JP2002207851A - Construction plan preparation method - Google Patents

Construction plan preparation method

Info

Publication number
JP2002207851A
JP2002207851A JP2001004745A JP2001004745A JP2002207851A JP 2002207851 A JP2002207851 A JP 2002207851A JP 2001004745 A JP2001004745 A JP 2001004745A JP 2001004745 A JP2001004745 A JP 2001004745A JP 2002207851 A JP2002207851 A JP 2002207851A
Authority
JP
Japan
Prior art keywords
work
construction
construction plan
character string
plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001004745A
Other languages
Japanese (ja)
Inventor
Shigeo Higuchi
重雄 樋口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Plant Technologies Ltd
Original Assignee
Hitachi Plant Technologies Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Plant Technologies Ltd filed Critical Hitachi Plant Technologies Ltd
Priority to JP2001004745A priority Critical patent/JP2002207851A/en
Publication of JP2002207851A publication Critical patent/JP2002207851A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction plan preparation method by which an optimum construction plan is prepared for the handling physical amount of distributed work sites. SOLUTION: In the case of applying this method to the tollgate building construction of an expressway, respectively intrinsic work numbers are attached to construction works to be executed at respective tollgates and data regarding work occupation types engaged in the work of the work number and the data regarding the number of workers are related. Respectively intrinsic construction plane candidate numbers are attached to construction plans composed of a number string for which the work numbers are cited in the order of work schedules and construction plan candidate data are constructed. Construction plan candidates are extracted on the basis of the construction plan candidate data of the respective tollgates and the combination of the construction plan candidates is expressed by a character string. For the character string, construction period shortening and a resource leveling degree (the leveling of the maximum number of the workers required per day) are taken into consideration and the character string is functionally optimized by utilizing a genetic algorithm.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、工事計画作成方法
に係り、特にコンピュータを用い、予め設定された工事
現場の取扱い物量に対して、最適な工事計画を作成する
ことができる工事計画作成方法及び装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction plan creation method, and more particularly to a construction plan creation method capable of creating an optimum construction plan for a predetermined work volume at a construction site using a computer. And an apparatus.

【0002】[0002]

【従来の技術】建設工事を能率良く、かつ円滑に進める
ためには、工事の作業手順が大変重要であり各種の工事
計画方法が提案されている。代表的な手法の一つとし
て、関根智明著「 PERT・CPM 」(日科技連) に記載されて
いるPERT(Performance Evaluation and Review Techniq
ue、 CPM(Critical Path Method)がある。これらの方法
は、まず各作業の順序関係を示す工程ネットワークを作
成する。次に、各作業での取扱い物量(t) 、標準的な単
位作業当たりの作業工数(工数/t) (他に単位長さ、作
業点数など) や作業環境の影響(作業効率)を考慮し、
下記の(1)式により各作業の作業工数を求める。更
に、作業員の1 日平均従事者数を考慮することで各作業
の作業日数を(2)式より求める。
2. Description of the Related Art In order to efficiently and smoothly carry out construction work, the work procedure of the construction is very important, and various construction planning methods have been proposed. One of the typical methods is the PERT (Performance Evaluation and Review Techniq) described in `` PERT / CPM '' by Tomoaki Sekine (Nikkagiren).
ue and CPM (Critical Path Method). In these methods, first, a process network indicating the order relation of each operation is created. Next, the amount of work to be handled in each work (t), the standard man-hours per unit work (man-hours / t) (other than unit length, number of work points, etc.) and the effect of work environment (work efficiency) are considered. ,
Work man-hours for each work are obtained by the following equation (1). Further, the number of working days for each work is obtained from equation (2) by taking into account the average number of workers per day.

