JP2000355483A - Hook set of power shovel having crane specifications - Google Patents

Hook set of power shovel having crane specifications

Info

Publication number
JP2000355483A
JP2000355483A JP11168893A JP16889399A JP2000355483A JP 2000355483 A JP2000355483 A JP 2000355483A JP 11168893 A JP11168893 A JP 11168893A JP 16889399 A JP16889399 A JP 16889399A JP 2000355483 A JP2000355483 A JP 2000355483A
Authority
JP
Japan
Prior art keywords
bucket
ball bearing
power shovel
hook
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11168893A
Other languages
Japanese (ja)
Other versions
JP2000355483A5 (en
Inventor
Shoichi Sakai
正一 酒井
Toshio Nishioka
敏雄 西岡
Toshihiko Sakashita
敏彦 坂下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MARTEC KK
Muroto Tekkosho KK
Original Assignee
MARTEC KK
Muroto Tekkosho KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MARTEC KK, Muroto Tekkosho KK filed Critical MARTEC KK
Priority to JP11168893A priority Critical patent/JP2000355483A/en
Publication of JP2000355483A publication Critical patent/JP2000355483A/en
Publication of JP2000355483A5 publication Critical patent/JP2000355483A5/ja
Pending legal-status Critical Current

Links

Landscapes

  • Shovels (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

PROBLEM TO BE SOLVED: To prevent the damage of a support shaft by the slant pulling except the hand down direction of the regular direction of a vertical direction. SOLUTION: This power shovel is provided with a bucket on the end of an arm connected to the boom of the power shovel, a hook set installed on the outside end of the bucket and specifications taken as available. In the power shovel, a support body 22 is arranged in parallel at intervals down the bottom of a boss 21 turnably supported to the fixed shaft provided the shaft in the horizontal direction fixingly, while penetrating right/left two projections provided integrally on the upper end of the bucket and connected to a hydraulic cylinder through a bucket link. A link pin 23 is fixed to two support bodies 22 and a swivel 25 stored a ball bearing 24 for supporting the rotation of the vertical axis direction turnably in its inside is provided on the link pin 23 and the hook 26 supporting an upper shaft 26a is connectingly provided through the inside ball bearing 24.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明が属する技術分野】本発明は、パワーショベルの
ブームに連結されるアーム端部に、油圧操作によって回
動されるバケットを設け、クレーン仕様を可能にしたパ
ワーショベルのフックセットに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a hook set for a power shovel, which is provided with a bucket pivoted by hydraulic operation at an end of an arm connected to a boom of the power shovel to enable a crane specification.

【0002】[0002]

【従来の技術】従来、パワーショベルで荷重(品物)の
吊り作業を行うクレーン使用時に、バケットにフックセ
ットを設けたものが使用されており、図3(a)はその
一例を示す全体構造の概略説明図である。
2. Description of the Related Art Conventionally, when a crane is used for suspending a load (article) by a power shovel, a bucket is provided with a hook set, and FIG. 3 (a) shows an example of the whole structure. FIG.

【0003】図において、パワーショベル本体1からブ
ーム2及びアーム3が連結され、アーム3の端部にバケ
ット4が取り付けられており、使用時に安全性の見地か
らブーム2と本体1の垂直線とが成すブーム角αや、ブ
ーム2とアーム3とのアーム角度βを角度センサで検知
し、またブーム2の吊り荷重を検知して、該パワーショ
ベル本体1に対して、アーム3の先端部に油圧等によっ
て回動可能に取り付けられ、バケット4の外側端部に取
り付けられたフック5に掛かる外部吊り下げ荷重など
が、労働基準法等の関係法規の許容範囲内にあるように
監視されている。
[0003] In the figure, a boom 2 and an arm 3 are connected to a power shovel body 1, and a bucket 4 is attached to an end of the arm 3. Angle and the arm angle β between the boom 2 and the arm 3 are detected by an angle sensor, and the suspension load of the boom 2 is detected. An external hanging load, which is rotatably mounted by hydraulic pressure or the like and is applied to a hook 5 attached to the outer end of the bucket 4, is monitored so as to be within an allowable range of related laws and regulations such as the Labor Standards Act. .

【0004】図3(b)は、上記した図3(a)のA部
に相当するアーム3の先端部に油圧シリンダ3aにより
並列配置されたバケットリンク3bによって回動可能に
取り付けられるバケット4を、アーム3から取り外した
バケット単体の側面図である。図において、該バケット
4aは図で左側上端部に上記の油圧シリンダ3aからの
バケットリンク3bが固着される左右二個の突出部(耳
部)4aが設けられており、該突出部4aを貫通する軸
4bを介して、フック5が取り付けられており、その具
体的構造が図4に示されている。
FIG. 3 (b) shows a bucket 4 rotatably attached to a tip end of an arm 3 corresponding to the portion A in FIG. 3 (a) by bucket links 3b arranged in parallel by a hydraulic cylinder 3a. FIG. 4 is a side view of the single bucket removed from the arm 3. In the figure, the bucket 4a is provided with two left and right protrusions (ears) 4a to which the bucket link 3b from the hydraulic cylinder 3a is fixed at the upper left end in the figure, and penetrates the protrusion 4a. The hook 5 is attached via a shaft 4b to be connected, and the specific structure is shown in FIG.

