JP2001234553A - Construction method for storage equipment for high pressure gas in bedrock - Google Patents

Construction method for storage equipment for high pressure gas in bedrock

Info

Publication number
JP2001234553A
JP2001234553A JP2000043931A JP2000043931A JP2001234553A JP 2001234553 A JP2001234553 A JP 2001234553A JP 2000043931 A JP2000043931 A JP 2000043931A JP 2000043931 A JP2000043931 A JP 2000043931A JP 2001234553 A JP2001234553 A JP 2001234553A
Authority
JP
Japan
Prior art keywords
pressure
lining layer
concrete
bedrock
buffer layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000043931A
Other languages
Japanese (ja)
Inventor
Tomoyuki Shimura
友行 志村
Kunifumi Takeuchi
邦文 武内
Daihachi Okai
大八 岡井
Hisafumi Kagawa
尚史 香川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Osaka Gas Co Ltd
Original Assignee
Obayashi Corp
Osaka Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp, Osaka Gas Co Ltd filed Critical Obayashi Corp
Priority to JP2000043931A priority Critical patent/JP2001234553A/en
Publication of JP2001234553A publication Critical patent/JP2001234553A/en
Pending legal-status Critical Current

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To reduce construction period and cost. SOLUTION: The storage structure is provided with a lining layer 14 formed at the internal face of a cave 12, a pressure-resistant buffer layer 16, and an air-tight material 18, formed in bedrock 10. When constructing the storage structure, the bedrock is excavated to form the cave 12, and further, the lining layer 14 is formed to cover the excavated face of the cave 12. After the lining layer 14 has been formed, forms are installed in the inside of the lining layer 14a and reinforcements 24 and a joint material 26 dividing concrete to be placed thereafter into a plurality of sections along the peripheral and axial directions are arranged. Then, concrete is placed in the space 22. When the forms are removed, the storage structure in the bedrock is constructed as the outer peripheral edge of the air-tight material 18 is welded to the joint material 26.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、高圧ガスの岩盤
内貯蔵設備の構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a storage facility for high-pressure gas in rock.

【0002】[0002]

【従来の技術】都市ガスなどの気体を岩盤内に高圧で貯
蔵するための設備の構築方法として、例えば、岩盤内に
トンネル工法により空洞部を掘削形成し、その内面に、
鉄筋コンクリート製のセグメントを裏込め固定し、セグ
メントの内面に金属ライニングなどの気密材を設ける方
法が検討されている。
2. Description of the Related Art As a method of constructing a facility for storing gas such as city gas at high pressure in a rock, for example, a hollow portion is excavated and formed in a rock by a tunnel construction method,
A method of back-fixing a reinforced concrete segment and providing an airtight material such as a metal lining on the inner surface of the segment has been studied.

【0003】このような構築方法で構築される貯蔵設備
では、気密性を金属ライニングなどの気密材で確保し、
耐圧性を岩盤で保持させるとともに、セグメントおよび
裏込め層で内圧の均等な伝達を図る複合構造になってい
る。
[0003] In a storage facility constructed by such a construction method, airtightness is ensured by an airtight material such as a metal lining.
It has a composite structure that allows pressure resistance to be maintained by the bedrock, and even transmission of internal pressure by the segments and the backfill layer.

【0004】しかしながら、このような高圧ガスの岩盤
内貯蔵設備の構築方法には、以下に説明する技術的な課
題があった。
[0004] However, such a method of constructing a storage facility for high-pressure gas in a rock has the following technical problems.

【0005】[0005]

【発明が解決しようとする課題】すなわち、岩盤内貯蔵
設備は、岩盤内の空洞部を掘削した後に、その内面側に
沿ってセグメントを設置して、これを裏込め材で固定さ
せた後に、気密材を後施工で設置する施工手順なので、
セグメントを所定の位置に設置する作業が煩雑で、工期
が長くなり、工費も嵩むという問題があった。
That is, the storage facility in the bedrock, after excavating a cavity in the bedrock, installs a segment along the inner surface side and fixes it with backfill material. Since it is a construction procedure to install the airtight material in post-construction,
There is a problem that the work of installing the segment at a predetermined position is complicated, the construction period is lengthened, and the construction cost is increased.

