JP2001112171A - Distribution system facility plan supporting device and storage medium storing program for executing the same - Google Patents

Distribution system facility plan supporting device and storage medium storing program for executing the same

Info

Publication number
JP2001112171A
JP2001112171A JP28565899A JP28565899A JP2001112171A JP 2001112171 A JP2001112171 A JP 2001112171A JP 28565899 A JP28565899 A JP 28565899A JP 28565899 A JP28565899 A JP 28565899A JP 2001112171 A JP2001112171 A JP 2001112171A
Authority
JP
Japan
Prior art keywords
countermeasure
distribution system
plan
construction
power demand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP28565899A
Other languages
Japanese (ja)
Inventor
Hiroyuki Mori
弘幸 森
Akinori Iwai
昭則 岩井
Hisaaki Hatano
寿明 羽田野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP28565899A priority Critical patent/JP2001112171A/en
Publication of JP2001112171A publication Critical patent/JP2001112171A/en
Pending legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To automatically calculate power demand which is foreseen in the future, investigate construction cost with respect to it and evaluate a measure construction plan. SOLUTION: A load data preserving means 11 for inputting the present power demand of a distribution system via a remote monitor controller and preserving it as load data, a load assumption means 13 for predicting future power demand, based on load data of past and present power demand preserved in the load data preservation means, a supply force lack cause extraction means 16 for extracting a facility where power demand predicted by the load assumption means exceeds supply possible capacity and the cause, a measure deriving means 18 for dissolving the cause with respect to the facility, where the demand exceeds supply possible capacity and deriving a measure construction plan which does not generate new causes, and a measure construction cost calculation means 192 for calculating measure construction cost with respect to the measure construction plan derived by the measure-deriving means are installed.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、電気事業における
配電系統の設備投資計画に際して使用する配電系統設備
計画支援装置とこれを実行するためのプログラムを記憶
した記憶媒体に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a distribution system facility planning support device used for planning a capital investment in a distribution system in an electric power business and a storage medium storing a program for executing the system.

【0002】[0002]

【従来の技術】配電系統において、毎年変動する電力需
要に対して、電圧,電流が適正か、電力損失が最小か、
予算に見合っているか等を考慮の上、適正な供給形態を
計画する際、将来の負荷を予測してそれに見合った対策
工事の決定及び決定した対策工事の実施に伴う経費の算
出(このような作業を以下設備計画の策定と称する)は
以下のように行なっていた。
2. Description of the Related Art In a distribution system, whether the voltage and current are appropriate, the power loss is minimum,
When planning an appropriate supply form in consideration of whether it is appropriate for the budget, etc., when predicting the future load, deciding the countermeasure work corresponding to it, and calculating the costs associated with the implementation of the decided countermeasure work (such as The work is hereinafter referred to as the establishment of a facility plan) was performed as follows.

【0003】 オペレータは将来予想される電力需要
を算出し、配電系統設備計画支援装置に入力し、過負
荷,電流超過,電圧降下の計算を指示し、配電系統での
過負荷,電流超過,電圧降下の計算結果を出力する。
An operator calculates a power demand expected in the future, inputs the calculated power demand to a distribution system facility planning support device, instructs calculation of overload, excess current, and voltage drop, and overloads, excess current, and voltage in the distribution system. Outputs the calculation result of descent.

【0004】 の出力結果をもとに、オペレータは
将来、対策工事が必要であるかどうか(過負荷,電流超
過,電圧降下が適正範囲内であるかどうか)を判定し、
過負荷,電流超過,電圧降下を解消するための対策工事
案を必要であれば複数、配電系統設備計画支援装置に入
力していた。
[0004] Based on the output result, the operator determines whether or not countermeasures are required in the future (whether overload, excess current, and voltage drop are within appropriate ranges),
If necessary, a plurality of countermeasure construction plans for eliminating overload, excess current, and voltage drop were input to the distribution system facility planning support device.

【0005】 で入力された対策工事案に従って配
電系統設備計画支援装置が工事内容を反映した将来系統
を作成する。オペレータは再度、過負荷,電流超過,電
圧降下の計算を指示し、過負荷,電流超過,電圧降下が
解消されているかどうかを確認していた。
[0005] According to the countermeasure construction plan input in the above, the distribution system facility planning support device creates a future system reflecting the construction contents. The operator again instructed the calculation of overload, excess current, and voltage drop, and confirmed whether the overload, excess current, and voltage drop were eliminated.

【0006】上記工事案において未解消であれば、オペ
レータは別の対策工事案を入力し、,を繰り返し、
解消しているならば、将来発生する恐れがある事故想定
(変電所全停事故,バンク事故,配電線事故等)を配電
系統設備計画支援装置に入力することで、事故発生後の
供給支障有無を出力する。オペレータは供給支障有りの
時は、更に別の対策工事案を入力し、,の処理を繰
り返していた。
If the above-mentioned construction plan has not been resolved, the operator inputs another countermeasure construction plan, and repeats the above.
If it has been resolved, input the assumed accidents that may occur in the future (substation outages, bank accidents, distribution line accidents, etc.) to the distribution system facility planning support device to check for supply interruptions after the occurrence of the accident. Is output. When there was a supply hindrance, the operator entered another countermeasure construction plan and repeated the processing of (1) and (2).

【0007】 で供給支障が無い時、この工事内容
での工事費計算実行をオペレータが指示すると、配電系
統設備計画支援装置が工事費を計算し出力する。オペレ
ータはこの工事費をもとに、最適な対策工事案を決定し
ていた。
[0007] When there is no trouble in the supply, when the operator instructs execution of the construction cost calculation in this construction content, the distribution system facility planning support device calculates and outputs the construction cost. The operator has determined an optimal countermeasure construction plan based on the construction cost.

【0008】[0008]

【発明が解決しようとする課題】上記したように、従来
は設備計画の策定において、オペレータによる将来予想
される電力需要の手動入力、オペレータによる将来発生
する恐れのある事故ケースの手動作成、オペレータによ
る対策工事案の手動作成、工事費計算での各種計算定数
の変動による計算精度の向上、工事及び設備の同時手配
による更なるコストミニマム化、複数の対策工事案から
の最適評価に関して、次のような解決しなければならな
い問題があった。
As described above, conventionally, in formulating a facility plan, the operator manually inputs power demand expected in the future, manually creates an accident case that may occur in the future by the operator, Regarding manual creation of countermeasure construction plans, improvement of calculation accuracy by fluctuation of various calculation constants in construction cost calculation, further cost minimization by simultaneous arrangement of construction and equipment, optimal evaluation from multiple countermeasure construction plans There were problems that had to be solved.

【0009】まず、オペレータによる将来予想される電
力需要の算出と入力作業に関する労力と所要時間の問題
がある。オペレータは予め変電所単位,バンク単位,配
電線単位に過去の負荷を集計したものから将来変化する
であろう電力需要を予測するが集計作業及び予測作業に
は多くの労力を必要としていた。又、オペレータによる
将来の電力需要の予測にはバラツキや精度の問題もあっ
た。
First, there is a problem of labor and time required for calculation and input work of the power demand expected by the operator in the future. The operator predicts the power demand that will change in the future from the total of past loads for each substation, bank, and distribution line, but requires a great deal of labor for the totaling and predicting operations. In addition, the prediction of the future power demand by the operator also has problems of variation and accuracy.

【0010】又、オペレータによる将来発生するであろ
う事故ケースの作成作業に関する労力と所要時間の問題
がある。近年は配電系統を構成する設備あるいは機器の
信頼性も向上し、実際の事故を経験していないオペレー
タにとっては将来発生するであろう事故ケースの作成に
は多くの労力を必要としていた。
Further, there is a problem of labor and time required for an operator to create an accident case that may occur in the future. In recent years, the reliability of facilities or equipment constituting a distribution system has been improved, and operators who have not experienced an actual accident have required much effort to create an accident case that may occur in the future.

【0011】次に、オペレータによる対策工事案の作成
作業に関する労力と所要時間の問題がある。対策工事案
の作成においては、過去に実施した対策工事案の作成の
経験の有無がその所要時間に大きく影響してくる。
[0011] Next, there is a problem of labor and time required for the operator to create a countermeasure construction plan. In preparing a countermeasure construction plan, the experience of preparing a countermeasure construction plan in the past greatly affects the required time.

【0012】更に、工事費計算で用いる各種計算定数は
予め、配電系統設備計画支援装置内に保有しているがこ
れらの計算定数は変動しており、それらの変動に追従で
きていない問題がある。このために工事費計算での計算
精度に影響が出ている。従って、工事費計算を精度良
く、又、工事費ができる限り少なくなるように工事計画
を作成する必要がある。
Furthermore, various calculation constants used in the construction cost calculation are previously stored in the distribution system facility planning support apparatus, but these calculation constants fluctuate, and there is a problem that these fluctuations cannot be followed. . This has an effect on the calculation accuracy in the construction cost calculation. Therefore, it is necessary to prepare a construction plan with high accuracy in the construction cost calculation and to minimize the construction cost.

