GB2049895A - Apparatus for preheating material to be charged into steel making equipment - Google Patents
Apparatus for preheating material to be charged into steel making equipment Download PDFInfo
- Publication number
- GB2049895A GB2049895A GB7918302A GB7918302A GB2049895A GB 2049895 A GB2049895 A GB 2049895A GB 7918302 A GB7918302 A GB 7918302A GB 7918302 A GB7918302 A GB 7918302A GB 2049895 A GB2049895 A GB 2049895A
- Authority
- GB
- United Kingdom
- Prior art keywords
- preheating
- bucket
- duct
- hood
- bypass duct
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F27—FURNACES; KILNS; OVENS; RETORTS
- F27D—DETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
- F27D13/00—Apparatus for preheating charges; Arrangements for preheating charges
- F27D13/002—Preheating scrap
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Furnace Details (AREA)
- Vertical, Hearth, Or Arc Furnaces (AREA)
- Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)
Abstract
Apparatus for preheating scrap material to be charged into steel making equipment utilizing the heat energy in the exhaust gases discharged from said equipment. the apparatus comprising a bypass duct 6 supplied with exhaust gases from a dust collection chamber 1 and carrying a hood 8 at one end, said hood 8 and duct 6 being selectively movable to a position above any one of a number of preheating pits 31, a charging bucket 19 removably located in each of the preheating pits and having exhaust gas passages 24, 47 in its interior and bottom discharge means 21, and duct means 36, 37 communicating with each of said preheating pits 31 for collecting the gases leaving the respective bucket in said pit, said dust means 36, 37 communicating with an outlet duct 3 from said dust collection chamber 1. <IMAGE>
Description
SPECIFICATION
Apparatus for preheating material to be charged into steel making equipment
This invention relates to an apparatus for preheating the material to be charged into steel making equipment.
In steel making processes, it is desirable to preheat materials such as scrap, alloy iron, directly reduced iron and lime before they are placed for example into an electric furnace.
Thus the steel making material is preheated to avoid a steam explosion accident when it is charged into the equipment for the safety of operation and to achieve an improved steel making efficiency by promoting melting of the material.
While auxiliary burners have heretofore been most widely used as means for preheating the material, such means are undesirable for the economical use of energy which is presently demanded.
Accordingly a method has been introduced into use which utilizes an exhaust gas as recovered from a dust collector by which the gas generated in the furnace is forcibly withdrawn therefrom. This method nevertheless has the following drawbacks.
In addition to the basic problem that it is difficult to stabilize the pressure loss involved in the dust collector, it is impossible to adapt the method for the operation cycle of the highly advanced steel making process in which the melting time has been remarkably shortened. The known method requires the use of a large number of buckets which, however, are serviceable only for a short period of time because they are placed directly into a preheating chamber, while such buckets must be provided with a lining or cooled with water.
Furthermore, scraps and like materials which are available in snowy or rainy districts contain large quantities of water and are prone to steam explosion accidents when charged into the equipment since it is difficult to fuliy dewater the materials. It is also important to provide a sealed structure for preventing heat losses.
SUMMARY OF THE INVENTION
An object of the present invention is to provide an apparatus for preheating the material to be charged into steel making equipment by which the heat energy of exhaust gas resuiting from a steel making process is recovered from a combustion chamber through a bypass circuit and introduced into a charging bucket serving as a preheating chamber to thereby achieve savings in energy, improved productivity, enhanced safety and a remarkable cost reduction.
Another object of this invention 5 to provide a preheating apparatus of the type described in which the bypass circuit extending from the combustion chamber is in the form of a water-cooled duct and turnable, and the charging bucket is provided along its inner periphery and in its center with means for facilitating the flow of the exhaust gas and achieving a greatly improved heat exchange efficiency to prevent pressure losses, the bucket further being provided with a water-cooling jacket around its outer periphery for use with a high-temperature exhaust gas.
