JP2001146713A - Continuous beam bridge structure - Google Patents

Continuous beam bridge structure

Info

Publication number
JP2001146713A
JP2001146713A JP32925899A JP32925899A JP2001146713A JP 2001146713 A JP2001146713 A JP 2001146713A JP 32925899 A JP32925899 A JP 32925899A JP 32925899 A JP32925899 A JP 32925899A JP 2001146713 A JP2001146713 A JP 2001146713A
Authority
JP
Japan
Prior art keywords
prestress
girder
steel sheet
corrugated steel
sheet web
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP32925899A
Other languages
Japanese (ja)
Other versions
JP3728391B2 (en
Inventor
Setsuo Iwata
節雄 岩田
Susumu Matsuno
松野  進
Kazuhiro Yasuda
和宏 安田
Takeshi Shiomi
塩見  健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Zosen Corp
Original Assignee
Hitachi Zosen Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Zosen Corp filed Critical Hitachi Zosen Corp
Priority to JP32925899A priority Critical patent/JP3728391B2/en
Publication of JP2001146713A publication Critical patent/JP2001146713A/en
Application granted granted Critical
Publication of JP3728391B2 publication Critical patent/JP3728391B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a continuous beam bridge structure capable of easily introducing prestress to an intermediate supporting point of a continuous beam bridge. SOLUTION: A corrugated steel plate wave 11 is placed to a steel girder 1 part in an intermediate supporting point of a continuous beam. Prestress is introduced to a concete floor slab 2 in the intermediate supporting point placing the corrugated steel plate wave 11 thereto. Prestress can be easily introduced to the intermediate supporting point of a continuous beam bridge. A space for introducing prestress is not required, introduced prestress is clarified, and even when prestress is decreased by drying shrinkage and creep, optimum prestress can be always reintroduced. When reintroduction of prestress is used together with prestress introduction in the direction of a bridge axis by jack up/down, more accurate prestress can be introduced.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、連続桁橋梁の構造
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a continuous girder bridge.

【0002】[0002]

【従来の技術】図9に2径間連続合成桁形式の橋梁を示
すが、この合成桁は、鋼桁1とコンクリート床版2とが
スタッド3を介して機械的に結合されているもので、非
合成桁に比べて撓み等の合成が増加し、鋼桁1の重量を
減じることができるので、コストダウンが図れる。ま
た、疲労クラックが発生しにくい等、損傷しにくい有利
な橋梁構造である。
2. Description of the Related Art FIG. 9 shows a two-span continuous composite girder bridge in which a steel girder 1 and a concrete floor slab 2 are mechanically connected via studs 3. As compared with the non-composite girder, the composition such as bending increases and the weight of the steel girder 1 can be reduced, so that the cost can be reduced. In addition, the bridge structure is advantageous in that it is not easily damaged due to, for example, the occurrence of fatigue cracks.

【0003】ところで、連続桁橋梁では、一般に橋の中
間部にも中間支承4を配置し、図9(b)に示すよう
に、鋼桁1がこの中間支承4によって支持されている。
そして、このような連続桁が自動車などの荷重(活荷
重)を受けると、支間中間部Aにおいては、図9(c)
に示したような正曲げモーメントm1 によって、コンク
リート床版2に図9(d)に示したような圧縮応力σc
が生じるので、コンクリート床版2にクラックを発生さ
せるような引張り応力は生じない。
[0003] In a continuous girder bridge, an intermediate bearing 4 is generally arranged also at an intermediate portion of the bridge, and the steel girder 1 is supported by the intermediate bearing 4 as shown in FIG.
When such a continuous girder receives a load (live load) of an automobile or the like, in the span intermediate portion A, FIG.
Due to the positive bending moment m1 shown in FIG. 9, the compressive stress σc shown in FIG.
Therefore, no tensile stress that causes cracks in the concrete floor slab 2 is generated.

【0004】しかし、中間支点部Bにおいては、図9
(c)に示したような負曲げモーメントm2 によって、
コンクリート床版2に図9(e)に示したような引張り
応力σtが発生するために、その引張り応力がコンクリ
ートのクラック発生応力を超える場合には、図9(c)
に示したように、コンクリート床版2にクラック5が発
生する可能性がある。
However, at the intermediate fulcrum B, FIG.
By the negative bending moment m2 as shown in (c),
When the tensile stress .sigma.t as shown in FIG. 9 (e) is generated in the concrete slab 2 and the tensile stress exceeds the crack generation stress of concrete, FIG. 9 (c)
As shown in (1), there is a possibility that cracks 5 may occur in the concrete slab 2.

【0005】そこで、上記したような、中間支点部Bに
おけるコンクリート床版2のクラック5の発生を防止す
るために、当該部分にプレストレスを導入したものが採
用されるようになってきた。
Therefore, in order to prevent the occurrence of cracks 5 in the concrete slab 2 at the intermediate fulcrum B as described above, a structure in which prestress is introduced into the portion has been adopted.

【0006】このうち、図10は合成桁の中間支点部B
におけるコンクリート床版部分に、直接プレストレスを
導入する場合を示したもので、中間支点部Bに例えばプ
レキャスト床版6を配置し、このプレキャスト床版6の
橋軸方向に、プレストレス鋼線7を用いてプレストレス
を導入することで、図10(c)に示したように、中間
支点部Bにおけるプレキャスト床版6に、一様に圧縮応
力σcを発生させるものである。
FIG. 10 shows an intermediate fulcrum B of the composite girder.
Shows a case where prestress is directly introduced into the concrete slab portion of the present invention. For example, a precast slab 6 is disposed at the intermediate fulcrum portion B, and a prestressed steel wire 7 is provided in the bridge axis direction of the precast slab 6. By introducing a prestress using the method, a compressive stress σc is uniformly generated in the precast floor slab 6 at the intermediate fulcrum B as shown in FIG.

【0007】そして、このプレストレスの導入により、
活荷重が作用して鋼桁1の下フランジに引張り応力σt
が発生しても、プレストレスによる圧縮応力σcと差し
引きすると、図10(d)に示したように、プレキャス
ト床版6には圧縮応力σc1が残留することになって、
プレキャスト床版6にクラックが発生しないようにな
る。
[0007] With the introduction of this prestress,
A live load acts on the lower flange of steel girder 1, resulting in a tensile stress σt.
However, when the prestress is subtracted from the compressive stress .sigma.c due to the prestress, the compressive stress .sigma.c1 remains in the precast floor slab 6, as shown in FIG.
Cracks do not occur in the precast floor slab 6.

