IE41580B1 - Improvements in or relating to martime assemblies - Google Patents

Improvements in or relating to martime assemblies

Info

Publication number
IE41580B1
IE41580B1 IE1529/75A IE152975A IE41580B1 IE 41580 B1 IE41580 B1 IE 41580B1 IE 1529/75 A IE1529/75 A IE 1529/75A IE 152975 A IE152975 A IE 152975A IE 41580 B1 IE41580 B1 IE 41580B1
Authority
IE
Ireland
Prior art keywords
raft
tower structure
tower
foundation
foundation raft
Prior art date
Application number
IE1529/75A
Other versions
IE41580L (en
Original Assignee
Redpath Dorman Long Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Redpath Dorman Long Ltd filed Critical Redpath Dorman Long Ltd
Publication of IE41580L publication Critical patent/IE41580L/en
Publication of IE41580B1 publication Critical patent/IE41580B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/01Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells specially adapted for obtaining from underwater installations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/02Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/003Supports for the drilling machine, e.g. derricks or masts adapted to be moved on their substructure, e.g. with skidding means; adapted to drill a plurality of wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Aerials With Secondary Devices (AREA)
  • Foundations (AREA)

Abstract

1512634 Building and launching offshore structures REDPATH DORMAN LONG (NORTH SEA) Ltd 23 July 1975 [23 July 1974] 32513/74 Heading E1H A maritime platform assembly is constructed by first stabilizing a foundation raft 132 on supports 121, 122 alongside quay 123. Structure 133, 134 is then moved from the quay onto the raft, secured thereto and the assembly so formed is floated away from the quay side. Specifications 1512635, 1512636, 1485755, 1501861 are referred to.

