JP2001336142A - Executed condition control method for ground improvement and executed condition control system - Google Patents

Executed condition control method for ground improvement and executed condition control system

Info

Publication number
JP2001336142A
JP2001336142A JP2000156106A JP2000156106A JP2001336142A JP 2001336142 A JP2001336142 A JP 2001336142A JP 2000156106 A JP2000156106 A JP 2000156106A JP 2000156106 A JP2000156106 A JP 2000156106A JP 2001336142 A JP2001336142 A JP 2001336142A
Authority
JP
Japan
Prior art keywords
construction
data
stirring
amount
slurry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000156106A
Other languages
Japanese (ja)
Inventor
Yuji Kazehari
裕二 風張
Kazuyoshi Ota
和善 太田
Atsushi Murayama
篤史 村山
Toshiaki Yamane
利明 山根
Shinichi Hibino
信一 日比野
Setsu Horikiri
節 堀切
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tenox Corp
Original Assignee
Tenox Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tenox Corp filed Critical Tenox Corp
Priority to JP2000156106A priority Critical patent/JP2001336142A/en
Publication of JP2001336142A publication Critical patent/JP2001336142A/en
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

PROBLEM TO BE SOLVED: To enable a site representative to collectively perform centralized management for execution control, quality control, labor control, etc., accurately and rapidly in a construction site where a ground improving way using the deep mixing stabilization method is executed. SOLUTION: At least a work quantity of an agitation head, the number of agitation, and a hardener added volume at every excavation unit length are obtained by a control device 2 in a construction site and the data are stored in a memory media as execution data. Digital image data of an uncured core sample obtained by an early quality confirmation system 3 at site and compression strength data obtained by compression tests after the uncured core samples are accelerated to cure are obtained and these execution data, image data, compression strength data are investigated by the site representative to check the execution condition and perform the execution control, quality control, labor control, etc.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地盤中に地盤改良
固化材等と水を混合して製作したセメントミルクを注入
し、地盤とセメントミルクを攪拌混合することにより地
盤を固結する深層混合処理工法に適用される地盤改良の
施工状態管理方法および施工状態管理システムに関する
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a deep mixing method in which cement milk produced by mixing ground improvement solidification material and the like with water is poured into the ground, and the ground and cement milk are stirred and mixed to consolidate the ground. The present invention relates to a construction state management method and a construction state management system for ground improvement applied to a treatment method.

【0002】[0002]

【従来の技術】深層混合処理工法には地盤改良機が用い
られており、この地盤改良機は、図16に示すように、
地盤改良機11の前面に略鉛直に設置されたリーダマス
ト30のガイドレールに攪拌軸31の駆動部32を昇降
自在に設けると共に、ワイヤーやチェーン33等で吊り
保持し、攪拌軸31の先端部に掘削翼や攪拌翼を有する
攪拌ヘッド34を設けて構成されている。施工に際して
は、駆動部32のモータにより攪拌軸31および攪拌ヘ
ッド34を回転させて掘進し、攪拌ヘッドにより地盤と
セメントミルクを攪拌混合する。プラントで製作された
セメントミルクは、掘進時もしくは引上げ時、あるいは
掘進時と引上げ時の両方において攪拌軸の中空部を通し
て、攪拌ヘッドより地盤に吐出される。
2. Description of the Related Art A ground improvement machine is used in the deep mixing treatment method. As shown in FIG.
A drive part 32 of a stirring shaft 31 is provided on a guide rail of a leader mast 30 installed substantially vertically on the front surface of the ground improvement machine 11 so as to be able to move up and down, and is suspended and held by a wire, a chain 33, or the like. Is provided with a stirring head 34 having excavating blades and stirring blades. At the time of construction, the stirring shaft 31 and the stirring head 34 are rotated by the motor of the drive unit 32 to excavate, and the ground and the cement milk are stirred and mixed by the stirring head. The cement milk produced in the plant is discharged from the stirring head to the ground through the hollow portion of the stirring shaft during excavation or pulling, or both during excavation and pulling.

【0003】このような深層混合処理工法における施工
管理は、従来、攪拌軸31の掘進・引上げ速度V(深度
D/時間t)と、スラリー(セメントミルク)の吐出量
Qと、攪拌軸31の回転数Rを個々に測定し、それぞれ
の検出量が所定の管理値に収まるように行われている。
また、必要改良深さは、事前の土質調査により得られた
平面方向および鉛直方向に変化する地層構成および地盤
の硬さなどの土質調査結果を基に判断して決めていた。
Conventionally, the construction management in such a deep-mixing method is performed by excavating / pulling speed V (depth D / time t) of the stirring shaft 31, discharge amount Q of the slurry (cement milk), The number of rotations R is measured individually, and each detection amount is set so as to fall within a predetermined management value.
The required improvement depth was determined based on the results of soil surveys such as the stratum composition and the hardness of the ground that changed in the plane direction and the vertical direction obtained by the preliminary soil survey.

【0004】[0004]

【発明が解決しようとする課題】従来の攪拌軸の昇降速
度V・スラリー吐出量Q・攪拌軸の回転数Rを個々に調
整する方法では、管理項目が多いため管理が難しく、
昇降速度Vとスラリー吐出量Qの2項目を同時に制御
して地盤土への固化材添加量を確保し、昇降速度Vと回
転数Rの2項目を同時に制御して混合度を確保する必要
があり、煩雑でオペレーターの労力が大きく、良好な
施工管理が行われているかの判断を即座に行うことがで
きないなどの問題があった。
In the conventional method of individually adjusting the ascending and descending speed V of the stirring shaft, the slurry discharge amount Q, and the rotation speed R of the stirring shaft, the management is difficult because of many management items.
It is necessary to simultaneously control the two items of the elevating speed V and the slurry discharge amount Q to secure the amount of the solidifying material added to the ground soil, and to simultaneously control the two items of the elevating speed V and the number of revolutions R to ensure the degree of mixing. There was a problem that it was complicated, the labor of the operator was large, and it was not possible to immediately judge whether good construction management was performed.

【0005】また、設計で決められた深度で必要改良深
さを管理すると、当初予想していなかった地層の変化、
例えば、支持層が傾斜している場合、改良部底面の一部
が支持層に乗り、一部は軟弱地盤中にとどまっている状
態も予想される。鉛直支持力を期待する改良の場合は、
支持力不足が一部の範囲で生じ、上部構造物の不同沈下
につながるという問題があった。
[0005] In addition, when the required improvement depth is managed at the depth determined by the design, the change of the stratum which was not expected at first,
For example, when the support layer is inclined, it is expected that a part of the bottom surface of the improved portion rides on the support layer and a part of the bottom surface stays in the soft ground. In the case of improvement that expects vertical bearing capacity,
There was a problem in that the bearing capacity was insufficient in some areas, leading to uneven settlement of the superstructure.

【0006】このような問題を解決すべく、本出願人
は、管理項目を減らすことで管理が容易となり、また良
好な施工管理が行われているかの判断を瞬時に正確に行
うことができ、さらに、当初予想していなかった地層の
変化に対しても対応することができる地盤改良工法の管
理方法および地盤改良機の管理装置を既に出願している
(特願平11−25145号)。
[0006] In order to solve such a problem, the applicant has made it easy to manage by reducing the number of management items, and can instantaneously and accurately judge whether or not good construction management is performed. Further, a management method of a ground improvement method and a management apparatus of a ground improvement machine capable of responding to a change in the stratum that was not expected at the beginning have already been filed (Japanese Patent Application No. 11-25145).

【0007】本発明は、前記管理方法および装置をさら
に発展させたものであり、深層混合処理による地盤改良
工法を実施している施工現場の施工管理・品質管理・労
務管理等を施工現場管理者が一括して集中管理すること
ができ、さらにこれらの管理を正確にかつ迅速に実施す
ることのできる地盤改良の施工状態管理方法および施工
状態管理システムを提供することにある。
[0007] The present invention is a further development of the above-mentioned management method and apparatus, and performs construction management, quality management, labor management and the like of a construction site where a ground improvement method by deep mixing processing is implemented. It is an object of the present invention to provide a construction state management method and a construction state management system for ground improvement that can perform centralized management collectively and can perform these managements accurately and quickly.

【0008】[0008]

【課題を解決するための手段】本発明の請求項1は、少
なくとも掘削翼と攪拌翼を装備した攪拌ヘッドを先端に
使用して地盤中を掘進しつつ、固化材等と水を混合した
スラリーを吐出し、前記攪拌翼で掘削土とスラリーを攪
拌混合することにより地盤改良を行う際の施工状態の管
理方法であって、施工現場で少なくとも単位掘進長毎の
攪拌ヘッドの仕事量と単位掘進長毎の攪拌回数と単位掘
進長毎の固化材添加量またはスラリー吐出量を求める施
工データ取得工程と、前記施工データから施工現場管理
者が施工状態を把握する工程よりなることを特徴とする
地盤改良の施工状態管理方法である。前記施工状態の把
握の対象としては、施工データを用いて行う施工時間確
認等の労務管理あるいはソイルセメントコラム合否確認
や不良コラム原因調査等の施工管理などの例が挙げられ
る。
According to a first aspect of the present invention, there is provided a slurry in which a solidified material and water are mixed while excavating in the ground by using a stirring head equipped with at least a cutting blade and a stirring blade at a tip. Is a method of managing the construction state when soil improvement is performed by stirring and mixing the excavated soil and slurry with the stirring blade, wherein the work amount of the stirring head and the unit excavation at least for each unit excavation length at the construction site A ground characterized by comprising a construction data acquisition step of obtaining a solidifying material addition amount or a slurry discharge amount for each length of stirring and unit excavation length, and a step of a construction site manager grasping the construction state from the construction data. This is an improved construction state management method. Examples of the object of grasping the construction state include labor management such as construction time confirmation performed using construction data and construction management such as soil cement column pass / fail confirmation and defective column cause investigation.

【0009】本発明の請求項2は、請求項1の施工状態
管理方法において、施工現場で採取した未固化のコア試
料をデジタル画像で記録する工程(デジタルカメラ等を
使用する)を追加し、このコア試料の画像データと施工
データから施工現場管理者が施工状態を把握することを
特徴とする。前記施工状態の把握の対象としては、画像
データを用いて行う土と固化材の混合状態や固化材の盛
り上がり程度を確認する品質管理と、施工データを用い
て行う施工時間確認等の労務管理あるいはソイルセメン
トコラム合否確認や不良コラム原因調査等の施工管理な
どの例が挙げられる。施工データは、施工と同時に施工
現場管理者へ送り(持ち込み、あるいはデータ送信)、
施工完了後に採取した画像データを後から施工現場管理
者へ送る。また、施工データと画像データを一緒にして
施工現場管理者へ送ってもよい。
According to a second aspect of the present invention, there is provided the construction state management method according to the first aspect, further comprising a step of using a digital camera or the like to record an unsolidified core sample collected at the construction site as a digital image, The construction site manager grasps the construction state from the image data of the core sample and the construction data. As the object of grasping the construction state, quality control to confirm the mixed state of soil and solidified material and the degree of swelling of the solidified material performed using image data, and labor management such as construction time confirmation performed using the construction data or Examples include construction management such as soil cement column pass / fail confirmation and defective column cause investigation. The construction data is sent to the construction site manager at the same time as the construction (take-in or data transmission),
The image data collected after the completion of the construction is sent to the construction site manager later. Further, the construction data and the image data may be sent together to the construction site manager.

【0010】本発明の請求項3は、請求項2の施工状態
管理方法において、未固化のコア試料を促進養生して圧
縮強度の測定を行う工程を追加し、この圧縮強度のデー
タと施工データとコア試料の画像データから施工現場管
理者が施工状態を把握することを特徴とする。前記施工
状態の把握の対象としては、圧縮強度のデータを用いて
行う圧縮強度を確認する品質管理と、画像データを用い
て行う土と固化材の混合状態や固化材の盛り上がり程度
を確認する品質管理と、施工データを用いて行う施工時
間確認等の労務管理あるいはソイルセメントコラム合否
確認や不良コラム原因調査等の施工管理などの例が挙げ
られる。圧縮強度データは、施工後、少なくとも1日後
に得られるので、施工データや画像データの後に施工現
場管理者に送る。また、施工データや画像データと一緒
にして施工現場管理者に送ってもよい。
According to a third aspect of the present invention, in the construction state management method of the second aspect, a step of accelerating and curing the unsolidified core sample and measuring the compressive strength is added. And the construction site manager grasps the construction state from the image data of the core sample and the core sample. As an object of grasping the construction state, quality control for confirming compressive strength using data of compressive strength and quality for confirming the mixed state of soil and solidified material and the degree of swelling of solidified material performed using image data Examples include management and labor management such as construction time confirmation using construction data, and construction management such as soil cement column pass / fail confirmation and defective column cause investigation. Since the compression strength data is obtained at least one day after the construction, it is sent to the construction site manager after the construction data and the image data. Further, it may be sent to the construction site manager together with the construction data and the image data.