【0006】本発明は、このような問題点に鑑みてなさ
れたものであって、その目的とするところは、工期の短
縮と、工費の低減とが達成される高圧ガスの岩盤内貯蔵
設備の構築方法を提供することにある。
The present invention has been made in view of the above problems, and an object of the present invention is to provide a high-pressure gas storage facility for a high-pressure gas in a rock, which can shorten the construction period and reduce the construction cost. It is to provide a construction method.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するため
に、本発明は、岩盤掘削により形成した空洞部の内面に
覆工層を形成し、前記覆工層の内面側に所定の空間部を
設けて型枠を設置した後に、前記空間部内にコンクリー
トを打設して、前記覆工層を覆う耐圧緩衝層を形成し、
前記型枠を脱型した後に、前記耐圧緩衝層の内面側に金
属ライニングなどの気密材を覆設する高圧ガスの岩盤内
貯蔵設備の構築方法であって、前記コンクリートを打設
する前に、前記空間部内に所定の配筋を施すとともに、
打設された前記コンクリートを周および軸方向に沿って
複数に分断する目地材を設置し、前記気密材の周縁を前
記目地材に固着して、前記耐圧緩衝層の内面側に覆設す
るようにした。このように構成した高圧ガスの岩盤内貯
蔵設備の構築方法によれば、耐圧緩衝層は、型枠を用い
て施工現場で打設形成するので、予め工場生産するセグ
メントを用いる場合よりも、工期を短縮することがで
き、その結果工費の低減も図れるし、専用の製作ヤード
も必要としない。また、本発明の岩盤内貯蔵設備の構築
方法では、型枠で画成した空間部内に所定の配筋を施す
とともに、打設されたコンクリートを周および軸方向に
沿って複数に分断する目地材を設置し、気密材の周縁を
目地材に固着して、耐圧緩衝層の内面側に覆設する。こ
のようにして気密材を目地材に固着すると、少なくとも
周方向において、気密材は、目地材の部分で分断されて
いる。このため、貯蔵設備内に高圧ガスを収容した時
に、気密材および耐圧緩衝層の内径を広げようとする力
が作用した際に、目地材の部分で変形することが可能に
なり、気密材や耐圧緩衝層に損傷を及ぼすことなく、変
形追随性を確保することができる。前記型枠には、環状
に形成された前記覆工層の全内周を覆う全断面型枠を用
いることができる。このような型枠を用いると、より一
層施工性が向上する。
According to the present invention, a lining layer is formed on an inner surface of a hollow portion formed by rock excavation, and a predetermined space portion is formed on an inner surface side of the lining layer. After installing the formwork, concrete is poured into the space to form a pressure-resistant buffer layer that covers the lining layer,
After removing the mold, a method for constructing a high-pressure gas storage facility in a rock mass for covering an airtight material such as a metal lining on the inner surface side of the pressure-resistant buffer layer, and before placing the concrete, While applying a predetermined reinforcing bar in the space,
A joint material for dividing the poured concrete into a plurality of pieces along the circumferential and axial directions is installed, and a peripheral edge of the airtight material is fixed to the joint material, and is covered on the inner surface side of the pressure-resistant buffer layer. I made it. According to the construction method of the high-pressure gas in-bed storage facility configured as described above, the pressure-resistant buffer layer is cast and formed at the construction site using the formwork. , And as a result, the construction cost can be reduced, and a special production yard is not required. Further, in the method for constructing a storage facility in a rock according to the present invention, a joint material for applying a predetermined reinforcing bar in a space defined by a formwork and dividing a poured concrete into a plurality of pieces along a circumferential direction and an axial direction. Is installed, the periphery of the airtight material is fixed to the joint material, and the airtight material is covered on the inner surface side of the pressure-resistant buffer layer. When the airtight material is fixed to the joint material in this way, the airtight material is divided at least in the circumferential direction at the joint material portion. Therefore, when a high-pressure gas is accommodated in the storage facility, when a force acting to expand the inner diameter of the airtight material and the pressure-resistant buffer layer acts, it becomes possible to deform the joint material, and the airtight material and Deformation followability can be ensured without damaging the pressure-resistant buffer layer. As the mold, a full-section mold that covers the entire inner periphery of the lining layer formed in an annular shape can be used. Use of such a mold further improves workability.

【0008】[0008]

【発明の実施の形態】以下、本発明の好適な実施の形態
について、添付図面に基づいて詳細に説明する。図1〜
図4は、本発明にかかる高圧ガスの岩盤内貯蔵設備の構
築方法の一実施例を示している。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings. Figure 1
FIG. 4 shows an embodiment of a method for constructing a high-pressure gas in-rock storage facility according to the present invention.

