JP2001159907A - Production planning system - Google Patents

Production planning system

Info

Publication number
JP2001159907A
JP2001159907A JP34342799A JP34342799A JP2001159907A JP 2001159907 A JP2001159907 A JP 2001159907A JP 34342799 A JP34342799 A JP 34342799A JP 34342799 A JP34342799 A JP 34342799A JP 2001159907 A JP2001159907 A JP 2001159907A
Authority
JP
Japan
Prior art keywords
molding
load
production
product
production plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP34342799A
Other languages
Japanese (ja)
Inventor
Hisaaki Kono
寿明 河野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Chemical Co Ltd
Original Assignee
Sekisui Chemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Chemical Co Ltd filed Critical Sekisui Chemical Co Ltd
Priority to JP34342799A priority Critical patent/JP2001159907A/en
Publication of JP2001159907A publication Critical patent/JP2001159907A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Abstract

PROBLEM TO BE SOLVED: To create a production plan suitable for a production line consisting of forming processes and working processes by considering not only the production adjustment of the forming processes but also the production adjustment of the working processes. SOLUTION: The production planning system is provided with a production process allocation part for allocating parts and products to multiple forming processes and working processes on the basis of the number of products required to be replenished as stocks, a load judgmnet part 1c to be a load adjusting means for executing the load adjustment of a forming process and a working process generating load over when the parts and the products are allocated to respective processes by the allocation part 1b, a process-to-be-processed determination part 1d, and a production amount adjustment part 1e. A production plan is created by allocating respective parts to practical forming processes on the basis of the required quantity of adjustment after adjusting the loads of respective processes by the load adjusting means.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、複数の成型工程
と、これら成型工程で成形された部品を用いて製品を組
み立てる加工工程とを有する生産ラインに適用され、製
品の在庫補充要求量に基づいて生産計画を作成する在庫
補充方式の生産計画作成システムに関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is applied to a production line having a plurality of molding steps and a processing step of assembling a product using parts molded in these molding steps. The present invention relates to a production plan creation system of an inventory replenishment method for creating a production plan by using a stock replenishment method.

【0002】[0002]

【従来の技術】従来の生産計画作成システムの一例とし
て、特公平7−43746号公報に開示されている生産
計画微調整システムがある。
2. Description of the Related Art As an example of a conventional production plan creation system, there is a production plan fine-tuning system disclosed in Japanese Patent Publication No. 7-43746.

【0003】この生産計画微調整システムは、生産計画
作成システムで作成された所定の計画立案期間における
製品の生産計画に基づき部品の各生産工程の負荷を求
め、この求めた負荷と、計画立案期間における各生産工
程の生産能力との差を算出し、その差が最大となってい
る生産工程の負荷を他の生産工程に移動することによっ
て、全ての生産工程の負荷と生産能力との差をできるだ
け小さくするというものである。
This production plan fine-tuning system determines the load of each production process of parts based on the product production plan during a predetermined planning period created by the production planning system, and calculates the determined load and the planning period. By calculating the difference between the production capacity of each production process and the load of the production process with the largest difference to other production processes, the difference between the load and production capacity of all the production processes is calculated. The goal is to make it as small as possible.

【0004】この生産計画微調整システムによれば、作
成された生産計画が、微調整を行うことによって最終的
に所定の計画期間中に実施可能となることが前提条件と
なっている。しかし、例えば、注文に応じて必要な数の
製品を出荷するような場合には、製品の生産方式は、出
荷量を予測して倉庫にある程度の数の製品を予め格納す
るために、製品の品切れ日を予測して在庫補充要求量を
算出し製品を製造するという在庫補充型となる。この方
式によれば、特に製品の受注量の変動が多い場合には、
在庫補充要求量を全て満たすように製品の生産計画を作
成することは、部品の生産工程の生産能力の限界という
点から不可能である。そのため、上記の生産計画微調整
システムを用いて生産計画の微調整を行っても、計画立
案期間中に全ての生産工程の負荷を収めることができな
いという問題があった。
According to this production plan fine adjustment system, it is a precondition that the created production plan can be finally executed during a predetermined planning period by performing fine adjustment. However, for example, in the case where a required number of products are shipped according to an order, the product production method predicts the amount of shipment and stores a certain number of products in a warehouse in advance. This is an inventory replenishment type in which the product remanufacturing is performed by predicting the out-of-stock date to calculate the required inventory replenishment amount. According to this method, especially when the order quantity of products fluctuates greatly,
It is not possible to create a product production plan that satisfies all inventory replenishment requirements in terms of the production capacity of the parts production process. Therefore, even if the production plan is fine-tuned using the above-described production plan fine-tuning system, there is a problem that the load of all the production processes cannot be reduced during the planning period.

【0005】そこで、本出願人は、このような問題を解
決する一手段として、特願平10−138728号公報
に記載の生産計画作成システムを提案している。この生
産計画作成システムは、生産工程に割り付ける前に生産
量の調整を行うものであって、在庫補充要求量を計算す
る際に、製品の品切れ予測日を計算し、その品切れ予測
日をもとに、不急分(品切れ予測日が一番遅い製品に対
応する部品)の負荷カットを行い、すべての工程が負荷
オーバすることがないように調整してから、生産計画を
作成するものである。
Therefore, the present applicant has proposed a production planning system described in Japanese Patent Application No. 10-138728 as one means for solving such a problem. This production planning system adjusts the production amount before assigning it to the production process.When calculating the stock replenishment request amount, the system calculates the product out-of-stock date and calculates the product out-of-stock date. Then, the production plan is created after the load is cut for the urgent part (the part corresponding to the product with the latest out-of-stock forecast date) so that the load does not exceed all the processes. .

【0006】[0006]

【発明が解決しようとする課題】しかしながら、実際の
生産工程が、単に成形工程のみにとどまらず、成形工程
と加工(組立)工程とからなる場合、つまり、成形工程
の後に人手による組立加工工程がある場合、成形ができ
ても人手不足で組立加工ができないといった事態が発生
する可能性がある。
However, the actual production process is not limited to the molding process, but includes a molding process and a processing (assembly) process. In other words, a manual assembly process is required after the molding process. In some cases, there is a possibility that a situation may occur in which even if molding can be performed, assembly processing cannot be performed due to lack of manpower.

【0007】この場合、上記の生産計画作成システムで
は、この加工工程での負荷調整が考慮されていないた
め、このような成形工程と加工(組立)工程とからなる
生産ラインの生産計画には十分に対応しきれていないと
いった問題が残されていた。
In this case, the production planning system described above does not consider the load adjustment in the machining process, and therefore is not sufficient for the production planning of a production line including such a molding process and a machining (assembly) process. The problem that it was not able to cope with was left.

【0008】本発明は係る問題点を解決すべく創案され
たもので、その目的は、成形工程での生産調整のみなら
ず、加工工程での生産調整も考慮することにより、この
ような成形工程と加工(組立)工程とからなる生産ライ
ンの生産計画に好適な生産計画作成システムを提供する
ことにある。
The present invention has been made in order to solve such a problem. The purpose of the present invention is to consider not only the production adjustment in the molding process but also the production adjustment in the machining process. And a processing (assembly) process.

【0009】ところで、成形工程は、部品単位で負荷を
計算する必要があるが、加工工程では製品単位で負荷を
計算する必要がある。また、成形工程は機械工程である
が、加工工程は人手作業であるため、負荷基準工数を加
減することができるので、必ずしも固定する必要はな
い。さらに、実際に山積みを行う場合、成形工程では、
成形機の段取り替え時間や、ノイズ等による工場ライン
の一時的停止等があり、稼働率は100%にはならない
ので、稼働率を考慮した負荷調整を行わない限り、正確
な負荷調整が行えない。
By the way, in the forming step, it is necessary to calculate the load for each part, but in the processing step, it is necessary to calculate the load for each product. Although the forming step is a mechanical step, the processing step is a manual operation, and the load-based man-hours can be adjusted. Furthermore, when actually piled up, in the molding process,
The operation rate does not become 100% due to the setup change time of the molding machine, temporary stoppage of the factory line due to noise, etc., so accurate load adjustment cannot be performed unless load adjustment considering the operation rate is performed. .

【0010】本発明は、このような成形工程と加工工程
とからなる生産ラインに特有の条件を考慮したものとな
っている。
The present invention takes into consideration the conditions specific to a production line including such a molding step and a processing step.

【0011】[0011]

【課題を解決するための手段】上記課題を解決するた
め、本発明の生産計画作成システムは、複数の成型工程
と、これら成型工程で成型された部品を用いて製品を組
み立てる加工工程とを有する生産ラインに適用され、製
品の在庫補充要求量に基づいて生産計画を作成する在庫
補充方式の生産計画作成システムであって、製品の在庫
補充要求量に基づいて前記複数の成型工程および前記加
工工程に部品および製品を割り付ける工程割付手段と、
この工程割付手段によって部品および製品を各工程に割
り付けた結果、負荷オーバが生じる成型工程および加工
工程について、その成型工程の負荷調整と加工工程の負
荷調整とを行う負荷調整手段とを備え、この負荷調整手
段によって各工程の負荷を調整した後の調整要求量に基
づき、各部品を実際の工程に割り付けて生産計画を作成
することを特徴とする。
In order to solve the above-mentioned problems, a production planning system according to the present invention has a plurality of molding steps and a processing step of assembling a product using parts molded in these molding steps. An inventory replenishment type production plan creation system that is applied to a production line and creates a production plan based on a product inventory replenishment request amount, wherein the plurality of molding processes and the processing steps are performed based on a product inventory replenishment request amount. Means for allocating parts and products to
As a result of allocating parts and products to each process by the process allocating means, a load adjusting means for performing a load adjustment of the molding step and a load adjustment of the processing step is provided for a molding step and a processing step in which an overload occurs. Each part is assigned to an actual process and a production plan is created based on the required adjustment amount after the load of each process is adjusted by the load adjusting means.

【0012】このような特徴を有する本発明によれば、
負荷調整手段で成型工程の負荷調整と加工工程の負荷調
整とを行うので、成型工程の後に人手による組立加工工
程がある場合、成型ができても人手不足で組立加工がで
きないといった事態は発生しない。
According to the present invention having the above features,
Since the load adjustment of the molding process and the load adjustment of the processing process are performed by the load adjustment means, if there is a manual assembly process after the molding process, the situation that the assembly process cannot be performed due to shortage of labor even if the molding can be performed does not occur. .