【0013】又、複数作成された対策工事案からオペレ
ータによる最適な対策工事案としての評価作業に関する
労力と所要時間の問題がある。しかも、これらオペレー
タによる評価条件を加味した最終評価には多くの労力を
必要としていた。
[0013] Further, there is a problem of labor and time required for an evaluation work as an optimal countermeasure construction plan by an operator from a plurality of prepared countermeasure construction plans. In addition, a lot of labor is required for final evaluation taking into account the evaluation conditions by these operators.

【0014】本発明は上記問題を解決するためになされ
たものであり、従来の配電系統設備計画支援装置におけ
る将来予想される電力需要の算出及び入力、将来発生す
るであろう事故ケースの作成、対策工事案の作成、工事
費計算で使用する各種計算定数の変更、対策工事費のコ
ストミニマム化、対策工事案の評価を短時間でかつ、労
力をかけずに実現することができる配電系統設備計画支
援装置とこれを実行するためのプログラムを記憶した記
憶媒体を提供することを目的としている。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-described problems, and calculates and inputs a power demand expected in the future in a conventional power distribution system equipment planning support apparatus, creates an accident case that may occur in the future, Distribution system equipment that can create countermeasure construction plans, change various calculation constants used in construction cost calculation, minimize cost of countermeasure construction costs, and evaluate countermeasure construction plans in a short time and without labor. It is an object of the present invention to provide a plan supporting apparatus and a storage medium storing a program for executing the plan supporting apparatus.

【0015】[0015]

【課題を解決するための手段】本発明の[請求項1]に
係る配電系統設備計画支援装置は、刻々変化する配電系
統の現在の電力需要(負荷)を遠方監視制御装置を介し
て入力し、負荷データとして保存する負荷データ保存手
段と、前記負荷データ保存手段で保存した過去及び現在
の電力需要の負荷データをもとに将来の電力需要を予測
する負荷想定手段と、前記負荷想定手段により予測され
た電力需要が、供給可能容量を超過する設備とその要因
とを抽出する供給力不足要因抽出手段と、供給可能容量
を超過した設備に対して、その要因を解消し、かつ新た
な要因を発生させることのない対策工事案を導出する対
策導出手段と、前記対策導出手段により導出された対策
工事案に対する対策工事費用を算出する対策工事費用算
出手段とを備えたものである。
According to a first aspect of the present invention, there is provided a power distribution system facility planning support device which inputs a current power demand (load) of a power distribution system that changes every moment via a remote monitoring control device. Load data storage means for saving as load data, load estimation means for predicting future power demand based on load data of past and current power demand stored in the load data storage means, and the load estimation means The power supply shortage factor extraction means for extracting the equipment whose predicted power demand exceeds the available capacity and its factor, and for the equipment exceeding the available capacity, eliminating the factor and adding a new factor A countermeasure deriving means for deriving a countermeasure construction plan that does not cause a problem, and a countermeasure construction cost calculating means for calculating a countermeasure construction cost for the countermeasure construction plan derived by the countermeasure derivation means. Than it is.

【0016】本発明の[請求項2]に係る配電系統設備
計画支援装置は、[請求項1]において、実際の配電系
統にて発生した事故ケースをその都度、保存しておく事
故ケース保存手段と、対策工事案の将来での配電系統に
おける想定事故を、前記事故ケース保存手段にて保存し
た過去に発生した事故ケースを用いて供給支障状況を計
算する事故想定手段とを備えたものである。
According to a second aspect of the present invention, there is provided a distribution system facility planning support apparatus according to the first aspect, wherein an accident case occurring in an actual distribution system is stored every time. And an accident estimating means for calculating a supply obstruction situation using an accident case that occurred in the past in the distribution system in the future of the countermeasure construction plan and stored in the accident case storing means. .

【0017】本発明の[請求項3]に係る配電系統設備
計画支援装置は、[請求項1]において、対策導出手段
にて対策工事案を導出される都度、その対策工事案を保
存する対策案保存手段と、供給力不足要因抽出手段によ
り抽出された供給可能容量を超過した設備に対して、前
記対策案保存手段にて保存したこれまでの対策工事案の
中から同一要因あるいは同一設備に係わる対策工事案を
表示する対策案表示手段とを備えたものである。
In the power distribution system facility planning support device according to claim 3 of the present invention, in claim 1, each time a measure construction plan is derived by the measure deriving means, the measure construction plan is stored. For the equipment that exceeds the suppliable capacity extracted by the plan storage means and the supply capacity shortage factor extraction means, the same factor or the same equipment is selected from the previous countermeasure construction plans stored by the measure plan storage means. And a measure display means for displaying a related measure construction plan.

【0018】本発明の[請求項4]に係る配電系統設備
計画支援装置は、[請求項1]において、対策工事費用
算出手段にてその対策工事費用の算出時に用いて計算定
数を変更する計算定数修正手段を有し、前記対策工事費
用算出手段は前記計算定数修正手段により計算定数が変
更される度に、当該変更された計算定数により対策工事
費用を算出できるようにしたものである。
According to a fourth aspect of the present invention, there is provided the distribution system facility planning support device according to the first aspect, wherein the countermeasure work cost calculation means uses a calculation constant to change a calculation constant when calculating the countermeasure work cost. It has a constant correction means, and the countermeasure construction cost calculation means can calculate a countermeasure construction cost by the changed calculation constant every time the calculation constant is changed by the calculation constant correction means.

【0019】本発明の[請求項5]に係る配電系統設備
計画支援装置は、[請求項1]において、対策案保存手
段を設け、対策導出手段が導出した対策工事案の対策工
事費用を対策工事費用算出手段で算出し、この対策工事
費用を更に低減させるために、対策導出手段が導出した
対策工事案と、前記、対策案保存手段で保存した他の対
策工事案から、同時期の工事あるいは同じ設備であるか
を判断し、工事及び設備の同時手配による無駄を除いた
対策工事費用を算出する対策工事同時手配手段を付加し
たものである。
In the power distribution system facility planning support device according to claim 5 of the present invention, in claim 1, a countermeasure storage means is provided, and countermeasure construction cost of the countermeasure construction plan derived by the countermeasure derivation means is taken as a countermeasure. In order to further reduce this countermeasure construction cost, the countermeasure derivation unit calculates the countermeasure construction plan and the other countermeasure construction plans saved by the countermeasure plan storage unit to calculate the countermeasure construction cost. Alternatively, a measure construction simultaneous arrangement means for judging whether or not the facilities are the same and calculating a measure construction cost excluding waste caused by construction and facility simultaneous arrangement is added.

【0020】本発明の[請求項6]に係る配電系統設備
計画支援装置は、[請求項1]ないし[請求項5]記載
の各々の配電系統設備計画支援装置において、供給力不
足要因抽出手段にて保存した供給力不足要因と、対策工
事案案と、対策工事同時手配手段にて保存した対策工事
費用とをもとに、最適な設備計画の策定を評価するため
に、その評価条件(供給力不足、対策工事費の許容範囲
など)を設定する評価条件設定手段と、その設定された
評価条件をもとに複数の対策工事案から評価の高い順番
に評価結果を出力する評価判定手段を付加したものであ
る。
According to a sixth aspect of the present invention, there is provided a distribution system facility planning support apparatus according to any one of the first to fifth aspects, wherein the supply system shortage factor extracting means is provided. In order to evaluate the optimal equipment plan formulation based on the supply power shortage factor saved in the above, the countermeasure construction draft, and the countermeasure construction cost saved by the countermeasure construction simultaneous arrangement means, the evaluation conditions ( Evaluation condition setting means for setting supply power shortage, allowable range of countermeasure construction costs, etc., and evaluation judging means for outputting evaluation results from a plurality of countermeasure construction plans in descending order of evaluation based on the set evaluation conditions. Is added.

【0021】本発明の[請求項7]に係る記憶媒体は、
電力需要(負荷)の増加によって発生する配電系統を構
成する各設備の導入更新計画を支援する配電系統設備計
画支援装置において、刻々変化する配電系統の電力需要
を遠方監視制御装置を介して負荷データとして取り込む
負荷データ保存手段を実行する機能と、前記負荷データ
保存手段にて保存した過去及び現在の電力需要の負荷デ
ータをもとに将来の電力需要を予測する負荷想定手段を
実行する機能と、前記負荷想定手段により予測した将来
の電力需要と、配電系統を構成する各設備の供給可能容
量を比較して供給可能容量を超過する設備とその要因と
を供給力不足要因として抽出する供給力不足要因抽出手
段を実行する機能と、供給可能容量を超過した設備に対
して、その要因を解消する対策工事案を導出する対策導
出手段を実行する機能と、前記対策導出手段が導出した
対策工事案に対する対策工事費用を算出する対策工事費
用算出手段を実行する機能とを実行させるためのプログ
ラムを記憶した記憶媒体である。
The storage medium according to claim 7 of the present invention is:
In a distribution system equipment planning support device that supports an introduction and renewal plan of each device constituting a distribution system generated by an increase in power demand (load), load data is transmitted via a remote monitoring control device to a constantly changing power demand of the distribution system. A function of executing load data storage means to be taken in as a function of executing load estimation means for predicting future power demand based on load data of past and current power demand stored in the load data storage means, Insufficient power to extract future power demand predicted by the load estimating means and the available capacity of each facility constituting the distribution system and to extract facilities that exceed the available capacity and their factors as factors of insufficient power Executes a function for executing factor extraction means and executes a measure deriving means for deriving a countermeasure construction plan for eliminating the factor for equipment having exceeded the available capacity. Noh, a storage medium storing a program for executing the function of executing the countermeasure work costs calculation means for calculating a countermeasure work costs for remediation work proposed the measures deriving means is derived.