【0011】本発明の請求項4は、少なくとも掘削翼と
攪拌翼を装備した攪拌ヘッドを先端に使用して地盤中を
掘進しつつ、固化材等と水を混合したスラリーを吐出
し、前記攪拌翼で掘削土とスラリーを攪拌混合すること
により地盤改良を行う際の施工状態の管理システムであ
って、施工現場で少なくとも単位掘進長毎の攪拌ヘッド
の仕事量と単位掘進長毎の攪拌回数と単位掘進長毎の固
化材添加量またはスラリー吐出量からなる施工データを
求めて表示手段に表示できる管理装置と、前記施工デー
タから施工現場管理者が施工状態を把握できる手段を備
えていることを特徴とする地盤改良の施工状態管理シス
テムである。前記施工状態の把握は、請求項1の発明と
同じである。
According to a fourth aspect of the present invention, a slurry in which a solidified material or the like is mixed with water is discharged while digging in the ground using a stirring head equipped with at least a digging blade and a stirring blade at a tip end, and discharging the slurry. It is a construction state management system when performing ground improvement by stirring and mixing excavated soil and slurry with wings, and at least at the construction site, the work amount of the stirring head per unit excavation length and the number of agitation times per unit excavation length A management device capable of obtaining construction data comprising a solidified material addition amount or a slurry discharge amount per unit excavation length and displaying the same on a display means, and having a means for a construction site manager to grasp the construction state from the construction data. It is a construction condition management system for soil improvement. The grasp of the construction state is the same as that of the first aspect.

【0012】本発明の請求項5は、請求項4の施工状態
管理システムにおいて、施工現場で採取した未固化のコ
ア試料をデジタル画像で記録できる手段(デジタルカメ
ラ等)を追加し、このコア試料の画像データと施工デー
タから施工現場管理者が施工状態を把握することを特徴
とする。前記施工状態の把握は、請求項2の発明と同じ
である。
According to a fifth aspect of the present invention, in the construction state management system of the fourth aspect, a means (such as a digital camera) for recording a digital image of an unsolidified core sample collected at the construction site is added. The construction site manager grasps the construction state from the image data and the construction data. The grasp of the construction state is the same as that of the second aspect of the invention.

【0013】本発明の請求項6は、請求項4の施工状態
管理システムにおいて、前記未固化のコア試料を促進養
生して圧縮強度の測定を行うための手段(例えば55°C
温水養生装置と一軸圧縮試験器など)を追加し、この圧
縮強度のデータを施工データとコア試料の画像データか
ら施工現場管理者が施工状態を把握することを特徴とす
る。前記施工状態の把握は、請求項3の発明と同じであ
る。
According to a sixth aspect of the present invention, in the construction state management system according to the fourth aspect, means for accelerating curing of the unsolidified core sample and measuring compressive strength (for example, 55 ° C.)
(A hot water curing device and a uniaxial compression tester, etc.) are added, and the construction site manager grasps the construction state of the compression strength data from the construction data and the image data of the core sample. The grasp of the construction state is the same as that of the third aspect.

【0014】請求項1〜請求項6において、施工データ
は、記憶媒体(ICカード,フロッピー(登録商標)デ
ィスク,CD,CVD等)に記録して、その施工現場の
施工現場管理者に持ち込んでもよいし、有線や無線等に
よる通信システムにより施工現場管理者に直接送信する
ようにしてもよい。
In the first to sixth aspects, the construction data is recorded on a storage medium (IC card, floppy (registered trademark) disk, CD, CVD, or the like) and brought to a construction site manager at the construction site. Alternatively, the information may be directly transmitted to the construction site manager by a wired or wireless communication system.

【0015】施工現場の施工管理システムは、管理装置
と、掘削翼・攪拌翼・共回り防止翼を装備した地盤改良
機と、セメントミルクの製造プラントなどから構成さ
れ、管理装置は、地盤改良機などに設置され、施工デー
タ演算手段・記憶手段・施工データ表示手段・警報出力
手段などを備え、地盤改良機やスラリーのプラントに設
けた検出器などからの測定データ(施工時間・掘削深度
・攪拌軸回転数・スラリー吐出量など)が入力され、さ
らにソイルセメントコラムの番号や改良径等が別途入力
され、これらの入力データに基づいて施工データ演算手
段により施工データ(単位掘進長毎の攪拌ヘッドの仕事
量・単位掘進長毎の攪拌回数・単位掘進長毎の固化材添
加量またはスラリー吐出量など)が算出され、施工デー
タ表示手段により施工データおよび入力データがグラフ
等で表示される。また、施工データ表示手段では、施工
データおよび入力データが時間を遡って再現表示可能と
されている。なお、施工データの固化材添加量はスラリ
ー吐出量でもよい。
The construction management system at the construction site is composed of a management device, a ground improvement machine equipped with excavating wings, stirring blades, and counter-rotating wings, a cement milk production plant, and the like. It is equipped with construction data calculation means, storage means, construction data display means, alarm output means, etc., and measures measurement data (construction time, excavation depth, agitation, etc.) from detectors installed in ground improvement machines and slurry plants. The number of shaft revolutions, slurry discharge volume, etc.) are input, and the soil cement column number and improved diameter are separately input. Based on these input data, execution data is calculated by the execution data calculation means (mixing head for each unit excavation length). Work volume, the number of agitation times per unit excavation length, the amount of solidified material added per unit excavation length or the amount of slurry discharged) are calculated, and the Data and the input data is displayed in a graph or the like. In the construction data display means, the construction data and the input data can be reproduced and displayed retroactively. In addition, the solidification material addition amount of the construction data may be a slurry discharge amount.

【0016】各施工現場の早期品質確認システムは、施
工直後の未だ固まっていないコア試料を地盤改良機を利
用して全長にわたり採取する未固化採取治具と、この採
取された全長のコア試料をデジタル画像で記録するデジ
タルカメラ等から構成され、更には、このコア試料から
作成された供試体を促進養生する促進養生装置(例えば
55°C の温水により約24時間で促進養生する温水促進養
生装置)と、この促進養生後の供試体強度を測定する簡
易一軸圧縮試験器などを含んで構成してもよい。
The early quality check system at each construction site includes an unsolidified sampling jig for collecting an unsolidified core sample immediately after construction over the entire length by using a ground improvement machine, and It is composed of a digital camera or the like that records digital images, and further, an accelerated curing device (eg,
(A warm water accelerated curing device that accelerates and cures with 55 ° C hot water in about 24 hours), and a simple uniaxial compression tester that measures the strength of the specimen after the accelerated curing.

【0017】以上のような構成において、施工管理シス
テムにより、施工現場で得られたソイルセメントコラム
の施工データが施工現場管理者に送られ、施工現場の施
工管理・品質管理・労務管理等を施工現場管理者が一括
して集中管理することができ、管理にかかるコストおよ
び労力を低減することができ、また施工現場に必要な指
示を行うことで良好な地盤改良工を実施することができ
る。さらに、施工管理システム・早期品質管理システム
による施工データ・コア試料の画像データ・場合によっ
てはコア試料の圧縮強度データを用いて管理を行うこと
により、施工現場の施工管理・品質管理・労務管理等を
より正確にかつ迅速に実施することができる。
In the above configuration, the construction management system sends the construction data of the soil cement column obtained at the construction site to the construction site manager, and performs construction management, quality control, labor management, etc. at the construction site. The site manager can perform centralized management in a lump, reduce the cost and labor required for the management, and perform good ground improvement work by giving necessary instructions to the construction site. In addition, by using the construction management system, early quality management system, construction data, core sample image data, and in some cases, compressive strength data of the core sample, management is performed, such as construction management, quality management, and labor management at the construction site. Can be performed more accurately and quickly.

【0018】本発明で用いる管理装置においては、良好
な地盤改良を実現するための次の3つを主要な管理項目
としている。
In the management device used in the present invention, the following three main items for realizing good ground improvement are the main management items.

【0019】(1) 先ず、第1点として、地盤と固化材を
結合させることにより強度増加を図る改良原理から、改
良地盤の強度は地盤中に注入した固化材添加量に比例す
ることが、図13に示すように、実験的に確かめられて
いる。従って、単位掘進長毎の固化材添加量またはスラ
リー吐出量を管理する。例えば、単位掘進長毎の固化材
の添加量としては、逐次、地盤中に投入される固化材添
加量WC [kg/m3 ](地盤土1m3 に投入される固
化材の重量)を管理する。この固化材添加量WCは、セ
メントミルクプラントから地盤中へ吐出されるセメント
ミルクの吐出量Qと、攪拌ヘッドの深度D・速度Vと、
別途測定した水・固化材比W/Cおよび固化材比重等を
用いて求める。即ち、吐出量Qと水・固化材比W/Cお
よび固化材比重等を用いて固化材投入量WC ’を算出
し、この固化材投入量WC ’を固化材が投入された単位
掘進長区間の体積で除して、地盤の単位体積当たりの固
化材添加量WC を得る(後述の式(1)参照)。例えば
所定の単位掘進長区間毎に前記固化材添加量WC と固化
材添加量設定値とを比較して判定を行い、満足しない場
合にはその単位掘進長区間の再施工を促す警報を出力す
る。前述のように不良区間は、再施工が原則である。再
施工は、攪拌ヘッドを回転させながら上方へ引き上げ、
再度セメントミルクを追加吐出させながら掘進すること
により行われる。
(1) First, the first point is that the strength of the improved ground is proportional to the amount of the solidified material added to the ground, based on the improvement principle of increasing the strength by bonding the ground and the solidified material. As shown in FIG. 13, it has been experimentally confirmed. Therefore, the amount of solidified material added or the amount of slurry discharged for each unit excavation length is managed. For example, as the amount of the solidified material added per unit excavation length, the amount of solidified material added W C [kg / m 3 ] (the weight of the solidified material charged into 1 m 3 of ground soil) is sequentially charged into the ground. to manage. The solidification material addition amount W C is determined based on the discharge amount Q of the cement milk discharged from the cement milk plant into the ground, the depth D and speed V of the stirring head,
The water / solidified material ratio W / C and solidified material specific gravity separately measured are used to determine the ratio. In other words, 'it is calculated, and the solidifying material input amount W C' solidifying material input amount W C using a discharge amount Q of water and solidified material ratio W / C and solidifying material specific gravity such units excavation solidified material is charged with by dividing by the volume of the long interval, obtaining a solidifying material amount W C per unit volume of soil (see formula below (1)). For example a judgment by comparing the solidifying material amount W C and solidifying material amount set values for each predetermined unit excavation length sections, if not satisfied outputs an alarm to prompt re-construction of the unit excavation length section I do. As mentioned above, rebuilding is a principle of defective sections. For rebuilding, rotate the stirring head and pull it up,
It is performed by digging while additionally discharging cement milk again.

【0020】なお、得られた固化材添加量WC 、あるい
は攪拌ヘッドの昇降速度Vに基づいて、セメントミルク
吐出ポンプを自動制御し、固化材添加量WC を固化材添
加量設定値に一致させることもできる。即ち、ある区間
で固化材添加量WC が少ないことが判明した場合には、
続く区間でセメントミルクの吐出量Qを増やし、所定の
単位掘進長区間の固化材添加量WC が設定値を満足する
ようにする。昇降速度Vが低下した場合には、吐出量Q
を低下させ、所定の単位掘進長区間の固化材添加量WC
が設定値を満足するようにする。このように攪拌ヘッド
の昇降速度Vに基づいて、セメントミルク吐出ポンプを
調整し、固化材添加量WC を固化材添加量設定値に一致
させる。調整は、オペレータ室の遠隔操作盤などで行う
ことができる。以上のように、瞬間的には吐出量が少し
バラツキがあっても単位掘進長区間毎に所定量が満足さ
れると、この区間では充分に攪拌混合されるため所定の
強度が得られる。
The cement milk discharge pump is automatically controlled based on the obtained solidified material addition amount W C or the elevating speed V of the stirring head, so that the solidified material addition amount W C matches the solidified material addition amount set value. It can also be done. That is, when it is found that the amount of solidified material addition W C is small in a certain section,
Increase the discharge amount Q of cement milk in the subsequent section, solidifying material amount W C of a predetermined unit excavation length interval so as to satisfy the set value. When the elevating speed V decreases, the discharge amount Q
And the added amount of solidified material W C in a predetermined unit excavation length section
Satisfy the set value. Thus, based on the elevating velocity V of the stirring head to adjust the cement milk dispensing pump, to match the solidifying material amount W C in solidifying material amount set value. The adjustment can be performed by a remote control panel or the like in the operator room. As described above, even if there is a slight variation in the discharge amount momentarily, if the predetermined amount is satisfied in each unit excavation length section, a predetermined strength is obtained because sufficient stirring and mixing is performed in this section.