BRIEF DESCRIPTION OF THE DRAWINGS
Fig. 1 is an elevation showing an apparatus of this invention in its entirety;
Fig. 2 is a view showing the flow of exhaust gas;
Fig. 3 is a front view partly broken away and showing a charging bucket serving as a preheating chamber;
Fig. 4 is a plan view showing the bucket;
Fig. 5 is a fragmentary enlarged view in section showing the side wall of the bucket;
Fig 6. is a schematic plan view showing a preheating pit;
Fig. 7 is an enlarged view in section taken along the line 7-7 in Fig. 2;
Figs. 8 (a) and (b) are diagrams illustrating how to charge a material (scraps) into the bucket; and
Figs. 9 (a) to (i) are diagrams illustrating preheating steps.
DETAILED DESCRIPTION OF THE INVENTION
With reference to Fig. 1 showing an overall arrangement of an existing electric furnace dust collector and an apparatus of the invention as attached to the dust collector, a combustion chamber 1 communicates with a water-cooled duct 2 connected to a side wall upper portion thereof and with another water-cooled duct 3 connected to a side wall lower portion thereof.
Exhaust gas from an unillustrated electric furnace is introduced into the combustion chamber 1 by way of unillustrated elbows, movable duct and the duct 2. Dust is led through the other water-cooled duct 3, unillustrated gas cooler, air-cooled duct, etc. into a baghouse (not shown) by a motor-driven blower.
The heat energy of the exhaust gas introduced into the dust collector is recovered and used by the apparatus of this invention for preheating materials such as scraps, directly reduced iron, alloy iron, etc.
As seen in Fig. 1, the combustion chamber 1 is surrounded by a frame 4, on top of which there is a turning assembly 5 for reciprocally turning a bypass duct 6 about a vertical axis over the range of 1 80 degrees. According to the preferred embodiment shown in Fig. 2, the bypass duct 6 is in communication with an upper outlet 7 of the combustion chamber and is easily turnable, with consideration given so that large particles of duct will settle in the combustion chamber 1 to the greatest possible extent and will not ingress into the duct 6. The bypass duct 6 has a downwardly bent free end. A downwardly flared hood 8 is vertically movably fitted to the free end.
The turning assembly 5 includes a shaft 10 which is driven about its axis in a positive or negative direction by a motor through gear transmission means 9, whereby the bypass duct 6 is turned about the axis of the turning shaft 1 0. The shaft 10 is substantially in alignment with the outlet 7 vertically. The duct 6 is turnable over the range of 1 80 degrees. Indicated at 11 in Fig. 1 is a turning boom, the length of which is made variable with use of a turnbuc!tle or the like.
A hydraulically movable damper 12 is attached to the connection between the bypass duct 6 and the combustion chamber 1 to open or close the duct 6. The damper 12 thus positioned can be opened and closed free from the deposition of dust.
An assembly 1 3 for raising or lowering the hood 8 comprises a winch 1 5 disposed at the base end of the duct 6 and reversibly rotatable by an electric motor 14. A wire 1 6, which is wound on the winch 1 5 and can be paid off, extends over a guide sheave 1 7 and is connected to the hood 8. In the illustrated embodiment, the hood 8 is raised when the wire 1 6 is wound up on the winch 1 5 and is lowered when the wire 16 is paid off.
With the preferred embodiment shown in Fig. 2, the bypass duct 6 and hood 8 are provided with water-cooling jackets 6A and 8A therearound for protection from the high-temperature exhaust gas.
The hood 8 is provided in the center of its interior with a tubular diffuser 1 8 to cause the exhaust gas to flow downward over the entire inner periphery of the hood 8 as shown in Fig. 2.
A charging bucket 19 has a suspender arm 20 pivoted to its body and openable bottom means 21 of the clamshell type at its lower portion.
According to this invention, the bucket 1 9 has the structure shown in Figs. 2 to 5 and Fig. 7 so as to be serviceable as a preheating chamber.
