」が登録され
る。
In this step S327, as shown in FIG. 13, each task (process) parameter including the man-hour, the quantity, the unit man-hour, the setup time, the efficiency improvement coefficient, and the setup efficiency improvement coefficient is calculated by the man-hour calculation formula. Is entered, and this man-hour calculation formula is registered in the man-hour calculation formula table. As the task parameters, when the main girder diaphragm is a box girder, and when the stage name is “5 machining” and the process name is “65 NC cutting” as shown in FIG. 14, the quantity is “= [diaphragm number ]] And the unit man-hour is “= (([[flange width] *
[Web height] / 1000)) * 2 * 1.5 * 2 * 2)
/ 12/60 + (([Web height] / 1000/2 +
[Flange width] / 2) * 2 * 2) /2.5/60+
(([Flange width] + ([web height] ...), setup time is "= 0.4 [number of diaphragms]", efficiency factor is "1.5", and setup efficiency factor is "1" .0 "is registered.

【0045】このようにして工数計算基本モデルを予め
工数計算モデルテーブルに登録しておくことにより、こ
の工数計算基本モデルを使用して、前述したステップS
303で実行する物件管理処理において工数計算を行う
ことができる。この工数計算処理は、橋種に応じてステ
ップS314の工数計算モデル処理で登録した工数計算
モデルを選択し、選択された工数計算基本モデルと前記
簡易物量算出処理で登録されたブロック物量データ及び
部材物量データとに基づいて工数計算を行い、工数、数
量、単位工数、段取時間を演算すると共に、効率化係数
及び段取効率化係数を選定する。
By pre-registering the man-hour calculation basic model in the man-hour calculation model table in this manner, the above-described step S
In the property management processing executed in 303, man-hour calculation can be performed. In this man-hour calculation processing, the man-hour calculation model registered in the man-hour calculation model processing in step S314 is selected according to the bridge type, and the selected man-hour calculation basic model and the block physical quantity data and members registered in the simple physical quantity calculation processing are selected. The man-hour calculation is performed based on the physical quantity data, the man-hour, the quantity, the unit man-hour, and the setup time are calculated, and the efficiency improvement coefficient and the setup efficiency improvement coefficient are selected.

【0046】この工数計算処理は、具体的には、図15
に示すように、先ず、ステップS331で、物件テーブ
ルから対象物件を選択し、次いでステップS332に移
行して、橋種に応じて前記ステップS314の工数計算
モデル処理で登録した工数計算基本モデルを選択し、次
いでステップS333に移行して、選択した工数計算基
本モデルを複写することにより、物件専用の工数計算モ
デルを作成してからステップS334に移行する。
This man-hour calculation processing is specifically described in FIG.
As shown in (1), first, in step S331, the target property is selected from the property table, and then the process proceeds to step S332, and the man-hour calculation basic model registered in the man-hour calculation model process in step S314 is selected according to the bridge type. Then, the process proceeds to step S333, where the man-hour calculation model dedicated to the property is created by copying the selected man-hour calculation basic model, and then the process proceeds to step S334.

【0047】このステップS334では、物件特有の組
部材があるか否かを判定し、物件特有の組部材があると
きにはステップS335に移行して、組部材の追加・削
除を行い、次いでステップS336に移行して、追加し
た組部材があるか否かを判定し、追加した組部材がある
ときにはステップS337に移行して、追加した組部材
の工程パラメータの計算式を値で入力してからステップ
S338に移行し、前記ステップS334の判定結果が
物件特有の組部材がないとき及び前記ステップS336
の判定結果が追加した組部材がないときには直接ステッ
プ338に移行する。
In this step S334, it is determined whether or not there is a member-specific assembly member. If there is a member-specific assembly member, the flow shifts to step S335 to add or delete the assembly member, and then to step S336. Then, it is determined whether or not there is an added assembly member. If there is an added assembly member, the process proceeds to step S337, and the calculation formula of the process parameter of the added assembly member is input as a value, and then step S338 is performed. And the determination result in step S334 indicates that there is no property-specific assembly member and that step S336
If there is no added member with the determination result of (3), the process directly proceeds to step 338.

【0048】ステップS338では、前述した簡易物量
算出処理で登録した簡易物量算出データを例えば表計算
アプリケーションのブックに形成した工数Prmシート
に組部材番号*100+パラメータ番号を行アドレスと
し、列アドレス“1”を定義名、列アドレス“2”を物
量パラメータとして読込み、次いでステップS339に
移行して、読込んだ簡易物量算出データをもとに、設定
された工数計算式に従って工数、数量、単位工数、段取
時間を算出すると共に、効率化係数及び段取効率化係数
の各工程パラメータを算出し、算出した各工程パラメー
タをタスクパラメータテーブルに登録してからステップ
S340に移行する。
In step S338, the simplified physical quantity calculation data registered in the simple physical quantity calculation processing described above is set, for example, on the man-hour Prm sheet formed in the book of the spreadsheet application, with the assembly member number * 100 + the parameter number as the row address and the column address "1". Is read as the definition name and the column address “2” is read as the physical quantity parameter. Then, the process proceeds to step S339, and based on the read simple physical quantity calculation data, the man-hour, quantity, unit man-hour, In addition to calculating the setup time, each process parameter of the efficiency enhancement factor and the setup efficiency enhancement factor is calculated, and the calculated process parameters are registered in the task parameter table, and then the process proceeds to step S340.

【0049】このステップS340では、工程パラメー
タの算出結果を修正するか否かを判定し、これを修正す
る場合にはステップS341に移行して、効率化係数及
び段取効率化係数をこれらの夫々について修正係数を乗
算して修正し、修正値に基づいて再度工程パラメータを
算出し直し、算出し直した各工程パラメータをタスクパ
ラメータテーブルに登録してからステップS342に移
行し、工程パラメータの修正を行わないときにはそのま
まステップS342に移行する。
In this step S340, it is determined whether or not the calculation result of the process parameter is to be corrected, and if it is to be corrected, the flow shifts to step S341 to set the efficiency improvement coefficient and the setup efficiency improvement coefficient respectively. Is corrected by multiplying by a correction coefficient, the process parameters are recalculated based on the corrected values, and the recalculated process parameters are registered in the task parameter table, and the process proceeds to step S342 to correct the process parameters. If not, the process moves directly to step S342.

【0050】このステップS342では、簡易物量算出
データに基づいて物件物量表を出力すると共に、算出し
た工程パラメータを元に工数計画表を出力する。物件物
量表としては、図16に示すように、組部材名を横軸方
向に記載し、各組部材に対する数量等の物量パラメータ
を縦軸方向に記載した表形式に構成されている。また、
工数計画表としては、図17に示すように、組部材名を
横軸方向に記載し、各部材名の夫々に対して効率化係
数、工数、単位工数及び数量の工程パラメータを横軸方
向に記載し、ステージ名及び工程名を縦軸方向に記載し
た表形式に構成されている。
In step S342, a property quantity table is output based on the simple physical quantity calculation data, and a man-hour plan table is output based on the calculated process parameters. As shown in FIG. 16, the property quantity table is configured in a table format in which the names of the assembly members are described in the horizontal axis direction, and the physical quantity parameters such as the quantity for each assembly member are described in the vertical axis direction. Also,
As the man-hour planning table, as shown in FIG. 17, the assembly member names are described in the horizontal axis direction, and the process parameters such as the efficiency factor, the man-hour, the unit man-hour, and the quantity are described in the horizontal axis direction for each of the member names. The table name is described in a table format in which the stage name and the process name are described in the vertical axis direction.

【0051】このようにして工数計算が行われた後に、
工程計画が行われる。この工程計画では、図18に示す
ように、工程計画時期に応じて標準工程における工程順
・工程間繋がり登録、工数計算における工程順・工程間
繋がり登録、確定工程における工程順・工程間繋がり登
録の3種類に分けられる。このうち、標準工程における
工程順・工程間繋がり登録は、引き合い時に長期的な工
程計画を作成するスケジュールのデータであり、前述し
た簡易物量算出システム11で橋種毎に登録してある基
本モデルに基づいて算出した工程情報に基づいて工程順
・工程間繋がりを行い、その結果を標準工程スケジュー
ルテーブルに登録する。
After the man-hour calculation is performed in this manner,
A process plan is performed. In this process plan, as shown in FIG. 18, the process order and inter-process connection registration in the standard process, the process order and inter-process connection registration in the man-hour calculation, and the process order and inter-process connection registration in the fixed process, as shown in FIG. Are divided into three types. Among these, the process order / interprocess connection registration in the standard process is schedule data for creating a long-term process plan at the time of inquiries, and is registered in the basic model registered for each bridge type in the above-described simple physical quantity calculation system 11. Based on the calculated process information, the order of the processes and the connection between the processes are performed, and the result is registered in the standard process schedule table.

【0052】また、工数計算における工程順・工程間繋
がり登録は、予算作成時に長期的な工程計画を作成する
スケジュールのデータであり、前述した工数計算処理で
作成された工程情報に基づいて工程順・工程間繋がりを
行い、その結果を標準工程スケジュールテーブルに登録
する。さらに、確定工程における工程順・工程間繋がり
登録は、物量及び工程が確定した時点で作成するスケジ
ュールのデータであり、原寸展開処理に基づいて作成さ
れたタスクテーブルの工程情報に基づいて工程順・工程
間繋がりを行い、その結果を確定工程スケジュールテー
ブルに登録する。
The process order / process connection registration in the man-hour calculation is schedule data for creating a long-term process plan at the time of budget creation, and is based on the process information created in the man-hour calculation process described above. -Connect between processes and register the result in the standard process schedule table. Furthermore, the process order / inter-process connection registration in the confirmation process is data of a physical quantity and a schedule created when the process is decided, and is based on the process information of the task table created based on the original size development process. The connection between the processes is performed, and the result is registered in the fixed process schedule table.