【0008】また、図11は橋梁端部の支点の上下方向
変位を拘束したまま、鋼桁1を中間支点部Bで、δだけ
ジャッキアップすることで、橋軸方向にプレストレスを
導入する場合を示したもので、鋼桁1には予めスタッド
3が溶接されており、図11(a)に示したように、中
間支点部Bをδだけジャッキアップしたままでコンクリ
ート床版2を打設し(図11(b))、硬化した後ジャ
ッキを緩めて前記δだけダウンさせると(図11
(c))、鋼桁1は前に上昇させた分のスプリングバッ
ク量とコンクリート床版2及び鋼桁1の自重によって元
の位置に沈下し、コンクリート床版2には、図11
(d)に示すように、圧縮応力σcが導入される。
FIG. 11 shows a case where prestress is introduced in the bridge axis direction by jacking up the steel girder 1 by δ at the intermediate fulcrum B while restraining the vertical displacement of the fulcrum at the bridge end. The stud 3 is welded to the steel girder 1 in advance, and as shown in FIG. 11A, the concrete floor slab 2 is cast while the intermediate fulcrum B is jacked up by δ. (FIG. 11 (b)), and after hardening, the jack is loosened to reduce the value by δ (FIG. 11 (b)).
(C)) The steel girder 1 sinks to its original position due to the springback amount and the weight of the concrete slab 2 and the steel girder 1 which have been raised before.
As shown in (d), a compressive stress σc is introduced.

【0009】[0009]

【発明が解決しようとする課題】しかしながら、図10
に示したような、コンクリート床版に直接プレストレス
を導入する方法では、次に列挙するような問題がある。 プレキャスト床版6が、鋼桁1とスタッド3で拘束
されているので、主桁近傍では、プレストレスが入りに
くく、コンクリート床版全域に均等にプレストレスが導
入されない。
However, FIG.
The method of directly introducing prestress into a concrete slab as described in (1) has the following problems. Since the precast slab 6 is constrained by the steel girder 1 and the stud 3, prestress is unlikely to enter near the main girder, and prestress is not uniformly introduced to the entire concrete slab.

【0010】 プレストレスを導入するためのジャッ
キを配置するスペースを確保する必要があるが、このス
ペースをプレストレス導入後に目地コンクリート8で埋
める必要があるので、その分、工程が延びることにな
る。 プレストレスの導入後にプレストレス量が、乾燥収
縮やクリープによって減少する量を推定できない。ま
た、プレストレス量が減少しても、プレストレスを再導
入して一定のプレストレスを確保することが困難であ
る。
It is necessary to secure a space for arranging jacks for introducing prestress, but it is necessary to fill this space with joint concrete 8 after introducing the prestress, so that the process is extended accordingly. After the introduction of prestress, it is not possible to estimate the amount by which the prestress decreases due to drying shrinkage or creep. Further, even if the amount of prestress is reduced, it is difficult to reintroduce the prestress and secure a certain prestress.

【0011】また、図11に示したような、ジャッキア
ップ・ジャッキダウンによるプレストレス導入法では、
以下に列挙する問題がある。 鋼桁1の嵩上げ量が現実には約1m程度になり、現
場作業の安全性に十分な注意が必要になる。
[0011] In the prestress introduction method using jack-up and jack-down as shown in FIG.
There are problems listed below. The raised amount of the steel girder 1 is actually about 1 m, and it is necessary to pay sufficient attention to the safety of field work.

【0012】 コンクリートの硬化中にコンクリート
の乾燥収縮によって同一嵩上げ量でも導入するプレスト
レス量が異なり、必ずしも所定のプレストレスを導入で
きない可能性がある。 一度ジャッキアップ量を設定してコンクリートが硬
化すると、ジャッキダウン時にプレストレス量が不足し
ても修正することができない。
[0012] The amount of prestress to be introduced is different even if the amount of raising is the same due to drying shrinkage of the concrete during hardening of the concrete, and a predetermined prestress may not always be introduced. Once the amount of jack-up is set and the concrete hardens, it cannot be corrected even if the amount of pre-stress is insufficient when jacking down.

【0013】 ジャッキダウン時以降にコンクリート
の乾燥収縮及びクリープによって予想以上にプレストレ
ス量が減少しても修正することができない。なお、プレ
ストレスの減少量を測定するには、センサーなどを埋め
込むことで可能であるが、このような方法は、非常に高
価であり、特殊技術を必要とする。
[0013] Even if the amount of prestress is unexpectedly reduced due to drying shrinkage and creep of the concrete after the jack down, it cannot be corrected. It is to be noted that the amount of decrease in prestress can be measured by embedding a sensor or the like, but such a method is very expensive and requires special techniques.

【0014】本発明は、上記した連続桁橋梁にあった問
題点に鑑みてなされたものであり、連続桁橋梁の中間支
点部にプレストレスを導入することなく、活荷重が作用
した場合にも、中間支点部の床版にクラックが発生する
ことのない連続桁橋梁構造を提供することを目的として
いる。
The present invention has been made in view of the above-described problems of the continuous girder bridge, and has been developed even when a live load is applied without introducing prestress to the intermediate fulcrum portion of the continuous girder bridge. It is an object of the present invention to provide a continuous girder bridge structure in which cracks do not occur in the floor slab of the intermediate fulcrum.

【0015】[0015]

【課題を解決するための手段】上記した目的を達成する
ために、本発明の連続桁橋梁構造は、連続桁の中間支点
部における鋼桁部分に、波形鋼板ウェブを配置し、この
波形鋼板ウェブを配置した中間支点部のコンクリート床
版にプレストレスを導入することとしている。そして、
このようにすることで、連続桁の中間支点部に容易にプ
レストレスを導入することができる。
In order to achieve the above-mentioned object, a continuous girder bridge structure of the present invention has a corrugated steel sheet web disposed on a steel girder portion at an intermediate fulcrum of a continuous girder. The prestress is to be introduced into the concrete slab at the middle fulcrum where the is placed. And
This makes it possible to easily introduce prestress into the intermediate fulcrum of the continuous girder.