The bucket main body is cylindrical as shown in Figs. 3 and 4 and is provided with a water-cooling jacket 22 therearound. Twelve channel forming members 23 attached to the inner peripheral wall of the bucket main body are equidistantly arranged circumferentially thereof and extend longitudinally of the bucket. The channel forming members 23 are in the form of a rib triangular in cross section. The members 23 form channels 24 extending through the bucket main body from a portion thereof slightly below its upper end to its lower end. Each of the members 23 has ports 25 arranged at specified spacing longitudinally of the channel 24 and extending obliquely downward. The bucket main body has such a diameter that the hood 8 is seated thereon as seen in Fig. 2. Alternatively the hood 8 may be fitted in the bucket main body.Instead of being triangular in section as illustrated, the channel forming members 23 may be semi-circular insofar as they cause the exhaust gas to flow along the inner peripheral wall of the bucket and then radially inwardly of the bucket while assuring the flow of the gas over the entire length of the cylindricai bucket. The channel forming members 23 may be arranged circumferentially of the bucket at any desired spacing, provided that they define a channel 26 between each two adjacent members 23.
The bottom means 21, as seen in greater detail in Fig. 3, comprises a pair of bottom plates 28 pivoted to the bucket main body as at 29 and having upwardly extending plates 27 surrounding a lower peripheral portion of the bucket main body. The bottom plates 28 are provided with chains 30, which, when raised, open the bottom plates 28 as indicated in broken lines in Fig. 3. The pair of bottom plates 28 are provided with unillustrated means by which they are held closed. Accordingly the chains 30 are pulled up against this means to open the bottom plates 28.
The illustrated embodiment includes two preheating pits 31 which are arranged on the opposite sides of the combustion chamber 1 as angularly displaced from each other by 1 80 degrees. As shown in
Figs. 2 and 6, the preheating pit 31 has a support 32 adapted to place the bottom means 21 of the bucket 1 9 thereon and partitioning the interior of the pit 31. The support 32 extends upwardly outward radially thereof in the form of a bowl to support the bottom means 21 in a closed state with stability to guide and position the bucket 1 9 concentrically with the pit when the bucket 19 is to be placed into the pit. The support 32 is formed with apertures 33 equidistantly arranged circumferentially thereof.
The top opening of the pit 31 is provided with a pair of openable lids 34 which have semi-circular cutout portions 35 opposed to each other for surrounding the outer periphery of the bucket as seen in
Fig. 6. When the bucket 19 has been placed into the pit 31, the pair of lids 34 are slidingly closed, while the lids 34 are opened as indicated in broken lines in Fig. 6 before the bucket 1 9 is removed. The lids 34 have sealing means where they contact the pit and the bucket 1 9 to seal off the interior of the pit.
With reference to Figs. 1 and 2, the pit has a duct 36 and a connecting duct 37 with an openable switch damper 38 interposed between the ducts 36 and 37. The pit duct 36 extends outward from a body portion of the pit 31, while the connecting duct 37 is in communication with the water-cooled duct 2. The damper 38 is hydraulically openable and closable. The damper 38 and ducts 36 and 37 each have a water-cooling means.
The operation of the present apparatus will be described below with reference to Figs. 8 and 9 in the order of sequential steps.
With use of a crane 40 or the like, a jig 41 is set in the bucket 19 placed in a pit 39 as shown in
Fig. 9 (a). The jig 41 is T-shaped and includes a horizontal bar 42 having a book and a vertical bar 43 extending from the horizontal bar 42. The horizontal bar 42 of the jig 41 is placed on the upper ends of opposed channel forming members 23 in the bucket 1 9 to position the vertical bar 43 in the center of the bucket 1 9 as seen in Fig. 8 (a). With the jig 41 thus set in position, a material such as scrap 46 is placed in a specified amount into the bucket 1 9 by a dump truck 44 (Fig. 9 (b)) or a magnetic crane 45 (Fig. 8 (a)). At this time, pieces of the scrap 46 form spaces therebetween, while the channel forming members 23 provide the channels 26 shown in Fig. 7.Moreover, the members 23 serve as reinforcing ribs against the impact produced when the scrap is placed in.
After the specified amount of scrap 46 has been placed into the bucket, the jig 41 is withdrawn as by the crane 40 shown in Fig. 9 (c), whereby a vertical channel 47 is formed in the center of the bucket (Fig.8(b)).