【0021】(2) 第2点として、改良土の品質が均一に
なるためには固化材と地盤を十分に混合することが重要
である。その混合度として、地盤中を回転している攪拌
ヘッドの攪拌回数と、強度ばらつきの指標となる強度の
変動係数(=標準偏差/平均値)との相関を調べた結果
を図14に示す。従って、所定の単位掘進長区間毎の攪
拌回数を管理する。例えば、この攪拌回数N[回/m]
は、速度Vと、攪拌軸の回転数Rと、攪拌ヘッドの羽根
枚数nを用いて求める。即ち、掘進時および引上時に、
ある単位掘進長区間における羽根の合計通過回転数によ
り、単位長さ当たりの攪拌回数Nを得る(後述の式
(3)参照)。例えば所定の単位掘進長区間毎に前記攪
拌回数Nと攪拌回数基準値とを比較して判定を行い、満
足しない場合にはその単位掘進長区間の再施工を促す警
報を出力する。
(2) As a second point, it is important to sufficiently mix the solidified material and the ground in order to make the quality of the improved soil uniform. FIG. 14 shows the result of examining the correlation between the number of agitation of the agitation head rotating in the ground and the coefficient of variation of the intensity (= standard deviation / average value) as an index of the intensity variation. Therefore, the number of times of stirring for each predetermined unit excavation length section is managed. For example, the stirring frequency N [times / m]
Is determined using the speed V, the rotation speed R of the stirring shaft, and the number n of blades of the stirring head. In other words, when excavating and pulling up,
From the total number of rotations of the blades in a unit excavation length section, the number of times of stirring N per unit length is obtained (see the following equation (3)). For example, the agitation frequency N is compared with the agitation frequency reference value for each predetermined unit excavation length section to make a determination, and if not satisfied, an alarm is output to prompt re-construction of the unit excavation length section.

【0022】(3) 第3点として、構造物を支持する地盤
の補強として地盤改良を用いる場合、所定の支持力を発
揮できる深度まで確実に改良する必要がある。そこで、
支持層を判断するために、単位掘進長毎の攪拌ヘッドの
仕事量を求める。例えば、攪拌ヘッド先端の地盤の硬さ
を計測判断するため、攪拌ヘッドによる単位長さ当たり
の掘進攪拌抵抗値(仕事量)W[kJ/m]を常時監視
する。この掘進攪拌抵抗値をデータ表示器に表示し、こ
の掘進攪拌抵抗値が設定値に達したとき攪拌ヘッドが所
定の支持層に到達したと判定する。この掘進攪拌抵抗値
は、駆動部のモータの電流値A(電動モータ)またはト
ルク(油圧モータ)と、攪拌ヘッドの掘進速度Vを用い
て求める。即ち、1m掘進するのに要した時間に攪拌ヘ
ッドのした仕事量を掘進攪拌抵抗値Wとする(後述の式
(2)参照)。
(3) As a third point, when the ground improvement is used to reinforce the ground supporting the structure, it is necessary to surely improve the ground to a depth at which a predetermined supporting force can be exhibited. Therefore,
In order to determine the support layer, the work amount of the stirring head for each unit excavation length is obtained. For example, in order to measure and determine the hardness of the ground at the tip of the stirring head, the excavation stirring resistance value (work amount) W [kJ / m] per unit length by the stirring head is constantly monitored. The excavation agitation resistance is displayed on a data display, and when the excavation agitation resistance reaches a set value, it is determined that the agitation head has reached a predetermined support layer. This excavation stirring resistance value is obtained using the current value A (electric motor) or torque (hydraulic motor) of the motor of the drive unit and the excavation speed V of the stirring head. That is, the amount of work performed by the stirring head during the time required to excavate 1 m is defined as the excavation agitation resistance value W (see the following equation (2)).

【0023】さらに、管理装置においては、攪拌ヘッド
に設けられた共回り防止翼の攪拌軸に対する相対回転を
常時監視し、例えば共回り防止翼が静止した状態から共
回りによる回転を始めると警報を出力する。即ち、共回
り防止翼と攪拌軸が一緒に回ると、土が攪拌軸に付着し
土の共回り現象が生じていると判定し、修正施工を促
す。
Further, the management device constantly monitors the relative rotation of the co-rotation prevention blade provided on the stirring head with respect to the stirring shaft, and issues an alarm when, for example, the co-rotation prevention blade starts rotating by co-rotation from a stationary state. Output. That is, when the co-rotation prevention blade and the stirring shaft rotate together, it is determined that the soil adheres to the stirring shaft and the co-rotation phenomenon of the soil has occurred, and the correction construction is encouraged.

【0024】以上に示したように、本発明の管理装置で
は、VとQから地盤中に投入される固化材添加量W
C [kg/m3 ]を算出して、これを1元管理すること
により、管理が容易となり、また省力化・迅速化が図ら
れる。これに対して、従来のように、攪拌軸の昇降速度
V・スラリー吐出量Q・攪拌軸の回転数Rを個々に測定
した場合、攪拌軸の昇降速度Vとスラリー吐出量Qの2
項目を同時に制御することで、地盤中に投入される所定
の固化材添加量を確保しなければならず、煩雑でオペレ
ーターの労力が大きかった。
As described above, in the management device of the present invention, the amount of solidified material added W
By calculating C [kg / m 3 ] and centrally managing this, management becomes easy and labor saving and speeding up are achieved. On the other hand, when the rising and falling speed V of the stirring shaft, the slurry discharge amount Q, and the rotation speed R of the stirring shaft are individually measured as in the related art, the rising and falling speed V of the stirring shaft and the slurry discharge amount Q are two.
By controlling the items at the same time, it was necessary to secure a predetermined amount of the solidifying agent to be introduced into the ground, which was cumbersome and labor-intensive for the operator.

【0025】さらに、本発明の管理装置では、前述の場
合と同様に、深度方向の所定区間内における攪拌回数N
[回/m]を算出して、これを1元管理することによ
り、管理が容易となり、また省力化・迅速化が図られ
る。これに対して、従来においては、攪拌軸の昇降速度
Vと攪拌軸の回転数Rの2項目を同時に制御すること
で、所定の攪拌回数としての混合度を確保しなければな
らず、煩雑でオペレーターの労力が大きかった。
Further, in the management apparatus according to the present invention, the number of agitation N
By calculating [times / m] and centrally managing this, management becomes easy, and labor saving and speeding up are achieved. On the other hand, in the related art, it is necessary to secure the degree of mixing as a predetermined number of times of stirring by controlling the two items of the vertical speed V of the stirring shaft and the rotation speed R of the stirring shaft at the same time. The operator's labor was great.

【0026】また、必要改良深さに関しては、攪拌ヘッ
ドの掘進攪拌抵抗値(仕事量)W[kJ/m]を検出し
て支持層への到達を判定するため、当初予想していなか
った地層の変化にも対応することができる。
Further, regarding the required improvement depth, since the arrival at the support layer is determined by detecting the excavation resistance (work amount) W [kJ / m] of the agitation head, the formation is not expected at first. Can also be changed.

【0027】さらに、良好な地盤改良に必要な単位掘進
長毎の固化材添加量・攪拌回数・掘進攪拌抵抗値である
攪拌ヘッドの仕事量がディスプレイに各単位掘進長区間
毎に逐次表示され、オペレーターに瞬時に伝達されるた
め、正確な施工が可能となり、また設定値や基準値を満
足しない場合には警報も発せられるので安心して施工を
行うことができると共に、警報箇所を再施工することで
良好な地盤改良を行うことができる。
Further, the amount of solidified material added per unit excavation length required for good ground improvement, the number of times of agitation, and the work amount of the agitation head, which is the excavation agitation resistance value, are sequentially displayed on the display for each unit excavation length section, It is transmitted instantly to the operator, enabling accurate construction.Also, if the set value or reference value is not satisfied, an alarm will be issued so that the construction can be performed with peace of mind and the alarm location must be reconstructed. And good ground improvement can be performed.

【0028】[0028]

【発明の実施の形態】以下、本発明を図示する実施の形
態に基づいて説明する。図1は本発明の地盤改良の施工
状態管理方法を実施するための施工現場における施工管
理の1例を示したものである。図1では、現場Aと現場
Bとが示され、現場B内に示された現場管理者b2 ,b
3 ,…は、現場Bと異なる現場であっても、現場Bが広
い現場で多数箇所で施工して多数の現場管理者の元でそ
れぞれ施工を行っていてもよい。図2は本発明の施工状
態管理システムの1例を示したものである。図3は本発
明の早期品質確認システムの1例を示したものである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below based on an embodiment shown in the drawings. FIG. 1 shows an example of construction management at a construction site for implementing the construction condition management method for ground improvement of the present invention. In FIG. 1, a site A and a site B are shown, and site managers b 2 and b shown in the site B.
3 ,... May be constructed at a large number of sites in a site where the site B is wide, and may be constructed under a large number of site managers, even if the site is different from the site B. FIG. 2 shows an example of the construction state management system of the present invention. FIG. 3 shows an example of the early quality check system of the present invention.

【0029】図1に示すように、各施工現場には、施工
管理を行う施工現場管理者1がおり、施工管理システム
の管理装置2を少なくとも設置し、好ましくは更に早期
品質確認システム3を設置する。後に詳述するように、
施工中の地盤改良機やプラントから得られた測定データ
から管理装置2により施工データを求める。また地盤改
良体(ソイルセメントコラム)から採取した試料から早
期品質確認システム3により画像データを少なくとも
得、好ましくは更に圧縮強度データを得る。これら施工
データを(場合によっては画像データ・圧縮強度データ
なども)施工現場管理者1に送り、施工現場管理者1が
一括して集中管理する。
As shown in FIG. 1, at each construction site, there is a construction site manager 1 who performs construction management. At least a management device 2 for the construction management system is installed, and preferably, an early quality check system 3 is further installed. I do. As detailed below,
Management data is obtained by the management device 2 from measurement data obtained from a ground improvement machine or a plant under construction. Further, at least the image data is obtained by the early quality check system 3 from the sample collected from the ground improvement body (soil cement column), and preferably the compressive strength data is further obtained. These construction data are sent to the construction site manager 1 (and image data, compression strength data, etc. in some cases), and the construction site manager 1 collectively manages the data.

【0030】管理装置2は、例えば図2に示すように、
地盤改良機11に搭載されており、管理装置2で得られ
た施工データD1 をICカード6等の記録媒体に記録す
る。このICカード6等は、必要により、デジタルカメ
ラ7のデジタル画像データD 2 やコア試料の圧縮強度デ
ータD3 も一緒に記録してもよい。また、施工データD
1 ,デジタル画像データD2 ,コア試料の圧縮強度デー
タD3 を別個のICカード6等に記録する場合は、施工
ロッド番号を付すことが好ましい。これらデータを現場
事務所等へ持ち込み、現場事務所等のコンピュータ8に
入力する。管理装置2の施工データD1 は、有線あるい
は無線等による通信システム(インターネット等)によ
りコンピュータ8へ直接送信することもできる。また、
管理装置2のディスプレイで表示されたデータをコンピ
ュータ8にリアルタイムで表示させることも可能であ
る。施工現場管理者1はコンピュータ8の施工データD
1 ・画像データD2 ・圧縮強度データD3 から施工状態
をチェックし、必要に応じて施工指示を地盤改良機11
のオペレータに伝え、あるいは施工指示データD4 をオ
ペレータへ送信する。なお、各データをD1 〜D3 を遠
隔地である本社における施工チェック部署・工事部・施
工監理者・管理者・施主等へも送信することができる。
The management device 2 is, for example, as shown in FIG.
Installed in the ground improvement machine 11 and obtained by the management device 2
Construction data D1On a recording medium such as an IC card 6.
You. This IC card 6 etc. can be
Digital image data D of LA7 TwoAnd core sample compressive strength data
Data DThreeMay also be recorded together. In addition, construction data D
1, Digital image data DTwo, Core sample compressive strength data
TA DThreeWhen recording on a separate IC card 6 etc.
Preferably, a rod number is assigned. These data can be
Bring it to the office, etc.
input. Construction data D of management device 21Is a wired or
Is based on a wireless communication system (Internet, etc.)
Can be directly transmitted to the computer 8. Also,
The data displayed on the display of the management device 2 is compiled.
It is also possible to display on the computer 8 in real time.
You. The construction site manager 1 uses the construction data D of the computer 8
1・ Image data DTwo・ Compression strength data DThreeFrom construction state
Is checked, and if necessary, a construction instruction is given to the ground improvement machine 11.
To the operator or the construction instruction data DFourThe
Send to the perlator. In addition, each data is D1~ DThreeFar
Construction check department, construction department, facility at headquarters in a remote area
It can also be sent to construction supervisors, managers, owners, etc.

【0031】なお、デジタル画像や圧縮強度データを得
るための試料の採取はその現場で施工する初期のソイル
セメントコラムにて実施し、そこで良好な結果が得られ
たら、その施工現場では同一条件で施工を続ける。この
試料採取は所定のロット毎に行うこともある。
The sampling for obtaining the digital image and the compressive strength data is carried out in an initial soil cement column to be constructed at the site, and when a good result is obtained there, the same conditions are used at the site. Continue construction. This sampling may be performed for each predetermined lot.