【0005】図4において、上記したようにバケット4
を回動させるため、油圧シリンダ3aに接続されたバケ
ットリンク3b、3bがバケット4の図で左側上端部に
突出して設けられた左右二個の突出部4a、4aに連結
されており、これら二個の突出部4a、4aを貫通し
て、軸4bが固定してバケット4に取り付けられてい
る。
[0005] In FIG.
The bucket links 3b, 3b connected to the hydraulic cylinder 3a are connected to two left and right protrusions 4a, 4a projecting from the upper left end of the bucket 4 in FIG. The shaft 4b is fixedly attached to the bucket 4 through the projecting portions 4a, 4a.

【0006】一方、上記固定軸4bに、先端にフック1
1(図3の5に相当する)を取り付けたボス6が回動自
在に取り付けられている。該ボス6には、下方に中間に
二個の凹部を形成した三個の突出部7a〜7cを一体に
備えたシャンクカップリング7がねじ込まれ、ナット8
によって固定されている。
On the other hand, a hook 1 is attached to the tip of the fixed shaft 4b.
A boss 6 to which 1 (corresponding to 5 in FIG. 3) is attached is rotatably attached. The boss 6 is screwed with a shank coupling 7 integrally provided with three projecting portions 7a to 7c having two concave portions formed in the middle below.
Has been fixed by.

【0007】上記シャンクカップリング7の三個の突出
部7a〜7cによって形成された中間部の凹部に嵌合す
る(噛み合う)ように三個の突出部9a〜9cを上部に
備え、下部にも同形状の突出部9d〜9fを備え、内部
に(図の位置で以下同じ)垂直方向の回転を支持するボ
ールベアリングを収納したボールベアリングスイベル9
が、上記シャンクカップリング7の、突出部7a〜7c
と嵌合するボールベアリングスイベル9の上部突出部9
a〜9cとがピン10を介して回動可能に接続されてい
る。
The upper part is provided with three projections 9a to 9c so as to be fitted (engaged) with the concave part of the intermediate part formed by the three projections 7a to 7c of the shank coupling 7. A ball bearing swivel 9 having protrusions 9d to 9f of the same shape and containing therein a ball bearing that supports vertical rotation (the same applies hereinafter in the figure).
Are the protruding portions 7a to 7c of the shank coupling 7.
Upper projection 9 of ball bearing swivel 9 fitted with
a to 9 c are rotatably connected via a pin 10.

【0008】一方、該ボールベアリングスイベル9の下
方の突出部9d〜9fに、上記同様に嵌合する三個の突
起11a〜11cを上端部に有するフック11が、ピン
12を介して回動可能に連結される。尚、図中13はフ
ックの開口部に設けられた外れ止め具である。
On the other hand, a hook 11 having three projections 11a to 11c fitted on the lower projections 9d to 9f of the ball bearing swivel 9 in the same manner as described above is rotatable via a pin 12. Linked to Reference numeral 13 in the figure denotes a stopper provided at the opening of the hook.

【0009】クレーン作業時、フック11に品物(荷重
体)に固定した吊り下げ紐や鎖の上端部を引っかけて、
外れ止め具13で係止した後、パワーショベル本体のエ
ンジンを駆動して、ブーム2及びアーム3、並びに油圧
シリンダ3aを作動して荷重体を吊り上げ、所定の位置
まで移動し、吊り下げて作業をするようになっている。
At the time of crane work, hook the upper end of a hanging string or a chain fixed to an article (loading body) on the hook 11,
After locking with the stopper 13, the engine of the power shovel body is driven to operate the boom 2, the arm 3, and the hydraulic cylinder 3a to lift the load, move to a predetermined position, and suspend the work. It is supposed to.

【0010】[0010]

【発明が解決しようとする課題】前記した従来公知のも
のにおいては、次のような問題点があった。図5(b)
は図4のフックセット部を横向きに大地に静止した状態
を示す小型機種の側面図であり、同図(a)は平面図で
ある。図5において、
The above-mentioned known devices have the following problems. FIG. 5 (b)
FIG. 5 is a side view of a small model showing a state in which the hook set unit of FIG. 4 is stationary on the ground in the horizontal direction, and FIG. 4A is a plan view. In FIG.

【0011】(i)品物をフック11に引掛け、正規な
吊り上げ方は真上に吊り上げるので問題は生じないが、
斜め方向に引き、パワーショベルが旋回または走行する
と、フック11の向きが、図5の横置き姿勢に対し、或
る角度(矢印Bのように)で回転しようとする時には、
フック11に近いピンに近接したC部が回動しない場合
がある。
(I) There is no problem because the article is hooked on the hook 11 and the normal lifting is lifted right above.
When the power shovel turns or runs in an oblique direction and the hook 11 is turned at a certain angle (as indicated by an arrow B) with respect to the horizontal position shown in FIG.
The portion C close to the pin close to the hook 11 may not rotate.

【0012】この状況が発生すると、ボス6に近いピン
10とフック11の内径までの寸法(オーバーハング)
Lによって、図4及び図5に示されたボス6に近い側の
ピン10に偏荷重が掛かり、該ピン10が折れるという
問題点があった。
When this situation occurs, the dimension up to the inner diameter of the pin 10 and the hook 11 close to the boss 6 (overhang)
Due to L, an unbalanced load is applied to the pin 10 on the side near the boss 6 shown in FIGS. 4 and 5, and the pin 10 is broken.