Subsequently the bucket 1 9 accommodating the scrap is transferred from the pit 39 to the preheating pit 31 with use of the crane 40 as shown in Fig. 9 (d). The lids 34 are then closed, while the bypass duct 6 is turned about the shaft 10 by the assembly 5 shown in Fig. 1 to bring the hood 8 on the free end of the duct 6 to a position immediately above the bucket 1 9 in the preheating pit 31 (see Fig. 9 (e)). Subsequently the winch 1 5 of the lift assembly 1 3 shown in Fig. 1 is driven to lower the hood 8 to close the bucket 1 9 as seen in Fig. 2. The dampers 12 and 38 on the bypass circuit are both opened to start preheating.In the meantime, another bucket 1 9 is placed in the outer preheating pit 31 as seen in
Fig. 9 (f), and scrap is placed into this bucket in the manner shown in Figs. 9 (a) to (c). With the preferred embodiment of the invention, three buckets are used.
The scrap in the bucket 1 9 is preheated with the flow of exhaust gas illustrated in Figs. 2 and 7.
The heat energy of the gas drawn off from the combustion chamber 1 through the outlet 7 is led through the bypass duct 6 to the hood 8, where the diffuser 1 8 spreads the flow of the gas over the entire upper portion of the bucket 1 9 as indicated by arrows in Fig. 2, permitting the heat energy of the gas to preheat the scrap 46 or like material in the bucket.
The channels 24 provided by the members 23, the downwardly slanting ports 25 and the channel 47 formed by the jig 41 within the bucket 19 assure uniform preheating the scrap 46 in its entirety, while minimizing the pressure loss which is objectionable to the dust collector. The extreneous matter adhering to the scrap is burned out or evaporated off during the preheating. The waste gas from the preheating pit 31 is led through the pit duct 36 and connecting duct 37 to the water-cooled duct 2.
After the completion of the preheating of the scrap 46, the dampers 12 and 38 are closed, the hood 8 raised by the winch 1 5 of the lift assembly 13 shown in Fig. 1 and placed on the other bucket 1 9 already prepared by turning the bypass duct 6 by the assembly 5 as shown in Fig. 9 (g). The scrap is then preheated in the same manner as above.
On the other hand, the bucket 1 9 accommodating the preheated material shown in Fig. 9 (g) is transferred by the crane 40 to an electric furnace 48 shown in Fig. 9 (h). The bottom means 21 is opened to charge the material into the furnace. At this time, hot waste water at 40 to 500C from the furnace 48 may be supplied to the jacket 22 of the bucket 1 9 to warm up the material to be placed thereinto. With water completely removed from the material charged into the furnace, explosion accidents can be avoided. Current is then passed through the furnace to start melting as shown in Fig. 9 (i).
For reference, operation with use of the preheating apparatus of the invention will be compared with usual operation below.
STEEL MAKING EQUIPMENT 1. E.A.F. Capacity
a. Nominal: 30 tons/charge
b. Normal: 42.5 tons/charge
c. Maximum: 43.5 tons/charge 2. E.A.F. Operation
a. Power on to tap: 70 minutes
b. Charge/2 shifts/day: 13-14 charges
c. Monthly production: 13,000 tons 3. Scrap Bucket
a. Volume: 30 M3
b. The number of unit: 3 units
c. Scrap bulk density: 0.6 ton/m3 4. Dust Collector
a. Volume of exhaust gas treated: 1 500M3/min at 2000C
b. The number of Blower: 2 blowers
c. Motor capacity: 200 x 2 5. Preheating Apparatus
a. Temperature at inlet of
preheating chamber: 8000C
b. Volume of gas in preheating
chamber: 1000 M3/min
c. Preheating time (3 charges)
Initial charge 15 min.
Additional charge I - 10 min.
