JP2000213168A - Construction method of frame body - Google Patents

Construction method of frame body

Info

Publication number
JP2000213168A
JP2000213168A JP11013604A JP1360499A JP2000213168A JP 2000213168 A JP2000213168 A JP 2000213168A JP 11013604 A JP11013604 A JP 11013604A JP 1360499 A JP1360499 A JP 1360499A JP 2000213168 A JP2000213168 A JP 2000213168A
Authority
JP
Japan
Prior art keywords
skeleton
rail
floor
hoist
lifting machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11013604A
Other languages
Japanese (ja)
Inventor
Yasuo Kajioka
保夫 梶岡
Yoji Takasugi
洋二 高杉
Mikio Okato
美紀雄 岡登
Gentaro Koshiro
源太郎 小城
Hideo Kodera
英夫 小寺
Yoichi Seki
洋一 関
Hiroshi Tokuda
浩 徳田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP11013604A priority Critical patent/JP2000213168A/en
Publication of JP2000213168A publication Critical patent/JP2000213168A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction method of a frame body by which a building with a large planar shape can be efficiently and costlessly erected. SOLUTION: Traveling rails 23 for a crane are laid on the frame body 10 right under a floor precedently constructed and the frame body 10 of the constructing floor is erected while transferring the crane on the traveling rails 23. In this time, the traveling rails 23 for the crane are supported on the beam 12 of the frame body 10 right under the floor and further, two units of traveling rails 23 for the crane are prepared to transfer the crane 22 while alternately advancing them.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、例えばショッピン
グセンターや倉庫等、特に大平面形状の建物を構築する
ときに用いて好適な躯体構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a building suitable for use in constructing a large flat building, for example, a shopping center or a warehouse.

【0002】[0002]

【従来の技術】ショッピングセンターや倉庫、工場等、
平面積の大きな建物の躯体を構築するに際しては、大型
のクレーン車、あるいはタワークレーン等の揚重機を用
いているのが通常である。
[Prior Art] Shopping centers, warehouses, factories, etc.
When constructing the frame of a building having a large flat area, it is common to use a large crane truck or a lifting machine such as a tower crane.

【0003】このように大型の揚重機を用いた大平面形
状の建物の躯体構築方法としては、例えば以下に示すよ
うなものがある。
[0003] As a method of constructing a frame of a building having a large planar shape using such a large lifting machine, for example, there is the following method.

【0004】まず、図7に示すように、構築すべき躯体
1の外周部から内部に至る仮設通路スペース2を確保
し、この仮設通路スペース2に大型の揚重機を進入させ
てその周囲の部分の躯体1Aを最上階まで構築した後、
この仮設通路スペース2の部分を後施工で構築する方法
がある。また、図8に示すように、構築すべき躯体1の
内方部分にタワークレーン等の揚重機4を設置する穴状
のスペース5を確保し、このスペース5に設置した揚重
機4を用いてその周囲の部分の躯体1Bを先行して構築
した後、揚重機4を撤去し、このスペース5の部分の躯
体を後施工で構築する方法もある。
First, as shown in FIG. 7, a temporary passage space 2 extending from the outer peripheral portion to the inside of a frame 1 to be constructed is secured, and a large lifting machine is entered into the temporary passage space 2 to surround a portion around the temporary passage space. After building the skeleton 1A up to the top floor,
There is a method of constructing the temporary passage space 2 by post-processing. As shown in FIG. 8, a hole-shaped space 5 for installing a lifting machine 4 such as a tower crane is secured in an inner portion of the skeleton 1 to be constructed, and the lifting machine 4 installed in this space 5 is used. There is also a method of constructing the skeleton 1B of the surrounding portion in advance, removing the lifting machine 4, and constructing the skeleton of the space 5 by post-construction.

【0005】さらに、図9に示すように、構築すべき躯
体1の外周側から揚重機6のブーム6aを伸ばして躯体
1を構築する方法もある。
Further, as shown in FIG. 9, there is also a method of extending the boom 6a of the lifting machine 6 from the outer peripheral side of the frame 1 to be constructed to construct the frame 1.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、上述し
たような従来の躯体構築方法には、以下のような問題が
存在する。まず、図7および図8に示したような方法で
は、仮設通路スペース2や穴状のスペース5の部分が後
施工となってしまうため、躯体1自体の施工に手間がか
かる。また設備や内装仕上等の工事も、各フロア全体の
躯体完成を待っていると工事着手が遅くなり、逆に仮設
通路スペース2や穴状のスペース5がある状態で工事に
着手すると、仮設通路スペース2や穴状のスペース5の
部分の完成後に、別途この部分の設備・内装仕上工事を
行わなければならず非効率的である。さらに、仮設通路
スペース2や穴状のスペース5の周囲においては、高所
作業となるため、足場や養生ネット等を設ける必要があ
り、仮設工事費が嵩むという問題もある。
However, the above-described conventional frame building method has the following problems. First, in the method as shown in FIGS. 7 and 8, since the temporary passage space 2 and the hole-shaped space 5 are post-processed, it takes time to construct the frame 1 itself. In addition, construction work such as equipment and interior finishing is delayed when waiting for the completion of the skeleton of the entire floor, and conversely, when construction starts with the temporary passage space 2 and the hole-shaped space 5, the temporary passage After completion of the space 2 and the hole-shaped space 5, the equipment / interior finishing work of this portion must be performed separately, which is inefficient. Furthermore, since the work is performed at a high place around the temporary passage space 2 and the hole-shaped space 5, it is necessary to provide a scaffold, a curing net, and the like, and there is a problem that the cost of the temporary construction work increases.

【0007】一方、図9に示したように、躯体1の外周
側から施工を行う方法では、まず外周部に十分なスペー
スを確保できなければこのような方法は採用することが
できない。また、外周側から作業を行うと、揚重機6の
作業範囲が大きくなるため、これに伴って揚重機6も大
型化するが、その割に軽いものを吊ることとなり、揚重
機6の利用効率が悪くなるという問題がある。
On the other hand, as shown in FIG. 9, in the method of performing construction from the outer peripheral side of the skeleton 1, such a method cannot be adopted unless a sufficient space is first secured in the outer peripheral portion. In addition, when the work is performed from the outer peripheral side, the working range of the lifting machine 6 is increased, and accordingly, the lifting machine 6 is also increased in size. However, a lighter object is suspended, and the utilization efficiency of the lifting machine 6 is increased. There is a problem that becomes worse.