【0013】(ii)一方、小型機械においてはボス6と
シャンクカップリング7との間に図4に示されたシャン
クカップリング7のネジ止めナット8を挿入するスペー
スがないので、図5に示すように、ねじ込まれるシャン
クカップリング7の位置決めは、回り止めピン8aで行
っている。
(Ii) On the other hand, in a small machine, there is no space between the boss 6 and the shank coupling 7 for inserting the screw nut 8 of the shank coupling 7 shown in FIG. As described above, the positioning of the shank coupling 7 to be screwed is performed by the detent pin 8a.

【0014】この場合もボールベアリングスイベル9の
旋回機能が正常であれば、ピン10及び12には、小さ
いトルクしか作用しないが、何らかの理由、例えばボー
ルベアリングスイベル9の中にゴミや砂等が混入するな
どのトラブルが発生した時には、上記した回り止めピン
8aに回転トルクが生じ、これによって該ピン止め8a
が折損する恐れがあるという問題点があった。
In this case as well, if the swiveling function of the ball bearing swivel 9 is normal, only a small torque acts on the pins 10 and 12, but for some reason, for example, dust or sand is mixed in the ball bearing swivel 9. When a trouble such as the occurrence of trouble occurs, a rotation torque is generated in the above-described detent pin 8a, thereby causing
However, there is a problem that there is a risk of breakage.

【0015】(iii)また、当該フックセットを海水中
に浸す作業もあり、上記回り止めピン8aが腐食すると
折損につながり、シャンクカップリング7のネジが緩む
という問題点があった。
(Iii) There is also a work of immersing the hook set in seawater, and if the detent pin 8a is corroded, it will be broken, and the screw of the shank coupling 7 will be loosened.

【0016】(iv)他方、上方のシャンクカップリング
7と下方のフック11に各々連結するために、ボールベ
アリングスイベル9の上部と下部にそれぞれ設けられる
三個の突出部9a〜9cと9d〜9fをそれぞれ貫通す
るピン10としては、これらの各突出部と該突出部との
間の凹部に嵌合する相手側の突出部とによってせん断応
力を受ける。
(Iv) On the other hand, three projections 9a to 9c and 9d to 9f provided respectively on the upper and lower parts of the ball bearing swivel 9 for connecting to the upper shank coupling 7 and the lower hook 11, respectively. Are subjected to shear stress by the respective projecting portions and the projecting portion of the mating side which fits into the concave portion between the projecting portions.

【0017】図6は、上記(i)で述べた特にボス6に
近いシャンクリングカップ7と、ボールベアリングスイ
ベル9が互いに嵌合する突出部を貫通するピン10によ
って、連結される状態を示した要部説明用図面である。
図示のように貫通するピン10は、イ〜ニの四点で平均
せん断応力を受けており、これら各点の断面積をSと
し、ピンの直径をdとすると、 S=(πd/4)× 4倍 従って、垂直方向に吊り下げられる時は平均力がFであ
り、許容せん断応力の範囲内で済むが、斜め引きにする
と、支点Eからm離れた所にF′なる力が働くため、断
面イ、ロの加重負担が増大して折損する。
FIG. 6 shows a state where the shank ring cup 7 which is particularly close to the boss 6 and the ball bearing swivel 9 described in the above (i) are connected by the pin 10 penetrating the projecting portion in which the ball bearing swivel 9 is fitted. It is a drawing for principal part description.
Pin 10 which penetrates as shown, has received an average shear stress in the four points of the i-d, the cross-sectional area of each of these points and S, when the diameter of the pin and d, S = (πd 2/ 4 Therefore, when suspended in the vertical direction, the average force is F, which is within the range of the allowable shear stress, but when obliquely pulled, a force F 'acts at a distance of m from the fulcrum E. Therefore, the load on the cross-sections (a) and (b) is increased, resulting in breakage.

【0018】本発明は、垂直方向の正規の方向が吊り下
げ方向以外の斜め引き等によっても特に支持軸部が破損
しない、簡単な構造のクレーン仕様パワーショベルのフ
ックセットを提供することを課題としている。
It is an object of the present invention to provide a crane-specific power shovel hook set having a simple structure in which a support shaft portion is not particularly damaged even when a normal vertical direction is inclined other than a hanging direction. I have.

【0019】[0019]

【課題を解決するための手段】上記の課題を解決するた
めに本発明が採った手段は、パワーショベルに連結され
るアームの端部に、油圧操作によって回動されるバケッ
トを設け、該バケットの外側端部にフックセットを取り
付けてクレーン仕様を可能としたパワーショベルにおい
て、上記アーム端部に回動可能に取り付けられたバケッ
トの上端部に一体に設けられ、油圧シリンダにバケット
リンクを介して連結された左右二個の突出部を貫通する
水平方向に軸を固定して設け、該固定軸にボス部を回動
自在に支持して設け、該水平方向のボス部の底部の下方
に、上記固定軸に対して垂直方向に二個の支持体を間隔
をあけて並列配置し且つ一体に固定して設け、該並列に
配置された二個の支持体を貫通して固定するリンクピン
を設け、該リンクピンに回動自在に支持され、内部に垂
直軸方向の回転を支持するボールベアリングを収納した
ボールベアリングスイベルを設け、上記内部のボールベ
アリングによって上部軸部を支持されたフックを連結し
て設けたことを特徴としている。
In order to solve the above-mentioned problems, the present invention adopts a method in which a bucket pivoted by hydraulic operation is provided at an end of an arm connected to a power shovel. In a power shovel that has a crane specification by attaching a hook set to an outer end of the bucket, the bucket is integrally provided at an upper end of a bucket rotatably attached to the arm end, and is connected to a hydraulic cylinder via a bucket link. A fixed shaft is provided in the horizontal direction passing through the two connected left and right protrusions, and a boss is rotatably supported on the fixed shaft, and below the bottom of the horizontal boss, A link pin is provided in which two support members are arranged in parallel and spaced apart from each other in the direction perpendicular to the fixed axis and fixed integrally, and penetrates and fixes the two support members arranged in parallel. Provided the link A ball bearing swivel, which is rotatably supported by the bearing and accommodates a ball bearing that supports rotation in the vertical axis direction, is provided, and a hook whose upper shaft portion is supported by the internal ball bearing is connected. It is characterized by:

【0020】また、上記バケットの上端部に水平方向に
固定して設けらる固定軸に回動自在に支持して設けられ
るボス部を、中空円筒状に形成し、該ボス部の底部の下
方に設けられる二個の支持体を、それぞれ板状に形成し
て一体に固定して設けたことを特徴としている。
Further, a boss portion rotatably supported on a fixed shaft fixed to the upper end portion of the bucket and fixed in a horizontal direction is formed in a hollow cylindrical shape, and is formed below a bottom portion of the boss portion. The two support members provided in each of the above are formed in a plate shape, and are fixed and provided integrally.

【0021】[0021]

【本発明の実施の形態】次に本発明の実施の形態を添付
図面に示した実施例を用いて説明する。図1は本発明の
一実施形態を示すクレーン仕様パワーショベルに取り付
けられるフックセットを示し、(a)は正面断面図、
(b)は要部側面図である。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, embodiments of the present invention will be described with reference to the embodiments shown in the accompanying drawings. FIG. 1 shows a hook set attached to a crane-type power shovel showing one embodiment of the present invention, wherein (a) is a front sectional view,
(B) is a side view of a main part.

【0022】図において、21は前記したバケットの上
端部に一体に設けられ、油圧シリンダにアームを介して
連接された左右二個の突出部(図4の4a)を貫通する
固定軸(図4の4b)に回動自在に嵌合支持される図1
(a)に示すような、中空円筒状のボス部であり、該ボ
ス部21の底部の周面に接して垂直方向下方に、二枚の
板状支持体22が間隔をあけて並列に配置されており、
溶接などによって一体に固定して設けられている。
In the figure, reference numeral 21 denotes a fixed shaft (FIG. 4) which is integrally provided at the upper end of the bucket and penetrates two left and right protrusions (4a in FIG. 4) connected to the hydraulic cylinder via an arm. FIG. 1 which is rotatably fitted to and supported by 4b) of FIG.
(A) is a hollow cylindrical boss portion, and two plate-like support members 22 are arranged in parallel at an interval vertically below and in contact with the peripheral surface of the bottom of the boss portion 21. Has been
It is fixed and provided integrally by welding or the like.

【0023】そしてこれらの二枚の板状支持体22の紙
面に対して直角方向の長さは、図1(b)の側面図に示
すように、図で水平方向の円筒状のボス部21の両端面
の長さと等しく形成される。
The length of these two plate-like supports 22 in the direction perpendicular to the plane of the paper is, as shown in the side view of FIG. Are formed equal in length to both end faces.

【0024】上記並列配置された円筒状ボス部21の底
部と一体に固定された二枚の板状支持体22を貫通する
ように図面上で水平方向にリンクピン23が固定して設
けられており、該リンクピン23に回動自在に支持さ
れ、内部に図面上で垂直軸方向の回転を支持するボール
ベアリング24を内蔵したボールベアリングスイベル2
5の上部突出部25aが設けられている。
A link pin 23 is fixedly provided horizontally in the drawing so as to pass through two plate-like supports 22 integrally fixed to the bottoms of the cylindrical boss portions 21 arranged in parallel. And a ball bearing swivel 2 having a built-in ball bearing 24 rotatably supported by the link pin 23 and supporting rotation in the vertical axis direction in the drawing.
5 upper protrusions 25a are provided.

【0025】更に、上記ボールベアリングスイベル25
の内部のボールベアリング24には、フック26の上部
軸部26aが固定して取り付けられており、また該フッ
ク26の開口部には外れ止め部材27が外方へ突出しな
いように上部でピン止め27aによって止められてい
る。
Further, the ball bearing swivel 25
The upper shaft portion 26a of the hook 26 is fixedly attached to the ball bearing 24 inside. The hooking member 26 is pinned to the opening of the hook 26 at the upper portion so as not to protrude outward. Stopped by 27a.