【0013】また、本発明の生産計画作成システムは、
上記構成において、負荷調整手段は、負荷オーバが生じ
る加工工程については、その工程に割り付けられた製品
の中で品切れ予測日が一番遅い製品の生産計画を削除す
ることで、その工程での加工能力内になるように負荷調
整を行い、負荷オーバが生じる成型工程については、そ
の工程に割り付けられた部品の中で品切れ予測日が一番
遅い製品に関連する部品の生産計画を削除することで、
その工程での成型能力内になるように負荷調整を行うこ
とを特徴とする。
Further, the production plan creation system of the present invention comprises:
In the above configuration, the load adjusting means deletes the production plan of the product with the latest out-of-stock predicted date among the products assigned to the process for the machining process in which the load is over, thereby performing the machining in the process. Adjust the load so that it is within the capacity, and for the molding process where overload occurs, delete the production plan of the part related to the product with the latest out-of-stock forecast date among the parts assigned to that process. ,
It is characterized in that the load is adjusted so as to be within the molding ability in the process.

【0014】このような特徴を有する本発明によれば、
成型工程での負荷調整と加工工程での負荷調整とを別々
に管理することで、より現実に則した負荷調整を実現す
ることができる。
According to the present invention having such features,
By separately managing the load adjustment in the molding step and the load adjustment in the processing step, a more realistic load adjustment can be realized.

【0015】また、本発明の生産計画作成システムは、
上記各構成において、負荷調整手段は、加工工程におい
て製品の負荷調整を行ったときには、その負荷調整に対
応する部品が割り付けられている成型工程においても当
該部品の負荷調整を行い、成型工程において部品の負荷
調整を行ったときには、その負荷調整の対象となった部
品に関連する製品の負荷調整を加工工程においても行う
ことを特徴とする。
Further, the production planning system of the present invention
In each of the above configurations, when the load adjustment of the product is performed in the processing step, the load adjustment unit also performs the load adjustment of the part in the molding step to which a part corresponding to the load adjustment is allocated, and performs the component adjustment in the molding step. When the load adjustment is performed, the load adjustment of the product related to the component subjected to the load adjustment is also performed in the machining process.

【0016】このような特徴を有する本発明によれば、
成型工程での負荷調整と加工工程での負荷調整とを関連
付けて管理することで、成型工程および加工工程全体と
しての生産計画をより現実に則した形で作成することが
できる。
According to the present invention having such features,
By managing the load adjustment in the molding step and the load adjustment in the processing step in association with each other, a production plan for the molding step and the processing step as a whole can be created in a more realistic manner.

【0017】また、本発明の生産計画作成システムは、
上記各構成において、負荷調整手段は、成型負荷および
加工負荷をパラメータとして各工程での負荷オーバの判
定基準となる成型能力および加工能力を設定することを
特徴とする。また、本発明の生産計画作成システムは、
上記構成において、成型工程では稼働率をパラメータと
して、この稼働率を成型能力に掛け合わせ、加工工程で
は加工人員数をパラメータとして、この加工人員数を加
工能力に掛け合わせることを特徴とする。
Further, the production plan creation system of the present invention
In each of the above configurations, the load adjusting means sets a molding ability and a machining ability as a criterion for determining an overload in each step using the molding load and the machining load as parameters. Also, the production plan creation system of the present invention
The above configuration is characterized in that in the molding step, the operating rate is used as a parameter, and the operating rate is multiplied by the molding capacity. In the processing step, the number of processing personnel is used as a parameter, and the number of processing personnel is multiplied by the processing capacity.

【0018】このような特徴を有する本発明によれば、
成型工程では部品単位での山積みを行い、成型能力に稼
働率というパラメータを掛け合わせるようにして、より
現実に近い負荷オーバの判定基準を設定できるようにし
ている。また、加工工程では製品単位での山積みを行
い、負荷調整を行う条件は、加工人員数というパラメー
タを設定し、加工能力に加工人員数というパラメータを
掛け合わせるようにして、より現実に近い負荷オーバの
判定基準を設定できるようにしている。
According to the present invention having such features,
In the molding process, a pile of parts is piled up, and a parameter called an operation rate is multiplied by the molding capacity, so that a more realistic overload judgment criterion can be set. In the machining process, piles are created in product units, and the conditions for adjusting the load are as follows: a parameter called the number of machining personnel is set, and the machining capacity is multiplied by a parameter called the number of machining personnel. Criterion can be set.

【0019】また、本発明の生産計画作成システムは、
上記構成において、パラメータである稼働率および加工
人員数を、過去の在庫補充要求量および調整要求量の変
化に対応させて変更することを特徴とする。すなわち、
負荷オーバを削除する2つの基準である稼働率および加
工人員数を、在庫補充要求量と調整要求量(生産量の調
整を行った後の要求量)の変動傾向に従い、一定基準で
自動的に変更することにより、最適な負荷調整を行える
ようにしている。なお、ここでいう「補充要求量」と
は、従来周知の在庫補充方式における在庫の補充量のこ
とで、在庫設定量に見合うだけの生産要求量のことであ
る。また、「調整要求量」とは、補充要求量のうち、実
際に工程の生産能力を加味して、工程計画に割り付ける
ことのできた量のことである。
Further, the production planning system of the present invention
The above configuration is characterized in that the operation rate and the number of processing personnel, which are parameters, are changed in accordance with changes in the past required stock replenishment and the required adjustment. That is,
The operating rate and the number of machining personnel, which are the two criteria for eliminating overload, are automatically adjusted according to the fluctuation trend of the required inventory replenishment and the required adjustment (the required quantity after adjusting the production volume) on a fixed basis. By changing, the optimal load adjustment can be performed. Here, the "requested replenishment amount" refers to the replenishment amount of the stock in the conventionally known inventory replenishment method, and is a required production amount corresponding to the set inventory amount. The “requested adjustment amount” is the amount of the replenishment request amount that can be actually allocated to the process plan in consideration of the production capacity of the process.

【0020】すなわち、計画立案時ごとの補充要求量の
合計重量と、調整要求量の合計重量とを記憶しておき、
両者の傾向によって負荷オーバの判定基準(負荷調整基
準)を変動させる。つまり、補充要求量の変動は、受注
量の変動を考慮することになり、調整要求量の変動は、
受注量の変動に対する成型量の追従の具合を表している
ため、これらの挙動を見れば、現状の生産計画が妥当か
どうかが判断できる。そして、その結果から負荷オーバ
の判定基準を最適な状態に変動させることで、最適な生
産計画を作成することができる。また、工程負荷を調整
する場合、人手である加工工程については、人員の増減
で対応できるが、成型工程では成型機を増減するという
わけにはいかない。しかしながら、実際の成型工程で
は、ノイズ等による工場ラインの一時的停止や段取り替
え時間等の余裕を持たせているため、通常時の成型負荷
率は、例えば70〜80%程度の負荷率で稼働させてい
る。そのため、段取り替え要員を増やしたり、ノイズ等
による工場ラインの一時的停止での復旧時間の設定を短
縮したりという工夫により、この負荷率(稼働率)を増
やすことができる。よって、成型工程においても負荷率
(稼働率)を変動させることが可能である。
That is, the total weight of the replenishment request amount and the total weight of the adjustment request amount for each planning are stored.
The criterion of load over (load adjustment criterion) is varied according to both tendencies. In other words, the change in the replenishment request amount will take into account the change in the order amount, and the change in the adjustment request amount will be
Since the degree of follow-up of the molding amount with respect to the fluctuation of the order quantity is shown, it is possible to judge whether or not the current production plan is appropriate by looking at these behaviors. Then, an optimum production plan can be created by changing the determination standard for overload from the result to an optimal state. In addition, when adjusting the process load, a manual processing step can be dealt with by increasing or decreasing the number of personnel, but it is not always possible to increase or decrease the number of molding machines in the molding step. However, in the actual molding process, since a margin such as a temporary stop of a factory line or a changeover time due to noise or the like is provided, the molding load factor in a normal operation is, for example, a load factor of about 70 to 80%. Let me. For this reason, this load factor (operating rate) can be increased by increasing the number of setup change personnel or shortening the setting of the recovery time when the factory line is temporarily stopped due to noise or the like. Therefore, it is possible to change the load factor (operating rate) also in the molding process.

【0021】[0021]

【発明の実施の形態】以下、本発明の実施形態につい
て、図面を参照して説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0022】本発明の生産計画作成システムは、複数の
成型工程と、これら成型工程で成形された部品を用いて
製品を組み立てる加工工程とを有する生産ラインに適用
される。すなわち、この生産計画作成システムは、少な
くとも1つの部品から構成される製品の在庫補充要求量
データに従って、所定の計画立案期間における製品の生
産計画を作成するシステムであって、その製品の生産計
画に従って部品を生産(本実施形態では、成型機による
成型)する場合において、計画立案期間内に部品の成型
を完了できず負荷オーバが生じている成型工程がある場
合には、製品が計画立案期間中に品切れしない範囲で所
定の部品の成型を取消すか、部品の成型量を減少させる
ことによって、成型工程の負荷を調整するものである。
The production plan creation system of the present invention is applied to a production line having a plurality of molding steps and a processing step of assembling a product using parts molded in these molding steps. That is, this production plan creation system is a system that creates a product production plan for a predetermined planning period in accordance with inventory replenishment request data of a product composed of at least one part, and according to the product production plan. In the case of producing a part (in the present embodiment, molding by a molding machine), if there is a molding process in which the molding of the part cannot be completed within the planning period and an overload occurs, the product is not manufactured during the planning period. The load of the molding process is adjusted by canceling the molding of a predetermined part or reducing the molding amount of the part as long as the part does not run out.

【0023】図1は、本実施形態の生産計画作成システ
ムのブロック図である。
FIG. 1 is a block diagram of a production plan creation system according to this embodiment.

【0024】この生産計画作成システムは、少なくとも
1つの部品から構成される製品の在庫補充要求量に従っ
て、所定の計画立案期間における製品の生産計画を作成
するシステムであり、システム全体を統括的に制御する
制御プログラムを格納した主制御部(以下、「CPU」
という)1と、このCPU1に接続された記憶装置2
と、CPU1と相互接続されている入出力制御部3と、
この入出力制御部3を介してCPU1に接続された、キ
ーボードやマウス等のポインティングデバイスからなる
入力装置4と、入力データや出力データのモニタに用い
る表示装置5と、演算結果等を出力する出力装置6とか
ら構成されている。
This production plan creation system is a system for creating a production plan of a product during a predetermined planning period in accordance with a stock replenishment request amount of a product composed of at least one part, and totally controls the entire system. Main control unit (hereinafter referred to as “CPU”)
1) and a storage device 2 connected to the CPU 1
An input / output control unit 3 interconnected with the CPU 1;
An input device 4 composed of a pointing device such as a keyboard and a mouse, a display device 5 used for monitoring input data and output data, and an output for outputting calculation results and the like, connected to the CPU 1 via the input / output control unit 3. And an apparatus 6.