【0022】[0022]

【発明の実施の形態】([請求項1]に対応)図1は本
発明の[請求項1]に係る配電系統設備計画支援装置の
実施の形態を示す構成図である。図1において、1は配
電系統設備計画支援装置、2は遠方監視制御装置であ
り、配電系統設備計画支援装置は、負荷データ保存手段
11,負荷データ12,負荷想定手段13,想定最大負
荷データ14,設備DB15,供給力不足要因抽出手段
16,供給力不足要因17,対策導出手段18,対策工
事案19,計算定数データ191、対策工事費用算出手
段192,対策工事費用193,CRT入出力装置19
4からなる。
DESCRIPTION OF THE PREFERRED EMBODIMENTS (corresponding to [Claim 1]) FIG. 1 is a configuration diagram showing an embodiment of a distribution system facility planning support apparatus according to [Claim 1] of the present invention. In FIG. 1, reference numeral 1 denotes a distribution system facility planning support device, and 2 denotes a remote monitoring control device. The distribution system facility planning support device includes a load data storage unit 11, load data 12, a load estimation unit 13, and an assumed maximum load data 14. , Equipment DB 15, supply power shortage factor extraction means 16, supply power shortage factor 17, measure derivation means 18, measure construction plan 19, calculation constant data 191, measure construction cost calculation means 192, measure construction cost 193, CRT input / output device 19
Consists of four.

【0023】図1において、負荷データ12は負荷デー
タ保存手段11にて遠方監視制御装置2を介して一定周
期で取り込んだ配電系統設備毎の電流、電圧の計測値で
あり、過去及び現在の電力需要である。オペレータは設
備計画の策定を行なおうとする将来(西暦等)をCRT
入出力装置194より入力することで負荷想定手段13
は、前記負荷データ12に保存されている過去及び現在
の電力需要をもとに将来の電力需要の想定最大負荷を自
動的に算出後、想定最大負荷データ14へ保存し、供給
力不足要因抽出手段16を起動する。
In FIG. 1, load data 12 is a measured value of a current and a voltage of each distribution system equipment taken in a fixed cycle via the remote monitoring control device 2 by the load data storage means 11, and the past and present electric power are measured. Demand. The operator will report on the future (E.g.
By inputting from the input / output device 194, the load estimating means 13
Automatically calculates an assumed maximum load of future power demand based on the past and present power demand stored in the load data 12 and then saves it in the assumed maximum load data 14 to extract supply power shortage factor Activate means 16.

【0024】負荷想定手段13のフローチャートを図2
に示す。まず最初に負荷データ12に保存されている過
去及び現在の電力需要を取り込む(S21)。過去及び
現在の電力需要からこれまでの電力需要の伸び率を求め
る(S22)。現在の電力需要にこの伸び率を乗じてC
RT入出力装置194から入力された将来(西暦等)の
電力需要を求める(S23)。求めた将来の電力需要を
想定最大負荷として想定最大負荷データ14に保存する
(S24)。
FIG. 2 is a flow chart of the load estimating means 13.
Shown in First, the past and present power demands stored in the load data 12 are fetched (S21). From the past and present power demands, the growth rate of the power demand so far is obtained (S22). Multiply the current power demand by this growth rate to get C
The power demand in the future (such as the Christian era) input from the RT input / output device 194 is determined (S23). The obtained future power demand is stored as the assumed maximum load in the assumed maximum load data 14 (S24).

【0025】想定最大負荷データ14は負荷想定手段1
3にて想定した将来の最大負荷を設備毎に保存するファ
イルである。設備DB15は配電系統の各設備のつなが
り、供給可能容量を保存しておくファイルである。供給
力不足要因抽出手段16は想定最大負荷データ14と、
設備DB15を参照し、想定した最大負荷が供給可能容
量を超えている設備と、その要因(バンク過負荷,配電
線過負荷,区間電流超過,電圧降下)と供給可能超過量
を抽出し、それらのデータを供給力不足要因17に保存
し、対策導出手段18を起動する。
The assumed maximum load data 14 is the load estimating means 1
3 is a file for storing the maximum future load assumed for each facility. The facility DB 15 is a file that stores the connection of each facility in the distribution system and the suppliable capacity. The supply power shortage factor extraction means 16 calculates the estimated maximum load data 14,
With reference to the equipment DB 15, the equipment in which the assumed maximum load exceeds the suppliable capacity, the factors (bank overload, distribution line overload, section current excess, voltage drop) and the suppliable excess amount are extracted. Is stored in the supply power shortage factor 17 and the countermeasure deriving means 18 is activated.

【0026】対策導出手段18は供給力不足要因17に
保存された設備と要因について、設備と要因に応じた対
策工事案を以下のように導出して対策工事案19に保存
し、対策工事費用算出手段192を起動する。供給力不
足要因抽出手段16により抽出された供給力不足要因1
7は、その要因によって対策検討項目が異なる。要因別
の対策検討項目を図3に示す。図3の要因別対策検討項
目一覧を基に対策導出手段18により、各要因の対策工
事案を導出する。
The countermeasure deriving means 18 derives a countermeasure construction plan corresponding to the equipment and the factor stored in the supply capacity shortage factor 17 as follows and saves the countermeasure construction plan 19 as a countermeasure construction cost. The calculating means 192 is started. Supply power shortage factor 1 extracted by supply power shortage factor extraction means 16
7 has different measures to be considered depending on the factors. Fig. 3 shows the items to consider for each factor. The countermeasure deriving means 18 derives a countermeasure construction plan for each factor based on the list of countermeasure study items by factor in FIG.

【0027】対策導出手段18のフローチャートを図4
に示す。まず最初に負荷切替え対策を行なう(S4
1)。負荷切替え対策により要因が解消した場合は、負
荷切替えにより変化した配電用区分開閉器の入/切状態
を対策案とする(S43)。負荷切替え対策で要因が解
消しない場合、要因が区間電流超過、電圧降下超過であ
れば区間増強対策を行なう(S45)。
FIG. 4 is a flow chart of the measure deriving means 18.
Shown in First, load switching measures are taken (S4
1). If the cause is eliminated by the load switching measure, the on / off state of the distribution switchgear changed by the load switching is taken as a measure (S43). If the cause is not eliminated by the load switching measure, if the cause is excess section current or excessive voltage drop, section enhancement measures are taken (S45).

【0028】区間増強対策により要因が解消した場合
は、増強した区間及び配電用区分開閉器を対策案とする
(S47)。区間増強対策で要因が解消しない場合は、
配電線(バンク)の増強又は新設を対策案とし(S4
8)、増強又は新設した配電線(バンク)の所属系統決
定により入/切状態が変化した配電用区分開閉器を対策
案とする(S49)。
If the cause is eliminated by the section reinforcement measure, the section and power distribution section switch that have been strengthened are taken as a measure (S47). If the factor is not resolved by section reinforcement measures,
As a countermeasure plan, increase or newly install distribution lines (banks) (S4
8) The distribution switchgear whose on / off state has changed due to the determination of the system to which the distribution line (bank) that has been reinforced or newly installed is set as a countermeasure (S49).

【0029】対策導出手段18の各対策検討項目の詳細
を図5で説明する。負荷切替え対策は、連系他回線選出
処理181により要因発生設備の配電系統回線に連係す
る他配電系統回線を選出し、選出された他配電系統回線
に対して隣接区間切替え処理182により要因発生配電
系統回線の区間を順次切替えて、要因発生配電系統回線
の負荷を供給可能超過量分減らして要因を解消させる。
Details of each measure examination item of the measure deriving means 18 will be described with reference to FIG. The load switching measure is to select another distribution system line linked to the distribution system line of the factor generating equipment by the interconnection other line selection processing 181 and to perform factor generation distribution by the adjacent section switching processing 182 for the selected other distribution system line. The section of the system line is sequentially switched, and the load on the factor generating distribution system line is reduced by the suppliable excess amount to eliminate the cause.

【0030】この際他配電系統回線に新たな要因が発生
する負荷切替えは実施しない。負荷切り替えの例を図6
を用いて説明すると、配電線引出し用しゃ断器FCB1
が過負荷となっている場合、まずFCB1からの配電系
統回線で常開開閉器にて連係する他配電系統回線(他回
線A,B,C)を選出する。
At this time, load switching which causes a new factor in other distribution system lines is not performed. Figure 6 shows an example of load switching
If it explains using, the breaker FCB1
Is overloaded, first, the other distribution system lines (other lines A, B, and C) that are linked by the normally open switch in the distribution system line from FCB1 are selected.

