GB2289078A - Improved soil nail installation - Google Patents

Improved soil nail installation Download PDF

Info

Publication number
GB2289078A
GB2289078A GB9508961A GB9508961A GB2289078A GB 2289078 A GB2289078 A GB 2289078A GB 9508961 A GB9508961 A GB 9508961A GB 9508961 A GB9508961 A GB 9508961A GB 2289078 A GB2289078 A GB 2289078A
Authority
GB
United Kingdom
Prior art keywords
lime
hole
soil
nail bar
nail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
GB9508961A
Other versions
GB2289078B (en
GB9508961D0 (en
Inventor
David A Greenwood
Leonard Threadgold
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cementation Skanska Ltd
Original Assignee
Cementation Piling and Foundations Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cementation Piling and Foundations Ltd filed Critical Cementation Piling and Foundations Ltd
Publication of GB9508961D0 publication Critical patent/GB9508961D0/en
Publication of GB2289078A publication Critical patent/GB2289078A/en
Application granted granted Critical
Publication of GB2289078B publication Critical patent/GB2289078B/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Abstract

A method of reinforcing a soft clay soil is disclosed, the method comprising the steps of boring at least one hole in the soil, introducing a nail bar 4 into the hole, and filling the space between the nail bar and the sides of the hole with lime 6. <IMAGE>

Description

IMPROVED SOIL NAIL INSTALLATION The present invention relates to the installation of soil nails as a soil reinforcement in construction work, and in particular, but not exclusively, to the reinforcement of soft clay soils.
Construction work on soft clay soils is problematic because the clays, which are generally naturally occurring poorly consolidated soils or poorly compacted fills, are susceptible to moisture ingress and swelling if not originally wet. In locations such as the slopes of cuttings or embankments, soft clay soils may creep progressively or may even collapse.
It is known to stiffen and strengthen soft clay soils by using lime columns. The soil is stiffened and achieves greater shear strength by boring holes, which are generally temporarily cased, and introducing quicklime compound into each hole as the casing is withdrawn. As the quick-lime slakes, it absorbs water from the pore spaces of the surrounding soil. Because of the low permeability of the clays, the water cannot be replaced quickly in existing hydraulic circumstances. The clay therefore shrinks and consolidates as it dries in an annulus surrounding the column. This creates tension cracks into which the lime may migrate, enabling longer term chemical reactions to occur in these cracks, thereby locally hardening the clay. In the process of slaking, the lime may expand in volume by between 50 to 100% while the surrounding soil shrinks as water is removed.The consolidated and stabilised soil does not easily soften again on exposure to moisture in the longer term. Such lime columns are generally 100 to 300mm in diameter, and are spaced 1 to 3m apart to cover the volume of soil requiring treatment. The stabilising effect of a lime column, however, is concentrated around the bore and diminishes radially. A bulk mass of soil penetrated by lime columns therefore has improved average shear resistance across potentially sliding surfaces, but the soil does not acquire any significant tensile strength.
It is also known to provide soil reinforcement, in particular to cut slopes, by using soil nails, which comprise 100 to 150mm diameter sub-horizontal bores into which grout is introduced along with a central steel bar of diameter typically around 20 to 30mm. The soil is bonded to the grout and the grout is bonded to the bar, thereby enabling the bar to restrict deformation of the soil by imparting tensile strength to the soil though shear bonding. By installing such soil nails generally 1 to 3m apart in a matrix as excavations proceed, it is possible to reinforce and stabilise a cut face in soil.
The known type of soil nail works best in overconsolidated soils which are dense, compact and relatively stiff, although not always enough to be stable. This is because the stress transferred by the soil to the bar is through bonding. A weak soil cannot transfer as much stress as a strong soil, and larger holes and closer spacing are therefore required for weak soils. The known type of soil nail is therefore impractical for use in soft clay soils.
According to the present invention, there is provided a method of reinforcing a soft clay soil, which method comprises the steps of boring at least one hole in the soil, introducing a nail bar into the hole, and filling the space between the nail bar and the sides of the hole with lime.
This method of reinforcement gives improved shear strength as well as a degree of tensile strength to the soil.
The holes may be bored or drilled at any appropriate angle, and are advantageously temporarily cased. The nail bar is preferably provided with centralising spacers, the spacers at each end of the nail bar advantageously being solid discs so as to resist longitudinal expansion of the lime at the ends of the nail bar. The lime is preferably quick-lime, although the precise nature and composition of the lime will generally be determined by installation constraints.
When the holes are temporarily cased, the lime may be introduced at the mouth of the hole as the casing is withdrawn. Depending on the orientation of the hole, the lime, which will generally be in pellet or powder form, may simply be tipped into the hole, or be introduced by pneumatic means along a tremie pipe inserted alongside the nail, or by any other convenient means. In order to ensure proper packing, the lime may be compacted along the length of the hole by using a tubular ram surrounding the nail bar. This process may be repeated as the casing lengths are withdrawn, leaving the nail bar compacted in lime within the hole.
A top plate or centraliser may then be fitted to the end of the nail bar and any residual length of the hole may then be plugged with grout or rammed soil or similar suitable material.
The effect of the swelling lime as it slakes is to provide a frictional bond between the nail bar and the surrounding soil. The associated water absorption and chemical reactions generate an annular region of stiffened clay around the hole, thereby increasing the effective perimeter of the nail. This allows a greater degree of soil reinforcement per nail to be achieved, and therefore results in greater installation economy.
The nail bars are preferably ribbed in order to enhance bonding. The lime may be mixed with pulverised fuel ash if a permanent hardening is required.
Alternatively or in addition, the lime may be mixed with Ordinary Portland Cement, preferably in a proportion of 25 to 50% by dry weight to achieve early hardening.
For a better understanding of the present invention, and to show how the same may be carried into effect, reference will now be made to the drawings, in which: FIGURES 1 to 4 show the installation of a soil nail according to the present invention; and FIGURE 5 shows cross-section I-I of Figure 4.
In order to reinforce a soft clay embankment 1, as shown in Figure 1, a hole 2 (with a diameter typically between 100 to 150mm) is drilled and lined with a casing 3. A nail bar 4 (with a diameter typically between 20 and 30mm), including an end centraliser 5, is then introduced into the hole 2 as shown in Figure 2, and lime 6 is then poured into the hole 2. Figure 3 shows the casing 3 being withdrawn as the lime 6 is compacted with a tubular rammer 7. Once the casing 3 has been completely withdrawn, a top centraliser 8 is fitted to the end of the nail bar 4, and the mouth of the hole 2 is packed with grout or similar material 9.
A number of installations as shown in Figure 4 are generally provided to stabilise and reinforce a mass of soil 1, and are typically spaced between 1.5 to 4m apart.
Figure 5 shows a section through a soil nail installed according to the present invention. The annular space between the nail bar 4 and the side of the hole 2 is packed with lime 6. The lime 6 absorbs water from the soil 1 as it slakes, which causes the lime to expand. This improves the frictional bond between the nail bar 4, the lime 6 and the soil 1.
Furthermore, the absorption by the lime 6 of water from the surrounding soil 1 consolidates and chemically stabilises an annular volume of soil 1 around the hole 2.