【0009】本実施例の構築方法で構築される岩盤内貯
蔵設備は、図4にその鉛直断面を示すように、岩盤10
内に形成された空洞部12の内面に形成された覆工層1
4と、この覆工層14の内面側に、これを覆うようにし
て形成される耐圧緩衝層16と、耐圧緩衝層16の内面
側に設けられる気密材18とを有している。
The storage facility in the bedrock constructed by the construction method of the present embodiment has a bedrock 10 as shown in FIG.
Lining layer 1 formed on the inner surface of cavity 12 formed therein
4, a pressure-resistant buffer layer 16 formed on the inner surface of the lining layer 14 so as to cover it, and an airtight material 18 provided on the inner surface of the pressure-resistant buffer layer 16.

【0010】このように構造の岩盤内貯蔵設備を構築す
る際には、まず、図1に示すように、岩盤10に空洞部
12が掘削形成される。この空洞部12は、例えば、ト
ンネルボーリングマシンなどで掘削される。
[0010] When constructing a storage facility in a rock mass having such a structure, first, as shown in FIG. The hollow portion 12 is excavated by, for example, a tunnel boring machine.

【0011】所定形状の空洞部12が形成されると、空
洞部12の掘削面を覆うようにして覆工層14が形成さ
れる。この覆工層14は、例えば、モルタルやコンクリ
ートを吹付けることにより所定厚みに形成され、本実施
例の場合には、鉛直断面が環状になっている。
When the cavity 12 having a predetermined shape is formed, a lining layer 14 is formed so as to cover the excavated surface of the cavity 12. The lining layer 14 is formed to have a predetermined thickness by, for example, spraying mortar or concrete, and in the case of the present embodiment, the vertical cross section is annular.

【0012】覆工層14が形成されると、次に、図2に
示すように、覆工層14の内面側に型枠20が設置され
る。同図に示した型枠20は、相互にヒンジ結合された
クラウン部20a,サイド部20bおよびインバート部
20cを備えた、いわゆる、全断面セントル型枠であっ
て、縮径および拡径自在な構造になっている。
When the lining layer 14 is formed, next, as shown in FIG. 2, a mold 20 is placed on the inner surface side of the lining layer 14. The formwork 20 shown in the figure is a so-called full-section centre formwork provided with a crown portion 20a, a side portion 20b, and an invert portion 20c hinged to each other, and has a structure that can be reduced in diameter and expanded in diameter. It has become.

【0013】この型枠20を設置する際には、覆工層1
4の内面から所定の間隔を隔てて設置し、これらの間に
空間部22を画成する。このように画成した空間部22
内には、あらかじめ籠状に組立てられた配筋24が施さ
れる。
When installing the formwork 20, the lining layer 1
4 are set at a predetermined distance from the inner surface of the inner surface 4 and a space 22 is defined therebetween. The space 22 defined in this way
Inside, reinforcing bars 24 assembled in a cage shape in advance are provided.

【0014】また,空間部22内には,この配筋24と
ともに、この後に打設されるコンクリートを周および軸
方向に沿って複数に分断する目地材26が設置される。
本実施例の目地材26は、所定厚みのチャンネル鋼鈑を
2枚重ね合わせたものであって、ほぼ空間部22の厚み
に相当する長さを有していて、鋼鈑同士は、単に平坦な
背面同士を相互に接触させた状態になっている。なお、
目地材26は、このような形状の鋼材に限ることはな
く、例えば、L字形形状の鋼材や硬質プラスチックスな
どてあってもよい。
In the space 22, together with the reinforcing bars 24, a joint material 26 for dividing concrete to be cast thereafter into a plurality of pieces along the circumferential and axial directions is installed.
The joint material 26 of the present embodiment is obtained by stacking two channel steel plates having a predetermined thickness, has a length substantially corresponding to the thickness of the space 22, and the steel plates are simply flat. The rear surfaces are in contact with each other. In addition,
The joint material 26 is not limited to a steel material having such a shape, and may be, for example, an L-shaped steel material or hard plastics.

【0015】また、各目地材26は、コンクリートの打
設完了後に、型枠20を脱型する際には、型枠20から
分離するようになっている。空間部22内に配筋24お
よび目地材26の設置が完了すると、空間部22内にコ
ンクリートが打設される。
Further, the joint members 26 are separated from the form 20 when the form 20 is removed after the concrete has been poured. When the installation of the reinforcing bars 24 and the joint members 26 in the space 22 is completed, concrete is poured into the space 22.