【0016】[0016]

【発明の実施の形態】本発明の連続桁橋梁構造は、連続
桁の中間支点部における鋼桁部分に、波形鋼板ウェブを
配置し、この波形鋼板ウェブを配置した中間支点部のコ
ンクリート床版にプレストレスを導入したものである。
すなわち、本発明の連続桁橋梁構造は、図1(c)に示
すように、連続桁の中間支点部の負曲げモーメント(−
M)の範囲内に波形鋼板ウェブを使用し、この波形鋼板
ウェブ上のコンクリート床版にプレストレスを導入する
ようにしたものである。
BEST MODE FOR CARRYING OUT THE INVENTION A continuous girder bridge structure according to the present invention has a corrugated steel sheet web disposed on a steel girder portion at an intermediate fulcrum portion of a continuous girder, and is provided on a concrete slab of the intermediate fulcrum portion where the corrugated steel sheet web is disposed. Prestress is introduced.
That is, as shown in FIG. 1 (c), the continuous girder bridge structure of the present invention has a negative bending moment (-
M) The corrugated steel sheet web is used in the range of M), and prestress is introduced into the concrete slab on the corrugated steel sheet web.

【0017】本発明の連続桁橋梁構造は、連続桁の中間
支点部における鋼桁部分に、波形鋼板ウェブを配置する
ことで、この波形鋼板ウェブ上のコンクリート床版に容
易にプレストレスを導入することができるようになる。
In the continuous girder bridge structure of the present invention, the prestress is easily introduced into the concrete slab on the corrugated steel web by arranging the corrugated steel web on the steel girder portion at the middle fulcrum of the continuous girder. Will be able to do it.

【0018】本発明の連続桁橋梁構造において、波形鋼
板ウェブの中間支点位置に添接板を取付け、この添接板
と波形鋼板ウェブとで形成された空洞に、コンクリート
を充填した場合には、コンクリート充填部においては、
圧縮荷重に対する耐力が増加する。
In the continuous girder bridge structure of the present invention, when an adhering plate is attached to the middle fulcrum position of the corrugated steel sheet web and concrete is filled in a cavity formed by the adhering plate and the corrugated steel sheet web, In the concrete filling section,
Strength against compressive load increases.

【0019】また、本発明の連続桁橋梁構造において、
波形鋼板ウェブの上フランジに代えて、多数のリング状
ジベルを取付けた場合には、より有効にコンクリート床
版にプレストレスを導入することができる。
Further, in the continuous girder bridge structure of the present invention,
When a large number of ring-shaped dowels are attached instead of the upper flange of the corrugated steel sheet web, prestress can be more effectively introduced into the concrete slab.

【0020】そして、この際、鋼桁と波形鋼板ウェブと
の取付けに際し、鋼桁の上フランジのみを波形鋼板ウェ
ブ側に張出させ、この張出し部に設けた嵌入用切欠きに
波形鋼板ウェブを嵌入させて溶接一体化した場合には、
接合部での応力集中を小さくすることができる。また、
鋼桁の上フランジの張出し部に丸みをつけた場合には、
接合部での応力集中をより小さくすることができる。
At this time, when the steel girder and the corrugated steel sheet web are attached, only the upper flange of the steel girder is extended toward the corrugated steel sheet web side, and the corrugated steel sheet web is inserted into the notch for insertion provided in this projection. In the case of fitting and welding integrated,
The stress concentration at the joint can be reduced. Also,
If the overhang of the upper flange of the steel girder is rounded,
Stress concentration at the joint can be further reduced.

【0021】[0021]

【実施例】以下、本発明の連続桁橋梁構造を図1〜図8
に示す実施例に基づいて説明する。図1は本発明の連続
桁橋梁構造の概要を説明する図で、(a)は橋脚間に橋
桁を掛け渡した図、(b)は橋桁の上にコンクリートを
打設した図、(c)は橋桁に作用する曲げモーメントを
説明した図、図2は本発明の連続桁橋梁構造の説明図
で、中間支点部分の斜視図、図3の(a)は図2を側面
方向から見た図、(b)は図2を平面方向から見た図、
(c)は図2を正面方向から見た図、図4は図2に示し
た本発明の連続桁橋梁構造において、プレストレスを導
入する際の説明図(斜視図)、図5の(a)は図4のA
−A断面を平面方向から見た図、(b)は図4のA−A
断面図、(c)は図4のB−B断面図、(d)は図4の
C−C断面図、図6は本発明の連続桁橋梁構造の他の実
施例の説明図で、(a)は側面方向から見た図、(b)
は中間支点部の斜視図、図7は図6(b)の要部拡大斜
視図、図8は図6に示した実施例における鋼桁と波形鋼
板ウェブとの溶接部の説明図で、(a)は通常の溶接構
造図、(b)は本発明の構造を採用した鋼桁の上フラン
ジの説明図、(c)は(b)の構造を採用した場合の溶
接構造図である。
1 to 8 show a continuous girder bridge structure of the present invention.
A description will be given based on the embodiment shown in FIG. 1A and 1B are diagrams for explaining the outline of a continuous girder bridge structure of the present invention. FIG. 1A is a diagram in which a bridge girder is bridged between piers, FIG. 1B is a diagram in which concrete is cast on the bridge girder, and FIG. FIG. 2 is a view for explaining a bending moment acting on a bridge girder, FIG. 2 is an explanatory view of a continuous girder bridge structure of the present invention, a perspective view of an intermediate fulcrum portion, and FIG. 3A is a view of FIG. , (B) is a view of FIG. 2 viewed from a plane direction,
(C) is a view of FIG. 2 as viewed from the front, FIG. 4 is an explanatory view (perspective view) when introducing a prestress in the continuous girder bridge structure of the present invention shown in FIG. 2, (a) of FIG. ) Is A in FIG.
FIG. 4A is a view of a cross section viewed from a plane direction, and FIG.
FIG. 6 (c) is a cross-sectional view taken along line BB of FIG. 4, FIG. 6 (d) is a cross-sectional view taken along line CC of FIG. 4, and FIG. 6 is an explanatory view of another embodiment of the continuous girder bridge structure of the present invention. (a) is a view from the side, (b)
7 is a perspective view of an intermediate fulcrum, FIG. 7 is an enlarged perspective view of a main part of FIG. 6B, FIG. 8 is an explanatory view of a welded portion between the steel girder and the corrugated steel sheet web in the embodiment shown in FIG. FIG. 3A is a diagram of a normal welding structure, FIG. 3B is an explanatory diagram of an upper flange of a steel girder adopting the structure of the present invention, and FIG. 3C is a diagram of a welding structure adopting the structure of FIG.

