Prior art keywords
plant
shutdown
information
signal
setting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4638899A
Other languages
Japanese (ja)
Inventor
Shoichi Sasaki
尚一 佐々木
Yukihiro Usui
幸博 碓井
Mototsugu Nezu
基嗣 根津
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP4638899A priority Critical patent/JP2000242322A/en
Publication of JP2000242322A publication Critical patent/JP2000242322A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Abstract

PROBLEM TO BE SOLVED: To facilitate starting or stopping operation at the start or end of a training and to lighten the burden on a training instructor. SOLUTION: This training device is equipped with an operation console panel 1 for operation training operation, a simulation state setting device 3 for setting the simulation state of plant operation, a plant simulating device 4 which inputs the setting information and operation signal and simulates the plant state, a plant monitor device 5 which inputs the plant signal from the plant simulating device and monitors the plant state, a plant data display device 6 which inputs the plant information from the plant monitor device and displays plant data, a power unit 7 as a driving power source for those devices, and a shutdown means 8 which sends a shutdown indication to the simulation state setting device 3, plant simulating device 4, plant monitor device 5, and plant data display device 6 once a stop signal is inputted.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、発電所等のプラン
ト運転訓練のために使用される操作用制御盤、プラント
模擬装置並びにプラント監視装置等より構成されたプラ
ント運転訓練装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a plant operation training device comprising an operation control panel, a plant simulation device, a plant monitoring device, and the like used for plant operation training of a power plant or the like.

【0002】[0002]

【従来の技術】一般に火力・水力・原子力発電所等の発
電プラントの起動や停止操作、並びに事故時の操作訓練
において、プラント模擬機能やプラント監視機能を有す
るプラント運転訓練装置が使用されている。
2. Description of the Related Art In general, a plant operation training apparatus having a plant simulation function and a plant monitoring function is used for starting and stopping operations of a power plant such as a thermal power plant, a hydroelectric power plant, a nuclear power plant, and the like, and an operation training in an accident.

【0003】図22は従来のプラント運転訓練装置の概
略構成を示すもので、1は運転訓練操作を行う操作制御
盤、2はこの操作制御盤1からの操作信号を入力並びに
操作制御盤1へプラント信号を出力する信号入出力装
置、3はプラント運転の模擬状態を設定する模擬状態設
定装置である。
FIG. 22 shows a schematic configuration of a conventional plant operation training apparatus, wherein 1 is an operation control panel for performing operation training operation, and 2 is an operation signal input from the operation control panel 1 and transmitted to the operation control panel 1. A signal input / output device 3 for outputting a plant signal is a simulation state setting device for setting a simulation state of plant operation.

【0004】また、4はこの模擬状態設定装置3からの
設定情報と信号入出力装置2からの操作信号を入力して
プラント状態を模擬し、そのプラント信号を信号入出力
装置2へ出力するプラント模擬装置、5はプラント模擬
装置4からのプラント信号を入力してプラントを監視す
るプラント監視装置、6はプラント監視装置5からのプ
ラント情報を入力してプラントデータの表示を行うプラ
ントデータ表示装置である。
A plant 4 simulates a plant state by inputting setting information from the simulated state setting device 3 and an operation signal from the signal input / output device 2, and outputs the plant signal to the signal input / output device 2. A simulation device 5 is a plant monitoring device that receives a plant signal from the plant simulation device 4 to monitor the plant, and 6 is a plant data display device that receives plant information from the plant monitoring device 5 and displays plant data. is there.

【0005】これら操作制御盤1、信号入出力装置2、
模擬状態設定装置3、プラント模擬装置4、プラント監
視装置5及びプラントデータ表示装置6は、電源装置7
から各々駆動電源を得て、実際のプラントの中央操作室
にて稼働している制御盤や制御装置を忠実に模擬し、実
際のプラントと違和感なく訓練が実施できるようにして
いる。
The operation control panel 1, the signal input / output device 2,
The simulation state setting device 3, the plant simulation device 4, the plant monitoring device 5, and the plant data display device 6 include a power supply device 7
From each other, and faithfully simulate the control panels and control devices operating in the central operation room of the actual plant, so that training can be performed without feeling uncomfortable with the actual plant.

【0006】また、模擬状態設定装置3とプラント模擬
装置4では、任意のプラント状態や予め準備されたプラ
ント事故の模擬の設定操作を容易にし、プラントの起動
停止から事故時訓練までの幅広い訓練が実施できるよう
にしている。
The simulated state setting device 3 and the plant simulating device 4 facilitate setting operation for simulating an arbitrary plant state or a previously prepared plant accident, and provide a wide range of training from starting and stopping of the plant to training at the time of an accident. So that it can be implemented.

【0007】[0007]

【発明が解決しようとする課題】このように従来のプラ
ント運転訓練装置では、模擬状態設定、プラント模擬、
プラント監視、プラントデータ表示の機能が各々独立し
た装置で構成されており、訓練終了時には訓練指導員が
装置別にシャットダウン操作を実施した後に電源の切断
操作を行っていた。
As described above, in the conventional plant operation training apparatus, the simulation state setting, the plant simulation,
The functions of plant monitoring and plant data display are each configured by an independent device, and at the end of training, a training instructor performs a shutdown operation for each device and then performs a power-off operation.

【0008】同様に訓練開始時においては、訓練開始時
間の前に電源の投入と装置の起動操作を行うなど、訓練
指導員の訓練以外での拘束時間を増加させており、プラ
ント運転訓練装置の停止操作の時間短縮と簡易化を行う
ことが必要であった。
Similarly, at the start of the training, the restraint time other than the training of the training instructor is increased by, for example, turning on the power and activating the apparatus before the training start time. It was necessary to shorten and simplify the operation.

【0009】さらに、電源投入切断の順序や手順の複雑
さ等の理由により、各装置を24時間連続稼働している
場合もあり、保安上の問題から警備員による夜間巡回や
24時間連続稼働に伴う電気使用料等の資金面での負担
もあり、電源投入切断の順序や手順の改善を行うことが
必要であった。
Further, there are cases where each device is operated continuously for 24 hours due to the order of turning on and off the power supply and the complexity of the procedure. There was also a financial burden such as electricity usage fees, and it was necessary to improve the order and procedure of turning on and off the power.

【0010】しかしながら、上記の課題を実現するに
は、相当する設備といったハード的要素や、実現に向け
ての方法、技術等のソフト的要素をうまく組み合わせる
ことが難しく、実現されていなかった。
However, in order to realize the above-mentioned problems, it has been difficult to properly combine hardware elements such as corresponding equipment and software elements such as a method and a technique for realizing the same, and it has not been realized.

【0011】本発明は上記のような事情に鑑みてなされ
たもので、訓練開始又は終了時における起動又は停止操
作の簡易化と訓練指導員の負荷の軽減を図ることができ
るプラント運転訓練装置を提供することを目的とする。
The present invention has been made in view of the above circumstances, and provides a plant operation training apparatus capable of simplifying a start or stop operation at the start or end of training and reducing the load on a training instructor. The purpose is to do.

【0012】[0012]

【課題を解決するための手段】本発明は上記の目的を達
成するため、次のような手段によりプラント運転訓練装
置を構成する。
According to the present invention, in order to achieve the above object, a plant operation training apparatus is constituted by the following means.

【0013】請求項1に対応する発明は、運転訓練操作
を行う操作制御手段と、プラント運転の模擬状態を設定
する模擬状態設定手段と、この模擬状態設定手段からの
設定情報と前記操作制御手段からの操作信号を入力して
プラント状態を模擬するプラント模擬手段と、このプラ
ント模擬手段からのプラント信号を入力してプラント状
態を監視するプラント監視手段と、このプラント監視手
段からのプラント情報を入力してプラントデータの表示
を行うプラントデータ表示手段と、これら操作制御手
段、模擬状態設定手段、プラント模擬手段、プラント監
視手段及びプラントデータ表示手段の駆動電源となる電
源装置と、停止信号が入力されると模擬状態設定手段と
プラント模擬手段及びプラント監視手段とプラントデー
タ表示手段にそれぞれシャットダウン指示を行うシャッ
トダウン手段とを備える。
[0013] The invention corresponding to claim 1 is an operation control means for performing a training operation, a simulated state setting means for setting a simulated state of plant operation, setting information from the simulated state setting means, and the operation control means. A plant simulation means for simulating a plant state by inputting an operation signal from the plant, a plant monitoring means for monitoring a plant state by inputting a plant signal from the plant simulation means, and a plant information input from the plant monitoring means Plant data display means for displaying plant data, a power supply device serving as a driving power source for these operation control means, simulation state setting means, plant simulation means, plant monitoring means and plant data display means, and a stop signal. Then, the simulation state setting means, the plant simulation means, the plant monitoring means, and the plant data display means respectively. And a shutdown means to shut down instruction.