【0016】このコンクリートの打設に当たっては、目
地材26でコンクリートの流動が阻止されるので、目地
材26で区画されている部分毎に、コンクリートを充填
することになる。
At the time of casting the concrete, since the flow of the concrete is prevented by the joint material 26, the concrete is filled in each portion partitioned by the joint material 26.

【0017】そして、打設したコンクリートの強度が発
現された段階で型枠20が脱型される。型枠20を脱型
すると、鉄筋コンクリート製の耐圧緩衝層16が覆工層
14の内面側に覆設形成されるが、この耐圧緩衝層16
は、図3に示すように、目地材26により周および軸方
向に沿って複数に分断されたセグメント状になってい
る。
Then, the mold 20 is released at the stage when the strength of the poured concrete is developed. When the mold 20 is removed from the mold, a pressure-resistant buffer layer 16 made of reinforced concrete is formed on the inner surface side of the lining layer 14.
As shown in FIG. 3, each of the segments is divided into a plurality of segments along the circumferential and axial directions by the joint material 26.

【0018】このような耐圧緩衝層16が得られると、
目地材26の先端をハツリ出して、その金属面を露出さ
せ、鋼鈑などの金属ライニングからなる気密材18の外
周縁を目地材26に溶着すると、図4に示した構造の岩
盤内貯蔵設備が構築される。
When such a pressure-resistant buffer layer 16 is obtained,
When the tip of the joint material 26 is cut out to expose its metal surface, and the outer peripheral edge of the hermetic material 18 made of a metal lining such as a steel plate is welded to the joint material 26, the rock storage facility having the structure shown in FIG. Is constructed.

【0019】さて、以上のように構成された岩盤内貯蔵
設備の構築方法によれば、耐圧緩衝層16は、型枠20
を用いて施工現場で打設形成するので、セグメントを用
いる場合よりも工期を短縮することができ、その結果工
費の低減も図れる。
Now, according to the construction method of the in-rock storage facility constructed as described above, the pressure-resistant buffer layer 16 is
Since it is cast and formed at a construction site using, the construction period can be shortened as compared with the case of using segments, and as a result, the construction cost can be reduced.

【0020】この場合、セグメントを用いる場合のよう
に、特注型枠や専用の製作ヤードが不要になり、また、
現場搬入部材の重量も低減するので、これらの点から
も、工期の短縮と工費の低減に寄与する。
In this case, unlike the case of using a segment, a custom-made formwork and a dedicated manufacturing yard are not required.
Since the weight of the on-site carrying member is also reduced, these points also contribute to shortening the construction period and the cost.

【0021】また、本発明の岩盤内貯蔵設備の構築方法
では、型枠20で画成した空間部22内に所定の配筋2
4を施すとともに、打設されたコンクリートを周および
軸方向に沿って複数に分断する目地材26を設置し、気
密材18の周縁を目地材26に溶着して、耐圧緩衝層1
6の内面側に覆設する。
Further, according to the method for constructing a storage facility in a bedrock of the present invention, a predetermined reinforcing arrangement 2 is provided in a space 22 defined by a formwork 20.
4, a joint material 26 for dividing the poured concrete into a plurality of pieces along the circumferential and axial directions is installed, and the peripheral edge of the airtight material 18 is welded to the joint material 26 to form the pressure-resistant buffer layer 1.
6 on the inner surface side.

【0022】このようにして気密材18を目地材26に
溶着すると、少なくとも周方向において、気密材18
は、目地材26の部分で分断されている。
When the airtight material 18 is welded to the joint material 26 in this manner, at least in the circumferential direction, the airtight material 18 is welded.
Is divided at the joint material 26.

【0023】このため、貯蔵設備内に高圧ガスを収容し
た時に、気密材18および耐圧緩衝層16の内径を広げ
ようとする作用力が作用した際に、目地材26の部分
で、両者間の間隔が広がることで、変形可能になってい
る。
For this reason, when a high-pressure gas is accommodated in the storage facility and an action force for expanding the inner diameters of the airtight material 18 and the pressure-resistant buffer layer 16 is applied, the joint material 26 and the joint material 26 By increasing the distance, it can be deformed.

【0024】このため、気密材18や耐圧緩衝層16に
損傷を及ぼすことなく、変形追随性を確保することがで
きる。
For this reason, the deformation followability can be ensured without damaging the airtight material 18 and the pressure-resistant buffer layer 16.