【0022】図1〜図8において、11は波形鋼板ウェ
ブで、本発明の連続桁橋梁構造では、この波形鋼板ウェ
ブ11を、連続桁の中間支点部Bにおける鋼桁1部分に
配置しているのである。
1 to 8, reference numeral 11 denotes a corrugated steel sheet web. In the continuous girder bridge structure of the present invention, the corrugated steel sheet web 11 is disposed on a steel girder 1 at an intermediate fulcrum B of the continuous girder. It is.

【0023】そして、施工に際しては、先ず、波形鋼板
ウェブ11とI型の鋼桁1とを溶接し、図1(a)に示
すように、橋脚12間に波形鋼板ウェブ11と鋼桁1と
を溶接して一体化した橋桁を掛け渡す。この時、波形鋼
板ウェブ11には上下にフランジ11a,11bがつい
ているので、波形鋼板ウェブ11がアコーディオンのよ
うに広がることはない。
At the time of construction, first, the corrugated steel sheet web 11 and the I-shaped steel girder 1 are welded to each other, and as shown in FIG. And bridge the bridge girder. At this time, since the corrugated steel sheet web 11 has upper and lower flanges 11a and 11b, the corrugated steel sheet web 11 does not spread like an accordion.

【0024】この状態で、鋼桁1や波形鋼板ウェブ11
の上フランジ1a,11a上にコンクリートを打設する
と、鋼桁1や波形鋼板ウェブ11の上フランジ1a,1
1a上に溶接されたスタッド3を介してコンクリート床
版2と鋼桁1や波形鋼板ウェブ11が結合される。
In this state, the steel girder 1 and the corrugated steel web 11
When concrete is cast on the upper flanges 1a, 11a, the steel beams 1 and the corrugated steel sheet web 11 have upper flanges 1a, 1a.
The concrete slab 2 and the steel girder 1 and the corrugated steel sheet web 11 are joined via the studs 3 welded on 1a.

【0025】そして、コンクリートの硬化後に、図1
(b)に示すように、鋼桁1の波形鋼板ウェブ11近傍
に取付けたアンカー金具13にPC鋼棒14及びナット
15を取付け、PC鋼棒14を締付けることによって、
波形鋼板ウェブ11の範囲のコンクリート床版2にプレ
ストレスを導入する。
After hardening of the concrete, FIG.
As shown in (b), the PC steel rod 14 and the nut 15 are attached to the anchor 13 attached near the corrugated steel sheet web 11 of the steel girder 1, and the PC steel rod 14 is tightened.
Prestress is introduced into the concrete slab 2 in the area of the corrugated steel sheet web 11.

【0026】導入するプレストレス量Pは、コンクリー
ト床版2に導入する平均圧縮応力を1.47MPaとす
ると、コンクリート床版2(幅16m、厚さ0.32
m)全体では、 P=16×0.32×1.47×106 =752640
0N となる。
Assuming that the average prestress to be introduced into the concrete slab 2 is 1.47 MPa, the prestress amount P to be introduced is the concrete slab 2 (width 16 m, thickness 0.32
m) Overall, P = 16 × 0.32 × 1.47 × 10 6 = 752640
0N.

【0027】従って、1桁当たり約400トンとする
と、PC鋼棒14は1本当たり約490kNの力をかけ
られるので、図3(c)に示したように、1桁当たり8
本のPC鋼棒14をセットできるように、アンカー金具
13を設計すればよいことになる。一般に鋼桁1の上フ
ランジ1aの幅は500〜600mmであるから、1桁
当たり8本程度のPC鋼棒14を取付けるのは、それほ
ど困難ではない。
Therefore, if the power is set to about 400 tons per digit, the PC steel rod 14 can be applied with a force of about 490 kN per rod, and as shown in FIG.
What is necessary is just to design the anchor 13 so that the PC steel rod 14 can be set. Generally, the width of the upper flange 1a of the steel girder 1 is 500 to 600 mm, and it is not so difficult to mount about eight PC steel rods 14 per girder.

【0028】図2は本発明の連続桁橋梁構造における中
間支点部分の斜視図を示したものであるが、中間支点部
に配置される中間支承4にはかなりの荷重が作用する。
従って、図2、図3に示した実施例では、波形鋼板ウェ
ブ11の中間支承4に相当する位置に、添接板16を取
付けて、この添接板16と波形鋼板ウェブ11とで形成
された空洞にコンクリート17を充填し、圧縮荷重に抵
抗させるようにしている。なお、中間支点部上では鋼桁
1の捩れ変形を拘束するために、横桁18が配置される
が、この横桁18は波形鋼板ウェブ11に溶接或いはボ
ルトによって接合させる。
FIG. 2 is a perspective view of an intermediate fulcrum portion in the continuous girder bridge structure of the present invention. A considerable load acts on the intermediate bearing 4 disposed at the intermediate fulcrum portion.
Therefore, in the embodiment shown in FIGS. 2 and 3, the contact plate 16 is attached to the corrugated steel sheet web 11 at a position corresponding to the intermediate support 4, and the contact sheet 16 and the corrugated steel sheet web 11 are formed. The cavity 17 is filled with concrete 17 so as to resist a compressive load. A cross girder 18 is disposed on the intermediate fulcrum to restrain the steel girder 1 from torsional deformation. The cross girder 18 is joined to the corrugated steel sheet web 11 by welding or bolts.

【0029】図4及び図5にPC鋼棒14の詳細配置を
示す。このうち、図4の断面Aは鋼桁1、波形鋼板ウェ
ブ11、コンクリート床版2からなる主桁の外側橋軸方
向断面を、断面Bは同じく主桁の内側断面を、断面Cは
同じく主桁の支間中央断面を示すものである。
FIGS. 4 and 5 show the detailed arrangement of the PC steel rod 14. FIG. Among them, section A in FIG. 4 is an outer bridge axial section of a main girder made of steel girder 1, corrugated steel web 11, and concrete slab 2, section B is an inner cross section of the main girder, and section C is also a main girder. It is a diagram showing a center cross section of a girder.