【0025】CPU1は、OS(Operating
system)等の制御プログラム、当該システムを用
いて行う処理手順を規定したプログラム、および所要デ
ータを格納するための内部メモリを有し、部品展開部1
aと、生産工程割付部1bと、負荷判断部1cと、処理
対象生産工程決定部1dと、生産量調整部1eと、動作
制御部1fとを実現している。
The CPU 1 executes an OS (Operating)
system, etc., a program that defines processing procedures to be performed using the system, and an internal memory for storing required data.
a, a production process allocating unit 1b, a load determining unit 1c, a processing target production process determining unit 1d, a production amount adjusting unit 1e, and an operation control unit 1f.

【0026】部品展開部1aは、製品の在庫補充要求量
に従って製品の生産計画数量を算出し、この生産計画数
量を製品と関連付けた状態で部品の成型量に展開する手
段である。
The part developing section 1a is a means for calculating the planned production quantity of the product in accordance with the requested stock replenishment of the product, and developing the planned production quantity into the molding quantity of the part in a state associated with the product.

【0027】生産工程割付部1bは、部品展開部1aに
よって展開した部品の成型量に従って、各部品の成型を
複数の成型工程に山積みする形で順次割り付けるととも
に、複数の成型工程に割り付いた部品に関連する製品
を、加工工程に山積みする形で順次割り付ける手段であ
る。ここで、上記した「山積みする形で順次割り付け
る」とは、次のような割り付け方を意味している。すな
わち、成型工程の場合には、展開した部品に関連する製
品のうち、後述する品切れ予測日が一番早い製品に関連
する部品から順番に割り付けていくことを意味してお
り、加工工程の場合には、その成型工程に割り付けた部
品に関連する製品のうち、後述する品切れ予測日が一番
早い製品から順番に割り付けていくことを意味してい
る。つまり、最後の方に割り付けるものほど、すぐには
品切れする可能性の少ない部品および製品となってい
る。
The production process allocating unit 1b sequentially allocates the molding of each component to a plurality of molding processes in a piled manner according to the molding amount of the component developed by the component developing unit 1a. This is a means for sequentially allocating products related to (1) in a pile in the processing process. Here, “sequentially laying out in piles” means the following way of allocating. In other words, in the case of the molding process, it means that among the products related to the developed parts, the parts related to the product with the earliest out-of-stock forecast date described later are allocated in order from the part related to the developed part. This means that among the products related to the parts allocated to the molding process, the products with the predicted out-of-stock date described later are allocated in order from the earliest product. In other words, the components and products that are assigned to the last are less likely to be out of stock immediately.

【0028】負荷判断部1cは、生産工程割付部1bに
よって各部品の成型を各成型工程に割り付けた結果、計
画立案期間内に部品の生産を完了できず負荷オーバが生
じる生産工程があるか否かを判断する。また、生産工程
割付部1bによって製品の加工を加工工程に割り付けた
結果、計画立案期間内に製品の生産を完了できず負荷オ
ーバが生じるか否かを判断する手段である。
As a result of allocating the molding of each component to each molding process by the production process allocating unit 1b, the load determining unit 1c determines whether or not there is a production process in which the production of the component cannot be completed within the planning period and an overload occurs. Judge. Further, as a result of allocating the processing of the product to the processing process by the production process allocating unit 1b, it is a means for determining whether or not the production of the product cannot be completed within the planning period and an overload occurs.

【0029】処理対象生産工程決定部1dは、負荷判断
部1cによって負荷オーバが生じている成型工程が1つ
あると判断された場合には、この負荷オーバが生じてい
る成型工程を処理対象生産工程とし、負荷判断部1cに
よって負荷オーバが生じている成型工程が複数あると判
断された場合には、負荷オーバが生じている複数の成型
工程のうち一番負荷が高い成型工程を処理対象生産工程
として決定する。また、負荷判断部1cによって加工工
程に負荷オーバが生じていると判断された場合には、こ
の加工工程を処理対象生産工程として決定する手段であ
る。
When the load determining unit 1c determines that there is one molding process in which the load is over, the production process determining unit 1d determines the molding process in which the load is over by the production process. When the load determining unit 1c determines that there are a plurality of molding processes in which the load is over, the molding process having the highest load among the plurality of molding processes in which the load is over is processed. Determined as a process. When the load determining unit 1c determines that the processing step is overloaded, the processing unit determines the processing step as a target production step.

【0030】生産量調整部1eは、処理対象生産工程決
定部1dでの決定に従い、負荷オーバが生じる加工工程
については、その加工工程に割り付けられた製品の中で
品切れ予測日が一番遅い製品の生産計画を削除すること
で、その工程での加工能力内になるように負荷調整を行
う。また、処理対象生産工程決定部1dでの決定に従
い、負荷オーバが生じる成型工程については、その成型
工程に割り付けられた部品の中で品切れ予測日が一番遅
い製品に関連する部品の生産計画を削除することで、そ
の工程での成型能力内になるように負荷調整を行う手段
である。なお、この場合、加工工程において製品の負荷
調整を行ったときには、その負荷調整に関連する部品が
割り付けられている成型工程においてもその部品の負荷
調整を行い、成型工程において部品の負荷調整を行った
ときには、その負荷調整の対象となった部品に関連する
製品の負荷調整を加工工程においても行うようになって
いる。また、生産量調整部1eでは、成型負荷および加
工負荷をパラメータとして各工程での負荷オーバの判定
基準となる成型能力および加工能力を設定することが可
能となっている。具体的には、成型工程では稼働率をパ
ラメータとして、この稼働率を成型能力に掛け合わせて
負荷オーバの判定基準とし、加工工程では加工人員数を
パラメータとして、この加工人員数を加工能力に掛け合
わせて負荷オーバの判定基準としている。さらに、パラ
メータである稼働率および加工人員数は、過去の在庫補
充要求量および調整要求量の変化に対応させて変更可能
となっている。
According to the decision made by the process-to-be-processed determining step 1d, the production amount adjusting unit 1e determines, for the machining process in which the overload occurs, the product with the latest out-of-stock predicted date among the products assigned to the machining process. By deleting the production plan, the load is adjusted to be within the processing capacity in the process. In addition, in accordance with the determination by the process-to-be-processed determining unit 1d, for a molding process in which an overload occurs, a production plan for a component related to a product having the latest predicted out-of-stock date among components assigned to the molding process is determined. This is a means for adjusting the load by removing it so that it is within the molding capability in that step. In this case, when the load of the product is adjusted in the processing process, the load of the component is also adjusted in the molding process to which the component related to the load adjustment is allocated, and the load of the component is adjusted in the molding process. In such a case, the load adjustment of the product related to the component subjected to the load adjustment is also performed in the processing step. In addition, the production amount adjustment unit 1e can set the molding ability and the machining ability as a criterion of overload in each process using the molding load and the machining load as parameters. Specifically, in the molding process, the operating rate is used as a parameter, and this operating rate is multiplied by the molding capacity to determine the overload. In the processing step, the number of processing personnel is used as a parameter to multiply the processing capacity by the processing capacity. It is also used as a criterion of overload. Further, the operation rate and the number of processing personnel, which are parameters, can be changed in accordance with changes in the past stock replenishment request amount and adjustment request amount.

【0031】動作制御部1fは、部品の成型を各成型工
程に割り付けた場合、およびこの割り付けた部品に関連
する製品の加工を加工工程に割り付けた場合に、負荷判
断部1cによって負荷オーバが生じる成型工程および加
工工程が無いと判断されるまで、部品展開手段1a、生
産工程割付部1b、負荷判断部1c、処理対象生産工程
決定部1dおよび生産量調整部1eでの処理動作を順次
実行させる手段である。
The operation control section 1f causes the load judging section 1c to overload when the molding of the component is allocated to each molding step and when the processing of the product related to the allocated component is allocated to the processing step. Until it is determined that there is no molding step and processing step, the processing operations in the part expanding means 1a, the production step allocating section 1b, the load determining section 1c, the target production step determining section 1d, and the production amount adjusting section 1e are sequentially executed. Means.

【0032】また、記憶装置2は、ハードディスクや、
フレキシブルディスク、あるいは光ディスク等から構成
されており、在庫補充要求量ファイル2aと、部品構成
ファイル2bと、生産計画ファイル2cと、生産能力フ
ァイル2dと、処理対象生産工程ファイル2eと、品切
れ予測ファイル2fとを格納している。
The storage device 2 includes a hard disk,
It is composed of a flexible disk, an optical disk, or the like, and is composed of an inventory replenishment request amount file 2a, a parts configuration file 2b, a production plan file 2c, a production capacity file 2d, a processing target production process file 2e, and an out-of-stock prediction file 2f. And are stored.

【0033】在庫補充要求量ファイル2aは、在庫補充
要求量を示す在庫補充要求量データが予め記録されてい
るファイルである。図2に在庫補充要求量データの一例
を示す。製品番号Aの製品(以下、単に「製品A」とい
う)の在庫補充要求量(図2中では、単に「要求量」と
記載している)は100個であり、製品番号Bの製品
(以下、単に「製品B」という)の在庫補充要求量は1
50個であり、製品番号Cの製品(以下、単に「製品
C」という)の在庫補充要求量は100個であり、製品
番号Dの製品(以下、単に「製品D」という)の在庫補
充要求量は100個であり、製品番号Eの製品(以下、
単に「製品E」という)の在庫補充要求量は100個で
あり、製品番号Fの製品(以下、単に「製品F」とい
う)の在庫補充要求量は150個である。
The requested stock replenishment amount file 2a is a file in which the requested stock replenishment amount data indicating the requested stock replenishment amount is recorded in advance. FIG. 2 shows an example of the inventory replenishment request amount data. The stock replenishment request amount (hereinafter simply referred to as “request amount” in FIG. 2) of the product of product number A (hereinafter, simply referred to as “product A”) is 100 pieces, and the product of product number B (hereinafter, simply referred to as “request amount”). , Simply called “Product B”) is 1
The inventory replenishment request quantity of the product of product number C (hereinafter, simply referred to as “product C”) is 100 pieces, and the inventory replenishment request of the product of product number D (hereinafter, simply “product D”) is 50 pieces. The quantity is 100 pieces and the product of product number E (hereinafter, referred to as
The requested amount of stock replenishment for the product “product E”) is 100 pieces, and the requested quantity of stock replenishment for the product of the product number F (hereinafter, simply referred to as “product F”) is 150 pieces.