【0014】請求項2に対応する発明は、運転訓練操作
を行う操作制御手段と、プラント運転の模擬状態を設定
する模擬状態設定手段と、この模擬状態設定手段からの
設定情報と前記操作制御手段からの操作信号を入力して
プラント状態を模擬するプラント模擬手段と、このプラ
ント模擬手段からのプラント信号を入力してプラント状
態を監視するプラント監視手段と、このプラント監視手
段からのプラント情報を入力してプラントデータの表示
を行うプラントデータ表示手段と、これら操作制御手
段、模擬状態設定手段、プラント模擬手段、プラント監
視手段及びプラントデータ表示手段の駆動電源となる電
源装置と、停止信号が入力されると模擬状態設定手段、
前記プラント模擬手段、プラント監視手段、プラントデ
ータ表示手段のいずれかにシャットダウン指示を行うシ
ャットダウン手段とを備え、前記模擬状態設定手段、前
記プラント模擬手段、プラント監視手段、プラントデー
タ表示手段はシャットダウン指示を受けると停止処理を
すると共に、シャットダウン指示を行う機能を持たせ
て、最初にシャットダウン指示を受けたものから最後ま
で順次シャットダウン指示を出して停止処理を行うよう
にしたものである。
According to a second aspect of the present invention, there is provided an operation control means for performing an operation training operation, a simulated state setting means for setting a simulated state of plant operation, setting information from the simulated state setting means, and the operation control means. A plant simulation means for simulating a plant state by inputting an operation signal from the plant, a plant monitoring means for monitoring a plant state by inputting a plant signal from the plant simulation means, and a plant information input from the plant monitoring means Plant data display means for displaying plant data, a power supply device serving as a driving power source for these operation control means, simulation state setting means, plant simulation means, plant monitoring means and plant data display means, and a stop signal. And simulation state setting means,
The plant simulation means, the plant monitoring means, and a shutdown means for giving a shutdown instruction to any of the plant data display means, wherein the simulation state setting means, the plant simulation means, the plant monitoring means, and the plant data display means output a shutdown instruction. Upon receipt of the shutdown instruction, a shutdown instruction is provided and a function of issuing a shutdown instruction is provided. The shutdown instruction is sequentially issued from the first shutdown instruction to the last shutdown instruction, and the shutdown processing is performed.

【0015】上記請求項1及び請求項2に対応する発明
のプラント運転訓練装置にあっては、模擬状態設定手
段、前記プラント模擬手段、プラント監視手段、プラン
トデータ表示手段がシャットダウン指示を受けると所定
の処理を行って停止するので、訓練指導員は個々の構成
要素の存在を意識することなく停止を行うことが可能と
なる。
In the plant operation training apparatus according to the first and second aspects of the present invention, when the simulated state setting means, the plant simulating means, the plant monitoring means, and the plant data display means receive a shutdown instruction, the predetermined state is set. Then, the training instructor can perform the stop without being conscious of the existence of the individual components.

【0016】請求項3に対応する発明は、請求項1に対
応する発明のプラント運転訓練装置において、シャット
ダウン手段に起動又は停止信号が入力されると前記電源
装置に電源投入又は切断指示を行う機能を持たせて前記
電源装置の電源投入又は切断を行うようにしたものであ
る。
According to a third aspect of the present invention, in the plant operation training apparatus according to the first aspect of the present invention, a function of instructing the power supply to turn on or off when a start or stop signal is input to the shutdown means. The power supply of the power supply device is turned on or off.

【0017】請求項4に対応する発明は、請求項3に対
応する発明のプラント運転訓練装置において、前記電源
装置に対して電源の投入と切断指示を行う機能を持た
せ、且つ時限装置を付加して予め設定された時間を経過
すると装置毎の電源に対して切断と投入を行う機能を持
たせたものである。
According to a fourth aspect of the present invention, in the plant operation training apparatus according to the third aspect of the present invention, a function of instructing the power supply to turn on and off the power is provided, and a time limiter is added. Then, after a preset time has elapsed, a function of turning off and on the power supply of each device is provided.

【0018】上記請求項3及び請求項4に対応する発明
のプラント運転訓練装置にあっては、シャットダウン手
段から電源装置に対して電源投入又は切断の指示を行う
ため、24時間連続稼働の必要がなく、保守上の夜間巡
回や設備不使用時の不要な電気料の削減を図ることがで
きる。
In the plant operation training apparatus according to the third and fourth aspects of the present invention, it is necessary to operate continuously for 24 hours since the shutdown means instructs the power supply to turn on or off the power supply. In addition, unnecessary electricity charges can be reduced when patrol at night for maintenance or when equipment is not used.

【0019】請求項5に対応する発明は、請求項3に対
応する発明のプラント運転訓練装置において、シャット
ダウン手段から各装置のシャットダウン状態の情報を入
力し、その状態情報を表示する装置状態表示手段を設け
たものである。
According to a fifth aspect of the present invention, in the plant operation training apparatus according to the third aspect of the present invention, information on a shutdown state of each device is inputted from the shutdown means and the state information is displayed. Is provided.

【0020】上記請求項5に対応する発明のプラント運
転訓練装置にあっては、装置状態表示手段はシャットダ
ウン手段から各装置のシャットダウン指示状況と電源装
置への停止通知の状況情報を入力し、その停止結果を含
む情報が訓練指導員に提供されるので、停止処理状況の
確認が容易になる。
In the plant operation training apparatus according to the fifth aspect of the invention, the apparatus state display means inputs the shutdown instruction state of each apparatus and the state information of the stop notification to the power supply apparatus from the shutdown means. Since the information including the stop result is provided to the training instructor, it is easy to check the stop processing status.

【0021】請求項6に対応する発明は、請求項3に対
応する発明のプラント運転訓練装置において、装置を個
別にシャットダウンするための装置指定情報を入力し、
この情報をシャットダウン手段に停止信号として出力す
る装置指定手段を設けたものである。
According to a sixth aspect of the present invention, in the plant operation training apparatus according to the third aspect of the present invention, device designation information for individually shutting down the devices is input,
A device designating means for outputting this information as a stop signal to the shutdown means is provided.

【0022】上記請求項6に対応する発明のプラント運
転訓練装置にあっては、個別の装置を指定して停止信号
を入力するのみで、指定された装置のシャットダウンが
実行されるため、保守等でその装置のみ停止させたい場
合の停止操作が容易になる。
In the plant operation training apparatus according to the sixth aspect of the present invention, the shutdown of the designated apparatus is executed only by designating the individual apparatus and inputting the stop signal. Thus, the stop operation when only the device is to be stopped is facilitated.

【0023】請求項7に対応する発明は、請求項3に対
応する発明のプラント運転訓練装置において、予め決め
られた時刻に起動したり、停止させるための設定情報が
入力され、且つ現在時刻が設定時刻に合致したとき前記
シャットダウン手段に起動又は停止要求を通知するスケ
ジュール管理手段を設けたものである。
According to a seventh aspect of the present invention, in the plant operation training apparatus according to the third aspect, setting information for starting or stopping at a predetermined time is input, and the current time is set. A schedule management means is provided for notifying the shutdown means of a start or stop request when the time coincides with the set time.

【0024】上記請求項7に対応する発明のプラント運
転訓練装置にあっては、起動時刻と停止時刻を設定する
ことで、タイマにより自動的に起動したり、停止したり
できるため、訓練実施日の起動や停止操作が容易にな
る。
In the plant operation training apparatus according to the present invention, since the start time and the stop time are set, the start and stop can be automatically performed by the timer. Start and stop operations become easier.

【0025】請求項8に対応する発明は、請求項7に対
応する発明のプラント運転訓練装置において、前記スケ
ジュール管理手段により設定した停止時刻に到達する前
に停止時刻が間近であることを表示装置へ通知する事前
通知処理手段を設けたものである。
According to an eighth aspect of the present invention, in the plant operation training apparatus according to the seventh aspect of the present invention, the display device indicates that the stop time is approaching before reaching the stop time set by the schedule management means. In advance is provided.

【0026】上記請求項8に対応する発明のプラント運
転訓練装置にあっては、設定した停止時刻を記憶してい
なくても、停止時刻の前に事前通知することでタイマに
よる停止操作の利便性が向上する。
In the plant operation training apparatus according to the present invention, even if the set stop time is not stored, the stop operation by the timer can be performed by giving a notice in advance before the stop time. Is improved.

【0027】請求項9に対応する発明は、請求項8に対
応する発明のプラント運転訓練装置において、前記事前
通知処理手段からの停止時刻の事前通知により、時間情
報を入力し前記スケジュール管理手段に停止時刻の延長
を通知する停止時間延長手段を設けたものである。
According to a ninth aspect of the present invention, in the plant operation training apparatus according to the eighth aspect of the present invention, time information is inputted by the advance notification of the stop time from the advance notification processing means, and the schedule management means is provided. Is provided with a suspension time extension means for notifying the extension of the suspension time.

【0028】上記請求項9に対応する発明のプラント運
転訓練装置にあっては、スケジュール管理手段により設
定した停止時刻をいちいち変更することなく、プラント
運転訓練の実施状況に応じて停止時刻の延長が可能であ
り、タイマによる停止操作の利便性がさらに向上する。
In the plant operation training apparatus according to the ninth aspect of the present invention, the stop time can be extended according to the state of the plant operation training without changing the stop time set by the schedule management means. It is possible, and the convenience of the stop operation by the timer is further improved.