【0030】そして、断面Aでは、橋軸方向に水平状に
PC鋼棒14を配置する。また、断面Bでは、断面Aと
同じようにPC鋼棒14を配置すると共に、コンクリー
ト床版2内に圧縮力を導入するために曲線状のPC鋼線
19を配置する。このPC鋼線19は、例えば楔形金具
20を用いて、アンカー金具13に固定する。但し、水
平状のPC鋼棒14のみで、十分なプレストレスが導入
できる場合には、前記したPC鋼線19は不要である。
In the section A, the PC steel rod 14 is arranged horizontally in the bridge axis direction. In the section B, the PC steel bars 14 are arranged in the same manner as in the section A, and the curved PC steel wires 19 are arranged to introduce a compressive force into the concrete slab 2. The PC steel wire 19 is fixed to the anchor 13 using, for example, a wedge-shaped bracket 20. However, when sufficient prestress can be introduced only by the horizontal PC steel rod 14, the above-mentioned PC steel wire 19 is unnecessary.

【0031】また、断面Cでは、上記したような主桁か
ら導入するプレストレスだけでは十分でない場合に、コ
ンクリート床版2に直接、橋軸方向のプレストレスを導
入するPC鋼線19の配置を示したものである。この場
合、PC鋼線19の定着部は、コンクリート床版2の下
面を少し大きくなるように張出し、その部分にPC鋼線
19からの圧縮力によるひび割れを防止するための補強
鉄筋21を埋設する。この断面Cにおけるプレストレス
の導入は、コンクリート床版2の下方からジャッキを用
いて行なうことになる。
In the section C, when the prestress introduced from the main girder as described above is not enough, the arrangement of the PC steel wire 19 for introducing the prestress in the bridge axis direction directly to the concrete slab 2 is adopted. It is shown. In this case, the anchoring portion of the PC steel wire 19 extends the lower surface of the concrete slab 2 so as to be slightly larger, and a reinforcing steel bar 21 for preventing cracking due to the compressive force from the PC steel wire 19 is embedded in that portion. . The introduction of the prestress in the section C is performed using a jack from below the concrete slab 2.

【0032】以上の実施例は、波形鋼板ウェブ11に上
フランジ11aが設けられているものについて示したも
のであるが、図6〜図8は上フランジがない実施例を示
している。この上フランジがない場合には、プレストレ
スを導入した場合に、この上フランジが抵抗しないの
で、より有効にコンクリート床版2にプレストレスを導
入することができるようになる。
In the above embodiment, the corrugated steel sheet web 11 is provided with the upper flange 11a, but FIGS. 6 to 8 show embodiments without the upper flange. If the upper flange is not provided, when the prestress is introduced, the upper flange does not resist, so that the prestress can be more effectively introduced into the concrete slab 2.

【0033】このような上フランジを設けない場合、波
形鋼板ウェブ11とコンクリート床版2との結合は、波
形鋼板ウェブ11の上部に孔を開け、この孔にリング状
のジベル22を取付けることによって行なう。このよう
なリング状のジベル22の場合には、直筋に比べて鉄筋
の位置保持が容易であるという利点がある。
When such an upper flange is not provided, the corrugated steel sheet web 11 and the concrete slab 2 are connected by forming a hole in the upper part of the corrugated steel sheet web 11 and attaching a ring-shaped dowel 22 to the hole. Do. In the case of such a ring-shaped dowel 22, there is an advantage that the position of the reinforcing bar can be easily maintained as compared with the straight bar.

【0034】また、このような上フランジを設けない波
形鋼板ウェブ11を用いた場合、桁を中間支承4に掛け
ていく場合には、曲げ剛性が不足するという問題がある
が、このような問題に対しては、PC鋼棒14を予め取
り付けることによって、上フランジが受け持っていた引
張り力を分担するようにすればよい。なお、図6〜図8
に示した上フランジを設けない波形鋼板ウェブ11を用
いた場合でも、中間支承4上で横桁18を取付けるが、
この横桁18と波形鋼板ウェブ11との接合は、溶接或
いはボルトによって行なう。
When the corrugated steel sheet web 11 without such an upper flange is used, when the girder is hung on the intermediate support 4, there is a problem that bending rigidity is insufficient. In order to cope with this problem, the tensile strength held by the upper flange may be shared by attaching the PC steel rod 14 in advance. 6 to 8.
In the case of using the corrugated steel sheet web 11 without the upper flange shown in FIG.
The connection between the cross beam 18 and the corrugated steel sheet web 11 is performed by welding or bolts.

【0035】ところで、前後の鋼桁1と波形鋼板ウェブ
11との接合は、通常、モーメントが小さくなる位置で
突き合わせ溶接によって行なうが、上フランジを設けな
い波形鋼板ウェブ11を用いた場合、鋼桁1の上フラン
ジ1a部分では図8(a)に示したように、急激な断面
変化が生じ、疲労クラックが発生する原因になることが
懸念される。
The front and rear steel girders 1 and the corrugated steel web 11 are usually joined by butt welding at a position where the moment is small. However, when the corrugated steel web 11 having no upper flange is used, the steel girder is used. As shown in FIG. 8A, there is a concern that a sharp cross-sectional change may occur at the upper flange 1a of the tire 1 to cause fatigue cracks.

【0036】そこで、このような場合には、図8(b)
に示したように、前後の鋼桁1の上フランジ1aのみを
波形鋼板ウェブ11側に張出させ、この張出し部に設け
た嵌入用切欠き1bに、図8(c)に示すように、波形
鋼板ウェブ11を嵌入させて溶接一体化する。このよう
にした場合には、接合部での応力集中を小さくすること
ができる。
Therefore, in such a case, FIG.
As shown in FIG. 8, only the upper flange 1a of the front and rear steel girders 1 is extended toward the corrugated steel sheet web 11, and the notch for insertion 1b provided in this extended portion is provided with a notch as shown in FIG. The corrugated steel sheet web 11 is fitted and integrated by welding. In this case, the stress concentration at the joint can be reduced.

【0037】また、この時、鋼桁1の上フランジ1aの
張出し部には、図8(b)に示したように、丸みをつけ
て上フランジ1aの剛性が急激に変化しないようにした
場合には、この部分での応力集中を避けることができ
る。
At this time, as shown in FIG. 8B, the overhang of the upper flange 1a of the steel girder 1 is rounded so that the rigidity of the upper flange 1a does not change suddenly. In this case, stress concentration at this portion can be avoided.