【0003】[0003]

【数1】 (Equation 1)

【0004】[0004]

【数2】 このようにして求めた作業日数を、作業順序を表す工程
ネットワークの作業に当てはめて工事計画を作成し、そ
の後で要求される工期内で作業が終了するように、個々
の作業期間や作業従事者数などの作業情報を修正し、工
事計画を作成する。
(Equation 2) The work days obtained in this way are applied to the work of the process network representing the work sequence to create a construction plan, and then the individual work periods and workers are set so that the work is completed within the required work period. Modify work information such as numbers and create a construction plan.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、上記の
PERTやCPM を用いた方法では、計画作成時に各作業の順
序関係を明確にしておく必要がある。しかし、どちらの
作業を実施しても許されるとき、例えば作業場所が分散
している高速道路上の料金所などの建設工事では、料金
所内での作業順序関係を明確にできるが、料金所間での
作業順序を明確に決めることは容易ではない。このよう
なときには、予め複数個の作業順序関係を想定し、それ
ぞれの工事計画を作成した後で最適な工事計画を選定す
る必要があった。しかし、このような作業順序関係が不
明な点が多いと作成する工事計画の量が多くなり、特に
その数が多いときには計画を実用的な時間内に作成でき
ないという問題点があった。
SUMMARY OF THE INVENTION
In the method using PERT and CPM, it is necessary to clarify the order relation of each work at the time of planning. However, when it is permissible to carry out either of these works, for example, in the construction of a tollgate on a highway where the workplaces are dispersed, it is possible to clarify the work sequence within the tollgate, It is not easy to clearly determine the order of work in the office. In such a case, it is necessary to presuppose a plurality of work order relationships, create a respective work plan, and then select an optimum work plan. However, when there are many points where the work order relation is unknown, the amount of the construction plan to be created increases, and especially when the number is large, the plan cannot be created within a practical time.

【0006】本発明はこのような事情に鑑みてなされた
もので、前記従来技術の不都合を解消し、 予め設定され
た工事現場の取扱い物量に対して、最適な工事計画を作
成することができる工事計画作成方法を提供することを
目的とする。
The present invention has been made in view of such circumstances, and can solve the above-described disadvantages of the prior art, and can create an optimum construction plan for a predetermined work volume at a construction site. The purpose is to provide a construction plan creation method.

【0007】[0007]

【課題を解決するための手段】本発明は、前記目的を達
成するために、分散した場所にある複数の作業場所から
成る工事現場での全体の工事計画を作成する方法におい
て、各作業場所で実施される作業にそれぞれ固有の作業
番号を付与し、各作業番号の作業に従事する作業職種に
関するデータ及び従事作業員数に関するデータをその作
業番号に関連付け、各作業場所に関して前記作業番号を
作業日程順に羅列して成る番号列を作成して工事計画を
行い、各番号列が示す工事計画に固有の工事計画候補番
号を付けて工事計画候補データを構築し、計画対象の全
作業場所の工事計画を作成する上で、各作業場所の前記
工事計画候補データの中から一つの工事計画候補番号を
抽出し、この抽出された工事計画候補番号を作業場所順
に結合させて文字列を作成し、前記文字列が示す工事計
画を評価し、その評価に基づいて最適な計画を作成する
ことを特徴としている。
SUMMARY OF THE INVENTION In order to achieve the above object, the present invention provides a method for preparing an overall construction plan at a construction site comprising a plurality of work sites at distributed locations. A unique work number is assigned to each work to be performed, data relating to the type of work engaged in the work of each work number and data relating to the number of engaged workers are associated with the work number, and the work numbers for each work place are arranged in the order of work schedule. A construction plan is created by creating a series of numbers, and the construction plan candidate data is constructed by attaching a unique construction plan candidate number to the construction plan indicated by each number series. In the creation, one construction plan candidate number is extracted from the construction plan candidate data of each work place, and the extracted construction plan candidate numbers are combined in the order of the work place to form a character. Create and evaluate the construction plan of the string shown, it is characterized in that to create an optimal plan based on the evaluation.

【0008】本発明によれば、文字列の作成と評価を繰
り返すことにより、評価の高い文字列を機能的に探索し
て文字列を最適化し、最適化された文字列が示す工事計
画を最適な工事計画として提示することができる。
According to the present invention, by repeatedly creating and evaluating a character string, a character string having a high evaluation is functionally searched to optimize the character string, and a construction plan indicated by the optimized character string is optimized. It can be presented as a simple construction plan.