【0053】これら3つの工程順・工程間繋がり登録
は、参照する工程情報が異なるだけで、処理としては同
一の処理を行う。この工程計画は、生産管理システムを
起動して、図8の生産管理処理を実行したときに、図9
に示す初期画面で、工程計画ボタン87を選択すること
により実行され、図19に示すように、先ずステップS
500で図20に示す工程計画支援メニュー画面を表示
してからステップS501に移行する。
The registration of the three steps in the order of the steps and the connection between the steps is the same as the processing except that the referenced step information is different. When the production management system is activated and the production management process shown in FIG.
In the initial screen shown in FIG. 19, the process is executed by selecting the process plan button 87. First, as shown in FIG.
The process planning support menu screen shown in FIG. 20 is displayed at 500, and the process proceeds to step S501.

【0054】この工程計画支援メニュー画面は、図20
に示すように、工程順・工程間繋がりを前述した簡易物
量算出処理で登録された工程情報に基づいて物件毎に工
程順・工程間繋がりを登録・更新する登録ボタン301
と、工数計算モデルで登録された工程情報に基づいて物
件毎に工程順・工程間繋がりを登録・更新する工数計算
・工程間繋がり登録ボタン302と、設計を終了した後
のタスク情報に基づく物件毎の工程順・工程間繋がりを
登録・更新する確定工程・工程間繋がり登録ボタン30
3と、新規物件の工程スケジューラ15に受け渡す工程
計画データを作成する工程計画データ作成ボタン304
と、スケジュール調整時の工程計画データを作成する工
程計画調整データ作成ボタン305と、確定した工程ス
ケジュールをファイルから読込む確定スケジュール取込
みボタン306と、工程間繋がりの登録を実施している
物件の一覧を表示する工程間繋がり登録状況ボタン30
7と、工程計画帳票を要求する工程計画帳票要求メニュ
ーボタン308と、戻るボタン309とを備えている。
The process plan support menu screen is shown in FIG.
As shown in the figure, a registration button 301 for registering / updating the process order / inter-process connection for each property based on the process information registered in the above-described simple physical quantity calculation process.
And a man-hour calculation / inter-process connection registration button 302 for registering / updating the process order / inter-process connection for each property based on the process information registered in the man-hour calculation model, and a property based on the task information after the design is completed. Confirmation process / process connection registration button 30 for registering / updating the process order / process connection for each
3 and a process plan data creation button 304 for creating process plan data to be passed to the process scheduler 15 of the new property.
, A process plan adjustment data creation button 305 for creating process plan data at the time of schedule adjustment, a fixed schedule import button 306 for reading the determined process schedule from a file, and a list of properties for which the connection between processes is registered. Button 30 indicating the connection status between processes that displays
7, a process plan form request menu button 308 for requesting a process plan form, and a return button 309.

【0055】ステップS501では、標準工程・工程間
繋がり登録ボタン301が選択されているか否かを判定
し、これが選択されているときにはステップS502に
移行して、後述する確定工程・工程間繋がり登録・更新
処理において読込むタスク情報に代えて簡易物量算出シ
ステム11で算出した工程情報を取込むことを除いては
同様の処理を行う標準工程・工程間繋がり登録・更新処
理を実行してから前記ステップS500に戻る。
In step S501, it is determined whether or not the standard process / process connection registration button 301 has been selected. When the button 301 has been selected, the flow shifts to step S502 to determine a fixed process / process connection registration / registration described later. After performing the standard process / inter-process connection registration / update process, the same process is performed except that the process information calculated by the simplified physical quantity calculation system 11 is taken in instead of the task information read in the update process. It returns to S500.

【0056】また、前記ステップS501の判定結果が
標準工程・工程間繋がり登録ボタン301が選択されて
いないものであるときにはステップS503に移行し
て、工数計算・工程間繋がり登録ボタン302が選択さ
れているか否かを判定し、これが選択されているときに
は、ステップS504に移行して、後述する確定工程・
工程間繋がり登録・更新処理において読込むタスク情報
に代えて、工数計算システム13で算出したタスク情報
を取込むことを除いては同様の処理を行う工数計算・工
程間繋がり登録処理を行ってから前記ステップS500
に戻る。
If the result of the determination in step S501 is that the standard process / process connection registration button 301 has not been selected, the flow shifts to step S503, where the man-hour calculation / process connection registration button 302 is selected. It is determined whether or not it has been selected, and if this is selected, the process proceeds to step S504 to determine
After performing the man-hour calculation and the process-to-process connection registration process that performs the same process except that the task information calculated by the man-hour calculation system 13 is taken in instead of the task information read in the process-to-process connection registration / update process. Step S500
Return to

【0057】さらに、前記ステップS503の判定結果
が、工数計算・工程間繋がり登録ボタン302を選択し
ていないものであるときには、ステップS505に移行
して、確定工程・工程間繋がり登録ボタン303が選択
されているか否かを判定し、これが選択されているとき
にはステップS506に移行して、後述する図21に示
す工程順・工程間繋がり登録・更新処理を実行してから
前記ステップS500に戻る。
If the result of the determination in step S503 is that the man-hour calculation / inter-process connection registration button 302 has not been selected, the process proceeds to step S505, and the confirmation step / inter-process connection registration button 303 is selected. It is determined whether or not the process has been performed. If it has been selected, the process proceeds to step S506, and the process sequence / interprocess connection registration / update process shown in FIG. 21 described later is executed, and then the process returns to step S500.

【0058】さらにまた、前記ステップS505の判定
結果が確定工程・工程間繋がり登録ボタン303を選択
していないものであるときには、ステップS507に移
行して、工程計画データ作成ボタン304が選択されて
いるか否かを判定し、これが選択されているときにはス
テップS508に移行して、後述する図28に示す工程
計画データ作成処理を実行してから前記ステップS50
0に戻る。
Further, if the result of the determination in the step S505 is that the button for registering the fixed process / step connection 303 has not been selected, the flow shifts to step S507 to determine whether or not the button 304 for creating the process plan data has been selected. It is determined whether or not the process has been selected, and if it is selected, the process proceeds to step S508 to execute a process plan data creation process shown in FIG.
Return to 0.

【0059】なおさらに、前記ステップS507の判定
結果が、工程計画データ作成ボタン304が選択されて
いないものであるときには、ステップS509に移行し
て、工程計画調整データ作成ボタン305が選択されて
いるか否かを判定し、これが選択されているときにはス
テップS510に移行して、進捗状況を表す工程実績デ
ータに基づいてスケジュール調整を行った工程計画デー
タを作成する工程計画調整データ作成処理を実行してか
らステップS500に戻る。
If the result of the determination in step S507 is that the process plan data creation button 304 has not been selected, the flow shifts to step S509 to determine whether the process plan adjustment data creation button 305 has been selected. If this is selected, the process proceeds to step S510 to execute a process plan adjustment data creating process for creating process plan data that has been adjusted based on the process actual data indicating the progress. It returns to step S500.

【0060】また、前記ステップS509の判定結果
が、工程計画調整データ作成ボタン305が選択されて
いないものであるときには、ステップS511に移行し
て、確定スケジュール取込みボタン306が選択されて
いる否かを判定し、これが選択されているときにはステ
ップS512に移行して、工程スケジューラ15で確定
された確定スケジュールをファイルから取込んで表示す
る確定スケジュール取込み処理を行ってから前記ステッ
プS500に戻る。
If the result of the determination in step S509 is that the process plan adjustment data creation button 305 has not been selected, the flow shifts to step S511 to determine whether or not the fixed schedule capture button 306 has been selected. If it is determined that the selected schedule has been selected, the process proceeds to step S512, in which the fixed schedule determined by the process scheduler 15 is read from the file and displayed, and the process returns to step S500.

【0061】さらに、前記ステップS511の判定結果
が、確定スケジュール取込みボタン306が選択されて
いないものであるときには、ステップS513に移行し
て、工程間繋がり登録状況ボタン307が選択されてい
るか否かを判定し、これが選択されているときにはステ
ップS514に移行して、工程間繋がり登録を行った物
件一覧を表示してから前記ステップS500に戻る。
If the result of the determination in step S 511 is that the button 306 for accepting a fixed schedule has not been selected, the flow shifts to step S 513 to determine whether or not the connection status button 307 has been selected. If it is determined that this is selected, the process proceeds to step S514, where a list of properties for which the inter-process connection has been registered is displayed, and then the process returns to step S500.