【0029】請求項10に対応する発明は、請求項7に
対応する発明のプラント運転訓練装置において、前記ス
ケジュール管理手段に停止時刻の延長を通知する停止時
間延長手段と、停止信号と設定情報と時間情報とを任意
に設定して遠隔送信するリモコン装置と、このリモコン
装置からの信号を受光して各情報により前記シャットダ
ウン手段と前記スケジュール管理手段と前記停止時間延
長手段に出力する信号受光手段とを設けたものである。
According to a tenth aspect of the present invention, in the plant operation training apparatus according to the seventh aspect of the present invention, a stop time extending means for notifying the schedule managing means of an extension of the stop time, a stop signal and setting information. A remote control device for arbitrarily setting time information and remotely transmitting the signal; a signal receiving unit for receiving a signal from the remote control device and outputting the information to the shutdown unit, the schedule management unit, and the stop time extension unit according to each information; Is provided.

【0030】上記請求項10に対応する発明のプラント
運転訓練装置にあっては、リモコン装置を使用すること
で、決められた装置とは別に情報特定をリモコン装置に
集約させることで、遠隔操作が可能となり、起動又は停
止操作が容易になる。
In the plant operation training apparatus according to the present invention corresponding to the tenth aspect, by using the remote control device, the information specification is collected in the remote control device separately from the determined device, so that the remote operation can be performed. It becomes possible, and starting or stopping operation becomes easy.

【0031】[0031]

【発明の実施の形態】以下本発明の実施の形態を図面を
参照して説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0032】図1は本発明によるプラント運転訓練装置
の第1の実施の形態を示すブロック図で、図22に示す
従来例の構成要素と同一部分には同一符号を付して示
す。
FIG. 1 is a block diagram showing a first embodiment of a plant operation training apparatus according to the present invention, in which the same components as those of the conventional example shown in FIG.

【0033】図1に示すプラント運転訓練装置は、運転
訓練操作を行う操作制御盤1と、操作制御盤1からの操
作信号を入力する信号入出力装置2と、プラント運転の
模擬状態を設定する模擬状態設定装置3と、模擬状態設
定装置3からの設定情報と信号入出力装置2からの操作
信号を入力してプラント状態を模擬し、そのプラント信
号を信号入出力装置2へ出力するプラント模擬装置4
と、プラント模擬装置4からのプラント信号を入力しプ
ラント監視するプラント監視装置5と、プラント監視装
置5からのプラント情報を入力しプラントデータの表示
を行うプラントデータ表示装置6と、これら操作制御盤
1、信号入出力装置2、模擬状態設定装置3、プラント
模擬装置4、プラント監視装置5及びプラントデータ表
示装置6の駆動電源となる電源装置7と、停止信号が入
力されると模擬状態設定装置3とプラント模擬装置4及
びプラント監視装置5とプラントデータ表示装置6にシ
ャットダウン指示を行うシャットダウン手段8とで構成
される。
The plant operation training apparatus shown in FIG. 1 sets an operation control panel 1 for performing an operation training operation, a signal input / output device 2 for inputting an operation signal from the operation control panel 1, and a simulated state of plant operation. Simulated state setting device 3, plant information that inputs setting information from the simulated state setting device 3 and operation signals from the signal input / output device 2 to simulate a plant state, and outputs the plant signal to the signal input / output device 2 Device 4
A plant monitoring device 5 for inputting a plant signal from the plant simulation device 4 and monitoring the plant; a plant data display device 6 for inputting plant information from the plant monitoring device 5 and displaying plant data; 1, a signal input / output device 2, a simulation state setting device 3, a plant simulation device 4, a power supply device 7 serving as a driving power source for a plant monitoring device 5 and a plant data display device 6, and a simulation state setting device when a stop signal is input. 3, a plant simulation device 4, a plant monitoring device 5, and a shutdown means 8 for giving a shutdown instruction to the plant data display device 6.

【0034】図2は上記シャットダウン手段8の一構成
例を示すもので、このシャットダウン手段8は停止信号
が入力される信号入力手段81と、各装置毎のシャット
ダウン手続きの情報が格納されている手続き情報格納部
82と、各装置へシャットダウン指示を出力するシャッ
トダウン指示手段83とで構成されている。
FIG. 2 shows an example of the configuration of the shutdown means 8. The shutdown means 8 includes a signal input means 81 to which a stop signal is input, and a procedure in which information on a shutdown procedure for each device is stored. The information storage unit 82 includes a shutdown instruction unit 83 that outputs a shutdown instruction to each device.

【0035】次に、上記構成のプラント運転訓練装置の
作用を図1及び図2を用いて説明する。
Next, the operation of the plant operation training apparatus having the above configuration will be described with reference to FIGS.

【0036】いま、操作制御盤1より訓練員の運転操作
を行った操作信号が信号入出力装置2を介してプラント
模擬装置4に入力されると、このプラント模擬装置4は
模擬状態設定装置3により設定されたプラント模擬情報
と操作信号をもとにプラント状態を模擬する。
Now, when an operation signal of the operation of the trainee from the operation control panel 1 is input to the plant simulation device 4 via the signal input / output device 2, the plant simulation device 4 The plant state is simulated based on the plant simulation information and the operation signal set by (1).

【0037】このプラント模擬装置4は、模擬したプラ
ント信号をプラント入出力装置2を介して操作制御盤1
に出力する。また、プラント模擬装置4からプラント信
号が、プラント監視装置5に入力されると、このプラン
ト監視装置5はプラント監視を行い、そのプラント情報
をプラントデータ表示装置6に与えることによりデータ
表示される。
The plant simulation device 4 transmits the simulated plant signal to the operation control panel 1 via the plant input / output device 2.
Output to Further, when a plant signal is input from the plant simulation device 4 to the plant monitoring device 5, the plant monitoring device 5 performs plant monitoring, and the data is displayed by giving the plant information to the plant data display device 6.

【0038】一方、シャットダウン手段8は図2に示す
ように停止信号が信号入力手段81に入力されると、こ
の停止信号をシャットダウン指示手段83に出力する。
この停止信号を受けたシャットダウン指示手段83は、
各装置毎のシャットダウン手続きの情報が格納されてい
る手続き情報格納部82より情報を取出し、図1に示す
模擬状態設定装置3とプラント模擬装置4及びプラント
監視装置5とプラントデータ表示装置6にシャットダウ
ン指示を行う。
On the other hand, when a stop signal is input to the signal input means 81 as shown in FIG. 2, the shutdown means 8 outputs this stop signal to the shutdown instruction means 83.
Upon receiving this stop signal, the shutdown instruction means 83
Information is taken out from the procedure information storage unit 82 in which information on the shutdown procedure for each device is stored, and shut down to the simulated state setting device 3, plant simulation device 4, plant monitoring device 5, and plant data display device 6 shown in FIG. Make instructions.

【0039】この場合、停止信号はスイッチ操作によっ
ても良いし、タイマスイッチ等によるものでも良い。
In this case, the stop signal may be generated by a switch operation or a timer switch.

【0040】従って、シャットダウン指示を受けた模擬
状態設定装置3とプラント模擬装置4及びプラント監視
装置5とプラントデータ表示装置6は、所定の処理を行
って順次停止する。
Accordingly, the simulation state setting device 3, the plant simulation device 4, the plant monitoring device 5, and the plant data display device 6, which have received the shutdown instruction, perform predetermined processing and sequentially stop.

【0041】このような構成のプラント運転訓練装置に
よれば、シャットダウン手段8へ停止信号を入力するの
みで、各装置毎のシャットダウン手続きが順次実施され
るので、訓練指導員は個々の装置の存在を意識すること
なく停止を行うことができ、訓練終了時の停止操作が容
易となる。
According to the plant operation training apparatus having such a configuration, the shutdown procedure for each apparatus is sequentially performed only by inputting a stop signal to the shutdown means 8, so that the training instructor determines whether each apparatus exists. The stop can be performed without being conscious, and the stop operation at the end of the training becomes easy.

【0042】図3は本発明によるプラント運転訓練装置
の第2の実施の形態を示すブロック図で、図1と同一構
成要素には同一符号を付してその説明を省略し、ここで
は異なる点についてのみ述べる。
FIG. 3 is a block diagram showing a second embodiment of the plant operation training apparatus according to the present invention. The same components as those in FIG. 1 are denoted by the same reference numerals, and description thereof will be omitted. Is described only.

【0043】第2の実施の形態では、図3に示すように
シャットダウン手段8に停止信号を入力した際に、模擬
状態設定装置3にシャットダウン指示を行い、その後は
模擬状態設定装置3からプラント模擬装置4、プラント
模擬装置4からプラント監視装置5、プラント監視装置
5からプラントデータ表示装置6へと順次シャットダウ
ン指示が行われるようにしたものである。
In the second embodiment, when a stop signal is input to the shutdown means 8 as shown in FIG. 3, a shutdown instruction is issued to the simulated state setting device 3, and thereafter, the simulated state setting device 3 sends a plant simulation. The shutdown instruction is sequentially issued from the device 4, the plant simulation device 4 to the plant monitoring device 5, and from the plant monitoring device 5 to the plant data display device 6.