【0038】[0038]

【発明の効果】以上説明したように、本発明に係る連続
桁橋梁構造によれば、連続桁橋梁の中間支点部に、容易
にプレストレスを導入することができる。また、本発明
に係る橋梁の主桁構造では、プレストレス導入のための
スペースを必要とせず、しかも、導入プレストレス量が
明確で、仮に乾燥収縮及びクリープによってプレストレ
スが減少しても、常に最適な量に再導入することが可能
である。また、本発明に係る橋梁の主桁構造では、ジャ
ッキアップ・ジャッキダウンによる橋軸方向のプレスト
レス導入と併用した場合には、さらに正確なプレストレ
スを導入することができる。
As described above, according to the continuous girder bridge structure of the present invention, prestress can be easily introduced into the intermediate fulcrum of the continuous girder bridge. Further, the main girder structure of the bridge according to the present invention does not require a space for introducing prestress, and furthermore, the introduced prestress amount is clear, and even if the prestress is reduced by drying shrinkage and creep, it is always It is possible to reintroduce to the optimal amount. Further, in the main girder structure of a bridge according to the present invention, more accurate prestress can be introduced when used together with prestress introduction in the bridge axis direction by jack-up / jack-down.

【0039】また、本発明の連続桁橋梁構造において、
波形鋼板ウェブの中間支点位置に添接板を取付け、この
添接板と波形鋼板ウェブとで形成された空洞に、コンク
リートを充填した場合には、このコンクリート充填部で
は、圧縮荷重に対する耐力を増加させることができる。
In the continuous girder bridge structure of the present invention,
When a contact plate is attached to the middle fulcrum position of the corrugated steel sheet web and concrete is filled in the cavity formed by this contact plate and the corrugated steel sheet web, the concrete filling portion increases the proof stress against the compressive load. Can be done.

【0040】また、本発明の連続桁橋梁構造において、
波形鋼板ウェブの上フランジに代えて、多数のリング状
ジベルを取付けた場合には、より有効にコンクリート床
版にプレストレスを導入することができる。そして、そ
の際、鋼桁と波形鋼板ウェブとの取付けに際し、鋼桁の
上フランジのみを波形鋼板ウェブ側に張出させ、この張
出し部に設けた嵌入用切欠きに波形鋼板ウェブを嵌入さ
せて溶接一体化した場合には、接合部での応力集中を小
さくすることができる。また、鋼桁の上フランジの張出
し部に丸みをつけた場合には、接合部での応力集中をよ
り小さくすることができる。
In the continuous girder bridge structure of the present invention,
When a large number of ring-shaped dowels are attached instead of the upper flange of the corrugated steel sheet web, prestress can be more effectively introduced into the concrete slab. Then, at that time, when mounting the steel girder and the corrugated steel sheet web, only the upper flange of the steel girder is extended toward the corrugated steel sheet web side, and the corrugated steel sheet web is inserted into the notch for insertion provided in this overhang portion. When integrated by welding, stress concentration at the joint can be reduced. Further, when the overhang portion of the upper flange of the steel girder is rounded, the stress concentration at the joint portion can be further reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の連続桁橋梁構造の概要を説明する図
で、(a)は橋脚間に橋桁を掛け渡した図、(b)は橋
桁の上にコンクリートを打設した図、(c)は橋桁に作
用する曲げモーメントを説明した図である。
1A and 1B are diagrams illustrating an outline of a continuous girder bridge structure of the present invention, wherein FIG. 1A is a diagram in which a bridge girder is bridged between piers, FIG. 1B is a diagram in which concrete is cast on the bridge girder, and FIG. () Is a diagram for explaining the bending moment acting on the bridge girder.

【図2】本発明の連続桁橋梁構造の説明図で、中間支点
部分の斜視図である。
FIG. 2 is an explanatory view of a continuous girder bridge structure of the present invention, and is a perspective view of an intermediate fulcrum portion.

【図3】(a)は図2を側面方向から見た図、(b)は
図2を平面方向から見た図、(c)は図2を正面方向か
ら見た図である。
3A is a diagram of FIG. 2 viewed from the side, FIG. 3B is a diagram of FIG. 2 viewed from the plane, and FIG. 3C is a diagram of FIG. 2 viewed from the front.

【図4】図2に示した本発明の連続桁橋梁構造におい
て、プレストレスを導入する際の説明図(斜視図)であ
る。
FIG. 4 is an explanatory view (perspective view) when introducing a prestress in the continuous girder bridge structure of the present invention shown in FIG. 2;

【図5】(a)は図4のA−A断面を平面方向から見た
図、(b)は図4のA−A断面図、(c)は図4のB−
B断面図、(d)は図4のC−C断面図である。
5 (a) is a view of the AA cross section of FIG. 4 viewed from the plane direction, FIG. 5 (b) is a cross sectional view of AA of FIG. 4, and FIG.
FIG. 4D is a sectional view taken along line B-C of FIG. 4.

【図6】本発明の連続桁橋梁構造の他の実施例の説明図
で、(a)は側面方向から見た図、(b)は中間支点部
の斜視図である。
FIGS. 6A and 6B are explanatory views of another embodiment of the continuous girder bridge structure of the present invention, wherein FIG. 6A is a view seen from the side, and FIG. 6B is a perspective view of an intermediate fulcrum.

【図7】図6(b)の要部拡大斜視図である。FIG. 7 is an enlarged perspective view of a main part of FIG. 6 (b).

【図8】図6に示した実施例における鋼桁と波形鋼板ウ
ェブとの溶接部の説明図で、(a)は通常の溶接構造
図、(b)は本発明の構造を採用した鋼桁の上フランジ
の説明図、(c)は(b)の構造を採用した場合の溶接
構造図である。
8 (a) and 8 (b) are explanatory views of a welded portion between the steel girder and the corrugated steel sheet web in the embodiment shown in FIG. 6, wherein (a) is a normal welding structure diagram and (b) is a steel girder employing the structure of the present invention. FIG. 3C is an explanatory view of the upper flange, and FIG. 4C is a welding structure diagram when the structure of FIG.