【0034】部品構成ファイル2bは、部品と製品とを
関連付ける関連情報が付加されておりかつ各製品を構成
する部品を示す部品構成データを記録するファイルであ
る。図3に部品構成データの一例を示す。製品Aは、部
品番号Vの部品(以下、単に「部品V」という)1個
と、部品番号Yの部品(以下、単に「部品Y」という)
2個とから構成されており、製品Bは、部品番号Xの部
品(以下、単に「部品X」という)1個と、部品V1個
と、部品番号Rの部品(以下、単に「部品R」という)
1個とから構成されており、製品Cは、部品番号Zの部
品(以下、単に「部品Z」という)2個と、部品X1個
とから構成されており、製品Dは、部品R1個と、部品
番号Sの部品(以下、単に「部品S」という)1個とか
ら構成されており、製品Eは、部品R2個と、部品Z1
個とから構成されており、製品Fは、部品S1個とから
構成されている。
The component configuration file 2b is a file to which related information for associating a component with a product is added, and that records component configuration data indicating components constituting each product. FIG. 3 shows an example of the component configuration data. The product A includes one part having a part number V (hereinafter simply referred to as “part V”) and a part having a part number Y (hereinafter simply referred to as “part Y”).
The product B is composed of two parts. The product B has one part with the part number X (hereinafter, simply referred to as “part X”), one part V, and the part with the part number R (hereinafter, simply “part R”). That)
The product C is composed of two parts having a part number Z (hereinafter, simply referred to as “part Z”) and one part X, and the product D is composed of one part R. , A part number S (hereinafter, simply referred to as “part S”), and a product E is composed of two parts R and a part Z1.
The product F is composed of one part S1.

【0035】生産計画ファイル2cは、部品展開部1a
による展開処理によって得られた生産計画データと生産
量調整部1eによる負荷調整処理によって得られた生産
計画データとを記録するファイルである。この生産計画
ファイル2cについては図8に示されているが、後の生
産計画を作成する手順のところで詳細に述べる。
The production plan file 2c is stored in the parts development section 1a.
This is a file for recording the production plan data obtained by the development processing by and the production plan data obtained by the load adjustment processing by the production amount adjustment unit 1e. This production plan file 2c is shown in FIG. 8, and will be described in detail in a procedure for creating a production plan later.

【0036】生産能力ファイル2dは、各生産工程(成
型工程および加工工程)の生産能力を示す生産能力デー
タ(成型能力データおよび加工能力データ)を記録する
ファイルである。この生産能力データは、負荷オーバの
判定基準となるデータである。ここで、成型工程では、
成型能力に稼働率というパラメータを掛け合わせるよう
にして、より現実に近い負荷オーバの判定基準を設定で
きるようにしている。また、加工工程では、加工人員数
というパラメータを設定し、加工能力に加工人員数とい
うパラメータを掛け合わせるようにして、より現実に近
い負荷オーバの判定基準を設定できるようにしている。
The production capacity file 2d is a file for recording production capacity data (molding capacity data and processing capacity data) indicating the production capacity of each production step (molding step and processing step). This production capacity data is data serving as a criterion for determining an overload. Here, in the molding process,
By multiplying the molding capacity by a parameter called the operating rate, a more realistic overload judgment criterion can be set. Also, in the machining process, a parameter called the number of machining personnel is set, and the parameter of the number of machining personnel is multiplied by the machining capacity so that a more realistic load over judgment criterion can be set.

【0037】つまり、成型工程は、下式(1)、 計画立案期間(日)×24(時間)×稼働率(%)・・・(1) で計算した値を負荷オーバの判定基準とし、加工工程で
は、下式(2)、 計画立案期間(日)×7.5(時間/人)×加工人員数・・・(2) で計算した値を負荷オーバの判定基準としている。
That is, in the molding process, the value calculated by the following equation (1), planning period (days) × 24 (hours) × operating rate (%) (1) In the machining process, the value calculated by the following equation (2), planning period (days) × 7.5 (hours / person) × number of machining personnel (2) is used as a criterion for determining the overload.

【0038】すなわち、ここでの説明では、判定基準は
時間となっている。例えば、計画立案期間を7日とし、
稼働率を80%とすると、成型工程の判定基準は、上記
(1)式より、7×24×0.8=134.4(時間)
となり、加工人員数を50とすれば、加工工程の判定基
準は、上記(2)式より、7×7.5×50=2625
時間となる。
That is, in the description here, the criterion is time. For example, the planning period is 7 days,
Assuming that the operation rate is 80%, the criterion of the molding process is 7 × 24 × 0.8 = 13.4 (time) from the above equation (1).
Assuming that the number of machining personnel is 50, the criterion for the machining process is 7 × 7.5 × 50 = 2625 from the above equation (2).
Time.

【0039】ただし、本実施形態では、これらの時間を
部品または製品の個数に置き換えて表した方が、後の説
明上分かりやすいので、ここでは時間を個数に置き換え
て説明する。つまり、上記(1)式で計算した時間を、
任意の部品の成型単位時間で割ることにより、その部品
の成型個数として、その成型工程の成型能力を表すこと
ができる。同様に、上記(2)式で計算した時間を、任
意の製品の組立単位時間で割ることにより、その製品の
組立個数として、その加工工程の加工能力を表すことが
できる。
However, in the present embodiment, it is easier to understand these times by replacing them with the number of parts or products in the following description. That is, the time calculated by the above equation (1) is
By dividing by the unit molding time of an arbitrary part, the molding capability of the molding process can be represented as the number of molded parts. Similarly, by dividing the time calculated by the above equation (2) by the unit assembly time of an arbitrary product, the processing capability of the processing step can be expressed as the number of assembled products.

【0040】図4(a)は、成型能力を各部品の成型個
数で表した場合の各成型工程の判定基準(成型能力)の
一例を示し、同図(b)は、加工能力を各製品の組立個
数で表した場合の加工工程の判定基準(加工能力)の一
例を示している。本実施形態では、3つの成型工程(す
なわち3つの生産設備)を用いて部品を成型するものと
し、第1成型工程L1は部品Rまたは部品Xを1日で6
0個成型することができ、第2成型工程L2は部品Sま
たは部品Yを1日で60個成型することができ、第3成
型工程L3は部品Vまたは部品Zを1日で60個成型す
ることができる能力を持っている。つまり、これが各成
型工程での負荷オーバの判定基準となる。また、加工工
程では、製品A〜Fのそれぞれについて、1日で90個
組み立てることができる能力を持っている。つまり、こ
れが加工工程での負荷オーバの判定基準となる。ただ
し、ここでは説明を簡単にするために、成型工程および
加工工程のいずれも、判定基準については1つの基準
(成型工程では60個、加工工程では90個)に統一し
ている。しかし、実際には、成型する部品によって成型
能力が異なる場合があることは当然であり、組み立てる
製品によって加工能力が異なる場合があることは当然で
ある。なお、上記の説明では、成型工程を第1から第3
の3つの成型工程として説明しているが、成型工程のク
ラス分けとしては、型締め圧ごとに、Sクラス(350
トン以下)、Fクラス(550トン以下、Mクラス(8
50トン以下)、Lクラス(850トン超)の4クラス
があり、各クラスごとにさらに、S15、S17、S2
2、S35、F45、F55、F55A、M85、L1
05、L180などの成型工程(成型機)があるが、こ
こでは上記3つの成型工程として説明する。
FIG. 4A shows an example of a criterion (molding ability) of each molding step when the molding ability is represented by the number of molded parts, and FIG. 5 shows an example of a criterion (machining capability) of a machining process when the number of assembly is expressed by the number of pieces. In the present embodiment, it is assumed that a part is molded using three molding steps (that is, three production facilities), and the first molding step L1 is performed by converting the part R or the part X into 6 parts per day.
Zero molding can be performed, the second molding step L2 can mold 60 parts S or Y in one day, and the third molding step L3 can mold 60 parts V or Z in one day. Have the ability to be. In other words, this is a criterion for determining an overload in each molding step. In the processing step, each of the products A to F has an ability to assemble 90 pieces in one day. In other words, this is a criterion for determining the load over in the machining process. However, here, for simplicity of description, both the molding step and the processing step are standardized to one criterion (60 in the molding step and 90 in the processing step). However, in actuality, it is natural that the molding ability may be different depending on the part to be molded, and it is natural that the processing ability may be different depending on the product to be assembled. In the above description, the molding process is performed in the first to third steps.
Are described as three molding steps, but the classification of the molding steps is as follows: S class (350
Tons), F class (550 tons or less, M class (8
50 tons or less) and L class (more than 850 tons). Each class has S15, S17, S2
2, S35, F45, F55, F55A, M85, L1
There are molding processes (molding machines) such as 05 and L180, but here, the above three molding processes will be described.

【0041】処理対象生産工程ファイル2eは、処理対
象生産工程決定部1dによる処理によって得られた処理
対象生産工程データを記録するファイルである。例え
ば、処理対象生産工程に選ばれた生産工程を示すデータ
と、この生産工程において生産される部品を示すデータ
と、この部品に関連する製品を示すデータとから構成さ
れている。この処理対象生産工程ファイル2eについて
は、後の生産計画を作成する手順のところで詳細に述べ
る。
The processing target production process file 2e is a file for recording processing target production process data obtained by the processing by the processing target production process determining unit 1d. For example, it is composed of data indicating a production process selected as a production process to be processed, data indicating a part produced in the production process, and data indicating a product related to the part. The processing target production process file 2e will be described in detail in a procedure for creating a production plan later.

【0042】品切れ予測ファイル2fは、製品の品切れ
予測日を示す品切れ予測データが予め記録されているフ
ァイルである。図5に品切れ予測データの一例を示す。
なお、この品切れ予測データは、例えば図6に示すよう
な各製品の在庫量と平均出荷量とを示すデータに基づき
作成される。図6によれば、製品Aの在庫量は100個
であり、平均出荷量は1日当たり10個であり、製品B
の在庫量は150個であり、平均出荷量は1日当たり1
0個であり、製品Cの在庫量は70個であり、平均出荷
量は1日当たり10個であり、製品Dの在庫量は50個
であり、平均出荷量は1日当たり10個であり、製品E
の在庫量は20個であり、平均出荷量は1日当たり10
個であり、製品Fの在庫量は70個であり、平均出荷量
は1日当たり10個である。従って、図5に示すよう
に、製品Aは10日後に品切れし、製品Bは15日後に
品切れし、製品Cは7日後に品切れし、製品Dは5日後
に品切れし、製品Eは2日後に品切れし、製品Fは7日
後に品切れすると予測できる。
The out-of-stock predicted file 2f is a file in which out-of-stock predicted data indicating a predicted out-of-stock date of a product is recorded in advance. FIG. 5 shows an example of the out-of-stock prediction data.
The out-of-stock prediction data is created based on data indicating the stock amount and the average shipment amount of each product as shown in FIG. 6, for example. According to FIG. 6, the stock quantity of the product A is 100 pieces, the average shipment quantity is 10 pieces per day,
Has an inventory of 150 units and an average shipment of 1 per day
0 pieces, the stock quantity of the product C is 70 pieces, the average shipment quantity is 10 pieces per day, the stock quantity of the product D is 50 pieces, the average shipment quantity is 10 pieces per day, E
Has an inventory of 20 units and an average shipment of 10 units per day.
And the stock quantity of the product F is 70 pieces, and the average shipment quantity is 10 pieces per day. Thus, as shown in FIG. 5, product A is out of stock after 10 days, product B is out of stock after 15 days, product C is out of stock after 7 days, product D is out of stock after 5 days, and product E is out of stock 2 days. It can be predicted that the product F will be out of stock later and the product F will be out of stock after 7 days.