【0062】さらにまた、前記ステップS513の判定
結果が、工程間繋がり登録状況ボタン307が選択され
ていないものであるときには、ステップS515に移行
して、工程計画帳票要求メニューボタン308が選択さ
れているか否かを判定し、これが選択されているときに
は、ステップS516に移行して、図30に示す総括工
程表及び図31に示す製作工数山積表を作成し、これを
出力する工程計画帳票出力処理を行ってから前記ステッ
プS500に戻り、工程計画帳票要求メニューボタン3
08が選択されていないときにはステップS517に移
行して、戻るボタン309が選択されているか否かを判
定し、これが選択されていないときには前記す500に
戻り、選択されているときには工程管理処理を終了して
図8のステップS304に戻る。
If the result of the determination in step S513 is that the inter-process connection registration status button 307 has not been selected, the flow shifts to step S515 to determine whether the process plan form request menu button 308 has been selected. It is determined whether or not this is selected, and if it is selected, the process proceeds to step S516 to create a general process chart shown in FIG. 30 and a production man-hour pile table shown in FIG. 31 and perform a process plan form output process for outputting these. After returning to step S500, the process plan form request menu button 3
If 08 has not been selected, the process proceeds to step S517 to determine whether or not the return button 309 has been selected. If this has not been selected, the process returns to step 500. If it has been selected, the process management process ends. Then, the process returns to step S304 in FIG.

【0063】また、ステップS506の工程間繋がり登
録処理は、図21に示すように、先ず、ステップS52
1で、図23に示す確定工程・工程間繋がり登録画面を
ディスプレイに表示し、物件名を入力するコンボボック
ス401で物件テーブルに登録された物件名を選択し、
次いでステップS522に移行して、選択した物件が確
定工程スケジュールテーブルに登録されているか否かを
判定し、確定工程スケジュールテーブルに登録されてい
るときにはステップS523に移行して、処理区分コン
ボボックス402に“修正”をセットしてからステップ
S525に移行し、確定工程スケジュールテーブルに登
録されてないときにはステップS524に移行して、処
理区分コンボボックスに“新規”をセットしてからステ
ップS525に移行する。
As shown in FIG. 21, the inter-process connection registration process of step S506 is performed first in step S52.
In step 1, the confirmation process / inter-process connection registration screen shown in FIG. 23 is displayed on the display, and the property name registered in the property table is selected with a combo box 401 for inputting the property name.
Next, the process proceeds to step S522 to determine whether or not the selected property is registered in the fixed process schedule table. If the selected property is registered in the fixed process schedule table, the process proceeds to step S523 and the process classification combo box 402 is displayed. The process proceeds to step S525 after “correction” is set. If not registered in the fixed process schedule table, the process proceeds to step S524, and “new” is set in the process category combo box, and then the process proceeds to step S525.

【0064】ステップS525では、図23の確定・工
程間繋がり登録画面の処理区分を選択するコンボボック
ス402で修正又は新規を選択すると、ステップS52
6に移行して、選択された処理区分がコンボボックス4
02に表示し、次いでステップS527に移行して、処
理区分で新規を選択されているか否かを判定し、新規が
選択されているときにはステップS528に移行して、
タスクテーブルから工程情報を読出、これをテキストボ
ックス404に表示してからステップS532に移行す
る。
In step S525, when the user selects "Modify" or "New" in the combo box 402 for selecting the processing category on the confirmation / inter-process connection registration screen in FIG.
6 and the selected processing category is set to combo box 4
02, and then proceeds to step S527 to determine whether or not new is selected in the processing category, and when new is selected, proceeds to step S528.
The process information is read from the task table, and is displayed in the text box 404, and the process proceeds to step S532.

【0065】また、ステップS527の判定結果が処理
区分で修正が選択されているものであるときには、ステ
ップS529に移行して、確定工程スケジュールテーブ
ルから工程情報を読込み、これをテキストボックス40
4に表示してからステップS530に移行し、工程の追
加・削除があるか否かを判定し、工程の追加・削除があ
るときにはステップS532に移行し、工程の追加・削
除がないときには項目修正入力を行ってから後述するス
テップS538に移行する。
If the result of the determination in step S527 is that the correction has been selected in the processing category, the flow shifts to step S529 to read the process information from the fixed process schedule table and enter it in the text box 40.
4, the process proceeds to step S530, and it is determined whether or not there is a process addition / deletion. If there is a process addition / deletion, the process proceeds to step S532, and if there is no process addition / deletion, the item is corrected. After the input, the process proceeds to step S538 described below.

【0066】ステップS532では、図23の確定・工
程間繋がり登録画面の通過順付与ボタン405を選択す
ることにより、ステップS533に移行して、製作する
部材の優先順位、作業工程の工程順により、製作部材毎
に通過順位を編集したり、製作部材内で通過順の入れ替
えを行う通過順編集処理を行ってからステップS534
に移行する。
In step S 532, by selecting the pass-through button 405 on the confirmation / inter-process connection registration screen in FIG. 23, the flow shifts to step S 533, where the priority of the members to be manufactured and the process order of the work process are determined. Step S534 is performed after the passage order is edited for editing the passage order for each production member or changing the passage order within the production member.
Move to

【0067】ここで、通過順編集処理は、図22に示す
ように、先ず、ステップS551で組部材番号を昇順に
ソートすると共に、各組部材グループ内の工程順を昇順
にソートする。次いで、ステップS552に移行して、
ソート結果を昇順に一つづつ読込み、次いでステップS
553に移行して、読込んだ工程が“部材加工手切断”
であるか否かを判定し、“部材加工手切断”であるとき
にはステップS554に移行して、通過順の発番を保留
してから前記ステップS552に戻り、“部材加工手切
断”ではないときにはステップS555に移行する。
Here, in the pass order editing processing, as shown in FIG. 22, first, in step S551, the assembly member numbers are sorted in ascending order, and the process order in each assembly member group is sorted in ascending order. Next, the process proceeds to step S552,
Read the sorted results one by one in ascending order, then step S
553, and the read process is “member processing hand cutting”
Is determined, the process proceeds to step S554 if it is "member processing hand cutting", and returns to the step S552 after suspending the numbering in the passing order. If it is not "member processing hand cutting", The process moves to step S555.

【0068】このステップS555では、読込んだ工程
が“部材加工ベーダ”であるか否かを判定し、“部材加
工ベーダ”であるときには前記ステップS554に移行
し、“部材加工ベーダ”でないときにはステップS55
6に移行して、読込んだ工程が“部材加工曲げ”である
か否かを判定し、“部材加工曲げ”であるときには前記
ステップS554に移行し、“部材加工曲げ”でないと
きにはステップS557に移行する。
In this step S555, it is determined whether or not the read process is a "member processing beader". If the read process is a "member processing bader", the flow shifts to the step S554. S55
6 to determine whether the read process is “member bending” or not. If “member bending”, the process proceeds to step S554. Otherwise, the process proceeds to step S557. Transition.

【0069】このステップS557では、発番保留の工
程が存在するか否かを判定し、発番保留の工程がないと
きにはステップS558に移行して、連続した通過順を
発番してからステップS559に移行して、全ての工程
に対して発番完了したか否かを判定し、発番が完了して
いないときには前記ステップS552に戻る。また、前
記ステップS557の判定結果が発番保留の工程がある
ものであるときには、ステップS560に移行して、機
械加工の“機械加工MAM”、“機械加工NC罫書”、
“機械加工NC切断”、“機械加工SCOM”、“機械
加工BV”、“機械加工手孔明”及び“機械加工孔計
測”の全ての通過順の発番が完了しているか否かを判定
し、完了していないときには前記ステップS558に移
行し、完了したときには、ステップS561に移行し
て、発番保留の工程を“部材加工手切断”、“部材加工
ベーダ”及び“部材加工曲げ”の順番で通過順を発番し
てから前記ステップS559に移行する。
In this step S557, it is determined whether or not there is a number-pending process, and if there is no number-pending process, the flow shifts to step S558 to generate a continuous passing order and then proceeds to step S559. Then, it is determined whether or not the numbering has been completed for all the processes. If the numbering has not been completed, the process returns to step S552. If the result of the determination in step S557 is that there is a process of suspending a number, the process proceeds to step S560, where "machining MAM", "machining NC score",
It is determined whether or not the numbering of all the passing orders of “Machining NC cutting”, “Machining SCOM”, “Machining BV”, “Machining hand drilling” and “Machining hole measurement” has been completed. If not completed, the process proceeds to step S558, and if completed, the process proceeds to step S561, and the process of numbering suspension is performed in the order of “member processing hand cutting”, “member processing bader”, and “member processing bending”. , And the process proceeds to step S559.

【0070】さらに、ステップS559の判定結果が全
ての工程について発番を完了したものであるときにはス
テップS562に移行して、図24に示すように、溶接
工程が連続する場合に、先工程の歪取工程を遅らせて次
工程の歪取工程と連続させる通過順入換えが必要である
か否かを判定し、通過順入換えが必要である場合には、
ステップS563に移行して通過順を入換えてから通過
順編集処理を終了して図21のステップS534に移行
する。
If the result of the determination in step S559 is that the numbering has been completed for all the steps, the flow shifts to step S562, and as shown in FIG. Determine whether it is necessary to change the passing order to delay the taking process and continue with the distortion removing process of the next process, and if the changing of the passing order is necessary,
The process proceeds to step S563 to change the order of passage, and then ends the passage order editing process and proceeds to step S534 in FIG.