【0032】早期品質確認システム3は、例えば図3に
示すように、未固化採取治具12と、デジタルカメラ7
から構成され、温水促進養生装置14と、簡易一軸圧縮
試験器15などを含んで構成してもよい。地盤改良機1
1を利用して施工直後の未だ固まっていないソイルセメ
ントコラム16内に未固化採取治具12を挿入し、未固
化のコア試料17を全長にわたり採取する。この全長の
コア試料17を水平に置き、デジタルカメラ7で撮影
し、画像データD2 を得る。次いで、このコア試料17
から未固化のソイルセメントを採取し、モールド13に
充填することにより強度確認のための供試体18を作製
する。この供試体18を温水促進養生装置14により1
日で促進養生した後、簡易一軸圧縮試験器15で強度試
験を行い、圧縮強度データD3 を得る。
As shown in FIG. 3, for example, the early quality check system 3 includes an unsolidified collection jig 12 and a digital camera 7.
, And may include the hot water accelerating curing device 14, the simple uniaxial compression tester 15, and the like. Ground improvement machine 1
The unsolidified collecting jig 12 is inserted into the unsolidified soil cement column 16 immediately after the construction by using 1 to collect the unsolidified core sample 17 over the entire length. Place the core sample 17 of the full-length horizontal, captured by a digital camera 7, obtaining image data D 2. Next, this core sample 17
An unsolidified soil cement is collected from the sample and filled into a mold 13 to prepare a specimen 18 for confirming the strength. The specimen 18 is heated for 1
After accelerated curing in days, subjected to a strength test by simple uniaxial compression test 15, to obtain a compressive strength data D 3.

【0033】上記の未固化採取治具12は、例えば、本
出願人の出願に係る試料土採取方法および装置(特願平
11−123556号)を用いることができる。この試
料土採取方法は、H形鋼等の開放された側面を有する開
放断面の長尺採取部材12aを地盤改良機11からワイ
ヤロープ12b等で吊り下げ、施工終了直後のソイルセ
メントコラム16内に採取部材の自重,地盤改良機ある
いはバイブロハンマー等で挿入し、所定の深度に達する
と、この長尺採取部材12aの底面を底蓋により閉塞す
ると共に開放側面を側面板により周囲の改良土から縁切
りし、試料土が充填された長尺採取部材12aを地上に
引き上げるものであり、連続した試料土を確実に迅速に
採取することができる。
As the unsolidified sampling jig 12, for example, a sample soil sampling method and apparatus (Japanese Patent Application No. 11-123556) according to the present applicant's application can be used. In this method of sampling soil, a long sampling member 12a having an open section having an open side surface such as an H-section steel is suspended from a ground improvement machine 11 with a wire rope 12b or the like, and is placed in a soil cement column 16 immediately after completion of construction. When the collecting member is inserted by its own weight, a ground improvement machine or a vibro hammer, and reaches a predetermined depth, the bottom surface of the long collecting member 12a is closed by a bottom cover, and the open side surface is cut off from the surrounding improved soil by a side plate. Then, the long sampling member 12a filled with the sample soil is pulled up to the ground, so that a continuous sample soil can be reliably sampled quickly.

【0034】圧縮強度の測定には、例えば、本出願人の
出願に係る地盤改良工法の品質管理方法および温水養生
装置(特願平11−156359号)を用いることがで
きる。これは、クーラーボックス等の温水養生槽14a
に自動温度調節装置付きのヒーターと循環ポンプ等を設
け、この温水養生槽14a内に円柱供試体18をモール
ドごと格納し、55°C の温水により約24時間で促進養生
し、この温水養生後に簡易一軸圧縮試験器15で供試体
強度を測定し、この55°C 温水養生1日強度から関係式
を用いて通常期間養生後の供試体強度すなわち20°C 養
生材令28日強度を推定するものであり、改良土の設計強
度評価を約1日で行うことができる。なお、供試体強度
の測定は、施工現場で行っているが、温水促進養生装置
14は持ち運びできるため、他の場所で供試体強度の測
定を行うことも可能である。
For the measurement of the compressive strength, for example, a quality control method of a ground improvement method and a hot water curing device (Japanese Patent Application No. 11-156359) according to the application of the present applicant can be used. This is a hot water curing tank 14a such as a cooler box.
A heater equipped with an automatic temperature controller and a circulating pump are provided in the tank. The cylindrical specimen 18 is stored together with the mold in the hot water curing tank 14a, and is accelerated and cured with hot water of 55 ° C for about 24 hours. The strength of the specimen is measured by the simple uniaxial compression tester 15, and the strength of the specimen after curing for a normal period, that is, the strength of the curing material at 28 days at 20 ° C is estimated from the 55 ° C warm water curing one-day strength by using a relational expression. The design strength of the improved soil can be evaluated in about one day. Although the measurement of the specimen strength is performed at the construction site, the measurement of the specimen strength can be performed at another place because the warm water promotion curing device 14 is portable.

【0035】以上のようにして得られたデータが図2に
例示するように施工現場管理者1のコンピュータ8に入
力され、このデータに基づいて、次に示すような管理な
どが行われる。なお、施工データD1 は、例えば図5に
示すようにコンピュータ8の画面に表示される。
The data obtained as described above is input to the computer 8 of the construction site manager 1 as illustrated in FIG. 2, and the following management is performed based on the data. Incidentally, the construction data D 1 is displayed for example on a computer screen 8 as shown in FIG.

【0036】(1) 進捗率管理 施工データD1 を用い、施工されたソイルセメントコラ
ムの施工数等の予定と実績を図4(a) に示すようなグラ
フで表し、工事の進捗率を確認する。 (2) 労務管理 施工データD1 を用い、図4(b) に示すように、各施工
日における施工時間を確認する。 (3) 品質管理 画像データD2 を用い、土と固化材の混合状態(土の
塊が混在していないかどうか)およびソイルセメントコ
ラム上方の盛り上がり量(固化材を吐出していない上部
区間に固化材が盛り上がっている状態)をチェックす
る。 圧縮強度データD3 を用い、55°C 温水養生1日強度
から材令28日強度を推定することにより、固化材添加量
等の可否を判定する。 上記の画像データD2 と、もしくは画像データD2
他に圧縮強度データD 3 と、施工データD1 を比較検討
し、品質不良の対策案を策定する。 (4) 施工管理 施工データD1 を用いてグラフ表示された図5の一覧
表(後に詳述する)により、築造されたソイルセメント
コラムの合否を判定する。この図5において、攪拌回数
や固化材添加量は一定深度毎に表示しているが、これに
限らず、仕事量のように深度毎のグラフとしてもよい。
また、固化材添加量はスラリー吐出量でもよい。 施工データD1 を用いて不良コラムの原因調査を行
う。 (5) 報告書作成 以上の管理項目に必要事項を盛り込んで報告書を作成す
る。施工データD1 および画像データD2 は即日提出が
可能であり、圧縮強度データD3 も翌日に提出が可能で
ある。 (6) 施工指示 以上の結果から施工指示を地盤改良機のオペレータに与
える。
(1) Progress rate management Construction data D1Soil cement cola constructed using
As shown in Fig. 4 (a), the planned and actual
And confirm the progress of the construction. (2) Labor management Construction data D1As shown in Fig. 4 (b),
Check the construction time per day. (3) Quality control Image data DTwoUsing a mixture of soil and solidified material (soil
Lump is not mixed) and soil cement
The amount of swelling above the ram (the upper part where the solidified material is not discharged)
Check that the solidified material is rising in the section)
You. Compressive strength data DThree, 55 ° C hot water curing 1 day strength
Estimated 28 days strength from material age
Is determined. The above image data DTwoOr image data DTwoof
Other compressive strength data D ThreeAnd construction data D1Compare
And formulate countermeasures for quality defects. (4) Construction management Construction data D1List of FIG. 5 graphically displayed by using
According to the table (detailed below), the built soil cement
Determine whether the column is acceptable. In this FIG.
And the amount of solidified material added are displayed at certain depths.
The graph is not limited thereto, and may be a graph for each depth, such as the amount of work.
Further, the solidifying material addition amount may be a slurry discharge amount. Construction data D1Investigate the cause of the defective column using
U. (5) Report creation A report is created by incorporating the necessary items in the above management items.
You. Construction data D1And image data DTwoIs submitted on the same day
It is possible and the compression strength data DThreeCan be submitted the next day
is there. (6) Construction instructions Based on the above results, the construction instructions are given to the ground improvement machine operator.
I can.

【0037】次に、管理装置2による施工データの検出
方法の1例について詳述する。図5は施工データのディ
スプレイ表示例を示したものである。図6は地盤改良機
・プラント・管理装置の全体構成を模式的に示したもの
である。図7は地盤改良機の攪拌軸先端の攪拌ヘッドを
示したものである。図8〜図10はデータの施工記録例
を示したものである。図11は本発明の管理方法のフロ
ーチャート、図12は地盤改良施工例を深度−時間図で
示したものである。
Next, an example of a method of detecting construction data by the management device 2 will be described in detail. FIG. 5 shows an example of display of construction data on a display. FIG. 6 schematically shows the entire configuration of the ground improvement machine / plant / management device. FIG. 7 shows the stirring head at the tip of the stirring shaft of the ground improvement machine. 8 to 10 show examples of data construction records. FIG. 11 is a flowchart of the management method of the present invention, and FIG. 12 is a depth-time diagram showing an example of ground improvement construction.

【0038】図6において、地盤改良機11の前面に設
けられたリーダーマスト30には攪拌軸31の駆動部3
2がガイドレールにより昇降自在に取付けられ、ワイヤ
ー33により吊り保持され、攪拌軸31の先端部には攪
拌ヘッド34が設けられている。攪拌ヘッド34は、図
7に示すように、先端側から順に、掘削翼35と、共回
り防止翼36と、上下に間隔をおいて複数の攪拌翼37
が設けられている。共回り防止翼36は、攪拌ヘッド部
分に粘着性のある土が団子状に付着して攪拌ヘッド34
と共に同期回転する、いわゆる土の共回り現象を防止す
るためのものであり、掘削径より外に出ている先端が掘
削孔壁に貫入されて土中に静止するように攪拌軸31に
回転自在に取付けられている。
In FIG. 6, a driving part 3 of a stirring shaft 31 is attached to a leader mast 30 provided in front of the ground improvement machine 11.
2 is attached by a guide rail so as to be able to move up and down, is suspended and held by a wire 33, and a stirring head 34 is provided at the tip of the stirring shaft 31. As shown in FIG. 7, the stirring head 34 includes, in order from the tip side, a digging blade 35, a co-rotation preventing blade 36, and a plurality of stirring blades 37 spaced vertically.
Is provided. The co-rotation preventing blades 36 are formed by sticky soil adhering to the stirring head portion in a dumpling manner.
This is to prevent the so-called co-rotation phenomenon of the soil that rotates synchronously with the agitating shaft 31 so that the tip outside the excavation diameter penetrates the excavation hole wall and stops in the soil. Mounted on

【0039】一方、図6に示すように、プラント40で
は水Wと固化材C(セメント)等を混練してセメントミ
ルク41を作製する。作製されたセメントミルク41は
吐出量の制御が可能なスラリーポンプ42を介して地盤
改良機11に送られ、攪拌軸31の内部を通り、攪拌ヘ
ッド34の先端部の吐出口43から吐出される(図7参
照)。吐出されたセメントミルク41は、掘削翼35・
共回り防止翼36・攪拌翼37により、掘削土砂と効率
良く攪拌混合され、ソイルセメントコラムが築造され
る。なお、スラリーポンプ42と地盤改良機との間のセ
メントミルク41の通路に吐出量検出機47が設置され
ている。
On the other hand, as shown in FIG. 6, in a plant 40, water W and a solidifying material C (cement) are kneaded to produce a cement milk 41. The produced cement milk 41 is sent to the ground improvement machine 11 via a slurry pump 42 whose discharge amount can be controlled, passes through the inside of the stirring shaft 31, and is discharged from the discharge port 43 at the tip of the stirring head 34. (See FIG. 7). The discharged cement milk 41 has a
By the co-rotation preventing blades 36 and the stirring blades 37, the excavated earth and sand are efficiently stirred and mixed, and a soil cement column is built. In addition, a discharge amount detector 47 is provided in a passage of the cement milk 41 between the slurry pump 42 and the ground improvement machine.