【0008】本発明は、以上のような点を考慮してなさ
れたもので、大平面形状の建物を効率良く、低コストで
かつ短工期で施工することのできる躯体構築方法を提供
することを課題とする。
SUMMARY OF THE INVENTION The present invention has been made in view of the above points, and provides a method of constructing a frame capable of efficiently constructing a large planar building at low cost and in a short construction period. Make it an issue.

【0009】[0009]

【課題を解決するための手段】請求項1に係る発明は、
建物の躯体を構築する方法であって、先に構築した直下
階の躯体上にレールを敷設し、揚重機を前記レール上で
移動させつつ、前記直下階の上階の躯体を構築すること
を特徴としている。
The invention according to claim 1 is
A method of constructing a building skeleton, in which a rail is laid on the skeleton on the immediately lower floor constructed earlier, and a lifting machine is moved on the rail, while building a skeleton on the upper floor of the immediately lower floor. Features.

【0010】これにより、各階の施工を、当該階で移動
する揚重機で行うことができ、大型の揚重機を用いる必
要が無くなる。
[0010] Thus, the construction of each floor can be performed by the lifting machine moving on the floor, and it is not necessary to use a large lifting machine.

【0011】請求項2に係る発明は、請求項1記載の躯
体構築方法であって、前記直下階の躯体上に敷設するレ
ールを、前記直下階の躯体を構成する梁上に支持させて
敷設することを特徴としている。
According to a second aspect of the present invention, there is provided the method of constructing a skeleton according to the first aspect, wherein the rail laid on the skeleton on the immediately lower floor is supported on a beam constituting the skeleton on the immediately lower floor. It is characterized by doing.

【0012】これにより、揚重機の荷重は直下階の梁に
伝わり、床には伝わらないことになる。
As a result, the load of the hoist is transmitted to the beam directly below the floor, but not to the floor.

【0013】請求項3に係る発明は、請求項1または2
記載の躯体構築方法であって、前記レールとして、所定
長を有したレール部材を少なくとも二組用い、一の前記
レール部材上に前記揚重機を載せ、該一のレール部材の
前方に他の前記レール部材を敷設した後、前記揚重機を
前方の前記レール部材上に移動させる工程と、前記揚重
機の後方に位置する前記レール部材を、前記揚重機でそ
の前方に移動して敷設する工程とを交互に繰り返すこと
によって、前記揚重機を前記躯体上で移動させることを
特徴としている。
The invention according to claim 3 is the invention according to claim 1 or 2
The skeleton building method according to claim, wherein at least two sets of rail members having a predetermined length are used as the rails, the lifting machine is placed on one of the rail members, and the other of the other rail members is provided in front of the one of the rail members. After laying a rail member, a step of moving the hoist over the rail member in front, and a step of moving the rail member located behind the hoist and moving it forward with the hoist to lay the rail member. By alternately repeating the above, the lifting machine is moved on the skeleton.

【0014】このように、いわば尺取り虫のように揚重
機を移動させることにより、レール部材の本数が最小限
で済み、また揚重機の後方側においてはレールが撤去さ
れるので、設備や内装仕上等の工事に着手することがで
きる。
As described above, by moving the lifting machine like a so-called worm, the number of rail members can be minimized, and the rails are removed at the rear side of the lifting machine. Work can be undertaken.

【0015】請求項4に係る発明は、請求項1から3の
いずれかに記載の躯体構築方法であって、前記揚重機の
荷重を受ける荷重受け部材を、前記直下階の躯体上に設
置する構成とし、かつ、前記荷重受け部材の下面には、
前記揚重機からの荷重で前記荷重受け部材が撓んだとき
にその下面が前記直下階床面に直接接触しないよう、前
記揚重機の荷重を受ける部分に対してオフセットした位
置にベース部材を設けておくことを特徴としている。
According to a fourth aspect of the present invention, there is provided the method for constructing a skeleton according to any one of the first to third aspects, wherein a load receiving member for receiving the load of the hoist is installed on the skeleton on the immediately lower floor. And the lower surface of the load receiving member,
When the load receiving member is bent by the load from the hoist, a base member is provided at a position offset with respect to a portion receiving the load of the hoist, so that the lower surface does not directly contact the floor immediately below the floor. It is characterized by keeping.

【0016】これにより、揚重機の荷重は床には伝わら
ず直下階の梁に伝わり、しかも荷重受け部材が直下階の
床面に直接接触しないようになる。
Thus, the load of the lifting machine is not transmitted to the floor but to the beam on the immediately lower floor, and the load receiving member does not directly contact the floor surface on the immediately lower floor.

【0017】請求項5に係る発明は、請求項1から4の
いずれかに記載の躯体構築方法であって、前記躯体の端
部と前記揚重機の近傍位置との間に、台車用レールを敷
設し、該台車用レール上を走行する搬送台車によって、
組み立てるべき資材等を前記揚重機の近傍位置まで搬送
することを特徴としている。
According to a fifth aspect of the present invention, there is provided the frame building method according to any one of the first to fourth aspects, wherein the bogie rail is provided between an end of the frame and a position near the hoist. By laying, by the carrier truck traveling on the truck rail,
It is characterized in that materials to be assembled and the like are transported to a position near the hoist.

【0018】これにより、組み立てるべき躯体の構成部
材や、揚重機用のレール部材等を揚重機近傍まで搬送す
ることができ、揚重機自体は躯体の組立作業専用とする
ことができる。
Thus, it is possible to convey the components of the skeleton to be assembled, the rail members for the hoist, etc. to the vicinity of the hoist, and the hoist itself can be dedicated to the assembling work of the skeleton.

【0019】[0019]

【発明の実施の形態】以下、本発明に係る躯体構築方法
の実施の形態の一例を、図1ないし図6を参照して説明
する。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view showing an embodiment of a method for constructing a skeleton according to the present invention; FIG.

【0020】図1ないし図6の各図において、符号10
は構築すべき建物の躯体を示している。構築すべき建物
は、例えば地上5階建て程度の低層で、その階数に比較
して平面積が大きな大平面形状のものとなっている。そ
して、この建物の躯体10は、例えば、柱11が鋼管充
填コンクリート造、梁12が鉄骨造、床13がデッキプ
レート上にコンクリートが打設された構成となってい
る。
In each of FIGS. 1 to 6, reference numeral 10 is used.
Indicates the frame of the building to be constructed. The building to be constructed is a low-rise building having, for example, about five floors above the ground, and has a large planar shape having a large plane area compared to the number of floors. The frame 10 of this building has, for example, a configuration in which the pillars 11 are made of steel pipe-filled concrete, the beams 12 are made of steel, and the floor 13 is cast on a deck plate.

