GB2063958A - Improvements in or relating to bridge piers - Google Patents
Improvements in or relating to bridge piers Download PDFInfo
- Publication number
- GB2063958A GB2063958A GB8037457A GB8037457A GB2063958A GB 2063958 A GB2063958 A GB 2063958A GB 8037457 A GB8037457 A GB 8037457A GB 8037457 A GB8037457 A GB 8037457A GB 2063958 A GB2063958 A GB 2063958A
- Authority
- GB
- United Kingdom
- Prior art keywords
- crib
- bridge pier
- cribs
- grillage
- legs
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/005—Piers, trestles, bearings, expansion joints or parapets specially adapted for portable or sectional bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
A bridge pier is constructed from cribs (1) nestable one within the other for transportation and manually mountable one upon the other in order of decreasing size by the use or rotatable davits (24) attachable to each upper-most crib in turn. The cribs may be mounted upon a pair of telescopic legs (39/38) each pivotally connected to a load-spreading grillage 32. The cribs may be mounted upon a pontoon. <IMAGE>
Description
SPECIFICATION
Improvements in or relating to bridge piers
This invention relates to bridge piers which are transportable and can be manually erected.
Transportable bridge piers suffer variously from a number of disadvantages such as a need for ancillary construction equipment, large stowed volume, heavy weight, lengthy construction time, small load bearing capacity and insufficient adaptability to ground settlement. One known example of a manually erectable bridge pier comprises a multiplicity of identical rectangular frameworks or cribs which can be manually assembled in any specific configuration. These cribs are easy to handle, weighing normally about 1 50 Ibs each, but have a large stowed volume which is inconvenient for transportation purposes.
The time taken for construction is fairly lengthy owing to the need to apply clamps at every interface and the completed assembly has no flexibility for settlement.
The present invention seeks to provide a bridge pier having the handling advantages of the known crib assembly, but with less stowed volume per load bearing capacity and with shorter construction time.
In accordance with the present invention, a bridge pier includes a multiplicity of serially gradated cribs, each nestable within the next larger in a stowed configuration and each mountable upon the next larger in an erected configuration, and a pair of davits attachable to two opposing end faces respectively of any one of the cribs so as to be rotatable in a substantially vertical plane when the crib is disposed in the erected configuration.
Preferably each davit comprises a jib and a counter jib adapted for mutual rotation in a derricking plane, i.e. vertical in use, each of which jibs bears adjacent its outermost end a pulley rotatable in the said derricking plane, a single line being reeved round both pulleys.
Where the bridge pier is to be used in bridging wet gaps, the cribs may be disposed in the erected configuration with the largest crib directly supported on a pontoon.
For use in bridging dry gaps however, the bridge pier further includes two base units each comprising a grillage and a telescopic leg pivotally supportable upon the grillage, the two telescopic legs being jointly adapted for supporting the largest crib.
Preferably the grillage comprises a multiplicity of substantially parallel platens all independently pivoted to tiered support members, the final one of which supports a socket member engageable with a ball attached to the base of the telescopic leg.
An embodiment of the invention will now be described by way of example only with reference to the attached drawings of which
Figure 1 is a general view of a semi-erected bridge pier,
Figure 2 is an oblique view of any one of the cribs illustrated in Figure 1,
Figure 3 illustrates a stowed configuration for all of the cribs illustrated in Figure 1, and
Figure 4 is a cut-away view of the leg clamp illustrated in Figure 1.
The bridge pier illustrated under construction in
Figure 1 comprises six cribs 1 a, 1 b, 1 C, 1 d, 1 e, 1 f of identical form but of serially reducing size each comprising a rectangular framework of steel girders as illustrated in Figure 2. Each crib 1 has an open base 2 and a recessed top 3 within which the next smaller crib can be located, support being provided adjacent each end of the crib by cross braces 4, 5 and 6 and support plates 7. Holes 8 are provided in side top members 9 and 10 which holes align with corresponding holes 11 in the side base members 12 and 13 of the next smaller crib. Securing pins 14 (Figure 1) are inserted in the aligned holes during erection.
Cross braces 1 5 and 1 6 are provided at each end face 1 7 of the crib 1 which are pierced at their intersection to provide a shaft bearing 18. A lifting eye 1 9 is also provided at each end face 1 7.
The open base 2 of the cribs 1 permits all six cribs to be nested when inverted, as illustrated in
Figure 3.
Two davits 24 are used during erection, each comprising a jib 25 and a counter jib 26 mounted radially upon a shaft 27, which shaft is slidably insertable in the shaft bearings 1 8 of each crib 1.
Pulleys 28a and 28b are mounted at the outer extremity of the jib 25 and the counter jib 26 respectively and a line 29 reeved round both pulleys in turn.