Claims (13)

CLAIMS:
1. A method of reinforcing a soft clay soil comprising the steps of boring at least one hole in the soil, introducing a nail bar into the hole, and filling the space between the nail bar and the sides of the hole with lime.
2. A method according to claim 1, wherein the nail bar is provided with at least one centralising spacer.
3. A method according to claim 2, wherein at least one end of the nail bar is provided with a centralising spacer in the form of a solid disc.
4. A method according to any preceding claim, wherein the holes are temporarily cased.
5. A method according to claim 4, wherein the lime is introduced at the mouth of the hole as the temporary casing is withdrawn.
6. A method according to claim 5, wherein the lime is compacted along the length of the hole through the application of a tubular ram surrounding the nail bar as the temporary casing is withdrawn.
7. A method according to claims 4, 5 or 6, wherein an end plate or centralising spacer is fitted to the exposed end of the nail bar after the temporary casing has been substantially withdrawn.
8. A method according to any preceding claim, wherein any residual length of the hole is plugged with grout, rammed soil or a similar material or materials.
9. A method according to any preceding claim, wherein the nail bar is ribbed.
10. A method according to any preceding claim, wherein the lime is mixed with pulverised fuel ash.
11. A method according to any previous claim, wherein the lime is mixed with Ordinary Portland Cement.
12. A method according to claim 11, wherein the proportion of Ordinary Portland Cement in the mix is from 25 to 50% by dry weight.
13. A method of reinforcing a soft clay soil, substantially as hereinbefore described with reference to the accompanying drawings.
GB9508961A 1994-05-03 1995-05-03 Improved soil nail installation Expired - Fee Related GB2289078B (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB9408713A GB9408713D0 (en) 1994-05-03 1994-05-03 Improved soil installation

Publications (3)

Publication Number Publication Date
GB9508961D0 GB9508961D0 (en) 1995-06-21
GB2289078A true GB2289078A (en) 1995-11-08
GB2289078B GB2289078B (en) 1997-06-04