Description

The invention relates to the building of maritime assemblies for incorporation inter alia into oil production platforms. The invention is particularly but not exclusively concerned with the building of hybrid gravity platforms in which a steel tower structure extends upwardly from a foundation raft set on a sea bed.
To produce oil from deep sea locations, production platforms can be founded on the sea bed and then have oil wells drilled outwardly therefrom. The platforms should be securely located on the sub aqua terrain; and to this end it has been proposed to build concrete platforms in which concrete towers extend upwardly from massive concrete bases. Such platforms suffer from at least three major disadvantages.
Firstly since the current method of building a concrete platform is to start at the base, and to continue pouring concrete until the top is reached, it is not possible to fabricate concurrently sub assemblies for different heights above the base.
Secondly it has been found difficult to secure suitable sites for construction yards. This has been due in part to the need for sites to be located adjacent to sheltered deep water close in-shore at localities where both adequate transport facilities and the necessary skilled personnel are readily available.
Thirdly, due to their great mass, concrete platforms impose high stresses on the sea bed, which limits their use to ground conditions capable of resisting these stresses.
As an alternative to an all concrete gravity platform it has been proposed to build hybrid platforms in which a concrete (or steel) foundation raft supports a steel jacket or tower structure. This alternative enables work to proceed concurrently on the tower structure and the foundation raft, thus allowing a quicker construction programme. Moreover the work can be carried out without the need for deep water close inshore, and results in a lighter structure which can be adapted to.a wider range of seabed soil conditions.
However, difficulties arise in joining the two parts together. For instance it has been proposed to sink the foundation raft at its installation site, and then lower the tower structure on to it as described in Patent Specification No. 39145. Another proposal has been for the tower structure to be lowered onto the foundation raft when the latter has been temporarily submerged in a Sheltered deep water fiord; the foundation raft is then raised, a permanent joint effected, and the completed assembly Is thereafter towed off to its intended site as described in British Patent Specification No. 1,501,861. Both these proposals involve accurate alignment of the parts to be joined while those parts are deep under water.
It is desirable for towage considerations to reduce the built in weight which must be floated out with the platform. As a consequence of reducing the weight the initial draft of the platform can be reduced, so widening the choice of sites for a construction yard. - 4 In particular, existing sites dould be used to construct shallow draft hybrid platforms without the need to create new sites in hitherto undeveloped areas.
The invention provides a method of fabricating a 5 maritime platform assembly intended to be founded on the sea bed, comprising the steps of stabilising a sinkable foundation raft so that part of its undersurface rests on a support alongside a fixed quay, translationally moving at least substantially the whole of an erect tower structure, comprising a wave-penetrable three-dimensional framework, from land adjacent the quay onto the foundation raft, permanently securing the tower structure to the foundation raft, and floating the assembly so formed away from the quayside site.
In one preferred form the foundation raft is floated to the quayside site at which it is stabilised.
In this form it is further preferred that the foundation raft is floated to the quayside site in the form of several raft sections.
Conveniently the tower structure is slid down a skidway extending from land adjacent to the quay to the foundation raft.
It is preferred that the skidway has removable 25 portions on the foundation raft arranged to overlie inboard leg portions for the tower structure.
It is also preferred that the tower structure is supported on rotation saddles used to locate base member on the tower platform, and the saddles are disposed over sledge positions for sledges arranged to slide down the skidway.
It is further preferred that the skidways on the foundation raft overlie intermediate walls in the foundation raft structure.
Advantageously the tower structure is lowered onto the foundation raft using sandjacks to transfer the weight of the tower structure onto appropriate lands on the foundation raft.
If necessary the completed assembly is floated away from the quayside site with the aid of temporary floatation aids fixed to the foundation raft.
According to a feature of the invention the tower structure is fabricated by the steps of constructing two side frame elements on the ground with their bases occupying their respective places on the platform of the completed tower, and then raising the side frame elements to a generally vertical position by pivotal action about their respective bases, and joining adjacent edges of the side frame elements.
It is preferred that the tower structure is fitted at least partially over a rearing tower disposed on the platform of the tower structure between the side frame elements.
It is further preferred that the pivotal action is effected by a sideways force acting through a point on the rearing tower above the level at which the frame was constructed.