【0031】次に選出された他回線に隣接する区間を順
次他回線に切替えるために他回線Aに区間Dを、他回線
Bに区間Hを、他回線Cに区間I更に他回線Bに区間G
を切替えFCB1の配電線過負荷を解消させる(他回線
Aに区間Cまで切替えると他回線Aの供給可能容量を超
えてしまうため切替えを行なわない)。
Next, in order to sequentially switch the section adjacent to the selected other line to another line, the other line A has the section D, the other line B has the section H, the other line C has the section I and the other line B has the section. G
To eliminate the distribution line overload of the FCB1 (if the line is switched to the other line A to the section C, the supply capacity of the other line A will be exceeded, so that the switching is not performed).

【0032】区間増強対策は、要因発生設備の径間に対
して増強区間サイズ決定処理183により供給可能超過
量に見合った電線種別と電線サイズを決定するととも
に、増強開閉器サイズ決定処理184により配電用区分
開閉器も供給可能超過量に見合った開閉器容量を決定し
て要因を解消させる。
In the section reinforcement measures, the wire type and the wire size corresponding to the excess amount that can be supplied are determined by the reinforcement section size determination processing 183 for the span of the factor generating equipment, and the power distribution is performed by the reinforcement switch size determination processing 184. Also, the switchgear for each of the units determines the capacity of the switch corresponding to the excess amount that can be supplied and eliminates the factor.

【0033】配電線(バンク)増強/新設対策は、要因
発生設備の配電線又はバンクに対し増強配電線(バン
ク)サイズ決定処理185により供給可能超過量に見合
った配電線容量又はバンク容量を決定し要因を解消させ
る。要因が解消しない場合は、新設配電線所属系統決定
処理186により要因発生設備の配電線に対し供給可能
超過量に見合った他配電系統回線と連系がある連続する
区間群を新設配電線所属系統とする。
The distribution line (bank) reinforcement / new construction measures are to determine the distribution line capacity or the bank capacity corresponding to the excess supplyable amount by the distribution line (bank) size determination processing 185 for the distribution line or the bank of the factor generating equipment. And eliminate the cause. If the cause is not resolved, the new distribution line belonging system determination processing 186 determines a continuous section group that is interconnected with another distribution system line corresponding to the excess supply available for the distribution line of the factor generating equipment, by the new distribution line belonging system. And

【0034】そして新設配電線サイズ決定処理187に
より新設配電線の容量を新設配電線所属系統に見合った
容量とすることで、要因発生設備の配電線が所属する変
電所内の既設バンクに対し配電系統回線を新設する。配
電系統回線を新設できる既設バンクがない場合は新設/
増強バンクサイズ決定処理188により、既設バンクの
容量を増加させるか、増加できない場合は既設バンクの
所属する変電所にバンクを新設し、新設配電系統回線を
所属させる。
Then, the capacity of the newly installed distribution line is set to a capacity corresponding to the system to which the newly installed distribution line belongs by the new installation distribution line size determination processing 187, so that the distribution system for the existing bank in the substation to which the distribution line of the factor generating equipment belongs is assigned. Establish a new line. If there is no existing bank where a new distribution system line can be established,
By the augmented bank size determination processing 188, the capacity of the existing bank is increased, or if the capacity cannot be increased, a new bank is installed in the substation to which the existing bank belongs, and the new distribution system line is made to belong.

【0035】バンクの新設もできない場合は新設変電所
決定処理189により、変電所を新設し、その後に新設
したバンクを新設変電所の所属バンクとして決定するこ
とで新設バンクに接続する新設配電線と新設配電線の所
属系統も新設変電所の所属設備となる。これらの対策工
事案により要因を解消させる。
If a new bank cannot be established, a new substation is newly established by a new substation determination process 189, and then the newly established bank is determined as a bank to which the new substation belongs. The system to which the new distribution line belongs will also be the equipment to which the new substation belongs. The factors will be eliminated by these measures.

【0036】次に、対策工事費用算出手段192が対策
工事案19と予め設定された計算定数データ191の工
事単価,金利,原価償却費,固定資産税,事業税,ロス
単価等の計算定数をもとに対策工事の費用を算出し、対
策工事費用193へ保存する。対策工事の費用の算出に
ついては特開平4−54828号と同様であり、説明は
割愛する。
Next, the countermeasure construction cost calculating means 192 calculates the calculation constants such as the construction unit price, the interest rate, the cost depreciation cost, the fixed asset tax, the business tax, the loss unit price of the countermeasure construction plan 19 and the preset calculation constant data 191. The cost of the countermeasure construction is calculated based on the calculated cost and stored in the countermeasure construction cost 193. The calculation of the cost of the countermeasure work is the same as in JP-A-4-54828, and the description is omitted.

【0037】以上のように、設備計画策定を全て自動で
行なう[請求項1]の全体処理フローを図7に示す。S
71で将来負荷を想定し、S72で供給力不足要因を抽
出する。S73で対策工事案を導出し、S74で対策工
事費用を算出するものである。
As described above, FIG. 7 shows an overall processing flow of claim 1 in which the facility planning is completely performed automatically. S
At 71, a future load is assumed, and at S72, a supply shortage factor is extracted. In S73, a countermeasure construction plan is derived, and in S74, a countermeasure construction cost is calculated.

【0038】本実施の形態によれば、将来予想される電
力需要をオペレータの手を煩わすことなく自動的に想定
できる。又、将来の電力需要の想定から対策工事費用算
出までの一連の設備計画策定の作業を、全くオペレータ
の手を煩わすことなく実行することが可能であると共
に、設備計画策定の精度向上と、省力化に大きく寄与す
ることができる。
According to the present embodiment, the power demand expected in the future can be automatically assumed without bothering the operator. In addition, it is possible to execute a series of equipment planning work from the estimation of future power demand to the calculation of countermeasure construction costs without any operator's hand, and to improve the accuracy of equipment planning and to save labor. It can greatly contribute to the development.

【0039】([請求項2]に対応)図8は本発明の
[請求項2]に係る配電系統設備計画支援装置の実施の
形態を示す構成図である。図8において、図1と同一機
能部分については同一符号を付して説明を省略する。本
実施の形態では過去に実際に発生した事故を、将来発生
し得る事故の1つとして加えたものであり、そのために
付加した構成は事故ケース保存手段21と事故ケース2
2と事故想定手段23とである。
(Corresponding to [Claim 2]) FIG. 8 is a configuration diagram showing an embodiment of a distribution system facility planning support apparatus according to [Claim 2] of the present invention. 8, the same functional portions as those in FIG. 1 are denoted by the same reference numerals, and description thereof will be omitted. In the present embodiment, an accident that has actually occurred in the past is added as one of the accidents that may occur in the future.
2 and the accident assumption means 23.

【0040】図8において、事故ケース保存手段21は
遠方監視制御装置2を介して配電系統を構成する機器の
入/切等(地絡,短絡等の事故要因含め)の状態を取り
組み、配電系統における変電所事故,バンク事故,配電
線事故等を検出し、事故情報を時系列に事故ケース22
へ保存する。遠方監視制御装置2から配電系統を構成す
る機器の入/切等(事故要因含め)を取り込み、及び配
電系統における事故の検出については従来技術である配
電系統を監視制御する配電系統監視システムそのもので
あり、説明は割愛する。
In FIG. 8, the accident case storage means 21 works on the state of on / off (including an accident factor such as ground fault, short circuit, etc.) of the equipment constituting the power distribution system via the remote monitoring control device 2, and Substation accidents, bank accidents, distribution line accidents, etc., and categorizes accident information in chronological order.
Save to The on / off of the equipment constituting the distribution system (including the cause of the accident) is taken in from the remote monitoring control device 2 and the detection of an accident in the distribution system is performed by the distribution system monitoring system itself that monitors and controls the distribution system, which is a conventional technique. Yes, explanation is omitted.

【0041】図1では想定した将来の想定最大負荷時の
電力需要による配電系統を構成する各設備の新設又は増
強の対策工事計画により将来系統状態を作成したが、事
故想定手段23はこの将来の系統状態において事故の発
生を想定する場合、事故ケース保存手段21にて保存し
た事故情報を基に過去発生した任意の事故ケース(変電
所事故,バンク事故,配電線事故)を発生させることに
より、更に配電系統を構成する各設備の新設又は増強の
対策工事案を導出するようにしたものである。
In FIG. 1, a future system state is created by a countermeasure work plan for new installation or reinforcement of each facility constituting the distribution system based on the power demand at the assumed maximum load in the future. When an accident is assumed to occur in the system state, any accident case (substation accident, bank accident, distribution line accident) that has occurred in the past is generated based on the accident information stored in the accident case storage unit 21. In addition, measures for countermeasures for new installation or reinforcement of each facility constituting the distribution system are derived.