【0044】このような構成のプラント運転訓練装置に
よれば、シャットダウン手段8へ停止信号の入力のみ
で、各装置毎のシャットダウン手続きが順次実施される
ので、訓練指導員は個々の装置の存在を意識することな
く停止を行うことが可能となり、訓練終了時の停止操作
が容易となる。
According to the plant operation training device having such a configuration, the shutdown procedure for each device is sequentially performed only by inputting the stop signal to the shutdown means 8, so that the training instructor is aware of the existence of each device. It is possible to stop without performing, and the stop operation at the end of training becomes easy.

【0045】図4は本発明によるプラント運転訓練装置
の第3の実施の形態を示すブロック図で、図1と同一構
成要素には同一符号を付してその説明を省略し、ここで
は異なる点についてのみ述べる。
FIG. 4 is a block diagram showing a third embodiment of the plant operation training apparatus according to the present invention. The same components as those in FIG. 1 are denoted by the same reference numerals, and description thereof will be omitted. Is described only.

【0046】第3の実施の形態では、図1と同様に停止
信号が入力されると模擬状態設定装置3とプラント模擬
装置4及びプラント監視装置5とプラントデータ表示装
置6にシャットダウン指示を行うシャットダウン手段8
に、さらに電源装置7に対して電源の投入と切断指示を
行う機能を持たせたものである。
In the third embodiment, when a stop signal is input as in FIG. 1, a shutdown instruction is issued to the simulation state setting device 3, the plant simulation device 4, the plant monitoring device 5, and the plant data display device 6 to perform a shutdown instruction. Means 8
In addition, a function of instructing the power supply 7 to turn on and off the power is provided.

【0047】図5は上記シャットダウン手段8の一構成
例を示すもので、このシャットダウン手段8は図2に示
す構成に加えて、起動/停止信号が入力されるとシャッ
トダウン指示手段83から信号種別に応じて、電源投入
/切断手段84に信号が通知され、電源装置7に対して
電源の投入と切断指示を行うものである。
FIG. 5 shows an example of the configuration of the above-described shutdown means 8. In addition to the configuration shown in FIG. In response, a signal is notified to the power on / off means 84, and the power on / off instruction is issued to the power supply device 7.

【0048】このような構成のプラント運転訓練装置に
よれば、第1の実施の形態と同様の作用効果が得られる
ことは勿論、シャットダウン手段8への停止信号の入力
のみで、各装置の電源の投入と切断が順次実行されるの
で、各装置毎の操作が不要となり、起動と停止操作が容
易となる。
According to the plant operation training apparatus having such a configuration, the same operation and effect as those of the first embodiment can be obtained, and of course, the power supply of each apparatus can be obtained only by inputting the stop signal to the shutdown means 8. Since the turning on and off are sequentially performed, the operation for each device is not required, and the starting and stopping operations are facilitated.

【0049】従って、24時間連続稼働の必要がなく、
保安上の夜間巡回や設備不使用時の不要な電気使用料の
削減を図ることができる。ここで、電源切断の指示の他
に電源投入の指示も可能である。
Therefore, there is no need to operate continuously for 24 hours.
It is possible to reduce unnecessary electricity usage charges during security night patrols and when equipment is not used. Here, in addition to the power-off instruction, a power-on instruction is also possible.

【0050】図6は本発明によるプラント運転訓練装置
の第4の実施の形態を示すブロック図で、図1と同一構
成要素には同一符号を付してその説明を省略し、ここで
は異なる点についてのみ述べる。
FIG. 6 is a block diagram showing a fourth embodiment of the plant operation training apparatus according to the present invention. The same components as those in FIG. 1 are denoted by the same reference numerals, and description thereof will be omitted. Is described only.

【0051】第4の実施の形態では、図4と同様に停止
信号が入力されると模擬状態設定装置3とプラント模擬
装置4及びプラント監視装置5とプラントデータ表示装
置6にシャットダウン指示を行うシャットダウン手段8
に、さらに電源装置7に対して電源の投入と切断指示を
行う機能を持たせ、且つ電源装置7にタイマリレー装置
16を加えて予め設定された時間或いは、リレー接点の
変化をトリガーとして装置毎の電源に対して切断と投入
を行う機能を持たせたものである。
In the fourth embodiment, when a stop signal is input in the same manner as in FIG. 4, a shutdown instruction is issued to the simulation state setting device 3, the plant simulation device 4, the plant monitoring device 5, and the plant data display device 6 to perform a shutdown instruction. Means 8
In addition, the power supply device 7 is provided with a function of instructing the power supply device to be turned on and off, and a timer relay device 16 is added to the power supply device 7 so that a predetermined time or a change in a relay contact is used as a trigger for each device. It has a function of turning off and on the power supply.

【0052】このような構成のプラント運転訓練装置に
よれば、シャットダウン手段8への起動又は停止信号の
入力のみで、各装置の電源の投入と切断が順次実行され
るため、各装置毎の操作が不要となり、起動と停止操作
が容易となる。
According to the plant operation training apparatus having such a configuration, the power-on and power-off of each apparatus is sequentially performed only by inputting the start or stop signal to the shutdown means 8, so that the operation of each apparatus is performed. Becomes unnecessary, and the starting and stopping operations are facilitated.

【0053】図7は本発明によるプラント運転訓練装置
の第5の実施の形態を示すブロック図で、図1と同一構
成要素には同一符号を付してその説明を省略し、ここで
は異なる点についてのみ述べる。
FIG. 7 is a block diagram showing a fifth embodiment of the plant operation training apparatus according to the present invention. The same components as those in FIG. 1 are denoted by the same reference numerals, and description thereof will be omitted. Is described only.

【0054】第5の実施の形態では、図4と同様に停止
信号が入力されると模擬状態設定装置3とプラント模擬
装置4及びプラント監視装置5とプラントデータ表示装
置6にシャットダウン指示を行うシャットダウン手段8
に、さらに電源装置7に対して電源の投入と切断指示を
行う機能を持たせ、且つ各装置のシャットダウン状況や
電源装置7の電源切断状況の情報を装置状態表示手段9
に出力する機能を持たせ、装置状態表示手段9に情報表
示させるようにしたものである。
In the fifth embodiment, when a stop signal is input in the same manner as in FIG. 4, a shutdown instruction is issued to the simulation state setting device 3, the plant simulation device 4, the plant monitoring device 5, and the plant data display device 6 to perform a shutdown instruction. Means 8
Has a function of instructing the power supply 7 to turn on and off the power supply, and displays information on the shutdown status of each device and the power off status of the power supply 7 to the device status display means 9.
To output information to the device status display means 9 for displaying information.

【0055】図8は上記シャットダウン手段8と装置状
態表示手段9の一構成例を示すもので、シャットダウン
手段8は図5に示す構成に加えて、シャットダウン指示
手段83から各装置シャットダウン状況や電源装置の電
源切断状況の情報を受けて、装置状態表示手段9へ出力
する装置状態情報出力手段85を備えている。また、装
置状態表示手段9は、置状態情報出力手段を85からの
装置状態情報を入力する装置状態情報入力手段91と、
その情報を受け表示装置に情報出力する装置状態情報表
示手段92とから構成されている。
FIG. 8 shows an example of the configuration of the above-mentioned shutdown means 8 and apparatus status display means 9. In addition to the configuration shown in FIG. The apparatus status information output means 85 receives the information on the power-off status of the apparatus and outputs the information to the apparatus status display means 9. Further, the device status display means 9 includes: a device status information input device 91 for inputting device status information from the device status information output device 85;
And a device status information display means 92 for receiving the information and outputting the information to a display device.

【0056】次に上記のように構成されたプラント運転
訓練装置の作用を図8により説明するに、ここでは図5
と異なる点についてのみ述べる。
Next, the operation of the plant operation training apparatus configured as described above will be described with reference to FIG.
Only the points that differ from are described.

【0057】シャットダウン指示手段83で実施したシ
ャットダウン指示や電源投入/切断指示等の装置状態情
報は装置状態情報出力手段85より装置状態表示手段9
の装置状態情報入力手段91に出力する。装置状態情報
入力手段91では、その情報を受けると装置状態情報表
示手段92に情報出力し、表示装置に各装置の状況並び
に結果情報を表示する。図9は装置状態表示手段により
表示される状態表示の一例を示している。
The apparatus status information such as the shutdown instruction and the power on / off instruction executed by the shutdown instruction means 83 is transmitted from the apparatus status information output means 85 to the apparatus status display means 9.
Is output to the device state information input means 91. Upon receiving the information, the device status information input means 91 outputs the information to the device status information display means 92, and displays the status and result information of each device on the display device. FIG. 9 shows an example of a status display displayed by the device status display means.

【0058】このような構成のプラント運転訓練装置に
よれば、装置状態表示手段により各装置シャットダウン
状況や電源装置を含めた各装置の電源の投入又は切断状
態が把握でき、起動と停止操作の処理状況の確認が容易
になる。
According to the plant operation training apparatus having such a configuration, the apparatus state display means can grasp the shutdown state of each apparatus and the power on / off state of each apparatus including the power supply apparatus. The status can be easily checked.

【0059】図10は本発明によるプラント運転訓練装
置の第6の実施の形態を示すブロック図で、図1と同一
構成要素には同一符号を付してその説明を省略し、ここ
では異なる点についてのみ述べる。
FIG. 10 is a block diagram showing a sixth embodiment of the plant operation training apparatus according to the present invention. The same components as those in FIG. 1 are denoted by the same reference numerals, and their description is omitted. Is described only.