【0009】本発明の一態様によれば、前記文字列が示
す工事計画の最適性の評価は、職種毎の1日に従事する
作業員の最大数や工期などの情報を基に、1日当たりに
要する作業員の最大数の平準化と工期短縮の観点から行
われることを特徴としている。この場合、前記文字列で
示される工事計画の最適化手法として遺伝的アルゴリズ
ムを用いることができる。
According to one aspect of the present invention, the evaluation of the optimality of the construction plan indicated by the character string is performed on a daily basis based on information such as the maximum number of workers engaged in one day for each job type and the construction period. It is performed from the viewpoint of equalization of the maximum number of workers required and the shortening of the construction period. In this case, a genetic algorithm can be used as a method for optimizing the construction plan indicated by the character string.

【0010】[0010]

【発明の実施の形態】以下、 添付図面に従って本発明に
係る工場計画作成方法の好ましい実施の形態について詳
説する。図1は本発明の実施形態に係る工事計画作成装
置のブロック図である。図1において工事計画作成装置
10は、 各種処理を行うコンピュータ20と、このコン
ピュータ20に接続した出力部40と入力部50とから
構成してある。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A preferred embodiment of a factory plan creation method according to the present invention will be described below in detail with reference to the accompanying drawings. FIG. 1 is a block diagram of a construction plan creation device according to an embodiment of the present invention. In FIG. 1, the construction plan creation device 10 includes a computer 20 for performing various processes, and an output unit 40 and an input unit 50 connected to the computer 20.

【0011】コンピュータ20は、工事計画を作成する
ための処理部21を備えており、 この処理部21に入力
データ処理部22、データ抽出部23、データ処理部2
4、工事計画作成部25と入力部50から入力されたデ
ータを取り込んだり、処理部21が処理したデータを出
力部40に送る入出力制御部30が設けてある。また、
コンピュータ20は、 処理部21に接続した作業データ
格納部26、作業ネットワークデータ格納部27及び演
算結果格納部28を有している。
The computer 20 includes a processing unit 21 for creating a construction plan. The processing unit 21 includes an input data processing unit 22, a data extraction unit 23, and a data processing unit 2.
4. An input / output control unit 30 is provided for taking in data input from the construction plan creation unit 25 and the input unit 50 and sending the data processed by the processing unit 21 to the output unit 40. Also,
The computer 20 has a work data storage unit 26, a work network data storage unit 27, and a calculation result storage unit 28 connected to the processing unit 21.

【0012】作業データ格納部26は、 各料金所での作
業に関するデータ、作業量、作業効率、従事する職種、
更に演算により求めた作業日数などのデータを記憶して
いる。作業ネットワークデータ格納部27は、 各料金所
の工事計画候補がネットワークの形で格納されている。
また、演算結果格納部28には、各料金所の工事計画の
工事計画候補を基に作成された全体の工事計画のデータ
を格納している。
The work data storage unit 26 stores data on work at each tollgate, work amount, work efficiency, occupation type,
Further, data such as the number of working days obtained by calculation is stored. The work network data storage unit 27 stores construction plan candidates for each tollgate in the form of a network.
The calculation result storage unit 28 stores data of the entire construction plan created based on the construction plan candidates for the construction plan of each tollgate.

【0013】一方、出力部40は、処理部21が作成し
た工事計画などを表示するための表示装置41、それら
を印刷物等として出力するプリンタ42から構成してあ
る。
On the other hand, the output section 40 is composed of a display device 41 for displaying the construction plan and the like created by the processing section 21 and a printer 42 for outputting them as printed matter or the like.

【0014】また、 入力部50は、オペレータが各種の
データを直接入力するためのキーボード51やマウス5
2、コンピュータを起動するためのオペレーションシス
テム、各種アプリケーションソフトやデータなどを格納
するハードディスク53他の計算機システムからデータ
ファイルの形式で入力するためのフロッピー(登録商
標)ディスク駆動装置54、他のコンピュータ等から通
信回線を介してデータを入力するためのモデム55等か
ら構成してある。
The input unit 50 includes a keyboard 51 and a mouse 5 for the operator to directly input various data.
2. An operation system for starting a computer, a hard disk 53 for storing various application software and data, and a floppy (registered trademark) disk drive 54 for inputting data in the form of a data file from another computer system, other computers, etc. And a modem 55 for inputting data through a communication line.