【0043】次に、図1に示す生産計画作成システムを
用いて部品および製品の負荷調整(生産量の調整)を行
う処理手順について、図7に示すフローチャートを参照
して説明する。
Next, a processing procedure for performing load adjustment (adjustment of production amount) of parts and products using the production plan creation system shown in FIG. 1 will be described with reference to a flowchart shown in FIG.

【0044】まず、部品展開部1aによって、在庫補充
要求量ファイル2aに予め記録されている在庫補充要求
量データに従って、製品の生産計画数量を求めて生産計
画を作成し、生産計画データとして生産計画ファイル2
cに記録し、部品構成ファイル2bに予め記録されてい
る部品構成データに従い、生産計画数量を製品と関連付
けた状態で部品の生産量(成型量)に展開する(ステッ
プS1)。図8(a)は、このステップS1で作成した
生産計画データの一例を示している。製品の生産計画は
在庫補充要求量に従って作成するので、各製品の生産計
画数量はそれぞれの在庫補充要求量(図2参照)と等し
い。すなわち、製品Aの生産計画数量は100個であ
り、製品Bの生産計画数量は150個であり、製品Cの
生産計画数量は100個であり、製品Dの生産計画数量
は100個であり、製品Eの生産計画数量は100個で
あり、製品Fの生産計画数量は150個である。また、
このステップS1において、100個の製品Aは100
個の部品Vと200個の部品Yに展開され、150個の
製品Bは150個の部品Xと150個の部品Vと150
個の部品Rに展開され、100個の製品Cは200個の
部品Zと100個の部品Xに展開され、100個の製品
Dは100個の部品Rと100個の部品Sに展開され、
100個の製品Eは200個の部品Rと100個の部品
Zに展開され、150個の製品Fは150個の部品Sに
展開される。
First, the parts development unit 1a creates a production plan by obtaining the production plan quantity of the product in accordance with the required inventory replenishment data recorded in the required inventory replenishment file 2a, and creates the production plan as production plan data. File 2
c, and according to the component configuration data recorded in advance in the component configuration file 2b, the production plan quantity is developed into the component production quantity (molding quantity) in a state of being associated with the product (step S1). FIG. 8A shows an example of the production plan data created in step S1. Since the product production plan is created according to the required inventory replenishment, the production planned quantity of each product is equal to the respective required inventory replenishment (see FIG. 2). That is, the production planned quantity of the product A is 100 pieces, the production planned quantity of the product B is 150 pieces, the production planned quantity of the product C is 100 pieces, the production planned quantity of the product D is 100 pieces, The production planned quantity of the product E is 100 pieces, and the production planned quantity of the product F is 150 pieces. Also,
In this step S1, 100 products A are 100
Parts V and 200 parts Y, 150 products B are 150 parts X, 150 parts V and 150 parts
100 parts C are developed into 200 parts Z and 100 parts X, 100 products D are developed into 100 parts R and 100 parts S,
100 products E are developed into 200 parts R and 100 parts Z, and 150 products F are developed into 150 parts S.

【0045】次に、生産工程割付部1bでは、部品展開
部1aによって展開した部品の生産量に従って、各部品
の成型を複数の成型工程に山積みする形で順次割り付け
るとともに、複数の成型工程に割り付いた部品に関連す
る製品を、加工工程に山積みする形で順次割り付ける
(ステップS2)。すなわち、成型工程では、展開した
部品に関連する製品のうち、品切れ予測ファイル2fに
記録されている品切れ予測日が一番早い製品に関連する
部品から順番に割り付けていき、加工工程では、その成
型工程に割り付けた部品に関連する製品のうち、品切れ
予測ファイル2fに記録されている品切れ予測日が一番
早い製品から順番に割り付けていく。つまり、この場合
には、まず品切れ予測日が2日後と最も早い製品Eとこ
の製品Eに関連する部品R、Zをそれぞれの工程に割り
付け、次に品切れ予測日が5日後である製品Dとこの製
品Dに関連する部品R、Sをそれぞれの工程に割り付
け、次に品切れ予測日が7日後である製品CまたはF
と、この製品CまたはFに関連する部品Z、Xまたは部
品Sをそれぞれの工程に割り付け、次に品切れ予測日が
10日後である製品Aとこの製品Aに関連する部品V、
Yをそれぞれの工程に割り付け、最後に品切れ予測日が
15日後と最も遅い製品Bとこの製品Bに関連する部品
X、V、Rをそれぞれの工程に割り付ける。
Next, the production process allocating unit 1b sequentially allocates the molding of each component to a plurality of molding processes according to the production amount of the component developed by the component developing unit 1a, and allocates the molding to the plurality of molding processes. Products related to the attached parts are sequentially allocated in a piled-up manner in the processing process (step S2). In other words, in the molding process, among the products related to the developed parts, the parts related to the product with the earliest out-of-stock predicted date recorded in the out-of-stock prediction file 2f are sequentially allocated, and in the processing step, the molding is performed. Among the products related to the parts allocated to the process, the products are allocated in order from the product with the earliest out-of-stock predicted date recorded in the out-of-stock predicted file 2f. In other words, in this case, first, the product E whose out-of-stock predicted date is two days later and the components R and Z related to this product E are allocated to the respective processes, and then the product D whose out-of-stock predicted date is 5 days later is assigned to each process. Parts R and S related to this product D are allocated to respective processes, and then products C or F whose out-of-stock predicted date is 7 days later.
And a part Z, X or part S related to the product C or F is allocated to each process, and then a product A whose predicted out-of-stock date is 10 days later and a part V related to the product A,
Y is assigned to each process, and finally, a product B with a predicted out-of-stock date of 15 days later and components X, V, and R related to the product B are assigned to each process.

【0046】図9(a)は、このようにして部品および
製品を各成型工程および加工工程に割り付けた結果を示
している。なお、図9中のa(b)=cという表現にお
いて、aは生産する部品の部品番号、bは部品aに関連
する製品の製品番号、cは部品の成型数を示す。
FIG. 9 (a) shows the result of allocating parts and products to each molding step and processing step in this way. In the expression a (b) = c in FIG. 9, a represents the part number of the part to be produced, b represents the product number of the product related to the part a, and c represents the number of parts molded.

【0047】図9(a)に示すように、第1成型工程L
1には、品切れ予測日の早いものから順に、製品Eに関
連する部品Rが200個、製品Dに関連する部品Rが1
00個、製品Cに関連する部品Xが100個、製品Bに
関連する部品Xが150個、製品Bに関連する部品Rが
150個、山積みする形で割り付けられている。また、
第2成型工程L2には、品切れ予測日の早いものから順
に、製品Dに関連する部品Sが100個、製品Fに関連
する部品Sが150個、製品Aに関連する部品Yが20
0個が、山積みする形で割り付けられている。また、第
3成型工程L3には、品切れ予測日の早いものから順
に、製品Eに関連する部品Zが100個、製品Cに関連
する部品Zが200個、製品Bに関連する部品Vが15
0個、製品Aに関連する部品Vが100個、山積みする
形で割り付けられている。また、加工工程には、品切れ
予測日の早いものから順に、製品Eが100個、製品D
が100個、製品Cが100個、製品Bが150個、製
品Aが100個、山積みする形で割り付けられている。
As shown in FIG. 9A, the first molding step L
1 includes 200 parts R related to the product E and 1 part R related to the product D in order from the earliest out-of-stock prediction date.
00 parts, 100 parts X related to the product C, 150 parts X related to the product B, and 150 parts R related to the product B are arranged in a pile. Also,
In the second molding process L2, 100 parts S related to the product D, 150 parts S related to the product F, and 20 parts Y related to the product A
0 pieces are allocated in piles. In the third molding step L3, 100 parts Z related to the product E, 200 parts Z related to the product C, and 15 parts V related to the product B are arranged in the order from the earliest out-of-stock prediction date.
0 parts and 100 parts V related to the product A are allocated in piles. In the processing step, 100 products E and D
, 100 products C, 150 products B, 100 products A, and 100 piles.

【0048】次に、このようにして各部品の成型および
各製品の加工を各成型工程および加工工程に割り付けた
結果に基づき、負荷判断部1cでは、まず、加工工程に
おいて、計画立案期間内に製品の組立を完了できず負荷
オーバが生じるか否かを判断する(ステップS3)。な
お、本実施形態においては、計画立案期間を7日間とし
ており、図4(b)に示す加工工程の加工能力による
と、1日に90個の製品を組み立てできるので、計画立
案期間内において630個の製品を組み立てることがで
きる。つまり、負荷オーバの判定基準が630個となっ
ている。これに対し、図9(a)に示すように、加工工
程には700個の製品が割り付けられているので、加工
工程において負荷オーバが生じており、ステップS3の
判断結果はYesとなる。そのため、処理対象生産工程
決定部1dでは、この加工工程を処理対象生産工程とし
て決定し、処理対象生産工程データとして処理対象生産
工程ファイル2eに記録する(ステップS4)。一方、
ステップS3での判断結果がNoの場合には、次に成型
工程において負荷オーバが生じているか否かを判断する
ため、ステップS7へと動作を進める。
Next, based on the result of allocating the molding of each part and the processing of each product to each molding step and processing step in this manner, the load determining unit 1c firstly performs the processing step within the planning period within the planning period. It is determined whether the assembly of the product cannot be completed and an overload occurs (step S3). In the present embodiment, the planning period is set to 7 days, and according to the processing capacity of the processing step shown in FIG. 4B, 90 products can be assembled per day. Individual products can be assembled. That is, the overload determination criteria are 630. On the other hand, as shown in FIG. 9A, since 700 products are allocated to the processing step, an overload occurs in the processing step, and the determination result in step S3 is Yes. Therefore, the processing target production process determination unit 1d determines this processing step as a processing target production process, and records it as the processing target production process data in the processing target production process file 2e (step S4). on the other hand,
If the result of the determination in step S3 is No, the operation proceeds to step S7 in order to determine whether or not an overload has occurred in the molding process.