【0071】この通過順編集処理では、先ず、タスクテ
ーブルの組部材データを、組部材番号順で且つ工程順に
ソートすることにより、図26に示すように、主桁フラ
ンジ、主桁ウェブ、主桁横リブ等の組部材毎に、工程順
に並べたソートデータを形成し、このソートデータを昇
順に順次読出しながら、通過順を発番する。このとき、
主桁フランジには、“部材加工曲げ”、“部材加工ベー
ダ”及び“部材加工手切断”が“機械加工MAM”、
“機械加工NC罫書”、“機械加工NC切断”及び“機
械加工SCOM”の前に存在することから、“部材加工
曲げ”、“部材加工ベーダ”及び“部材加工手切断”の
発番が保留されて、“機械加工MAM”、“機械加工N
C罫書”、“機械加工NC切断”及び“機械加工SCO
M”の発番が先に行われ、これらの発番が完了した時点
で“部材加工手切断”、“部材加工ベーダ”及び“部材
加工曲げ”の順で通過発番が行われることにより、図2
7に示すように、“機械加工MAM”、“機械加工NC
罫書”、“機械加工NC切断”及び“機械加工SCO
M”が通過順22〜25となり、“部材加工手切断”、
“部材加工ベーダ”及び“部材加工曲げ”が通過順26
〜28に設定され、実際の工程に合わせた通過順を設定
することかできる。
In this pass order editing process, first, the assembly member data of the task table is sorted in the order of the assembly member number and in the order of the processes, so that the main girder flange, main girder web, main girder, as shown in FIG. Sort data arranged in the process order is formed for each of the assembled members such as the horizontal ribs, and the passing order is numbered while sequentially reading the sorted data in ascending order. At this time,
On the main girder flange, “Material processing bending”, “Material processing beader” and “Material processing hand cutting” are “Machining MAM”
Since there are "Machining NC scribing", "Machining NC cutting" and "Machining SCOM", the numbers of "Material bending", "Material bader" and "Material cutting" are reserved. "Machining MAM", "Machining N
"C-scribing", "Machining NC cutting" and "Machining SCO"
The numbering of "M" is performed first, and when these numbers are completed, the passing numbering is performed in the order of "member processing hand cutting", "member processing bader", and "member processing bending". FIG.
7, "machined MAM", "machined NC"
"Scribing", "Machining NC cutting" and "Machining SCO"
M ”becomes the passing order 22 to 25, and“ member processing hand cutting ”
The “member processing beader” and “member processing bending” are passed in the order of 26.
~ 28, and the passing order can be set according to the actual process.

【0072】図21に戻って、ステップS534では、
図23の確定・工程間繋がり登録画面の工程連結ボタン
406が選択されたときに、ステップS535に移行し
て、工程間繋がり編集処理を行う。この工程間繋がり編
集処理は、図25に示すように、先ず、ステップS57
1で、“設計”、“材料手配”、“原寸処理”、“切板
加工”の工程通過順を求めると共に、部品グループ「共
通」の“仕分受入”、“仕分配材”の工程通過順を求め
る事前処理を行う。次いで、ステップS572に移行し
て、前工程順セット処理を行う。この前工程順セット処
理は、“設計”の前工程順にスペースをセットし、“材
料手配”の前工程順に“設計”の工程通過順をセット
し、“原寸処理”の前工程順に“材料手配”の工程通過
順をセットし、さらに“切板加工”の前工程順に“原寸
処理”の工程通過順をセットする。
Returning to FIG. 21, in step S534,
When the process connection button 406 on the confirmation / inter-process connection registration screen in FIG. 23 is selected, the process shifts to step S535 to perform inter-process connection editing processing. As shown in FIG. 25, this inter-process connection editing process first includes step S57.
In step 1, the process passing order of “design”, “material arrangement”, “actual size processing”, and “cut plate processing” is obtained, and the process passing order of “sorting acceptance” and “distribution material” of the part group “common” is obtained. Is performed in advance. Next, the flow shifts to step S572, where a pre-process order setting process is performed. In this pre-process order setting process, a space is set in the pre-process of “design”, the process passing order of “design” is set in the pre-process of “material arrangement”, and the “material arrangement” is performed in the pre-process of “full size process” Is set, and then the order of the process of “actual size processing” is set in the order of the process before the “cut plate processing”.

【0073】また、部品グループ「共通」の先頭工程の
前工程順に“切板加工”の工程通過順をセットし、部品
グループ「共通」以外の各部品グループの先頭工程の前
工程順の編集を行う。この編集処理は、先頭工程が“仕
分受入”であれば、“切板加工”の工程通過順をセット
し、先頭工程が“仕分配材”であれば、“仕分受入”の
工程通過順をセットし、先頭工程が“仕分受入”“仕分
配材”以外であれば、前記事前処理における部品グルー
プ「共通」の“仕分配材”の工程通過順をセットし、
“仕分配材”の工程が無ければ、“仕分受入”の工程通
過順をセットし、事前処理で“仕分受入”及び“仕分配
材”の工程が無ければ、スペースをセットする。
Also, the process passing order of “cut plate processing” is set in the order of the preceding process of the leading process of the component group “common”, and the order of the preceding process of the leading process of each component group other than the component group “common” is edited. Do. In this editing process, if the leading process is “sorting acceptance”, the process passing order of “cut plate processing” is set. If the leading process is “sorting material”, the process passing order of “sorting receiving” is set. If the first step is other than “sorting reception” and “distribution material”, the process passing order of “distribution material” of the component group “common” in the pre-processing is set,
If there is no "distribution material" process, the order of passing "sorting reception" is set. If there is no "sorting reception" and "distribution material" process in the pre-processing, a space is set.

【0074】このようにして、図23に示すように、共
通グループの前工程が設定される。次いで、各部品グル
ープ毎に2番目以降の工程の前工程順の編集を行う。こ
の編集は、同一部品グループ内で一件前の工程の工程通
過順をセットする。次いで、前工程順の修正処理を行
う。この修正処理は、部品グループ「共通」に“機械加
工孔計測”の工程があれば前工程順をクリアし、部品グ
ループ「共通」に“仮組立”の工程があれば前工程順を
クリアし、各部品グループ毎で、“板継ライン組立”
“板継オフライン組立”の2工程があれば、“板継ライ
ン組立”の前工程順を“板継オフライン組立”の前工程
順にセットする。
In this way, as shown in FIG. 23, the preceding process of the common group is set. Next, editing is performed in the order of steps before the second and subsequent steps for each part group. This editing sets the process passing order of the previous process in the same part group. Next, a correction process is performed in the order of the previous process. This correction process clears the previous process order if there is a “machined hole measurement” process in the component group “common”, and clears the previous process order if there is a “temporary assembly” process in the component group “common”. , "Sheet joint line assembly" for each part group
If there are two processes of “plate splicing off-line assembly”, the pre-process order of “plate splicing line assembling” is set in the order of the pre-process of “plate splicing off-line assembly”.

【0075】次いで、前工程順をセットした工程の連結
タイプ・ラグの編集を行い、連結タイプに同時進行可能
を表す“SS”をセットすると共に、ラグに“1”をセ
ットする。次いで、ステップS573に移行して、集約
工程の工程通過順検索処理を行う。この検索処理は、
“ブロック組立”“仮組立解体”“塗装準備”“出荷ク
レーンOP”の工程通過順を求める。これらの工程は、
部品グループごとで複数件ある場合があるため、部品グ
ループ番号の昇順で検索する。
Next, the connection type / lag of the process in which the previous process order is set is edited, and "SS" indicating simultaneous progress is set in the connection type, and "1" is set in the lag. Next, the process shifts to step S573 to perform a process passage order search process of the aggregation process. This search process
The process passing order of “block assembly”, “temporary assembly disassembly”, “painting preparation”, and “shipping crane OP” is obtained. These steps are
Since there may be multiple cases for each part group, search is performed in ascending order of the part group numbers.

【0076】次いで、ステップS574に移行して、後
工程順2編集処理を行う。この後工程順2編集処理は、
各部品グループの最終工程のステージ名が“ブロック
組”であれば、その最終工程の後工程順2に“仮組立解
体”の工程通過順をセットし、各部品グループの最終工
程のステージ名が“仮組立”であれば、その最終工程の
後工程順2に“塗装準備”の工程通過順をセットし、各
部品グループの最終工程のステージ名が“塗装”であれ
ば、その最終工程の後工程2に“出荷クレーンOP”の
工程通過順をセットする。また、後工程順2の修正処理
としては、各部品グループ毎で“板継ライン溶接”“板
継オフライン溶接”の2工程があれば、同一部品グルー
プ内で、“板継オフライン溶接”の工程通過順を前工程
順としている工程を検索して、その工程の工程通過順を
“板継ライン溶接”の後工程順2にセットする。さら
に、後工程順2をセットした工程の連結タイプ・ラグの
編集を行い、連結タイプに同時スタートを表す“SS”
をセットすると共に、ラグに“1”をセットする。
Then, the flow shifts to step S574, where a post-process order 2 editing process is performed. Subsequent process order 2 editing process
If the stage name of the final process of each component group is “block set”, the process passing order of “temporary assembly disassembly” is set in the process order 2 after the final process, and the stage name of the final process of each component group is If it is “temporary assembly”, set the order of “painting preparation” in the post-process order 2 of the final process, and if the stage name of the final process of each component group is “painting”, In the post-process 2, the order of passing the process of the “shipping crane OP” is set. In addition, as the correction process in the post-process order 2, if there are two processes of “plate splicing line welding” and “plate splicing offline welding” for each component group, the process of “plate splicing offline welding” within the same component group A process in which the passing order is set to the preceding process order is searched, and the process passing order of the process is set to the second process order of “plate joining line welding”. Furthermore, edit the connection type / lag of the process in which the post-process order 2 was set, and set the connection type to "SS" indicating simultaneous start.
Is set, and "1" is set in the lug.