【0021】このような躯体10を構築するには、基本
的に、図1に示すように、 柱11を構成する鋼管14の建て込み(図1(a)参
照)、 梁12との仕口部を構成するブラケット15の鋼管1
4上部への建て込み(図1(b)参照)、 梁12を構成する鉄骨16の建て込み(図1(c)参
照)、および床13を構成するデッキプレート17の敷
き込み(図1(d)参照)、 柱11と梁12との接合部への鉄筋18の落とし込
み、および鋼管14内およびデッキプレート17上への
コンクリート打設(図1(d)参照)、 という上記〜の工程を、各施工階において繰り返す
ことによって、下層階から上層階へと躯体10を積層構
築していく工法を採用する。ちなみに、図1(e)は、
直上階を施工階としたときの前記の工程を示したもの
である。
In order to construct such a skeleton 10, basically, as shown in FIG. 1, a steel pipe 14 constituting a column 11 is laid (see FIG. 1A), and a connection with a beam 12 is made. Steel pipe 1 of bracket 15 constituting part
4 (see FIG. 1 (b)), the steel frame 16 which constitutes the beam 12 (see FIG. 1 (c)), and the deck plate 17 which constitutes the floor 13 (see FIG. 1 ( d)), dropping the reinforcing bar 18 into the joint between the column 11 and the beam 12, and placing concrete in the steel pipe 14 and on the deck plate 17 (see FIG. 1 (d)). The construction method in which the frame 10 is stacked and constructed from the lower floor to the upper floor by repeating the process on each construction floor is adopted. By the way, FIG. 1 (e)
It shows the above-described steps when the immediately upper floor is a construction floor.

【0022】次に、上記躯体10の各施工階における構
築方法について説明する。まず、最下階の躯体10につ
いては、後述する揚重装置20を用い、これを基礎上で
自走させて柱11,梁12,床13の構築を行っても良
いし、また後述する上階と同様の施工方法を適用して構
築しても良いし、さらには他の揚重機等を用いて構築を
行っても良い。
Next, a method of constructing the building 10 at each construction floor will be described. First, for the frame 10 on the lowest floor, a lifting device 20, which will be described later, may be used to self-propelled on a foundation to construct columns 11, beams 12, and floors 13, or to be described later. The construction may be performed by applying the same construction method as the floor, or the construction may be performed using another lifting machine or the like.

【0023】図2から図4に示したように、最下階の躯
体10を構成する柱11,梁12,床13の構築完了
後、その直上階の躯体10を構築するには、揚重装置2
0と搬送装置21とから構成された揚重システムを用い
る。
As shown in FIGS. 2 to 4, after the construction of the pillars 11, beams 12, and floor 13 constituting the frame 10 on the lowest floor is completed, the lifting of the frame 10 on the floor immediately above is carried out by lifting. Device 2
A lifting system composed of a transport device 21 and a transport device 21 is used.

【0024】揚重装置20は、揚重機22と、この揚重
機22の揚重機走行レール(レール,レール部材,荷重
受け部材)23とから構成されている。
The lifting device 20 includes a lifting device 22 and a lifting device traveling rail (rail, rail member, load receiving member) 23 of the lifting device 22.

【0025】図5に示すように、揚重機22は、いわゆ
るラフテレンクレーンのような移動式クレーンであり、
車輪25aを備えて自走可能な移動部25と、この移動
部25に対して両側に張り出し、この移動部25を固定
するアウトリガー26と、移動部25上に旋回自在に設
けられたブーム27とを備えて構成されている。
As shown in FIG. 5, the lifting machine 22 is a mobile crane such as a so-called rough terrain crane.
A movable portion 25 having wheels 25a which can move on its own, an outrigger 26 which protrudes to both sides of the movable portion 25 and fixes the movable portion 25, and a boom 27 which is rotatably provided on the movable portion 25; It is provided with.

【0026】また、揚重機走行レール23は、例えば、
2本一対のH型鋼からなり、その上部フランジの上面を
移動部25の車輪25aが走行するようになっている。
そして、揚重機走行レール23の上部フランジの端部に
は、車輪25aの脱輪を防止するため断面視L字状のア
ングル部材23bが一体に設けられている。図3に示し
たように、これら2本一対の揚重機走行レール23は、
それぞれ躯体10の梁12,12の間隔に対応した長さ
を有しており、さらに図5に示したように、移動部25
の車輪25a,25aの間隔に対応した間隔で連結部材
28によって一体化されている。この揚重機走行レール
23は、施工中の躯体10にセットされるときには、そ
の両端部を、梁12,12の上面に対応した位置に、そ
れぞれベース部材29を介して載置されるようになって
いる。このベース部材29は、揚重機22が揚重機走行
レール23上で揚重作業を行うために停止した状態で、
揚重機22の荷重を受ける位置、つまり車輪25aを受
ける位置に対してオフセットしており、これにより揚重
機22の荷重が作用し、揚重機走行レール23が撓んで
も、その下面が床13の上面に接触するのを防止するよ
うになっている。
The hoist traveling rail 23 is, for example,
It consists of a pair of H-shaped steel, and the wheel 25a of the moving part 25 runs on the upper surface of the upper flange.
An end member of an upper flange of the lifting machine traveling rail 23 is integrally provided with an angle member 23b having an L-shaped cross section in order to prevent the wheels 25a from coming off. As shown in FIG. 3, these two pairs of lifting machine traveling rails 23
Each of them has a length corresponding to the interval between the beams 12 and 12 of the frame 10, and as shown in FIG.
Are integrated by the connecting member 28 at intervals corresponding to the intervals between the wheels 25a. When the crane traveling rail 23 is set on the skeleton 10 under construction, both ends thereof are placed via the base member 29 at positions corresponding to the upper surfaces of the beams 12, 12, respectively. ing. This base member 29 is in a state where the hoisting machine 22 is stopped to perform the hoisting operation on the hoisting machine traveling rail 23,
It is offset with respect to the position where the load of the hoist 22 is received, that is, the position where the wheel 25a is received, so that even if the load of the hoist 22 acts and the hoist traveling rail 23 flexes, the lower surface of the floor 13 It is designed to prevent contact with the upper surface.