【0015】上記のように構成した工事計画作成装置の
作用は、 次の通りである。
The operation of the construction plan creating apparatus configured as described above is as follows.

【0016】図2に、本発明に基づく工事計画作成の概
略手順を示す。初めに料金所内での工事計画を作成す
る。そのため、 S102で料金所を選択し、そこで行わ
れる作業を割り付ける。料金所で行われる作業の一例を
図3工事計画設定例に示す。図3にはA料金所での作業
を示している。作業は、はつり作業、 型枠作業、 配管作
業からなるものとする。図2のS102で料金所を選択
後、S103で開始作業を設定する。この場合、はつり
作業になるがその開始日を工事開始日以降、乱数を用い
任意の日に設定する。ただし、その作業の最遅開始日よ
りも早い日に設定する。
FIG. 2 shows a schematic procedure for creating a construction plan based on the present invention. First, a construction plan in the tollgate is created. Therefore, a tollgate is selected in S102, and the work performed there is allocated. An example of the work performed at the tollgate is shown in FIG. FIG. 3 shows the work at the toll booth A. The work shall consist of hanging work, formwork work and plumbing work. After selecting a tollgate in S102 of FIG. 2, a start operation is set in S103. In this case, hanging work is performed, but the start date is set to an arbitrary date using a random number after the construction start date. However, set the date earlier than the latest start date of the work.

【0017】次にS104の後続作業設定で型枠作業を
設定する。その際、 先行作業の終了日以降で乱数を用い
任意に設定するが、S105で余裕日数が存在するか否
か、すなわち最遅開始日以前に開始日がなるか判断す
る。最遅開始日以降であれば再度設定する。このS10
4からS106までを全作業が終了するまで実施する。
ここで作成した料金所の工事計画を工事計画侯補と呼
ぶ。
Next, form work is set in the subsequent work setting in S104. At this time, the random number is set arbitrarily using the random number after the end date of the preceding work. In S105, it is determined whether or not there is a surplus number of days, that is, whether the start date is before the latest start date. If it is after the latest start date, set it again. This S10
Steps 4 to S106 are performed until all operations are completed.
The construction plan of the tollgate created here is called the construction plan candidate.

【0018】その後、S107で全料金所の工事計画が
作成されるまでS102からS107までの作業を続け
る。なお、 本例では、このような工事計画をS108に
おいてS102〜S107を複数回繰返して工事計画侯
補作成し、 詳細を後述するS109の遺伝的アルゴリズ
ム操作により、S110の最適工事計画抽出により工事
計画を作成する。そのため、作成した工事計画を文字列
で表現する。
Thereafter, the operations from S102 to S107 are continued until the construction plans for all tollgates are created in S107. In this example, such a construction plan is repeatedly created in S108 through S102 to S107 in S108, and a candidate for the construction plan is created. Create Therefore, the created construction plan is represented by a character string.

【0019】各作業には図3に示したように作業名称を
作業番号で表現し、 かつ作業番号に作業職種、1日に従
事する作業員数のデータを持たせる。文字列の並びは、
工事開始日からの日付順に、 作業がないか、 はつり作業
か、 型枠作業か、 配管作業かのいずれが行われるかを表
現している。図3の例では工事開始日から6日間は作業
がなく、 その後はつり作業を3日実施し、 3日作業がな
い日が続いた後型枠作業を3日実施し、 更に作業のない
日が6日続いた後配管作業を3日行い、 工事終了日まで
作業がないことを表している。
As shown in FIG. 3, each work has a work name represented by a work number, and the work number has data on the type of work type and the number of workers engaged in one day. The sequence of strings is
It expresses whether there is no work, whether it is hanging work, formwork work, or plumbing work in chronological order from the construction start date. In the example of Fig. 3, there is no work for 6 days from the construction start date, after that, the hanging work is performed for 3 days, the formwork work is performed for 3 days after the 3 days without work, and the days with no work are further After six days, plumbing was performed for three days, indicating that there was no work until the end of construction.