In one form of the invention incorporating the aforesaid feature the two side frame elements are raised and their adjacent edges are then joined by two further side frame elements which are themselves pivotally raised about their respective base : on the platform of the tower structure.
Alternatively the two side frame elements are in the form of, three-dimensional lattice frameworks which, when raised,' substantially fill the space betweei them in their erect position.
In this alternative form it is preferred that a rearing tower for raising the side frame elements is located between them, and the erected tower structure can subsequently be moved away laterally over the rearing tower without disturbing it.
It is further preferred that sub-assemblies for the lattice frameworks are themselves constructed horizontally and are then raised by pivotal action about leg tubulars intended to assume vertical or near vertical positions in the completed tower structure.
The opposed side frame elements may be raised simultaneously.
It is preferred that the bases are rotatable upon sledges capable of moving the tower structure to any location along a skidway.
The axes of rotation may be perpendicular to or parallel the skidway.
Conveniently the bases of the side elements are tubulars capable of rotation in saddles, and stub axle extensions may be fitted to the base tubulars to give additional load bearing capacity during rotation.
According to another feature of the invention the foundation raft is constructed of raft sections which are made on dry land, and are then loaded out using sinkable pontoons brought into a dry dock, or sunk onto a sea bed adjacent the building area.
In one form the raft sections are joined together whilst floating using pre or post tensioned cables in one or more of the sections.
Alternatively the raft sections are joined 30 together on hard pads or ground beams sunk on to a sea bed at a shallow water location.
Preferably grouting material is added to the raft - 7 sections after they have been joined together by using floating seals arranged to confine the grouting material.
The invention includes maritime assembly in accordance with the method of the invention.
Some specific embodiments of the invention will now be described by way of example with reference to the accompanying drawings in which: Figures la and b to 6a and b show in plan and section respectively successive stages in the fabrication of a foundation raft for a hybrid maritime assembly and the connection-of a tower structure to that foundation raft.
Figure 7 is a diagrammatic perspective view showing how a raft section can be moved onto a pontoon.
Figure 8 is a plan illustrating an alternative method to that shown in Figure 4a for joining sections of the foundation raft together.
Figure 9 i.s a cross-section on Figure 8.
Figure 10 is a perspective view of a partially completed raft.
Figure 11 is a diagrammatic side view showing a second method of fabricating a tower structure and connecting that tower structure to a foundation raft.
Figure 12 is a perspective view showing early stages in a third method of fabricating a tower structure.
Figure 13 is a side view illustrating later stages of the method begun in Figure 12.
Figure 14 is a perspective view showing the tower structure of Figure 13 being moved down a pair of skidways , and Figure 15 shows that tower structure being moved onto a foundation raft.
In the description relating to Figures 1 to 6 all the 'a' suffix drawings are plans, and all the 'b' suffix drawings are longitudinal sections corresponding to those plans.
Figures la and lb show two docks 21 and 22 separated by a finger jetty 23, bounded at its seaward end by a quay face 24. A submersible pontoon 25 has been introduced into the dock 21, and has been ballasted to sink on the dock bed; while a similar pontoon (26) is just being moved into dock 22.
A concrete foundation raft section 27 is constructed on top of the pontoon 25, or alternatively is moved onto it down tracks 42 as shown in Figure 7.
When the raft section 27 is sufficiently formed the pontoon 25 is pumped out, floated off the dock bed, and then moved out of the dock, as shown in Figures 2a and 2b. In deeper water a small distance off shore the pontoon 25 is sunk, and the raft section 27 is left floating as shown in Figures 3a and 3b. If the section 27 has not already been completed it can be moved alongside the quay 24, where further concrete can be poured.
In any case the pontoon 25 is freed from its burden, so that it can be moved back into the dock 21 where the process can be repeated to produce a second raft section (28).
While the raft sections 27 and 28 are being constructed in dock 21 two further raft sections 29 and 30 can be constructed in dock 22. Clearly one dock could be used four times, or four docks could each be used to produce one raft section, but for scheduling reasons it is convenient to use each of two docks twice.
In a varient (not illustrated) the docks 21 and could be transformed into dry docks by using floating gates, so that the pontoons could be dispensed with.
The raft section 27 to 30 are of cellular concrete construction, reinforced with intermediate beams 19 (Fig. 9) to receive tower legs and to rest on ground beams or pads. The raft sections include internal column locating bolts, and pre and post stressing bars. Additionally they may be adapted to provide oil storage tanks.
Figures 4a and 4b show a composite foundation raft 32 formed by joining the four raft sections 27 to 30 in end to edge relationship while they are afloat, so to form a square raft with a central aperture 33.