【図9】従来の連続桁橋梁の問題点を説明する図で、
(a)は側面から見た図、(b)は(a)の中間支点部
を正面方向から見た図、(c)は連続桁橋梁に活荷重が
作用した場合の説明図、(d)は連続桁橋梁に活荷重が
作用した場合に、支間中間部に作用する応力の説明図、
(e)は連続桁橋梁に活荷重が作用した場合に、中間支
点部に作用する応力の説明図である。
FIG. 9 is a diagram illustrating a problem of a conventional continuous girder bridge;
(A) is a view from the side, (b) is a view from the front of the intermediate fulcrum part of (a), (c) is an explanatory view when a live load acts on the continuous girder bridge, (d) Is an illustration of the stress acting on the mid-span when a live load is applied to the continuous girder bridge,
(E) is an explanatory view of the stress acting on the intermediate fulcrum when a live load acts on the continuous girder bridge.

【図10】連続桁橋梁の中間支点部にプレストレスを導
入する従来方法の説明図で、(a)はプレストレスの導
入中の説明図、(b)はプレストレスの導入後の説明
図、(c)はプレストレスの導入後に中間支点部に作用
する応力の説明図、(d)は活荷重が作用した場合に、
中間支点部に作用する応力の説明図である。
FIG. 10 is an explanatory view of a conventional method of introducing a prestress to an intermediate fulcrum portion of a continuous girder bridge, wherein (a) is an explanatory view during the introduction of the prestress, (b) is an explanatory view after the introduction of the prestress, (C) is an explanatory view of the stress acting on the intermediate fulcrum after the introduction of the prestress, (d) when a live load is applied,
It is explanatory drawing of the stress which acts on an intermediate fulcrum part.

【図11】連続桁橋梁の中間支点部にプレストレスを導
入する従来の他の方法の説明図で、(a)は鋼桁のジャ
ッキアップ中の説明図、(b)はコンクリートを打設中
の説明図、(c)は鋼桁をジャッキダウンした時の説明
図、(d)はジャッキダウンによってコンクリート床版
に導入された圧縮応力の説明図である。
FIG. 11 is an explanatory view of another conventional method for introducing a prestress to an intermediate fulcrum portion of a continuous girder bridge. (A) is an explanatory view of jacking up a steel girder, and (b) is casting concrete. (C) is an explanatory diagram when the steel girder is jacked down, and (d) is an explanatory diagram of the compressive stress introduced into the concrete slab by jacking down.

【符号の説明】[Explanation of symbols]

1 鋼桁 1a 上フランジ 1b 切欠き 4 中間支承 11 波形鋼板ウェブ 11a 上フランジ 13 アンカー金具 14 PC鋼棒 15 ナット 16 添接板 17 コンクリート 19 PC鋼線 22 リング状ジベル DESCRIPTION OF SYMBOLS 1 Steel girder 1a Upper flange 1b Notch 4 Intermediate bearing 11 Corrugated steel sheet web 11a Upper flange 13 Anchor fitting 14 PC steel bar 15 Nut 16 Attached plate 17 Concrete 19 PC steel wire 22 Ring dowel

───────────────────────────────────────────────────── フロントページの続き (72)発明者 安田 和宏 大阪府大阪市住之江区南港北1丁目7番89 号 日立造船株式会社内 (72)発明者 塩見 健 大阪府大阪市住之江区南港北1丁目7番89 号 日立造船株式会社内 Fターム(参考) 2D059 AA05 AA14 BB35 CC04 GG55 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Kazuhiro Yasuda 1-89, Minamikohoku, Suminoe-ku, Osaka-shi, Osaka Inside Hitachi Zosen Corporation (72) Inventor Takeshi Takeshi 1-chome, Minamikohoku, Suminoe-ku, Osaka-shi, Osaka 7-89 F-term in Hitachi Zosen Corporation (reference) 2D059 AA05 AA14 BB35 CC04 GG55

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 連続桁の中間支点部における鋼桁部分
に、波形鋼板ウェブを配置し、この波形鋼板ウェブを配
置した中間支点部のコンクリート床版にプレストレスを
導入したことを特徴とする連続桁橋梁構造。
1. A continuous girder, wherein a corrugated steel sheet web is disposed on a steel girder part at an intermediate fulcrum part of a continuous girder, and a prestress is introduced into a concrete slab of the intermediate fulcrum part where the corrugated steel sheet web is disposed. Girder bridge structure.
【請求項2】 波形鋼板ウェブの中間支点位置に添接板
を取付け、この添接板と波形鋼板ウェブとで形成された
空洞に、コンクリートを充填したことを特徴とする請求
項1記載の連続桁橋梁構造。
2. The continuity according to claim 1, wherein an adhering plate is attached to a middle fulcrum position of the corrugated steel sheet web, and a cavity formed by the adhering plate and the corrugated steel sheet web is filled with concrete. Girder bridge structure.
【請求項3】 波形鋼板ウェブの上フランジに代えて、
多数のリング状ジベルを取付けたことを特徴とする請求
項1又は2記載の連続桁橋梁構造。
3. Instead of the upper flange of the corrugated steel sheet web,
The continuous girder bridge structure according to claim 1 or 2, wherein a number of ring-shaped dowels are attached.
【請求項4】 請求項3記載の連続桁橋梁構造における
鋼桁と波形鋼板ウェブとの取付けに際し、鋼桁の上フラ
ンジのみを波形鋼板ウェブ側に張出させ、この張出し部
に設けた嵌入用切欠きに波形鋼板ウェブを嵌入させて溶
接一体化したことを特徴とする連続桁橋梁構造。
4. A steel girder and a corrugated steel sheet web in the continuous girder bridge structure according to claim 3, wherein only the upper flange of the steel girder is extended toward the corrugated steel sheet web side, and a fitting provided on the extended part is provided. A continuous girder bridge structure in which a corrugated steel sheet web is inserted into a notch and integrated by welding.
【請求項5】 鋼桁の上フランジの張出し部に丸みをつ
けたことを特徴とする請求項4記載の連続桁橋梁構造。
5. The continuous girder bridge structure according to claim 4, wherein the overhang portion of the upper flange of the steel girder is rounded.
JP32925899A 1999-11-19 1999-11-19 Continuous girder bridge structure Expired - Fee Related JP3728391B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32925899A JP3728391B2 (en) 1999-11-19 1999-11-19 Continuous girder bridge structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32925899A JP3728391B2 (en) 1999-11-19 1999-11-19 Continuous girder bridge structure

Publications (2)

Publication Number Publication Date
JP2001146713A true JP2001146713A (en) 2001-05-29
JP3728391B2 JP3728391B2 (en) 2005-12-21