【0026】図2は本発明の別の実施形態を示す図1と
同様のクレーン仕様パワーショベルに取り付けられる主
として小型のフックセットを示し、(a)は正面断面
図、(b)は要部側面図であり、図中、図1に記載した
符号と同一の符号は同一ないし同類部分を示すものとす
る。このもの(図2)は、図1に示すようにボールベア
リングスイベル25がボールベアリングの外側のケーシ
ング24aを、外側から嵌合するようにしてビス24b
で固定するようにしたのに比べて、ボールベアリングス
イベル25の下部が、ボールベアリング24を内蔵した
ボールベアリングの外側ケーシング24aと接合するよ
うにして、ビス24bで結合されるように構成されてい
る。
FIGS. 2A and 2B mainly show a small hook set attached to a crane type power shovel similar to FIG. 1 showing another embodiment of the present invention, wherein FIG. 2A is a front sectional view, and FIG. It is a figure, and in the figure, the same code | symbol as the code | symbol described in FIG. 1 shall show the same or similar part. In this case (FIG. 2), as shown in FIG. 1, the ball bearing swivel 25 engages the casing 24a outside the ball bearing from the outside so that the screw 24b is fitted.
The lower part of the ball bearing swivel 25 is connected to the outer casing 24a of the ball bearing in which the ball bearing 24 is built in, and the lower part of the ball bearing swivel 25 is connected with the screw 24b as compared with the case of fixing with the screw 24b. .

【0027】次に作用について説明すると、本発明によ
るフックセット20(図1、2)を図3〜図4に示すバ
ケット4の上端部に一体となって設けられ、油圧シリン
ダ3aにバケットリンク3bを介して連接された左右二
個の突出部4aを貫通する固定軸4bに取り付けるに当
たり、当該フックセット20の図1、2に示された最上
部の円筒状ボス部21の内径穴21aを上記固定軸4b
に回動自在に嵌合して支持される。
Next, the operation will be described. The hook set 20 (FIGS. 1 and 2) according to the present invention is provided integrally with the upper end of the bucket 4 shown in FIGS. When attaching the hook set 20 to the fixed shaft 4b penetrating the two left and right protrusions 4a connected via the inner hole 21a of the uppermost cylindrical boss portion 21 of the hook set 20 shown in FIGS. Fixed shaft 4b
Are rotatably fitted and supported.

【0028】次いで、最下部のフック26に品物(荷重
物)に固定された吊り具の上端部を係止し、パワーショ
ベルを運転状態にして、図3のブーム2及びアーム3及
び油圧シリンダ3aを駆動して、バケット4によってク
レーン仕様として作動させると、正規の吊り上げ時には
従来品と同様な問題は生じない。即ち、品物による捩れ
運動はボールベアリングスイベルによって吸収されるか
らである。
Next, the upper end of the hanging member fixed to the article (load) is locked to the lowermost hook 26, the power shovel is operated, and the boom 2, arm 3 and hydraulic cylinder 3a shown in FIG. Is driven to operate as a crane by the bucket 4, the same problem as the conventional product does not occur at the time of normal lifting. That is, the torsional motion of the article is absorbed by the ball bearing swivel.

【0029】ところが品物を斜め方向に引いて、パワー
ショベルが旋回または走行する場合、図5に示す従来品
においては、紙面に直角方向の曲げ作用を司るピンが、
二個(10及び12)ベアリングスイベルの両端にそれ
ぞれ設けられるため、フックの回転角度によって前記し
たようにフックに近い側のピン12が円滑に作動しない
ことがあり、この場合、ボス6に近いピン10に偏荷重
が掛かりピン折れが発生することが度々見られた。また
この場合、二本のピン10、12は、構造上太さ(直
径)に制限があり且つ、図6に示すようにせん断応力の
掛かる部分が多かった。また、小型機械はシャンクカッ
プリングの回り止めナット8の代わりに用いられる回り
止めピン8aが細いため、折損する恐れが多かった。
However, in the case where the power shovel turns or runs by pulling an article in an oblique direction, in the conventional article shown in FIG. 5, a pin that performs a bending action in a direction perpendicular to the paper surface is provided.
Since the two (10 and 12) bearing swivels are respectively provided at both ends, the pin 12 near the hook may not operate smoothly due to the rotation angle of the hook as described above. It was frequently observed that an eccentric load was applied to 10 and pin breakage occurred. Further, in this case, the two pins 10 and 12 were limited in thickness (diameter) in terms of structure, and many portions were subjected to shear stress as shown in FIG. Further, in the small-sized machine, since the detent pin 8a used in place of the detent nut 8 of the shank coupling is thin, there is a high possibility of breakage.

【0030】これに対し、本発明のものでは、図1、2
において紙面に沿った揺動運動が、最上部の円筒状ボス
部21とボス穴21aを貫通するバケット4側の固定軸
4b(図4)とによって円滑に行われ、また紙面に対し
て直角方向の揺動運動は、上記ボス部21の底部に一体
に固定された二個の並列に配置された板状支持体22を
貫通するリンクピン23と、該ピン23に回動自在に嵌
合支持されたボールベアリングスイベル25の上部突出
部25aとによって、円滑に行われるようになってい
る。
On the other hand, in the case of the present invention, FIGS.
, The swinging motion along the plane of the paper is smoothly performed by the uppermost cylindrical boss portion 21 and the fixed shaft 4b (FIG. 4) of the bucket 4 penetrating through the boss hole 21a, and in a direction perpendicular to the plane of the paper. The rocking motion of the link pin 23 penetrates two parallel plate-like supports 22 integrally fixed to the bottom of the boss portion 21 and is rotatably fitted to and supported by the pin 23. With the upper projecting portion 25a of the ball bearing swivel 25, the operation is performed smoothly.