【0049】次に、生産量調整部1eでは、ステップS
4において処理対象生産工程として決定された加工工程
について、その加工工程に割り付けられた製品の中で品
切れ予測日が一番遅い製品から順番に、負荷オーバして
いる製品(判定基準を超えている製品)の生産計画を削
除する(ステップS5)。この場合には、製品A(=1
00個)の生産計画を削除し、図8(b)に示すよう
に、生産計画ファイル2cに記録されている生産計画デ
ータの中の製品Aの生産計画量を0個に変更する。ま
た、加工工程における製品Aの削除に伴い、これに関連
する部品の生産計画を、各成型工程から削除して生産量
を調整する(ステップS6)。すなわち、製品Aに関連
する部品は部品構成ファイル2bより部品VとYであ
り、これらの部品を成型している成型工程はL2とL3
であるので、この各成型工程L2、L3から部品V、Y
の生産計画を削除する。
Next, in the production amount adjusting section 1e, step S
For the machining process determined as the production process to be processed in 4, the products that are overloaded (exceeding the judgment criterion) in order from the product with the latest out-of-stock predicted date among the products assigned to the machining process. The production plan of (product) is deleted (step S5). In this case, the product A (= 1
8), the production plan quantity of the product A in the production plan data recorded in the production plan file 2c is changed to 0, as shown in FIG. 8B. Further, with the deletion of the product A in the processing step, the production plan of the part related thereto is deleted from each molding step to adjust the production amount (step S6). That is, the parts related to the product A are the parts V and Y from the part configuration file 2b, and the molding steps for molding these parts are L2 and L3.
Therefore, the parts V and Y are obtained from the molding steps L2 and L3.
Delete a production plan.

【0050】図9(b)は、このようにして製品Aおよ
びこれに関連する部品V、Yの生産計画を削除した後
の、各成型工程および加工工程の割り付け結果を示して
いる。図9(a)に示す割付結果と図9(b)に示す割
付結果とを比較すると明らかなように、製品Aの生産が
加工工程から削除されており、部品Yの生産が第2成型
工程L2から削除されており、部品Vの生産が第3成型
工程L3から削除されている。その結果、加工工程には
600個の製品の生産が割り付けられることになって、
負荷オーバが解消されている。一方、この段階で、第1
成型工程L1と第3成型工程L3で、依然として負荷オ
ーバが生じている。
FIG. 9 (b) shows the result of the allocation of each molding step and processing step after the production plan of the product A and the parts V and Y related thereto is deleted. As is clear from the comparison between the allocation result shown in FIG. 9A and the allocation result shown in FIG. 9B, the production of the product A has been deleted from the processing step, and the production of the part Y has been omitted from the second molding step. The production of the part V has been deleted from the third molding step L3. As a result, production of 600 products will be allocated to the processing process,
Overload has been resolved. Meanwhile, at this stage, the first
In the molding step L1 and the third molding step L3, overload still occurs.

【0051】次に、負荷判断部1cでは、各成型工程に
おいて、計画立案期間内に部品の成型を完了できず負荷
オーバが生じるか否かを判断する(ステップS7)。な
お、本実施形態においては、計画立案期間を7日間とし
ており、図4(a)に示す各成型工程の成型能力による
と、各成型工程は1日に60個の部品をそれぞれ成型で
きるので、計画立案期間内に各成型工程において420
個の部品をそれぞれ成型することができる。つまり、負
荷オーバの判定基準は420個となっている。そして、
この時点(加工工程の負荷オーバが解消された時点)
で、第1成型工程L1には合計700個の部品の生産が
割り付けられており、第2成型工程L2には合計250
個の部品の生産が割り付けられおり、第3成型工程L3
には合計650個の部品の生産が割り付けられている。
つまり、第1成型工程L1と第3成型工程L3とにおい
て負荷オーバが生じており、ステップS7の判断結果は
Yesとなる。なお、ステップS7の判断結果がNoと
なった場合、全ての成型工程において負荷オーバは解消
されているので、負荷調整処理を終了する。
Next, in each molding step, the load determining unit 1c determines whether or not the molding of the component cannot be completed within the planning period and an overload occurs (step S7). In the present embodiment, the planning period is set to 7 days, and according to the molding capability of each molding process shown in FIG. 4A, each molding process can mold 60 parts each day, 420 in each molding process within the planning period
Individual parts can each be molded. That is, there are 420 overload determination criteria. And
At this time (when the overload of the machining process is eliminated)
Thus, the production of a total of 700 parts is allocated to the first molding step L1, and the total of 250 parts is allocated to the second molding step L2.
The production of individual parts is allocated, and the third molding process L3
Has a total production of 650 parts.
That is, the load is excessive in the first molding process L1 and the third molding process L3, and the determination result in step S7 is Yes. When the result of the determination in step S7 is No, the load over has been resolved in all the molding steps, and the load adjustment processing ends.

【0052】ステップS7での判断結果がYesとなる
と、処理対象生産工程決定部1dでは、処理対象となる
成型工程を決定する(ステップS8)。ここでは、一番
負荷の高い第1成型工程L1が処理対象となる。
When the result of the determination in step S7 is Yes, the target production process determining unit 1d determines a molding process to be processed (step S8). Here, the first molding process L1 with the highest load is to be processed.

【0053】そのため、生産量調整部1eでは、第1生
産工程L1に割り当てられている部品の中で、品切れ予
測日が一番遅い製品に関連する部品から順番に、負荷オ
ーバしている部品(判定基準を超えている部品)の生産
計画を削除するとともに、この部品に関連する製品およ
びこの製品に関連する他の部品をそれぞれの工程の生産
計画から削除する(ステップS9)。この場合、成型工
程で山積みされているのは部品であるため、削除する手
順としては、まず部品構成ファイル2bからこの部品に
関連する製品を検索して、この製品の生産計画を加工工
程から削除し、次にこの製品に関連する部品の生産計画
を、割り付けられている成型工程から削除することにな
る。すなわち、この場合には、負荷オーバしている部品
はX、Rであり、この部品に関連する製品は部品構成フ
ァイル2bから製品Bであるので、加工工程からこの製
品Bの生産計画を削除し、次にこの製品Bに関連する部
品X、Rの生産計画を第1成型工程L1から削除すると
ともに、製品Bに関連する部品Vの生産計画を第3成型
工程L3から削除する。また、製品Bを成型工程および
加工工程から削除したので、図8(b)に示す生産計画
ファイル2cの生産計画データから製品Bの生産計画を
削除し、図8(c)に示すように、製品Bの生産計画数
量を0個に変更する。
For this reason, in the production quantity adjusting unit 1e, among the parts assigned to the first production process L1, the parts (for which the out-of-stock predicted date is related to the product with the latest out-of-stock date) are overloaded in order. In addition to deleting the production plan of the part exceeding the determination standard), the product related to this part and other parts related to this product are deleted from the production plan of each process (step S9). In this case, since parts are piled up in the molding process, as a deletion procedure, first, a product related to this part is searched from the component configuration file 2b, and the production plan of this product is deleted from the machining process. Then, the production plan of the part related to the product is deleted from the assigned molding process. That is, in this case, the parts overloaded are X and R, and the product related to this part is the product B from the component configuration file 2b. Therefore, the production plan of this product B is deleted from the machining process. Then, the production plan of the parts X and R related to the product B is deleted from the first molding step L1, and the production plan of the part V related to the product B is deleted from the third molding step L3. Further, since the product B has been deleted from the molding step and the processing step, the production plan of the product B is deleted from the production plan data of the production plan file 2c shown in FIG. 8B, and as shown in FIG. The production plan quantity of the product B is changed to 0 pieces.

【0054】図9(c)は、このようにして製品Bおよ
びこれに関連する部品X、R、Vの計画を削除した後
の、各成型工程および加工工程の割り付け結果を示して
いる。図9(b)に示す割付結果と図9(c)に示す割
付結果とを比較すると明らかなように、製品Bの生産計
画が加工工程から削除されており、部品XとRの生産計
画が第1成型工程L1から削除されており、部品Vの生
産計画が第3成型工程L3から削除されている。その結
果、第1成型工程L1には400個の部品の生産が割り
付けられ、第3成型工程L3には300個の部品の生産
が割り付けられることになり、全ての成型工程において
負荷オーバが解消されている。つまり、ステップS9か
らステップS7に戻ると、この場合にはステップS7で
の判断結果がNoとなるので、図8(c)に示す生産計
画を最終的な生産計画(調整後の生産要求量)として、
処理を終了する。なお、ステップS9の処理を行って
も、なお任意の成型工程で負荷オーバが生じている場合
には、全ての成型工程で負荷オーバが無くなるまで、ス
テップS7〜ステップS9の処理を繰り返すことにな
る。
FIG. 9C shows the allocation result of each molding step and processing step after deleting the plan of the product B and the parts X, R, and V related thereto. As is clear from the comparison between the allocation result shown in FIG. 9B and the allocation result shown in FIG. 9C, the production plan of the product B has been deleted from the machining process, and the production plans of the parts X and R have been deleted. It has been deleted from the first molding step L1, and the production plan of the part V has been deleted from the third molding step L3. As a result, the production of 400 parts is allocated to the first molding step L1, and the production of 300 parts is allocated to the third molding step L3, and the overload is eliminated in all the molding steps. ing. In other words, when the process returns from step S9 to step S7, in this case, the determination result in step S7 is No. Therefore, the production plan shown in FIG. 8C is changed to the final production plan (adjusted production request amount). As
The process ends. In addition, even if the processing of step S9 is performed, if the overload still occurs in any molding process, the processing of steps S7 to S9 is repeated until the overload is eliminated in all the molding processes. .

【0055】このように、本実施形態では、成型工程で
の負荷調整のみならず、その後の加工工程(組立工程)
での負荷調整も合わせて行うことで、成型工程の後に人
手による組立加工工程がある場合、成型ができても人手
不足で組立加工ができないといった事態は発生しなくな
り、成型工程と加工工程とからなる生産ラインに則した
負荷調整が可能となる。
As described above, in the present embodiment, not only the load adjustment in the molding step but also the subsequent processing step (assembly step)
By performing the load adjustment at the same time, if there is a manual assembly process after the molding process, the situation that the assembly process cannot be performed due to shortage of labor even if the molding can be done will not occur, and the molding process and the processing process will be It is possible to adjust the load according to the production line.

【0056】この場合、上記実施形態では、各成型工程
での判断基準および加工工程での判断基準は、最初に上
記(1)式および(2)式で計算した値を用いている
が、この判断基準も場合によって変更するように構成す
れば、さらに現実に則した負荷調整が可能となる。
In this case, in the above-described embodiment, as the criterion for each molding step and the criterion for the processing step, the values calculated by the above equations (1) and (2) are used. If the criterion is changed in some cases, the load can be adjusted more realistically.