【0077】次いで、ステップS575に移行して、後
工程順1編集処理を行ってから図21のステップS53
6に移行する。この後工程順1編集処理は、部品グルー
プ間で同一工程があれば、部品グループ間の工程間繋が
りを後工程順1に編集する。但し、“仕分受入”“仕分
配材”以外の工程のみ。すなわち、工程順(昇順)、部
品グループ番号(降順)でソートし、同一工程内で2番
目以降の工程の後工程順1に1件前の工程の工程通過順
をセットしてから、後工程順1をセットした工程の連結
タイプ・ラグの編集を行い、連結タイプに終了後処理開
始を表す“FS”をセットすると共に、ラグに“0”を
セットする。
Subsequently, the flow shifts to step S575, where post-process order 1 editing processing is performed, and thereafter, step S53 in FIG.
Move to 6. In the post-process order 1 editing process, if there is the same process between the component groups, the connection between processes between the component groups is edited in the post-process order 1. However, only processes other than “sorting acceptance” and “distribution materials”. That is, the process is sorted by the process order (ascending order) and the component group number (descending order), and the post-process order of the previous process is set to the post-process order 1 of the second and subsequent processes in the same process. The connection type / lag of the process in which the order 1 is set is edited, and “FS” indicating the start of processing after completion is set in the connection type, and “0” is set in the lag.

【0078】次いで、図21のステップS536では、
修正項目があるか否かを判定し、修正項目があるときに
はステップS537に移行して、項目修正入力を行って
からステップS538に移行し、修正項目がないときに
は直接ステップS538に移行する。ステップS538
では、図23の確定工程・工程間繋がり登録画面におけ
る更新ボタン408が選択されたときにステップS53
9に移行して、作成された工程計画データを確定工程ス
ケジュールテーブルに登録する登録処理を行ってから確
定工程における工程順・工程間繋がり登録処理を終了す
る。
Next, in step S536 in FIG.
It is determined whether or not there is a correction item. If there is a correction item, the process proceeds to step S537. After performing item correction input, the process proceeds to step S538. If there is no correction item, the process directly proceeds to step S538. Step S538
Then, when the update button 408 on the confirmation step / step connection registration screen of FIG.
Then, the process proceeds to step S9, where the registration process for registering the created process plan data in the fixed process schedule table is performed, and then the process order / inter-process connection registration process in the fixed process is completed.

【0079】また、図19におけるステップS508の
工程計画データ作成処理は、図28に示すように、先
ず、ステップS580で、図29に示す工程計画データ
作成画面を表示してからステップS581に移行する。
この工程計画データ作成画面は、図29に示すように、
物件名を選択するコンボボックス411と、選択された
物件名の橋種名及びモデル名を表示する表示欄412及
び413と、現在の工程間繋がり登録の状況を表示する
表示欄414と、工期を入力するテキストボックス41
5と、工程間繋がりの送信有無を選択するオプションボ
タン416及び増えた工程情報の送信有無を選択するオ
プションボタン417と、工程計画データを作成するフ
ァイルを指定するテキストボックス418〜421と、
作成ボタン422、戻るボタン423とを少なくとも備
えている。
Further, in the process plan data creation processing of step S508 in FIG. 19, as shown in FIG. 28, first, in step S580, the process plan data creation screen shown in FIG. 29 is displayed, and then the process proceeds to step S581. .
As shown in FIG. 29, this process plan data creation screen
A combo box 411 for selecting a property name, display fields 412 and 413 for displaying a bridge type name and a model name of the selected property name, a display field 414 for displaying a current status of connection between processes, and a construction period. Text box 41 to enter
5, an option button 416 for selecting whether or not to transmit the connection between processes, an option button 417 for selecting whether or not to transmit the increased process information, and text boxes 418 to 421 for specifying a file for creating process plan data.
At least a create button 422 and a return button 423 are provided.

【0080】ステップS582では、オプションボタン
416及び417の設定処理を行う。この設定処理は、
スケジュール取込済であるときには繋がり送信無を表す
オプションボタンを選択すると共に、増加工程送信有り
を表すオプションボタンを選択し、逆にスケジュール取
込未であるときには繋がり送信有りを表すオプションボ
タンを選択すると共に、増加工程の工程情報を送信しな
いを表すオプションボタンを選択する。
In step S582, setting processing of option buttons 416 and 417 is performed. This setting process
When the schedule has been imported, the user selects the option button indicating that there is no connection transmission, and at the same time, selects the option button that indicates that the increase process has been transmitted. Conversely, when the schedule has not been imported, the user selects the option button that indicates that connection has been transmitted. At the same time, an option button indicating that the process information of the increase process is not transmitted is selected.

【0081】次いで、ステップS583に移行して、選
択したオプションボタンをロックし、次いで、ステップ
S584に移行して、作成ボタン422が選択されたか
否かを判定し、これが選択されていないときにはステッ
プS585に移行して、戻るボタン423が選択されて
いるか否かを判定し、これが選択されていないときには
前記ステップS584に戻り、戻るボタン423が選択
されているときには工程計画データ作成処理を終了して
図19のステップS500に戻る。
Next, the flow shifts to step S583 to lock the selected option button, and then shifts to step S584 to determine whether or not the create button 422 has been selected. If not, the flow advances to step S585. Then, it is determined whether or not the return button 423 has been selected. If the return button 423 has not been selected, the process returns to the step S584. If the return button 423 has been selected, the process plan data creation processing ends. It returns to step S500 of 19.

【0082】また、ステップS584の判定結果が、作
成ボタン422が選択されているときにはステップS5
86に移行して、確定スケジュールテーブルに該当物件
の工程情報が登録済であるか否かを判定し、これが登録
済であるときにはステップS587に移行して、第1の
工程計画データ作成処理を実行してから工程計画データ
作成処理を終了して図19のステップS500に戻る。
If the result of the determination in step S584 is that the create button 422 has been selected, step S5
Then, the process proceeds to S86, where it is determined whether or not the process information of the corresponding property has been registered in the fixed schedule table. If the process information has been registered, the process proceeds to Step S587 to execute the first process plan data creation process. After that, the process plan data creation process ends, and the process returns to step S500 in FIG.

【0083】ここで、第1の工程計画データ作成処理
は、確定工程スケジュールテーブルに登録されている工
程計画を行う物件の情報を表す計画データ情報と、部
材、作業工程毎にスケジュール期間を決定するための物
量・作業工数と作業工程順番とで構成されるアクティビ
ティ情報を作成する工程手順情報(但し、繋がり送信有
オプションボタンが選択されているときのみ)と、部材
毎の作業工程の工程間繋がり、部材間での同一作業工程
の工程間繋がり及び部材間での集約作業工程の工程間繋
がりを作成する工程手順ネットワーク情報と、個々のア
クティビティの部品情報とを含む工程スケジューラ15
で工程スケジュールを作成するための工程計画データを
例えばCSVファイルに作成する。
Here, the first process plan data creation process determines plan data information representing information on a property for which a process plan is registered in the fixed process schedule table, and a schedule period for each member and work process. Procedure information (however, only when the connection transmission option button is selected) that creates activity information composed of the physical quantity / man-hour and the work process order for the connection between the work processes of each member , A process scheduler 15 including process procedure network information for creating a connection between processes of the same work process among members and a connection between processes of an integrated work process between members, and component information of each activity.
Creates process plan data for creating a process schedule in, for example, a CSV file.

【0084】また、前記ステップS586の判定結果
が、確定工程スケジュールテーブルに登録されていない
ものであるときには、ステップS588に移行して、標
準工程スケジュールテーブルに該当物件の工程情報が登
録済であるか否かを判定し、これが登録済であるときに
はステップS589に移行して、第2の工程計画データ
作成処理を実行してから工程計画データ作成処理を終了
して図19のステップS500に戻る。
If the result of the determination in step S586 is not registered in the fixed process schedule table, the flow shifts to step S588 to determine whether the process information of the article is already registered in the standard process schedule table. It is determined whether or not the process has been registered. If it has been registered, the process proceeds to step S589, where the second process plan data creation process is executed, the process plan data creation process ends, and the process returns to step S500 in FIG.

【0085】ここで、第2の工程計画データ作成処理
は、標準工程スケジュールテーブルに登録されている工
程計画を行う物件の情報を表す計画データ情報と、部
材、作業工程毎にスケジュール期間を決定するための物
量・作業工数と作業工程順番とで構成されるアクティビ
ティ情報を作成する工程手順情報(但し、繋がり送信有
オプションボタンが選択されているときのみ)と、部材
毎の作業工程の工程間繋がり、部材間での同一作業工程
の工程間繋がり及び部材間での集約作業工程の工程間繋
がりを作成する工程手順ネットワーク情報とを含む工程
スケジューラ15で工程スケジュールを作成するための
工程計画データを例えばCSVファイルに作成する。
Here, the second process plan data creation processing determines plan data information representing information on a property for which a process plan is registered in the standard process schedule table, and a schedule period for each member and work process. Procedure information (however, only when the connection transmission option button is selected) that creates activity information composed of the physical quantity / man-hour and the work process order for the connection between the work processes of each member The process schedule data for creating a process schedule by the process scheduler 15 including, for example, the process connection between the processes of the same work process among the members and the process procedure network information for creating the process connection of the integrated work process between the members, Create in CSV file.