【0031】上記のように直角方向の二つの揺動運動
は、それぞれバケット側の強度の大きい固定軸4bと、
フックセット側の円筒状のボス部21との嵌合作用及
び、上記円筒状のボス部21の底部に一体に並列配置し
て固定された二個の支持体22を貫通する一定の太さを
有するリンクピン23と、ベアリングスイベル上部突出
部25aとの嵌合作用の二箇所により、円滑に行われ、
従来品に比べて構造が簡単なため、強度を強く構成する
ことが可能となる。また、せん断応力を受ける箇所も少
ない。従って前記した従来品で起こりがちであった各種
のトラブルを解消することが可能である。
As described above, the two swinging motions in the right-angle direction are performed by the fixed shaft 4b having a high strength on the bucket side, and
The fitting action with the cylindrical boss portion 21 on the hook set side, and a constant thickness penetrating the two support members 22 arranged and fixed integrally in parallel on the bottom of the cylindrical boss portion 21 are provided. The link pin 23 and the bearing swivel upper protruding portion 25a are fitted smoothly to each other by two places of the fitting action,
Since the structure is simpler than that of a conventional product, it is possible to increase the strength. Also, there are few places where shear stress is applied. Therefore, it is possible to eliminate various troubles that are likely to occur in the above-mentioned conventional products.

【0032】なお、上記したこの実施形態(図1、2)
においてバケット4の上端部に水平方向に固定して設け
られる固定軸4bに回動自在に支持して設けられるボス
部21を、中空円筒材を形成し且つ、該ボス部21の底
部の下方に設けられる二個の支持体22を、それぞれ板
状に形成して一体に固定して設けた構造について説明し
たが、上記ボス部21は内径穴21aに挿通される固定
軸4bによって、回動自在に支持されるものであればよ
く、外周部が必ずしも円筒状でなくてもよい。また該ボ
ス部21の底部の下方に設けられる二個の支持体は、板
状体とは限らないことは勿論である。
The above embodiment (FIGS. 1 and 2)
A boss 21 rotatably supported by a fixed shaft 4b fixed to the upper end of the bucket 4 in a horizontal direction is formed into a hollow cylindrical member, and is provided below the bottom of the boss 21. Although the structure in which the two support members 22 provided are formed in a plate shape and fixed integrally is described, the boss portion 21 is rotatable by the fixed shaft 4b inserted into the inner diameter hole 21a. The outer peripheral portion may not necessarily be cylindrical. Of course, the two supports provided below the bottom of the boss 21 are not limited to plate-like bodies.

【0033】[0033]

【発明の効果】以上説明したように、本発明によれば、
パワーシャベルのブームに連結されるアームの端部に、
油圧操作によって回動されるバケットを設け、該バケッ
トの外側端部にフックセットを取付けて、クレーン仕様
を可能としたパワーシャベルにおいて、上記アーム端部
に回動可能に取付けられたバケットの上端部に一体に設
けられ油圧シリンダにバケットリンクを介して連接され
た左右二個の突出部を貫通して、水平方向に軸を固定し
て設け、該固定軸にボス部を回動自在に支持して設け、
該水平方向のボス部の底部の下方に、上記固定軸に対し
て垂直方向に二個の支持体を間隔を空けて並列配置し且
つ一体に設け、該並列に配置された二個の支持体を貫通
してリンクピンを固定して設け、該リンクピンに回動自
在に支持され、内部に垂直軸線方向の回転を支持するボ
ールベアリングを収納したボールベアリングスイベルを
設け、上記内部のボールベアリングによって、上部軸部
を支持したフックを連結して設けるようにしたことによ
り、直角方向の二つの揺動運動は、それぞれバケット側
の強度の大きい固定軸とフックセット側の円筒状のボス
部との嵌合作用及び、上記円筒状のボス部の底部に一体
に並列に配置して固定された二個の支持体22を貫通す
る一定の太さを有するリンクピン23とベアリングスイ
ベル上部突出部25aとの嵌合作用の二箇所により円滑
に行われ、従来品に比べて構造が簡単なため、強度を強
く構成することが可能となる。またせん断応力を受ける
箇所も少ない。ゆえに前記従来品で起こりがちであった
各種のトラブルを解消することが可能である。
As described above, according to the present invention,
At the end of the arm connected to the boom of the power shovel,
An upper end of a bucket rotatably attached to the arm end of a power shovel provided with a bucket pivoted by hydraulic operation and a hook set attached to an outer end of the bucket to enable crane specification. The left and right protrusions connected to the hydraulic cylinder via a bucket link are provided integrally with the hydraulic cylinder, and the shaft is fixedly provided in the horizontal direction, and the boss is rotatably supported on the fixed shaft. Provided
Below the bottom of the horizontal boss portion, two support members are arranged in parallel in a direction perpendicular to the fixed axis at an interval and integrally provided, and the two support members arranged in parallel A ball bearing swivel is provided which is fixedly provided with a link pin, is rotatably supported by the link pin, and houses therein a ball bearing which supports rotation in the vertical axis direction. The hooks supporting the upper shaft portion are connected and provided, so that the two swinging motions in the perpendicular direction are caused by the strong shaft on the bucket side and the cylindrical boss portion on the hook set side. A link pin 23 having a constant thickness penetrating the two support members 22 arranged and fixed integrally and in parallel to the bottom of the cylindrical boss portion, and the upper portion 2 of the bearing swivel and the fitting swivel. Smoothly performed by two positions for fitting cooperation with a, since the structure is simple as compared with the conventional products, it is possible to constitute a strong intensity. There are also few places where shear stress is applied. Therefore, it is possible to eliminate various troubles that are likely to occur in the conventional product.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施形態を示し(a)は正面断面図、
(b)は要部側面図である。
1A and 1B show an embodiment of the present invention, and FIG.
(B) is a side view of a main part.