【0057】すなわち、計画立案時ごとの補充要求量の
合計重量と、調整要求量の合計重量とを記憶装置2の図
示しない領域に記憶しておき、両者の傾向によって負荷
オーバの判定基準を変動させるようにすればよい。つま
り、補充要求量の変動は、受注量の変動を考慮すること
になり、調整要求量の変動は、受注量の変動に対する成
型量の追従の具合を表しているため、これらの挙動を見
れば、現状の生産計画が妥当かどうかが判断できる。そ
して、その結果から負荷オーバの判定基準を最適な状態
に変動させることで、最適な生産計画を作成することが
できる。
That is, the total weight of the replenishment request amount and the total weight of the adjustment request amount for each time of planning are stored in an area (not shown) of the storage device 2, and the criterion of the overload is changed according to the tendency of both. What should be done is. In other words, the change in the replenishment request amount will take into account the change in the order amount, and the change in the adjustment request amount indicates the degree of follow-up of the molding amount with respect to the change in the order amount. It can be determined whether the current production plan is appropriate. Then, an optimum production plan can be created by changing the determination standard for overload from the result to an optimal state.

【0058】具体的に説明すると、成型工程の判定基準
は、上記した如く、[計画立案期間(日)×24(時
間)×稼働率(%)]であり、加工工程の判断基準は、
[計画立案期間(日)×7.5(時間/人)×加工人員
数]である。ここで、パラメータである稼働率を経験上
の数値である80%に固定し、加工人員数を現場作業者
の人数の制限などにより例えば50人に固定したとする
と(上記実施形態の場合)、どんなに大量の補充要求量
がきても、工程割り付けをするための調整要求量がほと
んど変わらなくなるといった融通性のない負荷調整にな
ってしまう可能性がある。つまり、図9(a)〜(c)
に示すように、部品と製品との関連で削除していくた
め、かなりの量を削除してしまい、削除し過ぎの状態に
なってしまう。
More specifically, as described above, the criterion of the molding process is [planning period (days) × 24 (hours) × operating rate (%)].
[Planning period (days) x 7.5 (hours / person) x number of processing personnel]. Here, assuming that the operation rate, which is a parameter, is fixed to 80%, which is an empirical numerical value, and the number of machining personnel is fixed to, for example, 50 by limiting the number of field workers (in the case of the above embodiment). No matter how large a replenishment request amount comes, there may be inflexible load adjustment such that the adjustment request amount for process allocation hardly changes. That is, FIGS. 9 (a) to 9 (c)
As shown in (2), since a part is deleted in relation to a product, a considerable amount is deleted, resulting in an excessively deleted state.

【0059】そこで、本実施形態では、過去3回分の計
画立案時の補充要求量の合計量(単位は重量)と、調整
要求量の合計量(単位は重量)とを記憶装置2に記憶し
ておき、それぞれの遷移状況に応じて直線近似する。こ
のときの補充要求量と調整要求量との近似直線の関係を
図10に対応表の形で示す。この表の中の各エリアの意
味は、以下に説明する通りである。
Therefore, in the present embodiment, the total amount (unit is weight) of the replenishment request amount and the total amount (unit is weight) of the adjustment request amount in the past three times of planning are stored in the storage device 2. In advance, linear approximation is performed according to each transition situation. FIG. 10 shows the relationship of the approximate straight line between the replenishment request amount and the adjustment request amount at this time in the form of a correspondence table. The meaning of each area in this table is as described below.

【0060】は補充要求量、調整要求量とも上昇して
いるケースであり、この場合には、受注量が増え、それ
に伴って工程割り付け量(数)も増えているので、パラ
メータを操作することなく現状を維持する。
In the case where both the replenishment request amount and the adjustment request amount are increasing. In this case, since the order amount increases and the process allocation amount (number) also increases accordingly, it is necessary to operate the parameters. Without the status quo.

【0061】は補充要求量が上昇しているにもかかわ
らず、調整要求量が横ばいのケースであり、この場合に
は、受注量が増えているのに工程割り付け量(数)は横
ばいであるため、工程割り付け量(数)が増える方向に
パラメータ操作を行う。
In the case of (a), although the requested replenishment amount is increasing, the adjustment request amount is flat. In this case, the process allocation amount (number) is flat even though the order receiving amount is increased. Therefore, the parameter operation is performed in a direction in which the process allocation amount (number) increases.

【0062】は補充要求量が上昇しているにもかかわ
らず、調整要求量は下降しているケースであり、この場
合には、受注量が増えているのに工程割り付け量(数)
は下降しているため、工程割り付け量(数)が増える方
向にパラメータ操作を行う。
The case in which the adjustment request amount is decreasing although the replenishment request amount is increasing. In this case, the process allocation amount (number) is increased even though the order amount is increasing.
Is decreased, the parameter operation is performed in a direction to increase the process allocation amount (number).

【0063】は補充要求量が横ばいにもかかわらず、
調整要求量は上昇しているケースであり、この場合に
は、受注量が増えていないのに工程割り付け量(数)は
増えているため、工程割り付け量(数)が減る方向にパ
ラメータ操作を行う。
Although the replenishment request amount is flat,
In this case, the adjustment request amount is increasing. In this case, although the order allocation amount has not increased, the process allocation amount (number) has increased, so the parameter operation has to be performed in the direction in which the process allocation amount (number) decreases. Do.

【0064】は補充要求量、調整要求量ともに横ばい
のケースであり、この場合には、受注量、工程割り付け
量(数)とも安定しているため、パラメータを操作する
ことなく現状を維持する。
Is the case where both the replenishment request amount and the adjustment request amount are flat. In this case, since both the order reception amount and the process allocation amount (number) are stable, the current state is maintained without operating the parameters.

【0065】は補充要求量が横ばいにもかかわらず、
調整要求量は下降しているケースであり、受注量は安定
しているのに、工程割り付け量(数)は減っているた
め、工程割り付け量(数)が増える方向にパラメータ操
作を行う。
Although the replenishment request amount is flat,
In this case, the adjustment request amount is falling. The order amount is stable, but the process allocation amount (number) is decreasing. Therefore, the parameter operation is performed in the direction in which the process allocation amount (number) increases.

【0066】は補充要求量が下降しているにもかかわ
らず、調整要求量は上昇しているケースであり、この場
合には、工程割り付け量(数)が減る方向にパラメータ
操作を行う。
In the case of (a), although the replenishment request amount is falling, the adjustment request amount is rising. In this case, the parameter operation is performed in a direction in which the process allocation amount (number) decreases.

【0067】は補充要求量が下降しているにもかかわ
らず、調整要求量は安定しているケースであり、この場
合には、受注量が減っているのに工程割り付け量(数)
は横ばいであるため、工程割り付け量(数)が減る方向
にパラメータ操作を行う。
In the case where the adjustment request amount is stable despite the decrease in the replenishment request amount, in this case, the process allocation amount (number) is reduced even though the order amount is decreasing.
Is flat, the parameter operation is performed in the direction in which the process allocation amount (number) decreases.

【0068】は補充要求量、調整要求量ともに下降し
ているケースであり、この場合には、受注量が減ってき
て、工程割り付け量(数)も減っているので、パラメー
タを操作することなく現状を維持する。
In the case where both the replenishment request amount and the adjustment request amount are falling, in this case, the order receiving amount has decreased and the process allocation amount (number) has also decreased. Maintain the status quo.

【0069】このようなパラメータ操作によって、生産
量の調整を需要に合わせた形で自動的に調整すること
で、需要変動に合わせたより最適な生産計画が作成でき
る。
By automatically adjusting the production amount according to the demand by such parameter operation, a more optimal production plan can be created in accordance with the demand fluctuation.

【0070】[0070]

【発明の効果】本発明の生産計画作成システムによれ
ば、負荷調整手段で成型工程の負荷調整と加工工程の負
荷調整とを行うので、成型工程の後に人手による組立加
工工程がある場合、成型ができても人手不足で組立加工
ができないといった事態は発生しない。つまり、より現
実に則した負荷調整を行うことができるので、より適正
な生産計画を作成することができる。
According to the production planning system of the present invention, the load adjustment means performs the load adjustment in the molding process and the load adjustment in the machining process. Even if it is possible, the situation that assembly processing cannot be performed due to lack of labor does not occur. That is, the load can be adjusted more realistically, so that a more appropriate production plan can be created.

【0071】また、本発明の生産計画作成システムによ
れば、成型工程では部品単位での山積みを行い、成型能
力に稼働率というパラメータを掛け合わせることによっ
て、より現実に近い負荷オーバの判定基準を設定でき、
また、加工工程では製品単位での山積みを行い、加工能
力に加工人員数というパラメータを掛け合わせることに
よって、より現実に近い負荷オーバの判定基準を設定で
きるので、負荷調整が現実に則したものとなり、その結
果、より適正な生産計画を作成することができる。
Further, according to the production planning system of the present invention, in the molding process, piles are made in units of parts, and by multiplying the molding capacity by a parameter called the operating rate, a more realistic load over judgment criterion can be obtained. Can be set,
In addition, in the machining process, a pile of individual products is piled up, and by multiplying the machining capacity by the parameter of the number of machining personnel, it is possible to set a more realistic overload judgment criterion, so that the load adjustment is in line with reality. As a result, a more appropriate production plan can be created.

【0072】また、本発明の生産計画作成システムによ
れば、負荷オーバを削除する2つの基準である稼働率お
よび加工人員数を、在庫補充要求量と調整要求量の変動
傾向に従い、一定基準で自動的に変更するように構成し
たので、生産量の調整を需要に合わせた形で自動的に調
整できるため、需要変動に合わせたより最適な生産計画
を作成することができる。
Further, according to the production plan creation system of the present invention, the operating rate and the number of machining personnel, which are the two criteria for eliminating the overload, are set on a constant basis in accordance with the fluctuation tendency of the required inventory replenishment and the required adjustment. Since it is configured to change automatically, the adjustment of the production amount can be automatically adjusted according to the demand, so that a more optimal production plan can be created according to the fluctuation of demand.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の生産計画作成システムの一実施形態を
示すブロック図である。
FIG. 1 is a block diagram illustrating an embodiment of a production plan creation system according to the present invention.