【0060】第6の実施の形態では、図4と同様に停止
信号が入力されると模擬状態設定装置3とプラント模擬
装置4及びプラント監視装置5とプラントデータ表示装
置6にシャットダウン指示を行うシャットダウン手段8
に、さらに電源装置7に対して電源の投入と切断指示を
行う機能を持たせ、且つ各装置のシャットダウン状況や
電源装置7の電源切断状況の情報を装置状態表示手段9
に出力する機能を持たせ、さらにシャットダウンしたい
装置の装置指定情報が入力されると、その情報をシャッ
トダウン手段8に出力する装置指定手段10を設けたも
のである。
In the sixth embodiment, when a stop signal is input in the same manner as in FIG. 4, a shutdown instruction is issued to the simulation state setting device 3, the plant simulation device 4, the plant monitoring device 5, and the plant data display device 6 to perform a shutdown instruction. Means 8
Has a function of instructing the power supply 7 to turn on and off the power supply, and displays information on the shutdown status of each device and the power off status of the power supply 7 to the device status display means 9.
And a device specifying means 10 for outputting the information to the shutdown means 8 when the device specifying information of the device to be shut down is input.

【0061】図11は上記シャットダウン手段8と装置
状態表示手段9及び装置指定手段10の一構成例を示す
もので、図8の構成に加えて設けられた装置指定手段1
0は装置指定情報が入力される装置指定入力手段101
と、その情報からシャットダウン手段8にシャットダウ
ン信号を出力するシャットダウン信号出力手段102と
から構成されている。
FIG. 11 shows an example of the configuration of the shutdown means 8, the apparatus status display means 9 and the apparatus designating means 10. The apparatus designating means 1 provided in addition to the configuration of FIG.
0 is a device designation input unit 101 to which device designation information is inputted
And a shutdown signal output unit 102 that outputs a shutdown signal to the shutdown unit 8 based on the information.

【0062】次に上記のように構成されたプラント運転
訓練用装置の作用を図11により説明するに、ここでは
図8と異なる点についてのみ述べる。
Next, the operation of the plant operation training apparatus configured as described above will be described with reference to FIG. 11. Here, only points different from FIG. 8 will be described.

【0063】装置指定手段10の装置指定入力手段10
1に個別の装置指定情報が入力されると、その情報をシ
ャットダウン信号出力手段102に出力する。このシャ
ットダウン信号出力手段102では、その装置情報を受
けると、シャットダウン手段8の信号入力手段81にシ
ャットダウン信号を出力する。この信号入力手段81は
このシャットダウン信号を受けると、シャットダウン指
示手段83にシャットダウン指示を通知する。
The device designation input means 10 of the device designation means 10
When the individual device designation information is input to 1, the information is output to the shutdown signal output means 102. Upon receiving the device information, the shutdown signal output means 102 outputs a shutdown signal to the signal input means 81 of the shutdown means 8. When receiving the shutdown signal, the signal input unit 81 notifies the shutdown instruction unit 83 of a shutdown instruction.

【0064】このような構成のプラント運転訓練装置と
すれば、シャットダウンさせたい装置を装置指定情報と
して装置指定手段10に入力して得られる装置情報より
装置指定手段からシャットダウン手段8に対して指定装
置の停止信号が出力され、その停止信号によりシャット
ダウン手段8から当該装置に対してシャットダウン指示
が行われる。
With the plant operation training device having such a configuration, the device to be shut down is input to the device specifying means 10 as device specifying information from the device information. Is output, and the shutdown signal is sent from the shutdown means 8 to the device in response to the stop signal.

【0065】従って、個別の装置を指定して停止信号を
入力するのみで、指定した装置のシャットダウンが自動
で実行されるため、装置の停止操作が容易となる。
Therefore, simply by designating an individual device and inputting a stop signal, the shutdown of the designated device is automatically executed, thereby facilitating the operation of stopping the device.

【0066】図12は本発明によるプラント運転訓練装
置の第7の実施の形態を示すブロック図で、図1と同一
構成要素には同一符号を付してその説明を省略し、ここ
では異なる点についてのみ述べる。
FIG. 12 is a block diagram showing a seventh embodiment of the plant operation training apparatus according to the present invention. The same components as those in FIG. 1 are denoted by the same reference numerals, and the description thereof will be omitted. Is described only.

【0067】第7の実施の形態では、図4と同様に停止
信号が入力されると模擬状態設定装置3とプラント模擬
装置4及びプラント監視装置5とプラントデータ表示装
置6にシャットダウン指示を行うシャットダウン手段8
に、さらに電源装置7に対して電源の投入と切断指示を
行う機能を持たせ、且つカレンダ情報を用いて毎日の起
動と停止時間を設定するスケジュール管理手段11を設
けたものである。
In the seventh embodiment, when a stop signal is input as in FIG. 4, a shutdown instruction is issued to the simulation state setting device 3, the plant simulation device 4, the plant monitoring device 5, and the plant data display device 6 to perform a shutdown instruction. Means 8
In addition, the power supply device 7 is provided with a function of instructing the power supply to be turned on and off, and a schedule management means 11 for setting the daily start and stop times using calendar information is provided.

【0068】図13は図12に示すシャッダウン手段8
とスケジュール管理手段11の一構成例を示すもので、
図5の構成に加えて設けられたスケジュール管理手段1
1は起動停止時刻等の設定情報を入力する情報入力手段
111と、この設定情報を受けると装置の起動と停止時
刻の設定を行う起動又は停止時刻設定手段112と、カ
レンダ情報が格納されているカレンダデータ部115
と、カレンダデータ部115より休日情報を取出して休
日設定を行う休日設定手段113と、起動又は停止時刻
設定手段112と休日設定手段113により設定された
情報を格納する時刻設定データ格納部114と、時間管
理を行う時計部117と、時刻設定データ格納部114
から設定データを取出すと共に、時計部117からの時
間情報を受けて起動又は停止設定時刻に現在時刻が合致
したときにシャットダウン手段8の信号入力手段81に
信号を出力するスケジュール処理手段116とから構成
されている。
FIG. 13 shows the shutdown means 8 shown in FIG.
And an example of the configuration of the schedule management means 11.
Schedule management means 1 provided in addition to the configuration of FIG.
Reference numeral 1 denotes an information input unit 111 for inputting setting information such as a start / stop time, a start / stop time setting unit 112 for setting a start / stop time of the apparatus upon receiving the set information, and calendar information. Calendar data section 115
A holiday setting unit 113 that extracts holiday information from the calendar data unit 115 and performs holiday setting; a start or stop time setting unit 112 and a time setting data storage unit 114 that stores information set by the holiday setting unit 113; A clock unit 117 for managing time and a time setting data storage unit 114
And a schedule processing means 116 for receiving the time information from the clock section 117 and outputting a signal to the signal input means 81 of the shutdown means 8 when the current time matches the start or stop set time. Have been.

【0069】次に上記のように構成されたプラント運転
訓練用装置の作用を図13を用いて説明するに、ここで
は図5と異なる点についてのみ述べる。
Next, the operation of the plant operation training apparatus configured as described above will be described with reference to FIG. 13. Here, only points different from FIG. 5 will be described.

【0070】プラント運転訓練装置の起動停止時刻等の
設定情報をスケジュール管理手段11の情報入力手段1
11に入力すると、この設定情報を起動又は停止時刻設
定手段112により時刻設定データ格納部114に格納
する。また、プラント運転訓練用装置を使用しない休日
や訓練無し日において、自動起動の時刻設定を無効にす
る休日の設定情報を情報入力手段111に入力すると、
更にカレンダー部115より休日情報を取出し、設定し
た休日設定情報と共に休日設定手段113により時刻設
定データ格納部114に設定情報を格納する。
The setting information such as the start / stop time of the plant operation training apparatus is stored in the information input means 1 of the schedule management means 11.
11, the setting information is stored in the time setting data storage unit 114 by the start or stop time setting means 112. In addition, on a holiday that does not use the plant operation training device or a day without training, when setting information of a holiday that invalidates the time setting of automatic startup is input to the information input unit 111,
Further, the holiday information is extracted from the calendar section 115, and the holiday setting means 113 stores the setting information in the time setting data storage section 114 together with the set holiday setting information.

【0071】図14は起動又は停止時刻設定手段112
の設定データの一例を示し、また図15は休日設定手段
113の設定データの一例を示すものである。
FIG. 14 shows the start or stop time setting means 112.
15 shows an example of the setting data of the holiday setting means 113. FIG.

【0072】また、スケジュール処理手段116は、時
刻設定データ格納部114の設定データと時計部117
の時刻情報を取組み、設定時間に現在時刻が合致したと
きにシャットダウン手段8の信号入力手段81にシャッ
トダウン信号や電源投入信号の出力を行う。
The schedule processing means 116 stores the setting data in the time setting data storage 114 and the clock 117
When the current time matches the set time, a shutdown signal or a power-on signal is output to the signal input means 81 of the shutdown means 8.