Family

ID=18219442

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32925899A Expired - Fee Related JP3728391B2 (en) 1999-11-19 1999-11-19 Continuous girder bridge structure

Country Status (1)

Country Link
JP (1) JP3728391B2 (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100800393B1 (en) 2007-09-14 2008-02-01 노윤근 Steel synthetic concrete u girder
JP2009144411A (en) * 2007-12-13 2009-07-02 Central Nippon Expressway Co Ltd Moving work vehicle assembling/disassembling omission method for cantilever erection method, and corrugated steel plate for use in the same
CN101831869A (en) * 2010-05-07 2010-09-15 同济大学 Connecting structure of combined beam and concrete bearing cross beam
CN102535346A (en) * 2012-02-15 2012-07-04 中南大学 Construction method of preloaded prestressed bridge
CN102561202A (en) * 2012-02-15 2012-07-11 中南大学 Construction method of preloaded and prestressed bridge
CN103161122A (en) * 2013-03-27 2013-06-19 广东省冶金建筑设计研究院 Longitudinal mixed continuous beam system with concrete beams and corrugated steel web concrete beams
JP2015151768A (en) * 2014-02-14 2015-08-24 株式会社高速道路総合技術研究所 Change-over method of concrete slab for highway road, and change-over pc slab by the method
JP2017014824A (en) * 2015-07-02 2017-01-19 ショーボンド建設株式会社 Existing bridge rebuilding method and rebuilding bridge
CN106948257A (en) * 2017-05-05 2017-07-14 绵阳市川交公路规划勘察设计有限公司 A kind of method for preventing pre-stressed bridge beam lower end crackle
CN108824162A (en) * 2018-07-30 2018-11-16 重庆大学 A kind of steel_concrete composite beam and its construction method using plain plate and corrugated sheet steel mixing web
JP2021119296A (en) * 2016-11-11 2021-08-12 オリエンタル白石株式会社 Construction method for connection structure of precast structural member and overtime hardening material
CN113338152A (en) * 2021-06-22 2021-09-03 广西北投公路建设投资集团有限公司 Steel-concrete composite web and construction method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105951575B (en) * 2016-06-20 2019-01-22 深圳市市政设计研究院有限公司 A kind of Wavelike steel webplate beam bridge promoting whole cracking resistance

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100800393B1 (en) 2007-09-14 2008-02-01 노윤근 Steel synthetic concrete u girder
JP2009144411A (en) * 2007-12-13 2009-07-02 Central Nippon Expressway Co Ltd Moving work vehicle assembling/disassembling omission method for cantilever erection method, and corrugated steel plate for use in the same
CN101831869A (en) * 2010-05-07 2010-09-15 同济大学 Connecting structure of combined beam and concrete bearing cross beam
CN102535346A (en) * 2012-02-15 2012-07-04 中南大学 Construction method of preloaded prestressed bridge
CN102561202A (en) * 2012-02-15 2012-07-11 中南大学 Construction method of preloaded and prestressed bridge
CN103161122B (en) * 2013-03-27 2015-05-27 广东省冶金建筑设计研究院 Longitudinal mixed continuous beam system with concrete beams and corrugated steel web concrete beams
CN103161122A (en) * 2013-03-27 2013-06-19 广东省冶金建筑设计研究院 Longitudinal mixed continuous beam system with concrete beams and corrugated steel web concrete beams
JP2015151768A (en) * 2014-02-14 2015-08-24 株式会社高速道路総合技術研究所 Change-over method of concrete slab for highway road, and change-over pc slab by the method
JP2017014824A (en) * 2015-07-02 2017-01-19 ショーボンド建設株式会社 Existing bridge rebuilding method and rebuilding bridge
JP2021119296A (en) * 2016-11-11 2021-08-12 オリエンタル白石株式会社 Construction method for connection structure of precast structural member and overtime hardening material
CN106948257A (en) * 2017-05-05 2017-07-14 绵阳市川交公路规划勘察设计有限公司 A kind of method for preventing pre-stressed bridge beam lower end crackle
CN108824162A (en) * 2018-07-30 2018-11-16 重庆大学 A kind of steel_concrete composite beam and its construction method using plain plate and corrugated sheet steel mixing web
CN113338152A (en) * 2021-06-22 2021-09-03 广西北投公路建设投资集团有限公司 Steel-concrete composite web and construction method thereof

Also Published As

Publication number Publication date
JP3728391B2 (en) 2005-12-21

Similar Documents

Publication Publication Date Title
JP2001146713A (en) Continuous beam bridge structure
KR100837608B1 (en) J.K Bracket Method
US5305575A (en) Composite, prestressed structural member and method of forming same
JP2000144905A (en) Mixed structural beam
WO2004059089A1 (en) Prestressed composite girder, continuous prestressed composite girder structure and methods of fabricating and connecting the same
JP2008111228A (en) Crack suppressing structure, crack suppressing method, and precast concrete member
US5553439A (en) Composite, prestressed structural members and methods of forming same
JP2750556B2 (en) Manufacturing method of prestressed concrete girder
JP2744955B2 (en) Reinforcement structure and reinforcement method of hinge part of gel bar bridge
JP3741975B2 (en) Joint structure of support pile and footing
JP2963879B2 (en) Bridge girder
JP2010159568A (en) Structure and method for reinforcing existing simple girder bridge
JP4293696B2 (en) Construction method of composite floor slab bridge
JP2002275833A (en) Continuing method of simple beam of existing bridge and continuous beam structure
JP2601304Y2 (en) Beam-column joint structure
JP2009293198A (en) Column base structure and its construction method
JP2006070614A (en) Reinforcing structure of steel girder bridge
JP3009582B2 (en) Construction method of continuous composite girder bridge between concrete slab and steel girder
JP2001123414A (en) Continuous girder bridge structure
JP2006132174A (en) Connector and connecting structure using the same
JP2003227109A (en) Mounting method of horizontal force buffer of structure and mounting structure
KR102619855B1 (en) Construction method for continuous bridge using single supporter
JP2002294628A (en) Continuous girder for bridge
JP3856745B2 (en) Bending reinforcement method for joints between existing columns and beams or slabs
JP4695790B2 (en) Beam-column joint structure

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050727

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050906

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051003

LAPS Cancellation because of no payment of annual fees