【0020】次に、文字列を最適化する手法について説
明する。文字列を最適化する手法として、 遺伝的アルゴ
リズム(GA)が利用される。遺伝的アルゴリズムと
は、 与えられた問題を文字列に置き換え、 その文字列を
生物の染色体とみなし、 多数の染色体から評価の高いも
のを選び出し(選択、 淘汰)、選ばれた染色体を分断し
つなぎ合わせ(交叉)、或いは染色体の一部分を他の遺伝
子と取り替える(突然変異)という操作を行いながら全
く新しい染色体を作成し、 更にそれらを評価して、 選択
するという操作を繰り返し行うことにより、 帰納的に最
適な染色体を見つけ出すという手法である。
Next, a method for optimizing a character string will be described. A genetic algorithm (GA) is used as a method for optimizing a character string. A genetic algorithm is a method that replaces a given problem with a character string, regards the character string as a chromosome of an organism, selects high-value ones from a large number of chromosomes (selection, selection), and disconnects the selected chromosomes. By performing an operation of combining (crossover) or replacing a part of the chromosome with another gene (mutation), creating an entirely new chromosome, and then evaluating and selecting them, iterative operations are repeated. It is a method to find the optimal chromosome for

【0021】本実施の形態では、 料金所の工事計画に対
応付けられた工事計画候補番号の組み合わせから成る文
字列が作成されているので、 この遺伝的アルゴリズムの
手法が適用でき、 最適な工事計画の組み合わせが帰納的
に導かれる。図4に工事計画侯補を文字列化するデータ
構造を示す。すなわち、料金所番号を遺伝子座とし、工
事計画候補番号を遺伝子とすることにより、 各料金所の
工事計画の組み合わせを表す染色体(文字列)が形成さ
れる。料金所番号毎に作成された工事計画候補番号
(A,B,C…)は対立遺伝子に相当し、 これら対立遺
伝子のうちの一つが対応する遺伝子座に置かれる。
In the present embodiment, since a character string composed of a combination of construction plan candidate numbers associated with a construction plan at a tollgate is created, the method of this genetic algorithm can be applied, and an optimal construction plan can be applied. Is derived inductively. FIG. 4 shows a data structure for converting a construction plan candidate into a character string. That is, a chromosome (character string) representing a combination of construction plans of each tollgate is formed by setting the tollgate number as a locus and the construction plan candidate number as a gene. The construction plan candidate numbers (A, B, C...) Created for each tollgate number correspond to alleles, and one of these alleles is placed at the corresponding locus.

【0022】次に、 遺伝的アルゴリズムにおいて染色体
を評価するための目的関数を作成する。評価の項目とし
ては、 工期と、 資源平準化度、 ここでは職種別の1日の
最大従事者数を考慮する。具体的には、工期が短いほう
が全体のコストが少なく、かつ作業員の1日の最大従事
者数が小さく平準化されているほうが作業員のコストが
少ない。これには、 各料金所の工事計画候補のデータを
日付順に集計し評価する。
Next, an objective function for evaluating a chromosome in a genetic algorithm is created. Evaluation items include the construction period and the level of resource leveling. In this case, the maximum number of workers per day by job type is considered. Specifically, the shorter the construction period, the lower the overall cost, and the lower the number of workers per day, the smaller the number of workers per day, and the lower the cost of the workers. For this purpose, the data of the construction plan candidates at each tollgate are compiled and evaluated in chronological order.