【0027】さらに、揚重機22のアウトリガー26を
受ける位置には、例えばH型鋼からなる受け部材(荷重
受け部材)30を配置するようになっている。この受け
部材30は、その上面にアウトリガー26の接地部が当
接するようになっており、この状態でアウトリガー26
の接地部と受け部材30の上部フランジとは、クランプ
金具31によって着脱自在に固定されるようになってい
る。この受け部材30は、揚重機走行レール23と同様
に、梁12,12の間隔に対応した長さを有しており、
さらにその両端部の下面には、所定厚さのベース部材3
2が設けられている。図4に示したように、このベース
部材32は、アウトリガー26を受ける位置に対してオ
フセットしており、これによりアウトリガー26を介し
て揚重機22の荷重が作用し、受け部材30が撓んで
も、その下面が床13の上面に接触するのを防止するよ
うになっている。
Further, a receiving member (load receiving member) 30 made of, for example, H-section steel is disposed at a position where the outrigger 26 of the hoisting machine 22 is received. The grounding portion of the outrigger 26 comes into contact with the upper surface of the receiving member 30, and in this state, the outrigger 26
The grounding portion and the upper flange of the receiving member 30 are detachably fixed by a clamp fitting 31. The receiving member 30 has a length corresponding to the interval between the beams 12, 12, like the hoisting machine traveling rail 23,
Further, a base member 3 having a predetermined thickness is provided on the lower surface at both ends.
2 are provided. As shown in FIG. 4, the base member 32 is offset with respect to the position where the outrigger 26 is received, so that even if the load of the hoisting machine 22 acts via the outrigger 26 and the receiving member 30 bends. The lower surface is prevented from contacting the upper surface of the floor 13.

【0028】一方、搬送装置21は、例えば電動走行式
の搬送台車35と、2本一対のレールが一体にユニット
化された台車用レール36とから構成されている。図6
に示すように、搬送台車35は、走行車輪37aを備え
たベース枠37の上面に荷台38が形成され、さらに荷
台38の両側に側枠39が設けられた構成となってい
る。この搬送台車35は図示しないモーター等によって
走行車輪37aを駆動することによって、台車用レール
36上を自走可能となっている。図4に示したように、
この台車用レール36は、揚重機22の揚重機走行レー
ル23等と同様、躯体10の梁12,12のピッチに対
応した長さを有している。この台車用レール36につい
ても、揚重機走行レール23や受け部材30と同様に、
その両端部下面には、図示しないベース部材が設けられ
ており、各ベース部材は、搬送台車35の荷重を受ける
位置に対してオフセットしており、これにより搬送台車
35の荷重が作用して台車用レール36が撓んでも、そ
の下面が床13の上面に接触するのを防止するようにな
っている。
On the other hand, the transfer device 21 is composed of, for example, an electric traveling transfer truck 35 and a truck rail 36 in which a pair of two rails are unitized integrally. FIG.
As shown in (1), the carrier 35 has a configuration in which a carrier 38 is formed on the upper surface of a base frame 37 provided with running wheels 37a, and side frames 39 are provided on both sides of the carrier 38. The transport vehicle 35 can run on a truck rail 36 by driving a traveling wheel 37a by a motor (not shown) or the like. As shown in FIG.
The bogie rail 36 has a length corresponding to the pitch of the beams 12, 12 of the skeleton 10, like the hoisting machine traveling rail 23 of the hoisting machine 22 and the like. This bogie rail 36 is also similar to the hoisting machine traveling rail 23 and the receiving member 30,
Base members (not shown) are provided on the lower surfaces of both ends thereof, and each base member is offset with respect to a position where the load of the transport vehicle 35 is received. Even if the use rail 36 is bent, the lower surface thereof is prevented from contacting the upper surface of the floor 13.

【0029】上記のような揚重装置20と搬送装置21
とからなる揚重システムを用いて躯体10の施工階を構
築する方法について説明する。
The lifting device 20 and the transfer device 21 as described above
A method of constructing the construction floor of the skeleton 10 using the lifting system comprising

【0030】まず、躯体10の施工階の端部に、二組の
揚重機走行レール23,23を連結して設置する。そし
て、施工階の端部側に位置する揚重機走行レール23に
揚重機22を載せる。
First, two sets of lifting machine running rails 23 are connected and installed at the end of the construction floor of the frame 10. Then, the hoist 22 is placed on the hoist traveling rail 23 located at the end of the construction floor.

【0031】次いで、揚重機22を揚重機走行レール2
3上で自走させ、進行方向前方のもう一組の揚重機走行
レール23上に移動させる。そして、受け部材30を揚
重機22の両側にセットし、アウトリガー26を張って
揚重機22の荷重を受け部材30で受けるようにし、ア
ウトリガー26の接地面と受け部材30とをクランプ金
具31で一体に固定する。
Next, the lifting machine 22 is moved to the lifting rail 2
3 and move on another set of lifting machine traveling rails 23 in front of the traveling direction. Then, the receiving member 30 is set on both sides of the hoist 22, the outrigger 26 is stretched so that the load of the hoist 22 is received by the receiving member 30, and the ground surface of the outrigger 26 and the receiving member 30 are integrated with the clamp metal 31. Fixed to.

【0032】続いて、揚重機22のブーム27で後方の
揚重機走行レール23を吊り上げ、これを当該揚重機2
2が載っている揚重機走行レール23の前方側に移動さ
せて接続する。そして今度は、揚重機22を前方の揚重
機走行レール23に移動させた後、後方の揚重機走行レ
ール23をブーム27で吊り上げて前方に移動させる。
このときは、アウトリガー26を一旦縮めるが、受け部
材30はクランプ金具31によってアウトリガー26の
接地面に一体化したままとしておく。
Subsequently, the trailing hoist traveling rail 23 is lifted by the boom 27 of the hoist 22, and this is lifted by the hoist 2.
2 is moved to the front side of the lifting machine traveling rail 23 on which is mounted and connected. Then, after moving the hoist 22 to the front hoist traveling rail 23 this time, the rear hoist traveling rail 23 is lifted by the boom 27 and moved forward.
At this time, the outrigger 26 is once contracted, but the receiving member 30 is kept integrated with the ground surface of the outrigger 26 by the clamp metal 31.

【0033】この後は、上記動作を繰り返すことによっ
て、二組の揚重機走行レール23,23を交互に前方に
送り、いわば尺取り虫のように揚重機22を進行させる
ことができる。
Thereafter, by repeating the above operation, the two sets of lifting machine traveling rails 23, 23 are alternately sent forward, and the lifting machine 22 can be advanced like a so-called insect.