【0025】また、本実施例の場合には、型枠20に
は、環状に形成された覆工層14の全内周を覆う全断面
型枠を用いるので、より一層施工性が向上する。
Further, in the case of this embodiment, since the mold 20 is a full-section mold that covers the entire inner periphery of the lining layer 14 formed in a ring shape, the workability is further improved.

【0026】なお、上記実施例では、本発明にかかる構
築方法を円形断面の岩盤内貯蔵設備に適用した場合を例
示したが、本発明の実施は、これに限られることはな
く、例えば、楕円断面や多角形断面の貯蔵設備にも適用
できる。
In the above embodiment, the case where the construction method according to the present invention is applied to a storage facility in a rock having a circular cross section is exemplified. However, the present invention is not limited to this. It can also be applied to storage facilities with cross sections or polygonal cross sections.

【0027】[0027]

【発明の効果】以上、詳細に説明したように、本発明に
かかる高圧ガスの岩盤内貯蔵設備の構築方法によれば、
工期の短縮と、工費の低減とが達成される。
As described above in detail, according to the method for constructing a high-pressure gas in-rock storage facility according to the present invention,
Shortening of the construction period and reduction of the construction cost are achieved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明にかかる高圧ガスの岩盤内貯蔵設備の構
築方法の一実施例を示す施工初期段階の縦断面図であ
る。
FIG. 1 is a longitudinal sectional view showing an embodiment of a method for constructing a high-pressure gas in-rock storage facility according to the present invention at an initial stage of construction.

【図2】図1に引き続いて行われる工程の断面説明図で
ある。
FIG. 2 is an explanatory sectional view of a step performed subsequent to FIG. 1;

【図3】図2に引き続いて行われる工程の断面説明図で
ある。
FIG. 3 is an explanatory cross-sectional view of a step performed subsequent to FIG. 2;

【図4】図3に引き続いて行われる工程の断面説明図で
ある。
FIG. 4 is an explanatory cross-sectional view of a step performed subsequent to FIG. 3;

【符号の説明】[Explanation of symbols]

10 岩盤 12 空洞部 14 覆工層 16 耐圧緩衝層 18 気密材 20 型枠 22 空間部 24 配筋 26 目地材 DESCRIPTION OF SYMBOLS 10 Rock 12 Cavity part 14 Lining layer 16 Pressure-resistant buffer layer 18 Airtight material 20 Formwork 22 Space part 24 Arrangement 26 Joint material

───────────────────────────────────────────────────── フロントページの続き (72)発明者 武内 邦文 東京都港区港南2丁目15番2号 株式会社 大林組本社内 (72)発明者 岡井 大八 大阪府大阪市中央区平野町4丁目1番2号 大阪瓦斯株式会社内 (72)発明者 香川 尚史 大阪府大阪市中央区平野町4丁目1番2号 大阪瓦斯株式会社内 Fターム(参考) 2D047 AB02 2D055 AA10 CA01 CA03 CA04 DA01 KB04 KB05 KB11 KC00 3E072 AA03 BA07 DA05  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Kunifumi Takeuchi 2-15-2 Konan, Minato-ku, Tokyo Obayashi Gumi head office (72) Inventor Daihachi Okai 4-1-1 Hiranocho, Chuo-ku, Osaka-shi, Osaka No. 2 Inside Osaka Gas Co., Ltd. (72) Inventor Naofumi Kagawa 4-1-2 Hirano-cho, Chuo-ku, Osaka City, Osaka Prefecture F-term in Osaka Gas Co., Ltd. (Reference) 2D047 AB02 2D055 AA10 CA01 CA03 CA04 DA01 KB04 KB05 KB11 KC00 3E072 AA03 BA07 DA05