【0023】図5に工事計画の文字を評価する方法を示
した。各料金所の工事計画候補を抽出し料金所順に並べ
たのを(1)工事計画候補と示したが、 各料金所のデー
タを職種別に、 日付順に集計し文字列化したものを
(2)工事計画侯補の評価方法として示している。この
ように表示方法を変更することで職種別の1日に従事す
る最大人員数や工期をデータに基づいて求める。
FIG. 5 shows a method for evaluating the characters of the construction plan. The construction plan candidates for each tollgate were extracted and arranged in tollgate order. (1) The construction plan candidates were shown as (1) Construction plan candidates. It is shown as an evaluation method of the candidate for the construction plan. By changing the display method in this way, the maximum number of employees and the work period to be engaged in one day for each job type are obtained based on the data.

【0024】こうして求めた工期と職種別の1日の最大
従事者数を加算して遺伝的アルゴリズム(GA)の評価
方法とした。すなわち、これらの加算値が小さいものほ
ど良好な染色体(文字列)として評価する。そして、 良
い文字列を複数抽出して(選択、 淘汰)、 その文字列を
途中で分断して他の文字列と入れ替えたり(交叉)文字
列中の文字(遺伝子)を他の文字に書き換えたりしなが
ら(突然変異)、新しい文字列を作成し、 その新しい文字
列を再評価することを繰り返しながら、 さらによい文字
列を作成していくことによって、 帰納的に評価値が最小
の文字列を見つける。なお、 遺伝的アルゴリズムの処理
に用いられるGAオペレータに関しては、 一般的なSele
ction(選択、 淘汰) 、Crossover(交叉) 、 Mutation(突
然変異)を利用した。すなわち、 Selection( 選択、 淘
汰) 処理では、 世代の最小値が1つ保存され、 残りはル
ーレットルールが採用される。Crossover(交叉) 処理で
は、 遺伝子数が固定であり、 遺伝子座による差別は生じ
ないため、 通常の一点交叉が行われる。また、 Mutation
( 突然変異) 処理では、 その世代で選択されている遺伝
子以外の遺伝子を確率的に発生させるようにしている。
The thus-calculated construction period and the maximum number of workers per day for each job type are added to obtain a genetic algorithm (GA) evaluation method. In other words, the smaller the sum is, the better the chromosome (character string) is evaluated. Then, it extracts several good character strings (selection and selection), cuts the character string in the middle and replaces it with another character string (crossover), and replaces the character (gene) in the character string with another character While (mutating), a new string is created, and the new string is reevaluated repeatedly to create a better string. locate. The GA operator used for the genetic algorithm processing is a general Sele
ction (selection, selection), Crossover (crossover), Mutation (mutation) was used. In other words, in the selection processing, one minimum value of generations is stored, and the rest of the generation uses roulette rules. In the crossover process, the number of genes is fixed and no discrimination by loci occurs, so normal single-point crossover is performed. Also, Mutation
In the (mutation) process, a gene other than the gene selected in that generation is stochastically generated.

【0025】かかる方法を用いて遺伝的アルゴリズムを
動作させた結果、 評価値の最小の一つの文字列を求める
ことができ、 その文字列を工事計画に置き換えることに
より、 最適な工事計画を行うことができる。
As a result of operating the genetic algorithm using such a method, it is possible to obtain one character string having the smallest evaluation value, and to replace the character string with a construction plan to perform an optimal construction plan. Can be.

【0026】上述した実施形態によれば、各料金所の工
事計画データに基づいて工事計画候補を抽出して、それ
ら工事計画候補の組合せを文字列で表現し、その文字列
を工期、資源平準化度に着目し、機能的に文字列を最適
化するようにしている。これにより、最適な工事計画の
組合せを短時間で効率的に導き出すことができる。
According to the above-mentioned embodiment, construction plan candidates are extracted based on the construction plan data of each tollgate, combinations of these construction plan candidates are represented by character strings, and the character strings are represented by the construction period and the resource level. Focusing on the degree of conversion, the character string is optimized functionally. As a result, an optimal combination of construction plans can be efficiently derived in a short time.

【0027】本発明の工事計画作成方法をコンピュータ
によって実施するためのプログラムをCD−ROMその
他の記録媒体に格納して第三者に提供したり、インター
ネットなどのネットワークを介してダウンロードできる
ようにしてもよい。
A program for executing the construction plan creation method of the present invention by a computer is stored on a CD-ROM or other recording medium and provided to a third party, or can be downloaded via a network such as the Internet. Is also good.