【0086】さらに、前記ステップS588の判定結果
が、標準工程スケジュールテーブルに工程情報が登録さ
れていないものであるときには、ステップS590に移
行して、工程繋がり登録なしのメッセージを表示してか
ら工程計画データ作成処理を終了して図19のステップ
S500に戻る。この図19のステップS500〜S5
08の処理、図21、図22、図25及び図28の処理
が工程計画データ作成手段に対応し、図19のステップ
S509及び510の処理が工程計画調整データ作成手
段に対応している。
If the result of the determination in step S588 is that the process information is not registered in the standard process schedule table, the flow shifts to step S590 to display a message indicating that there is no process connection registration, and then displays the process plan. The data creation process ends, and the process returns to step S500 in FIG. Steps S500 to S5 in FIG.
The process 08 and the processes of FIGS. 21, 22, 25, and 28 correspond to the process plan data creation unit, and the processes of steps S509 and S510 in FIG. 19 correspond to the process plan adjustment data creation unit.

【0087】このようにして、工程計画データがガント
チャートを作成する工程管理スケジューラで取り扱い可
能なCSVファイルとして作成されると、このCSVフ
ァイルを工程管理スケジューラ15に読み込ませること
により、この工程管理スケジューラ15でガントチャー
トを作成して工程スケジュールを確定する。そして、確
定した工程スケジュールを格納したCSVファイルを読
込み、確定スケジュールデータに基づいてを確定工程ス
ケジュールテーブル及びタスクテーブルを更新する。
In this way, when the process plan data is created as a CSV file that can be handled by the process management scheduler that creates the Gantt chart, the process management scheduler 15 reads this CSV file, thereby At 15, a Gantt chart is created and the process schedule is determined. Then, a CSV file storing the determined process schedule is read, and the determined process schedule table and the task table are updated based on the determined schedule data.

【0088】更新した確定工程スケジュールテーブル及
びタスクテーブルを参照して工数指示を行って、橋梁の
生産管理を開始する。このように生産管理が開始され
て、橋梁の製作が開始されると、作業実績(進捗率)を
反映させたスケジュール調整を行う。このスケジュール
調整は、図20の工程計画支援メニュー画面で工程計画
調整データ作成ボタン305を選択することにより、ス
テップS510に移行して、工程手順に対しては部材、
作業工程毎にアクティビティ情報即ち物量・作業工数
(生産性で再計算)・進捗率及び作業工程順番の工程手
順及び個々のアクティビティの部品情報でなる工程計画
調整データを作成し、これをCSVファイルとして工程
管理スケジューラに読込ませることにより、スケジュー
ル調整を行う。
The man-hour is instructed with reference to the updated fixed process schedule table and task table, and the production management of the bridge is started. When the production management is started and the production of the bridge is started in this way, the schedule is adjusted to reflect the work results (progress rate). This schedule adjustment is performed by selecting a process plan adjustment data creation button 305 on the process plan support menu screen of FIG.
Process plan adjustment data consisting of activity information, that is, physical quantity, work man-hours (recalculated by productivity), progress rate, process sequence of work process sequence, and component information of each activity is created for each work process, and this is created as a CSV file. The schedule is adjusted by causing the process management scheduler to read the schedule.

【0089】そして、工程間繋がり登録状況ボタン30
7を選択することにより、ステップS514に移行し
て、工程間繋がり登録を行っている物件の一覧を画面表
示させることができ、さらに、工程計画帳票要求メニュ
ーボタン308を選択することにより、ステップS51
6に移行して、物件毎に概略の作業工程を全物件一覧で
表示する図30に示す総括工程表や、指示工数・実績累
積工数・最終予想工数を全物件一覧で表示する図31に
示す製作工数山積表を印刷することができる。
Then, the process connection registration status button 30
By selecting No. 7, the process proceeds to step S514, where a list of properties for which the inter-process connection is registered can be displayed on the screen. Further, by selecting the process plan form request menu button 308, the process proceeds to step S51.
6 and the overall work schedule shown in FIG. 30 for displaying a rough work process for each property in a list of all properties, and in FIG. The manufacturing man-hour pile table can be printed.

【0090】以上のように、上記実施形態によると、設
計が完了する以前では、簡易物量算出システムで橋種に
応じた基本モデルに従って物量データを作成し、この物
量データに基づいて工数管理システムで、工数を算出
し、この工数と物量データとに基づいて工程管理システ
ムで工程計画データを作成し、この工程計画データに基
づいて工程スケジューラで工程スケジュールを確定し、
確定した工程スケジュールを生産管理システムに登録す
ることにより、工程スケジュールを正確に予想すること
ができ、物件を受注するか否かの判断を正確に行うこと
ができる。
As described above, according to the above-described embodiment, before the design is completed, the simple physical quantity calculation system creates physical quantity data according to the basic model corresponding to the bridge type, and the man-hour management system based on the physical quantity data. , Calculate the man-hours, create process plan data in the process management system based on the man-hours and physical quantity data, determine the process schedule in the process scheduler based on the process plan data,
By registering the determined process schedule in the production management system, the process schedule can be accurately predicted, and it can be accurately determined whether or not to receive an order for a property.

【0091】また、橋梁を受注した後に、設計が完了す
ることにより、正確な物量データ決定された時点で、再
度工数管理システムで工数を計算し、工程管理システム
で工程計画データを作成し、これに基づいて工程スケジ
ューラで工程スケジュールを確定することにより、より
正確な工程スケジュールを確定することができ、この確
定された正確な工程スケジュールに基づいて工数指示を
行うことにより、正確な生産管理を行うことができ、さ
らに橋梁の生産が開始された後に実績情報に基づいて予
想工数と実績工数との偏差に基づいて工程スケジュール
を調整することにより、より確実な生産管理を行うこと
ができる。
Further, when the design is completed after receiving the order for the bridge, when the accurate quantity data is determined, the man-hour is calculated again by the man-hour management system, and the process plan data is created by the process management system. A more accurate process schedule can be determined by determining a process schedule with a process scheduler based on the process schedule, and an accurate production management is performed by giving man-hour instructions based on the determined accurate process schedule. Further, after the production of the bridge is started, the process schedule is adjusted based on the deviation between the estimated man-hour and the actual man-hour based on the actual information, so that more reliable production management can be performed.

【0092】なお、上記実施形態においては、橋種モデ
ルが鈑桁、箱桁、鋼床版箱桁の3種類である場合につい
て説明したが、これに限定されるものではなく、他の任
意の橋種のモデルも形成するようにしてもよいことは言
うまでもない。また、上記実施形態においては、鋼橋に
ついて生産管理を行う場合について説明したが、これに
限定されるものではなく、鋼橋とコンクリートとを組み
合わせた合成橋にも本発明を適用することができる。
In the above embodiment, a description has been given of the case where there are three types of bridge types, namely, a plate girder, a box girder, and a steel deck slab box girder. However, the present invention is not limited to this. It goes without saying that seed models may also be formed. Further, in the above embodiment, the case where the production management is performed on the steel bridge is described. However, the present invention is not limited to this, and the present invention can be applied to a composite bridge combining a steel bridge and concrete. .

【0093】さらに、上記実施形態においては、1台の
管理用サーバ21に生産管理システムを設定した場合に
ついて説明したが、これに限定されるものではなく、複
数台のサーバを使用して分散処理するようにしてもよ
い。さらに、上記実施形態においては、橋梁の工程管理
に本発明を適用した場合について説明したが、これに限
定されるものではなく、橋梁以外の建築物、人口地盤、
護岸設備等の大型構造物の工程管理を行う場合にも、本
発明を適用することができる。
Further, in the above embodiment, the case where the production management system is set in one management server 21 has been described. However, the present invention is not limited to this, and the distributed processing is performed by using a plurality of servers. You may make it. Further, in the above embodiment, the case where the present invention is applied to the process management of the bridge has been described. However, the present invention is not limited to this, and the building other than the bridge, the artificial ground,
The present invention can also be applied to the case where the process management of large structures such as revetment facilities is performed.

【0094】[0094]

【発明の効果】以上説明したように、請求項1及び3に
係る発明によれば、橋梁等の構造物を構成する最小単位
部材及びこの最小単位部材を組み合わせた組合せ部材の
作成に必要とする部材データ及び処理工程データを生産
管理データベースに登録することにより、この生産管理
データベースを参照して部材データと処理工程データと
から工程順及び工程間つながりを設定して工程計画デー
タを作成し、これを工程管理手段に送出することによ
り、工程管理に必要なガントチャート等の工程管理スケ
ジュールを作成するようにしたので、工程管理手段に入
力する工程順・工程間繋がり等を登録した工程計画デー
タを自動的に作成することができ、工程スケジュールの
作成を容易に行うことができるという効果が得られる。
As described above, according to the first and third aspects of the present invention, it is necessary to produce a minimum unit member constituting a structure such as a bridge and a combination member combining the minimum unit members. By registering the member data and the process data in the production management database, the process sequence and the connection between the processes are set from the member data and the process data with reference to the production management database, and the process plan data is created. Is sent to the process management means, so that a process management schedule such as a Gantt chart necessary for the process management is created. It is possible to automatically create the process schedule, and it is possible to easily create a process schedule.