【0073】このような構成のプラント運転訓練装置に
よれば、毎日の起動及び停止時刻の設定と休日の設定を
しておくことで、訓練開始や訓練終了時の人手を介した
起動停止操作が必要なくなり、起動停止操作が容易とな
る。
According to the plant operation training apparatus having such a configuration, by setting the daily start and stop times and setting the holidays, the start and stop operations through manual operation at the start and end of the training can be performed. It is no longer necessary, and the start / stop operation becomes easy.

【0074】図16は本発明によるプラント運転訓練装
置の第8の実施の形態を示すブロック図で、図1と同一
構成要素には同一符号を付してその説明を省略し、ここ
では異なる点についてのみ述べる。
FIG. 16 is a block diagram showing an eighth embodiment of the plant operation training apparatus according to the present invention. The same components as those in FIG. 1 are denoted by the same reference numerals, and the description thereof will be omitted. Is described only.

【0075】第8の実施の形態では、図4と同様に停止
信号が入力されると模擬状態設定装置3とプラント模擬
装置4及びプラント監視装置5とプラントデータ表示装
置6にシャットダウン指示を行うシャットダウン手段8
に、さらに電源装置7に対して電源の投入と切断指示を
行う機能を持たせ、且つカレンダ情報を用いて毎日の起
動と停止時間を設定するスケジュール管理手段11と、
このスケジュール管理手段11により設定した停止時刻
に到達する前に、停止時刻が間近であることを表示装置
へ通知する事前通知処理手段12とを設けたものであ
る。
In the eighth embodiment, when a stop signal is input as in FIG. 4, a shutdown instruction is issued to the simulation state setting device 3, the plant simulation device 4, the plant monitoring device 5, and the plant data display device 6 to perform a shutdown instruction. Means 8
A schedule management unit 11 further having a function of instructing the power supply 7 to turn on and off the power and setting daily start and stop times using calendar information;
Prior to reaching the stop time set by the schedule management means 11, a prior notification processing means 12 for notifying the display device that the stop time is imminent is provided.

【0076】図17は図16に示すシャッダウン手段8
と、スケジュール管理手段11及び事前通知処理手段1
2の一構成例を示すもので、図13のスケジュール管理
手段11の構成要素に加えて、停止時刻のどのくらい前
に事前通知を行うかの情報を格納する事前通知時間格納
部118を設け、この事前通知を表示装置に対して行う
事前通知手段12とから構成される。
FIG. 17 shows the shutdown means 8 shown in FIG.
Schedule management means 11 and advance notification processing means 1
13 shows an example of the configuration, in addition to the components of the schedule management means 11 of FIG. 13, a prior notification time storage unit 118 for storing information indicating how long before the stop time is to be notified is provided. And a prior notification unit 12 for performing prior notification to the display device.

【0077】次に上記のように構成されたプラント運転
訓練装置の作用を図17を用いて説明するに、ここでは
図13と異なる点についてのみ述べる。
Next, the operation of the plant operation training apparatus configured as described above will be described with reference to FIG. 17. Here, only points different from FIG. 13 will be described.

【0078】スケジュール管理手段11において、スケ
ジュール管理手段116により停止時刻のどのくらい前
に事前通知を行うかの情報を格納している事前通知時間
格納部118から時間データを取出すと、このスケジュ
ール管理手段116は時計部117からの時刻情報によ
り、現在時刻が停止時刻から求めた事前通知時刻に合致
した段階で、通知メッセージを出力するように、事前通
知手段12に対して指示する。
In the schedule management means 11, when the schedule management means 116 extracts time data from the advance notification time storage unit 118 which stores information on how long before the stop time is to be notified, the schedule management means 116 Instructs the advance notification means 12 to output a notification message when the current time matches the advance notification time obtained from the stop time based on the time information from the clock unit 117.

【0079】この事前通知手段12はこの指示を受ける
と、表示装置に事前通知メッセージを出力する。図18
は図17の事前通知手段12より出力された事前通知メ
ッセージ9lの一例を示すものである。
Upon receiving this instruction, the prior notification means 12 outputs a prior notification message to the display device. FIG.
Shows an example of the advance notification message 91 output from the advance notification means 12 in FIG.

【0080】このような構成のプラント運転訓練装置に
よれば、設定した停止時刻を記憶していなくとも、停止
時刻の前に事前通知されることで、タイマーによる停止
操作の利便性が向上する。
According to the plant operation training apparatus having such a configuration, even if the set stop time is not stored, the stop operation is notified in advance before the stop time, thereby improving the convenience of the stop operation using the timer.

【0081】図19は本発明によるプラント運転訓練装
置の第9の実施の形態を示すブロック図で、図1と同一
構成要素には同一符号を付してその説明を省略し、ここ
では異なる点についてのみ述べる。
FIG. 19 is a block diagram showing a ninth embodiment of the plant operation training apparatus according to the present invention. The same components as those in FIG. 1 are denoted by the same reference numerals, and description thereof will be omitted. Is described only.

【0082】第9の実施の形態では、図13と同様に停
止信号が入力されると模擬状態設定装置3とプラント模
擬装置4及びプラント監視装置5とプラントデータ表示
装置6にシャットダウン指示を行うシャットダウン手段
8に、さらに電源装置7に対して電源の投入と切断指示
を行う機能を持たせ、且つカレンダ情報を用いて毎日の
起動と停止時間を設定するスケジュール管理手段11
と、このスケジュール管理手段11により設定した停止
時刻に到達する前に、停止時刻が間近であることを表示
装置へ通知する事前通知処理手段12と、この事前通知
手段12からの停止前の事前通知メッセージに対して、
停止時間を延長するための時間情報を入力する停止時間
延長手段13を設けたものである。
In the ninth embodiment, when a stop signal is input in the same manner as in FIG. 13, a shutdown instruction is issued to the simulation state setting device 3, the plant simulation device 4, the plant monitoring device 5, and the plant data display device 6 to perform a shutdown instruction. Means 8 for providing a function of instructing the power supply 7 to turn on and off the power supply, and a schedule management means 11 for setting daily start and stop times using calendar information.
Prior notification processing means 12 for notifying the display device that the stop time is imminent before the stop time set by the schedule management means 11 is reached; and advance notification before stop from the prior notification means 12 For the message,
A stop time extending means 13 for inputting time information for extending the stop time is provided.

【0083】図20は図19に示すスケジュール管理手
段11の一構成例を示すもので、図17に示す構成に加
えて、延長時間情報が入力される情報入力手段111
と、その時間情報を受けるとスケジュール処理手段11
6に情報通知する停止時間延長手段119とを設けたも
のである。
FIG. 20 shows an example of the structure of the schedule management means 11 shown in FIG. 19. In addition to the structure shown in FIG.
Receiving the time information, the schedule processing means 11
6 is provided with a suspension time extension means 119 for notifying information.

【0084】次に上記のように構成されたプラント運転
訓練装置の作用を図20を用いて説明するに、このでは
図17と異なる点についてのみ述べる。
Next, the operation of the plant operation training apparatus configured as described above will be described with reference to FIG. 20. Here, only points different from FIG. 17 will be described.

【0085】スケジュール管理手段11において、延長
時間情報が情報入力手段111に入力されると、その時
間情報は停止時間延長手段119に出力される。この停
止時間延長手段119ではその時間情報をスケジュール
処理手段116に情報通知すると、このスケジュール処
理手段116では延長時間情報より停止予定時刻を変更
し、現在時刻が変更した停止予定時刻に合致するまでシ
ャットダウン手段8に停止信号の通知を行わない。
In the schedule management means 11, when the extended time information is input to the information input means 111, the time information is output to the stop time extending means 119. When the stop time extending means 119 notifies the schedule processing means 116 of the time information, the schedule processing means 116 changes the scheduled stop time from the extended time information and shuts down until the current time matches the changed scheduled stop time. The stop signal is not notified to the means 8.

【0086】このような構成のプラント運転訓練装置に
よれば、スケジュール管理手段11により設定した停止
時刻をいちいち変更することなく、プラント運転訓練の
実施状況に応じて、停止時刻の延長が指定可能であり、
タイマーによる停止操作の利便性がさらに向上する。
According to the plant operation training apparatus having such a configuration, it is possible to specify the extension of the stop time according to the implementation status of the plant operation training without changing the stop time set by the schedule management means 11 each time. Yes,
The convenience of the stop operation by the timer is further improved.

【0087】図21は本発明によるプラント運転訓練装
置の第10の実施の形態を示すブロック図で、図19に
示す構成に加えて、起動/停止信号、起動停止時刻設定
情報、並びに延長時間情報を設定後送信するリモコン装
置15と、その信号を受ける信号受光手段14を備えて
いる。
FIG. 21 is a block diagram showing a tenth embodiment of the plant operation training apparatus according to the present invention. In addition to the configuration shown in FIG. 19, a start / stop signal, start / stop time setting information, and extension time information And a signal receiving means 14 for receiving the signal.

【0088】次に上記のように構成されたプラント運転
訓練装置の作用を図21を用いて説明するに、ここでは
図19と異なる点についてのみ述べる。
Next, the operation of the plant operation training apparatus configured as described above will be described with reference to FIG. 21. Here, only the points different from FIG. 19 will be described.