【0042】事故想定手段23のフローチャートを図9
に示す。まず最初に対策導出手段にて導出した対策工事
案を取り込む(S91)。取り込んだ対策工事案から模
擬事故の内容選定を行なう(S92)。選定した結果か
ら過去の事故と比較し、最も近いケースを事故ケースよ
り取り込む(S93)。
FIG. 9 is a flowchart of the accident estimating means 23.
Shown in First, the measure construction plan derived by the measure deriving means is fetched (S91). The content of the simulated accident is selected from the taken countermeasure construction plan (S92). The selected case is compared with a past accident, and the closest case is taken from the accident case (S93).

【0043】取り込んだ事故ケースから事故を模擬的に
発生させる(S94)。健全区間の負荷の切替え対策を
行なう(S95)。前記(S95)の結果、供給支障の
有無の判断を行なう(S96)。(S96)の判断にて
供給支障が有る場合、区間の増強対策を行なう(S9
7)。(S96)の判断にて供給支障が無い場合は、負
荷の切替えにて対策可能であることで対策工事案が導出
される。
An accident is simulated from the taken accident case (S94). Measures for switching the load in the healthy section are taken (S95). As a result of the above (S95), it is determined whether there is a supply obstruction (S96). If there is a supply hindrance in the judgment of (S96), measures to increase the section are taken (S9).
7). If there is no supply obstacle in the judgment of (S96), a countermeasure construction plan is derived because a countermeasure can be taken by switching the load.

【0044】前記(S97)の結果、供給支障の有無の
判断を行なう(S98)。(S98)の判断にて供給支
障が有る場合、配電線やバンクの増強又は新設対策を行
なう(S99)。前記(S97),(S99)対策から
区間増強結果又は配電線の増強/新設結果を対策工事案
とする(S991)。(S98)の判断にて供給支障が
無い場合は、区間増強対策の結果を対策工事案とする。
As a result of the above (S97), it is determined whether or not there is a supply obstruction (S98). If there is a supply obstruction in the judgment of (S98), the distribution lines and banks are strengthened or newly installed (S99). Based on the measures (S97) and (S99), the section reinforcement result or the distribution line reinforcement / new construction result is taken as a countermeasure construction plan (S991). If there is no supply obstacle in the judgment of (S98), the result of the section reinforcement measure is taken as the measure construction plan.

【0045】前記事故想定手段23にて導出した対策工
事案は図1と同様に対策工事案19に保存され、対策工
事費算出手段192を起動する。起動された対策工事費
算出手段192は図1と同様に対策工事の費用を算出
し、対策工事費用193へ保存する。
The countermeasure construction plan derived by the accident assumption means 23 is stored in the countermeasure construction plan 19 as in FIG. The started countermeasure construction cost calculation means 192 calculates the cost of the countermeasure construction in the same manner as in FIG.

【0046】本実施の形態によれば、図1の配電系統設
備計画支援装置で導出した対策工事案に更に将来発生し
得る事故を想定した設備計画策定を行なう場合、過去に
実際発生した事故を用いることにより現実に近い事故の
想定が容易に可能となり、より設備計画策定の精度を更
に向上させることができる。
According to the present embodiment, in the case of formulating an equipment plan that assumes an accident that may occur in the future based on the countermeasure construction plan derived by the distribution system equipment planning support device of FIG. By using this, it is possible to easily assume an accident that is close to reality, and the accuracy of equipment planning can be further improved.

【0047】([請求項3]に対応)図10は本発明の
[請求項3]に係る配電系統設備計画支援装置の実施の
形態を示す構成図である。図10において、図1と同一
機能部分については同一符号を付して説明を省略する。
本実施の形態ではこれまでに導出した対策工事案を表示
することにより、オペレータの判断による新たな対策工
事案の作成が容易にできるようにしたものである。その
ために付加した構成は対策案表示手段31と対策工事案
(実績)32と対策案保存手段33とである。
(Corresponding to [Claim 3]) FIG. 10 is a configuration diagram showing an embodiment of a distribution system facility planning support apparatus according to [Claim 3] of the present invention. 10, the same reference numerals are given to the same functional portions as those in FIG. 1, and description thereof will be omitted.
In the present embodiment, by displaying the countermeasure construction plans derived so far, it is possible to easily create a new countermeasure construction plan at the discretion of the operator. The configuration added for that purpose is a measure proposal display means 31, a measure construction plan (actual) 32, and a measure plan storage means 33.

【0048】次に図1と異なる動作部分のみの説明をす
ると、対策導出手段18において対策工事案を導出する
都度、対策工事案19に保存し、対策工事費用算出手段
192を起動するが、対策案保存手段33も起動する。
起動された対策案保存手段33は対策工事案19をその
都度、対策工事案(実績)32に保存する。供給力不足
要因17のデータより、オペレータが供給力不足要因1
7を解消するための対策工事案を作成し、配電系統設備
計画支援装置へ入力する。
Next, only the operation part different from that in FIG. 1 will be described. Each time the countermeasure derivation means 18 derives a countermeasure construction plan, it is stored in the countermeasure construction plan 19 and the countermeasure construction cost calculation means 192 is started. The plan storage unit 33 is also activated.
The activated measure plan storage means 33 stores the measure construction plan 19 in the measure construction plan (actual) 32 each time. From the data of the supply power shortage factor 17, the operator indicates that the supply power shortage factor 1
A countermeasure construction plan for solving the problem 7 is created and input to the distribution system facility planning support device.

【0049】オペレータが入力した対策工事案は対策工
事案19に保存し、対策工事費用算出手段192を起動
する。オペレータが対策工事案を作成しようとするとき
に、前記対策案保存手段33にて保存した、これまで導
出済みの対策工事案(実績)32を対策案表示手段31
によりCRT入出力装置194に表示する。オペレータ
は表示された、これまで導出済みの対策工事案を参考に
しながら最適な対策工事案をマニュアル作成する。
The countermeasure construction plan input by the operator is stored in the countermeasure construction plan 19 and the countermeasure construction cost calculation means 192 is started. When the operator intends to create a countermeasure construction plan, the countermeasure construction plan (actual) 32 that has been derived so far and stored in the countermeasure plan storage unit 33 is displayed as a countermeasure plan display unit 31.
On the CRT input / output device 194. The operator manually creates an optimal countermeasure construction plan while referring to the displayed countermeasure construction plan that has been derived so far.

【0050】本実施の形態によれば、これまでに導出し
た対策工事案をオペレータに提供することにより、オペ
レータの判断による新たな対策工事案の作成が容易に行
なえ、設備計画策定の精度を更に向上させることができ
る。
According to the present embodiment, by providing a countermeasure construction plan derived so far to the operator, a new countermeasure construction plan can be easily created by the operator's judgment, and the accuracy of the equipment plan formulation can be further improved. Can be improved.

【0051】([請求項4]に対応)114は本発明の
[請求項4]に係る配電系統設備計画支援装置の実施の
形態を示す構成図である。図11において、図1と同一
機能部分については同一符号を付して説明を省略する。
本実施の形態では配電系統設備計画支援装置で用いる計
算定数データを変動の都度、修正できるようにしたもの
である。そのために付加した構成は計算定数修正手段4
1と単価管理システム3とである。
(Corresponding to [Claim 4]) 114 is a configuration diagram showing an embodiment of a distribution system facility planning support apparatus according to [Claim 4] of the present invention. 11, the same reference numerals are given to the same functional portions as in FIG. 1, and the description will be omitted.
In the present embodiment, the calculation constant data used in the distribution system facility planning support device can be corrected each time it changes. The configuration added for that purpose is calculated constant correction means 4.
1 and a unit price management system 3.

【0052】次に図1と異なる部分のみの動作説明をす
ると、計算定数修正手段41は、計算定数データ191
を、計算定数(工事単価,金利,原価償却費,固定資産
税,事業税,ロス単価等)の改訂に応じて、単価管理シ
ステム3からの情報をもとに自動更新、あるいは、計算
定数データ191をCRT入出力装置194に表示さ
せ、オペレータが任意に計算定数を設定し、その設定さ
れた計算定数で計算定数データ191を更新する。対策
工事費算出手段192は、対策工事案19と計算定数修
正手段41で更新された計算定数データ191をもと
に、より精度の高い対策工事費用を算出し、対策工事費
用193に保存する。
Next, the operation of only the parts different from those in FIG. 1 will be described.
Is automatically updated based on information from the unit price management system 3 in accordance with revision of calculation constants (construction unit price, interest rate, depreciation cost, fixed asset tax, business tax, loss unit price, etc.), or calculation constant data 191 is displayed on the CRT input / output device 194, the operator arbitrarily sets a calculation constant, and updates the calculation constant data 191 with the set calculation constant. The countermeasure construction cost calculating unit 192 calculates a more accurate countermeasure construction cost based on the countermeasure construction plan 19 and the calculation constant data 191 updated by the calculation constant correction unit 41, and stores the calculated cost in the countermeasure construction cost 193.

【0053】本実施の形態によれば、図1の配電系統設
備計画支援装置で用いる計算定数データを変動の都度、
修正できることにより、設備計画策定の精度を更に向上
させることができる。
According to the present embodiment, the calculation constant data used in the distribution system equipment planning support apparatus of FIG.
Being able to make corrections can further improve the accuracy of equipment planning.