Two rocker plates 30 for supporting transversely rockable bridge rollers 20 are mountable on the support plates 7 in the recessed top 3 of any one of the cribs 1 fas drawn).
Two base units 31 each include a grillage 32 consisting of four platens 33 pivotally connected in pairs to secondary support plates 34 and 35 which plates are themselves pivotally connected to a primary support plate 36. Two sets of the support plates 34, 35 and 36 are provided for the grillage 32, the two plates 36 being mutually connected to a platform 37.
The platform 37 supports a telescopic leg comprising an inner leg 38 and an adjustable outer leg 39, the inner leg 38 being pivotally connected to the platform 37 by means of a ball and socket joint (not shown). The outer leg 39 is vertically adjustable with respect to the inner leg 38 by means of a hand operated hydraulic jack (not shown) and is locked into position after adjustment by serrated clamps 40 (illustrated in
Figure 4) located one at each corner of the leg, each of which is brought into engagement with a rack 41 attached to the inner leg 38, by advancing screws 42 through threaded bushes 43 attached to the outer leg 39, the screws 42 being rotatably captive within the clamps 40. Secured to the outer leg 39 by pins 45 is a U-shaped mounting block 44 having a shoulder 46 at its upper edge for locating and supporting the base 2 of the crib 1 a.
Two outriggers 47 having adjustable legs 48 are attachable to each block 44 at the front and back faces (as drawn) to support the pier during construction.
Erection of the bridge pier is as follows. After suitably positioning the base units 31 with the grillage platens 33 orientated to lie in a direction normal to the slope of the ground upon which they are sited, the crib 1 a is lifted onto the two mounting blocks 44 so that its base 2 engages with the shoulders 46 and is pinned in position by securing pins 14 inserted in the holes 11 and corresponding holes in the blocks. Preliminary levelling of the crib la is carried out by means of the hydraulic jacks and the outrigger legs 48 are adjusted accordingly.
The shafts 27 of the davits 24 are then mounted in the shaft bearings 18 at each end face of the crib 1 a and the two lines 29 extending from the two pulleys 28a are respectively attached to the two lifting eyes 19 of the crib 1 b. The crib 1 b is then hauled up as far as the pulley 28a by means of the lines 29 extending from the pulleys 28b, whereupon further tension on the lines causes the shafts 27 to rotate in the shaft bearings 18 thereby rotating the jib 25 upwards and swinging the crib 1 b onto the top of the crib 1 a to locate in its recessed top 7. Over-swing is prevented by arrest of the counter jib 26 against the crib 1 a.
The crib 1 b is secured to the crib 1 a with further securing pins 14 and the davits 24 moved up from the crib 1 a to the crib 1 b. This process is repeated until all six cribs, or as many as are required, are in position and the rollers 20 have been mounted. The davits 24 are then removed, guy lines (not shown) secured to the top crib, the pier finally levelled by means of the hydraulic jacks, the outer legs 39 locked into position by engaging the clamps 40 with the racks 41 and the adjustable legs 48 of the outriggers 47 raised from the ground. The pier is then ready for a bridge span to be laid on the rollers.
Adjustment for any settlement that may occur during use can be made without removing the bridge span, simply by releasing the leg clamps 40, re-levelling the pier by means of the jacks and re-engaging the clamps. The provision of these leg clamps permits the use of hydraulic jacks for adjustment purposes which need only have sufficient power to lift the dead weight of the bridge, all further operational loads being borne by the leg clamps. This reduces the necessary jack diameter with consequent improvement in adjustment rate.
A specific example of this embodiment, having a largest crib weighing approximately 250 Ibs and measuring 14 feet by 5 feet can be erected by 8 men in 1 5 minutes and is capable of carrying a load of 60 tons on each base unit 31. Each grillage 32 weighs about 300 Ibs and can be lifted by 4 men. The davits 24 weigh about 25 Ibs each and can be deployed by one man climbing on the cribs. The ball and socket joint connecting the inner leg 38 to the platform 37 can accommodate ground slopes of one in twenty, whilst the pivoted support plates 34, 35 and 36 ensure that the load is evenly distributed to all four grillage platens 33.
In its stowed configuration the whole pier can be packed onto a single pallet to occupy a volume no greater than 14 ft by 8 ft by 6 ft with a total weight of approximately 4,000 Ibs, which is well within the lifting capability of a medium-lift helicopter.
This embodiment can be erected on dry land and in shallow water of up to two feet in depth.
Piers required to be situated in deeper waters may be erected upon pontoons, in which case the base units 31 are omitted, the lowest crib 1 a being supported directly upon the pontoon.
Claims (9)
1. A bridge pier including a multiplicity of serially gradated cribs, each nestable within the next larger in a stowed configuration and each mountable upon the next larger in an erected configuration, and a pair of davits attachable to two opposing end faces respectively of any one of the cribs so as to be rotatable in a substantially vertical plane when the crib is disposed in the erected configuration.