【0034】さらに、この揚重機22の後方側に、躯体
10の施工階端部との間に、搬送装置21用の台車用レ
ール36を例えば二組並行に敷設する。そして、各台車
用レール36上にそれぞれ搬送台車35を載せ、この後
は、これら搬送台車35を用いて、組み立てるべき柱1
1、梁12、床13等の部材や、延長用の台車用レール
36等を搬送するようにする。
Further, on the rear side of the hoisting machine 22, for example, two sets of truck rails 36 for the transporting device 21 are laid in parallel with the construction floor end of the frame 10. Then, the carriages 35 are mounted on the rails 36 for the carriages, respectively.
1, the members such as the beam 12, the floor 13, etc., and the rail 36 for the trolley for extension, etc. are transported.

【0035】そして、前記の二組の揚重機走行レール2
3,23を交互に用いて、揚重機22を順次施工階の反
対側の端部まで移動させつつ、その後方においては搬送
装置21用の台車用レール36を漸次延長していく。
Then, the two sets of the lift traveling rails 2
While the hoisting machine 22 is sequentially moved to the opposite end of the construction floor by using 3 and 23 alternately, the bogie rail 36 for the transfer device 21 is gradually extended behind the hoisting machine 22.

【0036】揚重機22が施工階の反対側の端部(この
場合の「端部」とは、ブーム27の旋回範囲が施工階の
外周部に位置する柱11等を組み立てることのできる位
置のことである)にまで到達したら、揚重機22の移動
を停止させる。
The end of the hoisting machine 22 on the opposite side of the construction floor (the "end" in this case is defined as a position where the turning range of the boom 27 can assemble the pillar 11 or the like located on the outer periphery of the construction floor. ), The movement of the lifting machine 22 is stopped.

【0037】この後、図2および図3に示したように、
搬送装置21の搬送台車35に、施工階の躯体10を構
成する柱11や梁12、床13等の部材を、順次揚重機
22の後方まで搬送し、搬送されてきた部材は揚重機2
2のブーム27で吊り上げ、施工階の所定位置に順次組
み付けていく。なお、このときの当該施工階の躯体10
の施工順序は、前記〜に示した通りの順序で作業を
行う(図1参照)。
Thereafter, as shown in FIGS. 2 and 3,
The members such as the pillars 11, the beams 12, and the floor 13, which constitute the building 10 on the construction floor, are sequentially transported to the rear of the hoisting machine 22 to the transporting cart 35 of the transporting device 21.
It is lifted by the second boom 27 and is sequentially assembled at a predetermined position on the construction floor. At this time, the skeleton 10 of the construction floor concerned is
The work is performed in the order shown in the above (1) (see FIG. 1).

【0038】このようにして、施工階の躯体10を構築
しながら、今度は揚重機22を順次後退させていく。こ
のときには、揚重機22を、二組の揚重機走行レール2
3,23のうち、後方側に位置する揚重機走行レール2
3に移動させる工程と、ブーム27で前方の揚重機走行
レール23を吊り上げて後方に移設し、この後に、揚重
機22を後退させる工程とを順次繰り返していく。搬送
装置21用の台車用レール36については、揚重機22
の後退に伴い、前端部の台車用レール36を取り外し、
これを搬送台車35で後方に撤去していけばよい。
In this manner, the crane 22 is sequentially retracted while constructing the frame 10 on the construction floor. At this time, the hoist 22 is connected to the two sets of hoist traveling rails 2.
3 and 23, the lift traveling rail 2 located on the rear side
3 and the step of lifting the front lifting machine traveling rail 23 by the boom 27 and moving the same rearward, and thereafter, the step of retracting the lifting machine 22 are sequentially repeated. For the truck rail 36 for the transfer device 21,
With the retreat, remove the truck rail 36 at the front end,
This may be removed rearward by the transport trolley 35.

【0039】このようにして揚重機22を後退させつ
つ、施工階の躯体10を反対側の端部から端部に向けて
揚重機22を用いて順次構築していけばよいのである。
In this way, it is only necessary to sequentially construct the building 10 on the construction floor from the opposite end to the end while using the crane 22 while retracting the crane 22.

【0040】上述したような構成によれば、大平面形状
の建物であっても、後施工となる部分が存在せず各階を
完全に施工することができるので、従って、躯体10を
下層から上層に積層構築していく工法を採用することが
可能となる。これにより、従来のように、後施工となる
部分が無くなるため、施工の効率化を図ることができ
る。また、後施工となる部分に足場や養生ネット等を設
ける必要がなく、仮設工事費を削減することができる。
しかも、各フロアーの躯体10が完全にできあがること
になるので、各階の設備や内装仕上げ工事などを早期に
着工することが可能となる。このようにして、建物の施
工効率を大幅に向上し、コストおよび工期を削減するこ
とが可能となる。
According to the above-described configuration, even in a large-plan building, each floor can be completely constructed without any post-construction portion. It is possible to adopt a construction method of layering construction. As a result, unlike the related art, there is no portion to be post-constructed, so that the efficiency of construction can be improved. In addition, there is no need to provide a scaffold, a curing net, or the like in a portion to be post-constructed, so that temporary construction costs can be reduced.
In addition, since the frame 10 of each floor is completely completed, it becomes possible to start construction of the equipment and interior finishing work of each floor at an early stage. In this way, it is possible to greatly improve the construction efficiency of the building, and to reduce the cost and the construction period.

【0041】また、揚重機走行レール23を二組を用
い、これを交互に前方に送りながら揚重機22を前進さ
せる構成としたので、最小限の揚重機走行レール23で
揚重機22の移動が可能となり、機材コストを最小限に
抑えることができる。
Also, since the lifting machine 22 is advanced by using two sets of the lifting machine traveling rails 23 and alternately sending them forward, the lifting machine 22 can be moved with the minimum lifting machine traveling rails 23. And equipment costs can be kept to a minimum.

【0042】さらに、受け部材30をアウトリガー26
の接地部にクランプ金具31で取り付けるようにしたの
で、一旦これを取り付けてしまえば、揚重機22の移動
にともなって受け部材30も自動的に移動することとな
り、受け部材30を別途盛り替える必要がなくなり、揚
重機22の移動を容易に行うことができる。
Further, the receiving member 30 is connected to the outrigger 26.
The receiving member 30 is automatically moved with the movement of the lifting machine 22 once the mounting member is attached to the grounding portion, so that the receiving member 30 needs to be separately rearranged. And the lifting machine 22 can be easily moved.