【0054】([請求項5]に対応)図12は本発明の
[請求項5]に係る配電系統設備計画支援装置の実施の
形態を示す構成図である。図12において、図1と同一
機能部分については同一符号を付して説明を省略する。
本実施の形態では対策工事案で導出した実績をもとに同
時に一括での工事及び設備の手配による対策工事費用の
補正を行なうようにしたものである。そのために付加し
た構成は対策工事案(実績)32と対策案保存手段33
と対策工事同時手配手段51である。
(Corresponding to [Claim 5]) FIG. 12 is a configuration diagram showing an embodiment of a distribution system facility planning support apparatus according to [Claim 5] of the present invention. 12, the same reference numerals are given to the same functional portions as in FIG. 1, and the description will be omitted.
In the present embodiment, based on the results derived in the countermeasure construction plan, the countermeasure construction cost is corrected simultaneously by collective construction and arrangement of equipment. The configuration added for that purpose is a countermeasure construction plan (actual) 32 and a countermeasure plan storage unit 33.
And countermeasure construction simultaneous arrangement means 51.

【0055】次に図1との差異部分についての動作を説
明する。対策案保存手段33は、対策導出手段18にお
いて対策工事案19を導出する都度起動され、対策工事
案19を対策工事案(実績)32に保存する。対策工事
費用算出手段192は、対策工事案19と計算定数デー
タ191をもとに、対策工事の費用を算出し、対策工事
同時手配手段51を起動する。
Next, the operation for the difference from FIG. 1 will be described. The countermeasure plan storage unit 33 is activated every time the countermeasure derivation unit 18 derives the countermeasure construction plan 19, and stores the countermeasure construction plan 19 in the countermeasure construction plan (actual) 32. The countermeasure construction cost calculating means 192 calculates the cost of the countermeasure work based on the countermeasure work plan 19 and the calculation constant data 191, and activates the countermeasure work simultaneous arrangement means 51.

【0056】起動された対策工事同時手配手段51は、
対策工事案19と前記対策案保存手段33にて保存した
対策工事案(実績)32の中に、対策工事実施時期が同
じ、あるいは同じ設備の工事がないかをチェックし、対
策工事実施時期が同じ、あるいは同じ設備がある場合、
一括での工事及び設備の手配による対策工事費用の補正
(低減)を行ない、対策工事費用193に保存する。
The activated countermeasure construction simultaneous arrangement means 51 is
In the countermeasure construction plan 19 and the countermeasure construction plan (actual) 32 stored by the countermeasure plan storage means 33, it is checked whether the countermeasure construction execution time is the same or there is no construction of the same equipment. If you have the same or the same equipment,
Correction (reduction) of the countermeasure construction cost by collective construction and arrangement of equipment is performed, and saved in the countermeasure construction cost 193.

【0057】本実施の形態によれば、配電系統設備計画
支援装置で導出した対策工事案で同時手配を図ることで
工事費用を更に低減できる。
According to the present embodiment, construction costs can be further reduced by simultaneously arranging countermeasure construction plans derived by the distribution system facility planning support apparatus.

【0058】([請求項6]に対応)図13は本発明の
[請求項6]に係る配電系統設備計画支援装置の実施の
形態を示す構成図である。図13において、図1,図
8,図10ないし図12と同一機能部分については同一
符号を付して説明を省略する。本実施の形態では第1の
実施の形態の構成を基本とし、これに第1〜第5の実施
の形態までに示す個々の機能を付加することにより、全
体構成としたものである。
(Corresponding to [Claim 6]) FIG. 13 is a block diagram showing an embodiment of a distribution system facility planning support apparatus according to [Claim 6] of the present invention. 13, the same reference numerals are given to the same functional portions as those in FIGS. 1, 8, 10 to 12, and the description will be omitted. In the present embodiment, the overall configuration is based on the configuration of the first embodiment, and the individual functions shown in the first to fifth embodiments are added thereto.

【0059】そして個々の構成及び作用は、各実施の形
態にて既に説明済みであるため割愛し、本実施の形態に
特有の部分のみの作用を説明する。まず、評価条件設定
手段61は、評価条件データ62をCRT入出力装置1
94に表示する。オペレータは、表示された内容を確認
して必要に応じて評価条件を再設定し、設定終了により
評価条件設定手段61が起動され、評価条件データ62
を更新後、評価判定手段63を起動する。
The individual configurations and operations have already been described in the respective embodiments, and thus will be omitted, and the operations of only the parts unique to the present embodiment will be described. First, the evaluation condition setting means 61 stores the evaluation condition data 62 in the CRT input / output device 1.
Display at 94. The operator confirms the displayed contents and resets the evaluation conditions as necessary. Upon completion of the setting, the evaluation condition setting means 61 is activated, and the evaluation condition data 62 is set.
Is updated, the evaluation determination means 63 is activated.

【0060】評価判定手段63は、供給力不足要因抽出
手段16にて保存した供給力不足要因17と、対策導出
手段18にて導出した対策工事案19、あるいは、事故
想定手段23にて導出した対策工事案19、あるいは、
オペレータが独自に検討し、入力した対策工事案19
を、対策案保存手段33にて保存した対策工事案(実
績)32と、対策工事同時手配手段51にて保存した対
策工事費用193を、評価条件データ62をもとに評価
し、評価の高い順番に結果をCRT入出力装置194に
表示する。
The evaluation determining means 63 derives the supply power shortage factor 17 stored by the supply power shortage factor extracting means 16, the countermeasure construction plan 19 derived by the countermeasure deriving means 18, or the accident deducing means 23. Countermeasure construction plan 19, or
Countermeasure construction plan 19 that the operator independently considered and entered
Is evaluated on the basis of the evaluation condition data 62 based on the evaluation condition data 62 of the countermeasure construction plan (actual result) 32 stored by the countermeasure plan storage unit 33 and the countermeasure construction cost 193 stored by the countermeasure construction simultaneous arrangement unit 51. The results are displayed on the CRT input / output device 194 in order.

【0061】評価判定手段63のフォローチャートを図
14に示す。まず、評価条件設定手段にて設定された評
価条件データを読み込む(S141)。以降の処理を対
策工事案(実績)の数分繰り返す(S142)。対策工
事案(実績)から対策工事案を1つ取り出し、当該対策
工事案に対応する供給力不足要因と対策工事費用を読み
込む(S143)。当該対策工事案と当該対策工事案に
対応する供給不足要因、対策工事費用は、評価条件デー
タの条件を全て満足しているか判定する(S144)。
FIG. 14 shows a follow chart of the evaluation judging means 63. First, the evaluation condition data set by the evaluation condition setting means is read (S141). The subsequent processing is repeated for the number of countermeasure construction plans (actual results) (S142). One of the countermeasure construction plans is taken out from the countermeasure construction plan (actual results), and the factor of supply shortage and the countermeasure construction cost corresponding to the countermeasure construction plan are read (S143). It is determined whether the countermeasure construction plan, the supply shortage factor corresponding to the countermeasure construction plan, and the countermeasure construction cost all satisfy the conditions of the evaluation condition data (S144).

【0062】条件を満足していない場合は、次の対策工
事案を処理する。条件を満足している場合は、当該対策
工事案、当該対策工事案に対応する供給力不足要因、対
策工事費用と既に評価済みの他の対策工事案、供給力不
足要因、対策工事費用を比較して評価順位を決定し、そ
の評価順位の高い順番に並べ替えを行なう(S14
5)。
If the conditions are not satisfied, the next countermeasure construction plan is processed. If the conditions are satisfied, compare the proposed countermeasure work, the factor of insufficient supply capacity corresponding to the proposed measure, the countermeasure construction cost and other measures already evaluated, the factor of insufficient supply capacity, and the measure cost To determine the evaluation order, and rearrange them in the order of higher evaluation order (S14).
5).

【0063】これを、対策工事案(実績)の数分繰り返
し、全ての評価が終了した時点で、結果(評価条件を満
足しないものは表示対象外であり、条件を満足したもの
は評価の高い順番で表示)をCRT入出力装置に表示す
る。この表示結果をもとにオペレータは、最適な設備計
画の策定を決定する。
This is repeated for several minutes of the countermeasure construction plan (actual results), and when all the evaluations are completed, the results (things that do not satisfy the evaluation conditions are not displayed, and those that satisfy the conditions have high evaluations). (Displayed in order) on the CRT input / output device. Based on the display result, the operator decides to formulate an optimal equipment plan.

【0064】本実施の形態によれば、複数の設備計画の
策定工事案の中から、オペレータの評価条件に応じて供
給力不足要因,対策工事案,対策工事費用を評価し、評
価結果を出力するため、オペレータによる最適な設備計
画の策定作業の省力化に大きく寄与する。
According to the present embodiment, among a plurality of construction plans for preparing a facility plan, factors of supply shortage, countermeasure construction plans, and countermeasure construction costs are evaluated according to the evaluation conditions of the operator, and the evaluation results are output. Therefore, it greatly contributes to labor saving of the operation of formulating an optimal equipment plan by the operator.