【図2】図1に示す生産計画作成システムを構成する在
庫補充要求量ファイルに記録されている在庫補充要求量
データの一例を示す説明図である。
FIG. 2 is an explanatory diagram showing an example of required inventory replenishment amount data recorded in a required inventory replenishment amount file constituting the production plan creating system shown in FIG. 1;

【図3】図1に示す生産計画作成システムを構成する部
品構成ファイルに記録されている部品構成データの一例
を示す説明図である。
FIG. 3 is an explanatory diagram showing an example of component configuration data recorded in a component configuration file constituting the production plan creation system shown in FIG. 1;

【図4】図1に示す生産計画作成システムを構成する生
産能力ファイルに記録されている生産能力データの一例
を示す説明図である。
FIG. 4 is an explanatory diagram showing an example of production capacity data recorded in a production capacity file constituting the production plan creation system shown in FIG. 1;

【図5】図1に示す生産計画作成システムを構成する品
切れ予測ファイルに記録されている品切れ予測データの
一例を示す説明図である。
FIG. 5 is an explanatory diagram showing an example of out-of-stock prediction data recorded in an out-of-stock prediction file included in the production plan creation system shown in FIG. 1;

【図6】図5に示す品切れ予測データを作成する際に用
いられる、各製品の在庫量と平均出荷量とを示すデータ
の一例を示す説明図である。
FIG. 6 is an explanatory diagram showing an example of data indicating a stock amount and an average shipment amount of each product used when creating the out-of-stock prediction data shown in FIG. 5;

【図7】図1に示す生産計画作成システムを用いて製品
の生産計画を作成する手順を説明するフローチャートで
ある。
FIG. 7 is a flowchart illustrating a procedure for creating a product production plan using the production plan creation system shown in FIG. 1;

【図8】図1に示す生産計画作成システムを用いて作成
した生産計画データの一例を示す説明図である。
FIG. 8 is an explanatory diagram showing an example of production plan data created by using the production plan creation system shown in FIG. 1;

【図9】図1に示す生産計画作成システムを用いて作成
した生産計画に従って、複数の生産工程に対する部品の
割付けを行った結果の一例を示す説明図である。
FIG. 9 is an explanatory diagram showing an example of a result of allocating parts to a plurality of production processes according to a production plan created by using the production plan creation system shown in FIG. 1;

【図10】補充要求量と調整要求量との近似直線の関係
を示す説明図である。
FIG. 10 is an explanatory diagram showing a relationship between an approximate straight line between a replenishment request amount and an adjustment request amount.

【符号の説明】[Explanation of symbols]

1 CPU 1a 部品展開部 1b 生産工程割付部 1c 負荷判断部 1d 処理対象生産工程決定部 1e 生産量調整部 1f 動作制御部 2 記憶装置 2a 在庫補充要求量ファイル 2b 部品構成ファイル 2c 生産計画ファイル 2d 生産能力ファイル 2e 処理対象生産工程ファイル 2f 品切れ予測ファイル 3 入出力制御部 4 入力装置 5 表示装置 6 出力装置 DESCRIPTION OF SYMBOLS 1 CPU 1a Parts development part 1b Production process allocation part 1c Load judgment part 1d Processing target production process determination part 1e Production amount adjustment part 1f Operation control part 2 Storage device 2a Inventory replenishment request amount file 2b Parts configuration file 2c Production plan file 2d Production Performance file 2e Production process file to be processed 2f Out-of-stock forecast file 3 Input / output control unit 4 Input device 5 Display device 6 Output device

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 複数の成型工程と、これら成型工程で成
型された部品を用いて製品を組み立てる加工工程とを有
する生産ラインに適用され、製品の在庫補充要求量に基
づいて生産計画を作成する在庫補充方式の生産計画作成
システムであって、 製品の在庫補充要求量に基づいて前記複数の成型工程お
よび前記加工工程に部品および製品を割り付ける工程割
付手段と、 この工程割付手段によって部品および製品を各工程に割
り付けた結果、負荷オーバが生じる成型工程および加工
工程について、その成型工程の負荷調整と加工工程の負
荷調整とを行う負荷調整手段とを備え、 この負荷調整手段によって各工程の負荷を調整した後の
調整要求量に基づき、各部品を実際の成型工程に割り付
けて生産計画を作成することを特徴とする生産計画作成
システム。
The present invention is applied to a production line having a plurality of molding steps and a processing step of assembling a product using parts molded in these molding steps, and creates a production plan based on a required stock replenishment amount of the product. An inventory replenishment type production plan creation system, comprising: a process allocating means for allocating parts and products to the plurality of molding processes and the machining processes based on a product replenishment request amount; For a molding process and a machining process in which an overload occurs as a result of being assigned to each process, a load adjusting means for performing a load adjustment in the molding process and a load adjustment in the machining process is provided. A production plan creation system characterized by allocating each part to an actual molding process and creating a production plan based on the adjusted required amount after adjustment. Stem.
【請求項2】 前記負荷調整手段は、負荷オーバが生じ
る加工工程については、その工程に割り付けられた製品
の中で品切れ予測日が一番遅い製品の生産計画を削除す
ることで、その工程での加工能力内になるように負荷調
整を行い、負荷オーバが生じる成型工程については、そ
の工程に割り付けられた部品の中で品切れ予測日が一番
遅い製品に関連する部品の生産計画を削除することで、
その工程での成型能力内になるように負荷調整を行うこ
とを特徴とする請求項1に記載の生産計画作成システ
ム。
2. The method according to claim 1, wherein the load adjustment unit deletes a production plan of a product having a latest out-of-stock predicted date among the products assigned to the process in the process in which the load is over. Adjust the load so that it is within the processing capacity of the part, and for the molding process where the load is over, delete the production plan of the part related to the product with the latest out-of-stock forecast date among the parts allocated to that process By that
2. The production plan creation system according to claim 1, wherein the load is adjusted so as to be within the molding capacity in the process.
【請求項3】 前記負荷調整手段は、加工工程において
製品の負荷調整を行ったときには、その負荷調整に関連
する部品が割り付けられている成型工程においても当該
部品の負荷調整を行い、成型工程において部品の負荷調
整を行ったときには、その負荷調整の対象となった部品
に関連する製品の負荷調整を加工工程においても行うこ
とを特徴とする請求項2に記載の生産計画作成システ
ム。
3. When the load adjustment of the product is performed in the processing step, the load adjustment means also adjusts the load of the part in the molding step to which a part related to the load adjustment is allocated. 3. The production plan creation system according to claim 2, wherein when the load adjustment of the component is performed, the load adjustment of the product related to the component subjected to the load adjustment is also performed in the processing step.
【請求項4】 前記負荷調整手段は、成型負荷および加
工負荷をパラメータとして各工程での負荷オーバの判定
基準となる成型能力および加工能力を設定することを特
徴とする請求項1、2または3に記載の生産計画作成シ
ステム。
4. The method according to claim 1, wherein said load adjusting means sets a molding ability and a machining ability as a criterion for determining an overload in each step by using the molding load and the machining load as parameters. Production planning system described in 1.
【請求項5】 前記成型工程では稼働率をパラメータと
して、この稼働率を成型能力に掛け合わせ、前記加工工
程では加工人員数をパラメータとして、この加工人員数
を加工能力に掛け合わせることを特徴とする請求項4に
記載の生産計画作成システム。
5. The method according to claim 1, wherein the operating ratio is multiplied by the molding capacity in the molding step, and the operating capacity is multiplied by the machining capacity in the processing step. The production plan creation system according to claim 4, wherein
【請求項6】 前記パラメータである稼働率および加工
人員数を、過去の在庫補充要求量および調整要求量の変
化に対応させて変更することを特徴とする請求項5に記
載の生産計画作成システム。
6. The production plan creating system according to claim 5, wherein the operating rate and the number of processing personnel, which are the parameters, are changed in accordance with a change in a past stock replenishment request amount and an adjustment request amount. .
JP34342799A 1999-12-02 1999-12-02 Production planning system Pending JP2001159907A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP34342799A JP2001159907A (en) 1999-12-02 1999-12-02 Production planning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP34342799A JP2001159907A (en) 1999-12-02 1999-12-02 Production planning system

Publications (1)

Publication Number Publication Date
JP2001159907A true JP2001159907A (en) 2001-06-12

Family

ID=18361440

Family Applications (1)

Application Number Title Priority Date Filing Date
JP34342799A Pending JP2001159907A (en) 1999-12-02 1999-12-02 Production planning system

Country Status (1)

Country Link
JP (1) JP2001159907A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013196381A (en) * 2012-03-19 2013-09-30 Mitsubishi Heavy Ind Ltd Production planning device, production planning method and production planning program
KR101512472B1 (en) 2012-11-07 2015-04-16 한국타이어 주식회사 Tread and sidewall production plan system and method in extruding process
CN114248149A (en) * 2020-09-23 2022-03-29 上海赛科利汽车模具技术应用有限公司 Method, system and equipment for calculating workpiece angle in die numerical control machining process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013196381A (en) * 2012-03-19 2013-09-30 Mitsubishi Heavy Ind Ltd Production planning device, production planning method and production planning program
KR101512472B1 (en) 2012-11-07 2015-04-16 한국타이어 주식회사 Tread and sidewall production plan system and method in extruding process
CN114248149A (en) * 2020-09-23 2022-03-29 上海赛科利汽车模具技术应用有限公司 Method, system and equipment for calculating workpiece angle in die numerical control machining process

Similar Documents

Publication Publication Date Title
US5321620A (en) Inference planning system
JPH05225205A (en) Sequential defined production planning system
US20030033180A1 (en) System and method for optimizing resource plans
CN116529741A (en) Closed loop APS scheduling optimization method, system and storage medium based on simulation
JP2007034429A (en) Production planning system
JP2002373013A (en) Production scheduling method, program for computer to execute the same method and computer-readable recording medium with the program recorded thereon
JP6317910B2 (en) Parts equipment allocation device, parts equipment allocation method, and program
JPH06231135A (en) Production planning system
JP4135311B2 (en) Production planning method and system
EP2169495A1 (en) Method for modelling a manufacturing process
JP2001159907A (en) Production planning system
JP3240237B2 (en) Production planning system
JP4746334B2 (en) Production planning method, apparatus, and computer program for manufacturing process
JP5244662B2 (en) Production management system and alternative BOM configuration development method and program
Gola et al. Mathematical models for manufacturing systems capacity planning and expansion–an overview
JP3241714B2 (en) Plan type inference method and apparatus
US8185420B2 (en) Approximating cycle times within material flow network
JP4224854B2 (en) Push-pull mixed type optimum mixed production planning method, push-pull mixed type optimum mixed production planning device, and program
KR101498528B1 (en) Steel bias cutter allocating plan system and method in cutting Process
WO2006077930A1 (en) Production scheduling system
JP2000158300A (en) Production plan preparing method and system thereof
JPH11114784A (en) Production schedule forming device
JP2004005378A (en) Method and device for optimizing production planning
JP2001184115A (en) Production plan forming system and production plan forming method using the system
WO2024090395A1 (en) Production management device, production management method, production management program, and recording medium