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 岩盤掘削により形成した空洞部の内面に
覆工層を形成し、 前記覆工層の内面側に所定の空間部を設けて型枠を設置
した後に、前記空間部内にコンクリートを打設して、前
記覆工層を覆う耐圧緩衝層を形成し、 前記型枠を脱型した後に、前記耐圧緩衝層の内面側に金
属ライニングなどの気密材を覆設する高圧ガスの岩盤内
貯蔵設備の構築方法であって、 前記コンクリートを打設する前に、前記空間部内に所定
の配筋を施すとともに、打設された前記コンクリートを
周および軸方向に沿って複数に分断する目地材を設置
し、 前記気密材の周縁を前記目地材に固着して、前記耐圧緩
衝層の内面側に覆設することを特徴とする高圧ガスの岩
盤内貯蔵設備の構築方法。
1. A lining layer is formed on an inner surface of a hollow portion formed by rock excavation, a predetermined space is provided on an inner surface side of the lining layer, a formwork is installed, and concrete is poured into the space. Casting to form a pressure-resistant buffer layer that covers the lining layer, and after removing the mold, pressurized gas-filled rock that covers an airtight material such as a metal lining on the inner surface side of the pressure-resistant buffer layer. A method for constructing a storage facility, comprising: before placing the concrete, applying a predetermined reinforcing arrangement in the space portion, and dividing the placed concrete into a plurality of pieces along a circumferential direction and an axial direction. A method for constructing a high-pressure gas in-rock storage facility, comprising: fixing a peripheral edge of the airtight material to the joint material and covering the inner surface of the pressure-resistant buffer layer.
【請求項2】 前記型枠は、環状に形成された前記覆工
層の内周を覆う全断面型枠であることを特徴とする請求
項1記載の高圧ガスの岩盤内貯蔵設備の構築方法。
2. The method according to claim 1, wherein the mold is a full-section mold covering an inner circumference of the lining layer formed in an annular shape. .
JP2000043931A 2000-02-22 2000-02-22 Construction method for storage equipment for high pressure gas in bedrock Pending JP2001234553A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000043931A JP2001234553A (en) 2000-02-22 2000-02-22 Construction method for storage equipment for high pressure gas in bedrock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000043931A JP2001234553A (en) 2000-02-22 2000-02-22 Construction method for storage equipment for high pressure gas in bedrock

Publications (1)

Publication Number Publication Date
JP2001234553A true JP2001234553A (en) 2001-08-31

Family

ID=18566769

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000043931A Pending JP2001234553A (en) 2000-02-22 2000-02-22 Construction method for storage equipment for high pressure gas in bedrock

Country Status (1)

Country Link
JP (1) JP2001234553A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008208889A (en) * 2007-02-26 2008-09-11 Shimizu Corp Low-temperature baserock reservoir
JP2019085759A (en) * 2017-11-06 2019-06-06 鹿島建設株式会社 Concrete structure
CN111594269A (en) * 2020-05-18 2020-08-28 中铁第一勘察设计院集团有限公司 Underground oil gas tunnel storage tank structure and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008208889A (en) * 2007-02-26 2008-09-11 Shimizu Corp Low-temperature baserock reservoir
JP2019085759A (en) * 2017-11-06 2019-06-06 鹿島建設株式会社 Concrete structure
CN111594269A (en) * 2020-05-18 2020-08-28 中铁第一勘察设计院集团有限公司 Underground oil gas tunnel storage tank structure and construction method thereof

Similar Documents

Publication Publication Date Title
JP5033068B2 (en) Pile head treatment method in cast-in-place concrete pile method
JP2010255394A (en) Sc pile, manufacturing method therefor, and pile head treatment method
JP4250050B2 (en) Tunnel construction method
CN112065467B (en) Underground engineering supporting structure and construction method thereof
CN105626098A (en) Combination type tunnel lining, culvert or underground comprehensive pipe gallery
JP3285261B2 (en) Precast formwork for tunnel lining
JP2001234553A (en) Construction method for storage equipment for high pressure gas in bedrock
JP4493936B2 (en) Method for constructing tunnel junction and tunnel junction
JP2017008522A (en) Composite steel shell member and method of manufacturing the same
JP7050637B2 (en) Pile head treatment method
CN110645001A (en) Construction method for expanding and digging existing transverse channel into air channel
JP5117369B2 (en) Underpass construction method
CN113250705B (en) Multi-arch tunnel construction method
JPH04357293A (en) Flexible pipe and executing method thereof
KR100941437B1 (en) 2 arch tunnel construction method for upper girder void proofing and efficient construction
JP2839138B2 (en) Tunnel support material support method and support device
CN205243532U (en) Modular tunnel lining , culvert or utility tunnel
KR200241025Y1 (en) Tunnel Construction Structure for using Wave Profile Type Steel Plate
JP3930358B2 (en) How to build a tunnel
JP4430191B2 (en) High pressure gas storage facility in bedrock
JPH0772476B2 (en) How to build a tunnel lining
JP2002194997A (en) Tunnel construction method
JPS5873619A (en) Construction work of bulb pile and tremie tube
JPH09328987A (en) Tunnel and its construction method
JPH07119167A (en) Building structure and execution method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070123

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090225

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090310

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20090707