【0065】上記した各説明において記載した手法は、
コンピュータに実行させることのできるプログラムとし
て、例えば磁気ディスク,光ディスク,半導体メモリな
どの記憶媒体に書き込んで、各種装置に適用したり、通
信媒体により伝送して各種装置に適用することも可能で
ある。又、これらを実現するコンピュータは、記憶媒体
に記憶されたプログラムを読み込み、このプログラムに
よって動作が制御されることにより、上述した処理を実
行する。
The method described in each of the above descriptions is as follows.
As a program that can be executed by a computer, for example, the program can be written in a storage medium such as a magnetic disk, an optical disk, or a semiconductor memory and applied to various devices, or transmitted to a communication medium and applied to various devices. Also, a computer that implements these processes reads the program stored in the storage medium, and executes the above-described processing by controlling the operation of the program.

【0066】[0066]

【発明の効果】以上説明したように、本発明によれば配
電系統設備計画支援装置における将来予想される電力需
要の算出及び入力,将来発生するであろう事故ケースの
作成,対策工事案の作成,工事費計算で使用する各種計
算定数の変更,対策工事費のコストミニマム化,対策工
事案の評価を、単時間でかつ労力をかけずに実現するこ
とができる。
As described above, according to the present invention, calculation and input of power demand expected in the distribution system facility planning support apparatus, creation of an accident case that may occur in the future, and creation of a countermeasure construction plan according to the present invention. In addition, it is possible to realize the change of various calculation constants used in the construction cost calculation, the minimization of the cost of the countermeasure construction cost, and the evaluation of the measure for the construction of the countermeasure in a single time and without labor.

【図面の簡単な説明】[Brief description of the drawings]

【図1】[請求項1]の実施の形態を示す構成図。FIG. 1 is a configuration diagram showing an embodiment of [claim 1].

【図2】図1の負荷想定処理フローチャート。FIG. 2 is a flowchart of a load assumption process of FIG. 1;

【図3】図1の要因別対策検討項目一覧。FIG. 3 is a list of countermeasure study items by factor in FIG. 1;

【図4】図1の対策案導出処理フローチャート。FIG. 4 is a flowchart of a countermeasure plan deriving process in FIG. 1;

【図5】図1の対策導出手段の各対策検討項目の構成
図。
FIG. 5 is a configuration diagram of each measure examination item of the measure deriving means of FIG. 1;

【図6】図1の負荷切り替え例。FIG. 6 is an example of load switching in FIG. 1;

【図7】図1の処理フローチャート。FIG. 7 is a processing flowchart of FIG. 1;

【図8】[請求項2]の実施の形態を示す構成図。FIG. 8 is a configuration diagram showing an embodiment of [claim 2].

【図9】図8の事故想定処理フローチャート。9 is a flowchart of an accident assumption process of FIG.

【図10】[請求項3]の実施の形態を示す構成図。FIG. 10 is a configuration diagram showing an embodiment of [claim 3].

【図11】[請求項4]の実施の形態を示す構成図。FIG. 11 is a configuration diagram showing an embodiment of claim 4.

【図12】[請求項5]の実施の形態を示す構成図。FIG. 12 is a configuration diagram showing an embodiment of [claim 5].

【図13】[請求項6]の実施の形態を示す構成図。FIG. 13 is a configuration diagram showing an embodiment of [claim 6].

【図14】図13の評価判定処理フローチャート。FIG. 14 is a flowchart of an evaluation determination process in FIG. 13;

【符号の説明】[Explanation of symbols]

1 配電系統設備計画支援装置 2 遠方監視制御装置 11 負荷データ保存手段 12 負荷データ 13 負荷想定手段 14 最大想定負荷 15 設備DB 16 供給力不足要因抽出手段 17 供給力不足要因 18 対策導出手段 19 対策工事案 191 計算定数データ 192 対策工事費用算出手段 193 対策工事費用 194 CRT入出力装置 21 事故ケース保存手段 22 事故ケース 23 事故想定手段 31 対策案表示手段 32 対策工事案(実績) 33 対策案保存手段 41 計算定数修正手段 42 単価管理システム 51 対策工事同時手配手段 61 評価条件設定手段 62 評価条件データ 63 評価判定手段 REFERENCE SIGNS LIST 1 distribution system equipment planning support device 2 remote monitoring control device 11 load data storage means 12 load data 13 load estimation means 14 maximum assumed load 15 equipment DB 16 supply power shortage factor extraction means 17 supply power shortage factor 18 countermeasure derivation means 19 countermeasure construction Plan 191 Calculation constant data 192 Measure construction cost calculation means 193 Measure construction cost 194 CRT input / output device 21 Accident case storage means 22 Accident case 23 Accident assumption means 31 Measure plan display means 32 Measure construction plan (actual) 33 Measure plan save means 41 Calculation constant correction means 42 Unit price management system 51 Countermeasure construction simultaneous arrangement means 61 Evaluation condition setting means 62 Evaluation condition data 63 Evaluation judgment means

───────────────────────────────────────────────────── フロントページの続き (72)発明者 羽田野 寿明 福岡県福岡市中央区長浜2−4−1 株式 会社東芝九州支社内 Fターム(参考) 5G066 AA02 AA03 AE07 AE09  ────────────────────────────────────────────────── ─── Continuing on the front page (72) Inventor Toshiaki Hanano 2-4-1 Nagahama, Chuo-ku, Fukuoka City, Fukuoka F-term (reference) 5G066 AA02 AA03 AE07 AE09