【0043】加えて、台車用レール36上を走行する搬
送台車35によって、組み立てるべき資材等を揚重機2
2の近傍位置まで搬送する構成となっている。これによ
り、組み立てるべき躯体10の構成部材や、揚重機走行
レール23等を搬送することができ、揚重機22自体は
躯体10の組立作業専用とすることができる。したがっ
て、揚重機22の利用効率を高め、施工を効率良く行う
ことができる。しかも、資材等を特定位置(台車用レー
ル36の端部)から荷揚げすることができ、外周部にス
ペースが少ない現場においても作業を円滑に行うことが
できる。
In addition, materials to be assembled and the like are transported by the carriage 35 traveling on the carriage rail 36 to the hoist 2.
2 is conveyed to a position in the vicinity. Thus, the components of the skeleton 10 to be assembled, the lifting rail 23, and the like can be transported, and the hoist 22 itself can be dedicated to the assembling work of the skeleton 10. Therefore, the utilization efficiency of the lifting machine 22 can be increased, and the construction can be performed efficiently. Moreover, materials and the like can be unloaded from a specific position (the end of the trolley rail 36), so that work can be performed smoothly even in a site where there is little space in the outer peripheral portion.

【0044】また、揚重機22の揚重機走行レール23
を、直下階の梁12上に設置するようにしたので、床1
3のコンクリート上には一切揚重機22の荷重がかかる
ことがなく、揚重装置20の使用にともなう床13のコ
ンクリートのひび割れなどを防止することができる。
Also, the lifting machine traveling rail 23 of the lifting machine 22
Is installed on the beam 12 directly below the floor.
The load of the hoisting machine 22 is not applied on the concrete of No. 3 at all, and it is possible to prevent the concrete on the floor 13 from cracking due to the use of the hoisting device 20.

【0045】しかも、アウトリガー26を受ける受け部
材30についても、その下面にはベース部材32を設
け、揚重機22の荷重により受け部材30が撓んでも、
既に施工した直下階の床13の上面に接触することがな
く、コンクリート面のひび割れなどを防止することがで
きる。
Further, the base member 32 is provided on the lower surface of the receiving member 30 for receiving the outrigger 26, and even if the receiving member 30 is bent by the load of the hoisting machine 22,
It is possible to prevent the concrete surface from cracking or the like without contacting the upper surface of the floor 13 of the immediately lower floor already constructed.

【0046】加えて、搬送装置21の揚重機走行レール
23および台車用レール36ついても、同様にして直下
階の梁12にその荷重を支持させる構成としたので、こ
れについても床13のコンクリートのひび割れなどを防
止することができる。
In addition, the lifting device running rail 23 and the bogie rail 36 of the transfer device 21 are similarly configured to support the load on the beam 12 on the immediately lower floor. Cracks and the like can be prevented.

【0047】上記躯体10の構築方法では前記〜に
示したように躯体10を下層から上層に積層していく工
法を採用しているので、この工法に上記揚重装置20と
搬送装置21とを用いた施工方法を適用することによ
り、より効果的に施工を行うことが可能となる。
In the method of constructing the skeleton 10, the construction method of laminating the skeleton 10 from the lower layer to the upper layer as described above is adopted. Therefore, the lifting device 20 and the transfer device 21 are used in this method. By applying the construction method used, construction can be performed more effectively.

【0048】なお、上記実施の形態において、本発明を
適用する対象については、どのような建物であっても良
く、その形状や階高を何ら限定する意図はない。
In the above embodiment, the object to which the present invention is applied may be any building, and there is no intention to limit its shape and floor height.

【0049】また、上記の実施の形態では、搬送装置2
1を二組用いる構成としたがもちろんこれを一組のみと
してもよい。また、上記のような揚重装置20と搬送装
置21とからなる揚重システムを、複数組並行して用い
るようにしてもよい。さらに、揚重機22自体の構成
や、その他、使用する揚重機走行レール23の使用本数
等については何ら限定する意図はない。また、搬送台車
35などについても同様である。
In the above embodiment, the transfer device 2
Although two sets of 1 are used, it is needless to say that only one set may be used. In addition, a plurality of sets of the lifting system including the lifting device 20 and the transfer device 21 as described above may be used in parallel. Further, there is no intention to limit the configuration of the hoist 22 itself, the number of hoist running rails 23 to be used, and the like. The same applies to the transport carriage 35 and the like.

【0050】加えて、揚重機走行レール23,受け部材
30,台車用走行レール36にベース部材29,32,
(図示なし)を備える構成としたが、これについては、
揚重機走行レール23,受け部材30,台車用走行レー
ル36に予め一体化しておき、同時に盛り替え可能とす
る構成としても良いし、また、別個に独立させておく構
成としても良い。
In addition, the hoist lifting rail 23, the receiving member 30, and the bogie traveling rail 36 have the base members 29, 32,
(Not shown), but regarding this,
The lifting rail 23, the receiving member 30, and the bogie traveling rail 36 may be integrated in advance, and may be re-arranged at the same time, or may be separately and independently provided.

【0051】さらに、揚重機22を施工階の一端から他
端側に移動させつつ台車用レール36を敷設していき、
この後に揚重機22を後退させつつ躯体10を構築する
構成としたが、本願発明の主旨は揚重機22を施工階で
移動させながら躯体10を構築することにあり、例えば
台車用レール36を躯体10の外周側から他の揚重機等
で敷設する等してもよい。
Further, while moving the hoisting machine 22 from one end of the construction floor to the other end side, the truck rail 36 is laid.
After that, the structure 10 is constructed while the lifting machine 22 is retracted. However, the gist of the present invention is to construct the body 10 while moving the lifting machine 22 on the construction floor. It may be laid by another lifting machine or the like from the outer peripheral side of 10.

【0052】これ以外にも、本発明の主旨を逸脱しない
範囲内であれば、いかなる構成を採用しても良く、また
上記したような構成を適宜選択的に組み合わせたものと
しても良いのは言うまでもない。
Other than this, any configuration may be adopted as long as it does not depart from the gist of the present invention, and it goes without saying that the above-mentioned configurations may be appropriately selectively combined. No.