【0028】[0028]

【発明の効果】以上述べたように本発明に係る工事計画
作成方法によれば、作業場所が分散した高速道路上の料
金所間の作業順序関係が明確でない場合でも、 工期や職
種別の1日の最大従事者数を考慮した、 すなわち資源平
準化を考慮した最適かつ理論的な工事計画を短時間で自
動的に計画することができる。
As described above, according to the construction plan creation method according to the present invention, even if the work order relation between tollgates on expressways with dispersed work places is not clear, it is possible to obtain one work period and one job type. An optimal and theoretical construction plan that takes into account the maximum number of workers per day, that is, resource leveling, can be planned automatically in a short time.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明を実施する工事計画作成装置の一例を示
すブロック図である。
FIG. 1 is a block diagram illustrating an example of a construction plan creation device that implements the present invention.

【図2】本例の工事計画作成手順を示すフローチャート
である。
FIG. 2 is a flowchart showing a construction plan creation procedure of the present embodiment.

【図3】本実施形態における工事計画設定例を示す図表
である。
FIG. 3 is a chart showing a construction plan setting example according to the embodiment;

【図4】本実施形態における工事計画候補を文字列化す
るデータ構造例を示す図である。
FIG. 4 is a diagram showing an example of a data structure for converting a construction plan candidate into a character string in the embodiment.

【図5】工事計画の文字を評価する方法の例を示す図表
である。
FIG. 5 is a chart showing an example of a method for evaluating characters of a construction plan.

【符号の説明】[Explanation of symbols]

10…工事計画作成装置、20…コンピュータ、21…
処理部、22…入力データ処理部、23…データ抽出
部、24…データ処理部、25…工事計画作成部、26
…作業データ格納部、27…作業ネットワークデータ格
納部、28…演算結果格納部、30…入出力制御部、4
0…出力部、50…入力部
10: Construction plan creation device, 20: Computer, 21 ...
Processing unit, 22 input data processing unit, 23 data extraction unit, 24 data processing unit, 25 construction plan creation unit, 26
... Work data storage unit, 27 ... Work network data storage unit, 28 ... Calculation result storage unit, 30 ... Input / output control unit, 4
0: output unit, 50: input unit

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 分散した場所にある複数の作業場所から
成る工事現場での全体の工事計画を作成する方法におい
て、 各作業場所で実施される作業にそれぞれ固有の作業番号
を付与し、各作業番号の作業に従事する作業職種に関す
るデータ及び従事作業員数に関するデータをその作業番
号に関連付け、各作業場所に関して前記作業番号を作業
日程順に羅列して成る番号列を作成して工事計画を行
い、各番号列が示す工事計画に固有の工事計画候補番号
を付けて工事計画候補データを構築し、計画対象の全作
業場所の工事計画を作成する上で、各作業場所の前記工
事計画候補データの中から一つの工事計画候補番号を抽
出し、この抽出された工事計画候補番号を作業場所順に
結合させて文字列を作成し、前記文字列が示す工事計画
を評価し、その評価に基づいて最適な計画を作成するこ
とを特徴とする工事計画作成方法。
In a method for creating an overall construction plan at a construction site comprising a plurality of work sites at distributed locations, each work performed at each work site is assigned a unique work number. The data relating to the type of work engaged in the work of the number and the data relating to the number of engaged workers are associated with the work number, and a work sequence is created by creating a number sequence in which the work numbers are arranged in order of work schedule for each work place. When constructing construction plan candidate data by assigning a unique construction plan candidate number to the construction plan indicated by the number sequence and creating a construction plan for all work sites to be planned, the construction plan candidate data of each work site Extract one construction plan candidate number from, create a character string by combining the extracted construction plan candidate number in the order of work place, evaluate the construction plan indicated by the character string, Construction planning method which is characterized in that to create an optimal plan based on the value.
【請求項2】 前記文字列が示す工事計画の最適性の評
価は、職種毎の1日に従事する作業員の最大数や工期な
どの情報を基に、1日当たりに要する作業員の最大数の
平準化と工期短縮の観点から行われることを特徴とする
請求項1に記載の工事計画作成方法。
2. The evaluation of the optimality of the construction plan indicated by the character string is based on information such as the maximum number of workers engaged in one day for each job type and the construction period, and the maximum number of workers required per day. The method according to claim 1, wherein the method is performed from the viewpoint of leveling and shortening a construction period.
【請求項3】 前記文字列で示される工事計画の最適化
手法として遺伝的アルゴリズムを用いることを特徴とす
る請求項2に記載の工事計画作成方法。
3. The construction plan creation method according to claim 2, wherein a genetic algorithm is used as a method for optimizing the construction plan indicated by the character string.
JP2001004745A 2001-01-12 2001-01-12 Construction plan preparation method Pending JP2002207851A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001004745A JP2002207851A (en) 2001-01-12 2001-01-12 Construction plan preparation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001004745A JP2002207851A (en) 2001-01-12 2001-01-12 Construction plan preparation method