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 電力需要の増加によって発生する配電系
統を構成する各設備の導入更新計画を支援する配電系統
設備計画支援装置において、刻々変化する配電系統の電
力需要を遠方監視制御装置を介して負荷データとして取
り込む負荷データ保存手段と、前記負荷データ保存手段
にて保存した過去及び現在の電力需要の負荷データをも
とに将来の電力需要を予測する負荷想定手段と、前記負
荷想定手段により予測した将来の電力需要と、配電系統
を構成する各設備の供給可能容量を比較して供給可能容
量を超過する設備とその要因とを供給力不足要因として
抽出する供給力不足要因抽出手段と、供給可能容量を超
過した設備に対して、その要因を解消する対策工事案を
導出する対策導出手段と、前記対策導出手段が導出した
対策工事案に対する対策工事費用を算出する対策工事費
用算出手段とを備えたことを特徴とする配電系統設備計
画支援装置。
1. A power distribution system facility planning support apparatus for supporting an introduction and renewal plan of each facility constituting a power distribution system caused by an increase in power demand, the power demand of the power distribution system changing from time to time via a remote monitoring control device. Load data storage means for taking in as load data, load estimation means for predicting future power demand based on load data of past and current power demand stored in the load data storage means, prediction by the load estimation means A power supply shortage factor extracting means for comparing the future power demand with the available capacity of each facility constituting the distribution system and extracting the facilities that exceed the available capacity and the factors as the shortage factor; Measures deriving means for deriving a countermeasure construction plan for eliminating the factor for the equipment exceeding the available capacity, and a countermeasure construction plan derived by the countermeasure deriving means. A distribution system facility planning support device, comprising: a countermeasure construction cost calculation means for calculating a countermeasure construction cost.
【請求項2】 請求項1記載の配電系統設備計画支援装
置において、実際の配電系統にて発生した事故情報を事
故ケースとして保存する事故ケース保存手段と、前記事
故ケース保存手段にて保存した過去に発生した事故ケー
スを基に供給支障状況を計算し、供給支障状況からその
要因を解消する対策工事案を更に導出する事故想定手段
とを備えたことを特徴とする配電系統設備計画支援装
置。
2. The distribution system facility planning support apparatus according to claim 1, wherein accident information storage means for storing accident information generated in an actual distribution system as an accident case, and a past information stored by said accident case storage means. A power distribution system facility planning support apparatus, comprising: an accident assumption means for calculating a supply obstruction state based on an accident case that has occurred in the above, and further deriving a countermeasure construction plan for eliminating the cause from the supply obstruction state.
【請求項3】 請求項1記載の配電系統設備計画支援装
置において、対策導出手段で対策工事案を導出する都
度、その対策工事案を常に保存する対策案保存手段と、
供給力不足要因抽出手段により抽出された供給可能容量
を超過した設備に対して、前記対策案保存手段にてこれ
まで保存してある対策工事案の中から同一要因あるいは
当該設備に関わる対策工事案を表示する対策案表示手段
とを備えたことを特徴とする配電系統設備計画支援装
置。
3. The distribution system facility planning support device according to claim 1, wherein each time a countermeasure construction plan is derived by the countermeasure derivation unit, a countermeasure plan storage unit that always saves the countermeasure construction plan,
For equipment that exceeds the suppliable capacity extracted by the supply capacity shortage factor extraction means, the same factor or the countermeasure work plan related to the equipment is selected from the countermeasure work plans previously stored by the countermeasure plan storage means. And a countermeasure display means for displaying a message.
【請求項4】 請求項1記載の配電系統設備計画支援装
置において、対策工事費用算出手段にてその対策工事費
用の算出時に用いて計算定数を変更する計算定数修正手
段を有し、前記対策工事費用算出手段は前記計算定数修
正手段により計算定数が変更される度に、当該変更され
た計算定数により対策工事費用を算出することを特徴と
する配電系統設備計画支援装置。
4. The distribution system facility planning support device according to claim 1, further comprising a calculation constant correction means for changing a calculation constant by use of the countermeasure work cost calculation means when calculating the countermeasure work cost. The distribution system facility planning support device, wherein the cost calculation means calculates the countermeasure construction cost based on the changed calculation constant every time the calculation constant is changed by the calculation constant correction means.
【請求項5】 請求項1記載の配電系統設備計画支援装
置において、対策導出手段にて対策工事案を導出する都
度、その対策工事案を保存する対策案保存手段と、前記
対策案保存手段にて保存した対策工事案で工事の実施時
期が同時期か、あるいは同じ増設、新設の設備かを判断
し、工事及び設備の同時手配による対策工事費の最小化
を図る対策工事同時手配手段とを備えたことを特徴とす
る配電系統設備計画支援装置。
5. The distribution system facility planning support device according to claim 1, wherein each time a countermeasure derivation unit derives a countermeasure construction plan, the countermeasure plan storage unit stores the countermeasure construction plan, and Judgment of whether the implementation time of the construction is the same time or the same extension or new facilities based on the saved construction plan, and the means for simultaneous construction of the construction works to minimize the construction cost of the construction by the simultaneous arrangement of construction and facilities A distribution system facility planning support device, comprising:
【請求項6】 請求項1ないし請求項5記載の各々の配
電系統設備計画支援装置において、供給力不足要因と対
策工事案と対策工事費用とをもとに、最適な設備計画の
策定を評価するための評価条件を設定する評価条件設定
手段と、その設定された評価条件をもとに複数の対策工
事案から評価の高い順番に評価結果を出力し、オペレー
タによる最適な設備計画の策定を導き出すための情報を
提供する評価判定手段とを備えたことを特徴とする配電
系統設備計画支援装置。
6. In each of the distribution system facility planning support devices according to claim 1, the formulation of an optimal facility plan is evaluated based on a factor of insufficient supply capacity, a countermeasure construction plan, and a countermeasure construction cost. Evaluation condition setting means for setting evaluation conditions to perform the evaluation, and output the evaluation results from the plurality of countermeasure construction plans in descending order of evaluation based on the set evaluation conditions, so that the operator can formulate an optimal equipment plan. A power distribution system facility planning support device comprising: an evaluation determining unit that provides information for deriving the power distribution system.
【請求項7】 電力需要の増加によって発生する配電系
統を構成する各設備の導入更新計画を支援する配電系統
設備計画支援装置において、刻々変化する配電系統の電
力需要を遠方監視制御装置を介して負荷データとして取
り込む負荷データ保存手段を実行する機能と、前記負荷
データ保存手段にて保存した過去及び現在の電力需要の
負荷データをもとに将来の電力需要を予測する負荷想定
手段を実行する機能と、前記負荷想定手段により予測し
た将来の電力需要と、配電系統を構成する各設備の供給
可能容量を比較して供給可能容量を超過する設備とその
要因とを供給力不足要因として抽出する供給力不足要因
抽出手段を実行する機能と、供給可能容量を超過した設
備に対して、その要因を解消する対策工事案を導出する
対策導出手段を実行する機能と、前記対策導出手段が導
出した対策工事案に対する対策工事費用を算出する対策
工事費用算出手段を実行する機能とを実行させるための
プログラムを記憶したコンピュータ読み取り可能な記憶
媒体。
7. A power distribution system facility planning support apparatus for supporting an introduction and renewal plan of each facility constituting a power distribution system caused by an increase in power demand, the power demand of the power distribution system changing every moment via a remote monitoring control device. A function of executing load data storage means for taking in as load data, and a function of executing load estimation means for predicting future power demand based on load data of past and current power demand stored by the load data storage means And comparing the future power demand predicted by the load estimating means with the suppliable capacity of each facility constituting the distribution system to extract facilities that exceed the suppliable capacity and their factors as factors for the shortage of supply capacity. Function to execute power shortage factor extraction means and execution of measure derivation means to derive a countermeasure construction plan for equipment that exceeds the available capacity A computer-readable storage medium storing a program for executing a function of executing a countermeasure construction cost calculation unit for calculating a countermeasure construction cost for a countermeasure construction plan derived by the countermeasure derivation unit.
JP28565899A 1999-10-06 1999-10-06 Distribution system facility plan supporting device and storage medium storing program for executing the same Pending JP2001112171A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28565899A JP2001112171A (en) 1999-10-06 1999-10-06 Distribution system facility plan supporting device and storage medium storing program for executing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28565899A JP2001112171A (en) 1999-10-06 1999-10-06 Distribution system facility plan supporting device and storage medium storing program for executing the same

Publications (1)

Publication Number Publication Date
JP2001112171A true JP2001112171A (en) 2001-04-20

Family

ID=17694395

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28565899A Pending JP2001112171A (en) 1999-10-06 1999-10-06 Distribution system facility plan supporting device and storage medium storing program for executing the same

Country Status (1)

Country Link
JP (1) JP2001112171A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009060749A (en) * 2007-09-03 2009-03-19 Chugoku Electric Power Co Inc:The Power system planning support system
JP2010009136A (en) * 2008-06-24 2010-01-14 Chugoku Electric Power Co Inc:The Electricity bill calculation system and electricity bill calculation method
JP2018110489A (en) * 2017-01-04 2018-07-12 株式会社東芝 Power system maintenance support system and power system maintenance support method
JP2019154113A (en) * 2018-03-01 2019-09-12 株式会社日立製作所 Computer system and management method for system configuration
KR20220011506A (en) * 2020-07-21 2022-01-28 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009060749A (en) * 2007-09-03 2009-03-19 Chugoku Electric Power Co Inc:The Power system planning support system
JP2010009136A (en) * 2008-06-24 2010-01-14 Chugoku Electric Power Co Inc:The Electricity bill calculation system and electricity bill calculation method
JP2018110489A (en) * 2017-01-04 2018-07-12 株式会社東芝 Power system maintenance support system and power system maintenance support method
JP2019154113A (en) * 2018-03-01 2019-09-12 株式会社日立製作所 Computer system and management method for system configuration
KR20220011506A (en) * 2020-07-21 2022-01-28 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR102464083B1 (en) 2020-07-21 2022-11-08 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR20220150260A (en) * 2020-07-21 2022-11-10 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR20220150259A (en) * 2020-07-21 2022-11-10 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR20220150261A (en) * 2020-07-21 2022-11-10 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR20220150861A (en) * 2020-07-21 2022-11-11 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR20220153527A (en) * 2020-07-21 2022-11-18 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR102511704B1 (en) 2020-07-21 2023-03-21 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR102512188B1 (en) 2020-07-21 2023-03-22 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR102512790B1 (en) 2020-07-21 2023-03-23 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR102513738B1 (en) 2020-07-21 2023-03-27 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium
KR102514243B1 (en) 2020-07-21 2023-03-29 한국전력공사 System and Method for estimating power demand over the long term, Computer readable storage medium

Similar Documents

Publication Publication Date Title
US5798939A (en) System for optimizing power network design reliability
Abiri-Jahromi et al. An efficient mixed-integer linear formulation for long-term overhead lines maintenance scheduling in power distribution systems
JP2013102676A (en) Power outage management apparatus and method in ems
JP2019180163A (en) Management device, management method and management system
CN105162110A (en) Configuration method for sectionalizing and interconnection switches of power distribution network
JP2006340552A (en) Electric power quality evaluation system and method, and program therefor
JP4556946B2 (en) Tidal current calculation method and apparatus
CN103150605B (en) Power grid planning auxiliary system
JP2002183347A (en) Maintenance planning system and method
JP2001112171A (en) Distribution system facility plan supporting device and storage medium storing program for executing the same
Hilber et al. Monetary importance of component reliability in electrical networks for maintenance optimization
Larsson et al. Monitoring and operation of transmission corridors
CN114336634A (en) Load flow calculation method, device and equipment of power grid system
JP7254041B2 (en) SYSTEM PLANNING SUPPORT SYSTEM AND SYSTEM PLANNING SUPPORT METHOD
WO2019008856A1 (en) System operation support device and method in power system, and wide-area monitoring protection control system
EP3750223B1 (en) Predicting voltage stability of a power system post-contingency
JPH10164756A (en) Method and apparatus for controlling power system
EP4235997A1 (en) System for assisting with creation of grid plan for changing structure of power grid, and method for same
JP4341034B2 (en) System switching procedure planning method, system switching procedure planning system, program, and recording medium
Sperr et al. Service restoration in the medium voltage grid minimizing the SAIDI contribution after primary substation failures
Jardim et al. Brazilian system operator online security assessment system
JP2008199855A (en) Distribution system excessive facility check system
Hoffmann et al. Situation adapted display of information for operating very large interconnected grids
CN113095952A (en) Power grid splitting early warning method and system considering real-time and N-X forecast information
CN113609780B (en) Control method and device for clock running strategy based on event network and electronic equipment