【0089】起動/停止信号、起動停止時刻設定情報、
並びに延長時間情報の各設定情報は、全てリモコン装置
15にて設定されその設定情報信号を送信すると、その
設定情報信号は信号受光手段14により受信される。こ
の場合、その情報信号の種別に応じてシャットダウン手
段8、スケジュール処理手段11、並びに停止時間延長
手段13に通知する。
Start / stop signal, start / stop time setting information,
All the setting information of the extended time information is set by the remote control device 15 and when the setting information signal is transmitted, the setting information signal is received by the signal light receiving means 14. In this case, the shutdown unit 8, the schedule processing unit 11, and the stop time extension unit 13 are notified according to the type of the information signal.

【0090】このような構成のプラント運転訓練装置に
よれば、情報設定をリモコン装置に集約させることで、
決められた装置とは別の場所からの遠隔操作が可能とな
り、起動/停止操作が容易となる。
According to the plant operation training apparatus having such a configuration, the information setting is integrated in the remote control device,
Remote control can be performed from a place different from the determined device, and start / stop operations are facilitated.

【0091】[0091]

【発明の効果】以上述べたように本発明によれば、訓練
開始又は終了時における起動又は停止操作の簡易化と訓
練指導員の負荷の軽減を図ることができるプラント運転
訓練装置を提供できる。
As described above, according to the present invention, it is possible to provide a plant operation training apparatus capable of simplifying the start or stop operation at the start or end of the training and reducing the load on the training instructor.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明によるプラント運転訓練装置の第1の実
施の形態を示すブロック図。
FIG. 1 is a block diagram showing a first embodiment of a plant operation training device according to the present invention.

【図2】同実施の形態におけるシャットダウン手段の一
構成例を示すブロック図。
FIG. 2 is a block diagram showing a configuration example of a shutdown unit according to the embodiment;

【図3】本発明によるプラント運転訓練装置の第2の実
施の形態を示すブロック図。
FIG. 3 is a block diagram showing a second embodiment of the plant operation training device according to the present invention.

【図4】本発明によるプラント運転訓練装置の第3の実
施の形態を示すブロック図。
FIG. 4 is a block diagram showing a third embodiment of the plant operation training device according to the present invention.

【図5】同実施の形態におけるシャットダウン手段の一
構成例を示すブロック図。
FIG. 5 is a block diagram showing a configuration example of a shutdown unit according to the embodiment;

【図6】本発明によるプラント運転訓練装置の第4の実
施の形態を示すブロック図。
FIG. 6 is a block diagram showing a fourth embodiment of the plant operation training apparatus according to the present invention.

【図7】本発明によるプラント運転訓練装置の第5の実
施の形態を示すブロック図。
FIG. 7 is a block diagram showing a fifth embodiment of the plant operation training device according to the present invention.

【図8】同実施の形態におけるシャットダウン手段の一
構成例を示すブロック図。
FIG. 8 is a block diagram showing a configuration example of a shutdown unit according to the embodiment;

【図9】同実施の形態において、装置状態表示手段によ
り表示される状態表示の一例を示す図。
FIG. 9 is a diagram showing an example of a status display displayed by the device status display means in the embodiment.

【図10】本発明によるプラント運転訓練装置の第6の
実施の形態を示すブロック図。
FIG. 10 is a block diagram showing a sixth embodiment of the plant operation training apparatus according to the present invention.

【図11】同実施の形態におけるシャットダウン手段と
装置状態表示手段及び装置指定手段の一構成例を示すブ
ロック図。
FIG. 11 is a block diagram showing a configuration example of a shutdown unit, a device state display unit, and a device designation unit according to the embodiment;

【図12】本発明によるプラント運転訓練装置の第7の
実施の形態を示すブロック図。
FIG. 12 is a block diagram showing a seventh embodiment of the plant operation training device according to the present invention.

【図13】同実施の形態におけるシャッダウン手段とス
ケジュール管理手段の一構成例を示すブロック図。
FIG. 13 is a block diagram showing a configuration example of a shutdown unit and a schedule management unit according to the embodiment;

【図14】同実施の形態において、起動又は停止時刻設
定手段の設定データの一例を示す図。
FIG. 14 is a diagram showing an example of setting data of a start or stop time setting unit in the embodiment.

【図15】同実施の形態において、休日設定手段の設定
データの一例を示す図。
FIG. 15 is a diagram showing an example of setting data of a holiday setting unit in the embodiment.

【図16】本発明によるプラント運転訓練装置の第8の
実施の形態を示すブロック図。
FIG. 16 is a block diagram showing an eighth embodiment of the plant operation training device according to the present invention.

【図17】同実施の形態におけるシャッダウン手段と、
スケジュール管理手段及び事前通知処理手段の一構成例
を示すブロック図。
FIG. 17 shows a shutdown means in the embodiment;
FIG. 3 is a block diagram showing a configuration example of a schedule management unit and a prior notification processing unit.

【図18】同実施の形態において、事前通知手段より出
力された事前通知メッセージの一例を示す図。
FIG. 18 is a diagram showing an example of a prior notification message output from a prior notification unit in the embodiment.

【図19】本発明によるプラント運転訓練装置の第9の
実施の形態を示すブロック図。
FIG. 19 is a block diagram showing a ninth embodiment of the plant operation training device according to the present invention.

【図20】同実施の形態におけるスケジュール管理手段
の一構成例を示すブロック図。
FIG. 20 is an exemplary block diagram illustrating a configuration example of a schedule management unit according to the embodiment;

【図21】本発明によるプラント運転訓練装置の第10
の実施の形態を示すブロック図。
FIG. 21 shows a tenth embodiment of the plant operation training apparatus according to the present invention.
FIG. 2 is a block diagram showing an embodiment.

【図22】従来のプラント運転訓練装置を示すブロック
図。
FIG. 22 is a block diagram showing a conventional plant operation training device.

【符号の説明】[Explanation of symbols]

1…操作制御盤 2…信号入出力装置 3…模擬状態設定装置 4…プラント模擬装置 5…プラント監視装置 6…プラントデータ表示装置 7…電源装置 8…シャットダウン手段 9…装置状態表示手段 10…装置指定手段 11…スケジュール管理手段 12…事前通知手段 13…停止時間延長手段 14…信号受光手段 15…リモコン装置 16…タイマリレー装置 REFERENCE SIGNS LIST 1 operation control panel 2 signal input / output device 3 simulated state setting device 4 plant simulated device 5 plant monitoring device 6 plant data display device 7 power supply device 8 shutdown means 9 device status display device 10 device Designating means 11 Schedule management means 12 Prior notification means 13 Stop time extension means 14 Signal receiving means 15 Remote control device 16 Timer relay device

───────────────────────────────────────────────────── フロントページの続き (72)発明者 根津 基嗣 東京都府中市東芝町1番地 株式会社東芝 府中工場内 Fターム(参考) 2G075 AA01 BA20 CA02 DA20 FC04 FD01 GA24 5H223 AA03 EE06 EE08 FF05  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Mototsugu Nezu 1 Toshiba-cho, Fuchu-shi, Tokyo F-term in the Fuchu Plant of Toshiba Corporation (reference) 2G075 AA01 BA20 CA02 DA20 FC04 FD01 GA24 5H223 AA03 EE06 EE08 FF05

Claims (10)