【0040】以上のような地盤改良機において、この実
施例では、図6に示すように、駆動部32の移動距離か
ら攪拌ヘッド34の深度を検出する深度(速度)検出器
(例えば、ワイヤーのシーブに取付けたエンコーダ)4
4を地盤改良機11に設け、攪拌軸31の回転数を検出
する回転数検出器45を駆動部32に設け、駆動部32
の電動モータ(または油圧モータ)の電流値(または油
圧力)を検出する電流検出器(または油圧力検出器)4
6を地盤改良機11に設ける。一方、プラント側には、
セメントミルク41の吐出量を検出する吐出量検出器
(流量検出器)47を設ける。施工条件によっては、図
7(b) に示すように、攪拌ヘッド34には、攪拌軸31
と共回り防止翼36の相対回転を検出する検出用マグネ
ット48aと磁気式近接スイッチ48bなどからなる相
対回転検出器48を設ける。
In the above-described ground improvement machine, in this embodiment, as shown in FIG. 6, a depth (speed) detector (for example, a wire detector) for detecting the depth of the stirring head 34 from the moving distance of the drive unit 32. Encoder mounted on sheave) 4
4 is provided in the ground improvement machine 11, and a rotation speed detector 45 for detecting the rotation speed of the stirring shaft 31 is provided in the drive unit 32.
Current detector (or hydraulic pressure detector) 4 for detecting the current value (or hydraulic pressure) of the electric motor (or hydraulic motor)
6 is provided in the ground improvement machine 11. On the other hand, on the plant side,
A discharge amount detector (flow rate detector) 47 for detecting the discharge amount of the cement milk 41 is provided. Depending on the construction conditions, as shown in FIG.
And a relative rotation detector 48 including a detection magnet 48a for detecting the relative rotation of the corotation prevention blade 36 and a magnetic proximity switch 48b.

【0041】施工機側には、図6に示すように、重機計
測盤49が設置されており、この重機計測盤49に深度
検出器44・回転数検出器45・電流検出器(または油
圧力検出器)46・相対回転検出器48からの検出値が
入力される。この重機計測盤49では、入力された検出
値により、次のような演算処理を行う(詳細は後述す
る)。
As shown in FIG. 6, a heavy equipment measuring panel 49 is installed on the construction machine side. The heavy equipment measuring panel 49 has a depth detector 44, a rotation speed detector 45, a current detector (or an oil pressure). Detector) 46. The detection value from the relative rotation detector 48 is input. The heavy equipment measuring panel 49 performs the following arithmetic processing based on the input detection value (details will be described later).

【0042】 深度検出器44からの深度Dと、施工
時間を計測するタイマーからの施工時間tを用いて、攪
拌ヘッド34の昇降速度V[m/分]を算出する。 単位掘進長区間(例えば0.5m)毎に、昇降速度
Vと、回転数検出器45からの攪拌軸回転数Rと、攪拌
ヘッド34の羽根枚数nを用いて、地盤土の単位長さ当
たりの攪拌回数N[回/m]を算出する。 単位掘進長区間(本実施例では0.5m)毎に攪拌
回数Nが基準値Nthを満足するか否かの判定を行い、満
足しない場合には、その単位掘進長区間の再施工を促す
判定結果を出力する。 攪拌ヘッド34の掘進速度Vと、電流検出器46か
らの電流値A(またはトルク)を用いて、地盤土の単位
長さ当たりの掘進攪拌抵抗値W[kJ/m]を算出す
る。 単位掘進長区間(この場合は0.1m)毎に掘進攪
拌抵抗値(仕事量)Wが支持層管理設定値Wthを上回る
かどうかの判定を行い、攪拌ヘッドが支持層へ到達した
か否かの判断を行う。 攪拌ヘッド34に設けた相対回転検出器48の検出
値を用いて、土の共回りが発生したかどうかを検出す
る。相対回転数が攪拌ヘッド34の回転数に一致する
と、共回り防止翼36は静止し、土の共回りは全く発生
していないことを示す。
Using the depth D from the depth detector 44 and the construction time t from the timer for measuring the construction time, the vertical speed V [m / min] of the stirring head 34 is calculated. For each unit excavation length section (for example, 0.5 m), the elevation speed V, the rotation speed R of the stirring shaft from the rotation speed detector 45, and the number n of blades of the stirring head 34 are used to determine the unit length of the ground soil. Is calculated N [times / m]. Performed for determining whether or not stirring number N for each satisfies the reference value N th (0.5 m in this embodiment) the unit excavation length section, if not satisfied, urging re construction of the unit excavation length section Output the judgment result. Using the excavation speed V of the agitation head 34 and the current value A (or torque) from the current detector 46, the excavation agitation resistance value W [kJ / m] per unit length of the ground soil is calculated. For each unit excavation length section (in this case, 0.1 m), it is determined whether the excavation stirring resistance value (work amount) W exceeds the support layer management set value Wth, and whether the stirring head reaches the support layer. Is determined. Using the detection value of the relative rotation detector 48 provided on the stirring head 34, it is detected whether the co-rotation of the soil has occurred. When the relative rotation speed matches the rotation speed of the stirring head 34, the co-rotation prevention blade 36 stops, indicating that no co-rotation of the soil has occurred.

【0043】一方、プラント側には、図6に示すよう
に、プラント計測盤50が設置されており、このプラン
ト計測盤50に吐出量検出器47からの検出値が入力さ
れ、また重機計測盤49から深度D・昇降速度Vが入力
される。このプラント計測盤50では、入力された検出
値により、次のような演算処理を行う(詳細は後述す
る)。
On the other hand, as shown in FIG. 6, a plant measuring panel 50 is installed on the plant side, and a detection value from the discharge amount detector 47 is input to the plant measuring panel 50. From 49, the depth D and the elevation speed V are input. The plant measurement panel 50 performs the following arithmetic processing based on the input detection value (details will be described later).

【0044】 深度Dまたは昇降速度Vと、吐出量検
出器47からのセメントミルク吐出量Qと、固化材の比
重GC 等を用いて、地盤土の単位体積当たりの固化材添
加量W C [kg/m3 ]を算出する。 単位掘進長区間(本実施例では0.5m)毎に固化
材添加量WC が設定値W Cth を満足するか否かの判定を
行い、満足しない場合には、必要なセメントミルク吐出
量Qを算出し、固化材添加量が設定値を満足するように
スラリーポンプ42を自動制御あるいは調整してセメン
トミルク吐出量をコントロールする。また、昇降速度V
が変化した場合にも、固化材添加量が設定値を満足する
ようにスラリーポンプ42を自動制御あるいは調整して
セメントミルク吐出量をコントロールする。 さらに、何らかの原因により、固化材添加量WC
設定値WCth を満足しない場合に、その単位掘進長区間
の再施工を促す判定結果を出力する。
The depth D or the elevation speed V and the discharge amount detection
Ratio of cement milk discharge amount Q from dispenser 47 to solidified material
Heavy GCThe solidification material per unit volume of the ground soil
Addition W C[Kg / mThree] Is calculated. Solidified every unit excavation length section (0.5 m in this embodiment)
Material addition amount WCIs the set value W CthTo determine whether or not
If you are not satisfied, discharge the necessary cement milk
Calculate the amount Q so that the amount of solidifying material added satisfies the set value
Automatically control or adjust the slurry pump 42 for cement
Control the amount of milk discharged. The lifting speed V
The amount of solidifying material added satisfies the set value even if
Control or adjust the slurry pump 42 as
Controls the amount of cement milk discharged. Further, for some reason, the solidification material addition amount WCBut
Set value WCthIf not satisfied, the unit excavation length section
And outputs the judgment result prompting the re-construction of.

【0045】地盤改良機11のオペレータ室11aに
は、図6に例示するように、データ表示器51、遠隔操
作盤52、警報報知器53、通話器54が設置されてお
り、重機計測盤49・プラント計測盤50における入力
データおよび処理データがデータ表示器51に表示され
る。
As shown in FIG. 6, in the operator room 11a of the ground improvement machine 11, a data display 51, a remote control panel 52, an alarm device 53, and a talker 54 are installed. -Input data and processing data in the plant measurement panel 50 are displayed on the data display 51.

【0046】図5は、データ表示器51の施工中の画面
イメージの1例であり、下記の〜などが数値やグラ
フなどで表示され、誤視認のない分かりやすい画面表示
となっている。
FIG. 5 is an example of a screen image during the construction of the data display 51. The following (1) to (5) are displayed in numerical values, graphs, and the like, and the screen display is easy to understand without erroneous recognition.

【0047】 施工日付・時分秒(施工時間)・コラ
ムNo. と径・深度・速度・電流値(油圧力)・軸回転数
・吐出量 固化材添加量・攪拌回数・仕事量の設定値・基準値
(下側に表示されている。) 所定の単位掘進長区間毎の固化材添加量・攪拌回数
・仕事量の検出値 固化材添加量が設定値を満足するために現在必要と
なる必要吐出量 固化材添加量・攪拌回数が設定値・基準値を満足し
ない場合の警報 掘進攪拌抵抗値が管理設定値に達した場合の着底表
示 共回り防止翼と攪拌軸の相対回転数と、共回り現象
が確認された場合の警報表示
Set values of construction date, hour, minute, second (construction time), column number and diameter, depth, speed, current value (oil pressure), shaft rotation number, discharge amount, amount of solidified material added, number of agitation, work amount・ Reference value (displayed on the lower side) Detected value of solidification material addition amount, number of agitation, and work for each predetermined unit excavation length section Currently required for the solidification material addition amount to satisfy the set value Required discharge amount Warning when solidification material addition amount and number of agitation do not satisfy the set value and reference value Settlement display when excavation agitation resistance value reaches control set value Relative rotation speed of co-rotation prevention blade and agitation shaft , Alarm display when co-rotation phenomenon is confirmed

【0048】また、上記〜などの警報が発せられる
場合は、警報報知器53で音声による警報を発する。さ
らに、データ表示器51は施工データおよび入力データ
が時間を遡って再現表示可能とされている。また、上記
〜などの警報が発せられる場合、音声による警報と
ともに、データ表示器51に赤色の反転文字で点滅表示
することもできる。
When an alarm such as the above is issued, the alarm alarm 53 issues an audio alarm. Further, the data display 51 can reproduce and display the construction data and the input data retroactively. In addition, when an alarm such as above is issued, the data display 51 can be displayed in a blinking red color on the data display 51 together with the audio alarm.

【0049】オペレータ室11aの遠隔操作盤52で
は、コラムNo. の選択、施工設定値・基準値の入力・変
更、施工開始、施工終了等の操作が行われる。また、遠
隔操作盤52により重機計測盤49、プラント操作盤5
0を介してスラリーポンプ42へ信号を送り、スラリー
ポンプ42を遠隔操作し、セメントミルク吐出量を調整
することができる。
On the remote control panel 52 of the operator room 11a, operations such as selection of a column number, input / change of a set value and a reference value, start and end of construction are performed. Further, the heavy equipment measuring panel 49 and the plant operation panel 5 are controlled by the remote control panel 52.
A signal can be sent to the slurry pump 42 via 0 to remotely control the slurry pump 42 to adjust the amount of cement milk discharged.

【0050】施工中に検出された施工データは、図6に
例示するように、全てが遠隔操作盤52の内部にある記
憶装置に保存され、このデータはICカード6やフロッ
ピーディスク等の記憶媒体を介して現場事務所等におけ
る日報作成システム55に移動・複写することができ
る。この日報作成システム55は、コンピュータ8とプ
リンター56からなり、施工記録・日報・施工集計表・
固化材管理表の作成・印刷を行う。図8は、印刷された
帳票例である。コラムNo. ,所要時間,施工機No. ,改
良径,掘削長,固化材使用量,単位掘進長毎の固化材添
加量・攪拌回数・仕事量などが記されている。図9に示
すような時間軸に対する深度,速度,電流値,ロッド軸
回転数,吐出量などのチャート式の施工記録の印刷も可
能である。また、必要に応じて、図10に示すような改
良部(ソイルセメントコラム)における各深度毎の固化
材添加量や攪拌回数をプロットして解析することも可能
である。
As shown in FIG. 6, all the construction data detected during construction is stored in a storage device inside the remote control panel 52, and this data is stored in a storage medium such as an IC card 6 or a floppy disk. Can be moved / copied to the daily report creation system 55 in the field office or the like via the Internet. The daily report creation system 55 is composed of a computer 8 and a printer 56, and includes a construction record, a daily report, a construction summary table,
Create and print the solidification material management table. FIG. 8 is an example of a printed form. Column No., required time, construction machine No., improved diameter, excavation length, amount of solidified material used, amount of solidified material added per unit excavation length, number of agitation, work amount, etc. are described. It is also possible to print a chart type construction record such as a depth, a speed, a current value, a rod shaft rotation speed, and a discharge amount with respect to a time axis as shown in FIG. If necessary, it is also possible to plot and analyze the solidification material addition amount and the number of times of stirring at each depth in the improved portion (soil cement column) as shown in FIG.

【0051】図11は、掘進時にセメントミルクを吐出
する場合の施工管理フローの例を示したものである。掘
進工程において、固化材添加量・支持層の確認等を行
い、引上工程において攪拌回数の確認等を行っている。
FIG. 11 shows an example of a construction management flow in the case of discharging cement milk during excavation. In the excavation process, the amount of the solidified material added and the support layer are checked, and in the pulling process, the number of agitation is checked.