【0053】[0053]

【発明の効果】以上説明したように、請求項1に係る躯
体構築方法によれば、直下階の躯体上に敷設したレール
上で揚重機を移動させつつ、施工階の躯体を構築する構
成となっている。これにより、各階の施工を、当該階で
移動する揚重機で行うことができ、大型の揚重機を用い
る必要が無くなり、揚重機を効率的に使用することがで
きる。しかも、大平面形状の建物であっても、後施工と
なる部分が存在せず各階を完全に施工することができる
ので、躯体を下層から上層に積層していく工法を採用す
ることが可能となる。これにより、施工の効率化を図る
とともに、仮設工事費を削減することができ、コストお
よび工期を削減することが可能となる。
As described above, according to the method for constructing a skeleton according to the first aspect, the structure for constructing the skeleton on the construction floor while moving the lifting machine on the rail laid on the skeleton on the immediately lower floor. Has become. Accordingly, the construction of each floor can be performed by the lifting machine moving on the floor, and it is not necessary to use a large-sized lifting machine, and the lifting machine can be used efficiently. Moreover, even in a large flat building, there is no post-construction part and each floor can be completely constructed, so it is possible to adopt a construction method in which the skeleton is laminated from the lower layer to the upper layer. Become. As a result, construction efficiency can be improved, temporary construction costs can be reduced, and costs and construction periods can be reduced.

【0054】請求項2に係る躯体構築方法によれば、直
下階の躯体上に敷設するレールを直下階の梁上に支持さ
せて敷設する構成となっている。これにより、揚重機の
荷重は直下階の梁に伝わり、床には伝わらないことにな
る。したがって、揚重装置の使用にともなう床コンクリ
ートのひび割れなどを防止することができる。
According to the skeleton building method of the second aspect, the rail laid on the skeleton on the immediately lower floor is laid while being supported on the beam on the immediately lower floor. As a result, the load of the hoist is transmitted to the beams directly below the floor, and is not transmitted to the floor. Therefore, it is possible to prevent floor concrete from cracking due to the use of the lifting device.

【0055】請求項3に係る躯体構築方法によれば、二
本のレール部材を交互に前方に送りつつ揚重機を移動さ
せることにより、レール部材の本数が最小限で済み、ま
た揚重機の後方側においてはレールが順次撤去されるこ
とになるので、設備や内装仕上等の工事に着手すること
ができる。
According to the frame building method of the third aspect, by moving the lifting machine while alternately sending the two rail members forward, the number of rail members can be minimized, and the rear of the lifting machine can be maintained. Since the rails will be sequentially removed on the side, construction such as equipment and interior finishing can be started.

【0056】請求項4に係る躯体構築方法によれば、揚
重機の荷重を受ける荷重受け部材を、直下階の梁上に設
置する構成とし、かつ、荷重受け部材の下面にはベース
部材を設けておく構成としたので、揚重機の荷重は床に
は伝わらず直下階の梁に伝わり、しかも荷重受け部材が
直下階の床面に直接接触しないようになるので、コンク
リート面のひび割れなどを防止することができる。
According to the method for constructing a skeleton according to the fourth aspect, the load receiving member for receiving the load of the hoist is installed on the beam on the immediately lower floor, and the base member is provided on the lower surface of the load receiving member. The load of the hoist will not be transmitted to the floor, but to the beam on the lower floor, and the load receiving member will not directly contact the floor on the lower floor, preventing cracks on the concrete surface can do.

【0057】請求項5に係る躯体構築方法によれば、台
車用レール上を走行する搬送台車によって、組み立てる
べき資材等を揚重機の近傍位置まで搬送する構成となっ
ている。これにより、組み立てるべき躯体の構成部材
や、揚重機用のレール等を搬送することができ、揚重機
自体は躯体の組立作業専用とすることができるので、揚
重機の利用効率を高め、施工の迅速化を図ることができ
る。
According to the skeleton building method of the fifth aspect, the material to be assembled and the like are transported to a position near the hoist by the transport vehicle traveling on the rail for the vehicle. As a result, it is possible to transport the components of the skeleton to be assembled and rails for the hoist, etc., and the hoist itself can be dedicated to the assembling work of the skeleton. Speeding up can be achieved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明に係る躯体構築方法を適用する躯体の
基本的な組立工程を示す工程図である。
FIG. 1 is a process diagram showing a basic assembly process of a skeleton to which a skeleton building method according to the present invention is applied.

【図2】 前記躯体構築方法で躯体を組み立てている状
態を示す側面図である。
FIG. 2 is a side view showing a state where a skeleton is assembled by the skeleton building method.

【図3】 図2の平面図である。FIG. 3 is a plan view of FIG. 2;

【図4】 図3の要部を示す平面図である。FIG. 4 is a plan view showing a main part of FIG. 3;

【図5】 前記躯体構築方法に用いる揚重機の構成を示
す立断面図である。
FIG. 5 is an elevational sectional view showing a configuration of a hoist used in the skeleton building method.

【図6】 同方法に用いる搬送台車および台車用レール
を示す立断面図である。
FIG. 6 is a sectional elevational view showing a transport trolley and a trolley rail used in the method.

【図7】 従来の躯体構築方法の一例を示す図である。FIG. 7 is a diagram showing an example of a conventional frame building method.

【図8】 従来の躯体構築方法の他の一例を示す図であ
る。
FIG. 8 is a view showing another example of a conventional frame building method.

【図9】 従来の躯体構築方法のさらに他の一例を示す
図である。
FIG. 9 is a view showing still another example of the conventional frame building method.

【符号の説明】[Explanation of symbols]

10 躯体 12 梁 22 揚重機 23 揚重機走行レール(レール,レール部材,荷重受
け部材) 30 受け部材(荷重受け部材) 32 ベース部材 35 搬送台車 36 台車用レール
DESCRIPTION OF SYMBOLS 10 Frame 12 Beam 22 Lifting machine 23 Lifting machine running rail (rail, rail member, load receiving member) 30 Receiving member (load receiving member) 32 Base member 35 Carriage truck 36 Rail for truck

───────────────────────────────────────────────────── フロントページの続き (72)発明者 岡登 美紀雄 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 小城 源太郎 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 小寺 英夫 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 関 洋一 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 徳田 浩 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 Fターム(参考) 2E174 AA01 AA03 BA01 BA03 CA03 CA06 CA09 CA14 CA30 CA43 DA12 DA13 DA17  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Mikio Okato 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Gentaro Ogi 1-2-3, Shibaura, Minato-ku, Tokyo Shimizu Corporation (72) Inventor Hideo Kodera 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation (72) Inventor Yoichi Seki 1-2-3 Shibaura, Minato-ku, Tokyo Shimizu Corporation (72) Inventor Hiroshi Tokuda 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Corporation F-term (reference) 2E174 AA01 AA03 BA01 BA03 CA03 CA06 CA09 CA14 CA30 CA43 DA12 DA13 DA17