【図2】本発明は他の実施形態を示し(a)は正面断面
図、(b)は要部側面図である。
FIGS. 2A and 2B show another embodiment of the present invention, wherein FIG. 2A is a front sectional view, and FIG.

【図3】(a)は従来のクレーン仕様パワーショベルの
概略説明図であり、(b)は(a)の要部拡大側面図で
ある。
3 (a) is a schematic explanatory view of a conventional crane-type power shovel, and FIG. 3 (b) is an enlarged side view of a main part of FIG. 3 (a).

【図4】従来のクレーン仕様パワーショベルのフックセ
ットを示した正面図である。
FIG. 4 is a front view showing a hook set of a conventional crane-type power shovel.

【図5】図4のフックセットの使用例を示す側面図であ
る。
FIG. 5 is a side view showing an example of use of the hook set of FIG. 4;

【図6】従来品のフックセット部の要部を示した図面で
ある。
FIG. 6 is a view showing a main part of a hook set part of a conventional product.

【符号の説明】 1 パワーショベル 2 ブーム 3 アーム 3a 油圧シリンダ 3b バケットリンク 4 バケット 4a 突出部 4b 固定軸 20 フックセット 21 ボス部 21a内径穴 22 支持体 23 リンクピン 24 ボールベアリング 24aボールベアリング外側ケーシング 24bビス 25 ボールベアリングスイベル 25aフックの上部軸部 26 フック 27 外れ止め部材 27aピン止め[Description of Signs] 1 Power shovel 2 Boom 3 Arm 3a Hydraulic cylinder 3b Bucket link 4 Bucket 4a Projection 4b Fixed shaft 20 Hook set 21 Boss 21a Inner hole 22 Support body 23 Link pin 24 Ball bearing 24a Ball bearing outer casing 24b Screw 25 Ball bearing swivel 25a Upper shaft of hook 26 Hook 27 Detachable member 27a Pinned

フロントページの続き (72)発明者 西岡 敏雄 石川県小松市串町工業団地1−3 株式会 社室戸鉄工所内 (72)発明者 坂下 敏彦 石川県小松市串町工業団地1−3 株式会 社室戸鉄工所内 Fターム(参考) 2D012 DA03 FA00 3F004 CB06 DA02 NA01 Continued on the front page (72) Inventor Toshio Nishioka 1-3 Kushimachi Industrial Park, Komatsu-shi, Ishikawa Pref. Inside Muroto Ironworks Co., Ltd. (72) Inventor Toshihiko Sakashita 1-3 Kushimachi Industrial Park, Komatsu-shi, Ishikawa Pref. Muroto Co., Ltd. F term in ironworks (reference) 2D012 DA03 FA00 3F004 CB06 DA02 NA01

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】パワーシャベルのブームに連結されるアー
ムの端部に、油圧操作によって回動されるバケットを設
け、該バケットの外側端部にフックセットを取付けて、
クレーン仕様を可能としたパワーシャベルにおいて、上
記アーム端部に回動可能に取付けられたバケットの上端
部に一体に設けられ油圧シリンダにバケットアームを介
して連接された左右二個の突出部を貫通して、水平方向
に軸を固定して設け、該固定軸にボス部を回動自在に支
持して設け、該水平方向のボス部の底部の下方に、上記
固定軸に対して垂直方向に二個の支持体を間隔を空けて
並列配置し且つ一体に設け、該並列に配置された二個の
支持体を貫通してリンクピンを固定して設け、該リンク
ピンに回動自在に支持され、内部に垂直軸線方向の回転
を支持するボールベアリングを収納したボールベアリン
グスイベルを設け、上記内部のボールベアリングによっ
て、上部軸部を支持したフックを連結して設けたことを
特徴とするクレーン仕様パワーショベルのフックセッ
ト。
A bucket which is turned by hydraulic operation is provided at an end of an arm connected to a boom of a power shovel, and a hook set is attached to an outer end of the bucket.
In a power shovel capable of crane specification, two left and right protrusions are provided integrally with the upper end of a bucket rotatably attached to the arm end and connected to a hydraulic cylinder via a bucket arm. Then, a shaft is provided fixedly in the horizontal direction, a boss is rotatably supported on the fixed shaft, and provided below the bottom of the boss in the horizontal direction, in a direction perpendicular to the fixed shaft. Two support members are arranged side by side at an interval and integrally provided, and a link pin is fixedly provided through the two support members arranged in parallel and rotatably supported on the link pin. And a ball bearing swivel containing a ball bearing for supporting rotation in the vertical axis direction is provided therein, and a hook for supporting an upper shaft portion is connected to the ball bearing by the internal ball bearing. Hook set of specifications power shovel.
【請求項2】バケットの上端部に水平方向に固定して設
けらる固定軸に回動自在に支持して設けられるボス部
を、中空円筒状に形成し、該ボス部の底部の下方に設け
られる二個の支持体を、それぞれ板状に形成して一体に
固定して設けたことを特徴とする請求項1に記載のクレ
ーン仕様パワーショベルのフックセット。
2. A boss portion rotatably supported on a fixed shaft provided in the upper end portion of the bucket and fixed in a horizontal direction is formed in a hollow cylindrical shape, and is provided below a bottom portion of the boss portion. The hook set for a crane-specific power shovel according to claim 1, wherein the two support members provided are each formed in a plate shape and fixed integrally.
JP11168893A 1999-06-15 1999-06-15 Hook set of power shovel having crane specifications Pending JP2000355483A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11168893A JP2000355483A (en) 1999-06-15 1999-06-15 Hook set of power shovel having crane specifications