【0052】以下に各処理について詳述する。 (i) 固化材添加量 掘進工程において、攪拌ヘッド34の深度D・掘進速度
Vと、セメントミルク41の地盤への注入量(吐出量)
Qと、固化材Cの比重GC から、地盤の単位体積当たり
の固化材添加量WC [kg/m3 ]を算出する。また、
各単位掘進長区間(本実施例では0.5m)毎に固化材
添加量WC が設定値WCth を満足するか否かの判定を行
い、固化材添加量WC が設定値WCth を常に満足するよ
うに、必要吐出量Qを算出してスラリーポンプ42へ必
要吐出量を指示し、スラリーポンプ42を自動制御ある
いは調整する。また、昇降速度Vに応じてスラリーポン
プ42を自動制御あるいは調整し、固化材添加量WC
設定値WCth を満足するようにする。さらに、このよう
な制御等を行っても、何らかの原因により、固化材添加
量WC が設定値WCth より低い場合には、警報が発せら
れ当該単位掘進長区間の修正施工を行う。
Hereinafter, each processing will be described in detail. (i) Solidification material addition amount In the excavation process, the depth D and the excavation speed V of the stirring head 34 and the amount of cement milk 41 injected into the ground (discharge amount).
And Q, from the specific gravity G C of solidifying material C, and calculates the solidifying material amount per unit volume of soil W C [kg / m 3] . Also,
A judgment of whether solidifying material amount W C per satisfies the set value W Cth (0.5 m in this embodiment) the unit excavation length section, solidifying material amount W C is the set value W Cth The required discharge amount Q is calculated and the required discharge amount is instructed to the slurry pump 42 so that the slurry pump 42 is automatically controlled or adjusted so that the slurry pump 42 is always satisfied. In addition, the slurry pump 42 is automatically controlled or adjusted according to the elevating speed V so that the solidified material addition amount W C satisfies the set value W Cth . Furthermore, even if such control or the like is performed, if for some reason the solidified material addition amount W C is lower than the set value W Cth , an alarm is issued and correction work is performed for the unit excavation length section.

【0053】固化材添加量WC [kg/m3 ]の算出方
法は以下による。即ち、次に示す(1)式を用いて、セ
メントミルク吐出量(注入量)Q[L/分]と水・固化
材比W/C等を用いて固化材投入量WC ’[kg/分]
を求める。ここで、添加材等を使用しない場合には、B
=0となり、(1)式を用いて固化材投入量WC ’を算
出することができる。
The method of calculating the solidification material addition amount W C [kg / m 3 ] is as follows. That is, using the formula (1) shown below, the cement material discharge amount (injection amount) Q [L / min] and the water-solidifier ratio W / C, etc., and the solidified material input amount W C ′ [kg / Minutes]
Ask for. Here, when no additive is used, B
= 0, and the solidified material input amount W C ′ can be calculated using the equation (1).

【0054】[0054]

【数1】 (Equation 1)

【0055】以上により求まる固化材投入量WC ’を、
投入された区間の体積で除したものが固化材添加量WC
[kg/m3 ]となる。即ち、区間の長さをΔD
[m]、この区間の通過時間をΔt[分]、コラムの横
断面積をa[m2 ]とすれば、WCは、次式で求めるこ
とができる。 WC =(WC ’×Δt)/(ΔD×a) = WC ’/(V・a)
The solidification material input amount W C ′ obtained as described above is
The solidification material addition amount W C divided by the volume of the input section is
[Kg / m 3 ]. That is, the length of the section is ΔD
If [m], the transit time of this section is Δt [minutes], and the cross-sectional area of the column is a [m 2 ], W C can be obtained by the following equation. W C = (W C ′ × Δt) / (ΔD × a) = W C ′ / (V · a)

【0056】固化材添加量の管理は例えば次のように行
うこともできる。所要固化材添加量(設定値)が300
kg/m3 の場合、例えば改良径1mで単位掘進長1m
当りに必要となる固化材投入量は236kgとなる。単
位区間1mのうち0.5mまで改良が進んでいる時、地
盤中に投入された固化材量が100kgだとすると、設
定値より18kg不足していることになる。この場合
は、不足分の18kg分を加算した固化材量136kg
を残りの0.5mで投入すればよい。この場合、残りの
0.5mの区間の必要吐出量Qを算出し、この必要吐出
量でスラリーポンプ42を自動制御あるいは調整し、1
m当りにおける固化材添加量が設定値を満足するように
する。上記のような自動制御・調整を管理区間長内(本
実施例では0.5m)で行う。なお、このような不良区
間における単位区間1mのうち上部が固化材量不足、下
部が固化材量過大となるが、この程度の区間距離では上
下方向に十分に攪拌混合されるため強度不足となること
はない。なお、単位区間距離が2単位を越える領域で固
化材量の過不足を生じる場合、このような不良区間は再
施工されるのが原則である。
The amount of the solidifying agent added can be controlled, for example, as follows. Required solidification material addition (set value) is 300
In the case of kg / m 3 , for example, improved excavation diameter 1m and unit excavation length 1m
The required amount of solidified material charged per hit is 236 kg. When the improvement is progressing to 0.5 m in a unit section of 1 m, assuming that the amount of solidified material injected into the ground is 100 kg, the amount is 18 kg short of the set value. In this case, the amount of solidified material 136 kg, which is obtained by adding the shortage of 18 kg
Should be charged with the remaining 0.5 m. In this case, the required discharge amount Q for the remaining 0.5 m section is calculated, and the slurry pump 42 is automatically controlled or adjusted based on the required discharge amount.
The amount of the solidifying material added per m should satisfy the set value. The automatic control and adjustment as described above are performed within the management section length (0.5 m in this embodiment). In the unit section 1m in such a defective section, the upper portion of the unit section 1m has an insufficient amount of the solidified material, and the lower section has an excessive amount of the solidified material. However, at such a section distance, sufficient stirring and mixing in the vertical direction results in insufficient strength. Never. In the case where the amount of the solidified material is excessive or deficient in a region where the unit section distance exceeds 2 units, such a defective section is basically reconstructed.

【0057】また、掘進速度Vが0.5m/分のときの
必要吐出量Qが100L/分の場合、単位単位掘進長区
間1mに100/0.5=200L吐出することになる
が、掘進速度が0.4m/分に低下し同一吐出量のまま
施工すると、100/0.4=250Lと過大に吐出す
ることになる。このような場合には、掘進速度Vの低下
に応じ、吐出量も80L/分に低下させればよい。逆
に、掘進速度Vが速くなれば、それに応じて吐出量Qを
増やせばよい。この場合、掘進速度Vに応じてスラリー
ポンプ42を自動制御あるいは調整し、固化材添加量が
設定値を満足するようにする。
When the required discharge amount Q is 100 L / min when the excavation speed V is 0.5 m / min, 100 / 0.5 = 200 L is discharged per unit excavation length section 1 m. If the speed is reduced to 0.4 m / min and the discharge is performed with the same discharge amount, the discharge is excessively large as 100 / 0.4 = 250 L. In such a case, the discharge rate may be reduced to 80 L / min in accordance with the decrease in the excavation speed V. Conversely, if the excavation speed V increases, the discharge amount Q may be increased accordingly. In this case, the slurry pump 42 is automatically controlled or adjusted according to the excavation speed V so that the amount of the solidified material added satisfies the set value.

【0058】以上の機能により、固化材添加量は常に設
定値を満足し、かつ過不足のない値となる。何らかのト
ラブルにより、単位区間で設定値を満足することができ
なかった場合には、データ表示器51に警報が表示され
る。また、警報報知器53より警報が発せられ、修正施
工が促される。その場合には、いったん攪拌ヘッド34
を引上げ、再度注入攪拌を行うことにより(図12参
照)、確実な固化材添加量管理を行うことができる。
With the above functions, the amount of the solidifying material added always satisfies the set value and is a value without excess or deficiency. If the set value cannot be satisfied in the unit section due to some trouble, an alarm is displayed on the data display 51. Further, an alarm is issued from the alarm annunciator 53 to urge the corrective construction. In that case, once the stirring head 34
, And the injection and agitation are performed again (see FIG. 12), so that the amount of the solidifying material added can be reliably controlled.

【0059】(ii)掘進攪拌抵抗値 掘進工程において、攪拌ヘッド34の掘進速度V(1m
掘進に要した時間t[秒/m])と、駆動部32のモー
タ電流値Aなどから、オーガモータのした仕事量に相当
する掘進攪拌抵抗値Wを算出し、予め土質柱状図の近傍
にて試験施工をすることにより得られた掘進攪拌抵抗値
(設定値)との比較を行い、攪拌ヘッド34が支持層に
到達したかどうかの判定を行う。支持層に到達したと判
断された場合には、データ表示器51、警報報知器53
によりオペレータに通知される。掘進攪拌抵抗値Wの算
出は次の(2)式による。図15は掘進攪拌抵抗(仕事
量)の実測例を示す。
(Ii) Excavation agitation resistance value In the excavation process, the excavation speed V (1 m
From the time t [sec / m] required for excavation) and the motor current value A of the drive unit 32, etc., the excavation stirring resistance value W corresponding to the work done by the auger motor is calculated, and the excavation agitation resistance value W is calculated in advance near the soil column diagram A comparison is made with the excavation stirring resistance value (set value) obtained by performing the test construction, and it is determined whether the stirring head 34 has reached the support layer. When it is determined that the vehicle has reached the support layer, the data display 51 and the alarm information 53
Informs the operator. The excavation stirring resistance value W is calculated according to the following equation (2). FIG. 15 shows an actual measurement example of the excavation stirring resistance (work amount).

【0060】[0060]

【数2】 (Equation 2)

【0061】(iii) 攪拌回数 引上工程において、攪拌ヘッド34の深度D・速度V
と、攪拌軸31の回転数Rと、攪拌ヘッド34の羽根枚
数nから、各単位掘進長区間(本実施例では0.5m)
毎の攪拌回数Nを算出する。また、この算出された攪拌
回数Nが、ばらつきの小さい高品質な地盤改良柱体を築
造するために必要となる攪拌回数の基準値Nthを満足し
ているかの判定を行う。ある単位区間で基準値を満足す
ることができなかった場合には、データ表示器51に警
報が表示され、警報報知器53より警報が発せられ、修
正施工が促される。その場合には、いったん攪拌ヘッド
34を引下げ、再度攪拌混合を行うことにより(図12
参照)、攪拌回数の確保を確実に行うことができる。攪
拌回数Nは、掘進時および引上時のある区間における羽
根の合計通過回転数より求まり、次の(3)式による。
なお、攪拌回数Nの基準値は、図14(b) に示すよう
に、改良対象土質毎に試験施工を行い、攪拌回数と一軸
圧縮強さのばらつきの関係を調査した結果より決定して
いる。
(Iii) Number of Stirring In the lifting step, the depth D and speed V of the stirring head 34
From the rotation speed R of the stirring shaft 31 and the number n of blades of the stirring head 34, each unit excavation length section (0.5 m in this embodiment).
The number of times of stirring N for each time is calculated. Further, the calculated stirred number N, it is determined whether to satisfy the criteria value N th of the stirring times required to construction of small variations quality ground improvement pillar. If the reference value cannot be satisfied in a certain unit section, an alarm is displayed on the data display 51, an alarm is issued from the alarm alarm 53, and correction construction is encouraged. In this case, the stirring head 34 is once lowered and the stirring and mixing are performed again (FIG. 12).
), And the number of times of stirring can be ensured. The number of times of stirring N is obtained from the total number of rotations of the blades in a certain section during excavation and lifting, and is calculated by the following equation (3).
As shown in FIG. 14 (b), the reference value of the number of times of agitation N is determined from the result of conducting a test construction for each soil to be improved and examining the relationship between the number of times of agitation and the variation in the uniaxial compressive strength. .

【0062】[0062]

【数3】 (Equation 3)

【0063】(iv) 共回り防止翼の相対回転 掘進工程・先端部練り返し工程・引上工程において、図
7(b) に例示するように、攪拌ヘッド34に設けられた
相対回転検出器48(検出用マグネット48aと磁気式
近接スイッチ48b)からのON信号をカウントするこ
とで、共回り防止翼36と攪拌軸31の相対回転数を常
時計測する。共回り防止翼36が静止状態の場合には、
攪拌軸31の回転数と同じ相対回転数が得られるが、相
対回転数が0に近い場合(攪拌軸31と共回り防止翼3
6の回転数が同程度の場合)には、共回り防止翼36が
攪拌軸31と共に回転し、土と攪拌ヘッドが同期回転す
る土の共回り現象が発生していると判断される。この場
合、データ表示器51・警報報知器53により警報が発
せられ、修正施工が促される。この修正施工は攪拌ヘッ
ド34を引上げ、再掘進等を行えばよく、迅速な処理が
可能である。
(Iv) Relative rotation of the anti-corotating wings In the excavation step, the tip end kneading step, and the pulling-up step, as shown in FIG. 7B, a relative rotation detector 48 provided on the stirring head 34. By counting ON signals from (the detection magnet 48a and the magnetic proximity switch 48b), the relative rotation speed of the co-rotation prevention blade 36 and the stirring shaft 31 is constantly measured. When the co-rotation prevention wing 36 is stationary,
Although the same relative rotation speed as the rotation speed of the stirring shaft 31 is obtained, when the relative rotation speed is close to 0 (the rotation speed of the stirring shaft 31 and the co-
6 is about the same), it is determined that the co-rotation prevention blade 36 rotates together with the stirring shaft 31 and the co-rotation phenomenon of the soil and the soil in which the stirring head rotates synchronously has occurred. In this case, an alarm is issued by the data display 51 and the alarm notifier 53, and the repair work is encouraged. For this correction work, it is only necessary to pull up the stirring head 34 and carry out re-digging, etc., and quick processing is possible.