2. A bridge pier as claimed in Claim 1 wherein each davit comprises a jib and a counter jib adapted for mutual rotation in a derricking plane, each of which jibs bears adjacent its outer-most end a pulley rotatable in the said derricking plane.
3. A bridge pier as claimed in either of the preceding claims further including two base units each comprising a grillage and a telescopic leg pivotally supportable upon the grillage, the two telescopic legs being jointly adapted for supporting the largest crib.
4. A bridge pier as claimed in Claim 3 wherein the grillage comprises a multiplicity of substantially parallel platens all independently pivoted to pivotally tiered support members, the upper-most one of which in use supports a socket member engageable with a ball attached to the base of the telescopic leg.
5. A bridge pier as claimed in either one of
Claims 3 and 4 wherein each telescopic leg comprises an inner leg and a relatively axially slideable outer leg, having co-engageable transversely serrated clamping means.
6. A bridge pier as claimed in any one of the
Claims 3 to 5 further including adjustable outrigger legs attached to the base unit.
7. A bridge pier as claimed in any one of the preceding claims further including a pair of rockable bridge rollers mountable upon any one of the erected cribs.
8. A method of erecting a bridge pier as claimed in Claim 7 including the steps of
a. positioning the base units at a chosen site with the grillage platens orientated so as to lie transversely to the slope of the site,
b. securing the largest crib to the two base units,
c. levelling the largest crib by preliminary adjustment of the telescopic legs,
d. adjusting the outrigger legs so as to provide lateral stability to the assembled crib and base units,
e. sequentially liftirig the cribs by means of the davits to rest one upon the other in order of decreasing size,
f. securing the bridge rollers to the top-most crib,
g. securing the top-most crib by guylines.
h. levelling the complete assembly by final adjustment of the telescopic legs,
i. locking the telescopic legs with the serrated adjusting means,
j. tightening the guylines, and
k. raising the outrigger legs from the ground.
9. A bridge pier substantially as herein before described with reference to the accompanying drawings.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB8037457A GB2063958B (en) | 1979-11-27 | 1980-11-21 | Bridge pier |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB7940912 | 1979-11-27 | ||
GB8037457A GB2063958B (en) | 1979-11-27 | 1980-11-21 | Bridge pier |
Publications (2)
Publication Number | Publication Date |
---|---|
GB2063958A true GB2063958A (en) | 1981-06-10 |
GB2063958B GB2063958B (en) | 1983-06-29 |
Family
ID=26273698
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
GB8037457A Expired GB2063958B (en) | 1979-11-27 | 1980-11-21 | Bridge pier |
Country Status (1)
Country | Link |
---|---|
GB (1) | GB2063958B (en) |
-
1980
- 1980-11-21 GB GB8037457A patent/GB2063958B/en not_active Expired
Also Published As
Publication number | Publication date |
---|---|
GB2063958B (en) | 1983-06-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU714518B2 (en) | Method and apparatus for installing prefabricated deck packages on offshore jacket foundations | |
US3752261A (en) | Multi-stage lift | |
US4579234A (en) | Self-erecting mobile crane | |
US8584801B2 (en) | Self-climbing hoist, deck and scaffold platform system | |
US3972553A (en) | Collapsible lift frame having means to adjust point of lift | |
US4134237A (en) | Modular section mast | |
EP0395297B1 (en) | Rescue frame | |
WO1998010145A2 (en) | Method and apparatus for the offshore installation of multi-ton packages | |
US4508232A (en) | Counterbalanced crane structure | |
US3777900A (en) | Building crane | |
US5975807A (en) | Method and apparatus for the offshore installation of multi-ton packages such as deck packages and jackets | |
JP3343817B2 (en) | Hoisting device | |
US2772004A (en) | Portable gantry crane | |
US3794184A (en) | Crane | |
US2904126A (en) | Multiplatform scaffolds | |
US4175908A (en) | Method of loading and unloading heavy objects from a vessel | |
JPH10291777A (en) | Balance weight handling device for ring support type crane | |
JP6756518B2 (en) | How to operate the crane and the crane | |
US3923163A (en) | Crane | |
US4696135A (en) | Method and apparatus for constructing towers | |
US4359795A (en) | Bridge piers | |
CN113795642B (en) | Tool arrangement for pivoting a tower or a tower section from a non-erected position to an erected position | |
CN113716472A (en) | Double-arm holding pole | |
US4498596A (en) | Supplementary equipment for use with a self-propelled crane with a telescopic jib | |
US10071889B1 (en) | PiƱata hoisting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PCNP | Patent ceased through non-payment of renewal fee |