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11168893A JP2000355483A (en) 1999-06-15 1999-06-15 Hook set of power shovel having crane specifications

Publications (2)

Publication Number Publication Date
JP2000355483A true JP2000355483A (en) 2000-12-26
JP2000355483A5 JP2000355483A5 (en) 2006-04-06

Family

ID=15876530

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11168893A Pending JP2000355483A (en) 1999-06-15 1999-06-15 Hook set of power shovel having crane specifications

Country Status (1)

Country Link
JP (1) JP2000355483A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101053901B1 (en) * 2009-01-22 2011-08-04 주식회사 흥진티엔디 Heavy Carrying Crane Wire Coupling Device
CN102530708A (en) * 2011-12-29 2012-07-04 重庆平伟实业股份有限公司 Lifting device
CN105858454A (en) * 2016-06-21 2016-08-17 合肥市神雕起重机械有限公司 Conveniently swerved crane hook
JP2016175769A (en) * 2015-03-23 2016-10-06 株式会社日立産機システム Electric chain block
CN110510511A (en) * 2019-07-11 2019-11-29 国家深海基地管理中心 A kind of lifting jettison system for ocean scientific investigation equipment field operation
KR20210055219A (en) * 2019-11-07 2021-05-17 주식회사 브랜드뉴 Quick coupler with commonality for excavator
CN113213328A (en) * 2021-04-30 2021-08-06 郑煤集团(河南)白坪煤业有限公司 Hoisting mechanism for mining equipment
CN115286122A (en) * 2022-06-23 2022-11-04 南通佳景健康科技股份有限公司 Sterilization and scale removal device embedded into water circulation loop for hydrotherapy equipment
CN117856136A (en) * 2024-03-07 2024-04-09 温州市恒盛照明电器有限公司 High-voltage warning device and mounting tool thereof

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101053901B1 (en) * 2009-01-22 2011-08-04 주식회사 흥진티엔디 Heavy Carrying Crane Wire Coupling Device
CN102530708A (en) * 2011-12-29 2012-07-04 重庆平伟实业股份有限公司 Lifting device
JP2016175769A (en) * 2015-03-23 2016-10-06 株式会社日立産機システム Electric chain block
CN105858454A (en) * 2016-06-21 2016-08-17 合肥市神雕起重机械有限公司 Conveniently swerved crane hook
CN110510511A (en) * 2019-07-11 2019-11-29 国家深海基地管理中心 A kind of lifting jettison system for ocean scientific investigation equipment field operation
KR20210055219A (en) * 2019-11-07 2021-05-17 주식회사 브랜드뉴 Quick coupler with commonality for excavator
KR102323064B1 (en) 2019-11-07 2021-11-09 주식회사 브랜드뉴 Quick coupler with commonality for excavator
CN113213328A (en) * 2021-04-30 2021-08-06 郑煤集团(河南)白坪煤业有限公司 Hoisting mechanism for mining equipment
CN113213328B (en) * 2021-04-30 2022-08-02 郑煤集团(河南)白坪煤业有限公司 Hoisting mechanism for mining equipment
CN115286122A (en) * 2022-06-23 2022-11-04 南通佳景健康科技股份有限公司 Sterilization and scale removal device embedded into water circulation loop for hydrotherapy equipment
CN117856136A (en) * 2024-03-07 2024-04-09 温州市恒盛照明电器有限公司 High-voltage warning device and mounting tool thereof

Similar Documents

Publication Publication Date Title
CN108975244B (en) Tower drum turnover device and tower mounting system
JP2000355483A (en) Hook set of power shovel having crane specifications
JP5943697B2 (en) Anti-seismic insert anchor
CN202346581U (en) Cantilever type sling
CN201284195Y (en) Miniature crane
JP6309224B2 (en) Suspension structure and method of using the suspension structure
JP2001208033A (en) Shackle type hanger
JP2001019344A (en) Safety hook
JPH0861294A (en) Pump unit lifting device for pull-out type submerged motor pump
CN114321277B (en) Counterweight dismounting device and engineering machinery
CN214141238U (en) Modified crane hook tongue depressor
CN220376146U (en) Simple lifting device
CN220549885U (en) Movable hoisting mechanism for pipeline laying
CN210855058U (en) Lengthened arm, crane boom and crane
CN215755953U (en) Improved anti-swing hook for crane
CN217478858U (en) Crane hook
CN114104954B (en) Hoisting hook and hoisting equipment for furnace door
CN214298921U (en) Lifting appliance convenient to replace and capable of preventing lifting rope from being abraded
CN220412615U (en) Crane hook
CN218261535U (en) Central air conditioning hoist device
JPH0532399Y2 (en)
CN214527721U (en) Electric hoist
CN216549195U (en) Headstock lifts by crane auxiliary fixtures
CN211664543U (en) Hanging bracket for specially manufacturing large-scale hoisting equipment
CN215886024U (en) Flywheel housing hoisting tool

Legal Events

Date Code Title Description
A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060216

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060216

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20081121

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090128

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20090527