From the plan view it can be seen that one end of each section abuts and·, is fixed to one side of the next section. When the'sections have been joined, additional concrete can be poured to complete the raft.
While the foundation raft has been described as being made of concrete it could alternatively be made of steel.
The completed raft 32 is next floated to a position against a sea wall, which may conveniently be the quay face 24. To stabilize the raft sand 31 may be pumped underneath it to provide support as shown in Figure 5b.
Alternatively resiliently capped reinforced concrete pads 43 are cast onto bed rock just off the quayside or sea wall as shown in plan in Figure 8 and in section in Figure 9. The pads provide a base upon which the combined foundation raft can be assembled and then stabilized for installation of an erect tower structure.
The raft sections are brought individually to the site, and the section 27 is stabilized alongside the sea wall 24. The sectioh 28 is positioned in end to edge relationship therewith using cables 45, and is then drawn into its appropriate position on the pads 43 Subsequently the sections 29 and 30 (shown in chain dotted lines in Figure δ) are similarly located and sunk onto the pads.
The raft sections may be ballasted onto the pads 43 by admitting water only to the midside compartments thus leaving the corners of the foundation raft empty for subsequent assembly work when the tower legs are placed thereon. Floatable seals beneath the raft sections may be used to confine grouting material used in the joining procedure.
While the foundation raft is being constructed a a tower structure 40 may concurrently be fabricated on an adjacent shore site.
As shown in Figure 5a four side frames 101 to 104 of the tower structure are laid out on the ground and welded up with their bases 105 to 108 (i.e. their tubulars which will rest on the raft) occupying the platform of the tower structure, and hinged for rotation about the axes of those tubulars. When the four side frames have been welded up at ground level they are swung upwardly by cranes and/or tackle mounted on rearing towers to form the tower structure, and adjacent edges of the side frames are welded together by means of ties. In this way each of the four corners of the tower structure is constituted by a twin leg formed by the longitudinals (e.g. 109 and 110) of adjacent side frames. At this stage cross bracing can if necessary be welded in situ to strengthen the tower structure.
Advantageously the pivot arrangements for raising the side fr; mes would be mounted directly on a sledge unit, and a suitable ground beam would be installed between the sledges supporting opposite side frames in order to prevent movement during rearing.
It will be understood that while the tower structure in Figure 5a is square, with four identical side frames, the technique of fabricating side frames on the ground and then pivoting them upwardly to form a tower structure can be used to erect any generally planar components if their base lines are spaced apart and lie on the platform of the tower structure.
As shown in Figure 5b the completed tower structure (or jacket) 40 is slid onto the stabilized foundation raft 32 on sledges (not shown). In order to equalise (as far as possible) the jacket leg loads during sledging the sledges are arranged centrally between each pair of corner legs (109 and 110) and support the legs on a transverse beam between them. Allowance is made in the concrete raft sections to allow the tower structure to be slid on at this stage. When the tower structure is in position it can be secured to the foundation raft, and when this has been done the assembly can be completed. Clearly advantages are gained by doing this adjacent the yard in which the tower structure was fabricated.
The addition of the tower structure adds considerable weight on top of the foundation raft, and to float the assembly off the sand positioned beneath it the raft sections can be pumped out.
The raft is preferably designed to have sufficient buoyancy (when the raft sections 27 to 30 have been pumped out) to float the assembly off the sand 31. However if additional buoyancy is need the pontoons 25 and 26 can be submerged on either side of the assembly, attached thereto, and floated out to sea as shown in Figures 6a and 6b.
In order to give additional stability while the assembly is being towed to its installation area, and during the subsequent sinking operation to the sea bed, steel cylinders 41 are added to the corners, and if necessary to the midpoints of the sides, of the foundation raft.
The cylinders 41 may a(j(3 sufficient buoyancy to the assembly to pull the centre of buoyancy above the centre of gravity when they become fully submerged, and permit the foundation raft to be fully flooded, thus protecting the raft against excessive differential water pressures during the sinking operation. These cylinders may be detachable from the assembly when it is installed on its production site, for re-use on another assembly, or may remain in position on the completed production platform to form an oil storage facility. The installation of the cylinders is shown in Figure 10, whioh shows a cylinder being slid onto the foundation raft along a track way 47, whereafter it is erected using a crane 48, and bolted to other such cylinders to form a cluster.
When on site, production wells can be passed through the aperture 33. The provision of an aperture in the middle of the foundation raft diminishes the danger from a well blow out. Also, in the event of sliding, the aperture will allow the production wells to deflect without shearing the down pipes, as would happen with a solid based raft.