【特許請求の範囲】[Claims] 【請求項1】 運転訓練操作を行う操作制御手段と、プ
ラント運転の模擬状態を設定する模擬状態設定手段と、
この模擬状態設定手段からの設定情報と前記操作制御手
段からの操作信号を入力してプラント状態を模擬するプ
ラント模擬手段と、このプラント模擬手段からのプラン
ト信号を入力してプラント状態を監視するプラント監視
手段と、このプラント監視手段からのプラント情報を入
力してプラントデータの表示を行うプラントデータ表示
手段と、これら操作制御手段、模擬状態設定手段、プラ
ント模擬手段、プラント監視手段及びプラントデータ表
示手段の駆動電源となる電源装置と、停止信号が入力さ
れると模擬状態設定手段とプラント模擬手段及びプラン
ト監視手段とプラントデータ表示手段にそれぞれシャッ
トダウン指示を行うシャットダウン手段とを備えたこと
を特徴とするプラント運転訓練装置。
An operation control means for performing a driving training operation, a simulated state setting means for setting a simulated state of plant operation,
A plant simulating means for simulating a plant state by inputting setting information from the simulated state setting means and an operation signal from the operation control means, and a plant for monitoring a plant state by inputting a plant signal from the plant simulating means Monitoring means, plant data display means for displaying plant data by inputting plant information from the plant monitoring means, operation control means, simulated state setting means, plant simulation means, plant monitoring means, and plant data display means And a shutdown unit for issuing a shutdown instruction to the simulation state setting unit, the plant simulation unit, the plant monitoring unit, and the plant data display unit when a stop signal is input. Plant operation training equipment.
【請求項2】 運転訓練操作を行う操作制御手段と、プ
ラント運転の模擬状態を設定する模擬状態設定手段と、
この模擬状態設定手段からの設定情報と前記操作制御手
段からの操作信号を入力してプラント状態を模擬するプ
ラント模擬手段と、このプラント模擬手段からのプラン
ト信号を入力してプラント状態を監視するプラント監視
手段と、このプラント監視手段からのプラント情報を入
力してプラントデータの表示を行うプラントデータ表示
手段と、これら操作制御手段、模擬状態設定手段、プラ
ント模擬手段、プラント監視手段及びプラントデータ表
示手段の駆動電源となる電源装置と、停止信号が入力さ
れると模擬状態設定手段、前記プラント模擬手段、プラ
ント監視手段、プラントデータ表示手段のいずれかにシ
ャットダウン指示を行うシャットダウン手段とを備え、 前記模擬状態設定手段、前記プラント模擬手段、プラン
ト監視手段、プラントデータ表示手段はシャットダウン
指示を受けると停止処理をすると共に、シャットダウン
指示を行う機能を持たせて、最初にシャットダウン指示
を受けたものから最後まで順次シャットダウン指示を出
して停止処理を行うようにしたことを特徴とするプラン
ト運転訓練装置。
2. An operation control means for performing a driving training operation, a simulated state setting means for setting a simulated state of plant operation,
A plant simulating means for simulating a plant state by inputting setting information from the simulated state setting means and an operation signal from the operation control means, and a plant for monitoring a plant state by inputting a plant signal from the plant simulating means Monitoring means, plant data display means for displaying plant data by inputting plant information from the plant monitoring means, operation control means, simulated state setting means, plant simulation means, plant monitoring means, and plant data display means A power supply device serving as a driving power supply for the simulation, and a shutdown means for issuing a shutdown instruction to any one of the simulation state setting means, the plant simulation means, the plant monitoring means, and the plant data display means when a stop signal is input; Status setting means, said plant simulation means, plant monitoring means, In response to the shutdown instruction, the shutdown data display means performs a shutdown process, and has a function of issuing a shutdown instruction, and issues a shutdown instruction sequentially from the first shutdown instruction received to the last to perform the shutdown process. A plant operation training device characterized by the above-mentioned.
【請求項3】 請求項1記載のプラント運転訓練装置に
おいて、シャットダウン手段に起動又は停止信号が入力
されると前記電源装置に電源投入又は切断指示を行う機
能を持たせて前記電源装置の電源投入又は切断を行うよ
うにしたことを特徴とするプラント運転訓練装置。
3. The plant operation training apparatus according to claim 1, wherein when a start or stop signal is input to a shutdown means, the power supply apparatus has a function of giving a power on / off instruction to turn on the power supply apparatus. Or a plant operation training device characterized by performing cutting.
【請求項4】 請求項3記載のプラント運転訓練装置に
おいて、前記電源装置に対して電源の投入と切断指示を
行う機能を持たせ、且つ時限装置を付加して予め設定さ
れた時間を経過すると装置毎の電源に対して切断と投入
を行う機能を持たせたでの構成要素とを付加することを
特徴とするプラント運転訓練装置。
4. The plant operation training apparatus according to claim 3, wherein the power supply apparatus has a function of instructing the power supply to be turned on and off, and when a preset time elapses after a time limit apparatus is added. A plant operation training device characterized by adding a component having a function of turning off and on a power supply for each device.
【請求項5】 請求項3記載のプラント運転訓練装置に
おいて、前記シャットダウン手段から各装置のシャット
ダウン状態の情報を入力し、その状態情報を表示する装
置状態表示手段を設けたことを特徴とするプラント運転
訓練装置。
5. The plant operation training apparatus according to claim 3, further comprising a device state display unit for inputting information on a shutdown state of each device from the shutdown unit and displaying the state information. Driving training equipment.
【請求項6】 請求項5記載のプラント運転訓練装置に
おいて、装置を個別にシャットダウンするための装置指
定情報を入力し、この情報を前記シャットダウン手段に
停止信号として出力する装置指定手段を設けたことを特
徴とするプラント運転訓練装置。
6. The plant operation training device according to claim 5, further comprising a device designation unit for inputting device designation information for individually shutting down the device and outputting the information as a stop signal to the shutdown unit. A plant operation training device characterized by the following.
【請求項7】 請求項3記載のプラント運転訓練装置に
おいて、予め決められた時刻に起動したり、停止させる
ための設定情報が入力され、且つ現在時刻が設定時刻に
合致したとき前記シャットダウン手段に起動又は停止要
求を通知するスケジュール管理手段を設けたことを特徴
とするプラント運転訓練装置。
7. The plant operation training apparatus according to claim 3, wherein setting information for starting or stopping at a predetermined time is input, and when the current time matches the set time, the shutdown means is transmitted to the shutdown means. A plant operation training device provided with schedule management means for notifying a start or stop request.
【請求項8】 請求項7記載のプラント運転訓練装置に
おいて、前記スケジュール管理手段により設定した停止
時刻に到達する前に停止時刻が間近であることを表示装
置へ通知する事前通知処理手段を設けたことを特徴とす
るプラント運転訓練装置。
8. The plant operation training apparatus according to claim 7, further comprising a prior notification processing means for notifying the display device that the stop time is approaching before reaching the stop time set by the schedule management means. A plant operation training device characterized by the above-mentioned.
【請求項9】 請求項8記載のプラント運転訓練装置に
おいて、前記事前通知処理手段からの停止時刻の事前通
知により、時間情報を入力し前記スケジュール管理手段
に停止時刻の延長を通知する停止時間延長手段を設けた
ことを特徴とするプラント運転訓練装置。
9. The plant operation training apparatus according to claim 8, wherein a stop time for inputting time information and notifying the schedule management means of extension of the stop time is notified by the advance notification of the stop time from the advance notification processing means. A plant operation training device provided with extension means.
【請求項10】 請求項7記載のプラント運転訓練装置
において、前記スケジュール管理手段に停止時刻の延長
を通知する停止時間延長手段と、停止信号と設定情報と
時間情報とを任意に設定して遠隔送信するリモコン装置
と、このリモコン装置からの信号を受光して各情報によ
り前記シャットダウン手段と前記スケジュール管理手段
と前記停止時間延長手段に出力する信号受光手段とを設
けたことを特徴とするプラント運転訓練装置。
10. The plant operation training apparatus according to claim 7, wherein a stop time extension means for notifying the schedule management means of extension of the stop time, and a stop signal, setting information, and time information are arbitrarily set to remotely control the schedule management means. A plant operation, comprising: a remote control device for transmitting, and a signal light receiving device for receiving a signal from the remote control device and outputting the information to the shutdown means, the schedule management means, and the stop time extension means according to each information. Training equipment.
JP4638899A 1999-02-24 1999-02-24 Plant operation training device Pending JP2000242322A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4638899A JP2000242322A (en) 1999-02-24 1999-02-24 Plant operation training device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4638899A JP2000242322A (en) 1999-02-24 1999-02-24 Plant operation training device

Publications (1)

Publication Number Publication Date
JP2000242322A true JP2000242322A (en) 2000-09-08

Family

ID=12745772

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4638899A Pending JP2000242322A (en) 1999-02-24 1999-02-24 Plant operation training device

Country Status (1)

Country Link
JP (1) JP2000242322A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014006915A (en) * 2007-08-10 2014-01-16 Smiths Medical Asd Inc Transmission of preventative maintenance data to medical device
JP2016064883A (en) * 2014-09-24 2016-04-28 株式会社日立ビルシステム Earthquake training operation system of elevator

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014006915A (en) * 2007-08-10 2014-01-16 Smiths Medical Asd Inc Transmission of preventative maintenance data to medical device
JP2016064883A (en) * 2014-09-24 2016-04-28 株式会社日立ビルシステム Earthquake training operation system of elevator

Similar Documents

Publication Publication Date Title
CN108353163A (en) The method for being provided with the display device of video display unit and measuring the display of video display unit
CN109857353B (en) Method and system for controlling display content of LED screen
JP2000242322A (en) Plant operation training device
JP4335731B2 (en) Air conditioning control monitoring device, air conditioning control monitoring method, and building management system
US20140088775A1 (en) Apparatus control system, mobile terminal and program
CA3015341A1 (en) System, method, apparatus, and program for light tower control
JP2012146250A (en) Monitoring device
CN105116969A (en) Power switch timing method and device
JP2000078751A (en) Power saving electronic apparatus
CN108609444B (en) Elevator display capable of modifying display floor and modifying operation device
JP2007309813A (en) Reserved operation system of heating/cooling equipment and its program
Ayson Microcontroller-based school bell system for the College of Engineering, DMMMSU-MLUC
TWI623711B (en) Intelligent air conditioning power distribution unit
JP2001324204A (en) Monitor system for air conditioner and monitor device
CN111400140B (en) Control system, method, device, computing device and storage medium for communication device
CN203520062U (en) Projector control system for multimedia electric classroom
JPH10274920A (en) Plant simulator
TWM535789U (en) Intelligent air-conditioner power distribution device
WO2021056800A1 (en) Fatigue testing system
JP2000242204A (en) Video display device
JP2919472B2 (en) Program timer device
KR940008438A (en) How to control the individual functions of the timer
CN105991208A (en) Wireless communication signal interference and shielding system for classrooms
KR200189906Y1 (en) Vehicles revolve limit notice and multifunction character display apparatus
KR20010009523A (en) Remote control process Remote controller for a traffic signal