【0064】[0064]

【発明の効果】本発明は、以上のような構成からなるの
で、次のような効果を奏することができる。
Since the present invention has the above-described configuration, the following effects can be obtained.

【0065】(1) 少なくとも施工現場で得られたソイル
セメントコラムの施工データが施工現場管理者に送ら
れ、必要に応じて更にコア試料の画像データやコア試料
の圧縮強度データが施工現場管理者に送られ、施工現場
の施工管理・品質管理・労務管理等を施工現場管理者が
一括して集中管理することができ、管理にかかるコスト
および労力を低減することができ、また施工現場に必要
な指示を行うことで良好な地盤改良工を実施することが
できる。
(1) At least the construction data of the soil cement column obtained at the construction site is sent to the construction site manager, and the image data of the core sample and the compressive strength data of the core sample are further provided as necessary. The construction site manager can centrally manage the construction management, quality control, labor management, etc. of the construction site collectively, reducing the cost and labor required for management, and A good ground improvement work can be implemented by giving a proper instruction.

【0066】(2) 施工データを用いて管理を行うことに
より、各施工現場の施工管理・品質管理・労務管理等を
より正確にかつ迅速に実施することができる。なお、施
工管理や品質管理には、必要に応じて画像データ, 圧縮
強度データを用いて管理することにより、管理がより確
実なものとなる。
(2) By performing management using construction data, construction management, quality management, labor management, and the like at each construction site can be performed more accurately and promptly. In the construction management and quality management, management is performed using image data and compression strength data as needed, so that the management becomes more reliable.

【0067】(3) 従来の管理項目が、深度・速度・回転
数・吐出量・電流値と多数にわたっていたのに対し、本
発明の管理方法やシステムでは、単位掘進長毎の固化材
添加量・攪拌回数・攪拌ヘッドの仕事量に集約して管理
項目を減らすことができ、そのため管理が容易となる。
(3) In contrast to the conventional management items that are many in depth, speed, rotation speed, discharge amount, and current value, the management method and system according to the present invention use the solidification material addition amount per unit excavation length. -The number of agitation times and the work amount of the agitation head can be reduced to reduce the number of management items, thereby facilitating management.

【0068】(4) 本発明の管理方法やシステムでは、良
好な地盤改良に必要な固化材添加量・攪拌回数・攪拌ヘ
ッドの仕事量がディスプレイに各単位掘進長区間毎に逐
次表示することも可能になり、オペレーターに瞬時に伝
達されるため、正確な施工が可能となり、また不満足の
場合には警報も発せられるので安心して施工を行うこと
ができると共に、警報箇所を再施工することで良好な地
盤改良を行うことができる。
(4) In the management method and system of the present invention, the addition amount of the solidifying material, the number of times of agitation, and the work amount of the agitation head required for good ground improvement may be sequentially displayed on the display for each unit excavation length section. It is possible to be transmitted instantly to the operator, so accurate construction is possible, and if unsatisfied, an alarm is issued so that construction can be done with peace of mind, and good by reconstructing the alarm location Ground improvement can be performed.

【0069】(5) 本発明の管理方法やシステムでは、攪
拌ヘッドの掘進攪拌抵抗値(仕事量)を検出して支持層
への到達を判定するため、当初予想していなかった地層
の変化にも対応することができ、構造物の支持力不足を
解消することができる。
(5) According to the management method and system of the present invention, the arrival at the support layer is determined by detecting the excavation resistance (work amount) of the excavating stirring of the stirring head. Can be dealt with, and the shortage of the supporting force of the structure can be solved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の地盤改良の施工状態管理方法を実施す
るための施工管理の1例を示すブロック図である。
FIG. 1 is a block diagram showing an example of construction management for implementing a construction condition management method for ground improvement according to the present invention.

【図2】本発明の施工状態管理システムの1例を示す装
置構成図である。
FIG. 2 is an apparatus configuration diagram showing an example of a construction state management system of the present invention.

【図3】本発明の早期品質確認システムの1例を示す装
置構成図である。
FIG. 3 is an apparatus configuration diagram showing an example of an early quality check system of the present invention.

【図4】本発明の施工状態管理方法における管理項目の
1例を示すグラフである。
FIG. 4 is a graph showing one example of management items in the construction state management method of the present invention.

【図5】本発明の施工状態管理方法におけるディスプレ
表示例を示す図である。
FIG. 5 is a diagram showing a display example of display in the construction state management method of the present invention.

【図6】本発明の管理方法やシステムを実施する装置の
1例を示す装置構成図である。
FIG. 6 is an apparatus configuration diagram showing an example of an apparatus for implementing the management method and system of the present invention.

【図7】本発明の地盤改良機における攪拌ヘッド部分で
あり、(a) は側面図、(b) は共回り防止翼の相対回転を
検出するセンサーを示す部分断面図である。
FIGS. 7A and 7B are stirring head portions in the ground improvement machine of the present invention, in which FIG. 7A is a side view, and FIG. 7B is a partial cross-sectional view showing a sensor for detecting relative rotation of the co-rotation prevention blade.

【図8】本発明の管理方法やシステムによるデータの記
録例を示す図である。
FIG. 8 is a diagram showing an example of data recording by the management method and system of the present invention.

【図9】本発明の管理方法やシステムによるデータのチ
ャート式記録例を示す図である。
FIG. 9 is a diagram showing a chart-type recording example of data by the management method and system of the present invention.

【図10】本発明の管理方法やシステムによるデータの
解析例を示す図である。
FIG. 10 is a diagram showing an example of data analysis by the management method and system of the present invention.

【図11】本発明の管理方法やシステムによるフローチ
ャートである。
FIG. 11 is a flowchart according to the management method or system of the present invention.

【図12】本発明の地盤改良の施工例を深度−時間図で
示したグラフである。
FIG. 12 is a graph showing a construction example of ground improvement of the present invention in a depth-time diagram.

【図13】本発明における固化材添加量と現場平均強度
の関係を示すグラフである。
FIG. 13 is a graph showing the relationship between the amount of solidified material added and the average strength in-situ in the present invention.

【図14】(a) は本発明における攪拌回数と改良地盤の
一軸圧縮強度の変動係数の関係を示すグラフ、(b) は各
種土質に対する攪拌回数基準値を示す図である。
14A is a graph showing the relationship between the number of agitation and the coefficient of variation of the unconfined compressive strength of the improved ground in the present invention, and FIG. 14B is a diagram showing a reference value of the number of agitation for various soil types.

【図15】本発明における地盤のN値と仕事量の測定例
を示す図である。
FIG. 15 is a diagram showing a measurement example of the N value and work amount of the ground according to the present invention.

【図16】従来における地盤改良機の施工管理装置を示
す装置構成図である。
FIG. 16 is an apparatus configuration diagram showing a conventional construction management apparatus for a ground improvement machine.

【符号の説明】[Explanation of symbols]

1……施工現場管理者 2……管理装置 3……早期品質確認システム 6……ICカード 7……デジタルカメラ 8……施工現場のコンピュータ 11……地盤改良機 12……未固化採取治具 13……モールド 14……温水養生装置 15……簡易一軸圧縮試験器 16……ソイルセメントコラム 17……コア試料 18……供試体 30……リーダマスト 31……攪拌軸 32……駆動部 33……ワイヤー 34……攪拌ヘッド 35……掘削翼 36……共回り防止翼 37……攪拌翼 40……プラント 41……セメントミルク 42……スラリーポンプ 43……吐出口 44……深度(速度)検出器 45……回転数検出器 46……電流検出器(または油圧力検出器) 47……吐出量(流量)検出器 48……相対回転検出器 48a…検出用マグネット 48b…磁気式近接スイッチ 49……重機計測盤 50……プラント計測盤 51……データ表示器 52……遠隔操作盤 53……警報報知器 54……通話器 55……日報作成システム 56……プリンター 1 ... construction site manager 2 ... management device 3 ... early quality check system 6 ... IC card 7 ... digital camera 8 ... construction site computer 11 ... ground improvement machine 12 ... unsolidified sampling jig 13: Mold 14: Hot water curing device 15: Simple uniaxial compression tester 16: Soil cement column 17: Core sample 18: Specimen 30: Leader mast 31: Stirring shaft 32: Drive unit 33 … Wire 34… Stirring head 35… Drilling wing 36… Co-rotating wing 37… Stirring wing 40… Plant 41… Cement milk 42… Slurry pump 43… Discharge port 44… Depth (speed) ) Detector 45 Rotational speed detector 46 Current detector (or hydraulic pressure detector) 47 Discharge amount (flow rate) detector 48 Relative rotation detector 48a Magnet for detection G 48b: Magnetic proximity switch 49: Heavy equipment measuring panel 50: Plant measuring panel 51: Data display 52: Remote control panel 53: Alarm annunciator 54: Telephone 55: Daily report creation system 56 …printer

───────────────────────────────────────────────────── フロントページの続き (72)発明者 村山 篤史 東京都港区赤坂6丁目13番7号 株式会社 テノックス (72)発明者 山根 利明 東京都港区赤坂6丁目13番7号 株式会社 テノックス (72)発明者 日比野 信一 東京都港区赤坂6丁目13番7号 株式会社 テノックス (72)発明者 堀切 節 東京都港区赤坂6丁目13番7号 株式会社 テノックス Fターム(参考) 2D040 AB05 BA08 BC03 BD05 CA01 CB03 DB07 EA18 EA21 EB01 FA08 GA02  ────────────────────────────────────────────────── ─── Continued on the front page (72) Inventor Atsushi Murayama 6-13-7 Akasaka, Minato-ku, Tokyo Tenox Corporation (72) Inventor Toshiaki Yamane 6-13-7 Akasaka, Minato-ku, Tokyo Tenox Corporation ( 72) Inventor Shinichi Hibino 6-13-7 Akasaka, Minato-ku, Tokyo Tenox Co., Ltd. (72) Inventor Horikiri 6-13-7 Akasaka, Minato-ku, Tokyo Tenox F-term (reference) 2D040 AB05 BA08 BC03 BD05 CA01 CB03 DB07 EA18 EA21 EB01 FA08 GA02