The sliding resistance of the assembly can be improved by placing sand or gravel within the rim or shield consisting of the raft elements surrounding the aperture 33. The weight of the sand or gravel may be used to force shear keys through soft layers of sea bed - 13 strata when necessary. External anti scouring protection can be added in the form of hinged panels (or a downwardly extending skirt) on the outside of the foundation raft, and any space between the base of the foundation raft and the sea bed can be back filled with sand.
Referring now to Figure 11, illustrating a second embodiment of the invention, a tower structure is erected on a site 124 at the head of a slipway 125 (the slope of which is greatly exaggerated in the drawing-the actual slope being 1:100). In this case the tower structure is erected in two halves 133 and 134 with its feet 126 resting on sledges 127. The two halves are pivoted about their base lines perpendicular to the direction of the Slipway 125; that is from the positions shown in dotted lines to the positions shown in full lines on the left hand side of figure 11.
When the tower structure is substantially complete the sledges 127 are moved down the slipway to position 128. At this stage the space between the sledges is filled with a temporary track 129 level with corresponding tracks on the combined raft 132. As shown in Figure 11 reinforced concrete ground beams 121 (upon which the combined foundation raft can rest) are cast onto bed rock 122 just off the quayside or sea wall 123. When the raft sections have been sunk onto the ground beams, and prior to the pull out step, the joints between the raft sections can be grouted. The sledge nearest the foundation raft is kept apart from the raft by spacers 131, and the feet 126 of the tower structure are pulled out to their position in the completed assembly.
A third and preferred technique for raising the tower structure is shown in figures 12 and 13. In this case the two halves of the tower structure are assembled with their base tubulars lying on its platform parallel ι to and overlying the slipways upon which the completed tower structure will be slid onto a foundation raft; thus the '.ower halves initially lie perpendicular to the slipway. As shown particularly in figure 12 sub assemblies, such as 150 (as shown in dotted lines), are constructed very close to ground level as flat frames. The nodes of the sub assembly 150 are supported on concrete Standings 151, and saddle assembles 152 are arranged along what will become one leg of the completed tower structure. When the sub assembly 150 is complete, it is reared as illustrated by the dotted line 153 so that it lies in a vertical plane. Similarly another sub assembly 154 is constructed for rotation about the axis of another of the legs of the completed tower structure.
The space between the two sub assemblies 150 and 154 is then spanned by cross members 155 and an integral super-structure support assembly or deck 156. It will be appreciated that all this work is done close to ground level, and so is less susceptible to interference by adverse weather conditions. When the sub assemblies have been raised,the base tubular 160 is extended with stub axles 157, and is supported on rearing saddles 158.
While the tower halves are being assembled, two rearing towers 159 are erected between the two halves of the tower structure. The rearing towers are stayed by cables 161, and are connected to the super structure support assemblies 156 by rearing cables 162.
Referring now to figure 13 the two half tower assemblies lie flat on the ground with their bases lying along the slipways 163 and 164. When the cross members 155 have been fitted, the rearing cables 162 and high cranes 165 are used to pivot the tower halves simultaneously about tho base tubulars lying on the tower platform into the position shown in chain dotted lines 166. As the tower halves pass over top dead centre the rearing cables 162 become unloaded, and support cables 167 prevent the two sides of the tower structure from overturning and fouling the rearing towers.
A small amount of infill bracing 168 can now be added, and the tower structure is then able to slide down the slipways 163 and 164 over the rearing towers onto a foundation raft.
The tower structure described above can be made of small diameter tubulars, which are relatively transparent to approaching waves, and moreover require little internal stiffening.
Figures 14 and 15 illustrate a third and preferred technique for placing an erect tower structure on a foundation raft. In this case the tower structure 166 has been reared in two halves 169 and 170, by pivotal action on axes overlying two skidways 163 and 164.
The tower structure 166 is lowered onto sledges 171 overlying! the skidways using sandjacks, and is then moved clear of the rearing towers to the position shown in chain dotted lines in Figure 15, where intermediate frame members 178 between the two tower halves are completed.
The erect tower structure is then moved down the skidways and over a fender 172 spanning the gap 174 and so onto the foundation raft 179. The skidways on the foundation raft are removable and overlie intermediate beams 19. The legs 175 of the jacket are designed to fit onto precast bolted connections 176 on the raft sections, and are lowered thereonto using further sand jacks 177. Thereafter the legs can be bolted down - 1δ using tensile bolts and then grouted up.
It will be appreciated that clusters of cylinders (not shown in figure 14) can be disposed on the four corners of the foundation raft, and at the mid points of the three sides away from the skidways without hindering movement of the tower structure onto the foundation raft.