Additional charge II 10 min.
d. Scrap preheating temperature: 200-5000C COMPARISION BETWEEN NORMAL OPERATION AND OPERATION WITH PREHEATING (1)
ITEM Normal Operation with Operation Preheating Difference 1. Melting time 53 48 -5 (Power-on to 2. Refining time 18 16 -2 (Melt-down to tap) 3. Power-ontotap 1 Hr.17 1 Hr.10 -7 4. Burner operation time (min/4 105 95 -10 burnerslcharge) 5. Lance oxygen cutting time (min/2 45 37 8 lance/charge) 6. Tapping yield (X) 90 90.6 7. Electric power consumption a. For melting only (KWH) 12,000 11,000 -1000 b. For melting only 282.4 258.9 -23.5 (KWH/charge ton) c. KWH/charge 15,500 14,200 -1300 d. KWH/charge 364.7 334.1 -30.6 8. Oil consumption (for E.A.F.) a. Nm'/charge 1,168 1,026 -142 b. Nm /charge ton 27.5 24.1 -3.4 9. Oil consumption (for EAF.) a. literlcharge 302 277 -25 b. Uterlcharge ton 7.1 6.5 ---0.6 10. Electrode consumption 3.6 3.5 ---0.1 (Kg/charge ton) COMPARISON BETWEEN NORMAL OPERATION AND OPERATION WITH PREHEATING (2)
The following is the cost reduction based on Comparison (1) 1. Energy:
(1) Electric power
-30.6KWH/charge ton 60.05 (US$) 1.53 (US$/charge ton)
(2) Oxygen
-3.4Nm3/charge ton @0.21 " 0.71
(3) Oil
-0.6 liter/charge ton @0.16 ,, 0.10
Total 2.34 (US$/charge ton)
2. Electrode
-0.1 kg/charge ton @2;368.42(US$) 0.24 (US$/charge ton) 3. Other cost reduction due to production increase through reduction in melting time.
(1) Bricks, consumables, labor cost 0.53 (US$/charge ton)
(2) Overhead costs 0.53
TOTAL: 1. + 2. + 3. = 3.64 US$/charge ton
Therefore, cost reduction per month is (Production -- 13,000 ton/month, Tapping yield - 90.6%) 14,343 charge ton/ month x 3.64 US$/charge ton = 52,226.72 US$/month.
If tapping yield is taken into consideration, cost reduction per month is US$47,317.41 Although this invention has been described above with reference to the illustrated preferred embodiments, the apparatus can be modified as follows.
The bypass duct 6 which is connected to a top portion of the combustion chamber for drawing off the exhaust gas therefrom in the above embodiment may be attached to a suitable portion on the side wall of the combustion chamber 1. Since the hood 8 on the bypass duct 6 needs only to be shiftable to the position of one of a plurality of the preheating pits 31, the duct 6 may be attached to a suitable side portion of the combustion chamber 1 and made extendable or collapsible instead of using the turning assembly 5 and lift assembly 1 3 described above. However, it will be apparent from the foregoing description that the use of such turning assembly 5 and lift assembly 13 is most preferable to render the hood 8 on the duct 6 so shiftable as stated above.
Claims (6)
1. An apparatus for preheating the material to be charged into steel making equipment with the heat energy of exhaust gas from a dust collecting combustion chamber for the equipment, the apparatus comprising a bypass duct connected to the combustion chamber, a hood fitting to the duct and shiftable to the position of one of preheating pits selectively, a charging bucket removably placed in each of the preheating pits and having an exhaust gas passage in its interior and openable bottom means at its bottom, and a communicating duct for holding an outlet duct of the combustion chamber in communication with each of the preheating pits.
2. A preheating apparatus as defined in claim 1 wherein the bypass duct is connected to the top wall of the combustion chamber in communication therewith, and means for selectively shifting the hood to the position of one of the preheating pits comprises an assembly for turning the bypass duct about the connection between the bypass duct and the top wall and an assembly for raising or lowering the hood relative to the bypass duct.
3. A preheating apparatus as defined in claim 1 wherein the hood, the bypass duct and the communicating duct each have a water-cooled structure, the charging bucket serving as a preheating chamber and having a water-cooling jacket around its body portion, the openable bottom means of the bucket having a clamshell structure.
4. A preheating apparatus as defined in claim 1 wherein the exhaust gas passage in the interior of the bucket comprises channels circumferentially equidistantly arranged along the inner periphery of the bucket main body and extending vertically through the bucket, ports permitting the channels to communicate with the interior of the bucket radially inwardly thereof, and a passageway to be formed vertically in the center of the bucket.
5. A preheating apparatus as defined in claim 1 wherein the hood is internally provided with a diffuser for diffusing the heat energy of the exhaust gas through the whole interior space of the bucket placed in the preheating pit after the gas has been introduced to the hood through the bypass duct.