Publications (1)

Publication Number Publication Date
JP2002207851A true JP2002207851A (en) 2002-07-26

Family

ID=18872891

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001004745A Pending JP2002207851A (en) 2001-01-12 2001-01-12 Construction plan preparation method

Country Status (1)

Country Link
JP (1) JP2002207851A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7372504B1 (en) * 2023-01-13 2023-11-01 株式会社アラヤ Systems, methods, and programs for deriving schedules forming part of a construction plan
WO2024010137A1 (en) * 2022-07-08 2024-01-11 Samsung Engineering Co.,Ltd. Method and system for automatic establishment of optimal schedule for construction project

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024010137A1 (en) * 2022-07-08 2024-01-11 Samsung Engineering Co.,Ltd. Method and system for automatic establishment of optimal schedule for construction project
JP7372504B1 (en) * 2023-01-13 2023-11-01 株式会社アラヤ Systems, methods, and programs for deriving schedules forming part of a construction plan

Similar Documents

Publication Publication Date Title
Chaudhry et al. A research survey: review of flexible job shop scheduling techniques
Ponnambalam et al. Comparative evaluation of genetic algorithms for job-shop scheduling
EP1359529A1 (en) Computer-implemented product development planning method
CN104484582B (en) The biological information project automatic analysis method and system realized by modularization selection
CN109543372A (en) Service authority data processing method, device, computer equipment and storage medium
Damci et al. Impacts of different objective functions on resource leveling in construction projects: A case study
JP2779736B2 (en) Optimization device and process plan creation device using the same
US7930679B2 (en) Source-code-generation supporting method and computer product
JP2006277060A (en) Schedule preparation support system, schedule preparation method and program
US20030050065A1 (en) Contingency planning in a scheduling process
Lin et al. Optimizing the schedule of dispatching earthmoving trucks through genetic algorithms and simulation
CN115700639A (en) Intelligent production scheduling method, device, equipment and storage medium
CN113793135A (en) Project process management method and system
JP4113469B2 (en) Business process management method and business process management program
JP2002207851A (en) Construction plan preparation method
CN113033990A (en) Intelligent designer matching method
JP2007102435A (en) Production scheduling device, production scheduling method, and program
Chen et al. Automatic manpower allocation for public construction projects using a rough set enhanced neural network
JP2002244716A (en) Line capacity evaluation system
CN114971922A (en) Damage assessment method, device and equipment for vehicle survey and storage medium
Sapiecha et al. An application of developmental genetic programming for automatic creation of supervisors of multi-task real-time object-oriented systems
Cochran et al. Generating daily production plans for complex manufacturing facilities using multi-objective genetic algorithms
JP2005190174A (en) Server and program for sales work assisting system, and sales assisting apparatus and program
Corne et al. Evolutionary optimisation of methodist preaching timetables
Qiu et al. A new hybrid variable-length GA and PSO algorithm in continuous facility location problem with capacity and service level constraints