Claims (28)

1. A method of fabricating a maritime platform assembly intended to be founded on the sea bed, comprising the steps of stabilising a sinkable foundation raft so that part of its undersurface rests on a support alongside a fixed quay, translationally moving at least substantially the whole of an erect tower structure comprising a wave penetrable three dimensional framework, from land adjacent the quay onto the foundation raft, permanently securing the tower structure to the foundation raft, and floating the assembly so formed away from the quayside site.
2. A method as claimed in claim 1 in which the foundation raft is floated to the quayside site at which it is stablised.
3. A method as claimed in claim 2 in which the foundation raft is floated to the quayside site in the form of several raft sections.
4. A method as claimed in any one of the preceding claims in which the tower structure is slid down a skidway extending from land adjacent to the quay to the foundation raft.
5. A method as claimed in claim 4 in which the skidway has removable portions on the foundation raft arranged to overlie inboard leg portions for the tower structure.
6. A method as claimed in claim 4 or claim 5 in which the tower structure is supported on rotation saddles used to locate a tubular base member on the tower platform, and the saddles are disposed over sledge positions for sledges arranged to slide down the skidway.
7. A method as claimed in any one of claims 4 1580 to 6 in whioh the skidways on the foundation raft overlie intermediate walls in the foundation raft structure.
8. A method as claimed in any one of the preceding claims in which the tower structure is lowered onto the foundation raft using sandjacks to transfer the weight of the tower structure onto appropriate lands on the foundation raft.
9. A method as claimed in any one of the preceding claims in which the completed assembly is floated away from the quayside site with the aid of temporary floatation aids fixed to the foundation raft.
10. A method as claimed in any of the preceding claims in Which the tower structure is fabricated by the steps of constructing two side frame elements on the ground with their bases accupying their respective places on the platform of the completed tower, and then raising the side frame elements to a generally vertical position by pivotal action about their respective bases, and joining adjacent edges of the side frame elements.
11. A method as claimed in claim 10 in which the tower structure is fitted at least partially, over a rearing tower disposed on the platform of the tower structure between the side frame elements.
12. A method as claimed in claim 11 in which tht pivotal action is effected by a side-ways force acting through a point on the rearing tower above the level at which the frame was constructed.
13. A method as claimed in any one of the preceding claims 10 to 12 in which the two side frame elements are raised, and their adjacent edges are then joined by two further side frame elements which are themselves pivotally raised about their respective bases on the platform of the tower structure.
14. A method as claimed in any one of claims 10 to 12 in which the two side frame elements are in the form of three-dimensional lattice frameworks which, when raised, substantially fill the space between them in their erect position.
15. A method as claimed in claim 14 in which a rearing tower for raising the side frame elements is located between them, and the erected tower structure can subsequently be moved away laterally over the rearing tower without disturbing it.
16. A method as claimed in claim 14 or claim 15 in which sub-assemblies for the lattice frameworks are themselves constructed horizontally and are then raised by pivotal action about leg tubulars intended to assume vertical or near vertical positions in the completed tower structure.
17. A method as claimed in any one of the preceding claims 10 to 16 in which opposed side frame elements are raised simultaneously.
18. A method as claimed in any one of the preceding claims 10 to 17 in which the bases are rotatable upon sledges capable of moving the tower structure to any location along a skidway.
19. A method as claimed in claim 18 in which the axes of rotation are perpendicular to the skidway.
20. A method as claimed in claim 18 in which the axes of rotation are parallel to the skidway.
21. A method as claimed in any one of the preceding claims 10 to 20 in which the bases of the side elements are tubulars capable of rotation in saddles.
22. A method as claimed in claim 21 in which stub axle extensions are fitted to the base tubulars to give additional load bearing capacity during rotation.
23. A method as claimed in any one of the preceding claims in which the foundation raft is constructed of raft sections which are made on dry land, and are then loaded out using sinkable pontoons brought into a dry dock, or sunk onto a sea bed adjacent the building area.
24. A method as claimed in claim 23 in which the raft sections are joined together whilst floating using pre or post tensioned cables in one or more of the sections.
25. A method as claimed in claim 23 in which the raft sections are joined together on hard pads or ground beams sunk on to a sea bed at a shallow water location.
26. A method as claimed in any one of claims 23 to 25 in which grouting material is added to the raft sections after they have been joined together by using floatable seals arranged to confine the grouting material.
27. A method substantially as hereinafter described with reference to Figures la to 6b, Figures 11, or Figure 7 to 10 and 12 to 15 of the accompanying drawings.
28. A maritime assembly constructed in accordance with any one of the preceding claims.
IE1529/75A 1974-07-23 1975-07-09 Improvements in or relating to martime assemblies IE41580B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB32513/74A GB1512634A (en) 1974-07-23 1974-07-23 Maritime assemblies