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 少なくとも掘削翼と攪拌翼を装備した攪
拌ヘッドを先端に使用して地盤中を掘進しつつ、固化材
等と水を混合したスラリーを吐出し、前記攪拌翼で掘削
土とスラリーを攪拌混合することにより地盤改良を行う
際の施工状態の管理方法であって、 施工現場で少なくとも単位掘進長毎の攪拌ヘッドの仕事
量と単位掘進長毎の攪拌回数と単位掘進長毎の固化材添
加量またはスラリー吐出量を求める施工データ取得工程
と、 前記施工データから施工現場管理者が施工状態を把握す
る工程よりなることを特徴とする地盤改良の施工状態管
理方法。
1. A slurry in which a solidified material or the like is mixed with water is discharged while excavating in the ground using at least a stirring head equipped with a drilling blade and a stirring blade at a tip, and excavated soil and slurry are discharged by the stirring blade. Is a method of managing the construction state when performing ground improvement by stirring and mixing the work, at least at the construction site, the work amount of the stirring head per unit excavation length, the number of agitation times per unit excavation length, and the solidification per unit excavation length A construction state management method for ground improvement, comprising: a construction data acquisition step of obtaining a material addition amount or a slurry discharge amount; and a step of a construction site manager grasping a construction state from the construction data.
【請求項2】 少なくとも掘削翼と攪拌翼を装備した攪
拌ヘッドを先端に使用して地盤中を掘進しつつ、固化材
等と水を混合したスラリーを吐出し、前記攪拌翼で掘削
土とスラリーを攪拌混合することにより地盤改良を行う
際の施工状態の管理方法であって、 施工現場で少なくとも単位掘進長毎の攪拌ヘッドの仕事
量と単位掘進長毎の攪拌回数と単位掘進長毎の固化材添
加量またはスラリー吐出量を求める施工データ取得工程
と、 施工現場で採取した未固化のコア試料をデジタル画像で
記録する工程と、 前記施工データと前記コア試料の画像データから施工現
場管理者が施工状態を把握する工程よりなることを特徴
とする地盤改良の施工状態管理方法。
2. Excavating in the ground using at least a stirring head equipped with a drilling wing and a stirring blade at the tip, discharging a slurry in which a solidified material and the like are mixed with water, and excavating soil and slurry by the stirring blade. Is a method of managing the construction state when performing ground improvement by stirring and mixing the work, at least at the construction site, the work amount of the stirring head per unit excavation length, the number of agitation times per unit excavation length, and the solidification per unit excavation length A construction data acquisition step for determining the material addition amount or slurry discharge amount, a step of recording an unsolidified core sample collected at the construction site in a digital image, and a construction site manager from the construction data and the core sample image data. A construction state management method for ground improvement, comprising a step of grasping the construction state.
【請求項3】 少なくとも掘削翼と攪拌翼を装備した攪
拌ヘッドを先端に使用して地盤中を掘進しつつ、固化材
等と水を混合したスラリーを吐出し、前記攪拌翼で掘削
土とスラリーを攪拌混合することにより地盤改良を行う
際の施工状態の管理方法であって、 施工現場で少なくとも単位掘進長毎の攪拌ヘッドの仕事
量と単位掘進長毎の攪拌回数と単位掘進長毎の固化材添
加量またはスラリー吐出量を求める施工データ取得工程
と、 施工現場で採取した未固化のコア試料をデジタル画像で
記録する工程と、 前記未固化のコア試料を促進養生して圧縮強度の測定を
行う工程と、 前記施工データと前記コア試料の画像データと前記圧縮
強度のデータから施工現場管理者が施工状態を把握する
工程よりなることを特徴とする地盤改良の施工状態管理
方法。
3. A slurry in which a solidified material or the like is mixed with water is discharged while digging through the ground by using a stirring head equipped with at least a drilling blade and a stirring blade at a tip, and excavated soil and slurry are mixed by the stirring blade. Is a method of managing the construction state when performing ground improvement by stirring and mixing the work, at least at the construction site, the work amount of the stirring head per unit excavation length, the number of agitation times per unit excavation length, and the solidification per unit excavation length A process of acquiring construction data to determine the amount of material added or the amount of slurry discharged; a process of recording an unsolidified core sample collected at the construction site in a digital image; and a process of accelerating curing of the unsolidified core sample and measuring compressive strength. Performing, and the construction state management of the ground improvement characterized by comprising a step in which a construction site manager grasps the construction state from the construction data, the image data of the core sample, and the data of the compressive strength. Law.
【請求項4】 少なくとも掘削翼と攪拌翼を装備した攪
拌ヘッドを先端に使用して地盤中を掘進しつつ、固化材
等と水を混合したスラリーを吐出し、前記攪拌翼で掘削
土とスラリーを攪拌混合することにより地盤改良を行う
際の施工状態の管理システムであって、 施工現場で少なくとも単位掘進長毎の攪拌ヘッドの仕事
量と単位掘進長毎の攪拌回数と単位掘進長毎の固化材添
加量またはスラリー吐出量からなる施工データを求めて
表示手段に表示できる管理装置と、 前記施工データから施工現場管理者が施工状態を把握で
きる手段を備えていることを特徴とする地盤改良の施工
状態管理システム。
4. Excavating in the ground using at least a stirring head equipped with a drilling blade and a stirring blade at the tip, discharging a slurry in which a solidified material and the like are mixed with water, and excavating soil and slurry by the stirring blade. This is a system for managing the construction state when performing ground improvement by mixing and mixing the work. At the construction site, at least the work amount of the stirring head per unit excavation length, the number of agitation times per unit excavation length, and the solidification per unit excavation length A management device capable of obtaining construction data consisting of a material addition amount or a slurry discharge amount and displaying the construction data on a display means, and a ground improvement method comprising: a construction site manager capable of grasping a construction state from the construction data by a construction site manager. Construction status management system.
【請求項5】 少なくとも掘削翼と攪拌翼を装備した攪
拌ヘッドを先端に使用して地盤中を掘進しつつ、固化材
等と水を混合したスラリーを吐出し、前記攪拌翼で掘削
土とスラリーを攪拌混合することにより地盤改良を行う
際の施工状態の管理システムであって、 施工現場で少なくとも単位掘進長毎の攪拌ヘッドの仕事
量と単位掘進長毎の攪拌回数と単位掘進長毎の固化材添
加量またはスラリー吐出量からなる施工データを求めて
表示手段に表示できる管理装置と、 施工現場で採取した未固化のコア試料をデジタル画像で
記録できる手段と、 前記施工データと前記コア試料の画像データから施工現
場管理者が施工状態を把握できる手段を備えていること
を特徴とする地盤改良の施工状態管理システム。
5. Excavation in the ground using a stirring head equipped with at least a drilling blade and a stirring blade at the tip, discharging a slurry in which a solidified material and the like are mixed with water, and excavating soil and slurry by the stirring blade. This is a system for managing the construction state when performing ground improvement by mixing and mixing the work. At the construction site, at least the work amount of the stirring head per unit excavation length, the number of agitation times per unit excavation length, and the solidification per unit excavation length A management device capable of obtaining construction data consisting of a material addition amount or a slurry discharge amount and displaying the same on a display means; a means capable of recording an unsolidified core sample collected at a construction site in a digital image; and A construction condition management system for ground improvement, comprising means for allowing a construction site manager to grasp the construction condition from image data.
【請求項6】 少なくとも掘削翼と攪拌翼を装備した攪
拌ヘッドを先端に使用して地盤中を掘進しつつ、固化材
等と水を混合したスラリーを吐出し、前記攪拌翼で掘削
土とスラリーを攪拌混合することにより地盤改良を行う
際の施工状態の管理システムであって、 施工現場で少なくとも単位掘進長毎の攪拌ヘッドの仕事
量と単位掘進長毎の攪拌回数と単位掘進長毎の固化材添
加量またはスラリー吐出量からなる施工データを求めて
表示手段に表示し記憶媒体に記録できる管理装置と、 施工現場で採取した未固化のコア試料をデジタル画像で
記録できる手段と、 前記未固化のコア試料を促進養生して圧縮強度の測定を
行うための手段と、 前記施工データと前記コア試料の画像データと前記圧縮
強度のデータから施工現場管理者が施工状態を把握でき
る手段を備えていることを特徴とする地盤改良の施工状
態管理システム。
6. A slurry in which a solidified material or the like is mixed with water is discharged while digging in the ground using a stirring head equipped with at least a drilling blade and a stirring blade at a tip, and excavated soil and slurry are mixed by the stirring blade. This is a system for managing the construction state when performing ground improvement by mixing and mixing the work. At the construction site, at least the work amount of the stirring head per unit excavation length, the number of agitation times per unit excavation length, and the solidification per unit excavation length A management device capable of obtaining construction data consisting of a material addition amount or a slurry discharge amount and displaying the same on a display means and recording it on a storage medium; a means capable of recording an unsolidified core sample collected at a construction site in a digital image; Means for accelerating curing of the core sample and measuring the compressive strength; and a construction site manager grasping the construction state from the construction data, the image data of the core sample, and the data of the compressive strength. Construction state management system of ground improvement, characterized in that it comprises a means capable.
JP2000156106A 2000-05-26 2000-05-26 Executed condition control method for ground improvement and executed condition control system Pending JP2001336142A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000156106A JP2001336142A (en) 2000-05-26 2000-05-26 Executed condition control method for ground improvement and executed condition control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000156106A JP2001336142A (en) 2000-05-26 2000-05-26 Executed condition control method for ground improvement and executed condition control system

Publications (1)

Publication Number Publication Date
JP2001336142A true JP2001336142A (en) 2001-12-07

Family

ID=18660938

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000156106A Pending JP2001336142A (en) 2000-05-26 2000-05-26 Executed condition control method for ground improvement and executed condition control system

Country Status (1)

Country Link
JP (1) JP2001336142A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014156730A (en) * 2013-02-15 2014-08-28 Japan Pile Corp Pile construction management system
JP2015140551A (en) * 2014-01-28 2015-08-03 日本車輌製造株式会社 construction machinery
JP2017066795A (en) * 2015-09-30 2017-04-06 株式会社ワイビーエム Co-rotation detector and co-rotation monitoring method of ground improvement blade
JP6293352B1 (en) * 2017-12-13 2018-03-14 株式会社大林組 Ground improvement method and ground improvement device
JP2020084501A (en) * 2018-11-21 2020-06-04 株式会社ワイビーエム Diagram representation method of pile installation data
JP2021056021A (en) * 2019-09-27 2021-04-08 太平洋セメント株式会社 Quality evaluation method for improved ground
CN114036625A (en) * 2021-12-09 2022-02-11 中冶建筑研究总院(深圳)有限公司 Intelligent construction method and system suitable for in-situ reinforcement of large-area soft foundation
JP7104228B1 (en) 2021-11-19 2022-07-20 小野田ケミコ株式会社 Flow state detection device and detection method for soil to be improved in the ground improvement method
JP2023075899A (en) * 2021-11-19 2023-05-31 小野田ケミコ株式会社 Method and device for detecting flow state of soil to be improved in ground improvement construction method

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014156730A (en) * 2013-02-15 2014-08-28 Japan Pile Corp Pile construction management system
JP2015140551A (en) * 2014-01-28 2015-08-03 日本車輌製造株式会社 construction machinery
JP2017066795A (en) * 2015-09-30 2017-04-06 株式会社ワイビーエム Co-rotation detector and co-rotation monitoring method of ground improvement blade
JP6293352B1 (en) * 2017-12-13 2018-03-14 株式会社大林組 Ground improvement method and ground improvement device
JP2019105084A (en) * 2017-12-13 2019-06-27 株式会社大林組 Ground improvement method and ground improvement device
JP7174404B2 (en) 2018-11-21 2022-11-17 株式会社ワイビーエム Diagram representation method of pile construction data
JP2020084501A (en) * 2018-11-21 2020-06-04 株式会社ワイビーエム Diagram representation method of pile installation data
JP2021056021A (en) * 2019-09-27 2021-04-08 太平洋セメント株式会社 Quality evaluation method for improved ground
JP7401238B2 (en) 2019-09-27 2023-12-19 太平洋セメント株式会社 Quality evaluation method of improved ground
JP7104228B1 (en) 2021-11-19 2022-07-20 小野田ケミコ株式会社 Flow state detection device and detection method for soil to be improved in the ground improvement method
JP2023075899A (en) * 2021-11-19 2023-05-31 小野田ケミコ株式会社 Method and device for detecting flow state of soil to be improved in ground improvement construction method
JP2023075409A (en) * 2021-11-19 2023-05-31 小野田ケミコ株式会社 Method and device for detecting flow state of soil to be improved in ground improvement construction method
JP7307242B2 (en) 2021-11-19 2023-07-11 小野田ケミコ株式会社 Apparatus and method for detecting flow state of soil to be improved in ground improvement method
CN114036625A (en) * 2021-12-09 2022-02-11 中冶建筑研究总院(深圳)有限公司 Intelligent construction method and system suitable for in-situ reinforcement of large-area soft foundation
CN114036625B (en) * 2021-12-09 2024-04-19 中冶建筑研究总院(深圳)有限公司 Intelligent construction method and system suitable for in-situ reinforcement of large-area soft foundation

Similar Documents

Publication Publication Date Title
AU2020101353A4 (en) Indoor drilling perception test system for mechanical properties of rock masses
JP3437108B2 (en) Management method of ground improvement method and management device of ground improvement machine
CN210104818U (en) Intelligent construction model test device for cement mixing pile
CN112365222B (en) Intelligent construction informatization system for cast-in-situ bored pile
US9809934B2 (en) Method for characterizing the seat of a railroad track, device for viewing the inside of a ground and assembly for characterizing the seat of a railroad track comprising such a device
CN106638719B (en) Bored pile piling quality automatic monitoring controller and method
JP2001336142A (en) Executed condition control method for ground improvement and executed condition control system
CN110230503B (en) Automatic grouting method for grouting trolley and grouting trolley
JP2001336143A (en) Executed condition control method for ground improvement and executed condition control system
CN106840265A (en) A kind of scaffold safety pre-warning system
JP2002348868A (en) Construction method for foot protection layer of pile hole, and device and method for managing execution of work for foundation pile
CN109736300A (en) A kind of intelligence cement-soil mixing pile machine
CN109811807A (en) Uniform thickness cement-earth underground continuous wall engineering method simulation test device and test method
CN110185383A (en) A kind of small indoor drilling parameter device for quick collecting
KR101478906B1 (en) auto measurement equipment of standard penetration test
KR100870722B1 (en) Deep cement mixing device for sea construction and construction work method using therewith
US20220260466A1 (en) Systems and methods for determining concrete strength
JP2003097181A (en) Plastic fluidization measuring method of mud and shield machine having plastic fluidization measuring device
JP3753240B2 (en) Management method for ground improvement method and management device for ground improvement machine
CN109162280A (en) A kind of underwater gliders absolute altitude automation control method
JP2021036103A (en) Quality prediction method of improvement body
JP2002038463A (en) Indicating device of executed condition in ground inprovement method
CN113832808A (en) Thin slurry mixture mixing device and method
CN107542080B (en) Recording method for compacted graded broken stone pile driving construction
JP3893572B2 (en) Sand pile construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060804

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080229

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080311

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20080701