【0095】また、請求項2及び4に係る発明によれ
ば、請求項1又は3に係る発明の効果に加えて、工程管
理手段で工程管理を行っているときに、工程管理スケジ
ュールと実際の進捗状況とに基づいて工程管理スケジュ
ールを調整することにより、進捗状況に応じた最適な工
程管理スケジュールを作成することができるという効果
が得られる。
According to the second and fourth aspects of the present invention, in addition to the effect of the first or third aspect of the present invention, when the process management means performs the process management, the process management schedule and the actual By adjusting the process management schedule based on the progress status, it is possible to obtain an effect that an optimal process management schedule according to the progress status can be created.

【0096】さらに、請求項5又は6に係る発明によれ
ば、記憶媒体に工程管理に必要とする所定手順を実行す
るためのプログラムがコンピュータ読み取り可能に記憶
されているので、携帯が容易であり、この記憶媒体に記
憶されているプログラムをコンピュータにインストール
するか又はコンピュータで読み取ることにより、構造物
の工程管理を容易に行うことができるという効果が得ら
れる。
Further, according to the fifth or sixth aspect of the present invention, since the program for executing the predetermined procedure required for the process management is stored in the storage medium in a computer-readable manner, it is easy to carry. By installing the program stored in the storage medium in the computer or reading the program by the computer, it is possible to easily perform the process control of the structure.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明を適用し得る橋梁製作現場を示す概略構
成図である。
FIG. 1 is a schematic configuration diagram showing a bridge manufacturing site to which the present invention can be applied.

【図2】ステージ方式を採用した橋梁の生産工程を示す
説明図である。
FIG. 2 is an explanatory diagram showing a production process of a bridge employing a stage method.

【図3】生産管理システムの構成を示すシステム構成図
である。
FIG. 3 is a system configuration diagram showing a configuration of a production management system.

【図4】生産管理システムのハードウェアを示すブロッ
ク図である。
FIG. 4 is a block diagram showing hardware of the production management system.

【図5】ブロック物量算出モデルを示す説明図である。FIG. 5 is an explanatory diagram showing a block physical quantity calculation model.

【図6】部材物量算出モデルを示す説明図である。FIG. 6 is an explanatory diagram showing a member physical quantity calculation model.

【図7】生産管理データベースを示す説明図である。FIG. 7 is an explanatory diagram showing a production management database.

【図8】生産管理システムの処理手順の一例を示すフロ
ーチャートである。
FIG. 8 is a flowchart illustrating an example of a processing procedure of the production management system.

【図9】生産管理システム初期画面を示す説明図であ
る。
FIG. 9 is an explanatory diagram showing a production management system initial screen.

【図10】工数計算モデルの登録及び更新処理手順の一
例を示すフローチャートである。
FIG. 10 is a flowchart illustrating an example of a procedure for registering and updating a man-hour calculation model.

【図11】組部材登録画面を示す説明図である。FIG. 11 is an explanatory diagram showing an assembly member registration screen.

【図12】工数計算パラメータ登録画面を示す説明図で
ある。
FIG. 12 is an explanatory diagram showing a man-hour calculation parameter registration screen.

【図13】工数計算式登録画面を示す説明図である。FIG. 13 is an explanatory diagram showing a man-hour calculation formula registration screen.

【図14】工数パラメータの一例を示す説明図である。FIG. 14 is an explanatory diagram illustrating an example of man-hour parameters.

【図15】工数パラメータ演算処理手順の一例を示すフ
ローチャートである。
FIG. 15 is a flowchart illustrating an example of a man-hour parameter calculation processing procedure.

【図16】物量表の一例を示す説明図である。FIG. 16 is an explanatory diagram showing an example of a physical quantity table.

【図17】工程計画表の一例を示す説明図である。FIG. 17 is an explanatory diagram showing an example of a process plan table.

【図18】工程管理手順を示す説明図である。FIG. 18 is an explanatory diagram showing a process management procedure.

【図19】工程管理処理手順の一例を示すフローチャー
トである。
FIG. 19 is a flowchart illustrating an example of a process management processing procedure.

【図20】工程計画支援メニューを示す説明図である。FIG. 20 is an explanatory diagram showing a process plan support menu.

【図21】工程間繋がり登録処理を示すフローチャート
である。
FIG. 21 is a flowchart showing a process connection registration process.

【図22】図21の通過順編集処理手順の一例を示すフ
ローチャートである。
FIG. 22 is a flowchart illustrating an example of a pass order editing process procedure of FIG. 21;

【図23】確定工程・工程間繋がり登録画面を示す説明
図である。
FIG. 23 is an explanatory view showing a registration step / step connection registration screen.

【図24】通過順の入れ替え処理を示す説明図である。FIG. 24 is an explanatory diagram showing a process of changing the order of passage.

【図25】図21の工程間繋がり編集処理手順の一例を
示すフローチャートである。
FIG. 25 is a flowchart illustrating an example of an inter-process connection editing process procedure of FIG. 21;

【図26】組部材を工程順にソートした結果を示す説明
図である。
FIG. 26 is an explanatory view showing the result of sorting the assembled members in the order of steps.

【図27】組部材を通過順に設定した結果を示す説明図
である。
FIG. 27 is an explanatory diagram showing the result of setting the assembly members in the order of passage.

【図28】図19の工程計画データ作成処理手順の一例
を示すフローチャートである。
FIG. 28 is a flowchart illustrating an example of a process plan data creation processing procedure of FIG. 19;

【図29】工程計画データ作成画面を示す説明図であ
る。
FIG. 29 is an explanatory diagram showing a process plan data creation screen.

【図30】総括工程表の一例を示す説明図である。FIG. 30 is an explanatory diagram showing an example of a general process chart.

【図31】製作工数山積表を示す説明図である。FIG. 31 is an explanatory view showing a manufacturing man-hour pile table.

【符号の説明】[Explanation of symbols]

2 部材仕分ヤード 3 フランジパネルライン 4 ウェブパネルライン 5 部材加工ヤード 6 屋外組立場 11 簡易物量算出システム 12 生産管理システム 13 工数管理システム 14 自動原寸システム 15 工程スケジューラ 16 生産制御健評価システム 21 管理用サーバ LAN ローカルエリアネットワーク PCF パーソナルコンピュータ PCO パーソナルコンピュータ PR プリンタ 2 Member sorting yard 3 Flange panel line 4 Web panel line 5 Member processing yard 6 Outdoor assembly site 11 Simple quantity calculation system 12 Production management system 13 Man-hour management system 14 Automatic full-scale system 15 Process scheduler 16 Production control health evaluation system 21 Management server LAN Local area network PCF Personal computer PCO Personal computer PR Printer

フロントページの続き (72)発明者 山切 清一郎 岡山県倉敷市水島川崎通1丁目(番地な し) 川鉄情報システム株式会社西日本事 業所内 (72)発明者 原田 成美 岡山県倉敷市水島川崎通1丁目(番地な し) 川鉄情報システム株式会社西日本事 業所内 (72)発明者 若山 紘一郎 兵庫県加古郡播磨町新島1番地 川崎製鉄 株式会社播磨工場内 (72)発明者 守屋 弘司 兵庫県加古郡播磨町新島1番地 川崎製鉄 株式会社播磨工場内 Fターム(参考) 2D059 GG61 5B075 KK07 KK13 KK33 KK38 ND03 ND20 ND23 PP03 PP13 PP30 PQ02 UU21 UU22 Continued on the front page (72) Inventor Seiichiro Yamagiri 1-chome, Mizushima-Kawasaki-dori, Kurashiki-shi, Okayama Pref. Chome (without address) Kawatetsu Information System Co., Ltd. West Japan Office (72) Inventor Koichiro Wakayama 1st Harima, Harima-cho, Kako-gun, Hyogo Kawasaki Steel Harima Plant (72) Inventor Hiroshi Moriya, Harima, Kako-gun, Hyogo No. 1, Niijimacho Kawasaki Steel Harima Factory Co., Ltd. F-term (reference) 2D059 GG61 5B075 KK07 KK13 KK33 KK38 ND03 ND20 ND23 PP03 PP13 PP30 PQ02 UU21 UU22