Publications (2)

Publication Number Publication Date
IE41580L IE41580L (en) 1976-01-23
IE41580B1 true IE41580B1 (en) 1980-01-30

Family

ID=10339753

Family Applications (1)

Application Number Title Priority Date Filing Date
IE1529/75A IE41580B1 (en) 1974-07-23 1975-07-09 Improvements in or relating to martime assemblies

Country Status (5)

Country Link
BR (1) BR7504674A (en)
DK (1) DK334975A (en)
GB (1) GB1512634A (en)
IE (1) IE41580B1 (en)
ZA (1) ZA754471B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2187778A (en) * 1986-03-03 1987-09-16 Earl & Wright Ltd Offshore platform with two jacket portions
EP2511423B1 (en) * 2011-04-15 2017-03-22 Siemens Aktiengesellschaft Jacket structure and method of assembling such a jacket structure
EP2511424B1 (en) * 2011-04-15 2017-07-12 Siemens Aktiengesellschaft Jacket assembly guide

Also Published As

Publication number Publication date
BR7504674A (en) 1976-07-06
IE41580L (en) 1976-01-23
ZA754471B (en) 1976-07-28
DK334975A (en) 1976-01-24
GB1512634A (en) 1978-06-01

Similar Documents

Publication Publication Date Title
JPS6315381Y2 (en)
US3896628A (en) Marine structures
US5125769A (en) Floatable structure
US20220002961A1 (en) Suction Anchors and Their Methods of Manufacture
FI80747B (en) SJOEBUREN PLATTFORM AV ARMERAD BETONG.
US4080916A (en) Maritime platform assemblies
GB1503208A (en) Offshore marine structures and methods for the construction thereof
US2598329A (en) Offshore drilling platform and method of constructing same
US4767238A (en) Method of accurately positioning a prefabricated structure on the sea bed or on a river bed by grounding, and a sea or a river construction obtained by said method
KR101703441B1 (en) Cassion manufacturing method of bottom-up, pre-cast and a base plate type using floating dock, system, floating dock and cassion using thereof
RU2310721C1 (en) Protection device to protect self-elevating floating drilling installation for exploratory well drilling in ice conditions and method for protection device construction
CA1078631A (en) Oil-production platform and method of assembling and installing the same on a sea bed
IE41580B1 (en) Improvements in or relating to martime assemblies
JPH09268562A (en) Dry working method and working case employed therefor
CN212452552U (en) Deposit and beat integrative low wave influence offshore construction platform
GB2182375A (en) Method of constructing an offshore structure
US2935854A (en) Offshore drilling platform
De Wit et al. North/South Metro Line, Amsterdam, The Netherlands Technical challenges in immersed tunnelling
CN218969958U (en) Assembled ocean platform module and ocean platform
GB2518356A (en) Method of suspension bridge construction
US1394571A (en) Subaqueous structure and method
JP3377756B2 (en) Bridge
US12000375B1 (en) Mobile modular platforms and method for near-shore assembly of floating offshore wind turbines
CN214574092U (en) Prefabricated assembly bottom sealing structure for bearing platform concrete in tidal water
CN215906728U (en) Floating type drilling construction platform