Family

ID=10754463

Family Applications (2)

Application Number Title Priority Date Filing Date
GB9408713A Pending GB9408713D0 (en) 1994-05-03 1994-05-03 Improved soil installation
GB9508961A Expired - Fee Related GB2289078B (en) 1994-05-03 1995-05-03 Improved soil nail installation

Family Applications Before (1)

Application Number Title Priority Date Filing Date
GB9408713A Pending GB9408713D0 (en) 1994-05-03 1994-05-03 Improved soil installation

Country Status (2)

Country Link
GB (2) GB9408713D0 (en)
HK (1) HK1000212A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1998049399A1 (en) * 1997-04-30 1998-11-05 Bilfinger + Berger Bauaktiengesellschaft Method for stabilizing embankments
GB2356884A (en) * 1999-12-03 2001-06-06 Keller Ltd Slope stabilisation using a ground anchor and soil nail
US6742967B1 (en) * 2002-11-07 2004-06-01 Nelson N. S. Chou Structure for fastening soil nails to reinforced soil retaining walls
US7338233B2 (en) 2003-12-18 2008-03-04 Barrett Robert K Soil nail and method of installing a subsurface support
US7384217B1 (en) 2007-03-29 2008-06-10 Barrett Robert K System and method for soil stabilization of sloping surface

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8376661B2 (en) 2010-05-21 2013-02-19 R&B Leasing, Llc System and method for increasing roadway width incorporating a reverse oriented retaining wall and soil nail supports

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4360292A (en) * 1980-05-28 1982-11-23 Keeler Andrew L Grouted strand anchor and method of making same
US4952097A (en) * 1988-03-18 1990-08-28 Kulchin & Associates Permanent concrete wall construction and method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4360292A (en) * 1980-05-28 1982-11-23 Keeler Andrew L Grouted strand anchor and method of making same
US4952097A (en) * 1988-03-18 1990-08-28 Kulchin & Associates Permanent concrete wall construction and method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1998049399A1 (en) * 1997-04-30 1998-11-05 Bilfinger + Berger Bauaktiengesellschaft Method for stabilizing embankments
GB2356884A (en) * 1999-12-03 2001-06-06 Keller Ltd Slope stabilisation using a ground anchor and soil nail
GB2356884B (en) * 1999-12-03 2001-11-07 Keller Ltd Slope stabilising means
US6742967B1 (en) * 2002-11-07 2004-06-01 Nelson N. S. Chou Structure for fastening soil nails to reinforced soil retaining walls
US7338233B2 (en) 2003-12-18 2008-03-04 Barrett Robert K Soil nail and method of installing a subsurface support
US7384217B1 (en) 2007-03-29 2008-06-10 Barrett Robert K System and method for soil stabilization of sloping surface

Also Published As

Publication number Publication date
HK1000212A1 (en) 1998-02-06
GB9408713D0 (en) 1994-06-22
GB2289078B (en) 1997-06-04
GB9508961D0 (en) 1995-06-21

Similar Documents

Publication Publication Date Title
WO2000047826A1 (en) Short aggregate pier techniques
AU781819B2 (en) Soil reinforcement method and apparatus
CN108756976A (en) A kind of self-expanding anchor pole and its preparation and application
JP2008127793A (en) Support structure of adit
GB2289078A (en) Improved soil nail installation
ZA823250B (en) Elongated underground construction having a uniform section and method of building this construction
Essler et al. Compensation grouting: concept, theory and practice
JP2003129476A (en) Pile burying construction method and its device
JP3380861B1 (en) Pile construction method
KR20050118318A (en) Soil reinforcement method
WO2000050358A1 (en) Concrete comprising an elastic substance and pile made of such a concrete
Pourakbara Deep mixing columns
Brandl et al. Special applications of geosynthetics in geotechnical engineering
Bilal et al. A study on advances in ground improvement techniques
JP2003221828A (en) Burying method for prefabricated pile
JP2001152448A (en) Construction method for underground concrete structure
JPH10331149A (en) Improving method for poor clayey soil
RU2277147C1 (en) Method for tunnel lining forming
Egger Rock stabilization
JP4754121B2 (en) Improvement method for soft ground
JPH0355628B2 (en)
JP3894893B2 (en) Construction method of foundation ground
KR100377839B1 (en) Method for reinforcement of reclamation land filling up waste material and its apparatus
JPS626049B2 (en)
JPS61233113A (en) Formation of pile utilizing fiber

Legal Events

Date Code Title Description
PCNP Patent ceased through non-payment of renewal fee

Effective date: 20110503