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 構造物を製作する際の工程管理スケジュ
ールを作成する工程管理手段を使用した構造物の工程管
理方法において、少なくとも前記構造物を構成する最小
単位部材及び当該最小単位部材を組み合わせた組合せ部
材の作成に必要とする部材データ及び処理工程データを
生産管理データベースに登録するステップと、前記生産
管理データベースに登録された前記部材データ及び処理
工程データに基づいて工程順及び工程間つながりを設定
して工程計画データを作成し、これを前記工程管理手段
に送出するステップとを備えていることを特徴とする構
造物の工程管理方法。
In a structure process management method using a process management means for creating a process management schedule for manufacturing a structure, at least a minimum unit member constituting the structure and the minimum unit member are combined. Registering member data and processing process data required for creating a combined member in a production management database, and setting a process order and a connection between processes based on the member data and processing process data registered in the production management database Creating process plan data and sending the process plan data to the process management means.
【請求項2】 構造物を製作する際の工程管理スケジュ
ールを作成する工程管理手段を使用した構造物の工程管
理方法において、少なくとも前記構造物を構成する最小
単位部材及び当該最小単位部材を組み合わせた組合せ部
材の作成に必要とする部材データ及び処理工程データを
生産管理データベースに登録するステップと、前記生産
管理データベースに登録された前記部材データ及び処理
工程データに基づいて工程順及び工程間つながりを設定
して工程計画データを作成し、これを前記工程管理手段
に送出するステップと、前記工程管理手段で作成された
工程管理スケジュールと実際の進捗状況とに基づいて当
該工程管理スケジュールを調整するステップとを備えて
いることを特徴とする構造物の工程管理方法。
2. A process management method for a structure using a process management means for creating a process management schedule for manufacturing a structure, wherein at least a minimum unit member constituting the structure and the minimum unit member are combined. Registering member data and processing process data required for creating a combined member in a production management database, and setting a process order and a connection between processes based on the member data and processing process data registered in the production management database Creating the process plan data and sending it to the process management means, and adjusting the process management schedule based on the process management schedule and the actual progress created by the process management means. A process control method for a structure, comprising:
【請求項3】 構造物を製作する際の工程管理スケジュ
ールを作成する工程管理手段を備えた構造物の工程管理
装置において、前記構造物を構成する最小単位部材及び
当該最小単位部材を組み合わせた組合せ部材の作成に必
要とする必要情報を登録した部品テーブルと、該部品テ
ーブルに基づいて個々の最小単位部材及び組合せ部材に
ついて処理工程からみた処理加工量を登録し、作業指示
の単位となるタスクテーブルとを少なくとも備えた生産
管理データベースと、該生産管理データベースのタスク
テーブルを参照して工程順及び工程間つながりを登録し
て工程計画データを作成し、当該工程管理計画データを
前記工程管理手段に送出する工程計画データ作成手段と
を少なくとも備えていることを特徴とする構造物の工程
管理装置。
3. A process management apparatus for a structure, comprising a process management means for creating a process management schedule for manufacturing a structure, wherein a minimum unit member constituting the structure and a combination of the minimum unit members are combined. A part table in which necessary information necessary for creating members is registered, and a processing table in which processing amounts of individual minimum unit members and combination members as viewed from processing steps are registered based on the part table, and which is a unit of a work instruction. A production management database having at least the following, and registering the process order and the connection between processes with reference to the task table of the production management database to create process plan data, and sending the process management plan data to the process management means. A process management device for a structure, at least comprising:
【請求項4】 構造物を製作する際の工程管理スケジュ
ールを作成する工程管理手段を備えた構造物の工程管理
装置において、前記構造物を構成する最小単位部材及び
当該最小単位部材を組み合わせた組合せ部材の作成に必
要とする必要情報を登録した部品テーブルと、該部品テ
ーブルに基づいて個々の最小単位部材及び組合せ部材に
ついて処理工程からみた処理加工量を登録し、作業指示
の単位となるタスクテーブルとを少なくとも備えた生産
管理データベースと、該生産管理データベースのタスク
テーブルを参照して工程順及び工程間つながりを登録し
て工程計画データを作成し、当該工程管理計画データを
前記工程管理手段に送出する工程計画データ作成手段
と、前記工程管理手段で設定された工程の進捗状態を検
出する進捗状態検出手段と、前記工程管理手段で確定さ
れた工程管理スケジュールと前記進捗状態検出手段で検
出した進捗状態とに基づいて工程管理調整データを作成
し、当該工程計画調整データを前記工程管理手段に送出
する工程計画調整データ作成手段とを少なくとも備えた
ことを特徴とする構造物の工程管理装置。
4. A process management apparatus for a structure including a process management means for creating a process management schedule for manufacturing a structure, wherein a minimum unit member constituting the structure and a combination of the minimum unit members are combined. A part table in which necessary information necessary for creating members is registered, and a processing table in which processing amounts of individual minimum unit members and combination members as viewed from processing steps are registered based on the part table, and which is a unit of a work instruction. A production management database having at least the following, and registering a process order and a connection between processes with reference to a task table of the production management database to create process plan data, and sending the process management plan data to the process management means. A progress plan detecting means for detecting a progress status of the process set by the process managing means. And step management adjustment data is created based on the step, the process management schedule determined by the process management unit, and the progress detected by the progress detection unit, and the process plan adjustment data is sent to the process management unit. A process management apparatus for a structure, comprising at least process schedule adjustment data creation means.
【請求項5】 少なくとも構造物を構成する最小単位部
材及び当該最小単位部材を組み合わせた組合せ部材の作
成に必要とする部材データ及び処理工程データを生産管
理データベースに登録する手順と、前記生産管理データ
ベースに登録された前記部材データ及び処理工程データ
に基づいて工程順及び工程間つながりを設定して工程計
画データを作成し、これを前記工程管理手段に送出する
手順とを実行するためのプログラムをコンピュータ読み
取り可能に記憶したことを特徴とする記憶媒体。
5. A procedure for registering at least a minimum unit member constituting a structure and member data and processing step data necessary for creating a combined member combining said minimum unit member in a production management database, and said production management database. A program for setting a process order and a connection between processes based on the member data and the process process data registered in the computer, creating process plan data, and sending the process plan data to the process management means. A storage medium characterized by being readablely stored.
【請求項6】 少なくとも構造物を構成する最小単位部
材及び当該最小単位部材を組み合わせた組合せ部材の作
成に必要とする部材データ及び処理工程データを生産管
理データベースに登録する手順と、前記生産管理データ
ベースに登録された前記部材データ及び処理工程データ
に基づいて工程順及び工程間つながりを設定して工程計
画データを作成し、これを前記工程管理手段に送出する
手順と、前記工程管理手段で作成された工程管理スケジ
ュールと実際の進捗状況とに基づいて当該工程管理スケ
ジュールを調整する手順とを実行するためのプログラム
をコンピュータ読み取り可能に記憶したことを特徴とす
る記憶媒体。
6. A procedure for registering at least a minimum unit member constituting a structure and member data and processing step data required for creating a combination member combining said minimum unit member in a production management database, and said production management database. A procedure for setting process order and connection between processes based on the member data and process process data registered in the process, creating process plan data, and transmitting the process plan data to the process management unit, and a process created by the process management unit. A program for executing a procedure for adjusting the process management schedule based on the process management schedule and the actual progress status, wherein the program is stored in a computer-readable manner.
JP2001023156A 2001-01-31 2001-01-31 Method and device for managing work progress of structure and recording medium used for these method and device Pending JP2002227413A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001023156A JP2002227413A (en) 2001-01-31 2001-01-31 Method and device for managing work progress of structure and recording medium used for these method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001023156A JP2002227413A (en) 2001-01-31 2001-01-31 Method and device for managing work progress of structure and recording medium used for these method and device

Publications (1)

Publication Number Publication Date
JP2002227413A true JP2002227413A (en) 2002-08-14

Family

ID=18888473

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001023156A Pending JP2002227413A (en) 2001-01-31 2001-01-31 Method and device for managing work progress of structure and recording medium used for these method and device

Country Status (1)

Country Link
JP (1) JP2002227413A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004355526A (en) * 2003-05-30 2004-12-16 Toshiba Corp Job navigation system and its method
CN111622110A (en) * 2020-04-24 2020-09-04 中交第二航务工程局有限公司 Intelligent installation and construction method for prefabricated bent cap based on three-dimensional measurement lofting technology

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004355526A (en) * 2003-05-30 2004-12-16 Toshiba Corp Job navigation system and its method
CN111622110A (en) * 2020-04-24 2020-09-04 中交第二航务工程局有限公司 Intelligent installation and construction method for prefabricated bent cap based on three-dimensional measurement lofting technology
CN111622110B (en) * 2020-04-24 2021-10-29 中交第二航务工程局有限公司 Intelligent installation and construction method for prefabricated bent cap based on three-dimensional measurement lofting technology

Similar Documents

Publication Publication Date Title
Fischer et al. Characteristics of design-relevant constructability knowledge
Kaner et al. Case studies of BIM adoption for precast concrete design by mid-sized structural engineering firms
Luth et al. Lessons from using BIM to increase design-construction integration
Noorzai et al. Lessons learned on selecting the best mass housing method based on performance evaluation criteria in Iran
Firoz et al. Modelling concept of sustainable steel building by Tekla Software
Mark et al. Industrializing precast productions: Adaptive modularized constructions made in a flux
Chen et al. Integration of information and automation technologies in bridge engineering and management: Extending the state of the art
Ko et al. Making formwork design lean
EP1915657A2 (en) System and process for the detailed design and production of reinforcement for buildings
Sanders An analysis of factors affecting labor productivity in masonry construction
Ginigaddara et al. Industry 4.0 driven emerging skills of offsite construction: a multi-case study-based analysis
JP2002227413A (en) Method and device for managing work progress of structure and recording medium used for these method and device
JP3756416B2 (en) Simple quantity setting method of structure, simple quantity setting device, and storage medium used therefor
Sacks Evaluation of economic impact of three-dimensional modeling in precast concrete engineering
JP3756417B2 (en) Structure production management equipment
JPH09166957A (en) Device for constructing three-dimensional model for design and construction of bridge
JPH11237000A (en) Pipeline construction planning administrative system
Tamang A Complete Modelling Guide for Precast Element Wall Using Tekla Structures
JP2002229626A (en) Production controlling method and device for structure and storage medium to be used for the same
Dindorf et al. Challenges of robotic technology in sustainable construction practice
JP2613016B2 (en) Construction method of 3D model for bridge design and fabrication
Bergsten Industrialised building systems: Vertical extension of existing buildings by use of light gauge steel framing systems and 4D CAD tools
Li Process automation for flexible residential wall panel manufacturing
Ruby Constructability of structural steel buildings
Zaiman et al. Comparison Analysis for Implementation Time of Column Formwork Using Three Formwork Methods in a Building Project at Bandung Province

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060328

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060529

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20060829