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 建物の躯体を構築する方法であって、先
に構築した直下階の躯体上にレールを敷設し、揚重機を
前記レール上で移動させつつ、前記直下階の上階の躯体
を構築することを特徴とする躯体構築方法。
1. A method for constructing a skeleton of a building, wherein a rail is laid on a skeleton on a directly lower floor previously constructed, and a lifting machine is moved on the rail while the cradle on the upper floor of the immediately lower floor is moved. A method for building a skeleton, comprising:
【請求項2】 請求項1記載の躯体構築方法であって、
前記直下階の躯体上に敷設するレールを、前記直下階の
躯体を構成する梁上に支持させて敷設することを特徴と
する躯体構築方法。
2. The method according to claim 1, wherein:
A method for constructing a skeleton, wherein a rail laid on the skeleton on the immediately lower floor is supported and laid on a beam constituting the skeleton on the immediately lower floor.
【請求項3】 請求項1または2記載の躯体構築方法で
あって、前記レールとして、所定長を有したレール部材
を少なくとも二組用い、一の前記レール部材上に前記揚
重機を載せ、該一のレール部材の前方に他の前記レール
部材を敷設した後、 前記揚重機を前方の前記レール部材上に移動させる工程
と、 前記揚重機の後方に位置する前記レール部材を、前記揚
重機でその前方に移動して敷設する工程とを交互に繰り
返すことによって、前記揚重機を前記躯体上で移動させ
ることを特徴とする躯体構築方法。
3. The method according to claim 1, wherein at least two sets of rail members having a predetermined length are used as the rails, and the lifting machine is mounted on one of the rail members. After laying another rail member in front of one rail member, a step of moving the hoist onto the rail member in front of the rail member, and the rail member located behind the hoist, A step of moving the hoist over the frame by alternately repeating the step of moving forward and laying the frame.
【請求項4】 請求項1から3のいずれかに記載の躯体
構築方法であって、前記揚重機の荷重を受ける荷重受け
部材を、前記直下階の躯体上に設置する構成とし、か
つ、前記荷重受け部材の下面には、前記揚重機からの荷
重で前記荷重受け部材が撓んだときにその下面が前記直
下階床面に直接接触しないよう、前記揚重機の荷重を受
ける部分に対してオフセットした位置にベース部材を設
けておくことを特徴とする躯体構築方法。
4. The method for constructing a skeleton according to claim 1, wherein a load receiving member for receiving a load of the lifting machine is installed on the skeleton on the immediately lower floor, and On the lower surface of the load receiving member, when the load receiving member is bent by the load from the hoist, the lower surface does not directly contact the floor directly below the floor, so that the portion receiving the load of the hoist A method for constructing a skeleton, wherein a base member is provided at an offset position.
【請求項5】 請求項1から4のいずれかに記載の躯体
構築方法であって、前記躯体の端部と前記揚重機の近傍
位置との間に、台車用レールを敷設し、該台車用レール
上を走行する搬送台車によって、組み立てるべき資材等
を前記揚重機の近傍位置まで搬送することを特徴とする
躯体構築方法。
5. The method for constructing a skeleton according to claim 1, wherein a trolley rail is laid between an end of the skeleton and a position near the lifting machine. A method for constructing a skeleton, wherein materials to be assembled and the like are transported to a position near the hoist by a transport trolley traveling on rails.
JP11013604A 1999-01-21 1999-01-21 Construction method of frame body Pending JP2000213168A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11013604A JP2000213168A (en) 1999-01-21 1999-01-21 Construction method of frame body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11013604A JP2000213168A (en) 1999-01-21 1999-01-21 Construction method of frame body

Publications (1)

Publication Number Publication Date
JP2000213168A true JP2000213168A (en) 2000-08-02

Family

ID=11837845

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11013604A Pending JP2000213168A (en) 1999-01-21 1999-01-21 Construction method of frame body

Country Status (1)

Country Link
JP (1) JP2000213168A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010265608A (en) * 2009-05-12 2010-11-25 Takenaka Komuten Co Ltd Method for moving skeleton, and structure
JP2011094456A (en) * 2009-11-02 2011-05-12 Ohbayashi Corp Load bearing base, supporting material, and load bearing method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010265608A (en) * 2009-05-12 2010-11-25 Takenaka Komuten Co Ltd Method for moving skeleton, and structure
JP2011094456A (en) * 2009-11-02 2011-05-12 Ohbayashi Corp Load bearing base, supporting material, and load bearing method

Similar Documents

Publication Publication Date Title
JP2023164951A (en) Heavy object movement device and heavy object movement method using the heavy object movement device
JP5769961B2 (en) Construction method and removal method of structure
JP2000213168A (en) Construction method of frame body
JP7299103B2 (en) Elevated structure construction system and construction method
JP3000090B2 (en) Assembling method of preassembled steel rebar
JPH07259334A (en) Bearing structure of form panel used for self-elevation type form device
JP2002339585A (en) Method for constructing multistory parking facility and crane for use therein
JP6618116B2 (en) Construction method of pier
JP7330411B2 (en) Floor slab moving method and floor slab moving device
JP2003343087A (en) Conveying equipment and working method for building site
JP2768281B2 (en) Bridge construction method
JP3471248B2 (en) Portal crane
JP2768279B2 (en) Construction girder for precast block method
JPH10316365A (en) Installation structure for heavy object conveying crane in pit
JP3121224B2 (en) Assembling / arrangement of reinforcing bars for culverts
JP3042677B2 (en) Reinforcing bar arrangement device and method
JP2761518B2 (en) Construction method of building
JP2792330B2 (en) Temporary beam assembly equipment for building construction
JP2017160680A (en) Vehicle loading-type lifter and bridge construction method
JP2835880B2 (en) High-rise building frame construction method
JP2001171975A (en) Heavy cargo carrying-in method into building and heavy cargo carrying-out method out of building
JP2530453B2 (en) Ceiling construction method and equipment for large span structures
JP2580880Y2 (en) Parking pallets
JPH07324487A (en) Horizontal conveying system
JPH11280262A (en) Carrying method of concrete panel and device therefor

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20031209