6. A preheating apparatus as defined in claim 1 wherein the connection between the bypass duct and the combustion chamber and the communicating duct are each provided with an openable damper.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB7918302A GB2049895B (en) | 1979-05-25 | 1979-05-25 | Apparatus for preheating material to be charged into steel making equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB7918302A GB2049895B (en) | 1979-05-25 | 1979-05-25 | Apparatus for preheating material to be charged into steel making equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
GB2049895A true GB2049895A (en) | 1980-12-31 |
GB2049895B GB2049895B (en) | 1983-06-15 |
Family
ID=10505449
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
GB7918302A Expired GB2049895B (en) | 1979-05-25 | 1979-05-25 | Apparatus for preheating material to be charged into steel making equipment |
Country Status (1)
Country | Link |
---|---|
GB (1) | GB2049895B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3107548A1 (en) * | 1980-02-29 | 1982-01-07 | Daidotokushuko K.K., Nagoya, Aichi | PREHEATING METHOD AND DEVICE FOR STEEL MELTING MATERIAL |
EP0063201A1 (en) * | 1981-04-16 | 1982-10-27 | DANECO-DANIELI ECOLOGIA Spa | Procedure to cool the walls of a skip to charge scrap, and skips for charging scrap |
-
1979
- 1979-05-25 GB GB7918302A patent/GB2049895B/en not_active Expired
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3107548A1 (en) * | 1980-02-29 | 1982-01-07 | Daidotokushuko K.K., Nagoya, Aichi | PREHEATING METHOD AND DEVICE FOR STEEL MELTING MATERIAL |
EP0063201A1 (en) * | 1981-04-16 | 1982-10-27 | DANECO-DANIELI ECOLOGIA Spa | Procedure to cool the walls of a skip to charge scrap, and skips for charging scrap |
Also Published As
Publication number | Publication date |
---|---|
GB2049895B (en) | 1983-06-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
RU2044977C1 (en) | Melting unit and method for preliminary heating and melting of charge | |
RU2096706C1 (en) | Electric arc furnace for steel production, steel production from scrap, and/or from sponge iron, and/or from blast-furnace cast iron in electric arc furnace, and method for steel production from scrap in electric arc furnace | |
AU600206B2 (en) | Method for melting scrap or other materials and apparatus for implementing the method | |
US4642048A (en) | Apparatus for continuously preheating and charging raw materials for electric furnace | |
RU2092599C1 (en) | Plant for continuously melting copper | |
US4249721A (en) | Apparatus for preheating material to be charged into steel making equipment | |
JP2001524598A (en) | Melting furnace equipment | |
GB2049895A (en) | Apparatus for preheating material to be charged into steel making equipment | |
EP2414760B1 (en) | Electric arc furnace | |
CA1142354A (en) | Apparatus for preheating material to be charged into steel making equipment | |
US3367769A (en) | Method and apparatus for continuously melting scrap vehicles | |
US4385889A (en) | Apparatus for preheating material for making steel | |
JP3092083B2 (en) | Preheating apparatus and preheating method for iron scrap | |
US4395280A (en) | Preheating process for steel-making materials | |
RU2360010C2 (en) | Stove unit and melting method of metallic or metal-bearing raw materials | |
US3880648A (en) | Method for producing steel in an electric arc furnace | |
US5533043A (en) | Installation for producing liquid metal by melting scrap iron | |
JP3162610B2 (en) | Arc furnace | |
US3219439A (en) | Open hearth utilization | |
US3424445A (en) | Open hearth having preheat and charge means | |
JP3650193B2 (en) | Method for melting metal raw materials | |
GB2103771A (en) | Preheating material for steel making | |
CN211527059U (en) | Cupola furnace for casting speed reducer box | |
FR2492077A1 (en) | Preheating scrap for charging into furnace - using heat energy in exhaust gases discharged from the furnace | |
DE3038515A1 (en) | Preheating scrap for charging into furnace - using heat energy in exhaust gases discharged from the furnace |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PCNP | Patent ceased through non-payment of renewal fee |